Vous êtes sur la page 1sur 22

Long-Term Stresses

O
O
O
O
O
O
O
and Deformation of
O
O
O
O
Segmental Bridges
O
O
O
O
O
O
O
O
O
O
O
O
O
O Maher K. Tadros
O Associate Professor of Civil Engineering
O The University of Nebraska at Omaha
O
Omaha, Nebraska
O
O
O
O
O
O
O
O
O
O
O
O
O Amin Ghali
O Professor of Civil Engineering
O The University of Calgary
O Calgary, Alberta
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O
O Walter H. Dilger
O Professor of Civil Engineering
O The University of Calgary
O Calgary, Alberta

66
n the segmental method of bridge While the erection of a cantilever is
' construction,' 4 units (or segments) in progress, it continues to deflect
of the bridge are precast, assembled in with time; so do parts of the bridge
appropriate position and tied together which have been previously erected.
by prestressing to form the bridge When the cantilever is connected with
superstructure. Segments can also be the rest of the structure, there may be
cast in place. a significant difference between the
Several methods are used for levels of the ends to be joined. This
erecting segmental bridges.5- 7 One difference can be eliminated or re-
common method suitable for medium duced by jacking or by constructing
to long span bridges is called the predetermined camber during the
"Cantilever Construction." In this casting of the segments.
method, segments are placed progres- The prestressing forces, which are
sively to form a balanced cantilever, introduced in consecutive stages, will
starting generally from the piers. be subjected to gradual change due to
When the cantilevers from two adja- creep and shrinkage of concrete and
cent piers meet, they are joined to- stress relaxation of prestressed steel.
gether to form a continuous span. The analysis of the prestress loss and
Continuity prestressing cables are the associated deformations becomes
often used to resist bending moments more involved when the concrete
caused by superimposed loads and segments are of different ages and
those developed gradually with time when the segments are joined to form
as a result of creep and shrinkage of a statically indeterminate structure.
concrete and relaxation of prestressed Time-dependent statically indetermi-
steel. nate forces gradually develop, causing

PCI JOURNAUJuly-August 1979 67


TYPICAL TENDONS, STRESSED IN STAGES

ur uirrt tj'lt Huw SUPPORT CONDITIONS CAN


ERECTED SUCCESSIVELY VARY DURING ERECTION OR
AFTERWARDS

BRIDGE ELEVATION

Ap91. A92,...

CENTROID
^ x
NON PRESTRESSE
STEEL A ns CONCRETE SECTION, AREA Ac,
MOMENT OF INERTIA = IC
Y
SECT/ON A-A

Fig. 1. Longitudinal view and section of typical segmental bridge.

further stress redistribution in the The objective of this paper is to


bridge. If these are not carefully ac- present a method for evaluating the
counted for, cracking and other signs time development of the displace-
of distress may appear in the first few ments and the stresses in concrete and
years after construction. steel at any cross section in a statically
When the segments are cast-in- indeterminate plane frame due to the
place, concrete is loaded when it is effects of creep and shrinkage of con-
relatively young. Also, a longer con- cretc and stress relaxation of steel.
struction time is usually required. The frame is assumed to be composed
Time-dependent effects are therefore of segments of different ages rein-
more significant. forced with non-prestressed steel and
Time-dependent effects in statically with multistage prestressing (see Fig.
determinate structures prestressed in 1).
stages were studied by Danon and The method is directly applicable,
Gamble$ and by Ghali, et al. 9 Stresses but not limited, to bridges built by the
and deformations for each cross sec- cantilever erection method. The loads
tion were considered separately. De- considered are self weight, prestress,
flection was obtained by numerical and superimposed sustained loads.
integration of the curvatures at various Variation of the support conditions
cross sections along the member. during construction or afterwards is
Thenoz 10 used the force method of also considered. Data related to mate-
analysis to investigate the effect of rial and geometric properties, and
creep only on the statically indeter- construction schedule are assumed to
minate forces which develop when be available.
two concrete cantilevers are joined to The method of analysis assumes
form a single span with built-in ends. that concrete creep is proportional to
The concrete had the same age stress, and thus superposition of
throughout and the effect of the pres- stresses and strains is assumed valid.
ence of steel was not considered. The stiffness (displacement) method

