Vous êtes sur la page 1sur 45

ELECTRICITY TARIFF - 2018

K.E.R.C. ORDER DATED: 11th April, 2017

Effective for the Electricity consumed from the first meter


reading date falling on or after 01.04.2017

Bangalore
Electricity Supply Company Ltd.,

cclxxxiv
ELECTRICITY TARIFF-2018

GENERAL TERMS AND CONDITIONS OF TARIFF:

(APPLICABLE TO BOTH HT AND LT)

1. Supply of power is subject to execution of agreement by the


Consumer in the prescribed form, payment of prescribed
deposits and compliance of terms and conditions as stipulated
in the Conditions of Supply of Electricity of the Distribution
Licensees in the State of Karnataka and Regulations issued
under the Electricity Act, 2003 at the time of supply and
continuation of power supply is subject to compliance of the
said Conditions of Supply / Regulations as amended from time
totime.

2. The tariffs are applicable to only single point of supply unless


otherwise approved by theLicensee.

3. The Licensee does not bind himself to energize any installation,


unless the Consumer guarantees the minimum charges. The
minimum charge is the power supply charges in accordance
with the tariff in force from time to time. This shall be payable by
the Consumer until power supply agreement is terminated,
irrespective of the installation being in service or under
disconnection.

4. The tariffs in the schedule are applicable to power supply within


the area of operation of thelicensee.

5. The tariffs are subject to levy of Tax and Surcharges thereon as


may be decided by the State Government from time totime.

cclxxxv
6. For the purpose of these tariffs, the following conversion table would
be used:
1 HP=0.746 KW. 1HP=0.878 KVA.
7. The bill amount will be rounded off to the nearest Rupee, i.e., the bill
amount of 50 Paise and above will be rounded off to the next higher
Rupee and the amount less than 50 Paise will beignored.

8. Use of power for temporary illumination in the premises already having


permanent power supply for marriages, exhibitions in hotels, sales
promotions etc., is limited to sanctioned load at the applicable
permanent power supply tariff rates. Temporary tariff rates will be
applicable in case the load exceeds sanctioned load as per the
Conditions of Supply of Electricity of the Distribution Licensees in the
State ofKarnataka.

9. No LT power supply will be given where the requisitioned load is 50


KW/67 HP and above. This condition does not apply for installations
serviced under clause 3.1.1 of K.E.R.C. (Recovery of Expenditure for
supply of Electricity) Regulations, 2004 and its amendments from time
to time. The applicant is however at liberty to avail HT supply for lesser
loads. The minimum contract demand for HT supply shall be 25 KVA or
as amended from time to time by the Licensee with the approval of
KERC.

10. The Consumer shall not resell electricity purchased from the Licensee
to a third party except

(a) Where the Consumer holds a sanction or a tariff provision for


distribution and sale ofenergy,

(b) Under special contract permitting the Consumer for resale of


energy in accordance with the provisions of thecontract.

11. Non-receipt of the bill by the Consumer is not a valid reason for non-
payment. The Consumer shall notify the office of issue of the bill, if the
same is not received within 7 days from the meter reading date.
Otherwise, it will be deemed that the bills have reached the Consumer
in duetime.

cclxxxvi
12. The Licensee will levy the following charges for non-realization of
eachCheque.

1 Cheque amount upto 5% of the amount subject to a


Rs. 10,000/- minimum of Rs.100/-
2 Cheque amount of 3% of the amount subject to a
Rs. 10,001/- and upto minimum of Rs.500/-
Rs. 1,00,000/-
3 Cheque amount above 2% of the amount subject to a
Rs. 1 Lakh: minimum of Rs3000/-

13. In respect of power supply charges paid by the Consumer through


money order, Cheque /DD sent by post, receipt will be drawn and the
Consumer has to collect thesame.

14. In case of any belated payment, simple interest at the rate of 1 % per
month will be levied on the actual No. of days of delay subject to a
minimum of Re.1/- for LT installation and Rs.100/- for HT installation. No
interest is however levied for arrears of Rs.10/- andless.

15. All LT Consumers, except BhagyaJyothi and KutirJyothi Consumers, shall


provide current limiter/Circuit Breakers of capacity prescribed by the
Licensee depending upon the sanctionedload.

16. All payments made by the Consumer will be adjusted in the following
order of priority:-

(a) Interest on arrears of ElectricityTax


(b) Arrears of ElectricityTax
(c) Arrears of Interest on Electricitycharges
(d) Arrears of Electricitycharges
(e) Current monthsdues

17. For the purpose ofbilling,

(i) the higher of the rated load or sanctioned load in respect of LT


installations which are not provided with Electronic Tri-Vector
meter,

(ii) sanctioned load or MD recorded, whichever is higher, in respect


of installations provided with static meter or Electronic Tri-Vector
meter or static meter, will beconsidered.

cclxxxvii
Penalty and other clauses shall apply if sanctioned load is
exceeded.

18. The bill amount shall be paid within 15 days from the date of
presentation of the bill failing which the interest becomespayable.

19. For individual installations, more than one meter shall not be provided
under the same tariff. Wherever two or more meters are existing for
individual installation, the sum of the consumption recorded by the
meters shall be taken for billing, till they aremerged.

20. In case of multiple connections in a building, all the meters shall be


provided at one easily accessible place in the groundfloor.

21. Reconnection charges: The following reconnection charges shall be


levied in case of disconnection and included in the monthlybill.

For reconnection of:

a Single Phase Domestic installations Rs.20/-per Installation.


under Tariff schedule LT 1 & LT2 (a)
b Three Phase Domestic installations Rs.50/-per Installation.
under Tariff schedule LT2 (a) and
Single Phase Commercial & Power
installations.
c All LT installations with 3 Phase supply Rs.100/- per
other than LT2 (a) Installation.
d All HT& EHT installations Rs. 500/-per
Installation.

22. Revenue payments upto and inclusive of Rs.10, 000/- shall be made by
cash or cheque or D.D and payments above Rs.10, 000/- shall be
made by cheque or D.D only. Payments under other heads of
account shall be made by cash or D.D up to and inclusive of
Rs.10,000/- and payment aboveRs.10, 000/-shall be by D.Donly.

Note: The Consumers can avail the facility of payment of monthly power
supply bill through Electronic clearing system (ECS)/ Credit cards /
RTGS/ NEFT/ on-line E-Payment / Digital mode of payments as per
the guidelines issued by the RBI wherever such facility is provided
by the Licensee in respect of revenue payments up to the limit
prescribed by theRBI.

cclxxxviii
23. For the types of installations not covered under any Tariff schedules,
the Licensee is permitted to classify such installations under
appropriate Tariff schedule under intimation to theK.E.R.C.

24. SeasonalIndustries

Applicable to all Seasonal Industries.

i) The industries that intend to avail this benefit shall have Electronic Tri-
Vector Meter installed to theirinstallations.

ii) Working season months and off-season months shall be


determined by an order issued by the Executive Engineer of the
concerned O&M Division of the Licensee as per the request of the
Consumer and will continue from year to year unless otherwise
altered. The Consumer shall give a clear one months notice in case
he intends to change his workingseason.

iii) The consumption during any month of the declared off-season shall
not be more than 25% of the average consumption of the previous
workingseason.

iv) The Working season months and off-season months shall be full
calendar months. If the power availed during a month exceeds the
allotment for the off-season month, it shall be taken for calculating
the billing demand as if the month is the working seasonmonth.

v) The Consumer can avail the facility of off-season up to six months


in a calendar year not exceeding in two spells in that year. During
the off-season period, the Consumer may use power for
administrative offices etc., and for overhauling and repairing plant
andmachinery.

