Vous êtes sur la page 1sur 2144

Analysis of PWD SoR 2014 for Civil Works 56

DIVISION 01 : GENERAL AND SITE FACILITIES


Item No.- 01.1.1
Erect and remove semi-permanent engineer's site office (minimum 15 sqm plinth area) with facilities

Considering one site


1. Erect and maintain engineer's site office with facilities (less salvaged value) L.S. = Tk. 57,768.00
2. Office furniture (less salvaged value) L.S. = Tk. 6,960.00
3. Stationeries, consumables etc. L.S. = Tk. 6,728.00
4. First-aid box, safety helmet, umbrella, gum-boots, crockeries, water purifier etc. L.S. = Tk. 8,584.00
5. Provide and maintain theodolie / level facilities L.S. = Tk. 5,800.00
6. Remove Engineer's Site facilities L.S. = Tk. 4,060.00
Total = Tk. 89,900.00
Profit 10.00% = Tk. 8,990.00
Overhead 3.50% = Tk. 3,146.50
Total cost Tk. 102,036.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5,938.63
Grand total = Tk. 107,975.13
Multiplier for 2014 from cost study 0.16
Say, Tk. 125,251 .00 Per site.

Item No.- 01.1.2


Erect and remove semi-permanent engineer's site office (minimum 38 sqm plinth area) with facilities
including security fencing
38 sqm
Considering one site
1. Erect and maintain engineer's site office with facilities in/c
providing security fencing (less salvaged value) L.S. = Tk. 149,547.20
2. Office furniture (less salvaged value) L.S. = Tk. 20,300.00
3. Stationeries, consumables etc. L.S. = Tk. 13,920.00
4. First-aid box, safety helmet, umbrella, gum-boots, crockeries, water purifier etc. L.S. = Tk. 23,200.00
5. Provide and maintain 5 KVA stand-bye Generator, theodolie / level facilities L.S. = Tk. 60,320.00
6. Remove Engineer's Site facilities L.S. = Tk. 11,930.98
Total = Tk. 279,218.18
Profit 10.00% = Tk. 27,921.82
Overhead 3.50% = Tk. 9,772.64
Tk. 316,912.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18,444.63
Grand total = Tk. 335,357.27
Multiplier for 2014 from PLA R study 0.16
Say, Tk. 389,014 .00 Per site.

Item No.- 01.1.3


Erect and remove semi-permanent Engineer's Site Office (minimum 38 sqm plinth area) with facilities including
security fencing and providing PC with monitor, Laserjet Printer, UPS etc.
38 sqm
Considering one site
1. Erect and maintain engineer's site office with facilities in/c
providing security fencing (less salvaged value) L.S. = Tk. 149,547.20
2. Office furniture (less salvaged value) L.S. = Tk. 20,300.00
3. Stationeries, consumables etc. L.S. = Tk. 13,920.00
4. First-aid box, safety helmet, umbrella, gum-boots, crockeries, water purifier etc. etc. L.S. = Tk. 23,200.00
5. Provide and maintain 5 KVA stand-bye Generator, theodolie / level facilities L.S. = Tk. 60,320.00
6. Provide and maintain PC, Monitor, Laserjet Printer, UPS etc facilities. L.S. = Tk. 81,200.00
7. Remove Engineer's Site facilities L.S. = Tk. 11,930.98
Total = Tk. 360,418.18
Profit 10.00% = Tk. 36,041.82
Analysis of PWD SoR 2014 for Civil Works 57

Overhead 3.50% = Tk. 12,614.64


Multiplier for 2014 from PLA R study 0.16 Tk. 409,074.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 23,808.55
Grand total = Tk. 432,883.19

Say, Tk. 502,145 .00 Per site.

Item No.- 01.1.4


Erect and remove semi-permanent Engineer's Site office (minimum 38 sqm plinth area) with facilities including
security fencing and providing PC with monitor, Laserjet Printer, UPS ETC, Photocopier & freeze
38 sqm
Considering one site
1. Erect and maintain engineer's site office with facilities in/c
providing security fencing (less salvaged value) L.S. = Tk. 149,547.20
2. Office furniture (less salvaged value) L.S. = Tk. 20,300.00
3. Stationeries, consumables etc. L.S. = Tk. 13,920.00
4. First-aid box, safety helmet, umbrella, gum-boots, crockeries, water purifier etc.etc. L.S. = Tk. 23,200.00
5. Provide and maintain 5 KVA stand-bye Generator, theodolie / level facilities L.S. = Tk. 60,320.00
6. Provide and maintain PC, Monitor, Laserjet Printer, UPS, freeze etc. facilities. L.S. = Tk. 104,400.00
7. Remove Engineer's Site facilities L.S. = Tk. 11,930.98
Total = Tk. 383,618.18
Profit 10.00% = Tk. 38,361.82
Overhead 3.50% = Tk. 13,426.64
Multiplier for 2014 from PLA R study 0.16 Tk. 435,406.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25,341.10
Grand total = Tk. 460,747.74

Say, Tk. 534,467 .00 Per site.


Item No.- 01.1.5
Erect and remove engineer's site office (minimum 10 sqm plinth area) with facilities
for low value simple work 10 sqm
Considering one site
1. Erect and maintain engineer's site office with facilities (less salvaged value) L.S. = Tk. 8,526.00
2. Office furniture (less salvaged value) L.S. = Tk. 2,552.00
3. Stationeries, consumables etc. L.S. = Tk. 597.40
4. First-aid box, safety helmet, umbrella, gum-boots etc. L.S. = Tk. 2,784.00
6. Remove Engineer's Site facilities L.S. = Tk. 2,706.66
Total = Tk. 17,166.06
Profit 10.00% = Tk. 1,716.61
Overhead 3.50% = Tk. 600.81
Tk. 19,483.48
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,133.96
Grand total = Tk. 20,617.44
Multiplier for 2014from PLA R study 0.16
Say, Tk. 23,916 .00 Per site.

Item No.- 01.1.6


Provide window type 1800 BTU A.C. for Employer's / Engineer's Office at site and remove after completion of contract.

Considering one A.C.

1. Cost of 18000 BTU A.C. 1 60000 = Tk. 60,000.00


2. Installation 1 Tk. 1,360.00 = Tk. 1,360.00
3. Remove after completion of contract 1 Tk. 660.00 = Tk. 660.00
Sub-total = Tk. 62,020.00
4. Less re-sale value = Tk. -18,000.00
Total = Tk. 44,020.00
Analysis of PWD SoR 2014 for Civil Works 58

Profit 10.00% = Tk. 4,402.00


Overhead 3.50% = Tk. 1,540.70
Tk. 49,962.70
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,907.88
Multiplier for 2014 from PLA R study Grand total = Tk. 52,870.58

Say, Tk. 52,871 .00 each

Item No.- 01.1.7


Provision and maintenance of Sign-Board (1 m x 2 m)
3.28 6.56 2 21.5168 sft
1. Cost of Sign Board including painting, lettering etc. 200 Tk. per sft L.S. = Tk. 4,303.36
2. Hoisting 1 303 Tk. L.S. = Tk. 303.00
3. Remove after completion of contract 1 303 Tk. L.S. = Tk. 303.00
Sub-total = Tk. 4,909.36
4. Less re-sale value = Tk. -1,200.00
Total = Tk. 3,709.36
Profit 10.00% = Tk. 370.94
Overhead 3.50% = Tk. 129.83
Tk. 4,210.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 245.03
Grand total = Tk. 4,455.16

Say, Tk. 2,228 .00 per sqm

Item No.- 01.2.1


Provide 3 sets as-built drawing using AutoCAD software in 23.38" x 16.54" (A-2) size standard drawing paper on
completeion of works

Considering per tender 23.38 16.54 2.69 sft


1. Survey, extg drg study by Engineer/ arch 7 day Tk. 1,500.00 = 10,500.00
2. Inventory listing 3 day Tk. 550.00 = 1,650.00
3. autocad operator 3 day Tk. 550.00 day = 1,650.00
4 Checking by Arch/Engr 1 day 60000 2000
5 sundries LS 395.00 395.00
Total = 16,195.00
Profit 10.00% = Tk. 1,619.50
Overhead 3.50% = Tk. 566.83
Tk. 18,381.33
Add VAT with adjustment factor1.0582 5.50% = Tk. 1,069.81
Grand total = Tk. 19,451.14

Say, Tk. 19,451 per tender

Item No.- 01.2.2


Provide additional copy of as-built drawing using AutoCAD software in 23.38" x 16.54" (A-2) size standard
drawing paper on completeion of works

Considering 1 sheet 23.38" x 16.54" 23.38 16.54 2.685 sft


1. Hardcopy 2.69 sft @ Tk. 16.50 sft = 44.39
2. Incidental, sundries etc. LS = 11.10
Total = 55.49
Profit 10.00% = Tk. 5.55
Overhead 3.50% = Tk. 1.94
Tk. 62.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3.67
Grand total = Tk. 66.65
Analysis of PWD SoR 2014 for Civil Works 59

=
Rate per sft. = Tk. 24.82
Rate per sqm. = Tk. 267.16

Say, Tk. 267 .00 Per sqm of drawing sheet

Item No.- 01.2.3


Provide colored post-card size 10 Nos. progress photographs
of works in 3 sets in each month during entire contract period of works
1. Cost for taking and developing photographs 1 1000 day 1,000.00
2. printing & sundries 10 5 each 50.00
Total = 1,050.00
Profit 10.00% = Tk. 105.00
Overhead 3.50% = Tk. 36.75
Tk. 1,191.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 69.36
Grand total = Tk. 1,261.11

Say, Tk. 1,261 .00 Each month

Item No.- 01.2.4


Prepare and Submission of Implementation Schedule using M.S. Project software (CPM Networking)

1. Planning Implementation Schedule & micro networking using M.S. Project


7 software
day or in equivalent
100000 soft ware month = Tk. 23,333.33
2. Developing hard-copy of networking 0.5 day 1500 day = Tk. 750.00
3 Printing of Hard copy in 3 set approx. 12.08 sft Tk. 16.50 199.32

Total = Tk. 24,282.65


Profit 10.00% = Tk. 2,428.27
Overhead 3.50% = Tk. 849.89
Tk. 27,560.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,604.07
Grand total = Tk. 29,164.88

Say, Tk. 29,165 per tender


Item No.- 01.2.5
Updating of Implementation Schedule prepared in M.S. Project software(CPM net working)

1. Updating Implementation Schedule prepared in M.S. Project software 3 day 100000 month = Tk. 10,000.00
2. Printing : 3set 12.08 sft day Tk. 16.50 L.S. = Tk. 300.00
Total = Tk. 10,300.00
Profit 10.00% = Tk. 1,030.00
Overhead 3.50% = Tk. 360.50
Tk. 11,690.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 680.40
Grand total = Tk. 12,370.90

Say, Tk. 12,371 .00 Each month


Item No.- 01.2.6
Logistic support to monthly progress meeting between Contractor and Emplyer at the Engineer's office at site

1. Logistic support to arrange and conducting progress meeting L.S. = Tk. 1,500.00
2. Incidental, sundries etc. L.S. = Tk. 225.00
Total = Tk. 1,725.00
Profit 10.00% = Tk. 172.50
Overhead 3.50% = Tk. 60.38
Tk. 1,957.88
Analysis of PWD SoR 2014 for Civil Works 60

Add VAT with adjustment factor 1.0582 5.50% = Tk. 113.95


Grand total = Tk. 2,071.83
Multiplier for 2014 from PLAR study 1.16
Say, Tk. 2,403 .00 each month

Item No.- 01.3


Setting out: providing layout, bench-mark, property line, formation level etc.
Considering 5000 sft ground area
1. Surveyor 1 No. @ Tk. 1,200.00 per day = Tk. 1,200.00
2. Helper to surveyor 1 No. @ Tk. 750.00 per day = Tk. 750.00
3. Hire charge of Level/Theodolite 1 set Tk. 884.00 per day = Tk. 884.00
4. Ordinary labour 2 No. @ Tk. 245.00 per day = Tk. 490.00
5. Cost for construct and protect bench-mark, test pit etc. L.S. = Tk. 4,600.00
6. Tools and plant, spike, nails, chalk-powder etc. L.S. = Tk. 612.50
Total = Tk. 8,536.50
Profit 10.00% = Tk. 853.65
Overhead 3.50% = Tk. 298.78
Tk. 9,688.93
Add VAT with adjustment factor 1.0582 5.50% = Tk. 563.91
Grand total = Tk. 10,252.84
Rate per sft. = Tk. 2.05
Multiplier for 2011 from PLA R study 1.16 Rate per sqm. = Tk. 22.07

Say, Tk. 26 .00 Per sqm.


Item No.- 01.4
Mobilization, cleaning site before commencing actual Physical works and demobilization
on completion of work
Considering a site of 5000 sft. Ground area
1. Contractor's site office, store, stackyard, Labour shed, service
connections, toilet facilities etc. cleaning site L.S. = Tk. 40,000.00
2. Cleaning and removal L.S. = Tk. 10,000.00
Total = Tk. 50,000.00
Profit 10.00% = Tk. 5,000.00
Overhead 3.50% = Tk. 1,750.00
Tk. 56,750.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,302.91
Grand total = Tk. 60,052.91
Rate per sft. = Tk. 12.01
Multiplier for 2011 from PLA R study 1.16 Rate per sqm. = Tk. 129.28

Say, Tk. 150 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 61

DIVISION 02 : EXCAVATION, FILLING AND SITE DEVELOPMENT & PALISADING

Item No.- 02.1.1


Layout and marking for earthwork in excavation for foundation
Considering 2000 sft. plinth area
1. Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
2. Skilled labour 1 No. @ Tk. 303.00 each Tk. 303.00
3. Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
4. Tools and plant, spikes, nails, chalk-powder etc. L.S. = Tk. 306.25
Total = Tk. 1,666.25
Profit 10.00% = Tk. 166.63
Overhead 3.50% = Tk. 58.32
Tk. 1,891.20
Add VAT with adjustment factor 1.0582 5.50% = Tk. 110.07
Grand total = Tk. 2,001.27
Rate per sft. = Tk. 1.00
Rate per sqm. = Tk. 10.76

Say, Tk. 11 .00 Per sqm.

Item No.- 02.1.2


Earth work in foundation trenches up to 1.5 m depth and maximum 10 m lead including
protecting and maintaining the trench: Soft claye soil/ loose sand / silt
Considering 1000 cft. work
1. Ordinary labour 5 Nos. @ Tk. 245.00 each = Tk. 1,225.00
2. Skilled labour 1 Nos. @ Tk. 303.00 each = Tk. 303.00
3. Tools and plant, protecting and maintaining trench dry L.S. = Tk. 61.25
Total = Tk. 1,589.25
Profit 10.00% = Tk. 158.93
Overhead 3.50% = Tk. 55.62
Tk. 1,803.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 104.98
Grand total = Tk. 1,908.78
Rate per cft. = Tk. 1.91
Rate per cum. = Tk. 67.45

Say, Tk. 67 .00 Per cum.

Item No.- 02.1.3


Earth work in foundation trenches up to 1.5 m depth and maximum 10 m lead including
protecting and maintaining the trench: medium stiff claye soil
Considering 1000 cft. work
1. Ordinary labour 7 Nos. @ Tk. 245.00 each = Tk. 1,715.00
2. Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
3. Tools and plant, protecting and maintaining trench dry L.S. = Tk. 102.08
Total = Tk. 2,271.58
Profit 10.00% = Tk. 227.16
Overhead 3.50% = Tk. 79.51
Tk. 2,578.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 150.06
Grand total = Tk. 2,728.31
Rate per cft. = Tk. 2.73
Rate per cum. = Tk. 96.41

Say, Tk. 96 .00 Per cum.

Item No.- 02.1.4


Analysis of PWD SoR 2014 for Civil Works 62

Earth work in foundation trenches up to 1.5 m depth and maximum 10 m lead including
protecting and maintaining the trench: Very stiff (hard) claye soil / rubbish
Considering 1000 cft. work
1. Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
2. Ordinary labour 10.00 Nos. @ Tk. 245.00 each = Tk. 2,450.00
3. Skilled labour 2.5 Nos. @ Tk. 303.00 each = Tk. 757.50
4. Tools and plant, protecting and maintaining trench dry L.S. = Tk. 102.08
Total = Tk. 3,406.83
Profit 10.00% = Tk. 340.68
Overhead 3.50% = Tk. 119.24
Tk. 3,866.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 225.05
Grand total = Tk. 4,091.80
Rate per cft. = Tk. 4.09
Rate per cum. = Tk. 144.44

Say, Tk. 144 .00 Per cum.

Item No.- 02.1.5


Earth work in foundation trenches up to 1.5 m depth and maximum 10 m lead including
protecting and maintaining the trench: Very soft / saturated / organic claye soil/ soil of semi-liquid state
Considering 1000 cft. work
1. Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
2. Ordinary labour 11 Nos. @ Tk. 245.00 each = Tk. 2,695.00
3. Skilled labour 3 Nos. @ Tk. 303.00 each = Tk. 909.00
4. Tools and plant, protecting and maintaining trench dry L.S. = Tk. 204.17
Total = Tk. 3,905.42
Profit 10.00% = Tk. 390.54
Overhead 3.50% = Tk. 136.69
Tk. 4,432.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 257.98
Grand total = Tk. 4,690.63
Rate per cft. = Tk. 4.69
Rate per cum. = Tk. 165.63

Say, Tk. 166 .00 Per cum.

Item No.- 02.1.6


Extra rate for each additional 0.5 meter depth exceeding 1.5 meter
Considering 1000 cft. work
1. Ordinary labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
Total = Tk. 367.50
Profit 10.00% = Tk. 36.75
Overhead 3.50% = Tk. 12.86
Tk. 417.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 24.28
Grand total = Tk. 441.39
Rate per cft. = Tk. 0.44
Rate per cum. = Tk. 15.54

Say, Tk. 16 .00 Per cum.


Analysis of PWD SoR 2014 for Civil Works 63

Item No.- 02.1.7


Extra rate for each 1 m additional lead beyond 10 m
Considering 1000 cft. work
1. Ordinary labour 0.20 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 49.00
Profit 10.00% = Tk. 4.90
Overhead 3.50% = Tk. 1.72
Tk. 55.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3.24
Grand total = Tk. 58.86
Rate per cft. = Tk. 0.06
Rate per cum. = Tk. 2.12

Say, Tk. 2.12 Per cum.

Item No.- 02.2


Bailing out water during earthwork in excavation for foundation
Break-up for 4 hours use of pump in one day to Discharge -- cft water
1. Hire charge of pump 1.00 day @ Tk. 588.00 Per day = Tk. 588.00
2. Fuel for 4 hours 3.00 liter @ Tk. 33.00 Per liter = Tk. 99.00
3. Pump operator 1.00 No. @ Tk. 423.00 Per day = Tk. 423.00
Total = Tk. 1,110.00
Profit 10.00% = Tk. 111.00
Overhead 3.50% = Tk. 38.85
Tk. 1,259.85
Add VAT with adjustment factor 1.0582 5.50% = Tk. 73.32
Grand total = Tk. 1,333.17
Rate per hour = Tk. 333.29

Say, Tk. 333 .00 Per hour

Item No.- 02.3


Supplying and driving of borrack bamboo post minimum 3" dia
Consider 1 No. bamboo of 8 rft. long
1. Cost of bamboo min 3" dia 8 rft. @ Tk. 15.00 Per rft. = Tk. 120.00
2. Driving cost
@ 4'-0" below G.L. 4 rft. @ Tk. 6.13 Per rft. = Tk. 24.52
3. Local carriage and sundries L.S. = Tk. 7.35
Total = Tk. 151.87
Profit 10.00% = Tk. 15.19
Overhead 3.50% = Tk. 5.32
= Tk. 172.38
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10.03
Grand total = Tk. 182.41
Rate per rft. = Tk. 22.80
Rate per rm. = Tk. 74.81

Say, Tk. 75 .00 Per rm.

Item No.- 02.4


Supplying and driving wooden ballah in Palisading
Considering 20 rft. of work
(a) Cost of ballah in/c carriage 20 rft. @ Tk. 120.00 Per rft. = Tk. 2,400.00
(b) Labour for driving
(i) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(ii) Ordinary labour 3 Nos. @ Tk. 245.00 each = Tk. 735.00
(c) Sundries, removing of skin, sizing and coaltaring
Analysis of PWD SoR 2014 for Civil Works 64

in/c hire charge of monkey with driving arranement. L.S. = Tk. 183.75
Total = Tk. 3,621.75
Profit 10.00% = Tk. 362.18
Overhead 3.50% = Tk. 126.76
= Tk. 4,110.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 239.25
Grand total = Tk. 4,349.94
Rate per rft. = Tk. 217.50
Rate per rm. = Tk. 713.62

Say, Tk. 714 .00 Per rm.

Item No.- 02.5


Palisading work with drum sheet excluding cost of vertical post
Considering 30'-0" x 5'-0"= 150 sft. of work
1. Half split borrak bamboo runner @ maximum 1'-6" c/c
horizontally, minimum 4 Nos.
0.50 x 4.00 x 30.00= 60 rft. @ Tk. 15.00 Per rft. = Tk. 900.00
2. Bitumen drum sheet: '@ 3.14 x 2 x 3
=18.84 sft. per drum 12 Nos. @ Tk. 318.00 each = Tk. 3,816.00
3. Nails, gozzal & wire etc. 5.00 kg. @ Tk. 73.04 Per kg. = Tk. 365.20
4. Labour for cutting and straightening drum sheet, placing and fixing
the same with bamboo post and runner etc. complete.
(a) Skilled labour 2.00 Nos. @ Tk. 303.00 each = Tk. 606.00
(b) Ordinary labour 3.00 Nos. @ Tk. 245.00 each = Tk. 735.00
5. Local carriage L.S. = Tk. 490.00
Total = Tk. 6,912.20
Profit 10.00% = Tk. 691.22
Overhead 3.50% = Tk. 241.93
= Tk. 7,845.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 456.61
Grand total = Tk. 8,301.96
Rate per sft. = Tk. 55.35
Rate per sqm. = Tk. 595.79

Say, Tk. 596 .00 Per sqm.

Item No.- 02.6


Supplying and fitting-fixing horizontal bracing in Palisading with split wooden ballah.
Considering 20 rft. of work
(a) Cost for 1/2 split ballah in/c carriage 20 rft. @ Tk. 60.00 Per rft. = Tk. 1,200.00
(b) Labour for fitting-fixing including spliting
(i) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(ii) Ordinary labour 0.25 Nos. @ Tk. 245.00 each = Tk. 61.25
(c) Gajals, Nails and wires etc. L.S. = Tk. 29.87
Total = Tk. 1,366.87
Profit 10.00% = Tk. 136.69
Overhead 3.50% = Tk. 47.84
= Tk. 1,551.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 90.29
Grand total = Tk. 1,641.69
Rate per rft. = Tk. 82.08
Rate per rm. = Tk. 269.30

Say, Tk. 269 .00 Per rm.


Item No.- 02.7.1
Shore protection during earthwork in excavation for foundation: depth up to 1.5 m depth
Analysis of PWD SoR 2014 for Civil Works 65

considering 2 x 22'-0" x 5'-0"= 220.00 sft.


2 x 12'-0" x 5'-0"= 120.00 sft.
340.00 sft. area of palisading

1. Palisading 340.00 sft. @ Tk. 46.08 Per sft. = Tk. 15,667.20


2. Bamboo for driving
2 x 5 x 8'-0"= 80.00 rft.
2 x 1 x 8'-0"= 16.00 rft.
96.00 rft. @ Tk. 18.98 Per rft. = Tk. 1,822.08
3. 1/8" G.I. wire for anchoring:
2 x 2 x 5 x 7'-0"= 140.00 rft.
2 x 2 x 1 x 7'-0"= 28.00 rft.
168.00 rft.
= 3.21 kg @ Tk. 110.00 Per kg = Tk. 353.10
Total = Tk. 17,842.38
Profit 10.00% = Tk. 1,784.24
Overhead 3.50% = Tk. 624.48
Tk. 20,251.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,178.63
Grand total = Tk. 21,429.73
Rate per sft. = Tk. 63.03
Rate per sqm = Tk. 678.45

Say, Tk. 678 .00 Per sqm.

Item No.- 02.7.2


Shore protection during earthwork in excavation for foundation: depth beyond 1.5 m
Considering: 2 x 22'-0" x 8'-0"= 352.00 sft.
2 x 12'-0" x 8'-0"= 192.00 sft.
544.00 sft. Area

1. Palisading 544.00 sft. @ Tk. 46.08 Per sft. = Tk. 25,067.52


2. Ballah driving for anchoring:
2 x 5 x 12'-0"= 120.00 rft.
2 x 1 x 12'-0"= 24.00 rft.
144.00 rft. @ Tk. 120.00 Per rft. = Tk. 17,280.00
3. Ballah post for tieing:
2 x 5 x 5'-0"= 50.00 rft.
2 x 1 x 5'-0"= 10.00 rft.
60.00 rft. @ Tk. 120.00 Per rft. = Tk. 7,200.00
4. 3/8" dia M.S. rod for anchoring ballah post:
2 x 5 x 5'-0"= 50.00 rft.
2 x 1 x 5'-0"= 10.00 rft.
60.00 rft.
= 22.56 Ibs @ Tk. 26.76 Per Ib. = Tk. 603.71
(a) Skilled labour 3 Nos. @ Tk. 303.00 each = Tk. 909.00
(b) Head mason 1 Nos. @ Tk. 493.00 each = Tk. 493.00
6. Plank: 2 x 11 x 4" x 2" x 8'-6" = 10.39 cft.
2 x 5 x 4" x 2" x 8'-6" = 4.72 cft.
= 15.1 cft.
Add wastage 5% 0.8 cft.
15.9 cft. @ Tk. 470.00 Per cft.
Using 6 times = Tk. 1,245.50
7. Ballah for runner
2 x 3 x 22'-0"= 132 rft.
2 x 3 x 12'-0"= 72 rft.
Analysis of PWD SoR 2014 for Civil Works 66

204 rft. @ Tk. 120.00 Per rft.


Using 6 times = Tk. 4,080.00
8. Nails, gazals etc. L.S. 18 kg @ Tk. 73.04 Per kg = Tk. 1,314.72
Sub-total = Tk. 58,193.45
Less salvaged value of ballaha, wooden plank, M.S. rod etc. L.S. = Tk. 7,000.00
Total = Tk. 51,193.45
Profit 10.00% = Tk. 5,119.35
Overhead 3.50% = Tk. 1,791.77
Tk. 58,104.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,381.74
Grand total = Tk. 61,486.31
Rate per sft. = Tk. 113.03
Rate per sqm. = Tk. 1,216.65

Say, Tk. 1,217 .00 Per sqm.

Item No.- 02.8


Supplying and laying minimum 2 mm thick Geo-textile for protection of filled earth
Considering 100 sft. of work
1. Geo-textile in/c 7.5% wastage 107.5 sft. @ Tk. 7.50 Per sft. = Tk. 806.25
2. G.I. Wire, spning etc. L.S. = Tk. 55.00
3. Labour
(a) Skilled labour 1/4 No. @ Tk. 303.00 each = Tk. 75.75
(b) Ordinary labour 1/4 No. @ Tk. 245.00 each = Tk. 61.25
4. Tools and plant, sundries etc. L.S. = Tk. 10.00
Total = Tk. 1,008.25
Profit 10.00% = Tk. 100.83
Overhead 3.50% = Tk. 35.29
Tk. 1,144.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 66.60
Grand total = Tk. 1,210.97
Rate per cft. = Tk. 12.11
Rate per cum. = Tk. 130.35

Say, Tk. 130 .00 Per cum.

Item No.- 02.9


Removing Sludge/semi-liquid clay etc. from the bottom of any type of Marshy land/Lake/Ditch/Pond in/c
mixing fine local sand of Fm. 0.8 to a proportion (1:10) 1 10 ratio
Considering 1000 cft.= 1000.00 100

1. Fine Sand (F.M. 0.8) 100.00 cft. @ Tk. 900.00 Per % cft. = Tk. 900.00
2. Labour for mixing sand and cutting loose sludge
in/c spreading and stacking 12.00 Nos. @ Tk. 245.00 Each = Tk. 2,940.00
3. Labour cutting dried sludge in/c loading,
unloading and truck/cart etc. 7.00 Nos. @ Tk. 245.00 Each = Tk. 1,715.00
4. Hire charge of truck 7.00 Trip @ Tk. 1,300.00 Per trip = Tk. 9,100.00
5. Tools and plant, sundries, incidental etc. L.S. = Tk. 1,327.08
Total = Tk. 15,982.08
Profit 10.00% = Tk. 1,598.21
Overhead 3.50% = Tk. 559.37
Tk. 18,139.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,055.75
Grand total = Tk. 19,195.41
Rate per cft. = Tk. 19.20
Rate per cum. = Tk. 678.05
Analysis of PWD SoR 2014 for Civil Works 67

Say, Tk. 678 .00 Per cum.

Item No.- 02.10.1


Sand filling in foundation and plinth with local sand (F.M. 0.5 to 0.80)
Considering 100 cft. of work
1. Sand (F.M. 0.5 to 0.8) considering additional
30% for compaction 130 cft. @ Tk. 900.00 Per % cft. = Tk. 1,170.00
2. Head mason 1/8 No. @ Tk. 493.00 each = Tk. 61.63
3. Labour for levelling,
compacting, watering etc. 2/3 No. @ Tk. 245.00 each = Tk. 163.33
4. Sundries, T & P etc. L.S. = Tk. 24.50
Total = Tk. 1,419.46
Profit 10.00% = Tk. 141.95
Overhead 3.50% = Tk. 49.68
Tk. 1,611.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 93.77
Grand total = Tk. 1,704.86
Rate per cft. = Tk. 17.05
Rate per cum. = Tk. 602.12

Say, Tk. 602 .00 Per cum.


Item No.- 02.10.2
Sand filling in foundation and plinth with local sand (F.M. 1.2)
Considering 100 cft. of work
1. Sand (F.M. 1.2) considering additional
30% for compaction 130 cft. @ Tk. 1,700.00 Per % cft. = Tk. 2,210.00
2. Head mason 1/8 No. @ Tk. 493.00 each = Tk. 61.63
3. Labour for levelling,
compacting, watering etc. 2/3 No. @ Tk. 245.00 each = Tk. 163.33
4. Sundries, T & P etc. L.S. = Tk. 24.50
Total = Tk. 2,459.46
Profit 10.00% = Tk. 245.95
Overhead 3.50% = Tk. 86.08
Tk. 2,791.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 162.47
Grand total = Tk. 2,953.96
Rate per cft. = Tk. 29.54
Rate per cum. = Tk. 1,043.21

Say, Tk. 1,043 .00 Per cum.


Item No.- 02.10.3
Sand filling in foundation and plinth with local sand (F.M. 2.2)
Considering 100 cft. of work
1. Sand (F.M. 2.2) considering additional
30% for compaction 130 cft. @ Tk. 3,000.00 Per % cft. = Tk. 3,900.00
2. Head Mason 1/8 No. @ Tk. 493.00 each = Tk. 61.63
3. Labour for levelling, compacting etc.
watering etc. 2/3 No. @ Tk. 245.00 each = Tk. 163.33
4. Sundries, T & P etc. L.S. = Tk. 24.50
Total = Tk. 4,149.46
Profit 10.00% = Tk. 414.95
Overhead 3.50% = Tk. 145.23
Tk. 4,709.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 274.11
Grand total = Tk. 4,983.75
Rate per cft. = Tk. 49.84
Rate per cum. = Tk. 1,760.10
Analysis of PWD SoR 2014 for Civil Works 68

Say, Tk. 1,760 .00 Per cum.

Item No.- 02.11


Khoa consolidation (2:1) in foundation trenches or floor: 50 mm down well graded brick-chips and sand
(F.M. 1.2)
Considering 100 cft. of work (loose volume 135 cft)
1. Picked jhama or 1st class
bricks for 90 cft. khoa 765 Nos. @ Tk. 7,500.00 Per % 0Nos. = Tk. 5,737.50
2. Breaking 50mm down well graded chips 90 cft. @ Tk. 719.00 Per % cft. = Tk. 647.10
3. Sand (F.M. 1.2) 45 cft. @ Tk. 1,700.00 Per % cft. = Tk. 765.00
4. Labour for mixing, spreading, levelling, compacting, watering etc.
(a) Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
(b) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
(c) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
5. Local carriage, T & P, sundries etc. L.S. = Tk. 73.50
Total = Tk. 8,610.85
Profit 10.00% = Tk. 861.09
Overhead 3.50% = Tk. 301.38
Tk. 9,773.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 568.82
Grand total = Tk. 10,342.14
Rate per cft. = Tk. 103.42
Rate per cum. = Tk. 3,652.28

Say, Tk. 3,652 .00 Per cum

Item No.- 02.12


Khoa consolidation in foundation trenches or floor with cement : sand (F.M. 1.2): brick-chips = 1 : 6: 12 using mixer machine
Considering 100 cft. of work (loose volume 135 cft)
1. Picked jhama or 1st class
bricks for 90 cft. khoa 765 Nos. @ Tk. 7,500.00 Per % 0Nos. = Tk. 5,737.50
2. Breaking 50mm down well graded chips 90 cft. @ Tk. 719.00 Per % cft. = Tk. 647.10
3. Sand (F.M. 1.2) 45 cft. @ Tk. 1,700.00 Per % cft. = Tk. 765.00
4. Cement 5.5 bag @ Tk. 440.00 Per bag = Tk. 2,420.00
4. Cost for mixing, spreading,
levelling, compacting, watering etc. 100 cft. @ Tk. 950.46 Per % cft. = Tk. 950.46
5. Local carriage, T & P, sundries etc. L.S. = Tk. 108.21
Total = Tk. 10,628.27
Profit 10.00% = Tk. 1,062.83
Overhead 3.50% = Tk. 371.99
Tk. 12,063.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 702.08
Grand total = Tk. 12,765.17
Rate per cft. = Tk. 127.65
Rate per cum. = Tk. 4,507.96

Say, Tk. 4,508 .00 Per cum


Analysis of PWD SoR 2014 for Civil Works 69

Item No.- 02.13


Earth filling in foundation trenches and plinth (earth available at site)
Considering 1000 cft. of work
1. Labour for filling
including local carriage 8 Nos. @ Tk. 245.00 each = Tk. 1,960.00
3. Skilled labour for dressing
& consolidation 2 Nos. @ Tk. 303.00 each = Tk. 606.00
4. Sundries, T & P etc. L.S. = Tk. 122.50
Total = Tk. 2,688.50
Profit 10.00% = Tk. 268.85
Overhead 3.50% = Tk. 94.10
Tk. 3,051.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 177.60
Grand total = Tk. 3,229.05
Rate per cft. = Tk. 3.23
Rate per cum. = Tk. 114.07

Say, Tk. 114 .00 Per cum.

Item No.- 02.14


Carriage of excavated earth from the construction site by truck or any other means
to the selected government land within metropolitan area
Break-up for 1000 cft = 1150 cft loose earth
1. Ordinary labour for cutting,
loading and unloading 7 No. @ Tk. 245.00 each = Tk. 1,715.00
2. Skilled labour 1.5 No. @ Tk. 303.00 each = Tk. 454.50
3. Truck fare 6 trips @ Tk. 1,300.00 trip = Tk. 7,800.00
4. Ordinary labour for local carriage,
leveling and dressing etc. 3 No. @ Tk. 245.00 each = Tk. 735.00
5. Tools and plant, sundries etc. LS = Tk. 61.25
Total = Tk. 10,765.75
Profit 10.00% = Tk. 1,076.58
Overhead 3.50% = Tk. 376.80
= Tk. 12,219.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 711.17
Grand total = Tk. 12,930.30
Rate per cft. = Tk. 12.93
Rate per cum. = Tk. 456.62

Say Tk. 457 .00 per cum.

Item No.- 02.15.1


Earth filling in foundation trenches with carted earth carried by truck or any other means
Considering 1000 cft. of work in/c compacting, dressing and local carriage
For Dhaka Metropolitan Area
Loose earth required in/c 15% shrinkage = 1,150.00 cft.
1. Royalty for earth 1150 cft. @ Tk. 700.00 Per % 0 cft. = Tk. 805.00
2 Truck hire charge including cost of labour for loading6and unloading
Trucks @ Tk. 1,300.00 Per truck = Tk. 7,800.00
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 6 Nos. @ Tk. 245.00 each = Tk. 1,470.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
4 Sundries, T & P etc. L.S. = Tk. 73.50
Total = Tk. 10,451.50
Profit 10.00% = Tk. 1,045.15
Overhead 3.50% = Tk. 365.80
Tk. 11,862.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 690.41
Analysis of PWD SoR 2014 for Civil Works 70

Grand total = Tk. 12,552.86


Rate per cft. = Tk. 12.55
Rate per cum. = Tk. 443.20

Say, Tk. 443 .00 Per cum.


Item No.- 02.15.2
Earth filling in foundation trenches with carted earth carried by truck or any other means
Considering 1000 cft. of work in/c compacting, dressing and local carriage
For Chittagong / Sylhet/ Narayanganj Area
Loose earth required in/c 15% shrinkage = 1,150.00 cft.
1. Royalty for earth 1150 cft. @ Tk. 700.00 Per % 0 cft. = Tk. 805.00
2 Truck hire charge including cost of labour for loading6and unloading
Trips @ Tk. 1,000.00 Per trip = Tk. 6,000.00
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 6 Nos. @ Tk. 245.00 each = Tk. 1,470.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
4 Sundries, T & P etc. L.S. = Tk. 73.50
Total = Tk. 8,651.50
Profit 10.00% = Tk. 865.15
Overhead 3.50% = Tk. 302.80
Tk. 9,819.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 571.50
Grand total = Tk. 10,390.95
Rate per cft. = Tk. 10.39
Rate per cum. = Tk. 366.92

Say, Tk. 367 .00 Per cum.

Item No.- 02.15.3


Earth filling in foundation trenches with carted earth carried by truck or any other means
Considering 1000 cft. of work in/c conmpacting, dressing and local carriage
For Rajshahi / Barishal / Khulna metropolitan area
Loose earth required in/c 15% shrinkage = 1,150.00 cft.
1. Royalty for earth 1150 cft. @ Tk. 700.00 Per % 0 cft. = Tk. 805.00
3. Truck hire charge including cost of labour for loading6and unloading
Trips @ Tk. 850.00 Per trips = Tk. 5,100.00
4. Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 6 Nos. @ Tk. 245.00 each = Tk. 1,470.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
5. Sundries, T & P etc. L.S. = Tk. 73.50
Total = Tk. 7,751.50
Profit 10.00% = Tk. 775.15
Overhead 3.50% = Tk. 271.30
Tk. 8,797.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 512.05
Grand total = Tk. 9,310.00
Rate per cft. = Tk. 9.31
Rate per cum. = Tk. 328.78

Say, Tk. 329 .00 Per cum.

Item No.- 02.15.4


Earth filling in foundation trenches with carted earth carried by truck or any other means
Considering 1000 cft. of work in/c compacting, dressing and local carriage
(d) For other than Dhaka, Ctg., Sylhet, Rajshahi, Barishal, Khulna metropolitan area and N'ganj district
Loose earth required in/c 15% shrinkage = 1,150.00 cft.
1. Royalty for earth 1150 cft. @ Tk. 700.00 Per % 0 cft. = Tk. 805.00
2 Truck hire charge including cost of labour for loading6and unloading
Trucks @ Tk. 700.00 Per truck = Tk. 4,200.00
3 Labour for local carriage, levelling & compacting etc. complete:
Analysis of PWD SoR 2014 for Civil Works 71

(a) Ordinary labour 6 Nos. @ Tk. 245.00 each = Tk. 1,470.00


(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
4 Sundries, T & P etc. L.S. = Tk. 73.50
Total = Tk. 6,851.50
Profit 10.00% = Tk. 685.15
Overhead 3.50% = Tk. 239.80
Tk. 7,776.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 452.60
Grand total = Tk. 8,229.05
Rate per cft. = Tk. 8.23
Rate per cum. = Tk. 290.64

Say, Tk. 291 .00 Per cum.


Item No.- 02.16.1 For Dhaka Metropolitan Area
Item No.- 02.16.1.1
Site development / improvement by other than dredging
Considering 1000 cft. of work in/c dressing and local carriage 1000 cft
wastage, no shrinkage as it is coming & placing in saturated saturated15%
condition
wastage 1,150.00 cft.
1. Royalty for dredge material 1,150.00 cft. @ Tk. 700.00 Per % 0 cft. = Tk. 805.00
2 Carriage of earth including cost of labour for loading
1150
and unloadingcft. @ Tk. 7.76 cft. = Tk. 8,924.00
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
4 Sundries, T & P etc. L.S. = Tk. 82.68
Total = Tk. 10,417.68
Profit 10.00% = Tk. 1,041.77
Overhead 3.50% = Tk. 364.62
Tk. 11,824.07
Add VAT with adjustment factor 1.0582 5.50% = Tk. 688.17
Grand total = Tk. 12,512.24
Rate per cft. = Tk. 12.51
Rate per cum. = Tk. 441.73

Say, Tk. 441 .73 Per cum.

Item No.- 02.16.1.2


Site development / improvement by deredging
Considering 1000 cft. of work in/c dressing and local carriage 1000
wastage, no shrinkage as it is coming & placing in saturated saturated
0.50%condition
= 1,005.00 cft.
1. Royalty for dredge material 1,005.00 cft. @ Tk. 650.00 Per % 0 cft. = Tk. 653.25
2 Carriage of earth including cost of labour for loading
1150
and unloadingcft. @ Tk. 4.75 cft. = Tk. 5,462.50
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 0.25 Nos. @ Tk. 245.00 each = Tk. 61.25
4 Sundries, T & P etc. L.S. = Tk. 73.50
Total = Tk. 6,250.50
Profit 10.00% = Tk. 625.05
Overhead 3.50% = Tk. 218.77
Tk. 7,094.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 412.90
Grand total = Tk. 7,507.22
Rate per cft. = Tk. 7.51
Rate per cum. = Tk. 265.22

Say, Tk. 265 .00 Per cum.


Analysis of PWD SoR 2014 for Civil Works 72

Item No.- 02.16.2 For Chittagong / Sylhet/ Narayanganj Area


Item No.- 02.16.2.1
Site development / improvement by other than dredging
Considering 1000 cft. of work in/c consolidation, dressing and local carriage 1000
wastage, no shrinkage as it is coming & placing in saturated saturated
15.00%condition
= 1,150.00 cft.
1. Royalty for earth 1,150.00 cft. @ Tk. 700.00 Per % 0 cft. = Tk. 805.00
2 Carriage of earth including cost of labour for loading
1,150.00
and unloadingcft. @ Tk. 5.22 cft. = Tk. 5,246.10
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
4 Sundries, T & P etc. L.S. = Tk. 45.00
Total = Tk. 6,702.10
Profit 10.00% = Tk. 670.21
Overhead 3.50% = Tk. 234.57
Tk. 7,606.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 442.73
Grand total = Tk. 8,049.61
Rate per cft. = Tk. 8.05
Rate per cum. = Tk. 284.25

Say, Tk. 284 .25 Per cum.


Item No.- 02.16.2.2
Site development / improvement by deredging.
Considering 1000 cft. of work in/c consolidation, dressing and local carriage 1000
wastage, no shrinkage as it is coming & placing in saturated saturated
0.50%condition
= 1,005.00 cft.
1. Royalty for earth 1,005.00 cft. @ Tk. 650.00 Per % 0 cft. = Tk. 653.25
2 Carriage of earth including cost of labour for loading
1,005.00
and unloadingcft. @ Tk. 3.65 cft. = Tk. 3,668.25
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 0.25 Nos. @ Tk. 245.00 each = Tk. 61.25
4 Sundries, T & P etc. L.S. = Tk. 45.00
Total = Tk. 4,427.75
Profit 10.00% = Tk. 442.78
Overhead 3.50% = Tk. 154.97
Tk. 5,025.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 292.49
Grand total = Tk. 5,317.99
Rate per cft. = Tk. 5.32
Rate per cum. = Tk. 187.88

Say, Tk. 188 .00 Per cum.


Item No.- 02.16.3 For Rajshahi / Barishal / Khulna metropolitan area
Item No.- 02.16.3.1
Site development / improvement by other than dredging.
Considering 1000 cft. of work in/c dressing and local carriage 1000
wastage, no shrinkage as it is coming & placing in saturated saturated
15.00%condition
= 1,150.00 cft.
1. Royalty for earth 1,150.00 cft. @ Tk. 700.00 Per % 0 cft. = Tk. 805.00
2 Carriage of earth including cost of labour for loading
1,150.00
and unloadingcft. @ Tk. 4.43 cft. = Tk. 4,452.15
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
4 Sundries, T & P etc. L.S. = Tk. 45.00
Total = Tk. 5,908.15
Profit 10.00% = Tk. 590.82
Overhead 3.50% = Tk. 206.79
Tk. 6,705.76
Add VAT with adjustment factor 1.0582 5.50% = Tk. 390.28
Grand total = Tk. 7,096.04
Rate per cft. = Tk. 7.10
Rate per cum. = Tk. 250.70
Analysis of PWD SoR 2014 for Civil Works 73

Say, Tk. 250 .70 Per cum.


Item No.- 02.16.3.2
Site development / improvement by deredging.
Considering 1000 cft. of work in/c dressing and local carriage 1000
wastage, no shrinkage as it is coming & placing in saturated saturated
0.50%condition
= 1,005.00 cft.
1. Royalty for earth 1,005.00 cft. @ Tk. 650.00 Per % 0 cft. = Tk. 653.25
2 Carriage of earth including cost of labour for loading
1,005.00
and unloadingcft. @ Tk. 3.10 cft. = Tk. 3,115.50
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 0.25 Nos. @ Tk. 245.00 each = Tk. 61.25
4 Sundries, T & P etc. L.S. = Tk. 45.00
Total = Tk. 3,875.00
Profit 10.00% = Tk. 387.50
Overhead 3.50% = Tk. 135.63
Tk. 4,398.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 255.98
Grand total = Tk. 4,654.11
Rate per cft. = Tk. 4.65
Rate per cum. = Tk. 164.21

Say, Tk. 164 .00 Per cum.

Item No.- 02.16.4 For other than Dhaka, Ctg., Sylhet, Rajshahi, Barishal, Khulna metropolitan area and N'ganj district

Site development / improvement by other than dredging.


Considering 1000 cft. of work in/c consolidation, dressing and local carriage 1000
wastage, no shrinkage as it is coming & placing in saturated saturated
15.00%condition
= 1,150.00 cft.
1. Royalty for earth 1,150.00 cft. @ Tk. 700.00 Per % 0 cft. = Tk. 805.00
2 Carriage of earth including cost of labour for loading
1,150.00
and unloadingcft. @ Tk. 3.65 cft. = Tk. 3,668.25
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
4 Sundries, T & P etc. L.S. = Tk. 45.00
Total = Tk. 5,124.25
Profit 10.00% = Tk. 512.43
Overhead 3.50% = Tk. 179.35
Tk. 5,816.03
Add VAT with adjustment factor 1.0582 5.50% = Tk. 338.50
Grand total = Tk. 6,154.53
Rate per cft. = Tk. 6.15
Rate per cum. = Tk. 217.16

Say, Tk. 217 .16 Per cum.


Item No.- 02.16.4.2
Site development / improvement by deredging.
Considering 1000 cft. of work in/c consolidation, dressing and local carriage 1000
wastage, no shrinkage as it is coming & placing in saturated saturated
0.50%condition
= 1,005.00 cft.
1. Royalty for earth 1,005.00 cft. @ Tk. 650.00 Per % 0 cft. = Tk. 653.25
2 Carriage of earth including cost of labour for loading
1,005.00
and unloadingcft. @ Tk. 2.56 cft. = Tk. 2,572.80
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 0.25 Nos. @ Tk. 150.00 each = Tk. 37.50
4 Sundries, T & P etc. L.S. = Tk. 45.00
Total = Tk. 3,308.55
Profit 10.00% = Tk. 330.86
Overhead 3.50% = Tk. 115.80
Tk. 3,755.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 218.56
Grand total = Tk. 3,973.77
Analysis of PWD SoR 2014 for Civil Works 74

Rate per cft. = Tk. 3.97


Rate per cum. = Tk. 140.20

Say, Tk. 140 .00 Per cum.

Item No.- 02.17


Mechanical compaction of sand in 150 mm layers including leveling, watering and consolidation
each layer with chain dozer, grader up to finished level
1. For 100 cft. Work
(a) Labour for leveling,
compaction, watering 1/6 Nos. @ Tk. 303.00 each = Tk. 50.50
(b) Local carriage: Ordinary Labour 2.00 Nos. @ Tk. 245.00 each = Tk. 490.00
(c) Tools and plant, sundries etc. L.S. = Tk. 20.42
Tk. 560.92
2. Mechanical compaction: 7500 cft per day by one chain dozer
(a) Hire charge of chain dozer 1 day @ Tk. 12,774.45 Per day = Tk. 12,774.45
(b) Fuel
(i) Diesel: @ 16 liter/hour 128.00 liter @ Tk. 53.11 Per liter = Tk. 6,798.08
(ii) Mintenance in/c lubricant and incidental expenditure L.S. = Tk. 200.00
Tk. 19,772.53
Cost for 100 cft. incuding considering 10% break-down etc. = Tk. 290.00
3. Add 3% for (mobilization and demobilization) ransportation cost for chain dozer by trailor = Tk. 8.70
Grand total (1 +2 + 3) = Tk. 859.62
Profit 10.00% = Tk. 85.96
Overhead 3.50% = Tk. 30.09
= Tk. 975.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 56.78
Grand total = Tk. 1,032.45
Rate per cft. = Tk. 10.32
Rate per cum. = Tk. 364.45

Say Tk. 364 .00 per cum.


Analysis of PWD SoR 2014 for Civil Works 75

DIVISION 03 : BRICK SOLING, CC, DPC ETC.

Item No.- 03.1


One layer brick flat soling in foundation or in floor.
Considering 100 sft of work
1. Bricks 300 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 2,250.00
2. Fine sand 5 cft. @ Tk. 900.00 Per % cft. = Tk. 45.00
3. Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
4. Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
5. Local carriage, sundries, T & P etc. L.S. = Tk. 49.00
Total = Tk. 2,744.25
Profit 10.00% = Tk. 274.43
Overhead 3.50% = Tk. 96.05
Tk. 3,114.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 181.28
Grand total = Tk. 3,296.01
Rate per sft. = Tk. 32.96
Rate per sqm. = Tk. 354.78

Say, Tk. 355 .00 Per sqm.


Item No.- 03.2
One layer herrring bone bond soling in foundation or in floor.
Considering 100 sft of work
1. Bricks 500 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 3,750.00
2. Fine sand 10 cft. @ Tk. 900.00 Per % cft. = Tk. 90.00
3. Mason 0.33 No. @ Tk. 389.00 each = Tk. 128.37
4. Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
5. Local carriage, sundries, T & P etc. L.S. = Tk. 73.50
Total = Tk. 4,344.87
Profit 10.00% = Tk. 434.49
Overhead 3.50% = Tk. 152.07
Tk. 4,931.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 287.01
Grand total = Tk. 5,218.44
Rate per sft. = Tk. 52.18
Rate per sqm. = Tk. 561.67

Say, Tk. 562 .00 Per sqm.


Item No.- 03.3
Brick on end edging
Considering 100 rft of work
1. Bricks 250 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 1,875.00
2. Fine sand 2 cft. @ Tk. 900.00 Per % cft. = Tk. 18.00
3. Mason 0.2 No. @ Tk. 389.00 each = Tk. 77.80
4. Skilled labour 0.75 No. @ Tk. 303.00 each = Tk. 227.25
5. Local carriage, sundries, T & P etc. L.S. = Tk. 36.75
Total = Tk. 2,234.80
Profit 10.00% = Tk. 223.48
Overhead 3.50% = Tk. 78.22
Tk. 2,536.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 147.63
Grand total = Tk. 2,684.13
Rate per rft. = Tk. 26.84
Rate per rm. = Tk. 88.06

Say, Tk. 88 .00 Per rm.


Item No.- 03.4.1
Analysis of PWD SoR 2014 for Civil Works 76

Mass concrete in foundation (1:3:6) with brick chips & 100% local sand of F.M. 1.2
Considering 100 cft. of work
1. Cost of concrete 100 cft. @ Tk. 13,272.10 Per % cft. = Tk. 13,272.10
2. Laying / placing concrete 100 cft. @ Tk. 950.46 Per % cft. = Tk. 950.46
3. Curing for 7 days L.S. = Tk. 102.08
4. Extra cost of wood for side shutter: for 100 cft
2 x 60'-0" x 4" x 1"= 3.33 cft.
2 x 5'-0" x 4" x 1"= 0.28 cft.
10 x 6" x 2" x 1" = 0.07 cft.
3.68 cft.
Add 5% wastage 0.18 cft.
3.86 cft. @ Tk. 470.00 Per cft.
Using 6 times = Tk. 302.37
5. Labour for side shutter
2 x 40'-0" x 6" = 40.00 sft.
2 x 5' - 0" x 6" = 5.00 sft.
45.00 sft. @ Tk. 6.00 Per sft. = Tk. 270.00
Total = Tk. 14,897.01
Profit 10.00% = Tk. 1,489.70
Overhead 3.50% = Tk. 521.40
Tk. 16,908.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 984.07
Grand total = Tk. 17,892.18
Rate per cft. = Tk. 178.92
Rate per cum. = Tk. 6,318.56

Say, Tk. 6,319 .00 Per cum.

Item No.- 03.4.2


Mass concrete in floor (1:3:6) with brick chips & 100% local sand of F.M. 1.2
Considering 100 cft. of work
1. Cost of concrete 100 cft. @ Tk. 13,272.10 Per % cft. = Tk. 13,272.10
2. Laying / placing concrete 100 cft. @ Tk. 950.46 Per % cft. = Tk. 950.46
3. Extra Mason for floor finish 1 No. @ Tk. 389.00 each = Tk. 389.00
4. Curing for 7 days L.S. = Tk. 102.08
Total = Tk. 14,713.64
Profit 10.00% = Tk. 1,471.36
Overhead 3.50% = Tk. 514.98
Tk. 16,699.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 971.96
Tk. 17,671.94
Rate per cft. = Tk. 176.72
Rate per cum. = Tk. 6,240.87

Say, Tk. 6,241 .00 Per cum.

Item No.- 03.5.1


Mass concrete in foundation (1:2:4) with brick chips & 100% local sand of F.M. 1.2
Considering 100 cft. of work
1. Cost of concrete 100 cft. @ Tk. 16,012.10 Per % cft. = Tk. 16,012.10
2. Laying / placing concrete 100 cft. @ Tk. 950.46 Per % cft. = Tk. 950.46
3. Curing for 7 days L.S. = Tk. 102.08
4. Extra cost of wood for side shutter: for 100 cft
2 x 60'-0" x 4" x 1"= 3.33 cft.
2 x 5'-0" x 4" x 1"= 0.28 cft.
10 x 6" x 2" x 1" = 0.07 cft.
3.68 cft.
Analysis of PWD SoR 2014 for Civil Works 77

Add 5% wastage 0.18 cft.


3.86 cft. @ Tk. 470.00 Per cft.
Using 6 times = Tk. 302.37
5. Labour for side shutter
2 x 40'-0" x 6" = 40.00 sft.
2 x 5' - 0" x 6" = 5.00 sft.
45.00 sft. @ Tk. 6.00 Per sft. = Tk. 270.00
Total = Tk. 17,637.01
Profit 10.00% = Tk. 1,763.70
Overhead 3.50% = Tk. 617.30
Tk. 20,018.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,165.07
Grand total = Tk. 21,183.08
Rate per cft. = Tk. 211.83
Rate per cum. = Tk. 7,480.78

Say, Tk. 7,481 .00 Per cum.


Item No.- 03.5.2
Mass concrete in floor (1:2:4) with brick chips & 100% local sand of F.M. 1.2
Considering 100 cft. of work
1. Cost of concrete 100 cft. @ Tk. 16,012.10 Per % cft. = Tk. 16,012.10
2. Laying / placing concrete 100 cft. @ Tk. 950.46 Per % cft. = Tk. 950.46
3. Extra Mason for floor finish 1 No. @ Tk. 389.00 each = Tk. 389.00
4. Curing for 7 days L.S. = Tk. 102.08
Total = Tk. 17,453.64
Profit 10.00% = Tk. 1,745.36
Overhead 3.50% = Tk. 610.88
Tk. 19,809.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,152.95
Tk. 20,962.83
Rate per cft. = Tk. 209.63
Rate per cum. = Tk. 7,403.08

Say, Tk. 7,403 .00 Per cum.


Item No.- 03.6.1
(i) 75 mm or 3" thick damp proof course (1:1.5:3) with 50% Sylhet sand (F.M. 2.5) & 50%
local sand (F.M. 1.2) and 1/2 " down brick chips
Considering 100 cft. of work (covering 400 sft. area)
1. Cost for concrete:
(a) Bricks for chips 706 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 5,295.00
(b) Sand (F.M. 2.5) 20.75 cft. @ Tk. 3,000.00 Per % cft. = Tk. 622.50
(c) Sand (F.M 1.2) 20.75 cft. @ Tk. 1,700.00 Per % cft. = Tk. 352.75
(d) Cement 22 bags @ Tk. 440.00 Per bag. = Tk. 9,680.00
(e) Breaking chips in/c screening 83 cft. @ Tk. 1,091.88 Per % cft. = Tk. 906.26
(f) Curing L.S. = Tk. 122.50
(g) Mixture machine, pump, local carriage, sundries, T & P etc. L.S. = Tk. 404.25
Total = Tk. 17,383.26
Cost for 100 sft. = Tk. 4,345.82
2. Labour for casting 100 sft.
(i) Head mason 0.50 No. @ Tk. 493.00 each = Tk. 246.50
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary labour 3 Nos. @ Tk. 245.00 each = Tk. 735.00
(ix) Bitumenous coating 100 sft. @ Tk. 822.00 Per % sft. = Tk. 822.00
3. Cost of wood for side shutter (considering 10" width & 120 rft long wall):
2 x 120'-0" x 3" x 1"= 5.00 cft.
25 x 1'-3" x 1.5" x 1"= 0.33 cft.
2 x 25 x 1'-0" x 2" x 1"= 0.69 cft.
Analysis of PWD SoR 2014 for Civil Works 78

6.02 cft.
Add 5% wastage 0.30 cft.
= 6.32 cft. @ Tk. 470.00 Per cft.
Using 6 times = Tk. 495.07
4. Labour for side shutter:
2 x 120'-0" x 3" = 60.00 sft. @ Tk. 12.00 Per sft. = Tk. 720.00
Total = Tk. 7,753.39
Profit 10.00% = Tk. 775.34
Overhead 3.50% = Tk. 271.37
Tk. 8,800.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 512.17
Grand total = Tk. 9,312.27
Rate per sft. = Tk. 93.12
Rate per sqm. = Tk. 1,002.34

Say, Tk. 1,002 .00 Per sqm.

Item No.- 03.6.2


(ii) 75 mm or 3" thick damp proof course (1:1.5:3) with Sylhet sand (F.M. 2.3) and 1/2 " down stone chips
Considering 100 cft. of work (covering 400 sft. area)
1. Cost for concrete:
(i) Crushed stone chips 83 cft. @ Tk. 13,500.00 Per % cft. = Tk. 11,205.00
(ii) Sand (F.M. 2.3) 41.5 cft. @ Tk. 3,000.00 Per % cft. = Tk. 1,245.00
(iii) Cement 22 bags @ Tk. 440.00 Per bag. = Tk. 9,680.00
(iv) Curing. L.S. = Tk. 122.50
(v) Mixture machine, pump, local carriage, sundries, T & P etc. L.S. = Tk. 404.25
Total = Tk. 22,656.75
Cost for 100 sft. = Tk. 5,664.19
2. Labour for casting 100 sft.
(i) Head mason 0.50 No. @ Tk. 493.00 each = Tk. 246.50
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary labour 3 Nos. @ Tk. 245.00 each = Tk. 735.00
(iv) Bitumenous coating 100 sft. @ Tk. 822.00 Per % sft. = Tk. 822.00
3. Cost of wood for side shutter (considering 10" width & 120 rft long wall):
2 x 120'-0" x 3" x 1"= 5.00 cft.
25 x 1'-3" x 2" x 1"= 0.43 cft.
2 x 25 x 1'-0" x 2" x 1"= 0.69 cft.
6.12 cft.
Add 5% wastage 0.31 cft.
= 6.43 cft. @ Tk. 470.00
Using 6 times = Tk. 503.68
4. Labour for side shutter:
2 x 120'-0" x 3" = 60.00 sft. @ Tk. 12.00 Per sft. = Tk. 720.00
Total = Tk. 9,080.37
Profit 10.00% = Tk. 908.04
Overhead 3.50% = Tk. 317.81
Tk. 10,306.22
Add VAT with adjustment factor 1.0582 5.50% = Tk. 599.83
Grand total = Tk. 10,906.05
Rate per sft. = Tk. 109.06
Rate per sqm. = Tk. 1,173.92

Say, Tk. 1,174 .00 Per sqm.


Item No.- 03.6.3
(iii) 150 mm or 6" thick damp proof course (1:1.5:3) with Sylhet sand (F.M. 2.3) and 1/2" down stone chips
using water-proofing admixture / agent
Considering 100 cft. of work (covering 400 sft. area)
Analysis of PWD SoR 2014 for Civil Works 79

1. Cost for concrete:


(i) Crushed stone chips 83 cft. @ Tk. 13,500.00 Per % cft. = Tk. 11,205.00
(ii) Sand (F.M. 2.3) 41.5 cft. @ Tk. 3,000.00 Per % cft. = Tk. 1,245.00
(iii) Cement 22 bags @ Tk. 440.00 Per bag. = Tk. 9,680.00
(iv) Water proofing Admixure / agent 4.4 liter @ Tk. 180.00 Per liter = Tk. 792.00
(v) Curing. L.S. = Tk. 122.50
(vi) Mixture machine, pump, local carriage, sundries, T & P etc. L.S. = Tk. 404.25
Total for 100 cft = Tk. 23,448.75
2. Labour for casting 100 cft. @ Tk. 1,900.92 Per % cft. = Tk. 1,900.92
3. Cost of wood for side shutter (considering 10" width & 240 rft long wall):
2 x 240'-0" x 6" x 1"= 20.00 cft.
25 x 1'-3" x 2" x 1"= 0.43 cft.
2 x 25 x 1'-0" x 2" x 1"= 0.69 cft.
21.12 cft.
Add 5% wastage 1.06 cft.
= 22.18 cft. @ Tk. 470.00
Using 6 times = Tk. 1,737.43
4. Labour for side shutter:
2 x 240'-0" x 6" = 240.00 sft. @ Tk. 12.00 Per sft. = Tk. 2,880.00
Total = Tk. 29,967.10
Profit 10.00% = Tk. 2,996.71
Overhead 3.50% = Tk. 1,048.85
Tk. 34,012.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,979.57
Grand total = Tk. 35,992.23
Rate per cft. = Tk. 359.92
Rate per cum = Tk. 12,710.57

Say, Tk. 12,711 .00 Per cum.

Item No.- 03.7


Supplying and laying polythene sheet
Considering 216 sft. of work
Assuming 2 Nos. 9'-0" x 12'-0" pieces with 6" over lap to cover 216 sft.
Extra length required:
2 x 9'-0" = 18 rft.
2 x 12'-0" = 24 rft.
42 rft.
1. Cost of polythene sheet:
2 x 9'-0" x 12'-0" = 216 sft.
Lap: 42 x 0'-6" = 21 sft.
= 237 sft. @ Tk. 207.00 Per % sft = Tk. 490.59
2. Skilled labour for laying polythene: 1/4 No. @ Tk. 303.00 each = Tk. 75.75
Total = Tk. 566.34
Profit 10.00% = Tk. 56.63
Overhead 3.50% = Tk. 19.82
= Tk. 642.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 37.41
Grand total = Tk. 680.20
Rate per sft. = Tk. 3.15
Rate per sqm. = Tk. 33.91
Say, Tk. 34 .00 Per sqm.

DIVISION 04 : BRICKWORKS, PATENT STONEF IN FLOOR AND FANCY SCREEN BLOCK WORKS

Item No.- 04.1


Brick work with first class bricks in foundation (1:6)
Considering 100 cft. work
Analysis of PWD SoR 2014 for Civil Works 80

1. Bricks 1100 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 8,250.00


2. Sand (F.M 1.2) in/c wastage 36 cft. @ Tk. 1,700.00 Per % cft. = Tk. 612.00
3. Cement 4 bags @ Tk. 440.00 Per bag = Tk. 1,760.00
4. Head mason 0.10 No. @ Tk. 493.00 each = Tk. 49.30
5. Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
6. Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
7. Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
8. Labour for soaking &
cleaning bricks 2 Nos. @ Tk. 245.00 each = Tk. 490.00
9. Labour for 7 days curing
@ 1/8 labour per day: 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
10. Local carriage, sundries, T & P etc. ( times of ordinary labour rate) L.S. = Tk. 122.50
Total = Tk. 12,557.68
Profit 10.00% = Tk. 1,255.77
Overhead 3.50% = Tk. 439.52
Tk. 14,252.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 829.54
Grand total = Tk. 15,082.51
Rate per cft. = Tk. 150.83
Rate per cum. = Tk. 5,326.56

Say, Tk. 5,327 .00 Per cum

Item No.- 04.2


Brick work with first class bricks in superstructure (1:6)
Considering 100 cft. of work
1. Materials and labour as per item No. 8 = Tk. 12,557.68
2. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
3. Extra labour for carriage 1 No. @ Tk. 245.00 each = Tk. 245.00
4. Extra labour for 7 days curing 1/4 No. @ Tk. 245.00 each = Tk. 61.25
5. Labour for screening & washing sand 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 13,288.93
Profit 10.00% = Tk. 1,328.89
Overhead 3.50% = Tk. 465.11
Tk. 15,082.93
Add VAT with adjustment factor 1.0582 5.50% = Tk. 877.84
Grand total = Tk. 15,960.77
Rate per cft. = Tk. 159.61

(a) Ground floor Rate per cft. = Tk. 159.61


Rate per cum. = Tk. 5,636.55

Say, Tk. 5,637 .00 Per cum.

Item No.- 04.3


Brickwork with 1st class bricks in superstructure (1:4)
Considering 100 cft. of work
1. Bricks 1100 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 8,250.00
2. Sand (F.M 1.2) in/c wastage 40 cft. @ Tk. 1,700.00 Per % cft. = Tk. 680.00
3. Cement 6 bags @ Tk. 440.00 Per bag = Tk. 2,640.00
4. Head mason 0.10 No. @ Tk. 493.00 each = Tk. 49.30
5. Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
6. Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
7. Ordinary labour 2.5 Nos. @ Tk. 245.00 each = Tk. 612.50
8. Labour for soaking
& cleaning bricks 2 Nos. @ Tk. 245.00 each = Tk. 490.00
9. Screening and washing sand 1 No. @ Tk. 245.00 each = Tk. 245.00
Analysis of PWD SoR 2014 for Civil Works 81

10. Labour for 7 days curing


@ 1/8 labour per day: 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
11. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, sundries, T & P etc. ( times of ordinary labour rate) L.S. = Tk. 122.50
Total = Tk. 14,175.68
Profit 10.00% = Tk. 1,417.57
Overhead 3.50% = Tk. 496.15
Tk. 16,089.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 936.42
Grand total = Tk. 17,025.82
(a) Ground floor Rate per cft. = Tk. 170.26
Rate per cum. = Tk. 6,012.73

Say, Tk. 6,013 .00 Per cum

Item No.- 04.4


Exposed brick work in exterior wall in superstructure (1:4) with special quality (sorted) first class bricks
Considering 100 cft. of work
1. Bricks 1100 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 8,250.00
Extra cost for special quality 1st class bricks
in/c sorting out the bricks @ 20% = Tk. 1,650.00
2. Sand (F.M. 1.2) in/c wastage 40 cft. @ Tk. 1,700.00 Per % cft. = Tk. 680.00
3. Cement in/c pointing 6.5 bags @ Tk. 440.00 Per bag = Tk. 2,860.00
4. Head mason 1/2 No. @ Tk. 493.00 each = Tk. 246.50
5. Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
6. Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
7. Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
8. Labour for soaking &
cleaning bricks 2 Nos. @ Tk. 245.00 each = Tk. 490.00
9. Labour for screening &
washing sand 1 No. @ Tk. 245.00 each = Tk. 245.00
10. Labour for 7 days curing
@ 1/8 labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
11. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, storage & sundries etc. L.S. = Tk. 122.50
Total = Tk. 16,466.38
Profit 10.00% = Tk. 1,646.64
Overhead 3.50% = Tk. 576.32
Tk. 18,689.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,087.74
Grand total = Tk. 19,777.08
(a) Ground floor Rate per cft. = Tk. 197.77
Rate per cum. = Tk. 6,984.25

Say, Tk. 6,984 .00 Per cum

Item No.- 04.5


Exposed brick work in exterior wall in superstructure (1:4) with automatic machine made first class bricks
Considering 100 cft. of work
1. Bricks 1100 Nos. @ Tk. 9,000.00 Per % 0 Nos. = Tk. 9,900.00
2. Sand (F.M. 1.2) in/c wastage 40 cft. @ Tk. 1,700.00 Per % cft. = Tk. 680.00
3. Cement in/c pointing 6.5 bags @ Tk. 440.00 Per bag = Tk. 2,860.00
4. Head mason 1/2 No. @ Tk. 493.00 each = Tk. 246.50
5. Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
6. Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
7. Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
8. Labour for soaking &
Analysis of PWD SoR 2014 for Civil Works 82

cleaning bricks 2 Nos. @ Tk. 245.00 each = Tk. 490.00


9. Labour for screening &
washing sand 1 No. @ Tk. 245.00 each = Tk. 245.00
10. Labour for 7 days curing
@ 1/8 labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
11. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, storage & sundries etc. L.S. = Tk. 122.50
Total = Tk. 16,466.38
Profit 10.00% = Tk. 1,646.64
Overhead 3.50% = Tk. 576.32
Tk. 18,689.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,087.74
Grand total = Tk. 19,777.08
(a) Ground floor Rate per cft. = Tk. 197.77
Rate per cum. = Tk. 6,984.25

Say, Tk. 6,984 .00 Per cum

Item No.- 04.6


Brick work with 10 holes machine made bricks (1:4)
Considering 100 cft. work
1. Bricks 1100 Nos. @ Tk. 17,500.00 Per % 0 Nos. = Tk. 19,250.00
2. Sand (F.M 1.2) in/c wastage 40 cft. @ Tk. 1,700.00 Per % cft. = Tk. 680.00
3. Cement 6.5 bags @ Tk. 440.00 Per bag = Tk. 2,860.00
4. Head mason 0.50 No. @ Tk. 493.00 each = Tk. 246.50
5. Mason 1.5 No. @ Tk. 389.00 each = Tk. 583.50
6. Skilled labour 1.5 No. @ Tk. 303.00 each = Tk. 454.50
7. Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
8. Labour for soaking &
cleaning bricks 2 Nos. @ Tk. 245.00 each = Tk. 490.00
9. Labour for screening and
washing sand 1.00 No. @ Tk. 245.00 each = Tk. 245.00
10. Labour for 7 days curing
@ 1/8 labour per day: 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
11. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, sundries, T & P etc. ( times of ordinary labour rate) L.S. = Tk. 122.50
Total = Tk. 25,816.38
Profit 10.00% = Tk. 2,581.64
Overhead 3.50% = Tk. 903.57
Tk. 29,301.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,705.38
Grand total = Tk. 31,006.97
(a) Ground floor Rate per cft. = Tk. 310.07
Rate per cum. = Tk. 10,950.12

Say, Tk. 10,950 .00 Per cum


Analysis of PWD SoR 2014 for Civil Works 83

Item No.- 04.7


Brick work with 9.5" x 4.5" x 2.75" size machine made solid klinker facing bricks (1:4)
Considering 100 cft. work
1. Bricks 1100 Nos. @ Tk. 13,125.00 Per % 0 Nos. = Tk. 14,437.50
2. Sand (F.M 1.2) in/c wastage 40.0 cft. @ Tk. 1,700.00 Per % cft. = Tk. 680.00
3. Cement 6.5 bags @ Tk. 440.00 Per bag = Tk. 2,860.00
4. Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
5. Mason 2.0 No. @ Tk. 389.00 each = Tk. 778.00
6. Skilled labour 1.5 No. @ Tk. 303.00 each = Tk. 454.50
7. Ordinary labour 2.0 Nos. @ Tk. 245.00 each = Tk. 490.00
8. Labour for soaking
& cleaning bricks 1.0 Nos. @ Tk. 245.00 each = Tk. 245.00
9. Labour for screening and
washing sand 1/2 No. @ Tk. 245.00 each = Tk. 122.50
10. Labour for 7 days curing
@ 1/4 labour per day: 1.75 Nos. @ Tk. 245.00 each = Tk. 428.75
11. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, sundries, T & P etc. ( times of ordinary labour rate) L.S. = Tk. 122.50
Total = Tk. 20,922.00
Profit 10.00% = Tk. 2,092.20
Overhead 3.50% = Tk. 732.27
Tk. 23,746.47
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,382.07
Grand total = Tk. 25,128.54
(a) Ground floor Rate per cft. = Tk. 251.29
Rate per cum. = Tk. 8,874.31

Say, Tk. 8,874 .00 Per cum


Item No.- 04.8
Brick work with 9.5" x 4.5" x 2.75" size 10 hole machine made rock-face/textured klinker
facing bricks (1:4)
Considering 100 cft. work
1. Bricks 1100 Nos. @ Tk. 13,067.83 Per % 0 Nos. = Tk. 14,374.61
2. Sand (F.M 1.2) in/c wastage 40 cft. @ Tk. 1,700.00 Per % cft. = Tk. 680.00
3. Cement 6.5 bags @ Tk. 440.00 Per bag = Tk. 2,860.00
4. Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
5. Mason 2 No. @ Tk. 389.00 each = Tk. 778.00
6. Skilled labour 1.5 No. @ Tk. 303.00 each = Tk. 454.50
7. Ordinary labour 2.0 Nos. @ Tk. 245.00 each = Tk. 490.00
8. Labour for soaking &
cleaning bricks 1 No. @ Tk. 245.00 each = Tk. 245.00
9. Screening and washing sand 1/2 No. @ Tk. 245.00 each = Tk. 122.50
10. Labour for 7 days curing
@ 1/8 labour per day: 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
11. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, sundries, T & P etc. ( times of ordinary labour rate) L.S. = Tk. 122.50
Total = Tk. 20,644.74
Profit 10.00% = Tk. 2,064.47
Overhead 3.50% = Tk. 722.57
Tk. 23,431.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,363.75
Grand total = Tk. 24,795.53
(a) Ground floor Rate per cft. = Tk. 247.96
Rate per cum. = Tk. 8,756.71

Say, Tk. 8,757 .00 Per cum


Item No.- 04.9
Analysis of PWD SoR 2014 for Civil Works 84

Brick work with 9.5" x 4.5" x 2.75" size 3 hole machine made reinforced klinker facing bricks (1:4)
Considering 100 cft. work
1. Bricks 1100 Nos. @ Tk. 20,000.00 Per % 0 Nos. = Tk. 22,000.00
Sand (F.M 2.5) in/c wastage 24 cft. @ Tk. 3,000.00 Per % cft. = Tk. 720.00
2. Sand (F.M 1.2) in/c wastage 40 cft. @ Tk. 1,700.00 Per % cft. = Tk. 680.00
3. Cement 6.5 bags @ Tk. 440.00 Per bag = Tk. 2,860.00
4. Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
5. Mason 2 No. @ Tk. 389.00 each = Tk. 778.00
6. Skilled labour 1.5 No. @ Tk. 303.00 each = Tk. 454.50
7. Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
8. Labour for soaking
& cleaning bricks 1 Nos. @ Tk. 245.00 each = Tk. 245.00
9. Screening and washing sand 1/2 No. @ Tk. 245.00 each = Tk. 122.50
10. Labour for 7 days curing
@ 1/8 labour per day: 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
11. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, sundries, T & P etc. ( times of ordinary labour rate) L.S. = Tk. 122.50
Total = Tk. 28,990.13
Profit 10.00% = Tk. 2,899.01
Overhead 3.50% = Tk. 1,014.65
Tk. 32,903.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,915.03
Grand total = Tk. 34,818.82
(a) Ground floor Rate per cft. = Tk. 348.19
Rate per cum. = Tk. 12,296.33

Say, Tk. 12,296 .00 Per cum

Item No.- 04.10


Extra rate for each additional floor for brick works (items Nos.- 4.2 to 4.9)
04.10.1 Add for each addl. floor up to 5th floor (@ 1.25 Nos. lab per % cft.) Per cum = Tk. 130.00
04.10.2 Add for each addl. floor for 6th floor to 9th floor (@ 1.75 Nos. lab per % cft.) Per cum = Tk. 182.00
04.10.3 Add for each addl. floor for 10th floor and above (@ 2.0 Nos. lab per % cft.) Per cum = Tk. 208.00

Item No.- 04.11


Extra rate (for per meter increase of height) over the rate of item No.- 4.2 to 4.9 where free
height of the structure exceeds 4 meter.
Considering 100 cft. of work
1. Extra head mason 0.05 No. @ Tk. 493.00 each = Tk. 24.65
2. Extra mason 0.2 No. @ Tk. 389.00 each = Tk. 77.80
3. Extra skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
4. Extra ordinary labour 0.3 No. @ Tk. 245.00 each = Tk. 73.50
5. Extra for scaffolding 12.5 sft. @ Tk. 7.20 Per sft. = Tk. 90.00
6. Extra for local carriage, storage & sundries etc. ( 10% of ordinary labour rate) L.S. = Tk. 24.50
Total = Tk. 320.75
Profit 10.00% = Tk. 32.08
Overhead 3.50% = Tk. 11.23
Tk. 364.06
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.19
Grand total = Tk. 385.25
Rate per cft. = Tk. 3.85
Rate per cum. = Tk. 135.96

Say, Tk. 136 .00 Per cum.

Item No.- 04.12


Facing brick work with 200 x 100 x 50 mm machine made hard pressed klinker facing bricks (1:4)
Analysis of PWD SoR 2014 for Civil Works 85

with out side pointing.


Considering 100 sft. of work
1. 200 x 100 x 50 mm facing bricks (facing 200 x 100 mm)
in/c 5% wastage 452 Nos. @ Tk. 18,500.00 Per % 0 Nos. = Tk. 8,362.00
2. Sand (F.M. 1.2) in/c wastage 12 cft. @ Tk. 1,700.00 Per % cft. = Tk. 204.00
3. Cement in/c for pointing 2.26 bags @ Tk. 440.00 Per bag = Tk. 994.40
4. Head mason 1 No. No. Tk. 493.00 each = Tk. 493.00
5. Mason 2.25 Nos. @ Tk. 389.00 each = Tk. 875.25
6. Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
7. Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
8. Labour for 7 days curing
@ 1/8 labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
9. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
10. Washing of sand, local carriage, storage & sundries etc. ( times of ordinary labour rate) L.S. = Tk. 122.50
Total = Tk. 12,267.53
Profit 10.00% = Tk. 1,226.75
Overhead 3.50% = Tk. 429.36
Tk. 13,923.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 810.37
Grand total = Tk. 14,734.01
(i) Ground floor Rate per sft. = Tk. 147.34
Rate Per sqm. = Tk. 1,585.97

Say, Tk. 1,586 .00 Per sqm.

Item No.- 04.13


Facing brick work with 200 x 50 x 50 mm machine made klinker facing strips (1:4) with outside pointing.
Considering 100 sft. of work
1. 200 x 50 x 50 mm facing bricks (facing 200 x 50 mm)
in/c 5% wastage 856 Nos. @ Tk. 14,000.00 Per % 0 Nos. = Tk. 11,984.00
2. Sand (F.M. 1.2) in/c wastage 14 cft. @ Tk. 1,700.00 Per % cft. = Tk. 238.00
3. Cement in/c for pointing 2.75 bags @ Tk. 440.00 Per bag = Tk. 1,210.00
4. Head mason 1 No. No. Tk. 493.00 each = Tk. 493.00
5. Mason 2 1/3 Nos. @ Tk. 389.00 each = Tk. 907.67
6. Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
7. Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
8. Labour for 7 days curing
@ 1/8 labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
9. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
10. Washing of sand, local carriage, storage & sundries etc. ( times of ordinary labour rate) L.S. = Tk. 122.50
Total = Tk. 16,171.55
Profit 10.00% = Tk. 1,617.16
Overhead 3.50% = Tk. 566.00
Tk. 18,354.71
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,068.26
Grand total = Tk. 19,422.97
(i) Ground floor Rate per sft. = Tk. 194.23
Rate Per sqm. = Tk. 2,090.69

Say, Tk. 2,091 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 86

Item No.- 04.14


Facing brick work with 200 x 62 x 16.51 mm machine made klinker red strips (1:4) with out side pointing.
Considering 100 sft. of work
1. 200 x 62 x 16.51 mm machine made klinker
facing red strips (facing 200 x 62 mm)
in/c 5% wastage 704 Nos. @ Tk. 16,750.00 Per % 0 Nos. = Tk. 11,792.00
2. Sand (F.M. 1.2) in/c wastage 14 cft. @ Tk. 1,700.00 Per % cft. = Tk. 238.00
3. Cement in/c for pointing 2.75 bags @ Tk. 440.00 Per bag = Tk. 1,210.00
4. Head mason 1 No. No. Tk. 493.00 each = Tk. 493.00
5. Mason 2 Nos. @ Tk. 389.00 each = Tk. 778.00
6. Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
7. Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
8. Labour for 7 days curing
@ 1/8 labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
9. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
10. Washing of sand, local carriage, storage & sundries etc. (1 times of ordinary labour rate) L.S. = Tk. 245.00
Total = Tk. 15,972.38
Profit 10.00% = Tk. 1,597.24
Overhead 3.50% = Tk. 559.03
Tk. 18,128.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,055.11
Grand total = Tk. 19,183.76
(i) Ground floor Rate per sft. = Tk. 191.84
Rate Per sqm. = Tk. 2,064.97

Say, Tk. 2,065 .00 Per sqm.

Item No.- 04.15


125 mm brick work with first class bricks (1:6) in superstructure
Considering 100 sft. work
1. Bricks 480 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 3,600.00
2. Sand (F.M. 1.2) 18 cft. @ Tk. 1,700.00 Per % cft. = Tk. 306.00
3. Cement 1.75 bags @ Tk. 440.00 Per bag = Tk. 770.00
4. Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
5. Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
6. Skilled labour 1/2 No. @ Tk. 303.00 each = Tk. 151.50
7. Ordinary labour 1/2 No. @ Tk. 245.00 each = Tk. 122.50
8. Labour for soaking &
cleaning bricks 1 No. @ Tk. 245.00 each = Tk. 245.00
9. Labour for screening &
washing sand 1/2 No. @ Tk. 245.00 each = Tk. 122.50
10. Labour for 7 days curing
@ 1/8 No. labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
11. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, storage & sundries etc. ( times of ordinary labour rate) L.S. = Tk. 122.50
Total = Tk. 6,175.43
Profit 10.00% = Tk. 617.54
Overhead 3.50% = Tk. 216.14
Tk. 7,009.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 407.94
Grand total = Tk. 7,417.05
Rate per sft. = Tk. 74.17
(i) Ground floor Rate per sft. = Tk. 74.17
Rate per sqm. = Tk. 798.37

Say, Tk. 798 .00 Per sqm.


Item No.- 04.16
Analysis of PWD SoR 2014 for Civil Works 87

125 mm brick work with first class bricks (1:4) in superstructure


Considering 100 sft. work
1. Bricks 480 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 3,600.00
2. Sand (F.M. 1.2) 17 cft. @ Tk. 1,700.00 Per % cft. = Tk. 289.00
3. Cement 2.6 bags @ Tk. 440.00 Per bag = Tk. 1,144.00
4. Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
5. Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
6. Skilled labour 1/2 No. @ Tk. 303.00 each = Tk. 151.50
7. Ordinary labour 1/2 No. @ Tk. 245.00 each = Tk. 122.50
8. Labour for soaking &
cleaning bricks 1 No. @ Tk. 245.00 each = Tk. 245.00
9. Labour for screening &
washing sand 1/4 No. @ Tk. 245.00 each = Tk. 61.25
10. Labour for 7 days curing
@ 1/8 No. labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
11. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, storage & sundries etc. ( times of ordinary labour rate) L.S. = Tk. 122.50
Total = Tk. 6,471.18
Profit 10.00% = Tk. 647.12
Overhead 3.50% = Tk. 226.49
Tk. 7,344.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 427.47
Grand total = Tk. 7,772.26
Rate per sft. = Tk. 77.72
(i) Ground floor Rate per sft. = Tk. 77.72
Rate per sqm. = Tk. 836.58

Say, Tk. 837 .00 Per sqm.

Item No.- 04.17


Exposed 125 mm pointing extra ordinary ornamental brick work (1:4)
Considering 100 sft. of work
1. Bricks 480 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 3,600.00
Extra cost for special quality 1st class bricks
in/c sorting out the bricks @ 20% = Tk. 720.00
2. Sand (F.M. 1.2) in/c wastage 23 cft. @ Tk. 1,700.00 Per % cft. = Tk. 391.00
3. Cement in/c pointing 3 bags @ Tk. 440.00 Per bag = Tk. 1,320.00
4. Head mason 0.10 No. @ Tk. 493.00 each = Tk. 49.30
5. Mason 1 Nos. @ Tk. 389.00 each = Tk. 389.00
6. Skilled labour 0.5 Nos. @ Tk. 303.00 each = Tk. 151.50
7. Ordinary labour 0.5 Nos. @ Tk. 245.00 each = Tk. 122.50
8. Labour for soaking &
cleaning bricks 1 Nos. @ Tk. 245.00 each = Tk. 245.00
9. Labour for screening &
washing sand 0.25 No. @ Tk. 245.00 each = Tk. 61.25
10. Labour for 7 days curing
@ 1/4 labour per day 1.75 Nos. @ Tk. 245.00 each = Tk. 428.75
11. Scaffolding and stageing 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, storage & sundries etc. L.S. = Tk. 204.17
Total = Tk. 7,862.47
Profit 10.00% = Tk. 786.25
Overhead 3.50% = Tk. 275.19
= Tk. 8,923.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 519.38
Grand total = Tk. 9,443.29
(a) Ground floor Rate per sft. = Tk. 94.43
Rate per sqm. = Tk. 1,016.44
Analysis of PWD SoR 2014 for Civil Works 88

Say, Tk. 1,016 .00 Per sqm.

ITEM NO.- 04.18


Exposed 125 mm pointing extra ordinary ornamental brick work (1:4) with automatic machine made 1st classs bricks
Considering 100 sft. of work
1. Bricks 480 Nos. @ Tk. 9,000.00 Per % 0 Nos. = Tk. 4,320.00
2. Sand (F.M. 1.2) in/c wastage 23 cft. @ Tk. 1,700.00 Per % cft. = Tk. 391.00
3. Cement in/c pointing 3 bags @ Tk. 440.00 Per bag = Tk. 1,320.00
4. Head mason 0.10 No. @ Tk. 493.00 each = Tk. 49.30
5. Mason 1 Nos. @ Tk. 389.00 each = Tk. 389.00
6. Skilled labour 0.5 Nos. @ Tk. 303.00 each = Tk. 151.50
7. Ordinary labour 0.5 Nos. @ Tk. 245.00 each = Tk. 122.50
8. Labour for soaking &
cleaning bricks 1 Nos. @ Tk. 245.00 each = Tk. 245.00
9. Labour for screening &
washing sand 0.25 No. @ Tk. 245.00 each = Tk. 61.25
10. Labour for 7 days curing
@ 1/4 labour per day 1.75 Nos. @ Tk. 245.00 each = Tk. 428.75
11. Scaffolding and stageing 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, storage & sundries etc. L.S. = Tk. 306.25
Total = Tk. 7,964.55
Profit 10.00% = Tk. 796.46
Overhead 3.50% = Tk. 278.76
= Tk. 9,039.77
Add VAT with adjustment factor 1.0582 5.50% = Tk. 526.12
Grand total = Tk. 9,565.89
(a) Ground floor Rate per sft. = Tk. 95.66
Rate per sqm. = Tk. 1,029.68

Say, Tk. 1,030 .00 Per sqm.

Item No.- 04.19


125 mm brick work with 10 hole machine made ceramic bricks (1:4) in superstructure
Considering 100 sft. work
1. Bricks 480 Nos. @ Tk. 17,500.00 Per % 0 Nos. = Tk. 8,400.00
2. Sand (F.M. 1.2) 18 cft. @ Tk. 1,700.00 Per % cft. = Tk. 306.00
3. Cement 2.8 bags @ Tk. 440.00 Per bag = Tk. 1,232.00
4. Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
5. Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
6. Skilled labour 1/2 No. @ Tk. 303.00 each = Tk. 151.50
7. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
8. Labour for soaking &
cleaning bricks 1 No. @ Tk. 245.00 each = Tk. 245.00
9. Labour for screening &
washing sand 1/4 No. @ Tk. 245.00 each = Tk. 61.25
10. Labour for 7 days curing
@ 1/8 No. labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
11. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
12. Local carriage, storage & sundries etc. L.S. = Tk. 122.50
Total = Tk. 11,595.93
Profit 10.00% = Tk. 1,159.59
Overhead 3.50% = Tk. 405.86
Tk. 13,161.38
Add VAT with adjustment factor 1.0582 5.50% = Tk. 766.01
Grand total = Tk. 13,927.39
Rate per sft. = Tk. 139.27
Analysis of PWD SoR 2014 for Civil Works 89

(i) Ground floor Rate per sft. = Tk. 139.27


Rate per sqm. = Tk. 1,499.10

Say, Tk. 1,499 .00 Per sqm.

Item No.- 04.20.1


Fancy screen work in wall with 4'' x 4'' x 4'' design block in all floors (1:3).
Considering 100 sft. of work
A. Materials:
1. 4" x 4" x 4" design
block in/c wastage 990 Nos. @ Tk. 28,000.00 Per % 0 Nos. = Tk. 27,720.00
2. Sand (F.M. 1.2) 3.75 cft. @ Tk. 1,700.00 Per % cft. = Tk. 63.75
3. Cement 1 bag @ Tk. 440.00 Per bag = Tk. 440.00
4. Colour pigment 1 Ib @ Tk. 55.00 Per Ib = Tk. 55.00
B. Labour:
1. Head mason 1.25 No. @ Tk. 493.00 each = Tk. 616.25
2. Mason 2.75 Nos. @ Tk. 389.00 each = Tk. 1,069.75
3. Skilled labour 2.5 Nos. @ Tk. 303.00 each = Tk. 757.50
4. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
5. Labour for soaking &
cleaning blocks. 1 No. @ Tk. 245.00 each = Tk. 245.00
6. Labour for 7 days curing
@ 1/8 No. labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
7. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
8. Washing of sand, local carriage & storage etc. L.S. = Tk. 122.50
Total = Tk. 31,729.13
Profit 10.00% = Tk. 3,172.91
Overhead 3.50% = Tk. 1,110.52
Tk. 36,012.56
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,095.97
Grand total = Tk. 38,108.53
(i) Ground floor Rate per sft. = Tk. 381.09
Rate per sqm = Tk. 4,102.05

Say, Tk. 4,102 .00 Per sqm.

