Académique Documents
Professionnel Documents
Culture Documents
Contract No.
DEVELOPMENT DESIGN
SPECIFICATION
D7
STORMWATER MANAGEMENT
Return to Contents
This Specification is Councils edition of the AUS-SPEC generic specification part and includes Councils primary amendments.
Details are provided below outlining the clauses amended from the Council edition of this Specification Part. The clause numbering
and context of each clause are preserved. New clauses are added towards the rear of the specification part as special requirements
clauses. Project specific additional script is shown in the specification as italic font.
The amendment code indicated below is A for additional script M for modification to script and O for omission of script. An
additional code P is included when the amendment is project specific.
Amendment Key Topic addressed in amendment Clause No. Amendment Author Amendment
Sequence No. Code Initials Date
GENERAL ................................................................................................................................3
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 1
STORMWATER MANAGEMENT
Contract No.
D7.36 DEFINITIONS...........................................................................................................................35
APPENDIX A.......................................................................................................................39
TABLE D7A 2 WETLAND ZONES , TYPICAL SPECIES AND FUNCTIONAL PROCESS (Somerset et al 1996)..................39
TABLE D7A 6 POLLUTANT REDUCTION EFFICIENCIES ( Brisbane City Council Design Guidelines for Stormwater Quality
Improvement Devices Final Draft 4 November 1999)...........................................................................49
TABLE D7A 7 Brisbane City Council design guidelines for Stormwater Quality Improvement Devices Final
Draft 4 November 1999 .........................................................................................................50
Figure D7-10 Hastings and Camden Haven River Catchments water quality regions ......................................51
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 2
STORMWATER MANAGEMENT
Contract No.
STORMWATER MANAGEMENT
GENERAL
D7.01 SCOPE
1. Works covered by this specification include any land development or use including
Private, Council or other Authority works which may impact on the quality and quantity of runoff Land Development
discharging from the site or to any natural or artificial waterway or water body. It includes, but, is not limited to and Authority
construction, operation and use of: Works
Subdivisions
Buildings, structures and surrounds
Earthworks, dams, lakes, roadworks and drainage works
Trenches, pipelines
Development site works (access roads, car parks, landscaping, drainage works, pedestrian facilities,
fencing etc)
Extractive industries
Mining
2. This specification details the information relating to stormwater quality required to accompany development Specification
applications and construction certificate applications. Or in the case of Council or Authority works, Part V Details
assessments and detailed engineering plans.
D7.02 OBJECTIVES
1. To provide detailed design provisions in line with Ecologically Sustainable Development (ESD), Water Principles
Sensitive Urban Design (WSUD) and Total Water Cycle Management (TCM) and principles.
2. Ensure retention and enhancement of natural watercourses, aquatic habitat and riparian vegetation. Retain natural
watercourses
3. Ensure stormwater runoff meets specified quality objectives during the construction and occupation Stormwater Quality
phase of a development.
4. To promote scenic, landscape and recreational values for stream corridors through the integration of Integration
stormwater treatment techniques into the landscape by incorporating multiple use corridors that maximise the
visual and recreational amenity of developments.
5. Provide an effective major and minor stormwater system that is cost effective and incorporates life Effective
cycle costs (LCC) of investigation, design, operation, maintenance and replacement of stormwater infrastructure. Stormwater
systems
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 3
STORMWATER MANAGEMENT
Contract No.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 4
STORMWATER MANAGEMENT
Contract No.
(e) Other
Tweed Shire Council
- D7 Stormwater Quality
North Coast NSW Sustainable Water Model Planning Provisions (Draft 2003)
Lower Hunter and Central Coast Regional Environmental Management Strategy (LHCCREMS)
- Draft Model Planning Provisions 1999 (Donovan, Cameron and Coombes)
AUSTROADS
- AP-R232 Guidelines for treatment of stormwater runoff from road infrastructure.
Water quality design objectives include, but are not limited to, the following: Water Quality
Objectives
Existing natural watercourses and riparian vegetation (with appropriate buffer widths) are to be retained
and restored. Natural watercourses shall not be replaced with artificial drains or pipes.
Land use development design will have regard to landform and drainage of the site, the physical
characteristics and limitations of soils (including identification of actual and potential acid sulphate soils)
and likely impacts on stormwater quality.
Designs shall ensure stormwater runoff discharged from development sites conforms with water quality
objectives as outlined in this specification.
Plan submission requirements include, but are not limited to the following:
Plans submitted with a development application must be sufficiently detailed to allow the feasibility of
stormwater quality management proposals to be assessed.
Plans submitted with a construction certificate must contain all appropriate engineering drawings,
operation/cleaning/monitoring/action/maintenance schedules.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 5
STORMWATER MANAGEMENT
Contract No.
2. No site works shall commence prior to approval of the Erosion & Sediment Control Plan (ESCP) and/or the
Stormwater Management Plan (SMP). Implementation must be supervised by personnel with appropriate Approval of the
qualifications and/or experience in soil conservation on construction sites. ESCP & SMP
1. Unless advised elsewhere in this specification, works to capture pollutants from stormwater runoff shall be Design Average
designed to accommodate a design storm equivalent to a 3 Month ARI Storm Event (for calculation purposes 40% Recurrence Interval
of the 1 year ARI storm event is to be adopted.), overflow / bypass arrangements are to be designed to (ARI)
accommodate a 1 in 100 year ARI storm event without erosion, scouring or structural damage to erosion or
sediment control devices, or remobilisation of previously deposited sediment.
2. Erosion and sediment control works shall be designed in accordance with Managing Urban Stormwater
Soils and Construction NSW Dept of Housing 1998 (referred to subsequently as [REF 1] . Australian Runoff References
Quality Manual The Institution of Engineers Australia (ARQ) and Acid Sulphate Soil Manual NSW Acid Sulphate
Soil Management Advisory Committee 1998 (ASSM).
b. An estimation of the average annual pollution loads from stormwater in kilograms of pollutant
exported per year, relating land use, annual rainfall, catchment runoff characteristics and
average pollutant concentrations to estimate the annual pollutant load generated from the
catchment under both pre and post development conditions (refer to D7.06.8). Once the
increase in pollutant loads is determined appropriate Stormwater Quality Improvement Devices
(SQIDs) shall be selected to conform to the criteria specified in Table D7-7. Refer to D7.25 and
Appendix A Tables D7A-6 & D7A-7 for SQID selection.
Refer to Appendix A and Specification D5 Stormwater Drainage Design for the parameters required for modelling Parameters
of catchments within the Hastings LGA.
7. Rainfall Data Set.
Refer to Aus-Spec D5 Stormwater Drainage for IFD information for each region within the Hastings LGA Rainfall Data Set
The file (refer to Drains & Music Base Files) available from council provides the climatic data set to be used for
modelling purposes.
8. For preliminary calculations, checking purposes and determination of pollutant loads for Low Risk Preliminary
Development the modelling technique using constant concentration levels may be used. The following Calculations Low
formula shall apply. Risk Developments
L = PCvCA
C = average event mean pollutant concentration (EMC) (mg/L) (refer to Chapter 3 of ARQ for landuse &
predicted pollutant loads) Refer to Table D7.4 and Appendix A Table D7A 9
9. For Preliminary calculations, determination of increased annual runoff volumes and determination of Preliminary
increased pollutant loads for High Risk developments and works the Spreadsheet file: Runoff Calculations High
Transposition V3-2.xls shall be available from Council. Risk Developments
10. For design purposes the Hastings LGA has been divided into regions with similar annual rainfall as Rainfall Regions
follows:
a. Coastal Region the area bounded by the eastern coastline, the northern & southern boundaries of the
Council LGA and the area east of the Pacific Highway.
b. Lower Inland Region the area bounded by the northern and southern boundaries of the Council LGA,
all areas west of the Pacific Highway with an elevation below 150m AHD.
c. Upper Inland Region the area as specified for the Lower Inland Region with an elevation above 150m
AHD.
11. The annual rainfall readings for the average dry, average and average wet year shall be used in Range of Rainfall
calculations to determine the variation in pollutant loads and to size proposed infrastructure accordingly.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 7
STORMWATER MANAGEMENT
Contract No.
TWMP
D7.07 TOTAL WATERCYCLE MANAGEMENT PLAN
1. A Total Water Cycle Management Plan shall be required for developments consisting of greater than 100
lots or greater than 8 Hectares in area (which ever is lesser). Refer to Appendix A Table D7A - 3 for
details of the requirements for a Total Watercycle Management Plan.
SMP
D7.08 STORMWATER MANAGEMENT PLAN
1. A Stormwater Management Plan shall be required for all developments. For the plan requirements of
High Risk Developments (Developments greater than 6 Lots and / or greater than 2500m) and Low Risk
Developments (Single dwellings and Duplexes less than 6 Lots or less than 2500m in area). Refer to
Appendix A Table D7A - 4
1. Buffer zones are corridors of vegetation adjacent to ephemeral and permanent waterways or disturbed Filters
areas. The vegetation shall be retained in order to filter suspended solids and reduce the nutrient levels in run-off.
Wetlands, stream and rivers adjacent to construction sites shall be protected by buffer zones.
2. Buffer zone performance increases as catchment area and slope gradient decreases. Buffer widths shall be Performance
nominated in accordance with Tables D7.2 and D7.3.
3. Where a conflict occurs in the determination of buffer widths between: slope, area, sensitivity & minor Width
tributaries the greater distance shall be adopted. Refer to Fig. D7.1 To determine the category of drainage channel
4 Buffer zones can reduce the need for other erosion and sediment control measures. However, Contaminated
contaminated water in a concentrated form shall require treatment both at its sources point and final disposal. Water
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 8
STORMWATER MANAGEMENT
Contract No.
1. Any change of landuse within a catchment causes a variation to flow rate and duration of stormwater Landuse
runoff.