25. Whether an institution availing Power supply can be considered as


charitable or not will be decided by the Licensee on the
production of certificate Form-12 A from the Income Tax
department.

cclxxxix
26 Time of the Tariff(ToD)

The Commission as decided in the earlier tariff orders, decides to


continue compulsory Time of Day Tariff for HT2 (a) , HT2 (b) and HT2(c)
consumers with a contract demand of 500 KVA and above. Further,
the optional ToD will continue as existing for HT2 (a),HT2 (b) and HT 2(C)
consumers with contract demand of less than 500 KVA. Also the ToD for
HT1 consumers on optional basis would continue as existing earlier.
Details of ToD tariff are indicated under the respective tariffcategory.

27. SICKINDUSTRIES:
The Government of Karnataka has extended certain reliefs for
revival/rehabilitation of sick industries under the New Industrial Policy
2001-06 vide G.O. No. CI 167 SPI 2001, dated 30.06.2001. Further, the
Government of Karnataka has issued G.O No.CI2 BIF 2010, dated
21.10.2010. The Commission, in its Tariff Order 2002, has accorded
approval for implementation of reliefs to the sick industries as per the
Government policy and the same was continued in the subsequent
Tariff Orders. In view of issue of the G.O No.CI2 BIF 2010, dated
21.10.2010, the Commission has accorded approval to ESCOMs for
implementation of the reliefs extended to sick industrial units for their
revival / rehabilitation on the basis ofthe orders issued by the
Commissioner for Industrial Development and Director of Industries &
Commerce, Government of Karnataka.

28. Incentive for Prompt Payment / Advance Payment: An incentive at the


rate of 0.25% of such bill shall be given to the following Consumers by
way of adjustment in the subsequent monthsbill:

(i) In all cases of payment throughECS.


(ii) And in the case of monthly bills exceeding Rs.1, 00,000/- (Rs. one
lakh), if the payment is made 10 days in advance of the due
date.
(iii) Advance Payment exceeding Rs 1000/-made by the Consumers
towards monthlybills.

ccxc
29. Conditions of Supply of Electricity of the Distribution Licensees in the
State of Karnataka and amendments issued thereon from time to time
and Regulations issued under the Electricity Act, 2003 will prevail over
the extract given in this tariff book in the event of anydiscrepancy.

30. Self-Reading ofMeters:

The Commission has approved Self-Reading of Meters by Consumers


and issue of bills by the Licensee based on such readings and the
Licensee shall take the reading at least once in six months and
reconcile the difference, if any and raise the bills accordingly. This
procedure may be implemented by the Licensee as stipulated under
Section 26.01 of Conditions of Supply of Electricity of the Distribution
Licensees in the State of Karnataka.

ELECTRICITY TARIFF - 2018

PART-1

HIGH TENSION SUPPLY

ccxci
Applicable to Bulk Power Supply of
Voltages at 11KV (including 2.3/4.6
KV) and above at Standard High
Voltage or Extra High Voltages when
the Contract Demand is 50 KW / 67
HP andabove.

ccxcii
ELECTRICITY TARIFF 2018

PART-1

HIGH TENSION SUPPLY

Applicable to Bulk Power Supply at Voltages of 11KV (including 2.3/4.6


KV) and above at Standard High Voltage or Extra High Voltages when
the Contract Demand is 50 KW / 67 HP and above.

ccxciii
CONDITIONS APPLICABLE TO BILLING OF HT INSTALLATIONS:

1. BillingDemand

A) The billing demand during unrestricted period shall be the maximum


demand recorded during the month or 75% of the CD, whichever is
higher.

B) When the Licensee has imposed demand cut of 25% or less, the
conditions stipulated in (A) shallapply.

C) When the demand cut is in excess of 25%, the billing demand shall be
the maximum demand recorded or 75% of the restricted demand,
whichever ishigher.

D) If at any time the maximum demand recorded exceeds the CD or the


demand entitlement, or opted demand entitlement during the period
of restrictions, if any, the Consumer shall pay for the quantum of excess
demand at two times the normal rate per KVA per month as deterrent
charges as per Section 126(6) of the Electricity Act, 2003. For over-
drawal during the billing period, the penalty shall be two times the
normalrate.

E) During the periods of disconnection, the billing demand shall be 75% of


CD, or 75% of the demand entitlement that would have been
applicable, had the installation been in service, whichever is less. This
provision is applicable only, if the installation is under disconnection for
the entire billingmonth.

F) During the period of energy cut, the Consumer may get his demand
entitlement lowered, but not below the percentage of energy
entitlement, (For example, in case the energy entitlement is 40% and
the demand entitlement is 80%, the re-fixation of demand entitlement
cannot be lower than 40% of the CD). The benefit of lower demand

ccxciv
entitlement will be given effect to from the meter reading date of the
same month, if the option is exercised on or before 15th of the month. If
the option is exercised on or after 16th of the month, the benefit will be
given effect to from the next meter reading date. The Consumer shall
register such option by paying a processing fee of Rs.100/- at the
Jurisdictional sub-division office.

(i) The billing demand in such cases, shall be the Revised (Opted)
Demand Entitlement or, the recorded demand, whichever is
higher. Such option for reduction of demand entitlement, is allowed
only once during the entire span of that particular Energy Cut
Period. The Consumer, can however, opt for a higher demand
entitlement upto the level permissible under the demand cut
notification, and the benefit will be given effect to from the next
meter reading date. Once the Consumer opts for enhancement of
demand, which has been reduced under Clause (F), no further
revision is permitted during that particular energy cutperiod.

(ii) The opted reduced demand entitlement will automatically cease


to be effective, when the energy cut is revised. The facility for
reduction and enhancement can however be exercised afresh by
the Consumer as indicated in the previousparas.

G) For the purpose of billing, the billing demand of 0.5 KVA and above will
be rounded off to the next higher KVA, and billing demand of less
than 0.5 KVA shall beignored.

2. Power factor(PF)

It shall be the responsibility of the HT Consumer to determine the


capacity of PF correction apparatus and maintain an average PF of
not less than 0.90.

(i) The specified P.F. is 0.90. If the power factor goes below 0.90
Lag, a surcharge of 3 Paise per unit consumed will be levied for
every reduction of P.F. by 0.01 below 0.90Lag.

ccxcv
(ii) The power factor when computed as the ratio of KWh / KVAh
will be determined upto 3 decimals (ignoring figures in the other
decimal places), and then rounded off to the nearest second
decimal as illustratedbelow:

(a) 0.8949 to be rounded off to0.89


(b) 0.8951 to be rounded off to0.90

In respect of Electronic Tri-Vector meters, the recorded average PF


over the billing period shall be considered for billing purposes. If the
same is not available, the ratio of KWh to KVAh consumed in the billing
month shall beconsidered.

