Vous êtes sur la page 1sur 9

J.G.

Delfin status showed that it could no longer complete the projects as


agreed upon. Respondent also informed petitioner that it was
G.R. No. 173155 March 21, 2012 already in default having failed to complete the projects within
R.S. TOMAS, INC., Petitioner, 120 days from the effectivity of the contract. Respondent further
vs. notified petitioner that the former was terminating the contract.
RIZAL CEMENT COMPANY, INC., Respondent. It also demanded for the refund of the amount already paid to
DECISION petitioner, otherwise, the necessary action would be instituted.
PERALTA, J.: Respondent sent another demand letter17 to Times Insurance for
This is a petition for review on certiorari under Rule 45 of the the payment of 1,472,000.00 pursuant to the performance bond
Rules of Court filed by petitioner R.S. Tomas, Inc. against it issued.
respondent Rizal Cement Company, Inc. assailing the Court of On November 14, 1991,18 respondent entered into two contracts
Appeals (CA) Decision1 dated December 19, 2005 and with Geostar Philippines, Inc. (Geostar) for the completion of the
Resolution2 dated June 6, 2006 in CA-G.R. CV No. 61049. The projects commenced but not completed by petitioner for a total
assailed decision reversed and set aside the Regional Trial consideration of 3,435,000.00.
Court3 (RTC) Decision4 dated June 5, 1998 in Civil Case No. 92- On December 14, 1991, petitioner reiterated its desire to
1562. complete J.O. #P-90-212 and J.O. #P-90-213 and to exclude J.O.
The facts of the case, as culled from the records, are as follows: #P-90-214,19 but the same was denied by respondent in a
On December 28, 1990, respondent and petitioner entered into a letter20 dated January 14, 1992. In the same letter, respondent
Contract5 for the supply of labor, materials, and technical pointed out that amicable settlement is impossible. Hence, the
supervision of the following projects: Complaint for Sum of Money21 filed by respondent against
1. J.O. #P-90-212 Wiring and installation of primary and petitioner and Times Surety & Insurance Co., Inc. praying for
secondary lines system. the payment of the following: 493,695.00 representing the
2. J.O. #P-90-213 Supply and installation of primary protection amount which they owed respondent from the downpayment and
and disconnecting switch. advances made by the latter vis--vis the work accomplishment;
3. J.O. #P-90-214 Rewinding and conversion of one (1) unit 2,550,945.87 representing the amount incurred in excess of the
3125 KVA, 34.5 KV/2.4 KV, 3 Transformer to 4000 KVA, 34.5 cost of the projects as agreed upon; 294,000.00 as liquidated
KV/480V, 3 Delta Primary, Wye with neutral secondary. 6 damages; plus interest and attorneys fees.22
Petitioner agreed to perform the above-mentioned job orders. Times Insurance did not file any pleading nor appeared in court.
Specifically, it undertook to supply the labor, equipment, For its part, petitioner denied23 liability and claimed instead that
supervision, and materials as specified in the detailed scope of it failed to complete the projects due to respondents fault. It
work.7 For its part, respondent agreed to pay the total sum of explained that it relied in good faith on respondents
2,944,000.00 in consideration of the performance of the job representation that the transformer subject of the contract could
orders. Petitioner undertook to complete the projects within one still be rewound and converted but upon dismantling the core-
hundred twenty (120) days from the effectivity of the contract. 8 It coil assembly, it discovered that the coils were already badly
was agreed upon that petitioner would be liable to respondent for damaged and the primary bushing broken. This discovery
liquidated damages in the amount of 29,440.00 per day of delay allegedly entailed price adjustment. Petitioner thus requested
in the completion of the projects which shall be limited to 10% respondent for additional time within which to complete the
of the project cost.9 To secure the full and faithful performance project and additional amount to finance the same. Petitioner
of all its obligations and responsibilities under the contract, also insisted that the proximate cause of the delay is the
petitioner obtained from Times Surety & Insurance Co. Inc. misrepresentation of the respondent on the extent of the defect
(Times Insurance) a performance bond10 in an amount equivalent of the transformer.
to fifty percent (50%) of the contract price or 1,458,618.18. After the presentation of the parties respective evidence, the
Pursuant to the terms of the contract, respondent made an initial RTC rendered a decision on June 5, 1998 in favor of petitioner,
payment of 1,458,618.18 on January 8, 1991. 11 the dispositive portion of which reads:
In a letter12 dated March 9, 1991, petitioner requested for an Wherefore, finding defendant-contractors evidence more
extension of seventy-five (75) days within which to complete the preponderant than that of the plaintiff, judgment is hereby
projects because of the need to import some of the materials rendered in favor of the defendant-contractor against the plaintiff
needed. In the same letter, it also asked for a price adjustment of and hereby orders:
255,000.00 to cover the higher cost of materials. 13 In another (1) that the instant case be DISMISSED;
letter14 dated March 27, 1991, petitioner requested for another 75 (2) that plaintiff pays defendant the amount of 4,000,000.00;
days extension for the completion of the transformer portion of for moral and exemplary & other damages;
the projects for failure of its supplier to deliver the materials. (3) 100,000.00 for attorneys fees and cost of suit.
On June 14, 1991,15 petitioner manifested its desire to complete SO ORDERED.24
the project as soon as possible to prevent further losses and The RTC held that the failure of petitioner to complete the
maintain goodwill between the companies. Petitioner requested projects was not solely due to its fault but more on respondents
for respondents assistance by facilitating the acquisition of misrepresentation and bad faith.25 Therefore, the Court
materials and supplies needed to complete J.O. #P-90-212 and dismissed respondents complaint. Since respondent was found
J.O. #P-90-213 by directly paying the suppliers. It further sought to have committed deceit in its dealings with petitioner, the court
that it be allowed to back out from J.O. #P-90-214 covering the awarded damages in favor of the latter.26
rewinding and conversion of the damaged transformer. Respondent, however, successfully obtained a favorable
In response16 to petitioners requests, respondent, through decision when its appeal was granted by the CA. The appellate
counsel, manifested its observation that petitioners financial court reversed and set aside the RTC decision and awarded
respondent 493,695.34 for the excess payment made to conclusions of the trial and appellate courts impel us to re-
petitioner, 508,510.00 for the amount spent in contracting examine the evidence presented.