Item No.- 04.20.2


Fancy screen work in wall with 5.5'' x 5.5'' x 4'' design block in all floors (1:3) facing 5.5" x 4"
Considering 100 sft. of work
A. Materials:
1. 6.5" x 4.75" x 4" design
block in/c wastage 525 Nos. @ Tk. 28,000.00 Per % 0 Nos. = Tk. 14,700.00
2. Sand (F.M. 1.2) 3.75 cft. @ Tk. 1,700.00 Per % cft. = Tk. 63.75
3. Cement 1 bag @ Tk. 440.00 Per bag = Tk. 440.00
4. Colour pigment 1 Ib @ Tk. 55.00 Per Ib = Tk. 55.00
B. Labour:
1. Head mason 1.25 No. @ Tk. 493.00 each = Tk. 616.25
2. Mason 2.75 Nos. @ Tk. 389.00 each = Tk. 1,069.75
3. Skilled labour 2.5 Nos. @ Tk. 303.00 each = Tk. 757.50
4. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
5. Labour for soaking & .
cleaning blocks 0.50 No. @ Tk. 245.00 each = Tk. 122.50
6. Labour for 7 days curing
@ 1/8 No. labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
7. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
8. Washing of sand, local carriage & storage etc. L.S. = Tk. 122.50
Total = Tk. 18,586.63
Analysis of PWD SoR 2014 for Civil Works 90

Profit 10.00% = Tk. 1,858.66


Overhead 3.50% = Tk. 650.53
Tk. 21,095.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,227.80
Grand total = Tk. 22,323.62
(i) Ground floor Rate per sft. = Tk. 223.24
Rate per sqm = Tk. 2,402.96

Say, Tk. 2,403 .00 Per sqm.

Item No.- 04.20.3


Fancy Screen work with 6'' x 6'' x 4'' design block in all floors (1:3)
Considering 100 sft. of work
A. Materials:
1. 6.5" x 6" x 4" design
block in/c wastage 440 Nos. @ Tk. 32,000.00 Per % 0 Nos. = Tk. 14,080.00
2. Sand (F.M. 1.2) 3.75 cft. @ Tk. 1,700.00 Per % cft. = Tk. 63.75
3. Cement 1 bag @ Tk. 440.00 Per bag = Tk. 440.00
4. Colour pigment 1 Ib @ Tk. 55.00 Per Ib = Tk. 55.00
B. Labour:
1. Head mason 1.25 No. @ Tk. 493.00 each = Tk. 616.25
2. Mason 2.75 Nos. @ Tk. 389.00 each = Tk. 1,069.75
3. Skilled labour 2.5 Nos. @ Tk. 303.00 each = Tk. 757.50
4. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
5. Labour for soaking &
cleaning blocks. 0.50 No. @ Tk. 245.00 each = Tk. 122.50
6. Labour for 7 days curing
@ 1/8 No. labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
7. Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
8. Washing of sand, local carriage & storage etc. L.S. = Tk. 122.50
Total = Tk. 17,966.63
Profit 10.00% = Tk. 1,796.66
Overhead 3.50% = Tk. 628.83
Tk. 20,392.12
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,186.84
Grand total = Tk. 21,578.96
(i) Ground floor Rate per sft. = Tk. 215.79
Rate per sqm = Tk. 2,322.76

Say, Tk. 2,323 .00 Per sqm.

Item No.- 04.21


Extra rate for each additional floor for brick and screen block work (Item Nos.- 4.12 to 4.20)

04.21.1 Add for each addl. floor up to 5th floor (@ 0.75 No. lab per % sft.) Per sqm = Tk. 24.00
04.21.2 Add for each addl. floor for 6th floor to 9th floor (@ 1 No. lab per % sft.) Per sqm = Tk. 32.00
04.21.3 Add for each addl. floor 10th floor and above (@ 1.25 Nos. lab per % sft.) Per sqm = Tk. 40.00

Item No.- 04.22.1


50 mm thick flat brick pavement with 200 x 100 x 50 mm klinker paving bricks (1:4)
Considering 100 sft. of work
A. Materials:
1. 200 x 100 x 50 mm klinker paving
bricks (facing 200 x 50 mm)
in/c 5% wastage 856 Nos. @ Tk. 18,500.00 Per % 0 Nos. = Tk. 15,836.00
2. Sand (F.M. 1.2) 16 cft. @ Tk. 1,700.00 Per % cft. = Tk. 272.00
3. Cement (in/c for flush pointing) 3.25 bags @ Tk. 440.00 Per bag = Tk. 1,430.00
Analysis of PWD SoR 2014 for Civil Works 91

B. Labour:
1. Head mason 1/4 No. @ Tk. 493.00 each = Tk. 123.25
2. Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
3. Skilled labour 3 Nos. @ Tk. 303.00 each = Tk. 909.00
4. Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
5. Labour for soaking &
cleaning bricks 1 No. @ Tk. 245.00 each = Tk. 245.00
6. Labour for 7 days curing
@ 1/8 labour per day. 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
7. Local carriage & storage, sundries etc. L.S. = Tk. 122.50
Total = Tk. 20,103.13
Profit 10.00% = Tk. 2,010.31
Overhead 3.50% = Tk. 703.61
Tk. 22,817.05
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,327.98
Grand total = Tk. 24,145.03
Rate per sft. = Tk. 241.45
Rate per sqm. = Tk. 2,598.97

Say, Tk. 2,599 .00 Per sqm.

Item No.- 04.22.2


100 mm thick brick on edge pavement with 200 x 100 x 50 mm klinker paving bricks (1:4)
Considering 100 sft. of work
A. Materials:
1. 200 x 100 x 50 mm klinker paving
bricks (facing 200 x 100 mm)
in/c 5% wastage 452 Nos. @ Tk. 18,500.00 Per % 0 Nos. = Tk. 8,362.00
2. Sand (F.M. 1.2) 13 cft. @ Tk. 1,700.00 Per % cft. = Tk. 221.00
3. Cement (in/c for flush pointing) 2.5 bags @ Tk. 440.00 Per bag = Tk. 1,100.00
B. Labour:
1. Head mason 1/4 No. @ Tk. 493.00 each = Tk. 123.25
2. Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
3. Skilled labour 2.5 Nos. @ Tk. 303.00 each = Tk. 757.50
4. Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
5. Labour for soaking &
cleaning bricks 0.50 No. @ Tk. 245.00 each = Tk. 122.50
6. Labour for 7 days curing
@ 1/8 labour per day. 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
7. Local carriage & storage, sundries etc. L.S. = Tk. 122.50
Total = Tk. 11,779.63
Profit 10.00% = Tk. 1,177.96
Overhead 3.50% = Tk. 412.29
Tk. 13,369.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 778.14
Grand total = Tk. 14,148.02
Rate per sft. = Tk. 141.48
Rate per sqm. = Tk. 1,522.89

Say, Tk. 1,523 .00 Per sqm.

Item No.- 04.22.3


50 mm thick flat brick pavement with 200 x 50 x 50 mm klinker paving bricks (1:4)
facing 200 mm x 50 mm
Considering 100 sft. of work
A. Materials:
1. 200 x 50 x 50 mm klinker paving
Analysis of PWD SoR 2014 for Civil Works 92

bricks (facing 200 x 50 mm)


in/c 5% wastage 856 Nos. @ Tk. 14,000.00 Per % 0 Nos. = Tk. 11,984.00
2. Sand (F.M. 1.2) 10 cft. @ Tk. 1,700.00 Per % cft. = Tk. 170.00
3. Cement (in/c for flush pointing) 2.5 bags @ Tk. 440.00 Per bag = Tk. 1,100.00
B. Labour:
1. Head mason 1/4 No. @ Tk. 493.00 each = Tk. 123.25
2. Mason 1.25 Nos. @ Tk. 389.00 each = Tk. 486.25
3. Skilled labour 2.5 Nos. @ Tk. 303.00 each = Tk. 757.50
4. Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
5. Labour for soaking &
cleaning bricks 1 No. @ Tk. 245.00 each = Tk. 245.00
6. Labour for 7 days curing
'@ 1/8 labour per day. 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
7. Local carriage & storage, sundries etc. L.S. = Tk. 122.50
Total = Tk. 15,570.38
Profit 10.00% = Tk. 1,557.04
Overhead 3.50% = Tk. 544.96
Tk. 17,672.38
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,028.55
Grand total = Tk. 18,700.93
Rate per sft. = Tk. 187.01
Rate per sqm. = Tk. 2,012.98

Say, Tk. 2,013 .00 Per sqm.

Item No.- 04.23


125 mm thick brick pavement with 1st class bricks (1:4)
Considering 100 sft. work
A. Materials:
1. 1st class bricks in/c wastage 480 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 3,600.00
2. Sand (F.M. 1.2) 15 cft. @ Tk. 1,700.00 Per % cft. = Tk. 255.00
3. Cement (in/c for flush pointing) 3 bags @ Tk. 440.00 Per bag = Tk. 1,320.00
B. Labour:
1. Head mason 1/4 No. @ Tk. 493.00 each = Tk. 123.25
2. Mason 1.25 Nos. @ Tk. 389.00 each = Tk. 486.25
3. Skilled labour 2.25 Nos. @ Tk. 303.00 each = Tk. 681.75
4. Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
5. Labour for soaking &
cleaning bricks 1/2 No. @ Tk. 245.00 each = Tk. 122.50
6. Labour for 7 days curing
@ 1/8 labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
7. Local carriage, storage & sundries etc. L.S = Tk. 122.50
Total = Tk. 7,293.13
Profit 10.00% = Tk. 729.31
Overhead 3.50% = Tk. 255.26
Tk. 8,277.70
Add VAT with adjustment factor 1.0582 5.50% = Tk. 481.77
Grand total = Tk. 8,759.47
Rate per sft. = Tk. 87.59
Rate per sqm. = Tk. 942.82

Say, Tk. 943 .00 Per sqm.

Item No.- 04.24


125 mm thick brick pavement with 10 holes ceramic bricks (1:4)
Analysis of PWD SoR 2014 for Civil Works 93

Considering 100 sft. of work


A. Materials:
1. 10 holes ceramic bricks 480 Nos. @ Tk. 17,500.00 Per % 0 Nos. = Tk. 8,400.00
2. Sand (F.M. 1.2) 15 cft. @ Tk. 1,700.00 Per % cft. = Tk. 255.00
3. Cement (in/c for flush pointing) 3.25 bags @ Tk. 440.00 Per bag = Tk. 1,430.00
B. Labour:
1. Head mason 1/4 No. @ Tk. 493.00 each = Tk. 123.25
2. Mason 1.25 Nos. @ Tk. 389.00 each = Tk. 486.25
3. Skilled labour 2.25 Nos. @ Tk. 303.00 each = Tk. 681.75
4. Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
5. Labour for soaking &
cleaning bricks 1/2 No. @ Tk. 245.00 each = Tk. 122.50
6. Labour for 7 days curing
@ 1/8 labour per day 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
7. Local carriage, storage & sundries etc. L.S = Tk. 122.50
Total = Tk. 12,203.13
Profit 10.00% = Tk. 1,220.31
Overhead 3.50% = Tk. 427.11
Tk. 13,850.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 806.12
Grand total = Tk. 14,656.67
Rate per sft. = Tk. 146.57
Rate per sqm. = Tk. 1,577.68

Say, Tk. 1,578 .00 Per sqm.

Item No.- 04.25


3" thick cement concrete (C.C.) in floor (1:3:6)
Considering 100 sft. of work
From item No.-03.4.2 cost of concrete = Tk. 14,713.64
1. For 3" thick 100 sft of work = Tk. 3,678.41
2. Add extra for floor casting: Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
Total = Tk. 4,067.41
Profit 10.00% = Tk. 406.74
Overhead 3.50% = Tk. 142.36
Tk. 4,616.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 268.69
Grand total = Tk. 4,885.20
Rate Per sft = Tk. 48.85
Rate Per sqm. = Tk. 525.82

Say, Tk. 526 .00 Per sqm.


Item No.- 04.26
25 mm thick artificial patent stone flooring (1:2:4) with brick chips
Considering 100 cft. of work covering 1200 sft. area
1. Bricks @ 8.5 Nos. per cft. chips 765 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 5,737.50
2. Sand (F.M. 1.2) 22.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 382.50
3. Sand (F.M. 2.5) 22.5 cft. @ Tk. 3,000.00 Per % cft. = Tk. 675.00
4. Cement 18 bags @ Tk. 440.00 Per bag = Tk. 7,920.00
5. Breaking chips in/c screening 90 cft. @ Tk. 1,091.88 Per % cft. = Tk. 982.69
6. Labour for 7 days curing
@ 1/8 labour per day. 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
7. Local carriage, sundries, T & P and washing of sand etc. L.S. = Tk. 367.50
Sub-total = Tk. 16,279.57
For 100 sft. of work = Tk. 1,356.63
8. Extra cement for finishing 1/2 bag @ Tk. 440.00 Per bag = Tk. 220.00
9. Labour cost:
Analysis of PWD SoR 2014 for Civil Works 94

i) Head mason 1/5 No. @ Tk. 493.00 each = Tk. 98.60


ii) Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
iii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
iv) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
10. Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1" x 3/4" = 0.21 cft.
Add 5% wastage 0.01 cft.
0.22 cft. @ Tk. 2,000.00 Per cft.
Using 10 times @ Tk. 200.00 Per cft. = Tk. 44.00
11. Labour for shuttering
2 x 4 x 5'-0" x 1" = 3.33 sft. @ Tk. 2.00 Per sft. = Tk. 6.66
Total = Tk. 2,565.64
Profit 10.00% = Tk. 256.56
Overhead 3.50% = Tk. 89.80
Tk. 2,912.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 169.48
Grand total = Tk. 3,081.48
(i) Ground floor Rate per sft. = Tk. 30.81
Rate per sqm. = Tk. 331.64

Say, Tk. 332 .00 Per sqm.

Item No.- 04.27


38 mm thick artificial patent stone flooring (1:2:4) with brick chips
Considering 100 cft. of work covering 800 sft. area
1. Bricks @ 8.5 Nos. per cft. chips 765 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 5,737.50
2. Sand (F.M. 1.2) 22.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 382.50
3. Sand (F.M. 2.5) 22.5 cft. @ Tk. 3,000.00 Per % cft. = Tk. 675.00
4. Cement 18 bags @ Tk. 440.00 Per bag = Tk. 7,920.00
5. Breaking brick chips
in/c screening 90 cft. @ Tk. 1,091.88 Per % cft. = Tk. 982.69
6. Labour for 7 days curing
@ 1/8 labour per day. 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
7. Local carriage, sundries, T & P and washing of sand etc. L.S. = Tk. 367.50
Sub-total = Tk. 16,279.57
For 100 sft. of work = Tk. 2,034.95
8. Extra cement for finishing 1/2 bag @ Tk. 440.00 Per bag = Tk. 220.00
9. Labour cost:
(a) Head mason 1/5 No. @ Tk. 493.00 each = Tk. 98.60
(b) Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
(c) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(d) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
10. Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1.5" x 3/4" = 0.31 cft.
Add 5% wastage 0.02 cft.
0.33 cft. @ Tk. 2,000.00 Per cft.
Using 10 times @ Tk. 200.00 Per cft. = Tk. 66.00
11. Labour for shuttering
2 x 4 x 5'-0" x 1.5" = 5 sft. @ Tk. 2.00 Per sft. = Tk. 10.00
Total = Tk. 3,269.30
Profit 10.00% = Tk. 326.93
Overhead 3.50% = Tk. 114.43
Tk. 3,710.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 215.96
Grand total = Tk. 3,926.62
(i) Ground floor Rate per sft. = Tk. 39.27
Rate per sqm. = Tk. 422.70
Analysis of PWD SoR 2014 for Civil Works 95

Say, Tk. 423 .00 Per sqm.

Item No.- 04.28


25 mm thick artificial patent stone flooring (1:2:4) with 1/2" down graded stone chips
Considering 100 cft. of work covering 1200 sft. area
1. Crushed stone chips 90 cft. @ Tk. 13,500.00 Per % cft. = Tk. 12,150.00
2. Sand (F.M. 1.2) 22.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 382.50
3. Sand (F.M. 2.5) 22.5 cft. @ Tk. 3,000.00 Per % cft. = Tk. 675.00
4. Cement 18 bags @ Tk. 440.00 Per bag = Tk. 7,920.00
5. Labour for 7 days curing
@ 1/8 labour per day. 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
6. Local carriage, sundries, T & P and washing of sand etc. L.S. = Tk. 367.50
Sub-total = Tk. 21,709.38
For 100 sft. of work = Tk. 1,809.12
7. Extra cement for finishing 1/2 bag @ Tk. 440.00 Per bag = Tk. 220.00
8. Labour cost:
(a) Head mason 1/5 No. @ Tk. 493.00 each = Tk. 98.60
(b) Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
(c) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(d) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
10. Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1" x 3/4" = 0.21 cft.
Add 5% wastage 0.01 cft.
0.22 cft. @ Tk. 2,000.00 Per cft.
Using 10 times @ Tk. 200.00 Per cft. = Tk. 44.00
11. Labour for shuttering
2 x 4 x 5'-0" x 1" = 3.33 sft. @ Tk. 2.00 Per sft. = Tk. 6.66
Total = Tk. 3,018.13
Profit 10.00% = Tk. 301.81
Overhead 3.50% = Tk. 105.63
Tk. 3,425.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 199.37
Grand total = Tk. 3,624.94
(i) Ground floor Rate per sft. = Tk. 36.25
Rate per sqm. = Tk. 390.20

Say, Tk. 390 .00 Per sqm.

Item No.- 04.29


38 mm thick artificial patent stone flooring (1:2:4) with 1/2" down graded stone chips
Considering 100 cft. of work covering 800 sft. area
1. Crushed stone chips 90 cft. @ Tk. 13,500.00 Per % cft. = Tk. 12,150.00
2. Sand (F.M. 1.2) 22.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 382.50
3. Sand (F.M. 2.5) 22.5 cft. @ Tk. 3,000.00 Per % cft. = Tk. 675.00
4. Cement 18 bags @ Tk. 440.00 Per bag = Tk. 7,920.00
5. Labour for 7 days curing
@ 1/8 labour per day. 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
6. Local carriage, sundries, T & P and washing of sand etc. L.S. = Tk. 367.50
Sub-total = Tk. 21,709.38
For 100 sft. of work = Tk. 2,713.67
7. Extra cement for finishing 1/2 bag @ Tk. 440.00 Per bag = Tk. 220.00
8. Labour cost:
(a) Head mason 1/5 No. @ Tk. 493.00 each = Tk. 98.60
(b) Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
(c) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(d) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Analysis of PWD SoR 2014 for Civil Works 96

10. Extra cost of Garjan batten for side shutter


2 x 4 x 5'-0" x 1.5" x 3/4" = 0.31 cft.
Add 5% wastage 0.02 cft.
0.33 cft. @ Tk. 2,000.00 Per cft.
Using 10 times @ Tk. 200.00 Per cft. = Tk. 66.00
11. Labour for shuttering
2 x 4 x 5'-0" x 1.5" = 5 sft. @ Tk. 2.00 Per sft. = Tk. 10.00
Total = Tk. 3,948.02
Profit 10.00% = Tk. 394.80
Overhead 3.50% = Tk. 138.18
Tk. 4,481.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 260.80
Grand total = Tk. 4,741.80
(i) Ground floor Rate per sft. = Tk. 47.42
Rate per sqm. = Tk. 510.43

Say, Tk. 510 .00 Per sqm.

Item No.- 04.30


25 mm thick artificial patent stone flooring (1 : 1.5 : 3) with 1/2" down graded stone chips
Considering 100 cft. of work covering 1200 sft. area
1. Crushed stone chips 90 cft. @ Tk. 13,500.00 Per % cft. = Tk. 12,150.00
2. Sand (F.M. 1.2) 22.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 382.50
3. Sand (F.M. 2.5) 22.5 cft. @ Tk. 3,000.00 Per % cft. = Tk. 675.00
4. Cement 22 bags @ Tk. 440.00 Per bag = Tk. 9,680.00
5. Labour for 7 days curing
@ 1/8 labour per day. 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
6. Local carriage, sundries, T & P and washing of sand etc. L.S. = Tk. 367.50
Sub-total = Tk. 23,469.38
For 100 sft. of work = Tk. 1,955.78
7. Extra cement for finishing 1/2 bag @ Tk. 440.00 Per bag = Tk. 220.00
8. Labour cost:
(a) Head mason 1/5 No. @ Tk. 493.00 each = Tk. 98.60
(b) Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
(c) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(d) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
10. Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1" x 3/4" = 0.21 cft.
Add 5% wastage 0.01 cft.
0.22 cft. @ Tk. 2,000.00 Per cft.
Using 10 times @ Tk. 200.00 Per cft. = Tk. 44.00
11. Labour for shuttering
2 x 4 x 5'-0" x 1" = 3.33 sft. @ Tk. 2.00 Per sft. = Tk. 6.66
Total = Tk. 3,164.79
Profit 10.00% = Tk. 316.48
Overhead 3.50% = Tk. 110.77
Tk. 3,592.04
Add VAT with adjustment factor 1.0582 5.50% = Tk. 209.06
Grand total = Tk. 3,801.10
(i) Ground floor Rate per sft. = Tk. 38.01
Rate per sqm. = Tk. 409.14

Say, Tk. 409 .00 Per sqm.

Item No.- 04.31


38 mm thick artificial patent stone flooring (1: 1.5 : 3) with 1/2" down graded stone chips
Considering 100 cft. of work covering 800 sft. area
Analysis of PWD SoR 2014 for Civil Works 97

1. Crushed stone chips 90 cft. @ Tk. 13,500.00 Per % cft. = Tk. 12,150.00
2. Sand (F.M. 1.2) 22.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 382.50
3. Sand (F.M. 2.5) 22.5 cft. @ Tk. 3,000.00 Per % cft. = Tk. 675.00
4. Cement 22 bags @ Tk. 440.00 Per bag = Tk. 9,680.00
5. Labour for 7 days curing
@ 1/8 labour per day. 0.875 Nos. @ Tk. 245.00 each = Tk. 214.38
6. Local carriage, sundries, T & P and washing of sand etc. L.S. = Tk. 367.50
Sub-total = Tk. 23,469.38
For 100 sft. of work = Tk. 2,933.67
7. Extra cement for finishing 1/2 bag @ Tk. 440.00 Per bag = Tk. 220.00
8. Labour cost:
(a) Head mason 1/5 No. @ Tk. 493.00 each = Tk. 98.60
(b) Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
(c) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(d) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
10. Extra cost of Garjan batten for side shutter
2 x 4 x 5'-0" x 1.5" x 3/4" = 0.31 cft.
Add 5% wastage 0.02 cft.
0.33 cft. @ Tk. 2,000.00 Per cft.
Using 10 times @ Tk. 200.00 Per cft. = Tk. 66.00
11. Labour for shuttering
2 x 4 x 5'-0" x 1.5" = 5 sft. @ Tk. 2.00 Per sft. = Tk. 10.00
Total = Tk. 4,168.02
Profit 10.00% = Tk. 416.80
Overhead 3.50% = Tk. 145.88
Tk. 4,730.70
Add VAT with adjustment factor 1.0582 5.50% = Tk. 275.33
Grand total = Tk. 5,006.03
(i) Ground floor Rate per sft. = Tk. 50.06
Rate per sqm. = Tk. 538.85

Say, Tk. 539 .00 Per sqm.

Item No.- 04.32


Extra rate for each additional floor for patent stone flooring
04.32.1 Add for each addl. floor up to 5th floor (@ 0.75 No. lab per % sft.) Per sqm = Tk. 24.00
04.32.2 Add for each addl. floor for 6th floor to 9th floor (@ 1 No. lab per % sft.) Per sqm = Tk. 32.00
04.32.3 Add for each addl. floor 10th floor and above (@ 1.25 Nos. lab per % sft.) Per sqm = Tk. 40.00
Analysis of PWD SoR 2014 for Civil Works 98

DIVISION 05 : MOSAIC WORKS

Item No.- 05.1.1


10 mm thick (finished) mosaic in floor with Indian chips & glass strip using 100% white cement in/c 25 mm thick patent stone (1:2:4) with BRICK
chips

Considering 100 sft. of work


A. Materials:
1. White cement 125 kg @ Tk. 25.00 Per kg = Tk. 3,125.00
2. Mosaic chips (Indian: Deradun) 125 kg @ Tk. 17.00 Per kg = Tk. 2,125.00
3. Minar stone @ 300 sft/stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. 5 x 20 mm glass strip 120 rft. @ Tk. 8.00 Per rft. = Tk. 960.00
5. Cost of patent stone excluding cost of
1/2 bag cement for neat finish
& 1/4 No. mason 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 8,591.72
B. Labour:
(a) For mixing, laying, compacting & curing:
1. Head mason 3/4 No. @ Tk. 493.00 each = Tk. 369.75
2. Skilled labour 3/4 No. @ Tk. 303.00 each = Tk. 227.25
3. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(b) For glass strip laying: =
1. Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
2. Ordinary labour 3/4 No. @ Tk. 245.00 each = Tk. 183.75
(c) Hire charge of mosaic cutting machine in/c operation:
1. Hire charge in/c meter
setting and electricity cost. 1 day @ Tk. 300.00 Per day = Tk. 300.00
2. Machine operator 1 No. @ Tk. 423.00 each = Tk. 423.00
3. Helper/Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
4. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
5. Pumic stone 3 Nos. @ Tk. 60.00 each = Tk. 180.00
For spreading oxalic acid and washing:
1. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Sub-total = Tk. 3,013.50
Total = Tk. 11,605.22
Profit 10.00% = Tk. 1,160.52
Overhead 3.50% = Tk. 406.18
Tk. 13,171.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 766.62
Grand total = Tk. 13,938.54
(i) Ground floor Rate per sft. = Tk. 139.39
Rate per sqm. = Tk. 1,500.39

Say, Tk. 1,500 .00 Per sqm.

Item No.- 05.1.2


10 mm thick (finished) mosaic in floor with Indian chips & glass strip using

100% grey cement in/c 25 mm thick patent stone (1:2:4) with BRICK chips

Considering 100 sft. of work


A. Materials:
1. Grey cement 2.40 bag. @ Tk. 440.00 Per bag = Tk. 1,056.00
2. Indian Deradun mosaic chips 125 kg @ Tk. 17.00 Per kg = Tk. 2,125.00
3. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. 5 x 20 mm glass strip 120 rft. @ Tk. 8.00 Per rft. = Tk. 960.00
5. Cost of patent stone excluding cost of cement for
neat finish and 1/4 No. mason 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 6,522.72
B. Labour:
Analysis of PWD SoR 2014 for Civil Works 99

Same as 05.1.1 100 sft. @ Tk. 3,013.50 Per % sft. = Tk. 3,013.50
Total = Tk. 9,536.22
Profit 10.00% = Tk. 953.62
Overhead 3.50% = Tk. 333.77
Tk. 10,823.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 629.94
Grand total = Tk. 11,453.55
(i) Ground floor Rate per sft. = Tk. 114.54
Rate per sqm. = Tk. 1,232.91

Say, Tk. 1,233 .00 Per sqm.

Item No.- 05.1.3


10 mm thick (finished) mosaic in floor with Pakistani chips & glass strip using 100% white cement in/c 25 mm thick
patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Materials
1. White cement 125 kg @ Tk. 25.00 Per kg = Tk. 3,125.00
2 Pakistani onix mosaic chips 125 kg @ Tk. 19.00 Per kg = Tk. 2,375.00
3. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. 5 x 20 mm glass strip 120 rft. @ Tk. 8.00 Per rft. = Tk. 960.00
5. Cost of patent stone excluding cost of cement for
neat finish and 1/4 No. mason 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 8,841.72
B. Labour:
Same as 05.1.1 100 sft. @ Tk. 3,013.50 Per % sft. = Tk. 3,013.50
Total = Tk. 11,855.22
Profit 10.00% = Tk. 1,185.52
Overhead 3.50% = Tk. 414.93
Tk. 13,455.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 783.13
Grand total = Tk. 14,238.80
(i) Ground floor Rate per sft. = Tk. 142.39
Rate per sqm. = Tk. 1,532.69

Say, Tk. 1,533 .00 Per sqm.

Item No.- 05.1.4


10 mm thick (finished) mosaic in floor with Indian chips & without glass strip using 100% white cement
in/c 25 mm thick patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Materials:
1. White cement 125 kg @ Tk. 25.00 Per kg = Tk. 3,125.00
2. Indian Deradun mosaic chips 125 kg @ Tk. 17.00 Per kg = Tk. 2,125.00
3. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. Cost of patent stone excluding cost of cement for
neat finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft = Tk. 2,248.39
Sub-Total = Tk. 7,631.72
B. Labour:
(a) For mixing, laying, compacting and curing:
1. Head mason 3/4 No. @ Tk. 493.00 each = Tk. 369.75
2. Skilled labour 3/4 No. @ Tk. 303.00 each = Tk. 227.25
3. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(b) Hire charge of mosaic cutting machine and operation:
1. Hire charge in/c meter setting 1 day @ Tk. 300.00 Per day = Tk. 300.00
2. Machine operator 1 No. @ Tk. 423.00 each = Tk. 423.00
3. Helper/Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Analysis of PWD SoR 2014 for Civil Works 100

4. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00


5. Pumic stone 3 Nos. @ Tk. 60.00 each = Tk. 180.00
(c) Pumic stone oxalic acid and washing:
1. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Sub-total = Tk. 2,538.00
Total = Tk. 10,169.72
Profit 10.00% = Tk. 1,016.97
Overhead 3.50% = Tk. 355.94
Tk. 11,542.63
Add VAT with adjustment factor 1.0582 5.50% = Tk. 671.79
Grand total = Tk. 12,214.42
(i) Ground floor Rate per sft. = Tk. 122.14
Rate per sqm = Tk. 1,314.71

Say, Tk. 1,315 .00 Per sqm.

Item No.- 05.1.5


10 mm thick (finished) mosaic in floor with Indian chips without glass strip using
100% grey cement in/c 25 mm thick patent stone (1:2:4) with BRICK chips

Considering 100 sft. of work


A. Materials:
1. Grey cement 2.40 bag. @ Tk. 440.00 Per bag = Tk. 1,056.00
2. Indian Deradun mosaic chips 125 kg @ Tk. 17.00 Per kg = Tk. 2,125.00
3. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. Cost of patent stone excluding cost of cement for
neat finish and 1/4 No. mason 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 5,562.72
B. Labour:
Same as 05.1.1 100 sft. @ Tk. 3,013.50 Per % sft. = Tk. 3,013.50
Total = Tk. 8,576.22
Profit 10.00% = Tk. 857.62
Overhead 3.50% = Tk. 300.17
Tk. 9,734.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 566.53
Grand total = Tk. 10,300.54
(i) Ground floor Rate per sft. = Tk. 103.01
Rate per sqm. = Tk. 1,108.80

Say, Tk. 1,109 .00 Per sqm.

Item No.- 05.1.6


10 mm thick (finished) mosaic in floor with Pakistani chips & without glass strip using 100% white cement
in/c 25 mm thick patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Materials
1. White cement 125 kg @ Tk. 25.00 Per kg = Tk. 3,125.00
2. Pakistani onix mosaic chips 125 kg @ Tk. 19.00 Per kg = Tk. 2,375.00
3. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. Cost of patent stone excluding cost of cement for
neat finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft = Tk. 2,248.39
Sub-Total = Tk. 7,881.72
B. Labour:
For mixing, laying, compacting and curing:
1. Head mason 3/4 No. @ Tk. 493.00 each = Tk. 369.75
2. Skilled labour 3/4 No. @ Tk. 303.00 each = Tk. 227.25
3. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Analysis of PWD SoR 2014 for Civil Works 101

Hire charge of mosaic cutting machine and operation:


1. Hire charge in/c meter setting 1 day @ Tk. 300.00 Per day = Tk. 300.00
2. Machine operator 1 No. @ Tk. 423.00 each = Tk. 423.00
3. Helper/Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
4. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
5. Pumic stone 3 Nos. @ Tk. 60.00 each = Tk. 180.00
Pumic stone oxalic acid and washing:
Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Sub-total = Tk. 2,538.00
Total = Tk. 10,419.72
Profit 10.00% = Tk. 1,041.97
Overhead 3.50% = Tk. 364.69
Tk. 11,826.38
Add VAT with adjustment factor 1.0582 5.50% = Tk. 688.31
Grand total = Tk. 12,514.69
(i) Ground floor Rate per sft. = Tk. 125.15
Rate per sqm = Tk. 1,347.11

Say, Tk. 1,347 .00 Per sqm.

Item No.- 05.2.1


12 mm thick (finished) mosaic in floor with Indian chips & glass strip using 100% white cement
in/c 25 mm thick patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Materials:
1. White cement 140 kg @ Tk. 25.00 Per kg = Tk. 3,500.00
2. Indian Deradun mosaic chips 140 kg @ Tk. 17.00 Per kg = Tk. 2,380.00
3. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. 5 x 20 mm glass strip 120 rft. @ Tk. 8.00 Per rft. Tk. 960.00
5. Cost of patent stone excluding cost of cement
for neat finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft = Tk. 2,248.39
Sub-total = Tk. 9,221.72
B. Labour:
Same as item No. 05.1.1 100 sft. @ Tk. 3,013.50 Per % sft. = Tk. 3,013.50
Total = Tk. 12,235.22
Profit 10.00% = Tk. 1,223.52
Overhead 3.50% = Tk. 428.23
Tk. 13,886.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 808.24
Grand total = Tk. 14,695.21
(i) Ground floor Rate per sft. = Tk. 146.95
Rate per sqm = Tk. 1,581.77

Say, Tk. 1,582 .00 Per sqm.

Item No.- 05.2.2


12 mm thick (finished) mosaic in floor with Pakistani chips & glass strip using 100% white cement in/c 25 mm thick
Considering 100 sft. of work
A. Materials
1. White cement 140 kg @ Tk. 25.00 Per kg = Tk. 3,500.00
2. Pakistani onix mosaic chips 140 kg @ Tk. 19.00 Per kg = Tk. 2,660.00
3. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. 5 x 20 mm glass strip 120 rft. @ Tk. 8.00 Per rft. = Tk. 960.00
5. Cost of patent stone excluding cost of cement for
neat finish and 1/4 No. mason 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 9,501.72
B. Labour:
Analysis of PWD SoR 2014 for Civil Works 102

Same as 05.1.1 100 sft. @ Tk. 3,013.50 Per % sft. = Tk. 3,013.50
Total = Tk. 12,515.22
Profit 10.00% = Tk. 1,251.52
Overhead 3.50% = Tk. 438.03
Tk. 14,204.77
Add VAT with adjustment factor 1.0582 5.50% = Tk. 826.73
Grand total = Tk. 15,031.50
(i) Ground floor Rate per sft. = Tk. 150.32
Rate per sqm. = Tk. 1,618.04

Say, Tk. 1,618 .00 Per sqm.

Item No.- 05.2.3


12 mm thick (finished) mosaic in floor with Indian chips & without glass strip using 100% white cement in/c 25 mm thick
patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Materials:
1. White cement 140 kg @ Tk. 25.00 Per kg = Tk. 3,500.00
2. Indian Deradun mosaic chips 140 kg @ Tk. 17.00 Per kg = Tk. 2,380.00
3. Minar Stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. Cost of patent stone excluding cost of cement for neat
finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft = Tk. 2,248.39
B. Labour:
Same as item No.- 05.1.4 100 sft. @ Tk. 2,538.00 Per % sft. = Tk. 2,538.00
Sub-total = Tk. 10,799.72
Profit 10.00% = Tk. 1,079.97
Overhead 3.50% = Tk. 377.99
Tk. 12,257.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 713.41
Grand total = Tk. 12,971.09
(i) Ground floor Rate per sft. = Tk. 129.71
Rate per sqm = Tk. 1,396.20

Say, Tk. 1,396 .00 Per sqm.


Item No.- 05.2.4
12 mm thick (finished) mosaic in floor with Pakistani chips & without glass strip using 100% white cement in/c 25 mm
thick patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Materials:
1. White cement 140 kg @ Tk. 25.00 Per kg = Tk. 3,500.00
2. Pakistani onix mosaic chips 140 kg @ Tk. 19.00 Per kg = Tk. 2,660.00
3. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. Cost of patent stone excluding cost of cement for neat
finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft = Tk. 2,248.39
Sub-total = Tk. 8,541.72
B. Labour:
Same as item No.- 05.1.4 100 sft. @ Tk. 2,538.00 Per % sft. = Tk. 2,538.00
Total = Tk. 11,079.72
Profit 10.00% = Tk. 1,107.97
Overhead 3.50% = Tk. 387.79
Tk. 12,575.48
Add VAT with adjustment factor 1.0582 5.50% = Tk. 731.91
Grand total = Tk. 13,307.39
(i) Ground floor Rate per sft. = Tk. 133.07
Rate per sqm = Tk. 1,432.37
Analysis of PWD SoR 2014 for Civil Works 103

Say, Tk. 1,432 .00 Per sqm.

Item No.- 05.3.1


10 mm thick (finished) silver grey situ mosaic in floor with Indian chips and with glass
strip in/c 25 mm thick patent stone with BRICK-CHIPS: (white cement : grey cement = 1:1)
Considering 100 sft of work
A. Materials:
1. White cement 62.5 kg @ Tk. 25.00 Per kg = Tk. 1,562.50
2. Grey cement 1.25 bag @ Tk. 440.00 Per bag. = Tk. 550.00
3. India Deradun mosaic chips 125 kg @ Tk. 17.00 Per kg = Tk. 2,125.00
4. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
5. 5 x 20 mm glass strip 120 rft. @ Tk. 8.00 Per rft. = Tk. 960.00
6. Cost of patent stone excluding cost of cement for
neat finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 7,579.22
B. Labour:
Same as item No.- 05.1.1 100 sft. @ Tk. 3,013.50 Per % sft. = Tk. 3,013.50
Total = Tk. 10,592.72
Profit 10.00% = Tk. 1,059.27
Overhead 3.50% = Tk. 370.75
Tk. 12,022.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 699.74
Grand total = Tk. 12,722.48
(i) Ground floor Rate per sft. = Tk. 127.22
Rate per sqm = Tk. 1,369.40

Say, Tk. 1,369 .00 Per sqm.

Item No.- 05.3.2


10 mm thick (finished) silver grey situ mosaic in floor with Pakistani chips and with glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS: (white cement : grey cement = 1:1)
Considering 100 sft. of work
A. Materials:
1. White cement 62.5 kg @ Tk. 25.00 Per kg = Tk. 1,562.50
2. Grey cement 1.25 bag @ Tk. 440.00 Per bag. = Tk. 550.00
3. Pakistani Onix mosaic chips 125 kg @ Tk. 19.00 Per kg = Tk. 2,375.00
4. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
5. 5 x 20 mm glass strip 120 rft. @ Tk. 8.00 Per rft. = Tk. 960.00
6. Cost of patent stone excluding cost of cement for neat
finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 7,829.22
B. Labour:
Same as item No.-- 05.1.1 100 sft. @ Tk. 3,013.50 Per % sft. = Tk. 3,013.50
Total = Tk. 10,842.72
Profit 10.00% = Tk. 1,084.27
Overhead 3.50% = Tk. 379.50
Tk. 12,306.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 716.25
Grand total = Tk. 13,022.74
(i) Ground floor Rate per sft. = Tk. 130.23
Rate per sqm = Tk. 1,401.80

Say, Tk. 1,402 .00 Per sqm.

Item No.- 05.3.3


10 mm thick (finished) silver grey situ mosaic in floor with Indian chips and without glass strip
Analysis of PWD SoR 2014 for Civil Works 104

in/c 25 mm thick patent stone with BRICK-CHIPS: (white cement : grey cement = 1:1)
Considering 100 sft. of work
A. Materials:
1. White cement 62.5 kg @ Tk. 25.00 Per kg = Tk. 1,562.50
2. Grey cement 1.25 bag @ Tk. 440.00 Per bag. = Tk. 550.00
3. India Deradun mosaic chips 125 kg @ Tk. 17.00 Per kg = Tk. 2,125.00
4. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
5. Cost of patent stone excluding cost of cement for neat
finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 6,619.22
B. Labour:
Same as item No.- 05.1.4 100 sft. @ Tk. 2,538.00 Per % sft. = Tk. 2,538.00
Total = Tk. 9,157.22
Profit 10.00% = Tk. 915.72
Overhead 3.50% = Tk. 320.50
Tk. 10,393.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 604.91
Grand total = Tk. 10,998.35
(i) Ground floor Rate per sft. = Tk. 109.98
Rate per sqm = Tk. 1,183.82

Say, Tk. 1,184 .00 Per sqm.

Item No.- 05.3.4


10 mm thick (finished) silver grey situ mosaic in floor with Pakistani chips and without glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS: (white cement : grey cement = 1:1)
Considering 100 sft. of work
A. Materials:
1. White cement 62.5 kg @ Tk. 25.00 Per kg = Tk. 1,562.50
2. Grey cement 1.25 bag @ Tk. 440.00 Per bag. = Tk. 550.00
3. Pakistani Onix mosaic chips 125 kg @ Tk. 19.00 Per kg = Tk. 2,375.00
4. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
5. Cost of patent stone excluding cost of cement for neat
finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 6,869.22
B. Labour:
Same as item No.- 05.1.4 100 sft. @ Tk. 2,538.00 Per % sft. = Tk. 2,538.00
Total = Tk. 9,407.22
Profit 10.00% = Tk. 940.72
Overhead 3.50% = Tk. 329.25
Tk. 10,677.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 621.42
Grand total = Tk. 11,298.61
(i) Ground floor Rate per sft. = Tk. 112.99
Rate per sqm = Tk. 1,216.22

Say, Tk. 1,216 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 105

Item No.- 05.4.1


12 mm thick (finished) silver grey situ mosaic in floor with Indian chips and with glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS: (white cement : grey cement = 1:1)
Considering 100 sft. of work
A. Materials:
1. White cement 70 kg @ Tk. 25.00 Per kg = Tk. 1,750.00
2. Grey cement 1.4 bag @ Tk. 440.00 Per bag. = Tk. 616.00
3. Indian Deradun mosaic chips 140 kg @ Tk. 17.00 Per kg = Tk. 2,380.00
4. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
5. 5 x 20 mm glass strip 120 rft. @ Tk. 8.00 Per rft. = Tk. 960.00
6. Cost of patent stone excluding cost of cement for neat
finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-Total = Tk. 8,087.72
B. Labour:
Same as item No.- 05.1.1 100 sft. @ Tk. 3,013.50 Per % sft. = Tk. 3,013.50
Total = Tk. 11,101.22
Profit 10.00% = Tk. 1,110.12
Overhead 3.50% = Tk. 388.54
Tk. 12,599.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 733.33
Grand total = Tk. 13,333.21
(i) Ground floor Rate per sft. = Tk. 133.33
Rate per sqm = Tk. 1,435.16

Say, Tk. 1,435 .00 Per sqm.

Item No.- 05.4.2


12 mm thick (finished) silver grey situ mosaic in floor with Pakistani chips and with glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS: (white cement : grey cement = 1:1)
Considering 100 sft. of work
A. Materials:
1. White cement 70 kg @ Tk. 25.00 Per kg = Tk. 1,750.00
2. Grey cement 1.4 bags @ Tk. 440.00 Per bag. = Tk. 616.00
3. Pakistan Onix mosaic chips 140 kg @ Tk. 19.00 Per kg = Tk. 2,660.00
4. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
5. 5 x 20 mm glass strip 120 rft. @ Tk. 8.00 Per rft. = Tk. 960.00
6. Cost of patent stone excluding cost of cement for neat
finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 8,367.72
B. Labour:
Same as item No.- 05.1.1 100 sft. @ Tk. 3,013.50 Per % sft. = Tk. 3,013.50
Total = Tk. 11,381.22
Profit 10.00% = Tk. 1,138.12
Overhead 3.50% = Tk. 398.34
Tk. 12,917.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 751.82
Grand total = Tk. 13,669.50
(i) Ground floor Rate per sft. = Tk. 136.70
Rate per sqm = Tk. 1,471.44

Say, Tk. 1,471 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 106

Item No.- 05.4.3


12 mm thick (finished) silver grey situ mosaic in floor with Indian chips and without glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS: (white cement : grey cement = 1:1)
Considering 100 sft. of work
A. Materials:
1. White cement 70 kg @ Tk. 25.00 Per kg = Tk. 1,750.00
2. Grey cement 1.4 bag @ Tk. 440.00 Per bag. = Tk. 616.00
3. Indian Deradun mosaic chips 140 kg @ Tk. 17.00 Per kg = Tk. 2,380.00
4. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
5. Cost of patent stone excluding cost of cement
for neat finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 7,127.72
B. Labour:
Same as item No.- 05.1.4 100 sft. @ Tk. 2,538.00 Per % sft. = Tk. 2,538.00
Total = Tk. 9,665.72
Profit 10.00% = Tk. 966.57
Overhead 3.50% = Tk. 338.30
Tk. 10,970.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 638.50
Grand total = Tk. 11,609.09
(i) Ground floor Rate per sft. = Tk. 116.09
Rate per sqm = Tk. 1,249.59

Say, Tk. 1,250 .00 Per sqm.

Item No.- 05.4.4


12 mm thick (finished) silver grey situ mosaic in floor with Pakistani chips and without glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS: (white cement : grey cement = 1:1)
Considering 100 sft. of work
A. Materials:
1. White cement 70 kg @ Tk. 25.00 Per kg = Tk. 1,750.00
2. Grey cement 1.4 bag @ Tk. 440.00 Per bag. = Tk. 616.00
3. Pakistani Onix mosaic chips 140 kg @ Tk. 19.00 Per kg = Tk. 2,660.00
4. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
5. Cost of patent stone excluding cost of cement
for neat finish and 1/4 No. mason. 100 sft. @ Tk. 2,248.39 Per % sft. = Tk. 2,248.39
Sub-total = Tk. 7,407.72
B. Labour:
Same as item No-05.1.4 100 sft. @ Tk. 2,538.00 Per % sft. = Tk. 2,538.00
Total = Tk. 9,945.72
Profit 10.00% = Tk. 994.57
Overhead 3.50% = Tk. 348.10
Tk. 11,288.39
Add VAT with adjustment factor 1.0582 5.50% = Tk. 657.00
Grand total = Tk. 11,945.39
(i) Ground floor Rate per sft. = Tk. 119.45
Rate per sqm = Tk. 1,285.76

Say, Tk. 1,286 .00 Per sqm.

Item No.- 05.5.1


10 mm thick (finished) mosaic on wall with Indian chips using 100% white cement.
Considering 100 sft. of work
A. Materials:
1. White cement 125 kg @ Tk. 25.00 Per kg = Tk. 3,125.00
2. Indian Deradun mosaic chips 125 kg @ Tk. 17.00 Per kg = Tk. 2,125.00
3. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
Analysis of PWD SoR 2014 for Civil Works 107

4. 1/2" thick plaster (1:4) 100 sft. @ Tk. 15.27 Per sft. = Tk. 1,527.00
Sub-total = Tk. 6,910.33
B. Labour:
(a) For mixing, laying, compacting and curing:
1. Head mason 1 No. @ Tk. 493.00 each = Tk. 493.00
2. Skilled labour 3/4 No. @ Tk. 303.00 each = Tk. 227.25
3. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(b) For cutting mosaic mosaic wall surface with mumic stone:
1. Skilled labour 10 Nos. @ Tk. 303.00 each = Tk. 3,030.00
2. Pumic stone 2.5 Nos. @ Tk. 60.00 each = Tk. 150.00
(c) For spreading oxalic acid and washing:
1. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Sub-total = Tk. 4,390.25
Total (A+B) = Tk. 11,300.58
Profit 10.00% = Tk. 1,130.06
Overhead 3.50% = Tk. 395.52
Tk. 12,826.16
Add VAT with adjustment factor 1.0582 5.50% = Tk. 746.50
Grand total = Tk. 13,572.66
(i) Ground floor Rate per sft. = Tk. 135.73
Rate per sqm = Tk. 1,461.00

Say, Tk. 1,461 .00 Per sqm.

Item No.- 05.5.2


10 mm thick (finished) mosaic on wall with Pakistani chip susing 100% white cement.
Considering 100 sft. of work
A. Materials
1. White cement 125 kg @ Tk. 25.00 Per kg = Tk. 3,125.00
2. Pakistan Onix mosaic chips 125 kg @ Tk. 19.00 Per kg = Tk. 2,375.00
3. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. 1/2" thick plaster (1:4) 100 sft. @ Tk. 15.27 Per sft. = Tk. 1,527.00
Sub-total = Tk. 7,160.33
B. Labour:
Same as item No.- 05.5.1 100 sft. @ Tk. 4,390.25 Per % sft. = Tk. 4,390.25
Total = Tk. 11,550.58
Profit 10.00% = Tk. 1,155.06
Overhead 3.50% = Tk. 404.27
Tk. 13,109.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 763.01
Grand total = Tk. 13,872.92
(i) Ground floor Rate per sft. = Tk. 138.73
Rate per sqm = Tk. 1,493.29

Say, Tk. 1,493 .00 Per sqm.


Item No.- 05.6.1
10 mm thick (finished) mosaic on wall with Indian chips: (White cement : Grey cement = 1 : 1)
Considering 100 sft. of work
A. Materials:
1. White cement 62.5 kg @ Tk. 25.00 Per kg = Tk. 1,562.50
2. Grey cement 1.25 bag @ Tk. 440.00 Per bag = Tk. 550.00
3. Indian Deradun mosaic chips 125 kg @ Tk. 17.00 Per kg = Tk. 2,125.00
4. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
5. 1/2" thick plaster (1:4) 100 sft. @ Tk. 15.27 Per sft. = Tk. 1,527.00
Sub-total = Tk. 5,897.83
B. Labour:
(a) For mixing, laying, compacting & curing:
Analysis of PWD SoR 2014 for Civil Works 108

1. Head mason 1 No. @ Tk. 493.00 each = Tk. 493.00


2. Skilled labour 3/4 No. @ Tk. 303.00 each = Tk. 227.25
3. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(b) Labour for cutting mosaic wall surface with mumic stone:
1. Skilled labour 10 Nos. @ Tk. 303.00 each = Tk. 3,030.00
2. Pumic stone 2.5 Nos. @ Tk. 60.00 each = Tk. 150.00
(c) For spreading oxalic acid and washing:
1. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Sub-total = Tk. 4,390.25
Total (A+B) = Tk. 10,288.08
Profit 10.00% = Tk. 1,028.81
Overhead 3.50% = Tk. 360.08
Tk. 11,676.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 679.61
Grand total = Tk. 12,356.58
(i) Ground floor Rate per sft. = Tk. 123.57
Rate per sqm = Tk. 1,330.11

Say, Tk. 1,330 .00 Per sqm.

Item No.- 05.6.2


10 mm thick (finished) mosaic on wall with Pakistani chips: (White cement : Grey cement = 1 : 1)
Considering 100 sft. of work
A. Materials:
1. White cement 62.5 kg @ Tk. 25.00 Per kg = Tk. 1,562.50
2. Grey cement 1.25 bag @ Tk. 440.00 Per bag = Tk. 550.00
3. Pakistani Onix mosaic chips 125 kg @ Tk. 19.00 Per kg = Tk. 2,375.00
4. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
5. 1/2" thick plaster (1:4) 100 sft. @ Tk. 15.27 Per sft. = Tk. 1,527.00
Sub-total = Tk. 6,147.83
B. Labour:
Same as item No.- 05.6.1 100 sft. @ Tk. 4,390.25 Per % sft. = Tk. 4,390.25
Total (A+B) = Tk. 10,538.08
Profit 10.00% = Tk. 1,053.81
Overhead 3.50% = Tk. 368.83
Tk. 11,960.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 696.13
Grand total = Tk. 12,656.85
(i) Ground floor Rate per sft. = Tk. 126.57
Rate per sqm = Tk. 1,362.40

Say, Tk. 1,362 .00 Per sqm.


Item No.- 05.6.3
10 mm thick (finished) mosaic on wall with Indian chips using 100% grey cement
Considering 100 sft. of work
A. Materials:
1. Grey cement 2.5 bag @ Tk. 440.00 Per bag = Tk. 1,100.00
2. Indian deradun mosaic chips 125 kg @ Tk. 17.00 Per kg = Tk. 2,125.00
3. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
4. 1/2" thick plaster (1:4) 100 sft. @ Tk. 15.27 Per sft. = Tk. 1,527.00
Sub-total = Tk. 4,885.33
B. Labour:
Same as item No.- 05.6.1 100 sft. @ Tk. 4,390.25 Per % sft. = Tk. 4,390.25
Total (A+B) = Tk. 9,275.58
Profit 10.00% = Tk. 927.56
Overhead 3.50% = Tk. 324.65
Tk. 10,527.79
Analysis of PWD SoR 2014 for Civil Works 109

Add VAT with adjustment factor 1.0582 5.50% = Tk. 612.73


Grand total = Tk. 11,140.52
(i) Ground floor Rate per sft. = Tk. 111.41
Rate per sqm = Tk. 1,199.22

Say, Tk. 1,199 .00 Per sqm.

Item No.- 05.7.1


10 mm thick (finished) coloured mosaic in floor with Indian chips and with glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Cost of materials, labour in/c T & P:
Same as item No.- 05.1.1 100 sft. @ Tk. 11,605.22 Per % sft. = Tk. 11,605.22
B. Add for colour pigment 8 Ibs @ Tk. 55.00 Per Ib. = Tk. 440.00
Total = Tk. 12,045.22
Profit 10.00% = Tk. 1,204.52
Overhead 3.50% = Tk. 421.58
Tk. 13,671.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 795.68
Grand total = Tk. 14,467.00
(i) Ground floor Rate per sft. = Tk. 144.67
Rate per sqm = Tk. 1,557.23

Say, Tk. 1,557 .00 Per sqm.

Item No.- 05.7.2


10 mm thick (finished) coloured mosaic in floor with Pakistani chips and with glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Cost of materials, labour in/c T & P:
Same as item No.- 05.1.3 100 sft. @ Tk. 11,855.22 Per % sft. = Tk. 11,855.22
B. Add for colour pigment 8 Ibs @ Tk. 55.00 Per Ib. = Tk. 440.00
Total = Tk. 12,295.22
Profit 10.00% = Tk. 1,229.52
Overhead 3.50% = Tk. 430.33
Tk. 13,955.07
Add VAT with adjustment factor 1.0582 5.50% = Tk. 812.20
Grand total = Tk. 14,767.27
(i) Ground floor Rate per sft. = Tk. 147.67
Rate per sqm = Tk. 1,589.52

Say, Tk. 1,590 .00 Per sqm.

Item No.- 05.7.3


10 mm thick (finished) coloured mosaic in floor with Indian chips and without glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS.
Considering 100 sft of work
A. Cost of materials, labour in/c T & P:
Same as item No.- 05.1.4 100 sft. @ Tk. 10,169.72 Per % sft. = Tk. 10,169.72
B. Add for colour pigment 8 Ibs @ Tk. 55.00 Per Ib. = Tk. 440.00
Total = Tk. 10,609.72
Profit 10.00% = Tk. 1,060.97
Overhead 3.50% = Tk. 371.34
Tk. 12,042.03
Add VAT with adjustment factor 1.0582 5.50% = Tk. 700.86
Grand total = Tk. 12,742.89
(i) Ground floor Rate per sft. = Tk. 127.43
Analysis of PWD SoR 2014 for Civil Works 110

Rate per sqm = Tk. 1,371.66

Say, Tk. 1,372 .00 Per sqm.

Item No.- 05.7.4


10 mm thick (finished) coloured mosaic in floor with Pakistani chips and without glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Cost of materials, labour in/c T & P:
Same as item No.- 05.3.4 100 sft. @ Tk. 9,407.22 Per % sft. = Tk. 9,407.22
B. Add for colour pigment 8 Ibs @ Tk. 55.00 Per Ib. = Tk. 440.00
Total = Tk. 9,847.22
Profit 10.00% = Tk. 984.72
Overhead 3.50% = Tk. 344.65
Tk. 11,176.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 650.49
Grand total = Tk. 11,827.08
(i) Ground floor Rate per sft. = Tk. 118.27
Rate per sqm = Tk. 1,273.06

Say, Tk. 1,273 .00 Per sqm.

Item No.- 05.8.1


12 mm thick (finished) coloured mosaic in floor with Indian chips and with glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS.
Considering 100 sft. work
A. Cost of materials, labour in/c T & P:
Same as item No. 5.2.1 100 sft. @ Tk. 12,235.22 Per sft. = Tk. 12,235.22
B. Add for colour pigment 8 Ibs @ Tk. 55.00 Per Ib. = Tk. 440.00
Total = Tk. 12,675.22
Profit 10.00% = Tk. 1,267.52
Overhead 3.50% = Tk. 443.63
Tk. 14,386.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 837.30
Grand total = Tk. 15,223.67
(i) Ground floor Rate per sft. = Tk. 152.24
Rate per sqm = Tk. 1,638.71

Say, Tk. 1,639 .00 Per sqm.

Item No.- 05.8.2


12 mm thick (finished) coloured mosaic in floor with Pakistani chips and with glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Cost of materials, labour in/c T & P:
Same as item No. 5.2.2 100 sft. @ Tk. 12,515.22 Per % sft. = Tk. 12,515.22
B. Add for colour pigment 8 Ibs @ Tk. 55.00 Per Ib. = Tk. 440.00
Total = Tk. 12,955.22
Profit 10.00% = Tk. 1,295.52
Overhead 3.50% = Tk. 453.43
Tk. 14,704.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 855.80
Grand total = Tk. 15,559.97
(i) Ground floor Rate per sft. = Tk. 155.60
Rate per sqm = Tk. 1,674.88

Say, Tk. 1,675 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 111

Item No.- 05.8.3


12 mm thick (finished) coloured mosaic in floor with Indian chips and without glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Cost of materials, labour in/c T & P:
Same as item No. 5.2.3 100 sft. @ Tk. 10,799.72 Per % sft. = Tk. 10,799.72
B. Add for colour pigment 8 Ibs @ Tk. 55.00 Per Ib. = Tk. 440.00
Total = Tk. 11,239.72
Profit 10.00% = Tk. 1,123.97
Overhead 3.50% = Tk. 393.39
Tk. 12,757.08
Add VAT with adjustment factor 1.0582 5.50% = Tk. 742.47
Grand total = Tk. 13,499.55
(i) Ground floor Rate per sft. = Tk. 135.00
Rate per sqm = Tk. 1,453.14

Say, Tk. 1,453 .00 Per sqm.


Item No.- 05.8.4
12 mm thick (finished) coloured mosaic in floor with Pakistani chips and without glass strip
in/c 25 mm thick patent stone with BRICK-CHIPS.
Considering 100 sft. of work
A. Cost of materials, labour in/c T & P:
Same as item No. 5.2.4 100 sft. @ Tk. 11,079.72 Per % sft. = Tk. 11,079.72
B. Add for colour pigment 8 Ibs @ Tk. 55.00 Per Ib. = Tk. 440.00
Total = Tk. 11,519.72
Profit 10.00% = Tk. 1,151.97
Overhead 3.50% = Tk. 403.19
Tk. 13,074.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 760.97
Grand total = Tk. 13,835.85
(i) Ground floor Rate per sft. = Tk. 138.36
Rate per sqm = Tk. 1,489.31

Say, Tk. 1,489 .00 Per sqm.


Item No.- 05.9.1
10 mm thick (finished) coloured mosaic on wall with Indian chips
Considering 100 sft. of work
A. Cost of materials, labour in/c T & P:
Same as item No. 5.5.1 100 sft. @ Tk. 11,300.58 Per % sft. = Tk. 11,300.58
B. Add for colour pigment 8 Ibs @ Tk. 55.00 Per Ib. = Tk. 440.00
Total = Tk. 11,740.58
Profit 10.00% = Tk. 1,174.06
Overhead 3.50% = Tk. 410.92
Tk. 13,325.56
Add VAT with adjustment factor 1.0582 5.50% = Tk. 775.56
Grand total = Tk. 14,101.12
(i) Ground floor Rate per sft. = Tk. 141.01
Rate per sqm = Tk. 1,517.83

Say, Tk. 1,518 .00 Per sqm.


Item No.- 05.9.2
10mm thick (finished) coloured mosaic on wall with Pakistani chips
Considering 100 sft. of work
A. Cost of materials, labour in/c T & P:
Same as item No. 5.5.2 100 sft. @ Tk. 11,550.58 Per % sft. = Tk. 11,550.58
B. Add for colour pigment 8 Ibs @ Tk. 55.00 Per Ib. = Tk. 440.00
Analysis of PWD SoR 2014 for Civil Works 112

Total = Tk. 11,990.58


Profit 10.00% = Tk. 1,199.06
Overhead 3.50% = Tk. 419.67
Tk. 13,609.31
Add VAT with adjustment factor 1.0582 5.50% = Tk. 792.08
Grand total = Tk. 14,401.39
(i) Ground floor Rate per sft. = Tk. 144.01
Rate per sqm = Tk. 1,550.12

Say, Tk. 1,550 .00 Per sqm.

Item No.- 05.10.1


200 x 200 x 20 mm (finished) mosaic terrazo tiles flooring with Indian chips
Considering 100 sft. of work
(a) Cost of materials
a) Sand-cement mortar base (3:1):
1. Grey cement for mortar & slury 4.25 bags @ Tk. 440.00 Per bag = Tk. 1,870.00
2. Sand (F.M.1.2) 7 cft. @ Tk. 1,700.00 Per % cft. = Tk. 119.00
3. Sand (F.M. 2.5) 7 cft. @ Tk. 3,000.00 Per % cft. = Tk. 210.00
b) Bottom of the tiles: sand - cement (2:1):
1. Grey cement 1.33 bags @ Tk. 440.00 Per bag = Tk. 585.20
2. Sand (F.M. 1.2) 1.67 cft. @ Tk. 1,700.00 Per % cft. = Tk. 28.39
3. Sand (F.M. 2.5) 1.67 cft. @ Tk. 3,000.00 Per % cft. = Tk. 50.10
c) Top of the tiles:
1. White cement 112.5 kg @ Tk. 25.00 Per kg = Tk. 2,812.50
2. Grey cement 0.25 bags @ Tk. 440.00 Per bag = Tk. 110.00
3. Indian Deradun mosaic chips 125 kg @ Tk. 17.00 Per kg = Tk. 2,125.00
Sub-total = Tk. 7,910.19
(b) Labour charges and others
a) Charges for mosaic tiles making:
1. Hire charges & setting
up machine 1 day @ Tk. 300.00 Per day = Tk. 300.00
2. Machine operator 3/4 No. @ Tk. 423.00 each = Tk. 317.25
3. Foreman 1/4 No. @ Tk. 567.00 each = Tk. 141.75
b) Labour for laying tiles:
1. Mosaic head mistry 1/2 No. @ Tk. 493.00 each = Tk. 246.50
2. Mosaic mistry 1/2 No. @ Tk. 415.00 each = Tk. 207.50
3. Ordinary labour 1/2 No. @ Tk. 245.00 each = Tk. 122.50
(c) Labour for curing:
1. Ordinary labour after making 1 No. @ Tk. 245.00 each = Tk. 245.00
2. Ordinary labour after laying 1/4 No. @ Tk. 245.00 each = Tk. 61.25
(d) Mosaic cutting machine:
1. Hire charge of machine 1 No. @ Tk. 300.00 Per day = Tk. 300.00
2. Machine operator 1 No. @ Tk. 423.00 each = Tk. 423.00
3. Helper/skilled operator 1 No. @ Tk. 303.00 Per day = Tk. 303.00
4. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
5. Pumic stone 3 Nos. @ Tk. 60.00 each = Tk. 180.00
6. Minar stone 1/3 No. @ Tk. 400.00 each = Tk. 133.33
(e) Labour for spreading acid & washing etc.:
1. Skilled labour 1/2 No. @ Tk. 303.00 each = Tk. 151.50
Sub-total = Tk. 3,377.58
Total (A+B) = Tk. 11,287.77
Profit 10.00% = Tk. 1,128.78
Overhead 3.50% = Tk. 395.07
Tk. 12,811.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 745.65
Grand total = Tk. 13,557.27
Analysis of PWD SoR 2014 for Civil Works 113

(i) Ground floor Rate per sft. = Tk. 135.57


Rate per sqm = Tk. 1,459.28

Say, Tk. 1,459 .00 Per sqm.

Item No.- 05.10.2


200 x 200 x 20 mm (finished) mosaic terrazo tiles flooring with Pakistani chips.
Considering 100 sft. of work
1. Cost of materials& labour:
Same as item No. 5.10.1 100 sft. @ Tk. 11,287.77 Per % sft. = Tk. 11,287.77
2. Less cost of Indian (deradun)
mosaic chips -120 kg @ Tk. 17.00 Per kg = Tk. (2,040.00)
3. Add cost of Pakistani (Onix)
mosaic chips 120 kg @ Tk. 19.00 Per kg = Tk. 2,280.00
Total = Tk. 11,527.77
Profit 10.00% = Tk. 1,152.78
Overhead 3.50% = Tk. 403.47
Tk. 13,084.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 761.50
Grand total = Tk. 13,845.52
(i) Ground floor Rate per sft. = Tk. 138.46
Rate per sqm = Tk. 1,490.38

Say, Tk. 1,490 .00 Per sqm.

Item No.- 05.11


Extra rate for each additional floor for mosaic and terazzo tiles works
(Item Nos. 5.1 to 5.10)
05.11.1 Add for each addl. floor up to 5th floor (@ 0.25 No. lab per % sft.) Per sqm = Tk. 8.00
05.11.2 Add for each addl. floor for 6th floor to 9th floor (@ 0.5 No. lab per % sft.) Per sqm = Tk. 16.00
05.11.3 Add for each addl. floor for 10th floor and above (@ 0.75 No. lab per % sft.) Per sqm = Tk. 24.00
Analysis of PWD SoR 2014 for Civil Works 114

DIVISION 06 : GLAZED TILES AND MARBLE STONE WORK


Item No.- 06.1.1
Marble stone flooring with 18 mm thick Indian black/ white marble stone
Considering 100 ( 10'-0" x 10'-0") sft. of work
(a) Cost of materials
1. 18 mm thick marble stone 100 sft. @ Tk. 395.00 Per sft = Tk. 39,500.00
2. White cement 4 kg @ Tk. 25.00 Per kg = Tk. 100.00
3. Grey cement for sand cement
mortar base & slury 3.64 bag @ Tk. 440.00 Per bag. = Tk. 1,601.60
4. Sand (F.M. 1.2) 4.16 cft. @ Tk. 1,700.00 Per % cft. = Tk. 70.72
5. Sand (F.M. 2.5) 4.16 cft. @ Tk. 3,000.00 Per % cft. = Tk. 124.80
Sub-total = Tk. 41,397.12
(b) Cost for cutting, shaping, tools and plants etc.
1. Hire charge of cutting and shaping
machine in/c cutting disc. 1 day @ Tk. 300.00 Per day = Tk. 300.00
2. Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
3. Machine operator 1 No. @ Tk. 423.00 each = Tk. 423.00
4. Helper 1 No. @ Tk. 304.00 each = Tk. 304.00
Sub-total = Tk. 1,594.00
(c) Labour cost for laying
1. Mason 5.5 Nos. @ Tk. 389.00 each = Tk. 2,139.50
2. Helper 2.0 Nos. @ Tk. 304.00 each = Tk. 608.00
Sub-total = Tk. 2,747.50
(d) Polishing
1. Hire charge of marble polishing
machine in/c polishing stone 2.5 days @ Tk. 400.00 Per day = Tk. 1,000.00
2. Operator 2.5 Nos. @ Tk. 423.00 each = Tk. 1,057.50
3. Helper 2.5 Nos. @ Tk. 304.00 each = Tk. 760.00
Sub-total = Tk. 2,817.50
Total (A+B+C+D) = Tk. 48,556.12
Profit 10.00% = Tk. 4,855.61
Overhead 3.50% = Tk. 1,699.46
Tk. 55,111.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,207.53
Grand total = Tk. 58,318.72
(i) Ground floor Rate per sft. = Tk. 583.19
Rate per sqm = Tk. 6,277.46

Say, Tk. 6,277 .00 Per sqm.


Item No.- 06.1.2
Marble stone flooring with 16 mm thick Indian black/ white marble stone
Considering 100 ( 10'-0" x 10'-0") sft. of work
A. Cost of marble works: Same as item No. 6.1.1 = Tk. 48,556.12
Less cost of 18 mm thick marble stone = Tk. (39,500.00)
Total = Tk. 9,056.12
B. 16 mm thick marble stone 100 sft. @ Tk. 350.00 Per sft. = Tk. 35,000
Sub-total = Tk. 44,056.12
Profit 10.00% = Tk. 4,405.61
Overhead 3.50% = Tk. 1,541.96
Tk. 50,003.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,910.26
Grand total = Tk. 52,913.95
(i) Ground floor Rate per sft. = Tk. 529.14
Rate per sqm = Tk. 5,695.66

Say, Tk. 5,696 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 115

Item No.- 06.2.1


Marble stone flooring with 18 mm thick Indian coloured/ grey marble stone
Considering 100 ( 10'-0" x 10'-0") sft. of work
(a) Cost of materials
1. 18 mm thick marble stone 100 sft. @ Tk. 410.00 Per sft = Tk. 41,000.00
2. White cement 4 kg @ Tk. 25.00 Per kg = Tk. 100.00
3. Grey cement for sand cement
mortar base & slury 3.64 bag @ Tk. 440.00 Per bag. = Tk. 1,601.60
4. Sand (F.M. 1.2) 4.16 cft. @ Tk. 1,700.00 Per % cft. = Tk. 70.72
5. Sand (F.M. 2.5) 4.16 cft. @ Tk. 3,000.00 Per % cft. = Tk. 124.80
Sub-total = Tk. 42,897.12
(b) Cost for cutting, shaping, tools and plants etc.
1. Hire charge of cutting and shaping
machine in/c cutting disc. 1 day @ Tk. 300.00 Per day = Tk. 300.00
2. Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
3. Machine operator 1 No. @ Tk. 423.00 each = Tk. 423.00
4. Helper 1 No. @ Tk. 304.00 each = Tk. 304.00
Sub-total = Tk. 1,594.00
(c) Labour cost for laying
1. Mason 5.5 Nos. @ Tk. 389.00 each = Tk. 2,139.50
2. Helper 2.0 Nos. @ Tk. 304.00 each = Tk. 608.00
Sub-total = Tk. 2,747.50
(d) Polishing
1. Hire charge of marble polishing
machine in/c polishing stone 2.5 days @ Tk. 400.00 Per day = Tk. 1,000.00
2. Operator 2.5 Nos. @ Tk. 423.00 each = Tk. 1,057.50
3. Helper 2.5 Nos. @ Tk. 304.00 each = Tk. 760.00
Sub-total = Tk. 2,817.50
Total (A+B+C+D) = Tk. 50,056.12
Profit 10.00% = Tk. 5,005.61
Overhead 3.50% = Tk. 1,751.96
Tk. 56,813.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,306.61
Grand total = Tk. 60,120.30
(i) Ground floor Rate per sft. = Tk. 601.20
Rate per sqm = Tk. 6,471.32

Say, Tk. 6,471 .00 Per sqm.

Item No.- 06.2.2


Marble stone flooring with 16 mm thick Indian coloured/ grey marble stone
Considering 100 sft. of work
A. Cost of marble works: Same as item No. 6.1.1 = Tk. 50,056.12
Less cost of 18 mm thick marble stone = Tk. (41,000.00)
Total = Tk. 9,056.12
B. 16 mm thick marble stone 100 sft. @ Tk. 360.00 Per sft. = Tk. 36,000
Sub-total = Tk. 45,056.12
Profit 10.00% = Tk. 4,505.61
Overhead 3.50% = Tk. 1,576.96
Tk. 51,138.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,976.32
Grand total = Tk. 54,115.01
(i) Ground floor Rate per sft. = Tk. 541.15
Rate per sqm = Tk. 5,824.94

Say, Tk. 5,825 .00 Per sqm.


Item No.- 06.3.1
Analysis of PWD SoR 2014 for Civil Works 116

Marble stone on walls with 12 mm thick Indian white / black marble stone
Considering 100 sft. of work
A. Cost of materials
1. 12 mm thick marble stone 100 sft. @ Tk. 315.00 Per sft. = Tk. 31,500.00
2. Grey cement 1.7 bag @ Tk. 440.00 Per bag = Tk. 748.00
3. Sand (F.M. 1.2) 2.08 cft. @ Tk. 1,700.00 Per % cft. = Tk. 35.36
4. Sand (F.M. 2.2) 2.08 cft. @ Tk. 3,000.00 Per % cft. = Tk. 62.40
5. White cement 4 kg @ Tk. 25.00 Per kg = Tk. 100.00
Sub-total = Tk. 32,445.76
B. Cost for cutting, shaping, tools and plants etc.
1. Hire charge of cutting and shaping
machine in/c cutting disc. 1 day @ Tk. 300.00 Per day = Tk. 300.00
2. Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
3. Machine operator 1 No. @ Tk. 423.00 each = Tk. 423.00
4. Helper 1 No. @ Tk. 304.00 each = Tk. 304.00
Sub-total = Tk. 1,594.00
C. Labour cost for laying
1. Mason 5.5 Nos. @ Tk. 389.00 each = Tk. 2,139.50
2. Helper 2 Nos. @ Tk. 304.00 each = Tk. 608.00
3. Scaffolding 100 sft. @ Tk. 7.20 Per sft. = Tk. 720.00
Sub-total = Tk. 3,467.50
D. Polishing
1. Hire charge of marble polishing
machine in/c polishing stone 2.5 days @ Tk. 400.00 Per day = Tk. 1,000.00
2. Machine operator 2.5 Nos. @ Tk. 423.00 each = Tk. 1,057.50
3. Helper 2.5 Nos. @ Tk. 304.00 each = Tk. 760.00
Sub-total = Tk. 2,817.50
Total (A+B+C+D) = Tk. 40,324.76
Profit 10.00% = Tk. 4,032.48
Overhead 3.50% = Tk. 1,411.37
Tk. 45,768.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,663.78
Grand total = Tk. 48,432.39
(i) Ground floor Rate per sft. = Tk. 484.32
Rate per sqm = Tk. 5,213.22

Say, Tk. 5,213 .00 Per sqm.

Item No.- 06.3.2


Marble stone on walls with 12 mm thick Indian coloured / grey marble stone
Considering 100 sft. of work
A. Cost of materials
1. 12 mm thick marble stone 100 sft. @ Tk. 345.00 Per sft. = Tk. 34,500.00
2. Grey cement 1.7 bag @ Tk. 440.00 Per bag = Tk. 748.00
3. Sand (F.M. 1.2) 2.08 cft. @ Tk. 1,700.00 Per % cft. = Tk. 35.36
4. Sand (F.M. 2.2) 2.08 cft. @ Tk. 3,000.00 Per % cft. = Tk. 62.40
5. White cement 4 kg @ Tk. 25.00 Per kg = Tk. 100.00
Sub-total = Tk. 35,445.76
B. Cost for cutting, shaping, tools and plants etc.
1. Hire charge of cutting and shaping
machine in/c cutting disc. 1 day @ Tk. 300.00 Per day = Tk. 300.00
2. Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
3. Machine operator 1 No. @ Tk. 423.00 each = Tk. 423.00
4. Helper 1 No. @ Tk. 304.00 each = Tk. 304.00
Sub-total = Tk. 1,594.00
C. Labour cost for laying
1. Mason 5.5 Nos. @ Tk. 389.00 each = Tk. 2,139.50
Analysis of PWD SoR 2014 for Civil Works 117

2. Helper 2 Nos. @ Tk. 304.00 each = Tk. 608.00


3. Scaffolding 100 sft. @ Tk. 7.20 Per sft. = Tk. 720.00
Sub-total = Tk. 3,467.50
D. Polishing
1. Hire charge of marble polishing
machine in/c polishing stone 2.5 days @ Tk. 400.00 Per day = Tk. 1,000.00
2. Machine operator 2.5 Nos. @ Tk. 423.00 each = Tk. 1,057.50
3. Helper 2.5 Nos. @ Tk. 304.00 each = Tk. 760.00
Sub-total = Tk. 2,817.50
Total (A+B+C+D) = Tk. 43,324.76
Profit 10.00% = Tk. 4,332.48
Overhead 3.50% = Tk. 1,516.37
Tk. 49,173.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,861.95
Grand total = Tk. 52,035.56
(i) Ground floor Rate per sft. = Tk. 520.36
Rate per sqm = Tk. 5,601.16

Say, Tk. 5,601 .00 Per sqm.

Item No.- 06.4


Marble stone FLOORING with 18 mm thick grey / coloured marble stone Italy

Considering 100 sft. of work


A. Cost of marble works excluding cost of marble stone: from item 06.1.2 = Tk. 9,056.12
B. 18 mm thick coloured
marble stone 100 sft. @ Tk. 550.00 Per sft. = Tk. 55,000.00
Sub-total = Tk. 64,056.12
Profit 10.00% = Tk. 6,405.61
Overhead 3.50% = Tk. 2,241.96
Tk. 72,703.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4,231.43
Grand total = Tk. 76,935.12
(i) Ground floor Rate per sft. = Tk. 769.35
Rate per sqm = Tk. 8,281.28

Say, Tk. 8,281 .00 Per sqm.

Item No.- 06.5.1


Labour Cost for making moulding in 18 mm tkick marble stone

Considering, 12 X 3'-2" = 38.04 rft


a) Labour cost for moulding:
i) Head Mason 2 No. @ Tk. 493.00 Each = Tk. 986.00
i) Helper 2 No. @ Tk. 245.00 Each = Tk. 490.00
b) Cost of Materials and Equipment:
i) Disk 1 No. @ Tk. 775.14 Per day = Tk. 775.14
ii) Water Proofing Paper (12 Size) 8 No. @ Tk. 17.00 Each = Tk. 136.00
iii) Water Proofing Paper (320 Size) 8 No. @ Tk. 20.00 Each = Tk. 160.00
iv) Hire charge of Electric grinding
Machine 2 Days @ Tk. 206.00 Per day = Tk. 412.00
v) Acid stone 1 No. @ Tk. 384.00 Each = Tk. 384.00
Total = Tk. 3,343.14
Profit 10.00% = Tk. 334.31
Overhead 3.50% = Tk. 117.01
= Tk. 3,794.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 220.84
Analysis of PWD SoR 2014 for Civil Works 118

Grand total = Tk. 4,015.30


Rate per rft. = Tk. 105.55
Rate per rm. = Tk. 346.31

Say Tk. 346 .00 Per rm


Item No.- 06.5.2
Labour Cost for making moulding in 16 mm tkick marble stone

Considering, 12 X 3'-2" = 38.04 rft


a) Labour cost for moulding:
i) Head Mason 2 No. @ Tk. 493.00 Each = Tk. 986.00
i) Helper 2 No. @ Tk. 245.00 Each = Tk. 490.00
b) Cost of Materials and Equipment:
i) Disk 1 No. @ Tk. 775.14 Per day = Tk. 775.14
ii) Water Proofing Paper (12 Size) 7 No. @ Tk. 17.00 Each = Tk. 119.00
iii) Water Proofing Paper (320 Size) 7 No. @ Tk. 20.00 Each = Tk. 140.00
iv) Hire charge of Electric grinding
Machine 2 Days @ Tk. 206.00 Per day = Tk. 412.00
v) Acid stone 1 No. @ Tk. 384.00 Each = Tk. 384.00
Total = Tk. 3,306.14
Profit 10.00% = Tk. 330.61
Overhead 3.50% = Tk. 115.71
= Tk. 3,752.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 218.40
Grand total = Tk. 3,970.86
Rate per rft. = Tk. 104.39
Rate per rm. = Tk. 342.50

Say Tk. 343 .00 Per rm


Item No.- 06.5.3
Labour Cost for making moulding in 12 mm tkick marble stone

Considering, 12 X 3'-2" = 38.04 rft


a) Labour cost for moulding:
i) Head Mason 1.5 No. @ Tk. 493.00 Each = Tk. 739.50
i) Helper 1.5 No. @ Tk. 245.00 Each = Tk. 367.50
b) Cost of Materials and Equipment:
i) Disk 1 No. @ Tk. 775.14 Per day = Tk. 775.14
ii) Water Proofing Paper (12 Size) 6 No. @ Tk. 17.00 Each = Tk. 102.00
iii) Water Proofing Paper (320 Size) 8 No. @ Tk. 20.00 Each = Tk. 160.00
iv) Hire charge of Electric grinding
Machine 2 Days @ Tk. 206.00 Per day = Tk. 412.00
v) Acid stone 1 No. @ Tk. 384.00 Each = Tk. 384.00
Total = Tk. 2,940.14
Profit 10.00% = Tk. 294.01
Overhead 3.50% = Tk. 102.90
= Tk. 3,337.05
Add VAT with adjustment factor 1.0582 5.50% = Tk. 194.22
Grand total = Tk. 3,531.27
Rate per rft. = Tk. 92.83
Rate per rm. = Tk. 304.58

Say Tk. 305 .00 Per rm


Item No.- 06.6.1
Supplying, fitting and fixing glazed WALL tiles on cement mortar base (3:1):
Laying cost on walls excluding cost of glazed tiles.
Considering 100 sft. of work
Analysis of PWD SoR 2014 for Civil Works 119

A. Cost of materials for base with 3/4'' (av.) thick cement mortar: (3:1):
1 Cement 1.87 bags @ Tk. 440.00 Per bag = Tk. 822.80
2. Sand (F.M. 1.2) 7.03 cft. @ Tk. 1,700.00 Per % cft. = Tk. 119.51
3. White cement 3.60 kg @ Tk. 25.00 Per kg = Tk. 90.00
B. Labour cost:
1. Head mason 2.00 Nos. @ Tk. 493.00 each = Tk. 986.00
2. Mason 2.00 Nos. @ Tk. 389.00 each = Tk. 778.00
3. Skilled labour 3.00 Nos. @ Tk. 303.00 each = Tk. 909.00
4. Ordinary labour 3.00 Nos. @ Tk. 245.00 each = Tk. 735.00
5. Local carriage, sundries, T & P & washing of sand etc. L.S. = Tk. 245.00
Total = Tk. 4,685.31
Laying cost per % sft. = Tk. 4,685.31
(i) Ground floor
(a) Wall tiles less than, equal or equivalent to 250mmx330mm in sizes
Considering 100 sft. of work
1. Cost of tiles 100 sft. @ Tk. 46.00 Per sft. = Tk. 4,600.00
Add wastage 5% = Tk. 230.00
2. Laying cost 100 sft. @ Tk. 4,685.31 Per % sft. = Tk. 4,685.31
Total = Tk. 9,515.31
Profit 10.00% = Tk. 951.53
Overhead 3.50% = Tk. 333.04
Tk. 10,799.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 628.56
Grand total = Tk. 11,428.44
Rate per sft. = Tk. 114.28
Rate per sqm = Tk. 1,230.11

Say, Tk. 1,230 .00 Per sqm.

Item No.- 06.6.2


Wall tiles more than 250x330 & less than 250x400 in sizes, or equivalent
Considering 100 sft. of work
1. Cost of tiles 100 sft. @ Tk. 54.00 Per sft. = Tk. 5,400.00
Add wastage 5% = Tk. 270.00
2. Laying cost 100 sft. @ Tk. 4,685.31 Per % sft. = Tk. 4,685.31
Total = Tk. 10,355.31
Profit 10.00% = Tk. 1,035.53
Overhead 3.50% = Tk. 362.44
Tk. 11,753.28
Add VAT with adjustment factor 1.0582 5.50% = Tk. 684.05
Grand total = Tk. 12,437.33
Rate per sft. = Tk. 124.37
Rate per sqm = Tk. 1,338.72

Say, Tk. 1,339 .00 Per sqm.

Item No.- 06.6.3


Wall tiles more 250x400mm in sizes or equivalent
Considering 100 sft. of work
1. Cost of tiles 100 sft. @ Tk. 75.00 Per sft. = Tk. 7,500.00
Add wastage 5% = Tk. 375.00
2. Laying cost 100 sft. @ Tk. 4,685.31 Per % sft. = Tk. 4,685.31
Total = Tk. 12,560.31
Profit 10.00% = Tk. 1,256.03
Overhead 3.50% = Tk. 439.61
Tk. 14,255.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 829.71
Analysis of PWD SoR 2014 for Civil Works 120

Grand total = Tk. 15,085.66


Rate per sft. = Tk. 150.86
Rate per sqm = Tk. 1,623.86

Say, Tk. 1,624 .00 Per sqm.

Item No.- 06.7.1


Supplying, fitting and fixing glazed FLOOR tiles on cement mortar base (4:1):
Laying cost on FLOOR excluding cost of glazed tiles.
Considering 100 sft. of work
A. Cost of materialsfor base with 3/4'' (av) thick cement mortar (4:1):
1. Cement 1.50 bags @ Tk. 440.00 Per bag. = Tk. 660.00
2. Sand (F.M. 1.2) 7.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 127.50
3. White cement 3.60 kg @ Tk. 25.00 Per kg = Tk. 90.00
B. Labour Cost :
1. Head mason 2 Nos. @ Tk. 493.00 each = Tk. 986.00
2. Mason 2 Nos. @ Tk. 389.00 each = Tk. 778.00
3. Skilled labour 3 Nos. @ Tk. 303.00 each = Tk. 909.00
4. Ordinary labour 3 Nos. @ Tk. 245.00 each = Tk. 735.00
5. Local carriage, sundries, T & P etc. L.S. = Tk. 245.00
Total = Tk. 4,530.50
Cost per % sft. = Tk. 4,530.50
(i) Ground floor
(a) GP (homogeneous) 300 x 300 mm size glazed floor tiles
Considering 100 sft. work
1. Cost of tiles 100 sft. @ Tk. 64.00 Per sft. = Tk. 6,400.00
Add wastage 5% = Tk. 320.00
2. Laying cost 100 sft. @ Tk. 4,530.50 Per % sft. = Tk. 4,530.50
Total = Tk. 11,250.50
Profit 10.00% = Tk. 1,125.05
Overhead 3.50% = Tk. 393.77
Tk. 12,769.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 743.19
Grand total = Tk. 13,512.51
Rate per sft. = Tk. 135.13
Rate per sqm = Tk. 1,454.54

Say, Tk. 1,455 .00 Per sqm.

Item No.- 06.7.2


GP (homogeneous) 400 x 400 mm size glazed floor tiles
Considering 100 sft. work
1. Cost of tiles 100 sft. @ Tk. 74.00 Per sft. = Tk. 7,400.00
Add wastage 5% = Tk. 370.00
2. Laying cost 100 sft. @ Tk. 4,530.50 Per % sft. = Tk. 4,530.50
Total = Tk. 12,300.50
Profit 10.00% = Tk. 1,230.05
Overhead 3.50% = Tk. 430.52
Tk. 13,961.07
Add VAT with adjustment factor 1.0582 5.50% = Tk. 812.55
Grand total = Tk. 14,773.62
Rate per sft. = Tk. 147.74
Rate per sqm = Tk. 1,590.27

Say, Tk. 1,590 .00 Per sqm.

Item No.- 06.8.1


Analysis of PWD SoR 2014 for Civil Works 121

Supplying, fitting and fixing unglazed homogeneous floor tiles on cement mortar base (4:1):
Cost for laying floor tiles: Same as item No. 6.7.1 Per % sft. = Tk. 4,530.50
(i) For ground floor
(a) GP (homogeneous) 300 x 300 mm floor tiles
Considering 100 sft. work
1. Cost of tiles 100 sft. @ Tk. 68.00 Per sft. = Tk. 6,800.00
Add wastage 5% = Tk. 340.00
2. Laying cost 100 sft. @ Tk. 4,530.50 Per % sft. = Tk. 4,530.50
Total = Tk. 11,670.50
Profit 10.00% = Tk. 1,167.05
Overhead 3.50% = Tk. 408.47
Tk. 13,246.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 770.93
Grand total = Tk. 14,016.95
Rate per sft. = Tk. 140.17
Rate per sqm = Tk. 1,508.79

Say, Tk. 1,509 .00 Per sqm.

Item No.- 06.8.2


GP (homogeneous) 400 x 400 mm floor tiles
Considering 100 sft. work
1. Cost of tiles 100 sft. @ Tk. 75.00 Per sft. = Tk. 7,500.00
Add wastage 5% = Tk. 375.00
2. Laying cost 100 sft. @ Tk. 4,530.50 Per % sft. = Tk. 4,530.50
Total = Tk. 12,405.50
Profit 10.00% = Tk. 1,240.55
Overhead 3.50% = Tk. 434.19
Tk. 14,080.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 819.48
Grand total = Tk. 14,899.72
Rate per sft. = Tk. 149.00
Rate per sqm = Tk. 1,603.84

Say, Tk. 1,604 .00 Per sqm.

Item No.- 06.9


Supplying, fitting and fixing mirror polished floor tiles on cement mortar base (4:1):

Cost for laying floor tiles: Same as item No. 6.7.1 Per % sft. = Tk. 4,530.50
(i) For ground floor
06.9.1 GP (mirror polished) 300 x 300 mm floor tiles
Considering 100 sft. work

1. Cost of tiles 100 sft. @ Tk. 78.00 Per sft. = Tk. 7,800.00
Add wastage 5% = Tk. 390.00
2. Laying cost 100 sft. @ Tk. 4,530.50 Per % sft. = Tk. 4,530.50
Total = Tk. 12,720.50
Profit 10.00% = Tk. 1,272.05
Overhead 3.50% = Tk. 445.22
Tk. 14,437.77
Add VAT with adjustment factor 1.0582 5.50% = Tk. 840.29
Grand total = Tk. 15,278.06
Rate per sft. = Tk. 152.78
Rate per sqm = Tk. 1,644.52

Say, Tk. 1,645 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 122

06.9.2 GP (mirror polished) 400 x 400 mm floor tiles


Considering 100 sft. work
1. Cost of tiles 100 sft. @ Tk. 88.00 Per sft. = Tk. 8,800.00
Add wastage 5% = Tk. 440.00
2. Laying cost 100 sft. @ Tk. 4,530.50 Per % sft. = Tk. 4,530.50
Total = Tk. 13,770.50
Profit 10.00% = Tk. 1,377.05
Overhead 3.50% = Tk. 481.97
Tk. 15,629.52
Add VAT with adjustment factor 1.0582 5.50% = Tk. 909.65
Grand total = Tk. 16,539.17
Rate per sft. = Tk. 165.39
Rate per sqm = Tk. 1,780.26

Say, Tk. 1,780 .00 Per sqm.

06.9.3 GP (mirror polished) 600 x 600 mm floor tiles


Considering 100 sft. work
1. Cost of tiles 100 sft. @ Tk. 107.00 Per sft. = Tk. 10,700.00
Add wastage 5% = Tk. 535.00
2. Laying cost 100 sft. @ Tk. 4,530.50 Per % sft. = Tk. 4,530.50
Total = Tk. 15,765.50
Profit 10.00% = Tk. 1,576.55
Overhead 3.50% = Tk. 551.79
Tk. 17,893.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,041.44
Grand total = Tk. 18,935.28
Rate per sft. = Tk. 189.35
Rate per sqm = Tk. 2,038.16

Say, Tk. 2,038 .00 Per sqm.