3. Rebate for supply at highvoltage:

If the Consumer is availing power at voltage higher than 13.2 KV, he will
be entitled to a rebate as indicated below:

Supply Voltage:Rebate

A) 33/66KV 2 Paise/unit of energyconsumed


B) 110KV 3 Paise/unit of energyconsumed
C) 220KV 5 Paise/unit of energyconsumed

The above rebate will be allowed in respect of all the installations of


the above voltage class, including the existing installations, and also
for installations converted from 13.2 KV and below to 33 KV and above
and also for installations converted from 33/66 KV to 110/220 KV, from
the next meter reading date after conversion / service / date of
notification of this Tariff order, as the case may be. The above rebate is
applicable only on the normal energy consumed by the Consumer
including the consumption under TOD Tariff, and is not applicable on
any other energy allotted and consumed, if any,viz.,

i) WheeledEnergy.
ii) Any energy, including the special energy allotted over and
above normalentitlement.

iii) Energy drawal under special incentive scheme, ifany.

The above rebate is not applicable for Railway Traction.

ccxcvi
4. In respect of Residential Quarters / Colonies availing Bulk power supply
by tapping the main HT supply, the energy consumed by such Colony
loads, metered at single point, shall be billed under HT-4 tariff schedule.
No reduction in demand recorded in the main HT meter will be
allowed.

5. Energy supplied may be utilized for all purposes associated with the
working of the installations, such as, Office, Stores, Canteens, Yard
Lighting, Water Supply and Advertisements within thepremises.

6. Energy can also be used for construction, modification and expansion


purposes within thepremises.

7. Power supply under HT-4 tariff schedule may be used for Commercial
and other purposes inside the colony for installations such as Canteen,
Club, Shop, Auditorium etc., provided, this load is less than 10% of the
CD.

8. In respect of Residential Apartments, availing HT Power supply under


HT-4 tariff schedule, the supply availed for Commercial and other
purposes like Shops, Hotels, etc., will be billed under appropriate tariff
schedule (Only Energy charges) duly deducting such consumption in
the main HT supply bill. No reduction in the recorded demand of the
main HT meter is allowed. Common areas shall be billed at Tariff
applicable to that of the predominant Consumercategory.

9. SeasonalIndustries

a. The industries, which intend to utilize seasonal industry benefit, shall


conform to the conditionalities under Para no. 24 of the General
terms and conditions of tariff (applicable to both HT &LT).
b. The industries that intend to avail this benefit shall have Electronic
Tri-Vector Meter fitted to theinstallation.
c. Monthly charges during the working season, shall be the demand
charges on 75% of the contract demand, or the recorded

ccxcvii
maximum demand during the month, whichever is higher, plus the
energy charges
d. Monthly charges during the off season shall be demand charges on
the maximum demand recorded during the month or 50% of the CD
whichever is higher plus the energycharges.

ccxcviii
TARIFF SCHEDULE HT-1

Applicable to Water Supply, Drainage / Sewerage water treatment plant and


Sewerage Pumping installations, belonging to Bangalore Water Supply and
Sewerage Board, Karnataka Urban Water Supply and Sewerage Board, other
local bodies, State and Central Government.
[

RATE SCHEDULE
Demand charges Rs.200 /kVA of billing demand/month
Energy charges
[
485 paise/unit

TOD Tariff at the option of the Consumer

Time of Day Increase (+) / reduction (-) in energy


charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 Hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
next day

Note: Energy supplied to residential quarters availing bulk supply by


the above category of Consumer, shall be metered separately
at a single point, and the energy consumed shall be billed at HT-
4 Tariff. No reduction in the demand recorded in the main HT
meter will beallowed.

TARIFF SCHEDULE HT-2(a)


Applicable to Industries, Factories, Workshops, Research &
Development Centres, Industrial Estates, Milk dairies, Rice Mills, Phova
Mills, Roller Flour Mills, News Papers, Printing Press, Railway
Workshops/KSRTC Workshops/ Depots, Crematoriums, Cold Storage,
Ice & Ice-cream mfg. Units, Swimming Pools of local bodies, Water
Supply Installations of KIADB and other industries, all Defence
Establishments. Hatcheries, Poultry Farm, Museum, Floriculture, Green
House, Bio Technical Laboratory, Hybrid Seeds processing Units, Stone
Crushers, Stone cutting, Bakery Product Manufacturing Units, Mysore
Palace illumination, Film Studios, Dubbing Theatres, Processing, Printing,
Developing and Recording Theaters, Tissue Culture, Aqua Culture,
Prawn Culture, Information Technology Industries engaged in

ccxcix
development of Hardware & Software, Information Technology (IT)
enabled Services / Start-ups(As defined in GOI notification dated
17.04.2015)/ Animation / Gaming / Computer Graphics as certified by
the IT & BT Department of GOK/GOI, Drug Mfg. Units, Garment Mfg.
Units, Tyre retreading units, Nuclear Power Projects, Stadiums
maintained by Government and local bodies, also Railway Traction,
Effluent treatment plants and Drainage water treatment plants owned
other than by the local bodies, LPG bottling plants, petroleum pipeline
projects, Piggery farms, Analytical Lab for analysis of ore metals, Saw
Mills, Toy/wood industries, Satellite communication centres, and
Mineral water processing plants / drinking water bottlingplants.

RATE SCHEDULE

HT-2(a)(i): Applicable to Areas under Bruhat Bangalore Mahangara Palike


(BBMP) and Municipal Corporations

Demand charges Rs.210 /kVA of billing demand/month


Energy charges
For the first one lakh units 665 paise per unit
For the balance units 695 paise per unit
Railway Traction and Effluent Treatment Plants

Demand charges Rs.210/kVA of billing demand/month


Energy Charges 620 paise per unit for all the units

Tariff applicable to Bangalore Metropolitan Railway Corporations


Ltd., (BMRCL)

Demand charges Rs.210/kVA of billing demand/month


Energy Charges 600 paise per unit for all the units

HT-2(a)(ii): Applicable to Areas other than those covered under HT-2(a)(i)

Demand charges Rs.200/kVA of billing demand/month


Energy charges
For the first one lakh units 660 paise per unit
For the balance units 680 paise per unit
Railway Traction and Effluent Treatment Plants

ccc
Demand charges Rs.210/kVA of billing demand/month
Energy Charges 620 paise per unit for all the units

ARIFF SCHEDULE HT-2(b)

Applicable to Commercial Complexes, Cinemas, Hotels, Boarding & Lodging,


Amusement Parks, Telephone Exchanges, Race Course, All Clubs, T.V.
Station, All India Radio, Railway Stations, Air Port, BMTC,KSRTC bus
stations, All offices, Banks, Commercial Multi-storied buildings, APMC Yards,
Stadiums other than those maintained by Government and Local Bodies,
Construction power for irrigation, Power Projects and Konkan Railway
Project, Petrol / Diesel and Oil storage plants, I.T. based medical transcription
centers, telecom, call centers / BPO / KPO, Diagnostic centres, concrete
mixture (Ready Mix Concrete)units.

RATE SCHEDULE

HT-2 (b)(i): Applicable to Areas under Bruhat Bangalore Mahangara Palike


(BBMP) and Municipal Corporations.
Demand charges Rs.230/kVA of billing demand/month
Energy charges
For the first two lakh units 845 paise per unit
For the balance units 855 paise per unit

HT-2(b)(ii): Applicable to all areas other than those covered under HT-2(b)(i)

Demand charges Rs.220/kVA of billing demand/month


Energy charges
For the first two lakh units 825 paise per unit
For the balance units 835 paise per unit

TARIFF SCHEDULE HT-2(c)

RATE SCHEDULE

HT-2 (c) (i) - Applicable to Government Hospitals, Hospitals run by


Charitable Institutions, ESI hospitals, Universities and Educational
Institutions belonging to Government and Local bodies, Aided
Educational Institutions and Hostels of all Educational Institutions.
Demand charges Rs.200/kVA of billing demand/month
Energy charges
For the first one lakh units 640 paise per unit
For the balance units 680 paise per unit

ccci
RATE SCHEDULE

HT-2 (c) (ii) -Applicable to Hospitals and Educational Institutions other than
those covered under HT-2 (c) (i).