Geostar and 294,400.00 as liquidated damages.27 Contrary to After a thorough review of the records of the case, we find no
the conclusion of the RTC, the CA found that petitioner failed to reason to depart from the conclusions of the CA.
prove that respondent made fraudulent misrepresentation to It is undisputed that petitioner and respondent entered into a
induce the former to enter into the contract. It further held that contract for the supply of labor, materials, and technical
petitioner was given the opportunity to inspect the transformer supervision primarily for the rewinding and conversion of one
before offering its bid. 28 This being so, the CA added that (1) unit of transformer and related works aimed at providing the
petitioners failure to avail of such opportunity is inexcusable, power needs of respondent. As agreed upon by the parties, the
considering that it is a company engaged in the electrical projects were to be completed within 120 days from the
business and the contract involved a sizable amount of effectivity of the contract. Admittedly, however, respondent
money.29 As to the condition of the subject transformer unit, the failed, not only to perform its part of the contract on time but, in
appellate court found the testimony of petitioners president fact, to complete the projects. Petitioner tried to exempt itself
insufficient to prove that the same could no longer be rewound from the consequences of said breach by passing the fault to
or converted.30 Considering that advance payments had been respondent. It explained that its failure to complete the project
made to petitioner, the court deemed it necessary to require it to was due to the misrepresentation of the respondent. It claimed
return to respondent the excess amounts, vis--vis its actual that more time and money were needed, because the condition of
accomplishment.31 In addition to the refund of the excess the subject transformer was worse than the representations of
payment, the CA also ordered the reimbursement of what respondent. Is this defense tenable?
respondent paid to Geostar for the unfinished projects of We answer in the negative.
petitioner as well as the payment of liquidated damages as Records show that petitioner indeed asked for price adjustment
stipulated in the contract.32 and extension of time within which to complete the projects. In
Aggrieved, petitioner comes before the Court in this petition for its letter45 dated March 9, 1991, petitioner anchored its request
review on certiorari under Rule 45 of the Rules of Court raising for extension on the following grounds:
the following issues: (1) whether or not respondent was guilty of 1. To maximize the existing 3125 KVA to 4000 KVA capacity
fraud or misrepresentation as to the actual condition of the using the same core, we will replace the secondary windings
transformer subject of the contract;33 (2) whether or not the from rectangular type to copper sheet which is more accurate in
evidence presented by petitioner adequately established the true winding to the required number of turns than using parallel
nature and condition of the subject transformer;34 (3) whether or rectangular or circular type of copper magnet wires. However,
not petitioner is guilty of inexcusable delay in the completion of these copper sheets are not readily available locally in volume
the projects;35 (4) whether or not petitioner is liable for liquidated quantities, and therefore, we will be importing this material and
damages;36 and (5) whether or not petitioner is liable for the cost it will take 60 days minimum time for its delivery.
of the contract between respondent and Geostar.37 2. We also find it difficult to source locally the replacement for
The petition is without merit. the damaged high voltage bushing.
The case stemmed from an action for sum of money or damages 3. The delivery of power cable no. 2/0 will also be delayed. This
arising from breach of contract. The contract involved in this will take 90 days to deliver from January 1991. 46
case refers to the rewinding and conversion of one unit of Also in its letter47 dated March 27, 1991, petitioner informed
transformer to be installed and energized to supply respondents respondent that the projects would be completed within the
power requirements.38 This project was embodied in three (3) job contract time table but explained that the delivery of the
orders, all of which were awarded to petitioner who represented transformer would only be delayed. The reasons advanced by
itself to be capable, competent, and duly licensed to handle the petitioner to justify the delay are as follows:
projects.39Petitioner, however, failed to complete the projects 1. Our supplier for copper sheets cannot complete the delivery
within the agreed period allegedly because of misrepresentation until April 30, 1991.
and fraud committed by respondent as to the true nature of the 2. Importation of HV Bushing will take approximately 45 days
subject transformer. The trial court found that respondent indeed delivery per advice of our supplier. x x x48
failed to inform petitioner of the true condition of the transformer Clearly, in the above letters, petitioner justified its inability to
which amounted to fraud thereby justifying the latters failure to complete the projects within the stipulated period on the alleged
complete the projects. The CA, however, had a different unavailability of the materials to be used to perform the projects
conclusion and decided in favor of respondent. Ultimately, the as stated in the job orders. Nowhere in said letters did petitioner
issue before us is whether or not there was breach of contract claim that it could not finish the projects, particularly the
which essentially is a factual matter not usually reviewable in a conversion of the transformer unit because the defects were
petition filed under Rule 45.40 worse than the representation of respondent. In other words,
In resolving the issues, the Court inquires into the probative there was no allegation of fraud, bad faith, concealment or
value of the evidence presented before the trial court.41Petitioner, misrepresentation on the part of respondent as to the true
indeed, endeavors to convince us to determine once again the condition of the subject transformer. Even in its letter49 dated
weight, credence, and probative value of the evidence presented May 25, 1991, petitioner only requested respondent that payment
before the trial court.42 While in general, the findings of fact of to the first progress billing be released as soon as possible and
the CA are final and conclusive and cannot be reviewed on without deduction. It further proposed that respondent make a
appeal to the Court because it is not a trier of facts, 43 there are direct payment to petitioners suppliers.
recognized exceptions44 as when the findings of fact are It was only in its June 14, 1991 letter50 when petitioner raised its
conflicting, which is obtaining in this case. The conflicting observations that the subject transformer needed more repairs
than what it knew during the bidding. 51 In the same letter,
however, petitioner repeated its request that direct payment be which makes it impossible for petitioner to perform its
made by respondent to petitioners suppliers.52 More obligations under the contract, we also agree with the CA that
importantly, petitioner admitted that it made a judgment error petitioner failed to prove that respondent was guilty of bad faith,
when it quoted for only 440,770.00 for the contract relating to fraud, deceit or misrepresentation.