68
is adopted for the determination of the prestressed steel is considered to be a
stress and displacement increments of linear elastic material obeying
the structure in a step-by-step proce- Hooke's law.
dure. For stresses within the service
range, the instantaneous strain and
creep of concrete are assumed to be
General Description linearly proportional to the applied
of Proposed Method stress. Thus, a stress increment Of^,
applied and sustained for a period of
A step-by-step computer procedure time, produces a strain which equals
is adapted.: The same method was de- (Of^/E,) (1 + v); where E, is the mod-
veloped in an earlier paper" for con- ulus of elasticity of concrete and v a
tinuous frames with composite cross creep coefficient equal to the ratio of
sections. The theoretical derivations creep at the end of the period consid-
will not be repeated here. Only the ered to the instantaneous strain.
differences in applying it to segmental Thevalue of E, is considered a
construction as well as the basic prin- function of the age of concrete at the
ciples and assumptions will be dis- time of application of stress incre-
cussed. ment, while the creep coefficient v is
The time for which the bridge is a function of both the age at loading
analyzed, usually an extensive period, and the duration for which the stress
is divided into discrete intervals. The is sustained.
stress increments in each interval are If the time is divided into intervals
assumed to occur at the middle of the during which the stress changes and
interval. The strain increments in an also shrinkage occurs freely, the total
interval are calculated in terms of the concrete strain (instantaneous plus
stresses applied in that interval and in creep plus shrinkage) occurring be-
preceding ones. Instantaneous ap- tween the beginning of the first inter-
plied loads such as the prestressing or val and the end of any interval i is:
the self weight are assumed to occur
at the middle of an interval of length E e (i + 1/2,0)=
zero.
The bridge superstructure is
f c U) [ 1+ v (+ )]}
,j +
idealized as an assemblage of linear E,
prismatic elements connected at Il l
1
nodes. The nodes are on the centroi- S(i + 1/2, 0) (1)
dal axis of the cross section. For each
interval, the usual displacement (stiff- where i and j refer to the time at the
ness) method of structural analysis is middle of the ith and jth intervals;
used to calculate the increments of [i + ( r/2)] refers to the time at the end
displacements and stresses. of the ith interval; and 0 refers to the
time at the beginning of the first
interval, in which the first stress in-
Constitutive Relations crement is applied to the concrete.
Thus, Of(j) = concrete stress in-
Three different materials are in- crement introduced at the middle of
volved: (1) concrete; (2) prestressing the jth interval; E(j) = modulus of
steel; and (3) non-prestressed rein- elasticity of concrete at the middle of
forcing bars. Because of creep, the the jth interval; s Pi + ( 1/2), 0] = the
first two materials have a time-de- free shrinkage of concrete between
pendent stress-strain relation. Non- the beginning of the first interval and

PCI JOURNAL/July-August 1979 69


the end of the ith interval; and v In segmental construction, pre-
Li + ( 1/2), j] = creep coefficient = ratio stressing is usually introduced in
of creep at the end of interval i to the stages. In the same cross section, ca-
instantaneous strain caused by a sus- bles tensioned at different stages ex-
tained stress introduced at the middle hibit different relaxation losses at any
of intervalj. specific time. This is accounted for in
Eq. (1) is a simple superposition of the present method by considering
strain caused by stress increments each set of cables tensioned at one
which are assumed to occur at the stage as a separate component.
middle of the time intervals. The non-prestressed steel under-
The strain change in prestressed goes no relaxation, thus its strain is
steel occurring between the begin- given by an equation similar to Eq. (2)
ning of the first interval and the end of but with the last term omitted:
the ith interval is:

1/2,0)= E.s (i + l/2 > 0) = E


1 S ^ f, (j)
E ns (i +
=1
(3)
1
E: ^fPS(7) .fr(1) (2) The subscripts ns refer to non-pre-
j=1 L stressed steel.
where E3 is the modulus of elasticity
of prestressed steel; AfPS (j) is a
change in its stress occurring during Step-by-Step Procedure
the middle of thejth interval; Of,. (J) is
a "reduced" value of the stress relax- The equations of the previous sec-
ation during the same period. This last tion are used to calculate the incre-
term is included because the relax- mental strain at any fiber of the bridge
ation causes a part of the tension to be cross section. During the ith interval,
lost without a corresponding change the change in concrete strain is the
in strain. difference of strain values calculated
In Eq. (2) a "reduced" relaxation by Eq. (1) at the end of the intervals i
value is used as compared with the and i-1.
"intrinsic" relaxation Lfro that would
occur in a test in which the tendon is L1e^(i)_ Af^(i) ^I+v(i+i/2,i)^ +
E,i)
stretched between two fixed points.
The reduction is due to the fact that in
a prestressed concrete member, creep I
SI I Ef v (i + 1/2,j) -
and shrinkage of concrete cause a l j=1

continual shortening of the tendons.


Their relaxation, therefore, occurs v(i r/2,j)II+As(i) (4)
under the effect of lower tensile
stresses than those encountered in The first term in this equation is the
constant length tendons. instantaneous strain plus creep caused
Empirical equations based on labo- by the incremental stress Of(i) occur-
ratory tests, expressing the intrinsic ring between the instant when it is
relaxation fro in terms of time and ini- introduced (which is the middle of the
tial stress, ffS0 , are available. 12 , 13 In- ith interval) and the end of the same
crement of reduced relaxation, Af,. (i) interval. The term inside the braces
in interval i can be calculated in terms sums up the effect of creep during the
of time, initial stress, fP80 and tendon ith interval due to stresses introduced
shortening in preceding intervals." in preceding intervals. The third term