Demand charges Rs.200/kVA of billing demand/month


Energy charges
For the first one lakh units 740 paise per unit.
For the balance units 780 paise per unit.

Note: Applicable to HT-2 (a), HT-2 (b)& HT-2(c) Tariff Schedule.

1. Energy supplied may be utilized for all purposes associated


with the working of the installation such as offices, stores,
canteens, yard lighting, water pumping and
advertisement within thepremises.
2. Energy can be used for construction, modification and
expansion purposes within thepremises.

3. In respect of industries availing HT power supply underHT2


(a) tariff schedule, the supply availed for Effluent
Treatment Plant situated within the premises by fixing the
separate sub-meter, a rebate of 50 paise per unit of
electricity consumed by such Effluent Treatment Plant shall
be given to the applicable tariff schedule. No reduction in
the recorded demand of the main HT supply isallowed.

TOD Tariff applicable to HT 2(a), HT2 (b) and HT2(c) category.

Time of Day Increase (+) / reduction (-) in energy


charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 Hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
next day

cccii
TARIFF SCHEDULE HT-3 (a)

Applicable to Lift irrigation Schemes/ Lift irrigation societies,

RATE SCHEDULE

HT-3 (a)(i): Applicable to LI schemes under Govt. Departments/


Govt. ownedCorporations.

Energy charges/ Minimum Charges 225 paiseper unit subject to an annual


minimum of Rs.1240 per HP/Annum.

HT-3(a)(ii): Applicable to Private LI schemes and Lift Irrigation societies fed


through express/ Urban feeders

Fixed Charges Rs.50 /HP/ per month of sanctioned


load
Energy charges 225 paise/unit

HT-3(a)(iii): Applicable to Private LI schemes and Lift Irrigation societies


other than those covered under HT-3 (a)(ii).

Fixed Charges Rs.30 /HP/ per month of sanctioned


load
Energy charges 225 paise/unit

TARIFF SCHEDULE HT-3 (b)

HT-3 (b): Applicable to Irrigation and Agricultural Farms, Government


Horticultural Farms, Private Horticulture nurseries, Coffee, Tea,
Rubber, Coconut & Arecanut Plantations.

RATE SCHEDULE

Energy charges / Minimum Charges 425 paise Per unit subject to an


annual minimum of Rs.1240/- per HP
of sanctioned load.

Note: These installations are to be billed on quarter yearly basis.

ccciii
TARIFF SCHEDULE HT-4

Applicable to Residential apartments and colonies (whether situated outside


or inside the premises of the main HT Installation) availing power supply
independently or by tapping the main H.T. line. Power supply can be used for
residences, theatres, shopping facility, club, hospital, guest house, yard/street
lighting, canteen located within the colony.
RATE SCHEDULE
Applicable to all areas.

Demand charges Rs.120/- per kVA of billing demand/


month
Energy charges 620 paise/unit

NOTE: (1) In respect of residential colonies availing power supply by tapping


the main H.T. supply, the energy consumed by such colony loads
metered at a single point, is to be billed at the above energy
rate. No reduction in the recorded demand of the main H.T.
supply isallowed.

(2) Energy under this tariff may be used for commercial and other
purposes inside the colonies, for installations such as, Canteens,
Clubs, Shops, Auditorium etc., provided, this commercial load is
less than 10% of the Contractdemand.

(3) In respect of Residential Apartments, availing HT Power supply


under HT-4 tariff schedule, the supply availed for Commercial and
other purposes like Shops, Hotels, etc., will be billed under
appropriate tariff schedule (Only Energy charges), duly deducting
such consumption in the main HT supply bill. No reduction in the
recorded demand of the main HT meter is allowed. Common
areas shall be billed at Tariff applicable to the predominant
Consumercategory.

TARIFF SCHEDULE HT-5

ccciv
Tariff applicable to sanctioned load of 67 HP and above for hoardings
and advertisement boards and construction power for industries
excluding those category of consumers covered under HT2(b) Tariff
schedule availing power supply for construction power for irrigation
and power projects and also applicable to power supply availed on
temporary basis with the contract demand of 67 HP and above of all
categories.

HT 5 Temporary supply
RATE SCHEDULE
67 HP and above:
Fixed charges / Rs.240/HP/month for the entire sanction load /
DemandCharges contract demand

Energy Charge 1000 paise / unit

HT-5 (a)- Temporary Supply

Applicable to power supply availed on temporary basis with the


contract demand of 67 HP and above by Bangalore International
Exhibition Centre.

RATE SCHEDULE
67 HP and above: Approved Tariff
Fixed Charges / Not Applicable
DemandCharges
Energy Charges 1100 paise / unit

Note:
1. Temporary power supply with or without extension of distribution main
shall be arranged through a prepaid energy meter duly observing the
provisions of Clause 12 of the Conditions of Supply of Electricity of the
Distribution Licensees in the State ofKarnataka.

2. This Tariff is also applicable to touring cinemas having licence for a


duration of less than oneyear.

cccv
3. All the conditions regarding temporary power supply as stipulated in
Clause 12 of the Conditions of Supply of Electricity of the Distribution
Licensees in the State of Karnataka shall be complied with before
service.

---0---

ELECTRICITY TARIFF-2018

PART-II

LOW TENSION SUPPLY

(400 Volts Three Phase and

230Volts Single Phase Supply)

cccvi
ELECTRICITY TARIFF-2018

PART-II

LOW TENSION SUPPLY

(400 Volts Three Phase and

230Volts Single Phase Supply)

cccvii
CONDITIONS APPLICABLE TO BILLING OF LT INSTALLATIONS:

1. In the case of LT Industrial / Commercial Consumers, Demand based


Tariff at the option of the Consumer, can be adopted. The Consumer
is permitted to have more connected load than the sanctioned load.
The billing demand will be the sanctioned load, or Maximum Demand
recorded in the Tri-Vector Meter during the month, whichever is higher.
If the Maximum Demand recorded is more than the sanctioned load,
penal charges at two times the normal rate shallapply.

2. Use of power within the Consumer premises for bonafide temporary


purpose is permitted, subject to the conditions that, total load of the
installation on the system does not exceed the sanctionedload.

3. Where it is intended to use power supply temporarily, for floor polishing


and such other portable equipments, in a premises having permanent
power supply, such equipments shall be provided with earth leakage
circuit breakers of adequatecapacity.

4. The laboratory installations in educational institutions are allowed to


install connected machineries up to 4 times the sanctioned load. The
fixed charges shall however be on the basis of sanctionedload.

5. Besides combined lighting and heating, electricity supply under tariff


schedules LT2 (a) & LT2 (b), can be used for Fans, Televisions, Radios,
Refrigerators and other household appliances, including domestic
water pumps and air conditioners, provided, they are under single
meter connection. If a separate meter is provided for Air-conditioner
load, the Consumer shall be served with a notice to merge this load,
and to have a single meter for the entire load. Till such time, the air
conditioner load will be billed under CommercialTariff.