J.O. #P-90-214 based on limited information. Bad faith does not simply connote bad judgment or negligence;
It can be inferred from the foregoing facts that there was not only it imports a dishonest purpose or some moral obliquity and
a delay but a failure to complete the projects as stated in the conscious doing of a wrong, a breach of a known duty through
contract; that petitioner could not complete the projects because some motive or interest or ill will that partakes of the nature of
it did not have the materials needed; and that it is in need of fraud.59 Fraud has been defined to include an inducement
financial assistance. through insidious machination. Insidious machination refers to a
As the Court sees it, the bid submitted by petitioner may have deceitful scheme or plot with an evil or devious purpose. Deceit
been sufficient to be declared the winner but it failed to anticipate exists where the party, with intent to deceive, conceals or omits
all expenses necessary to complete the projects. 53 When it to state material facts and, by reason of such omission or
incurred expenses it failed to foresee, it began requesting for concealment, the other party was induced to give consent that
price adjustment to cover the cost of high voltage bushing and would not otherwise have been given.60 These are allegations of
difference in cost of copper sheet and rectangular fact that demand clear and convincing proof. They are serious
wire.54 However, the scope of work presented by respondent accusations that can be so conveniently and casually invoked,
specifically stated that the wires to be used shall be pure copper and that is why they are never presumed.61 In this case, the
and that there was a need to supply new bushings for the evidence presented is insufficient to prove that respondent acted
complete rewinding and conversion of 3125 KVA to 4 MVA in bad faith or fraudulently in dealing with petitioner.1wphi1
Transformer.55 In other words, petitioner was aware that there Petitioner in fact admitted that its representatives were given the
was a need for complete replacement of windings to copper and opportunity to inspect the subject transformer before it offered
of secondary bushings. 56 It is, therefore, improper for petitioner its bid. If indeed the transformer was completely sealed, it should
to ask for additional amount to answer for the expenses that were have demanded that the same be opened if it found it necessary
already part and parcel of the undertaking it was bound to before it offered its bid. As contractor, petitioner had been remiss
perform. For petitioner, the contract entered into may have in its obligation to obtain as much information as possible on the
turned out to be an unwise investment, but there is no one to actual condition of the subject transformer or at least it should
blame but petitioner for plunging into an undertaking without have provided a qualification in its bid so as to make clear its
fully studying it in its entirety. 57 right to claim contract price and time adjustment.62 As aptly held
The Court likewise notes that petitioner repeatedly asked for by the CA, considering that petitioner is a company engaged in
extension allegedly because it needed to import the materials and the electrical business and the contract it had entered into
that the same could not be delivered on time. Petitioner also involved a sizable amount of money, its failure to conduct an
repeatedly requested that respondent make a direct payment to inspection of the subject transformer is inexcusable.63
the suppliers notwithstanding the fact that it contracted with In sum, the evidence presented by the parties lead to the
respondent for the supply of labor, materials, and technical following conclusions: (1) that the projects were not completed
supervision. It is, therefore, expected that petitioner would be by petitioner; (2) that petitioner was given the opportunity to
responsible in paying its suppliers because respondent is not inspect the subject transformer; (3) that petitioner failed to
privy to their (petitioner and its suppliers) contract. This is thoroughly study the entirety of the projects before it offered its
especially true in this case since respondent had already made bid; (4) that petitioner failed to complete the projects because of
advance payments to petitioner. It appears, therefore, that in the unavailability of the required materials and that petitioner
offering its bid, the source and cost of materials were not needed financial assistance; (5) that the evidence presented by
seriously taken into consideration. It appears, further, that petitioner were inadequate to prove that the subject transformer
petitioner had a hard time in fulfilling its obligations under the could no longer be repaired; and (6) that there was no evidence
contract that is why it asked for financial assistance from to show that respondent was in bad faith, acted fraudulently, or
respondent. This is contrary to petitioners representation that it guilty of deceit and misrepresentation in dealing with petitioner.
was capable, competent, and duly licensed to handle the projects. In view of the foregoing disquisitions, we find that there was not
As to the alleged damaged condition of the subject transformer, only delay but non-completion of the projects undertaken by
we quote with approval the CA conclusion in this wise: petitioner without justifiable ground. Undoubtedly, petitioner is
In the same vein, We cannot readily accept the testimony of guilty of breach of contract. Breach of contract is defined as the
Tomas that the transformer unit was severely damaged and was failure without legal reason to comply with the terms of a
beyond repair as it was not substantiated with any other contract. It is also defined as the failure, without legal excuse, to
evidence. R.S. Tomas could have presented an independent perform any promise which forms the whole or part of the
expert witness whose opinion may corroborate its stance that the contract.64 In the present case, petitioner did not complete the
transformer unit was indeed incapable of being restored. To our projects. This gives respondent the right to terminate the contract
mind, the testimony of Tomas is self-serving as it is easy to by serving petitioner a written notice. The contract specifically
concoct, yet difficult to verify. 58 stated that it may be terminated for any of the following causes:
This lack of evidence, coupled with petitioners failure to raise 1. Violation by Contractor of the terms and conditions of this
the same at the earliest opportunity, belies petitioners claim that Contract;
it could not complete the projects because the subject 2. Non-completion of the Work within the time agreed upon, or
transformer could no longer be repaired. upon the expiration of extension agreed upon;
Assuming for the sake of argument that the subject transformer 3. Institution of insolvency or receivership proceedings
was indeed in a damaged condition even before the bidding involving Contractor; and
4. Other causes provided by law applicable to this contract. 65 2. The cancellation of the annotations of the defendant-
Consequently, and pursuant to the agreement of the appellants Affidavit to Annul Contract to Sell and plaintiff-
parties,66 petitioner is liable for liquidated damages in the amount appellees Notice of Adverse Claim in the subject TCTs, namely,
of 29,440.00 per day of delay, which shall be limited to a TCT No. T-76.196 (M) and TCT No. T-76.197 (M);
maximum of 10% of the project cost or 294,400.00. In this case, 3. Payment by the intervenors-appellants of the remaining
petitioner bound itself to complete the projects within 120 days balance of the purchase price pursuant to their agreement with
from December 29, 1990. However, petitioner failed to fulfill the the defendant-appellant to suspend encashment of the three post-
same prompting respondent to engage the services of another dated checks issued since 1989.