4]
is the free shrinkage in interval i Thus, the initial strains Ye (i) are
Eq. (4) can be rewritten in the form: known quantities, which can be
treated in the same way as if they
fc (i) +
DE c (i) _ _ AE c(i) (5) were produced by a change of tem-
E ce (i) perature of known magnitude. The
where Dee is equal to the sum of the term "initial," often used in conjunc-
second and third terms in Eq. (4); its tion with the stress analysis for the
physical meaning is discussed above. effect of temperature variation, should
The value E Ce (i) represents an "effec- not be confused with the instantane-
tive" modulus of elasticity for con- ous elastic deformation.
crete in interval i: From the above discussion, it can
be seen that for each time interval a
linear elastic analysis is performed for
E ee(i ) = Ee(i) (6)
1 + U (i + ,i) the bridge structure, which is as-
sumed to have a composite cross sec-
By a similar treatment using the
tion made up of the three materials:
constitutive relation for prestressed
concrete, prestressed steel and non-
steel [see Eq. (2)] the incremental
prestressed steel.
strain occurring during the ith interval
For concrete, an effective modulus
can be expressed as follows:
of elasticity is used, with a value
varying in each interval according to
DE ng (Z ) _ fns
(Z) (i)
+ AEns (7) Eq. (6); for the two kinds of steel the
E,,
constant values E P, and E ns are
where employed in all intervals. In any
interval i, the concrete and the pre-
DEpg (i ) _ ^p (i) (8) stressed steel are considered as
though subjected to a change in tem-
The increment in strain in the non- perature producing initial (free)
prestressed steel occurring during the strains Dee (i) and Ye8 (i) of known
ith interval '[see Eq. (3)] is: magnitude.
The stress increment Af(i) in each of
(Z) (9)
AE ., (i ) _ A f,, the three materials is an unknown to
E,
be found by the analysis for interval i;
The constitutive relations for the it represents the stress produced by
three materials involved are in a the external loads (if any) applied at
linear form [Eq. (9)] or a pseudolinear the middle of the interval plus the
form [Eqs. (5) and (7)]. The strain stress necessary to restore compatibil-
AE (i) in each of Eqs. (5) and (7) repre- ity of strain in the three materials
sents "initial" deformation indepen- forming the composite cross section.
dent of the stress increment intro- This compatibility has been tem-
duced in interval i, and thus its value porarily violated by the introduction
can be determined if the stress incre- of the initial strain A (i).
ments in preceding intervals are In the analysis, plane cross sections
known [see the last two terms in Eq. of the bridge are assumed to remain
(4)] . plane during deformation. This im-
In the step-by-step method, a com- plies that the bending theory of shal-
plete analysis of the structure is done low beams is applicable. Brown and
in each interval. When the analysis is Burns" in their analysis of instantane-
done for interval i, the stress incre- ous stresses and deformations of the
ments in all preceding intervals would Corpus Christi segmental bridge,
have been determined in earlier steps. using a "finite segment" method, have

PCI JOURNAL/July-August 1979 71


confirmed the applicability of this as- elements with average properties of
sumption. the two end sections of each element.
Further, compatibility of strain is The prestressing forces are repre-
assumed in the concrete and adjacent sented by a set of self-equilibrating
steel at all fibers and at all sections; nodal forces. Their values are the ini-
that is, the strain increment in a given tial forces including friction losses at
time interval is equal in both concrete transfer. Losses due to creep, shrink-
and adjacent steel. This second as- age and relaxation of steel are auto-
sumption is not always valid during matically accounted for in the proce-
construction of the bridge. Grouting of dure described above.
the prestressing ducts in post-ten- As mentioned earlier, linear elastic
sioned segmental bridges is often analysis is performed for each time
postponed until the end of some or all interval; the usual displacement (stiff-
of the prestressing stages. During the ness) method of analysis is employed.
period the tendons are left unbonded, The analysis gives increments of dis-
the time-dependent stress changes placements and stresses occurring in
should be "averaged out" through the the interval. These are to be added to
entire length of the tendon. the increments in all the preceding
The proposed method can be ex- intervals to give the total values. The
tended to account for this by numeri- analysis is thus done step by step until
cally integrating the prestressing steel the end of the last time interval.
strain increments along the tendon Because the analysis of the structure
length and adjusting the concrete and covers a period that includes its con-
steel stress accordingly. However, it is struction stages, the length, number of
believed that this further iteration nodes and boundary conditions of the
within each time-interval would result structure can be different for different
in a considerable increase in compu- time intervals. In the choice of the
tation cost without significantly im- time intervals, their limits should
proving the overall stress and coincide with the events of applica-
deformation-time relationships. Fur- tion of external loads including pre-
ther research would help evaluate this stressing and of the change in bound-
hypothesis. ary conditions. External applied loads
are considered to be introduced at the
middle of time intervals of zero dura-
Computer Implementation tion. This is further clarified by the
example in the section "Application."
A computer program based on the Additional details of the method of
above theory is described by the flow analysis are given in Reference 11. A
chart in Appendix II. It is concerned listing of the computer program and
with structures considered as plane sufficient instructions for its use are
frames. The strain, and hence the given in Reference 15. In this pro-
stress at any fiber, are determined gram, the time variation of the con-
from three nodal displacements: crete modulus of elasticity E, the
translation components in two orthog- creep coefficient v, the shrinkage s,
onal directions plus a rotation at one and the intrinsic relaxation of pre-
point of the cross section (usually cho- stressed steel are assumed according
sen as the centroid of the section). to equations listed in Appendix 1 of
The structure may have curved mem- Reference 11. If, however, the analyst
bers of variable cross section, but in would like to use different equations,
the analysis they are approximated as they can be accommodated in the pro-
an assemblage of straight prismatic gram by changing the corresponding