Item No.- 06.10
Supplying, fitting and fixing stair tiles on cement mortar base (4:1):
GP 300 x 300 mm floor (stair) tiles
Considering 100 sft. work
1. Cost of tiles 100 sft. @ Tk. 70.00 Per sft. = Tk. 7,000.00
Add wastage 5% = Tk. 350.00
2. Laying cost 100 sft. @ Tk. 4,530.50 Per % sft. = Tk. 4,530.50
Total = Tk. 11,880.50
Profit 10.00% = Tk. 1,188.05
Overhead 3.50% = Tk. 415.82
Tk. 13,484.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 784.80
Grand total = Tk. 14,269.17
Rate per sft. = Tk. 142.69
Rate per sqm = Tk. 1,535.92

Say, Tk. 1,536 .00 Per sqm.


Item No.- 06.11
Supplying, fitting and fixing GP glazed homogenous/GP unglazed homogenous/Mirror polished floor tiles with tiles adhesives & Joint filler/ tiles grout

06.11.1 GP glazed homogenous floor tiles


Size 400mm x 400 mm
Considering 100 sft. of works
For Ground Floor
a) Cost of materials
Analysis of PWD SoR 2014 for Civil Works 123

i) Pasting tiles adhesives 50.00 kg @ Tk. 16.00 Per kg = Tk. 800.00


ii) Tiles grout/Joint filler 1.00 kg @ Tk. 75.00 Per kg = Tk. 75.00
b) Labour cost:
i) Head mason 0.75 Nos. @ Tk. 493.00 each = Tk. 369.75
ii) Mason 1.50 Nos. @ Tk. 389.00 each = Tk. 583.50
iii) Skilled labour 1.50 Nos. @ Tk. 303.00 each = Tk. 454.50
iv) Ordinary labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
v) Local carriage, sundries, T & P & washing of sand etc. L.S. = Tk. 100.000
Sub-total (A) = Tk. 2,750.25
c) Cost of tiles
Homogenous tiles 100.00 sft. @ Tk. 74.00 Per sft. = Tk. 7,400.00
Size 400mm x 400 mm Add: Wastage 5% = Tk. 370.00
Sub-total (B) = Tk. 7,770.00
Total (A+B) = Tk. 10,520.25
Profit 10.00% = Tk. 1,052.03
Overhead 3.50% = Tk. 368.21
Tk. 11,940.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 694.95
Grand total = Tk. 12,635.44
Rate per sft. = Tk. 126.35
Rate per sqm = Tk. 1,360.03

Say, Tk. 1,360 .00 Per sqm.

06.11.1.2 GP glazed homogenous floor tiles


Size 300mm x 300 mm
Considering 100 sft. of works
For Ground Floor
a) Cost of materials
i) Pasting tiles adhesives 50.00 kg @ Tk. 16.00 Per kg = Tk. 800.00
ii) Tiles grout/Joint filler 1.00 kg @ Tk. 75.00 Per kg = Tk. 75.00
b) Labour cost:
i) Head mason 0.75 Nos. @ Tk. 493.00 each = Tk. 369.75
ii) Mason 1.50 Nos. @ Tk. 389.00 each = Tk. 583.50
iii) Skilled labour 1.50 Nos. @ Tk. 303.00 each = Tk. 454.50
iv) Ordinary labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
v) Local carriage, sundries, T & P & washing of sand etc. L.S. = Tk. 100.000
Sub-total (A) = Tk. 2,750.25
c) Cost of tiles
Homogenous tiles 100.00 sft. @ Tk. 64.00 Per sft. = Tk. 6,400.00
Size 300mm x 300 mm Add: Wastage 5% = Tk. 320.00
Sub-total (B) = Tk. 6,720.00
Total (A+B) = Tk. 9,470.25
Profit 10.00% = Tk. 947.03
Overhead 3.50% = Tk. 331.46
Tk. 10,748.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 625.59
Grand total = Tk. 11,374.33
Rate per sft. = Tk. 113.74
Rate per sqm = Tk. 1,224.30

Say, Tk. 1,224 .00 Per sqm.

06.11.2.1 GP un-glazed homogenous floor tiles


Size 400mm x 400 mm
Considering 100 sft. of works
For Ground Floor
Analysis of PWD SoR 2014 for Civil Works 124

a) Cost of materials
i) Pasting tiles adhesives 50.00 kg @ Tk. 16.00 Per kt = Tk. 800.00
ii) Tiles grout/Joint filler 1.00 kg @ Tk. 75.00 Per kt = Tk. 75.00
b) Labour cost:
i) Head mason 0.75 Nos. @ Tk. 493.00 each = Tk. 369.75
ii) Mason 1.50 Nos. @ Tk. 389.00 each = Tk. 583.50
iii) Skilled labour 1.50 Nos. @ Tk. 303.00 each = Tk. 454.50
iv) Ordinary labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
v) Local carriage, sundries, T & P & washing of sand etc. L.S. = Tk. 100.000
Sub-total (A) = Tk. 2,750.25
c) Cost of tiles
Homogenous tiles 100.00 sft. @ Tk. 75.00 Per sft. = Tk. 7,500.00
Size 400mm x 400 mm Add: Wastage 5% = Tk. 375.00
Sub-total (B) = Tk. 7,875.00
Sub-total (A+B) = Tk. 10,625.25
Profit 10.00% = Tk. 1,062.53
Overhead 3.50% = Tk. 371.88
Tk. 12,059.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 701.88
Grand total = Tk. 12,761.54
Rate per sft. = Tk. 127.62
Rate per sqm = Tk. 1,373.70

Say, Tk. 1,374 .00 Per sqm.

06.11.3.1 GP un-glazed homogenous floor tiles


Size 300mm x 300 mm
Considering 100 sft. of works
For Ground Floor
a) Cost of materials
i) Pasting tiles adhesives 50.00 kg @ Tk. 16.00 Per kg = Tk. 800.00
ii) Tiles grout/Joint filler 1.00 kg @ Tk. 75.00 Per kg = Tk. 75.00
b) Labour cost:
i) Head mason 0.75 Nos. @ Tk. 493.00 each = Tk. 369.75
ii) Mason 1.50 Nos. @ Tk. 389.00 each = Tk. 583.50
iii) Skilled labour 1.50 Nos. @ Tk. 303.00 each = Tk. 454.50
iv) Ordinary labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
v) Local carriage, sundries, T & P & washing of sand etc. L.S. = Tk. 100.000
Sub-total (A) = Tk. 2,750.25
c) Cost of tiles
Homogenous tiles 100.00 sft. @ Tk. 68.00 Per sft. = Tk. 6,800.00
Size 300mm x 300 mm Add: Wastage 5% = Tk. 340.00
Sub-total (B) = Tk. 7,140.00
Total (A+B) = Tk. 9,890.25
Profit 10.00% = Tk. 989.03
Overhead 3.50% = Tk. 346.16
Tk. 11,225.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 653.33
Grand total = Tk. 11,878.77
Rate per sft. = Tk. 118.79
Rate per sqm = Tk. 1,278.66

Say, Tk. 1,279 .00 Per sqm.

06.11.4.1 GP Mirror Polished floor tiles


Size 300mm x 300 mm
Considering 100 sft. of works
Analysis of PWD SoR 2014 for Civil Works 125

For Ground Floor


a) Cost of materials
i) Pasting tiles adhesives 50.00 kg @ Tk. 16.00 Per kg = Tk. 800.00
ii) Tiles grout/Joint filler 1.00 kg @ Tk. 75.00 Per kg = Tk. 75.00
b) Labour cost:
i) Head mason 0.75 Nos. @ Tk. 493.00 each = Tk. 369.75
ii) Mason 1.50 Nos. @ Tk. 389.00 each = Tk. 583.50
iii) Skilled labour 1.50 Nos. @ Tk. 303.00 each = Tk. 454.50
iv) Ordinary labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
v) Local carriage, sundries, T & P & washing of sand etc. L.S. = Tk. 100.000
Sub-total (A) = Tk. 2,750.25
c) Cost of tiles
GP Mirror Polished Tiles 100.00 sft. @ Tk. 78.00 Per sft. = Tk. 7,800.00
Size 300mm x 300 mm Add: Wastage 5% = Tk. 390.00
Sub-total (B) = Tk. 8,190.00
Total (A+B) = Tk. 10,940.25
Profit 10.00% = Tk. 1,094.03
Overhead 3.50% = Tk. 382.91
Tk. 12,417.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 722.69
Grand total = Tk. 13,139.88
Rate per sft. = Tk. 131.40
Rate per sqm = Tk. 1,414.39

Say, Tk. 1,414 .00 Per sqm.

06.11.5.1 GP Mirror Polished floor tiles


Size 400mm x 400 mm
Considering 100 sft. of works
For Ground Floor
a) Cost of materials
i) Pasting tiles adhesives 50.00 kg @ Tk. 16.00 Per kg = Tk. 800.00
ii) Tiles grout/Joint filler 1.00 kg @ Tk. 75.00 Per kg = Tk. 75.00
b) Labour cost:
i) Head mason 0.75 Nos. @ Tk. 493.00 each = Tk. 369.75
ii) Mason 1.50 Nos. @ Tk. 389.00 each = Tk. 583.50
iii) Skilled labour 1.50 Nos. @ Tk. 303.00 each = Tk. 454.50
iv) Ordinary labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
v) Local carriage, sundries, T & P & washing of sand etc. L.S. = Tk. 100.000
Sub-total (A) = Tk. 2,750.25
c) Cost of tiles
GP Mirror Polished Tiles 100.00 sft. @ Tk. 88.00 Per sft. = Tk. 8,800.00
Size 400mm x 400 mm Add: Wastage 5% = Tk. 440.00
Sub-total (B) = Tk. 9,240.00
Total (A+B) = Tk. 11,990.25
Profit 10.00% = Tk. 1,199.03
Overhead 3.50% = Tk. 419.66
Tk. 13,608.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 792.05
Grand total = Tk. 14,400.99
Rate per sft. = Tk. 144.01
Rate per sqm = Tk. 1,550.12

Say, Tk. 1,550 .00 Per sqm.

06.11.6.1 GP Mirror Polished floor tiles


Size 600mm x 600 mm
Analysis of PWD SoR 2014 for Civil Works 126

Considering 100 sft. of works


For Ground Floor
a) Cost of materials
i) Pasting tiles adhesives 50.00 kg @ Tk. 16.00 Per kg = Tk. 800.00
ii) Tiles grout/Joint filler 1.00 kg @ Tk. 75.00 Per kg = Tk. 75.00
b) Labour cost:
i) Head mason 0.75 Nos. @ Tk. 493.00 each = Tk. 369.75
ii) Mason 1.50 Nos. @ Tk. 389.00 each = Tk. 583.50
iii) Skilled labour 1.50 Nos. @ Tk. 303.00 each = Tk. 454.50
iv) Ordinary labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
v) Local carriage, sundries, T & P & washing of sand etc. L.S. = Tk. 100.000
Sub-total (A) = Tk. 2,750.25
c) Cost of tiles
GP Mirror Polished Tiles 100.00 sft. @ Tk. 107.00 Per sft. = Tk. 10,700.00
Size 600mm x 600 mm Add: Wastage 5% = Tk. 535.00
Sub-total (B) = Tk. 11,235.00
Total (A+B) = Tk. 13,985.25
Profit 10.00% = Tk. 1,398.53
Overhead 3.50% = Tk. 489.48
Tk. 15,873.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 923.84
Grand total = Tk. 16,797.10
Rate per sft. = Tk. 167.97
Rate per sqm = Tk. 1,808.03

Say, Tk. 1,808 .00 Per sqm.

06.11.7.1
Extra Rate for each additional for Glazed Tiles and Marble Stone Works
06.12.1 Add for each addl. floor up to 5th floor (@ 0.25 No. lab per % sft.) Per sqm = Tk. 8.00
06.12.2 Add for each addl. floor for 6th floor to 9th floor (@ 0.5 No. lab per % sft.) Per sqm = Tk. 16.00
06.12.3 Add for each addl. floor for 10th floor and above (@ 0.75 No. lab per % sft.) Per sqm = Tk. 24.00

DIVISION 7 : REINFORCED CEMENT CONCRETE WORK

Item No.- 07.1.1


R.C.C. work (1:2:4) excluding the cost of reinforcement and its fabrication in individual and
continuous footings of column at plinth level with BRICK chips using WOODEN shutter

07.1.1.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 17,255.06
Profit 10.00% = Tk. 1,725.51
Analysis of PWD SoR 2014 for Civil Works 127

Overhead 3.50% = Tk. 603.93


= Tk. 19,584.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,139.84
Grand total = Tk. 20,724.34
Rate per cft. = Tk. 207.24
Rate per cum. = Tk. 7,318.68

Say, Tk. 7,319 .00 Per cum.

07.1.1.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 294.93
(From Secondary Input : Item C-1) Profit 10.00% = Tk. 29.49
Overhead 3.50% = Tk. 10.32
= Tk. 334.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.48
Grand total = Tk. 354.22

Say, Tk. 354 .00 Per sqm.


Item No.- 07.1.2
R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in raft/mat
with BRICK chips using WOODEN shutter

07.1.2.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 17,255.06
Profit 10.00% = Tk. 1,725.51
Overhead 3.50% = Tk. 603.93
= Tk. 19,584.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,139.84
Grand total = Tk. 20,724.34
Rate per cft. = Tk. 207.24
Rate per cum. = Tk. 7,318.68

Say, Tk. 7,319 .00 Per cum.

07.1.2.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 343.59
(From Secondary Input : Item C-2) Profit 10.00% = Tk. 34.36
Overhead 3.50% = Tk. 12.03
= Tk. 389.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.70
Grand total = Tk. 412.68

Ground floor and below plinth level Say, Tk. 413 .00 Per sqm..
Item No. - 07.1.3
R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in foundation beam
with BRICK chips using WOODEN shutter

07.1.3.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 17,255.06
Profit 10.00% = Tk. 1,725.51
Overhead 3.50% = Tk. 603.93
= Tk. 19,584.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,139.84
Analysis of PWD SoR 2014 for Civil Works 128

Grand total = Tk. 20,724.34


Rate per cft. = Tk. 207.24
Rate per cum. = Tk. 7,318.68

Say, Tk. 7,319 .00 Per cum.

07.1.3.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 295.15
(From Secondary Input : Item C-3) Profit 10.00% = Tk. 29.52
Overhead 3.50% = Tk. 10.33
= Tk. 335.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.50
Grand total = Tk. 354.50

Say, Tk. 355 .00 Per sqm..

Item No.- 07.1.4


R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in
Padestals, column capitals, lift walls and walls with BRICK chips using WOODEN shutter

07.1.4.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 800 cft. concreting using 1 mixer machine in one day) = Tk. 1,188.08
(From Secondary Input : Item A-2) Tk. 17,492.68
Profit 10.00% = Tk. 1,749.27
Overhead 3.50% = Tk. 612.24
= Tk. 19,854.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,155.53
Grand total = Tk. 21,009.72
Rate per cft. = Tk. 210.10
Rate per cum. = Tk. 7,419.68

Say, Tk. 7,420 .00 Per cum.

07.1.4.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 343.16
(From Secondary Input : Item C-4) Profit 10.00% = Tk. 34.32
Overhead 3.50% = Tk. 12.01
= Tk. 389.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.67
Grand total = Tk. 412.16

Say, Tk. 412 .00 Per sqm..


Item No.- 07.1.5
R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in tie beams and lintels
with BRICK chips using WOODEN shutter

07.1.5.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 500 cft. concreting using 1 mixer machine in one day) = Tk. 1,900.92
(From Secondary Input : Item A-4) Tk. 18,205.52
Profit 10.00% = Tk. 1,820.55
Overhead 3.50% = Tk. 637.19
= Tk. 20,663.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,202.62
Grand total = Tk. 21,865.88
Analysis of PWD SoR 2014 for Civil Works 129

Rate per cft. = Tk. 218.66


Rate per cum. = Tk. 7,721.98

Say, Tk. 7,722 .00 Per cum.

07.1.5.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 327.98
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 32.80
Overhead 3.50% = Tk. 11.48
= Tk. 372.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.67
Grand total = Tk. 393.93

Say, Tk. 394 .00 Per sqm..

Item No.- 07.1.6


R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Tee beams, Ell beams
and Rectangular beams etc with BRICK chips using WOODEN shutter

07.1.6.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 17,255.06
Profit 10.00% = Tk. 1,725.51
Overhead 3.50% = Tk. 603.93
= Tk. 19,584.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,139.84
Grand total = Tk. 20,724.34
Rate per cft. = Tk. 207.24
Rate per cum. = Tk. 7,318.68

Say, Tk. 7,319 .00 Per cum.

07.1.6.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 403.97
(From Secondary Input : Item C-6) Profit 10.00% = Tk. 40.40
Overhead 3.50% = Tk. 14.14
= Tk. 458.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 26.69
Grand total = Tk. 485.20

Say, Tk. 485 .00 Per sqm..

Item No.- 07.1.7


R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in floor and roof slab
with BRICK chips using WOODEN shutter

07.1.7.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 17,255.06
Profit 10.00% = Tk. 1,725.51
Overhead 3.50% = Tk. 603.93
= Tk. 19,584.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,139.84
Grand total = Tk. 20,724.34
Rate per cft. = Tk. 207.24
Analysis of PWD SoR 2014 for Civil Works 130

Rate per cum. = Tk. 7,318.68

Say, Tk. 7,319 .00 Per cum.

07.1.7.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 381.91
(From Secondary Input : Item C-7) Profit 10.00% = Tk. 38.19
Overhead 3.50% = Tk. 13.37
= Tk. 433.47
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25.23
Grand total = Tk. 458.70

Say, Tk. 459 .00 Per sqm.

Item No.- 07.1.8


R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in cornice,
railing, drop walls, louver, fins etc. with BRICK chips using WOODEN shutter

07.1.8.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 17,888.70
Profit 10.00% = Tk. 1,788.87
Overhead 3.50% = Tk. 626.10
= Tk. 20,303.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,181.69
Grand total = Tk. 21,485.36
Rate per cft. = Tk. 214.85
Rate per cum. = Tk. 7,587.43

Say, Tk. 7,587 .00 Per cum.

07.1.8.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 286.11
(From Secondary Input : Item C-9) Profit 10.00% = Tk. 28.61
Overhead 3.50% = Tk. 10.01
= Tk. 324.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.90
Grand total = Tk. 343.63

Say, Tk. 344 .00 Per sqm..

Item No.- 07.1.9


R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in sunshade, false ceiling
with BRICK chips using WOODEN shutter

07.1.9.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 17,888.70
Profit 10.00% = Tk. 1,788.87
Overhead 3.50% = Tk. 626.10
= Tk. 20,303.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,181.69
Grand total = Tk. 21,485.36
Rate per cft. = Tk. 214.85
Rate per cum. = Tk. 7,587.43
Analysis of PWD SoR 2014 for Civil Works 131

Say, Tk. 7,587 .00 Per cum.

07.1.9.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 328.73
(From Secondary Input : Item C-10) Profit 10.00% = Tk. 32.87
Overhead 3.50% = Tk. 11.51
= Tk. 373.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.72
Grand total = Tk. 394.83

Say, Tk. 395 .00 Per sqm.

Item No.- 07.1.10


R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in stair case slab
and steps with BRICK chips using WOODEN shutter

07.1.10.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 17,888.70
Profit 10.00% = Tk. 1,788.87
Overhead 3.50% = Tk. 626.10
= Tk. 20,303.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,181.69
Grand total = Tk. 21,485.36
Rate per cft. = Tk. 214.85
Rate per cum. = Tk. 7,587.43

Say, Tk. 7,587 .00 Per cum.

07.1.10.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 317.54
(From Secondary Input : Item C-11) Profit 10.00% = Tk. 31.75
Overhead 3.50% = Tk. 11.11
= Tk. 360.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.98
Grand total = Tk. 381.38

Say, Tk. 381 .00 Per sqm..

Item No.- 07.1.11


R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Waffle or Ribbed
floor/roof slab with BRICK chips using WOODEN shutter

07.1.11.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 17,888.70
Profit 10.00% = Tk. 1,788.87
Overhead 3.50% = Tk. 626.10
= Tk. 20,303.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,181.69
Grand total = Tk. 21,485.36
Rate per cft. = Tk. 214.85
Rate per cum. = Tk. 7,587.43
Analysis of PWD SoR 2014 for Civil Works 132

Say, Tk. 7,587 .00 Per cum.

07.1.11.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 485.89
(From Secondary Input : Item C-8) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59

Say, Tk. 584 .00 Per sqm..

Item No.- 07.2.1


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in individual and
continuous footings of column at plinth level with BRICK chips using STEEL shutter

07.2.1.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 17,255.06
Profit 10.00% = Tk. 1,725.51
Overhead 3.50% = Tk. 603.93
= Tk. 19,584.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,139.84
Grand total = Tk. 20,724.34
Rate per cft. = Tk. 207.24
Rate per cum = Tk. 7,318.68

Say, Tk. 7,319 .00 Per cum

07.2.1.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 317.86
(From Secondary Input : Item C-12) Profit 10.00% = Tk. 31.79
Overhead 3.50% = Tk. 11.13
= Tk. 360.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.00
Grand total = Tk. 381.78

Say, Tk. 382 .00 Per sqm.


Item No.- 07.2.2
R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in raft/mat with
BRICK chips using STEEL shutter

07.2.2.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 17,255.06
Profit 10.00% = Tk. 1,725.51
Overhead 3.50% = Tk. 603.93
= Tk. 19,584.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,139.84
Grand total = Tk. 20,724.34
Rate per cft. = Tk. 207.24
Rate per cum = Tk. 7,318.68

Say, Tk. 7,319 .00 Per cum


Analysis of PWD SoR 2014 for Civil Works 133

07.2.2.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 325.50
(From Secondary Input : Item C-13) Profit 10.00% = Tk. 32.55
Overhead 3.50% = Tk. 11.39
= Tk. 369.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.50
Grand total = Tk. 390.94

Say, Tk. 391 .00 Per sqm.

Item No.- 07.2.3


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in foundation beam
with BRICK chips using STEEL shutter

07.2.3.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 17,255.06
Profit 10.00% = Tk. 1,725.51
Overhead 3.50% = Tk. 603.93
= Tk. 19,584.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,139.84
Grand total = Tk. 20,724.34
Rate per cft. = Tk. 207.24
Rate per cum = Tk. 7,318.68

Say, Tk. 7,319 .00 Per cum

07.2.3.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 268.67
(From Secondary Input : Item C-14) Profit 10.00% = Tk. 26.87
Overhead 3.50% = Tk. 9.40
= Tk. 304.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.75
Grand total = Tk. 322.69

Say, Tk. 323 .00 Per sqm.

Item No.- 07.2.4


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Padestals, column,
column capitals, lift walla and walls with BRICK chips using STEEL shutter

07.2.4.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 800 cft. concreting using 1 mixer machine in one day) = Tk. 1,188.08
(From Secondary Input : Item A-2) Tk. 17,492.68
Profit 10.00% = Tk. 1,749.27
Overhead 3.50% = Tk. 612.24
= Tk. 19,854.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,155.53
Grand total = Tk. 21,009.72
Rate per cft. = Tk. 210.10
Rate per cum = Tk. 7,419.68

Say, Tk. 7,420 .00 Per cum


Analysis of PWD SoR 2014 for Civil Works 134

07.2.4.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 310.65
(From Secondary Input : Item C-15) Profit 10.00% = Tk. 31.07
Overhead 3.50% = Tk. 10.87
= Tk. 352.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.52
Grand total = Tk. 373.11

Say, Tk. 373 .00 Per sqm.

Item No.- 07.2.5


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in tie beams and lintels
with BRICK chips using STEEL shutter

07.2.5.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 500 cft. concreting using 1 mixer machine in one day) = Tk. 1,900.92
(From Secondary Input : Item A-4) Tk. 18,205.52
Profit 10.00% = Tk. 1,820.55
Overhead 3.50% = Tk. 637.19
= Tk. 20,663.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,202.62
Grand total = Tk. 21,865.88
Rate per cft. = Tk. 218.66
Rate per cum = Tk. 7,721.98

Say, Tk. 7,722 .00 Per cum

07.2.5.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 316.25
(From Secondary Input : Item C-16) Profit 10.00% = Tk. 31.63
Overhead 3.50% = Tk. 11.07
= Tk. 358.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.89
Grand total = Tk. 379.84

Say, Tk. 380 .00 Per sqm.

Item No.- 07.2.6


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Tee beams Ell beams
and Rectangular beams with BRICK chips using STEEL shutter

07.2.6.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 17,255.06
Profit 10.00% = Tk. 1,725.51
Overhead 3.50% = Tk. 603.93
= Tk. 19,584.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,139.84
Grand total = Tk. 20,724.34
Rate per cft. = Tk. 207.24
Rate per cum = Tk. 7,318.68

Say, Tk. 7,319 .00 Per cum

07.2.6.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 345.20
Analysis of PWD SoR 2014 for Civil Works 135

(From Secondary Input : Item C-17) Profit 10.00% = Tk. 34.52


Overhead 3.50% = Tk. 12.08
= Tk. 391.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.80
Grand total = Tk. 414.60

Say, Tk. 415 .00 Per sqm.

Item No.- 07.2.7


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in floor and roof slab
with BRICK chips using STEEL shutter

07.2.7.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 17,255.06
Profit 10.00% = Tk. 1,725.51
Overhead 3.50% = Tk. 603.93
= Tk. 19,584.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,139.84
Grand total = Tk. 20,724.34
Rate per cft. = Tk. 207.24
Rate per cum = Tk. 7,318.68

Say, Tk. 7,319 .00 Per cum

07.2.7.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 414.95
(From Secondary Input : Item C-18) Profit 10.00% = Tk. 41.50
Overhead 3.50% = Tk. 14.52
= Tk. 470.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.41
Grand total = Tk. 498.38

Say, Tk. 498 .00 Per sqm.


Item No.- 07.2.8
R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in
cornice, railing, drop walls, louver, fins etc. with BRICK chips using STEEL shutter.

07.2.8.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 17,888.70
Profit 10.00% = Tk. 1,788.87
Overhead 3.50% = Tk. 626.10
= Tk. 20,303.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,181.69
Grand total = Tk. 21,485.36
Rate per cft. = Tk. 214.85
Rate per cum. = Tk. 7,587.43

Say, Tk. 7,587 .00 Per cum.

07.2.8.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 286.43
(From Secondary Input : Item C-19) Profit 10.00% = Tk. 28.64
Analysis of PWD SoR 2014 for Civil Works 136

Overhead 3.50% = Tk. 10.03


= Tk. 325.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.92
Grand total = Tk. 344.02

Say, Tk. 344 .00 Per sqm.

Item No.- 07.2.9


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in sunshade, false ceiling
with BRICK chips using STEEL shutter

07.2.9.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 17,888.70
Profit 10.00% = Tk. 1,788.87
Overhead 3.50% = Tk. 626.10
= Tk. 20,303.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,181.69
Grand total = Tk. 21,485.36
Rate per cft. = Tk. 214.85
Rate per cum. = Tk. 7,587.43

Say, Tk. 7,587 .00 Per cum.

07.2.9.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 341.22
(From Secondary Input : Item C-20) Profit 10.00% = Tk. 34.12
Overhead 3.50% = Tk. 11.94
= Tk. 387.28
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.54
Grand total = Tk. 409.82

Say, Tk. 410 .00 Per sqm.

Item No.- 07.2.10


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in
stair case slab and steps with BRICK chips using STEEL shutter

07.2.10.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 17,888.70
Profit 10.00% = Tk. 1,788.87
Overhead 3.50% = Tk. 626.10
= Tk. 20,303.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,181.69
Grand total = Tk. 21,485.36
Rate per cft. = Tk. 214.85
Rate per cum. = Tk. 7,587.43

Say, Tk. 7,587 .00 Per cum..

07.2.10.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 335.94
(From Secondary Input : Item C-21) Profit 10.00% = Tk. 33.59
Overhead 3.50% = Tk. 11.76
Analysis of PWD SoR 2014 for Civil Works 137

= Tk. 381.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.19
Grand total = Tk. 403.48

Say, Tk. 403 .00 Per sqm.

Item No.- 07.2.11


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in
Waffle / Ribbed floor / Roof slab with BRICK chips using STEEL shutter

07.2.11.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,304.60
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 17,888.70
Profit 10.00% = Tk. 1,788.87
Overhead 3.50% = Tk. 626.10
= Tk. 20,303.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,181.69
Grand total = Tk. 21,485.36
Rate per cft. = Tk. 214.85
Rate per cum. = Tk. 7,587.43

Say, Tk. 7,587 .00 Per cum..

07.2.11.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 485.89
(From Secondary Input : Item C-8) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59

Say, Tk. 584 .00 Per sqm.

Item No.- 07.3.1


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in individual and
continuous footings of column at plinth level with STONE chips using WOODEN shutter.

07.3.1.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,055.46
Profit 10.00% = Tk. 2,405.55
Overhead 3.50% = Tk. 841.94
= Tk. 27,302.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,589.06
Grand total = Tk. 28,892.01
Rate per cft. = Tk. 288.92
Rate per cum = Tk. 10,203.21

Say, Tk. 10,203 .00 Per cum

07.3.1.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 294.93
(From Secondary Input : Item C-1) Profit 10.00% = Tk. 29.49
Overhead 3.50% = Tk. 10.32
= Tk. 334.74
Analysis of PWD SoR 2014 for Civil Works 138

Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.48


Grand total = Tk. 354.22

Say, Tk. 354 .00 Per sqm.

Item No.- 07.3.2


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in raft/mat with
STONE chips using WOODEN shutter.

07.3.2.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,055.46
Profit 10.00% = Tk. 2,405.55
Overhead 3.50% = Tk. 841.94
= Tk. 27,302.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,589.06
Grand total = Tk. 28,892.01
Rate per cft. = Tk. 288.92
Rate per cum = Tk. 10,203.21

Say, Tk. 10,203 .00 Per cum

07.3.2.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 343.59
(From Secondary Input : Item C-2) Profit 10.00% = Tk. 34.36
Overhead 3.50% = Tk. 12.03
= Tk. 389.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.70
Grand total = Tk. 412.68

Say, Tk. 413 .00 Per sqm.

Item No.- 07.3.3


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in foundation beam
with STONE chips using WOODEN shutter.

07.3.3.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,055.46
Profit 10.00% = Tk. 2,405.55
Overhead 3.50% = Tk. 841.94
= Tk. 27,302.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,589.06
Grand total = Tk. 28,892.01
Rate per cft. = Tk. 288.92
Rate per cum = Tk. 10,203.21

Say, Tk. 10,203 .00 Per cum

07.3.3.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 295.15
(From Secondary Input : Item C-3) Profit 10.00% = Tk. 29.52
Overhead 3.50% = Tk. 10.33
= Tk. 335.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.50
Analysis of PWD SoR 2014 for Civil Works 139

Grand total = Tk. 354.50

Say, Tk. 355 .00 Per sqm.

Item No.- 07.3.4


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Padestals, column,
column capitals, lift walla and walls with STONE chips using WOODEN shutter.

07.3.4.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 800 cft. concreting using 1 mixer machine in one day) = Tk. 1,188.08
(From Secondary Input : Item A-2) Tk. 24,293.08
Profit 10.00% = Tk. 2,429.31
Overhead 3.50% = Tk. 850.26
= Tk. 27,572.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,604.76
Grand total = Tk. 29,177.41
Rate per cft. = Tk. 291.77
Rate per cum = Tk. 10,303.86

Say, Tk. 10,304 .00 Per cum

07.3.4.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 343.16
(From Secondary Input : Item C-4) Profit 10.00% = Tk. 34.32
Overhead 3.50% = Tk. 12.01
= Tk. 389.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.67
Grand total = Tk. 412.16

Say, Tk. 412 .00 Per sqm.

Item No.- 07.3.5


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in tie beams and lintels
with STONE chips using WOODEN shutter.

07.3.5.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 500 cft. concreting using 1 mixer machine in one day) = Tk. 1,900.92
(From Secondary Input : Item A-4) Tk. 25,005.92
Profit 10.00% = Tk. 2,500.59
Overhead 3.50% = Tk. 875.21
= Tk. 28,381.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,651.84
Grand total = Tk. 30,033.56
Rate per cft. = Tk. 300.34
Rate per cum = Tk. 10,606.51

Say, Tk. 10,607 .00 Per cum

07.3.5.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 327.98
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 32.80
Overhead 3.50% = Tk. 11.48
= Tk. 372.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.67
Grand total = Tk. 393.93
Analysis of PWD SoR 2014 for Civil Works 140

Say, Tk. 394 .00 Per sqm.

Item No.- 07.3.6


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Tee beams Ell beams
and Rectangular beams with STONE chips using WOODEN shutter.

07.3.6.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,055.46
Profit 10.00% = Tk. 2,405.55
Overhead 3.50% = Tk. 841.94
= Tk. 27,302.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,589.06
Grand total = Tk. 28,892.01
Rate per cft. = Tk. 288.92
Rate per cum = Tk. 10,203.21

Say, Tk. 10,203 .00 Per cum

07.3.6.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 403.97
(From Secondary Input : Item C-6) Profit 10.00% = Tk. 40.40
Overhead 3.50% = Tk. 14.14
= Tk. 458.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 26.69
Grand total = Tk. 485.20

Say, Tk. 485 .00 Per sqm.

Item No.- 07.3.7


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in floor and roof slab
with STONE chips using WOODEN shutter.

07.3.7.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,055.46
Profit 10.00% = Tk. 2,405.55
Overhead 3.50% = Tk. 841.94
= Tk. 27,302.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,589.06
Grand total = Tk. 28,892.01
Rate per cft. = Tk. 288.92
Rate per cum = Tk. 10,203.21

Say, Tk. 10,203 .00 Per cum

07.3.7.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 381.91
(From Secondary Input : Item C-7) Profit 10.00% = Tk. 38.19
Overhead 3.50% = Tk. 13.37
= Tk. 433.47
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25.23
Grand total = Tk. 458.70
Analysis of PWD SoR 2014 for Civil Works 141

Say, Tk. 459 .00 Per sqm.

Item No.- 07.3.8


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in
cornice, railing, drop walls, louver, fins etc. with STONE chips using WOODEN shutter.

07.3.8.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 24,689.10
Profit 10.00% = Tk. 2,468.91
Overhead 3.50% = Tk. 864.12
= Tk. 28,022.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,630.92
Grand total = Tk. 29,653.05
Rate per cft. = Tk. 296.53
Rate per cum. = Tk. 10,471.96

Say, Tk. 10,472 .00 Per cum.

07.3.8.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 286.11
(From Secondary Input : Item C-9) Profit 10.00% = Tk. 28.61
Overhead 3.50% = Tk. 10.01
= Tk. 324.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.90
Grand total = Tk. 343.63

Say, Tk. 344 .00 Per sqm.

Item No.- 07.3.9


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in sunshade, false ceilin
with STONE chips using WOODEN shutter.

07.3.9.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 24,689.10
Profit 10.00% = Tk. 2,468.91
Overhead 3.50% = Tk. 864.12
= Tk. 28,022.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,630.92
Grand total = Tk. 29,653.05
Rate per cft. = Tk. 296.53
Rate per cum. = Tk. 10,471.96

Say, Tk. 10,472 .00 Per cum.

07.3.9.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 328.73
(From Secondary Input : Item C-10) Profit 10.00% = Tk. 32.87
Overhead 3.50% = Tk. 11.51
= Tk. 373.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.72
Grand total = Tk. 394.83

Say, Tk. 395 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 142

Item No.- 07.3.10


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in
stair case slab and steps with STONE chips using WOODEN shutter.

07.3.10.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 24,689.10
Profit 10.00% = Tk. 2,468.91
Overhead 3.50% = Tk. 864.12
= Tk. 28,022.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,630.92
Grand total = Tk. 29,653.05
Rate per cft. = Tk. 296.53
Rate per cum. = Tk. 10,471.96

Say, Tk. 10,472 .00 Per cum..

07.3.10.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 317.54
(From Secondary Input : Item C-11) Profit 10.00% = Tk. 31.75
Overhead 3.50% = Tk. 11.11
= Tk. 360.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.98
Grand total = Tk. 381.38

Say, Tk. 381 .00 Per sqm.

Item No.- 07.3.11


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in
Waffle / Ribbed floor / Roof slab with STONE chips using WOODEN shutter.

07.3.11.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 24,689.10
Profit 10.00% = Tk. 2,468.91
Overhead 3.50% = Tk. 864.12
= Tk. 28,022.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,630.92
Grand total = Tk. 29,653.05
Rate per cft. = Tk. 296.53
Rate per cum. = Tk. 10,471.96

Say, Tk. 10,472 .00 Per cum..

07.3.11.2 Formwork/shuttering, prop and necessary supports etc. (WOODEN) Per sqm. = Tk. 485.89
(From Secondary Input : Item C-8) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59

Say, Tk. 584 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 143

Item No.- 07.4.1


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in individual and
continuous footings of column at plinth level with STONE chips using STEEL shutter.

07.4.1.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,055.46
Profit 10.00% = Tk. 2,405.55
Overhead 3.50% = Tk. 841.94
= Tk. 27,302.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,589.06
Grand total = Tk. 28,892.01
Rate per cft. = Tk. 288.92
Rate per cum = Tk. 10,203.21

Say, Tk. 10,203 .00 Per cum

07.4.1.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 317.86
(From Secondary Input : Item C-12) Profit 10.00% = Tk. 31.79
Overhead 3.50% = Tk. 11.13
= Tk. 360.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.00
Grand total = Tk. 381.78

Say, Tk. 382 .00 Per sqm.

Item No.- 07.4.2


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in raft/mat with
STONE chips using STEEL shutter.

07.4.2.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,055.46
Profit 10.00% = Tk. 2,405.55
Overhead 3.50% = Tk. 841.94
= Tk. 27,302.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,589.06
Grand total = Tk. 28,892.01
Rate per cft. = Tk. 288.92
Rate per cum = Tk. 10,203.21

Say, Tk. 10,203 .00 Per cum

07.4.2.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 325.50
(From Secondary Input : Item C-13) Profit 10.00% = Tk. 32.55
Overhead 3.50% = Tk. 11.39
= Tk. 369.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.50
Grand total = Tk. 390.94

Say, Tk. 391 .00 Per sqm.

Item No.- 07.4.3


Analysis of PWD SoR 2014 for Civil Works 144

R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in foundation beam
with STONE chips using STEEL shutter.

07.4.3.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,055.46
Profit 10.00% = Tk. 2,405.55
Overhead 3.50% = Tk. 841.94
= Tk. 27,302.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,589.06
Grand total = Tk. 28,892.01
Rate per cft. = Tk. 288.92
Rate per cum = Tk. 10,203.21

Say, Tk. 10,203 .00 Per cum

07.4.3.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 268.67
(From Secondary Input : Item C-14) Profit 10.00% = Tk. 26.87
Overhead 3.50% = Tk. 9.40
= Tk. 304.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.75
Grand total = Tk. 322.69

Say, Tk. 323 .00 Per sqm.

Item No.- 07.4.4


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Padestals, column,
column capitals, lift walla and walls with STONE chips using STEEL shutter.

07.4.4.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 800 cft. concreting using 1 mixer machine in one day) = Tk. 1,188.08
(From Secondary Input : Item A-2) Tk. 24,293.08
Profit 10.00% = Tk. 2,429.31
Overhead 3.50% = Tk. 850.26
= Tk. 27,572.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,604.76
Grand total = Tk. 29,177.41
Rate per cft. = Tk. 291.77
Rate per cum = Tk. 10,303.86

Say, Tk. 10,304 .00 Per cum

07.4.4.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 310.65
(From Secondary Input : Item C-15) Profit 10.00% = Tk. 31.07
Overhead 3.50% = Tk. 10.87
= Tk. 352.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.52
Grand total = Tk. 373.11

Say, Tk. 373 .00 Per sqm.

Item No.- 07.4.5


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in tie beams and lintels
Analysis of PWD SoR 2014 for Civil Works 145

with STONE chips using STEEL shutter.

07.4.5.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 500 cft. concreting using 1 mixer machine in one day) = Tk. 1,900.92
(From Secondary Input : Item A-4) Tk. 25,005.92
Profit 10.00% = Tk. 2,500.59
Overhead 3.50% = Tk. 875.21
= Tk. 28,381.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,651.84
Grand total = Tk. 30,033.56
Rate per cft. = Tk. 300.34
Rate per cum = Tk. 10,606.51

Say, Tk. 10,607 .00 Per cum

07.4.5.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 316.25
(From Secondary Input : Item C-16) Profit 10.00% = Tk. 31.63
Overhead 3.50% = Tk. 11.07
= Tk. 358.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.89
Grand total = Tk. 379.84

Say, Tk. 380 .00 Per sqm.

Item No.- 07.4.6


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Tee beams Ell beams
and Rectangular beams with STONE chips using STEEL shutter.

07.4.6.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,055.46
Profit 10.00% = Tk. 2,405.55
Overhead 3.50% = Tk. 841.94
= Tk. 27,302.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,589.06
Grand total = Tk. 28,892.01
Rate per cft. = Tk. 288.92
Rate per cum = Tk. 10,203.21

Say, Tk. 10,203 .00 Per cum

07.4.6.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 345.20
(From Secondary Input : Item C-17) Profit 10.00% = Tk. 34.52
Overhead 3.50% = Tk. 12.08
= Tk. 391.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.80
Grand total = Tk. 414.60

Say, Tk. 415 .00 Per sqm.

Item No.- 07.4.7


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in floor and roof slab
with STONE chips using STEEL shutter.
Analysis of PWD SoR 2014 for Civil Works 146

07.4.7.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,055.46
Profit 10.00% = Tk. 2,405.55
Overhead 3.50% = Tk. 841.94
= Tk. 27,302.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,589.06
Grand total = Tk. 28,892.01
Rate per cft. = Tk. 288.92
Rate per cum = Tk. 10,203.21

Say, Tk. 10,203 .00 Per cum

07.4.7.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 414.95
(From Secondary Input : Item C-18) Profit 10.00% = Tk. 41.50
Overhead 3.50% = Tk. 14.52
= Tk. 470.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.41
Grand total = Tk. 498.38

Say, Tk. 498 .00 Per sqm.

Item No.- 07.4.8


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in
cornice, railing, drop walls, louver, fins etc. with STONE chips using STEEL shutter.

07.4.8.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 24,689.10
Profit 10.00% = Tk. 2,468.91
Overhead 3.50% = Tk. 864.12
= Tk. 28,022.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,630.92
Grand total = Tk. 29,653.05
Rate per cft. = Tk. 296.53
Rate per cum. = Tk. 10,471.96

Say, Tk. 10,472 .00 Per cum.

07.4.8.2 Formwork/shuttering, prop and necessary supports etc. STEEL) Per sqm. = Tk. 286.43
(From Secondary Input : Item C-19) Profit 10.00% = Tk. 28.64
Overhead 3.50% = Tk. 10.03
= Tk. 325.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.92
Grand total = Tk. 344.02

Say, Tk. 344 .00 Per sqm.

Item No.- 07.4.9


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in sunshade, false ceiling
with STONE chips using STEEL shutter.
Analysis of PWD SoR 2014 for Civil Works 147

07.4.9.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 24,689.10
Profit 10.00% = Tk. 2,468.91
Overhead 3.50% = Tk. 864.12
= Tk. 28,022.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,630.92
Grand total = Tk. 29,653.05
Rate per cft. = Tk. 296.53
Rate per cum. = Tk. 10,471.96

Say, Tk. 10,472 .00 Per cum.

07.4.9.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 341.22
(From Secondary Input : Item C-20) Profit 10.00% = Tk. 34.12
Overhead 3.50% = Tk. 11.94
= Tk. 387.28
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.54
Grand total = Tk. 409.82

Say, Tk. 410 .00 Per sqm.

Item No.- 07.4.10


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in
stair case slab and steps with STONE chips using STEEL shutter.

07.4.10.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 24,689.10
Profit 10.00% = Tk. 2,468.91
Overhead 3.50% = Tk. 864.12
= Tk. 28,022.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,630.92
Grand total = Tk. 29,653.05
Rate per cft. = Tk. 296.53
Rate per cum. = Tk. 10,471.96

Say, Tk. 10,472 .00 Per cum.

07.4.10.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 335.94
(From Secondary Input : Item C-21) Profit 10.00% = Tk. 33.59
Overhead 3.50% = Tk. 11.76
= Tk. 381.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.19
Grand total = Tk. 403.48

Say, Tk. 403 .00 Per sqm.

Item No.- 07.4.11


R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in
Waffle / Ribbed floor / Roof slab with STONE chips using STEEL shutter.
Analysis of PWD SoR 2014 for Civil Works 148

07.4.11.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-4) = Tk. 23,105.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 24,689.10
Profit 10.00% = Tk. 2,468.91
Overhead 3.50% = Tk. 864.12
= Tk. 28,022.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,630.92
Grand total = Tk. 29,653.05
Rate per cft. = Tk. 296.53
Rate per cum. = Tk. 10,471.96

Say, Tk. 10,472 .00 Per cum..

07.4.11.1 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 485.89
(From Secondary Input : Item C-8) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59

Say, Tk. 584 .00 Per sqm.

Item No.- 07.5.1


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication
in individual and continuous footings of column at plinth level with BRICK chips using WOODEN shutter.

07.5.1.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-5) = Tk. 17,867.02
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 18,817.48
Profit 10.00% = Tk. 1,881.75
Overhead 3.50% = Tk. 658.61
= Tk. 21,357.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,243.05
Grand total = Tk. 22,600.89
Rate per cft. = Tk. 226.01
Rate per cum. = Tk. 7,981.54

Say, Tk. 7,982 .00 Per cum.

07.5.1.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 294.93
(From Secondary Input : Item C-1) Profit 10.00% = Tk. 29.49
Overhead 3.50% = Tk. 10.32
= Tk. 334.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.48
Grand total = Tk. 354.22

Say, Tk. 354 .00 Per sqm..

Item No.- 07.5.2


R.C.C. work (1:1.5:3) complete excluding the cost of reinforcement with BRICK chips using WOODEN shutter
and its fabrication in raft/mat
Analysis of PWD SoR 2014 for Civil Works 149

07.5.2.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-5) = Tk. 17,867.02
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 18,817.48
Profit 10.00% = Tk. 1,881.75
Overhead 3.50% = Tk. 658.61
= Tk. 21,357.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,243.05
Grand total = Tk. 22,600.89
Rate per cft. = Tk. 226.01
Rate per cum. = Tk. 7,981.54

Say, Tk. 7,982 .00 Per cum.

07.5.2.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 343.59
(From Secondary Input : Item C-2) Profit 10.00% = Tk. 34.36
Overhead 3.50% = Tk. 12.03
= Tk. 389.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.70
Grand total = Tk. 412.68

Say, Tk. 413 .00 Per sqm..

Item No.- 07.5.3


R.C.C. work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication with BRICK chips using WOODEN shutter
in foundation beam

07.5.3.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-5) = Tk. 17,867.02
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 18,817.48
Profit 10.00% = Tk. 1,881.75
Overhead 3.50% = Tk. 658.61
= Tk. 21,357.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,243.05
Grand total = Tk. 22,600.89
Rate per cft. = Tk. 226.01
Rate per cum. = Tk. 7,981.54

Say, Tk. 7,982 .00 Per cum.

07.5.3.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 295.15
(From Secondary Input : Item C-3) Profit 10.00% = Tk. 29.52
Overhead 3.50% = Tk. 10.33
= Tk. 335.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.50
Grand total = Tk. 354.50

Say, Tk. 355 .00 Per sqm..

Item No.- 07.5.4


R.C.C. work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication withBRICK chips using WOODEN shutter
in Padestals, column capitals, lift walls and walls.
07.5.4.1 Cost of concrete
Considering 100 cft.
Analysis of PWD SoR 2014 for Civil Works 150

(i) Materials (From Secondary Input : Item B-5) = Tk. 17,867.02


(ii) Laying/placing concrete (@ 800 cft. concreting using 1 mixer machine in one day) = Tk. 1,188.08
(From Secondary Input : Item A-2) Tk. 19,055.10
Profit 10.00% = Tk. 1,905.51
Overhead 3.50% = Tk. 666.93
= Tk. 21,627.54
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,258.74
Grand total = Tk. 22,886.28
Rate per cft. = Tk. 228.86
Rate per cum. = Tk. 8,082.19

Say, Tk. 8,082 .00 Per cum.

07.5.4.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 343.16
(From Secondary Input : Item C-4) Profit 10.00% = Tk. 34.32
Overhead 3.50% = Tk. 12.01
= Tk. 389.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.67
Grand total = Tk. 412.16

Say, Tk. 412 .00 Per sqm..


Item No.- 07.5.5
R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its
fabrication in tie beam and lintel with BRICK chips using WOODEN shutter.

07.5.5.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-5) = Tk. 17,867.02
(ii) Laying/placing concrete (@ 500 cft. concreting using 1 mixer machine in one day) = Tk. 1,900.92
(From Secondary Input : Item A-4) Tk. 19,767.94
Profit 10.00% = Tk. 1,976.79
Overhead 3.50% = Tk. 691.88
= Tk. 22,436.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,305.83
Grand total = Tk. 23,742.44
Rate per cft. = Tk. 237.42
Rate per cum. = Tk. 8,384.49

Say, Tk. 8,384 .00 Per cum.

07.5.5.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 327.98
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 32.80
Overhead 3.50% = Tk. 11.48
= Tk. 372.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.67
Grand total = Tk. 393.93

Say, Tk. 394 .00 Per sqm..

Item No.- 07.5.6


R.C.C. work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication with BRICK chips using WOODEN shutter
in Tee beams, Ell beams and Rectangular beams etc.

07.5.6.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-5) = Tk. 17,867.02
Analysis of PWD SoR 2014 for Civil Works 151

(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-4) Tk. 18,817.48
Profit 10.00% = Tk. 1,881.75
Overhead 3.50% = Tk. 658.61
= Tk. 21,357.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,243.05
Grand total = Tk. 22,600.89
Rate per cft. = Tk. 226.01
Rate per cum. = Tk. 7,981.54

Say, Tk. 7,982 .00 Per cum.

07.5.6.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 403.97
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 40.40
Overhead 3.50% = Tk. 14.14
= Tk. 458.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 26.69
Grand total = Tk. 485.20

Say, Tk. 485 .00 Per sqm..


Item No.- 07.5.7
R.C.C. work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication with BRICK chips using WOODEN shutter
in floor and roof slab etc.

07.5.7.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-5) = Tk. 17,867.02
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 18,817.48
Profit 10.00% = Tk. 1,881.75
Overhead 3.50% = Tk. 658.61
= Tk. 21,357.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,243.05
Grand total = Tk. 22,600.89
Rate per cft. = Tk. 226.01
Rate per cum. = Tk. 7,981.54

Say, Tk. 7,982 .00 Per cum.

07.5.7.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 381.91
(From Secondary Input : Item C-6) Profit 10.00% = Tk. 38.19
Overhead 3.50% = Tk. 13.37
= Tk. 433.47
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25.23
Grand total = Tk. 458.70

Say, Tk. 459 .00 Per sqm..

Item No.- 07.5.8


R.C.C. work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in cornice,
railing, drop walls, louver, fins etc. with BRICK chips using WOODEN shutter

07.5.8.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-5) = Tk. 17,867.02
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 19,451.12
Analysis of PWD SoR 2014 for Civil Works 152

Profit 10.00% = Tk. 1,945.11


Overhead 3.50% = Tk. 680.79
= Tk. 22,077.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,284.90
Grand total = Tk. 23,361.92
Rate per cft. = Tk. 233.62
Rate per cum. = Tk. 8,250.29

Say, Tk. 8,250 .00 Per cum.

07.5.8.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 286.11
(From Secondary Input : Item C-9) Profit 10.00% = Tk. 28.61
Overhead 3.50% = Tk. 10.01
= Tk. 324.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.90
Grand total = Tk. 343.63

Say, Tk. 344 .00 Per sqm..

Item No.- 07.5.9


R.C.C. work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in sunshade, false ceiling
with BRICK chips using WOODEN shutter

07.5.9.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-5) = Tk. 17,867.02
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 19,451.12
Profit 10.00% = Tk. 1,945.11
Overhead 3.50% = Tk. 680.79
= Tk. 22,077.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,284.90
Grand total = Tk. 23,361.92
Rate per cft. = Tk. 233.62
Rate per cum. = Tk. 8,250.29

Say, Tk. 8,250 .00 Per cum.

07.5.9.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 328.73
(From Secondary Input : Item C-10) Profit 10.00% = Tk. 32.87
Overhead 3.50% = Tk. 11.51
= Tk. 373.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.72
Grand total = Tk. 394.83

Say, Tk. 395 .00 Per sqm.

Item No.- 07.5.10


R.C.C. work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in stair case slab
and steps with BRICK chips using WOODEN shutter

07.5.10.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-5) = Tk. 17,867.02
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 19,451.12
Profit 10.00% = Tk. 1,945.11
Analysis of PWD SoR 2014 for Civil Works 153

Overhead 3.50% = Tk. 680.79


= Tk. 22,077.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,284.90
Grand total = Tk. 23,361.92
Rate per cft. = Tk. 233.62
Rate per cum. = Tk. 8,250.29

Say, Tk. 8,250 .00 Per cum.

07.5.10.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 317.54
(From Secondary Input : Item C-11) Profit 10.00% = Tk. 31.75
Overhead 3.50% = Tk. 11.11
= Tk. 360.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.98
Grand total = Tk. 381.38

Say, Tk. 381 .00 Per sqm..


Item No.- 07.5.11
R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its
fabrication in waffle / ribbed floor with BRICK chips using WOODEN shutter.

07.5.11.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-5) = Tk. 17,867.02
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 19,451.12
Profit 10.00% = Tk. 1,945.11
Overhead 3.50% = Tk. 680.79
= Tk. 22,077.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,284.90
Grand total = Tk. 23,361.92
Rate per cft. = Tk. 233.62
Rate per cum. = Tk. 8,250.29

Say, Tk. 8,250 .00 Per cum.

07.5.11.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = 485.89
(From Secondary Input : Item C-8) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59

Say, Tk. 584 .00 Per sqm..

Item No.- 07.6.1


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in individual and
continuous footings of column, at plinth level with STONE chips using STEEL shutter and prop.

07.6.1.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,815.46
Profit 10.00% = Tk. 2,481.55
Overhead 3.50% = Tk. 868.54
Analysis of PWD SoR 2014 for Civil Works 154

= Tk. 28,165.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,639.26
Grand total = Tk. 29,804.81
Rate per cft. = Tk. 298.05
Rate per cum = Tk. 10,525.64

Say, Tk. 10,526 .00 Per cum

07.6.1.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 317.86
(From Secondary Input : Item C-12) Profit 10.00% = Tk. 31.79
Overhead 3.50% = Tk. 11.13
= Tk. 360.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.00
Grand total = Tk. 381.78

Say, Tk. 382 .00 Per sqm.

Item No.- 07.6.2


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in raft/mat
with STONE chips using STEEL shutter and prop.

07.6.2.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,815.46
Profit 10.00% = Tk. 2,481.55
Overhead 3.50% = Tk. 868.54
= Tk. 28,165.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,639.26
Grand total = Tk. 29,804.81
Rate per cft. = Tk. 298.05
Rate per cum = Tk. 10,525.64

Say, Tk. 10,526 .00 Per cum

07.6.2.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 325.50
(From Secondary Input : Item C-13) Profit 10.00% = Tk. 32.55
Overhead 3.50% = Tk. 11.39
= Tk. 369.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.50
Grand total = Tk. 390.94

Say, Tk. 391 .00 Per sqm.

Item No.- 07.6.3


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in foundation beam
with STONE chips using STEEL shutter and prop.

07.6.3.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,815.46
Profit 10.00% = Tk. 2,481.55
Overhead 3.50% = Tk. 868.54
= Tk. 28,165.55
Analysis of PWD SoR 2014 for Civil Works 155

Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,639.26


Grand total = Tk. 29,804.81
Rate per cft. = Tk. 298.05
Rate per cum = Tk. 10,525.64

Say, Tk. 10,526 .00 Per cum

07.6.3.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 268.67
(From Secondary Input : Item C-14) Profit 10.00% = Tk. 26.87
Overhead 3.50% = Tk. 9.40
= Tk. 304.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.75
Grand total = Tk. 322.69

Say, Tk. 323 .00 Per sqm.

Item No.- 07.6.4


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in Padestals, column,
column capitals lift walls and walls with STONE chips using STEEL shutter and prop.

07.6.4.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 800 cft. concreting using 1 mixer machine in one day) = Tk. 1,188.08
(From Secondary Input : Item A-2) Tk. 25,053.08
Profit 10.00% = Tk. 2,505.31
Overhead 3.50% = Tk. 876.86
= Tk. 28,435.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,654.96
Grand total = Tk. 30,090.21
Rate per cft. = Tk. 300.90
Rate per cum = Tk. 10,626.28

Say, Tk. 10,626 .00 Per cum

07.6.4.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 310.65
(From Secondary Input : Item C-15) Profit 10.00% = Tk. 31.07
Overhead 3.50% = Tk. 10.87
= Tk. 352.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.52
Grand total = Tk. 373.11

Say, Tk. 373 .00 Per sqm.

Item No.- 07.6.5


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in
Tie beam and lintle with STONE chips using STEEL shutter.

07.6.5.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,900.92
(From Secondary Input : Item A-4) Tk. 25,765.92
Profit 10.00% = Tk. 2,576.59
Overhead 3.50% = Tk. 901.81
= Tk. 29,244.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,702.05
Analysis of PWD SoR 2014 for Civil Works 156

Grand total = Tk. 30,946.37


Rate per cft. = Tk. 309.46
Rate per cum. = Tk. 10,928.58

Say, Tk. 10,929 .00 Per cum..

07.6.5.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 316.25
(From Secondary Input : Item C-16) Profit 10.00% = Tk. 31.63
Overhead 3.50% = Tk. 11.07
= Tk. 358.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.89
Grand total = Tk. 379.84

Say, Tk. 380 .00 Per sqm.

Item No.- 07.6.6


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in Tee beams, Ell beams
and Rectangular beams with STONE chips using STEEL shutter and prop.

07.6.6.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-4) Tk. 24,815.46
Profit 10.00% = Tk. 2,481.55
Overhead 3.50% = Tk. 868.54
= Tk. 28,165.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,639.26
Grand total = Tk. 29,804.81
Rate per cft. = Tk. 298.05
Rate per cum = Tk. 10,525.64

Say, Tk. 10,526 .00 Per cum

07.6.6.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 345.20
(From Secondary Input : Item C-16) Profit 10.00% = Tk. 34.52
Overhead 3.50% = Tk. 12.08
= Tk. 391.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.80
Grand total = Tk. 414.60

Say, Tk. 415 .00 Per sqm.

Item No.- 07.6.7


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in floor and roof slab
with STONE chips using STEEL shutter and prop.

07.6.7.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1 Tk. 24,815.46
Profit 10.00% = Tk. 2,481.55
Overhead 3.50% = Tk. 868.54
= Tk. 28,165.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,639.26
Grand total = Tk. 29,804.81
Analysis of PWD SoR 2014 for Civil Works 157

Rate per cft. = Tk. 298.05


Rate per cum = Tk. 10,525.64

Say, Tk. 10,526 .00 Per cum

07.6.7.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 414.95
(From Secondary Input : Item C-17) Profit 10.00% = Tk. 41.50
Overhead 3.50% = Tk. 14.52
= Tk. 470.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.41
Grand total = Tk. 498.38

Say, Tk. 498 .00 Per sqm.

Item No.- 07.6.8


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in cornice, railing and drop wall
with STONE chips using STEEL shutter and prop.

07.6.8.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-1) Tk. 25,449.10
Profit 10.00% = Tk. 2,544.91
Overhead 3.50% = Tk. 890.72
= Tk. 28,884.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,681.12
Grand total = Tk. 30,565.85
Rate per cft. = Tk. 305.66
Rate per cum = Tk. 10,794.38

Say, Tk. 10,794 .00 Per cum

07.6.8.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 286.43
(From Secondary Input : Item C-19) Profit 10.00% = Tk. 28.64
Overhead 3.50% = Tk. 10.03
= Tk. 325.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.92
Grand total = Tk. 344.02

Say, Tk. 344 .00 Per sqm.

Item No.- 07.6.9


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in sunshade and false ceiling
with STONE chips using STEEL shutter.

07.6.9.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 25,449.10
Profit 10.00% = Tk. 2,544.91
Overhead 3.50% = Tk. 890.72
= Tk. 28,884.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,681.12
Grand total = Tk. 30,565.85
Rate per cft. = Tk. 305.66
Analysis of PWD SoR 2014 for Civil Works 158

Rate per cum. = Tk. 10,794.38

Say, Tk. 10,794 .00 Per cum.

07.6.9.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 341.22
(From Secondary Input : Item C-20) Profit 10.00% = Tk. 34.12
Overhead 3.50% = Tk. 11.94
= Tk. 387.28
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.54
Grand total = Tk. 409.82

Say, Tk. 410 .00 Per sqm.

Item No.- 07.6.10


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in stair case slab
and steps with STONE chips using STEEL shutter and prop.

07.6.10.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-1) Tk. 25,449.10
Profit 10.00% = Tk. 2,544.91
Overhead 3.50% = Tk. 890.72
= Tk. 28,884.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,681.12
Grand total = Tk. 30,565.85
Rate per cft. = Tk. 305.66
Rate per cum = Tk. 10,794.38

Say, Tk. 10,794 .00 Per cum

07.6.10.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 335.94
(From Secondary Input : Item C-18) Profit 10.00% = Tk. 33.59
Overhead 3.50% = Tk. 11.76
= Tk. 381.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.19
Grand total = Tk. 403.48

Say, Tk. 403 .00 Per sqm.

Item No.- 07.6.11


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in Waffle and ribbed
floor or floor slab with STONE chips using STEEL shutter and prop.

07.6.11.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 25,449.10
Profit 10.00% = Tk. 2,544.91
Overhead 3.50% = Tk. 890.72
= Tk. 28,884.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,681.12
Grand total = Tk. 30,565.85
Rate per cft. = Tk. 305.66
Rate per cum = Tk. 10,794.38
Analysis of PWD SoR 2014 for Civil Works 159

Say, Tk. 10,794 .00 Per cum

07.6.11.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 485.89
(From Secondary Input : Item C-19) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59

Say, Tk. 584 .00 Per sqm.

Item No.- 07.7.1


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in individual and
continuous footings of column at plinth level with STONE chips using WOODEN shutter.

07.7.1.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,815.46
Profit 10.00% = Tk. 2,481.55
Overhead 3.50% = Tk. 868.54
= Tk. 28,165.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,639.26
Grand total = Tk. 29,804.81
Rate per cft. = Tk. 298.05
Rate per cum. = Tk. 10,525.64

Say, Tk. 10,526 .00 Per cum..

07.7.1.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 294.93
(From Secondary Input : Item C-1) Profit 10.00% = Tk. 29.49
Overhead 3.50% = Tk. 10.32
= Tk. 334.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.48
Grand total = Tk. 354.22

Say, Tk. 354 .00 Per sqm.

Item No.- 07.7.2


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in raft/mat with
STONE chips using WOODEN shutter.

07.7.2.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,815.46
Profit 10.00% = Tk. 2,481.55
Overhead 3.50% = Tk. 868.54
= Tk. 28,165.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,639.26
Grand total = Tk. 29,804.81
Rate per cft. = Tk. 298.05
Rate per cum. = Tk. 10,525.64
Analysis of PWD SoR 2014 for Civil Works 160

Say, Tk. 10,526 .00 Per cum..

07.7.2.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 343.59
(From Secondary Input : Item C-2) Profit 10.00% = Tk. 34.36
Overhead 3.50% = Tk. 12.03
= Tk. 389.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.70
Grand total = Tk. 412.68

Say, Tk. 413 .00 Per sqm.

Item No.- 07.7.3


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in foundation beam
with STONE chips using WOODEN shutter.

07.7.3.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,815.46
Profit 10.00% = Tk. 2,481.55
Overhead 3.50% = Tk. 868.54
= Tk. 28,165.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,639.26
Grand total = Tk. 29,804.81
Rate per cft. = Tk. 298.05
Rate per cum. = Tk. 10,525.64

Say, Tk. 10,526 .00 Per cum..

07.7.3.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 295.15
(From Secondary Input : Item C-3) Profit 10.00% = Tk. 29.52
Overhead 3.50% = Tk. 10.33
= Tk. 335.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.50
Grand total = Tk. 354.50

Say, Tk. 355 .00 Per sqm.

Item No.- 07.7.4


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in Padestals, column,
column capitals, lift walla and walls with STONE chips using WOODEN shutter.

07.7.4.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 800 cft. concreting using 1 mixer machine in one day) = Tk. 1,188.08
(From Secondary Input : Item A-2) Tk. 25,053.08
Profit 10.00% = Tk. 2,505.31
Overhead 3.50% = Tk. 876.86
= Tk. 28,435.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,654.96
Grand total = Tk. 30,090.21
Rate per cft. = Tk. 300.90
Rate per cum. = Tk. 10,626.28

Say, Tk. 10,626 .00 Per cum..


Analysis of PWD SoR 2014 for Civil Works 161

07.7.4.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 343.16
(From Secondary Input : Item C-4) Profit 10.00% = Tk. 34.32
Overhead 3.50% = Tk. 12.01
= Tk. 389.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.67
Grand total = Tk. 412.16

Say, Tk. 412 .00 Per sqm.

Item No.- 07.7.5


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in
Tie beam and lintle with STONE chips using WOODEN shutter.

07.7.5.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,900.92
(From Secondary Input : Item A-4) Tk. 25,765.92
Profit 10.00% = Tk. 2,576.59
Overhead 3.50% = Tk. 901.81
= Tk. 29,244.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,702.05
Grand total = Tk. 30,946.37
Rate per cft. = Tk. 309.46
Rate per cum. = Tk. 10,928.58

Say, Tk. 10,929 .00 Per cum..

07.7.5.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 327.98
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 32.80
Overhead 3.50% = Tk. 11.48
= Tk. 372.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.67
Grand total = Tk. 393.93

Say, Tk. 394 .00 Per sqm.

Item No.- 07.7.6


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in Tee beams Ell beams
and Rectangular beams with STONE chips using WOODEN shutter.

07.7.6.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-4) Tk. 24,815.46
Profit 10.00% = Tk. 2,481.55
Overhead 3.50% = Tk. 868.54
= Tk. 28,165.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,639.26
Grand total = Tk. 29,804.81
Rate per cft. = Tk. 298.05
Rate per cum. = Tk. 10,525.64

Say, Tk. 10,526 .00 Per cum.


Analysis of PWD SoR 2014 for Civil Works 162

07.7.6.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 403.97
(From Secondary Input : Item C-5) Profit 10.00% = Tk. 40.40
Overhead 3.50% = Tk. 14.14
= Tk. 458.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 26.69
Grand total = Tk. 485.20

Say, Tk. 485 .00 Per sqm.

Item No.- 07.7.7


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in floor and roof slab
with STONE chips using WOODEN shutter.

07.7.7.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 24,815.46
Profit 10.00% = Tk. 2,481.55
Overhead 3.50% = Tk. 868.54
= Tk. 28,165.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,639.26
Grand total = Tk. 29,804.81
Rate per cft. = Tk. 298.05
Rate per cum. = Tk. 10,525.64

Say, Tk. 10,526 .00 Per cum.

07.7.7.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 381.91
(From Secondary Input : Item C-6) Profit 10.00% = Tk. 38.19
Overhead 3.50% = Tk. 13.37
= Tk. 433.47
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25.23
Grand total = Tk. 458.70

Say, Tk. 459 .00 Per sqm.

Item No.- 07.7.8


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in cornice, railing and drop wall
with STONE chips using WOODEN shutter and prop.

07.7.8.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-1) Tk. 25,449.10
Profit 10.00% = Tk. 2,544.91
Overhead 3.50% = Tk. 890.72
= Tk. 28,884.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,681.12
Grand total = Tk. 30,565.85
Rate per cft. = Tk. 305.66
Rate per cum = Tk. 10,794.38

Say, Tk. 10,794 .00 Per cum

07.7.8.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 286.11
Analysis of PWD SoR 2014 for Civil Works 163

(From Secondary Input : Item C-9) Profit 10.00% = Tk. 28.61


Overhead 3.50% = Tk. 10.01
= Tk. 324.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.90
Grand total = Tk. 343.63

Say, Tk. 344 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 164

Item No.- 07.7.9


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in sunshade and false ceiling
with STONE chips using WOODEN shutter.

07.7.9.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 25,449.10
Profit 10.00% = Tk. 2,544.91
Overhead 3.50% = Tk. 890.72
= Tk. 28,884.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,681.12
Grand total = Tk. 30,565.85
Rate per cft. = Tk. 305.66
Rate per cum. = Tk. 10,794.38

Say, Tk. 10,794 .00 Per cum.

07.7.9.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 328.73
(From Secondary Input : Item C-10) Profit 10.00% = Tk. 32.87
Overhead 3.50% = Tk. 11.51
= Tk. 373.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.72
Grand total = Tk. 394.83

Say, Tk. 395 .00 Per sqm.

Item No.- 07.7.10


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in
stair case slab and steps with STONE chips using WOODEN shutter.

07.7.10.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-1) Tk. 25,449.10
Profit 10.00% = Tk. 2,544.91
Overhead 3.50% = Tk. 890.72
= Tk. 28,884.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,681.12
Grand total = Tk. 30,565.85
Rate per cft. = Tk. 305.66
Rate per cum = Tk. 10,794.38

Say, Tk. 10,794 .00 Per cum.

07.7.10.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 317.54
(From Secondary Input : Item C-7) Profit 10.00% = Tk. 31.75
Overhead 3.50% = Tk. 11.11
= Tk. 360.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.98
Grand total = Tk. 381.38

Say, Tk. 381 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 165

Item No.- 07.7.11


R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in
Waffle / Ribbed floor / Roof slab with STONE chips using WOODEN shutter.
Considering 100 cft. of work.

07.7.11.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-6) = Tk. 23,865.00
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 25,449.10
Profit 10.00% = Tk. 2,544.91
Overhead 3.50% = Tk. 890.72
= Tk. 28,884.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,681.12
Grand total = Tk. 30,565.85
Rate per cft. = Tk. 305.66
Rate per cum = Tk. 10,794.38

Say, Tk. 10,794 .00 Per cum.

07.7.11.2 Formwork/shuttering, prop and necessary supports etc. (wooden) Per sqm. = Tk. 485.89
(From Secondary Input : Item C-9) Profit 10.00% = Tk. 48.59
Overhead 3.50% = Tk. 17.01
= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59

Say, Tk. 584 .00 Per sqm.

Item No.- 07.8.1


Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixture
excluding the cost of reinforcement and its fabrication in individual and continuous footings of column,
at plinth level with STONE chips using STEEL shutter and prop (excluding cost of admixure and mix design).

07.8.1.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-7) = Tk. 24,912.50
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 25,862.96
Profit 10.00% = Tk. 2,586.30
Overhead 3.50% = Tk. 905.20
= Tk. 29,354.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,708.46
Grand total = Tk. 31,062.92
Rate per cft. = Tk. 310.63
Rate per cum = Tk. 10,969.90

Say, Tk. 10,970 .00 Per cum

07.8.1.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 317.86
(From Secondary Input : Item C-12) Profit 10.00% = Tk. 31.79
Overhead 3.50% = Tk. 11.13
= Tk. 360.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.00
Grand total = Tk. 381.78

Say, Tk. 382 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 166

Item No.- 07.8.2


Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixture
excluding the cost of reinforcement and its fabrication, in raft / mat with STONE chips using STEEL shutter and prop.
(excluding cost of admixure and mix design).

07.8.2.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-7) = Tk. 24,912.50
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 25,862.96
Profit 10.00% = Tk. 2,586.30
Overhead 3.50% = Tk. 905.20
= Tk. 29,354.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,708.46
Grand total = Tk. 31,062.92
Rate per cft. = Tk. 310.63
Rate per cum = Tk. 10,969.90

Say, Tk. 10,970 .00 Per cum

07.8.2.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 325.50
(From Secondary Input : Item C-13) Profit 10.00% = Tk. 32.55
Overhead 3.50% = Tk. 11.39
= Tk. 369.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.50
Grand total = Tk. 390.94

Say, Tk. 391 .00 Per sqm.

Item No.- 07.8.3


Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixture
excluding the cost of reinforcement and its fabrication in foundation beam withSTONE chips using STEEL shutter and prop.
(excluding cost of admixure and mix design).

07.8.3.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-7) = Tk. 24,912.50
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 25,862.96
Profit 10.00% = Tk. 2,586.30
Overhead 3.50% = Tk. 905.20
= Tk. 29,354.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,708.46
Grand total = Tk. 31,062.92
Rate per cft. = Tk. 310.63
Rate per cum = Tk. 10,969.90

Say, Tk. 10,970 .00 Per cum

07.8.3.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 268.67
(From Secondary Input : Item C-14) Profit 10.00% = Tk. 26.87
Overhead 3.50% = Tk. 9.40
= Tk. 304.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.75
Grand total = Tk. 322.69
Analysis of PWD SoR 2014 for Civil Works 167

Say, Tk. 323 .00 Per sqm.

Item No.- 07.8.4


Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixture
excluding the cost of reinforcement and its fabrication in Padestals, column, column capitals, lift walls
and walls with STONE chips using STEEL shutter and prop. (excluding cost of admixure and mix design).

07.8.4.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-7) = Tk. 24,912.50
(ii) Laying/placing concrete (@ 800 cft. concreting using 1 mixer machine in one day) = Tk. 1,188.08
(From Secondary Input : Item A-2) Tk. 26,100.58
Profit 10.00% = Tk. 2,610.06
Overhead 3.50% = Tk. 913.52
= Tk. 29,624.16
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,724.16
Grand total = Tk. 31,348.32
Rate per cft. = Tk. 313.48
Rate per cum = Tk. 11,070.55

Say, Tk. 11,071 .00 Per cum

07.8.4.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 310.65
(From Secondary Input : Item C-15) Profit 10.00% = Tk. 31.07
Overhead 3.50% = Tk. 10.87
= Tk. 352.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.52
Grand total = Tk. 373.11

Say, Tk. 373 .00 Per sqm.

Item No.- 07.8.5


R.C.C work (1:1.25:2.5) complete excluding the cost of reinforcement and its fabrication in
Tie beam and lintel with STONE chips using STEEL shutter.

07.8.5.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-7) = Tk. 24,912.50
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 26,496.60
Profit 10.00% = Tk. 2,649.66
Overhead 3.50% = Tk. 927.38
= Tk. 30,073.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,750.32
Grand total = Tk. 31,823.96
Rate per cft. = Tk. 318.24
Rate per cum. = Tk. 11,238.65

Say, Tk. 11,239 .00 Per cum..

07.8.5.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 316.25
(From Secondary Input : Item C-16) Profit 10.00% = Tk. 31.63
Overhead 3.50% = Tk. 11.07
= Tk. 358.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.89
Grand total = Tk. 379.84
Analysis of PWD SoR 2014 for Civil Works 168

Say, Tk. 380 .00 Per sqm.

Item No.- 07.8.6


Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range
admixture excluding the cost of reinforcement and its fabrication in Tee beams Ell beams
and Rectangular beams with STONE chips using STEEL shutter and prop.
(excluding cost of admixure and mix design).
07.8.6.1 Cost of concrete
Considering 100 cft.
(i) Materials (From Secondary Input : Item B-7) = Tk. 24,912.50
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 25,862.96
Profit 10.00% = Tk. 2,586.30
Overhead 3.50% = Tk. 905.20
= Tk. 29,354.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,708.46
Grand total = Tk. 31,062.92
Rate per cft. = Tk. 310.63
Rate per cum = Tk. 10,969.90

Say, Tk. 10,970 .00 Per cum

07.8.6.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 345.20
(From Secondary Input : Item C-17) Profit 10.00% = Tk. 34.52
Overhead 3.50% = Tk. 12.08
= Tk. 391.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.80
Grand total = Tk. 414.60

Ground floor and below plinth level Say, Tk. 415 .00 Per sqm.

Item No.- 07.8.7


Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixture
excluding the cost of reinforcement and its fabrication in floor and roof slab with STONE chips using STEEL shutter and prop.
(excluding cost of admixure and mix design).

07.8.7.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-7) = Tk. 24,912.50
(ii) Laying/placing concrete (@ 1000 cft. concreting using 1 mixer machine in one day) = Tk. 950.46
(From Secondary Input : Item A-1) Tk. 25,862.96
Profit 10.00% = Tk. 2,586.30
Overhead 3.50% = Tk. 905.20
= Tk. 29,354.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,708.46
Grand total = Tk. 31,062.92
Rate per cft. = Tk. 310.63
Rate per cum = Tk. 10,969.90

Say, Tk. 10,970 .00 Per cum


Analysis of PWD SoR 2014 for Civil Works 169

07.8.7.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 414.95
(From Secondary Input : Item C-18) Profit 10.00% = Tk. 41.50
Overhead 3.50% = Tk. 14.52
= Tk. 470.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.41
Grand total = Tk. 498.38

Say, Tk. 498 .00 Per sqm.

Item No.- 07.8.8


R.C.C work (1:1.25:2.5) complete excluding the cost of reinforcement and its fabrication in cornice, railing and drop wall
with STONE chips using STEEL shutter and prop.

07.8.8.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-7) = Tk. 24,912.50
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 26,496.60
Profit 10.00% = Tk. 2,649.66
Overhead 3.50% = Tk. 927.38
= Tk. 30,073.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,750.32
Grand total = Tk. 31,823.96
Rate per cft. = Tk. 318.24
Rate per cum = Tk. 11,238.65

Say, Tk. 11,239 .00 Per cum

07.8.8.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 286.43
(From Secondary Input : Item C-19) Profit 10.00% = Tk. 28.64
Overhead 3.50% = Tk. 10.03
= Tk. 325.10
1.0582 5.50% = Tk. 18.92
Grand total = Tk. 344.02

Say, Tk. 344 .00 Per sqm.

Item No.- 07.8.9


R.C.C work (1:1.25:2.5) complete excluding the cost of reinforcement and its fabrication in sunshade and false ceiling
with STONE chips using STEEL shutter.

07.8.9.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-7 = Tk. 24,912.50
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 26,496.60
Profit 10.00% = Tk. 2,649.66
Overhead 3.50% = Tk. 927.38
= Tk. 30,073.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,750.32
Grand total = Tk. 31,823.96
Rate per cft. = Tk. 318.24
Rate per cum. = Tk. 11,238.65

Say, Tk. 11,239 .00 Per cum.

07.8.9.2 Formwork/shuttering, prop and necessary supports etc. (STEEL) Per sqm. = Tk. 341.22
Analysis of PWD SoR 2014 for Civil Works 170

(From Secondary Input : Item C-20) Profit 10.00% = Tk. 34.12


Overhead 3.50% = Tk. 11.94
= Tk. 387.28
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.54
Grand total = Tk. 409.82

Say, Tk. 410 .00 Per sqm.

Item No.- 07.8.10


Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixturee
excluding the cost of reinforcement and its fabrication in stair case slab and steps with STONE chips using STEEL shutter and prop.
(excluding cost of admixure and mix design).

07.8.10.1 Cost of concrete


Considering 100 cft.
(i) Materials (From Secondary Input : Item B-7) = Tk. 24,912.50
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 26,496.60
Profit 10.00% = Tk. 2,649.66
Overhead 3.50% = Tk. 927.38
= Tk. 30,073.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,750.32
Grand total = Tk. 31,823.96
Rate per cft. = Tk. 318.24
Rate per cum = Tk. 11,238.65

Say, Tk. 11,239 .00 Per cum

07.8.10.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 335.94
(From Secondary Input : Item C-21) Profit 10.00% = Tk. 33.59
Overhead 3.50% = Tk. 11.76
= Tk. 381.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.19
Grand total = Tk. 403.48

Say, Tk. 403 .00 Per sqm.

Item No.- 07.8.11


Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range
admixture excluding the cost of reinforcement and its fabrication in Waffle / Ribbed floor / Roof slab with
STONE chips using STEEL shutter and prop. (excluding cost of admixure and mix design).
07.8.11.1 Cost of concrete
Considering 100 cft.
(i) Materials (From Secondary Input : Item B-7) = Tk. 24,912.50
(ii) Laying/placing concrete (@ 600 cft. concreting using 1 mixer machine in one day) = Tk. 1,584.10
(From Secondary Input : Item A-3) Tk. 26,496.60
Profit 10.00% = Tk. 2,649.66
Overhead 3.50% = Tk. 927.38
= Tk. 30,073.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,750.32
Grand total = Tk. 31,823.96
Rate per cft. = Tk. 318.24
Rate per cum = Tk. 11,238.65

Say, Tk. 11,239 .00 Per cum


07.8.11.2 Formwork/shuttering, prop and necessary supports etc. (steel) Per sqm. = Tk. 485.89
(From Secondary Input : Item C-8) Profit 10.00% = Tk. 48.59
Analysis of PWD SoR 2014 for Civil Works 171

Overhead 3.50% = Tk. 17.01


= Tk. 551.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.10
Grand total = Tk. 583.59

Say, Tk. 584 .00 Per sqm.

Item No.- 07.9


Extra rate over the rate of RCC (materials, consumables and laying/placing concrete) works in columns, capitals, liftwalls & walls where the free height of the
structure exceeds 4 meter [rate is considered for the height of each addl. 4 (four) meter or part]
Considering 100 cft. of work
(a) Extra head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(b) Extra mason 0.2 No. @ Tk. 389.00 each = Tk. 77.80
(c) Extra skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(d) Extra ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(e) Extra for local carriage, storage & sundries etc. L.S. = Tk. 14.70
Total = Tk. 447.40
Profit 10.00% = Tk. 44.74
Overhead 3.50% = Tk. 15.66
= Tk. 507.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 29.55
Grand total = Tk. 537.35
Rate per cft. = Tk. 5.37
Rate per cum. = Tk. 189.64

Say, Tk. 190 .00 Per cum.

IItem No.- 07.10


Extra rate over the rate of form work / shuttering (wooden) of RCC works in columns, capitals, liftwalls & walls where the free height of the
structure exceeds 4 meter [rate is considered for the height of each addl. 4 (four) meter or part]
Considering 1 sqm.
(a) Extra for scaffolding [5% of shuttering or form work
using wooden shutter for column, pedestal etc.) L.S. = Tk. 17.16
Total = Tk. 17.16
Profit 10.00% = Tk. 1.72
Overhead 3.50% = Tk. 0.60
= Tk. 19.48
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1.13
Grand total = Tk. 20.61

Say, Tk. 21 .00 Per sqm.

Item No.- 07.11


Extra rate over the rate of form work / shuttering (steel) of RCC works in columns, capitals, liftwalls & walls where the free height of the
structure exceeds 4 meter [rate is considered for the height of each addl. 4 (four) meter or part]
Considering 1 sqm.
(a) Extra for scaffolding [5% of shuttering or form work
using steel shutter for column, pedestal etc.) L.S. = Tk. 15.53
Total = Tk. 15.53
Profit 10.00% = Tk. 1.55
Overhead 3.50% = Tk. 0.54
= Tk. 17.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1.03
Grand total = Tk. 18.65
Analysis of PWD SoR 2014 for Civil Works 172

Say, Tk. 19 .00 Per sqm.

Item No.- 07.12


Extra rate over the rate of RCC (materials, consumables and laying/placing concrete) works in Tee beams, Ell beams and rectangular beams
where the of the structure exceeds 4 meter (rate is considered for each addl. meter height)
free height
Considering 100 cft. of work
(a) Extra head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(b) Extra mason 0.2 No. @ Tk. 389.00 each = Tk. 77.80
(c) Extra skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(d) Extra ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(e) Extra for local carriage, storage & sundries etc. L.S. = Tk. 24.50
Total = Tk. 457.20
Profit 10.00% = Tk. 45.72
Overhead 3.50% = Tk. 16.00
= Tk. 518.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 30.20
Grand total = Tk. 549.12
Rate per cft. = Tk. 5.49
Rate per cum. = Tk. 193.88

Say, Tk. 194 .00 Per cum.

Item No.- 07.13


Extra rate over the rate of form work / shuttering (wooden) of RCC works in Tee beams, Ell beams and rectangular beams where the
free height of the structure exceeds 4 meter (rate is considered for each addl. meter height)
Considering 1 sqm.
(a) Extra for scaffolding [10% of cost for shuttering/ formwork
using wooden shutter for Ell beams, Rectangular beams etc.] L.S. = Tk. 40.40
Total = Tk. 40.40
Profit 10.00% = Tk. 4.04
Overhead 3.50% = Tk. 1.41
= Tk. 45.85
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2.67
Grand total = Tk. 48.52

Say, Tk. 49 .00 Per sqm.

Item No.- 07.14


Extra rate over the rate of form work / shuttering (steel) of RCC works in Tee beams, Ell beams and rectangular beams where the
free height of the structure exceeds 4 meter (rate is considered for each addl. meter height)
Considering 1 sqm.
(a) Extra for scaffolding [10% of cost for shuttering/ formwork
using steel shutter for Ell beams, Rectangular beams etc.] L.S. = Tk. 34.52
Total = Tk. 34.52
Profit 10.00% = Tk. 3.45
Overhead 3.50% = Tk. 1.21
= Tk. 39.18
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2.28
Grand total = Tk. 41.46

Say, Tk. 41 .00 Per sqm.

Item No.- 07.15


Extra rate over the rate of RCC (materials, consumables and laying/placing concrete) works in floor / roof slab, cantilever slab,
waffle slab and drop panels where the free height of the structure exceeds 4 meter (rate is considered for each addl. meter height)
Considering 100 cft. of work
Analysis of PWD SoR 2014 for Civil Works 173

(a) Extra head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(b) Extra mason 0.2 No. @ Tk. 389.00 each = Tk. 77.80
(c) Extra skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(d) Extra ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(e) Extra for local carriage, storage & sundries etc. L.S. = Tk. 24.50
Total = Tk. 457.20
Profit 10.00% = Tk. 45.72
Overhead 3.50% = Tk. 16.00
= Tk. 518.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 30.20
Grand total = Tk. 549.12
Rate per cft. = Tk. 5.49
Rate per cum. = Tk. 193.88

Say, Tk. 194 .00 Per cum.

Item No.- 07.16


Extra rate over the rate of form work / shuttering for RCC works in floor / roof slab, cantilever slab,
waffle slab and drop panels where the free height of the structure exceeds 4 meter (rate is considered for each addl. meter height)
Considering 1 sqm.
(a) Extra for scaffolding [5% of shuttering / formwork
for ribbed or waffel slab) L.S. = Tk. 24.29
Total = Tk. 24.29
Profit 10.00% = Tk. 2.43
Overhead 3.50% = Tk. 0.85
= Tk. 27.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1.60
Grand total = Tk. 29.17

Say, Tk. 29 .00 Per sqm.

Item No.- 07.17


Extra rate for RCC work in additional floor: Concrete
07.17.1 Add for each addl. floor up to 5th floor: @ 0.75 Nos. lab per % cft. Per cum = Tk. 82.00
07.17.2 Add for each addl. floor from 6th floor to 9th floor: @ 1 Nos. lab per % cft. Per cum = Tk. 109.00
07.17.3 Add for each addl. floor for 10th floor & above: @ 1.25 Nos. lab. per % cft. Per cum = Tk. 136.00

Item No.- 07.18


Extra rate for RCC work in additional floor: Formwork / shuttering including curing
07.18.1 Add for each addl. floor up to 5th floor: @ 0.1 Nos. lab per sqm. Per sqm. = Tk. 31.00
07.18.2 Add for each addl. floor from 6th floor to 9th floor: @ 0.15 Nos. lab per sqm. Per sqm. = Tk. 46.00
07.18.3 Add for each addl. floor for 10th floor & above: @ 0.2 Nos. lab. per sqm. Per sqm. = Tk. 62.00

Item No.- 07.19


Extra cost for making as-cast surface of the reinforced cement concrete
Considering 100 sft finished surface area of concrete

(a) Extra cost for shorted out shutter 100 sft. @ Tk. 16.04 Per sft. = Tk. 1,604.00
(b) Extra labour for placing shutter 100 sft. @ Tk. 4.80 Per sft. = Tk. 480.00
(c) Shutter releasing agent / form oil 1 liter @ Tk. 150.00 Per liter = Tk. 150.00
(d) Sundries, incidental and extra supervision L.S. = Tk. 150.00
Total = Tk. 2,384.00
Profit 10.00% = Tk. 238.40
Overhead 3.50% = Tk. 83.44
= Tk. 2,705.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 157.48
Grand total = Tk. 2,863.32
Analysis of PWD SoR 2014 for Civil Works 174

Rate per sqm. = Tk. 308.21

Say, Tk. 308 .00 Per sqm.