contractor on November 14, 1991. Thus, despite the lapse of 4. Ordering the execution by the defendant-appellant Genato of
eleven months from the time of the effectivity of the contract the Deed of Absolute Sale over the subject two lots covered by
entered into between respondent and petitioner, the latter had not TCT No. T-76.196 (M) and TCT No. T-76.197 (M) in favor of
completed the projects. Undoubtedly, petitioner may be held to intervenors-appellants Spouses Da Jose;
answer for liquidated damages in its maximum amount which is 5. The return by defendant-appellant Genato of P50,000.00 paid
10% of the contract price. While we have reduced the amount of to him by the plaintiff-appellee Cheng, and
liquidated damages in some cases,67 because of partial 6. Payment by plaintiff-appellee Cheng of moral damages to
fulfillment of the contract and/or the amount is unconscionable, herein intervenors-appellants Da Jose of P100,000.00,
we do not find the same to be applicable in this case. It must be exemplary damages of P50,000.00, attorneys fees
recalled that the contract entered into by petitioner consists of of P50,000.00, and costs of suit; and to defendant-appellant,
three projects, all of which were not completed by petitioner. of P100,000.00 in exemplary damages, P50,000.00 in attorneys
Moreover, the percentage of work accomplishment was not fees. The amounts payable to the defendant-appellant may be
adequately shown by petitioner. Hence, we apply the general rule compensated by plaintiff-appellee with the amount ordered
not to ignore the freedom of the parties to agree on such terms under the immediately foregoing paragraph which defendant-
and conditions as they see fit as long as they are not contrary to appellant has to pay the plaintiff-appellee.
law, morals, good customs, public order or public policy.68 Thus, SO ORDERED.[2]
as agreed upon by the parties, we apply the 10% liquidated The antecedents of the case are as follows:
damages. Respondent Ramon B. Genato(Genato) is the owner of two
Considering that petitioner was already in delay and in breach of parcels of land located at Paradise Farms, San Jose Del Monte,
contract, it is liable for damages that are the natural and probable Bulacan covered by TCT No. T-76.196 (M)[3] and TCT No. T-
consequences of its breach of obligation.69 Since advanced 76.197 (M)[4]with an aggregate area of 35,821 square meters,
payments had been made by respondent, petitioner is bound to more or less.
return the excess vis--vis its work accomplishments. In order to On September 6, 1989, respondent Genato entered into an
finish the projects, respondent had to contract the services of agreement with respondent-spouses Ernesto R. Da Jose and
another contractor. We, therefore, find no reason to depart from Socorro B. Da Jose (Da Jose spouses) over the above-mentioned
the CA conclusion requiring the return of the excess payments two parcels of land.The agreement culminated in the execution
as well as the payment of the cost of contracting Geostar, in of a contract to sell for which the purchase price was P80.00 per
addition to liquidated damages.70 square meter. The contract was in a public instrument and was
WHEREFORE, premises considered, the petition is hereby duly annotated at the back of the two certificates of title on the
DENIED. The Court of Appeals Decision dated December 19, same day. Clauses 1 and 3 thereof provide:
2005 and Resolution dated June 6, 2006 in CA-G.R. CV No. '1. That the purchase price shall be EIGHTY (P80.00) PESOS,
61049 are AFFIRMED. Philippine Currency per square meter, of which the amount of
SO ORDERED. FIFTY THOUSAND (P50,000.00) Pesos shall be paid by the
VENDEE to the VENDOR as partial down payment at the time
of execution of this Contract to Sell.
[G.R. No. 129760. December 29, 1998] xxx xxx xxx
RICARDO CHENG, petitioner, vs. RAMON B. GENATO '3. That the VENDEE, thirty (30) DAYS after the execution of
and ERNESTO R. DA JOSE & SOCORRO B. DA this contract, and only after having satisfactorily verified and
JOSE, respondents. confirmed the truth and authenticity of documents, and that no
DECISION restrictions, limitations, and developments imposed on and/or
MARTINEZ, J.: affecting the property subject of this contract shall be detrimental
This petition for review on certiorari seeks to annul and set aside to his interest, the VENDEE shall pay to the VENDOR, NINE
the Decision of the Court of Appeals (CA) [1] dated July 7, 1997 HUNDRED FIFTY THOUSAND (P950,000.00) PESOS,
in CA-G.R. No. CV No. 44706 entitled Ricardo Cheng, plaintiff- Philippine Currency, representing the full payment of the agreed
appellee vs. Ramon B. Genato, defendant-appellant, Ernesto R. Down Payment, after which complete possession of the property
Da Jose & Socorro B. Da Jose, Intervenors-Appellants which shall be given to the VENDEE to enable him to prepare the
reversed the ruling of the Regional Trial Court, Branch 96 of premises and any development therein.[5]
Quezon City dated January 18, 1994. The dispositive portion of On October 4, 1989, the Da Jose spouses, not having finished
the CA Decision reads: verifying the titles mentioned in clause 3 as aforequoted, asked
WHEREFORE, based on the foregoing, appealed decision is for and was granted by respondent Genato an extension of
hereby REVERSED and SET ASIDE and judgment is rendered another 30 days or until November 5, 1989. However, according
ordering; to Genato, the extension was granted on condition that a new set
1. The dismissal of the complaint; of documents is made seven (7) days from October 4,
1989.[6] This was denied by the Da Jose spouses.
Pending the effectivity of the aforesaid extension period, and Thereafter, Ramon Genato advised Ricardo Cheng of his
without due notice to the Da Jose spouses, Genato executed an decision to continue his contract with the Da Jose spouses and
Affidavit to Annul the Contract to Sell,[7] on October 13, the return of Chengs P50,000.00 check. Consequently, on
1989. Moreover, no annotation of the said affidavit at the back October 30, 1989, Chengs lawyer sent a letter[12] to Genato
of his titles was made right away. The affidavit contained, inter demanding compliance with their agreement to sell the property
alia, the following paragraphs; to him stating that the contract to sell between him and Genato
xxx xxx xxx was already perfected and threatening legal action.