72
SEGMENT I SEGMENT 2

1 2

^ B

F
A C
JOINT I B B' 1 D2B '11 3
D3 2
"2C TYPICAL DISPLACEMENTS
INITIAL DISPLACEMENTS OF AT A JOINT
JOINT C: D3C^C'

D IC = DIB JOINT 3
D2C = D 2B + D 3 B !2 DIC

D 3C = 038
Fig. 2. Joint displacements before application of loads of Segment 2 in match-cast
cantilever construction method.

statements; the details of how this can Segment 2. The displacement incre-
be done are given in Reference 15. In ments in Stage 2, caused by the new
this way, the program can be used prestressing and the self weight of
with any chosen time functions. Segment 2, are to be measured from a
displaced "datum" AB' C' to give the
total displacements measured from
the horizontal ABC.
Deflections During Fig. 3a shows the time-dependent
Cantilever Erection deflection of a cantilever built in four
stages. For clarity, the deflected shape
Segmental construction is distin- of each segment is represented by a
guished by the type of joint between straight line and no horizontal dis-
the segments. The two basic types of placements are shown. At the end of
joints used are the wide cast-in-place Stage 4, and just before connecting
joints and the match-cast joints. 7 With the cantilever with the remainder of
the wide joints, curving (shaping) of the structure, the deflected shape of
the structure may be obtained within the cantilever is given by the line
the joint. Match-cast joints are more AB'C'D'E'.
commonly used. Perfect fit of adjacent A method to eliminate or reduce the
elements is achieved by casting each discontinuity (relative rotation and
segment against its neighbor. In this relative deflection) of the two meeting
type, the required shape of the ends of adjacent cantilevers is to build
superstructure has to be built into the camber into the segments. To elimi-
segments during the casting proce- nate the deflection of the cantilever at
dure. Match-cast jointing will be con- the end of Stage 4 (Fig. 3b), the
sidered in the following discussion. camber to be built into each segment,
The step-by-step method described is equal and opposite to the deflection
here gives increments of displace- measured from the tangent to its joint
ments occurring at each stage of con- with the preceding segment. It is
struction. Fig. 2 shows the horizontal therefore very important to accurately
and vertical translations and the rota- predict deformation of the structure at
tion of Joint B just before erecting various stages of construction.

PCI JOURNAL/July-August 1979 73


Segment I I 2 I 3 4

Stage I Stage 2

Di
A B C D E
Stage 3
B' Deflection at
Stage 4
end of cantilever
C' at time of its
D 2connection with
Dadjacent part
Camber to be built in of bridge
in individual segments E,

(a) Deflection without built-in camber

Stage I Di
Stage 4
D2

A B C D E

(b) Deflection with built-in camber


Fig. 3. Deflection of a four-segment cantilever.

ments, while supported on falsework,


Application and then stressing the bottom cables
in the span. The rotational restraint at
Pier 1 is then released. The process is
The method of analysis is applied to repeated for the other half of the
the three-span symmetrical bridge bridge starting from Pier 2 at Stages 6
shown in Figs. 4 and 5. The erection through 10.
of the bridge starts at Pier 1 where The bridge construction is com-
four segments are successively placed pleted by dropping in the central
on each side of the pier, and tied to- segment and stressing the continuity
gether by post-tensioning in four cables in Span 2 while allowing hori-
stages. While the cantilever erection zontal movement at Pier 2.
is in progress, the cantilever is tem- The area and eccentricity of the
porarily fixed to the pier to produce a prestressing steel at the various con-
stable system in which unbalanced struction stages are given in Fig. 4.
cantilever moments, if any, can be Other dimensions and concrete sec-
transferred to the pier. tion properties are shown in Fig. 5.
Span 1 is completed at Stage 5 by Non-prestressed steel is uniformly
assembling the remaining three seg- distributed in the cross section.