2. To maintain stormwater runoff from a catchment equivalent to the pre developed or existing flow rate
and duration a combination of detention and retention facilities shall be required.
3. Detention facilities shall be designed to attenuate the change in peak flow rate due to a change of Detention
landuse within a catchment to a level equal to the pre developed flow rate. Refer to Auspec Design Specification
D5 Stormwater Drainage for details of detention requirements.
4. Retention facilities shall be designed to hold stormwater runoff within the catchment for a period of time Retention
to enable water to continue in the hydrological cycle via infiltration and evapotranspiration. Refer to Section 7.31
Infiltration Systems and Section 7.33 Bioretention Systems of this specification for further details of design
requirements.
5. If the stormwater runoff flow rate and duration equivalent to the pre-developed conditions cannot be Downstream
achieved an upgrade of the existing council stormwater infrastructure downstream of the discharge shall be Infrastructure
required subject to approval by council.
6. Design details shall be submitted to council to prove the adequacy of the existing system and/or the
proposed upgrade works to handle the increase in flows.
7. Where the discharge point is located at a permanent natural waterway a permanent erosion control Downstream
design shall be provided to prevent the erosion of the downstream waterway to which the catchment runoff is Waterways
directed to. In lieu of NSW EPA documents relating to channel design (currently being developed) refer to Brisbane
City Council design guidelines Natural Channel Design December 2000 and Guidelines for Selecting Remedial
Works July 1997 .
8. Where in-stream erosion control measures or upgrade of infrastructure works cannot be carried out by
the proponent of the works a contribution (cost figures to be provided by Council) is to be provided for works to be
carried out by Council. Erosion control measures shall be required from the discharge point of the catchment to the
receiving waterway or to the next catchment discharge point with the shortest distance being the determinant.
1. Development or works that do not include water quality or quantity controls have the potential to
increase pollutant loads of receiving waters, relative to those occurring under pre-development
conditions.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 9
STORMWATER MANAGEMENT
Contract No.
2. An assessment of water quality impacts and control measures to mitigate or improve the water quality
shall be a carried out by the following process.
e. Determine the types of treatment measures to be used to mitigate or improve the water
quality from the proposed works.
3. Water Quality Objectives (WQO) are used to describe the quality of water that is needed in a receiving Water Quality
water to protect or enhance Environmental Values (EV). Environmental Values are those values that a Objectives.
community believe a particular waterway should hold eg: ability to safely swim in a river or adjacent ocean
beach, or the ability of a waterway to sustain healthy aquatic ecosystems.
Water quality objectives in this specification are based on the guidelines as specified in the Water Quality
and river flow interim Environmental Objectives for the Camden Haven and Hastings River catchments
Refer to Appendix A Fig. D7 10 and Table D7A 8 and Chapter six (6) of the Australian Runoff Quality
manual 2003. Aquatic ecosystem values are to be used as a base to determine the protection level
required for a specified development. Unless determined otherwise by Council.
4. Water quality objectives shall be evaluated over the full range of rainfall conditions (Refer to Appendix A
Fig. D7A 14 Regional Rainfall Distribution Hastings LGA)) to maintain the long-term protection of the pre
determined Environmental Values (EV).
5. Water quality objectives shall be determined based on a developments RISK to the environment. Low Low Risk
Risk development (eg: single dwelling construction) will not be required to identify relevant water quality Development &
objectives for down stream receiving waters but will be required to follow Best Management Practices BMPs
(BMP) in relation to the control of erosion, sediment and stormwater quality as outlined in this specification
and in accordance with the document Managing Urban Stormwater Soils and Construction,
Department of Housing 1998 Chapter 9 Building sites. (Or current equivalent document.)
6. High Risk developments are classified according to the following criteria. Any development or High Risk
development proposal: Development
a. Located in a waterway corridor.
b. Located within the catchment of a wetland area.
c. Consisting of multiple dwellings or commercial uses with an impermeable surface area ( including roof
area) in excess of 2500m and / or
d. Subdivisions greater than 6 lots and / or
e. Industrial activities that are not impact assessable and at least 1000m in uncovered storage/working
space.
f. Uncovered car parks > 100 spaces.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 10
STORMWATER MANAGEMENT
Contract No.
Ecosystem Type
7. The long-term water quality sustainability of a high-risk development shall be based on viable protection
levels of aquatic ecosystems. The classification of protection levels of aquatic ecosystems is defined as:
a. Pristine ecosystem or unmodified ecosystem, having high conservation values and protection status.
b. Slightly to moderately modified ecosystem, where the ecosystem is largely intact (habitats, limited
catchment clearing) such that some restoration of the original values is viable.
c. Highly modified ecosystem, where the original ecosystem is so disturbed that it cannot be restored to
a slightly to moderately disturbed condition, but is capable of sustaining some ecological and
conservation values with appropriate management. (Ref: ARQ Chapter 6)
Council shall confirm determination of the classification of the receiving ecosystem.
8. Estimation of Sustainable Average Annual Export Load (SAAEL) is to be a risk-based process where Sustainable
the export loads are compared to the trigger level for the receiving waterway Average Annual
(ref: ARQ 6.3.1 ARQ approach to estimating sustainable catchment loads). The median insitu water quality Export Load
indicator must be below the trigger level of a receiving waterway to comply with this specification. Refer to
tables D7.4 to D7.7
a. Changes in water quality discharging from a catchment and proposed management techniques to
ensure no increase of or an improvement in water quality.
b. Increase in the average annual load of key pollutants, above that occurring under existing conditions or
to levels compliant with predetermined water quality objectives.
10. Unmodified ecosystem median pollutant levels shall be within the or below those indicated in Table. D7.4 Unmodified
for compliance with this specification. (Sourced from ARQ and water quality and river flow interim Ecosystems
environmental objectives Hastings and Camden Haven Rivers 2000 .)
11. Modified ecosystem median pollutant levels shall be below those indicated in Table D7.5. for compliance Modified
with this specification. Ecosystems
12. Highly modified ecosystem median pollutant levels shall be below those indicated in Table D7.6 for Highly Modified
compliance with this specification. Ecosystems
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 11
STORMWATER MANAGEMENT
Contract No.
13. In addition to the aforementioned median pollutant levels, any stormwater treatments shall be designed to Pollution Retention
meet the minimum level of pollutant load objective in accordance with Table D7.7
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 12
STORMWATER MANAGEMENT
Contract No.
e. Infiltration systems shall be designed to focus on the control of pollutants and the retention of
stormwater.
f. Selection of stormwater quality enhancement devices and practises shall be based on current
environmental guidelines and best practise management procedures. As a guide Tables D7A-6 and 7
may be used to select appropriate treatments.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 13
STORMWATER MANAGEMENT
Contract No.
SQIDs
D7.13 SELECTION OF STORMWATER QUALITY IMPROVEMENT DEVICES
1. The appropriate selection of Stormwater Quality Improvement Devices. (SQIDs) will assist
developments meet Councils Water Quality Objectives (WQO). In selecting an appropriate SQID or
combination of SQIDs the following process shall be followed:
a. Risk Category identify whether the proposed development is low risk eg: Single dwellings &
Duplexes <6 Lots or < 2500m or high risk eg: Development >6 Lots and/or 2500m.
b. Pollutant Type identify the target stormwater pollutants for the proposed land use for the construction
and occupational phases of the development using tables D7A-3 And D7A-4 In appendix A
c. Construction Phase during this phase the primary contaminant of concern is usually sediment. To
identify the appropriate Best Management Practices (BMP) the guidelines contained within REF1 shall
be used.
d. Occupational Phase (low risk) if the development is low risk Water Quality Objectives (WQO) need
not be identified. Table D7A-6 (Appendix A) shall be used to select which type of quality control device
is appropriate. Table D7A -7 (Appendix A) may be then used to assist in sizing an appropriate device.
Additional references can be used to provide alternative treatment devices if appropriate.
e. Occupational Phase (high risk) if the development is high risk WQOs shall be identified as outlined
in section 7.06 Of this specification. Table D7A-6 (Appendix A) may be used to determine the
appropriate types of devices, but detailed analysis shall be required to determine pollutant export loads
and demonstrate that the device selection meets relevant WQOs for receiving waters.
f. Maintenance Plan where SQIDs are selected as an appropriate treatment device a maintenance plan
shall be required as specified in table D7A-4 (Appendix A).
g. Documentation the Stormwater Management Plan is to include details of the SQIDs selected, their
location, the timing for installation, and the maintenance regime.
1. An evaluation of costs shall be submitted stating the initial establishment costs and the annual
maintenance costs
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 14
STORMWATER MANAGEMENT
Contract No.
c. Total construction costs including project management and/or contract management costs.
b. Staff training.
c. Inspections.
d. Waste disposal.
Access requirements
Geological conditions
Shallow bedrock
Permeability
Erodibility
stability
1. Basins designed for water quality control should maximise the extent of settling. In general quiescent Maximise Infiltration
conditions and infiltration should be maximised.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 15
STORMWATER MANAGEMENT
Contract No.
2. A wet retention basin can be located either on-line or off-line . Its capacity however needs to be Location and Size
considerably greater if it is located on-line. The wet retention basin usually has some form of energy dissipation
at the inlet or a sufficient length-to-width ratio (greater than 2:1) to prevent short-circuiting of flow across the pond,
although its shape may vary considerably. Ponds may vary in size, with the settling velocity of particles being the
basis for design. Refer to chapter 11 of ARQ for details of appropriate design procedures to be adopted. Basins
may be installed as smaller multiple units (in series) or as large single units. Fig D7-2 shows a typical preferred
configuration of a wet retention basin.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 16
STORMWATER MANAGEMENT
Contract No.
