Académique Documents
Professionnel Documents
Culture Documents
Abstract:
Kathmandu University (KU) is an autonomous, not-for-profit, non-government institution dedicated to
maintain high standards of academic excellence. With technical support from Norwegian Institute of
Science and Technology (NTNU), KU has been upgrading its competency to support the ambitious plan
of Government of Nepal (2010) to develop 38,000 MW of Hydropower in 25 years. KU is collaborating
with national and international experts and institutions for this venture.
Turbine Testing Lab (TTL) has been recently constructed at KU with the major financial assistance from
NORAD, Norway. TTL aims to deliver its facilities to local and international developers and consultants
for research and development activities of hydro turbines and pumps. With 30 meter open head and 150
meter closed head, TTL is capable of testing different range of prototypes up to 300kW and conduct
model tests for larger sizes. In coming years, TTL intends to include state of the art technologies such as
Computational Fluid Dynamics (CFD), Finite Element Method (FEM) analysis, innovative design of
hydro-mechanical components for power plants, and specialized trainings to engineers and technicians.
TTL has been putting quality into practice since its construction phase. In order to meet the testing
standards of the similar facility at NTNU, the quality control (QC) tests were conducted during several
stages of construction. Major emphasis was given to hydro mechanical installations. The installations not
passing the QC were redesigned and tested to maintain the standard. During the operation of the lab, the
internationally recognized certification endorsed by International Electro technical Commission (IEC-
60193) will be maintained at TTL for model tests. Similarly for calibration of measuring tools and
facilities at TTL, the ISO standards will be maintained.
This paper introduces the KU-TTL with its past experiences and future ambitions in regards to research
and development of hydraulic turbines. It also discusses the quality control activities undertaken during
the testing of hydro-mechanical installations at TTL, with the problems encountered and solutions
extracted. The IEC-60193 standards of model test and ISO standards for calibration will also be described
with its applications at TTL and utility in Nepal.
Key Words: Turbine Testing Lab, Quality Control, Model Test, IEC, ISO
Introduction
Kathmandu University (KU) has been continuously working on R&D of hydro turbines so as to improve
its quality. Research works are being carried out at Pico-turbine laboratory and water power laboratory at
KU. Pico-turbine lab has been able to design and fabricate a low cost 800W Pico set which has an overall
efficiency of 90% (Fig 1a) [1]. Water power laboratory has been used for research on sand erosion which
is a major problem of the Nepalese hydropower industry. Using a rotating disc apparatus, tests have been
performed for stainless steel and HVOF coated WC-Co-Cr coating used in Kaligandaki hydropower
project in Nepal (Fig 1b) [2]. Also test for impact and flow visualization of five different Pelton bucket
designed at KU has been conducted in this lab (Fig 1c) [3]. Center of excellence for production and
transportation of electrical energy at KU has developed a 130kW Francis runner (Fig 1d) [4]. The newly
constructed Turbine Testing Lab is the continuation to further conduct R&D. The purpose of this lab is to
conduct research of the hydro-mechanical components and solve problems with new design philosophy.
This will help to develop new turbines with better performance. Also TTL aims to be the center for
performance measurement of hydraulic machines [5]. This will help to improve the quality and maintain
standard of the hydraulic machines in Nepal.
Test of Pump:
Two 250kW pumps were tested at the test
center of ITT, Austria in presence of the
representatives from TTL. Graphs of the
test showing discharge versus head, shaft
power, NPSH and efficiency were
obtained. These graphs showed a positive
result and acceptance was done according
to the EN ISO 9906 Class I (Fig 3).
Test of Pipes:
Hydrostatic tests of the High density
polyethylene (HDPE) pipes and the
stainless steel (SS) pipes were done at site
after its installation.
Pressure test of High density polyethylene
(HDPE) pipe:
During test, each of the three pipes was
completely filled with water and pressure
was increased until the required test
pressure was reached. As per the Fig 3. Test sheet showing the performance graph of a pump
requirement of TTL the pipes had to be at TTL
able to withstand pressure of 3 bar,
whereas the test was performed for 4.2 bar considering the safety margin. The test pressure was held for
20 min so as to detect for defects and leaks (Fig 4a).
Pressure test of Stainless steel (SS) pipe:
All the internal piping of the lab was done using SS-304 of 400 mm diameter and 5mm thickness. While
running the pump in series the maximum pressure in the lab will reach up to 15 bar. Initial pressure test
showed that there was design failure as leakage was observed at 14.1 bar pressure. Thinner flange and
low grade bolts were identified as the cause of this failure. Modification in design was done using SS
stiffener around the flange and using 10.9 grade bolts. Finally pressure test was done for 19.7 bar pressure
successfully (Fig 4b).