74

Pier
0.5m,typ.(1.6ft.) G-Fixed rotation and
against translation
G 0.2m,typ.(0.7ft.)
0 2.8 m erection
Ito 4, cantilever
9.2ft Stages
Z
D
G

A 5705 5379 5379 8150 7335 mm2


8.44 8.34 8.34 12.63
15.16 in2 (typical, spans I and 3)
11.37
1.15mk
3.77 of
Stage 5, completion span (j
I

0.15m,typ.(0.5ft.)
support
Roller Hinge
support Pier 2
A ps = 12600 11970 11970 7980 mm2
19.5318.55 in2
18.55//0.12

erection
Stages 6 to 9, cantilever
Soon I iSpan 2 , Span 3

Stage 10, completion of span


Aps = 3912 7335 5379 5379 7335 3912 mm2
6.06 11.37 1 8.34 8.34 111.37 p.06 in2

53.5 m (175 ft.) 65 m (213 ft.) i.' 53.5 m (175 ft.)


-4 Stage II, introduction of continuity in central
Fig. 4. Construction sequence of bridge example.
V
0)
Symm.
Pier I I Pier 2
Section A Section B I
Node I 2 3 4 5 6 7 18 9 10 II 12 13 14 15 16 17 18 19 20 21 22 23 24

m Concrete section
8 type

175 ft. H 21 175


(a) Longitudinal section
1_ 16m. _I
52 ft.

y= 0.974 m C entroidl of co ncrete Yns' 1.00 m


28m Centroid of nonprestressed
steel
9.2 ft. A ns = 22200 mm2
000
Type A2 y I m4
Tim I 10.035 0.974 10.058
231ft. 2 11.055 1.093 12.027
Prestressed 3 12.075 1.340 14.942
steel ducts
(b) Cross section (c) Concrete section properties
(lm=3.28 ft.; lm2 =10.7ft.2; Im4 =II6 ft4)
Fig. 5. Dimensions of bridge example.
0 Section A
C-
0
C
Creep,shrinkage and relaxation
z considered
CC Top ----- Creep,shrinkage and relaxation
ignored
Compression
CD
C
10 Rntlnm

CD
CD 9

o 6
a_ 8
N
N
0)
N
6
d 4 U)

3 4

2 ----)
2
I
I I I I
20
IC 40
30 50
+11
Tension
4
Fig. 6. Concrete stress in Section A, near Pier 1.
w
Pier

184

1260
82
1250
180
1240

1230 178
N
1220
O
a_ 176 y
1210 U)
4)

174 U)
1200

N 1190 172
1180
170
1170

1160 160

1150
10 30
20 40 1200
1000
50 1400 1600
1800 2000
Time (days)

Fig. 7. Stress in the prestressing steel at Section A, near Pier 1.


Material Properties Discussion of Results
Concrete:
Weight = 20 kN/m3 (125 lb/ft3) A computer program 15 based on the
method presented in this paper was
E, (28 days) = 34 GPa (5000 ksi)
used to give, for selected cross sec-
Non-prestressed steel: tions of the bridge, the variation with
E. = 196 GPa (28,000 ksi) time of stress in concrete, non-pre-
stressed steel and the prestressing
Prestressing steel: steel. The program also gives the time
E 8 = 190 CPa (27,000 ksi) development of the deflection, hori-
fps. = 1.77 GPa (256 ksi) zontal displacement and rotation at
fPB^ = 1.50 GPa (218 ksi) the nodes numbered in Fig. 5. Figs.
fp. = 1.24 GPa (179 ksi) and intrinsic 6-11 are plots of some of the results.
relaxation at time infinity Fig. 6 depicts the concrete stresses
fro = 31 MPa (4.5 ksi) in Section A, near Pier 1 (see Fig. 5).
The vertical lines indicate the instants
Segments are assumed to be cured of load application. The broken lines
for 3 days (t d = 3) and then kept in give the stresses when the time-de-
storage until they are transported and pendent effects are ignored, that is
erected at the age of 28 days; when v = s = f o = 0. The time-de-
Creep coefficient' s '" v N = 2.0 and pendent analysis yields tension
shrinkage s (t., 28 days) = 300 X 10-6. stresses in the top fibers of the sec-
The time variation of E, v, s and fro tion, while calculations ignoring the
are assumed to follow the equations time-dependent effects would show
given in the Appendix of Reference compression in the same fibers. Bas-
11. ing the live load capacity on this com-
pression stress is therefore not con-
Time Intervals servative.
29 time intervals are chosen; the The time-dependent effects on the
interval limits are (days): 2, 2, 5, 5, 8, concrete stress at Section B, near the
8, 11, 11, 15, 15, 19, 19, 22, 22, 25, 25, center of Span 2 (Fig. 9) are more pro-
28, 28, 32, 32, 35, 35, 45, 45, 60, 100, nounced compared to Section A. Con-
200, 500, 1000, and 2000. necting the two ends of the cantile-
Intervals with a zero duration are vers at Stage 11, rendering the struc-
those at the "middle" of which "sud- ture statically indeterminate, results
den" loads are applied or support in time-dependent indeterminate
conditions changed. forces preventing any further de-
velopment of differential deflections
Loading and rotations of the cantilever ends.
Loads representing prestress and Figs. 7 and 8 give the time-variation
self weight are applied in intervals 1, of the stress in the multi-stage pre-
3, 5, 7, 9, 11, 13, 15, 17, 19 and 21 stressing steels and in the nonpre-
which correspond to the eleven con- stressed reinforcement at Section A.
struction stages. In Interval 23, The deflected shape of the bridge at
superimposed dead load of intensity various construction stages is shown
45kN/m (3.1 kips/ft) is applied. in Fig. 10. By accurately predicting
deflection, it is possible to build in
Support Conditions
appropriate camber while casting the
Support conditions are changed in segments to eliminate the vertical de-
Intervals 1, 9, 11, 19 and 21; that is, in flection 18 19 at Nodes 4, 21, 12 (or 13).
Stages 1, 5, 6, 10 and 11 (see Fig. 4). Fig. 11 demonstrates the significance