6. Bulk LTsupply:

If power supply for lighting / combined lighting & heating {LT 2(a)}, is
availed through a bulk Meter for group of houses belonging to one

cccviii
Consumer, (ie, Where bulk LT supply is availed), the billing for energy
shall be done at the slab rate for energy charges matching the
consumption obtained, by dividing the bulk consumption by number
of houses. In addition, fixed charges for the entire sanctioned load shall
be charged as per Tariffschedule.

7. A rebate of 25 Paise per unit will be given for the House/ School/Hostels
meant for Handicapped, Aged, Destitute and Orphans, Rehabilitation
Centres under Tariff schedule LT2(a).

8. SOLAR REBATE: A rebate of 50 Paise per unit of electricity consumed


subject to a maximum of Rs. 50/- per installation per month will be
allowed to Tariff schedule LT 2(a), if solar water heaters are installed
and used. Where Bulk Solar Water Heater System is installed, Solar
Water Heater rebate shall be allowed to each of the individual
installations, provided that, the capacity of Solar Water Heater in such
apartment / group housing shall be a minimum capacity of 100 Ltr. per
household.

9. A rebate of 20% on fixed charges and energy charges will be allowed


in the monthly bill in respect of public Telephone booths having
STD/ISD/ FAX facility run by handicapped people, under Tariff schedule
LT3.

10. A rebate of 2 paise per unit will be allowed if capacitors are installed
as per Clause 23 of Conditions of Supply of Electricity of the Distribution
Licensees in the State of Karnataka in respect of all metered IP Set
Installations.

11. Power Factor(PF):

Capacitors of appropriate capacity shall be installed in accordance


with Clause 23 of Conditions of Supply of Electricity of the Distribution
Licensees in the State of Karnataka, in the case of installations covered
under Tariff category LT 3, LT4, LT 5, & LT 6, where motive power is
involved.

cccix
(i) The specified P.F. is 0.85. If the PF is found to be less than 0.85 Lag, a
surcharge of 2 Paise per unit consumed will be levied for every
reduction of P.F. by 0.01 below 0.85 Lag. In respect of LT installations,
however, this is subject to a maximum surcharge of 30 Paise perunit.

(ii) The power factor when computed as the ratio of KWh/KVA will be
determined up to 3 decimals (ignoring figures in the other decimal
places) and then rounded off to the nearest second decimal as
illustratedbelow:
(a) 0.8449 to be rounded off to0.84
(b) 0.8451 to be rounded off to0.85

(iii) In respect of Electronic Tri-Vector meters, the recorded average PF


over the billing period shall be considered for billingpurposes.

(iv) During inspection, if the capacity of capacitors provided is found to be


less than what is stipulated in Conditions of Supply of Electricity of the
Distribution Licensees in the State of Karnataka, a surcharge of 30
Paise/unit will be levied in the case of installations covered under Tariff
categories LT 3, LT 5, & LT 6 where motive power isinvolved.

(v) In the case of installations without electronic Tri-vector meters even


after providing capacitors as recommended in Clause 23.01 and 23.03
of Conditions of Supply of Electricity of the Distribution Licensees in the
State of Karnataka, if during any periodical or other testing / rating of
the installation by the Licensee, the PF of the installation is found to be
lesser than 0.85, a surcharge determined as above shall be levied from
the billing month following the expiry of Three months notice given by
the Licensee, till such time, the additional capacitors are installed and
informed to the Licensee in writing by the Consumer. This is also
applicable for LT installations provided with electronic Tri-vectormeters.

cccx
12. All new IP set applicants shall fix capacitors of adequate capacity in
accordance with Clause 23 of Conditions of Supply of Electricity of the
Distribution Licensees in the State of Karnataka before takingservice.

13. All the existing IP set Consumers shall also fix capacitors of adequate
capacity in accordance with Clause 23 of Conditions of Supply of
Electricity of the Distribution Licensees in the State of Karnataka, failing
which, PF surcharge at the rate of Rs.60/-per HP/ year shall be levied. If
the capacitors are found to be removed / not installed, a penalty at
the same rate as above (Rs. 60/-per HP / Year) shall belevied.

14. The Semi-permanent cinemas having Semi-permanent structure, with


permanent wiring and licence of not less than one year, will be billed
under commercial tariff schedule i.e., LT3.

15. Touring cinemas having an outfit comprising cinema apparatus and


accessories, taken from place to place for exhibition of
cinematography films and also outdoor shooting units, will be billed
under Temporary Tariff schedule i.e., LT7.

16. The Consumers under IP set tariff schedule, shall use the energy only for
pumping water to irrigate their own land as stated in the IP set
application / water right certificate and for bonafide agriculture use.
Otherwise, such installations shall be billed under appropriate Industrial
/ Commercial tariff, based on the recorded consumption if available,
or on the consumption computed as per the Table given under Clause
42.06 of the Conditions of Supply of Electricity of the Distribution
Licensees in the State of Karnataka.

17. The water pumped for agricultural purposes may also be used by the
Consumer for his bonafide drinking purposes and for supplying water to
animals, birds, Poultry farms, Dairy farms and fish farms maintained by
the Consumer in addition toagriculture.

18. The motor of IP set installations can be used with an alternative drive
for other agricultural operations like sugar cane crusher,coffee

cccxi
pulping, arecanut cutting etc., with the approval of the Licensee. The
energy used for such operation shall be metered separately by
providing alternate switch and charged at LT Industrial Tariff (Only
Energy charges) during the period of alternative use. However, if the
energy used both for IP Set and alternative operation, is measured
together by one energy meter, the energy used for alternate drive
shall be estimated by deducting the average IP Set consumption for
that month, as per the IP sample meter readings for the sub division, as
certified by the sub-divisionalOfficer.

19. The IP Consumer is permitted to use energy for lighting the pump house
and well limited to two lighting points of 40 Wattseach.

20. Billing shall be made at least once in a quarter year for all IPsets.

21. In the case of welding transformers, the connected load shall be taken
as:
a) Half the maximum capacity in KVA as per the nameplate specified
under IS:1851

OR

b) Half the maximum capacity in KVA as recorded during the rating by


the Licensee, whichever ishigher.

22. Electricity under Tariff LT 3 / LT 5 can also be used for Lighting, Heating
and Air-conditioning, Yard-Lighting, water supply in the respective of
premises of Commercial / IndustrialUnits.

23. Fluorescent fittings shall be provided by the Licensee for the Streetlights
in the case of villages covered under the Licensees electrification
programme for initialinstallation.

In all other cases, the entire cost of fittings including Brackets, Clamps,
etc., and labour for replacement, additions and modifications shall be met
by the organizations making such a request. Labour charges shall be paid
at the standard rates fixed by the Licensee for each type offitting.

cccxii
24. Lamps, fittings and replacements for defective components of fittings
shall be supplied by the concerned Village Panchayaths, Town
Panchayaths or Municipalities forreplacement.

25. Fraction of KW / HP shall be rounded off to the nearest quarter KW / HP


for purpose of billing and the minimum billing being for 1 KW / 1HP in
respect of all categories of LT installations including I.P. sets. In the case
of street lighting installations, fraction of KW shall be rounded off to
nearest quarter KW for the purpose of billing and the minimum billing
shall be quarterKW.