That it was agreed between the parties that the agreed On November 2, 1989, Genato sent a letter[13] to Cheng (Exh. 6)
downpayment of P950,000.00 shall be paid thirty (30) days after enclosing a BPI Cashiers Check for P50,000.00 and expressed
the execution of the Contract, that is on or before October 6, regret for his inability to consummate his transaction with
1989; him. After having received the letter of Genato on November 4,
The supposed VENDEES failed to pay the said full 1989, Cheng, however, returned the said check to the former via
downpayment even up to this writing, a breach of contract. RCPI telegram[14] dated November 6, 1989, reiterating that our
That this affidavit is being executed to Annul the aforesaid contract to sell your property had already been perfected.
Contract to Sell for the vendee having committed a breach of Meanwhile, also on November 2, 1989, Cheng executed an
contract for not having complied with the obligation as provided affidavit of adverse claim[15] and had it annotated on the subject
in the Contract to Sell;[8] TCTs.
On October 24, 1989, herein petitioner Ricardo Cheng (Cheng) On the same day, consistent with the decision of Genato and the
went to Genatos residence and expressed interest in buying the Da Jose spouses to continue with their Contract to Sell of
subject properties. On that occasion, Genato showed to Ricardo September 6, 1989, the Da Jose spouses paid Genato the
Cheng copies of his transfer certificates of title and the complete down payment of P950,000.00 and delivered to him
annotations at the back thereof of his contract to sell with the Da three (3) postdated checks (all dated May 6, 1990, the stipulated
Jose spouses. Genato also showed him the aforementioned due date) in the total amount of P1,865,680.00 to cover full
Affidavit to Annul the Contract to Sell which has not been payment of the balance of the agreed purchase price. However,
annotated at the back of the titles. due to the filing of the pendency of this case, the three (3)
Despite these, Cheng went ahead and issued a check postdated checks have not been encashed.
for P50,000.00 upon the assurance by Genato that the previous On December 8, 1989, Cheng instituted a complaint[16] for
contract with the Da Jose spouses will be annulled for which specific performance to compel Genato to execute a deed of sale
Genato issued a handwritten receipt (Exh. D), written in this to him of the subject properties plus damages and prayer for
wise. preliminary attachment. In his complaint, Cheng averred that
10/24/89 the P50,000.00 check he gave was a partial payment to the total
Received from Ricardo Cheng agreed purchase price of the subject properties and considered as
the Sum of Fifty Thousand Only (P50,000 -) an earnest money for which Genato acceded. Thus, their contract
as partial for T-76196 (M) was already perfected.
T-76197 (M) area 35,821 Sq.m. In Answer[17] thereto, Genato alleged that the agreement was
Paradise Farm, Gaya-Gaya, San Jose Del Monte only a simple receipt of an option-bid deposit, and never stated
P70/m2 Bulacan that it was a partial payment, nor is it an earnest money and that
Plus C.G.T. etc it was subject to the condition that the prior contract with the Da
(SGD) Ramon B. Genato Jose spouses be first cancelled.
Check # 470393 The Da Jose spouses, in their Answer in Intervention,[18] asserted
10/24/89[9] that they have a superior right to the property as first
On October 25, 1989, Genato deposited Chengs check. On the buyers. They alleged that the unilateral cancellation of the
same day, Cheng called up Genato reminding him to register the Contract to Sell was without effect and void. They also cited
affidavit to annul the contract to sell.[10] Chengs bad faith as a buyer being duly informed by Genato of
The following day, or on October 26, 1989, acting on Chengs the existing annotated Contract to Sell on the titles.
request, Genato caused the registration of the Affidavit to Annul After trial on the merits, the lower court ruled that the receipt
the Contract to Sell in the Registry of Deeds, Meycauayan, issued by Genato to Cheng unerringly meant a sale and not just
Bulacan as primary entry No. 262702.[11] a priority or an option to buy. It cannot be true that the
While the Da Jose spouses were at the Office of the Registry of transaction was subjected to some condition or reservation, like
Deeds of Meycauaya, Bulacan on October 27, 1989, they met the priority in favor of the Da Jose spouses as first buyer because,
Genato by coincidence. It was only then that the Da Jose spouses if it were otherwise, the receipt would have provided such
discovered about the affidavit to annul their contract. The latter material condition or reservation, especially as it was Genato
were shocked at the disclosure and protested against the himself who had made the receipt in his own hand. It also opined
rescission of their contract. After being reminded that he that there was a valid rescission of the Contract to Sell by virtue
(Genato) had given them (Da Jose spouses) an additional 30-day of the Affidavit to Annul the Contract to Sell.Time was of the
period to finish their verification of his titles, that the period was essence in the execution of the agreement between Genato and
still in effect, and that they were willing and able to pay the Cheng, under this circumstance demand, extrajudicial or
balance of the agreed down payment, later on in the day, Genato judicial, is not necessary. It falls under the exception to the rule
decided to continue the Contract he had with them. The provided in Article 1169[19] of the Civil Code. The right of
agreement to continue with their contract was formalized in a Genato to unilaterally rescind the contract is said to be under
conforme letter dated October 27, 1989. Article 1191[20] of the Civil Code. Additionally, after reference
was made to the substance of the agreement between Genato and
the Da Jose spouses, the lower court also concluded that Cheng resolution of the Da Jose spouses Contract to Sell, contrary to
should be preferred over the intervenors-Da Jose spouses in the petitioners contentions and the trial courts erroneous ruling.
