DETAILED METHOD STATEMENT

ITEM OF WORK QUANTITY DETAILED OF PLANT OUTPUT MANPOWER TIME


METHOD PRODUCTIVI REQUIRED
TY DAYS
General 1 lot Transport of 1-stake truck 1 Foreman 1 Day
Condition site facilities 8 Laborers
Mobilization and
equipment
needed at site
Temporary 100 lm Sawali Fences 1 Foreman 1 Day
Facilities with GI Gate 4 Carpenters
4 Mason
8 Laborers
Accommodation 1 lot Field Office, 1 bagger 1 Foreman 4 Day
Barracks, CR, mixer 4 Carpenters
warehouse 4 Mason
8 Laborers
Electrical 1 lot Install power 2 Electrician 1 Day
Consumption lines & lights
Water 1 lot Drive well & 1 Plumber 1 Day
consumption install pump 2 Laborer
Site Works Clear 176 sq.m. Clear Area of 1 Grader 1 Foreman 1 Day
& Grub Debris
Manual 129.1 cu.m Excavate 1.5m 1 md/cu.m. 1 Foreman 15 Days
Excavation from NGL 8 Laborers
Backfill 139.7 cu.m 0.5 md/cu.m. 8 Laborers 9 Days
1st floor
Reinforce concrete Foundation
Reinforcement 2220 kg Site Cut & 3 Bar cutters .16 mh/kg 9 Benders 3 Days
Bent 9 Installer
Concrete 22.5 cu.m Site Mixed 3 Bagger 17 mh/cu.m 4 Mason 4 Days
mixeer 8 Laborers
Columns 3007.6 kg Site Cut & 3 Bar cutters .16 mh/kg 9 Benders 4 Days
Reinforcement Bent 9 Installer
Column Forms 115.2 sq.m Site 20 frames 7 mh/sq.m. 20 Carpenters 4 Days
Fabricated 10 Laborers
Concrete 11.52 cu.m. Site Mixed 3 Bagger man 17 mh/cu.m 4 Mason 3 Days
column 1 Portalift 8 Laborers
Beams & slabs 7676.98 kg 3 Bar cutters .16 mh/kg 9 Benders 9 Days
Stairs 9 Installer
Reinforcement
Forms 342.6 sq.m. 7 mh/sq.m. 20 Carpenters 10 Days
10 Laborers
Concrete 40.68 cu.m. 3 Bagger man 17 mh/cu.m 4 Mason 8 Days
1 Portalift 8 Laborers
2nd floor
Columns 3007.6 kg Site Cut & 3 Bar cutters .16 mh/kg 9 Benders 4 Days
Reinforcement Bent 9 Installer
Column Forms 96 sq.m. Site 7 mh/sq.m. 20 Carpenters 3 Days
Fabricated 10 Laborers
Concrete 9.6 cu.m Site Mixed 3 Bagger man 17 mh/cu.m 4 Mason 2 Days
column 1 Portalift 8 Laborers
Beams & slabs 7676.98 kg 3 Bar cutters .16 mh/kg 9 Benders 9 Days
Stairs 9 Installer
Reinforcement
Forms 342.6 sq.m. 7 mh/sq.m. 20 Carpenters 10 Days
10 Laborers

Concrete 40.68 cu.m. 3 Bagger man 17 mh/cu.m 4 Mason 8 Days


1 Portalift 8 Laborers
DETAILED METHOD STATEMENT

3rd floor
Columns 3007.6 kg Site Cut & 3 Bar cutters .16 mh/kg 9 Benders 4 Days
Reinforcement Bent 9 Installer
Column Forms 96 sq.m. Site 7 mh/sq.m. 20 Carpenters 3 Days
Fabricated 10 Laborers
Concrete 9.6 cu.m Site Mixed 3 Bagger man 17 mh/cu.m 4 Mason 2 Days
column 1 Portalift 8 Laborers
Beams & slabs 7676.98 kg 3 Bar cutters .16 mh/kg 9 Benders 9 Days
Stairs 9 Installer
Reinforcement
Forms 342.6 sq.m. 7 mh/sq.m. 20 Carpenters 10 Days
10 Laborers
Concrete 40.68 cu.m. 3 Bagger man 17 mh/cu.m 4 Mason 8 Days
1 Portalift 8 Laborers
Masonry 528 sq.m. -Site 3 mh/sq.m. 4 Mason 25 Days
Ground Floor Fabricated 4 Laborers
-Site Mix
Mortar
-59 Truck CHB
2nd Floor 337.5 sq.m. -Site 3 mh/sq.m. 4 Mason 16 Days
Fabricated 4 Laborers
-Site Mix
Mortar
-59 Truck CHB
3rd Floor 337.5 sq.m. -Site 3 mh/sq.m. 4 Mason 16 Days
Fabricated 4 Laborers
-Site Mix
Mortar
-59 Truck CHB
Thermal 150 sq.m. Membrane Subcontract 14 Days
Protection Topping
Waterproofing
Doors & 1 Lot Glass Doors & Subcontract 45 Days
Windows Curtain Walls
Except at T&B
Finishes
Wall Finishes 792 sq.m. 3 bagger 1.5 mh/sq.m. 4 Mason 25 Days
Plastering 1st mixer 2 Laborers
Floor
2nd Floor 675 sq.m. 3 Bagger man 1.5 mh/sq.m. 4 Mason 21 Days
1 Portalift 2 Laborers
3rd Floor 675 sq.m. 3 Bagger man 1.5 mh/sq.m. 4 Mason 21 Days
1 Portalift 2 Laborers
2nd Floor CR 6 sq.m. 8 mh/sq.m. 1 Mason 3 Days
TILES 1 Laborer
3rd Floor CR 6 sq.m. 8 mh/sq.m. 1 Mason 3 Days
TILES 1 Laborer
Floor Finishes Ceramic Tiles
1st Floor 176 sq.m. 6 mh/sq.m. 4 Mason 17 Days
4 Laborers
2nd Floor 176 sq.m. 6 mh/sq.m. 4 Mason 17 Days
4 Laborers
3rd Floor 176 sq.m. 6 mh/sq.m. 4 Mason 17 Days
4 Laborers
Painting Interior 1 Lot Subcontract 20 Days
Exterior 1 Lot Subcontract 20 Days
Electricals 1 Lot Subcontract 80 Days
Rough-in
Fixtures 1 Lot Subcontract 30 Days
DETAILED METHOD STATEMENT

Plumbing 1 Lot Subcontract 80 Days


Rough-in
Fixtures 1 Lot Subcontract 10 Days
Demobilize Final Cleaning 4 Carpenters 7 Days
Clean-up 8 Laborers