PCI JOURNAL/July-August 1979 79


Compression

I(

o i
a.

v-i

0 20
10 30 50
40
Time (days)

Fig. 8. Stress in the non-prestressed steel at Section A, near Pier 1.

of time-dependent effects on vertical concrete segmental construction can


deflection near the center of the inner be greatly in error unless accurate ac-
span. count is taken of the effects of creep
The values plotted in Fig. 10 are and shrinkage of concrete and the re-
deflections measured from one hori- laxation of prestressed steel.
zontal datum without any modification The presence of the non-prestressed
which may be done by building in steel should not be ignored, particu-
camber in the precast segments, or by larly because of its important effect on
initially setting the falsework. For the deflections. Such an analysis re-
example, at t = 15 days, the deflection quires lengthy computations, because
at Node 4 is 1.7 mm (0.07 in.); the the loads are applied in several stages
abrupt change in deflection shown in and because the structure is composed
Fig. 10 can be eliminated in the actual of segments of different ages.
structure by adjusting the level of Furthermore, the structure changes
the falsework supporting the segments in geometry and support conditions as
at the left of Node 4. the construction progresses. The
problem is well suited to the step-by-
step computer method of solution
presented and used in this paper.
Conclusions The bridge example analyzed is a
precast segmental bridge erected by
The prediction of deflections and the -cantilever method. The results
stress redistribution in prestressed clearly demonstrate the significance of

80
C)

0C
C-

M
z
C Section B EVENTS:
c 31.1 m A - ERECTION STAGE 11
B - APPLICATION OF WEARING SURFACE
n
c 102 f t. I
c
to C on I Top Creep, shrinkage and relaxation
V
considered
---- Creep, shrinkage and relaxation
6 ignored
Bottom
0 A
B
a-
4 0.6
N

2 Bottom
----------_ -------- 0.2 `n
Top


10
20
30
40
50 1000
1200 1400 1600
1800 2000
Time (days)
Fig. 9. Concrete stress in Section B near the middle of Span 2.

00
1
Abutment Pier I Pier 2 Abutment
Stage No. 10 5 T^4.T^32 1 4 1 ( 1,i4 2^ 14 3 b ,^4 bj II I4 9 1, ^ B N 1 4 7 0 I^6 0 1,6^ 1 7 i1 _8^ i .,9'.110
^ ^` ^I' T T T T T"-T 7 T T T T ^ T 7 1
Node No. I 2 3 4 5 6 7 819 10 II 12 13 14 1.5 16 17 1.8 19 20 21 22 23 24
t 5 days r
8 days
10.8 mm 10.8 mm
II days 0.43 in. 0.43 in.
Fixed support
1.7mm1 11.7 mm
15 days 007in.T 0.07 in.
6 11.9mm Hmge support
0.54 7in.
19 days 24 mm
0.94 in.

15.9mm 14.2m
11.5mm

35 1 days 048 mm
0.90 in.

1.5mm T<2 0.7 mm I /Roller support 6.3 mm


0.06 in. /0.03 in. ,0.25 in.

23.6 mm
2000 days 13 mml0.93 in.
^ n.

Fig. 10. Vertical deflection of bridge at various construction stages (without any
corrections, as for example by built-in camber during casting of segments).
Deflection Deflection
(mm) (in.)
20

4
n
E -10
0
U
Time (days) 0.2
1000 200 1400 1600 1800
0

0.2

' 10 ----- fib ----------- 0.4


0
0.6
O
20 0.8

o`
I.0
3
30 1.2
0
0
1.4
40

Fig. 11. Deflection of Node 12; (a) Creep, shrinkage and relaxation considered;
(b) Creep, shrinkage and relaxation ignored.