Item No.- 07.20.1
Supply and use of water reducing chemical admixture in concrete: Type - A
Considering 1 liter
(a) Cost of admixture 1 liter @ Tk. 150.00 each = Tk. 150.00
(b) Carriage, safe storage, mixing & sundries etc. L.S. = Tk. 7.35
Total = Tk. 157.35
Profit 10.00% = Tk. 15.74
Overhead 3.50% = Tk. 5.51
= Tk. 178.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10.39
Grand total = Tk. 188.99
Rate per liter. = Tk. 188.99

Say, Tk. 189 .00 Per liter

Item No.- 07.20.2


Supply and use of retarding chemical admixture in concrete: Type - B
Considering 1 liter
(a) Cost of admixture 1 liter @ Tk. 155.00 each = Tk. 155.00
(b) Carriage, safe storage, mixing & sundries etc. L.S. = Tk. 7.35
Total = Tk. 162.35
Profit 10.00% = Tk. 16.24
Overhead 3.50% = Tk. 5.68
= Tk. 184.27
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10.72
Grand total = Tk. 194.99
Rate per liter. = Tk. 194.99

Say, Tk. 195 .00 Per liter

Item No.- 07.20.3


Supply and use of accelerating chemical admixture in concrete: Type - C
Considering 1 liter
(a) Cost of admixture 1 liter @ Tk. 160.00 each = Tk. 160.00
(b) Carriage, safe storage, mixing & sundries etc. L.S. = Tk. 7.35
Total = Tk. 167.35
Profit 10.00% = Tk. 16.74
Overhead 3.50% = Tk. 5.86
Tk. 189.95
VAT 5.50% = Tk. 10.45
Grand total = Tk. 200.40
Rate per liter. = Tk. 200.40

Say, Tk. 200 .00 Per liter


Item No.- 07.20.4
Supply and use of water-reducing and retarding chemical admixture in concrete: Type - D
Considering 1 liter
(a) Cost of admixture 1 liter @ Tk. 145.00 each = Tk. 145.00
(b) Carriage, safe storage, mixing & sundries etc. L.S. = Tk. 7.35
Total = Tk. 152.35
Profit 10.00% = Tk. 15.24
Overhead 3.50% = Tk. 5.33
= Tk. 172.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10.06
Analysis of PWD SoR 2014 for Civil Works 175

Grand total = Tk. 182.98


Rate per liter. = Tk. 182.98

Say, Tk. 183 .00 Per liter

Item No.- 07.20.5


Supply and use of water-reducing and accelerating chemical admixture in concrete: Type - E
Considering 1 liter
(a) Cost of admixture 1 liter @ Tk. 165.00 each = Tk. 165.00
(b) Carriage, safe storage, mixing & sundries etc. L.S. = Tk. 7.35
Total = Tk. 172.35
Profit 10.00% = Tk. 17.24
Overhead 3.50% = Tk. 6.03
= Tk. 195.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 11.39
Grand total = Tk. 207.01
Rate per liter. = Tk. 207.01

Say, Tk. 207 .00 Per liter

Item No.- 07.20.6


Supply and use of water-reducing high range chemical admixture in concrete: Type - F
Considering 1 liter
(a) Cost of admixture 1 liter @ Tk. 180.00 each = Tk. 180.00
(b) Carriage, safe storage, mixing & sundries etc. L.S. = Tk. 7.35
Total = Tk. 187.35
Profit 10.00% = Tk. 18.74
Overhead 3.50% = Tk. 6.56
= Tk. 212.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12.38
Grand total = Tk. 225.03
Rate per liter. = Tk. 225.03

Say, Tk. 225 .00 Per liter

Item No.- 07.20.7


Supply and use of water-reducing high range and retarding chemical admixture in concrete: Type - G
Considering 1 liter
(a) Cost of admixture 1 liter @ Tk. 135.00 each = Tk. 135.00
(b) Carriage, safe storage, mixing & sundries etc. L.S. = Tk. 7.35
Total = Tk. 142.35
Profit 10.00% = Tk. 14.24
Overhead 3.50% = Tk. 4.98
= Tk. 161.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 9.40
Grand total = Tk. 170.97
Rate per liter. = Tk. 170.97

Say, Tk. 171 .00 Per liter

Item No.- 07.21.1


Water-proofing membrane on external surface of primed vertical or inclined wall /on plastered and primed
back-wall and concrete cast against membrane (excluding cost of back fill/brick wall on back/plaster
when membrane laid on back-wall and concrete cast against membrane)
Considering 10 sqm. of work
1. Cost of primer on the
surface to be bonded 1 liter @ Tk. 500.00 Per liter = Tk. 500.00
Analysis of PWD SoR 2014 for Civil Works 176

2. Cost of membrane in/c 10%


wastage and laping 11 sqm. @ Tk. 605.00 Per sqm. = Tk. 6,655.00
3. Cost for laying membrance in/c cleaning surface
(a) Foreman 0.50 No. @ Tk. 567.00 each = Tk. 283.50
(b) Skilled labour 0.50 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(d) Local carriage, storage, tools & plant, sundries etc. L.S. = Tk. 122.50
Total = Tk. 7,957.50
Profit 10.00% = Tk. 795.75
Overhead 3.50% = Tk. 278.51
= Tk. 9,031.76
Add VAT with adjustment factor 1.0582 5.50% = Tk. 525.66
Grand total = Tk. 9,557.42
Rate per sqm. = Tk. 955.74

Say, Tk. 956 .00 Per sqm..

Item No.- 07.21.2


Water-proofing membrane on made up surface below the floor or below the horizontal surfaces with
temporary protective cover using polysterene/1.5" thick sand-cement mortar in 4:1 /or by equally
effective alternative (rate is excluding the cost of protective cover).
Considering 10 sqm. of work
1. Cost of membrane in/c
10% wastage and laping 11 sqm. @ Tk. 605.00 Per sqm. = Tk. 6,655.00
3. Cost for laying membrance in/c cleaning surface
4. Foreman 0.25 No. @ Tk. 567.00 each = Tk. 141.75
(a) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(b) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
(c) Local carriage, storage, tools & plant, sundries etc. L.S. = Tk. 122.50
Total = Tk. 7,117.50
Profit 10.00% = Tk. 711.75
Overhead 3.50% = Tk. 249.11
= Tk. 8,078.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 470.17
Grand total = Tk. 8,548.53
Rate per sqm. = Tk. 854.85

Say, Tk. 855 .00 Per sqm.

Item No.- 07.21.3


Water-proofing membrane on the floor or on the horizontal surfaces with permanent protective cover
& wearing coarse (rate is excluding the cost of protective cover and wearing coarse)
Considering 10 sqm of work
1. Cost of membrane in/c
15% wastage and laping 11.5 sqm. @ Tk. 605.00 Per sqm. = Tk. 6,957.50
2. Cost for laying membrance in/c cleaning surface
(a) Foreman 0.25 No. @ Tk. 567.00 each = Tk. 141.75
(b) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
(d) Local carriage, storage, tools & plant, sundries etc. L.S. = Tk. 122.50
Total = Tk. 7,420.00
Profit 10.00% = Tk. 742.00
Overhead 3.50% = Tk. 259.70
= Tk. 8,421.70
Add VAT with adjustment factor 1.0582 5.50% = Tk. 490.15
Grand total = Tk. 8,911.85
Rate per sqm. = Tk. 891.19
Analysis of PWD SoR 2014 for Civil Works 177

Say, Tk. 891 .00 Per sqm.

Item No.- 07.22


20 mm thick water-proofing work in masonry or concrete surface with sand-cement mortar mixed
with specified admixure
Considering 10 sqm. of work
1. Sand (F.M. 1.2) 7.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 127.50
2. Cement 3.25 bags @ Tk. 440.00 Per bag. = Tk. 1,430.00
3. Admixture 4.50 liter. @ Tk. 150.00 Per liter = Tk. 675.00
4. Mixing and laying
(a) Head mason 0.5 No. @ Tk. 493.00 each = Tk. 246.50
(b) Mason 2 Nos. @ Tk. 389.00 each = Tk. 778.00
(c) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
(d) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
5. Carriage, storage, tools & plant, safety provisions, scaffolding, sundries etc. L.S. = Tk. 122.50
Total = Tk. 4,230.50
Profit 10.00% = Tk. 423.05
Overhead 3.50% = Tk. 148.07
= Tk. 4,801.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 279.46
Grand total = Tk. 5,081.08
Rate per sqm. = Tk. 508.11

Say, Tk. 508 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 178

DIVISION 08 : M.S. FABRICATION, EXPANSION & BEARING JOINT


Item No.- 08.1.1
Supplying, fabrication etc of M.S. rod in RCC works in all floors: 300 grade (B300D-R) / B350DWR, deformed bar with
minimum fy = 300 Mpa,min fu=375Mpa or N/mm2
Considering 50 kg of work splice 5%
A. Materials: net wastage 1%
(i) M.S. rod: 275 grade in/c splice & wastage 53 kg @ Tk. 59.00 Per kg. = Tk. 3,127.00
(ii) G.I. Wire 0.5 kg @ Tk. 110.00 Per kg. = Tk. 55.00
B. Labour
(i) Rod binder 0.1 No. @ Tk. 421.00 each = Tk. 42.10
(ii) Helper to rod binder 0.45 No. @ Tk. 304.00 each = Tk. 136.80
(iii) Local carriage, T & P, laboratory test etc. L.S. = Tk. 49.00
Total = Tk. 3,409.90
Profit 10.00% = Tk. 340.99
Overhead 3.50% = Tk. 119.35
= Tk. 3,870.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 225.25
Grand total = Tk. 4,095.49
Rate per quintal = Tk. 8,190.98

Say, Tk. 8,191 .00 Per quintal(100kg)


Tk. 81.91 per kg
Item No.- 08.1.2
Supplying, fabrication etc of M.S. rod in RCC works in all floors: 420 grade deformed bar with
minimum fy = 420 Mpa or N/mm2 qty 50 kg
Considering 50 kg of work splice 5%
A. Materials: wastage 1%
(i) M.S. rod: 420 grade in/c 1% wastage 53 kg @ Tk. 61.50 Per kg. = Tk. 3,259.50
(ii) G.I. wire 0.5 kg @ Tk. 110.00 Per kg. = Tk. 55.00
B. Labour
(i) Rod binder 0.1 Nos. @ Tk. 421.00 each = Tk. 42.10
(ii) Helper to rod bindr 0.45 Nos. @ Tk. 304.00 each = Tk. 136.80
(iii) Local carriage, T & P, laboratory test test etc. L.S. = Tk. 49.00
Total = Tk. 3,542.40
Profit 10.00% = Tk. 354.24
Overhead 3.50% = Tk. 123.98
= Tk. 4,020.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 234.00
Grand total = Tk. 4,254.62
Rate per quintal = Tk. 8,509.24

Say, Tk. 8,509 .00 Per quintal


Tk. 85 per kg
Item No.- 08.2
Extra rate for RCC work in additional floor including contractor's profit and VAT: Reinforcement
08.2.1 Add for each addl. floor up to 5th floor: @ 1/8 Nos. labour per quintal per kg = Tk. 0.39
08.2.2 Add for each addl. floor from 6th floor to 9th floor: @ 1/4 Nos. lab per quintal per kg = Tk. 0.77
08.2.3 Add for each addl. floor for 10th floor & above: @ 0.3/8 Nos. lab. per quintal per kg = Tk. 1.15

Item No.- 08.3


Mild steel work in roof truss
Considering 50 kg of work
(i) M.S. sections in/c 3% wastage 51.5 kg @ Tk. 61.50 Per kg. = Tk. 3,167.25
(ii) Fabrication, fitting, fixing revetting,
welding and hoisting in/c cost of revets,
bolts etc, and painting complete. 50 kg @ Tk. 40.53 Per kg. = Tk. 2,026.50
Analysis of PWD SoR 2014 for Civil Works 179

Total = Tk. 5,193.75


Profit 10.00% = Tk. 519.38
Overhead 3.50% = Tk. 181.78
= Tk. 5,894.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 343.09
Grand total = Tk. 6,238.00
Rate per quintal = Tk. 12,476.00

Say, Tk. 12,476 .00 Per quintal


Tk. 125 per kg
Item No.- 08.4
Fabrication and supplying Fan hook of 5/8" dia M.S. rod in/c fitting fixing in RCC.
Considering 1 No. fan-hook
(a) 5/8" dia long M.S. rod 3.00 rft.
= 2.01 Ibs @ Tk. 27.89 Per Ib. = Tk. 56.06
(b) Fabtication & fitting fixing in position L.S. = Tk. 29.40
Total = Tk. 85.46
Profit 10.00% = Tk. 8.55
Overhead 3.50% = Tk. 2.99
= Tk. 97.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5.65
Grand total = Tk. 102.65
Rate per No. = Tk. 102.65
=
Say, Tk. 103 .00 Each

Item No.- 08.5.1


Construction of expansion joint in RCC floor/ roof slabs or beams with V-folded copper sheet.
Considering 10 rft. of work
1. Cost of (2 x 4'-0" + 2 x 3-0" + 2" av.)
= 16" width copper sheet: 13.33 sft. @ Tk. 198.00 Per sft. = Tk. 2,639.34
2. Mason 1 Nos. @ Tk. 389.00 each = Tk. 389.00
3. Skilled labour 1 Nos. @ Tk. 303.00 each = Tk. 303.00
4. Cost of mastic or hot bitumenous
sealing compound fill 10 rft. @ Tk. 109.60 Per rft = Tk. 1,096.00
Total = Tk. 4,427.34
Profit 10.00% = Tk. 442.73
Overhead 3.50% = Tk. 154.96
= Tk. 5,025.03
Add VAT with adjustment factor 1.0582 5.50% = Tk. 292.46
Grand total = Tk. 5,317.49
Rate per rft. = Tk. 531.75
Rate per rm = Tk. 1,744.67

Say, Tk. 1,745 .00 Per rm.

Item No.- 08.5.2


Construction of expansion joint in RCC floor/ roof slabs or beams with V-folded Aluminium Water Stop sheet.
Considering 10 rft. of work
1. Cost of (2 x 4'-0" + 2 x 0'-3" + 2" av.)
= 16" width aluminium sheet: 13.33 sft. @ Tk. 144.00 Per sft. = Tk. 1,919.52
2. Mason 1 Nos. @ Tk. 389.00 each = Tk. 389.00
3. Skilled labour 1 Nos. @ Tk. 303.00 each = Tk. 303.00
4. Cost of mastic or hot bitumenous
sealing compound fill 10 rft. @ Tk. 109.60 Per rft = Tk. 1,096.00
Total = Tk. 3,707.52
Profit 10.00% = Tk. 370.75
Analysis of PWD SoR 2014 for Civil Works 180

Overhead 3.50% = Tk. 129.76


= Tk. 4,208.03
Add VAT with adjustment factor 1.0582 5.50% = Tk. 244.91
Grand total = Tk. 4,452.94
Rate per rft. = Tk. 445.29
Rate per rm = Tk. 1,461.00

Say, Tk. 1,461 .00 Per rm.

Item No.- 08.5.3


Construction of expansion joint in RCC floor/ roof slabs or beams with V-folded Aluminium Water
Stop sheet and 1/4" thick M.S. Plate..
Considering 10 rft. of work
1. Cost of (2 x 4'-0" + 2 x 0'-3" + 2" av.)
= 16" width aluminium sheet: 13.33 sft. @ Tk. 144.00 Per sft. = Tk. 1,919.52
2. Cost of 1/4" thick & 6" wide M.S. plate:
@ 10.20 Ib per sft. 5.00 sft.
= 51.05 Ibs @ Tk. 38.55 Per Ib = Tk. 1,967.98
3. Mason 1 Nos. @ Tk. 389.00 each = Tk. 389.00
4. Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
5. Cost of mastic or hot bitumenous
sealing compound fill and
fabrication of steel plate etc. 10 rft. @ Tk. 120.56 Per rft = Tk. 1,205.60
Total = Tk. 6,088.10
Profit 10.00% = Tk. 608.81
Overhead 3.50% = Tk. 213.08
= Tk. 6,909.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 402.17
Grand total = Tk. 7,312.16
Rate per rft. = Tk. 731.22
Rate per rm = Tk. 2,399.13

Say, Tk. 2,399 .00 Per rm.


Item No.- 08.6
Item No.- 08.6.1
Supplying, fitting and fixing Ribbed (with non centre bulb) PVC water stopper of width approx. 250mm and approx 9mm thick, for immovable (non working) RCC joints,
with 1.5" x 2.5" wooden batten at the top and bottom, binding with GI wire etc.
Break-up for 20 rft. work
1. Water stopper in/c 5% wastage 21.00 rft. @ Tk. 138.00 Per rft. = Tk. 2,898.00
2. Wood (using 3 times)
2 x 20'-0" x 1.5" x 2.5" = 1.00 cft.
Wastage 5% = 0.05 cft.
1.05 cft. @ Tk. 470.00 Per cft. = Tk. 164.50
3. Carpentry work
(i) Carpenter 0.20 Nos. @ Tk. 423.00 each = Tk. 84.60
(ii) Helper 0.40 Nos. @ Tk. 304.00 each = Tk. 121.60
4. Placing and removing wooden bit in/c cleaning RCC surface
(i) Mason 1.00 Nos. @ Tk. 389.00 each = Tk. 389.00
(ii) Ordinary Labour 2.00 Nos. @ Tk. 245.00 each = Tk. 490.00
5. Watage of RCC work L.S. = Tk. 68.75
6. G.I. Wire, nails etc. L.S. = Tk. 18.26
7. Tools and plant, sundries etc.etc. L.S. = Tk. 81.67
Total = Tk. 4,316.38
Profit 10.00% = Tk. 431.64
Overhead 3.50% = Tk. 151.07
= Tk. 4,899.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 285.13
Analysis of PWD SoR 2014 for Civil Works 181

Grand total = Tk. 5,184.22


Rate per rft. = Tk. 259.21
Rate per rm = Tk. 850.47

Say Tk. 850 .00 per rm.

Item No.- 08.6.2


Supplying, fitting and fixing Ribbed with centre bulb PVC water stopper of width approx. 250mm and approx 9mm thick, for immovable (non working) RCC joints,
with 1.5" x 2.5" wooden batten at the top and bottom, binding with GI wire etc.
Break-up for 20 rft. work
1. Water stopper in/c 5% wastage 21.00 rft. @ Tk. 138.00 Per rft. = Tk. 2,898.00
2. Wood (using 3 times)
2 x 20'-0" x 1.5" x 2.5" = 1.00 cft.
Wastage 5% = 0.05 cft.
1.05 cft. @ Tk. 470.00 Per cft. = Tk. 164.50
3. Carpentry work
(i) Carpenter 0.20 Nos. @ Tk. 423.00 each = Tk. 84.60
(ii) Helper 0.40 Nos. @ Tk. 304.00 each = Tk. 121.60
4. Placing and removing wooden bit in/c cleaning RCC surface
(i) Mason 1.00 Nos. @ Tk. 389.00 each = Tk. 389.00
(ii) Ordinary Labour 2.00 Nos. @ Tk. 245.00 each = Tk. 490.00
5. Watage of RCC work L.S. = Tk. 68.75
6. G.I. Wire, nails etc. L.S. = Tk. 18.26
7. Tools and plant, sundries etc.etc. L.S. = Tk. 81.67
Total = Tk. 4,316.38
Profit 10.00% = Tk. 431.64
Overhead 3.50% = Tk. 151.07
= Tk. 4,899.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 285.13
Grand total = Tk. 5,184.22
Rate per rft. = Tk. 259.21
Rate per rm = Tk. 850.47

Say Tk. 936 .00 per rm.

Item No.- 08.7


Supplying, fitting and fixing 10" wide 16 SWG Aluminium Sheet water stopper in construction joint of RCC vertical
wall etc.
Break-up for 20 rft. work
1. 16 BWG Aluminium sheet
1 x 20'-0" x 10" = 16.60 sft.
Wastage 5% = 0.83 sft.
17.43 sft.
= 3.77 kg @ Tk. 335.18 Per kg. = Tk. 1,263.63
3. Labour for fitting, fixing in position
(i) Mason 0.20 Nos. @ Tk. 389.00 each = Tk. 77.80
(ii) Skilled Labour 0.20 Nos. @ Tk. 303.00 each = Tk. 60.60
4. G.I. Wire, nails etc. L.S. = Tk. 30.43
5. Tools and plants, sundries etc. L.S. = Tk. 20.42
Total = Tk. 1,452.88
Profit 10.00% = Tk. 145.29
Overhead 3.50% = Tk. 50.85
= Tk. 1,649.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 95.97
Grand total = Tk. 1,744.99
Rate per rft. = Tk. 87.25
Rate per rm = Tk. 286.27
Analysis of PWD SoR 2014 for Civil Works 182

Say Tk. 286 .00 per rm.

Item No.- 08.8


Providing bearing joints fixed or free with 10" x 15" x 3/8" M.S. shoe plate fitted in the truss angle.
Considering 1 No. shoe plate
1. Cost of 3/8" thick shoe plate: @ 15.31 Ib per sft.
2 x 0'-10" x 1'-3" = 2.08 sft
= 31.84 Ib @ Tk. 38.55 Per Ib. = Tk. 1,227.43
2. Cost of 2 Nos. 3/4" anchor rods: @ 1.5 Ib per rft.
2 x 4'-0" = 8 rft.
= 12 Ibs @ Tk. 27.89 Per Ib. = Tk. 334.68
3. Cost of counter sunk revets 10 Nos. @ Tk. 20.00 each = Tk. 200.00
4. Fabrication and fixing in position L.S. = Tk. 857.50
Total = Tk. 2,619.61
Profit 10.00% = Tk. 261.96
Overhead 3.50% = Tk. 91.69
= Tk. 2,973.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 173.05
Grand total = Tk. 3,146.31
Rate per No. = Tk. 3,146.31

Say, Tk. 3,146 .00 Each


Analysis of PWD SoR 2014 for Civil Works 183

DIVISION 09 : PILE WORK


Item No.- 09.1
Drilling /Boring including equipment and labour for cast-in-situ piling
09.1.1 400 mm dia 400 20
09.1.1.1 Considering executing 400 mm /16 inch dia & 20 meter long pile in day. 0.71 day
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance
and insurance coverage etc. 0.71 day @ Tk. 8,820.00 Per day = Tk. 6,262.20
2 Driving log recorder 0.71 No. @ Tk. 567.00 Per day Tk. 402.57
3 Foreman/supervisor 0.71 No. @ Tk. 567.00 Per day = Tk. 402.57
4 Skilled labour: (3*.75) nos 2.13 No. @ Tk. 303.00 Per day = Tk. 645.39
5 Ordinary labour : 6*.75 nos 4.26 No. @ Tk. 245.00 Per day = Tk. 1,043.70
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 8,756.43
Profit 10.00% = Tk. 875.64
Overhead 3.50% = Tk. 306.48
= Tk. 9,938.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 578.43
Grand total = Tk. 10,516.98
20m in .75 day Rate per meter = Tk. 525.85
1.33nos 20m long pile per day(8hrs)
0.0375day (18min) per m of pile Say, Tk. 536 .00 Per rm

09.1.1.2 Considering executing 400 mm /16 inch dia 29 meter long pile in days. 29 m 1.07 day
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance and
insurance coverage etc. 1.07 days @ Tk. 8,820.00 Per day = Tk. 9,437.40
2 Driving log recorder 1.07 Nos. @ Tk. 567.00 Per day = Tk. 606.69
3 Foreman/supervisor 1.07 Nos. @ Tk. 567.00 each = Tk. 606.69
4 Skilled labour 3.21 Nos. @ Tk. 303.00 each = Tk. 972.63
5 Ordinary labour 6.42 Nos. @ Tk. 245.00 each = Tk. 1,572.90
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 13,196.31
Profit 10.00% = Tk. 1,319.63
Overhead 3.50% = Tk. 461.87
= Tk. 14,977.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 871.72
Grand total = Tk. 15,849.53
Rate per meter = Tk. 546.54

Say, Tk. 557 .00 Per rm

So, extra cost for each addl. meter boring and length up to 30m = 1.5(B-A)/9 = Tk. 3.50
Say, Tk. 4 .00 Per meter

09.1.2 450 mm dia 450 20 r= 1.27 0.90 d


09.1.2.1 Considering executing one 450 mm / 18 inch dia & 20 meter long pile in days ?? 0.9 day
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance
and insurance coverage etc. 0.9 days @ Tk. 8,820.00 Per day = Tk. 7,938.00
2 Driving log recorder 0.9 days Tk. 567.00 Tk. 510.30
3 Foreman/supervisor 0.90 Nos. @ Tk. 567.00 each = Tk. 510.30
4 Skilled labour 2.7 Nos. @ Tk. 303.00 each = Tk. 818.10
5 Ordinary labour 5.4 Nos. @ Tk. 245.00 each = Tk. 1,323.00
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 11,099.70
Profit 10.00% = Tk. 1,109.97
Overhead 3.50% = Tk. 388.49
= Tk. 12,598.16
Analysis of PWD SoR 2014 for Civil Works 184

Add VAT with adjustment factor 1.0582 5.50% = Tk. 733.23


Grand total = Tk. 13,331.39
Rate per meter = Tk. 666.57

Say, Tk. 680 .00 Per rm

450 29
09.1.2.2 Considering executing 450 mm /18 inch dia & 29 meter long pile in days 1.36
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance
and insurance coverage etc. 1.36 days @ Tk. 8,820.00 Per day = Tk. 11,995.20
2 Driving log recorder 1.36 days @ Tk. 567.00 Per day = Tk. 771.12
2. Foreman/supervisor 1.36 Nos. @ Tk. 567.00 each = Tk. 771.12
3. Skilled labour 4.08 Nos. @ Tk. 303.00 each = Tk. 1,236.24
4. Ordinary labour 8.16 Nos. @ Tk. 245.00 each = Tk. 1,999.20
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 16,772.88
Profit 10.00% = Tk. 1,677.29
Overhead 3.50% = Tk. 587.05
= Tk. 19,037.22
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,107.99
Grand total = Tk. 20,145.21
Rate per meter = Tk. 694.66

Say, Tk. 709 .00 Per rm

So, extra cost for each addl. meter boring and length up to 29 m= 1.5(B-A)/9 = Tk. 4.83

Say, Tk. 5 .00 Per meter

09.1.3 500 mm dia 500 20 1.11


09.1.3.1 Considering executing 500 mm /20 inch dia & 20 meter long pile in days. 1.11 days
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance
and insurance coverage etc. 1.11 days @ Tk. 8,820.00 Per day = Tk. 9,790.20
2 Driving log recorder 1.11 days Tk. 567.00 Tk. 629.37
3 Foreman/supervisor 1.11 Nos. @ Tk. 567.00 each = Tk. 629.37
4. Skilled labour 3.33 Nos. @ Tk. 303.00 each = Tk. 1,008.99
5. Ordinary labour 6.66 Nos. @ Tk. 245.00 each = Tk. 1,631.70
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 13,689.63
Profit 10.00% = Tk. 1,368.96
Overhead 3.50% = Tk. 479.14
= Tk. 15,537.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 904.31
Grand total = Tk. 16,442.04
Rate per meter = Tk. 822.10

Say, Tk. 839 .00 Per rm

500 29 m 1.68
09.1.3.2 Considering executing 500 mm /20 inch dia & 29 meter long pile in days 1.68
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance and
insurance coverage etc. 1.68 days @ Tk. 8,820.00 Per day = Tk. 14,817.60
2 Driving log recorder 1.68 days @ Tk. 567.00 Tk. 952.56
3 Foreman/supervisor 1.68 Nos. @ Tk. 567.00 each = Tk. 952.56
4 Skilled labour 5.04 Nos. @ Tk. 303.00 each = Tk. 1,527.12
5 Ordinary labour 10.08 Nos. @ Tk. 245.00 each = Tk. 2,469.60
Analysis of PWD SoR 2014 for Civil Works 185

6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 20,719.44
Profit 10.00% = Tk. 2,071.94
Overhead 3.50% = Tk. 725.18
= Tk. 23,516.56
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,368.69
Grand total = Tk. 24,885.25
Rate per meter = Tk. 858.11

Say, Tk. 875 .00 Per rm

So, extra cost for each addl. meter boring and length up to 29 m=1.5 (B-A)/9 = Tk. 6.75

Say, Tk. 7 .00 Per meter

09.1.4 550 mm dia 550 20 1.34


09.1.4.1 Considering executing 550 mm/22 inch dia & 20 meter pile in days. 1.34
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance
and insurance coverage etc. 1.34 days @ Tk. 8,820.00 Per day = Tk. 11,818.80
2 Driving log recorder 1.34 days @ Tk. 567.00 Per day = Tk. 759.78
3. Foreman/supervisor 1.375 Nos. @ Tk. 567.00 each = Tk. 779.63
4 Skilled labour 4.02 Nos. @ Tk. 303.00 each = Tk. 1,218.06
5. Ordinary labour 8.04 Nos. @ Tk. 245.00 each = Tk. 1,969.80
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 16,546.07
Profit 10.00% = Tk. 1,654.61
Overhead 3.50% = Tk. 579.11
= Tk. 18,779.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,093.00
Grand total = Tk. 19,872.79
Rate per meter = Tk. 993.64

Say, Tk. 1,014 .00 Per rm


550 29 2.04
09.1.4.2 Considering executing 550 mm /22 inch dia & 29 meter long pile in days 2.04
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance
and insurance coverage etc. 2.04 days @ Tk. 8,820.00 Per day = Tk. 17,992.80
2 Driving log recorder 2.04 days @ Tk. 567.00 Per day = Tk. 1,156.68
3. Foreman/supervisor 2.04 Nos. @ Tk. 567.00 each = Tk. 1,156.68
4. Skilled labour 6.12 Nos. @ Tk. 303.00 each = Tk. 1,854.36
5. Ordinary labour 12.24 Nos. @ Tk. 245.00 each = Tk. 2,998.80
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 25,159.32
Profit 10.00% = Tk. 2,515.93
Overhead 3.50% = Tk. 880.58
= Tk. 28,555.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,661.98
Grand total = Tk. 30,217.81
Rate per meter = Tk. 1,041.99

Say, Tk. 1,063 .00 Per rm

So, extra cost for each addl. meter boring and length up to 29 m=1.5 (B-A)/9 = Tk. 8.17

Say, Tk. 8 .00 Per meter


09.1.5 600 mm / 24 inch dia pile 600 20 1.60
09.1.5.1 Considering executing 600 mm / 24 inch dia & 20 meter long pile in days. 1.6 days
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
Analysis of PWD SoR 2014 for Civil Works 186

mobilization, demobilization, maintenance


and insurance coverage etc. 1.60 days @ Tk. 8,820.00 Per day = Tk. 14,112.00
2 Driving log recorder 1.60 days @ Tk. 567.00 Per day Tk. 907.20
3 Foreman/supervisor 1.60 Nos. @ Tk. 567.00 each = Tk. 907.20
4 Skilled labour 4.80 Nos. @ Tk. 303.00 each = Tk. 1,454.40
5 Ordinary labour 9.60 Nos. @ Tk. 245.00 each = Tk. 2,352.00
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 19,732.80
Profit 10.00% = Tk. 1,973.28
Overhead 3.50% = Tk. 690.65
= Tk. 22,396.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,303.51
Grand total = Tk. 23,700.24
Rate per meter = Tk. 1,185.01

Say, Tk. 1,209 .00 Per rm


600 29 2.42
09.1.5.2 Considering executing 600 mm /24 inch dia & 29 meter pile in days. 2.42
1. Hire charge of rig set in/c fuel, lubricant, bentonite,
mobilization, demobilization, maintenance
and insurance coverage etc. 2.42 days @ Tk. 8,820.00 Per day = Tk. 21,344.40
2 Driving log recorder 2.42 days @ Tk. 567.00 Per day Tk. 1,372.14
3 Foreman/supervisor 2.42 Nos. @ Tk. 567.00 each = Tk. 1,372.14
4 Skilled labour 7.26 Nos. @ Tk. 303.00 each = Tk. 2,199.78
5 Ordinary labour 14.52 Nos. @ Tk. 245.00 each = Tk. 3,557.40
6 power ,bentonite ,water, clean & sundry 1.02 Total = Tk. 29,845.86
Profit 10.00% = Tk. 2,984.59
Overhead 3.50% = Tk. 1,044.61
= Tk. 33,875.06
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,971.56
Grand total = Tk. 35,846.62
Rate per meter = Tk. 1,236.09

Say, Tk. 1,261 .00 Per rm

So, extra cost for each addl. 1 m boring up to 29 meter = 1.5(B-A)/9 = Tk. 8.67

Say, Tk. 9 .00 Per meter

Item No.- 09.2


Removal of spoils/ mud accumulated during boring of cast in situ pile of different dia. With the help of mud pump and container set by truck.
Considering 200cft of spoils/ mud removing work.

1. Hire charge of 3HP mud pump 1/4 day @ Tk. 588.00 Per day = Tk. 147.00
2. Hire charge of MS steel tank (6'-6" x 10'-0" x 4'-0") 1 trip @ Tk. 350.00 Per trip = Tk. 350.00
3. Hire charge of truck 1 trip @ Tk. 975.00 Per trip = Tk. 975.00
4. Pump operator 1/4 Nos. @ Tk. 356.00 Per nos = Tk. 89.00
5. Ordinary labour 1/2 Nos. @ Tk. 245.00 Per nos = Tk. 122.50
6. Sundries and incidental cost L.S. = Tk. 100.00
Total (A+B) = Tk. 1,783.50
Profit 10.00% = Tk. 178.35
Overhead 3.50% = Tk. 62.42
= Tk. 2,024.27
Add VAT with adjustment factor 1.0582 5.50% = Tk. 117.81
Grand total = Tk. 2,142.08
Rate per cft. = Tk. 10.71
Rate per cum. = Tk. 378.22
Analysis of PWD SoR 2014 for Civil Works 187

Say, Tk. 378 .00 Per cum

Item No.- 09.3


Casting of cast in situ bored pile with reinforced cement concrete works (1 : 1.5 : 3) with stone chips to give a minimum
cylinder crushing strength of 20 Mpa.
Considering 16" dia, 65'-0" long 2 Nos pile. = 181.54 cft. concrete
A. Cost of Concrete
(a) Cost of Materials 181.54 cft. @ Tk. 23,865.00 Per % cft. = Tk. 43,324.52
(b) Cost for Placing Concrete 181.54 cft. @ Tk. 950.46 Per % cft. = Tk. 1,725.47
Tk. 45,049.99
(c) Add wastage, overflow & increase in diameter 10% = Tk. 4,505.00
Total (A) = Tk. 49,554.99
B. Hire charge of cast in situ pile driving
rig set for pouring concrete. 0 day @ Tk. 8,820.00 Per day = Tk. -
included in boring item Total (A+B) = Tk. 49,554.99
Profit 10.00% = Tk. 4,955.50
Overhead 3.50% = Tk. 1,734.42
= Tk. 56,244.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,273.51
Grand total = Tk. 59,518.42
Rate per cft. = Tk. 327.85
Rate per cum. = Tk. 11,578.02

Say, Tk. 11,578 .00 Per cum


Item No.- 09.4
Providing and making point welding
Considering 1 point welding
(a) Welding charge 1 Point @ Tk. 3.25 Per Point = Tk. 3.25
Profit 10.00% = Tk. 0.33
Overhead 3.50% = Tk. 0.11
= Tk. 3.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 0.21
Total = Tk. 3.90
Rate per point = Tk. 3.90

Say, Tk. 3.90 Per point

Item No.- 09.5


Providing and making joint weldingof min. 300 mm length
Considering 1 inch of welding two faces 2 1 inch
(a) Welding charge 1x2 2 inch @ Tk. 5.00 Per inch = Tk. 10.00
Profit 10.00% = Tk. 1.00
Overhead 3.50% = Tk. 0.35
= Tk. 11.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 0.66
Total = Tk. 12.01

472.83 rm of weld Say, Tk. 12.01 Per inch of two face


Analysis of PWD SoR 2014 for Civil Works 188

Item No.- 09.6


Labour for breaking head of cast-in-situ bored pile/pre-cast driven pile
Considering 1 cum. of work
(a) Skilled labour 7 Nos. @ Tk. 303.00 each = Tk. 2,121.00
(b) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(c) Repairing of pile head in/c materials L.S. = Tk. 194.50
(d) Straightening and bending of pile bars,
tools & plant, sundries etc. L.S. = Tk. 194.50
Total = Tk. 3,000.00
Profit 10.00% = Tk. 300.00
Overhead 3.50% = Tk. 105.00
= Tk. 3,405.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 198.17
Grand total = Tk. 3,603.17

Say, Tk. 3,603 .00 Per cum.


Item No.- 09.7.1
Conducting static load test for the cast in situ / precast pile providing required scaffolding.
For 25 tonne load for 1 test 25 29 Mton working vol
(a) Mobilization and demobilization of testing sand 90 lbs/cft 35 kg/bag 911
equipment (5 ton) by truck 2 trips @ Tk. 1,300.00 Per trip = Tk. 2,600.00
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 6,875.00
(i) Foreman 2 Nos. @ Tk. 567.00 each = Tk. 1,134.00
(ii) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(iii) Ordinary labour 10 Nos. @ Tk. 245.00 each = Tk. 2,450.00
(c) Hire charge of load testing equipment (joist, jacks and other
necessary devices in/c caliberation
charges, hydraulic fluid etc.) 1 test @ Tk. 10,642.00 Per test = Tk. 10,642.00
(d) Cost of empty gunny bags
(taking 2 times use) 455.71 bags. @ Tk. 4.50 Per bag = Tk. 2,050.70
(e) Cost of local sand as loading
materials (taking 2 times use) 455.71 cft @ Tk. 450.00 Per % cft. = Tk. 2,050.70
(f) Labour for bag filling,
stitching, loading & unloading: 911.43 bags @ Tk. 8.64 Per bag = Tk. 7,874.76
(h) Preparation of test result in standard
form in triplicate 1 test @ Tk. 6,250.00 Per test = Tk. 6,250.00
(i) Other incidental charge L.S. = Tk. 735.00
Total = Tk. 44,480.16
Profit 10.00% = Tk. 4,448.02
Overhead 3.50% = Tk. 1,556.81
= Tk. 50,484.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,938.28
Grand total = Tk. 53,423.27

Say, Tk. 53,423 .00 Per test


Tk. 2,137 per Mton
Item No.- 09.7.2
Conducting static load testfor the cast in situ / pre-cast pile providing required scaffolding.
For 75 ton load for 1 No. of test 75 87 Mton
(a) Mobilization and demobilization of load sand 2734.28571 bag
testing equipment (10 ton) by truck 3 trips @ Tk. 1,300.00 Per trip = Tk. 3,900.00
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 20,625.00
(i) Foreman 2 Nos. @ Tk. 567.00 each = Tk. 1,134.00
(ii) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(iii) Ordinary labour 12 Nos. @ Tk. 245.00 each = Tk. 2,940.00
(c) Hire charge of load testing equipment (joist, jacks
and other necessary devices in/c caliberation
Analysis of PWD SoR 2014 for Civil Works 189

charges, hydraulic fluid etc.) 1 test @ Tk. 10,642.00 Per test = Tk. 10,642.00
(d) Cost of empty gunny bags
(taking 2 times use) 1367.142857 bags. @ Tk. 4.50 Per bag = Tk. 6,152.14
(e) Cost of local sand as loading
materials (taking 2 times use) 1367.142857 cft @ Tk. 450.00 Per % cft. = Tk. 6,152.14
(f) Labour for bag filling,
stitching, loading & unloading: 2734.285714 bags @ Tk. 8.64 Per bag = Tk. 23,624.23
(h) Preparation of result in standard
form in triplicate 1 test @ Tk. 6,250.00 Per test = Tk. 6,250.00
(i) Other incidental charges L.S. = Tk. 735.00
Total = Tk. 83,972.51
Profit 10.00% = Tk. 8,397.25
Overhead 3.50% = Tk. 2,939.04
= Tk. 95,308.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5,547.07
Grand total = Tk. 100,855.87

Say, Tk. 100,856 .00 Per test


Tk. 1,345 per Mton test
Item No.- 09.7.3
Conducting static load test for the cast in situ / precast pile providing required scaffolding.
For 125 ton load for 1 No. of test 125 145
(a) Mobilization and demobilization of testing sand 3928.57143 bag
equipment (15 ton) by truck 4 trips @ Tk. 1,300.00 Per trip = Tk. 5,200.00
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 34,375.00
(i) Foreman 2 Nos. @ Tk. 567.00 each = Tk. 1,134.00
(ii) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(iii) Ordinary labour 12 Nos. @ Tk. 245.00 each = Tk. 2,940.00
(c) Hire charge of load testing equipment (joist, jacks
and other necessary devices in/c caliberation charges,
hydraulic fluid etc.) 1 test @ Tk. 10,642.00 Per test = Tk. 10,642.00
(d) Cost of empty gunny bags
(taking 2 times use) 1964.285714 bags. @ Tk. 4.50 Per bag = Tk. 8,839.29
(e) Cost of local sand as loading
materials (taking 2times use) 1964.285714 cft @ Tk. 450.00 Per % cft. = Tk. 8,839.29
(f) Labour for bag filling,
stitching, loading & unloading: 3928.571429 bags @ Tk. 8.64 Per bag = Tk. 33,942.86
(h) Preparation of result in standard
form in triplicate 1 test @ Tk. 6,250.00 Per test = Tk. 6,250.00
(i) Other incidental charges L.S. = Tk. 1,225.00
Total = Tk. 115,205.44
Profit 10.00% = Tk. 11,520.54
Overhead 3.50% = Tk. 4,032.19
= Tk. 130,758.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 7,610.26
Grand total = Tk. 138,368.43

Say, Tk. 138,368 . 00 Per test


Tk. 1,107 per Mton test
Item No.- 09.7.4
Conducting static load test for the cast in situ / precast pile providing required scaffolding.
For 175 tone load for 1 No. test 175 203
(a) Mobilization and demobilization of testing sand 6380
equipment (20 ton) by truck 5 trips @ Tk. 1,300.00 Per trip = Tk. 6,500.00
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 48,125.00
(i) Foreman 2 Nos. @ Tk. 567.00 each = Tk. 1,134.00
(ii) Skilled labour 8 Nos. @ Tk. 303.00 each = Tk. 2,424.00
Analysis of PWD SoR 2014 for Civil Works 190

(iii) Ordinary labour 16 Nos. @ Tk. 245.00 each = Tk. 3,920.00


(c) Hire charge of load testing equipment (joist, jacks
and other necessary devices in/c caliberation
charges, hydraulic fluid etc.) 1 test @ Tk. 11,824.44 Per test = Tk. 11,824.44
(d) Cost of empty gunny bags
(taking 2 times use) 3190 bags. @ Tk. 4.50 Per bag = Tk. 14,355.00
(e) Cost of local sand as loading
materials (taking 2 times use) 3190 cft @ Tk. 450.00 Per % cft. = Tk. 14,355.00
(f) Labour for bag filling,
stitching, loading & unloading: 6380 bags @ Tk. 8.64 Per bag = Tk. 55,123.20
(h) Preparation of result in
standard form in triplicate 1 test @ Tk. 6,250.00 Per test = Tk. 6,250.00
(i) Other incidental charges L.S. = Tk. 1,225.00
Total = Tk. 165,235.64
Profit 10.00% = Tk. 16,523.56
Overhead 3.50% = Tk. 5,783.25
= Tk. 187,542.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10,915.16
Grand total = Tk. 198,457.61

Say, Tk. 198,458 . 00 Per test


Tk. 1,134 per Mton test
Item No.- 09.7.5
Conducting static load test for the cast in situ / pre-cast pile providing required scaffolding.
For 225 tonne load for 1 No. test 225 261
(a) Mobilization and demobilization of testing sand 8202.85714 bag
equipment (25 ton) by truck 6 trips @ Tk. 1,300.00 Per trip = Tk. 7,800.00
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 61,875.00
(i) Foreman 2 Nos. @ Tk. 567.00 each = Tk. 1,134.00
(ii) Skilled labour 8 Nos. @ Tk. 303.00 each = Tk. 2,424.00
(iii) Ordinary labour 16 Nos. @ Tk. 245.00 each = Tk. 3,920.00
(c) Hire charge of load testing equipment (joist, jacks
and other necessary devices in/c caliberation
charges, hydraulic fluid etc.) 1 test @ Tk. 11,824.44 Per test = Tk. 11,824.44
(d) Cost of empty gunny bags
(taking 2 times use) 4101.428571 bags. @ Tk. 4.50 Per bag = Tk. 18,456.43
(e) Cost of local sand as loading
materials (taking 2 times use) 4101.428571 cft @ Tk. 450.00 Per % cft. = Tk. 18,456.43
(f) Labour for bag filling,
stitching, loading & unloading: 8202.857143 bags @ Tk. 8.64 Per bag = Tk. 70,872.69
(h) Preparation of result in standard
form in triplicate 1 test @ Tk. 6,250.00 Per test = Tk. 6,250.00
(i) Other incidental charges L.S. = Tk. 1,225.00
Total = Tk. 204,237.99
Profit 10.00% = Tk. 20,423.80
Overhead 3.50% = Tk. 7,148.33
= Tk. 231,810.12
Add VAT with adjustment factor 1.0582 5.50% = Tk. 13,491.58
Grand total = Tk. 245,301.70

Say, Tk. 245,302 . 00 Per test


Tk. 1,090.23 per Mton test
Analysis of PWD SoR 2014 for Civil Works 191

Item No.- 09.7.6


Conducting static load test for the cast in situ / precast pile providing required scaffolding.
For 275 tonne load for 1 No. of test 275 275 319 Mton
(a) Mobilization and demobilization of testing sand 10026 bag
equipment (30 ton) by truck 7 trips @ Tk. 1,300.00 Per trip = Tk. 9,100.00
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 75,625.00
(i) Foreman 2 Nos. @ Tk. 567.00 each = Tk. 1,134.00
(ii) Skilled labour 8 Nos. @ Tk. 303.00 each = Tk. 2,424.00
(iii) Ordinary labour 16 Nos. @ Tk. 245.00 each = Tk. 3,920.00
(c) Hire charge of load testing equipment (joist, jacks
and other necessary devices in/c caliberation
charges, hydraulic fluid etc.) 1 test @ Tk. 13,006.89 Per test = Tk. 13,006.89
(d) Cost of empty gunny bags
(taking 2 times use) 5012.857143 bags. @ Tk. 4.50 Per bag = Tk. 22,557.86
(e) Cost of local sand as loading
materials (taking 2 times use) 5012.857143 cft @ Tk. 450.00 Per % cft. = Tk. 22,557.86
(f) Labour for bag filling,
stitching, loading & unloading: 10025.71429 bags @ Tk. 8.64 Per bag = Tk. 86,622.17
(h) Preparation of result in standard
form in triplicate 1 test @ Tk. 6,250.00 Per test = Tk. 6,250.00
(i) Other incidental charges L.S. = Tk. 1,225.00
Total = Tk. 244,422.78
Profit 10.00% = Tk. 24,442.28
Overhead 3.50% = Tk. 8,554.80
= Tk. 277,419.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 16,146.11
Grand total = Tk. 293,565.97

Say, Tk. 293,566 . 00 Per test


Tk. 1,068
1313.54 av per Mton test

Item No.- 09.9.1


10" x 10" Pre-cast pile with reinforced cement concrete (1 : 1.5 : 3) with stone chips.
Considering 40 rft. long 10" x 10" size pile
Also Considering 100 rft. pile making work using 100 cft. concrete
A. Cost of concrete materials = Tk. 23,865.00
B. Labour, machinery, fuel & lubricants for casting = Tk. 950.46
C. Cost of shuttering for 11 Nos. of pile
Volume of concrete:
11 x 10" x 10" x 40'-0" = 305.56 cft.
(a) Cost of shuttering:
(i) 14 BWG steel sheet:
Sides: 1 x 12 x 40'-0" x 0'-10"= 400.00 sft
Add wastage 5%= 20.00 sft.
= 420.00 sft.
@ 3.05 Ib per sft.= 1281.00 Ibs. @ Tk. 38.55 Per Ib. = Tk. 49,382.55
(ii) 1.5 x 1.5 x 3/16" angle for frame:
Sides: 2 x 12 x 40'-0"= 960.00 rft.
Vertical: 12 x 41 x 1'-0"= 492.00 rft.
= 1452.00 rft.
Add wastage 5%= 72.60 rft.
1524.60 rft.
@ 1.79 Ib per rft = 2729.03 Ibs. @ Tk. 28.34 Per Ib. = Tk. 77,340.71

(iii) 1.5" x 3/16" F.I . Bar : @ 1'-0" c/c


Stiffner: 6 x 20 x 1'-2" = 140.00 rft.
Clamps: 6 x 12 x 6"= 36.00 rft.
Analysis of PWD SoR 2014 for Civil Works 192

= 176.00 rft.
Add 5% wastage= 8.8 rft.
= 184.80 rft.
@ 0.956 Ibs Per rft.= 176.67 Ibs. @ Tk. 25.40 Per Ib. = Tk. 4,487.42
(iv) Cost of nuts & bolts: 20.0 kg. @ Tk. 133.00 Per kg. = Tk. 2,660.00
(v) Manufacturing, fitting and fixing frame in/c drilling holes,
welding & supplying of chemicals etc.:
12 x 40'-0" x 0'-10"= 400.00 sft. @ Tk. 69.17 Per sft. = Tk. 27,668.00
Total = Tk. 161,538.68
Using 16 times = Tk. 10,096.17
(vi) Labour for fitting & fixing steel shuttering
in position as required 400.00 sft. @ Tk. 8.00 Per sft. = Tk. 3,200.00
(vii) Hessian tap for making
shutter water-proof. 400.00 sft. @ Tk. 1.13 Per sft. = Tk. 452.00
(viii) Curing 400.00 sft. @ Tk. 2.04 Per sft. = Tk. 816.00
Total for 305.56 cft. = Tk. 14,564.17
Cost for 100 cft. = Tk. 4,766.39
D. Cost of bed preparation:
Area of bed: 1 x 45'-0" x 13'-2"= 592.65 sft.
(a) One layer brick flat soling: 592.65 sft. @ Tk. 27.44 Per sft. = Tk. 16,262.32
(b) 1/2" thick cement finishing with
neat cement finishing 592.65 sft. @ Tk. 19.06 Per sft. = Tk. 11,295.91
Total for 305.56 cft. = Tk. 27,558.23
Cost for 100 cft. of work = Tk. 9,018.93
Using 8 times = Tk. 1,127.37
E. Polythene as separator between pile layers
during casting concrete 592.65 sft. @ Tk. 262.19 Per % sft. = Tk. 1,553.87
Cost for 100 cft. of work = Tk. 353.15
Abstract of cosr for 100 cft. of work
A. Cost of concrete = Tk. 23,865.00
B. Labour, machinery, fuel and lubricant for casting = Tk. 950.46
C. Cost of shuttering = Tk. 4,766.39
D. Cost of bed preparation = Tk. 1,127.37
E. Polythene = Tk. 353.15
Total = Tk. 31,062.37
Profit 10.00% = Tk. 3,106.24
Overhead 3.50% = Tk. 1,087.18
= Tk. 35,255.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,051.92
Grand total = Tk. 37,307.71
Rate per cft. = Tk. 373.08
Rate per rft. = Tk. 259.08
Rate per rm. = Tk. 850.04

Say, Tk. 850 . 00 Per rm.

Item No.- 09.9.2


12" x 12" Pre-cast pile with reinforced cement concrete (1 : 1.5 : 3) with stone chips.
Considering 40 rft. long 12" x 12" size pile
Also Considering 100 rft. pile making work using 100 cft. concrete
A. Cost of concrete materials = Tk. 23,865.00
B. Labour, machinery, fuel & lubricants for casting ?? = Tk. 950.46
C. Cost of shuttering for 11 Nos. of pile
Volume of concrete:
11 x 12" x 12" x 40'-0" = 440 cft.
(a) Cost of shuttering:
(i) 14 BWG steel sheet:
Analysis of PWD SoR 2014 for Civil Works 193

Sides: 1 x 12 x 40'-0" x 1'-0"= 480.00 sft


Add wastage 5%= 24.00 sft.
= 504.00 sft.
@ 3.05 Ib per sft.= 1537.20 Ibs. @ Tk. 38.55 Per Ib. = Tk. 59,259.06
(ii) 1.5 x 1.5 x 3/16" angle for frame:
Sides: 2 x 12 x 40'-0"= 960.00 rft.
Vertical: 12 x 41 x 1'-0"= 492.00 rft.
= 1452.00 rft.
Add wastage 5%= 72.60 rft.
1524.60 rft.
@ 1.79 Ib per rft = 2729.03 Ibs. @ Tk. 28.34 Per Ib. = Tk. 77,340.71

(iii) 1.5" x 3/16" F.I . Bar : @ 1'-0" c/c


Stiffner: 6 x 20 x 1'-2" = 140.00 rft.
Clamps: 6 x 12 x 6"= 36.00 rft.
= 176.00 rft.
Add 5% wastage= 8.8 rft.
= 184.80 rft.
@ 0.956 Ibs Per rft.= 176.67 Ibs. @ Tk. 25.40 Per Ib. = Tk. 4,487.42
(iv) Cost of nuts & bolts: 20.0 kg. @ Tk. 133.00 Per kg. = Tk. 2,660.00
(v) Manufacturing, fitting and fixing frame in/c drilling holes,
welding & supplying of chemicals etc.:
12 x 40'-0" x 1'-0"= 480.00 sft. @ Tk. 69.17 Per sft. = Tk. 33,201.60
Total = Tk. 176,948.79
Using 16 times = Tk. 11,059.30
(vi) Labour for fitting & fixing steel shuttering
in position as required 480.00 sft. @ Tk. 8.00 Per sft. = Tk. 3,840.00
(vii) Hessian tap for making
shutter water-proof. 480.00 sft. @ Tk. 1.13 Per sft. = Tk. 542.40
(viii) Curing 480.00 sft. @ Tk. 2.04 Per sft. = Tk. 979.20
Total for 440 cft. = Tk. 16,420.90
Cost for 100 cft. = Tk. 3,732.02
D. Cost of bed preparation:
Area of bed: 1 x 45'-0" x 15'-0"= 675.00 sft.
(a) One layer brick flat soling: 675.00 sft. @ Tk. 27.44 Per sft. = Tk. 18,522.00
(b) 1/2" thick cement finishing with
neat cement finishing 675.00 sft. @ Tk. 19.06 Per sft. = Tk. 12,865.50
Total for 440 cft. = Tk. 31,387.50
Cost for 100 cft. of work = Tk. 7,133.52
Using 8 times = Tk. 891.69
E. Polythene as separator between pile layers
during casting concrete 675.00 sft. @ Tk. 262.19 Per % sft. = Tk. 1,769.78
Cost for 100 cft. of work = Tk. 402.22
Abstract of cost for 100 cft. of work
A. Cost of concrete = Tk. 23,865.00
B. Labour, machinery, fuel and lubricant for casting = Tk. 950.46
C. Cost of shuttering = Tk. 3,732.02
D. Cost of bed preparation = Tk. 891.69
E. Polythene = Tk. 402.22
Total = Tk. 29,841.39
Profit 10.00% = Tk. 2,984.14
Overhead 3.50% = Tk. 1,044.45
= Tk. 33,869.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,971.27
Grand total = Tk. 35,841.25
Rate per cft. = Tk. 358.41
Rate per rft. = Tk. 358.41
Analysis of PWD SoR 2014 for Civil Works 194

Rate per rm. = Tk. 1,175.94

Say, Tk. 1,176 . 00 Per rm.

Item No.- 09.9.3


14" x 14" Pre-cast pile with reinforced cement concrete (1 : 1.5 : 3) with stone chips.
Considering 50 rft. long 14" x 14" size pile
Also considering 73.5 rft. long pile making work using 100 cft. concrete
A. Cost of concrete materials = Tk. 23,865.00
B. Labour, machinery, fuel & lubricants for casting = Tk. 950.46
C. Cost of shuttering for 11 No. of pile
Volume of concrete:
11 x 14" x 14" x 50'-0" = 748.61 cft.
(a) Cost of shuttering:
(i) 14 BWG steel sheet:
Sides: 12 x 50'-0" x 1'-2"= 700.00 sft.
Add wastage 5%= 35.00 sft.
= 735.00 sft.
@ 3.05 Ib per sft.= 2241.75 Ibs. @ Tk. 38.55 Per Ib. = Tk. 86,419.46
(ii) 1.5 x 1.5 x 3/16" angle for frame:
Sides: 2 x 12 x 50'-0"= 1200.00 rft.
Supports: 12 x 51 x 1'-2"= 714.00 rft.
= 1914.00 rft.
Add wastage 5%= 95.70 rft.
2009.70 rft.
@ 1.79 Ib per rft.= 3597.36 Ibs. @ Tk. 28.34 Per Ib. = Tk. 101,949.18

(iii) 1.5" x 3/16" F.I . bar: @ 1'-0" c/c


Stiffner: 6 x 25 x 1'-2"= 140.00 rft.
Clamps: 6 x 16 x 6"= 48.00 rft.
= 188.00 rft.
Add 5% wastage= 9.4 rft.
= 197.40 rft.
@ 0.956 Ibs Per rft.= 188.71 Ibs. @ Tk. 25.40 Per Ib. = Tk. 4,793.23
(iv) Cost of nuts & bolts: 25 kg. @ Tk. 133.00 Per kg. = Tk. 3,325.00
(v) Manufacturing, fitting and fixing frame in/c drilling holes,
welding & supplying of chemicals etc.:
2 x 6 x 50 x 1'-2"= 700.00 sft. @ Tk. 69.17 Per sft. = Tk. 48,419.00
Total = Tk. 244,905.87
Using 16 times = Tk. 15,306.62
(vi) Labour for fitting & fixing steel shuttering
in position as required 700.00 sft. @ Tk. 8.00 Per sft. = Tk. 5,600.00
(vii) Hessian tap for makin
shutter water proof 700.00 sft. @ Tk. 1.13 Per sft. = Tk. 791.00
Total = Tk. 21,697.62
Cost for 100 cft. of work = Tk. 2,898.39
D. Cost of bed preparation:
Area of bed: 1 x 55'-0" x 15'-0"= 825.00 sft.
(i) One layer brick flat soling: 825.00 sft. @ Tk. 27.44 Per sft. = Tk. 22,638.00
(ii) 1/2" thick cement plaster
with neat cement finishing 825.00 sft. @ Tk. 19.06 Per sft. = Tk. 15,724.50
Total = Tk. 38,362.50
Cost for 100 cft. of work = Tk. 5,124.50
Using 8 times = Tk. 640.56
E. Polythene as separator between pile layers
during casting concrete 825.00 sft. @ Tk. 262.19 Per % sft. = Tk. 2,163.07
Analysis of PWD SoR 2014 for Civil Works 195

Cost for 100 cft. of work = Tk. 288.94


Abstract of cosr for 100 cft. of work
A. Cost of concrete = Tk. 23,865.00
B. Labour, machinery, fuel and lubricant for casting = Tk. 950.46
C. Cost of shuttering = Tk. 2,898.39
D. Cost of bed preparation = Tk. 640.56
E. Polythene = Tk. 288.94
Total = Tk. 28,354.41
Profit 10.00% = Tk. 2,835.44
Overhead 3.50% = Tk. 992.40
= Tk. 32,182.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,873.04
Grand total = Tk. 34,055.29
Rate per cft. = Tk. 340.55
Rate per rft. = Tk. 463.34
Rate per rm. = Tk. 1,520.22

Say, Tk. 1,520 .00 Per rm.

Item No.- 09.9.4


Pile Shoe
Considering 1 No. of pile
A. Cost of materials
(i) 1/4" thick plate:
4 x 8" x 7" = 1.56 sft
Add wastage 5% = 0.08 sft
= 1.64 sft
@ 10.20 Ib per sft.= 16.73 Ibs @ Tk. 38.55 Per Ib = Tk. 644.94
(ii) 5/8" dia M.S. rod connected with M.S. plate:
5 x 2'-6" = 12.50 rft.
= 13.00 Ibs @ Tk. 26.76 Per Ib = Tk. 347.88
B. Labour
(i) Cost of welding, grinding etc 56.00 inch @ Tk. 5.00 Per inch = Tk. 280.00
(ii) Manufacturing cost for making, fitting and fixing of pile
shoe including cutting, shaping, sizing of M.S. plate L.S. = Tk. 735.00
(iii) Local carriage, sundries and T & P etc. L.S. = Tk. 122.50
Total = Tk. 2,130.32
Profit 10.00% = Tk. 213.03
Overhead 3.50% = Tk. 74.56
= Tk. 2,417.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 140.72
Grand total = Tk. 2,558.63
Rate per No. = Tk. 2,558.63

Say, Tk. 2,559 .00 each

Item No.- 09.10


Mobilization and demobilization of drop hammer type pre-cast pile driving rig.
Considering 1 set
1. Truck fare in/c loading and unloading 2 trips @ Tk. 1,300.00 Per trip = Tk. 2,600.00
2. Incidental and sundries etc. L.S = Tk. 245.00
Total = Tk. 2,845.00
Profit 10.00% = Tk. 284.50
Overhead 3.50% = Tk. 99.58
= Tk. 3,229.08
Add VAT with adjustment factor 1.0582 5.50% = Tk. 187.94
Grand total = Tk. 3,417.02
Analysis of PWD SoR 2014 for Civil Works 196

Say, Tk. 3,417 .00 Per set per site

Item No.- 09.11


Driving of (10" x 10") size pre-cast pile with drop hammer type rig.
Considering driving 20 rft. depth
1. Hire charge of driving equipment with liner
in/c cost of fuel and lubricant etc. 1/6 day @ Tk. 10,550.00 Per day = Tk. 1,758.33
2. Labour charge for pile carrying, lifting,
shifting and driving etc. complete:
(a) Rig operator 0.25 No. @ Tk. 499.00 each = Tk. 124.75
(b) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(c) Ordinary labour 2.00 No. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 2,448.83
Profit 10.00% = Tk. 244.88
Overhead 3.50% = Tk. 85.71
= Tk. 2,779.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 161.77
Grand total = Tk. 2,941.19
Rate per rft. = Tk. 98.04
09.11.1 From 0 meter to 6 meter Rate per meter = Tk. 321.67

Say, Tk. 322 . 00 Per rm.

09.11.2 From 6 meter to 12 meter add: 10% = Tk. 32.20


Total = Tk. 353.87

Say, Tk. 354 . 00 Per rm.

09.11.3 From 12 meter to 15 meter add: 10% = Tk. 35.39


Total = Tk. 389.26

Say, Tk. 389 . 00 Per rm.

Item No.- 09.12


Driving of (12" x 12") size pre-cast pile with drop hammer type rig.
Considering driving 20 rft. depth
(i) Hire charge of driving equipment with liner
in/c cost of fuel and lubricant etc. 1/6 day @ Tk. 10,550.00 Per day = Tk. 1,758.33
(ii) Labour charge for pile carrying, lifting,
shifting and driving etc. complete:
(a) Rig operator 0.25 No. @ Tk. 499.00 each = Tk. 124.75
(b) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(c) Ordinary labour 2.00 No. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 2,448.83
Profit 10.00% = Tk. 244.88
Overhead 3.50% = Tk. 85.71
= Tk. 2,779.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 161.77
Grand total = Tk. 2,941.19
Rate per rft. = Tk. 147.06
09.12.1 From 0 meter to 6 meter Rate per meter = Tk. 482.50

Say, Tk. 483 . 00 Per rm.

09.12.2 From 6 meter to 12 meter add: 10% = Tk. 48.30


Total = Tk. 530.80
Analysis of PWD SoR 2014 for Civil Works 197

Say, Tk. 531 . 00 Per rm.

09.12.3 From 12 meter to 15 meter add: 10% = Tk. 53.08


Total = Tk. 583.88

Say, Tk. 584 . 00 Per rm.

Item No.- 09.13


Driving of (14" x 14") size pre-cast pile with drop hammer type rig
Considering driving 20 rft. depth
1. Hire charge of driving equipment with liner
in/c cost of fuel and lubricant etc. 1/5 day @ Tk. 10,550.00 Per day = Tk. 2,110.00
2. Labour charge for pile carrying, lifting,
shifting and driving etc. complete:
(a) Rig operator 1/3 Nos. @ Tk. 499.00 each = Tk. 166.33
(b) Skilled labour 1/2 Nos. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 3.00 Nos. @ Tk. 245.00 each = Tk. 735.00
Total = Tk. 3,162.83
Profit 10.00% = Tk. 316.28
Overhead 3.50% = Tk. 110.70
= Tk. 3,589.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 208.93
Grand total = Tk. 3,798.74
Rate per rft. = Tk. 189.94
09.13.1 From 0 meter to 6 meter Rate per meter = Tk. 623.19

Say, Tk. 623 . 00 Per rm.

09.13.2 From 6 meter to 12 meter add: 10% = Tk. 62.30


Total = Tk. 685.49

Say, Tk. 685 .00 Per rm.

09.13.3 From 12 meter to 15 meter add: 10% = Tk. 68.55


Total = Tk. 754.04

Say, Tk. 754 . 00 Per rm.

09.13.4 From 15 meter to 18 meter add . 10% = Tk. 75.40


Total = Tk. 897.99

Say, Tk. 898 .00 Per rm.

Item No.- 09.14


Mobilization and demobilzation of automatic diesel hammer mounted complete rig set.
1. Lifting and carrying crane
(both ways) 2 trips @ Tk. 50,000.00 Per trip = Tk. 100,000.00
2. Truck fare (2 x 2 trips) in/c loading
& unloading by crane 4 trips @ Tk. 12,000.00 Per trip = Tk. 48,000.00
Total = Tk. 148,000.00
Profit 10.00% = Tk. 14,800.00
Overhead 3.50% = Tk. 5,180.00
= Tk. 167,980.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 9,776.60
Grand total = Tk. 177,756.60
Analysis of PWD SoR 2014 for Civil Works 198

Say, Tk. 177,757 Per set per site

Item No.- 09.15


Cost for driving pre-cast pile with automatic rig fitted with automatic diesel hammer: 10" x 10" size pile
Consider 6 Nos. Pile (40'-0" each)= 73.15 meter driving in 1 day
1. Hire charge of complete rig set
(Crane, Hammer, Rig,
Generator etc. complete.) 1 day @ Tk. 23,707.00 Per day = Tk. 23,707.00
2. Fuel, lubricant etc. L.S. = Tk. 3,694.61
3. Tools & plant, consumables, spares,
maintenance, insurance etc. L.S. = Tk. 2,450.00
4. Labour
(a) Foreman 2 Nos. @ Tk. 567.00 Per day = Tk. 1,134.00
(b) Diesel operated rig driver 1 No. @ Tk. 732.00 Per day = Tk. 732.00
(c) Helper to rig driver 8 Nos. @ Tk. 388.00 Per day = Tk. 3,104.00
(d) Skilled labour 5 Nos. @ Tk. 303.00 Per day = Tk. 1,515.00
Total = Tk. 36,336.61
Profit 10.00% = Tk. 3,633.66
Overhead 3.50% = Tk. 1,271.78
= Tk. 41,242.05
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,400.33
Grand total = Tk. 43,642.38
Rate per meter = Tk. 596.61

Say, Tk. 597 .00 per meter

Item No.- 09.16


Cost for driving pre-cast pile with automatic rig fitted with automatic diesel hammer: 12" x 12" size pile
Consider 5 Nos. Pile (35'-0" each)= 53.33 meter driving in 1 day
1. Hire charge of complete rig set
(Crane, Hammer, Rig,
Generator etc. complete.) 1 day @ Tk. 23,707.00 Per day = Tk. 23,707.00
2. Fuel, lubricant etc. L.S. = Tk. 3,694.61
3. Tools & plant, consumables, spares,
maintenance, insurance etc. L.S. = Tk. 2,450.00
4. Labour
(a) Foreman 2 Nos. @ Tk. 567.00 Per day = Tk. 1,134.00
(b) Diesel operated rig driver 1 No. @ Tk. 732.00 Per day = Tk. 732.00
(c) Helper to rig driver 8 Nos. @ Tk. 388.00 Per day = Tk. 3,104.00
(d) Skilled labour 5 Nos. @ Tk. 303.00 Per day = Tk. 1,515.00
Total = Tk. 36,336.61
Profit 10.00% = Tk. 3,633.66
Overhead 3.50% = Tk. 1,271.78
= Tk. 41,242.05
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,400.33
Grand total = Tk. 43,642.38
Rate per meter = Tk. 818.35

Say, Tk. 818 .00 per meter


Item No.- 09.17
Cost for driving pre-cast pile with automatic rig fitted with automatic diesel hammer: 14" x14" size
Consider 4 Nos. Pile (40'-0" each)= 48.76 m driving in 1 day
1. Hire charge of complete rig set
(Crane, Hammer, Rig,
Generator etc. complete.) 1 day @ Tk. 23,707.00 Per day = Tk. 23,707.00
2. Fuel, lubricant etc. L.S. = Tk. 3,694.61
3. Tools & plant, consumables, spares,
Analysis of PWD SoR 2014 for Civil Works 199

maintenance, insurance etc. L.S. = Tk. 2,450.00


4. Man-power
(a) Foreman 2 Nos. @ Tk. 567.00 Per day = Tk. 1,134.00
(b) Diesel operated rig driver 1 No. @ Tk. 732.00 Per day = Tk. 732.00
(c) Helper to diesel hammer
mounted rig driver 8 Nos. @ Tk. 388.00 Per day = Tk. 3,104.00
(d) Skilled labour 5 Nos. @ Tk. 303.00 Per day = Tk. 1,515.00
Total = Tk. 36,336.61
Profit 10.00% = Tk. 3,633.66
Overhead 3.50% = Tk. 1,271.78
= Tk. 41,242.05
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,400.33
Grand total = Tk. 43,642.38
Rate per meter = Tk. 895.04

Say, Tk. 895 .00 per meter

Item No.- 09.18.1


7" x 7" x 25'-0" Pile with reinforced cement concrete (1 : 1.25 : 2.5) with stone chips (micro-pile)
Considering 25 rft. long 1 No. pile
Also considering 100 cft. of work
A. Cost of Concrete 100 cft. @ Tk. 24,912.50 Per % cft. = Tk. 24,912.50
B. Cost for laying/placing concrete 100 cft. @ Tk. 1,584.10 Per % cft. = Tk. 1,584.10
C. Cost of shuttering (for 39 No. of pile)
Assuming 7" x 7" x 25'-0" pile
Concrete: 39 x 7" x 7" x 25'-0"= 331.77 cft.
(a) Cost of steel shuttering:
(i) 14 BWG steel sheet: @ 3.05 Ib per sft.
Sides: 40 x 25'-0" x 0'-7" = 583.33 sft.
Add 5% wastage= 29.17 sft.
= 612.50 sft.
= 1868.13 Ibs @ Tk. 38.55 Per Ib. = Tk. 72,016.41
(ii) 1.5" x 1.5" x 1/8" M.S. angle for frame: @ 1.22 Ib per rft.
Horizontal: 2 x 40 x 25'-0"= 2000.00 rft.
Vertical: 26 x 40 x 0'-7"= 606.67 rft.
= 2606.67 rft.
Add 5% wastage= 130.3335 rft.
= 2737.00 rft.
= 3339.14 Ibs. @ Tk. 28.34 Per Ib. = Tk. 94,631.23
(iii) 1" x 3/16 F.I. bar: @ 0.64 Ib per rft.
Stiffner: 13 x 20 x 0'- 10"= 216.67 rft.
Add 5% wastage= 10.83 rft.
= 227.50 rft.
= 145.60 Ibs @ Tk. 25.40 Per Ib. = Tk. 3,698.24
(iv) Cost of nuts & bolts: @ 3.5 kg per % sft steel shuter
20.00 kg. @ Tk. 133.00 Per kg. = Tk. 2,660.00
(v) Manufacturing, fitting and fixing
frame in/c drilling holes, welding
& supplying of chemical etc. 583.33 sft @ Tk. 69.17 Per sft. = Tk. 40,348.94
Sub-Total = Tk. 213,354.82
Using 16 times = Tk. 13,334.68
(vi) Labour for fitting and fixing steel shuttering in
position as required.
40 x 25'-0" x 0'-7"= 583.33 sft @ Tk. 8.00 Per sft. = Tk. 4,666.64
(vii) Hessian tap for making shutter
water-proof 583.33 sft @ Tk. 1.13 Per sft. = Tk. 659.16
(viii) Curing 583.33 sft. @ Tk. 2.04 Per sft. = Tk. 1,189.99
Analysis of PWD SoR 2014 for Civil Works 200

Total = Tk. 19,850.47


Cost for 100 cft. = Tk. 5,983.20
D. Cost of bed preparation
Area: 30'-0" x 27'-0"= 810 sft.
Concrete: 39 x 7" x 7" x 25'-0= 331.77 cft.
(a) One layer brick flat soling: 810 sft. @ Tk. 27.44 Per sft. = Tk. 22,226.40
(b) 1/2 thick cement plaster
with neat cement finishing: 810 sft. @ Tk. 19.06 Per sft. = Tk. 15,438.60
Total = Tk. 37,665.00
Cost for 100 cft. of work = Tk. 11,352.74
Using 8 times = Tk. 1,419.09
E. Polythene as separator between pile layers
during casting concrete 810.00 sft. @ Tk. 262.19 Per % sft. = Tk. 2,123.74
Cost for 100 cft. of work = Tk. 640.12
Abstract of cost for 100 cft. of work
(a) Cost of concrete = Tk. 24,912.50
(b) Labour, machinery, fuel and lubricants for casting = Tk. 1,584.10
(c) Cost of shuttering = Tk. 5,983.20
(d) Cost of bed preparation = Tk. 1,419.09
(e) Cost of polythene = Tk. 640.12
Total = Tk. 34,539.01
Profit 10.00% = Tk. 3,453.90
Overhead 3.50% = Tk. 1,208.87
= Tk. 39,201.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,281.58
Grand total = Tk. 41,483.36
Rate per cft. = Tk. 414.83
Rate per rft. = Tk. 141.10
Rate per rm = Tk. 462.95

Say, Tk. 463 .00 Per rm.

Item No.- 09.18.2


8" x 8" x 25'-0" Pile with reinforced cement concrete (1 : 1.25 : 2.5) with stone chips (micro-pile)
Considering 25 rft. long 1 No. pile
Also considering 100 cft. of work
A. Cost of Concrete 100 cft. @ Tk. 24,912.50 Per % cft. = Tk. 24,912.50
B. Cost for laying/placing concrete 100 cft. @ Tk. 1,584.10 Per % cft. = Tk. 1,584.10
C. Cost of shuttering (for 39 No. of pile)
Assuming 8" x 8" x 25'-0" pile
Concrete: 39 x 8" x 8" x 25'-0"= 437.68 cft.
(a) Cost of steel shuttering:
(i) 14 BWG steel sheet: @ 3.05 Ib per sft.
Sides: 40 x 25'-0" x 0'-8" = 670.00 sft.
Add 5% wastage= 33.50 sft.
= 703.50 sft.
= 2145.68 Ibs @ Tk. 38.55 Per Ib. = Tk. 82,715.96
(ii) 1.5" x 1.5" x 1/8" M.S. angle for frame: @ 1.22 Ib per rft.
Horizontal: 2 x 40 x 25'-0"= 2000.00 rft.
Vertical: 26 x 40 x 0'-7"= 606.67 rft.
= 2606.67 rft.
Add 5% wastage= 130.3335 rft.
= 2737.00 rft.
= 3339.14 Ibs. @ Tk. 28.34 Per Ib. = Tk. 94,631.23
(iii) 1" x 1/4" F.I. bar: @ 0.64 Ib per rft.
Stiffner: 13 x 20 x 0'- 10"= 216.67 rft.
Add 5% wastage= 10.83 rft.
Analysis of PWD SoR 2014 for Civil Works 201

= 227.50 rft.
= 145.60 Ibs @ Tk. 25.40 Per Ib. = Tk. 3,698.24
(iv) Cost of nuts & bolts: @ 3.5 kg per % sft steel shuter
20.00 kg. @ Tk. 133.00 Per kg. = Tk. 2,660.00
(v) Manufacturing, fitting and fixing
frame in/c drilling holes, welding
& supplying of chemical etc. 670.00 sft @ Tk. 69.17 Per sft. = Tk. 46,343.90
Sub-Total = Tk. 230,049.33
Using 16 times = Tk. 14,378.08
(vi) Labour for fitting and fixing steel shuttering in
position as required.
40 x 25'-0" x 0'-8"= 670 sft @ Tk. 8.00 Per sft. = Tk. 5,360.00
(vii) Hessian tap for making shutter
water-proof 670 sft @ Tk. 1.13 Per sft. = Tk. 757.10
(viii) Curing 670 sft. @ Tk. 2.04 Per sft. = Tk. 1,366.80
Total = Tk. 21,861.98
Cost for 100 cft. = Tk. 4,994.97
D. Cost of bed preparation
Area: 33'-3" x 27'-0"= 897.75 sft.
Concrete: 39 x 8" x 8" x 25'-0= 437.68 cft.
(a) One layer brick flat soling: 897.75 sft. @ Tk. 27.44 Per sft. = Tk. 24,634.26
(b) 1/2 thick cement plaster
with neat cement finishing: 897.75 sft. @ Tk. 19.06 Per sft. = Tk. 17,111.12
Total = Tk. 41,745.38
Cost for 100 cft. of work = Tk. 9,537.88
Using 8 times = Tk. 1,192.24
E. Polythene as separator between pile layers
during casting concrete 897.75 sft. @ Tk. 262.19 Per % sft. = Tk. 2,353.81
Cost for 100 cft. of work = Tk. 537.79
Abstract of cost for 100 cft. of work
(a) Cost of concrete = Tk. 24,912.50
(b) Labour, machinery, fuel and lubricants for casting = Tk. 1,584.10
(c) Cost of shuttering = Tk. 4,994.97
(d) Cost of bed preparation = Tk. 1,192.24
(e) Cost of polythene = Tk. 537.79
Total = Tk. 33,221.60
Profit 10.00% = Tk. 3,322.16
Overhead 3.50% = Tk. 1,162.76
= Tk. 37,706.52
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,194.56
Grand total = Tk. 39,901.08
Rate per cft. = Tk. 399.01
Rate per rft. = Tk. 175.56
Rate per rm = Tk. 576.01

Say, Tk. 576 .00 Per rm.


Item No.- 09.18.3
Driving of 7" x 7" x 25'-0" Pre-cast Pile (micro-pile)
Considering 25 rft. long 8 Nos. pile
(i) Hire charge of driving equipment
in/c cost of fuel and lubricant etc. 1 day @ Tk. 5,500.00 Per day = Tk. 5,500.00
(ii) Labour charge for pile carrying, lifting,
shifting and driving etc. complete:
(a) Rig operator 1.00 No. @ Tk. 499.00 each = Tk. 499.00
(b) Skilled labour 3 No. @ Tk. 303.00 each = Tk. 909.00
(c) Ordinary labour 7.00 Nos. @ Tk. 245.00 each = Tk. 1,715.00
Total = Tk. 8,623.00
Analysis of PWD SoR 2014 for Civil Works 202

Profit 10.00% = Tk. 862.30


Overhead 3.50% = Tk. 301.81
= Tk. 9,787.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 569.62
Grand total = Tk. 10,356.73
Rate per pile = Tk. 1,294.59
Rate per rft. = Tk. 51.78
Rate per rm = Tk. 169.89

Say, Tk. 170 . 00 Per rm.

Item No.- 09.18.4


Driving of 8" x 8" x 25'-0" Pre-cast Pile (micro-pile)
Considering 25 rft. long 7 Nos. pile
(i) Hire charge of driving equipment
in/c cost of fuel and lubricant etc. 1 day @ Tk. 5,500.00 Per day = Tk. 5,500.00
(ii) Labour charge for pile carrying, lifting,
shifting and driving etc. complete:
(a) Rig operator 1.00 No. @ Tk. 499.00 each = Tk. 499.00
(b) Skilled labour 3 No. @ Tk. 303.00 each = Tk. 909.00
(c) Ordinary labour 8.00 Nos. @ Tk. 245.00 each = Tk. 1,960.00
Total = Tk. 8,868.00
Profit 10.00% = Tk. 886.80
Overhead 3.50% = Tk. 310.38
= Tk. 10,065.18
Add VAT with adjustment factor 1.0582 5.50% = Tk. 585.80
Grand total = Tk. 10,650.98
Rate per pile = Tk. 1,521.57
Rate per rft. = Tk. 60.86
Rate per rm = Tk. 199.68

Say, Tk. 200 . 00 Per rm.


PIT : Pile Integrity Test
Item No.- 09.20.1

Mobilization & demobilization within 100km of dhaka in/c 1st 12 piles Tk. 20,000.00

profit 10.00% Tk. 2,000.00


Overhead 3.50% Tk. 700.00
Tk. 22,700.00
Add VAT with adjustment factor 1.0582 5.50% Tk. 1,321.16
Tk. 24,021.16

say Tk. 24,021

Item No.- 09.20.2


additional charge per km beyond 100km of dhaka Tk. 25.00
profit 10.00% Tk. 2.50
Overhead 3.50% Tk. 0.88
Tk. 28.38
Add VAT with adjustment factor 1.0582 5.50% Tk. 1.65
Tk. 30.03
say Tk. 30

Item No.- 09.20.3


PIT on piles beyond 12 piles each Tk. 1,000.00
Analysis of PWD SoR 2014 for Civil Works 203

profit 10.00% Tk. 100.00


Overhead 3.50% Tk. 35.00
Tk. 1,135.00
Add VAT with adjustment factor 1.0582 5.50% 66.06
1,201.06
say Tk. 1,201
Analysis of PWD SoR 2014 for Civil Works 204

DIVISION 10 : C.I. SHEET ROOFING


Item No.- 10.1
0.457 mm thick galvanized iron corrugated sheet roofing (Bangladesh made) fitted & fixed on M.S section or
wooden purlin etc. [1 bundle=70-72 rft = 63 - 65 kg.(app)= 0.065 ton covers 150 sft.]
Considering 150 sft. of work =180sft of actual area excess reqd for overlapped =180-150=30sft= 20%
Labour cost:
1. Carpenter 3/4 No. @ Tk. 423.00 each = Tk. 317.25
2. Helper to carpenter 3/8 No. @ Tk. 304.00 each = Tk. 114.00
3. Ordinary labour 3/4 No. @ Tk. 245.00 each = Tk. 183.75
4. Bamboo for scaffolding :
using 6 times 3 Nos. @ Tk. 240.00 each = Tk. 120.00
Total= Tk. 735.00
Cost per sft.= Tk. 4.90
Cost per sqm= Tk. 52.74
10.1.1 Galvanized C.I. sheet:
(i) Price for per sqm (4.66kg/sqm =65kg/13.94sqm=150sft)
1 sqm. @ Tk. 421.73 Per sqm. = Tk. 421.73
(ii) Screws, limpet, washer etc. 3% = Tk. 12.65
(iii) Labour cost = Tk. 52.74
Total = Tk. 487.12
Profit 10.00% = Tk. 48.71
Overhead 3.50% = Tk. 17.05
= Tk. 552.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.18
Grand total = Tk. 585.06
Rate per sqm. = Tk. 585.06

Say, Tk. 585 .00 Per sqm.


10.1.2 Coloured:
(i) Price for per sqm (4.66 kg) 1 sqm. @ Tk. 424.06 Per sqm. = Tk. 424.06
(ii) Screws, limpet, washer etc. 3% = Tk. 12.72
(iii) Labour cost = Tk. 52.74
Total = Tk. 489.52
Profit 10.00% = Tk. 48.95
Overhead 3.50% = Tk. 17.13
= Tk. 555.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.34
Grand total = Tk. 587.94
Rate per sqm. = Tk. 587.94

Say, Tk. 588 .00 Per sqm.

Item No.- 10.2


1.5 mm thick corrugated fibre glass sheet roofing fixed and fitted on M.S. sections or wooden purlin.
Considering 150 sft. of work
(a) Cost of material
(i) Cost of fibre glass in/c 15% laping 172.5 sft. @ Tk. 77.00 Per sft. = Tk. 13,282.50
(ii) Cost of fitting in/c j-hook 3% = Tk. 398.48
(b) Labour
(i) Carpenter 3/4 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Helper to carpenter 1/2 No. @ Tk. 304.00 each = Tk. 152.00
(iii) Ordinary labour 1/2 No. @ Tk. 245.00 each = Tk. 122.50
(iv) Bamboo (20'-0" long) for scaffolding:
using 6 times 3 Nos. @ Tk. 240.00 each = Tk. 120.00
Total = Tk. 14,392.73
Profit 10.00% = Tk. 1,439.27
Overhead 3.50% = Tk. 503.75
Analysis of PWD SoR 2014 for Civil Works 205

= Tk. 16,335.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 950.76
Grand total = Tk. 17,286.51
Rate per sft = Tk. 115.24
Rate per sqm. = Tk. 1,240.44

Say, Tk. 1,240 .00 Per sqm.

Item No.- 10.3.1


Galvanized iron plain sheet ridging with galvanized bolts and nuts
Considering 9.1 (30 rft) meter. of work
(i) Price considering 10% laping 10.010 rm @ Tk. 172.25 Per rm = Tk. 1,724.22
(ii) Screws, limpet, washer etc. 15% = Tk. 258.63
(iii) Carpenter 1 No. @ Tk. 423.00 each = Tk. 423.00
(iv) Helper to carpenter 1 No. @ Tk. 304.00 each = Tk. 304.00
Total= Tk. 2,709.85
Profit 10.00% = Tk. 270.99
Overhead 3.50% = Tk. 94.84
= Tk. 3,075.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 179.01
Grand total = Tk. 3,254.69
Rate per rm = Tk. 355.95

Say, Tk. 356 .00 per rm

Item No.- 10.3.2


Colored iron plain sheet ridging with galvanized bolts and nuts
Considering 9.1 meter. (30 rft) of work
(i) Price considering
10% laping 10.01 rm @ Tk. 199.57 Per rm = Tk. 1,997.70
(ii) Screws, limpet washer etc. 15% = Tk. 299.66
(iii) Carpenter 1 No. @ Tk. 423.00 each = Tk. 423.00
(iv) Helper to carpenter 1 No. @ Tk. 304.00 each = Tk. 304.00
Total= Tk. 3,024.36
Profit 10.00% = Tk. 302.44
Overhead 3.50% = Tk. 105.85
= Tk. 3,432.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 199.78
Grand total = Tk. 3,632.43
Rate per rm = Tk. 397.27

Say, Tk. 397 .00 per rm

Item No.- 10.4


1.5 mm thick corrugated fibre glass sheet ridging
Considering 30 rft. of work
(a) Cost of material
(i) Cost of fibre glass in/c 10% laping 33 rft. @ Tk. 117.00 Per rft. = Tk. 3,861.00
(ii) Cost of screw, washer etc. 3% = Tk. 115.83
(b) Labour
(i) Carpenter 1 No. @ Tk. 423.00 each = Tk. 423.00
(ii) Helper to carpenter 1 No. @ Tk. 304.00 each = Tk. 304.00
Total = Tk. 4,703.83
Profit 10.00% = Tk. 470.38
Overhead 3.50% = Tk. 164.63
= Tk. 5,338.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 310.73
Analysis of PWD SoR 2014 for Civil Works 206

Grand total = Tk. 5,649.57


Rate per rft= Tk. 188.32
Rate per rm.= Tk. 617.88

Say, Tk. 618 .00 Per rm.

Item 10.5 (ref: CE's-8.3, & CE's-10.1, 10.1.1)


Saftey Canopy
Considering area = 1 x 100'-0" x 12'-0" = 1200.00 sft = 111.48 sqm
arround under construction structure

A) Cost of M.S materials.


i) 40 x 40 x 6 mm M.S Angle.
TOP 1 X 18 X 13'-8" 246.06 rft
BOTTOM 1 X 18 X 12'-2" 219.06 rft
WALL SIDE 1 X 18 X 1'-6" 27.00 rft
VERTICAL TIE 1 X 18 X 1'-2" 21.06 rft
VERTICAL TIE 1 X 18 X 0'-10" 14.94 rft
VERTICAL TIE 1 X 18 X 0'-6" 9.00 rft
VERTICAL TIE(END) 1 X 18 X 2'-4" 41.94 rft
INCLINED TIE
1 X 18 X 4 X 4'-3" 306.00 rft
PURLINE(horizontal portion) 1 X 4 X 100'-0" 400.00 rft
PURLINE(vertical portion) 1 X 2 X 100'-0" 200.00 rft
1485.06 rft
ADD WASTAGE 5% 74.25 rft
1559.31 rft =475.25 rm
@2.944 kg per rm 1399.14 kg @ tk. 60/- per kg Tk. 83,948.40

ii) 12 mm dia M.S bar.


INCLINED TIE 1 x 17 x 16'-6" 280.50 rft.
HOOK (U) 1 x 17 x 2 x 1'-0" 34.00 rft
314.50 rft
ADD WASTAGE 5% 15.72 rft
330.22 rft. =100.64 rm
@ tk. 60/- per kg 89.36 kg @ tk. 60/- per kg Tk. 5,361.60

Mark A Tk. 89,310.00

B) Workshop charge:
(item i + ii = 1399.14 + 89.36 = 1488.50 kg)
Fabrication, welding, making charge etc. 1488.50 kg @ Tk. 32/- per kg Tk. 47,632.00

C) Cost oc C.I Sheet.(ref: CE's-10.1, 10.1.1)


i) 0.45 mm thick C.I sheet roofing.
over truss(horizontal portion) 1 x 100'-0" x 12'-0" 1200 sft
over truss(vertical portion) 1 x 100'-0" x 1'-6" 150 sft
1350 sft
125.42 sqm
@ Tk. 456.68 per sqm Tk. 57,276.81

Mark B Tk. 57,276.81

ii) Screws, limpet, washer etc @ 3% on Tk.57276/81 Tk. 1,781.30

iii) Labour cost 125.42 sqm @ tk. 40/80 per sqm Tk. 5,117.14

Sub Total Tk. 201,054.25

D) Resale value (Mark-A) @ 50% on tk. 89310.00 Tk. 44,655.00

Resale value (Mark-B) @ 25% on tk. 57276/81 Tk. 14,319.20


Tk. 58,974.20 (-)Tk 58974.20
Analysis of PWD SoR 2014 for Civil Works 207

Total Tk. 142,080.05

Profit 10% Tk. 14,208.00

Overhead 3.50% Tk. 4,972.80

Tk. 161,260.85

Add VAT with adjustment factor1.058 5.50% Tk. 9,385.54

Grand Total Tk. 170,646.39

Rate per sft. Tk. 142.21

Rate per sqm. Tk. 1,530.75


Say, Tk. 1531.00 per sqm.
Analysis of PWD SoR 2014 for Civil Works 208

DIVISION 11. WOOD WORK IN DOOR AND WINDOW FRAME, ROOF TRUSS AND RAILINGS
Item No.- 11.1.1
Supply and making door and window frames with seasoned wood
Considering 1 No. door frame
Considering for door size: 3'-4" x 7'-0"
Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-5" =1.5 cft. (finished)
= (2 x 7'-0" + 3'-6") x 0'-2.75" x 0'-5.25" = 1.75 (gross)
Garjan/Jam wood
(a) Cost of wood 1.75 cft. @ Tk. 2,000.0 Per cft. = Tk. 3,500.00
(b) Coaltaring: 2 coats
1 x (2 x 7'-2.5" + 3'-4") x 0'-5"= 7.5 sft @ Tk. 6.00 Per sft. = Tk. 45.00
(c) Labour for making frame =
(i) Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Carpenter helper 1.0 No. @ Tk. 304.00 each = Tk. 304.00
(d) Labour for fitting, fixing in position L.S. = Tk. 151.50
Total = Tk. 4,317.75
Profit 10.00% = Tk. 431.78
Overhead 3.50% = Tk. 151.12
= Tk. 4,900.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 285.22
Grand total = Tk. 5,185.87
Rate per cft. = Tk. 3,457.25
Rate per cum. = Tk. 122,092.78

Say, Tk. 122,093 .00 Per cum.

Item No.- 11.1.2


Supply and making door and window frames with seasoned wood
Considering 1 No. door frame
Considering for door size: 3'-4" x 7'-0"
Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-5" = 1.5 cft. (finished)
= (2 x 7'-0" + 3'-6") x 0'-2.75" x 0'-5.25" = 1.75 cft. (gross)
For Mehgoni
(a) Cost of wood 1.75 cft. @ Tk. 1,900.00 Per cft. = Tk. 3,325.00
(b) Coaltaring: 2 coats 7.5 sft. @ Tk. 6.00 Per sft. = Tk. 45.00
(c) Labour for making
(i) Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Carpenter helper 1.0 No. @ Tk. 304.00 each = Tk. 304.00
(d) Labour for fitting fixing in position L.S. = Tk. 151.50
Total = Tk. 4,142.75
Profit 10.00% = Tk. 414.28
Overhead 3.50% = Tk. 145.00
= Tk. 4,702.03
Add VAT with adjustment factor 1.0582 5.50% = Tk. 273.66
Grand total = Tk. 4,975.69
Rate per cft. = Tk. 3,317.13
Rate per cum. = Tk. 117,144.45

Say, Tk. 117,144 .00 Per cum.