3. Other design guides that will make the basin efficient in removing particles and provide for public safety Basin Safety
include the following.
a. The minimum depth should be not less than 1.5 metres with an average depth of 2.5 metres. This
discourages infiltration growth in the deeper portions of the pond and also the breeding of
mosquitos.
b. The basins should have side slopes of 6(H) to 1(V).
c. If side slopes are to be steeper than 6(H) to 1(V) the basin/pond shall be enclosed by child proof
security fence.
d. The maximum velocity through the pond based on a 1 in 1 year storm should not exceed 0.3
metres per second (at 2.5 metres depth, this is the maximum practical flow velocity at which
optimum sediment removal can be achieved).
e. A minimum freeboard of 0.3 metres should be provided between a restricted discharge outlet for
the pond and a storm overflow weir This discharge outlet should be designed so that the weir
overtops on average three times per year. A freeboard of 0.5m shall be provided between the 1 in
100 year flood level and floor levels of dwellings.
f. Inlet and outlet structures should be located at extreme ends of the basin, with short-circuiting of
flow further minimised by the use of baffles.
g. Depth indicators shall be provided indicating maximum depth in the basin spillway.
h. Appropriate hazard signage shall be provided for the basin and spillway.
i. Protection of the low flow intake shall be provided to prevent blockage and to prevent the risk of
people being trapped.
j. Basins shall be designed so that no ponding of water occurs on to private property or roads.
4. Basins should be constructed prior to the commencement of any site clearing or construction works, and Construction and
should be de-silted before the design sediment depth occurs. Maintenance
5. It is preferred that urban retention basins incorporate an outlet device that enables dewatering of the Outlet Design
basin. This simplifies de-silting, enabling earthmoving equipment to be used for de-silting operations.
6. The high level outlet shall have capacity to contain a minimum of the 100 year ARI storm event. Additional
spillway capacity may be required due to the hazard category of the structure determined by reference to
ANCOLD (1986).
9. An all weather access track shall be provided to the basin for maintenance works. Access Track
10. Basins shall be surrounded by buffer zones, typically comprising grassed foreshores of not less than 20 Buffer Zones
metres between the nearest development and the basin. This allows for some infiltration of drainage from
developments, permits the drainage authority scope to develop aesthetic surrounds and reduces the
likelihood of over the fence dumping of rubbish.
11. Wet retention basins are regarded as impoundments and normal dam safety requirements should be met. Basin Classification
A dam may be prescribed under the Dams Safety Act, 1978, depending on the recommendations of the
NSW Dams Safety Committee. A dam is normally prescribed if it is:
a. 10 metres or more in height and has a storage capacity of more than 20 megalitres; or
b. 5 metres or more in height and has a storage capacity of 50 megalitres or more.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 17
STORMWATER MANAGEMENT
Contract No.
12. If the wet retention basin is a prescribed dam, the Dams Safety Committee will maintain an interest in the Dam Safety
dam will seek information from its owner and will require that reports be prepared on the dam and submitted to Committee
the Committee.
1. Trash racks are usually permanent structures, which intercept trash and other debris to protect the Environmental
aesthetic and environmental quality of water. Quality
4. Trash racks may be incorporated in the design of gross pollutant traps. Gross Pollutant Trap
5. A maintenance schedule for any trash racks shall be included in the SQIDs Maintenance and Operations Maintenance
Procedures
1. Gross pollutant traps (GPTs) are permanent structures used to trap coarse sediments, trash, litter, and Description
other floating materials. Usually, they are located upstream of constructed wetlands and receiving waters.
2. These traps have restricted application and each should be justified on individual merits. Selection of Applications
the size and type of GPT shall be based on information and guidelines contained in Chapter 7 of ARQ and with
reference to Appendix A of this specification. Confirmation from Council shall be required when a GPT type is
selected to ensure consistency and conformance with catchment management plans.
Major gross pollutant traps can be located on major floodways and waterways to intercept medium to
high flows; and
Minor, enclosed gross pollutant traps can be located at heads of major floodways and/or where
stormwater discharges into floodways or water bodies.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 18
STORMWATER MANAGEMENT
Contract No.
4. Traps shall be designed to intercept at least 75 per cent of sediment with a grain size of 0.04mm or Sediment
greater under average annual runoff conditions. Further, ensure peak flow velocities are less than 0.3 metres per Interception
second in the design storm event, and taking into account any likely backwater effect from blockages.
5. The structure shall have sufficient capacity and stability to discharge the inlet flow with the trash rack fully Capacity
blocked without flooding adjacent properties.
6. Ensure GPTs are capable of gravity drainage to a dry condition for periodic cleaning and maintenance. Maintenance
Requirement
1. Litter baskets are proprietary devices primarily designed to capture litter and gross pollutants. Description
2. These traps have restricted application and should be justified on individual merits. Selection of the Application
type of location of Litter Baskets shall be based on information and guidelines contained in Chapter 7 of ARQ and
with reference to Appendix A of this specification. An intention to utilise Litter Baskets shall be approved of by
Council at the concept stage of a development.
3. Litter Baskets are typically located within stormwater side entry drainage pits and are designed to Definition
collect and retain a range of pollutants including 95% of all solids greater than 2 mm.
4. Design loads and capture capacity shall be verified for each pit proposed from information found in Design
Appendix A of this specification and by information supplied by the individual product manufacturer. Provision for
access and OHS issues shall comply with current Australian standards.
5. All costs relating to design installation and maintenance shall be provided in accordance with section Maintenance
D7.14 of this specification
1. Constructed wetlands and ponds shall be designed in accordance with the requirements of: Design
a) The primary reference documents shall be ARQ, Chapter 11, Austroads AP 232, Water Sensitive References
Road Design Design options for improving stormwater quality of road runoff Technical report 00/1
2000 CRC
2. The major elements include pre- treatment, inlet zone, ephemeral zone and macrophyte zone or
wetland zone as illustrated in Fig. D7-3
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 19
STORMWATER MANAGEMENT
Contract No.
3. A Pre Treatment zone is required to remove litter and organic matter from inflows to allow easy Pre Treatment
collection by maintenance crews. A litter trap shall be capable of retaining litter of a size greater than 5 mm for all
flows up to a flow rate of 1 in 3 month ARI(the design rainfall event). A sediment trap may also be located within Zone
this zone.
4. An Inlet Zone has the primary functions of energy dissipation and sedimentation. Details of methods of Inlet Zone
sizing of sediment basins may be found in the specified reference documents. The inlet zone shall have the
capacity to remove 95% of all suspended sediment down to 125um during the design rainfall event. If a natural
stream is used to convey the waters to a downstream wetland a 1in 2 Year ARI event shall be the design rainfall
event. When the Inlet Zone is to be a pond structure the following shall apply:
a. The length to width ratio shall be between 5:1 and 10:1 with sufficient energy dissipation to reduce
velocities to below 1.0m/s. The maximum width shall be 14m to allow access for maintenance plant.
c. The preferred top water level shall be 0.5m above the downstream wetland zone.
d. Bypass facilities shall be included in the design to allow the water level to be lowered by at least 0.5m
for maintenance of the pond.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 20
STORMWATER MANAGEMENT
Contract No.
5. The Ephemeral zone or marsh shall be used to trap leaf and other organic material prior to entering the Ephemeral Zone
wetland zone reducing the likelihood of anaerobic decomposition within the wetland zone. The design
requirements are:
b. A shallow rock lined channel shall meander to maximise length of travel and allow event flows to
inundate adjacent areas planted with ephemeral marsh plants.
c. Raised mounds consisting of topsoil positioned at 45 to the flow of water shall be included in the
design. It is preferable to form the mounds by removing material from the location of the mounds rather
than stripping the entire area and building the mounds.
e. A porous rock wall or similar shall be provided across the downstream end of the ephemeral zone to
allow flow attenuation during the design flow event.
6. The wetland Zone shall be designed to remove sediment less than 125 um and dissolved pollutants. Wetland Zone
Design criteria shall be as outlined in the reference documents, and shall include the following specific
requirements.
b. A residence time in the wetland shall be at least 72 hours for the design stored event volume.
c. The maximum stored water level shall be 450mm above the normal top water level unless Hastings
Council gives specific approval.
d. Provision shall be made to minimise the velocity through wetland to less than 0.2m/s during the initial
stages of a storm event.
e. An accessible outlet control shall be designed to be blockage free and able to change flow rates to allow
initial plant establishment and for maintenance purposes.
f. A minimum of 80% vegetated marsh is to be arranged in bands across the flow path. The remaining
area shall be allowed for submerged marsh or open water areas.
7. Emphasis in planting design should be given to species growing naturally in local wetland remnants. A Vegetation
vegetation and weed maintenance program of at least 24 months after the initial planting of the wetland shall be
incorporated in the maintenance and operation procedures. Refer to Appendix A Table D7A 2 Wetland
Vegetation Selection.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 21
STORMWATER MANAGEMENT
Contract No.
8. Safety considerations shall be included in the design of all structures. The following requirements shall Safety
be used as a minimum in the design.
a. Operational depths of sediment ponds to be from 1.5 to 2.0m. Shallow marsh areas, depths to 200mm,
deep marsh areas 200mm to 350mm with a periodic maximum up to 600mm.
b. Minimum offset to any allotment boundary to be 15m and up to 30m where access is available.
d. No formal access points to water shall be included in the design unless there is appropriate safety
benching.
e. All edges to waterbodies and wetlands shall have safety benches of at least 1.5m to 3.0m wide from the
normal top water level except where transitions to culverts or waterways occur. Safety benches shall
have maximum slopes of 1 in 8 for the first 1.5m to 3.0m, a transition to 1 in 5 over 0.5m (min.) prior to
steeper grades up to 1 in 3. The safety bench shall be densely planted with emergent macrophytes to
preclude access.