purchase of the subject properties. Thus, on January 18, 1994 the In a Contract to Sell, the payment of the purchase price is a
trial court rendered its decision the decretal portion of which positive suspensive condition, the failure of which is not a
reads: breach, casual or serious, but a situation that prevents the
WHEREFORE, judgment is hereby rendered: obligation of the vendor to convey title from acquiring an
1. Declaring the contract to sell dated September 6, 1989 obligatory force.[22] It is one where the happening of the event
executed between defendant Ramon Genato, as vendor, and gives rise to an obligation. Thus, for its non-fulfillment there will
intervenors Spouses Ernesto and Socorro Da Jose, as vendees, be no contract to speak of, the obligor having failed to perform
resolved and rescinded in accordance with Art. 1191, Civil Code, the suspensive condition which enforces a juridical relation. In
by virtue of defendants affidavit to annul contract to sell dated fact with this circumstance, there can be no rescission of an
October 13, 1989 and as the consequence of intervenors failure obligation that is still non-existent, the suspensive condition not
to execute within seven (7) days from October 4, 1989 another having occurred as yet.[23] Emphasis should be made that the
contract to sell pursuant to their mutual agreement with the breach contemplated in Article 1191 of the New Civil Code is
defendant; the obligors failure to comply with an obligation already extant,
2. Ordering defendant to return to the intervenors the sum not a failure of a condition to render binding that obligation. [24]
of P1,000,000.00, plus interest at the legal rate from November Obviously, the foregoing jurisprudence cannot be made to apply
2, 1989 until full payment; to the situation in the instant case because no default can be
3. Directing defendant to return to the intervenors the three (3) ascribed to the Da Jose spouses since the 30-day extension period
postdated checks immediately upon finality of this judgment; has not yet expired. The Da Jose spouses contention that no
4. Commanding defendant to execute with and in favor of the further condition was agreed when they were granted the 30-days
plaintiff Ricardo Cheng, as vendee, a deed of conveyance and extension period from October 7, 1989 in connection with clause
sale of the real properties described and covered in Transfer 3 of their contract to sell dated September 6, 1989 should be
Certificates of Title No. T-76-196 (M) and T-76.197 (M) of the upheld for the following reason, to wit; firstly, If this were not
Registry of Deeds of Bulacan, Meycauyan Branch, at the rate true, Genato could not have been persuaded to continue his
of P70.00/sqaure meter, less the amount of P50,000.00 already contract with them and later on agree to accept the full settlement
paid to defendant, which is considered as part of the purchase of the purchase price knowing fully well that he himself imposed
price, with the plaintiff being liable for payment of the capital such sine qua non condition in order for the extension to be
gains taxes and other expenses of the transfer pursuant to the valid; secondly, Genato could have immediately annotated his
agreement to sell dated October 24, 1989; and affidavit to annul the contract to sell on his title when it was
5. Ordering defendant to pay the plaintiff and the intervenors as executed on October 13, 1989 and not only on October 26, 1989
follows: after Cheng reminded him of the annotation; thirdly, Genato
a/ P50,000.00, as nominal damages, to plaintiff; could have sent at least a notice of such fact, there being no
b/ P50,000.00, as nominal damages, to intervenors; stipulation authorizing him for automatic rescission, so as to
c/ P20,000.00, as and for attorneys fees, to plaintiff; finally clear the encumbrance of his titles and make it available
d/ P20,000.00, as and for attorneys fees, to intervenors; and to other would be buyers. It likewise settles the holding of the
e/ Cost of the suit. trial court that Genato needed money urgently.
xxx xxx xxx Even assuming in gratia argumenti that the Da Jose spouses
Not satisfied with the aforesaid decision, herein respondents defaulted, as claimed by Genato, in their Contract to Sell, the
Ramon Genato and Da Jose spouses appealed to the court a execution by Genato of the affidavit to annul the contract is not
quo which reversed such judgment and ruled that the prior even called for.For with or without the aforesaid affidavit their
contract to sell in favor of the Da Jose spouses was not validly non-payment to complete the full downpayment of the purchase
rescinded, that the subsequent contract to sell between Genato price ipso facto avoids their contract to sell, it being subjected to
and Cheng, embodied in the handwritten receipt, was without a suspensive condition. When a contract is subject to a
force and effect due to the failure to rescind the prior contract; suspensive condition, its birth or effectivity can take place only
and that Cheng should pay damages to the respondents herein if and when the event which constitutes the condition happens or
being found to be in bad faith. is fulfilled.[25] If the suspensive condition does not take place, the
Hence this petition.[21] parties would stand as if the conditional obligation had never
This petition for review, assails the Court of Appeals Decision existed.[26]
on the following grounds: (1) that the Da Jose spouses Contract Nevertheless, this being so Genato is not relieved from the giving
to Sell has been validly rescinded or resolved; (2) that Ricardo of a notice, verbal or written, to the Da Jose spouses for decision
Chengs own contract with Genato was not just a contract to sell to rescind their contract. In many cases,[27] even though we
but one of conditional contract of sale which gave him better upheld the validity of a stipulation in a contract to sell
rights, thus precluding the application of the rule on double sales authorizing automatic rescission for a violation of its terms and
under Article 1544, Civil Code; and (3) that, in any case, it was conditions, at least a written notice must be sent to the defaulter
error to hold him liable for damages. informing him of the same. The act of a party in treating a
The petition must be denied for failure to show that the Court of contract as cancelled should be made known to the other.[28] For
Appeals committed a reversible error which would warrant a such act is always provisional. It is always subject to scrutiny
contrary ruling. and review by the courts in case the alleged defaulter brings the
No reversible error can be ascribed to the ruling of the Court of matter to the proper courts. In University of the Philippines vs.
Appeals that there was no valid and effective rescission of De Los Angeles,[29] this Court stressed and we quote:
In other words, the party who deems the contract violated may of Coronel vs. Court of Appeals[37] as the law that should
consider it resolved or rescinded, and act accordingly, without govern their Petition. We do not agree. Apparently, the factual
previous court action, but it proceeds at its own risk. For it is only milieu in Coronel is not on all fours with those in the case at bar.
the final judgment of the corresponding court that will In Coronel, this Court found that the petitioners therein clearly
conclusively and finally settle whether the action taken was or intended to transfer title to the buyer which petitioner themselves
was not correct in law. But the law definitely does not require admitted in their pleading. The agreement of the parties therein
that the contracting party who believes itself injured must first was definitively outline in the Receipt of Down Payment both as
file suit and wait for a judgment before taking extajudicial steps to property, the purchase price, the delivery of the seller of the
to protect its interest. Otherwise, the party injured by the others property and the manner of the transfer of title subject to the
breach will have to passively sit and watch its damages specific condition that upon the transfer in their names of the
accumulate during the pendency of the suit until the final subject property the Coronels will execute the deed of absolute
judgment of rescission is rendered when the law itself requires sale.
