Académique Documents
Professionnel Documents
Culture Documents
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
8.0 References
9.0 Appendices
Requirements as follows:
a) Extension of the scope to include all equipment used for lifting or lowering
loads;
b) inspection requirements for all lifting gear, cranes, hoists, excavators, piling
frames, etc. and new inspection requirements for other lifting equipment;
c) persons who have control of either equipment, a person who uses, supervises
or manages the use of equipment or the way in which equipment is used.
Page 2 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
a) employers who provide equipment for use by others on their premises and
who have some control over it e.g. a hoist provided by a Principal Contractor
for use by various contractors on a site;
b) plant hire companies who hire out equipment and have control over how it is
maintained;
c) Principal Contractors who have some control over the way in which sub-
contractors use equipment.
2.0 Scope
Regulations applies to any equipment used for, or any operation concerned with, the
lifting or lowering of a load or person.
Cranes
Goods and passenger lifts
Hoists
Mobile elevating work platforms (MEWP's)
Scissor lifts
Vehicle hoists
Gin wheels
Ropes used for access (e.g. by abseilers)
Fork lift trucks
Lorry loaders (HIAB's), etc.
Accessories for lifting (lifting gear) are also lifting equipment and include:-
Apart from lifting eyes which screw into the load, points provided on the load to assist
in lifting it, e.g. lifting lugs on a skip, are part of the load and are not part of the lifting
equipment. However they will need to be checked on a regular basis to ensure they
are of adequate strength. In some cases, particularly where lifting lugs are welded to
a load, it may be necessary to test the strength of the lifting points. (load test / NDT)
Page 3 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
Health and Safety Executive guidance says that competent persons must be
independent and impartial. This does not prevent someone working for the same
organisation being the competent person so long as they can prove independence
and impartiality from production, progress and/or profit.
To ensure that the condition of lifting equipment does not deteriorate so as to become
dangerous a regime of in-service inspections / thorough examinations must be carried
out at suitable intervals.
Due to the nature of work and the environment in which contractors carries out its
undertaking it is foreseeable for all lifting equipment to deteriorate. It could be
subjected to adverse weather conditions, hazardous chemicals or substances,
physical damage through miss-use or normal wear and tear.
The minimum inspection regime, set out below, should be based on manufacturers
information / instruction and other statutory obligations. A more stringent inspection
regime may be required dependant on the local site environment / conditions and the
likelihood/speed of possible deterioration.
Page 4 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
- Ropes
- Hooks
- Lifting beams or frames
- Eyebolts
- and other components for attaching loads to machinery for lifting
-
The means of inspection shall be proven by the following colour-coding:
- January - March : Yellow
- April June : Green
- July September : Orange
- October December : Blue
Note : These equipment should be inspected visually before every use for
possible defects.
Lifting equipment used for lifting persons must be thoroughly examined at least every
6 months.
Vehicular equipment used for lifting operations e.g. cranes, excavators, piling frames,
MEWPs, forklift trucks and telescopic handlers must be checked daily and any
defects recorded on the daily work equipment check form in Appendix 2. The vehicle
operator should also be competent to carry out the weekly visual inspection in
addition to the daily checks.
The weekly inspections of all lifting equipment, accessories and appliances should be
recorded on the form in Appendix 6. These weekly checks must be in addition to the
pre-use checks carried out by the slinger/signaller. Each individual item must be
entered separately with its unique identification number and a description. Following
the inspection the competent person must sign to confirm completion and add either
no defects found or detail any defects found.
Page 5 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
Lifting equipment used for lifting person should be subject to a formal daily visual
inspection by the operator. Any defects found must be rectified before use.
Records and Reports
The person carrying out a thorough examination must make a written report as soon
as possible. The information that must be contained in the report is set out in the
regulations. However, it can be in any suitable format such as a certificate, register
entry, etc provided a signature authenticates it. The report must be provided to the
user and, if it is hired equipment, to the hire company. Any potentially dangerous
defects should be notified to the user immediately. It is an offence to use the
equipment without rectifying the defects, either immediately or within the time period
specified.
If any defect is noted which constitutes an existing or imminent serious risk, a copy of
the report must be sent to the enforcing authority.
This means that hired or newly purchased second-hand equipment must have with it
at least a summary of the last examination/inspection report. The duty is on both the
person receiving the equipment and the person from whom it is being obtained e.g.
Page 6 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
the hire company must supply the information and the contractor receiving the
equipment must ensure that the information has been supplied. The information
required will include:
a) Name and address of the duty holder for whom the thorough examination or
inspection was made;
g) Safe working load of the equipment or its safe working load for each
configuration, as appropriate;
It is important when hiring equipment that there is no doubt over who will be
responsible for carrying out any inspections/examinations required during the period
of the hire. It will normally be sensible for this to be done by the hire company owning
the equipment and this should be reflected in the hire agreement.