26. SeasonalIndustries.

a) The industries which intend to utilize seasonal industry benefit, shall


comply with the conditionalities specified under Para no. 24 of the
General terms and conditions of tariff (applicable to both HT &LT).

b) The industries that intend to avail this benefit shall have Electronic
Tri-Vector Meter fitted to theirinstallation.

c) Monthly charges during the seasonal months shall be fixed charges


and energy charges. The monthly charges during the off seasonal
months shall be the energy charges plus 50% of the fixedcharges.

TARIFF SCHEDULE LT-1

LT-1: Applicable to installations serviced under Bhagya jyothi and Kutira jyothi
(BJ/KJ) schemes.

RATE SCHEDULE

Energy charges Nil*


(including recovery towards Fully subsidized by the GOK
service main charges)

Commission Determined Tariff (CDT) for the above category i.e., LT-1 is Rs.6.48
per unit.

cccxiii
*Since GOK is meeting the full cost of supply to BJ / KJ, the Tariff payable by
these Consumers is shown as Nil. However, if the GOK does not release the
subsidy in advance, CDT of Rs.6.48 per unit subject to monthly minimum ofRs.30/-
per installation per month shall be demanded and collected from these
consumers.

Note: If the consumption exceeds 40 units per month or any BJ/KJ installation
is found to have more than one out let, it shall be billed as per Tariff
Schedule LT2(a).

cccxiv
TARIFF SCHEDULE LT-2(a)

Applicable to lighting/combined lighting, heating and motive Power


installations of residential houses and also to such houses where a
portion is used by the occupant for (a) Handloom weaving (b) Silk
rearing and reeling and artisans using motors up to 200 watts (c)
Consultancy in, (i) Engineering (ii) Architecture (iii) Medicine (iv)
Astrology (v) Legal matters (vi) Income Tax (vii) Chartered Accountants
(d) Job typing (e) Tailoring (f) Post Office (g) Gold smithy (h)
Chawki rearing (i) Paying guests/Home stay guests (j) personal
Computers (k) Dhobis (l) Hand operated printing press (m) Beauty
Parlours (n) Water Supply installations, Lift which is independently
serviced for bonafide use of residential complexes/residence, (o) Farm
Houses and yard lighting limiting to 120 Watts, (p) Fodder Choppers &
Milking Machines with a connected load upto 1HP.

Also applicable to the installations of (i) Hospitals, Dispensaries, Health


Centres run by State/Central Govt. and local bodies; (ii) Houses,
schools and Hostels meant for handicapped, aged, destitute and
orphans; (iii) Rehabilitation Centres run by charitable institutions, AIDS
and drug addicts Rehabilitation Centres; (iv) Railway staff Quarters with
single meter (v) fire servicestations.

It is also applicable to the installations of (a) Temples, Mosques,


Churches, Gurudwaras, Ashrams, Mutts and religious/Charitable
institutions; (b) Hospitals, Dispensaries and Health Centres run by
Charitable institutions including X-ray units; (c) Jails and Prisons (d)
Schools, Colleges, Educational institutions run by State/Central
Govt.,/Local Bodies; (e) Seminaries; (f) Hostels run by the Government,
Educational Institutions, Cultural, Scientific and Charitable Institutions(g)
Guest Houses/Travellers Bungalows run in Government buildings or by
State/Central Govt./Religious/Charitable institutions; (h) Publiclibraries;
(i) Silk rearing; (j) Museums; (k) Installations of Historical Monuments of

cccxv
Archaeology Departments;(l) Public Telephone Booths without
STD/ISD/FAX facility run by handicapped people; (m) Sulabh / Nirmal
Souchalayas; (n) Viswa Sheds having Lighting Loads only.

RATE SCHEDULE
LT-2(a)(i) : Applicable to areas coming under Bruhat Bangalore
Mahanagara Palike (BBMP), Municipal Corporations and
all other Urban Local Bodies.

Fixed charges per For the first KW Rs.40/- per KW


month For every additional KW Rs.50/- per KW
For 0 - 30 units (Lifeline 325 paise/unit
consumption)
Energy charges
31 to 100 units 470paise/unit
101 to 200 units 625 paise /unit
201 to 300 units 730 paise /unit
301 to 400 units 735 paise /unit
Above 400 units 740 paise /unit

LT-2(a)(ii): Applicable to Areas under Village Panchayats

Fixed charges per For the first KW Rs.25/- per KW


month For every additional KW Rs.40/- per KW
Energy charges For 0 - 30 units (Lifeline 315 paise/unit
consumption)
31 to 100 units 440 paise/unit
101 to 200 units 595 paise/unit
201 to 300 units 680 paise /unit
Above 300 units 685 paise /unit

TARIFF SCHEDULE LT-2(b)

Applicable to the installations of Private Professional and other Private


Educational Institutions including aided, unaided institutions, Nursing
Homes and Private Hospitals having only lighting or combined lighting
& heating, and motivepower.

cccxvi
RATE SCHEDULE

LT-2(b)(i): Applicable to Areas under Bruhat Bangalore Mahangara Palike


(BBMP) and Municipal Corporations and all other urban Local
Bodies.

Fixed charges Rs.55 per KW subject to a minimum of Rs.85 per


month
Energy charges 0 to 200 units 650 paise/unit
Above 200 units 775paise/unit

LT-2(b)(ii): Applicable in Areas under Village Panchayats

Fixed charges Rs.45 per KW subject to a minimum of Rs.70per


month
Energy charges
0 to 200 units 595 paise/unit
Above 200 units 720 paise/unit

Note: Applicable to LT-2 (a), LT-2 (b) Tariff Schedules.

1 A rebate of 25 paise per unit shall be given for installation of a house/


School/ Hostels meant for Handicapped, Aged, Destitute and Orphans,
Rehabilitation Centres run by CharitableInstitutions.

2 (a) Use of power within the consumers premises for temporary purposes
for bonafide use is permitted subject to the condition that, the total
load of the installation on the system does not exceed the
sanctionedload.
(b) Where it is intended to use floor polishing and such other portable
equipment temporarily, in the premises having permanent supply,
such equipment shall be provided with an earth leakage circuit
breaker of adequatecapacity.

3 The laboratory installations in educational institutions are allowed to


install connected machinery up to 4 times the sanctioned load. The fixed
charges shall however be on the basis of sanctionedload.

cccxvii
4. Besides lighting and heating, electricity supply under this schedule can be
used for fans, Televisions, Radios, Refrigerators and other house-hold
appliances including domestic water pump and air conditioners,
provided, they are under single meter connection. If a separate meter is
provided for Air conditioner Load, the consumption shall be under
commercial tariff till it is merged with the mainmeter.

5. SOLAR REBATE: A rebate of 50 paise per unit of electricity consumed to a


maximum of Rs.50/- per installation per month will be allowed to Tariff
schedule LT 2(a), if solar water heaters are installed and used. Where Bulk
Solar Water Heater System is installed, Solar Water Heater rebate shall be
allowed to each of the individual installations, provided that, the
capacity of Solar Water Heater in such apartment / group housing shall
be a minimum capacity of 100 Ltr, perhousehold.