Item No.- 11.1.3


Supply and making door and window frames with seasoned wood
Considering 1 No. door frame
Considering for door size: 3'-4" x 7'-0"
Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-5" = 1.5 cft. (finished)
= (2 x 7'-0" + 3'-6") x 0'-2.75" x 0'-5.25" = 1.75 cft. (gross)
Analysis of PWD SoR 2014 for Civil Works 209

For Silkarai
(a) Cost of wood 1.75 cft. @ Tk. 2,800.0 Per cft. = Tk. 4,900.00
(b) Coaltaring: 2 coats 7.5 sft. @ Tk. 6.00 Per sft. = Tk. 45.00
(c) Labour for making
(i) Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Carpenter helper 1.0 No. @ Tk. 304.00 each = Tk. 304.00
(d) Labour for fitting fixing in position L.S. = Tk. 60.00
Total = Tk. 5,626.25
Profit 10.00% = Tk. 562.63
Overhead 3.50% = Tk. 196.92
= Tk. 6,385.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 371.66
Grand total = Tk. 6,757.46
Rate per cft. = Tk. 4,504.97
Rate per cum. = Tk. 159,093.02

Say, Tk. 159,093 .00 Per cum.

Item No.- 11.1.4


Supply and making door and window frames with seasoned wood
Considering 1 No. door frame
Considering for door size: 3'-4" x 7'-0"
Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-5" = 1.5 cft.( finished)
= (2 x 7'-0" + 3'-6") x 0'-2.75" x 0'-5.25" = 1.75 cft. (gross)
For Teak Chambal wood
(a) Cost of wood 1.75 cft. @ Tk. 3,100.00 Per cft. = Tk. 5,425.00
(b) Coaltaring: 2 coats 7.5 sft. @ Tk. 6.00 Per sft. = Tk. 45.00
(c) Labour for making
(i) Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Carpenter helper 1.0 No. @ Tk. 304.00 each = Tk. 304.00
(d) Labour for fitting fixing in position L.S. = Tk. 60.00
Total = Tk. 6,151.25
Profit 10.00% = Tk. 615.13
Overhead 3.50% = Tk. 215.29
= Tk. 6,981.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 406.34
Grand total = Tk. 7,388.01
Rate per cft. = Tk. 4,925.34
Rate per cum. = Tk. 173,938.38
Say, Tk. 173,938 .00 Per cum.

Item No.- 11.1.5


Supply and making door and window frames with seasoned wood
Considering 1 No. door frame
Considering for door size: 3'-4" x 7'-0"
Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-5" = 1.5 cft. (finished)
= (2 x 7'-0" + 3'-6") x 0'-2.75" x 0'-5.25" = 1.75 cft. (gross)
For Chittagong Teak
(a) Cost of wood 1.75 cft. @ Tk. 4,500.00 Per cft. = Tk. 7,875.00
(b) Coaltaring 2 coats 7.5 sft. @ Tk. 6.00 Per sft. = Tk. 45.00
(c) Labour for making
(i) Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Carpenter helper 1.0 No. @ Tk. 304.00 each = Tk. 304.00
(d) Labour for fitting fixing in position L.S. = Tk. 60.00
Total = Tk. 8,601.25
Profit 10.00% = Tk. 860.13
Overhead 3.50% = Tk. 301.04
Analysis of PWD SoR 2014 for Civil Works 210

= Tk. 9,762.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 568.18
Grand total = Tk. 10,330.60
Rate per cft. = Tk. 6,887.07
Rate per cum. = Tk. 243,216.88

Say, Tk. 243,217 .00 Per cum.

Item No.- 11.2


Supply, fitting & fixing M.S. flat bar clamps of size 0'-9" x 1.5" for door and windows
Considering 1 No. clamp.
(a) Clamp: 1.5" x 1/4" size F.I. bar 0.75 rft.
= 0.96 Ibs. @ Tk. 25.40 Per Ib. = Tk. 24.38
(b) Cost of concrete (1:2:4) 0.1 cft. @ Tk. 176.37 Per cft. = Tk. 17.64
(c) Labour cost L.S. = Tk. 29.40
Total = Tk. 71.42
Profit 10.00% = Tk. 7.14
Overhead 3.50% = Tk. 2.50
= Tk. 81.06
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4.72
Grand total = Tk. 85.78
Rate per No. = Tk. 85.78

Say, Tk. 86 .00 Each

Item No.- 11.3


Fitting fixing of chowkat (frame) using rowl plug
Considering work for 1 No. frame
1. 1.5" x 1/4" size F.I. bar 0.55 rft.
= 0.704 Ibs. @ Tk. 25.40 Per Ib. = Tk. 17.88
2. 2" rowel plug 4 Nos @ Tk. 39.53 Per dozon = Tk. 13.18
3. 2" screw 4 Nos @ Tk. 4.12 each = Tk. 16.48
4. 1.5" screw 2 Nos @ Tk. 2.45 each = Tk. 4.90
5. Cost of drilling 2" depth 4 Nos @ Tk. 2.45 each = Tk. 9.80
6. Labour cost plus carpentry of regened L.S. = Tk. 12.25
Total = Tk. 74.49
Profit 10.00% = Tk. 7.45
Overhead 3.50% = Tk. 2.61
= Tk. 84.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4.92
Grand total = Tk. 89.47
Rate per No. = Tk. 89.47

Say, Tk. 89 .00 Each

Item No.- 11.4


1.5" x 1.5" x 1/4" M.S. angle door frame (double leaf)
Considering 1 No. door frame
4'-0" x 7'-0" frame =
4'-0" + (2 x 7'-0") = 18.00 rft. of work
1. Cost of materials
(a) 1.5" x 1.5" x 1/4" angle: @ 2.34 Ibs per rft.
(i) Frame: 4'-0" + (2 x 7'-0") = 18.00 rft.
(ii) Clamp: 6 x 0'-6" = 2.52 rft.
= 20.52 rft.
Add wastage 5% = 1.03 rft.
= 21.55 rft.
Analysis of PWD SoR 2014 for Civil Works 211

= 50.43 Ibs @ Tk. 28.34 Per Ib = Tk. 1,429.19


(b) 4" long iron hinge 6 Nos. @ Tk. 24.00 each = Tk. 144.00

2. Labour for fabrication: 50.43 Ibs @ Tk. 275.85 Per cwt. = Tk. 124.21
3. Cost of welding:
Frame: 2 x 4 x 1.5" = 12.00 inch
Clamp: 6 x 4 x 1.5" = 36.00 inch
Hinge: 6 x (2 x 2"+4") = 48.00 inch
= 96.00 inch @ Tk. 5.00 Per inch = Tk. 480.00
4. Labour for fitting fixing in position, making @ 6 Nos. of holes in
existing brick work or making special arrangement
for fixing with concrete work 1 No. @ Tk. 226.92 each = Tk. 226.92
5. Cost of C.C. (1:2:4) in/c mending good the damages:
6 x 5" x 5" x 6" = 0.52 cft. @ Tk. 176.37 Per cft. = Tk. 91.71
6. Local carriage & carriage from workshop to site LS = Tk. 73.50
Total = Tk. 2,569.53
Profit 10.00% = Tk. 256.95
Overhead 3.50% = Tk. 89.93
= Tk. 2,916.41
Add VAT with adjustment factor 1.0582 5.50% = Tk. 169.74
Grand total = Tk. 3,086.15
Rate per rft. = Tk. 171.45
Rate per rm. = Tk. 562.53

Say, Tk. 563 .00 Per rm.

Item No.- 11.5


1.5" x 1.5" x 1/4" M.S. angle door frame (single leaf)
Considering 1 No. door frame
3'-0" x 7'-0" frame = 17.00 rft. of work
1. Cost of materials
(a) 1.5" x 1.5" x 1/4" angle: @ 2.34 Ibs per rft.
(i) Frame: 3'-0" + (2 x 7'-0") = 17.00 rft.
(ii) Clamp: 6 x 0'-5" = 2.52 rft.
= 19.52 rft.
Add wastage 5% = 0.98 rft.
= 20.50 rft.
= 47.97 Ibs @ Tk. 28.34 Per Ib = Tk. 1,359.47
(b) 4" long iron hinge 4 Nos. @ Tk. 24.00 each = Tk. 96.00

2. Labour for fabrication: 47.97 Ibs @ Tk. 3 Per Ib = Tk. 143.91


3. Cost of welding
Frame: 2 x 4 x 1.5" = 12.00 inch
Clamp: 6 x 4 x 1.5" = 36.00 inch
Hinge: 4 x (2 x 2"+4") = 32.00 inch
= 80.00 inch @ Tk. 5.00 Per inch = Tk. 400.00
4. Labour for fitting fixing in position, making @ 6 Nos. of holes in
existing brick work or making special arrangement
for fixing with concrete work 1 No. @ Tk. 226.92 each = Tk. 226.92
5. Cost of C.C. (1:2:4) in/c mending good the damages:
6 x 5" x 5" x 6" = 0.52 cft. @ Tk. 176.37 Per cft. = Tk. 91.71
6. Local carriage & carriage from workshop to site LS = Tk. 73.50
Total = Tk. 2,391.51
Profit 10.00% = Tk. 239.15
Overhead 3.50% = Tk. 83.70
= Tk. 2,714.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 157.98
Analysis of PWD SoR 2014 for Civil Works 212

Grand total = Tk. 2,872.34


Rate per rft. = Tk. 168.96
Rate per rm. = Tk. 554.36

Say, Tk. 554 .00 Per rm.

Item No.- 11.6.1


Wood works in frame of roof truss and wall plates
Considering 1 cft. of work
For Garjan / Local Sal wood/Jam
(a) Cost of wood in/c 5% wastage 1.05 cft. @ Tk. 2,000.0 Per cft. = Tk. 2,100.00
(b) Coaltering: 2 coats 14 sft. @ Tk. 6.00 Per sft. = Tk. 84.00
(c) Cost of nuts, bolts and nails 1 kg. @ Tk. 133.00 Per kg. = Tk. 133.00
(d) Labour for making, fitting & fixing
(i) Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(ii) Carpenter helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
Total = Tk. 2,498.75
Profit 10.00% = Tk. 249.88
Overhead 3.50% = Tk. 87.46
= Tk. 2,836.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 165.06
Grand total = Tk. 3,001.15
Rate per cft. = Tk. 3,001.15
Rate per cum. = Tk. 105,985.61

Say, Tk. 105,986 .00 Per cum.

Item No.- 11.6.2


Wood works in frame of roof truss and wall plates
Considering 1 cft. of work
For Mehgani wood
(a) Cost of wood in/c 5% wastage 1.05 cft. @ Tk. 1,900.00 Per cft. = Tk. 1,995.00
(b) Coaltering: 2 coats 14 sft. @ Tk. 6.00 Per sft. = Tk. 84.00
(c) Cost of nuts, bolts and nails 1 kg. @ Tk. 133.00 Per kg. = Tk. 133.00
(d) Labour for making, fitting & fixing
(i) Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(ii) Carpenter helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
Total = Tk. 2,393.75
Profit 10.00% = Tk. 239.38
Overhead 3.50% = Tk. 83.78
= Tk. 2,716.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 158.13
Grand total = Tk. 2,875.04
Rate per cft. = Tk. 2,875.04
Rate per cum. = Tk. 101,532.04

Say, Tk. 101,532 .00 Per cum.

Item No.- 11.6.3


Wood works in frame of roof truss and wall plates
Considering 1 cft. of work
For Silkarai/Chickrashi wood
(a) Cost of wood in/c 5% wastage 1.05 cft. @ Tk. 2,800.00 Per cft. = Tk. 2,940.00
(b) Coaltering: 2 coats 14 sft. @ Tk. 6.00 Per sft. = Tk. 84.00
(c) Cost of nuts, bolts and nails 1 kg. @ Tk. 133.00 Per kg. = Tk. 133.00
(d) Labour for making, fitting & fixing
(i) Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
Analysis of PWD SoR 2014 for Civil Works 213

(ii) Carpenter helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
Total = Tk. 3,338.75
Profit 10.00% = Tk. 333.88
Overhead 3.50% = Tk. 116.86
= Tk. 3,789.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 220.55
Grand total = Tk. 4,010.04
Rate per cft. = Tk. 4,010.04
Rate per cum. = Tk. 141,614.56

Say, Tk. 141,615 .00 Per cum.

Item No.- 11.7.1


Supply and making hand-rails of stair case including necessary moulding
Considering, 1 x 9'-6" x 2.75" x 6.25"= 1.134 cft. of work
For Silkarai / Chickrashi wood
(a) Cost of wood in/c 5% wastage 1.1907 cft. @ Tk. 2,800.00 Per cft. = Tk. 3,333.96
(b) Labour for making rails
(i) Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Carpenter helper 0.5 No. @ Tk. 304.00 each = Tk. 152.00
(c) Fitting, fixing in position in/c corner finishing
(i) Carpenter 0.5 No. @ Tk. 423.00 each = Tk. 211.50
(ii) Carpenter helper 0.5 No. @ Tk. 304.00 each = Tk. 152.00
Total = Tk. 4,166.71
Profit 10.00% = Tk. 416.67
Overhead 3.50% = Tk. 145.83
= Tk. 4,729.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 275.24
Grand total = Tk. 5,004.45
Rate per cft. = Tk. 4,413.10
Rate per cum. = Tk. 155,848.63

Say Tk. 155,849 .00 Per cum.

Item No.- 11.7.2


Supply and making hand-rails of stair case including necessary moulding
Considering, 1 x 9'-6" x 2.75" x 6.25"= 1.134 cft. of work
For Chittagong teak wood
(a) Cost of wood 1.1907 cft. @ Tk. 4,500.00 Per cft. = Tk. 5,358.15
(b) Labour for making rails
(i) Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Carpenter helper 0.5 No. @ Tk. 304.00 each = Tk. 152.00
(c) Fitting, fixing in position in/c corner finishing
(i) Carpenter 0.5 No. @ Tk. 423.00 each = Tk. 211.50
(ii) Carpenter helper 0.5 No. @ Tk. 304.00 each = Tk. 152.00
Total = Tk. 6,190.90
Profit 10.00% = Tk. 619.09
Overhead 3.50% = Tk. 216.68
= Tk. 7,026.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 408.96
Grand total = Tk. 7,435.63
Rate per cft. = Tk. 6,556.99
Rate per cum. = Tk. 231,560.10

Say Tk. 231,560 .00 Per cum

Item No.- 11.7.3


Analysis of PWD SoR 2014 for Civil Works 214

Supply and making hand-rails of stair case including necessary moulding


Considering, 1 x 9'-6" x 2.75" x 6.25"= 1.134 cft. of work
For Mehgoni wood
(a) Cost of wood 1.1907 cft. @ Tk. 1,900.00 Per cft. = Tk. 2,262.33
(b) Labour for making rails
(i) Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Carpenter helper 0.5 No. @ Tk. 304.00 each = Tk. 152.00
(c) Fitting, fixing in position in/c corner finishing
(i) Carpenter 0.5 No. @ Tk. 423.00 each = Tk. 211.50
(ii) Carpenter helper 0.5 No. @ Tk. 304.00 each = Tk. 152.00
Total = Tk. 3,095.08
Profit 10.00% = Tk. 309.51
Overhead 3.50% = Tk. 108.33
= Tk. 3,512.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 204.46
Grand total = Tk. 3,717.38
Rate per cft = Tk. 3,278.11
Rate per cum. = Tk. 115,766.45

Say Tk. 115,766 .00 Per cum.

Item No.- 11.7.4


Supply and making hand-rails of stair case including necessary moulding
Considering, 1 x 9'-6" x 2.75" x 6.25"= 1.134 cft. of work
For local Sal wood
(a) Cost of wood 1.1907 cft. @ Tk. 2,000.00 Per cft. = Tk. 2,381.40
(b) Labour for making rails
(i) Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
(ii) Carpenter helper 0.5 No. @ Tk. 304.00 each = Tk. 152.00
(c) Fitting, fixing in position in/c corner finishing
(i) Carpenter 0.5 No. @ Tk. 423.00 each = Tk. 211.50
(ii) Carpenter helper 0.5 No. @ Tk. 304.00 each = Tk. 152.00
Total = Tk. 3,214.15
Profit 10.00% = Tk. 321.42
Overhead 3.50% = Tk. 112.50
= Tk. 3,648.07
Add VAT with adjustment factor 1.0582 5.50% = Tk. 212.32
Grand total = Tk. 3,860.39
Rate per cft = Tk. 3,404.22
Rate per cum. = Tk. 120,220.03

Say Tk. 120,220 .00 Per cum.

DIVISION 12 : DOOR-WINDOW SHUTTER & FLY PROOF WIRE-NET SHUTTER


Item No.- 12.1.1
Supplying, fitting & fixing 1.5" thick solid wood shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
For Kathal wood
Analysis of PWD SoR 2014 for Civil Works 215

(a) Fittings:
(i) 10" long iron tower bolt 1 No. @ Tk. 39.00 each = Tk. 39.00
(ii) 8" socket bolt 1 No. @ Tk. 28.00 each = Tk. 28.00
(iii) Hatch bolt 1 No. @ Tk. 354.00 each = Tk. 354.00
(iv) 4" long hinges 4 No. @ Tk. 73.00 each = Tk. 292.00
(v) Nickle plated handle 2 No. @ Tk. 48.00 each = Tk. 96.00
(vi) Iron screws 5 dzn. @ Tk. 16.00 Per dzn = Tk. 80.00
(vii) Hinged cleats & buffer block 1 set @ Tk. 58.00 Per set = Tk. 58.00
Total of (A) = Tk. 947.00
(b) Labour:
(i) Carpenter 3 Nos. @ Tk. 423.00 each = Tk. 1,269.00
(ii) Carpenter helper 5 Nos. @ Tk. 304.00 each = Tk. 1,520.00
Total of (B) = Tk. 2,789.00
(c) Cost of wood: Kathal
Solid wood:
7'-0" x 3'-0" x 1.75"= 3.06 cft.
Wood for joint:
4 x 7'-0" x 0'-1" x 0.5"= 0.1 cft.
3.16 cft. @ Tk. 2,250.0 Per cft. = Tk. 7,110.00
Total (A+B+C) = Tk. 10,846.00
Profit 10.00% = Tk. 1,084.60
Overhead 3.50% = Tk. 379.61
= Tk. 12,310.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 716.47
Grand total = Tk. 13,026.68
Rate per sft. = Tk. 635.45
Rate per sqm. = Tk. 6,839.98

Say, Tk. 6,840 .00 Per sqm.

Item No.- 12.1.2


Supplying, fitting & fixing 1.5" thick solid wood shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
For Gamari
(a) Fittings: Same as item No.- 12.1.1 = Tk. 947.00
(b) Labour: Same as item No.- 12.1.1 = Tk. 2,789.00
(c) Cost of wood:
Wood req.: Same as 12.1.1 3.16 cft. @ Tk. 1,950.00 Per cft. = Tk. 6,162.00
Total = Tk. 9,898.00
Profit 10.00% = Tk. 989.80
Overhead 3.50% = Tk. 346.43
= Tk. 11,234.23
Add VAT with adjustment factor 1.0582 5.50% = Tk. 653.84
Grand total = Tk. 11,888.07
Rate per sft. = Tk. 579.91
Rate per sqm. = Tk. 6,242.15

Say, Tk. 6,242 .00 Per sqm.


Item No.- 12.1.3
Supplying, fitting & fixing 1.5" thick solid wood shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
For Teak chambal wood
(a) Fittings: Same as item No.- 12.1.1 = Tk. 947.00
(b) Labour: Same as item No.- 12.1.1 = Tk. 2,789.00
(c) Qty. of wood: Same as 12.1.1 3.16 cft. @ Tk. 3,100.00 Per cft. = Tk. 9,796.00
Analysis of PWD SoR 2014 for Civil Works 216

Total = Tk. 13,532.00


Profit 10.00% = Tk. 1,353.20
Overhead 3.50% = Tk. 473.62
= Tk. 15,358.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 893.90
Grand total = Tk. 16,252.72
Rate per sft. = Tk. 792.82
Rate per sqm. = Tk. 8,533.91

Say, Tk. 8,534 .00 Per sqm

Item No.- 12.1.4


Supplying, fitting & fixing 1.5" thick solid wood shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
For Chittagong teak wood
(a) Fittings: Same as item No.- 12.1.1 = Tk. 947.00
(b) Labour: Same as item No.- 12.1.1 = Tk. 2,789.00
(c) Qty. of wood: Same as 12.1.1 3.16 cft. @ Tk. 4,500.00 Per cft. = Tk. 14,220.00
Total = Tk. 17,956.00
Profit 10.00% = Tk. 1,795.60
Overhead 3.50% = Tk. 628.46
= Tk. 20,380.06
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,186.14
Grand total = Tk. 21,566.20
Rate per sft. = Tk. 1,052.01
Rate per sqm. = Tk. 11,323.84

Say, Tk. 11,324 .00 Per sqm.

Item No.- 12.1.5


Supplying, fitting & fixing 1.5" thick solid wood shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
For Chapalish wood
(a) Fittings: Same as item No.- 12.1.1 = Tk. 947.00
(b) Labour: Same as item No.- 12.1.1 = Tk. 2,789.00
(c) Qty. of wood: Same as- 12.1.1 3.16 cft. @ Tk. 2,100.00 Per cft. = Tk. 6,636.00
Total = Tk. 10,372.00
Profit 10.00% = Tk. 1,037.20
Overhead 3.50% = Tk. 363.02
= Tk. 11,772.22
Add VAT with adjustment factor 1.0582 5.50% = Tk. 685.15
Grand total = Tk. 12,457.37
Rate per sft. = Tk. 607.68
Rate per sqm. = Tk. 6,541.07

Say, Tk. 6,541 .00 Per sqm.


Item No.- 12.2.1
Supplying, fitting & fixing 1.5" thick wood flush door shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
For Kathal wood
(a) Fittings: Same as item No.- 12.1.1 = Tk. 947.00
(b) Labour:
(i) Carpenter 2 Nos. @ Tk. 423.00 each = Tk. 846.00
(ii) Capenter helper 4 Nos. @ Tk. 304.00 each = Tk. 1,216.00
Analysis of PWD SoR 2014 for Civil Works 217

Total of (B) = Tk. 2,062.00


(c) Cost of wood:
Wood required per shutter:
Style: 2 x 7'-0" x 4.25" x 1.75"= 0.723 cft
Rail: 4 x 3'-0" x 4.25" x 0.75"= 0.265 cft
Faces: 2 x 7'-0" x 2'-6" x 0.625"= 1.823 cft
2.811 cft. @ Tk. 2,250.0 Per cft. = Tk. 6,324.75
Total (A+B+C) = Tk. 9,333.75
Profit 10.00% = Tk. 933.38
Overhead 3.50% = Tk. 326.68
= Tk. 10,593.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 616.57
Grand total = Tk. 11,210.38
Rate per sft. = Tk. 546.85
Rate per sqm. = Tk. 5,886.29

Say, Tk. 5,886 .00 Per Sqm.

Item No.- 12.2.2


Supplying, fitting & fixing 1.5" thick wood flush door shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
For Gamari wood
(a) Fittings: Same as item No.- 12.2.1 = Tk. 947.00
(b) Labour: Same as item No.- 12.2.1 = Tk. 2,062.00
(c) Cost of wood:
Wood req.: Same as - 12.2.1 2.811 cft. @ Tk. 1,950.00 Per cft. = Tk. 5,481.45
Total = Tk. 8,490.45
Profit 10.00% = Tk. 849.05
Overhead 3.50% = Tk. 297.17
= Tk. 9,636.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 560.86
Grand total = Tk. 10,197.53
Rate per sft. = Tk. 497.44
Rate per sqm. = Tk. 5,354.44

Say, Tk. 5,354 .00 Per sqm.

Item No.- 12.2.3


Supplying, fitting & fixing 1.5" thick wood flush door shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
For Teak chambal wood
(a) Fittings: Same as item No. - 12.2.1 = Tk. 947.00
(b) Labour: Same as item No.- 12.2.1 = Tk. 2,062.00
(c) Cost of wood:
Wood req.: Same as - 12.2.1 2.811 cft. @ Tk. 3,100.00 Per cft. = Tk. 8,714.10
Total = Tk. 11,723.10
Profit 10.00% = Tk. 1,172.31
Overhead 3.50% = Tk. 410.31
= Tk. 13,305.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 774.41
Grand total = Tk. 14,080.13
Rate per sft. = Tk. 686.84
Rate per sqm. = Tk. 7,393.15

Say, Tk. 7,393 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 218

Item No.- 12.2.4


Supplying, fitting & fixing 1.5" thick wood flush door shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
For Chittagong teak wood
(a) Fittings: Same as item No. - 12.2.1 = Tk. 947.00
(b) Labour: Same as item No. - 12.2.1 = Tk. 2,062.00
(c) Cost of wood:
Wood req.: Same as - 12.2.1 2.811 cft. @ Tk. 4,500.00 Per cft. = Tk. 12,649.50
Total = Tk. 15,658.50
Profit 10.00% = Tk. 1,565.85
Overhead 3.50% = Tk. 548.05
= Tk. 17,772.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,034.37
Grand total = Tk. 18,806.77
Rate per sft. = Tk. 917.40
Rate per sqm. = Tk. 9,874.89

Say, Tk. 9,875 .00 Per sqm.

Item No.- 12.2.5


Supplying, fitting & fixing 1.5" thick wood flush door shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft (single leaf)
For Chapalish wood
(a) Fittings: Same as item No.- 12.2.1 = Tk. 947.00
(b) Labour: Same as item No.- 12.2.1 = Tk. 2,062.00
(c) Cost of wood:
Wood req.: Same as- 12.2.1 2.811 cft. @ Tk. 2,100.00 Per cft. = Tk. 5,903.10
Total = Tk. 8,912.10
Profit 10.00% = Tk. 891.21
Overhead 3.50% = Tk. 311.92
= Tk. 10,115.23
Add VAT with adjustment factor 1.0582 5.50% = Tk. 588.72
Grand total = Tk. 10,703.95
Rate per sft. = Tk. 522.14
Rate per sqm. = Tk. 5,620.31

Say, Tk. 5,620 .00 Per sqm.

Item No.- 12.3


Supplying, fitting and fixing 38 mm finished well matured, natural seasoned (min 10" wide plank) wooden ornamental special design (equivalent hatil) single panel flush d
Considering : 1X3'-0"X6'-10" = 20.49 sft

A) Cost of materials
Ctg. Teak Wood
5 1/4" X 1 1/2" X 6'-10" X 2 nos = 0.87 cft
9 1/4" X 3 3/4" X 3'-0" X 1 no = 0.34 "
6 1/4" X 1 3/4" X 3'-0" X 2 nos = 0.46 "
For foreign 4 1/4" X 1 3/4" X 1'-0" X 1 no = 0.05 "
Panel 7 1/2" X 1 3/4" X 3'-0" X 4 nos = 1.09 "
7 1/2" X 1 3/4" X 2'-6" X 4 nos = 0.91 "
= 3.72 cft Tk. 4,500.00 Per cft = Tk. 16,740.00
B) Cost of labour
i) Carpenter 3 Nos @ Tk. 423.00 Per day = Tk. 1,269.00
ii) Carpenter helper 5 Nos @ Tk. 304.00 Per day = Tk. 1,520.00
Analysis of PWD SoR 2014 for Civil Works 219

iii) Extra cost for design


a) Carpenter 3 Nos @ Tk. 423.00 Per day = Tk. 1,269.00
b) Carpenter helper 2 Nos @ Tk. 304.00 Per day = Tk. 608.00
C) Fitting
i) 10" long brass tower bolt 1 No. @ Tk. 321.00 Each = Tk. 321.00
ii) 8" long brass socket bolt 1 No. @ Tk. 259.00 Each = Tk. 259.00
iii) Brass Hasp bolt 1 No. @ Tk. 354.00 Each = Tk. 354.00
iv) 4" long brass hinges 4 Nos. @ Tk. 117.00 Each = Tk. 468.00
v) Brass Handle 2 Nos. @ Tk. 67.00 Each = Tk. 134.00
vi) Brass screws 1 Dozens @ Tk. 22.00 Per dozens = Tk. 22.00
vii) Hinged cleat & magnetic buffer block 1 Set @ = Tk. -
Total = Tk. 22,964.00
Profit 10.00% = Tk. 2,296.40
Overhead 3.50% = Tk. 803.74
= Tk. 26,064.14
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,516.96
Grand total = Tk. 27,581.10
Rate per sft. = Tk. 1,346.08
Rate per sqm. = Tk. 14,489.21
Say, Tk. 14,489 .00 Per sqm.

Item No.- 12.4.1


Supplying , fitting & fixing 1.5" thick wood panel door shitter with top rail & style section 4" x 1.5"
lockrail of section 5" x 1.5" and bottom rail 9" x 1.5" with 1.5" thick panelling etc. both side raised.
For 1 No. shutter
Considering 6'-9" x 3'-7"= 24.18 sft. (double leaf)
For Kathal wood
(a) Fittings:
(i) 10" long iron tower bolt 1 No. @ Tk. 39.00 each = Tk. 39.00
(ii) 8" socket bolt 1 No. @ Tk. 28.00 each = Tk. 28.00
(iii) Hatch bolt 1 No. @ Tk. 354.00 each = Tk. 354.00
(iv) 4" long hinges 8 No. @ Tk. 73.00 each = Tk. 584.00
(v) Nickle plated handle 2 No. @ Tk. 48.00 each = Tk. 96.00
(vi) Iron screws 5 dzn. @ Tk. 16.00 dzn = Tk. 80.00
(vii) Hinged cleats & buffer block 1 set @ Tk. 58.00 Per set = Tk. 58.00
Total of (A) = Tk. 1,239.00
(b) Labour:
(i) Carpenter 3 Nos. @ Tk. 423.00 each = Tk. 1,269.00
(ii) Carpenter helper 8 Nos. @ Tk. 304.00 each = Tk. 2,432.00
Total of (B) = Tk. 3,701.00
(c) Cost of wood:
4 x 6'-9" x 4.25" x 1.75"= 1.395 cft.
1 x 3'-9" x 9.25" x 1.75"= 0.422 cft.
1 x 3'-9" x 5.25" x 1.75"= 0.239 cft.
1 x 3'-9" x 4.25" x 1.75"= 0.194 cft.
panel: 1 x 5'-6" x 3'-0" x 1.75"= 2.406 cft.
= 4.656 cft. @ Tk. 2,250.0 Per cft. = Tk. 10,476.00
Total (A+B+C) = Tk. 15,416.00
Profit 10.00% = Tk. 1,541.60
Overhead 3.50% = Tk. 539.56
= Tk. 17,497.16
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,018.35
Grand total = Tk. 18,515.51
Rate per sft. = Tk. 765.74
Rate per sqm. = Tk. 8,242.43

Say, Tk. 8,242 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 220

Item No.- 12.4.2


Supplying, fitting & fixing 1.5" thick wood panel door shutter with top rail & styles section 4" x 1.5",
lockrail of section 5" x 1.5" and bottom rail 9" x 1.5" with 1.5" thick panelling etc. both side raised.
For 1 No. shutter
Considering 6'-9" x 3'-7"= 24.18 sft. (double leaf)
For Gamari wood
(a) Fittings: Same as item No.- 12.4.1 = Tk. 1,239.00
(b) Labour: Same as item No.- 12.4.1 = Tk. 3,701.00
(c) Cost of wood:
Wood req.: Same as 12.4.1 4.656 cft. @ Tk. 1,950.00 Per cft. = Tk. 9,079.20
Total = Tk. 14,019.20
Profit 10.00% = Tk. 1,401.92
Overhead 3.50% = Tk. 490.67
= Tk. 15,911.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 926.08
Grand total = Tk. 16,837.87
Rate per sft. = Tk. 696.36
Rate Per sqm. = Tk. 7,495.62

Say, Tk. 7,496 .00 Per sqm.

Item No.- 12.4.3


Supplying, fitting & fixing 1.5" thick wood panel door shutter with top rail & styles section 4" x 1.5",
lockrail of section 5" x 1.5" and bottom rail 9" x 1.5" with 1.5" thick panelling etc. both side raised.
For 1 No. shutter
Considering 6'-9" x 3'-7"= 24.18 sft. (double leaf)
For Teak chambal wood
(a) Fittings: Same as item No.- 12.4.1 = Tk. 1,239.00
(b) Labour: Same as item No.- 12.4.1 = Tk. 3,701.00
(c) Cost of wood:
Wood req.: Same as 12.4.1 4.656 cft. @ Tk. 3,100.00 Per cft. = Tk. 14,433.60
Total = Tk. 19,373.60
Profit 10.00% = Tk. 1,937.36
Overhead 3.50% = Tk. 678.08
= Tk. 21,989.04
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,279.78
Grand total = Tk. 23,268.82
Rate per sft. = Tk. 962.32
Rate per sqm. = Tk. 10,358.41

Say, Tk. 10,358 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 221

Item No.- 12.4.4


Supplying, fitting & fixing 1.5" thick wood panel door shutter with top rail & styles section 4" x 1.5",
lockrail of section 5" x 1.5" and bottom rail 9" x 1.5" with 1.5" thick panelling etc. both side raised.
For 1 No. shutter
Considering 6'-9" x 3'-7"= 24.18 sft. (double leaf)
For Chittagong teak wood
(a) Fittings: Same as item No.- 12.4.1 = Tk. 1,239.00
(b) Labour: Same as item No.- 12.4.1 = Tk. 3,701.00
(c) Cost of wood:
Wood req.: Same as - 12.4.1 4.656 cft. @ Tk. 4,500.00 Per cft. = Tk. 20,952.00
Total = Tk. 25,892.00
Profit 10.00% = Tk. 2,589.20
Overhead 3.50% = Tk. 906.22
= Tk. 29,387.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,710.38
Grand total = Tk. 31,097.80
Rate per sft. = Tk. 1,286.10
Rate per sqm. = Tk. 13,843.58

Say, Tk. 13,844 .00 Per sqm.

Item No.- 12.4.5


Supplying, fitting & fixing 1.5" thick wood panel door shutter with top rail & styles section 4" x 1.5",
lockrail of section 5" x 1.5" and bottom rail 9" x 1.5" with 1.5" thick panelling etc. both side raised.
For 1 No. shutter
Considering 6'-9" x 3'-7"= 24.18 sft. (double leaf)
For Chapalish wood
(a) Fittings: Same as item No.- 12.4.1 = Tk. 1,239.00
(b) Labour: Same as item No.- 12.4.1 = Tk. 3,701.00
(c) Cost of wood:
Wood req.: Same as - 12.4.1 4.656 cft. @ Tk. 2,100.00 Per cft. = Tk. 9,777.60
Total = Tk. 14,717.60
Profit 10.00% = Tk. 1,471.76
Overhead 3.50% = Tk. 515.12
= Tk. 16,704.48
Add VAT with adjustment factor 1.0582 5.50% = Tk. 972.22
Grand total = Tk. 17,676.70
Rate per sft. = Tk. 731.05
Rate per sqm. = Tk. 7,869.02

Say, Tk. 7,869 .00 Per sqm.

Item No.- 12.5.1


Supplying, fitting & fixing 1.5" thick wood panel door shutter with top rail & styles section 4" x 1.5",
lockrail of section 5" x 1.5" and bottom rail 9" x 1.5"with 1" thick panelling etc. both side raised.
For 1 No. shutter
Considering 6'-9" x 3'-7"= 24.18 sft. (double leaf)
For Kathal wood
(a) Fittings:
(i) 1'-0" long iron tower bolt 1 No. @ Tk. 39.00 each = Tk. 39.00
(ii) 8" socket bolt 1 No. @ Tk. 28.00 each = Tk. 28.00
(iii) Hatch bolt 1 No. @ Tk. 354.00 each = Tk. 354.00
(iv) 4" long hinges 8 No. @ Tk. 73.00 each = Tk. 584.00
(v) Nickle plated handle 2 No. @ Tk. 48.00 each = Tk. 96.00
(vi) Iron screws 5 dzn. @ Tk. 16.00 dzn = Tk. 80.00
(vii) Hinged cleats & buffer block 1 set @ Tk. 58.00 Per set = Tk. 58.00
Total of (A) = Tk. 1,239.00
Analysis of PWD SoR 2014 for Civil Works 222

(b) Labour:
(i) Carpenter 3 Nos. @ Tk. 423.00 each = Tk. 1,269.00
(ii) Carpenter helper 6.5 Nos. @ Tk. 304.00 each = Tk. 1,976.00
Total of (B) = Tk. 3,245.00
(c) Cost of wood:
4 x 6'-9" x 4.25" x 1.75"= 1.395 cft.
1 x 3'-9" x 9.25" x 1.75"= 0.422 cft.
1 x 3'-9" x 5.25" x 1.75"= 0.239 cft.
1 x 3'-9" x 4.25" x 1.75"= 0.194 cft.
panel: 1 x 5'-6" x 3'-0" x 1.25"= 1.719 cft.
= 3.969 cft. @ Tk. 2,250.0 Per cft. = Tk. 8,930.25
Total (A+B+C) = Tk. 13,414.25
Profit 10.00% = Tk. 1,341.43
Overhead 3.50% = Tk. 469.50
= Tk. 15,225.18
Add VAT with adjustment factor 1.0582 5.50% = Tk. 886.12
Grand total = Tk. 16,111.30
Rate per sft. = Tk. 666.31
Rate per sqm. = Tk. 7,172.16

Say, Tk. 7,172 .00 Per sqm.

Item No.- 12.5.2


Supplying, fitting & fixing 1.5" thick wood panel door shutter with top rail & styles section 4" x 1.5",
lockrail of section 5" x 1.5" and bottom rail 9" x 1.5"with 1" thick panelling etc. both side raised.
For 1 No. shutter
Considering 6'-9" x 3'-7"= 24.18 sft. (double leaf)
For Gamar wood
(a) Fittings: Same as- 12.5.1 = Tk. 1,239.00
(b) Labour : Same as- 12.5.1 = Tk. 3,245.00
(c) Cost of wood:
Wood req.: Same as- 12.5.1 3.969 cft. @ Tk. 1,950.00 Per cft. = Tk. 7,739.55
Total = Tk. 12,223.55
Profit 10.00% = Tk. 1,222.36
Overhead 3.50% = Tk. 427.82
= Tk. 13,873.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 807.46
Grand total = Tk. 14,681.19
Rate per sft. = Tk. 607.16
Rate per sqm. = Tk. 6,535.47

Say, Tk. 6,535 .00 Per sqm.


Item No.- 12.5.3
Supplying, fitting & fixing 1.5" thick wood panel door shutter with top rail & styles section 4" x 1.5",
lockrail of section 5" x 1.5" and bottom rail 9" x 1.5" with 1" thick panelling etc. both side raised.
For 1 No. shutter
Considering 6'-9" x 3'-7"= 24.18 sft. (double leaf)
For Teak chambal wood
(a) Fittings: Same as- 12.5.1 = Tk. 1,239.00
(b) Labour : Same as- 12.5.1 = Tk. 3,245.00
(c) Cost of wood:
Wood req.: Same as- 12.5.1 3.969 cft. @ Tk. 3,100.00 Per cft. = Tk. 12,303.90
Total = Tk. 16,787.90
Profit 10.00% = Tk. 1,678.79
Overhead 3.50% = Tk. 587.58
= Tk. 19,054.27
Analysis of PWD SoR 2014 for Civil Works 223

Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,108.98


Grand total = Tk. 20,163.25
Rate per sft. = Tk. 833.88
Rate per sqm. = Tk. 8,975.88

Say, Tk. 8,976 .00 Per sqm.


Item No.- 12.5.4
Supplying, fitting & fixing 1.5" thick wood panel door shutter with top rail & styles section 4" x 1.5",
lockrail of section 5" x 1.5" and bottom rail 9" x 1.5"with 1" thick panelling etc. both side raised.
For 1 No. shutter
Considering 6'-9" x 3'-7"= 24.18 sft. (double leaf)
For Chittagong teak wood
(a) Fittings: Same as- 12.5.1 = Tk. 1,239.00
(b) Labour : Same as- 12.5.1 = Tk. 3,245.00
(c) Cost of wood:
Wood req.: Same as- 12.5.1 3.969 cft. @ Tk. 4,500.00 Per cft. = Tk. 17,860.50
Total = Tk. 22,344.50
Profit 10.00% = Tk. 2,234.45
Overhead 3.50% = Tk. 782.06
= Tk. 25,361.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,476.04
Grand total = Tk. 26,837.05
Rate per sft. = Tk. 1,109.89
Rate per sqm. = Tk. 11,946.86
=
Say, Tk. 11,947 .00 Per sqm.

Item No.- 12.5.5


Supplying, fitting & fixing 1.5" thick wood panel door shutter with top rail & styles section 4" x 1.5",
lockrail of section 5" x 1.5" and bottom rail 9" x 1.5"with 1" thick panelling etc. both side raised.
For 1 No. shutter
Considering 6'-9" x 3'-7"= 24.18 sft. (double leaf)
For Chapalish wood
(a) Fittings: Same as- 12.5.1 = Tk. 1,239.00
(b) Labour : Same as- 12.5.1 = Tk. 3,245.00
(c) Cost of wood:
Wood req.: Same as- 12.5.1 3.969 cft. @ Tk. 2,100.00 Per cft. = Tk. 8,334.90
Total = Tk. 12,818.90
Profit 10.00% = Tk. 1,281.89
Overhead 3.50% = Tk. 448.66
= Tk. 14,549.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 846.79
Grand total = Tk. 15,396.24
Rate per sft. = Tk. 636.73
Rate per sqm. = Tk. 6,853.76

Say, Tk. 6,854 .00 Per sqm.

Item No.- 12.6.1


Supplying, fitting & fixing 1.5" thick wooden grooved panel flush door shutter
For 1 No. shutter
Considering 6'-9" x 3'-7"= 20.5 sft. (single leaf)
For Kathal wood
(a) Fittings: Same as item No.- 12.1.1 = Tk. 947.00
(b) Labour:
(i) Carpenter 3 Nos. @ Tk. 423.00 each = Tk. 1,269.00
(ii) Capenter helper 6.5 Nos. @ Tk. 304.00 each = Tk. 1,976.00
Analysis of PWD SoR 2014 for Civil Works 224

Total of (B) = Tk. 3,245.00


(c) Cost of wood:
Wood required per shutter:
Side style: 2 x 6'-10" x 4.25" x 1.75"= 0.706 cft
Top& mid rail: 2 x 3'-0" x 4.25" x 1.75"= 0.31 cft
Bottom rail: 1 x 3'-0" x 9.25" x 1.75"= 0.337 cft.
Top panel: 7 x 3'-6" x 5" x 1.75"= 1.489 cft.
Bottom panel: 7 x 2'-1" x 5" x 1.75"= 0.886 cft
3.728 cft. @ Tk. 2,250.0 Per cft. = Tk. 8,388.00
Total (A+B+C) = Tk. 12,580.00
Profit 10.00% = Tk. 1,258.00
Overhead 3.50% = Tk. 440.30
= Tk. 14,278.30
Add VAT with adjustment factor 1.0582 5.50% = Tk. 831.01
Grand total = Tk. 15,109.31
Rate per sft. = Tk. 737.04
Rate per sqm. = Tk. 7,933.50

Say, Tk. 7,934 .00 Per sqm.

Item No.- 12.6.2


Supplying, fitting & fixing 1.5" thick wooden grooved panel flush door shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
For Gamar wood
(a) Fittings: Same as item No.- 12.1.1 = Tk. 947.00
(b) Labour: Same as item No.- 12.1.1 = Tk. 3,245.00
(c) Cost of wood:
Wood req.: Same as- 12.6.1 3.728 cft. @ Tk. 1,950.00 Per cft. = Tk. 7,269.60
Total = Tk. 11,461.60
Profit 10.00% = Tk. 1,146.16
Overhead 3.50% = Tk. 401.16
= Tk. 13,008.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 757.13
Grand total = Tk. 13,766.05
Rate per sft. = Tk. 671.51
Rate per sqm. = Tk. 7,228.13

Say, Tk. 7,228 .00 Per sqm.

Item No.- 12.6.3


Supplying, fitting & fixing 1.5" thick wooden grooved panel flush door shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.50 sft. (single leaf)
For Chittagong teak wood
(a) Fittings: Same as item No.- 12.1.1 = Tk. 947.00
(b) Labour: Same as item No.- 12.1.1 = Tk. 3,245.00
(c) Cost of wood:
Wood req.: Same as - 12.6.1 3.728 cft. @ Tk. 4,500.00 Per cft. = Tk. 16,776.00
Total = Tk. 20,968.00
Profit 10.00% = Tk. 2,096.80
Overhead 3.50% = Tk. 733.88
= Tk. 23,798.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,385.11
Grand total = Tk. 25,183.79
Rate per sft. = Tk. 1,228.48
Rate per sqm. = Tk. 13,223.36
Analysis of PWD SoR 2014 for Civil Works 225

Say, Tk. 13,223 .00 Per sqm.

Item No.- 12.6.4


Supplying, fitting & fixing 1.5" thick wooden grooved panel flush door shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
For Chapalish wood
(a) Fittings: Same as item No.- 12.1.1 = Tk. 947.00
(b) Labour: Same as item No.- 12.1.1 = Tk. 3,245.00
(c) Cost of wood:
Wood req.: Same as- 12.6.1 3.728 cft. @ Tk. 2,100.00 Per cft. = Tk. 7,828.80
Total = Tk. 12,020.80
Profit 10.00% = Tk. 1,202.08
Overhead 3.50% = Tk. 420.73
= Tk. 13,643.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 794.07
Grand total = Tk. 14,437.68
Rate per sft. = Tk. 704.28
Rate per sqm. = Tk. 7,580.87

Say, Tk. 7,581 .00 Per sqm.


Item No.- 12.7
Supplying, fitting & fixing veneerd flush door shutter
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft (single leaf)
12.7.1 For Burma Teak veneered
(a) Fittings:
(i) 10" long iron tower bolt 1 No. @ Tk. 39.00 each = Tk. 39.00
(ii) 8" socket bolt 1 No. @ Tk. 28.00 each = Tk. 28.00
(iii) 4" long hinges 8 No. @ Tk. 73.00 each = Tk. 584.00
(iv) Nickle plated handle 2 No. @ Tk. 48.00 each = Tk. 96.00
(v) Iron screws 5 dzn. @ Tk. 16.00 dzn = Tk. 80.00
(vi) Hinged cleats & buffer block 1 set @ Tk. 58.00 Per set = Tk. 58.00
Total of ( A) = Tk. 885.00
(b) Labour
(i) Carpenter 0.25 Nos. @ Tk. 423.00 each = Tk. 105.75
(ii) Carpenter helper 0.50 Nos. @ Tk. 304.00 each = Tk. 152.00
Total of ( B) Tk. 257.75
(c) Cost of shutter: 36 mm thick
& 400 kg/cum 20.5 sft. @ Tk. 335.69 Per sft. = Tk. 6,881.65
Total (A+B+C) = Tk. 8,024.40
Profit 10.00% = Tk. 802.44
Overhead 3.50% = Tk. 280.85
= Tk. 9,107.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 530.08
Grand total = Tk. 9,637.77
Rate per sft. = Tk. 470.14
Rate per sqm. = Tk. 5,060.59

Say, Tk. 5,061 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 226

12.7.2 For Champ veneered


For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
(a) Fittings: Same as- 12.7.1 = Tk. 885.00
(b) Labour: Same as- 12.7.1 = Tk. 257.75
(c) Cost of shutter
Qty. Same as 12.7.1 20.5 sft. @ Tk. 240.61 = Tk. 4,932.51
Total = Tk. 6,075.26
Profit 10.00% = Tk. 607.53
Overhead 3.50% = Tk. 212.63
= Tk. 6,895.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 401.32
Grand total = Tk. 7,296.74
Rate per sft. = Tk. 355.94
Rate per sqm. = Tk. 3,831.34

Say, Tk. 3,831 .00 Per sqm.


12.7.3 For Chapalish veneered
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
(a) Fittings: Same as 12.7.1 = Tk. 885.00
(b) Labour: Same as 12.7.1 = Tk. 257.75
(c) Cost of shutter
Qty. Same as 12.7.1 20.5 sft. @ Tk. 239.59 = Tk. 4,911.60
Total = Tk. 6,054.35
Profit 10.00% = Tk. 605.44
Overhead 3.50% = Tk. 211.90
= Tk. 6,871.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 399.94
Grand total = Tk. 7,271.63
Rate per sft. = Tk. 354.71
Rate per sqm. = Tk. 3,818.10

Say, Tk. 3,818 .00 Per sqm.


12.7.4 For Garjan veneered
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft. (single leaf)
(a) Fittings: Same as 12.7.1 = Tk. 885.00
(b) Labour: Same as 12.7.1 = Tk. 257.75
(c) Cost of shutter
Qty.: Same as 12.7.1 20.5 sft. @ Tk. 216.42 = Tk. 4,436.61
Total = Tk. 5,579.36
Profit 10.00% = Tk. 557.94
Overhead 3.50% = Tk. 195.28
= Tk. 6,332.58
Add VAT with adjustment factor 1.0582 5.50% = Tk. 368.56
Grand total = Tk. 6,701.14
Rate per sft. = Tk. 326.88
Rate per sqm. = Tk. 3,518.54

Say, Tk. 3,519 .00 Per sqm.

Item No.- 12.8.1


Supplying, fitting & fixing seasoned wooden fixed louver shutter
For 1 No. louver shutter
Considering 5'-0" x 2'-8" = 13.35 sft. of work
For Gamari wood
Analysis of PWD SoR 2014 for Civil Works 227

(a) Cost of wood


Frame: 2 x 5'-0" x 2.75" x 5.25"= 1.003 cft.
Frame: 3 x 2'-9" x 2.75" x 5.25"= 0.827 cft.
In horizontal louver blade: 2" c/c
2 x 12 x 2'-6" x 6.25" x 1"= 2.604 cft.
Bit: 2 x 4 x 2'-3" x 0.5" x 0.5"= 0.031 cft.
= 4.465 cft. @ Tk. 1,950.000 Per cft. = Tk. 8,706.75
(b) Nails etc. 1.5 kg. @ Tk. 73.04 Per kg. = Tk. 109.56
(c) Labour cost:
Labour charge for making louver frames, cutting grooves, fitting,
fixing horizontal louver blades, fitting wooden bit etc.
(i) Carpenter 1.5 Nos. @ Tk. 423.00 each = Tk. 634.50
(ii) Carpenter helper 1.5 Nos. @ Tk. 304.00 each = Tk. 456.00
Total = Tk. 9,906.81
Profit 10.00% = Tk. 990.68
Overhead 3.50% = Tk. 346.74
= Tk. 11,244.23
Add VAT with adjustment factor 1.0582 5.50% = Tk. 654.43
Grand total = Tk. 11,898.66
Rate per sft. = Tk. 891.29
Rate per sqm. = Tk. 9,593.85

Say, Tk. 9,594 .00 Per sqm.

Item No.- 12.8.2


Supplying, fitting & fixing seasoned wooden fixed louver shutter
For 1 No. louver shutter
Considering 5'-0" x 2'-8" = 13.35 sft. of work
For Chittagong teak wood
(a) Cost of wood
Frame: 2 x 5'-0" x 2.75" x 5.25"= 1.003 cft.
Frame: 3 x 2'-9" x 2.75" x 5.25"= 0.827 cft.
In horizontal louver blade: 2" c/c
: 2 x 12 x 2'-6" x 6.25" x 1"= 2.604 cft.
Bit: 2 x 4 x 2'-3" x 0.5" x 0.5"= 0.031 cft.
= 4.465 cft. @ Tk. 4,500.00 Per cft. = Tk. 20,092.50
(b) Nails etc. 1.5 kg. @ Tk. 73.04 Per kg. = Tk. 109.56
(c) Labour cost:
Labour charge for making louver frames, cutting grooves, fitting,
fixing horizontal louver blades, fitting wooden bit etc.
(i) Carpenter 1.5 Nos. @ Tk. 423.00 each = Tk. 634.50
(ii) Carpenter helper 1.5 Nos. @ Tk. 304.00 each = Tk. 456.00
Total = Tk. 21,292.56
Profit 10.00% = Tk. 2,129.26
Overhead 3.50% = Tk. 745.24
= Tk. 24,167.06
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,406.55
Grand total = Tk. 25,573.61
Rate per sft. = Tk. 1,915.63
Rate per sqm. = Tk. 20,619.84

Say, Tk. 20,620 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 228

Item No.- 12.8.3


Supplying, fitting & fixing seasoned wooden fixed louver shutter
For 1 No. louver shutter
Considering 5'-0" x 2'-8" = 13.35 sft of work
For Chapalish wood
(a) Cost of wood
Frame: 2 x 5'-0" x 2.75" x 5.25"= 1.003 cft.
Frame: 3 x 2'-9" x 2.75" x 5.25"= 0.827 cft.
In horizontal louver blade: 2" c/c
2 x 12 x 2'-6" x 6.25" x 1"= 2.604 cft.
Bit: 2 x 4 x 2'-3" x 0.5" x 0.5"= 0.031 cft.
= 4.465 cft. @ Tk. 2,100.00 Per cft. = Tk. 9,376.50
(b) Nails etc. 1.5 kg. @ Tk. 73.04 Per kg. = Tk. 109.56
(c) Labour cost:
Labour charge for making louver frames, cutting grooves, fitting,
fixing horizontal louver blades, fitting wooden bit etc.
(i) Carpenter 1.5 Nos. @ Tk. 423.00 each = Tk. 634.50
(ii) Carpenter helper 1.5 Nos. @ Tk. 304.00 each = Tk. 456.00
Total = Tk. 10,576.56
Profit 10.00% = Tk. 1,057.66
Overhead 3.50% = Tk. 370.18
= Tk. 12,004.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 698.67
Grand total = Tk. 12,703.07
Rate per sft. = Tk. 951.54
Rate per sqm. = Tk. 10,242.38

Say, Tk. 10,242 .00 Per sqm.

Item No.- 12.9.1


Supplying, fitting & fixing seasoned wood glazed ventilator louver shutter
For 1 No. louver shutter
Considering 5'-0" x 2'-8" = 13.35 sft. of work
For Gamar wood
(a) Cost of materials
(i) Wood: Outer frame:
2 x 5'-0" x 2.75" x 5.25" = 1.003 cft.
3 x 2'-9" x 2.75" x 5.25 = 0.827 cft.
Inner shutter frame
2 x 2 x 2'-3.5" x 2.25" x 1.75" = 0.250 cft.
2 x 2 x 2'-4" x 2.25" x 1.65" = 0.255 cft.
sash, 2 x 3 x 2'-3.5" x 1.25" x 1.75" = 0.292 cft.
= 2.627 cft. @ Tk. 1,950.00 Per cft. = Tk. 5,122.65
(ii) Cost of 5 mm thick glass:
2 x 4 x 2'-4" x 0'-6" = 9.32 sft.
Wastage 10% = 0.93 sft.
= 10.25 sft. @ Tk. 65.60 Per sft. = Tk. 672.40
(iii) Cost of nails, screws, bit, putty etc.: L.S. = Tk. 29.22
(b) Labour:
(i) Carpenter 1.0 No. @ Tk. 423.00 each = Tk. 423.00
(ii) Helper to carpenter 1.5 Nos. @ Tk. 304.00 each = Tk. 456.00
Total = Tk. 6,703.27
Profit 10.00% = Tk. 670.33
Overhead 3.50% = Tk. 234.61
= Tk. 7,608.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 442.81
Grand total = Tk. 8,051.02
Analysis of PWD SoR 2014 for Civil Works 229

Rate per sft. = Tk. 603.07


Rate per sqm. = Tk. 6,491.45

Say, Tk. 6,491 .00 Per sqm.

Item No.- 12.9.2


Supplying, fitting & fixing seasoned wooden glazed ventilator louver shutter
For 1 No. louver shutter
Considering 5'-0" x 2'-8" = 13.35 sft. of work
For Teak chambal wood
(a) Cost of materials
(i) Qty. of wood Same as item 12.9.1 2.627 cft. @ Tk. 3,100.00 Per cft. = Tk. 8,143.70
(ii) 5 mm thick glass: item No. 12.9.1 10.25 sft. @ Tk. 65.60 Per sft. = Tk. 672.40
(ii) Cost of nails, screws, bit, putty etc.: L.S. = Tk. 29.22
(b) Labour:
(i) Carpenter 1 Nos. @ Tk. 423.00 each = Tk. 423.00
(ii) Helper to carpenter 1.5 Nos. @ Tk. 304.00 each = Tk. 456.00
Total = Tk. 9,724.32
Profit 10.00% = Tk. 972.43
Overhead 3.50% = Tk. 340.35
= Tk. 11,037.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 642.37
Grand total = Tk. 11,679.47
Rate per sft. = Tk. 874.87
Rate per sqm. = Tk. 9,417.10

Say, Tk. 9,417 .00 Per sqm.

Item No.- 12.9.3


Supplying, fitting & fixing seasoned wooden glazed ventilator louver shutter
For 1 No. louver shutter
Considering 5'-0" x 2'-8" = 13.35 sft. of work
For Chittagong teak wood
(a) Cost of materials
(i) Qty. of wood Same as item 12.9.1 2.627 cft. @ Tk. 4,500.00 Per cft. = Tk. 11,821.50
(ii) 5 mm thick glass:item No. 12.9.1 10.25 sft. @ Tk. 65.60 Per sft. = Tk. 672.40
(ii) Cost of nails, screws, bit, putty etc.: L.S. = Tk. 29.22
(b) Labour:
(i) Carpenter 1 Nos. @ Tk. 423.00 each = Tk. 423.00
(ii) Helper to carpenter 1.5 Nos. @ Tk. 304.00 each = Tk. 456.00
Total = Tk. 13,402.12
Profit 10.00% = Tk. 1,340.21
Overhead 3.50% = Tk. 469.07
= Tk. 15,211.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 885.32
Grand total = Tk. 16,096.72
Rate per sft. = Tk. 1,205.75
Rate per sqm. = Tk. 12,978.69

Say, Tk. 12,979 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 230

Item No.- 12.9.4


Supplying, fitting & fixing seasoned wooden glazed ventilator louver shutter
For 1 No. louver shutter
Considering 5'-0" x 2'-8" = 13.35 sft. of work
For Chapalish wood
(a) Cost of materials
(i) Qty. of wood: item 12.9.1 2.627 cft. @ Tk. 2,100.00 Per cft. = Tk. 5,516.70
(ii) 5 mm thick glass: item No. 12.9.1 10.25 sft. @ Tk. 65.60 Per sft. = Tk. 672.40
(ii) Cost of nails, screws, bit, putty etc.: L.S. = Tk. 29.22
(b) Labour:
(i) Carpenter 1 No. @ Tk. 423.00 each = Tk. 423.00
(ii) Helper to carpenter 1.5 Nos. @ Tk. 304.00 each = Tk. 456.00
Total = Tk. 7,097.32
Profit 10.00% = Tk. 709.73
Overhead 3.50% = Tk. 248.41
= Tk. 8,055.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 468.84
Grand total = Tk. 8,524.30
Rate per sft. = Tk. 638.52
Rate per sqm. = Tk. 6,873.03

Say, Tk. 6,873 .00 Per sqm.

Item No.- 12.10.1


Supplying, fitting & fixing 38 mm thick seasoned wooden glazed door shutter
For 1 No. glazed door shutter
Considering 2 x 2'-7.25" x 6'-10"= 35.57 sft. of work
For Chittagong teak wood
(a) Cost of wood
Style: 2 x 7'-0" x 6.25" x 1.75"= 1.063 cft.
Rail: 2 x 2'-9" x 6.25" x 1.75" = 0.418 cft.
Bit: 2 x 5'-10" x 0.75" x 0.75" = 0.046 cft.
Bit: 2 x 1'-9" x 0.75" x 0.75" = 0.014 cft.
Wood for one panel= 1.541 cft.
Wood for two panels= 3.082 cft. @ Tk. 4,500.00 Per cft. = Tk. 13,869.00
(b) 5 mm thick glass
2 x 7'-0" x 2'-0"= 28 sft. @ Tk. 65.60 Per sft. = Tk. 1,836.80
(c) Fittings:
(i) 2" best quality round lock 1 Nos. @ Tk. 610.00 each = Tk. 610.00
(ii) 10" long & 1/2" dia tower bolt 2 Nos. @ Tk. 39.00 each = Tk. 78.00
(iii) 4" long iron hinges 8 Nos. @ Tk. 73.00 each = Tk. 584.00
(iv) Nickle plated handle 2 Nos. @ Tk. 48.00 each = Tk. 96.00
(v) Screws 8 dzn. @ Tk. 16.00 Per dzn. = Tk. 128.00
(vi) Hinged cleats & buffer block 1 set @ Tk. 58.00 Per set = Tk. 58.00
Total of (C) = Tk. 1,554.00
(d) Labour for making & fitting fixing
(i) Carpenter 6 Nos. @ Tk. 423.00 each = Tk. 2,538.00
(ii) Carpenter helper 6 Nos. @ Tk. 304.00 each = Tk. 1,824.00
(iii) Glass cutting, fitting etc. complete
in/c cost of putty for 28 sft. @ Tk. 15.46 Per sft. = Tk. 432.88
Total of (D) = Tk. 4,794.88
Total (A+B+C+D) = Tk. 22,054.68
Profit 10.00% = Tk. 2,205.47
Overhead 3.50% = Tk. 771.91
= Tk. 25,032.06
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,456.89
Grand total = Tk. 26,488.95
Analysis of PWD SoR 2014 for Civil Works 231

Rate per sft. = Tk. 744.70


Rate per sqm. = Tk. 8,015.95

Say, Tk. 8,016 .00 Per sqm.

Item No.- 12.10.2


Supplying, fitting & fixing 38 mm thick seasoned wooden glazed door shutter
For 1 No. glazed door shutter
Considering 2 x 2'-7.25" x 6'-10"= 35.57 sft. of work
For Silkarai wood
(a) Cost of wood
Style: 2 x 7'-0" x 6.25" x 1.75"= 1.063 cft.
Rail: 2 x 2'-9" x 6.25" x 1.75" = 0.418 cft.
Bit: 2 x 5'-10" x 0.75" x 0.75" = 0.046 cft.
Bit: 2 x 1'-9" x 0.75" x 0.75" = 0.014 cft.
Wood for one panel= 1.541 cft.
Wood for two panels= 3.082 cft. @ Tk. 2,800.0 Per cft. = Tk. 8,629.60
(b) Cost of 5 mm thick glass
2 x 7'-0" x 2'-0"= 28 sft. @ Tk. 65.60 Per sft. = Tk. 1,836.80
(c) Fittings:
(i) 2" best quality round lock 1 No. @ Tk. 610.00 each = Tk. 610.00
(ii) 10" long & 1/2" dia tower bolt 2 Nos. @ Tk. 39.00 each = Tk. 78.00
(iii) 4" long iron hinges 8 Nos. @ Tk. 73.00 each = Tk. 584.00
(iv) Nickle plated handle 2 Nos. @ Tk. 48.00 each = Tk. 96.00
(v) Screws 8 dzn. @ Tk. 16.00 each = Tk. 128.00
(vi) Hinged cleats & buffer block 1 set @ Tk. 58.00 Per set = Tk. 58.00
Total of (C) = Tk. 1,554.00
(d) Labour for making & fitting fixing
(i) Carpenter 6 Nos. @ Tk. 423.00 each = Tk. 2,538.00
(ii) Carpenter helper 6 Nos. @ Tk. 304.00 each = Tk. 1,824.00
(iii) Glass cutting, fitting etc. complete
in/c cost of putty for 28 sft. @ Tk. 15.46 Per sft. = Tk. 432.88
Total of (D) = Tk. 4,794.88
Total (A+B+C+D) = Tk. 16,815.28
Profit 10.00% = Tk. 1,681.53
Overhead 3.50% = Tk. 588.53
= Tk. 19,085.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,110.79
Grand total = Tk. 20,196.13
Rate per sft. = Tk. 567.79
Rate per sqm. = Tk. 6,111.69

Say, Tk. 6,112 .00 Per sqm.

Item No.- 12.11


Supplying, fitting & fixing 25 mm / 1" thick wood batten door & window
shutters with 3" x 1" Z- battens fitted with iron screws etc.
For 1 No. shutter
Considering 6'-9" x 3'-7"= 24.18 sft. of work
For Kathal wood
(a) Fittings:
(i) 10" long & 1/2" dia tower bolt 1 Nos. @ Tk. 39.00 each = Tk. 39.00
(ii) 8" socket bolt 1 Nos. @ Tk. 28.00 each = Tk. 28.00
(iii) 4" long iron hinges 6 Nos. @ Tk. 73.00 each = Tk. 438.00
(iv) 2.5" dia iron rings 2 Nos. @ Tk. 14.00 each = Tk. 28.00
(v) Screws 6 dzn. @ Tk. 16.00 dzn. = Tk. 96.00
(vi) Hinged cleats & buffer block 1 set @ Tk. 58.00 Per set = Tk. 58.00
Analysis of PWD SoR 2014 for Civil Works 232

Total of (A) = Tk. 687.00


(b) Labour for making & fitting fixing
(i) Carpenter 2.5 Nos. @ Tk. 423.00 each = Tk. 1,057.50
(ii) Carpenter helper 3.5 Nos. @ Tk. 304.00 each = Tk. 1,064.00
Total of (B) = Tk. 2,121.50
(c) Cost of wood
1 x 6'-9" x 3'-9" x 1.25"= 2.637 cft.
2 x 3 x 1'-9" x 1.25" = 0.296 cft.
2 x 2 x 3'-6" x 3.25" x 1.25" = 0.395 cft.
= 3.328 cft. @ Tk. 2,250.0 Per cft. = Tk. 7,488.00
Total (A+B+C) = Tk. 10,296.50
Profit 10.00% = Tk. 1,029.65
Overhead 3.50% = Tk. 360.38
= Tk. 11,686.53
Add VAT with adjustment factor 1.0582 5.50% = Tk. 680.17
Grand total = Tk. 12,366.70
Rate Per sft. = Tk. 511.44
Rate Per sqm. = Tk. 5,505.14

Say, Tk. 5,505 .00 Per sqm.

Item No.- 12.12.1


Supplying, fitting & fixing 1.5" thick wood glazed window shutter having horizontal &
vertical section of 3.5" x 1.5" and having 1.5" x 1.5" sash bar.
For 1 No. glazed window shutter
Considering 5'-0" x 2'-9" = 13.75 sft. (double leaf)
For Kathal wood
(a) Fittings:
(i) 10" long & 1/2" dia tower bolt 1 Nos. @ Tk. 34.00 each = Tk. 34.00
(ii) 6" socket bolt 1 Nos. @ Tk. 27.00 each = Tk. 27.00
(iii) 3" long iron hinges 4 Nos. @ Tk. 54.75 each = Tk. 219.00
(iv) Nickle plated handle 1 Nos. @ Tk. 48.00 each = Tk. 48.00
(v) 9" long catch hook 2 Nos. @ Tk. 20.00 each = Tk. 40.00
(vi) Screws 3.5 dzn. @ Tk. 16.00 dzn. = Tk. 56.00
(vii) 3 mm glass pan: 14 x 10" x 8" = 7.78 sft.
Add wastage 10%= 0.78 sft.
8.56 sft. @ Tk. 41.00 Per sft. = Tk. 350.96
(viii) Fitting fixing of glass pans with
necessary iron pins & pucca putty 7.78 sft. @ Tk. 15.46 Per sft. = Tk. 120.28
Total of (A) = Tk. 895.24
(b) Labour
(i) Carpenter 1.75 Nos. @ Tk. 423.00 each = Tk. 740.25
(ii) Carpenter helper 2.5 Nos. @ Tk. 304.00 each = Tk. 760.00
Total of (B) = Tk. 1,500.25
(c) Cost of wood
Vertcal: 4 x 5'-0" x 3.75" x 1.75"= 0.911 cft.
Horizontal: 4 x 1'-6" x 3.75" x 1.75" = 0.273 cft.
Sash: 2 x 6 x 1'-6" x 1.75" x 1.75" = 0.383 cft.
= 1.567 cft. @ Tk. 2,250.0 Per cft. = Tk. 3,525.75
Total (A+B+C) = Tk. 5,921.24
Profit 10.00% = Tk. 592.12
Overhead 3.50% = Tk. 207.24
= Tk. 6,720.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 391.15
Grand total = Tk. 7,111.75
Rate per sft. = Tk. 517.22
Rate per sqm. = Tk. 5,567.36
Analysis of PWD SoR 2014 for Civil Works 233

Say, Tk. 5,567 .00 Per sqm.

Item No.- 12.12.2


Supplying, fitting & fixing 1.5" thick wood glazed window shutter having horizontal & vertical
section of 3.5" x 1.5" and having 1.5" x 1.5 sash bar.
For 1 No. glazed window shutter
Considering 5'-0" x 2'-9" = 13.75 sft. (double leaf)
For Gamar wood
(a) Fittings in/c glass panes: Same as item No. 12.12.1 = Tk. 895.24
(b) Labour: Same as item No. 12.12.1 = Tk. 1,500.25
(c) Cost of wood:
Wood req: Same as 12.12.1 1.567 cft. @ Tk. 1,950.000 Per cft. = Tk. 3,055.65
Total = Tk. 5,451.14
Profit 10.00% = Tk. 545.11
Overhead 3.50% = Tk. 190.79
= Tk. 6,187.04
Add VAT with adjustment factor 1.0582 5.50% = Tk. 360.09
Grand total = Tk. 6,547.13
Rate per sft. = Tk. 476.15
Rate per sqm. = Tk. 5,125.28

Say, Tk. 5,125 .00 Per sqm.

Item No.- 12.12.3


Supplying, fitting & fixing 1.5" thick wood glazed window shutter having horizontal & vertical section
of 3.5" x 1.5" and having 1.5" x 1.5 sash bar.
For 1 No. glazed window shutter
Considering 5'-0" x 2'-9" = 13.75 sft. (double leaf)
For Teak chambal wood
(a) Fittings in/c glass panes: Same as item No. 12.12.1 = Tk. 895.24
(b) Labour: Same as item No. 12.12.1 = Tk. 1,500.25
(c) Cost of wood:
Wood req: Same as 12.12.1 1.567 cft. @ Tk. 3,100.00 Per cft. = Tk. 4,857.70
Total = Tk. 7,253.19
Profit 10.00% = Tk. 725.32
Overhead 3.50% = Tk. 253.86
= Tk. 8,232.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 479.13
Grand total = Tk. 8,711.50
Rate per sft. = Tk. 633.56
Rate per sqm. = Tk. 6,819.64

Say, Tk. 6,820 .00 Per sqm.

Item No.- 12.12.4


Supplying, fitting & fixing 1.5" thick wood glazed window shutter having horizontal & vertical section
of 3.5" x 1.5" and having 1.5" x 1.5 sash bar.
For 1 No. glazed shutter
Considering 5'-0" x 2'-9" = 13.75 sft. (double leaf)
For Chittagong teak wood
(a) Fittings in/c glass panes: Same as item No. 12.12.1 = Tk. 895.24
(b) Labour: Same as item No. 12.12.1 = Tk. 1,500.25
(c) Cost of wood:
Wood req: Same as 12.12.1 1.567 cft. @ Tk. 4,500.00 Per cft. = Tk. 7,051.50
Total = Tk. 9,446.99
Profit 10.00% = Tk. 944.70
Analysis of PWD SoR 2014 for Civil Works 234

Overhead 3.50% = Tk. 330.64


= Tk. 10,722.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 624.05
Grand total = Tk. 11,346.38
Rate per sft. = Tk. 825.19
Rate per sqm. = Tk. 8,882.35

Say, Tk. 8,882 .00 Per sqm.

Item No.- 12.12.5


Supplying, fitting & fixing 1.5" thick wood glazed window shutter having horizontal &
vertical section of 3.5" x 1.5" and having 1.5" x 1.5 sash bar.
For 1 No. glazed window shutter
Considering 5'-0" x 2'-9" = 13.75 sft. (double leaf)
For Chapalish wood
(a) Fittings in/c glass panes: Same as item No. 12.12.1 = Tk. 895.24
(b) Labour: Same as item No. 12.12.1 = Tk. 1,500.25
(c) Cost of wood:
Wood req: Same as 12.12.1 1.567 cft. @ Tk. 2,100.00 Per cft. = Tk. 3,290.70
Total = Tk. 5,686.19
Profit 10.00% = Tk. 568.62
Overhead 3.50% = Tk. 199.02
= Tk. 6,453.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 375.62
Grand total = Tk. 6,829.45
Rate per sft. = Tk. 496.69
Rate per sqm. = Tk. 5,346.37

Say, Tk. 5,346 .00 Per sqm.

Item No.- 12.13.1


Supplying, fitting & fixing 1.5" thick wood window shutter, one third glazed & 1.5" thick,
two third both side raised panelling having horizontal & vertical section of 3.5" x 1.5"
and having 1.5" x 1.5 sash bar.
For 1 No. glazed window shutter
Considering 3'-7" x 3'-7"= 12.84 sft. of work (4'-0" x 4'-0" opening)
For Kathal wood
(a) Fittings:
(i) 10" long & 1/2" dia tower bolt 1 Nos. @ Tk. 34.00 each = Tk. 34.00
(ii) 6" Socket bolt 1 Nos. @ Tk. 27.00 each = Tk. 27.00
(iii) 3" long iron hinges 4 Nos. @ Tk. 54.75 each = Tk. 219.00
(iv) Nickle plated handle 1 Nos. @ Tk. 48.00 each = Tk. 48.00
(v) 9" long catch hook 2 Nos. @ Tk. 20.00 each = Tk. 40.00
(vi) Screws 3.5 dzn. @ Tk. 16.00 dzn. = Tk. 56.00
(vii) 3 mm glass pan: 4 x 1'-2" x 10" = 3.89 sft.
Add wastage 10%= 0.39 sft.
4.28 sft. @ Tk. 41.00 Per sft. = Tk. 175.48
(viii) Fitting fixing of glass pans with
necessary iron pins & pucca putty 3.89 sft. @ Tk. 15.46 Per sft. = Tk. 60.14
Total of (A) = Tk. 659.62
(b) Labour
i) Carpenter 1.75 Nos. @ Tk. 423.00 each = Tk. 740.25
ii) Carpenter helper 2.5 Nos. @ Tk. 304.00 each = Tk. 760.00
Total of (B) = Tk. 1,500.25
(c) Cost of wood
Vertcal: 4 x 3'-9" x 3.75" x 1.75"= 0.684 cft.
Horizontal: 6 x 3'-9" x 3.75" x 1.75"= 1.025 cft.
Analysis of PWD SoR 2014 for Civil Works 235

sash: 2 x 1'-0" x 1.75" x 1.75"= 0.043 cft.


panel: 2 x 1'-6" x 2'-0" x 1.75"= 0.875 cft.
= 2.627 cft. @ Tk. 2,250.0 Per cft. = Tk. 5,910.75
Total (A+B+C) = Tk. 8,070.62
Profit 10.00% = Tk. 807.06
Overhead 3.50% = Tk. 282.47
= Tk. 9,160.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 533.13
Grand total = Tk. 9,693.28
Rate per sft. = Tk. 754.93
Rate per sqm. = Tk. 8,126.07

Say, Tk. 8,126 .00 Per sqm.

Item No.- 12.13.2


Supplying, fitting & fixing 1.5" thick wood window shutter, one third glazed & 1.5" thick,
two third both side raised panelling having horizontal & vertical section of 3.5" x 1.5"
and having 1.5" x 1.5" sash bar.
For 1 No. glazed window shutter
Considering 3'-7" x 3'-7"= 12.84 sft. of work (4'-0" x 4'-0" opening)
For Gamari wood
(a) Fittings in/c glass panes: Same as item No. 12.13.1 = Tk. 659.62
(b) Labour Same as item No. 12.13.1 = Tk. 1,500.25
(c) Cost of wood
Wood req.: Same as 12.13.1 2.627 cft. @ Tk. 1,950.000 Per cft. = Tk. 5,122.65
Total = Tk. 7,282.52
Profit 10.00% = Tk. 728.25
Overhead 3.50% = Tk. 254.89
= Tk. 8,265.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 481.07
Grand total = Tk. 8,746.73
Rate Per sft. = Tk. 681.21
Rate Per sqm. = Tk. 7,332.54

Say, Tk. 7,333 .00 Per sqm.

Item No.- 12.13.3


Supplying, fitting & fixing 1.5" thick wood window shutter, one third glazed & 1.5" thick,
two third both side raised panelling having horizontal & vertical section of 3.5" x 1.5"
and having 1.5" x 1.5" sash bar.
For 1 No. glazed window shutter
Considering 3'-7" x 3'-7"= 12.84 sft. of work (4'-0" x 4'-0" opening)
For Teak chambal wood
(a) Fittings in/c glass panes: Same as item No. 12.13.1 = Tk. 659.62
(b) Labour Same as item No. 12.13.1 = Tk. 1,500.25
(c) Cost of wood
Wood req.: Same as 12.13.1 2.627 cft. @ Tk. 3,100.00 Per cft. = Tk. 8,143.70
Total = Tk. 10,303.57
Profit 10.00% = Tk. 1,030.36
Overhead 3.50% = Tk. 360.62
= Tk. 11,694.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 680.63
Grand total = Tk. 12,375.18
Rate per sft. = Tk. 963.80
Rate per sqm. = Tk. 10,374.34

Say, Tk. 10,374 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 236

Item No.- 12.13.4


Supplying, fitting & fixing 1.5" thick wood window shutter, one third glazed & 1.5" thick, two
third both side raised panelling having horizontal & vertical section of 3.5" x 1.5"
and having 1.5" x 1.5 sash bar.
For 1 No. glazed window shutter
Considering 3'-7" x 3'-7"= 12.84 sft. of work (4'-0" x 4'-0" opening)
For Chittagong teak wood
(a) Fittings in/c glass panes: Same as item No. 12.13.1 = Tk. 659.62
(b) Labour Same as item No. 12.13.1 = Tk. 1,500.25
(c) Cost of wood
Wood req.: Same as 12.13.1 2.627 cft. @ Tk. 4,500.00 Per cft. = Tk. 11,821.50
Total = Tk. 13,981.37
Profit 10.00% = Tk. 1,398.14
Overhead 3.50% = Tk. 489.35
= Tk. 15,868.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 923.58
Grand total = Tk. 16,792.44
Rate per sft. = Tk. 1,307.82
Rate per sqm. = Tk. 14,077.37

Say, Tk. 14,077 .00 Per sqm.

Item No.- 12.13.5


Supplying, fitting & fixing 1.5" thick wood window shutter, one third glazed & 1.5" thick, two
third both side raised panelling having horizontal & vertical section of 3.5" x 1.5" and
having 1.5" x 1.5 sash bar.
For 1 No. glazed window shutter
Considering 3'-7" x 3'-7"= 12.84 sft. of work (4'-0" x 4'-0" opening)
For Chapalish wood
(a) Fittings in/c glass panes: Same as item No. 12.13.1 = Tk. 659.62
(b) Labour Same as item No. 12.13.1 = Tk. 1,500.25
(c) Cost of wood
Wood req.: Same as 12.13.1 2.627 cft. @ Tk. 2,100.00 Per cft. = Tk. 5,516.70
Total = Tk. 7,676.57
Profit 10.00% = Tk. 767.66
Overhead 3.50% = Tk. 268.68
= Tk. 8,712.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 507.10
Grand total = Tk. 9,220.01
Rate per sft. = Tk. 718.07
Rate per sqm. = Tk. 7,729.31

Say, Tk. 7,729 .00 Per sqm.

Item No.- 12.14


Seasoning of timber in a bonafide mechanical timber seasoning plant upto a moisture content of
12% - 16% by weight as measured by a Electric moisture meter or any other moisture measuring
device etc. complete in all respect as per direction of Engineer-in-Charge
Considering 1 cft. of work
(a) Seasoning charge: (Market rate as
HA Timber Industries Ltd.) 1 cft @ Tk. 333.00 Per cft. = Tk. 333.00
(b) Labour for loading, unloading and carriage
of timber at both ends (1 x 2) 2 cft. @ Tk. 24.50 Per cft. = Tk. 49.00
Total = Tk. 382.00
Profit 10.00% = Tk. 38.20
Overhead 3.50% = Tk. 13.37
Analysis of PWD SoR 2014 for Civil Works 237

= Tk. 433.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25.23
Grand total = Tk. 458.80
Rate per cft. = Tk. 458.80
Rate per cum. = Tk. 16,202.52

Say, Tk. 16,203 .00 Per cum.

Item No.- 12.15.1


Supplying, fitting & fixing steel glazed window shutters with 25 x 25 x 5mm angle section
for chowkat and shutters and 50 x 25 x 5mm T-section for verticals
Considering 1 No. of steel window shutter
For 3'-0" x 4'-6"= 13.5 sft. of work (3 leaves each)
(a) Steel Materials:
(i) 1" x 1" x 3/16" angle (@1.16 Ib per rft.) for frame:-
Horizontal: 2 x 3'-0"= 6.00 rft.
Vertical: 2 x 3 x 4'-6"= 27.00 rft.
for clamp: 6 x 0'-6"= 3.00 rft.
= 36 rft.
Add wastage 5% = 1.8 rft.
= 37.8 rft.
= 43.85 Ibs. @ Tk. 28.34 Per Ib. = Tk. 1,242.71
(ii) 2" x 1" x 3/16" T-section (@ 1.91 Ibs per rft.)
Vertical: 2 x 4'-6"= 9.00 rft.
Add wastage 5% = 0.45 rft.
= 9.45 rft.
= 18.05 Ibs. @ Tk. 28.34 Per Ib. = Tk. 511.54
(iii) 1" x 1" x 3/16" angle (@1.14 Ib per rft.) for leaves:-
Vertical: 6 x 4'-4.5"= 26.25 rft.
Horizontal: 3 x 2 x 1'-0"= 6 rft.
= 32.25 rft.
Add wastage 5% = 1.61 rft.
= 33.86 rft.
= 38.60 Ibs. @ Tk. 28.34 Per Ib. = Tk. 1,093.92
(iv) 1" x 1" x 3/16" (@ 1.215 Ib per rft.) Tee for fixing glass panes:
3 x 4 x 1'-0"= 12 rft.
Add wastage 5% = 0.6 rft.
= 12.6 rft.
= 15.31 Ibs. @ Tk. 28.34 Per Ib. = Tk. 433.89
(v) 1" x 3/16" F.I. bars (@ 0.617 Ib per rft) for outer frame:
Vertical: 2 x 4'-6"= 9 rft.
Horizontal: 2 x 3'-0"= 6 rft.
= 15 rft.
Add wastage 5% = 0.75 rft.
= 15.75 rft.
= 9.72 Ibs. @ Tk. 25.40 Per Ib. = Tk. 246.89
(vi) 3/4" x 3/16" F.I. bar (@0.478 Ibs per rft.)
Vertical: 3 x 4'-6"= 13.5 rft.
Add wastage 5% = 0.675 rft.
= 14.175 rft.
= 6.78 Ibs. @ Tk. 25.40 Per Ib. = Tk. 172.21
(b) Fittings
(i) Stopper handle 2 Nos. @ Tk. 22.00 each = Tk. 44.00
(ii) 12" long iron cleats 3 Nos. @ Tk. 26.00 each = Tk. 78.00
(iii) 2" long pin hinges 6 Nos. @ Tk. 24.00 each = Tk. 144.00
(iv) Hand lock 3 Nos. @ Tk. 27.00 each = Tk. 81.00
(c) Workshop charges:
Analysis of PWD SoR 2014 for Civil Works 238

Manufacturing including fabrication, revetting,


welding in/c supply of all necessary
incidental materials 13.5 sft. @ Tk. 58.00 Per sft. = Tk. 783.00
(d) Labour charges
Labour charges for fitting fixing in position finished window shutter and
frames in the building including embeding clamp in
CC (1:2:4) & making grooves and mending
good the damage etc. complete. 1 No. @ Tk. 171.64 each = Tk. 171.64
(e) Carriage:
Carriage charge for iron materials from market to
workshop & carrying the finished window
from workshop to building site. 1 No. @ Tk. 53.30 each = Tk. 53.30
(f) Glass panes:
(i) 3 mm glass panes in/c wastage etc. 13.5 sft. @ Tk. 41.00 Per sft. = Tk. 553.50
(ii) Fitting fixing of glass panes with necessary
iron pins & pucca putty 13.5 sft. @ Tk. 15.46 Per sft. = Tk. 208.71
Total = Tk. 5,818.31
Profit 10.00% = Tk. 581.83
Overhead 3.50% = Tk. 203.64
= Tk. 6,603.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 384.35
Grand total = Tk. 6,988.13
Rate per sft. = Tk. 517.64
Rate per sqm. = Tk. 5,571.88

Say, Tk. 5,572 .00 Per sqm.

Item No.- 12.15.2


Supplying, fitting and fixing M.S. door shutter made with 1.5" x 1.5" x 1/4" angle outer frame,
inner member 1" x 1/4" F.I. Bar, cladding with 16 BWG M.S. sheet hinged with 2" x 2" x 1/4" M.S. angle chowkat
Considering 1 No. door
Considering 3'-4" x 7'-0"= 23.31 sft.
(a) Materials:
(i) 2" x 2" x 1/4" M.S. angle: @ 4.427 kg/m
Chowkat: 2 x 7'-0"= 14.00 rft.
1 x 3'-4" = 3.33 rft.
Clamp: 6 x 0'- 6" = 3.00 rft.
20.33 rft.
Add wastage 5%= 1.017 rft.
= 21.35 rft.
= 63.623 Ibs. @ Tk. 28.34 Per Ib. = Tk. 1,803.08
(ii) 1.5" x 1.5" x 1/4" M.S. angle @ 3.485 kg/m
2 x 6'- 11" = 13.84 rft.
2 x 3'-3" = 6.50 rft.
20.34 rft.
Add wastage 5%= 1.02 rft.
21.36 rft.
= 50.03 Ibs. @ Tk. 28.34 Per Ib. = Tk. 1,417.85
(iii) 1" x 1/4" M.S. F.I. bar: @ 1.178 kg/m
4 x 4'-11" = 19.68 rft.
1 x 3'-3" = 3.25 rft.
22.93 rft.
Add wastage 5%= 1.15 rft.
24.08 rft.
= 19.06 Ibs. @ Tk. 25.40 Per Ib. = Tk. 484.12
(iv) 16 BWG sheet: 9.96 kg/sqm. 23.31 sft.
Add wastage 5%= 1.17 sft.
Analysis of PWD SoR 2014 for Civil Works 239

24.48 sft.
= 49.95 Ibs. @ Tk. 38.55 Per Ib. = Tk. 1,925.57
(b) Fittings, hardwares and consumables:
(i) Locking arrangement 2.00 Nos. @ Tk. 229.00 each = Tk. 458.00
(ii) 3" long hinge 4.00 Nos. @ Tk. 5.00 each = Tk. 20.00
(iii) Electrodes 80.00 Nos. @ Tk. 10.00 each = Tk. 800.00
c) Fabrication and making in work-shop
(i) Welder / fabricator 2.00 Nos. @ Tk. 423.00 each = Tk. 846.00
(ii) Welder helper 2.00 Nos. @ Tk. 304.00 each = Tk. 608.00
(iii) Ordinary labour 2.00 Nos. @ Tk. 245.00 each = Tk. 490.00
d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 50.00
Sub-total = Tk. 8,902.62
e) Work-shop charges: 10% = Tk. 890.26
Total = Tk. 9,792.88
f) Ancillary works for fitting-fixing the door shutter
(i) Labour charge for cutting
2" x 2" x 6" size grooves 6 Nos @ Tk. 10.21 each = Tk. 61.26
(ii) CC (1:2:4):
6 x 3" x 3" x 6"= 0.19 cft. @ Tk. 17,637.01 Per % cft. = Tk. 33.51
g) Labour charge for fitting fixing the door shutter
(i) Mason 0.50 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Mason helper 1.00 No. @ Tk. 304.00 each = Tk. 304.00
(iii) Ordinary labour 0.50 No. @ Tk. 245.00 each = Tk. 122.50
Grand total = Tk. 10,508.65
Profit 10.00% = Tk. 1,050.87
Overhead 3.50% = Tk. 367.80
= Tk. 11,927.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 694.18
Grand total = Tk. 12,621.50
Rate per sft. = Tk. 541.46
Rate per sqm. = Tk. 5,828.28

Say, Tk. 5,828 .00 Per sqm.

