Vous êtes sur la page 1sur 4

Seat Number

- 077

*6925*

Estimating and Costing


(117102)

P. Pages : 4
Time : Four Hours Max. Marks : 80
________________________________________________________________________
Instructions to Candidates :
1. Do not write anything on question paper except Seat No.
2. Graph or diagram should be drawn with the black ink pen being used for
writing paper or black HB pencil.
3. Students should note, no supplement will be provided.
4. Solve any two questions from each unit.
5. Use of non-programmable calculator is allowed.
6. Answer to all sub questions of same unit should be written at one place.
7. Assume suitable data if necessary.

UNIT I

1. a) Enlist the methods of preparing approximate estimate for buildings. Explain 8


any two methods in detail.

b) What data is required for preparing detailed estimate differentiate between 8


revised and supplementary estimate.

c) Write short notes on any four. 8

i) Administrative approval.

ii) Work charged establishment.

iii) Contingencies.

iv) Registration of contractor in PWD.

v) Methods of execution of minor works in P.W.D.

- 077 1 P.T.O
- 077
UNIT II

2. Fig. 1 shows a plan of a small building and section of a wall. Calculate the
quantities of the following items (any two) and enter them in standard
measurement sheet.

a) Excavation for foundation. 8

b) U.C.R. masonry in foundation and plinth in C.M. 1 : 6. 8

c) D.P.C. in C.C. 1 : 2 : 4 8

- 077 2
- 077
UNIT III

3. a) Fig. (2) shows a R.C.C. beam. Calculate total quantity of M.S. 8


Reinforcement. Also prepare schedule of Bars.

b) Fig. (3) shows a footing and column reinforcement. Calculate the quantity of 8
steel for footing. Also prepare schedule of Bars for footing.
c) Fig. (3) shows a footing and column reinforcement calculate the quantity of 8
steel for column. Also prepare schedule of Bars for column.

Fig. (3) Assume clear cover for column = 40 mm


and clear cover for footing = 50 mm.

- 077 3 P.T.O
- 077
UNIT IV

4. a) Draft a specification for any one of the following. 8

i) Brick masonry work for superstructure in CM 1 : 4.

ii) 12 mm thick cement plaster to brick work in CM (1 : 5)

b) Prepare the rate analysis for any one of the following. 8

i) R.C.C. work (1 : 2 : 4) mix for Slab, Lintel, Chajja etc. excluding


reinforcement.

ii) Plastering 25 mm thick in CM (1 : 4) for 200 m2 surface area.

c) Write short notes on : 8

i) Task work ii) Red Book

UNIT V

5. a) Define various types of values. 8

i) Book Value ii) Market Value

iii) Salvage Value iv) Scrap Value

b) What are the methods of valuation. Explain any two methods for valuation of 8
buildings.

c) Write short notes on any two. 8

i) Free Hold and Lease hold property.

ii) Belting method of valuation of Land.

iii) Depreciation & its methods.

**********

- 077 4 116 / 30