9. Interim fencing is recommended between the construction and vegetation establishment where water Fencing
depths exceed 350mm.
Permanent fencing combined with dense impenetrable plantings shall be used adjacent to water depths
exceeding 350mm (normal top water level) areas where safety benches do not conform to the width criteria,
adjacent to unsafe structures, areas of high velocities or where batters are steeper than 1 in 6
Maintenance access areas shall be signed, fenced and gated where the safety measures above are not met.
10. Natural wetlands shall not be used for improvement of urban run-off quality. Figure D7-4 shows a Natural Wetlands
typical constructed wetland arrangement.
11. Where wetlands are natural, the provisions of State Environmental Planning Policy No 14 Coastal SEPP No 14
Wetlands, should be consulted. This policy protects wetlands from clearing, construction of levees, draining and
filing, but does not prevent wetlands being used for run-off control, provided safeguards and operation control
ensures their continued viability.
12. Wetlands are primarily to be designed to capture the ARI 3 month storm (deemed to be 40% of the ARI
one year event), however overflow structures and flow paths are to be provided to pass ARI 100 year storms Efficiency
ensuring no damage to the wetland or associated drainage or other ancillary works and no re-mobilisation of
captured sediments.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 22
STORMWATER MANAGEMENT
Contract No.
13. Where possible, small islands or shoals should be constructed in the upstream areas of the wetland to Short Circuiting
reduce water velocities, prevent short-circuiting and promote aquatic plant growth.
14. These areas are best planted with vegetation native to the area, but they can be used as grassed areas Native Vegetation
and as an aesthetic feature.
15. A variety of plant species should be planted in artificial wetlands to achieve efficient colonisation and Revegetation
maximise pollutant removal. Establishment of plants should be through transplantation of seedlings during spring
and early summer. Refer to Appendix A for a list of recommended plant species
16. Wetlands will serve other purposes than just improving a quality of urban run-off. They will serve to Aesthetic Feature
attract a large range of biota and bird habitat. In areas where they have been installed, they have become an
aesthetic feature. Indeed, this may present problems as surrounding communities may resist efforts by the
controlling authority to de-silt the wetland.
1. Infiltration systems are best utilised as part of a treatment train consisting of elements such as grassed
surfaces, vegetated strips, swales, sand filters, gravel based reed beds, treatment train tanks and geotextile
filters. Infiltration systems are to follow the guidelines in Chapter 10 of Ref: ARQ or similar equivalent.
2. The design capacity of infiltration systems can range from designs catering for the minor system flows to
the major system flows.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 23
STORMWATER MANAGEMENT
Contract No.
a. Leaky wells: typically concrete or PVC or similar pipe with perforated walls covered with
non-woven geotextile fabric. The well is to be surrounded with gravel, enclosed in non-woven
geotextile.
b. Trenches may be gravel or gravel with a slotted pipe, drainage cell or a combination of all. All
trenches embedded in host soil must be encased in non-woven geotextile fabric. Maximum
floor level below ground is to be 1.5m, top of gravel should covered with 0.3m of backfill.
c. Soakaways similar to trenches having a large plan area with depths ranging from 0.3m to
0.5m constructed of similar materials as trenches.
d. Infiltration dry ponds are structures similar in design to small-scale retention wetlands. They
are suited to sandy or sandy clay sites only with the screening of gross pollutants required
upstream of the structure. Safe water depths during runoff events are critical in the design of
this type of structure.
6. The existing soil classification, permeability and water reactivity is to be determined by a geotechnical
engineer or other suitably qualified person to determine how soil conditions at the project site will affect detailed
design.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 24
STORMWATER MANAGEMENT
Contract No.
Fig. D7- 5 Shallow retention/overflow trench Fig. D7-6 Perforated retention/overflow (Argue, 1994)
Fig. D7-7 Example of infiltration with pre-treatment provided by a grass buffer strip (Schueler, 1995)
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 25
STORMWATER MANAGEMENT
Contract No.
7. An alternative to clearance distances shown in Table D7.8 is to ensure that infiltration devices located in
soils with high heave potential are designed to empty rapidly. This type of design would allow a reduction in the
clearance distance of 50% to that recommended.
b) Leaky wells and gravel filled trenches are not to be used in areas of wind blown sands or Aeolian sands.
c) Infiltration devices in areas of rock or shale of zero or near zero permeability are deemed to be
unsuitable.
d) Areas consisting of shallow soils over rock or lower permeable sands (eg; coffee rock) detailed
investigations are to be carried out to determine the existence of stored water near the lower level
layers (ie. Perched water table ) and the location of the emergence point of stored water. The impact on
downstream areas is to be assessed in the selection of infiltration devices in these areas.
e) A maximum slope of 5% and soil depth of at least 3m throughout a down slope area is required before
infiltration devices are to be considered in areas of steep terrain.
f) Infiltration devices are not to be used in areas of high or rising water table.
g) Infiltration devices are not to be used in areas adjacent to underground Carpark areas or lower
basement areas unless seepage from such devices is adequately catered for by sump pumps or similar
design to transfer flows to an appropriate drainage system or lower aquifer.
h) The location of infiltration devices is to be assessed to determine the impact of upstream infiltration
devices on valley floor watertables.
1. Swales are open vegetated channels that can be used as an alternative stormwater conveyance
system to conventional kerb and gutter only with the approval of Council.
2. Vegetation of the swale can range from grass to native shrubs, depending on hydraulic requirements.
3. Criteria for the design of vegetated swales is to include but not confined to the following:
a. The swale dimensions or catchment ratio should be designed so as to ensure 1 year ARI
peak velocities do not exceed 0.5 m/s and 100 year ARI velocities do not exceed 1 m/s. In
some situations, a high-flow bypass channel or underground pipe may be required.
c. The swale shall be integrated into the landscape character to enhance its aesthetic value.
d. The application of swales shall match the target pollutant characteristics. Where very fine
particulates, or soluble material are of concern, other treatment measures such as infiltration
systems or small wetlands shall be considered.
e. Established vegetation shall not be more than 75% inundated during the major design flow.
f. Swale profiles of triangular cross section are not acceptable, wide uniform flow shall be a
design objective. Maximum width shall be 2.5m unless structural measures are used to
ensure uniform spread of flow.
g. Mannings n value shall be between 0.15 and 0.3 for low flow conditions where the depth of
flow is below the height of the vegetation. For the major storm event the Mannings n value
shall be a lower value (eg: 0.03) where flow is above the vegetation level.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 26
STORMWATER MANAGEMENT
Contract No.
1. Bioretention systems are designed to provide treatment of stormwater through fine filtration, extended
detention and some biological uptake.
2. Treatment Processes
Runoff is filtered through a fine media layer as it percolates downward into a perforated pipe or similar and
discharged either directly or via conventional stormwater conduit system.
An even flow distribution is required to allow water to infiltrate the filter media evenly and thus suited to flat terrain
of less 2%.
Selection of filter media is a function of the infiltration rate required, refer to Table D7.9, and the type of vegetation
utilised.
4. Vegetation Requirements
Vegetation shall be selected to complement the landscape of an area and to discourage movement and traffic
over the bioretention area.
Plants having extensive fibrous root systems or a spreading, rhizomatous or suckering habit are required for
efficient performance.
Plants with a clumped above ground habit shall not be used due to problems incurred by channelling, erosion and
preferential flow paths.
Fig D7-10 Schematic Representation of a Bioretention system (CRC Catchment Hydrology 2002)
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 27
STORMWATER MANAGEMENT
Contract No.
ESCP
D7.23 EROSION AND SEDIMENT CONTROL PLAN
1. An Erosion and Sediment Control Plan shall be required for all developments. For the plan requirements of
High Risk Developments (Developments greater than 6 Lots and / or greater than 2500m) and Low Risk
Developments (Single dwellings and Duplexes less than 6 Lots or less than 2500m in area) refer to Appendix A
Table D7A - 5
1. The erosion hazard of a development site can be minimised by scheduling activities to time periods when Timing of
rainfall is lowest. The ESCP shall use soil loss class data to ensure that works are seasonally programmed to keep Development
soil loss rate below the rate of 37.5 tonnes/hectare/year in any 2-week period. If scheduling of activities cannot be
programmed to coincide with low rainfall periods, the design of erosion control measures shall be carried out using
the maximum annual rainfall average for the region for design purposes. The Revised Universal Soil Loss
Equation (RUSLE) Appendix A REF1 combined with Tables D7.10, D7.11, D7.12 and Figures D7A-11 to D7A 14
shall be used as a guide for planning the proposed works.
Table D7.10Soil Loss Table D7.11 Soil Class and Development Period
Soil Loss Erosion Calculated soil loss Period Soil Classes
Class Hazard (tonnes/ha/year as That May be
calculated by RUSLE) Developed
1 Very Low 0 to 250 January and February 14
2 Low 251 to 300 February to end of April 13
3 Low Mod 301 to 375 May and June 14
4 Moderate 376 to 500 July to end of September 16
5 High 501 to 750 October to end of December 15
6 Very High 751 to 1500 Note: Soil Loss Class 7 not recommended for disturbance.
7 Extreme 1501 to 3750
2. The maximum length of exposed (disturbed) slope shall be: Max. slope length = 90-48[log(%slope)] metres
Length of disturbed
slope
1. Retained vegetation and buffers must be protected by a suitable fence barrier. Fenced areas shall be Fencing
clearly signposted No Access Area. A fence shall be used to exclude traffic from buffer zones to prevent
damage to the vegetation, particularly during any construction phase.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 28
STORMWATER MANAGEMENT
Contract No.
2. The no access fence locations shall be shown on the detailed design. These locations will be No Access
approximate only as machinery type, topography etc will determine actual on site location.
1. Diversion works may be in the form of earth drains and banks, straw bales, sand bags or pipelines and Diversion Types
may be permanent or temporary. All control measures must be installed prior to clearing of the site.