Item No.- 12.16.1


Supplying, fitting & fixing steel glazed window shutters with the provision of fan-light
with Z- section, T-section & F.I. Bars.
Considering 1 No. steel window shutter
For 3'-0" x 5'-0"= 15 sft. of work.
(a) Steel Materials:
(i) 3/4" x 3/4" x 3/4" x 1/8" Z-section (@ 0.96 Ib per rft.) for frame:-
Chowkat: 2 x 5'-0"= 10.00 rft.
3 x 3'-0"= 9.00 rft.
1 x 4'-0"= 4.00 rft.
Frame shutter: 4 x 4'-0"= 16.00 rft.
4 x 1'-6"= 6.00 rft.
Fan light: 2 x 3'-0"= 6.00 rft.
2 x 1'-0"= 2.00 rft.
= 53.00 rft.
Add wastage 5%= 2.65 rft.
= 55.65 rft.
= 53.42 Ibs. @ Tk. 28.34 Per Ib. = Tk. 1,513.92
(ii) 3/4" x 1/8" F.I. bar to make T-section (@ 0.32 Ibs per rft.)
Shutter frame: 2 x 2 x 4 x 1'-6"= 24.0 rft.
Fan light: 2 x 1'-0"= 2.00 rft.
= 26 rft.
Add wastage 5%= 1.30 rft.
Analysis of PWD SoR 2014 for Civil Works 240

= 27.30 rft.
= 8.74 Ibs. @ Tk. 25.40 Per Ib. = Tk. 222.00
(iii) 1" x 1/8" F.I. bar (@ 0.423 Ib per rft.)
Chowkat: 1 x 4'-0"= 4 rft.
1 x 3'-0"= 3 rft.
= 7 rft.
Add wastage 5% = 0.35 rft.
= 7.35 rft.
= 3.11 Ibs. @ Tk. 25.40 Per Ib. = Tk. 78.99
(b) Fittings
(i) Stopper handle 2 Nos. @ Tk. 22.00 each = Tk. 44.00
(ii) 12" long iron cleats 3 Nos. @ Tk. 26.00 each = Tk. 78.00
(iii) 2" long pin hinges 6 Nos. @ Tk. 24.00 each = Tk. 144.00
(iv) 6" long clamp for chowkat 4 Nos. @ Tk. 28.00 each = Tk. 112.00
(c) Workshop charges:
Manufacturing including fabrication,
revetting, welding in/c supply of
all necessary incidental materials 15 sft. @ Tk. 58.00 Per sft. = Tk. 870.00
(d) Labour charges
Labour charges for fitting fixing in position finished window shutter and
frames in the building including embeding clamp
in CC (1:2:4) & making grooves and mending
good the damage etc. complete. 1 No. @ Tk. 171.64 Per sft. = Tk. 171.64
(e) Carriage charges:
Carriage charge for iron materials from market to
workshop & carrying the finished window
from workshop to building site. 1 No. @ Tk. 36.75 each = Tk. 36.75
(f) Glass panes:
(i) 3 mm glass panes in/c wastage etc. 15 sft. @ Tk. 41.00 Per sft. = Tk. 615.00
(ii) Fitting fixing of glass panes with necessary
iron pins & pucca putty 15 sft. @ Tk. 15.46 Per sft. = Tk. 231.90
Total = Tk. 4,118.20
Profit 10.00% = Tk. 411.82
Overhead 3.50% = Tk. 144.14
= Tk. 4,674.16
Add VAT with adjustment factor 1.0582 5.50% = Tk. 272.04
Grand total = Tk. 4,946.20
Rate per sft. = Tk. 329.75
Rate per sqm. = Tk. 3,549.43

Say, Tk. 3,549 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 241

Item No.- 12.16.2


Supplying, fitting & fixing steel glazed window shutters with out provision of fan-light
with Z- section, T-section & F.I. Bars etc.
Considering 1 No. window shutter
For 3'-0" x 5'-0"= 15 sft. of work
(a) Steel Materials:
(i) 3/4" x 3/4" x 3/4" x 1/8" Z-section (@ 0.96 Ib per rft.) for frame:-
Chowkat: 3 x 5'-0"= 15.00 rft.
2 x 3'-0"= 6.00 rft.
Frame shutter: 2 x 2 x 5'-0"= 20.00 rft.
2 x 2 x 1'-6"= 6.00 rft.
= 47.00 rft.
Add wastage 5%= 2.35 rft.
= 49.35 rft.
= 47.38 Ibs. @ Tk. 28.34 Per Ib. = Tk. 1,342.75
(ii) 3/4" x 1/8" F.I. bar to make T-section (@ 0.32 Ibs per rft.)
Shutter frame: 2 x 2 x 4 x 1'-6"= 24.0 rft.
Add wastage 5%= 1.20 rft.
= 25.20 rft.
= 8.06 Ibs. @ Tk. 25.40 Per Ib. = Tk. 204.72
(iii0 1" x 1/8" F.I. bar (@ 0.423 Ib per rft.)
Chowkat: 1 x 5'-0"= 5 rft.
Add wastage 5% = 0.25 rft.
= 5.25 rft.
= 2.22 Ibs. @ Tk. 25.40 Per Ib. = Tk. 56.39
(b) Fittings
(i) Stopper handle 2 Nos. @ Tk. 22.00 each = Tk. 44.00
(ii) 12" long iron cleats 2 Nos. @ Tk. 26.00 each = Tk. 52.00
(iii) 2" long pin hinges 4 Nos. @ Tk. 24.00 each = Tk. 96.00
(iv) 6" long clamp for chowkat 4 Nos. @ Tk. 28.00 each = Tk. 112.00
(c) Workshop charges:
Manufacturing including fabrication,
revetting, welding in/c supply of all
necessary incidental materials. 15 sft. @ Tk. 58.00 Per sft. = Tk. 870.00
(d) Labour charges
Labour charges for fitting fixing in position finished window shutter
and frames in the building including embeding clamp in
CC (1:2:4) & making grooves and mending
good the damage etc. complete. 1 No. @ Tk. 171.64 Per sft. = Tk. 171.64
(e) Carriage charges:
Carriage charge for iron materials from market
to workshop & carrying the finished window
from workshop to building site. 1 No. @ Tk. 36.75 each = Tk. 36.75
(f) Glass panes:
(i) 3 mm glass panes in/c wastage etc. 15 sft. @ Tk. 41.00 Per sft. = Tk. 615.00
(ii) Fitting fixing of glass panes with necessary
iron pins & pucca putty 15 sft. @ Tk. 15.46 Per sft. = Tk. 231.90
Total = Tk. 3,833.15
Profit 10.00% = Tk. 383.32
Overhead 3.50% = Tk. 134.16
= Tk. 4,350.63
Add VAT with adjustment factor 1.0582 5.50% = Tk. 253.21
Grand total = Tk. 4,603.84
Rate per sft. = Tk. 306.92
Rate per sqm. = Tk. 3,303.69
Say, Tk. 3,304 .00 Per sqm.
Item No.- 12.17
Analysis of PWD SoR 2014 for Civil Works 242

Supplying, fitting & fixing of fixed glazed frame with outer member of 3/4" x 3/4" x 3/4" x 1/8" Z
& 3/4" x 3/4" x 1/8" T-section etc.
Considering 1 No. fixed glazed frame
For 5'-0" x 2'-0"= 10 sft. of work
(a) Steel materials:
(i) 3/4" x 3/4" x 3/4" x 1/8" Z-section (@0.96 Ib per rft.):-
2 x 5'-0" + 2 x 2'-0"= 14.00 rft.
Add wastage 5%= 0.70 rft.
= 14.70 rft.
= 14.11 Ibs. @ Tk. 28.34 Per Ib. = Tk. 399.88
(ii) 3/4" x 1/8" F.I. bar to make T-section
(@ 0.32 Ibs per rft.) for horizontal and vertical divider
2 x (1 x 5'-0") + 2 x (2 x 5 x 1'-0")= 30.00 rft.
Add wastage 5%= 1.50 rft.
= 31.50 rft.
= 20.48 Ibs. @ Tk. 25.40 Per Ib. = Tk. 520.19
(iii) 6" long clamp for chowkat: 6.00 Nos. @ Tk. 28.00 each = Tk. 168.00
(b) Workshop charges:
Manufacturing including fabrication,
revetting, welding in/c supply of all
necessary incidental materials 10 sft. @ Tk. 58.00 Per sft. = Tk. 580.00
(c) Labour charges
Labour charges for fitting fixing in position finished window frames in
the building shutter and including embeding clamp in
CC (1:2:4) & making grooves and mending
good the damage etc. complete. 1 No. @ Tk. 171.64 Per sft. = Tk. 171.64
(d) Carriage charges:
Carriage charge for iron materials from market to
workshop & carrying the finished window
from workshop to building site. 1 No. @ Tk. 36.75 each = Tk. 36.75
(f) Glass panes:
(i) 3 mm glass panes in/c wastage etc. 10 sft. @ Tk. 41.00 Per sft. = Tk. 410.00
(ii) Fitting fixing of glass panes with necessary
iron pins & pucca putty 10 sft. @ Tk. 15.46 Per sft. = Tk. 154.60
Total = Tk. 2,441.06
Profit 10.00% = Tk. 244.11
Overhead 3.50% = Tk. 85.44
= Tk. 2,770.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 161.25
Grand total = Tk. 2,931.86
Rate per sft. = Tk. 293.19
Rate per sqm. = Tk. 3,155.90

Say, Tk. 3,156 .00 Per sqm.

Item No.- 12.18.1


Supplying, fitting & fixing 25mm thick wooden fly proof wire netting window shutter (double shutter).
Considering 1 unit wire netting shutter
For 2'-8" x 4'-2"= 11.13 sft. of work
Kathal wood:
(a) Cost of wood:
Style: 2 x 2 x 4'-3" x 3.25" x 1.25"= 0.478 cft.
Rails: 2 x 2 x 1'-6" x 3.25" x 1.25" = 0.169 cft.
Sash bar: 2 x 2 x 1'-3" x 1.75" x 1.25" = 0.076 cft.
bit: 2 x 4 x 1'-0" x 0.75" x 0.75"= 0.031 cft.
bit: 2 x 2 x 3'-9" x 0.75" x 0.75"= 0.059 cft.
0.813 cft. @ Tk. 2,250.0 Per cft. = Tk. 1,829.25
Analysis of PWD SoR 2014 for Civil Works 243

(b) Cost of fittings:


(i) 6" long brass tower & socket bolt 2 Nos. @ Tk. 241.00 each = Tk. 482.00
(ii) 3" long brass hinges 4.00 Nos. @ Tk. 89.00 each = Tk. 356.00
(iii) 6" long catch hooks 2.00 Nos. @ Tk. 10.00 each = Tk. 20.00
(iv) Heavy type nickle plated handle 2.00 Nos. @ Tk. 46.00 each = Tk. 92.00
(v) Screws 4.00 dzn. @ Tk. 22.00 Per dzn. = Tk. 88.00
Total (B) = Tk. 1,038.00
(c) Cost of wire net:
20 mesh 24 BWG. G.I. wire net
Wire net: 2 x 1'-0" x 3'-9"= 7.5 sft.
Add 5% wastage= 0.38 sft.
= 7.88 sft. @ Tk. 20.25 Per sft. = Tk. 159.57
(d) Labour cost:
(i) Labour charge for making in/c fitting &
fixing the same with frame etc complete.
(a) Carpenter 1.00 No. @ Tk. 423.00 each = Tk. 423.00
(b) Carpenter helper 1.25 Nos. @ Tk. 304.00 each = Tk. 380.00
(ii) Labour charge for fitting & fixing wire netting to the wooden shutters
with wooden bit & screw after cutting the net as per requirement.
(a) Carpenter 1/8 Nos. @ Tk. 423.00 each = Tk. 52.88
(b) Carpenter helper 1/8 Nos. @ Tk. 304.00 each = Tk. 38.00
Total (D) = Tk. 893.88
Total (A+B+C+D) = Tk. 3,920.70
Profit 10.00% = Tk. 392.07
Overhead 3.50% = Tk. 137.22
= Tk. 4,449.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 258.99
Grand total = Tk. 4,708.98
Rate Per sft. = Tk. 423.09
Rate Per sqm. = Tk. 4,554.14

Say, Tk. 4,554 .00 Per sqm.

Item No.- 12.18.2


Supplying, fitting & fixing 25mm thick wooden fly proof wire netting window shutter (double shutter).
Considering 1 unit wire netting shutter
For 2'-8" x 4'-2"= 11.13 sft. of work
Teak chambal wood:
(a) Cost of wood:
Wood req.: Same as 97(a) 0.813 cft. @ Tk. 3,100.00 Per cft. = Tk. 2,520.30
(b) Cost of fittings Same as item No. 97(a) = Tk. 1,038.00
(c) Cost of wire net Same as item No. 97(a) = Tk. 159.57
(d) Labour cost Same as item No. 97(a) = Tk. 893.88
Total = Tk. 4,611.75
Profit 10.00% = Tk. 461.18
Overhead 3.50% = Tk. 161.41
= Tk. 5,234.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 304.64
Grand total = Tk. 5,538.98
Rate per sft. = Tk. 497.66
Rate per sqm. = Tk. 5,356.81

Say, Tk. 5,357 .00 Per sqm.

Item No.- 12.18.3


Supplying, fitting & fixing 25mm thick wooden fly proof wire netting window shutter (double shutter).
Considering 1 unit wire netting shutter
Analysis of PWD SoR 2014 for Civil Works 244

For 2'-8" x 4'-2"= 11.13 sft. of work


Chittagong teak wood:
(a) Cost of wood:
Wood req.: Same as 97(a) 0.813 cft. @ Tk. 4,500.00 Per cft. = Tk. 3,658.50
(b) Cost of fittings Same as item No. 97(a) = Tk. 1,038.00
(c) Cost of wire net Same as item No. 97(a) = Tk. 159.57
(d) Labour cost Same as item No. 97(a) = Tk. 893.88
Total = Tk. 5,749.95
Profit 10.00% = Tk. 575.00
Overhead 3.50% = Tk. 201.25
= Tk. 6,526.20
Add VAT with adjustment factor 1.0582 5.50% = Tk. 379.83
Grand total = Tk. 6,906.03
Rate per sft. = Tk. 620.49
Rate per sqm. = Tk. 6,678.95

Say, Tk. 6,679 .00 Per sqm.

Item No.- 12.19


Supplying, fitting and fixing louver shutter of ctg. Teak wood
Considering 3'-0" x 2'-6" = 7.50 sft.

(a) Material cost:


(i) Cost of ctg. Wood:
Outer frame=
2x 3'-0" x 3.25" x 1.75" = 0.24 cft.
2x 2'-6" x 3.25" x 1.75" = 0.20 cft.
Horizontal blade:
17x 2'-6" x 3" x 1" = 1.06 cft.
1.50 cft. @ Tk. 4,500.00 Per cft. = Tk. 6,750.00

(ii) Brass hinges 2 Nos. @ Tk. 89.00 each = Tk. 178.00


(iii) Screws 36 Nos. @ Tk. 1.83 each = Tk. 65.88
(iv) Knob catchment 1 Nos. @ Tk. 25.00 each = Tk. 25.00
(v) Magnetic 2 Nos. @ Tk. 45.00 each = Tk. 90.00

(b) Labour cost for making moulding


(i) Carpenter 1.5 Nos. @ Tk. 423.00 each = Tk. 634.50
(ii) Helper 1.5 Nos. @ Tk. 304.00 each = Tk. 456.00

(c) Labour cost for fitting & fixing:


(i) Carpenter 0.1 Nos. @ Tk. 423.00 each = Tk. 42.30
(ii) Helper 0.1 Nos. @ Tk. 304.00 each = Tk. 30.40
Total (A+B+C) = Tk. 8,272.08
Profit 10.00% = Tk. 827.21
Overhead 3.50% = Tk. 289.52
= Tk. 9,388.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 546.44
Grand total = Tk. 9,935.25
Rate Per sft. = Tk. 1,324.70
Rate Per sqm. = Tk. 14,259.07

Say, Tk. 14,259 .00 Per sqm


Item No.- 12.20
Supplying, fitting and fixing 3X3/4 Chittagong teak wood moulding bit
Considering 6'-9" x 3" x 3/4"

Purchased Size = 7- 0x 3.25x1= 0.15 cft.


Analysis of PWD SoR 2014 for Civil Works 245

(a) Material cost:


(i) Cost of ctg. Wood 0.15 cft. @ Tk. 4,500.00 Per cft. = Tk. 675.00
(ii) Cost of Rowel plug L.S. = Tk. 30.00

(b) Labour cost for making moulding


(i) Carpenter 1.5 Nos. @ Tk. 423.00 each = Tk. 634.50
(ii) Helper 1.5 Nos. @ Tk. 304.00 each = Tk. 456.00

(c) Labour cost for fitting & fixing:


(i) Carpenter 0.1 Nos. @ Tk. 423.00 each = Tk. 42.30
(ii) Helper 0.1 Nos. @ Tk. 304.00 each = Tk. 30.40
Total (A+B+C) = Tk. 1,868.20
Profit 10.00% = Tk. 186.82
Overhead 3.50% = Tk. 65.39
= Tk. 2,120.41
Add VAT with adjustment factor 1.0582 5.50% = Tk. 123.41
Grand total = Tk. 2,243.82
Rate Per rft. = Tk. 332.42
Rate Per rm. = Tk. 1,090.34

Say, Tk. 1,090 .00 Per rm.

Item No.- 12.21


Extra cost for using brass/ SS fittings in place of iron fittings in doors & windows for all floors (super quality local).
12.21.1 Brass fittings for 1 No. of door
For 20.5 sft. of work
Fittings Qty. Unit Price for iron Price for brass
(i) 12" long tower bolt 1 No. Tk. 39.00 Tk. 321.00
(ii) 8" socket bolt 1 No. Tk. 28.00 Tk. 259.00
(iii) 4" long hinges 4 Nos. Tk. 292.00 Tk. 468.00
(iv) Nickle plated handle 2 Nos. Tk. 96.00 Tk. 134.00
(v) Screws 5 dzn. Tk. 80.00 Tk. 110.00
(vi) Hinge cleat 1 No. Tk. 10.00 Tk. 10.00
(vii) Screws for hinge cleats. 0.5 dzn. Tk. 8.00 Tk. 11.00
Total= Tk. 553.00 Tk. 1,313.00
Extra cost for brass = Tk. 760.00
Profit 10.00% = Tk. 76.00
Overhead 3.50% = Tk. 26.60
= Tk. 862.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 50.20
Grand total = Tk. 912.80
Rate per sft. = Tk. 44.53
Rate per sqm. = Tk. 479.32

Say, Tk. 479 .00 Per sqm.

12.21.2 SS fittings for 1 No. of door


For 20.5 sft. of work
Fittings Qty. Unit Price for iron Price for SS
(i) 12" long tower bolt 1 No. Tk. 39.00 Tk. 150.00
(ii) 8" socket bolt 1 No. Tk. 28.00 Tk. 122.00
(iii) 4" long hinges 4 Nos. Tk. 292.00 Tk. 372.00
(iv) Nickle plated handle 2 Nos. Tk. 96.00 Tk. 114.00
(v) Screws 5 dzn. Tk. 80.00 Tk. 114.60
(vi) Hinge cleat 1 No. Tk. 10.00 Tk. 96.00
(vii) Screws for hinge cleats. 0.5 dzn. Tk. 8.00 Tk. 48.00
Analysis of PWD SoR 2014 for Civil Works 246

Total= Tk. 553.00 Tk. 1,016.60


Extra cost for brass = Tk. 463.60
Profit 10.00% = Tk. 46.36
Overhead 3.50% = Tk. 16.23
= Tk. 526.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 30.62
Grand total = Tk. 556.81
Rate per sft. = Tk. 27.16
Rate per sqm. = Tk. 292.35

Say, Tk. 292 .00 Per sqm.


12.21.3 Brass fittings for 1 No. of windows
For 13.75 sft. of work
Fittings Qty. Unit Price for iron Price for brass
(i) 10" long tower bolt 1 No. Tk. 34.00 Tk. 275.00
(ii) 6" socket bolt 1 No. Tk. 27.00 Tk. 259.00
(iii) 3" long hinges 4 Nos. Tk. 20.00 Tk. 380.00
(iv) Handle 1 Nos. Tk. 46.00 Tk. 67.00
(v) 9" long catch hook 2 Nos. Tk. 40.00 Tk. 40.00
(vi) Screws 3.5 dzn. Tk. 56.00 Tk. 77.00
Total = Tk. 223.00 Tk. 1,098.00
Extra cost for brass = Tk. 875.00
Profit 10.00% = Tk. 87.50
Overhead 3.50% = Tk. 30.63
= Tk. 993.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 57.80
Grand total = Tk. 1,050.93
Rate per sft. = Tk. 76.43
Rate per sqm. = Tk. 822.69

Say, Tk. 823 .00 Per sqm.


12.21.4 SS fittings for 1 No. of windows
For 13.75 sft. of work
Fittings Qty. Unit Price for iron Price for brass
(i) 10" long tower bolt 1 No. Tk. 34.00 Tk. 150.00
(ii) 6" socket bolt 1 No. Tk. 27.00 Tk. 122.00
(iii) 3" long hinges 4 Nos. Tk. 20.00 Tk. 372.00
(iv) Handle 1 Nos. Tk. 46.00 Tk. 57.00
(v) 9" long catch hook 2 Nos. Tk. 40.00 Tk. 40.00
(vi) Screws 3.5 dzn. Tk. 56.00 Tk. 80.22
Total = Tk. 223.00 Tk. 821.22
Extra cost for brass = Tk. 598.22
Profit 10.00% = Tk. 59.82
Overhead 3.50% = Tk. 20.94
= Tk. 678.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 39.52
Grand total = Tk. 718.50
Rate per sft. = Tk. 52.25
Rate per sqm. = Tk. 562.42

Say, Tk. 562 .00 Per sqm.


Item No.- 12.22
Supplying, fitting and fixing 'King Brand' hydraulic door closer.

Considering 1 No. door closer


(a) Cost of door closer 1 No. @ Tk. 1,917.00 each = Tk. 1,917.00
(b) Labour charge for fitting fixing in position after cutting
Analysis of PWD SoR 2014 for Civil Works 247

necessary grooves in door shutters and frame


(i) Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(ii) Carpenter helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
Total = Tk. 2,098.75
Profit 10.00% = Tk. 209.88
Overhead 3.50% = Tk. 73.46
= Tk. 2,382.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 138.64
Grand total = Tk. 2,520.73
Rate per No. = Tk. 2,520.73

Say, Tk. 2,521 .00 each

Item No.- 12.23.1


Supplying, fitting and fixing approved quality MORTICE door lock.

Considering 1 No. door lock


(a) Cost of door lock 1 No. @ Tk. 1,167.00 each = Tk. 1,167.00
(b) Labour charge for fitting fixing in position after cutting
necessary grooves in door shutters and frame
(i) Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(ii) Carpenter helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
Total = Tk. 1,348.75
Profit 10.00% = Tk. 134.88
Overhead 3.50% = Tk. 47.21
= Tk. 1,530.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 89.10
Grand total = Tk. 1,619.94
Rate per No. = Tk. 1,619.94

Say, Tk. 1,620 .00 each

Item No.- 12.23.2


Supplying, fitting and fixing approved quality RIM door lock.

Considering 1 No. door lock


(a) Cost of door lock 1 No. @ Tk. 619.00 each = Tk. 619.00
(b) Labour charge for fitting fixing in position after cutting
necessary grooves in door shutters and frame
(i) Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(ii) Carpenter helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
Total = Tk. 800.75
Profit 10.00% = Tk. 80.08
Overhead 3.50% = Tk. 28.03
= Tk. 908.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 52.90
Grand total = Tk. 961.76
Rate per No. = Tk. 961.76

Say, Tk. 962 .00 each


Item No.- 12.24
Supplying, fitting and fixing magnetic door shock absorber.
Considering 1 No. magnetic door shock absorber
(a) Door shock absorber 1 No. @ Tk. 45.00 each = Tk. 45.00
(b) Labour charge for fitting fixing in position after cutting
necessary grooves in door shutters and frame
(i) Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
Analysis of PWD SoR 2014 for Civil Works 248

(ii) Carpenter helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
Total = Tk. 226.75
Profit 10.00% = Tk. 22.68
Overhead 3.50% = Tk. 7.94
= Tk. 257.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 14.98
Grand total = Tk. 272.35
Rate per No. = Tk. 272.35

Say, Tk. 272 .00 each

Item No.- 12.25


Supplying, fitting and fixing best quality heavy type of 12" long brass hasp bolt
Considering 1 No. hasp bolt
(a) Cost of 12" long hasp bolt 1 No. @ Tk. 293.00 each = Tk. 293.00
(b) Labour charge for fitting fixing in position after cutting
necessary grooves in door shutters and frame
Carpenter 0.1 No. @ Tk. 423.00 each = Tk. 42.30
Total = Tk. 335.30
Profit 10.00% = Tk. 33.53
Overhead 3.50% = Tk. 11.74
= Tk. 380.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.15
Grand total = Tk. 402.72
Rate per No. = Tk. 402.72

Say, Tk. 403 .00 each


Analysis of PWD SoR 2014 for Civil Works 249

DIVISION 13 : WINDOW GRILL, VERANDAH GRILL & NETTING


Item No.- 13.1
Supply, fitting & fixing window grills made of 5/8" dia M.S. rod @ 4" c/c fitted
with 1.5" x 1/4" F.I. bars 3 Nos. horizontally.
For 1 No. window grill
Considering 3'-6" x 4'-6" = 15.75 sft. of work
(a) Materials:
(i) F.I.bars (@ 1.28 Ibs per rft): 3 x 4'-0"= 12.00 rft.
= 15.36 Ibs. @ Tk. 25.40 Per Ib. = Tk. 390.14
(ii) 5/8" dia M.S. rod (1.043 Ibs per rft.):
10 x 4' - 6" = 45 rft.
= 46.94 Ibs. @ Tk. 26.76 Per Ib. = Tk. 1,256.11
(b) Workshop charge:
Labour cost for manufacturing, welding
including supply of necessary electrode, cutting steel
to required sizes etx complete. 15.75 sft. @ Tk. 45.71 Per sft. Tk. 719.93
(c) Labour charges:
Labour charges for fitting and fixing in position of grills
(i) Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(ii) Carpenter helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
(ii) Cost of screws 3 dzn. @ Tk. 16.00 Per dzn. = Tk. 48.00
(d) Carriage charge for steel materials from market to
workshop and carrying the window grill
from workshop to building site. 1 No. @ Tk. 36.75 each = Tk. 36.75
Total = Tk. 2,632.68
Profit 10.00% = Tk. 263.27
Overhead 3.50% = Tk. 92.14
= Tk. 2,988.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 173.91
Grand total = Tk. 3,162.00
Rate per sft. = Tk. 200.76
Rate per sqm. = Tk. 2,160.98

Say, Tk. 2,161 .00 Per sqm.

Item No.- 13.2


Supplying, fitting and fixing window grill made of M.S section 3/4" x 1/8" with outer frames 1" x 1/4".
for 1 no window grill
considering 5'-0" x 4'-6" = 22.50 sft = 2.09 sqm.
a) Materials:
i) 1" x 1/4" F.I bars @ 0.85 lbs. per rft for outer frame.
2 x 5'-0" = 10.00 rft
2 x 4'-6" = 9.00 rft
19.00 rft
Add wastage 5% = 0.95 rft
19.95 rft
= 16.97 lbs @ Tk. 25.40 per lb =Tk. 431.06
ii) 3/4" x 1/8 F.I bars @ 0.319 lbs. per rft. For inner members
horizontal: 6 x 5'-0" = 30.00 rft
horizontal short piece 6 x 4 x 1.22' = 29.33 rft
vertical 6 x 4'-6" = 27.00 rft
F.I bars for clamps 4 x 2 x 0'-6" = 4.00 rft
= 90.33 rft
Add wastage 5% = = 4.52 rft
= 94.85 rft
= 31.468 lbs @ Tk. 25.40 per lb =Tk. 799.30
Analysis of PWD SoR 2014 for Civil Works 250

b) workshope charge
labour cost for manufacturing, welding, welding 22.50 sft @ Tk. 45.71 per sft =Tk. 1,028.48

c) labour charges
labour charges for fitting fixing in position of grill
i) mason 0.50 No. @ Tk. 389.00 each Tk. 194.50
ii) skilled labour 0.50 No. @ Tk. 303.00 each Tk. 151.50
iii) cost of screws 3.00 dzn @ Tk. 16.00 per dznTk. 48.00
d) carriage charge for steel materials from market to
workshop and carrying the window grill from 1.00 No. @ Tk. 36.75 each = Tk. 36.75
workshop to building site
S Total = Tk. 2,689.58
Contractors profit 10.00% = Tk. 268.96
Overhead expenses 3.50% = Tk. 94.14
Tk. 3,052.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 177.67
Grand total = Tk. 3,230.34
Rate per sft. = Tk. 143.57
Rate per sqm = Tk. 1,544.82

Say, Tk. 1,545 .00 Per sqm.

Item No.- 13.3


Supplying, fitting and fixing window grill made of M.S section 3/4" x 3/16" both inner and outer members
for 1 no window grill
considering 5'-0" x 4'-6" = 22.50 sft.
a) Materials:
i) 3/4" x 3/16" F.I bars @ 0.478 lbs. per rft for outer frame.
2 x 5'-0" = 10.00 rft
2 x 4'-6" = 9.00 rft
19.00 rft
Add wastage 5% = 0.95 rft
19.95 rft
= 9.55 lbs @ Tk. 25.40 per lb =Tk. 242.48
ii) 3/4" x 3/16 F.I bars @ 0.478 lbs. per rft. For inner members
horizontal 6 x 5'-0" = 30.00 rft
horizontal short piece 6 x 4 x 1.22' = 29.33 rft
vertical 6 x 4'-6" = 27.00 rft
F.I bars for clamps 4 x 2 x 0'-6" = 4.00 rft
90.33 rft
Add wastage 5% = 4.52 rft
94.85
= 45.39 lbs @ Tk. 25.40 per lb =Tk. 1,152.84
b) workshope charge
labour cost for manufacturing, welding, welding
including supply of necessary electrode, cutting steel to required size etc. complete 22.50 sft @ Tk. 45.71 per sft =Tk. 1,028.48
c) labour charges
labour charges for fitting fixing in position of grill
i) mason 0.50 No. @ Tk. 389.00 each = Tk. 194.50
ii) skilled labour 0.50 No. @ Tk. 303.00 each = Tk. 151.50
iii) cost of screws 3.00 dzn @ Tk. 16.00 per dznTk.
= 48.00
d) carriage charge for steel materials from market to 1.00 No. @ Tk. 36.75 each = Tk. 36.75
workshop and carrying the window grill from S Total = Tk. 2,854.55
workshop to building site Profit 10.00% = Tk. 285.46
Overhead 3.50% = Tk. 99.91
Tk. 3,239.92
Analysis of PWD SoR 2014 for Civil Works 251

Add VAT with adjustment factor 1.0582 5.50% = Tk. 188.57


Grand total = Tk. 3,428.49
Rate per sft. = Tk. 152.38
Rate per sqm. = Tk. 1,639.61

Say, Tk. 1,640 .00 Per sqm.

Item No.- 13.3.1 without outer frame


Supplying, fitting and fixing window grill made of M.S section 3/4" x 3/16".
for 1 no window grill
considering 5'-0" x 4'-6" = 22.50 sft.
a) Materials:
i) 3/4" x 3/16" F.I bars @ 0.478 lbs. per rft for inner members
horizontal 6 x 5'-0" = 30.00 rft
horizontal short piece 6 x 4 x 1.22' = 29.33 rft
vertical 6 x 4'-6" = 27.00 rft
F.I bars for clamps 6 x 2 x 0'-6" = 6.00 rft
92.33 rft
Add wastage 5% = 4.62 rft
96.95
= 46.39 lbs @ Tk. 25.40 per lb =Tk. 1,178.36
b) workshope charge
labour cost for manufacturing, welding, welding
including supply of necessary electrode, cutting steel to required size etc. complete 22.50 sft @ Tk. 45.71 per sft =Tk. 1,028.48
c) labour charges
labour charges for fitting fixing in position of grill
i) mason 0.50 No. @ Tk. 389.00 each = Tk. 194.50
ii) skilled labour 0.50 No. @ Tk. 303.00 each = Tk. 151.50
iii) cost of screws 3.00 dzn @ Tk. 16.00 per dznTk.
= 48.00
d) carriage charge for steel materials from market to 1.00 No. @ Tk. 36.75 each = Tk. 36.75
workshop and carrying the window grill from S Total = Tk. 2,637.59
workshop to building site Profit 10.00% = Tk. 263.76
Overhead 3.50% = Tk. 92.32
Tk. 2,993.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 174.23
Grand total = Tk. 3,167.90
Rate per sft. = Tk. 140.80
Rate per sqm. = Tk. 1,515.01

Say, Tk. 1,515 .00 Per sqm.

Item No.- 13.4.1


Supplying, fitting and fixing window grill made of M.S section 1" x 1/4" both inner and outer members
for 1 no window grill
considering 5'-0" x 4'-6" = 22.50 sft.
a) Materials:
i) 1" x 1/4" F.I bars @ 0.850 lbs. per rft for outer frame.
2 x 5'-0" = 10.00 rft
2 x 4'-6" = 9.00 rft
19.00 rft
Add wastage 5% = 0.95 rft
19.95 rft
= 16.97 lbs @ Tk. 25.40 per lb =Tk. 431.07

ii) 1" x 1/4 F.I bars @ 0.850 lbs. per rft. For inner members
horizontal 6 x 5'-0" = 30.00 rft
horizontal short piece 6 x 4 x 1.22' = 29.33 rft
Analysis of PWD SoR 2014 for Civil Works 252

vertical 6 x 4'-6" = 27.00 rft


F.I bars for clamps 4 x 2 x 0'-6" = 4.00 rft
90.33 rft
Add wastage 5% = 4.5165 rft
94.85 rft
= 80.69 lbs @ Tk. 25.40 per lb =Tk. 2,049.48

b) workshope charge
labour cost for manufacturing, welding, welding
including supply of necessary electrode, cutting steel to required size etc. complete 22.50 sft @ Tk. 45.71 per sft =Tk. 1,028.48
c) labour charges
labour charges for fitting fixing in position of grill
i) mason 0.50 No. @ Tk. 389.00 each = Tk. 194.50
ii) skilled labour 0.50 No. @ Tk. 303.00 each = Tk. 151.50
iii) cost of screws 3.00 dzn @ Tk. 16.00 per dznTk.
= 48.00
d) carriage charge for steel materials from market to 1.00 No. @ Tk. 36.75 each = Tk. 36.75
workshop and carrying the window grill from S. Total = Tk. 3,939.78
workshop to building site Profit 10.00% = Tk. 393.98
Overhead 3.50% = Tk. 137.89
= Tk. 4,471.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 260.25
Grand total = Tk. 4,731.90
Rate per sft. = Tk. 210.31
Rate per sqm. = Tk. 2,262.94

Say, 2,262 .94 Per sqm.

Item No.- 13.4.1.1 without outer frame


Supplying, fitting and fixing window grill made of M.S section 1" x 1/4" with inner members and without outer frames.
for 1 no window grill
considering 5'-0" x 4'-6" = 22.50 sft.
a) Materials:
i) 1" x 1/4" F.I bars @ 0.850 lbs. per rft for inner members
horizontal 6 x 5'-0" = 30.00 rft
horizontal short piece 6 x 4 x 1.22' = 29.33 rft
vertical 6 x 4'-6" = 27.00 rft
F.I bars for clamps 6 x 2 x 0'-6" = 6.00 rft
92.33 rft
Add wastage 5% = 4.62 rft
96.95 rft
= 82.47 lbs @ Tk. 25.40 per lb =Tk. 2,094.86
b) workshope charge
labour cost for manufacturing, welding, welding
including supply of necessary electrode, cutting steel to required size etc. complete 22.50 sft @ Tk. 45.71 per sft =Tk. 1,028.48
c) labour charges
labour charges for fitting fixing in position of grill
i) mason 0.50 No. @ Tk. 389.00 each = Tk. 194.50
ii) skilled labour 0.50 No. @ Tk. 303.00 each = Tk. 151.50
iii) cost of screws 3.00 dzn @ Tk. 16.00 per dznTk.
= 48.00
d) carriage charge for steel materials from market to 1.00 No. @ Tk. 36.75 each = Tk. 36.75
S. Total = Tk. 3,554.09
Profit 10.00% = Tk. 355.41
Overhead 3.50% = Tk. 124.39
Tk. 4,033.89
Add VAT with adjustment factor 1.0582 5.50% = Tk. 234.78
Grand total = Tk. 4,268.67
Analysis of PWD SoR 2014 for Civil Works 253

Rate per sft. = Tk. 189.72


Rate per sqm. = Tk. 2,041.39

Say, Tk. 2,041.00 .00 Per sqm.

Item No.- 13.4.2 25x6 outer 20x5 inner


Supplying, fitting and fixing window grill made of M.S section 1" x 1/4" both inner and outer members
for 1 no window grill
considering 5'-0" x 4'-6" = 22.50 sft.
a) Materials:
i) 1" x 1/4" F.I bars @ 0.850 lbs. per rft for outer frame.
2 x 5'-0" = 10.00 rft
2 x 4'-6" = 9.00 rft
19.00 rft
Add wastage 5% = 0.95 rft
19.95 rft
= 16.971 lbs @ Tk. 25.40 per lb =Tk. 431.07

ii) 3/4" x 3/16" F.I bars @ 0.478 lbs. per rft. For inner members
horizontal 6 x 5'-0" = 30.00 rft
horizontal short piece 6 x 4 x 1.22' = 29.33 rft
vertical 6 x 4'-6" = 27.00 rft
F.I bars for clamps 4 x 2 x 0'-6" = 4.00 rft
90.33 rft
Add wastage 5% = 4.52 rft
94.85 rft
= 45.39 lbs @ Tk. 25.40 per lb =Tk. 1,152.84
b) workshope charge
labour cost for manufacturing, welding, welding
including supply of necessary electrode, cutting steel to required size etc. complete 22.50 sft @ Tk. 45.71 per sft =Tk. 1,028.48
c) labour charges
labour charges for fitting fixing in position of grill
i) mason 0.50 No. @ Tk. 389.00 each = Tk. 194.50
ii) skilled labour 0.50 No. @ Tk. 303.00 each = Tk. 151.50
iii) cost of screws 3.00 dzn @ Tk. 16.00 per dznTk.
= 48.00
d) carriage charge for steel materials from market to 1.00 No. @ Tk. 36.75 each = Tk. 36.75
S. Total = Tk. 3,043.14
Profit 10.00% = Tk. 304.31
Overhead 3.50% = Tk. 106.51
Tk. 3,453.96
Add VAT with adjustment factor 1.0582 5.50% = Tk. 201.02
Grand total = Tk. 3,654.98
Rate per sft. = Tk. 162.44
Rate per sqm. = Tk. 1,747.85

Say, 1,747 .85 Per sqm.

Item No.- 13.5.1


Supply, fitting & fixing window grills made of M.S. section 12 x 12 mm solid bar with outer frame of 1.5" x 1/4" F.I. bar
Break-up for 1 x 6'-6" x 4'-6" = 29.25 sft. area
1. 1.5" x 1/4" F.I. Bar
4 x 4'-6" = 18.00 rft.
2 x 6'-6" = 13.00 rft.
31.00 rft.
Wastage 5% = 1.55 rft.
32.55 rft.
Analysis of PWD SoR 2014 for Civil Works 254

@ 1.28 per rft.= 41.66 Ibs @ Tk. 25.40 Per Ib. = Tk. 1,058.16

2. 1" x 1/4" F.I. bar for clamp


4 x 2 x 0'-6" = 4.00 rft.
@ 0.85 per rft.= 3.40 Ibs @ Tk. 25.40 Per Ib. = Tk. 86.36

3. 12 x 12 mm solid square bar


13 x 6-6" = 84.50 rft.
Add 5% watage = 4.23 rft.
88.73 rft.
@ 0.76 Ibs/rft = 67.43 Ibs @ Tk. 28.57 Per Ib. = Tk. 1,926.48
4. Workshop charge:
Labour cost for fabrication, welding, making hole in/c supply of
Electrode etc. etc. complete. 29.25 sft. @ Tk. 50.28 Per sft. = Tk. 1,470.69
5. Labour charge for fitting-fixing in position
(a) Mason 1.00 Nos. @ Tk. 389.00 each = Tk. 389.00
(b) Skilled Labour 1.00 Nos. @ Tk. 303.00 each = Tk. 303.00
6. Carrying Charges L.S. = Tk. 61.25
7. Cost of CC, curing, incidental, sundries etc. L.S. = Tk. 171.41
Total = Tk. 5,466.35
Profit 10.00% = Tk. 546.64
Overhead 3.50% = Tk. 191.32
= Tk. 6,204.31
Add VAT with adjustment factor 1.0582 5.50% = Tk. 361.10
Grand total = Tk. 6,565.41
Rate per sft. = Tk. 224.46
Rate per sqm. = Tk. 2,416.09

Say Tk. 2,416 .00 per sqm.

Item No.- 13.5.2


Supply, fitting & fixing window grills made of M.S. section 10x 10 mm solid bar with outer frame of 1.5" x 1/4" F.I. bar
Break-up for 1 x 6'-6" x 4'-6" = 29.25 sft. area
1. 1.5" x 1/4" F.I. Bar
4 x 4'-6" = 18.00 rft.
2 x 6'-6" = 13.00 rft.
31.00 rft.
Wastage 5% = 1.55 rft.
32.55 rft.
@ 1.28 per rft.= 41.66 Ibs @ Tk. 25.40 Per Ib. = Tk. 1,058.16

2. 1" x 1/4" F.I. bar for clamp


4 x 2 x 0'-6" = 4.00 rft.
@ 0.85 per rft.= 3.40 Ibs @ Tk. 25.40 Per Ib. = Tk. 86.36

3. 10 x 10 mm solid square bar


13 x 6-6" = 84.50 rft.
Add 5% watage = 4.23 rft.
88.73 rft.
@ 0.53 Ibs/rft = 47.03 Ibs @ Tk. 28.57 Per Ib. = Tk. 1,343.65
4. Workshop charge:
Analysis of PWD SoR 2014 for Civil Works 255

Labour cost for fabrication, welding, making hole in/c supply of


Electrode etc. etc. complete. 29.25 sft. @ Tk. 50.28 Per sft. = Tk. 1,470.69
5. Labour charge for fitting-fixing in position
(a) Mason 1.00 Nos. @ Tk. 389.00 each = Tk. 389.00
(b) Skilled Labour 1.00 Nos. @ Tk. 303.00 each = Tk. 303.00
6. Carrying Charges L.S. = Tk. 61.25
7. Cost of CC, curing, incidental, sundries etc. L.S. = Tk. 171.41
Total = Tk. 4,883.52
Profit 10.00% = Tk. 488.35
Overhead 3.50% = Tk. 170.92
= Tk. 5,542.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 322.60
Grand total = Tk. 5,865.39
Rate per sft. = Tk. 200.53
Rate per sqm. = Tk. 2,158.50

Say Tk. 2,159 .00 per sqm.

Item No.- 13.5.3


Supply, fitting & fixing window grills made of 12x 12 mm hollow M.S.
box made of 16 BWG M.S. sheet with outer frame of 1.5" x 1/4" F.I. Bar
Break-up for 1 x 6'-6" x 4'-6" = 29.25 sft. area
1. 1.5" x 1/4" F.I. Bar
4 x 4'-6" = 18.00 rft.
2 x 6'-6" = 13.00 rft.
31.00 rft.
Wastage 5% = 1.55 rft.
32.55 rft.
@ 1.28 per rft.= 41.66 Ibs @ Tk. 25.40 Per Ib. = Tk. 1,058.16

2. 1" x 1/4" F.I. bar for clamp


4 x 2 x 0'-6" = 4.00 rft.
@ 0.85 per rft.= 3.40 Ibs @ Tk. 25.40 Per Ib. = Tk. 86.36
3. 12 x 12 mm M.S. hollow box
13 x 6-6" = 84.50 rft.
Add 5% watage = 4.23 rft.
88.73 rft. @ Tk. 16.35 Per rft. = 1,450.74
4. Workshop charge:
Labour cost for fabrication, welding, making hole in/c supply of
Electrode etc. etc. complete. 29.25 sft. @ Tk. 50.28 Per sft. = Tk. 1,470.69
5. Labour charge for fitting-fixing in position
(a) Mason 1.00 Nos. @ Tk. 389.00 each = Tk. 389.00
(b) Skilled Labour 1.00 Nos. @ Tk. 303.00 each = Tk. 303.00
6. Carrying Charges L.S. = Tk. 61.25
7. Cost of CC, curing, incidental, sundries etc. L.S. = Tk. 171.41
Total = Tk. 4,990.61
Profit 10.00% = Tk. 499.06
Overhead 3.50% = Tk. 174.67
= Tk. 5,664.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 329.67
Grand total = Tk. 5,994.01
Rate per sft. = Tk. 204.92
Rate per sqm. = Tk. 2,205.76

Say Tk. 2,206 .00 per sqm.

Item No.- 13.6


Analysis of PWD SoR 2014 for Civil Works 256

Supply, fitting & fixing window grills made of 25 x 3 mm F. I. Bar

For 1 No window grill


Considering : 7'-6"X 4'-6" = 33.75 sft
a) Cost of Materials
i) 25mm x 3mm F.I. bars @ 0.43 lbs per rft
Horizontal 4 X 7'-6' = 30.00 rft
2 X 6'-8' = 13.33 "
4X 6 X 1'-5' = 34.00 "
8X 4'-6' = 36.00 "
2X 9 X 5.66' = 8.50 "
= 121.83 rft
Add 5% wastage= 6.09 "
= 127.92 rft
= 55.00 lbs @ Tk. 25.40 Per lb = Tk. 1,397.00
b) Workshop charge
Labour cost manufacturing, welding including supply of necessary electrode, cutting steel to required sizes etc. complete
33.75 sft @ Tk. 45.71 Per sft = Tk. 1,542.71
c) Labour charges:
i) Mason 0.7 No. @ Tk. 389.00 Each = Tk. 272.30
i) Skilled labour 0.7 No. @ Tk. 303.00 Each = Tk. 212.10
d) Cost of M.S. Clamp 24 Nos @ Tk. 28.00 Each = Tk. 672.00
e) Cost of CC curing incidental sunrays etc. L.S. = Tk. 100.00
f) Carriage charge for steel materials from market to worshop and carrying the window grill form workshop to building
L.S. = Tk. 100.00
= Tk. 4,296.11
Profit 10.00% = Tk. 429.61
Overhead 3.50% = Tk. 150.36
= Tk. 4,876.08
Add VAT with adjustment factor 1.0582 4.50% = Tk. 232.19
Grand total = Tk. 5,108.27
Rate per sft. = Tk. 151.36
Rate per sqm. = Tk. 1,629.24

Say, Tk. 1,629 .00 Per sqm.

Item No.- 13.7


Supply, fitting & fixing verendah grills made of 3/8" dia M.S. rod @ 4" c/c both
ways fitted with M.S. angle 1" x 1" x 1/4" outer angle.
For 1 No. verendah grill
Considering 8'-0" x 4'-0" = 32 sft. of work
(a) Materials:
(i) 1" x 1" x 1/4" M.S. angle (@ 1.49 Ibs per rft.) for outer frame:
2 x 8'-0" + 2 x 4'-0" = 24 rft.
Add wastage 5%= 1.2 rft.
= 25.2 rft.
= 37.55 Ibs. @ Tk. 28.34 Per Ib. = Tk. 1,064.17
(ii) 3/8" dia M.S. rod (@ 0.376 Ibs per rft.) for inner members:
Vertical: 23 x 4'-0" = 92 rft.
Horizontal: 11 x 8'-0" = 88 rft.
= 180 rft.
Add wastage 5%= 9 rft.
= 189.00 rft.
= 71.06 Ibs. @ Tk. 26.76 Per Ib. = Tk. 1,901.57
(ii) Cost of F.I. bar clamps: 6" long 8.00 Nos. @ Tk. 28.00 each = Tk. 224.00
(b) Workshop charge:
Labour cost for manufacturing, welding including
Analysis of PWD SoR 2014 for Civil Works 257

supply of necessary electrode, cutting steel to


required sizes etc. complete. 32 sft. @ Tk. 45.71 Per sft. Tk. 1,462.72
(c) Labour charges:
Labour charges for fitting and fixing in position of grills
(i) Skilled labour 0.50 No. @ Tk. 303.00 each = Tk. 151.50
(ii) Mason 0.50 Nos. @ Tk. 389.00 each = Tk. 194.50
(d) Cost of CC (1:2:4) in/c mending good the damages:
8 x 0'-6" x 0'-6" x 0'-3" = 0.5 cft. @ Tk. 176.37 Per cft. = Tk. 88.19
(e) Carriage charge for steel materials from market to
workshop and carrying the window grill from
workshop to building site. 1 No. @ Tk. 61.25 each = Tk. 61.25
Total = Tk. 5,147.90
Profit 10.00% = Tk. 514.79
Overhead 3.50% = Tk. 180.18
= Tk. 5,842.87
Add VAT with adjustment factor 1.0582 5.50% = Tk. 340.06
Grand total = Tk. 6,182.93
Rate per sft. = Tk. 193.22
Rate per sqm. = Tk. 2,079.82

Say, Tk. 2,080 .00 Per sqm.

Item No.- 13.8


Supply, fitting & fixing verendah grills made of 3/8" dia M.S. rod @ 3" c/c both
ways fitted with M.S. angle 1" x 1" x 1/4" outer angle frame.
For 1 No. verendah grill
Considering 8'-0" x 4'-0" = 32 sft. of work
(a) Materials:
(i) 1" x 1" x 1/4" M.S. angle (@ 1.49 Ibs per rft.) for outer frame:
2 x 8'-0" + 2 x 4'-0" = 24 rft.
Add wastage 5%= 1.2 rft.
= 25.2 rft.
= 37.55 Ibs. @ Tk. 28.34 Per Ib. = Tk. 1,064.17
(ii) 3/8" dia M.S. rod (@ 0.376 Ibs per rft.)for inner members:
Vertical: 31 x 4'-0" = 124 rft.
Horizontal: 15 x 8'-0" = 120 rft.
= 244 rft.
Add wastage 5%= 12.2 rft.
= 256.20 rft.
= 96.33 Ibs. @ Tk. 26.76 Per Ib. = Tk. 2,577.79
(iii) Cost of F.I. bar clamps: 6" long 8.00 Nos. @ Tk. 28.00 each = Tk. 224.00
(b) Workshop charge:
Labour cost for manufacturing, welding
including supply of necessary electrode, cutting
steel to required sizes etx complete. 32 sft. @ Tk. 45.71 Per sft. Tk. 1,462.72
(c) Labour charges:
Labour charges for fitting and fixing in position of grills
(i) Skilled labour 0.50 No. @ Tk. 303.00 each = Tk. 151.50
(ii) Mason 0.50 Nos. @ Tk. 389.00 each = Tk. 194.50
(d) Cost of CC (1:2:4) in/c mending good the damages:
8 x 0'-6" x 0'-6" x 0'-3" = 0.5 cft. @ Tk. 176.37 Per cft. = Tk. 88.19
(e) Carriage charge for steel materials from market to
workshop and carrying the window grill from
workshop to building site. 1 No. @ Tk. 61.25 each = Tk. 61.25
Total = Tk. 5,824.12
Profit 10.00% = Tk. 582.41
Overhead 3.50% = Tk. 203.84
Analysis of PWD SoR 2014 for Civil Works 258

= Tk. 6,610.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 384.73
Grand total = Tk. 6,995.10
Rate per sft. = Tk. 218.60
Rate per sqm. = Tk. 2,353.01

Say, Tk. 2,353 .00 Per sqm.

DIVISION 14 : ALUMINIUM DOOR, WINDOW FRAME, TINTED GLASS


Item No.- 14.1.1
Supplying, fitting and fixing Aluminium Swing door with spandrel (S.S colour)
Considering 1 No. door
Considering: 4'-0" x 6'-10"= 27.32 sft. of work
(A) Cost of aluminium section:
1. 101.60 mm, 44.45 mm wall frame of 1.2 mm thick
2 x 6'-10" = 13.66 rft. @ Tk. 119.70 Per rft. = Tk. 1,635.10
2. 54 mm, 46 mm wall frame of 1.8 mm shutter side of 2.3 mm thick
2 x 6'-10" = 13.66 rft. @ Tk. 132.30 Per rft. = Tk. 1,807.22
3. 16.54 mm, 15.49 mm door glass bit of 0.99 mm thick
2 x 2 x 6'-1"= 24.32 rft.
2 x 4 x 3'-3"= 26.00 rft.
= 50.32 rft. @ Tk. 16.80 Per rft. = Tk. 845.38
4. 101.54 mm, 42.93 mm closure section of 1.8 mm thick
1 x 3'-81/2"= 3.71 rft. @ Tk. 126.00 Per rft. = Tk. 467.46
5. 101.60 mm closure cover of 1.5 mm thick
1 x 3'-81/2"= 3.71 rft. @ Tk. 48.30 Per rft. = Tk. 179.19
6. 101.60 mm, 12.70 mm floor bottom of 4 mm thick
1 x 3'-81/2"= 3.71 rft. @ Tk. 135.45 Per rft. = Tk. 502.52
7. 82.60 mm, 43.99 mm shutter bottom of 1.8 mm thick
1 x 3'-4"= 3.33 rft. @ Tk. 161.70 Per rft. = Tk. 538.46
8. 51 mm, 43.99 mm shutter top of 1.8 mm thick
1 x 3'-4"= 3.33 rft. @ Tk. 132.30 Per rft. = Tk. 440.56
9. 101.60 mm, 38.10 mm, 25.4 mm handle (short) of 2.3 mm, 2.3 mm, 4.01 mm thick
2 x 0'-9"= 1.5 rft. @ Tk. 178.50 Per rft. = Tk. 267.75
10 31.75 mm shutter divider of 1.2 mm thick
1 x 3'-4"= 3.33 rft. @ Tk. 64.05 Per rft. = Tk. 213.29
11 7.14 mm spandrel of 1.4 mm to 1.2 mm thick
1 x 20'-0" = 20 rft. @ Tk. 72.45 Per rft. = Tk. 1,449.00
= Tk. 8,345.93
Cutting wastage 3% = Tk. 250.38
Sub total (A) = Tk. 8,596.31
(B) Accessories:
1) Swing door closer 1 set. @ Tk. 2,627.03 Per set = Tk. 2,627.03
2) Swing door lock 1 set. @ Tk. 572.70 Per set = Tk. 572.70
3) Swing door mohiar 13.66 rft. @ Tk. 4.25 Per rft. = Tk. 58.06
4) Bolts and screws in/c sealants L.S. = Tk. 225.72
Sub total (B) = Tk. 3,483.51
(C) Labour charge for fabrication, assembling and fitting-fixing in position
1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
Analysis of PWD SoR 2014 for Civil Works 259

2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
3) Tools and plant, sundries etc. L.S. = Tk. 180.00
Sub total (C) = Tk. 1,042.50
Total (A+B+C) = Tk. 13,122.32
Profit 10.00% = Tk. 1,312.23
Overhead 3.50% = Tk. 459.28
= Tk. 14,893.83
Add VAT with adjustment factor 1.0582 4.50% = Tk. 709.23
Grand total = Tk. 15,603.06
Rate Per sft. = Tk. 571.12
Rate per sqm. = Tk. 6,147.54
Say, Tk. 6,148 .00 Per sqm.
Analysis of PWD SoR 2014 for Civil Works 260

Item No.- 14.1.2


Supplying, fitting and fixing Aluminium Swing door with spandrel (Bronze colour)
Considering 1 No. door
Considering: 4'-0" x 6'-10"= 27.32 sft. of work
(A) Cost of aluminium section:
1. 101.60 mm, 44.45 mm wall frame of 1.2 mm thick
2 x 6'-10" = 13.66 rft. @ Tk. 117.60 Per rft. = Tk. 1,606.42
2. 54 mm, 46 mm wall frame of 1.8 mm shutter side of 2.3 mm thick
2 x 6'-10" = 13.66 rft. @ Tk. 130.20 Per rft. = Tk. 1,778.53
3. 16.54 mm, 15.49 mm door glass bit of 0.99 mm thick
2 x 2 x 6'-1"= 24.32 rft.
2 x 4 x 3'-3"= 26.00 rft.
= 50.32 rft. @ Tk. 15.75 Per rft. = Tk. 792.54
4. 101.54 mm, 42.93 mm closure section of 1.8 mm thick
1 x 3'-81/2"= 3.71 rft. @ Tk. 123.90 Per rft. = Tk. 459.67
5. 101.60 mm closure cover of 1.5 mm thick
1 x 3'-81/2"= 3.71 rft. @ Tk. 47.25 Per rft. = Tk. 175.30
6. 101.60 mm, 12.70 mm floor bottom of 4 mm thick
1 x 3'-81/2"= 3.71 rft. @ Tk. 133.35 Per rft. = Tk. 494.73
7. 82.60 mm, 43.99 mm shutter bottom of 1.8 mm thick
1 x 3'-4"= 3.33 rft. @ Tk. 158.55 Per rft. = Tk. 527.97
8. 51 mm, 43.99 mm shutter top of 1.8 mm thick
1 x 3'-4"= 3.33 rft. @ Tk. 130.20 Per rft. = Tk. 433.57
9. 101.60 mm, 38.10 mm, 25.4 mm handle (short) of 2.3 mm, 2.3 mm, 4.01 mm thick
2 x 0'-9"= 1.5 rft. @ Tk. 175.35 Per rft. = Tk. 263.03
10 31.75 mm shutter divider of 1.2 mm thick
1 x 3'-4"= 3.33 rft. @ Tk. 63.00 Per rft. = Tk. 209.79
11 7.14 mm spandrel of 1.4 mm to 1.2 mm thick
1 x 20'-0" = 20 rft. @ Tk. 70.35 Per rft. = Tk. 1,407.00
= Tk. 8,148.55
Cutting wastage 3% = Tk. 244.46
Sub total (A) = Tk. 8,393.01
(B) Accessories:
1) Swing door closer 1 set. @ Tk. 2,627.03 Per set = Tk. 2,627.03
2) Swing door lock 1 set. @ Tk. 572.70 Per set = Tk. 572.70
3) Swing door mohiar 13.66 rft. @ Tk. 4.25 Per rft. = Tk. 58.06
4) Bolts and screws in/c sealants L.S. = Tk. 225.72
Sub total (B) = Tk. 3,483.51
(C) Labour charge for fabrication, assembling and fitting-fixing in position
1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
3) Tools and plant, sundries etc. L.S. = Tk. 180.00
Sub total (C) = Tk. 1,042.50
Total (A+B+C) = Tk. 12,919.02
Profit 10.00% = Tk. 1,291.90
Overhead 3.50% = Tk. 452.17
= Tk. 14,663.09
Add VAT with adjustment factor 1.0582 4.50% = Tk. 698.24
Grand total = Tk. 15,361.33
Rate Per sft. = Tk. 562.27
Rate per sqm. = Tk. 6,052.27
Say, Tk. 6,052 .00 Per sqm.
Analysis of PWD SoR 2014 for Civil Works 261

Item No.- 14.1.3


Supplying, fitting and fixing Aluminium Swing door with spandrel (Silver colour)
Considering 1 No. door
Considering: 4'-0" x 6'-10"= 27.32 sft. of work
(A) Cost of aluminium section:
1. 101.60 mm, 44.45 mm wall frame of 1.2 mm thick
2 x 6'-10" = 13.66 rft. @ Tk. 115.50 Per rft. = Tk. 1,577.73
2. 54 mm, 46 mm wall frame of 1.8 mm shutter side of 2.3 mm thick
2 x 6'-10" = 13.66 rft. @ Tk. 126.00 Per rft. = Tk. 1,721.16
3. 16.54 mm, 15.49 mm door glass bit of 0.99 mm thick
2 x 2 x 6'-1"= 24.32 rft.
2 x 4 x 3'-3"= 26.00 rft.
= 50.32 rft. @ Tk. 14.70 Per rft. = Tk. 739.70
4. 101.54 mm, 42.93 mm closure section of 1.8 mm thick
1 x 3'-81/2"= 3.71 rft. @ Tk. 120.75 Per rft. = Tk. 447.98
5. 101.60 mm closure cover of 1.5 mm thick
1 x 3'-81/2"= 3.71 rft. @ Tk. 46.20 Per rft. = Tk. 171.40
6. 101.60 mm, 12.70 mm floor bottom of 4 mm thick
1 x 3'-81/2"= 3.71 rft. @ Tk. 129.15 Per rft. = Tk. 479.15
7. 82.60 mm, 43.99 mm shutter bottom of 1.8 mm thick
1 x 3'-4"= 3.33 rft. @ Tk. 154.35 Per rft. = Tk. 513.99
8. 51 mm, 43.99 mm shutter top of 1.8 mm thick
1 x 3'-4"= 3.33 rft. @ Tk. 126.00 Per rft. = Tk. 419.58
9. 101.60 mm, 38.10 mm, 25.4 mm handle (short) of 2.3 mm, 2.3 mm, 4.01 mm thick
2 x 0'-9"= 1.5 rft. @ Tk. 147.00 Per rft. = Tk. 220.50
10 31.75 mm shutter divider of 1.2 mm thick
1 x 3'-4"= 3.33 rft. @ Tk. 60.90 Per rft. = Tk. 202.80
11 7.14 mm spandrel of 1.4 mm to 1.2 mm thick
1 x 20'-0" = 20 rft. @ Tk. 68.25 Per rft. = Tk. 1,365.00
= Tk. 7,858.99
Cutting wastage 3% = Tk. 235.77
Sub total (A) = Tk. 8,094.76
(B) Accessories:
1) Swing door closer 1 set. @ Tk. 2,627.03 Per set = Tk. 2,627.03
2) Swing door lock 1 set. @ Tk. 572.70 Per set = Tk. 572.70
3) Swing door mohiar 13.66 rft. @ Tk. 4.25 Per rft. = Tk. 58.06
4) Bolts and screws in/c sealants L.S. = Tk. 225.72
Sub total (B) = Tk. 3,483.51
(C) Labour charge for fabrication, assembling and fitting-fixing in position
1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
3) Tools and plant, sundries etc. L.S. = Tk. 180.00
Sub total (C) = Tk. 1,042.50
Total (A+B+C) = Tk. 12,620.77
Profit 10.00% = Tk. 1,262.08
Overhead 3.50% = Tk. 441.73
= Tk. 14,324.58
Add VAT with adjustment factor 1.0582 4.50% = Tk. 682.12
Grand total = Tk. 15,006.70
Rate Per sft. = Tk. 549.29
Rate per sqm. = Tk. 5,912.56
Say, Tk. 5,913 .00 Per sqm.
Analysis of PWD SoR 2014 for Civil Works 262

Item No.- 14.2.1


Supplying, fitting and fixing of aluminium swing door (S.S. colour)
Considering 1 No. door
Considering: 3'-6" x 7'-0"= 24.5 sft. of work
(A) Cost of aluminium section:
1. 101.60 mm, 44.45 mm wall frame of 1.5 mm thick
2 x 7'-0" = 14 rft. @ Tk. 119.70 Per rft. = Tk. 1,675.80
2. 54 mm, 46 mm of 1.8 mm shutter side
2.3 mm thick
2 x 7'-0" = 14 rft. @ Tk. 132.30 Per rft. = Tk. 1,852.20
3. 16.54 mm, 15.49 mm door glass bit
of 0.99 mm thick
2 x 2 x 7'-0"= 28 rft.
2 x 2 x 3'-6"= 14 rft.
= 42 rft. @ Tk. 16.80 Per rft. = Tk. 705.60
4. 101.54 mm, 42.93 mm closure section
of 1.8 mm thick
1 x 3'-3"= 3.25 rft. @ Tk. 126.00 Per rft. = Tk. 409.50
5. 101.60 mm closure cover
of 1.5 mm thick
1 x 3'-3"= 3.25 rft. @ Tk. 48.30 Per rft. = Tk. 156.98
6. 101.60 mm, 12.70 mm floor bottom
of 4 mm thick
1 x 3'-3"= 3.25 rft. @ Tk. 135.45 Per rft. = Tk. 440.21
7. 82.60 mm, 43.99 mm shutter bottom
of 1.8 mm thick
1 x 3'-0"= 3 rft. @ Tk. 161.70 Per rft. = Tk. 485.10
8. 51 mm, 43.99 mm shutter top
of 1.8 mm thick
1 x 3'-0"= 3 rft. @ Tk. 132.30 Per rft. = Tk. 396.90
9. 101.60 mm, 38.10 mm, 25.4 mm handle (short)
of 2.3 mm, 2.3 mm, 4.01 mm thick
1 x 1'-6"= 1.5 rft. @ Tk. 178.50 Per rft. = Tk. 267.75
= Tk. 6,390.04
Cutting wastage 3% = Tk. 191.70
Sub total (A) = Tk. 6,581.74
(B) Accessories:
(1) Swing door clouser 1 set @ Tk. 2,627.03 Per set = Tk. 2,627.03
(2) Swing door lock 1 set. @ Tk. 572.70 Per set = Tk. 572.70
(3) Swing door mohiar 14 rft. @ Tk. 4.25 Per rft. = Tk. 59.50
(4) Bolts and screws in/c sealants L.S. = Tk. 235.20
Sub total (B) = Tk. 3,494.43
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
(2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
(3) Tools and plant, sundries etc. L.S. = Tk. 367.50
Sub total (C) = Tk. 1,230.00
Total (A+B+C) = Tk. 11,306.17
Profit 10.00% = Tk. 1,130.62
Overhead 3.50% = Tk. 395.72
= Tk. 12,832.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 746.86
Grand total = Tk. 13,579.37
Rate Per sft. = Tk. 554.26
Rate per sqm. = Tk. 5,966.05
Say, Tk. 5,966 .00 Per sqm.
Item No.- 14.2.2
Analysis of PWD SoR 2014 for Civil Works 263

Supplying, fitting and fixing of aluminium swing door (bronze colour)


Considering 1 No. door
Considering: 3'-6" x 7'-0"= 24.5 sft. of work
(A) Cost of aluminium section:
1. 101.60 mm, 44.45 mm wall frame of 1.5 mm thick
2 x 7'-0" = 14 rft. @ Tk. 117.60 Per rft. = Tk. 1,646.40
2. 54 mm, 46 mm of 1.8 mm shutter side
2.3 mm thick
2 x 7'-0" = 14 rft. @ Tk. 130.20 Per rft. = Tk. 1,822.80
3. 16.54 mm, 15.49 mm door glass bit
of 0.99 mm thick
2 x 2 x 7'-0"= 28 rft.
2 x 2 x 3'-6"= 14 rft.
= 42 rft. @ Tk. 15.75 Per rft. = Tk. 661.50
4. 101.54 mm, 42.93 mm closure section
of 1.8 mm thick
1 x 3'-3"= 3.25 rft. @ Tk. 123.90 Per rft. = Tk. 402.68
5. 101.60 mm closure cover
of 1.5 mm thick
1 x 3'-3"= 3.25 rft. @ Tk. 47.25 Per rft. = Tk. 153.56
6. 101.60 mm, 12.70 mm floor bottom
of 4 mm thick
1 x 3'-3"= 3.25 rft. @ Tk. 133.35 Per rft. = Tk. 433.39
7. 82.60 mm, 43.99 mm shutter bottom
of 1.8 mm thick
1 x 3'-0"= 3 rft. @ Tk. 158.55 Per rft. = Tk. 475.65
8. 51 mm, 43.99 mm shutter top
of 1.8 mm thick
1 x 3'-0"= 3 rft. @ Tk. 130.20 Per rft. = Tk. 390.60
9. 101.60 mm, 38.10 mm, 25.4 mm handle (short)
of 2.3 mm, 2.3 mm, 4.01 mm thick
1 x 1'-6"= 1.5 rft. @ Tk. 175.35 Per rft. = Tk. 263.03
= Tk. 6,249.61
Cutting wastage 3% = Tk. 187.49
Sub total (A) = Tk. 6,437.10
(B) Accessories:
(1) Swing door clouser 1 set @ Tk. 2,627.03 Per set = Tk. 2,627.03
(2) Swing door lock 1 set. @ Tk. 572.70 Per set = Tk. 572.70
(3) Swing door mohiar 14 rft. @ Tk. 4.25 Per rft. = Tk. 59.50
(4) Bolts and screws in/c sealants L.S. = Tk. 235.20
Sub total (B) = Tk. 3,494.43
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
(2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
(3) Tools and plant, sundries etc. L.S. = Tk. 367.50
Sub total (C) = Tk. 1,230.00
Total (A+B+C) = Tk. 11,161.53
Profit 10.00% = Tk. 1,116.15
Overhead 3.50% = Tk. 390.65
= Tk. 12,668.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 737.31
Grand total = Tk. 13,405.64
Rate Per sft. = Tk. 547.17
Rate per sqm. = Tk. 5,889.74
Say, Tk. 5,890 .00 Per sqm.
Item No.- 14.2.3
Supplying, fitting and fixing of aluminium swing door (silver colour)
Analysis of PWD SoR 2014 for Civil Works 264

Considering 1 No. door


Considering: 3'-6" x 7'-0"= 24.5 sft. of work
(A) Cost of aluminium section:
1. 101.60 mm, 44.45 mm wall frame of 1.5 mm thick
2 x 7'-0" = 14 rft. @ Tk. 115.50 Per rft. = Tk. 1,617.00
2. 54 mm, 46 mm wall frame of 1.8 mm shutter side
of 2.3 mm thick
2 x 7'-0" = 14 rft. @ Tk. 126.00 Per rft. = Tk. 1,764.00
3. 16.54 mm, 15.49 mm door glass bit
of 0.99 mm thick
2 x 2 x 7'-0"= 28 rft.
2 x 2 x 3'-6"= 14 rft.
= 42 rft. @ Tk. 14.70 Per rft. = Tk. 617.40
4. 101.54 mm, 42.93 mm closure section
of 1.8 mm thick
1 x 3'-3"= 3.25 rft. @ Tk. 120.75 Per rft. = Tk. 392.44
5. 101.60 mm closure cover
of 1.5 mm thick
1 x 3'-3"= 3.25 rft. @ Tk. 46.20 Per rft. = Tk. 150.15
6. 101.60 mm, 12.70 mm floor bottom
of 4 mm thick
1 x 3'-3"= 3.25 rft. @ Tk. 129.15 Per rft. = Tk. 419.74
7. 82.60 mm, 43.99 mm shutter bottom
of 1.8 mm thick
1 x 3'-0"= 3 rft. @ Tk. 154.35 Per rft. = Tk. 463.05
8. 51 mm, 43.99 mm shutter top
of 1.8 mm thick
1 x 3'-0"= 3 rft. @ Tk. 126.00 Per rft. = Tk. 378.00
9. 101.60 mm, 38.10 mm, 25.4 mm handle (short)
of 2.3 mm, 2.3 mm, 4.01 mm thick
1 x 1'-6"= 1.5 rft. @ Tk. 170.10 Per rft. = Tk. 255.15
= Tk. 6,056.93
Cutting wastage 3% = Tk. 181.71
Sub total (A) = Tk. 6,238.64
(B) Accessories:
(1) Swing door clouser 1 set. @ Tk. 2,627.03 Per set = Tk. 2,627.03
(2) Swing door lock 1 set. @ Tk. 572.70 Per set = Tk. 572.70
(3) Swing door mohiar 14 rft. @ Tk. 4.25 Per rft. = Tk. 59.50
(4) Bolts and screws in/c sealants L.S. = Tk. 226.80
Sub total (B) = Tk. 3,486.03
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
(2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
(3) Tools and plant, sundries etc. L.S. = Tk. 367.50
Sub total (C) = Tk. 1,230.00
Total (A+B+C) = Tk. 10,954.67
Profit 10.00% = Tk. 1,095.47
Overhead 3.50% = Tk. 383.41
= Tk. 12,433.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 723.65
Grand total = Tk. 13,157.20
Rate Per sft. = Tk. 537.03
Rate per sqm. = Tk. 5,780.59
Say, Tk. 5,781 .00 Per sqm.
Item No.- 14.3.1
Supplying, fitting and fixing of aluminium composite swing door with fixed partition (S.S. colour)
Considering 1 No. door
Analysis of PWD SoR 2014 for Civil Works 265

Considering 15'-0" x 10'-0"= 150 sft. of work


(A) Cost of aluminium sections:
1. 101.60 mm, 44.45 mm wall frame
of 1.5 mm thick
2 x 10'-0" = 20 rft. @ Tk. 119.70 Per Rft. = Tk. 2,394.00
2. 54 mm, 46 mm shutter side
of 1.8 mm thick
4 x 7'-0" = 28 rft. @ Tk. 132.30 Per rft. = Tk. 3,704.40
3. 16.54 mm, 15.49 mm door glass bit
of 1.00 mm thick
2 x 3 x 7'-0"= 42 rft.
2 x 3 x 7'-0"= 42 rft.
= 84 rft. @ Tk. 16.80 Per Rft. = Tk. 1,411.20
4. 101.54 mm, 42.93 mm closure system
of 1.8 mm thick
1 x 7'-0"= 7 rft. @ Tk. 126.00 Per rft. = Tk. 882.00
5. 101.60 mm closure cover
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 48.30 Per rft. = Tk. 338.10
6. 101.60 mm, 12.70 mm floor bottom
of 4 mm thick
1 x 7'-0"= 7 rft. @ Tk. 135.45 Per rft. = Tk. 948.15
7. 51 mm, 43.99 mm shutter top
of 1.8 mm thick
1 x 7'-0"= 7 rft. @ Tk. 132.30 Per rft. = Tk. 926.10
8. 82.60 mm, 43.99 mm shutter bottom
of 1.8 mm thick
1 x 7'-0"= 7 rft. @ Tk. 161.70 Per rft. = Tk. 1,131.90
9. 101.60 mm, 38.10 mm, 25.4 mm handle (short)
of 2.3 mm, 2.3 mm, 4.01 mm thick
1 x 3'-0"= 3 rft. @ Tk. 178.50 Per rft. = Tk. 535.50
10. 101.60 mm, 44.45 mm top & side
of 1.5 mm thick
2 x 10'-0" = 20 rft.
1 x 15-0" = 15 rft.
1 x 3'-0"= 3 rft.
= 38 rft. @ Tk. 154.35 Per rft. = Tk. 5,865.30
11. 101.35 mm, 44.45 mm bottom
of 1.5 mm thick
2 x 8'-0"= 16 rft. @ Tk. 114.45 Per rft. = Tk. 1,831.20
12. 44.32 mm ,19.61 mm bottom cover
of 1.5 m thick
2 x 8'-0"= 16 @ Tk. 43.05 Per rft. = Tk. 688.80
13. 83.21 mm, 16.00 mm grouve cover
of 1.5 mm thick
2 x 8'-0"= 16 rft.
1 x 15-0" = 15 rft.
= 31 rft. @ Tk. 66.15 Per rft. = Tk. 2,050.65
14. 39.09 mm, 14.81 mm fixed glass protector
of 1.00 mm thick
1 x 7'-0"= 7 rft.
2 x 3'-0"= 6 rft.
= 13 rft. @ Tk. 26.25 Per rft. = Tk. 341.25
15. 15.75 mm, 14.81 mm fixed glass protector
bit of 0.99 mm thick
1 x 7'-0"= 7 rft.
2 x 3'-0"= 6 rft.
Analysis of PWD SoR 2014 for Civil Works 266

= 13 rft. @ Tk. 17.85 Per rft. = Tk. 232.05


= Tk. 23,280.60
Cutting wastage 3% = Tk. 698.42
Sub total (A) = Tk. 23,979.02
(B) Cost of accessories:
(1) Swing door clouser 2 sets @ Tk. 2,627.03 Per set = Tk. 5,254.06
(2) Swing door lock 1 set @ Tk. 572.70 Per set = Tk. 572.70
(3) Swing door mohiar 21 rft. @ Tk. 4.25 Per rft. = Tk. 89.25
(4) Flush bolt 2 sets @ Tk. 307.43 Per set. = Tk. 614.86
(5) Bolts and screws in/c sealants L.S. = Tk. 603.91
Sub total (B) = Tk. 7,134.78
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3 No. @ Tk. 700.00 each = Tk. 2,100.00
(2) Semi- skilled technician 3 No. @ Tk. 450.00 each = Tk. 1,350.00
(3) Tools and plant, sundries etc. L.S. = Tk. 1,225.00
Sub total (C) = Tk. 4,675.00
Total (A+B+C) = Tk. 35,788.80
Profit 10.00% = Tk. 3,578.88
Overhead 3.50% = Tk. 1,252.61
= Tk. 40,620.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,364.14
Grand total = Tk. 42,984.43
Rate Per sft. = Tk. 286.56
Rate per sqm. = Tk. 3,084.53

Say, Tk. 3,085 .00 Per sqm.

Item No.- 14.3.2


Supplying, fitting and fixing of aluminium composite swing door with fixed partition (bronze colour)
Considering 1 No. door
Considering 15'-0" x 10'-0"= 150 sft. of work
(A) Cost of aluminium sections:
1. 101.60 mm, 44.45 mm wall frame
of 1.5 mm thick
2 x 10'-0" = 20 rft. @ Tk. 117.60 Per Rft. = Tk. 2,352.00
2. 54 mm, 46 mm shutter side
of 1.8 mm thick
4 x 7'-0" = 28 rft. @ Tk. 130.20 Per rft. = Tk. 3,645.60
3. 16.54 mm, 15.49 mm door glass bit
of 1.00 mm thick
2 x 3 x 7'-0"= 42 rft.
2 x 3 x 7'-0"= 42 rft.
= 84 rft. @ Tk. 15.75 Per Rft. = Tk. 1,323.00
4. 101.54 mm, 42.93 mm closure system
of 1.8 mm thick
1 x 7'-0"= 7 rft. @ Tk. 123.90 Per rft. = Tk. 867.30
5. 101.60 mm closure cover
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 47.25 Per rft. = Tk. 330.75
6. 101.60 mm, 12.70 mm floor bottom
of 4 mm thick
1 x 7'-0"= 7 rft. @ Tk. 133.35 Per rft. = Tk. 933.45
7. 51 mm, 43.99 mm shutter top
of 1.8 mm thick
1 x 7'-0"= 7 rft. @ Tk. 130.20 Per rft. = Tk. 911.40
8. 82.60 mm, 43.99 mm shutter bottom
of 1.8 mm thick
Analysis of PWD SoR 2014 for Civil Works 267

1 x 7'-0"= 7 rft. @ Tk. 158.55 Per rft. = Tk. 1,109.85


9. 101.60 mm, 38.10 mm, 25.4 mm handle (short)
of 2.3 mm, 2.3 mm, 4.01 mm thick
1 x 3'-0"= 3 rft. @ Tk. 175.35 Per rft. = Tk. 526.05
10. 101.60 mm, 44.45 mm top & side
of 1.5 mm thick
2 x 10'-0" = 20 rft.
1 x 15-0" = 15 rft.
1 x 3'-0"= 3 rft.
= 38 rft. @ Tk. 151.20 Per rft. = Tk. 5,745.60
11. 101.35 mm, 44.45 mm bottom
of 1.5 mm thick
2 x 8'-0"= 16 rft. @ Tk. 112.35 Per rft. = Tk. 1,797.60
12. 44.32 mm ,19.61 mm bottom cover
of 1.5 m thick
2 x 8'-0"= 16 @ Tk. 42.00 Per rft. = Tk. 672.00
13. 83.21 mm, 16.00 mm grouve cover
of 1.5 mm thick
2 x 8'-0"= 16 rft.
1 x 15-0" = 15 rft.
= 31 rft. @ Tk. 65.10 Per rft. = Tk. 2,018.10
14. 39.09 mm, 14.81 mm fixed glass protector
of 1.00 mm thick
1 x 7'-0"= 7 rft.
2 x 3'-0"= 6 rft.
= 13 rft. @ Tk. 25.20 Per rft. = Tk. 327.60
15. 15.75 mm, 14.81 mm fixed glass protector
bit of 0.99 mm thick
1 x 7'-0"= 7 rft.
2 x 3'-0"= 6 rft.
= 13 rft. @ Tk. 16.80 Per rft. = Tk. 218.40
= Tk. 22,778.70
Cutting wastage 3% = Tk. 683.36
Sub total (A) = Tk. 23,462.06
(B) Cost of accessories:
(1) Swing door clouser 2 sets @ Tk. 2,627.03 Per set = Tk. 5,254.06
(2) Swing door lock 1 set @ Tk. 572.70 Per set = Tk. 572.70
(3) Swing door mohiar 21 rft. @ Tk. 4.25 Per rft. = Tk. 89.25
(4) Flush bolt 2 sets @ Tk. 307.43 Per set. = Tk. 614.86
(5) Bolts and screws in/c sealants L.S. = Tk. 603.91
Sub total (B) = Tk. 7,134.78
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3 No. @ Tk. 700.00 each = Tk. 2,100.00
(2) Semi- skilled technician 3 No. @ Tk. 450.00 each = Tk. 1,350.00
(3) Tools and plant, sundries etc. L.S. = Tk. 1,225.00
Sub total (C) = Tk. 4,675.00
Total (A+B+C) = Tk. 35,271.84
Profit 10.00% = Tk. 3,527.18
Overhead 3.50% = Tk. 1,234.51
= Tk. 40,033.53
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,329.99
Grand total = Tk. 42,363.52
Rate Per sft. = Tk. 282.42
Rate per sqm. = Tk. 3,039.97

Say, Tk. 3,040 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 268

Item No.- 14.3.3


Supplying, fitting and fixing of aluminium composite swing door with fixed partition (silver colour)
Considering 1 No. door
Considering 15'-0" x 10'-0"= 150 sft. of work
(A) Cost of aluminium sections:
1. 101.60 mm, 44.45 mm wall frame
of 1.5 mm thick
2 x 10'-0" = 20 rft. @ Tk. 115.50 Per Rft. = Tk. 2,310.00
2. 54 mm, 46 mm wall frame of 1.8 mm shutter
side of 1.8 mm thick
4 x 7'-0" = 28 rft. @ Tk. 126.00 Per rft. = Tk. 3,528.00
3. 16.54 mm, 15.49 mm door glass bit
of 0.99 mm thick
2 x 3 x 7'-0"= 42 rft.
2 x 3 x 7'-0"= 42 rft.
= 84 rft. @ Tk. 14.70 Per Rft. = Tk. 1,234.80
4. 101.54 mm, 42.93 mm closure section
of 1.8 mm thick
1 x 7'-0"= 7 rft. @ Tk. 120.75 Per rft. = Tk. 845.25
5. 101.60 mm closure cover
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 46.20 Per rft. = Tk. 323.40
6. 101.60 mm, 12.70 mm floor bottom
of 4 mm thick
1 x 7'-0"= 7 rft. @ Tk. 129.15 Per rft. = Tk. 904.05
7. 51 mm, 43.99 mm shutter top
of 1.8 mm thick
1 x 7'-0"= 7 rft. @ Tk. 126.00 Per rft. = Tk. 882.00
8. 82.60 mm, 43.99 mm shutter bottom
of 1.8 mm thick
1 x 7'-0"= 7 rft. @ Tk. 154.35 Per rft. = Tk. 1,080.45
9. 101.60 mm, 38.10 mm, 25.4 mm handle (short)
of 2.3 mm, 2.3 mm, 4.01 mm thick
1 x 3'-0"= 3 rft. @ Tk. 170.10 Per rft. = Tk. 510.30
10. 101.60 mm, 44.45 mm top & side
1.5 mm thick
2 x 10'-0" = 20 rft.
1 x 15-0" = 15 rft.
1 x 3'-0"= 3 rft.
= 38 rft. @ Tk. 147.00 Per rft. = Tk. 5,586.00
11. 101.35 mm, 44.45 mm bottom
of 1.5 mm thick
2 x 8'-0"= 16 rft. @ Tk. 109.20 Per rft. = Tk. 1,747.20
12. 44.32 mm, 19.61 mm bottom cover
of 1.5 m thick
2 x 8'-0"= 16 rft. @ Tk. 40.95 Per rft. = Tk. 655.20
13. 83.21 mm, 16.00 mm grouve cover
of 1.5 mm thick
2 x 8'-0"= 16 rft.
1 x 15-0" = 15 rft.
= 31 rft. @ Tk. 64.05 Per rft. = Tk. 1,985.55
14. 39.09 mm, 14.81 mm fixed glass protector
of 1.00 mm thick
1 x 7'-0"= 7 rft.
2 x 3'-0"= 6 rft.
= 13 rft. @ Tk. 24.15 Per rft. = Tk. 313.95
15. 15.75 mm, 14.81 mm fixed glass protector bit
Analysis of PWD SoR 2014 for Civil Works 269

of 0.99 mm thick
1 x 7'-0"= 7 rft.
2 x 3'-0"= 6 rft.
= 13 rft. @ Tk. 16.80 Per rft. = Tk. 218.40
= Tk. 22,124.55
Cutting wastage 3% = Tk. 663.74
Sub total (A) = Tk. 22,788.29
(B) Cost of accessories:
(1) Swing door clouser 2 sets @ Tk. 2,627.03 Per set = Tk. 5,254.06
(2) Swing door lock 1 set @ Tk. 572.70 Per set = Tk. 572.70
(3) Swing door mohiar 21 rft. @ Tk. 4.25 Per rft. = Tk. 89.25
(4) Flush bolt 2 sets @ Tk. 307.43 Per set. = Tk. 614.86
(5) Bolts and screws in/c sealants L.S. = Tk. 603.91
Sub total (B) = Tk. 7,134.78
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3 No. @ Tk. 700.00 each = Tk. 2,100.00
(2) Semi- skilled technician 3 No. @ Tk. 450.00 each = Tk. 1,350.00
(3) Tools and plant, sundries etc. L.S. = Tk. 1,225.00
Sub total (C) = Tk. 4,675.00
Total (A+B+C) = Tk. 34,598.07
Profit 10.00% = Tk. 3,459.81
Overhead 3.50% = Tk. 1,210.93
= Tk. 39,268.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,285.48
Grand total = Tk. 41,554.29
Rate Per sft. = Tk. 277.03
Rate per sqm. = Tk. 2,981.95

Say, Tk. 2,982 .00 Per sqm.

Item No.- 14.4.1


Supplying, fitting and fixing of aluminium sliding doors with 75.50 mm wide section &
locking arrangement (S.S. colour)
Considering 1 No. door
Considering 7'-0" x 7'-0"= 49 sft. of work
(A) Cost of aluminium sections
1. 75.50 mm, 17.79 mm outer bottom
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 63.00 Per rft. = Tk. 441.00
2. 75.5 mm, 26.8 mm outer top
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 88.20 Per rft. = Tk. 617.40
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 6'-9"= 6.75 rft. @ Tk. 58.80 Per rft. = Tk. 396.90
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 6'-9"= 6.75 rft. @ Tk. 84.00 Per rft. = Tk. 567.00
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 68.25 Per rft. = Tk. 955.50
6. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 77.70 Per rft. = Tk. 1,087.80
7. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 81.90 Per rft. = Tk. 1,146.60
Analysis of PWD SoR 2014 for Civil Works 270

8. 31.75 mm shutter divider


of 1.5 mm thick
1 x 6'-9"= 6.75 rft. @ Tk. 64.05 Per rft. = Tk. 432.34
= Tk. 5,644.54
Cutting wastage 3% = Tk. 169.34
Sub total (A) = Tk. 5,813.88
(B) Cost of accessories:
(1) Sliding door key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding door wheel 4 No. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding door mohiar 50 rft. @ Tk. 1.36 Per rft. = Tk. 68.00
(4) Sliding door neoprene 50 rft. @ Tk. 2.73 Per rft. = Tk. 136.50
(5) Bolts and screws in/c sealants L.S. = Tk. 68.25
Sub total (B) = Tk. 791.75
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2 No. @ Tk. 700.00 each = Tk. 1,400.00
(2) Semi- skilled technician 2 No. @ Tk. 450.00 each = Tk. 900.00
(3) Tools and plant, sundries etc. L.S. = Tk. 367.50
Sub total (C) = Tk. 2,667.50
Total (A+B+C) = Tk. 9,273.13
Profit 10.00% = Tk. 927.31
Overhead 3.50% = Tk. 324.56
= Tk. 10,525.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 612.57
Grand total = Tk. 11,137.57
Rate Per sft. = Tk. 227.30
Rate per sqm. = Tk. 2,446.66

Say, Tk. 2,447 .00 Per sqm.

Item No.- 14.4.2


Supplying, fitting and fixing of aluminium sliding doors with 75.50 mm wide section &
locking arrangement (bronze colour)
Considering 1 No. door
Considering 7'-0" x 7'-0"= 49 sft. of work
(A) Cost of aluminium sections
1. 75.50 mm, 17.79 mm outer bottom
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 61.95 Per rft. = Tk. 433.65
2. 75.5 mm, 26.8 mm outer top
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 86.10 Per rft. = Tk. 602.70
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 6'-9"= 6.75 rft. @ Tk. 57.75 Per rft. = Tk. 389.81
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 6'-9"= 6.75 rft. @ Tk. 81.90 Per rft. = Tk. 552.83
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 67.20 Per rft. = Tk. 940.80
6. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 75.60 Per rft. = Tk. 1,058.40
7. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 79.80 Per rft. = Tk. 1,117.20
8. 31.75 mm shutter divider
Analysis of PWD SoR 2014 for Civil Works 271

of 1.5 mm thick
1 x 6'-9"= 6.75 rft. @ Tk. 63.00 Per rft. = Tk. 425.25
= Tk. 5,520.64
Cutting wastage 3% = Tk. 165.62
Sub total (A) = Tk. 5,686.26
(B) Cost of accessories:
(1) Sliding door key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding door wheel 4 No. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding door mohiar 50 rft. @ Tk. 1.36 Per rft. = Tk. 68.00
(4) Sliding door neoprene 50 rft. @ Tk. 2.73 Per rft. = Tk. 136.50
(5) Bolts and screws in/c sealants L.S. = Tk. 68.25
Sub total (B) = Tk. 791.75
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2 No. @ Tk. 700.00 each = Tk. 1,400.00
(2) Semi- skilled technician 2 No. @ Tk. 450.00 each = Tk. 900.00
(3) Tools and plant, sundries etc. L.S. = Tk. 367.50
Sub total (C) = Tk. 2,667.50
Total (A+B+C) = Tk. 9,145.51
Profit 10.00% = Tk. 914.55
Overhead 3.50% = Tk. 320.09
= Tk. 10,380.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 604.14
Grand total = Tk. 10,984.29
Rate Per sft. = Tk. 224.17
Rate per sqm. = Tk. 2,412.97

Say, Tk. 2,413 .00 Per sqm.

Item No.- 14.4.3


Supplying, fitting and fixing of aluminium sliding doors with 75.50 mm wide section &
locking arrangement (silver colour)
Considering 1 No. door
Considering 7'-0" x 7'-0"= 49 sft. of work
(A) Cost of aluminium sections
1. 75.50 mm, 17.79 mm outer bottom
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 58.80 Per rft. = Tk. 411.60
2. 75.5 mm, 26.8 mm outer top
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 82.95 Per rft. = Tk. 580.65
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 6'-9"= 6.75 rft. @ Tk. 55.65 Per rft. = Tk. 375.64
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 6'-9"= 6.75 rft. @ Tk. 79.80 Per rft. = Tk. 538.65
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 65.10 Per rft. = Tk. 911.40
6. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 73.50 Per rft. = Tk. 1,029.00
7. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 77.70 Per rft. = Tk. 1,087.80
8. 31.75 mm shutter divider
of 1.5 mm thick
Analysis of PWD SoR 2014 for Civil Works 272

1 x 6'-9"= 6.75 rft. @ Tk. 60.90 Per rft. = Tk. 411.08


= Tk. 5,345.82
Cutting wastage 3% = Tk. 160.37
Sub total (A) = Tk. 5,506.19
(B) Cost of accessories:
(1) Sliding door key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding door wheel 4 No. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding door mohiar 50 rft. @ Tk. 1.36 Per rft. = Tk. 68.00
(4) Sliding door neoprene 50 rft. @ Tk. 2.73 Per rft. = Tk. 136.50
(5) Bolts and screws in/c sealants L.S. = Tk. 68.25
Sub total (B) = Tk. 791.75
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2 No. @ Tk. 700.00 each = Tk. 1,400.00
(2) Semi- skilled technician 2 No. @ Tk. 450.00 each = Tk. 900.00
(3) Tools and plant, sundries etc. L.S. = Tk. 367.50
Sub total (C) = Tk. 2,667.50
Total (A+B+C) = Tk. 8,965.44
Profit 10.00% = Tk. 896.54
Overhead 3.50% = Tk. 313.79
= Tk. 10,175.77
Add VAT with adjustment factor 1.0582 5.50% = Tk. 592.24
Grand total = Tk. 10,768.01
Rate Per sft. = Tk. 219.76
Rate per sqm. = Tk. 2,365.50

Say, Tk. 2,366 .00 Per sqm.