TARIFF SCHEDULE LT-3

Applicable to Commercial Lighting, Heating and Motive Power


installations of Clinics, Diagnostic Centres, X-Ray units, Shops, Stores,
Hotels / Restaurants / Boarding and Lodging Homes, Bars, Private guest
Houses, Mess, Clubs, Kalyan Mantaps / Choultry, permanent Cinemas/
Semi Permanent Cinemas, Theatres, Petrol Bunks, Petrol, Diesel and oil
Storage Plants, Service Stations/ Garages, Banks, Telephone
Exchanges. T.V. Stations, Microwave Stations, All India Radio, Dish
Antenna, Public Telephone Booths/ STD, ISD, FAX Communication
Centers, Stud Farms, Race Course, Ice Cream Parlours, Computer
Centres, Photo Studio / colour Laboratory, Photo Copiers, Railway
Installation excepting Railway workshop, BMTC / KSRTC Bus Stations
excepting Workshop, All offices, Police Stations, Commercial
Complexes, Lifts of Commercial Complexes, Battery Charging units,
Tyre Vulcanizing Centres, Post Offices, Bakery shops, Beauty Parlours,
Stadiums other than those maintained by Govt. and Local Bodies. It is
also applicable to water supply pumps and street lights not covered
under LT 6, Cyber cafs, Internet surfing cafs, Call centres, BPO / KPO,
Telecom, I.T. based medical transcription centres, Private Hostelsnot

cccxviii
covered under LT -2 (a), Paying guests accommodation provided in an
independent / exclusive premises, concrete mixtures (Ready Mix
Concrete) units.

cccxix
RATE SCHEDULE
LT-3 (i): Applicable in areas coming under Bruhat Bangalore Mahanagara
Palike(BBMP), Municipal Corporations and other urban local bodies

Fixed charges Rs.60 per KW


Energy charges For 0 - 50 units 750 paise/unit
Above 50units 850 paise/unit

Demand based tariff (optional) where sanctioned load


is above 5 KW but below 50 KW

Fixed charges Rs.75 per KW


Energy charges As above

RATE SCHEDULE
LT-3 (ii):Applicable in Areas under Village Panchayats
Fixed charges Rs.50 per KW per month
Energy charges For 0 - 50 units 700 paise/unit
Above 50units 800 paise/unit

Demand based tariff (optional) where sanctioned load


is above 5 KW but below 50 KW
Fixed charges Rs.65 per KW per month
Energy charges As above

Note: 1. Besides Lighting, Heating and Motive power, electricity supply under
this Tariff can also be used for Yard lighting/ air Conditioning/water
supply in the premises.

2. The semi-permanent Cinemas should have semi-Permanent


Structure with permanent wiring and licence for duration of not less
than oneyear.

3. Touring Cinemas having an outfit comprising Cinema apparatus


and accessories taken from place to place for exhibition of
cinematography film and also outdoor shooting units shall be billed
under LT- 7 Tariff.

4. A rebate of 20% on fixed charges and energy charges shall be


allowed in the monthly bill in respect of telephone Booths having
STD / ISD/FAX facility run by handicappedpeople.

5. Demand based Tariff at the option of the consumer can be adopted


as per Para 1 of the conditions applicable to LTinstallations.

cccxx
TARIFF SCHEDULE LT-4 (a), LT-4 (b) & LT-4(c)

Applicable to (a) Agricultural Pump Sets including Sprinklers (b) Pump sets
used in; (i) Nurseries of forest and Horticultural Departments; (ii) Grass Farms
and Gardens; (iii) Plantations other than Coffee, Tea, Rubber and Private
Horticulture Nurseries.

TARIFF SCHEDULE LT-4 (a)


Applicable to I.P. Sets up to and inclusive of 10 HP

RATE SCHEDULE

Fixed charges Free


Energy charges

Commission Determined Tariff (CDT) for LT4 (a) category is 334 paise per unit

In case the GOK does not release the subsidy in advance in the manner
specified by the Commission in K.E.R.C. (Manner of Payment of subsidy)
Regulations, 2008, CDT of 334 paise per unit shall be demanded and collected
from these consumers.

Note: This Tariff is applicable for Coconut and Arecanut plantations also.

TARIFF SCHEDULE LT-4 (b):

Applicable to IP sets above 10 HP

RATE SCHEDULE

Fixed charges Rs.50 per HP per month.


Energy charges 300 paise per unit

TARIFF SCHEDULE LT-4 (c) (i):

Applicable to Private Horticultural Nurseries, Coffee, Tea and Rubber


plantations of sanctioned load upto and inclusive of 10 HP.

RATE SCHEDULE

Fixed charges Rs.40 per HP per month.


Energy charges 300 paise per unit

cccxxi
cccxxii
TARIFF SCHEDULE LT-4 (c) (ii):

Applicable to Private Horticultural Nurseries, Coffee, Tea and Rubber


plantations of sanctioned load above 10 HP.

RATE SCHEDULE

Fixed charges Rs.50 per HP per month.


Energy charges 300 paise per unit

Note:

1) The energy supplied under this tariff shall be used by the consumers only for pumping water to irrigate their own
land as stated in the I.P. Set application / water right certificate and for bonafide agriculture use. Otherwise,
such installations shall be billed under the appropriate Tariff (LT-3/ LT-5) based on the recorded consumption if
available, or on the consumption computed as per the Table given under Clause 42.06 of the Conditions of
SupplyofElectricityoftheDistributionLicenseesintheStateofKarnataka.
2) The motor of IP set installations can be used with an alternative drive for other agricultural operations like
sugar cane crusher, coffee pulping, arecanut cutting etc., with the approval of the Licensee. The energy
used for such operation shall be metered separately by providing alternate switch and charged at LT Industrial
Tariff (Only Energy charges) during the period of alternative use. If the energy used both for IP Set and
alternative operation, is however measured together by one energy meter, the energy used for alternate drive
shall be estimated by deducting the average IP Set consumption for that month as per the IP sample meter
readings for the sub division as certified by the sub-divisionalOfficer.

3) The Consumer is permitted to use the energy for lighting the pump house and well limited to 2 lighting points of
40 Weach.

4) The water pumped for agricultural purposes may also be used by the Consumer for his bonafide drinking purposes
and for supplying water to animals, birds, Poultry farms, Dairy farms and fish farms maintained by the Consumer
in addition toagriculture.

5) Billing shall be made at least once in a quarter year for all IPsets.

6) A rebate of 2 paise per unit will be allowed if capacitors are installed as per Clause 23 of Conditions of Supply of
ElectricityoftheDistributionLicenseesintheStateofKarnatakainrespectofallmeteredIPSetInstallations.

7) Only fixed charges as in Tariff Schedule for Metered IP Set Installations shall be collected during the disconnection
period of IP Sets under LT 4(a), LT 4(b) and LT 4(c) categories irrespective of whether the IP Sets are provided
with Meters ornot.