2. Upstream run-on water shall be diverted around the site. Such flows shall discharge to a legal drainage Discharge Point
point or open areas where level spreader banks shall ensure a broad water spread to minimise flow velocity.
3. Pipelines may also be used to convey such run-on through the development site, and discharge the flow Pipelines
to a formal drainage point/dissipater if necessary. Such pipelines may also form part of the overall final drainage
system.
5. Diversion works are to be designed to carry peak flows at non-erosive velocities in bare soil, vegetated or Peak Flows
lined drains/banks.
6. Channels shall be lined with turf. Where velocities are designed in excess of 2m per second, non-erosive Non-Erosive Linings
linings such as concrete, geotextiles, grouted rock etc or velocity reducers (check dams etc) are required.
Evidence of the suitability of the proposed material to be used will be required prior to approval of the ESCP
7. Diversion Structures are to generally comply with Section 5.2.4 of [Ref 1]. A typical arrangement of
diversion drains and banks is shown in Figure D7-11.
8. Diversion of stormwater onto downstream properties will require legal agreement and approval by Council
prior to issue of a construction certificate.
BATTER GRADE
BATTER GRADE LESS THAN 2:1
LESS THAN 2:1
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 29
STORMWATER MANAGEMENT
Contract No.
1. These are temporary or permanent drains, which divert concentrated run-off down slopes such as road Lined Drains
batters without causing erosion. They usually consist of a dished earth drain smoothly shaped, consolidated and
lined with a variety of materials or they may be a flexible/rigid pipe or half pipe.
2. Drop down drains shall have sufficient capacity for a minimum 1 in 5 year peak flow without eroding. Capacity
Energy dissipaters may be required to reduce the flow velocity at the outlet of the drop down drain.
D7.28 STOCKPILES
1. Location of stockpiles shall be indicated on the approved engineering plans. Approved Plan
3. Stockpiles must be protected from erosion and sediment loss by: Erosion Protection
4. Site topsoil shall be isolated from subsoil material in separate stockpiles. Separate Stockpiles
5. Stockpiles if intended to be left exposed for longer than 14 days shall be revegetated immediately (see
specification C273 Landscaping).
1. Sediment traps are either permanent or temporary sediment control devices that intercept sediment and Sediment Control
run-off usually at the final discharge point of the site or at a location to protect a downstream watercourse,
wetland, riparian vegetated area or receiving water. Preferably they are to be located off line.
4. Preferably sediment traps shall not be located directly upstream of residential areas. Location
5. Basin design must be in accordance with Managing Urban Stormwater Soils and Construction Design Criteria
(1998) Section 6.3.3.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 30
STORMWATER MANAGEMENT
Contract No.
6. Where sediment retention basins are required, they shall be designed to treat the runoff from the design
rainfall event emanating from the site during land development works and they must remain in place and
be fully operational until removal is authorised or required by Council.
7. Where required as part of a permanent, public stormwater management system, basins located on public
land (or land to be dedicated to the public), may be accepted for Council ownership.
8. Where required as part of a permanent, site stormwater management system, basins located on the site
must be retained, operated and maintained in perpetuity by the landowner.
10. A marker must be placed within each sediment retention basin to show the level above which design Permanent Wet
capacity occurs. Basins
11. Materials removed from sediment retention basins must be disposed of in a manner approved by Council
and in accordance with current EPA guidelines.
12. Plans shall indicate whether basins are to be temporary or permanent.
1. Silt retention/filtering structures of a temporary nature shall be used in situations where the catchment Filtering Structures
does not exceed 0.25 ha.
a. silt fences
b. straw bales
c. blue metal groynes/sausages
d. filter fabric located beneath stormwater grates
e. gabions
f. or a combination of the above.
3. The choice of material and type of treatment will depend on the size of the catchment the location and Location of
the structure being treated shall be required at: Structure
4. The design of sediment traps/barriers shall generally in accordance with [REF 1] chapter 6.3.4 except
as varied by the following criteria.
a) Maximum flow in to the silt fence from a design ARI 3 month storm is not to exceed 1.6l/sec/metre or
the maximum catchment per metre of fence etc. is not to exceed 45m and
b) The fence or structure must be structurally viable and able to support the hydraulic pressures generated
during the design recurrence storm
d) In fences or structures longer than 30m, spill through weirs shall be installed at 20 30m intervals.
e) Spill through weirs shall consist of a rock filled wall contained between an enclosed steel mesh fence
retaining wall of typical dimensions of 1.2m length, 0.6m height with enclosed rock of 25 50 mm
aggregate.
5. Sediment shall be removed and disposed/reused in accordance with Council and EPA guidelines after
each rainfall event. Weirs shall be regularly maintained and cleaned to ensure effective operational condition.
Straw bales and slit fence geotextiles shall be replaced when damaged or permanently blocked and fully replaced
at not more than six monthly intervals.
1. Level spreaders are outlets or sills having a level cross section. They convert erosive channelised flows Convert Flows
into non-erosive sheet flow.
2. Level spreaders can only be used to dissipate flows from small catchments. The area below the outlet Location
should be stable and of even cross section so that the water will not re-concentrate into channels.
3. To reduce flow velocity before the spreader, the channel grade shall not exceed 1 per cent for a minimum Design Criteria
of 8 metres. The outlet or sill width depends on contributing catchment, slope and ground conditions. The
minimum width should be four metres, and the maximum width 25 metres. Final discharge should be over a level
surface, which may require stabilising by turfing or seeding and fertilising or perhaps lining with a geotextile fabric
or something similar.
1. Access to construction sites shall be limited to a maximum of two locations. Number of Accesses
2. Access locations and shakedown areas shall require Council approval. Location Approval
3. Shakedown areas or access stabilisation shall comprise a bed of aggregate on filter cloth or a metal bar Types
cattle grid located at any point where traffic enters or leaves a construction site. Stabilised accesses reduce or
eliminate tracking of sediments onto public rights of way or streets. Should such tracking occur the contaminants
must be swept off the roadway each day or before rain. Clean off draw bars etc after dumping and before starting
journey.
4. If a shaker grid is used, this should be so placed as to ensure the vehicles when crossing the grid have Cattle Grid
sufficient speed to shake the mud or other contaminants such as gravel from the vehicle. It must not be placed
where the vehicle is slowing to enter a roadway. Cattle grids shall be a minimum length of 7 metres.
5. A stabilised access comprises a vehicular pathway suitably constructed to facilitate the collection of any Stabilised Access
site debris in order to prevent such material leaving the site. Stabilised accesses are generally used on small
sites. The entrance shall be at least 15 metres long with a minimum width of 3 metres for a one-way entrance
and 6 metres for a two-way entrance.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 32
STORMWATER MANAGEMENT
Contract No.
6. Surface water flowing to the street entrance/exit must be piped under the access, or a berm constructed Flow Control
to direct surface flow away from the exit.
1. Research has demonstrated average dust emission rates of over 2 tonnes per hectare per month at Erosion Rate
urban construction sites. This erosion rate is unacceptable.
a. limiting the area of lands exposed, maximum 2 ha, to erosive forces through phasing
works/progressive revegetation and/or provision of a protective ground cover and/or keeping
the ground surface damp (not wet) and/or by using onsite water from detention basins where
available.
b. on building sites, installing a barrier fence on the windward side effective to a distance of 15
times its height, assuming an acceptable soil flux of 5 grams per metre per second. See
Figure D7-12.
c. control techniques may include the use of water sprays, application of dust suppressants,
surface stabilisation or covering of exposed surfaces.
3. Dust control techniques must be employed on site at all times including outside normal working hours.
4. All permanent roads and trafficable areas must be sealed or hard surfaced to minimise dust generation.
5. Unless an exemption from Council is obtained, all sites where over 1500 m are to be disturbed must be
provided with a barrier fence wind break [Ref 1] 6.3.6(b)(iii).
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 33
STORMWATER MANAGEMENT
Contract No.
1. In addition to D7.23.1 and Council Code No.18 (Erosion and Sediment Control ), DCP 41 (Building
Construction and Site Management.), Council Policy No. E1/1 (Erosion and Sediment Control Policy) the following
shall apply.
2. The clearing of vegetation and preparation of building pads is to be undertaken in the last stages of Site Clearing
the development when the majority of the site has been effectively revegetated.
3. When the development calls for the construction of a number of buildings, the sediment trap/s and Development
other appropriate sediment controls shall remain operational. Control
4. Cross/catch drains shall be installed on long or steep unpaved driveways, disposing run-off to stable Driveway Control
areas.
5. Where a majority of the lot is disturbed the following controls or measures shall be undertaken: Lot Control
6. When roof structures and piped or artificial stormwater systems are in place, discharge water is to be
managed in a manner that reduces erosion. Roof water drainage systems must be functional and discharge to the
stormwater system before roof runoff begins. The stormwater system must prevent sediment from being eroded
from the site and deposited downstream.
1. Sediment control devices or stabilising works shall be provided outside construction sites where Necessary Controls
necessary or as directed by the Superintendent.
2. Where increased stormwater run-off is likely to or is found to accelerate erosion of any downstream Accelerate Erosion
watercourse, the necessary remedial work shall be provided concurrently with other sediment and erosion
requirements.
3. Where sediment is likely to be transported from the site, all immediate downstream drainage inlets shall Downstream
have appropriate controls installed. Controls
4. If such works require entry onto private property, written permission shall be obtained prior to the entry Written Permission
and commencement of such works.
5. All disturbed areas on private property to be reinstated to original condition and to the satisfaction of the Reinstated
owner.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 34
STORMWATER MANAGEMENT
Contract No.