Item No.- 14.5.1


Supplying, fitting and fixing of aluminium sliding doors with 75.50 mm wide section &
locking arrangement (S.S. colour)
Considering 1 No. door
Considering 6'-0" x 7'-0" = 42 sft. of work
(A) Cost of aluminium sections
1. 75.50 mm, 17.79 mm outer bottom
of 1.5 mm thick
1 x 6'-0"= 6 rft. @ Tk. 63.00 Per rft. = Tk. 378.00
2. 75.5 mm, 26.8 mm outer top
of 1.5 mm thick
1 x 6'-0"= 6 rft. @ Tk. 88.20 Per rft. = Tk. 529.20
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 5'-9"= 5.75 rft. @ Tk. 58.80 Per rft. = Tk. 338.10
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 5'-9"= 5.75 rft. @ Tk. 84.00 Per rft. = Tk. 483.00
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 68.25 Per rft. = Tk. 955.50
6. 31.00 mm, 26.00 mm sliding fixed side
of 1.5 mm thick
1 x 7"= 7 Rft. @ Tk. 49.35 Per rft. = Tk. 345.45
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 77.70 Per rft. = Tk. 543.90
8. 34.40 mm, 32.10 mm interlock
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 81.90 Per rft. = Tk. 1,146.60
Analysis of PWD SoR 2014 for Civil Works 273

9. 31.75 mm shutter divider


of 1.5 mm thick
1 x 5'-9"= 5.75 rft. @ Tk. 64.05 Per rft. = Tk. 368.29
10. 7.14 mm spandrel of 1.4 mm to
1.5 mm thick
12 x 2'-6" = 30 rft. @ Tk. 72.45 Per rft. = Tk. 2,173.50
= Tk. 7,261.54
Cutting wastage 3% = Tk. 217.85
Sub total (A) = Tk. 7,479.39
(B) Cost of accessories:
(1) Sliding door key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 46 rft. @ Tk. 1.36 Per rft. = Tk. 62.56
(4) Sliding door neoprene 52 rft. @ Tk. 2.73 Per rft. = Tk. 141.96
(5) Bolts and screws in/c sealants L.S. = Tk. 54.65
Sub total (B) = Tk. 691.65
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2 No. @ Tk. 700.00 each = Tk. 1,400.00
(2) Semi- skilled technician 2 No. @ Tk. 450.00 each = Tk. 900.00
(3) Tools and plant, sundries etc. L.S. = Tk. 367.50
Sub total (C) = Tk. 2,667.50
Total (A+B+C) = 10,838.54
Profit 10.00% = Tk. 1,083.85
Overhead 3.50% = Tk. 379.35
= Tk. 12,301.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 715.97
Grand total = Tk. 13,017.71
Rate Per sft. = Tk. 309.95
Rate per sqm. = Tk. 3,336.30

Say, Tk. 3,336 .00 Per sqm.

Item No.- 14.5.2


Supplying, fitting and fixing of aluminium sliding doors with 75.50 mm wide section &
locking arrangement (bronze colour)
Considering 1 No. door
Considering 6'-0" x 7'-0" = 42 sft. of work
(A) Cost of aluminium sections
1. 75.50 mm, 17.79 mm outer bottom
of 1.5 mm thick
1 x 6'-0"= 6 rft. @ Tk. 61.95 Per rft. = Tk. 371.70
2. 75.5 mm, 26.8 mm outer top
of 1.5 mm thick
1 x 6'-0"= 6 rft. @ Tk. 86.10 Per rft. = Tk. 516.60
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 5'-9"= 5.75 rft. @ Tk. 57.75 Per rft. = Tk. 332.06
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 5'-9"= 5.75 rft. @ Tk. 81.90 Per rft. = Tk. 470.93
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 67.20 Per rft. = Tk. 940.80
6. 31.00 mm, 26.00 mm sliding fixed side
of 1.5 mm thick
1 x 7"= 7 Rft. @ Tk. 48.30 Per rft. = Tk. 338.10
7. 49.20 mm, 26.20 mm shutter lock
Analysis of PWD SoR 2014 for Civil Works 274

of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 75.60 Per rft. = Tk. 529.20
8. 34.40 mm, 32.10 mm interlock
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 79.80 Per rft. = Tk. 1,117.20
9. 31.75 mm shutter divider
of 1.5 mm thick
1 x 5'-9"= 5.75 rft. @ Tk. 63.00 Per rft. = Tk. 362.25
10. 7.14 mm spandrel of 1.4 mm to
1.5 mm thick
12 x 2'-6" = 30 rft. @ Tk. 70.35 Per rft. = Tk. 2,110.50
= Tk. 7,089.34
Cutting wastage 3% = Tk. 212.68
Sub total (A) = Tk. 7,302.02
(B) Cost of accessories:
(1) Sliding door key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 46 rft. @ Tk. 1.36 Per rft. = Tk. 62.56
(4) Sliding door neoprene 52 rft. @ Tk. 2.73 Per rft. = Tk. 141.96
(5) Bolts and screws in/c sealants L.S. = Tk. 54.65
Sub total (B) = Tk. 691.65
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2 No. @ Tk. 700.00 each = Tk. 1,400.00
(2) Semi- skilled technician 2 No. @ Tk. 450.00 each = Tk. 900.00
(3) Tools and plant, sundries etc. L.S. = Tk. 367.50
Sub total (C) = Tk. 2,667.50
Total (A+B+C) = 10,661.17
Profit 10.00% = Tk. 1,066.12
Overhead 3.50% = Tk. 373.14
= Tk. 12,100.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 704.26
Grand total = Tk. 12,804.69
Rate Per sft. = Tk. 304.87
Rate per sqm. = Tk. 3,281.62

Say, Tk. 3,282 .00 Per sqm.

Item No.- 14.5.3


Supplying, fitting and fixing of aluminium sliding doors with 75.50mm wide section &
locking arrangement (silver colour)
Considering 1 No. door
Considering 6'-0" x 7'-0" = 42 sft. of work
(A) Cost of aluminium sections
1. 75.50 mm, 17.79 mm outer bottom
of 1.5 mm thick
1 x 6'-0"= 6 rft. @ Tk. 58.80 Per rft. = Tk. 352.80
2. 75.5 mm, 26.8 mm outer top
of 1.5 mm thick
1 x 6'-0"= 6 rft. @ Tk. 82.95 Per rft. = Tk. 497.70
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 5'-9"= 5.75 rft. @ Tk. 55.65 Per rft. = Tk. 319.99
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 5'-9"= 5.75 rft. @ Tk. 79.80 Per rft. = Tk. 458.85
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
Analysis of PWD SoR 2014 for Civil Works 275

2 x 7'-0"= 14 rft. @ Tk. 65.10 Per rft. = Tk. 911.40


6. 31.00 mm, 26.00 mm sliding fixed side
of 1.5 mm thick
1 x 7"= 7 Rft. @ Tk. 46.20 Per rft. = Tk. 323.40
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 7'-0"= 7 rft. @ Tk. 73.50 Per rft. = Tk. 514.50
8. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick
2 x 7'-0"= 14 rft. @ Tk. 77.70 Per rft. = Tk. 1,087.80
9. 31.75 mm shutter divider
of 1.5 mm thick
1 x 5'-9"= 5.75 rft. @ Tk. 60.90 Per rft. = Tk. 350.18
10. 7.14 mm spandrel of 1.4 mm
to 1.5 mm thick
12 x 2'-6"= 30 rft. @ Tk. 68.25 Per rft. = Tk. 2,047.50
= Tk. 6,864.12
Cutting wastage 3% = Tk. 205.92
Sub total (A) = Tk. 7,070.04
(B) Cost of accessories:
(1) Sliding door key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 46 rft. @ Tk. 1.36 Per rft. = Tk. 62.56
(4) Sliding neoprene 52 rft. @ Tk. 2.73 Per rft. = Tk. 141.96
(5) Bolts and screws in/c sealants L.S. = Tk. 97.01
Sub total (B) = Tk. 734.01
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2 No. @ Tk. 700.00 each = Tk. 1,400.00
(2) Semi- skilled technician 2 No. @ Tk. 450.00 each = Tk. 900.00
(3) Tools and plant, sundries etc. L.S. = Tk. 367.50
Sub total (C) = Tk. 2,667.50
Total (A+B+C) = 10,471.55
Profit 10.00% = Tk. 1,047.16
Overhead 3.50% = Tk. 366.50
= Tk. 11,885.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 691.73
Grand total = Tk. 12,576.94
Rate Per sft. = Tk. 299.45
Rate per sqm. = Tk. 3,223.28

Say, Tk. 3,223 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 276

Item No.- 14.6.1.1


Supplying, fitting and fixing aluminium sliding window frame and shutter (S.S. colour)
Considering 1 No. window
Considering 5'-0" x 4'-6" = 22.5 sft. of work
(A) Cost of aluminium sections:
1. 75.50 mm, 32 mm outer bottom (high)
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 80.85 Per rft. = Tk. 404.25
2. 75.5 mm, 26.80 mm outer top
of 1.5 mm thick
1x 5'-0"= 5 rft. @ Tk. 88.20 Per rft. = Tk. 441.00
3. 33 mm, 26.80mm, 22 mm shutter top
of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 58.80 Per rft. = Tk. 279.30
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 84.00 Per rft. Tk. 399.00
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 68.25 Per rft. = Tk. 614.25
6. 31.00 mm, 26.00 mm sliding fixed side
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 49.35 Per rft. = Tk. 222.08
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 77.70 Per rft. = Tk. 349.65
8. 34.40 mm, 32.10 mm inter-lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 81.90 Per rft. = Tk. 737.10
= Tk. 3,446.63
Cutting wastage 3% = Tk. 103.40
Total (A) = Tk. 3,550.03
(B) Cost of accessories:
(1) Sliding door key lock 1 set @ Tk. 67.28 Per set. = Tk. 67.28
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 33 rft. @ Tk. 1.36 Per rft. = Tk. 44.88
(4) Sliding neoprene 28 rft. @ Tk. 2.73 Per rft. = Tk. 76.44
(5) Bolts and screws in/c sealants L.S. = Tk. 52.88
Total (B) = Tk. 328.00
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1/2 No. @ Tk. 700.00 each = Tk. 350.00
(2) Semi- skilled technician 1/2 No. @ Tk. 450.00 each = Tk. 225.00
(3) Tools and plant, sundries etc. L.S. = Tk. 294.00
Sub total (C) = Tk. 869.00
Total (A+B+C) = 4,747.03
Profit 10.00% = Tk. 474.70
Overhead 3.50% = Tk. 166.15
= Tk. 5,387.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 313.58
Grand total = Tk. 5,701.46
Rate Per sft. = Tk. 253.40
Rate per sqm. = Tk. 2,727.60

Say, Tk. 2,728 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 277

Item No.- 14.6.1.2


Supplying, fitting and fixing aluminium sliding window frame and shutter (bronze colour)
Considering 1 No. window
Considering 5'-0" x 4'-6" = 22.5 sft. of work
(A) Cost of aluminium sections:
1. 75.50 mm, 32 mm outer bottom (high)
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 78.75 Per rft. = Tk. 393.75
2. 75.5 mm, 26.80 mm outer top
of 1.5 mm thick
1x 5'-0"= 5 rft. @ Tk. 86.10 Per rft. = Tk. 430.50
3. 33 mm, 26.80mm, 22 mm shutter top
of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 57.75 Per rft. = Tk. 274.31
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 81.90 Per rft. Tk. 389.03
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 67.20 Per rft. = Tk. 604.80
6. 31.00 mm, 26.00 mm sliding fixed side
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 48.30 Per rft. = Tk. 217.35
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 75.60 Per rft. = Tk. 340.20
8. 34.40 mm, 32.10 mm inter-lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 79.80 Per rft. = Tk. 718.20
= Tk. 3,368.14
Cutting wastage 3% = Tk. 101.04
Total (A) = Tk. 3,469.18
(B) Cost of accessories:
(1) Sliding door key lock 1 set @ Tk. 67.28 Per set. = Tk. 67.28
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 33 rft. @ Tk. 1.36 Per rft. = Tk. 44.88
(4) Sliding neoprene 28 rft. @ Tk. 2.73 Per rft. = Tk. 76.44
(5) Bolts and screws in/c sealants L.S. = Tk. 52.88
Total (B) = Tk. 328.00
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1/2 No. @ Tk. 700.00 each = Tk. 350.00
(2) Semi- skilled technician 1/2 No. @ Tk. 450.00 each = Tk. 225.00
(3) Tools and plant, sundries etc. L.S. = Tk. 294.00
Sub total (C) = Tk. 869.00
Total (A+B+C) = 4,666.18
Profit 10.00% = Tk. 466.62
Overhead 3.50% = Tk. 163.32
= Tk. 5,296.12
Add VAT with adjustment factor 1.0582 5.50% = Tk. 308.24
Grand total = Tk. 5,604.36
Rate Per sft. = Tk. 249.08
Rate per sqm. = Tk. 2,681.10

Say, Tk. 2,681 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 278

Item No.- 14.6.1.3


Supplying, fitting and fixing aluminium sliding window frame and shutter (silver colour)
Considering 1 No. window
Considering 5'-0" x 4'-6" = 22.5 sft. of work
(A) Cost of aluminium sections:
1. 75.50 mm, 32 mm outer bottom (high)
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 76.65 Per rft. = Tk. 383.25
2. 75.5 mm, 26.80 mm outer top
of 1.5 mm thick
1x 5'-0"= 5 rft. @ Tk. 82.95 Per rft. = Tk. 414.75
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 55.65 Per rft. = Tk. 264.34
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 79.80 Per rft. Tk. 379.05
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 65.10 Per rft. = Tk. 585.90
6. 31.00 mm, 26.00 mm sliding fixed side
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 46.20 Per rft. = Tk. 207.90
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 73.50 Per rft. = Tk. 330.75
8. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 77.70 Per rft. = Tk. 699.30
= Tk. 3,265.24
Cutting wastage 3% = Tk. 97.96
Total (A) = Tk. 3,363.20
(B) Cost of accessories:
(1) Sliding door key lock 1 set @ Tk. 67.28 Per set. = Tk. 67.28
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 33 rft. @ Tk. 1.36 Per rft. = Tk. 44.88
(4) Sliding neoprene 28 rft. @ Tk. 2.73 Per rft. = Tk. 76.44
(5) Bolts and screws in/c sealants L.S. = Tk. 52.88
Total (B) = Tk. 328.00
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1/2 No. @ Tk. 700.00 each = Tk. 350.00
(2) Semi- skilled technician 1/2 No. @ Tk. 450.00 each = Tk. 225.00
(3) Tools and plant, sundries etc. L.S. = Tk. 294.00
Sub total (C) = Tk. 869.00
Total (A+B+C) = 4,560.20
Profit 10.00% = Tk. 456.02
Overhead 3.50% = Tk. 159.61
= Tk. 5,175.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 301.24
Grand total = Tk. 5,477.07
Rate Per sft. = Tk. 243.43
Rate per sqm. = Tk. 2,620.28

Say, Tk. 2,620 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 279

Item No.- 14.6.2.1


Supplying, fitting and fixing aluminium sliding window frame and shutter (S.S. colour)
Considering 1 No. window
Considering 3'-0" x 4'-6" = 13.5 sft. of work
(A) Cost of aluminium sections:
1. 75.50 mm, 32 mm outer bottom (high)
of 1.5 mm thick
1 x 3'-0"= 3 rft. @ Tk. 80.85 Per rft. = Tk. 242.55
2. 75.5 mm, 26.80 mm outer top
of 1.5 mm thick
1x 3'-0"= 3 rft. @ Tk. 88.20 Per rft. = Tk. 264.60
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 2'-9"= 2.75 rft. @ Tk. 58.80 Per rft. = Tk. 161.70
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 2'-9"= 2.75 rft. @ Tk. 84.00 Per rft. Tk. 231.00
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 68.25 Per rft. = Tk. 614.25
6. 31.00 mm, 26.00 mm sliding fixed
side of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 49.35 Per rft. = Tk. 222.08
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 77.70 Per rft. = Tk. 349.65
8. 34.40 mm, 32.10 mm inter-lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 81.90 Per rft. = Tk. 737.10
= Tk. 2,822.93
Cutting wastage 3% = Tk. 84.69
Total (A) = Tk. 2,907.62
(B) Cost of Accessories:
(1) Sliding door key lock 1 set @ Tk. 67.28 Per set. = Tk. 67.28
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 27 rft. @ Tk. 1.36 Per rft. = Tk. 36.72
(4) Sliding neoprene 24 rft. @ Tk. 2.73 Per rft. = Tk. 65.52
(5) Bolts and screws in/c sealants L.S. = Tk. 53.37
Total (B) = Tk. 309.41
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1/3 No. @ Tk. 700.00 each = Tk. 233.33
(2) Semi- skilled technician 1/3 No. @ Tk. 450.00 each = Tk. 150.00
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 628.33
Total (A+B+C) = 3,845.36
Profit 10.00% = Tk. 384.54
Overhead 3.50% = Tk. 134.59
= Tk. 4,364.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 254.02
Grand total = Tk. 4,618.51
Rate Per sft. = Tk. 342.11
Rate per sqm. = Tk. 3,682.47

Say, Tk. 3,682 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 280

Item No.- 14.6.2.2


Supplying, fitting and fixing aluminium sliding window frame and shutter (bronze colour)
Considering 1 No. window
Considering 3'-0" x 4'-6" = 13.5 sft. of work
(A) Cost of aluminium sections:
1. 75.50 mm, 32 mm outer bottom (high)
of 1.5 mm thick
1 x 3'-0"= 3 rft. @ Tk. 78.75 Per rft. = Tk. 236.25
2. 75.5 mm, 26.80 mm outer top
of 1.5 mm thick
1x 3'-0"= 3 rft. @ Tk. 86.10 Per rft. = Tk. 258.30
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 2'-9"= 2.75 rft. @ Tk. 57.75 Per rft. = Tk. 158.81
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 2'-9"= 2.75 rft. @ Tk. 81.90 Per rft. Tk. 225.23
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 67.20 Per rft. = Tk. 604.80
6. 31.00 mm, 26.00 mm sliding fixed
side of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 48.30 Per rft. = Tk. 217.35
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 75.60 Per rft. = Tk. 340.20
8. 34.40 mm, 32.10 mm inter-lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 79.80 Per rft. = Tk. 718.20
= Tk. 2,759.14
Cutting wastage 3% = Tk. 82.77
Total (A) = Tk. 2,841.91
(B) Cost of Accessories:
(1) Sliding door key lock 1 set @ Tk. 67.28 Per set. = Tk. 67.28
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 27 rft. @ Tk. 1.36 Per rft. = Tk. 36.72
(4) Sliding neoprene 24 rft. @ Tk. 2.73 Per rft. = Tk. 65.52
(5) Bolts and screws in/c sealants L.S. = Tk. 53.37
Total (B) = Tk. 309.41
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1/3 No. @ Tk. 700.00 each = Tk. 233.33
(2) Semi- skilled technician 1/3 No. @ Tk. 450.00 each = Tk. 150.00
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 628.33
Total (A+B+C) = 3,779.65
Profit 10.00% = Tk. 377.97
Overhead 3.50% = Tk. 132.29
= Tk. 4,289.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 249.68
Grand total = Tk. 4,539.59
Rate Per sft. = Tk. 336.27
Rate per sqm. = Tk. 3,619.61

Say, Tk. 3,620 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 281

Item No.- 14.6.2.3


Supplying, fitting and fixing aluminium sliding window frame and shutter (silver colour)
Considering 1 No. window
Considering 3'-0" x 4'-6" = 13.5 sft. of work
(A) Cost of aluminium sections:
1. 75.50 mm, 32 mm outer bottom (high)
of 1.5 mm thick
1 x 3'-0"= 3 rft. @ Tk. 76.65 Per rft. = Tk. 229.95
2. 75.5 mm, 26.80 mm outer top
of 1.5 mm thick
1x 3'-0"= 3 rft. @ Tk. 82.95 Per rft. = Tk. 248.85
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 2'-9"= 2.75 rft. @ Tk. 55.65 Per rft. = Tk. 153.04
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 2'-9"= 2.75 rft. @ Tk. 79.80 Per rft. Tk. 219.45
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 65.10 Per rft. = Tk. 585.90
6. 31.00 mm, 26.00 mm sliding fixed side
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 46.20 Per rft. = Tk. 207.90
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 73.50 Per rft. = Tk. 330.75
8. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 77.70 Per rft. = Tk. 699.30
= Tk. 2,675.14
Cutting wastage 3% = Tk. 80.25
Total (A) = Tk. 2,755.39
(B) Cost of accessories:
(1) Sliding door key lock 1 set @ Tk. 67.28 Per set. = Tk. 67.28
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 27 rft. @ Tk. 1.36 Per rft. = Tk. 36.72
(4) Sliding neoprene 24 rft. @ Tk. 2.73 Per rft. = Tk. 65.52
(5) Bolts and screws in/c sealants L.S. = Tk. 53.37
Total (B) = Tk. 309.41
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1/3 No. @ Tk. 700.00 each = Tk. 233.33
(2) Semi- skilled technician 1/3 No. @ Tk. 450.00 each = Tk. 150.00
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 628.33
Total (A+B+C) = 3,693.13
Profit 10.00% = Tk. 369.31
Overhead 3.50% = Tk. 129.26
= Tk. 4,191.70
Add VAT with adjustment factor 1.0582 5.50% = Tk. 243.96
Grand total = Tk. 4,435.66
Rate Per sft. = Tk. 328.57
Rate per sqm. = Tk. 3,536.73

Say, Tk. 3,537 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 282

Item No.- 14.7.1.1


Supplying, fitting and fixing of aluminium sliding window (5'-0" x 4'-6") with mosquito net
(S.S. colour) with double locking arrangement.
Considering 1 No. window
Considering 5'-0" x 4'-6"= 22.5 sft. of work
(A) Cost of aluminium shutter
1. 95.00 mm, 38.00 mm outer bottom
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 106.05 Per rft. = Tk. 530.25
2. 95.00 mm, 28.5 mm outer top
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 109.20 Per rft. = Tk. 546.00
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 58.80 Per rft. = Tk. 279.30
4. 60 mm, 24.40 mm shutter bottom
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 84.00 Per rft. = Tk. 420.00
5. 95.00 mm, 19.50 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 84.00 Per rft. = Tk. 756.00
6. 49.20 mm, 26.2 mm shutter lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 77.70 Per rft. = Tk. 699.30
7. 34.40 mm, 32.10 mm, 25.4 mm inter lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 81.90 Per rft. = Tk. 737.10
8. 42.20 mm, 13.20 mm net section
of 1.5 mm thick
2 x 4'-6"= 9 rft.
2 x 2'-6"= 5 rft.
14 rft. @ Tk. 54.60 Per rft. = Tk. 764.40
9. Fibre net mesh
2'-6" x 4'-6"= 11.25 sft. @ Tk. 16.80 Per sft. = Tk. 189.00
Total = Tk. 4,921.35
Cutting wastage 3% = Tk. 147.64
Sub total (A) = Tk. 5,068.99
(B) Cost of accessories:
(1) Sliding window key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding window wheel 4 No. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding window mohiar 33 rft. @ Tk. 1.36 Per rft. = Tk. 44.88
(4) Sliding window neoprene 28 rft. @ Tk. 2.73 Per rft. = Tk. 76.44
(5) Sealant 100 gm @ Tk. 2.47 Per gm = Tk. 247.00
(6) Bolts and screws in/c sealants L.S. = Tk. 147.00
Sub total (B) = Tk. 1,034.32
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
(2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,107.50
Total (A+B+C) = 7,210.81
Profit 10.00% = Tk. 721.08
Overhead 3.50% = Tk. 252.38
= Tk. 8,184.27
Add VAT with adjustment factor 1.0582 5.50% = Tk. 476.33
Grand total = Tk. 8,660.60
Rate Per sft. = Tk. 384.92
Analysis of PWD SoR 2014 for Civil Works 283

Rate per sqm. = Tk. 4,143.28

Say, Tk. 4,143 .00 Per sqm.

Item No.- 14.7.1.2


Supplying, fitting and fixing of aluminium sliding window (5'-0" x 4'-6") with mosquito net
(bronze colour) with double locking arrangement.
Considering 1 No. window
Considering 5'-0" x 4'-6"= 22.5 sft. of work
(A) Cost of aluminium shutter
1. 95.00 mm, 38.00 mm outer bottom
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 103.95 Per rft. = Tk. 519.75
2. 95.00 mm, 28.5 mm outer top
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 107.10 Per rft. = Tk. 535.50
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 57.75 Per rft. = Tk. 274.31
4. 60 mm, 24.40 mm shutter bottom
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 81.90 Per rft. = Tk. 409.50
5. 95.00 mm, 19.50 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 81.90 Per rft. = Tk. 737.10
6. 49.20 mm, 26.2 mm shutter lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 75.60 Per rft. = Tk. 680.40
7. 34.40 mm, 32.10 mm, 25.4 mm inter lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 79.80 Per rft. = Tk. 718.20
8. 42.20 mm, 13.20 mm net section
of 1.5 mm thick
2 x 4'-6"= 9 rft.
2 x 2'-6"= 5 rft.
14 rft. @ Tk. 53.55 Per rft. = Tk. 749.70
9. Fibre net mesh
2'-6" x 4'-6"= 11.25 sft. @ Tk. 15.75 Per sft. = Tk. 177.19
Total = Tk. 4,801.65
Cutting wastage 3% = Tk. 144.05
Sub total (A) = Tk. 4,945.70
(B) Cost of accessories:
(1) Sliding window key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding window wheel 4 No. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding window mohiar 33 rft. @ Tk. 1.36 Per rft. = Tk. 44.88
(4) Sliding window neoprene 28 rft. @ Tk. 2.73 Per rft. = Tk. 76.44
(5) Sealant 100 gm @ Tk. 2.47 Per gm = Tk. 247.00
(6) Bolts and screws in/c sealants L.S. = Tk. 147.00
Sub total (B) = Tk. 1,034.32
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
(2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,107.50
Total (A+B+C) = 7,087.52
Profit 10.00% = Tk. 708.75
Overhead 3.50% = Tk. 248.06
Analysis of PWD SoR 2014 for Civil Works 284

= Tk. 8,044.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 468.19
Grand total = Tk. 8,512.52
Rate Per sft. = Tk. 378.33
Rate per sqm. = Tk. 4,072.34

Say, Tk. 4,072 .00 Per sqm.

Item No.- 14.7.1.3


Supplying, fitting and fixing of aluminium sliding window (5'-0" x 4'-6") with mosquito net
(silver colour) with double locking arrangement
Considering 1 No. window
(A) Cost of aluminium section
1. 95.00 mm, 38.00 mm outer bottom
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 100.80 Per rft. = Tk. 504.00
2. 95.00 mm, 28.5 mm outer top
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 103.95 Per rft. = Tk. 519.75
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 55.65 Per rft. = Tk. 264.34
4. 60 mm, 24.40 mm shutter bottom
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 79.80 Per rft. = Tk. 399.00
5. 95.00 mm, 19.50 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 79.80 Per rft. = Tk. 718.20
6. 49.20 mm, 26.2 mm shutter lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 73.50 Per rft. = Tk. 661.50
7. 34.40 mm, 32.10 mm, 25.4 mm inter-lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 77.70 Per rft. = Tk. 699.30
8. 42.20 mm, 13.20 mm net section
of 1.5 mm thick
2 x 4'-6"= 9 rft.
2 x 2'-6"= 5 rft.
= 14 rft. @ Tk. 51.45 Per rft = Tk. 720.30
9. Fibre net mesh
2'-6" x 4'-6"= 11.25 sft. @ Tk. 15.75 Per sft. = Tk. 177.19
Total = Tk. 4,663.58
Cutting wastage 3% = Tk. 139.91
Sub total (A) = Tk. 4,803.49
(B) Cost of accessories:
(1) Sliding window key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding window wheel 4 Nos. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding window mohiar 33 rft. @ Tk. 1.36 Per rft. = Tk. 44.88
(4) Sliding window neoprene 28 rft. @ Tk. 2.73 Per rft. = Tk. 76.44
(5) Sealant 100 gm @ Tk. 2.47 Per gm = Tk. 247.00
(6) Bolts and screws in/c sealants L.S. = Tk. 147.00
Sub total (B) = Tk. 1,034.32
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
(2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,107.50
Analysis of PWD SoR 2014 for Civil Works 285

Total (A+B+C) = 6,945.31


Profit 10.00% = Tk. 694.53
Overhead 3.50% = Tk. 243.09
= Tk. 7,882.93
Add VAT with adjustment factor 1.0582 5.50% = Tk. 458.79
Grand total = Tk. 8,341.72
Rate Per sft. = Tk. 370.74
Rate per sqm. = Tk. 3,990.65

Say, Tk. 3,991 .00 Per sqm.

Item No.- 14.7.2.1


Supplying, fitting and fixing of aluminium sliding window (4'-2" x 4'-6") with mosquito net
(S.S. colour) with double locking arrangement.
Considering 1 No. window
Considering 4'-2" x 4'-6"= 18.72 sft. of work
(A) Cost of aluminium section
1. 95.00 mm, 38.00 mm outer bottom
of 1.5 mm thick
1 x 4'-2"= 4.17 rft. @ Tk. 106.05 Per rft. = Tk. 442.23
2. 95.00 mm, 28.5 mm outer top
of 1.5 mm thick
1 x 4'-2"= 4.17 rft. @ Tk. 109.20 Per rft. = Tk. 455.36
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 4'-0"= 4 rft. @ Tk. 58.80 Per rft. = Tk. 235.20
4. 60 mm, 24.40 mm shutter bottom
of 1.5 mm thick
1 x 4'-2"= 4.17 rft. @ Tk. 84.00 Per rft. = Tk. 350.28
5. 95.00 mm, 19.50 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 84.00 Per rft. = Tk. 756.00
6. 49.20 mm, 26.2 mm shutter lock of
1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 77.70 Per rft. = Tk. 699.30
7. 34.40 mm, 32.10 mm, 25.4 mm inter-lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 81.90 Per rft. = Tk. 737.10
8. 42.20 mm, 13.20 mm net section of
1.5 mm thick
2 x 4'-6"= 9 rft.
2 x 2'-1"= 4.17 rft.
= 13.17 rft. @ Tk. 54.60 Per rft. = Tk. 719.08
9. Fibre net mesh
2'-6" x 4'-6"= 9.36 sft. @ Tk. 16.80 Per sft. = Tk. 157.25
= Tk. 4,551.80
Cutting wastage 3% = Tk. 136.55
Sub total (A) = Tk. 4,688.35
(B) Cost of Accessories:
(1) Sliding window key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding window wheel 4 Nos. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding window mohiar 22 rft. @ Tk. 1.36 Per rft. = Tk. 29.92
(4) Sliding window neoprene 22 rft. @ Tk. 2.73 Per rft. = Tk. 60.06
(5) Sealant 100 gm @ Tk. 2.47 Per gm = Tk. 247.00
(6) Bolts and screws in/c sealants L.S. = Tk. 122.50
Sub total (B) = Tk. 978.48
(C) Labour charge for fabrication, assembling and fitting-fixing in position
Analysis of PWD SoR 2014 for Civil Works 286

(1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
(2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,107.50
Total (A+B+C) = 6,774.33
Profit 10.00% = Tk. 677.43
Overhead 3.50% = Tk. 237.10
= Tk. 7,688.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 447.50
Grand total = Tk. 8,136.36
Rate Per sft. = Tk. 434.63
Rate per sqm. = Tk. 4,678.36

Say, Tk. 4,678 .00 Per sqm.

Item No.- 14.7.2.2


Supplying, fitting and fixing of aluminium sliding window (4'-2" x 4'-6") with mosquito net
(bronze colour) with double locking arrangement.
Considering 1 No. window
Considering 4'-2" x 4'-6"= 18.72 sft. of work
(A) Cost of aluminium section
1. 95.00 mm, 38.00 mm outer bottom
of 1.5 mm thick
1 x 4'-2"= 4.17 rft. @ Tk. 103.95 Per rft. = Tk. 433.47
2. 95.00 mm, 28.5 mm outer top
of 1.5 mm thick
1 x 4'-2"= 4.17 rft. @ Tk. 107.10 Per rft. = Tk. 446.61
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 4'-0"= 4 rft. @ Tk. 57.75 Per rft. = Tk. 231.00
4. 60 mm, 24.40 mm shutter bottom
of 1.5 mm thick
1 x 4'-2"= 4.17 rft. @ Tk. 81.90 Per rft. = Tk. 341.52
5. 95.00 mm, 19.50 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 81.90 Per rft. = Tk. 737.10
6. 49.20 mm, 26.2 mm shutter lock of
1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 75.60 Per rft. = Tk. 680.40
7. 34.40 mm, 32.10 mm, 25.4 mm inter-lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 79.80 Per rft. = Tk. 718.20
8. 42.20 mm, 13.20 mm net section of
1.5 mm thick
2 x 4'-6"= 9 rft.
2 x 2'-1"= 4.17 rft.
= 13.17 rft. @ Tk. 53.55 Per rft. = Tk. 705.25
9. Fibre net mesh
2'-6" x 4'-6"= 9.36 sft. @ Tk. 15.75 Per sft. = Tk. 147.42
= Tk. 4,440.97
Cutting wastage 3% = Tk. 133.23
Sub total (A) = Tk. 4,574.20
(B) Cost of Accessories:
(1) Sliding window key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding window wheel 4 Nos. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding window mohiar 22 rft. @ Tk. 1.36 Per rft. = Tk. 29.92
(4) Sliding window neoprene 22 rft. @ Tk. 2.73 Per rft. = Tk. 60.06
Analysis of PWD SoR 2014 for Civil Works 287

(5) Sealant 100 gm @ Tk. 2.47 Per gm = Tk. 247.00


(6) Bolts and screws in/c sealants L.S. = Tk. 122.50
Sub total (B) = Tk. 978.48
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
(2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,107.50
Total (A+B+C) = 6,660.18
Profit 10.00% = Tk. 666.02
Overhead 3.50% = Tk. 233.11
= Tk. 7,559.31
Add VAT with adjustment factor 1.0582 5.50% = Tk. 439.96
Grand total = Tk. 7,999.27
Rate Per sft. = Tk. 427.31
Rate per sqm. = Tk. 4,599.56

Say, Tk. 4,600 .00 Per sqm.

Item No.- 14.7.2.3


Supplying, fitting and fixing of aluminium sliding window (4'-2" x 4'-6") with mosquito net
(silver colour) with double locking arrangement
Considering 1 No. window
Considering 4'-2" x 4'-6"= 18.72 sft. of work
(A) Cost of aluminium section
1. 95.00 mm, 38.00 mm outer bottom
of 1.5 mm thick
1 x 4'-2"= 4.17 rft. @ Tk. 100.80 Per rft. = Tk. 420.34
2. 95.00 mm, 28.5 mm outer top of
1.5 mm thick
1 x 4'-2"= 4.17 rft. @ Tk. 103.95 Per rft. = Tk. 433.47
3. 33 mm, 26.80mm, 22 mm shutter top
of 1.5 mm thick
1 x 4'-0"= 4 rft. @ Tk. 55.65 Per rft. = Tk. 222.60
4. 60 mm, 24.40 mm shutter bottom
of 1.5 mm thick
1 x 4'-2"= 4.17 rft. @ Tk. 79.80 Per rft. = Tk. 332.77
5. 95.00 mm, 19.50 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 79.80 Per rft. = Tk. 718.20
6. 49.20 mm, 26.2 mm shutter lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 73.50 Per rft. = Tk. 661.50
7. 34.40 mm, 32.10 mm, 25.4 mm inter-lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 77.70 Per rft. = Tk. 699.30
8. 42.20 mm, 13.20 mm net section
of 1.5 mm thick
2 x 4'-6"= 9 rft.
2 x 2'-1"= 4.17 rft.
= 13.17 rft. @ Tk. 51.45 Per rft. = Tk. 677.60
9. Fibre net mesh
2'-6" x 4'-6"= 9.36 sft. @ Tk. 15.75 Per sft. = Tk. 147.42
Total = Tk. 4,313.20
Cutting wastage 3% = Tk. 129.40
Sub total (A) = Tk. 4,442.60
(B) Cost of accessories:
Analysis of PWD SoR 2014 for Civil Works 288

(1) Sliding window key lock 2 set @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding window wheel 4 Nos. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding window mohiar 22 rft. @ Tk. 1.36 Per rft. = Tk. 29.92
(4) Sliding window neoprene 22 rft. @ Tk. 2.73 Per rft. = Tk. 60.06
(5) Sealant 100 gm @ Tk. 2.47 Per gm = Tk. 247.00
(6) Bolts and screws L.S. = Tk. 122.50
Sub total (B) = Tk. 978.48
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 No. @ Tk. 700.00 each = Tk. 525.00
(2) Semi- skilled technician 3/4 No. @ Tk. 450.00 each = Tk. 337.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,107.50
Total (A+B+C) = 6,528.58
Profit 10.00% = Tk. 652.86
Overhead 3.50% = Tk. 228.50
= Tk. 7,409.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 431.27
Grand total = Tk. 7,841.21
Rate Per sft. = Tk. 418.87
Rate per sqm. = Tk. 4,508.72

Say, Tk. 4,509 .00 Per sqm.

Item No.- 14.7.3.1


Supplying, fitting and fixing of aluminium sliding window (2'-6" x 2'-0") with mosquito net
(S.S. colour) with double locking arrangement.
Considering 1 No. window
Considering 2'-6" x 2'-0"= 5 sft. of work
(A) Cost of aluminium sections
1. 95.00 mm, 38.00 mm outer bottom
of 1.5 mm thick
1 x 2'-6"= 2.5 rft. @ Tk. 106.05 Per rft. = Tk. 265.13
2. 95.00 mm, 28.5 mm outer top
of 1.5 mm thick
1 x 2'-6"= 2.5 rft. @ Tk. 109.20 Per rft. = Tk. 273.00
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 2'-3"= 2.25 rft. @ Tk. 58.80 Per rft. = Tk. 132.30
4. 60 mm, 24.40 mm shutter bottom
of 1.5 mm thick
1 x 2'-6"= 2.5 rft. @ Tk. 84.00 Per rft. = Tk. 210.00
5. 95.00 mm, 19.50 mm outer side
of 1.5 mm thick
2 x 2'-0"= 4 rft. @ Tk. 84.00 Per rft. = Tk. 336.00
6. 49.20 mm, 26.2 mm shutter lock
of 1.5 mm thick
2 x 2'-0"= 4 rft. @ Tk. 77.70 Per rft. = Tk. 310.80
7. 34.40 mm, 32.10 mm, 25.4 mm inter lock
of 1.5 mm thick
2 x 2'-0"= 4 rft. @ Tk. 81.90 Per rft. = Tk. 327.60
8. 42.20 mm, 13.20 mm net section
of 1.5 mm thick
2 x 2'-0"= 4 rft.
2 x 1'-3"= 2.5 rft.
= 6.5 rft. @ Tk. 54.60 Per rft. = Tk. 354.90
9. Fibre net mesh
1'-3" x 2'-0"= 2.5 sft. @ Tk. 16.80 Per sft. = Tk. 42.00
Analysis of PWD SoR 2014 for Civil Works 289

Total = Tk. 2,251.73


Cutting wastage 3% = Tk. 67.55
Sub total (A) = Tk. 2,319.28
(B) Cost of accessories:
(1) Sliding window key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding window wheel 4 Nos. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding window mohiar 10 rft. @ Tk. 1.36 Per rft. = Tk. 13.60
(4) Sliding window neoprene 8 rft. @ Tk. 2.73 Per rft. = Tk. 21.84
(5) Sealant 50 gm @ Tk. 2.47 Per gm = Tk. 123.50
(6) Bolts and screws L.S. = Tk. 73.50
Sub total (B) = Tk. 751.44
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1/3 No. @ Tk. 700.00 each = Tk. 233.33
(2) Semi- skilled technician 1/3 No. @ Tk. 450.00 each = Tk. 150.00
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 628.33
Total (A+B+C) = 3,699.05
Profit 10.00% = Tk. 369.91
Overhead 3.50% = Tk. 129.47
= Tk. 4,198.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 244.35
Grand total = Tk. 4,442.78
Rate Per sft. = Tk. 888.56
Rate per sqm. = Tk. 9,564.46

Say, Tk. 9,564 .00 Per sqm.

Item No.- 14.7.3.2


Supplying, fitting and fixing of aluminium sliding window (2'-6" x 2'-0") with mosquito net
(bronze colour) with double locking arrangement.
Considering 1 No. window
Considering 2'-6" x 2'-0"= 5 sft. of work
(A) Cost of aluminium sections
1. 95.00 mm, 38.00 mm outer bottom
of 1.5 mm thick
1 x 2'-6"= 2.5 rft. @ Tk. 103.95 Per rft. = Tk. 259.88
2. 95.00 mm, 28.5 mm outer top
of 1.5 mm thick
1 x 2'-6"= 2.5 rft. @ Tk. 107.10 Per rft. = Tk. 267.75
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 2'-3"= 2.25 rft. @ Tk. 57.75 Per rft. = Tk. 129.94
4. 60 mm, 24.40 mm shutter bottom
of 1.5 mm thick
1 x 2'-6"= 2.5 rft. @ Tk. 81.90 Per rft. = Tk. 204.75
5. 95.00 mm, 19.50 mm outer side
of 1.5 mm thick
2 x 2'-0"= 4 rft. @ Tk. 81.90 Per rft. = Tk. 327.60
6. 49.20 mm, 26.2 mm shutter lock
of 1.5 mm thick
2 x 2'-0"= 4 rft. @ Tk. 75.60 Per rft. = Tk. 302.40
7. 34.40 mm, 32.10 mm, 25.4 mm inter lock
of 1.5 mm thick
2 x 2'-0"= 4 rft. @ Tk. 79.80 Per rft. = Tk. 319.20
8. 42.20 mm, 13.20 mm net section
of 1.5 mm thick
2 x 2'-0"= 4 rft.
Analysis of PWD SoR 2014 for Civil Works 290

2 x 1'-3"= 2.5 rft.


= 6.5 rft. @ Tk. 53.55 Per rft. = Tk. 348.08
9. Fibre net mesh
1'-3" x 2'-0"= 2.5 sft. @ Tk. 15.75 Per sft. = Tk. 39.38
Total = Tk. 2,198.98
Cutting wastage 3% = Tk. 65.97
Sub total (A) = Tk. 2,264.95
(B) Cost of accessories:
(1) Sliding window key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding window wheel 4 Nos. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding window mohiar 10 rft. @ Tk. 1.36 Per rft. = Tk. 13.60
(4) Sliding window neoprene 8 rft. @ Tk. 2.73 Per rft. = Tk. 21.84
(5) Sealant 50 gm @ Tk. 2.47 Per gm = Tk. 123.50
(6) Bolts and screws L.S. = Tk. 73.50
Sub total (B) = Tk. 751.44
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1/3 No. @ Tk. 700.00 each = Tk. 233.33
(2) Semi- skilled technician 1/3 No. @ Tk. 450.00 each = Tk. 150.00
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 628.33
Total (A+B+C) = 3,644.72
Profit 10.00% = Tk. 364.47
Overhead 3.50% = Tk. 127.57
= Tk. 4,136.76
Add VAT with adjustment factor 1.0582 5.50% = Tk. 240.76
Grand total = Tk. 4,377.52
Rate Per sft. = Tk. 875.50
Rate per sqm. = Tk. 9,423.88

Say, Tk. 9,424 .00 Per sqm.

Item No.- 14.7.3.3


Supplying, fitting and fixing of aluminium sliding window (2'-6" x 2'-0") with mosquito net
(silver colour) with double locking arrangement
Considering 1 No. window
Considering 2'-6" x 2'-0"= 5 sft. of work
(A) Cost of aluminium sections
1. 95.00 mm, 38.00 mm outer bottom
of 1.5 mm thick
1 x 2'-6"= 2.5 rft. @ Tk. 100.80 Per rft. = Tk. 252.00
2. 95.00 mm, 28.5 mm outer top
of 1.5 mm thick
1 x 2'-6"= 2.5 rft. @ Tk. 103.95 Per rft. = Tk. 259.88
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 2'-3"= 2.25 rft. @ Tk. 55.65 Per rft. = Tk. 125.21
4. 60 mm, 24.40 mm shutter bottom
of 1.5 mm thick
1 x 2'-6"= 2.5 rft. @ Tk. 79.80 Per rft. = Tk. 199.50
5. 95.00 mm, 19.50 mm outer side
of 1.5 mm thick
2 x 2'-0"= 4 rft. @ Tk. 79.80 Per rft. = Tk. 319.20
6. 49.20 mm, 26.2 mm shutter lock
of 1.5 mm thick
2 x 2'-0"= 4 rft. @ Tk. 73.50 Per rft. = Tk. 294.00
7. 34.40 mm, 32.10 mm, 25.4 mm inter-lock of
1.5 mm thick
Analysis of PWD SoR 2014 for Civil Works 291

2 x 2'-0"= 4 rft. @ Tk. 77.70 Per rft. = Tk. 310.80


8. 42.20 mm, 13.20 mm net section
of 1.5 mm thick
2 x 2'-0"= 4 rft.
2 x 1'-3"= 2.5 rft.
= 6.5 rft. @ Tk. 51.45 Per rft. = Tk. 334.43
9. Fibre net mesh
1'-3" x 2'-0"= 2.5 sft. @ Tk. 15.75 Per sft. = Tk. 39.38
Total = Tk. 2,134.40
Cutting wastage 3% = Tk. 64.03
Sub total (A) = Tk. 2,198.43
(B) Cost of accessories:
(1) Sliding window key lock 2 sets @ Tk. 172.98 Per set = Tk. 345.96
(2) Sliding window wheel 4 Nos. @ Tk. 43.26 each = Tk. 173.04
(3) Sliding window mohiar 10 rft. @ Tk. 1.36 Per rft. = Tk. 13.60
(4) Sliding window neoprene 8 rft. @ Tk. 2.73 Per rft. = Tk. 21.84
(5) Sealant 50 gm @ Tk. 2.47 Per gm = Tk. 123.50
(6) Bolts and screws L.S. = Tk. 73.50
Sub total (B) = Tk. 751.44
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1/3 No. @ Tk. 700.00 each = Tk. 233.33
(2) Semi- skilled technician 1/3 No. @ Tk. 450.00 each = Tk. 150.00
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 628.33
Total (A+B+C) = 3,578.20
Profit 10.00% = Tk. 357.82
Overhead 3.50% = Tk. 125.24
= Tk. 4,061.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 236.37
Grand total = Tk. 4,297.63
Rate Per sft. = Tk. 859.53
Rate per sqm. = Tk. 9,251.98

Say, Tk. 9,252 .00 Per sqm.

Item No.- 14.8.1


Supplying, fitting and fixing aluminium sliding and fixed composite window frame
and shutter (S.S. colour)
Considering 1 No. window
Considering 5'-0" x 7'-0" = 35 sft. of work
(A) Cost of aluminium sections:
1. 75.50mm, 32 mm outer bottom (high)
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 80.85 Per rft. = Tk. 404.25
2. 75.5 mm, 26.80 mm outer top
of 1.5 mm thick
1x 5'-0"= 5 rft. @ Tk. 88.20 Per rft. = Tk. 441.00
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 58.80 Per rft. = Tk. 279.30
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick (0.736 kg/m)
1 x 4'-9"= 4.75 rft. @ Tk. 84.00 Per rft. Tk. 399.00
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 68.25 Per rft. = Tk. 614.25
6. 31.00 mm, 26.00 mm sliding fixed side
Analysis of PWD SoR 2014 for Civil Works 292

of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 49.35 Per rft. = Tk. 222.08
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 77.70 Per rft. = Tk. 349.65
8. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick (0.665 kg/m)
2 x 4'-6"= 9 rft. @ Tk. 81.90 Per rft. = Tk. 737.10
9. 37.78 mm, 31.78 mm bottom cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 34.65 Per rft. = Tk. 173.25
10. 76.20 mm, 38.10 mm grouve cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 86.10 Per rft. = Tk. 430.50
11. 57.15 mm, 15.80 mm grouve cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 50.40 Per rft. = Tk. 252.00
12. 76.20 mm, 38.10 mm, 57.15 mm top &
side of 1.5 mm thick
1 x 5'-0"= 5 rft.
3 x 2'-6"= 7.5 rft.
= 12.5 rft. @ Tk. 103.95 Per rft. = Tk. 1,299.38
= Tk. 5,601.76
Cutting wastage 3% = Tk. 168.05
Total (A) = Tk. 5,769.81
(B) Cost of accessories:
(1) Sliding door key lock 1 set @ Tk. 67.28 Per set. = Tk. 67.28
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 33 rft. @ Tk. 1.36 Per rft. = Tk. 44.88
(4) Sliding neoprene 28 rft. @ Tk. 2.73 Per rft. = Tk. 76.44
(5) Bolts and screws in/c sealants L.S. = Tk. 171.87
Total (B) = Tk. 446.99
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1.25 No. @ Tk. 700.00 each = Tk. 875.00
(2) Semi- skilled technician 1.25 No. @ Tk. 450.00 each = Tk. 562.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,682.50
Total (A+B+C) = 7,899.30
Profit 10.00% = Tk. 789.93
Overhead 3.50% = Tk. 276.48
= Tk. 8,965.71
Add VAT with adjustment factor 1.0582 5.50% = Tk. 521.81
Grand total = Tk. 9,487.52
Rate Per sft. = Tk. 271.07
Rate per sqm. = Tk. 2,917.80
Say, Tk. 2,918 .00 Per sqm.
Item No.- 14.8.2
Supplying, fitting and fixing aluminium sliding and fixed composite window frame
and shutter (bronze colour)
Considering 1 No. window
Considering 5'-0" x 7'-0" = 35 sft. of work
(A) Cost of aluminium sections:
1. 75.50mm, 32 mm outer bottom (high)
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 78.75 Per rft. = Tk. 393.75
2. 75.5 mm, 26.80 mm outer top
of 1.5 mm thick
Analysis of PWD SoR 2014 for Civil Works 293

1x 5'-0"= 5 rft. @ Tk. 86.10 Per rft. = Tk. 430.50


3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 57.75 Per rft. = Tk. 274.31
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick (0.736 kg/m)
1 x 4'-9"= 4.75 rft. @ Tk. 81.90 Per rft. Tk. 389.03
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 67.20 Per rft. = Tk. 604.80
6. 31.00 mm, 26.00 mm sliding fixed side
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 48.30 Per rft. = Tk. 217.35
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 75.60 Per rft. = Tk. 340.20
8. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick (0.665 kg/m)
2 x 4'-6"= 9 rft. @ Tk. 79.80 Per rft. = Tk. 718.20
9. 37.78 mm, 31.78 mm bottom cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 33.60 Per rft. = Tk. 168.00
10. 76.20 mm, 38.10 mm grouve cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 84.00 Per rft. = Tk. 420.00
11. 57.15 mm, 15.80 mm grouve cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 49.35 Per rft. = Tk. 246.75
12. 76.20 mm, 38.10 mm, 57.15 mm top &
side of 1.5 mm thick
1 x 5'-0"= 5 rft.
3 x 2'-6"= 7.5 rft.
= 12.5 rft. @ Tk. 101.85 Per rft. = Tk. 1,273.13
= Tk. 5,476.02
Cutting wastage 3% = Tk. 164.28
Total (A) = Tk. 5,640.30
(B) Cost of accessories:
(1) Sliding door key lock 1 set @ Tk. 67.28 Per set. = Tk. 67.28
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 33 rft. @ Tk. 1.36 Per rft. = Tk. 44.88
(4) Sliding neoprene 28 rft. @ Tk. 2.73 Per rft. = Tk. 76.44
(5) Bolts and screws in/c sealants L.S. = Tk. 171.87
Total (B) = Tk. 446.99
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1.25 No. @ Tk. 700.00 each = Tk. 875.00
(2) Semi- skilled technician 1.25 No. @ Tk. 450.00 each = Tk. 562.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,682.50
Total (A+B+C) = 7,769.79
Profit 10.00% = Tk. 776.98
Overhead 3.50% = Tk. 271.94
= Tk. 8,818.71
Add VAT with adjustment factor 1.0582 5.50% = Tk. 513.26
Grand total = Tk. 9,331.97
Rate Per sft. = Tk. 266.63
Rate per sqm. = Tk. 2,870.01
Analysis of PWD SoR 2014 for Civil Works 294

Say, Tk. 2,870 .00 Per sqm.

Item No.- 14.8.3


Supplying, fitting and fixing aluminium sliding and fixed composite window frame and
shutter (silver colour)
Considering 1 No. window
Considering 5'-0" x 7'-0" = 35 sft. of work
(A) Cost of aluminium sections:
1. 75.50 mm, 32 mm outer bottom (high)
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 76.65 Per rft. = Tk. 383.25
2. 75.5 mm, 26.80 mm outer top
of 1.5 mm thick
1x 5'-0"= 5 rft. @ Tk. 82.95 Per rft. = Tk. 414.75
3. 33 mm, 26.80 mm, 22 mm shutter
top of 1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 55.65 Per rft. = Tk. 264.34
4. 60 mm, 24 mm shutter bottom of
1.5 mm thick
1 x 4'-9"= 4.75 rft. @ Tk. 79.80 Per rft. Tk. 379.05
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 65.10 Per rft. = Tk. 585.90
6. 31.00 mm, 26.00 mm sliding fixed side
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 46.20 Per rft. = Tk. 207.90
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 4'-6"= 4.5 rft. @ Tk. 73.50 Per rft. = Tk. 330.75
8. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick
2 x 4'-6"= 9 rft. @ Tk. 77.70 Per rft. = Tk. 699.30
9. 37.78 mm, 31.78 mm bottom cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 32.55 Per rft. = Tk. 162.75
10. 76.20 mm, 38.10 mm grouve cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 81.90 Per rft. = Tk. 409.50
11. 57.15 mm, 15.80 mm grouve cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 49.35 Per rft. = Tk. 246.75
12. 76.20 mm, 38.10 mm, 57.15 mm top
& side of 1.5 mm thick
1 x 5'-0"= 5 rft.
3 x 2'-6"= 7.5 rft.
= 12.5 rft. @ Tk. 98.70 Per rft. = Tk. 1,233.75
= Tk. 5,317.99
Cutting wastage 3% = Tk. 159.54
Total (A) = Tk. 5,477.53
(B) Cost of accessories:
(1) Sliding door key lock 1 set @ Tk. 67.28 Per set. = Tk. 67.28
(2) Sliding door wheel 2 Nos. @ Tk. 43.26 each = Tk. 86.52
(3) Sliding door mohiar 33 rft. @ Tk. 1.36 Per rft. = Tk. 44.88
(4) Sliding neoprene 28 rft. @ Tk. 2.73 Per rft. = Tk. 76.44
(5) Bolts and screws in/c sealants L.S. = Tk. 66.10
Total (B) = Tk. 341.22
(C) Labour charge for fabrication, assembling and fitting-fixing in position
Analysis of PWD SoR 2014 for Civil Works 295

(1) Skilled technician 1.25 No. @ Tk. 700.00 each = Tk. 875.00
(2) Semi- skilled technician 1.25 No. @ Tk. 450.00 each = Tk. 562.50
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,682.50
Total (A+B+C) = 7,501.25
Profit 10.00% = Tk. 750.13
Overhead 3.50% = Tk. 262.54
= Tk. 8,513.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 495.52
Grand total = Tk. 9,009.44
Rate Per sft. = Tk. 257.41
Rate per sqm. = Tk. 2,770.76

Say, Tk. 2,771 .00 Per sqm.

Item No.- 14.9.1


Supplying, fitting and fixing aluminium top hung / casement window (S.S. colour)
Considering 1 No. window
Considering 3'-0" x 4'-0" = 12 sft. of work
(A) Cost of aluminium sections:
1. 38.88 mm, 36.63 mm casement outer
of 1.5 mm thick
2 x 4'-0"= 8 rft.
2 x 3'-0"= 6 rft.
= 14 rft. @ Tk. 55.65 Per rft. = Tk. 779.10
2. 47.62 mm, 28.57 mm, 40.82 mm casement shutter
of 1.9 mm thick
4 x 4'-0"= 16 rft.
2 x 3'-0"= 6 rft.
= 22 rft. @ Tk. 97.65 Per rft. = Tk. 2,148.30
3. 15.87 mm, 27.00 mm shutter glass clip
of 1.245 mm thick
4 x 4'-0"= 16
2 x 3'-0"= 6
= 22 rft. @ Tk. 27.30 Per rft. = Tk. 600.60
4. 1" x 1" square pipe 4 rft. @ Tk. 51.45 Per rft. Tk. 205.80
= Tk. 3,733.80
Cutting wastage 3% = Tk. 112.01
Total (A) = Tk. 3,845.81
(B) Cost of accessories:
(1) 4-bar hinge 4 Nos. @ Tk. 529.97 Per set. = Tk. 2,119.88
(2) Casement handle 2 Nos. @ Tk. 266.75 each = Tk. 533.50
(3) Bolts and screws in/c sealants L.S. = Tk. 468.24
Total (B) = Tk. 3,121.62
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1.50 No. @ Tk. 700.00 each = Tk. 1,050.00
(2) Semi- skilled technician 1.50 No. @ Tk. 450.00 each = Tk. 675.00
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,970.00
Total (A+B+C) = 8,937.43
Profit 10.00% = Tk. 893.74
Overhead 3.50% = Tk. 312.81
= Tk. 10,143.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 590.39
Grand total = Tk. 10,734.37
Rate Per sft. = Tk. 894.53
Rate per sqm. = Tk. 9,628.72
Analysis of PWD SoR 2014 for Civil Works 296

Say, Tk. 9,629 .00 Per sqm.

Item No.- 14.9.2


Supplying, fitting and fixing aluminium top hung / casement window (bronze colour)
Considering 1 No. window
Considering 3'-0" x 4'-0" = 12 sft. of work
(A) Cost of aluminium sections:
1. 38.88 mm, 36.63 mm casement outer
of 1.5 mm thick
2 x 4'-0"= 8 rft.
2 x 3'-0"= 6 rft.
= 14 rft. @ Tk. 54.60 Per rft. = Tk. 764.40
2. 47.62 mm, 28.57 mm, 40.82 mm casement shutter
of 1.9 mm thick
4 x 4'-0"= 16 rft.
2 x 3'-0"= 6 rft.
= 22 rft. @ Tk. 95.55 Per rft. = Tk. 2,102.10
3. 15.87 mm, 27.00 mm shutter glass clip
of 1.245 mm thick
4 x 4'-0"= 16
2 x 3'-0"= 6
= 22 rft. @ Tk. 26.25 Per rft. = Tk. 577.50
4. 1" x 1" square pipe 4 rft. @ Tk. 50.40 Per rft. Tk. 201.60
= Tk. 3,645.60
Cutting wastage 3% = Tk. 109.37
Total (A) = Tk. 3,754.97
(B) Cost of accessories:
(1) 4-bar hinge 4 Nos. @ Tk. 529.97 Per set. = Tk. 2,119.88
(2) Casement handle 2 Nos. @ Tk. 266.75 each = Tk. 533.50
(3) Bolts and screws in/c sealants L.S. = Tk. 468.24
Total (B) = Tk. 3,121.62
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1.50 No. @ Tk. 700.00 each = Tk. 1,050.00
(2) Semi- skilled technician 1.50 No. @ Tk. 450.00 each = Tk. 675.00
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,970.00
Total (A+B+C) = 8,846.59
Profit 10.00% = Tk. 884.66
Overhead 3.50% = Tk. 309.63
= Tk. 10,040.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 584.39
Grand total = Tk. 10,625.27
Rate Per sft. = Tk. 885.44
Rate per sqm. = Tk. 9,530.88

Say, Tk. 9,531 .00 Per sqm.


Item No.- 14.9.3
Supplying, fitting and fixing aluminium top hung/casement window (silver colour)
Considering 1 No. window
Considering 3'-0" x 4'-0" = 12 sft. of work
(A) Cost of aluminium sections:
1. 38.88 mm, 36.63 mm casement
outer 1.5 mm thick
2 x 4'-0"= 8 rft.
2 x 3'-0"= 6 rft.
= 14 rft. @ Tk. 52.50 Per rft. = Tk. 735.00
Analysis of PWD SoR 2014 for Civil Works 297

2. 47.62 mm, 28.57 mm, 40.82 mm casement


shutter of 1.9 mm thick
4 x 4'-0"= 16 rft.
2 x 3'-0"= 6 rft.
= 22 rft. @ Tk. 92.40 Per rft. = Tk. 2,032.80
3. 15.87 mm, 27.00 mm shutter glass
clip of 1.245 mm thick
4 x 4'-0"= 16
2 x 3'-0"= 6
= 22 rft. @ Tk. 25.20 Per rft. = Tk. 554.40
4. 1" x 1" square pipe 4 rft. @ Tk. 48.30 Per rft. Tk. 193.20
= Tk. 3,515.40
Add cutting wastage 3% = Tk. 105.46
Total (A) = Tk. 3,620.86
(B) Cost of accessories:
(1) 4-bar hinge 4 Nos. @ Tk. 529.97 Per set. = Tk. 2,119.88
(2) Casement handle 2 Nos. @ Tk. 266.75 each = Tk. 533.50
(3) Bolts and screws in/c sealants L.S. = Tk. 468.24
Total (B) = Tk. 3,121.62
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1.50 No. @ Tk. 700.00 each = Tk. 1,050.00
(2) Semi- skilled technician 1.50 No. @ Tk. 450.00 each = Tk. 675.00
(3) Tools and plant, sundries etc. L.S. = Tk. 245.00
Sub total (C) = Tk. 1,970.00
Total (A+B+C) = 8,712.48
Profit 10.00% = Tk. 871.25
Overhead 3.50% = Tk. 304.94
= Tk. 9,888.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 575.53
Grand total = Tk. 10,464.20
Rate Per sft. = Tk. 872.02
Rate per sqm. = Tk. 9,386.42

Say, Tk. 9,386 .00 Per sqm.

Item No.- 14.10.1.1


Supplying, fitting and fixing of corrugated aluminium curtain wall (S.S. colour)
Considering 1 No. curtain
Considering 10'-0" x 7'-0"= 70 sft. of work
(A) Cost of aluminium sections
1. 37.78 mm, 31.78 mm bottom cover
of 1.5 mm thick
3 x 10'-0"= 30 rft. @ Tk. 34.65 Per rft. = Tk. 1,039.50
2. 76.20 mm, 38.10 mm grouve cover
of 1.5 mm thick
3 x 10'-0"= 30 rft. @ Tk. 86.10 Per rft. = Tk. 2,583.00
3. 57.15 mm, 15.80 mm grouve cover
of 1.5 mm thick
2 x 7'-0"= 14 rft.
2 x 10'-0"= 20 rft.
= 34 rft @ Tk. 50.40 Per rft. = Tk. 1,713.60
4. 76.20 mm, 38.10 mm, 57.15 mm top
& side of 1.5 mm thick
4 x 7'-0"= 28 rft.
1 x 10'-0"= 10 rft.
= 38 rft. @ Tk. 103.95 Per rft. = Tk. 3,950.10
5. 7.14 mm span drel of 1.5 mm thick
Analysis of PWD SoR 2014 for Civil Works 298

22 x 7'-0"= 154 rft @ Tk. 72.45 Per rft. = Tk. 11,157.30


= Tk. 20,443.50
Cutting wastage 5% = Tk. 1,022.18
Sub total (A) = Tk. 21,465.68
(B) Cost of accessories:
(1) Rivet 100 pcs. @ Tk. 4.62 Per pc. = Tk. 462.00
(2) Screws 14 pcs. @ Tk. 0.94 Per pc. = Tk. 13.16
(3) Fixed neoprene 204 rft. @ Tk. 2.73 Per rft. = Tk. 556.92
Sub total (B) = Tk. 1,032.08
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2.75 No. @ Tk. 700.00 each = Tk. 1,925.00
(2) Semi- skilled technician 2.75 No. @ Tk. 450.00 each = Tk. 1,237.50
(3) Tools and plant, sundries etc. L.S. = Tk. 490.00
Sub total (C) = Tk. 3,652.50
Total (A+B+C) = 26,150.26
Profit 10.00% = Tk. 2,615.03
Overhead 3.50% = Tk. 915.26
= Tk. 29,680.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,727.44
Grand total = Tk. 31,407.99
Rate Per sft. = Tk. 448.69
Rate per sqm. = Tk. 4,829.70

Say, Tk. 4,830 .00 Per sqm.

Item No.- 14.10.1.2


Supplying, fitting and fixing of corrugated aluminium curtain wall (bronze colour)
Considering 1 No. curtain
Considering 10'-0" x 7'-0"= 70 sft. of work
(A) Cost of aluminium sections
1. 37.78 mm, 31.78 mm bottom cover
of 1.5 mm thick
3 x 10'-0"= 30 rft. @ Tk. 33.60 Per rft. = Tk. 1,008.00
2. 76.20 mm, 38.10 mm grouve cover
of 1.5 mm thick
3 x 10'-0"= 30 rft. @ Tk. 84.00 Per rft. = Tk. 2,520.00
3. 57.15 mm, 15.80 mm grouve cover
of 1.5 mm thick
2 x 7'-0"= 14 rft.
2 x 10'-0"= 20 rft.
= 34 rft @ Tk. 49.35 Per rft. = Tk. 1,677.90
4. 76.20 mm, 38.10 mm, 57.15 mm top
& side of 1.5 mm thick
4 x 7'-0"= 28 rft.
1 x 10'-0"= 10 rft.
= 38 rft. @ Tk. 101.85 Per rft. = Tk. 3,870.30
5. 7.14 mm span drel of 1.5 mm thick
22 x 7'-0"= 154 rft @ Tk. 70.35 Per rft. = Tk. 10,833.90
= Tk. 19,910.10
Cutting wastage 5% = Tk. 995.51
Sub total (A) = Tk. 20,905.61
(B) Cost of accessories:
(1) Rivet 100 pcs. @ Tk. 4.62 Per pc. = Tk. 462.00
(2) Screws 14 pcs. @ Tk. 0.94 Per pc. = Tk. 13.16
(3) Fixed neoprene 204 rft. @ Tk. 2.73 Per rft. = Tk. 556.92
Sub total (B) = Tk. 1,032.08
(C) Labour charge for fabrication, assembling and fitting-fixing in position
Analysis of PWD SoR 2014 for Civil Works 299

(1) Skilled technician 2.75 No. @ Tk. 700.00 each = Tk. 1,925.00
(2) Semi- skilled technician 2.75 No. @ Tk. 450.00 each = Tk. 1,237.50
(3) Tools and plant, sundries etc. L.S. = Tk. 490.00
Sub total (C) = Tk. 3,652.50
Total (A+B+C) = 25,590.19
Profit 10.00% = Tk. 2,559.02
Overhead 3.50% = Tk. 895.66
= Tk. 29,044.87
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,690.44
Grand total = Tk. 30,735.31
Rate Per sft. = Tk. 439.08
Rate per sqm. = Tk. 4,726.26

Say, Tk. 4,726 .00 Per sqm.

Item No.- 14.10.1.3


Supplying, fitting and fixing of corrugated aluminium curtain wall (Silver colour)
Considering 1 No. curtain
Considering 10'-0" x 7'-0"= 70 sft. of work
(A) Cost of aluminium sections
1. 37.78 mm, 31.78 mm bottom cover
of 1.5 mm thick
3 x 10'-0"= 30 rft. @ Tk. 32.55 Per rft. = Tk. 976.50
2. 76.20 mm, 38.10 mm grouve cover
of 1.5 mm thick
3 x 10'-0"= 30 rft. @ Tk. 81.90 Per rft. = Tk. 2,457.00
3. 57.15 mm, 15.80 mm grouve cover
of 1.5 mm thick
2 x 7'-0"= 14 rft.
2 x 10'-0"= 20 rft.
34 rft. @ Tk. 49.35 Per rft. = Tk. 1,677.90
4. 76.20 mm, 38.10 mm, 57.15 mm top
& side of 1.5 mm thick
4 x 7'-0"= 28 rft.
1 x 10'-0"= 10 rft.
= 38 rft. @ Tk. 98.70 Per rft. = Tk. 3,750.60
5. 7.14 mm span drel of 1.5 mm thick
22 x 7'-0"= 154 rft @ Tk. 68.25 Per rft. = Tk. 10,510.50
= Tk. 19,372.50
Cutting wastage 5% = Tk. 968.63
Sub total (A) = Tk. 20,341.13
(B) Cost of accessories:
(1) Rivet 100 pcs. @ Tk. 4.62 Per pc. = Tk. 462.00
(2) Screws 14 pcs. @ Tk. 0.94 Per pc. = Tk. 13.16
(3) Fixed neoprene 204 rft. @ Tk. 2.73 Per rft. = Tk. 556.92
Sub total (B) = Tk. 1,032.08
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2.75 No. @ Tk. 700.00 each = Tk. 1,925.00
(2) Semi- skilled technician 2.75 No. @ Tk. 450.00 each = Tk. 1,237.50
(3) Tools and plant, sundries etc. L.S. = Tk. 490.00
Sub total (C) = Tk. 3,652.50
Total (A+B+C) = 25,025.71
Profit 10.00% = Tk. 2,502.57
Overhead 3.50% = Tk. 875.90
= Tk. 28,404.18
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,653.15
Grand total = Tk. 30,057.33
Analysis of PWD SoR 2014 for Civil Works 300

Rate Per sft. = Tk. 429.39


Rate per sqm. = Tk. 4,621.95

Say, Tk. 4,622 .00 Per sqm.

Item No.- 14.10.2.1


Supplying, fitting and fixing of corrugated aluminium curtain wall (SS colour)
Considering 1 No. of curtain
Considering 10'-0" x 2'-6"= 25 sft. of work
(A) Cost of aluminium sections
1. 101.60 mm, 44.45 mm top & side
1.5 mm thick
2 x 10'-0"= 20 rft. @ Tk. 154.35 Per rft. = Tk. 3,087.00
2. 44.32 mm ,19.61 mm bottom cover
of 1.5 m thick
1 x 10'-0"= 10 rft. @ Tk. 43.05 Per rft. = Tk. 430.50
3. 101.35 mm, 44.45 mm bottom
of 1.5 mm thick
1 x 10'-0"= 10 rft. @ Tk. 114.45 Per rft. = Tk. 1,144.50
4. 83.21 mm, 16.00 mm grouve cover
of 1.5 mm thick
2 x 2'-6"= 5 rft. @ Tk. 66.15 Per rft. = Tk. 330.75
5. 7.14 mm span drel of 1.4 mm thick
1 x 60'-0"= 60 rft @ Tk. 72.45 Per rft. = Tk. 4,347.00
= Tk. 9,339.75
Cutting wastage 5% = Tk. 466.99
Sub total (A) = Tk. 9,806.74
(B) Cost of accessories:
(1) Rivet 88 pcs. @ Tk. 4.62 Per pc. = Tk. 406.56
(2) Screws 28 pcs. @ Tk. 0.94 Per pc. = Tk. 26.32
Sub total (B) = Tk. 432.88
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1.00 No. @ Tk. 700.00 each = Tk. 700.00
(2) Semi- skilled technician 1.00 No. @ Tk. 450.00 each = Tk. 450.00
(3) Tools and plant, sundries etc. L.S. = Tk. 490.00
Sub total (C) = Tk. 1,640.00
Total (A+B+C) = 11,879.62
Profit 10.00% = Tk. 1,187.96
Overhead 3.50% = Tk. 415.79
= Tk. 13,483.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 784.75
Grand total = Tk. 14,268.12
Rate Per sft. = Tk. 570.72
Rate per sqm. = Tk. 6,143.23

Say, Tk. 6,143 .00 Per sqm.

Item No.- 14.10.2.2


Supplying, fitting and fixing of corrugated aluminium curtain wall (bronze colour)
Considering 1 No. of curtain
Considering 10'-0" x 2'-6"= 25 sft. of work
(A) Cost of aluminium sections
1. 101.60 mm, 44.45 mm top & side 1.5 mm thick
2 x 10'-0"= 20 rft. @ Tk. 151.20 Per rft. = Tk. 3,024.00
2. 44.32 mm ,19.61 mm bottom cover
of 1.5 m thick
1 x 10'-0"= 10 rft. @ Tk. 42.00 Per rft. = Tk. 420.00
Analysis of PWD SoR 2014 for Civil Works 301

3. 101.35 mm, 44.45 mm bottom


of 1.5 mm thick
1 x 10'-0"= 10 rft. @ Tk. 112.35 Per rft. = Tk. 1,123.50
4. 83.21 mm, 16.00 mm grouve cover
of 1.5 mm thick
2 x 2'-6"= 5 rft. @ Tk. 65.10 Per rft. = Tk. 325.50
5. 7.14 mm span drel of 1.4 mm thick
1 x 60'-0"= 60 rft @ Tk. 70.35 Per rft. = Tk. 4,221.00
= Tk. 9,114.00
Cutting wastage 5% = Tk. 455.70
Sub total (A) = Tk. 9,569.70
(B) Cost of accessories:
(1) Rivet 88 pcs. @ Tk. 4.62 Per pc. = Tk. 406.56
(2) Screws 28 pcs. @ Tk. 0.94 Per pc. = Tk. 26.32
Sub total (B) = Tk. 432.88
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1.00 No. @ Tk. 700.00 each = Tk. 700.00
(2) Semi- skilled technician 1.00 No. @ Tk. 450.00 each = Tk. 450.00
(3) Tools and plant, sundries etc. L.S. = Tk. 490.00
Sub total (C) = Tk. 1,640.00
Total (A+B+C) = 11,642.58
Profit 10.00% = Tk. 1,164.26
Overhead 3.50% = Tk. 407.49
= Tk. 13,214.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 769.09
Grand total = Tk. 13,983.42
Rate Per sft. = Tk. 559.34
Rate per sqm. = Tk. 6,020.74

Say, Tk. 6,021 .00 Per sqm.


Item No.- 14.10.2.3
Supplying, fitting and fixing of corrugated aluminium curtain wall (silver colour)
Considering 1 No. curtain
Considering 10'-0" x 2'-6"= 25 sft. of work
(A) Cost of aluminium sections
1. 101.60 mm, 44.45 mm top &
side 1.8 mm thick
2 x 10'-0"= 20 rft. @ Tk. 147.00 Per rft. = Tk. 2,940.00
2. 44.32 mm ,19.61 mm bottom
cover of 1.5 mm thick
1 x 10'-0"= 10 rft. @ Tk. 40.95 Per rft. = Tk. 409.50
3. 101.35 mm, 44.45 mm bottom
of 1.8 mm thick
1 x 10'-0"= 10 rft. @ Tk. 109.20 Per rft. = Tk. 1,092.00
4. 83.21 mm, 16.00 mm grouve cover
of 1.5 mm thick
2 x 2'-6"= 5 rft. @ Tk. 64.05 Per rft. = Tk. 320.25
5. 7.14 mm span drel of 1.5 mm thick
1 x 60'-0"= 60 rft @ Tk. 68.25 Per rft. = Tk. 4,095.00
= Tk. 8,856.75
Cutting wastage 5% = Tk. 442.84
Sub total (A) = Tk. 9,299.59
(B) Cost of accessories:
(1) Rivet 88 pcs. @ Tk. 4.62 Per pc. = Tk. 406.56
(2) Screws 28 pcs. @ Tk. 0.94 Per pc. = Tk. 26.32
Sub total (B) = Tk. 432.88
(C) Labour charge for fabrication, assembling and fitting-fixing in position
Analysis of PWD SoR 2014 for Civil Works 302

(1) Skilled technician 1.00 No. @ Tk. 700.00 each = Tk. 700.00
(2) Semi- skilled technician 1.00 No. @ Tk. 450.00 each = Tk. 450.00
(3) Tools and plant, sundries etc. L.S. = Tk. 490.00
Sub total (C) = Tk. 1,640.00
Total (A+B+C) = 11,372.47
Profit 10.00% = Tk. 1,137.25
Overhead 3.50% = Tk. 398.04
= Tk. 12,907.76
Add VAT with adjustment factor 1.0582 5.50% = Tk. 751.24
Grand total = Tk. 13,659.00
Rate Per sft. = Tk. 546.36
Rate per sqm. = Tk. 5,881.02

Say, Tk. 5,881 .00 Per sqm.

Item No.- 14.11.1


Supplying, fitting and fixing of fixed fan light (S.S. colour)
Considering 1 No. fan-light
Considering 5'-0" x 2'-3"= 11.25 sft. of work
(A) Cost aluminium sections:
1. 17.40 mm, 31.78 mm bottom cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 34.65 Per rft = Tk. 173.25
2. 76.20 mm, 38.10 mm bottom cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 86.10 Per rft = Tk. 430.50
3. 57.15 mm, 15.80 mm grouve cover
of 1.5 mm thick
1 x 2'-3"= 2.25 rft. @ Tk. 50.40 Per rft = Tk. 113.40
4. 76.20 mm, 16 mm, 38.10 mm top &
side of 1.5 mm thick
3 x 2'-3"= 6.75 rft.
1 x 5'-0"= 5 rft.
11.75 rft. @ Tk. 103.95 Per rft = Tk. 1,221.41
= Tk. 1,938.56
Cutting wastage 3% = Tk. 58.16
Sub total (A) = Tk. 1,996.72
(B) Cost of accessories:
(1) Neoprene 68 rft. @ Tk. 3.21 Per rft = Tk. 218.28
(2) Bolts & nuts L.S. = Tk. 245.00
Sub total (B) = Tk. 463.28
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 0.50 No. @ Tk. 700.00 each = Tk. 350.00
(2) Semi- skilled technician 0.50 No. @ Tk. 450.00 each = Tk. 225.00
(3) Tools and plant, sundries etc. L.S. = Tk. 147.00
Sub total (C) = Tk. 722.00
Total (A+B+C) = 3,182.00
Profit 10.00% = Tk. 318.20
Overhead 3.50% = Tk. 111.37
= Tk. 3,611.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 210.20
Grand total = Tk. 3,821.77
Rate Per sft. = Tk. 339.71
Rate per sqm. = Tk. 3,656.64

Say, Tk. 3,657 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 303

Item No.- 14.11.2


Supplying, fitting and fixing of fixed fan light (bronze colour)
Considering 1 No. fan-light
Considering 5'-0" x 2'-3"= 11.25 sft. of work
(A) Cost aluminium sections:
1. 17.40 mm, 31.78 mm bottom cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 33.60 Per rft = Tk. 168.00
2. 76.20 mm, 38.10 mm bottom cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 84.00 Per rft = Tk. 420.00
3. 57.15 mm, 15.80 mm grouve cover
of 1.5 mm thick
1 x 2'-3"= 2.25 rft. @ Tk. 49.35 Per rft = Tk. 111.04
4. 76.20 mm, 16 mm, 38.10 mm top &
side of 1.5 mm thick
3 x 2'-3"= 6.75 rft.
1 x 5'-0"= 5 rft.
11.75 rft. @ Tk. 101.85 Per rft = Tk. 1,196.74
= Tk. 1,895.78
Cutting wastage 3% = Tk. 56.87
Sub total (A) = Tk. 1,952.65
(B) Cost of accessories:
(1) Neoprene 68 rft. @ Tk. 3.21 Per rft = Tk. 218.28
(2) Bolts & nuts L.S. = Tk. 245.00
Sub total (B) = Tk. 463.28
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 0.50 No. @ Tk. 700.00 each = Tk. 350.00
(2) Semi- skilled technician 0.50 No. @ Tk. 450.00 each = Tk. 225.00
(3) Tools and plant, sundries etc. L.S. = Tk. 147.00
Sub total (C) = Tk. 722.00
Total (A+B+C) = 3,137.93
Profit 10.00% = Tk. 313.79
Overhead 3.50% = Tk. 109.83
= Tk. 3,561.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 207.29
Grand total = Tk. 3,768.84
Rate Per sft. = Tk. 335.01
Rate per sqm. = Tk. 3,606.05

Say, Tk. 3,606 .00 Per sqm.

Item No.- 14.11.3


Supplying, fitting and fixing of fixed fan light (silver colour)
Considering 1 No. fan-light
Considering 5'-0" x 2'-3"= 11.25 sft. of work
(A) Cost aluminium sections:
1. 17.40 mm, 31.78 mm bottom cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 32.55 Per rft = Tk. 162.75
2. 76.20 mm, 38.10 mm bottom cover
of 1.5 mm thick
1 x 5'-0"= 5 rft. @ Tk. 81.90 Per rft = Tk. 409.50
3. 57.15 mm, 15.80 mm grouve cover
of 1.5 mm thick
1 x 2'-3"= 2.25 rft. @ Tk. 49.35 Per rft = Tk. 111.04
4. 76.20 mm, 16 mm, 38.10 mm top &
Analysis of PWD SoR 2014 for Civil Works 304

side of 1.5 mm thick


3 x 2'-3"= 6.75 rft.
1 x 5'-0"= 5 rft.
11.75 rft. @ Tk. 98.70 Per rft = Tk. 1,159.73
= Tk. 1,843.02
Cutting wastage 3% = Tk. 55.29
Sub total (A) = Tk. 1,898.31
(B) Cost of accessories:
(1) Neoprene 40 rft. @ Tk. 3.21 Per rft = Tk. 128.40
(2) Bolts & nuts L.S. = Tk. 214.00
Sub total (B) = Tk. 342.40
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 0.50 No. @ Tk. 700.00 each = Tk. 350.00
(2) Semi- skilled technician 0.50 No. @ Tk. 450.00 each = Tk. 225.00
(3) Tools and plant, sundries etc. L.S. = Tk. 147.00
Sub total (C) = Tk. 722.00
Total (A+B+C) = 2,962.71
Profit 10.00% = Tk. 296.27
Overhead 3.50% = Tk. 103.69
= Tk. 3,362.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 195.71
Grand total = Tk. 3,558.38
Rate Per sft. = Tk. 316.30
Rate per sqm. = Tk. 3,404.65

Say, Tk. 3,405 .00 Per sqm.

Item No.- 14.12.1


Supplying, fitting and fixing of aluminium fixed louver (S.S. colour)
Considering 1 No. fixed louver
Considering 4'-0" x 2'-3"= 9 sft. of work
(A) Cost aluminium sections:
1. 76.00 mm, 38.10 mm wall frame
of 1.5 mm thick
2 x 4'-0"= 8 rft.
2 x 2'-3"= 4.5 rft.
= 12.5 rft. @ Tk. 77.70 Per rft. = Tk. 971.25
2. 55.02 mm, 37.39 mm louver section
of 1.2 mm thick
2 x 9 x 4'-0"= 72 rft. @ Tk. 32.55 Per rft. = Tk. 2,343.60
3. 39.67 mm, 15.06 mm louver outer
section of 1.20 mm thick
2 x 2'-3"= 4.5 rft. @ Tk. 37.80 Per rft. = Tk. 170.10
= Tk. 3,484.95
Cutting wastage 3% = Tk. 104.55
Total (A) = Tk. 3,589.50
(B) Cost of accessories:
(1) Machineries charges L.S. = Tk. 245.00
(2) Bolts & nuts L.S. = Tk. 196.00
Sub total (B) = Tk. 441.00
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 0.33 No. @ Tk. 700.00 each = Tk. 231.00
(2) Semi- skilled technician 0.33 No. @ Tk. 450.00 each = Tk. 148.50
(3) Tools and plant, sundries etc. L.S. = Tk. 147.00
Sub total (C) = Tk. 526.50
Total (A+B+C) = 4,557.00
Profit 10.00% = Tk. 455.70
Analysis of PWD SoR 2014 for Civil Works 305

Overhead 3.50% = Tk. 159.50


= Tk. 5,172.20
Add VAT with adjustment factor 1.0582 5.50% = Tk. 301.03
Grand total = Tk. 5,473.23
Rate Per sft. = Tk. 608.14
Rate per sqm. = Tk. 6,546.02

Say, Tk. 6,546 .00 Per sqm.

Item No.- 14.12.2


Supplying, fitting and fixing of aluminium fixed louver (bronze colour)
Considering 1 No. fixed louver
Considering 4'-0" x 2'-3"= 9 sft. of work
(A) Cost aluminium sections:
1. 76.00 mm, 38.10 mm wall frame
of 1.5 mm thick
2 x 4'-0"= 8 rft.
2 x 2'-3"= 4.5 rft.
= 12.5 rft. @ Tk. 75.60 Per rft. = Tk. 945.00
2. 55.02 mm, 37.39 mm louver section
of 1.2 mm thick
2 x 9 x 4'-0"= 72 rft. @ Tk. 31.50 Per rft. = Tk. 2,268.00
3. 39.67 mm, 15.06 mm louver outer
section of 1.20 mm thick
2 x 2'-3"= 4.5 rft. @ Tk. 36.75 Per rft. = Tk. 165.38
= Tk. 3,378.38
Cutting wastage 3% = Tk. 101.35
Total (A) = Tk. 3,479.73
(B) Cost of accessories:
(1) Machineries charges L.S. = Tk. 245.00
(2) Bolts & nuts L.S. = Tk. 196.00
Sub total (B) = Tk. 441.00
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 0.33 No. @ Tk. 700.00 each = Tk. 231.00
(2) Semi- skilled technician 0.33 No. @ Tk. 450.00 each = Tk. 148.50
(3) Tools and plant, sundries etc. L.S. = Tk. 147.00
Sub total (C) = Tk. 526.50
Total (A+B+C) = 4,447.23
Profit 10.00% = Tk. 444.72
Overhead 3.50% = Tk. 155.65
= Tk. 5,047.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 293.78
Grand total = Tk. 5,341.38
Rate Per sft. = Tk. 593.49
Rate per sqm. = Tk. 6,388.33

Say, Tk. 6,388 .00 Per sqm.

Item No.- 14.12.3


Supplying, fitting and fixing of aluminium fixed louver (silver colour)
Considering 1 No. fixed louver
Considering 4'-0" x 2'-3"= 9 sft. of work
(A) Cost aluminium sections:
1. 76.00 mm, 38.10 mm wall frame
of 1.5 mm thick
2 x 4'-0"= 8 rft.
2 x 2'-3"= 4.5 rft.
Analysis of PWD SoR 2014 for Civil Works 306

= 12.5 rft. @ Tk. 73.50 Per rft. = Tk. 918.75


2. 55.02 mm, 37.39 mm louver section
of 1.20 mm thick
2 x 9 x 4'-0"= 72 rft. @ Tk. 30.45 Per rft. = Tk. 2,192.40
3. 39.67 mm, 15.06 mm louver outer section
of 1.20 mm thick
2 x 2'-3"= 4.5 rft. @ Tk. 35.70 Per rft. = Tk. 160.65
= Tk. 3,271.80
Cutting wastage 3% = Tk. 98.15
Total (A) = Tk. 3,369.95
(B) Cost of accessories:
(1) Machineries charges L.S. = Tk. 245.00
(2) Bolts & nuts L.S. = Tk. 196.00
Sub total (B) = Tk. 441.00
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 0.33 No. @ Tk. 700.00 each = Tk. 231.00
(2) Semi- skilled technician 0.33 No. @ Tk. 450.00 each = Tk. 148.50
(3) Tools and plant, sundries etc. L.S. = Tk. 147.00
Sub total (C) = Tk. 526.50
Total (A+B+C) = 4,337.45
Profit 10.00% = Tk. 433.75
Overhead 3.50% = Tk. 151.81
= Tk. 4,923.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 286.52
Grand total = Tk. 5,209.53
Rate Per sft. = Tk. 578.84
Rate per sqm. = Tk. 6,230.63

Say, Tk. 6,231 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 307

Item No.- 14.13


Supplying, fitting, fixing of Aluminium sliding fly proof Netting shutter
Considering : 1X4'-6"X 5'-0" = 22.50 sft
(a) Cost of materials
i) 38mm x 38mm Aluminium frame (Wall box) of 1.5 mm
Horizontal 2 x 4'-6"= 9.00 rft.
Vertical 2 x 5'-0"= 10.00 rft.
= 19.00 rft.
Add wastage 3%= 0.57 rft.
= 19.570 rft. @ Tk. 41.30 Per rft = Tk. 808.24
ii) 38mm x 12mm and 1.5 mm thick Aluminium frame of Netting shutter top, bottom & side etc.
Horizontal 2 x 2 x 2'-3"= 9.00 rft.
Vertical 2 x 2 x 5'-0"= 20.00 rft.
= 29.00 rft.
Add wastage 3%= 0.87 rft.
= 29.870 rft. @ Tk. 51.80 Per rft = Tk. 1,547.27
iii) Mosquito Net (plastic)
1 x 5'-0" x 4'-6"= 22.50 sft.
Add wastage 3%= 0.68 sft.
= 23.180 sft. @ Tk. 15.75 Per sft = Tk. 365.09
iv) Wheel 8 Nos. @ Tk. 43.26 Each = Tk. 346.08
v) Sealant 50 rft. @ Tk. 2.47 Per Gm = Tk. 123.50
vi) Rubber 1x 2x 14'-0" 28.00 rft. @ Tk. 2.14 Per rft = Tk. 59.92
v) Bolts & screws etc. L.S. = Tk. 40.00
b) Fitting and fixing of accessories
i) Skilled Technician 1/4 No. @ Tk. 700.00 each = Tk. 175.00
ii) Semi skilled technician 1/4 No. @ Tk. 450.00 each = Tk. 112.50
iii) Tools, plants and sundrise etc. L.S. = Tk. 60.00
Total = Tk. 3,637.60
Profit 10.00% = Tk. 363.76
Overhead 3.50% = Tk. 127.32
= Tk. 4,128.68
Add VAT with adjustment factor 1.0582 4.50% = Tk. 196.60
Grand total = Tk. 4,325.28
Rate per sft. = Tk. 192.23
Rate per sqm. = Tk. 2,069.16

Say, Tk. 2,069 .00 Per sqm.

Item No.- 14.14.1


Supplying, fitting and fixing of 5 mm clear glass in aluminium frame, partitions or windows.
Considering 1 No. partition
Considering 5'-0" x 4'-0"= 20 sft. of work
(A) Materials:
(i) 5 mm thick clear glass 20 sft. @ Tk. 65.60 Per sft. = Tk. 1,312.00
(ii) Wastage 5% 1 sft. @ Tk. 65.60 Per sft. = Tk. 65.60
(iii) Neoprene / rubber gasket 20 sft. @ Tk. 2.14 Per sft. = Tk. 42.80
(iv) Local carriage L.S. = Tk. 49.00
(B) Labour charges:
Labour cost for fitting and fixing in position of
5 mm thick tinted glass in aluminium frame,
partitions and windows. 20 sft. @ Tk. 9.80 Per sft. = Tk. 196.00
Total (A+B) = Tk. 1,665.40
Profit 10.00% = Tk. 166.54
Overhead 3.50% = Tk. 58.29
= Tk. 1,890.23
Add VAT with adjustment factor 1.0582 5.50% = Tk. 110.01
Analysis of PWD SoR 2014 for Civil Works 308

Grand total = Tk. 2,000.24


Rate per sft. = Tk. 100.01
Rate per sqm. = Tk. 1,076.51

Say, Tk. 1,077 .00 Per sqm.

Item No.- 14.14.2


Supplying, fitting and fixing of 5 mm tinted glass in aluminium frame, partitions or windows.
Considering 1 No. partition
Considering 5'-0" x 4'-0"= 20 sft. of work
(A) Materials:
(i) 5 mm thick tinted glass 20 sft. @ Tk. 82.77 Per sft. = Tk. 1,655.40
(ii) Wastage 5% 1 sft. @ Tk. 82.77 Per sft. = Tk. 82.77
(iii) Neoprene / rubber gasket 20 sft. @ Tk. 2.14 Per sft. = Tk. 42.80
(iv) Local carriage L.S. = Tk. 49.00
(B) Labour charges:
Labour cost for fitting and fixing in position of
5 mm thick tinted glass in aluminium frame,
partitions and windows. 20 sft. @ Tk. 9.80 Per sft. = Tk. 196.00
Total (A+B) = Tk. 2,025.97
Profit 10.00% = Tk. 202.60
Overhead 3.50% = Tk. 70.91
= Tk. 2,299.48
Add VAT with adjustment factor 1.0582 5.50% = Tk. 133.83
Grand total = Tk. 2,433.31
Rate per sft. = Tk. 121.67
Rate per sqm. = Tk. 1,309.66

Say, Tk. 1,310 .00 Per sqm.

