Batching Of Concrete Method Statement

The scope of this procedure covers checks required to be carried out prior to and during the site batching of concrete.

PROJECT: PROJECT NAME Ref No. CONC/09



PAGE 1Offline
OF 4
https://planningengineer.net/batching-of-concrete-method-statement/ 1/10
11/16/2017 Batching Of Concrete Method Statement Planning Engineer Est.

SECTION: DATE OF ISSUE

CONCRETING Dec. 2012

SUBJECT:

Batching Of Concrete Method Statement APPROVED BY:

QEHS MANAGER

ACTION VERIFY

1. SCOPE Project Source

The scope of this procedure covers checks required to be carried out prior to and during the Engineer Certificates
site batching of concrete.
Site Analysis
2. PROCEDURE
Engineer Report
.1 Checks Prior to Commencement of Activity:
Plant Approval
i) Basic constituents of concrete viz. cement, coarse and fine aggregates shall
comply with the contract specifications. In case of large projects and where specified, a Operator Operation

laboratory will be set up at site for conducting tests on materials and ensured product.
Manual,
Refer Work Procedure CONC/13.

Suppliers
ii) Availability of potable water and power shall be ensured. In case of supply failure
alternative arrangements shall also be planned.
instructions

iii) Verify the type of admixture if required, to be added. If required, receive approval
Manufactu-
from Consultants representative.
rers manual
.2 Handling and Storage of Materials: Offline
https://planningengineer.net/batching-of-concrete-method-statement/ 2/10
11/16/2017 Batching Of Concrete Method Statement Planning Engineer Est.

Special care shall be taken for proper storage of basic materials in order to avoid
contamination. Unless otherwise specified, the following measures shall be taken for proper
handling and storage of these materials:

.3 Cement (in bulk):

i) The silos shall be weatherproof and the mechanism will be cleaned regularly in
accordance with manufacturers manual.

ii) The air filter will be cleaned after every delivery.

iii) Care shall be taken to use stored cement in the order of delivery.

iv) Care shall be taken to minimise the contact of cement with air.

v) The silo shall be painted white and wherever possible, shaded from sun.

PROJECT: PROJECT NAME Ref No. CONC/09

PAGE 2 OF 4

SECTION: DATE OF ISSUE

CONCRETING Dec. 2012

SUBJECT: BY:

QA/QC ENGINEER

BATCHING OF CONCRETE APPROVED BY:

QHSE MANAGER

ACTION VERIFY

.4 Aggregates: Plant Manufactu-

i) Storage of aggregates shall be on clean; permanent clean hard-standing laid to fall Operator rers recom-
for drainage.
Store- mendation

Offline
https://planningengineer.net/batching-of-concrete-method-statement/ 3/10
11/16/2017 Batching Of Concrete Method Statement Planning Engineer Est.

ii) Different sizes of aggregates shall be separated from each other in bins or keeper
compartments with rigid dividing walls extending high enough to prevent different
aggregates from being mixed during batching. Plant

iii) In hot climates either shading or sprinkling clean water is required to reduce that Operator

fines and dust have not built up at the lower levels. If this has occurred, contaminated
aggregates shall be removed and washed or replaced with clean material.

iv) If aggregates are wet stockpiles shall be frequently inspected to make sure that
fines and dust have not built up at the lower levels. If this has occurred, contaminated
aggregates shall be removed and washed or replaced with clean material.

.5 Admixtures:

i) Storage of admixture shall be as per the manufacturers recommendations.

ii) The containers shall be levelled to indicate the contents, batch number, date of
manufacture, shelf life and any other requirements for storage.

.6 Water:

i) Water shall be stored as cool as possible, particularly if it has been supplied by


road tanker or shallow wells.

ii) Wherever possible, storage tanks shall be sited below ground. It this is not
possible, they should be at least be shaded from the sun and painted white.

iii) Tank to be covered properly to prevent the growth of algae.

iv) For cooling of water even site cooling towers can be used which reduces the
temperature up to 10OC or ice can be used.

PROJECT: PROJECT NAME Ref No. CONC/09

PAGE 3 OF 4

SECTION: DATE OF ISSUE



Offline
https://planningengineer.net/batching-of-concrete-method-statement/ 4/10
11/16/2017 Batching Of Concrete Method Statement Planning Engineer Est.

CONCRETING Dec. 2012

SUBJECT: BY:

QA/QC ENGINEER

BATCHING OF CONCRETE APPROVED BY:

QEHS MANAGER

ACTION VERIFY

.7 Plant: Plant

i) Batching and mixing plant shall be pained white and kept clean. Operator

ii) If possible, mixing and batching plant shall be shaded from the sun. Plant

iii) Provision shall be made to prevent dust accumulating in the plant and Operator
immediately before it is used each day (or after any substantial interruption in
concreting) it shall be flushed out with water.

iv) Feed belts and weigh batchers shall be protected from the wind so that cement
cant be blown away.

v) Ensure the accuracy of all weighing and measuring equipment falls within + 3%
unless specified otherwise calibrate plant as necessary.