D7.36 DEFINITIONS
Term Description
Average Recurrence Interval (ARI) Is the average time between storm events of a given value. Eg: a 1 in 2 year ARI storm event.[5]
Base Flows Underlying flow rate that cannot be directly attributed to storm events and is present during some or all dry periods.[5]
Best Management Practice (BMP) Structural and non structural measures used to reduce the impact of development on the urban
water cycle. [6]
Bioretention System A grassed or landscaped swale or basin promoting infiltration into the underlying
medium.[6]
Buffer zone The zone contiguous with a sensitive area that is required for the well being of the sensitive area.[7]
Catchment Area The contributing area of land which drains to a single point of interest.[7]
Constructed Wetland A man made artificial water body containing aquatic plants and designed to mimic the ecological and physical
tratment processes of natural wetlands.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 35
STORMWATER MANAGEMENT
Contract No.
Detention Basin Detention basins are structures designed to retard the flow of minor and major storm events and to provide
controlled outlet of stormwater flows. They are provided with low level and high level outlets and are designed for a series of peak flow
events through the use of hydrographs. The low level outlet is designed to release flow at a predetermined rate for minor storm events
and the high level outlet is designed as an overflow for major storms.[8]
Ecological Sustainable Development (ESD) "Development that improves the total quality of life, both now and in the future, in a way
that maintains the ecological processes on which life depends."
Environmental Values The actual or potential function carried out by the water body (eg: suitable for recreational use).
Event Mean Concentration EMC The total mass of a pollutant constituent divided by the volume of surface runoff.[7]
First Flush The Delivery of a disproportional large load of pollutants during the early part of storms due to the rapid suspension of
accumulated settled particles.[7]
Freeboard The distance required between a calculated or known water level to a specified location on a structure.
Floodway "A carriageway across a shallow depression subject to flooding, specially constructed to resist the effects of
submergence. [1]"
Gross Pollutant Trap(GPT) A structure designed to trap gross pollutants ( trash litter & vegetation > 5mm) for certain design storm
events.
Groundwater water saturating the voids in rocks; water in the zone of saturation in the earths crust eg: in aquifers.[5]
High Risk Development Any development in a waterway corridor; and/or Multiple dwellings or commercial developments with an
impermeable surface area in excess of 2500 m; and/or Subdivision where at least 6 lots are involved: and/or Industrial activities that are
not impact assessable and at least 1000m in uncovered storage/working space; and/or uncovered car parks with at least 100 spaces.
Infiltration System "A system which uses permeable material to infiltrate water into the soil. Infiltration trench, Infiltration wells,
Infiltration basins & onsite.
Intensity Frequency Duration (IFD) A three-way relationship that defines that statistical distribution of rainfalls expected to occur at a
particular location.
Interallotment Drainage A drainage system design to carry stormwater runoff from impervious surfaces that do not drain to a
street frontage, usually located along the rear boundary of a property. Primarily used where the natural slope drains to the rear of
property.
Life Cycle Cost "The total cost incurred to construct, operate, maintain and replace an asset over a given time frame.[6]"
Low Risk Development "Development subject to Council approval but specified as ""low risk development". Water quality impacts
shall be minimised by identifying and adopting best practice techniques."
Macrophyte zone That portion of a constructed wetland that contains macrophyte plants (eg: reeds, rushes)"
Mean Annual Runoff The average annual runoff from a catchment [5]
MUSIC The Model for Urban Stormwater Improvement Conceptualisation software developed by CRC for Catchment
Hydrology to model urban stormwater management schemes.
Natural Channel Design The design of hydraulic conveyance structures, which maintain the engineered and environmental values of a
waterway.
Natural Water Course "A river, creek or stream in which water flows either permanently, intermittenly or occasionally in a natural
channel, or in a natural channel artifically improved, or in an artificial channel that has changed the course of the water course.[7]"
Residence Time The average length of time the water stays in the wetland.[5]
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 36
STORMWATER MANAGEMENT
Contract No.
Retention Basin Basins designed similarly to detention basins.The difference is in their operation in that the outlet for low flow
is not provided but the high level overflow is retained. Wet retention basins are used in situations where significant reductions in pollution
concentrations are required. This is achieved by maintaining a constant pool of water within the basin and carrying out some form of
treatment process.[8]
River "A major watercourse with a large catchment, usually a wide flat channel bed, a high natural sediment flow and
a near constant base flow. In arid and semi-arid areas rivers can run dry. [4]"
Runoff Coefficient The ratio of how much water is likely to runoff a site against how much rain falls in any particular storm event
[10]
Sediment Basins "Permanent or semi permanent structures, which are used to trap sediment from disturbed or developed areas,
they are used as part of an overall designed system."
Sedimentation The process in which setteable solids are removed from the water column by gravity.
Short Circuiting "term used to describe a pond or wetland where water entering moves quickly to the outlet without interacting
with the treatment structures (eg: Ephemeral zone, wetland zone)"
Stochastic A random process that can be described using certain statisitical patterns.[5]
Stormwater Surface water run-off following a rain event (including piped flows)
Stormwater Management Plan (SMP) "A plan that evaluates options for the management of stormwater quantity, quality and ecological
values within a predetermined catchment. [9]"
Surcharge The increased water level in a storage beyond the designed operating level eg; storage of a reservoir above the
level of the spillway.
Total Catchment Management "The coordinated and sustainable use and management of land, water, vegetation and other natural
resources on a water catchment basis so as to balance resource utilisation and conservation.[5]"
TP Total Phosphorus - a measure of organic and inorganic phosphorus in particulate soluble forms.[5]
Trunk Drainage Those drainage systems having catchment areas greater than 15 Hectares or runoff in excess of 3m/s during a
20% ARI event (Urban Drainage Design Manual Sutherland Shire Council ).
Turbidity "Measure of the clarity of water using a colorimetric scale, generally relating to suspended material in water.[5]"
Water Sensitive Urban Design (WUSD) "A design principle which encourages the integration of principles such as detention of
stormwater, the use of vegetation for filtering purposes, water efficient landscaping, protection of water related environmental, recreational
and cultural values."
Water Table The surface of a body of ground water at which the pressure is atmospheric.[5]
Water Quality Indicator "an indicator for an environmental value measured in a quantitative way Eg. mg/L, pH . The water quality
indicator is compared to the water quality guidelines to determine if the environmental value is being achieved.[9]"
Water Quality Objectives measurable goals for the quality of receiving waters to ensure the Environmental Values are upheld.[9]
Source of definitions
"[1] Australian Standards (1972), Terms Used in Road Engineering. Australian Standard AS 1348-1972, Sydney."
"[2] Houghton, P.D. & Charman, P.E.V. (1986) Glossary of terms used in Soil Conservation. Soil Conservation Service of NSW."
"[3] Macquarie Library, (1981) The Macquarie Dictionary. Macquarie Library Pty Ltd, Sydney."
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 37
STORMWATER MANAGEMENT
Contract No.
"[4] National Steering Committee for the development of fish and flow friendly causeway, culvert and wetland inlet structures."
[6] Water Sensitive Urban Design - A stormwater management perspective -CRC Industry report 02/10 2002
[7] RTA Road Design Guide Section 7 stormwater Management and Drainage Design
[9] Guideline on identifying & applying water qualtiy objectives in Brisbane City (V1)
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 38
STORMWATER MANAGEMENT
Contract No.
APPENDIX A
TABLE D7A 1 MUSIC DEFAULT PARAMETERS ( Example Only-not for Design use )
Total Suspended Solids Total Phosphorus Total Nitrogen
(Log10 mg/L) (Log10 mg/L) (Log10 mg/L)
Land Use Parameter
Base Storm Base Storm Base Storm
Flow Flow Flow Flow Flow Flow
Urban
Mean 1.10 2.20 -0.82 -0.45 0.32 0.42
Std Deviation 0.17 0.32 0.19 0.25 0.12 0.19
Agriculture
Mean 1.40 2.30 -0.88 -0.27 0.07 0.59
Std Deviation 0.13 0.31 0.13 0.30 0.13 0.26
Forest
Mean 0.90 1.90 -1.50 -1.10 -0.14 -0.07
Std Deviation 0.13 0.20 0.13 0.22 0.13 0.24
TABLE D7A 2 WETLAND ZONES , TYPICAL SPECIES AND FUNCTIONAL PROCESS (Somerset et al 1996)
EPHEMERAL SWAMP
Typical Ecological Characteristics
Dominant species: eg. Eucalyptus, Melaleuca, Casurina, Juncus ; Vegetation: 2m woodland overstorey, low-high density
openclosed
canopy, ~0.5m low-high density grassland-rushland groundcover
Typical Physical Characteristics
Surface area : volume ratio: high (when inundated); Water depth: ~0.1-0.2m; Natural water regime: ephemeral (mostly dry,
occasional irregular inundation cycle)
Potential Treatment Processes and Mechanisms
Solids removal: sedimentation and filtration (particularly of fine particles); Mineralisation: microbial growth, enhanced by
wetting and drying; Nutrient uptake and transformation: microbial and macrophyte growth; Nutrient storage: sediment
adsorption
SHALLOW MARSH
Typical Ecological Characteristics
Dominant species: eg. Baumea articulata (Jointed Twig rush) ; Vegetation: 0.3-0.7m, low-medium density open canopy,
typically supports epiphytic algae on submerged culms
Typical Physical Characteristics
Surface area : volume ratio: high; Water depth: ~0.1-0.2m; Natural water regime: ephemeral (regular seasonal dry cycle)
Potential Treatment Processes and Mechanisms
Aeration: surface exchange and epiphytic photosynthesis; Solids removal: filtration (surface adhesion); Mineralisation:
microbial growth, enhanced by wetting and drying; Nutrient uptake and transformation: microbial, epiphyte and macrophyte
growth; Nutrient storage: sediment adsorption
MARSH
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 39
STORMWATER MANAGEMENT
Contract No.