Test of welding joints:
Dye penetration test were performed for the internal piping of the lab, i.e. welding joints of the SS pipes.
Cleaner, Penetrant and Developer were the chemicals used for the test. The test results were positive and
there were no flaws in the welding joints (Fig 4c).
Test of the Electrical overhead travelling (EOT) crane:
Deflection test of the EOT crane of capacity 5 ton was conducted. Test was conducted giving a load of 6
ton. The allowable deflection for this test was 5 mm whereas only 2 mm was the measured deflection (Fig
4d).
( )
Where: n=rotational speed, is the mechanical torque, is the density, is the discharge, g is the
acceleration due to gravity, h is the head.
IEC-60193 explains the various methods for performance measurement, choice of a method to find a
parameter depends upon the requirement of the accuracy as each method has different degree of
uncertainty. Hence certainty of measurement of efficiency depends entirely upon the accuracy in
measuring each parameter required to compute the efficiency. Fig 5 shows the general test procedure of
laboratory model test of hydraulic turbines and pumps recommended by the IEC-60193 standards.
Discharge measurement for lab test can be done using the primary method and the secondary method. The
primary method is the most accurate. Weighing method, volumetric method and moving screen method
are the types that fall under
this method. The weighing Measurements at Measurements at
Re =constant=Re * ReM variable
method is explained in detail M M
explained in ISO 8316. The Efficiency correction for Efficiency correction for
cavitations effect, if necessary cavitations effect, if necessary
secondary methods are
founded on various
Model results (hillcart) Correction from
principles. Although some of at ReM and at agreed ReM Variable to ReM constant
them are standardized, Model results (hillcart)
at ReM and at agreed
requirement of high accuracy
Correction
makes it mandatory to ReM ReMsp
calibrate the measurement Correction
ReM ReMsp
equipments. Weir, Model results (hillcart)
differential pressure devices at ReMsp and at agreed
Scale-up ReM Rep Scale-up ReM Rep
and various types of flow
meters fall under this
method. ISO 1438-1 is Results (hillchart) model efficiency Results (hillchart) model efficiency
at ReMsp and at agreed a function at ReMsp and at agreed a function
referred for the weir method of prototype parameters of prototype parameters
whereas ISO 5167-1 will be (QP, EP, PP etc.) (QP, EP, PP etc.)
Turbine Testing Lab will be useful for Research and Development and performance test of hydraulic
machines. This will help to improve the quality of the hydraulic machines. During the construction of the
lab quality control of each component has been conducted. Each of the components in the lab has passed
the quality test. Personals from Water power Laboratory, NTNU and ITT Norge AS commissioned the
lab. During the operation of the lab, test will be performed following IEC-60193 and related ISO
documents. The measuring standard will be followed so as to obtain reliable result and also for the
validation of the test results worldwide. It is expected that the lab will be successful to promote
hydropower developments in the country and the region inducing high quality R&D activities.
References:
[1] Cannell J.et al, 2005, Testing and development of Pico Hydro Turbines, International Journal
of Hydropower and Dams 12(3)
[2] Thapa B., P. Upadhyay, O.G. Dahlhaug, M. Timsina, R. Basnet, 2008, HVOF coatings for
erosion resistance of hydraulic turbines: Experience of Kaligandaki-A Hydropower Plant,
Water Resources and Renewable Energy Development in Asia, Danang, Vietnam
[3] K.C. B., Thapa B., 2009, Pressure distribution at inner surface of selected Pelton bucket for
micro hydro, Kathmandu University Journal of Science, Engineering and Technology Vol. 5,
No. II, 42-50
[4] Thapa B. S, Thapa B., Dahlhaug O. G., 2010, Center of Excellence at Kathmandu University
for R&D and test certification of hydraulic turbines, Proc. Int. Conf. on Hydraulic Efficiency
Measurement 2010; India.
[5] Thapa B. , Dahlhaug O. G., 2009, Turbine Testing Laboratory and its Role in Hydropower
Development, HydroNepal, Issue 5, 79-83
[6] IEC 60193, 1999, Hydraulic turbines, storage pumps and pump-turbines- Model acceptance
tests. Second Edition 1999-11, Published by the International Electro technical Commission.