Code | Description unit | Quantity | Ratez | Amount 2
MACHINERY
0024 | Hire and running charges of hydraulic piling
rig with power unit etc. including complete
accessories and shifting at site day 0.70 | 3400.00] 2380.00
(0025 | Hire and running charges of light crane. day 0.08 | 2500.00] 150.00
0026 | Hire and running charges of bentonite pump. day 0.75 | 4200.00} 3150.00
0018 | Hire and running charges of loader day 0.30 | 6000.00] 1800.00
0017 | Hire and running charges of tipper day 0.30 | 1800.00] 540.00
LABOUR
Work supervisor
o1s0 | Mistry day ota 487.00 68.18
o1t4 | Beldar day 3.50 368.00] 1288.00
TOTAL 74629.31
‘Add 1 % Water charges _on all except (A)
i.e. on (74629.31 - 42675,50) = 31953.81 319.54
TOTAL 74948.85,
Add 15 % Contractor's profit and overheads
‘on all except (A) i.e. on (7448.85 -
42675.50) = $2273.35 4841.00,
Gost of 15 metre pile 79789.85,
Cost of 1 metre pile 5319.32
Say 5319.30
20.2A.3 1000 mm dia piles
Code | Deseri unit | Quantity | Ratez | Amount &
Details of cost for 10 m length of pile
MATERIAL,
Concrete 3.14/4x1.00%10 = 7.85 cum
5.33.1 | Rate as per item no 5.33.1 of SH: RCC Work | cum 7.85 | 6446.45|50604.63(A)
7183 | Bentonite tonne 0.35 | 3100.00] 1085.00
9999 | Sundries LS. 175.89 173] 30429
MACHINERY
0024 | Hire and running charges of hydraulic piling
rig with power unit etc, including complete
accessories and shilling at site day 0.69 | 3400.00) 28460.00
0025 | Hire and running charges of light crane. day 0.08 | 2500.00] 150.00
0026 | Hire and running charges of bentonite purnp. day 075 | 4200.00] 3150.00
0018 | Hire and running charges of loader day 0.40 | 6000.00) 2400.00
0017 | Hire and running charges of tipper day 0.40 | 1800.00] 720.00
LABOUR,
Work supervisor
o1g0 | Mistry day o16 487.00 7.92
o1t4 | Beldar day 4.00 368.00] 1472.00
TOTAL 83423.84
‘Add 1 % Water charges on all except (A)
ive. on (83423.84 - §0604.63) = $2819.21 328.19
TOTAL 83752.03
Add 15 % Contractor's profit and overheads
‘on all except (A) i.e. on (83752.03 -
50604,63) = $3147.40 4972.11
Cost of 10 metre pile 88724.14
Gost of 1 metre pile 8872.41
Say 8872.40
‘SUB HEAD : 20- PILE WORK 149420.2A.4
1200 mm dia piles
Code | Description unit | quantity [ Ratez | Amount &
Details of cost for 9 m length of pile
MATERIAL,
Concrete 3.14/4x1.20%9 = 10.17 cum
5.33.1 | Rate as per item no 5.33.1 of SH: REC Work| cum 10.17 | 6446.45 |e5560.40(A)
7183 | Bentonite tonne 0.385 | 3100.00) 1193.50
9999 | Sundries LS. 290.79 1,73] $03.07
MACHINERY
0024 | Hire and running charges of hydraulic piling
rig with power unit etc. including complete
accessories and shifting at site day 0.67 | 3400.00) 22780.00
0025 | Hire and running charges of light crane. day 0.08 | 2500.00] 150.00
0028 | Hire and running charges of bentonite pump. day 075 | 4200.00] 3150.00
0018 | Hire and running charges of loader. day 0.50 | 6000.00] 3000.00
0017 | Hire and running charges of tipper day 0.50 | 1800.00] 00.00
LABOUR,
Work supervisor
o1g0 | Mistry day 018 487.00 87.66
o1t4 | Beldar day 4.50 368,00] 1656.00
TOTAL 98980.63
‘Add 1 % Water charges on all except (A)
i.e. on (98980.69 - 65560.40) = $3420.23 334.20
TOTAL, 99314.83
‘Add 15 % Contractor's profit and overheads
fon all except (A) i.e. on (99314.83,
= 88560.40) = 33754.43 5063.16
Gost of 8 mete pile 104377.99
Cost of 1 mete pile 1597.55
Say 11597.55
20.2A.5 1500 mm dia piles
Code | Description unit | Quantity | Rateg | Amount &
Details of cost for 9 m length of pile
MATERIAL,
Concrete 3.14/4x1.50%x9 = 15.90 cum
5.33.1 | Rate as per item no 5.93.1 of SH : RCC Work | cum 15.90 | 6446.45 |102498.56(A)
7183 | Bentonite tonne 0.45 | 3100.00] — 1395.00
9999 | Sundries LS. 593.48 173) 1026.72
MACHINERY
0024 | Hire and running charges of hydraulic piling
rig with power unit etc. including complete
accessories and shifting at site day 0.77 |34000.00] 26180.00
(0025 | Hire and running charges of light crane. day 0.10 | 2500.00 250.00
0026 | Hire and running charges of bentonite purnp. day 096 | 4200.00} 4032.00
0018 | Hire and running charges of loader day 0.75 | 6000.00] 4500.00
0017 | Hire and running charges of tipper day 0.75 | 1800.00] — 1380.00
LABOUR
Work supervisor
o1s0 | Mistry day 0.25 | 487.00 121.75
‘SUB HEAD : 20- PILE WORK 1495