the time-dependent effects despite


the fact that in precast construction, References
creep and shrinkage of concrete are
considerably less than those encoun- 1. Podolny, Jr., Walter, "An Overview of
tered when the bridge segments are Precast Prestressed Segmental
cast in place. Bridges, PCI JOURNAL, V. 24, No. 1,
Considerable misalignment prob- January-February 1979, pp. 56-87.
lems can develop due to differential
time-dependent deflections at the 2. Ballinger, C. A., and Podolny, W.,
"Segmental Bridge Construction in
ends of two joining parts of a bridge.
Western EuropeImpressions of an
These deflections can be predicted IRF Study Team," Proceedings, Con-
accurately by the method presented. ference conducted by Transportation
The anticipated misalignment can Research Board, National Academy of
then be prevented by adjusting the Sciences, Washington, D.C., TRR No.
formwork before the segments are 665, V. 2, September 1978, pp. 182-
cast. 191. See also a detailed report by Bal-
linger, Podolny and Abrahams, Inter-
national Road Federation, 1023
Washington Building, Washington,
D.C., July 1978, 150 pp.
Acknowledgment
3. Libby, J. R., and Perkins, N. D., Mod-
ern Prestressed Concrete Highway
This research was financially supported Bridge Superstructures, Design Prin-
by grants from the National Research ciples and Construction Methods,
Council of Canada, The University of Cal- Grantville Publishing Company, San
gary and West Virginia University. Diego, California, 1976, 254 pp.

PCI JOURNAL/July-August 1979 83


4. Precast Segmental Box Girder Bridge 12 Magura, D. D., Sozen, M. A., and
Manual, Prestressed Concrete Insti- Siess, C. P., "A. Study of Stress Relax-
tute, Chicago, 1978, 124 pp. ation in Prestressing Reinforcement,"
PCI JOURNAL, V. 9, No. 2, April
5. Lacey, G. C., Breen, J. E., and Burns, 1964, pp. 13-26.
N. H., "State-of-the-Art for Long Span
Prestressed Concrete Bridges of Seg-
13. PCI Committee on Prestress Loss,
mental Construction," PCI JOURNAL, "Recommendations for Estimating
V. 16, No. 5, September-October 1971, Prestress Losses," PCI JOURNAL, V.
pp. 53-77. See also discussion of paper 20, No. 4, July-August 1975, pp. 43-75.
in PCI JOURNAL, V. 17, No. 1, Janu-
ary-February 1972, pp. 104-108.
14. Brown, R. C., Jr., and Burns, N. H.,
6. Muller, Jean, "Ten Years of Experi- "Computer Analysis of Segmentally
ence in Precast Segmental Construc- Erected Bridges," Journal of the
tion," PCI JOURNAL, V. 20, No. 1, Structural Division, ASCE, V. 101, No.
January-February 1975, pp. 28-61. ST4, Proceedings Paper 11218, April
1975, pp. 761-778.
7. PCI Committee on Segmental Con-
struction, "Recommended Practice for
Segmental Construction in Prestressed 15. Tadros, M. K., Ghali, A., and Dilger,
Concrete," PCI JOURNAL, V. 20, No. W. H., "Computer Program for Anal-
2, March-April 1975, pp. 22-41. ysis of Stresses and Deformation in
Segmental Construction, a User's
Danon, J. R., and Gamble, W. L., Manual," Research Report, published
"Time-Dependent Deformations and by Departments of Civil Engineering,
Losses in Concrete Bridges Built by the University of Nebraska at Omaha,
the Cantilever Method," Report No. and the University of Calgary, Canada,
UILU-ENG-77-2002, Civil Engineer- 1979.
ing Studies, University of Illinois at
Urbana-Champaign, Urbana, Illinois, 16. ACT Committee 209, Subcommittee 2,
January 1977, 169 pp. "Prediction of Creep, Shrinkage and
Temperature Effects in Concrete
9. Ghali, A., Sisodiya, R. G., and Tadros, Structures," SP -27, American Concrete
C. S., "Displacements and Losses in Institute, Detroit, 1971, pp. 51-93.
Multistage Prestressed Members,"
Journal of the Structural Division, 17. International Recommendations for
ASCE, V. 100, No. ST11, Proceedings the Calculation and Execution of
Paper 10968, November 1974, pp. Concrete Structures, Comite Euro-
2307-2322. peen de Beton-Federation Inter-
nationale de la Precontrainte, June
10. Thenoz, M., "Redistribution des Ef- 1970, Cement and Concrete Associa-
forts Par Fluage dans les Ponts Con-
tion, London, England.
struits par Encorbellement" (Redis-
tribution of Internal Forces Due to
18. Mathivat, J., "Recents Developpe-
Creep in Segmental Construction), 7th
ments des Ponts a Voussoirs Prefab-
FIP Congress, Federation Inter-
riques" (Recent Developments in Pre-
nationale de la Precontrainte, Con-
cast Segmental Bridge Construction),
tribution of French Techniques, New
International Association for Bridge
York, 1974, pp. 25-27.
and Structural Engineering, IABSE
11. Tadros, M. K., Ghali, A., and Dilger, Surveys S-2/77, May 1977, 24 pp.
W. H., "Time-Dependent Analysis of
Composite Frames," Journal of the 19. Mathivat, J., Constructions par Encor-
Structural Division, ASCE, V. 103, No. bellement des Ponts en Beton Precon-
ST4, Proceedings Paper 12893, April traint, Editions Eyrolles, 1979, Paris,
1977, pp. 871-884. France, 340 pp.