DEEP MARSH
Typical Ecological Characteristics
Dominant species: eg. Eleocharis sphacelata (Tall spike rush) ; Vegetation: 1-2m, medium-dense semi-closed canopy,
supporting some epiphytic algae, moderate litter production
Typical Physical Characteristics
Surface area : volume ratio: medium; Water depth: ~0.4-0.6m; Natural water regime: permanent (occasional irregular dry
cycle)
Potential Treatment Processes and Mechanisms
Solids removal: sedimentation and filtration; Mineralisation: microbial growth; Nutrient uptake and transformation:
microbial, epiphyte and macrophyte growth; Nutrient storage: sediment adsorption and litter accumulation
OPEN WATER
Typical Ecological Characteristics
Dominant species: algae (or submerged macrophytes in low nutrient conditions) ; Vegetation: phytoplankton growth resulting
in secondary solids production, (macrophyte growth inhibiting mixing and removing solids by sedimentation and filtration)
Typical Physical Characteristics
Surface area : volume ratio: low; Water depth: 1m; Natural water regime: permanent, generally well mixed but may stratify
during still conditions, particularly in the warmer months
Potential Treatment Processes and Mechanisms
Solids removal: sedimentation (and filtration); Aeration: wind mixing, algal photosynthesis; Sterilisation: UV exposure;
Nutrient uptake and transformation: phytoplankton and submerged macrophyte growth; Nutrient storage: sediment
adsorption and accumulation
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 40
STORMWATER MANAGEMENT
Contract No.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 41
STORMWATER MANAGEMENT
Contract No.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 42
STORMWATER MANAGEMENT
Contract No.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 43
STORMWATER MANAGEMENT
Contract No.
STAGE OF PROJECT
DA Submission
Construction
Certificate
Pre DA : Preliminary (P) sketch/concept acceptable unless noted otherwise.
Pre- DA
DA Submission : Draft (D) sketch/concept acceptable unless noted otherwise.
Construction Certificate : Final (F) detail in accordance with relevant Council
Specification unless noted otherwise.
Site conditions topography, soils, groundwater, vegetation, and habitat
connectivity. P P F
Catchment context and land capability. P P F
Estimates of all water flows
o potable water supply requirements, N/A P F
o wastewater ( black and grey water components ), N/A P F
o roofwater volumes. N/A P F
Site and receiving water quality :-
o Water quality of the receiving waters
o Pre development modelled pollutant loads N/A P F
o Post development modelled pollutant loads. N/A P F
o A management plan identifying treatment measures, N/A P F
using a treatment train approach to meet water quality N/A P F
objectives. .
Site hydrology :-
o Pre development hydrology ;- runoff volumes, frequency,
and peaks. N/A P F
o Post development hydrology :- runoff volumes,
frequency, and peaks. N/A P F
o Stormwater volumes for pre and post development
scenario N/A P F
o A management plan which identifies measure to reduce N/A P F
hydrological changes.
Strategies for improving
o water efficiency and rainwater, stormwater, grey-water,
reclaimed wastewater, and reuse opportunities in P P F
accordance with Council policy/strategy
o protecting water quality,
o flood protection, P P F
o aquatic ecosystem protection or enhancement in P P F
degraded areas, P P F
o habitat connectivity protection or enhancement in
degraded areas. P P F
Integrated water infrastructure systems.
Proposed layout and street design measures to protect landform, natural P P F
water features and environment as per Chapter 4 of ARQ. P P F
Proposed trunk drainage measures to protect natural water feature and
environment . P P F
Proposed landscape features to protect natural water features and
environment as per Chapter 4 of ARQ. N/A P F
Provision of water tanks, detention, infiltration, SQID/s and other
stormwater infrastructure. N/A P F
Maintenance Operation Plan requirements for infrastructure and
stormwater treatment devices. N/A P F
Maintenance requirements for landscaping and rehabilitation.
Monitoring requirements (stream health, vegetation, water quality, N/A N/A N/A
rehabilitation works and systems). N/A P F
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 44
STORMWATER MANAGEMENT
Contract No.
DA Submission
DA Submission
STAGE OF PROJECT
Construction
Construction
Certificate
Certificate
Pre DA : Preliminary (P) sketch/concept acceptable unless noted otherwise.
Pre- DA
Pre- DA
DA Submission : Draft (D) sketch/concept acceptable unless noted otherwise.
Construction Certificate : Final (F) detail in accordance with relevant Council
Specification unless noted otherwise.
Details of the development showing :-
The boundary of the development. P F F P F F
The north point. P F F P F F
The location of services. N/A F F N/A F F
The footprint of the development. P F F P F F
The footprint of impermeable paved areas. N/A F F N/A F F
The location of fences P F F P F F
The total hardstand area of the site i.e the total area of roof area, garage area, N/A F F N/A F F
concreted area and impervious area ( footpaths, driveways, pool paved area).
A schematic showing the location and direction of flow of all sustainable water
elements (including: rainwater tank, infiltration, and detention system) and, if P F F P F F
applicable, the location of on site septic tank and disposal areas.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 45
STORMWATER MANAGEMENT
Contract No.
DA Submission
DA Submission
STAGE OF PROJECT
Construction
Construction
Certificate
Certificate
Pre DA : Preliminary (P) sketch/concept acceptable unless noted otherwise.
Pre- DA
Pre- DA
DA Submission : Draft (D) sketch/concept acceptable unless noted otherwise.
Construction Certificate : Final (F) detail in accordance with relevant Council
Specification unless noted otherwise.
the device chosen. N/A D F N/A N/A N/A
The Hydraulic regime of the SQID and the Hydraulic regime of the site, including
influence by tidal factors ( if applicable ). N/A D F N/A N/A N/A
The target pollutants to be removed by the SQID and how it relates to the
treatment train for the development. P D F N/A N/A N/A
An operations and maintenance plan detailing maintenance costs.
N/A D F N/A N/A N/A
SQID Maintenance and Operation Manual for the maintenance of Stormwater Quality
Improvement Devices must be prepared in accordance with Councils Maintenance
Operation Procedures Manual and contain:
Worksafe procedures (Workplace Health and Safety) for the safe operation and N/A P F N/A N/A N/A
maintenance of the SQID.
Supplier contact for parts, services and / or technical advice. N/A N/A F N/A N/A N/A
The mechanism required to clean the device ( eg manual removal, backhoe, N/A P F N/A N/A N/A
inductor truck ) etc.
Any consumables required for the maintenance of the device. N/A P F N/A N/A N/A
Maintenance and Inspection forms (REFER TO COUNCIL STD FORMS) which N/A N/A F N/A N/A N/A
clearly identify the data collection requirements.
A specified maintenance frequency Eg either in terms of maintenance on a N/A P F N/A N/A N/A
specific events basis, a periodic basis, or based on certain levels of material
trapped within the device. NOTE The statement Maintain as required is not
acceptable.
Dewatering and waste disposal procedures. This includes the names and N/A P F N/A N/A N/A
locations of licensed operators able to take the waste. Any and all regulated,
hazardous or other waste licensing requirements, which must be followed in the
transportation and disposal of the liquid and dry waste components.
Access points for vehicles / machinery as required. N/A P F N/A N/A N/A
An estimate of costs for maintenance incorporating the likely frequency of N/A P F N/A N/A N/A
cleanout, type of cleanout, the costs for transport, vehicle hire ( eg Inductor truck if
any ), disposal and consumables and replacement costs.
A schematic of the SQID, its connections to the drainage system, and description N/A P F N/A N/A N/A
of operations.
Electrical diagrams for any and all electronic components. N/A N/A F N/A N/A N/A
Inspection and monitoring frequency including the type of monitoring and data N/A P F N/A N/A N/A
collection required to assess the performance of the system.
Supplier contact for parts, services and / or technical advice. N/A N/A F N/A N/A N/A
The type of material likely to be caught in the device ( eg liquid or solid ). N/A P F N/A N/A N/A
A replacement cost for the asset. N/A P F N/A N/A N/A
Stakeholder notification requirements when undertaking maintenance. N/A N/A F N/A N/A N/A
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 46
STORMWATER MANAGEMENT
Contract No.
STAGE OF DEVELOPMENT
Construction Certificate
Construction Certificate
DA Submission
Pre DA : Preliminary (P) sketch/concept acceptable unless noted
DA Submission
otherwise.
DA Submission : Draft (D) sketch/concept acceptable unless noted
Pre DA
otherwise.
Pre-DA
Construction Certificate : Final (F) detail in accordance with relevant
Council Specification unless noted otherwise.
a. Plans of external and internal catchments N/A P F P F F
1. Site layout to include
Plans showing existing site topography, water courses, P F F P F F
contours
Final contours with cut and fill locations identified. P F F P F F
Property boundaries and lot lines. P F F P F F
General staging of works. P F F P F F
Staging of works including site clearing & topsoil stripping. N/A F F N/A F F
Location of site works, facilities and access. N/A N/A F N/A N/A F
Location of parking areas, roadways & tracks. N/A N/A F N/A N/A F
N/A N/A F N/A N/A F
Location of site storage & stockpile areas.
N/A N/A F N/A N/A F
Utility plans.
N/A P F N/A P F
Erosion risk mapping identification of low, medium, high and
extreme erosion risk areas. N/A F F N/A F F
Topographic site limitations which may include:- excessive
slope gradients; unstable hazardous terrain; flood inundation
areas; rock outcrops; active coastal dune systems; land
subject to wave attack; existing erosion; water bodies;
drainage problem areas; areas of potential mass movement.
2. Vegetation layout
General location, nature and condition of existing vegetation. P F F P F F
Identification of buffer width requirements adjacent to N/A F F N/A F F
watercourses.