TARIFF SCHEDULE LT-5

Applicable to Heating & Motive power (including lighting) installations


of industrial Units, Workshops, Poultry Farms, Sugarcane Crushers,
Coffee Pulping, Cardamom drying, Mushroom raising installations,
Flour, Huller & Rice Mills, Wet Grinders, Milk dairies, Ironing, Dry Cleaners
and Laundries having washing, Drying, Ironing etc., Tailoring shop, Bulk
Ice Cream and Ice manufacturing Units, Coffee Roasting andGrinding

cccxxiii
Works, Cold Storage Plants, Bakery Product Mfg. Units, BMTC/ KSRTC
workshops/Depots, Railway workshops, Drug manufacturing units and
Testing laboratories, Printing Presses, Garment manufacturing units, Bulk
Milk vending Booths, Swimming Pools of local Bodies, Tyre retreading
units, Stone crushers, Stone cutting, Chilly Grinders, Phova Mills,
pulverizing Mills, Decorticators, Iron & Red-Oxide crushing units,
crematoriums, hatcheries, Tissue culture, Saw Mills, Toy/wood industries,
Viswa Sheds with mixed load sanctioned under Viswa Scheme,
Cinematic activities such as Processing, Printing, Developing,
Recording theatres, Dubbing Theatres and film studios, Agarbathi
manufacturing unit., Water supply installations of KIADB & industrial
units, Gem & Diamond cutting Units, Floriculture, Green House, Biotech
Labs., Hybrid seed processing units. Information Technology industries
engaged in development of hardware & Software, Information
Technology (IT) enabled Services / Start-ups(As defined in GOI
notification dated 17.04.2015)/ Animation / Gaming / Computer
Graphics as certified by the IT & BT Department of GOK/GOI, Silk
filature units, Aqua Culture, Prawn Culture, Brick manufacturing units,
Silk / Cotton colour dying, Stadiums maintained by Govt. and local
bodies, Fire service stations, Gold / Silver ornament manufacturing
units, Effluent treatment plants, Drainage water treatment plants, LPG
bottling plants and petroleum pipeline projects, Piggery farms,
Analytical Lab. for analysis of ore metals, Satellite communication
centres, Mineral water processing plants / drinking water bottling plants
and soda fountainunits.

cccxxiv
RATE SCHEDULE

LT-5 (a): Applicable to Bruhat Bangalore MahanagaraPalikeand other


Municipal Corporation.
i. Fixedcharges

Fixed charges per i) Rs.40 per HP for 5 HP &below


month ii) Rs.45 per HP for above 5 HP & below 40 HP
iii)Rs.60 per HP for 40 HP & above but below 67HP
iv)Rs.120 per HP for 67 HP &above

ii. Demand based Tariff(optional)

Fixed Above 5 HP and less than 40 HP Rs.65 per KW of billing demand


charges 40 HP and above but less than Rs.90 per KW of billing demand
per month 67 HP
67 HP and above Rs.170 per KW of billing
demand

iii. EnergyCharges

0 to 500 units 525 paise/unit


Above 500 units 650 paise/unit

RATE SCHEDULE

LT-5 (b): Applicable to all Areas other than those covered under LT-5(a).

i. Fixedcharges

Fixed Charges i) Rs.35 per HP for 5 HP &below.


per Month ii) Rs.40 per HP for above 5 HP & below 40HP.
iii) Rs.55 per HP for 40 HP & above but below 67 HP.
iv)Rs.110 per HP for 67 HP &above.

ii. Demand based Tariff(optional)

Fixed Above 5 HP and less than 40 HP Rs.55 per KW of billing demand


Charges 40 HP and above but less than 67 Rs.80 per KW of billing demand
per HP
Month 67 HP and above Rs.160 per KW of billing
demand

cccxxv
iii. EnergyCharges

0 to 500 units 500 paise /unit


501 to 1000 units 590 paise /unit
Above 1000 units 620 paise/unit

TOD Tariff applicable to LT5 (a) & (b):At the option of the Consumer

Time of Day Increase (+) / reduction (-) in energy


charges over the normal tariff applicable
06.00 Hrs to 10.00 Hrs (+) 100 paise per unit
10.00 Hrs to 18.00 Hrs 0
18.00 Hrs to 22.00 Hrs (+) 100 paise per unit
22.00 Hrs to 06.00 Hrs (-) 100 paise per unit
next day

NOTE:

1. DEMAND BASEDTARIFF

In the case of LT Industrial Consumers, Demand based Tariff at the option of


the Consumer can be adopted. The Consumer is permitted to have more
connected load than the sanctioned load. The billing demand will be the
sanctioned load or Maximum Demand recorded in the Tri-Vector Meter
during the month whichever is higher. If the Maximum Demand recorded is
more than the sanctioned load, penal charges at two times the normal rate
shall apply.

2. Seasonal Industries: The industries which intend to utilize seasonal industry


benefit shall comply with the conditionalities under para no. 24 of general
terms and conditions applicable toLT.
3. Electricity can also be used for lighting, heating, and air-conditioning in the
premises.
4. In the case of welding transformers, the connected load shall be taken as,
(a) Half the maximum capacity in KVA as per the name plate specified
under-IS1851, or (b) Half the maximum capacity in KVA as recorded
during rating by the Licensee, whichever ishigher.

TARIFF SCHEDULE LT-6

Applicable to water supply and sewerage pumping installations and


also applicable to water purifying plants maintained by Government
and Urban Local Bodies/ Grama Panchayats for supplying pure
drinking water to residential areas Public Street lights/Park lights of
village Panchayat, Town Panchayat, Town Municipalities, City

cccxxvi
Municipalities / Corporations / State and Central Govt. / APMC, Traffic
signals, Survelliance Cameras at traffic locations belonging to
Government Department, subways, water fountains of local bodies.
Also applicable to Streetlights of residential Campus of universities,
other educational institutions, housing colonies approved by local
bodies/development authority, religious institutions, organizations run
on charitable basis, industrial area / estate and notified areas, also
applicable to water supply installations in residential Layouts, Street
lights along with signal lights including the gatemans shed with
associated equipment provided at the Railway level crossing, high
mast street lights, Lifts/ Escalators installed in pedestrian road crossing
maintained by Government and Urban local bodies/ Grama
Panchayats independently serviced.

RATE SCHEDULE
Water Supply- LT-6 (a)
Fixed charges Rs.55/HP/month
Energy charges 425 Paise/unit
Public lighting- LT-6 (b)
Fixed charges Rs.70/KW/month
Energy charges 585 Paise/unit
Energy Charges for LED/ Induction 485 paise/unit
Lighting

TARIFF SCHEDULE LT-7


Temporary Supply and Permanent Supply to Advertising Hoardings
TARIFF SCHEDULE LT-7(a)
Applicable to Temporary Power Supply for all purposes.

LT 7(a) Details Approved Tariff


Temporary Power Less than 67 HP: Energy charge at 1000 paise / unit
Supply for all subject to a weekly minimum of Rs.190
purposes. per KW of the sanctioned load.

TARIFF SCHEDULE LT-7(b)


Applicable to Hoardings & Advertisement boards, Bus Shelters with
Advertising Boards, Private Advertising Posts / Sign boards in the
interestofpublicsuchasPoliceCanopyDirectionboards,andother

cccxxvii
sign boards sponsored by Private Advertising Agencies / firms on
permanent connection basis.

LT 7(b) Details Approved Tariff


Power supply on Less than 67 HP: Fixed Charges at Rs.60 per KW / month
permanent Energy charges at 1000 paise / unit
connectionbasis

Note:
1. Temporary power supply with or without extension of distribution main shall
be arranged through a prepaid energy meter duly observing the
provisions of Clause 12 of the Conditions of Supply of Electricity of the
Distribution Licensees in the State ofKarnataka.

2. This Tariff is also applicable to touring cinemas having licence for duration
less than oneyear.
3. All the conditions regarding temporary power supply as stipulated in Clause
12 of the Conditions of Supply of Electricity of the Distribution Licensees in
the State of Karnataka shall be complied with beforeservice.

-O-

cccxxviii

Vous aimerez peut-être aussi