Lifting equipment is also work equipment Prior to the operation of any work
equipment used for lifting operations, line management must satisfy themselves that
the operator has sufficient training, knowledge and experience of the operation of the
equipment before authorising such operators in writing.
Page 7 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
c) How often the lifting equipment will be used to carry out the task;
For example, select a MEWP with an area of sufficient size and capacity to
accommodate the number of people who need to be present on it and the work
equipment that might be necessary.
Lifting equipment used for lifting persons should, where practicable, be specifically
designed for the purpose. Where it is necessary to use equipment that is not
specifically designed for the purpose e.g. a crane and man-riding cage or basket,
appropriate precautions must be taken.
Wherever anybody needs to stand on a part of the lifting equipment, whether for
operational, maintenance or inspection purposes, the working place/platform must be
such as to minimise the risk of slips, trips or falls. It should be big enough and have
edges and openings guarded. Where necessary, for example on the metal floor of a
MEWP, there should be suitable non-slip surfaces.
Operator Protection
Where the operator may be affected by the environment there must be adequate
protection; the environment may include the weather and any effects created by the
work being carried out e.g. noise or dust. Protection may include the provision of a
cab and ventilation or heating.
Lifting equipment that could be affected by high wind must be clearly marked with the
maximum wind speed up to which it can be used. It will then be necessary to be able
to determine the wind speed. In most cases this will mean using an anemometer.
Site limitation of wind speed of 10m/s (32kph) will be enforced and the lift must be
cancelled.
Tower cranes should be fitted with an anemometer at the most exposed position i.e.
the top. For other equipment, e.g. MEWP's used outdoors, fitted anemometers may
not be practicable but it will be necessary to have an anemometer available at the
work site.
Wind imposes a horizontal load on the crane as well as on the load that can cause
instability to both the crane and the load which could result in overturning. Lifting of
irregularly shaped loads will require more consideration and possibly the consultation
of manufacturer prior to the lift if necessary. The lifting operation should be
stopped if the load is found to be moving significantly
Page 8 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
It is required to ensure stability of lifting equipment for each load. However, cranes
and other equipment with a significant risk of overturning and/or overloading should
be provided with rated capacity indicators (ASLI's) or rated capacity limiters e.g.
hydraulic dump valves which limit the load that can be lifted.
Rated capacity limiters are often used in excavators, HIAB's, MEWP's, etc.
Skips used for lifting duties should be clearly marked with their maximum load and
either tested or lifted in a tested cradle.
*The design of lifting points welded to fabrications must take into account the type of
weld, the standard of welder required and the testing procedure. Non-destructive
testing (NDT) such as crack testing using penetrative dye may be sufficient in these
circumstances.
Where practicable lifting equipment for lifting persons should be specifically designed
for the purpose. Lifting equipment that is designed for lifting persons must be clearly
marked to this effect. The carrier must clearly display the maximum number of
persons to be carried as well as SWL. Lifting equipment that is not suitable for lifting
persons but may be used inadvertently must be clearly marked as not suitable for
lifting persons e.g. goods hoists or muck skips.
There are various requirements in respect of "carriers". This term refers to whatever
device is used to support people while being lifted or lowered and includes a lift car,
construction passenger hoist cage, bosun's chair, safety harness used by a rope
access expert (abseiler), etc.
Regulation creates the same duty, qualified by "so far as is reasonably practicable", in
relation to people working from carriers that are not fully enclosed e.g. MEWP
platforms, bosun's chair, etc. Examples of the type of precautions that may be
required include:
a) fencing or a trip device to prevent someone being injured by the scissor arms
or platform base of a MEWP;
Page 9 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
Regulation requires the lifting equipment to have suitable devices to prevent the
carrier falling in the event of failure of the primary means of lifting. This could include:
d) safety gear;
e) check valves (for hydraulically powered systems).
In addition to these devices, supplementary measures may be necessary to ensure
safety when equipment not specifically designed for lifting persons is used, e.g. a
crane with man-riding cage. These could include:
b) daily inspections;
There must be a means for any person trapped in a carrier to summon help.
Appropriate means should be determined by assessment of the circumstances and
may range from a shout for help where people are working nearby to a telephone or
radio link. In addition, a means of rescue must be provided. This can include an
emergency means of lowering the carrier to a safe position or self-rescue equipment
such as a rope ladder or an inertia reel system.
a) lifting equipment should be installed to minimise the need to lift loads over
people;
Lifting equipment with one fixed safe working load (SWL) e.g. an overhead crane,
forklift truck, chain, sling, etc, must be marked with the SWL.
Page 10 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
Where the SWL varies with operating radius or according to how the equipment is
configured it must be clearly marked with the SWL for each configuration or adequate
information must be provided to indicate to the user the SWL. This could be in the
form of a plate, chart or certificate.