84
APPENDIX I-NOTATION

A = cross-sectional area = used as prefix to indicate


incremental value

f
E = modulus of elasticity
e = normal strain, positive
= normal stress, positive when corresponds to ex-
when tensile; subscripts tension
pso, psy and psu indicate s [i + 1/2, j 1/2] = shrinkage of con-
initial, 0.1 offset and ulti- crete during period {t[i +
mate stress in prestressed 1/2] t U 1/2] }
steel, respectively t = time, in days, measured
I = moment of inertia of sec- from reference date
tion v[i + Y2, j] = creep coefficient, ratio of
i, j = time interval number, re- creep strain at time
ferred to in step-by-step t[ i + 1/2] to instantaneous
calculation; when used strain caused by constant
with time-dependent pa- sustained stress applied at
rameters, they indicate t (j ); subscript N is used to
time at middle of interval; indicate normal creep,
i /2 and i+ 1/2 refer to equals value of creep coef-
beginning and end of inter- ficient when t[i + 1/2] = in-
val i, respectively finity and t3 = 28 days

Subscripts
c = concrete r = reduced relaxation in short-
e = effective modulus of elas- ened prestressed tendon
ro = intrinsic relaxation in con-
ticity [Eq. (6)]
stant-length tendon
ns = non-prestressed steel
Superscript = "initial" value de-
PS = prestressed steel fined in Eqs. (5) and (7)

Additional Notation
Used in Flow Chart

DEL = nodal displacement incre- in prestressed steel re-


ments quired to eliminate initial
DFC = increment of stress result- strains
ant in concrete F = nodal forces
DFPS = increment of stress result- TDEL = total displacements at end
ant in prestressed steel of intermediate interval "i"
TFC = total stress resultant in con-
DFNS = increment of stress result- crete at end of interval "i"
ant in non-prestressed TFPS = total stress resultant in pre-
steel stressed steel at end of in-
DFRC = increment of internal force terval i
in concrete required to TFNS = total stress resultant in
eliminate initial strains non-prestressed steel at
DFRPS = increment of internal force end of interval i

PC I JOURNAL/July-August 1979 85
APPENDIX II-FLOW CHART
START

READ CREEP, SHRINKAGE, RELAXATION,


MODULUS OF ELASTICITY /

DIVIDE TIME INTO "m" SMALL


INTERVALS

INITIATE STRESS: TFC = O,TFNS = O,


TFPS = INITIAL PRESTRESSING;
AND DISPLACEMENTS: TDEL = 0

YES
READ CHANGES IN DIMENSIONS, REINFORCEMENT
GEOMETRY. SUPPORT CONDITIONS

READ EXTERNAL LOADS, PRESTRESS FORCES,


FORCES CAUSED BY CHANGE IN SUPPORTS....E7

DETERMINE THE "INITIAL" STRAIN INCREMENTS "A Ec" BASED


ON CREEP AND SHRINKAGE, AND "Alps" BASED ON RELAXATION.

CALCULATE THE RESTRAINING STRESSES "DFRC"& "DFRPS" NEEDED


TO COUNTERACT "A " AT EACH CROSS SECTION.

DETERMINE EQUIVALENT NODAL FORCES "F" TO


EQUILIBRATE "DFRC" AND "DFRPS"

NO
^
STAGE?

F = F + EXTERNAL FORCES

86
CALCULATE ELEMENT STRESS AND STIFFNESS MATRICES
USING "Ece ( i ')" AND COMPOSITE SECTION "A" AND "I"

GENERATE THE STRUCTURE STIFFNESS MATRIX FOR


ERECTED PART AND CURRENT SUPPORT CONDITIONS

SOLVE FOR NODAL DISPLACEMENT INCREMENTS "DEL"


AND STRESS INCREMENTS "DFC, DFPS, DFNS",
CAUSED BY "F" OR PRESCRIBED SUPPORT DISPLACEMENTS

TOTAL STRESS INCREMENTS IN 'i"


DFC = DFC + DFRC
DFPS = DFPS + DFRPS
DFNS = DFNS + 0

SAVE "DFC" ON TAPE TO BE USED


TO DETERMINE ",Zc" IN FOLLOWING INTERVALS

TOTAL STRESS AND DISPLACEMENT UP TO


THE END OF "i"
TFC = TFC + DFC
TFPS = TFPS + DFPS
TFNS = TFNS + DFNS
TDEL = TDEL + DEL

CORRECT "TDEL" FOR NONHORIZONTAL DATUM


AT CANTILEVER ENDS

WRITE "TFC, TFPS, TFNS, TDEL"

NO
i=i+1i=m?

YES

STOP

Discussion of this paper is invited.


Please forward your comments to
PCI Headquarters by Jan. 1, 1980.

PCI JOURNAL/July-August 1979 87

Vous aimerez peut-être aussi