that he should exercise due diligence to minimize its own Whereas, in the instant case, even by a careful perusal of the
damages (Civil Code, Article 2203). receipt, Exh. D, alone such kind of circumstances cannot be
This rule validates, both in equity and justice, contracts such as ascertained without however resorting to the exceptions of the
the one at bat, in order to avoid and prevent the defaulting party Rule on Parol Evidence.
from assuming the offer as still in effect due to the obligees To our mind, the trial court and the appellate court correctly held
tolerance for such non-fulfillment. Resultantly, litigations of this that the agreement between Genato and Cheng is a contract to
sort shall be prevented and the relations among would-be parties sell, which was, in fact, petitioner connection in his pleadings
may be preserved. Thus, Ricardo Chengs contention that the before the said courts. Consequently, both to mind, which read:
Contract to Sell between Genato and the Da Jose spouses was Article 1544. If the same thing should have been sold to
rescinded or resolved due to Genatos unilateral rescission finds different vendees, the ownership shall be transferred to the
no support in this case. person who may have first taken possession thereof in good faith,
Anent the issue on the nature of the agreement between Cheng if it should be movable property.
and Genato, the records of this case are replete with Should it be immovable property, the ownership shall belong to
admissions[30] that Cheng believed it to be one of a Contract to the person acquiring it who in good faith first recorded it in the
Sell and not one of Conditionl Contract of Sale which he, in a Registry of Property.
transparent turn-around, now pleads in this Petition. This Should there be no inscription, the ownership shall pertain to the
ambivalent stance of Cheng is even noted by the appellate court, person who in good faith was first in possession; and in the
thus: absence thereof, to the person who presents the oldest title,
At the outset, this Court notes that plaintiff-appellee was provided there is good faith
inconsistent in characterizing the contract he allegedly entered However, a meticulous reading of the aforequoted provision
into. In his complaint,[31] Cheng alleged that the P50,000.00 shows that said law is not apropos to the instant case. This
down payment was earnest money. And next, his provision connotes that the following circumstances must
testimony[32] was offered to prove that the transaction between concur:
him and Genato on October 24, 1989 was actually a perfected (a) The two (or more) sales transactions in the issue must pertain
contract to sell.[33] to exactly the same subject matter, and must be valid sales
Settled is the rule that an issue which was not raised during the transactions.
trial in the court below cannot be raised for the first time on (b) The two (or more) buyers at odds over the rightful
appeal.[34] Issues of fact and arguments not adequately brought ownership of the subject matter must each represent conflicting
to the attention of the trial court need not be and ordinarily will interests; and
not be considered by a reviewing court as they cannot be raised (c) The two (or more) buyers at odds over the rightful ownership
for the first time on appeal.[35] In fact, both courts below correctly of the subject matter must each have bought from the very same
held that the receipt which was the result of their agreement, is a seller.
contract to sell. This was, in fact Chengs contention in his These situations obviously are lacking in a contract to sell for
pleadings before said courts. This patent twist only operates neither a transfer of ownership nor a sales transaction has been
against Chengs posture which is indicative of the weakness of consummated. The contract to be binding upon the obligee or the
his claim. vendor depends upon the fulfillment or non-fulfillment of an
But even if we are to assume that the receipt, Exh. D, is to be event.
treated as a conditional contract of sale, it did not acquire any Notwithstanding this contrary finding with the appellate court,
obligatory force since it was subject to suspensive condition that we are of the view that the governing principle of Article 1544,
the earlier contract to sell between Genato and the Da Jose Civil Code, should apply in this
spouses should first be cancelled or rescinded a condition never situation. Jurisprudence[38] teaches us that the governing
met, as Genato, to his credit, upon realizing his error, redeemed principle is PRIMUS TEMPORE, PORTIOR JURE (first in time,
himself by respecting and maintaining his earlier contract with stronger in right). For not only was the contract between herein
the Da Jose spouses. In fact a careful reading of the receipt, Exh. respondents first in time; it was also registered long before
D, alone would not even show that a conditional contract of sale petitioners intrusion as a second buyer. This principle only
has been entered by Genato and Cheng.When the requisites of a applies when the special rules provided in the aforcited article of
valid contract of sale are lacking in said receipt, therefore the sale Civil Code do not apply or fit the specific circumstances
is neither valid or enforceable.[36] mandated under said law or by jurisprudence interpreting the
To support his now new theory that the transaction was a article.
conditional contract of sale, petitioner invokes the case
The rule exacted by Article 1544 of the Civil Code for the second of his vendor. A purchaser cannot close his eyes to facts which
buyer to be able to displace the first buyer are: should put a reasonable man upon his guard, and then claim that
(1) that the second buyer must show that he acted in good faith he acted in good faith under the belief that there was no defect
(i.e. in ignorance of the first sale and of the first buyers rights) in the title of the vendor. His mere refusal to believe that such
from the time of acquisition until title is transferred to him by defect exists, or his willful closing of his eyes to the possibility
registration or failing registration, by delivery of possession;[39] of the existence of a defect in his vendors title, will not make him
(2) the second buyer must show continuing good faith and an innocent purchaser for value, if it afterwards develops that the
innocence or lack of knowledge of the first sale until his contract title was in fact defective, and it appears that he had such notice
ripens into full ownership through prior registration as provided of the defect as would have led to its discovery had he acted with
by law.[40] that measure of precaution which may reasonably be required of
Thus, in the case at bar, the knowledge gained by the Da Jose a prudent man in a like situation. Good faith, or lack of it, is in
spouses, as first buyers, of the new agreement between Cheng its last analysis a question of intention; but in ascertaining the
and Genato will not defeat their rights as first buyers except intention by which one is actuated on a given occasion, we are
where Cheng, as second buyer, registers or annotates his necessarily controlled by the evidence as to the conduct and
transaction or agreement on the title of the subject properties in outward acts by which alone the inward motive may, with safety,
good faith ahead of the Da Jose spouses. Moreover, although the be determined. So it is that the honesty of intention, the honest
Da Jose spouses, as first buyers, knew of the second transaction lawful intent, which constitutes good faith implies a freedom
it will not bar them from availing of their rights granted by law, from knowledge and circumstances which ought to put a person
among them, to register first their agreement as against the on inquiry, and so it is that proof of such knowledge overcomes
second buyer. the presumption of good faith in which the courts always indulge
In contrast, knowledge gained by Cheng of the first transaction in the absence of the proof to the contrary. Good faith, or the
between the Da Jose spouses and Genato defeats his rights even want of it, is not a visible, tangible fact that can be seen or
if he is first to register the second transaction, since such touched, but rather a state or condition of mind which can only
knowledge taints his prior registration with bad faith. be judge of by actual or fancied tokens or signs. (Wilder vs.
