Académique Documents
Professionnel Documents
Culture Documents
KUALA LUMPUR
TWIN TOWER
PROCUREMENT
PROCUREMENT METHOD
Clients requirements:
TIME
1. This method is the most suitable as it provide lower cost risk to the
client due to the use of lump sum contract.
3. The amount is agreed between the parties in the contract before the
construction start.
The client is not interest to deal with too many parties except the
few key members of the project.
CONCLUSION
TRADITIONAL METHOD
- Longer time frame but ensures better quality and cost delivered
- Does not need to deal with multiple parties but only key players
Clients requirements:
Reasonably transparent
selection process
Eliminate potentially
non-performing contractor
RECOMMENDATION:
TWO STAGE
SELECTIVE TENDERING
SELECTIVE TENDERING
Tender Procedure
Pre-qualification Stage
1. Advertisement in newspaper
to invite interested tenderers
to submit their company
profiles for evaluation in the
Pre-qualification Form
2. A list of pre-qualified
contractors will then be
included in the final tender list
and invited to collect the
tender documents.
SELECTIVE TENDERING
Tender Procedure
Pre-qualification Stage
1. Advertisement in newspaper
to invite interested tenderers Reasonably transparent
to submit their company selection process
profiles for evaluation in the
Pre-qualification Form
Quality Assurance
CONTRACTUAL
ARRANGEMENT
CONTRACTUAL ARRANGEMENT
TYPE OF CONTRACT
LUMP SUM CONTRACT
Contractor is responsible for executing the complete contract work for a stated
total sum of money.
CONTRACTUAL ARRANGEMENT
TYPE OF CONTRACT
LUMP SUM CONTRACT
3) Minimum variation
CONTRACTUAL ARRANGEMENT
FORM OF CONTRACT
TIME
QUALITY
TIME
1. Clause 21.1
Possession of the site for execution of the works on the Date of Commencement
2. Article 7
Completion Date
3. Clause 22.1
Certificate of Non-Completion
4. Clause 22.2
Pay for the agreed Liquidated Damages (RM 250,000.00 a day)
5. Clause 15.2
Written notice for practically completed.
CONTRACTUAL ARRANGEMENT
QUALITY
Clauses 6.0
Material, Goods and Workmanship To Conform to Description, Testing And
Inspection supports the requirement of good workmanship
Clauses 6.3
Inspection and testing
Clauses 6.5
Work not in accordance with the contract
Clauses 6.8
Warranties in respect of materials and goods
CONTRACTUAL ARRANGEMENT