.8 Batching by Volume:

i) Prepare gauge boxes or similar standard containers of a size such that complete
filling is necessary when proportioning materials.

ii) Clear written instructions will be provided to the Plant operator on quantities of all
materials to be batched and batching sequence for each mix required.

iii) Priming of internal drum of mixer to be done at the time of loading the first batch
of materials.


Offline
https://planningengineer.net/batching-of-concrete-method-statement/ 5/10
11/16/2017 Batching Of Concrete Method Statement Planning Engineer Est.

iv) Mix ingredients for sufficient time as specified to ensure uniform distribution of
materials.

v) Check the zero reading when hopper is empty.

vi) Check the speed of mixer drum once a week and adjust to that given in the
manufacturers manual.

vii) Regular maintenance of moving parts shall be done in accordance with the
manufacturers manual.

viii) Transport the concrete with minimum delay so that it is placed before it comes
hardened and difficult to place and compact.

PROJECT: PROJECT NAME Ref No. CONC/09

PAGE 4 OF 4

SECTION: DATE OF ISSUE

CONCRETING Dec. 2012

SUBJECT: BY:

QA/QC ENGINEER

BATCHING OF CONCRETE APPROVED BY:

QEHS MANAGER

ACTION VERIFY

3. DOCUMENTATION Project

.1 Following documents may be appropriate as a minimum requirement: Engineer

i) Test certificates of cement, aggregates, water and admixtures.



ii) Mix design details. Offline
https://planningengineer.net/batching-of-concrete-method-statement/ 6/10
11/16/2017 Batching Of Concrete Method Statement Planning Engineer Est.

iii) Calibration record of all equipment of batching plant.

SEARCH

Search

PLANNING COURSES
Download theBatching Of Concrete Method Statement word format:Batching Of Concrete Method Statement
Free Arabic
How to cre
schedule w

Free
Tag: Batching, Batching Of Concrete Method Statement, Concrete, concrete method, issue dec, manager action, method statement, plant
operator, project project, section concreting Profession
Share: Planning E
(PPE) On
Workshop

$665.00

Claims
Manageme
Extension
(EOT) and D
Analysis-O
Workshop
Hany Ismael, Msc, PMP $399.00

Offline
https://planningengineer.net/batching-of-concrete-method-statement/ 7/10
11/16/2017 Batching Of Concrete Method Statement Planning Engineer Est.

Hany Ismael is the founder and CEO of Planning Engineer Est. in Egypt. He has started his career back in 2003 as a site engineer, Online Prim
Course for
technical o ce engineer, planning engineer, planning manager, and nally planning department manager where he has been
Engineers
involved in several mega construction projects in Egypt and Saudi Arabia. In 2016, he established his own company in Egypt Constructio
Planning Engineer Est. Hany gained his MSc degree in project management from Liverpool University-UK 2013-2016, PMP Managers!
certi ed from PMI-USA 2010, and BSc Civil Engineer Tanta University-Egypt 2003. Hany provided more than 3,500 hours of $149.00
planning and project management training on his website planningengineer.net, YouTube channel, and o ine courses since 2011.
He enjoys teaching project management in simple and practical way, and he developed several planning tools, techniques and Advanced P
courses. With Prima
Course-
Downloada

$150.00

Quantitativ
Previous post Next post
Schedule R
BORED PILING METHOD STATEMENT PROJECT PERFORMANCE REPORT Analysis w
February 8, 2014 February 9, 2014 Primavera
Course

$119.00

YOU MAY ALSO LIKE

Why you should add the advanced payment to your sched Primavera Currency How to Add New Currency or Chang
Sign-up
22 October, 2017 now! get useful contents into your email.8 October,
Your email address..
2017 SUBSCRIBE

Offline
https://planningengineer.net/batching-of-concrete-method-statement/ 8/10
11/16/2017 Batching Of Concrete Method Statement Planning Engineer Est.

1 COMMENT

Johnd101 October 16, 2016 Log in to Reply

Very informative blog post.Really thank you! Keep writing. ekdgfdfcfbak

LEAVE A REPLY

You must be logged in to post a comment.

Planning Engineer Est.


(00) 201277767728

info@planningengineer.net

FOLLOW US:


Offline
COMPANY
https://planningengineer.net/batching-of-concrete-method-statement/ 9/10
11/16/2017 Batching Of Concrete Method Statement Planning Engineer Est.
COMPANY

About Us

Contact Us

Terms of Service

Privacy Policy

Refund Policy

IMPORTANT LINKS

: Planning Blog

: Our Events

: Planning Jobs

Copyright 2017 planningengineer.net | All materials, unless otherwise noted, were developed originally for Planning Engineer Website. In the event that there is

still a problem or error with copyrighted material, the break of the copyright is unintentional and noncommercial and the material will be removed immediately

upon presented proof.


Offline
https://planningengineer.net/batching-of-concrete-method-statement/ 10/10

Vous aimerez peut-être aussi