Registration, as defined by Soler and Castillo, means any entry Gilman, 55 Vt. 504, 505; Cf. Cardenas vs. Miller, 108 Cal., 250;
made in the books of the registry, including both registration in Breaux-Renoudet, Cypress Lumber Co. vs. Shadel, 52 La. Ann.,
its ordinary and strict sense and cancellation, annotation, and 2094-2098; Pinkerton Bros. Co. vs. Bromely, 119 Mich., 8, 10,
even marginal notes.[41] In its strict acceptation, it is the entry 17.) Emphasis ours
made in the registry which records solemnly and permanently Damages were awarded by the appellate court on the basis of its
the right of ownership and other real rights. [42] We have finding that petitioner was in bad faith when he filed the suit for
ruled[43] before that when a Deed of Sale is inscribed in the specific performance knowing fully well that his agreement with
registry of property on the original document itself, what was Genato did not push through.[46] Such bad faith, coupled with his
done with respect to said entries or annotations and marginal wrongful interference with the contractual relations between
notes amounted to a registration of the sale. In this light, we see Genato and the Da Jose spouses, which culminated in his filing
no reason why we should not give priority in right the annotation of the present suit and thereby creating what the counsel for the
made by the Da Jose spouses with respect to their Contract to respondents describes as a prolonged and economically
Sell dated September 6, 1989. unhealthy gridlock[47] on both the land itself and the respondents
Moreover, registration alone in such cases without good faith is rights provides ample basis for the damages awarded. Based on
not sufficient. Good faith must concur with registration for such these overwhelming evidence of bad faith on the part of herein
prior right to be enforceable. In the instant case, the annotation petitioner Ricardo Cheng, we find that the award of damages
made by the Da Jose spouses on the titles of Genato of their made by the appellate court is in order.
Contract to Sell more than satisfies this requirement. Whereas in WHEREFORE, premises considered, the instant petition for
the case of Genatos agreement with Cheng such is review is DENIED and the assailed decision is hereby
unavailing. For even before the receipt, Exh. D, was issued to AFFIRMED EN TOTO.
Cheng information of such pre-existing agreement has been SO ORDERED.
brought to his knowledge which did not deter him from pursuing
his agreement with Genato. We give credence to the factual DIGEST
finding of the appellate court that Cheng himself admitted that it
was he who sought Genato in order to inquire about the property CHENG V. GENATO (December 29, 1998)
and offered to buy the same.[44] And since Cheng was fully FACTS:
aware, or could have been if he had chosen to inquire, of the Respondent Genato entered a contract to sell to spouses Da Jose
rights of the Da Jose spouses under the Contract to Sell duly pertaining to his property in Bulacan. The contract made in
annotated on the transfer certificates of titles of Genato, it now public document states that the spouses shall pay the down
becomes unnecessary to further elaborate in detail the fact that payment and 30 days after verifying the authenticity of the
he is indeed in bad faith in entering into such agreement. As we documents, they shall pay the remaining purchase price.
have held in Leung Yee vs. F.L. Strong Machinery Co.:[45]
One who purchases real estate with knowledge of a defect x x x Da Jose spouses was not able to finish verifying the documents
of title in his vendor cannot claim that he has acquired title and as such asked for a 30 day extension. Pending the extension
thereto in good faith as against x x x x an interest therein; and and without notice to the spouses, Genato made a document for
the same rule must be applied to one who has knowledge of facts the annulment of the contract.
which should have put him upon such inquiry and investigation
as might be necessary to acquaint him with the defects in the title
Petitioner Cheng expressed interest over the property and paid
50K check with the assurance that the contract between Genato
and the spouses Da Jose will be annulled. Da Jose spouses
protested with the annulment and persuaded Genato to continue
the contract. Genato returned the check to Cheng and hence, this
petition.

HELD:
The contract between Genato and spouses Da Jose was a contract
to sell which is subject to a suspensive condition. Thus, there will
be no contract to speak of, if the obligor failed to perform the
suspensive condition which enforces a juridical relation.
Obviously, the foregoing jurisprudence cannot be made to apply
to the situation in the instant case because no default can be
ascribed to the Da Jose spouses since the 30-day extension period
has not yet expired.

Even assuming that the spouses defaulted, the contract also


cannot be validly rescinded because no notice was given to them.
Thus, Cheng's contention that the Contract to Sell between
Genato and the Da Jose spouses was rescinded or resolved due
to Genato's unilateral rescission finds no support in this case.

The contract between Genato and Cheng is a contract to sell not


a contract of sale. But But even assuming that it should be treated
as a conditional contract of sale, it did not acquire any obligatory
force since it was subject to a suspensive condition that the
earlier contract to sell between Genato and the Da Jose spouses
should first be cancelled or rescinded.

Art.1544 should apply because for not only was the contract
between herein respondents first in time; it was also registered
long before petitioner's intrusion as a second buyer (PRIMUS
TEMPORE, PORTIOR JURE). (Spouses made annotation on
the title of Genato). Since Cheng was fully aware, or could have
been if he had chosen to inquire, of the rights of the Da Jose
spouses under the Contract to Sell duly annotated on the transfer
certificates of titles of Genato, it now becomes unnecessary to
further elaborate in detail the fact that he is indeed in bad faith in
entering into such agreement.

Vous aimerez peut-être aussi