Location plan of protected trees and bushland, non N/A F F N/A F F
disturbance areas, buffer zones, disturbance control fencing
and limits of clearing.
Revegetation landscape plan (including staging). N/A N/A F N/A N/A F
3. Soil properties
Location and limitations of major soil types on site. N/A F F N/A F F
Identification of all known areas of dispersive soils (more than N/A N/A F N/A N/A F
10% being dispersive).
The R and K factors for the RUSLE and Soil Loss Classes N/A N/A F N/A N/A F
(delineated where more than one occurs).
Soil hydrologic group [ Managing Urban Stormwater, Soils N/A N/A F N/A N/A F
and construction NSW Dept of Housing 1998 Appendix F].
Soil texture group Type C, F or D N/A N/A F N/A N/A F
4. Drainage
Plans of both temporary and permanent drainage, including N/A P F N/A P F
design/capacities of major drains.
identification of all proposed temporary and final overland flow N/A P F N/A P F
paths.
any proposed diversions of overland flow paths or N/A N/A F N/A N/A F
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 47
STORMWATER MANAGEMENT
Contract No.
STAGE OF DEVELOPMENT
Construction Certificate
Construction Certificate
DA Submission
Pre DA : Preliminary (P) sketch/concept acceptable unless noted
DA Submission
otherwise.
DA Submission : Draft (D) sketch/concept acceptable unless noted
Pre DA
otherwise.
Pre-DA
Construction Certificate : Final (F) detail in accordance with relevant
Council Specification unless noted otherwise.
watercourses from the site.
Lawful point of discharge, easements/land required for lawful N/A P F N/A P F
discharge.
5. Erosion and sediment control proposal including
Site specific text overview and design philosophy of erosion N/A P F N/A P F
and sediment control proposal
Location (on plans), type and function of drainage, erosion and N/A P F N/A P F
sediment control measures (the location plans must include
areas external to the site where these areas impact or are
impacted upon by the drainage or ESCP of the subject site).
Areas proposed for clearing (maximum of 2ha. Per stage ) N/A F F N/A F F
Calculation of Sediment pond sizes during construction. N/A N/A F N/A N/A F
Timetable, integration/sequencing of ESCP with staging of N/A F F N/A F F
works
RUSLE calculations to evaluate current annual soil loss and N/A P F N/A N/A F
likely annual soil losses from the proposed development
incorporating the proposed ESCP
Water quality monitoring program with water quality objectives, N/A N/A F N/A N/A F
parameters to be monitored, locations and monitoring
frequency.
N/A P F N/A P F
Proposed response to failure of system and non-compliance
with discharge quality standards.
N/A P F N/A P F
Reporting procedures.
N/A P F N/A P F
Procedures for amending the ESCP
g. Acid soil management plan. N/A P F N/A P F
h. Details of receiving waters including quality characteristics. N/A F F N/A F F
i. Assessment of effects of construction phase of development on N/A F F N/A F F
receiving waters.
j. Details of proposed water quality monitoring program. N/A P F N/A P F
k. If the development proposal is for a subdivision containing master N/A F F N/A F F
lots ie. Large lots to be further subdivided under a future DA, then the
ESCP must be prepared containing details of erosion and sediment
controls for each master lot, independent of the ESCP for any other
lots.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 48
STORMWATER MANAGEMENT Contract No.
TABLE D7A 6 POLLUTANT REDUCTION EFFICIENCIES ( Brisbane City Council Design Guidelines for Stormwater Quality Improvement Devices Final Draft 4 November 1999)
Litter CoarseSednt Suspended Nutrients (N & P) Oxygen Hydrocarbons Pathogens Heavy Metals
Management Device Solids Demanding
Substances
Source Controls
Street Sweeping HM M - - L - - L
Rubbish Bins HM - - - L - - -
Education L L L L L L L L
Primary Treatments Small Scale
Litter Baskets LM L - - L - - -
Baffle Pits L LM L L L - - L
Catch Pits L LM L L L - - L
Nets H - - - - - - -
Medium Scale Devices
Litter & Trash Racks M L - - L - - -
In Ground GPT H VH H L L LM L - L
In Line Separators M LM - - - - - -
Sediment Traps L H L L L L L L
Secondary Treatments
Filter Strips M H M LM L L M L
Grass Swales LM MH M LM L L M M
Sand Filters - MH MH M M M M M
Infiltration Trench / Basin - MH M M M M M MH
Porous Pavement - H MH M M M H MH
Extended Detention Basins - MH LM L L L M L
Tertiary Treatments
Water Quality Ponds M VH H LM LM L L L LM
Constructed Wetlands M - VH H M M L M M H
Legend: - = Neglible benefit L = 10 30 % Pollutant reduction efficiency M = 30-50% Pollutant reduction efficiency H = 50 75 % Pollution reduction efficiency VH = 75-100% Pollution reduction efficiency
TABLE D7A 7 Brisbane City Council design guidelines for Stormwater Quality Improvement Devices Final Draft 4 November 1999
Device / Practice Maximum Flow Rate (L/S) for Design Event (Q 3 month)
Target Size 30 50 70 100 150 200 250 300 350 400 450 500 600 700 800 1000 1250 1500 1750 2000 2500 3000 4000
Pollutants Criteria
In Ground GPT
Humes Humeguard in Litter, Model No CONTACT CSR HUMES FOR SIZING INFORMATION
line Gpt Sediments
Ecosol RSF 4000 Flow L/S 300 450 600 750 900 1050 1200 1350 1500 1800
Ecosol RSF 6000 Flow L/S 450 600 750 900 1050 1200 1350 1500 1800
Rocla Cleansall Inlet CL375 CL600 CL900 CL1350 CL1800
Rocla Downstream Flow L/S DD1200 DD1800 DD2400 DD3000
Defender
Baramy Inlet 300 1300
CDS CDS unit Flow L/s F0908 P1512 P1516 P2018 P2028 P3024 * Combinations
Oil and Grit Separators
Humes Humeceptor Hydrocarbons Model No STC2 to STC27 CONTACT CSR HUMES FOR SIZING INFORMATION
Ecosol RSF 5000 Sediments Flow L/s 300 450 600 750 900 1050 1200 1350 1500 1800
CDS CDS unit Flow L/s F0908 P1512 P2018 * SIZED ON FLOW, CAPACITY AND/OR MAINTENANCE COSTS
Grease Traps
Everhard Grease Traps Hydrocarbons Cap L 250-10000 L Traps
Open GPT
Baramy Direct Flow Litter, sediment Inlet Dia. 300 1500
Baramy Channel Litter Treatable Flow = 40% of Channel Depth
End of Pipe Litter Nets
Stormwater Pratten Trap PT Litter Inlet Dia PT 2000
Systems 2000
Net Tech Interceptor Inlet Dia ALL
Litter Baskets
Ecosol RSF Series Litter, Sediment Unit Dia. 300 450 600
Ingal Litter, Sediment
Side Entry Trap
Ecosol RSF 100 & GSP Litter, Sediment Pit Size Gully Pits and pavement grated inlets
Sediment Trap
Hydro Storm King Sediment Unit Size m 3.0 x 2.57 3.66 x 3 5.0 x 3.59 6.0 x 4.13
Hydro Overflow Sediment Unit Dia. 1.4 2.6 3.4 4.1 Sized to suit flow
Swales & Filter Strips
Grass Swales, Filter Strips, Nutrients, Sediments, Hydraulic residence time
Bioretention Systems Metals, Litter Refer to ARQ for design considerations
Notes:
Devices cannot be selected on the basis of size alone. All relevant design criteria must be taken into account when selecting a device.
Other relevant criteria include: Pollutant characteristics, maintenance, hydraulic head, pipe gradient, tidal influence, health, safety, aesthetics.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 50
STORMWATER MANAGEMENT Contract No.
Figure D7-10 Hastings and Camden Haven River Catchments water quality regions
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 51
STORMWATER MANAGEMENT Contract No.
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 52
STORMWATER MANAGEMENT Contract No.
Average
450.0
437 Average Max
Average Min
400.0 400
357
350.0
313
300.0 298
Rainfall (mm)
269
259
250.0 243
195.6
177.8
200.0 199
159.5
154.0
182
151.1
147.3
155
122.3
121.7
150.0
103.2
130
103
94
93
91
100.0
72.5
79
79
63.0
69
57.9
67
58
50.0
37
32
29
0.0
Oct
Nov
Dec
Mar
May
Jul
Jan
Feb
Jun
Apr
Aug
Sep
Month
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 53
STORMWATER MANAGEMENT Contract No.
433
450
392
400
336
328
350
318
Rainfall (mm)
300
258
255
235
250
200
200
175
167
158
140
143
138
150
118
115
114
111
106
95
100
102
91
49
48
80
44
50 72
60 63 63
53 50
0 25 24 22
May
Jul
Jan
Feb
Jun
Mar
Aug
Sep
Nov
Dec
Apr
Oct
Month
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 54
STORMWATER MANAGEMENT Contract No.
350
303 301
300
Average
Maximum
250 245
Minimum
200
Rainfall (mm)
187 189
157
151
159 161
140
150 146
128
110
105
97
96
100
83
89
78
92 86
69
64
63
61
53
48
47
47
50
21 40
33
16 31
24
23
0
Oct
Jul
Jan
Jun
Nov
Dec
May
Mar
Apr
Feb
Aug
Sep
Month
HASTINGS COUNCIL
AUSPEC-1 D07-Stormwater Management- Hastings 2003 Rev 1.doc February 2004 (Copyright )
Page 55
STORMWATER MANAGEMENT Contract No.
2500
Average Annual Max
2062
Avaerage Annual
Avaerage Annual Min.
2000 1814
1526
Rainfall Averages (mm)
1500
1225
1297
1172
1040
974
1000 837
500
0
Coastal Region Lower Inland Upper Inland
Region