Where there is significant hazard, such as in construction work, rated capacity indicators or
rated capacity limiters must be used.
Structural elements of lifting equipment that may be dismantled, e.g. crane jib
sections, must be clearly marked to show the equipment they are part of.
The competent person required to carry out the planning is unlikely to be the same
competent person required to carry out a thorough examination. They should have
adequate practical and theoretical knowledge and experience of planning lifting
operations.
Planning
Plans for lifting operations must consider the risks identified by the risk assessment
and determine the resources, procedures and responsibilities necessary for the
operation to be carried out safely.
a) initial planning to ensure that lifting equipment is provided which is suitable for the
range of tasks it will have to carry out;
b) planning of individual lifting operations so that they can be carried out safely with
the equipment provided.
Initial planning is essentially about selection and is therefore closely linked with the
requirements of Regulation.
For routine lifting operations the planning of each individual lift will be the
responsibility of the person using the equipment e.g. the slinger, forklift driver, rigger,
etc. It is important that this person has appropriate training, knowledge and
experience.
Page 11 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
Management has responsibility to ensure that all operators have sufficient training,
knowledge and experience of operating the equipment.
A typical plan for a slinger using a crane, forklift, MEWP, HIAB would be:
d) Prepare a place to set down the load (timber packing or similar may be
necessary to avoid trapping the slings or chains);
g) Make the lift (a trial lift may be necessary to establish the centre of gravity of
the load, tag lines may be necessary to stop it swinging);
i) Clear up.
This can form a standard set of instructions to a slinger. Similar instructions can be
formulated for routine operations involving other lifting equipment.
For routine operations a generic plan may be suitable taking cognisance of the above
list of considerations although it should be reviewed periodically to ensure that it
remains valid. For one-off or more complex lifts there will need to be a specific plan
for each lift.
Supervision
Supervision should be proportionate to the risk and the level of experience of the
personnel involved. Experienced operators will not require direct supervision each
time they carry out a routine lift but they may require supervision for an unusual lift or
a lift in hazardous conditions.
Safe Working
The requirement to carry out lifting operations in a safe manner clearly covers all
aspects of how a lift is done. Examples of the issues that need consideration are:
Page 12 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
These amount to good practice and do not require further elaboration in this
document.
Communications
Failures in communications are often root causes of lifting incidents and can also be
the most difficult to detect. Good training and adherence to correct procedures are
vital but checking the actual situation at the worksite is of utmost importance. For
example:
c) If not is there an established system of signals in strict use that they all know
and understand?
d) Warning signage is displayed where the personnel are able to see it?
f) What communication is required between the worksite and the source of any
technical assistance elsewhere?
Communication also extends to warning personnel of the lifting activity and keeping
the lift area clear of personnel not involved in the lifting operation. All members of the
lifting team must be sure of their individual tasks and their team members' roles in
order to fully and easily communicate with one another. Designated Slinger / Signaller
/ Banksman / Rigger shall be clearly and separately identifiable, by use of reflective
vest or other conspicuous clothing or marking.
Never start any lifting operation until all concerned have been briefed in an initial
safety meeting, ensuring that they understand their role and responsibilities and that
they have signed onto the Permit to Work or record of attendance at the initial safety
meeting.
Lifting operations of a routine nature that involve minimal hazards and low risk to
operatives, equipment and process plant. Where basic lifting operations are required
they may be undertaken accompanied by a task specific risk assessment that
identifies the related issues and control measures necessary to perform the
task/activity safely.
Lifting operations without suitable control methods may impose a medium risk to
personnel, equipment or process plant. Where such lifting tasks take place the activity
Page 13 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
may only proceed accompanied by a method statement and specific risk assessment.
See appendix 3 for Method statement contents.
Complex lifting operations are those that fall within the category of high risk and are
unique which require specific controls and procedures to eliminate unacceptable
hazards etc. Examples of complex lifts are tandem lifts, lifting loads on or near live
plant.
The person nominated by the project management, responsible for the planning and
management of lifting operations and ensuring that the operations are performed by
persons having appropriate knowledge and ability. The appointed person will have
been trained and must have detailed knowledge of cranes, lifting
operations/equipment and legislation to an appropriate level for the work that he/she
has been appointed to carry out.
A person with sufficient knowledge, skill, experience and training etc. and has been
authorised by the Project/Construction Manager to supervise the general movements
of cranes around site and specific lifting operations to ensure that they are carried out
in accordance with the plan laid down by the appointed person.
NB Any proposed changes to that plan must be referred back to the Appointed
Person for approval before the operation proceeds.
A trained competent person(s) whose duties are to locally control the lift operations,
assist in crane movements and takes instructions from the competent person.
It is essential that crane operators can clearly identify the nominated Slinger /
Signaller / banksman/rigger. This individual must be uniquely distinguishable from
other persons working in the area. This can be achieved by the wearing of specific
coloured PPE i.e. Orange safety helmet and orange hi-visibility clothing marked
banksman. Project may deviate from this colour standard, however the principles
must be implemented.
All hand signals must conform to British standard code of practice BS7121 and where
radios are used, a specific channel must be available for each operation. This will
avoid any confusion where multiple operations are taking place.
Page 14 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
5.0 Responsibilities
5.1 Project /Construction Manager
The project/construction manager will usually be the senior person in control of the
site/work location. His responsibilities are as follows and must be undertaken for all
lifting operations, before any crane is used.
d) To ensure that appropriate arrangements are in place for the control of change
of any method statements
e) Ensure all relevant site conditions are investigated, assessed and are made
known to all relevant personnel.
f) Any site constraints (i.e. access limitations) are to be included in the health
and safety plan.
Responsibilities are:
e) Check site conditions for proximity hazards e.g. overhead lines, space
available and stability of ground of foundations
Responsibilities are:
Page 15 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
a) Conduct periodic audits to confirm that pre-use checks are being conducted
and that defects are reported to supervision/nominated person.
c) Ensure that all equipment is suitable with adequate certification, that weekly
inspections are taking place and details recorded in the site register.
d) Ensure that maintenance, inspection and examination records are current and
copies held on file.
e) Ensure that cranes used for man riding have no free fall facility and automatic
braking (dead man's handle/switch).
g) Ensure the position of the crane and load to be lifted is agreed with the crane
operator and Rigger/Slinger/Signaller. Maintain a close liaison with the crane
operator(s)
i) Check clearances and available room for crane operations and barrier off as
appropriate to keep pedestrians away from the lifting activities.
J) Ensure the Rigger/Slinger/Signaller controlling the lift has been trained and is
clearly visible to the crane driver by wearing either a uniquely marked helmet,
arm-band (printed with name RIGGER or fluorescent vest,(printed with name
RIGGER at the back) etc.
b) Read and understand the lifting plan, method statement and risk assessment
Page 16 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
f) Ensure the crane is set up in agreement with the crane operator and the
nominated competent person
g) Erect adequate barriers and warning signs to ensure the area remains secure
k) Clean up
6.0 Procedures
6.1 Basic Lifting Operations
A competent person (Rigging Supervisor) must produce a task specific lifting
operations assessment part 1 of the questionnaire in Appendix 5. e.g. Use of lifting
blocks, pull-lifts etc.
Non routine lifting operations e.g. tandem lifts, lifting personnel (man riding), working
over/near live plant, fragile or expensive loads etc.
The Appointed Person assisted by the Competent Person must prepare a specific
lifting study/method statement and risk assessment for the actual activity. See
Appendix 3 for model lifting study content and complete the questionnaire at part 3 in
Appendix 5.
These requirements should be discussed at the initial safety meeting with contractors.
Page 17 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
c) Who the contractor has nominated as his Appointed Person to liase with the
Appointed person.
8.0 References
9.0 Appendices
Appendix 1 - Examination and Inspection Flow sheet
Page 18 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
NO YES
Does it have an
YES EC declaration of NO
conformity dated
within the last 12
months?
NO Does its safety depend on
how it is
installed/assembled?
YES
YES
Does it have a
Have it thoroughly examined current thorough
before use to check that it examination
has been installed/assembled certificate?
correctly and is safe to use.
NO
Have it thoroughly
Does it have a current in- NO
examined by a
service thorough examination
competent person.
report?
YES
Has a competent person (e.g.
the operator) inspected it in
the last 7 days and is a record
available?
NO YES
Arrange for the necessary
inspection and record it (e.g. Proceed
in a register)
Page 19 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
1. Responsible person(s)
2. Description of task
7. Load characteristics (e.g. Centre of gravity, weight, size, shape, bulk, integrity, availability
of suitable lifting points)
8. Lifting equipment and accessories (lifting gear) to be used including type, SWL, method
of attachments, anchor points etc.
Page 21 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
3. Load calculations
Page 22 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
Lifting Operations Assessment Questionnaire
If the answer to all questions is yes, you may proceed with the lifting operation in accordance with recognised good practice and
procedure.
If the answer to any of the above questions is no then please complete Part 2 of the assessment.
Signature
If you can answer yes to all the above questions proceed with the lift.
If the answer is no to any of the above questions seek advise from your immediate supervisor.
Signature..
Page 23 of 24
Unique Identifier: P-SCCJ-HSE-004
Document Type: PR
Procedure Revision: 0
Date: 22 December 2016
Title:
LIFTING EQUIPMENT PROCEDURE
Page 24 of 24