Item No.- 14.14.3


Supplying, fitting and fixing of 5 mm ambushed/ frosted glass in aluminium frame, partitions or windows.
Considering 1 No. partition
Considering 5'-0" x 4'-0"= 20 sft. of work
(A) Materials:
(i) 5 mm thick ambushed or frosted glass 20 sft. @ Tk. 77.00 Per sft. = Tk. 1,540.00
(ii) Wastage 5% 1 sft. @ Tk. 65.60 Per sft. = Tk. 65.60
(iii) Neoprene / rubber gasket 20 sft. @ Tk. 2.14 Per sft. = Tk. 42.80
(iv) Local carriage L.S. = Tk. 49.00
(B) Labour charges:
Labour cost for fitting and fixing in position of
5 mm thick tinted glass in aluminium frame,
partitions and windows. 20 sft. @ Tk. 9.80 Per sft. = Tk. 196.00
Total (A+B) = Tk. 1,893.40
Profit 10.00% = Tk. 189.34
Overhead 3.50% = Tk. 66.27
= Tk. 2,149.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 125.07
Grand total = Tk. 2,274.08
Rate per sft. = Tk. 113.70
Rate per sqm. = Tk. 1,223.87

Say, Tk. 1,224 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 309

Item No.- 14.14.4


Supplying, fitting and fixing of 6 mm reflecting glass (LBC) in aluminium frame partitions
1. 6 mm thick reflecting glass 20.00 sft. @ Tk. 101.00 Per sft. = Tk. 2,020.00
2. Neoprene / Rubber guskit 20.00 rft. @ Tk. 1.50 per rft. = Tk. 30.00
3. Local carriage and sundries LS = Tk. 20.00
4. Fitting-fixing charge 20 sft. @ Tk. 6.00 per sft. = Tk. 120.00
Total = Tk. 2,190.00
Profit 10.00% = Tk. 219.00
Overhead 3.50% = Tk. 76.65
= Tk. 2,485.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 144.67
Grand total = Tk. 2,630.32
Rate per sft. = Tk. 131.52
Rate per sqm. = Tk. 1,415.68

Say Tk. 1,416 .00 per sqm.

Item No.- 14.15


Supplying, fitting and fixing of 4 mm thick Aluminum composite Panel (European Origin) work in column, beam and wall surface providing
with 50 x 50 x 1.5 mm aluminum section including supply of necessary hardwares, consumables, scaffolding etc.
Considering : 1X 8'-0"X 4'-0" = 32.00 sft
A. Cost of Materials
i) Cost of 44mm X 44 mm aluminium box
3 X 8'-0' = 24.00 rft
3 X 4'-0' = 12.00
36.00 rft
Add 5% wastage= 1.80 "
37.80 rft @ Tk. 72.45 Per rft. = Tk. 2,738.61
ii) 25mm X 25 mm aluminium Angle
2X 4 X 4'-0' = 32.00 rft
2X 4 X 2'-0' = 16.00
= 48.00 rft
Add 3% wastage= 1.44 "
49.44 rft @ Tk. 22.05 Per rft. = Tk. 1,090.15
ii) 25mm X 25 mm Fitting Angle 2.00 rft @ Tk. 38.85 Per rft. = Tk. 77.70
B Accessories:
i) Rivet 100 Pcs @ Tk. 4.62 Per Pc = Tk. 462.00
ii) SS Screw 25 Pcs @ Tk. 1.91 Per Pc = Tk. 47.75
C Fitting, fixing charge
i) Skilled Technician 2 Nos @ Tk. 700.00 Each = Tk. 1,400.00
ii) Semi-Skilled Technician 2 Nos @ Tk. 450.00 Each = Tk. 900.00
C. Scaffolding & Local Carriage L.S. = Tk. 250.00
D Alluminium composite Panel
1X 8'-0" X 4'-0' = 32.00 rft
Add 5% wastage= 1.60 "
33.60 rft @ Tk. 238.73 Per rft. = Tk. 8,021.33
Total (A+B+C+D+E) = Tk. 14,987.54
Profit 10.00% = Tk. 1,498.75
Overhead 3.50% = Tk. 524.56
= Tk. 17,010.85
Add VAT with adjustment factor 1.0582 4.50% = Tk. 810.04
Grand total = Tk. 17,820.89
Rate per sft. = Tk. 556.90
Rate per sqm. = Tk. 5,994.47

Say, Tk. 5,994 .00 Per sqm.


Item No.- 14.16
Analysis of PWD SoR 2014 for Civil Works 310

Supplying, fitting and fixing of aluminium curtain wall and aluminium top hung/casement windows ad per the US Architectural aluminium Manufacturer's Association (AA
Considering : 1X 9'-0"X9'-7" = 86.22 sft
A. Cost of Materials
1) Curtain wall sub mullium (100mm X 50 mm X 2.00 mm)
4 X 9'-0' = 36.00 rft
4 X 9'-7' = 38.32 "
74.32 sft.
Add 3% wastage= 2.2296 sft.
76.55 sft. @ Tk. 324.45 Per rft. = Tk. 24,836.65
2) Casement outer frame (29mm X 20 mm X 1.20 mm)
2X 2 X 3'-2' = 12.68 rft
2X 2 X 3'-0' = 12.00 "
= 24.68 sft.
Add 3% wastage= 0.7404 sft.
25.42 sft. @ Tk. 33.60 Per rft. = Tk. 854.11
3) Casement outer section (52mm X 22 mm X 40mm X 1.5 mm)
2X 2 X 3'-2' = 12.68 rft
2X 2 X 3'-0' = 12.00 "
= 24.68 sft.
Add 3% wastage= 0.7404 sft.
25.42 sft. @ Tk. 155.40 Per rft. = Tk. 3,950.27
4) Aluminium angle (50mm X 50 mm X 6mm)
16 X 2' = 2.67 sft.
Add 3% wastage= 0.0801 sft.
2.75 sft. @ Tk. 180.60 Per rft. = Tk. 496.65
5) Aluminium cover (50mm X 6 mm X 1.5mm)
24 X 3' = 6.00 sft.
Add 3% wastage= 0.18 sft.
6.18 sft. @ Tk. 64.54 Per rft. = Tk. 398.86
6) 50mm X 6 mm X 1.5mm angle for casement shutter
12 X 2' = 2.00 sft.
Add 3% wastage= 0.06 sft.
2.06 sft. @ Tk. 55.26 Per rft. = Tk. 113.84
Sub Total (A) = Tk. 30,650.38
B Hard ware accessories:
1. Steel rowel bolt 32 Pcs @ Tk. 35.34 Each = Tk. 1,130.88
2. 2" SS Screw 65 Pcs @ Tk. 1.91 Each = Tk. 124.15
3. Rivets (Big) 230 Pcs @ Tk. 1.86 Each = Tk. 427.80
4. Rivets (Normal) 40 Pcs @ Tk. 4.62 Each = Tk. 184.80
5. Norton Tap 72 Pcs @ Tk. 25.71 Each = Tk. 1,851.12
6. Masking tape 1 Pcs @ Tk. 23.78 Each = Tk. 23.78
7. Structural sealant 6 Pcs @ Tk. 9.00 Each = Tk. 54.00
8. Casement 4-bar huge 4 Pcs @ Tk. 501.51 Each = Tk. 2,006.04
9. Casement handle 2 Pcs @ Tk. 206.45 Each = Tk. 412.90
10. Sealant Gum 2 Pcs @ Tk. 340.79 Each = Tk. 681.58
11. Arm lock 4 Pcs @ Tk. 375.04 Each = Tk. 1,500.16
12. M.S. angle 16 Pcs @ Tk. 90.22 Each = Tk. 1,443.52
Sub Total (b) = Tk. 9,840.73
C a) Labour Charge:
i) Skilled Technician 10 No. @ Tk. 700.00 Each = Tk. 7,000.00
ii) Semi-Skilled Technician 10 No. @ Tk. 450.00 Each = Tk. 4,500.00
iii) Machineries L.S. = Tk. 600.00
b) Labour cost for civil work
i) Mason 3 No. @ Tk. 389.00 Each = Tk. 1,167.00
ii) Ordinary Labour 3 No. @ Tk. 245.00 Each = Tk. 735.00
D Cost of high scaffolding L.S. = Tk. 300.00
E Carriage and Sundries L.S. = Tk. 700.00
Analysis of PWD SoR 2014 for Civil Works 311

Total (A+B+C+D+E) = Tk. 55,493.11


Profit 10.00% = Tk. 5,549.31
Overhead 3.50% = Tk. 1,942.26
= Tk. 62,984.68
Add VAT with adjustment factor 1.0582 4.50% = Tk. 2,999.27
Grand total = Tk. 65,983.95
Rate per sft. = Tk. 765.30
Rate per sqm. = Tk. 8,237.69

Say, Tk. 8,238 .00 Per sqm.

Item No.- 14.17


Supplying, fitting and fixing of aluminium curtain wall and aluminium top hung/basement windows ad per the US Architectural aluminium Manufacturer's Association (AA

Considering : 1X 9'-0"X9'-7" = 86.22 sft


A. Cost of Materials
1) Curtain wall sub millium (50mm X 50 mm X 1.50 mm)
4 X 9'-0' = 36.00 rft
4 X 9'-7' = 38.32 "
74.32 sft.
Add 3% wastage= 2.2296 sft.
76.55 sft. @ Tk. 206.85 Per rft. = Tk. 15,834.37
2) Casement outer frame (29mm X 20 mm X 1.20 mm)
2X 2 X 3'-2' = 12.68 rft
2X 2 X 3'-0' = 12.00 "
= 24.68 sft.
Add 3% wastage= 0.7404 sft.
25.42 sft. @ Tk. 33.60 Per rft. = Tk. 854.11
3) Casement outer section (52mm X 22 mm X 40mm X 1.5 mm)
2X 2 X 3'-2' = 12.68 rft
2X 2 X 3'-0' = 12.00 "
= 24.68 sft.
Add 3% wastage= 0.7404 sft.
25.42 sft. @ Tk. 155.40 Per rft. = Tk. 3,950.27
4) Aluminium angle (50mm X 50 mm X 6mm)
16 X 2' = 2.67 sft.
Add 3% wastage= 0.0801 sft.
2.75 sft. @ Tk. 180.60 Per rft. = Tk. 496.65
5) Aluminium cover (50mm X 6 mm X 1.5mm)
24 X 3' = 6.00 sft.
Add 3% wastage= 0.18 sft.
6.18 sft. @ Tk. 64.54 Per rft. = Tk. 398.86
6) 50mm X 6 mm X 1.5mm angle for casement shutter
12 X 2' = 2.00 sft.
Add 3% wastage= 0.06 sft.
2.06 sft. @ Tk. 55.26 Per rft. = Tk. 113.84
Sub Total (A) = Tk. 21,648.10
B Hard ware accessories:
1. Steel rowel bolt 32 Pcs @ Tk. 35.34 Each = Tk. 1,130.88
2. 2" SS Screw 64 Pcs @ Tk. 1.91 Each = Tk. 122.24
3. Rivets (Big) 230 Pcs @ Tk. 1.86 Each = Tk. 427.80
4. Rivets (Normal) 40 Pcs @ Tk. 4.62 Each = Tk. 184.80
5. Norton Tap 72 Pcs @ Tk. 25.71 Each = Tk. 1,851.12
6. Masking tape 1 Pcs @ Tk. 23.78 Each = Tk. 23.78
7. Structural sealant 6 Pcs @ Tk. 9.00 Each = Tk. 54.00
8. Casement 4-bar huge 4 Pcs @ Tk. 501.51 Each = Tk. 2,006.04
9. Casement handle 2 Pcs @ Tk. 206.45 Each = Tk. 412.90
Analysis of PWD SoR 2014 for Civil Works 312

10. Sealent Gum 2 Pcs @ Tk. 340.79 Each = Tk. 681.58


11. Arm lock 4 Pcs @ Tk. 375.04 Each = Tk. 1,500.16
12. M.S. angle 16 Pcs @ Tk. 90.22 Each = Tk. 1,443.52
Sub Total (b) = Tk. 9,838.82
C a) Labour Charge:
i) Skilled Technician 10 No. @ Tk. 700.00 Each = Tk. 7,000.00
ii) Semi-Skilled Technician 10 No. @ Tk. 450.00 Each = Tk. 4,500.00
iii) Machineries L.S. = Tk. 600.00
b) Labour cost for civil work
i) Mason 3 No. @ Tk. 389.00 Each = Tk. 1,167.00
ii) Ordinary Labour 3 No. @ Tk. 245.00 Each = Tk. 735.00
D Cost of high scaffolding L.S. = Tk. 300.00
E Carriage and Sundries L.S. = Tk. 700.00
Total (A+B+C+D+E) = Tk. 46,488.92
Profit 10.00% = Tk. 4,648.89
Overhead 3.50% = Tk. 1,627.11
= Tk. 52,764.92
Add VAT with adjustment factor 1.0582 4.50% = Tk. 2,512.61
Grand total = Tk. 55,277.53
Rate per sft. = Tk. 641.12
Rate per sqm. = Tk. 6,901.02

Say, Tk. 6,901 .00 Per sqm.

DIVISION 15 : CEMENT PLASTER, POINTING WORK & LIME TERRACING


Item No.- 15.1
Minimum 1/2" thick cement plaster (1:4) to walls (average of 1/2" on one side and 3/4" on
Analysis of PWD SoR 2014 for Civil Works 313

other side of the walls).


A. 1/2" thick cement plaster (1:4) on one side of the walls.
Considering 100 sft. of work
(a) Sand (F.M. 1.2) 5.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 85.00
(b) Cement 1.00 bag @ Tk. 440.00 Per bag = Tk. 440.00
(c) Labour =
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 1.00 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(d) Washing of sand, local carriage, scaffolding, curing, & sundries etc. L.S. = Tk. 245.00
Total = Tk. 1,527.25
Profit 10.00% = Tk. 152.73
Overhead 3.50% = Tk. 53.45
Tk. 1,733.43
VAT 5.50% = Tk. 95.34
Grand total = Tk. 1,828.77
B. 3/4" thick cement plaster (1:4) on other side of the walls.
Considering 100 sft. of work
(a) Sand (F.M. 1.2) 7.50 cft. @ Tk. 1,700.00 Per % cft. = Tk. 127.50
(b) Cement 1.50 bags @ Tk. 440.00 Per bag = Tk. 660.00
(c) Labour =
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 1.00 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(d) Washing of sand, local carriage, scaffolding, curing, & sundries etc. L.S. = Tk. 245.00
Total = Tk. 1,789.75
Profit 10.00% = Tk. 178.98
Overhead 3.50% = Tk. 62.64
= Tk. 2,031.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 118.23
Grand total = Tk. 2,149.60
Average of A & B = Tk. 1,989.19
Rate per sft. = Tk. 19.89
Rate per sqm. = Tk. 214.10

For ground floor Say, Tk. 214 .00 Per sqm.

Item No.- 15.2


Minimum 1/2" thick cement plaster (1:4) with neat cement finishing to plinth walls
upto 150 mm below ground level.
Considering 100 sft. of work
(a) Sand (F.M. 1.2) 5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 85.00
(b) Cement 1.5 bag @ Tk. 440.00 Per bag = Tk. 660.00
(c) Labour
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 1.25 Nos. @ Tk. 389.00 each = Tk. 486.25
(iii) Ordinary labour 1.25 Nos. @ Tk. 245.00 each = Tk. 306.25
(d) Washing of sand, local carriage, curing, & sundries etc. L.S. = Tk. 245.00
Total = Tk. 1,905.75
Profit 10.00% = Tk. 190.58
Overhead 3.50% = Tk. 66.70
= Tk. 2,163.03
Add VAT with adjustment factor 1.0582 5.50% = Tk. 125.89
Grand total = Tk. 2,288.92
Rate per sft. = Tk. 22.89
Rate per sqm. = Tk. 246.39
Analysis of PWD SoR 2014 for Civil Works 314

Say, Tk. 246 .00 Per sqm.

Item No.- 15.3


Minimum 1/2" thick cement plaster (1:4) with neat cement finishing to dado
(average of 1/2" on one side and 3/4" on other side).
For 3/4" thick plaster with neat cement finish on walls
Considering 100 sft. of work
(a) Sand (F.M. 1.2) 7.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 127.50
(b) Cement 2 bags @ Tk. 440.00 Per bag = Tk. 880.00
(c) Labour =
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 1.25 Nos. @ Tk. 389.00 each = Tk. 486.25
(iii) Ordinary labour 1.25 Nos. @ Tk. 245.00 each = Tk. 306.25
(d) Washing of sand, local carriage, curing, & sundries etc. L.S. = Tk. 245.00
Total = Tk. 2,168.25
Profit 10.00% = Tk. 216.83
Overhead 3.50% = Tk. 75.89
= Tk. 2,460.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 143.23
Grand total = Tk. 2,604.20
Average of 1/2"[from item No. 123 (a-ii)] and 3/4" = Tk. 2,446.56
Rate per sft. = Tk. 24.47
Rate per sqm. = Tk. 263.40

(i) Ground floor Say, Tk. 263 .00 Per sqm.

Item No.- 15.4


Min 1/2" thick cement plaster (1:6) to walls (average of 1/2" on one side and 3/4" on other side).
Considering 100 sft. of work
A. For 1/2" thick cement plaster (1:6) to walls
(a) Sand (F.M. 1.2) 6 cft. @ Tk. 1,700.00 Per % cft. = Tk. 102.00
(b) Cement 0.75 bag @ Tk. 440.00 Per bag = Tk. 330.00
(c) Labour
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 1.00 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(d) Washing of sand, local carriage, scaffolding, curing, & sundries etc. L.S. = Tk. 245.00
Total = Tk. 1,434.25
Profit 10.00% = Tk. 143.43
Overhead 3.50% = Tk. 50.20
Tk. 1,627.88
VAT 5.50% = Tk. 89.53
Grand total = Tk. 1,717.41
B. For 3/4" thick cement plaster (1:6) to walls
(a) Sand (F.M. 1.2) 8.25 cft. @ Tk. 1,700.00 Per % cft. = Tk. 140.25
(b) Cement 1.1 bag @ Tk. 440.00 Per bag = Tk. 484.00
(c) Labour =
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 1.00 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(d) Washing of sand, local carriage, scaffolding, curing, & sundries etc. L.S. = Tk. 245.00
Total = Tk. 1,626.50
Profit 10.00% = Tk. 162.65
Overhead 3.50% = Tk. 56.93
= Tk. 1,846.08
Add VAT with adjustment factor 1.0582 5.50% = Tk. 107.44
Grand total = Tk. 1,953.52
Analysis of PWD SoR 2014 for Civil Works 315

Average of A & B = Tk. 1,835.47


(i) Ground floor Rate per sft = Tk. 18.35
Rate per sqm. = Tk. 197.52

Say, Tk. 198 .00 Per sqm.

Item No.- 15.5


1/4" thick cement plaster (1:4) to ceiling, column, beams etc. and all other RCC surfaces
Considering 100 sft. of work
(a) Sand (F.M. 1.2) 2.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 42.50
(b) Cement 0.5 bag @ Tk. 440.00 Per bag = Tk. 220.00
(c) Extra cement for grouting 0.125 bag @ Tk. 440.00 Per bag = Tk. 55.00
(d) Labour
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 1.00 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(iv) Extra labour for chiping RCC surface 0.50 No. @ Tk. 245.00 each = Tk. 122.50
(v) Washing of sand, scaffolding, curing, sundries, local carriage etc. L.S. = Tk. 245.00
Total = Tk. 1,442.25
Profit 10.00% = Tk. 144.23
Overhead 3.50% = Tk. 50.48
= Tk. 1,636.96
Add VAT with adjustment factor 1.0582 5.50% = Tk. 95.27
Grand total = Tk. 1,732.23
Rate per sft. = Tk. 17.32
Rate per sqm. = Tk. 186.43

i) For ground floor Say, Tk. 186 .00 Per sqm.

Item No.- 15.6


Min 1/4" thick cement plaster (1:3) to walls
Considering 100 sft. of work
A. For 1/2" thick cement plaster (1:3) to walls
(a) Sand (F.M. 1.2) 4.7 cft. @ Tk. 1,700.00 Per % cft. = Tk. 79.90
(b) Cement 1.25 bag @ Tk. 440.00 Per bag = Tk. 550.00
(c) Labour
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 1.00 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(d) Washing of sand, local carriage, scaffolding, curing, & sundries etc. L.S. = Tk. 245.00
Total = Tk. 1,632.15
Profit 10.00% = Tk. 163.22
Overhead 3.50% = Tk. 57.13
= Tk. 1,852.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 107.82
Grand total = Tk. 1,960.32
B. For 1/4" thick cement plaster (1:3) to walls
(a) Sand (F.M. 1.2) 2.35 cft. @ Tk. 1,700.00 Per % cft. = Tk. 39.95
(b) Cement 0.625 bag @ Tk. 440.00 Per bag = Tk. 275.00
(c) Labour
(i) Head mason 1/4 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 1.00 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(d) Washing of sand, local carriage, scaffolding, curing, & sundries etc. L.S. = Tk. 245.00
Total = Tk. 1,317.20
Profit 10.00% = Tk. 131.72
Overhead 3.50% = Tk. 46.10
Analysis of PWD SoR 2014 for Civil Works 316

= Tk. 1,495.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 87.01
Grand total = Tk. 1,582.03
Average of A & B = Tk. 1,771.18
(i) Ground floor Rate per sft = Tk. 17.71
Rate per sqm. = Tk. 190.63

Say, Tk. 191 .00 Per sqm.

Item No.- 15.7


Flush pointing with cement mortar (1:2) to walls
Considering 100 sft. of work
(a) Sand (F.M. 1.2) 1.0 cft. @ Tk. 1,700.00 Per % cft. = Tk. 17.00
(b) Cement 0.4 bag @ Tk. 440.00 Per bag = Tk. 176.00
(c) Labour
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 0.5 No. @ Tk. 389.00 each = Tk. 194.50
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(d) Washing of sand, scaffolding, curing, sundries, local carriage etc. L.S. = Tk. 147.00
Total = Tk. 902.75
Profit 10.00% = Tk. 90.28
Overhead 3.50% = Tk. 31.60
= Tk. 1,024.63
Add VAT with adjustment factor 1.0582 5.50% = Tk. 59.63
Grand total = Tk. 1,084.26
Rate per sft. = Tk. 10.84
Rate per sqm. = Tk. 116.68

(i) For ground floor Say, Tk. 117 .00 Per sqm.

Item No.- 15.8


Ruled pointing with cement mortar (1:2) to walls
Considering 100 sft. of work
(a) Sand (F.M. 1.2) 1.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 25.50
(b) Cement 0.5 bag @ Tk. 440.00 Per bag = Tk. 220.00
(c) Labour
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(d) Washing of sand, scaffolding, curing, sundries, local carriage etc. L.S. = Tk. 147.00
Total = Tk. 1,149.75
Profit 10.00% = Tk. 114.98
Overhead 3.50% = Tk. 40.24
= Tk. 1,304.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 75.95
Grand total = Tk. 1,380.92
Rate per sft. = Tk. 13.81
Rate per sqm. = Tk. 148.65
(i) For ground floor Say, Tk. 149 .00 Per sqm.
Item No.- 15.9
Raised / Tack pointing with cement mortar (1:2) to walls
Considering 100 sft. of work
(a) Sand (F.M. 1.2) 3 cft. @ Tk. 1,700.00 Per % cft. = Tk. 51.00
(b) Cement 1 bag @ Tk. 440.00 Per bag = Tk. 440.00
(c) Cost of pumic stone 0.25 No. @ Tk. 60.00 each Tk. 15.00
(d) Labour
(i) Head mason 0.5 No. @ Tk. 493.00 each = Tk. 246.50
Analysis of PWD SoR 2014 for Civil Works 317

(ii) Mason 2 Nos. @ Tk. 389.00 each = Tk. 778.00


(iii) Skilled labour 2 Nos. @ Tk. 303.00 each Tk. 606.00
(iv) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(e) Washing of sand, scaffolding, curing, sundries, local carriage etc. L.S. = Tk. 147.00
Total = Tk. 2,773.50
Profit 10.00% = Tk. 277.35
Overhead 3.50% = Tk. 97.07
= Tk. 3,147.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 183.21
Grand total = Tk. 3,331.13
Rate per sft. = Tk. 33.31
Rate per sqm. = Tk. 358.55

(i) For ground floor Say, Tk. 359 .00 Per sqm.

Item No.- 15.10


Providing drip course / nosing / throating with cement mortar (1:2).
Considering 25 rft. of work
(a) Sand (F.M. 1.2) 0.52 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.84
(b) Cement 0.08 bag @ Tk. 440.00 Per bag = Tk. 35.20
(c) Labour
(i) Mason 1.0 No. @ Tk. 389.00 each = Tk. 389.00
(ii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
(d) Washing of sand, scaffolding, curing, sundries, local carriage etc. L.S. = Tk. 24.50
Total = Tk. 580.04
Profit 10.00% = Tk. 58.00
Overhead 3.50% = Tk. 20.30
= Tk. 658.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 38.32
Grand total = Tk. 696.66
Rate per rft. = Tk. 27.87
Rate per rm. = Tk. 91.44

Ground Floor Say, Tk. 91 .00 Per rm.

Item No.- 15.11.1

Making groove in plaster on outside wall upto size 50mm X 6mm


Consideration 20'-0" work
Size of groove 2" X 1/4"
a) Labour Cost:
a) Mason 0.125 No. @ 389 each = 48.63
b) Ordinary Labour 0.125 No. @ 245 each = 30.63
b) Scaffolding, Tools, Sundries etc. LS. = 10.00
Total = Tk. 89.26
Profit 10.00% = Tk. 8.93
Overhead 3.50% = Tk. 3.12
= Tk. 101.31
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5.90
Grand total = Tk. 107.21
Rate per rft. = Tk. 5.36
Rate per rm. = Tk. 17.59

Say, Tk. 18 .00 Per rm.

Item No.- 15.11.2


Groove cutting 38mm x 6mm in cement plaster (1:2) to wall at outer surface of window top and bottom level
Break-up for 25 rft
Analysis of PWD SoR 2014 for Civil Works 318

1. Mason 0.1875 No. @ Tk. 389.00 each = Tk. 72.94


2. Skilled labour 0.1875 No. @ Tk. 303.00 each = Tk. 56.81
3. Curing, tools and plant, sundries LS = Tk. 40.83
Total = Tk. 170.58
Profit 10.00% = Tk. 17.06
Overhead 3.50% = Tk. 5.97
= Tk. 193.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 11.27
Grand total = Tk. 204.88
Rate per rft. = Tk. 8.20
Rate per rm = Tk. 26.90

Say Tk. 27 .00 per rm.

Item No.- 15.12


Additional Rate for Plaster and Pointing work in additional floors
15.12.1 Add for each addl. floor up to 5th floor (1/3 lab. per % sft.) Per sqm = Tk. 11.00
15.12.2 Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft.) Per sqm = Tk. 17.00
15.12.3 Add for each addl. floor above 9th floor (2/3 lab. per % sft.) Per sqm = Tk. 22.00

Item No.- 15.13


Average 4" thick finished lime terracing with 3/4" down graded 1st class brick chips, surki and stone lime (7:2:2)
Considering 100 cft. of work (300 sft. Area)
(A) Cost of materials
(i) 1st class bricks 820 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 6,150.00
(ii) Stone lime 539.33 kg. @ Tk. 19.00 Per kg = Tk. 10,247.27
(iii) 1st class surki 34.77 cft. @ Tk. 58.00 Per cft. = Tk. 2,016.66
(iv) Cost for breaking chips 96.47 cft. @ Tk. 894.00 Per % cft. = Tk. 862.44
(B) Labour cost
(i) Labour for slacking lime 1 No.
(ii) Labour for dry mixing 2 Nos.
(iii) Labour for wet mixing 6 Nos.
(iv) Labour for lifting and casting 3 Nos.
(v) Labour for beating 12 Nos.
(vi) Labour for finishing 1 No.
Total 25 Nos. @ Tk. 245.00 each = Tk. 6,125.00
(vii) Head Mason 1 No. @ Tk. 493.00 each = Tk. 493.00
(viii) Mason for finishing (300 sft.) 2 Nos. @ Tk. 389.00 each = Tk. 778.00
C. Miscellaneous
(i) Expenditure for making platform: soling excluding cost of bricks L.S. = Tk. 306.25
(ii) Expenditure for providing polythene cover L.S. = Tk. 245.00
(iii) Local carriage, storage, tools & plants, gumboot, koppa etc. L.S. = Tk. 490.00
(iv) Curing 300 sft. @ Tk. 2.04 L.S. = Tk. 612.00
Total = Tk. 28,325.62
Profit 10.00% = Tk. 2,832.56
Overhead 3.50% = Tk. 991.40
= Tk. 32,149.58
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,871.14
Grand total = Tk. 34,020.72
Rate per cft. = Tk. 340.21
Rate per cum. = Tk. 12,014.52

Say, Tk. 12,015 .00 Per cum.

Item No.- 15.14


Precast ventilator with 1" thick cement mortar (1:2) including fitting fixing in position.
Considering 6 sft. of work
Analysis of PWD SoR 2014 for Civil Works 319

(a) Cement 0.25 bag. @ Tk. 440.00 Per bag = Tk. 110.00
(b) Sand 1.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 25.50
(c) Plaster (1:4) 18 sft. @ Tk. 15.27 Per sft. = Tk. 274.86
(d) Mason 0.75 Nos. @ Tk. 389.00 each = Tk. 291.75
(e) Labour 0.50 Nos. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 824.61
Profit 10.00% = Tk. 82.46
Overhead 3.50% = Tk. 28.86
= Tk. 935.93
Add VAT with adjustment factor 1.0582 5.50% = Tk. 54.47
Grand total = Tk. 990.40
Rate per sft. = Tk. 165.07
Rate per sqm. = Tk. 1,776.81

Say, Tk. 1,777 .00 Per sqm.

Item No.- 15.15


3" thick cornice of brick masonry (1:6)
Considering 100 rft. of work

(a) 0'-3" x 0'-3" Brick work (1:6) 6.25 cft. @ Tk. 132.89 Per cft. = Tk. 830.56
(b) Extra labour for brick moulding
& plastering 100 rft. @ Tk. 24.50 Per rft. = Tk. 2,450.00
(c) (3" + 3" + 3")= 9" width
and 1/2" thick cement plaster (1:6)
from item No. 123(a) - I 75 sft @ Tk. 15.27 Per sft. = Tk. 1,145.25
Total = Tk. 4,425.81
Profit 10.00% = Tk. 442.58
Overhead 3.50% = Tk. 154.90
= Tk. 5,023.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 292.36
Grand total = Tk. 5,315.65
Rate per rft. = Tk. 53.16
Rate per rm. = Tk. 174.42

Say, Tk. 174 .00 Per rm.

Item No.- 15.16


Supplying & embedding of 19 to 32 mm height and 19 mm width broken glass
placed @ app 25 mm c/c into plaster
Considering 100 sft. of work
1. Cost of 3 mm thick glass
(30% of cost of new glass) 95.00 sft.
Add 5% wastage= 4.75 sft.
99.75 sft. @ Tk. 12.30 Per sft. = Tk. 1,226.93
2. Mason 0.5 No. @ Tk. 389.00 each = Tk. 194.50
3. Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
4. Scaffolding L.S. = Tk. 60.00
Total = Tk. 1,632.93
Profit 10.00% = Tk. 163.29
Overhead 3.50% = Tk. 57.15
= Tk. 1,853.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 107.87
Grand total = Tk. 1,961.24
Rate Per sft. = Tk. 19.61
Rate per sqm. = Tk. 211.08
Analysis of PWD SoR 2014 for Civil Works 320

Say, Tk. 211 .00 Per sqm.

DIVISION 16 : WASHING, PAINTING, DISTEMPERING, POLISHING & VARNISHING


Item No.- 16.1
White washing: 3 coats
Considering 1000 sft. of work
(a) Slaked lime 18.66 kg @ Tk. 19.00 Per kg. = Tk. 354.54
(b) Gum 0.3 kg @ Tk. 115.00 Per kg. = Tk. 34.50
(c) Blue 0.2 kg @ Tk. 163.00 Per kg. = Tk. 32.60
(d) Labour
(i) Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
(ii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(d) Scaffolding, sundries, local carriage etc. L.S. = Tk. 122.50
Total = Tk. 1,372.64
Profit 10.00% = Tk. 137.26
Overhead 3.50% = Tk. 48.04
= Tk. 1,557.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 90.67
Grand total = Tk. 1,648.61
Rate per sft. = Tk. 1.65
Rate per sqm. = Tk. 17.76

Say, Tk. 18 .00 Per sqm.

Item No.- 16.2


Colour washing: 3 coats
Considering 1000 sft. of work
(a) Slaked lime 18.66 kg @ Tk. 19.00 Per kg. = Tk. 354.54
(b) Gum 0.3 kg @ Tk. 115.00 Per kg. = Tk. 34.50
(c) Blue 0.2 kg @ Tk. 163.00 Per kg. = Tk. 32.60
(d) Colour pigment 1 kg @ Tk. 182.00 Per kg. = Tk. 182.00
(e) Labour
(i) Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
(ii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(f) Scaffolding, sundries, local carriage etc. L.S. = Tk. 122.50
Total = Tk. 1,554.64
Profit 10.00% = Tk. 155.46
Overhead 3.50% = Tk. 54.41
= Tk. 1,764.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 102.70
Grand total = Tk. 1,867.21
Rate per sft. = Tk. 1.87
Rate per sqm. = Tk. 20.13
Say, Tk. 20 .00 Per sqm.
Item No.- 16.3
Cement paint 3 coats (one coat is for priming)
Considering 100 sft. of work
1. Skilled labour for cleaning,
washing and wetting etc. 0.10 No. @ Tk. 303.00 each = Tk. 30.30
2. Painter for applying paint 0.50 No. @ Tk. 423.00 each = Tk. 211.50
3. Helper to painter 0.50 No. @ Tk. 304.00 each = Tk. 152.00
4. Labour for 7 days curing: 1.00 No. @ Tk. 245.00 each = Tk. 245.00
5. Scaffolding, local carriage, sundries etc. L.S. = Tk. 61.25
6. Cement paint 3.25 kg. @ Tk. 90.00 Per kg. = Tk. 292.50
Total = Tk. 992.55
Profit 10.00% = Tk. 99.26
Analysis of PWD SoR 2014 for Civil Works 321

Overhead 3.50% = Tk. 34.74


= Tk. 1,126.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 65.57
Grand total = Tk. 1,192.12
Rate per sft. = Tk. 11.92
Rate per sqm. = Tk. 128.31

Say, Tk. 128 .00 Per sqm.

Item No.- 16.4


Applying 3-coat of weather coat in exterior wall surface
Break-up for 100 sft. Area
1. Painter 1 No. @ Tk. 423.00 each = Tk. 423.00
2. Helper 1 No. @ Tk. 304.00 each = Tk. 304.00
3. Cleaning surface with sand paper, scaffolding etc. L.S = Tk. 61.25
4. Weather coat paint 1.54 liter @ Tk. 318.40 liter = Tk. 490.34
5. Sealer 0.89 liter @ Tk. 209.60 liter = Tk. 186.54
Total = Tk. 1,465.13
Profit 10.00% = Tk. 146.51
Overhead 3.50% = Tk. 51.28
= Tk. 1,662.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 96.78
Grand total = Tk. 1,759.70
Rate per sft. = Tk. 17.60
Rate per sqm. = Tk. 189.45

Say Tk. 189 .00 per sqm.

Item No.- 16.5


Applying 3-coats silicon based water repellent on exposed brick surface
Break-up for 100 sft. Area
1. Painter 1 No. @ Tk. 423.00 each = Tk. 423.00
2. Helper 1 No. @ Tk. 304.00 each = Tk. 304.00
3. Scaffolding, local carriage, sundries etc. L.S = Tk. 122.50
4. Silicon based paint 2 liter @ Tk. 322.22 liter = Tk. 644.44
Total = Tk. 1,493.94
Profit 10.00% = Tk. 149.39
Overhead 3.50% = Tk. 52.29
= Tk. 1,695.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 98.69
Grand total = Tk. 1,794.31
Rate per sft. = Tk. 17.94
Rate per sqm. = Tk. 193.11
Say Tk. 193 .00 per sqm.
Item No.- 16.6
Painting to doors and windows frame and shutters with synthetic enamel paint two coats
over a coat of priming
Considering 100 sft. of work
1. Painter 1.00 No. @ Tk. 423.00 each = Tk. 423.00
2. Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
3. Scaffolding, sundries etc. L.S. = Tk. 147.00
4. Paint 1.00 liter @ Tk. 310.00 Per liter = Tk. 310.00
5. Sealer 1.00 liter @ Tk. 149.00 Per liter = Tk. 149.00
6. Thinner 1.00 liter @ Tk. 140.00 Per liter = Tk. 140.00
Tk. 1,414.00
Profit 10.00% = Tk. 141.40
Overhead 3.50% = Tk. 49.49
Analysis of PWD SoR 2014 for Civil Works 322

= Tk. 1,604.89
Add VAT with adjustment factor 1.0582 5.50% = Tk. 93.41
Grand total = Tk. 1,698.30
Rate per sft. = Tk. 16.98
Rate per sqm. = Tk. 182.77

Say, Tk. 183 .00 Per sqm.

Item No.- 16.7


Synthetic polyvinyl distempering 2 coats over a coat of priming
Considering 100 sft. of work
1. Painter 1.00 No. @ Tk. 423.00 each = Tk. 423.00
2. Painter helper 1.00 No. @ Tk. 304.00 each = Tk. 304.00
3. Scaffolding, sundries etc. L.S. = Tk. 81.67
4. Distemper 1.00 liter @ Tk. 116.66 Per liter = Tk. 116.66
5. Under-coat/sealer 1.00 liter @ Tk. 209.60 Per liter = Tk. 209.60
Total = Tk. 1,134.93
Profit 10.00% = Tk. 113.49
Overhead 3.50% = Tk. 39.72
= Tk. 1,288.14
Add VAT with adjustment factor 1.0582 5.50% = Tk. 74.97
Grand total = Tk. 1,363.11
Rate per sft. = Tk. 13.63
Rate per sqm. = Tk. 146.71
Say, Tk. 147 .00 Per sqm.
Item No.- 16.8.1
Plastic emulsion paint to walls and ceiling 2 coats over a coat of primer
Considering 100 sft. of work
1. Painter 1.00 No. @ Tk. 423.00 each = Tk. 423.00
2. Painter helper 1.00 No. @ Tk. 304.00 each = Tk. 304.00
3. Scaffolding, sundries etc. L.S. = Tk. 73.50
4. Plastic emulsion paint 1.00 litre @ Tk. 247.25 Per litre = Tk. 247.25
5. Sealer / under-coat 0.90 litre @ Tk. 205.00 Per litre = Tk. 184.50
Total = Tk. 1,232.25
Profit 10.00% = Tk. 123.23
Overhead 3.50% = Tk. 43.13
= Tk. 1,398.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 81.40
Grand total = Tk. 1,480.01
Rate per sft. = Tk. 14.80
Rate per sqm. = Tk. 159.31

Say, Tk. 159 .00 Per sqm.


Item No.- 16.8.2
Plastic emulsion paint to walls and ceiling 2 coats over lime putty
Break-up for 100 sft. Area
1. Painter 1.5 No. @ Tk. 423.00 each = Tk. 634.50
2. Helper 1.5 No. @ Tk. 304.00 each = Tk. 456.00
3. Cleaning surface with sand paper, scaffolding, tools and plant etc. L.S = Tk. 50.00
4. Ready-mix putty 1.54 liter @ Tk. 76.00 liter = Tk. 117.04
5. Sealer 0.89 liter @ Tk. 228.00 liter = Tk. 202.92
6. Plastic emulsion paint 1 liter @ Tk. 247.25 liter = Tk. 247.25
Total = Tk. 1,707.71
Profit 10.00% = Tk. 170.77
Overhead 3.50% = Tk. 59.77
= Tk. 1,938.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 112.81
Analysis of PWD SoR 2014 for Civil Works 323

Grand total = Tk. 2,051.06


Rate per sft. = Tk. 20.51
Rate per sqm. = Tk. 220.77

Say Tk. 221 .00 per sqm.

Item No.- 16.9.1


Acrylic emulsion paint to walls and ceiling 2 coats over a coat of acrylic sealer
Considering 100 sft. of work
1. Painter 1.00 No. @ Tk. 423.00 each = Tk. 423.00
2. Painter helper 1.00 No. @ Tk. 304.00 each = Tk. 304.00
3. Scaffolding, sundries etc. L.S. = Tk. 73.50
4. Acrylic emulsion paint 1.00 litre @ Tk. 228.70 Per litre = Tk. 228.70
5. Sealer / under-coat 1.00 litre @ Tk. 226.60 Per litre = Tk. 226.60
Total = Tk. 1,255.80
Profit 10.00% = Tk. 125.58
Overhead 3.50% = Tk. 43.95
= Tk. 1,425.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 82.96
Grand total = Tk. 1,508.29
Rate per sft. = Tk. 15.08
Rate per sqm. = Tk. 162.32

Say, Tk. 162 .00 Per sqm.


Item No.- 16.9.2
Acrylic emulsion paint to walls and ceiling 2 coats over lime putty
Break-up for 100 sft. Area
1. Painter 1.5 No. @ Tk. 423.00 each = Tk. 634.50
2. Helper 1.5 No. @ Tk. 304.00 each = Tk. 456.00
3. Cleaning surface with sand paper, scaffolding, tools and plant etc. L.S = Tk. 50.00
4. Ready-mix putty 1.54 liter @ Tk. 76.00 liter = Tk. 117.04
5. Sealer 0.89 liter @ Tk. 226.60 liter = Tk. 201.67
6. Acrylic emulsion paint 1 liter @ Tk. 228.70 liter = Tk. 228.70
Total = Tk. 1,687.91
Profit 10.00% = Tk. 168.79
Overhead 3.50% = Tk. 59.08
= Tk. 1,915.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 111.50
Grand total = Tk. 2,027.28
Rate per sft. = Tk. 20.27
Rate per sqm. = Tk. 218.19
Say Tk. 218 .00 per sqm.
Item No.- 16.10 Omitted

Providing antisalinity sealer before painting on damped plastered surface


Considering 100 sft. of work
a) Material
i) De-salt s-01 or equivalent (400 sft cover with per liter. 0.25
So 100 sftliter
of work @
requiredTk.
of 1/4 liter) - Per liter = 0
ii) Labour Charge:

b) Painter 0.125 No. @ Tk. 423.00 each = 52.875


Total = Tk. 52.88
Profit 10.00% = Tk. 5.29
Overhead 3.50% = Tk. 1.85
= Tk. 60.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3.49
Grand total = Tk. 63.51
Rate per sft. = Tk. 0.64
Rate per sqm. = Tk. 6.89
Analysis of PWD SoR 2014 for Civil Works 324

Say Tk. - .00 per sqm.

Item No.- 16.11 omitted

Renewing plaster in/c damp proof treatment with chemical Desalt S-01 & Foam Lub
Assuming cost for removing plaster and replasteing damp proping Treatment with chemical.
Considering 100 sft. of work
a) I) Striping of old plaster (R.S.1) 9.29 sqm @ Tk. 8.00 Per sqm = Tk. 74.32
II) Re plastering with (1:6) 100 sft @ Tk. 993.00 Per % sft = Tk. 993.00
b) I) De-salt S-01 on brick surface (400 sft covered with 1 liter
0.25
so 100.00
litersft of @
work requireed
Tk. 1/4
350.00
liter) Per liter = Tk. 87.50
ii) Foam lub or equivalent grounting in brick surface 3 coats
0.66150.00lbsft covered
@ withTk.
1 liter, 100.00
233.00sft of work required
Per lb0.66
= lb Tk. 153.78
iii) Foam lub with cement morter for plasteng (250 ml with
187.5
per bag of
mlcement@, so 100
Tk.
sft of work
233.00
required 187.50
Per
ml)liter = Tk. 43.69
iv) De-salt S-01 in plaster surface 400.00 sft covered with0.25
1 liter, so lb
100.00 sft
@ of work
Tk.equired
350.00
1/4 liter Per lb = Tk. 87.50
v) Labour fro De-salting. Foam lub groutng etc. 0.25 lb @ Tk. 245.00 Per lb = Tk. 61.25
Total = Tk. 1,501.04
Profit 10.00% = Tk. 150.10
Overhead 3.50% = Tk. 52.54
= Tk. 1,703.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 99.16
Grand total = Tk. 1,802.84
Rate per sft. = Tk. 18.03
Rate per sqm. = Tk. 194.07

Say Tk. - .00 per sqm.


Item No.- 16.12
Textured painting with sealer coat, texure coat and top coat
Considering 100 sft. of work
1. Machine operator 1.00 No. @ Tk. 423.00 each = Tk. 423.00
2. Helper 1.00 No. @ Tk. 304.00 each = Tk. 304.00
3. Cost of electricity, machinery hire charges etc. L.S. = Tk. 171.50
4. Scaffolding, sundries etc. L.S. = Tk. 73.50
5. Texured paint 12.12 liters @ Tk. 288.93 Per liter = Tk. 3,501.83
Total = Tk. 4,473.83
Profit 10.00% = Tk. 447.38
Overhead 3.50% = Tk. 156.58
= Tk. 5,077.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 295.53
Grand total = Tk. 5,373.32
Rate per sft. = Tk. 53.73
Rate per sqm. = Tk. 578.35
Say, Tk. 578 .00 Per sqm.
Item No.- 16.13
Chlorinated rubber painting of best quality & approved colour.
Considering 100 sft. of work
1. Painter 1.00 No. @ Tk. 423.00 each = Tk. 423.00
2. Painter helper 1.00 No. @ Tk. 304.00 each = Tk. 304.00
3. Scaffolding, sundries etc. L.S. = Tk. 147.00
4. Chlorinated rubber paint 1.10 litre @ Tk. 700.00 Per litre = Tk. 770.00
5. Sealer / under-coat 1.10 litre @ Tk. 545.00 Per litre = Tk. 599.50
6. Thinner : T-2 0.60 litre @ Tk. 212.00 Per litre = Tk. 127.20
Total = Tk. 2,370.70
Profit 10.00% = Tk. 237.07
Overhead 3.50% = Tk. 82.97
= Tk. 2,690.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 156.60
Grand total = Tk. 2,847.34
Rate per sft. = Tk. 28.47
Analysis of PWD SoR 2014 for Civil Works 325

Rate per sqm. = Tk. 306.45

Say, Tk. 306 .00 Per sqm.

Item No.- 16.14


French polishing 3 coats
Considering 100 sft. of work
(a) French powder 0.25 kg. @ Tk. 40.00 Per kg = Tk. 10.00
(b) Spirit 4 Ibs. @ Tk. 92.00 Per Ib. = Tk. 368.00
(c) Gala 0.15 kg. @ Tk. 1,600.00 Per kg = Tk. 240.00
(d) Karpa 0.05 kg. @ Tk. 500.00 Per kg = Tk. 25.00
(e) Sand paper 4 Nos. @ Tk. 11.33 each = Tk. 45.32
(f) Putty 0.5 kg. @ Tk. 78.00 Per kg = Tk. 39.00
(g) Markin cloth 0.5 yard @ Tk. 15.00 Per yard = Tk. 7.50
(h) Cotton 0.03 Ibs. @ Tk. 75.00 Per Ib. = Tk. 2.25
(i) Painter 2 Nos. @ Tk. 423.00 each = Tk. 846.00
(j) Helper 2 Nos. @ Tk. 304.00 each = Tk. 608.00
(k) Scaffolding, sundries etc. L.S. = Tk. 73.50
Total = Tk. 2,264.57
Profit 10.00% = Tk. 226.46
Overhead 3.50% = Tk. 79.26
= Tk. 2,570.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 149.59
Grand total Tk. 2,719.88
Rate per sft.= Tk. 27.20
Rate per sqm.= Tk. 292.78

Say, Tk. 293 .00 Per sqm.

Item No.- 16.15.1


Wood varnishing with varnish (Yacht)
Considering 100 sft. of work
1. Sand paper 4 Nos. @ Tk. 11.33 each = Tk. 45.32
2. Markin cloth 0.5 yard. @ Tk. 15.00 Per yard = Tk. 7.50
3. Painter 1 Nos. @ Tk. 423.00 each = Tk. 423.00
4. Ordinary labour 1 Nos. @ Tk. 245.00 each = Tk. 245.00
5. Scaffolding, sundries, T & P etc. L.S. = Tk. 73.50
6. Cost of varnish: Yacht 1.00 litre @ Tk. 250.00 Per litre = Tk. 250.00
7. Thinner 0.91 litre @ Tk. 104.00 Per litre = Tk. 94.64
Total = Tk. 1,138.96
Profit 10.00% = Tk. 113.90
Overhead 3.50% = Tk. 39.86
= Tk. 1,292.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 75.24
Grand total = Tk. 1,367.96
Rate per sft. = Tk. 13.68
Rate per sqm. = Tk. 147.25

Say, Tk. 147 .00 Per sqm.

Item No.- 16.15.2


Wood varnishing with varnish (Egg-shell)
Considering 100 sft. of work
1. Sand paper 4.00 Nos. @ Tk. 11.33 each = Tk. 45.32
2. Markin cloth 0.50 yard. @ Tk. 15.00 Per yard = Tk. 7.50
3. Painter 1.00 No. @ Tk. 423.00 each = Tk. 423.00
4. Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
Analysis of PWD SoR 2014 for Civil Works 326

5. Scaffolding, sundries, T & P etc. L.S. = Tk. 73.50


6. Cost of varnish: Egg-shell 1.33 litre @ Tk. 250.00 Per litre = Tk. 332.50
7. Thinner 0.34 litre @ Tk. 104.00 Per litre = Tk. 35.36
Total = Tk. 1,162.18
Profit 10.00% = Tk. 116.22
Overhead 3.50% = Tk. 40.68
= Tk. 1,319.08
Add VAT with adjustment factor 1.0582 5.50% = Tk. 76.77
Grand total = Tk. 1,395.85
Rate per sft. = Tk. 13.96
Rate per sqm. = Tk. 150.27

Say, Tk. 150 .00 Per sqm.

Item No.- 16.15.3


Wood varnishing with varnish (Matt)
Considering 100 sft. of work
1. Sand paper 4 Nos. @ Tk. 11.33 each = Tk. 45.32
2. Markin cloth 0.5 yard. @ Tk. 15.00 Per yard = Tk. 7.50
3. Painter 1 No. @ Tk. 423.00 each = Tk. 423.00
4. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
5. Scaffolding, sundries, T & P etc. L.S. = Tk. 73.50
6. Cost of varnish: Matt 1.30 litre @ Tk. 250.00 Per litre = Tk. 325.00
7. Thinner 0.35 litre @ Tk. 104.00 Per litre = Tk. 36.40
Total = Tk. 1,155.72
Profit 10.00% = Tk. 115.57
Overhead 3.50% = Tk. 40.45
= Tk. 1,311.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 76.34
Grand total Tk. 1,388.08
Rate per sft.= Tk. 13.88
Rate per sqm.= Tk. 149.40

Say, Tk. 149 .00 Per sqm.

DIVISION 17 : DRAIN AND APRON


Item No.- 17.1
Construction of 1'-0" clear width and depth upto 1'-0" masonry surface drain
(a) Earth work in excavation:
10'-0" x 1'-10" x 1'-3"(av.)= 22.92 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 52.06
(b) Brick-flat soling:
10'-0" x 1'-10"= 18.33 sft. @ Tk. 2,744.25 Per % sft. = Tk. 503.02
(c) Cement concrete (1:3:6):
10'-0" x 1'-10" x 0'-3"(av.)= 4.58 cft. @ Tk. 14,713.64 Per % cft. = Tk. 673.88
(d) 5" thick brick work (1:4):
2 x 10'-0" x 0'-9"= 15 sft. @ Tk. 6,471.18 Per % sft. = Tk. 970.68
(e) 1/2" thick cement plast:er (1:4)
with neat cement finish:
10'-0" x 4'-0"= 40 sft. @ Tk. 1,906.00 Per % sft = Tk. 762.40
Total = Tk. 2,962.04
Profit 10.00% = Tk. 296.20
Overhead 3.50% = Tk. 103.67
Analysis of PWD SoR 2014 for Civil Works 327

= Tk. 3,361.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 195.67
Grand total = Tk. 3,557.58
Rate per rft.. = Tk. 355.76
Rate per rm = Tk. 1,167.25

Say, Tk. 1,167 .00 Per rm.

Item No.- 17.2


Construction of surface drain of 2'-0" (av.) depth and 0'-9" clear width at bottom and 1'-0"
at top having 5" thick cement concrete curb etc. masonry surface drain
Considering 10 rft. of work
(a) Earth work in excavation:
10'-0" x (2'-7" + 1'-7")/2 x 2'-7"= 53.66 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 121.89
(b) Brick-flat soling:
10'-0" x 1'-10"= 18.30 sft. @ Tk. 2,744.25 Per % sft. = Tk. 502.20
(c) Cement concrete (1:2:4):
10'-0" x 3'-7" x 0'-5"= 14.93 cft. @ Tk. 17,637.01 Per % cft. = Tk. 2,633.21
(d) 5" thick brick work (1:4):
2 x 10'-0" x 1'-0"= 20 sft. @ Tk. 6,471.18 Per % sft. = Tk. 1,294.24
(e) 1/2" thick cement plast:er (1:4)
with neat cement finish:
10'-0" x 6'-7"= 65.83 sft. @ Tk. 1,906.00 Per % sft. = Tk. 1,254.72
(f) Cost of polythene:
10'-0" x 6'-0"= 50 sft. @ Tk. 262.19 Per % sft. Tk. 131.10
Total = Tk. 5,937.36
Profit 10.00% = Tk. 593.74
Overhead 3.50% = Tk. 207.81
= Tk. 6,738.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 392.21
Grand total = Tk. 7,131.12
Rate per rft. = Tk. 713.11
Rate per rm. = Tk. 2,339.71

Say, Tk. 2,340 .00 Per rm.


Analysis of PWD SoR 2014 for Civil Works 328

IItem No.- 17.3


Providing apron with 2" or 50 mm thick cement concrete (1:2:4) and one layer brick flat
soling at bottom.
Considering 100 sft. of work
(a) For concrete of (1:2:4) 100 cft. @ Tk. 17,637.01 Per % cft. = Tk. 17,637.01
Cost for 2" thick 100 sft. concrete = Tk. 2,939.50
Labour cost for 2" thick 100 sft. concrete
(i) Mason for neat finish 0.5 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Ordinary lab. for neat finish 1 No. @ Tk. 245.00 each = Tk. 245.00
(iii) Extra cement for neat finish 0.5 bag. @ Tk. 440.00 Per bag = Tk. 220.00
= Tk. 659.50
Total cost for 100 sft. concrete = Tk. 3,599.00
(b) One layer brick flat soling 100 sft. @ Tk. 2,744.25 Per % sft. = Tk. 2,744.25
(c) Earth work: 100 sft. x 0'-5"= 41.67 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 94.66
Total (A+B+C) = Tk. 6,437.91
Profit 10.00% = Tk. 643.79
Overhead 3.50% = Tk. 225.33
= Tk. 7,307.03
Add VAT with adjustment factor 1.0582 5.50% = Tk. 425.28
Grand total = Tk. 7,732.31
Rate per sft. = Tk. 77.32
Rate per sqm. = Tk. 832.27

Say, Tk. 832 .00 Per sqm.

Item No.- 17.4.1


Supplying and laying, fitting, fixing of 9" or 225 mm inside dia RCC pipe excluding cost
of earth cutting & back filling.
Considering 18 rft. of work
(a) Cost of machine made best quality 9" dia RCC
pipe in/c all necessary fittings 18 rft. @ Tk. 160.00 each = Tk. 2,880.00

(b) Sand filling 20 cft. @ Tk. 900.00 Per % sft. = Tk. 180.00

(c) Cement concrete(1:3:6) at 3 nos. joint 3.93 cft. @ Tk. 14,713.64 Per % cft. = Tk. 578.25
(d) Labour charge for laying pipe maintaining proper
slope in/c cost of gasket etc.
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(iii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Total = Tk. 4,161.75
Profit 10.00% = Tk. 416.18
Overhead 3.50% = Tk. 145.66
= Tk. 4,723.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 274.92
Grand total = Tk. 4,998.51
Rate per rft. = Tk. 277.70
Rate per rm. = Tk. 911.13

Say, Tk. 911 .00 Per rm.

Item No.- 17.4.2


Supplying and laying, fitting, fixing of 12" or 300 mm inside dia RCC pipe
excluding cost of earth cutting & back filling.
Considering 18 rft. of work
(a) Cost of machine made best quality 12" dia RCC
pipe in/c necessary fittings. 18 rft. @ Tk. 212.00 each = Tk. 3,816.00
Analysis of PWD SoR 2014 for Civil Works 329

(b) Sand filling 25 cft. @ Tk. 900.00 Per % sft. = Tk. 225.00

(c) Cement concrete(1:3:6) at 2 nos. junctions 4.82 cft. @ Tk. 14,713.64 Per % cft. = Tk. 709.20
(d) Labour charge for laying pipe maintaining proper
slope in/c cost of gasket etc.
(i) Head mason 0.25 No. @ Tk. 493.00 each = Tk. 123.25
(ii) Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(iii) Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
Total = Tk. 5,425.20
Profit 10.00% = Tk. 542.52
Overhead 3.50% = Tk. 189.88
= Tk. 6,157.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 358.38
Grand total = Tk. 6,515.98
Rate per rft. = Tk. 362.00
Rate per rm. = Tk. 1,187.72

Say, Tk. 1,188 .00 Per rm.

Item No.- 17.5


Supplying, laying and fitting-fixing 900 mm dia RCC pipe
Break-up for 4 x 6 rft (1.82 m) = 24 rft. (7.28 m)
1. Cost of pipe 4 No. @ Tk. 13,190.00 each = Tk. 52,760.00
2. Truck fare 1 trip @ Tk. 1,300.00 trip = Tk. 1,300.00
3. Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
4. Skilled labour 2 No. @ Tk. 303.00 each = Tk. 606.00
5. Ordinary labour 12 No. @ Tk. 245.00 each = Tk. 2,940.00
4. Tools and plant, sundries etc. LS = Tk. 510.42
Total = Tk. 58,556.42
Profit 10.00% = Tk. 5,855.64
Overhead 3.50% = Tk. 2,049.47
= Tk. 66,461.53
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,868.13
Grand total = Tk. 70,329.66
Rate per rft. = Tk. 2,930.40
Rate per rm. = Tk. 9,660.67

Say Tk. 9,661 .00 per rm

DIVISION 18 : FALSE CEILING, WALL PANELING


Analysis of PWD SoR 2014 for Civil Works 330

Item No.- 18.1.1


1/2" thick plain particle board ceiling screwed up with wooden frame for normal room height
Considering a panel of 12' x 16'= 192 sft. of work
(a) Cost of Garjan wood:
(7 x 16' + 9 x 12') x 3" x 2"= 9.17 cft.
Add 5% wastage= 0.46 cft.
9.63 cft. @ Tk. 2,000.00 Per cft. = Tk. 19,260.00
(b) Cost of 1/2" thick plain particle board
12'-0" x 16'-0"= 192 sft.
Add 5% wastage= 9.6 sft.
201.6 sft. @ Tk. 35.34 Per sft. = Tk. 7,124.54
(c) Cost of G.I. wire, rowel plug, nails and screws etc. necessary for
fabricating, hoisting and hanging frame and board
(7.5% of cost of wood and board) = Tk. 1,978.84
(d) Cost of fitting, fixing, levelling, finishing,
scaffolding etc (upto 3.5 m height)
(i) Carpenter 10 Nos. @ Tk. 423.00 each = Tk. 4,230.00
(ii) Carpenter helper 10 Nos. @ Tk. 304.00 each = Tk. 3,040.00
(iii) Painting 2 coats over a coat of priming (rate is 50%
more than the normal rate) 192 sft. @ Tk. 2,121.00 Per %sft. = Tk. 4,072.32
Total = Tk. 39,705.70
Profit 10.00% = Tk. 3,970.57
Overhead 3.50% = Tk. 1,389.70
= Tk. 45,065.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,622.88
Grand total = Tk. 47,688.85
Rate per sft. = Tk. 248.38
Rate per sqm = Tk. 2,673.56

Say, Tk. 2,674 .00 Per sqm.

Item No.- 18.1.2


1/2" thick plain particle board ceiling screwed up with wooden frame for auditorium
and other tall structures beyond 3.5 meter upto 6 meter height.
Consider 1 No. panel
Considering a panel of 12'-0" x 16'-0"= 192 sft. of work
(a) Cost of materials and labour Same as item No. 144(a) = Tk. 39,705.70
(b) Scaffolding beyond 12' upto 20' (double stage)
2 x 16'-0" x 12'-0"= 384 sft. @ Tk. 7.20 Per sft. = Tk. 2,764.80
Total = Tk. 42,470.50
Profit 10.00% = Tk. 4,247.05
Overhead 3.50% = Tk. 1,486.47
= Tk. 48,204.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,805.52
Grand total = Tk. 51,009.54
Rate per sft. = Tk. 265.67
Rate per sqm = Tk. 2,859.67

Say, Tk. 2,860 .00 Per sqm.

Item No.- 18.1.3


Supplying, fitting and fixing of 8 mm thick melamine board laminated by mechanical hot
press with a milk white PVC membrance with aluminum frame suspended from ceiling.
Consider 16'-0" x 10'-0"= 160 sft. of work
(A) Materials
1. Malamine board (8 mm thick):
8' -0" x 4'-0" size 5 Pcs. @ Tk. 1,946.50 Per pc. = Tk. 9,732.50
Analysis of PWD SoR 2014 for Civil Works 331

2. Aluminium section & accessories


(a) 1" main T-section 64.00 rft. @ Tk. 22.05 Per rft. = Tk. 1,411.20
(b) 1" cross T-section 30.00 rft. @ Tk. 22.05 Per rft. = Tk. 661.50
(c) 1" L-section 63.00 rft. @ Tk. 22.05 Per rft. = Tk. 1,389.15
(d) Revit L.S. = Tk. 232.57
(e) G.I. wire 1.50 kg. @ Tk. 110.00 Per sft. = Tk. 165.00
(f) 1.5" screw 10.50 doz. @ Tk. 22.00 Per doz. = Tk. 231.00
(g) Rowl plug 120.00 Nos. @ Tk. 0.71 each = Tk. 85.20
(h) Wall bit 2.00 Nos. @ Tk. 38.23 each = Tk. 76.46
(B) Labour
(i) Carpenter 6.00 Nos. @ Tk. 423.00 each = Tk. 2,538.00
(ii) Helper to carpenter 6.00 Nos. @ Tk. 304.00 each = Tk. 1,824.00
(iii) Carrying to site in/c sundries L.S. = Tk. 490.00
Total = Tk. 18,836.58
Profit 10.00% = Tk. 1,883.66
Overhead 3.50% = Tk. 659.28
= Tk. 21,379.52
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,244.31
Grand total = Tk. 22,623.83
Rate per sft. = Tk. 141.40
Rate per sqm = Tk. 1,522.03

Say, Tk. 1,522 .00 Per sqm.

Item No.- 18.2.1


Supplying, fitting and fixing of 9 mm thick gypsum board laminated by mechanical hot
press with a milk white PVC membrance with aluminum frame suspended from ceiling.
Consider 10'-0" x 10'-0"= 100 sft. of work
(a) Cost of materials
(i) Aluminium sections
Main T-section: 4 x 10'- 0"= 40.00 rft. @ Tk. 21.00 Per rft. = Tk. 840.00
Coss T-section 4 x 10' - 0"= 40.00 rft. @ Tk. 21.00 Per rft. = Tk. 840.00
Angle or L-section: 4 x 10'- 0"= 40.00 rft. @ Tk. 21.00 Per rft. = Tk. 840.00
(ii) Gypsum board 100.00 sft. @ Tk. 25.98 Per sft. = Tk. 2,598.00
(iii) Accessories, rowel bolts, G.I. wire,
machine charges for 100 sft. 40% of aluminium sections = Tk. 1,008.00
(b) Labour
(i) Skilled technician 5.00 Nos. @ Tk. 700.00 each = Tk. 3,500.00
(ii) Skilled labour 5.00 Nos. @ Tk. 303.00 each = Tk. 1,515.00
(iii) Ordinary labour 5.00 Nos. @ Tk. 245.00 each = Tk. 1,225.00
(iv) Scaffolding 100.00 sft. @ Tk. 7.20 Per sft. = Tk. 720.00
Total = Tk. 13,086.00
Profit 10.00% = Tk. 1,308.60
Overhead 3.50% = Tk. 458.01
= Tk. 14,852.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 864.44
Grand total = Tk. 15,717.05
Rate per sft. = Tk. 157.17
Rate per sqm = Tk. 1,691.78

Say, Tk. 1,692 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 332

Item No.- 18.2.2


Supplying, fitting and fixing of 12 mm thick vinyl board laminated by mechanical hot
press with a milk white PVC membrance with aluminum frame suspended from ceiling.
Consider ing 100 sft. of work
(a) Cost of false ceiling work
excluding cost of board Same as item No. 144(a) = Tk. 10,488.00
(b) Cost of vinyle board 100.00 @ Tk. 46.88 Per sft. = Tk. 4,688.00
Total = Tk. 15,176.00
Profit 10.00% = Tk. 1,517.60
Overhead 3.50% = Tk. 531.16
= Tk. 17,224.76
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,002.50
Grand total = Tk. 18,227.26
Rate per sft. = Tk. 182.27
Rate per sqm = Tk. 1,961.95

Say, Tk. 1,962 .00 Per sqm.

Item No.- 18.2.3


Supplying, fitting and fixing of 9 mm thick perforated board false ceiling with aluminium T bar frame in natural
anodized frame at 600 mm x 600 mm grid suspended from ceiling by 12 SWG double ply G.I. Wire

Consider ing 100 sft. of work


(a) Cost of false ceiling work
excluding cost of board Same as item No. 144(a) = Tk. 10,488.00
(b) Cost of perforated gypsum board 100.00 @ Tk. 30.57 Per sft. = Tk. 3,057.00
Total = Tk. 13,545.00
Profit 10.00% = Tk. 1,354.50
Overhead 3.50% = Tk. 474.08
= Tk. 15,373.58
Add VAT with adjustment factor 1.0582 5.50% = Tk. 894.76
Grand total = Tk. 16,268.34
Rate per sft. = Tk. 162.68
Rate per sqm = Tk. 1,751.09

Say, Tk. 1,751 .00 Per sqm.

Item No.- 18.3.1


Supplying, fitting and fixing of 12 mm thick B.T. veneered board in walling.
Consider 1 No. panel
Consider 12'-0" x 10'-0"= 120 sft. of work
a) Cost of materials
(i) Garjan wood:
batten: 7 x 10'-0" x 3" x 1.5"= 2.19 cft.
6 x 12'-0" x 3.25" x 1.5"= 2.25 cft.
= 4.44 cft.
Add wastage 5%= 0.22 cft.
= 4.66 cft. @ Tk. 2,000.0 Per cft. = Tk. 9,320.00
(ii) Cost of 12 mm B.T. veneered board:
12'-0" x 10'-0"= 120.00 sft.
Add wastage 5%= 6.00 sft.
= 126.00 sft. @ Tk. 110.42 Per sft. = Tk. 13,912.92
(iii) Cost of M.S. clamps, wooden block, screws,
nails etc. (10% of cost of wooden frame) = Tk. 932.00
(b) Cost of fitting, fixing, cutting to sizes, levelling, finishing, scaffolding
(i) Carpenter 6.00 Nos. @ Tk. 423.00 each = Tk. 2,538.00
(ii) Carpenter helper 6.00 Nos. @ Tk. 304.00 each = Tk. 1,824.00
Analysis of PWD SoR 2014 for Civil Works 333

(c) Local carriage L.S = Tk. 122.50


(d) French polishing 120.00 sft. @ Tk. 2,264.57 Per % sft. = Tk. 2,717.48
Total = Tk. 31,366.90
Profit 10.00% = Tk. 3,136.69
Overhead 3.50% = Tk. 1,097.84
= Tk. 35,601.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,072.04
Grand total = Tk. 37,673.47
Rate per sft. = Tk. 313.95
Rate per sqm = Tk. 3,379.36

Say, Tk. 3,379 .00 Per sqm.

Item No.- 18.3.2


Supplying, fitting and fixing of 12 mm thick particle board walling with wooden frame.
Consider 12'-0" x 10'-0"= 120 sft. of work
(a) Cost of walling excluding cost of board Same as item No. 145(a) = Tk. 17,453.98
(b) Cost of 12 mm thick particle
board in/c 5% wastage 126 sft. @ Tk. 35.34 Per sft. = Tk. 4,452.84
Total = Tk. 21,906.82
Profit 10.00% = Tk. 2,190.68
Overhead 3.50% = Tk. 766.74
= Tk. 24,864.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,447.12
Grand total = Tk. 26,311.36
Rate per sft. = Tk. 219.26
Rate per sqm = Tk. 2,360.11

Say, Tk. 2,360 .00 Per sqm.

DIVISION 19 : COLLAPSIBLE GATE, M.S. GATE, ROLLING SHUTTER ETC.


Analysis of PWD SoR 2014 for Civil Works 334

Item No.- 19.1.1


Manufacturing, supplying, fitting and fixing of collapsible gate with 3/4" x 3/4" 1/8" size
M.S. channel excluding cost of paint.
Considering 1 No. collapsible gate
Considering 8'-0" x 8'-0"= 64.00 sft. in two parts
(a) Cost of materials
(i) 3/4" x 3/8" x 1/8" channel: @ 0.53 Ibs per rft.
2 x 12 x 2 x 8'-6"= 384 rft.
Add wastage 5%= 19.2 rft.
= 403.2 rft.
= 213.696 Ibs. @ Tk. 28.34 Per Ib. = Tk. 6,056.14
(ii) 3/4" x 1/8" M.S. flat bar diagonals at 3 levels of length
1'-0" to 2'-0": @ 0.32 Ibs per rft.
2 x 9 x 2 x 3 x 2'-0"= 216.00 rft.
2 x 2 x 2 x 3 x 1'-9"= 42.00 rft.
= 258.00 rft.
Add wastage 5%= 12.90 rft.
= 270.90 rft.
= 86.69 Ibs. @ Tk. 25.40 Per Ib. = Tk. 2,201.93
(iii) 2" x 1/4" F.I. bar to make Tee (top & bottom rail) and
locking arrangement: @ 1.70 Ibs per rft.
4 x 8'-6"= 34 rft.
2 x 2 x 0'-6"= 2 rft.
36 rft.
Add wastage 5%= 1.8 rft.
= 37.8 rft.
= 64.26 Ibs. @ Tk. 25.40 Per Ib. = Tk. 1,632.20
(iv) 3/4" x 3/16" F.I. bar for making handle: @ 0.48 Ibs per rft.
4 x 0'-10"= 3.30 rft.
Add wastage 5%= 0.17 rft.
= 3.47 rft.
= 1.67 Ibs. @ Tk. 25.40 Per Ibs = Tk. 42.42
(b) Hardwares, fittings and consumables:
(i) Rivet and washer 2.00 kg. @ Tk. 76.00 Per kg. = Tk. 152.00
(ii) 1.5" dia M.S. wheel 6.00 Nos. @ Tk. 23.00 each = Tk. 138.00
(iii) M.S. clamp: 10 Nos. @ Tk. 25.00 each = Tk. 250.00
(iv) Locking arrangement 2 pairs @ Tk. 50.00 each pair = Tk. 100.00
(v) Electrodes 20 Pc. @ Tk. 10.00 Per pc. = Tk. 200.00
(vi) Greese 0.5 Ib. @ Tk. 56.00 Per Ib. = Tk. 28.00
(c) Making gate in work-shop
(i) Welder/ fabricator 3.5 Nos. @ Tk. 423.00 each = Tk. 1,480.50
(ii) Helper to welder 3.5 Nos. @ Tk. 304.00 each = Tk. 1,064.00
(iii) Ordinary labour 3.5 Nos. @ Tk. 245.00 each = Tk. 857.50
(d) Carrying cost: steel materials from market to workshop
& finished gate from workshop to site. L.S. = Tk. 367.50
Sub-total = Tk. 14,570.19
(e) Workshop charge 10% = Tk. 1,457.02
Total = Tk. 16,027.21
(f) Ancillary work for fitting-fixing the gate:
(i) Making holes 14.00 Nos. @ Tk. 15.20 each = Tk. 212.80
(ii) Making groove (channel) on floor:
1 x 8'-0"= 8.00 rft. @ Tk. 15.20 Per rft. = Tk. 121.60
(iii) Cost of CC (1:2:4):
14 x 6" x 4" x 4"= 1.00 cft (say) @ Tk. 17,637.01 Per % cft. = Tk. 176.37
(iv) 1/2" thick plaster (1:4)
3 x 8'-0" x 1'-0"= 24.00 sft. @ Tk. 1,527.00 Per % sft. = Tk. 366.48
(v) Repairing floor and plaster with neat cement finish:
Analysis of PWD SoR 2014 for Civil Works 335

1 x 8'-0" x 1'-6"= 12.00 sft. @ Tk. 1,906.00 Per % sft. = Tk. 228.72
(g) Labour for fitting-fixing the gate:
(i) Mason 0.5 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 17,479.18
Profit 10.00% = Tk. 1,747.92
Overhead 3.50% = Tk. 611.77
= Tk. 19,838.87
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,154.64
Grand total = Tk. 20,993.51
Rate per sft. = Tk. 328.02
Rate per sqm. = Tk. 3,530.81

Say, Tk. 3,531 .00 Per sqm.

Item No.- 19.1.2


Manufacturing, supplying, fitting and fixing of collapsible gate with 3/4" x 3/4" x 1/8"
M.S. angle excluding cost of paint.
Considering 1 No. collapsible gate
Considering 8'-0" x 8'-0"= 64.00 sft. in two parts
(a) Cost of materials
(i) 3/4" x 3/4" x 1/8" angle: @ 0.585 Ibs per rft.
2 x 12 x 2 x 8'-6"= 384 rft.
Add wastage 5%= 19.2 rft.
= 403.2 rft.
= 235.872 Ibs. @ Tk. 28.34 Per Ib. = Tk. 6,684.61
(ii) 3/4" x 1/8" M.S. flat bar diagonals at 3 levels of length
1'-0" to 2'-0": @ 0.32 Ibs per rft.
2 x 9 x 2 x 3 x 2'-0"= 216.00 rft.
2 x 2 x 2 x 3 x 1'-9"= 42.00 rft.
= 258.00 rft.
Add wastage 5%= 12.90 rft.
= 270.90 rft.
= 86.69 Ibs. @ Tk. 25.40 Per Ib. = Tk. 2,201.93
(iii) 2" x 1/4" F.I. bar to make Tee (top & bottom rail)
and locking arrangement: @ 1.70 Ibs per rft.
4 x 8'-6"= 34 rft.
2 x 2 x 0'-6"= 2 rft.
36 rft.
Add wastage 5%= 1.8 rft.
= 37.8 rft.
= 64.26 Ibs. @ Tk. 25.40 Per Ib. = Tk. 1,632.20
(b) Hardwares, fittings and consumables:
(i) Rivet and washer 2.50 kg. @ Tk. 76.00 Per kg. = Tk. 190.00
(ii) 1.5" dia M.S. wheel 6.00 Nos. @ Tk. 23.00 each = Tk. 138.00
(iii) M.S. clamp: 10 Nos. @ Tk. 25.00 each = Tk. 250.00
(iv) Locking arrangement 2 pairs @ Tk. 50.00 each pair = Tk. 100.00
(v) Handle with 5/8" dia M.S rod 4 Nos @ Tk. 54.96 each = Tk. 219.84
(vi) Electrodes 70 pcs. @ Tk. 10.00 Per pc. = Tk. 700.00
(vii) Greese 0.5 Ib. @ Tk. 56.00 Per Ib. = Tk. 28.00
(c) Making gate in work-shop
(i) Welder/ fabricator 4.5 Nos. @ Tk. 423.00 each = Tk. 1,903.50
(ii) Helper to welder 4.5 Nos. @ Tk. 304.00 each = Tk. 1,368.00
(iii) Ordinary labour 4.5 Nos. @ Tk. 245.00 each = Tk. 1,102.50
(d) Carrying cost: materials & finished gate. L.S. = Tk. 367.50
Sub-total = Tk. 16,886.08
(e) Workshop charge 10% = Tk. 1,688.61
Analysis of PWD SoR 2014 for Civil Works 336

Total = Tk. 18,574.69


(f) Anciliary work for fitting-fixing the gate:
9i) Making holes 14.00 Nos. @ Tk. 15.20 each = Tk. 212.80
(ii) Making groove (channel) on floor:
1 x 8'-0"= 8.00 rft. @ Tk. 15.20 Per rft. = Tk. 121.60
(iii) Cost of CC (1:2:4):
14 x 6" x 4" x 4"= 1.00 cft (say) @ Tk. 17,637.01 Per % cft. = Tk. 176.37
(iv) 1/2" thick plaster (1:4)
3 x 8'-0" x 1'-0"= 24.00 sft. @ Tk. 1,527.00 Per % sft. = Tk. 366.48
(v) Repairing floor and plaster with neat cement finish:
1 x 8'-0" x 1'-6"= 12.00 sft. @ Tk. 1,906.00 Per % sft. = Tk. 228.72
(g) Labour for fitting-fixing the gate:
(i) Mason 0.5 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 20,026.66
Profit 10.00% = Tk. 2,002.67
Overhead 3.50% = Tk. 700.93
= Tk. 22,730.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,322.92
Grand total = Tk. 24,053.18
Rate per sft. = Tk. 375.83
Rate per sqm. = Tk. 4,045.43

Say, Tk. 4,045 .00 Per sqm.

Item No.- 19.1.3


Manufacturing, supplying, fitting and fixing of collapsible gate with 1" x 1" x 1/8"
M.S. angle excluding cost of paint.
Considering 1 No. collapsible gate
Considering 8'-0" x 8'-0"= 64.00 sft. in two parts
(a) Cost of materials
(i) 1" x 1" x 1/8" angle: @ 0.8 Ibs per rft.
2 x 12 x 2 x 8'-6"= 384 rft.
Add wastage 5%= 19.2 rft.
= 403.2 rft.
= 322.56 Ibs. @ Tk. 28.34 Per Ib. = Tk. 9,141.35
(ii) 1" x 1/8" M.S. flat bar diagonals at 3 levels of length
1'-0" to 2'-0": @ 0.43 Ibs per rft.
2 x 9 x 2 x 3 x 2'-0"= 216.00 rft.
2 x 2 x 2 x 3 x 1'-9"= 42.00 rft.
= 258.00 rft.
Add wastage 5%= 12.90 rft.
= 270.90 rft.
= 116.49 Ibs. @ Tk. 25.40 Per Ib. = Tk. 2,958.85
(iii) 2" x 1/4" F.I. bar to make Tee (top & bottom rail)
and locking arrangement: @ 1.70 Ibs per rft.
4 x 8'-6"= 34 rft.
2 x 2 x 0'-6"= 2 rft.
36 rft.
Add wastage 5%= 1.8 rft.
= 37.8 rft.
= 64.26 Ibs. @ Tk. 25.40 Per Ib. = Tk. 1,632.20
(b) Hardwares, fittings and consumables:
(i) Rivet and washer 3.00 kg. @ Tk. 76.00 Per kg. = Tk. 228.00
(ii) 1.5" dia M.S. wheel 6.00 Nos. @ Tk. 23.00 each = Tk. 138.00
(iii) M.S. clamp: 10 Nos. @ Tk. 25.00 each = Tk. 250.00
(iv) Locking arrangement 2 pairs @ Tk. 50.00 each pair = Tk. 100.00
Analysis of PWD SoR 2014 for Civil Works 337

(v) Handle with 5/8" dia M.S rod 4 Nos @ Tk. 54.96 each = Tk. 219.84
(vi) Electrodes 70 pcs. @ Tk. 10.00 Per pc. = Tk. 700.00
(vii) Greese 0.5 Ibs. @ Tk. 56.00 Per Ib. = Tk. 28.00
(c) Making gate in work-shop
(i) Welder/ fabricator 5 Nos. @ Tk. 423.00 each = Tk. 2,115.00
(ii) Helper to welder 5 Nos. @ Tk. 304.00 each = Tk. 1,520.00
(iii) Ordinary labour 5 Nos. @ Tk. 245.00 each = Tk. 1,225.00
(d) Carrying cost: materials & finished gate. L.S. = Tk. 367.50
Sub-total = Tk. 20,623.74
(e) Workshop charge 10% = Tk. 2,062.37
Total = Tk. 22,686.11
(f) Anciliary work for fitting-fixing the gate:
(i) Making holes 14.00 Nos. @ Tk. 15.20 each = Tk. 212.80
(ii) Making groove (channel) on floor:
1 x 8'-0"= 8.00 rft. @ Tk. 15.20 Per rft. = Tk. 121.60
(iii) Cost of CC (1:2:4):
14 x 6" x 4" x 4"= 1.00 cft (say) @ Tk. 17,637.01 Per % cft. = Tk. 176.37
(iv) 1/2" thick plaster (1:4)
3 x 8'-0" x 1'-0"= 24.00 sft. @ Tk. 1,527.00 Per % sft. = Tk. 366.48
(v) Repairing floor and plaster with neat cement finish:
1 x 8'-0" x 1'-6"= 12.00 sft. @ Tk. 1,906.00 Per % sft. = Tk. 228.72
(g) Labour for fitting-fixing the gate:
(i) Mason 0.5 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 24,138.08
Profit 10.00% = Tk. 2,413.81
Overhead 3.50% = Tk. 844.83
= Tk. 27,396.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,594.52
Grand total = Tk. 28,991.24
Rate per sft. = Tk. 452.99
Rate per sqm. = Tk. 4,875.98

Say, Tk. 4,876 .00 Per sqm.

Item No.- 19.2.1


Manufacturing, supplying, fitting and fixing of ordinary type M.S.gate (double leaf) with 5/8" dia
M.S. rod and 1.5" x 1.5" x 1/4" angle frame excluding cost of painting.
Considering 1 No. of gate
Considering 10'-0" x 6'-8"= 66.67 sft. in two parts
(a) Cost of materials
(i) 1.5" x 1.5" x 1/4" angle for frame: @ 2.34 Ibs per rft.
2 x 2 x 6'-0"= 24.0 rft.
2 x 3 x 5'-0"= 30.0 rft.
1 x 3'-6"= 3.5 rft.
2 x 2'-0"= 4.0 rft.
2 x 3-6"= 7.0 rft.
68.5 rft.
Add wastage 5%= 3.425 rft.
= 71.93 rft.
= 168.32 Ibs. @ Tk. 28.34 Per Ib. = Tk. 4,770.19
(ii) 1.5" x 1/4" M.S. flat bar: @ 1.28 Ibs per rft.
2 x 2 x 5'-7"= 22.32 rft.
2 x 2'-6"= 5.00 rft.
2 x 5'-0"= 10.00 rft.
= 37.32 rft.
Add wastage 5%= 1.866 rft.
Analysis of PWD SoR 2014 for Civil Works 338

= 39.19 rft.
= 50.16 Ibs. @ Tk. 25.40 Per Ib. = Tk. 1,274.06
(iii) 2" x 1/4" F.I. bar for rails: @ 1.7 Ibs per rft.
2 x 3.142 x 10'-0"/4= 15.71 rft.
Add wastage 5%= 0.79 rft.
16.50 rft.
= 28.05 Ibs. @ Tk. 25.40 Per Ib = Tk. 712.47
(iv) 5/8" M.S. rod: @ 1.043 Ibs per rft.:
2 x 21 x 0'-8"= 28.14 rft.
2 x 19 x 3'-6"= 133.00 rft.
2 x 38 x 0'-3"= 19.00 rft.
180.14 rft.
Add wastage 5%= 9.01 rft.
= 189.15 rft.
= 197.28 Ibs. @ Tk. 25.40 Per Ib. = Tk. 5,010.91
(v) 1/8" thick M.S. plate: @ 5.10 lbs per sft.
2 x 2 x 1'-0" x 1'-0"= 4.00 sft.
2 x 1'-0" x 6" = 1 sft.
5.00 sft.
Add wastage 5%= 0.25 sft.
= 5.25 sft.
= 26.78 Ibs. @ Tk. 38.55 Per Ib. = Tk. 1,032.37
(vi) 1/4" thick M.S. plate: @ 10.2 Ibs per sft.
2 x 0-6" x 0'-6"= 0.50 sft.
Add wastage 5%= 0.03 sft.
= 0.53 sft.
= 5.41 Ibs. @ Tk. 38.55 Per Ib. = Tk. 208.56
(vii) 18 BWG M.S. plate: 2.04 Ibs per sft.
2 x 5'-0" x 2'-6"= 25.00 sft.
Add wastage 5%= 1.25 sft.
= 26.25 sft.
= 53.55 Ibs. @ Tk. 38.55 Per Ib. = Tk. 2,064.35
(b) Fittings and consumables
(i) Hinges for pocket gate: 2 Nos. @ Tk. 38.00 each = Tk. 76.00
(ii) 1.5" dia heavy duty wheel 2 Nos. @ Tk. 145.00 each = Tk. 290.00
(iii) Locking arrangement 3 Nos. @ Tk. 229.00 each = Tk. 687.00
(iv) Clamp with huskel dumney 6 Nos. @ Tk. 120.00 each = Tk. 720.00
(v) Clamp for rails 16 Nos. @ Tk. 28.00 each = Tk. 448.00
(vi) Electrodes 200 Pc. @ Tk. 10.00 each = Tk. 2,000.00
(c) Making steel gate in work-shop
(i) Welder / fabricator 6 Nos. @ Tk. 423.00 each = Tk. 2,538.00
(ii) Helper 5 Nos. @ Tk. 304.00 each = Tk. 1,520.00
(iii) Ordinary labour 5 Nos. @ Tk. 245.00 each = Tk. 1,225.00
(d) Carrying materials to work-shop & gate to site L.S. = Tk. 367.50
Sub-total = Tk. 24,944.41
(e) Work-shop charges 10% = Tk. 2,494.44
Total = Tk. 27,438.85
(f) Ancillary work for fitting -fixing the gate:
(i) Making holes 6 Nos. @ Tk. 12.67 each = Tk. 76.02
(ii) Plain concrete: (1:2:4)
6 x 10" x 6" x 6"= 1.25 cft.
16'-0" x 6" x 4"= 2.67 cft.
2 x 4 x 6" x 4"= 1.33 cft.
5.25 cft. @ Tk. 17,637.01 Per % cft. = Tk. 925.94
(g) Labour charge for hoisting the gate in position
(i) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(ii) Mason helper 2 No. @ Tk. 304.00 each = Tk. 608.00
Analysis of PWD SoR 2014 for Civil Works 339

(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00


Total = Tk. 29,682.81
Profit 10.00% = Tk. 2,968.28
Overhead 3.50% = Tk. 1,038.90
= Tk. 33,689.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,960.79
Grand total = Tk. 35,650.78
Rate per sft. = Tk. 534.73
Rate per sqm. = Tk. 5,755.83

Say, Tk. 5,756 .00 Per sqm.

Item No.- 19.2.2


Manufacturing, supplying, fitting and fixing of security door with 7/8" dia M.S. rod and
2" x 2" x 1/4" angle frame excluding cost of painting.
Considering 1 No. of gate
Considering 3'-4" x 7'-0"= 23.31 sft. in two parts
(a) Cost of materials
(i) 2" x 2" x 1/4" angle for frame: @ 3.19 Ibs per rft.
Vertical: 2 x 7'-0"= 14.0 rft.
Horizontal: 2 x 3'-4"= 6.67 rft.
Clamp: 4 x 1'-6"= 6.00 rft.
= 26.67 rft.
Add wastage 5%= 1.33 rft.
= 28.00 rft.
= 89.32 Ibs. @ Tk. 28.34 Per Ib. = Tk. 2,531.33
(ii) 7/8" M.S. rod: @ 2.04 Ibs per rft.:
10 x 6'-11.5"= 69.60 rft.
Add wastage 5%= 3.48 rft.
= 73.08 rft.
= 149.08 Ibs. @ Tk. 25.40 Per Ib. = Tk. 3,786.63
(iii) 2" x 1/4" F.I. bar: @ 1.7 Ibs per rft.
Horizontal: 4 x 3'-3.5= 15.71 rft.
Rails: 2 x 3.142 x 3'-4"= 20.93 rft.
36.64 rft.
Add wastage 5%= 1.83 rft.
38.47 rft.
= 65.40 Ibs. @ Tk. 25.40 Per Ib = Tk. 1,661.16
(iv) 1/8" thick M.S. plate: @ 5.10 lbs per sft.
1 x 2'-0" x 3'-0"= 6.00 sft.
Add wastage 5%= 0.3 sft.
= 6.30 sft.
= 32.13 Ibs. @ Tk. 38.55 Per Ib. = Tk. 1,238.61
(b) Fittings and consumables
(i) Hinges for pocket gate: 2 Nos. @ Tk. 38.00 each = Tk. 76.00
(ii) 1.5" dia heavy duty wheel 2 Nos. @ Tk. 145.00 each = Tk. 290.00
(iii) Locking arrangement 2 Nos. @ Tk. 229.00 each = Tk. 458.00
(iv) Clamp with huskel dumney 3 Nos. @ Tk. 120.00 each = Tk. 360.00
(v) Clamp for rails 6 Nos. @ Tk. 28.00 each = Tk. 168.00
(vi) Electrodes 98 Pc. @ Tk. 10.00 each = Tk. 980.00
(c) Making steel gate in work-shop
(i) Welder / fabricator 3 Nos. @ Tk. 423.00 each = Tk. 1,269.00
(ii) Helper 3 Nos. @ Tk. 304.00 each = Tk. 912.00
(iii) Ordinary labour 3 Nos. @ Tk. 245.00 each = Tk. 735.00
(d) Carrying materials to work-shop & gate to site L.S. = Tk. 129.85
Sub-total = Tk. 14,595.58
(e) Work-shop charges 10% = Tk. 1,459.56
Analysis of PWD SoR 2014 for Civil Works 340

Total = Tk. 16,055.14


(f) Ancillary work for fitting-fixing the gate:
(i) Making holes 80 Nos. @ Tk. 12.67 each = Tk. 1,013.60
(ii) Plain concrete: (1:2:4)
2 x 10" x 6" x 6"= 0.41 cft.
3'-4" x 6" x 4"= 0.55 cft.
2 x 3 x 6" x 4"= 0.99 cft.
1.95 cft. @ Tk. 17,637.01 Per % cft. = Tk. 343.92
(g) Labour charge for hoisting the gate in position
(i) Mason 0.5 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Mason helper 1 No. @ Tk. 304.00 each = Tk. 304.00
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 18,156.16
Profit 10.00% = Tk. 1,815.62
Overhead 3.50% = Tk. 635.47
= Tk. 20,607.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,199.36
Grand total = Tk. 21,806.61
Rate per sft. = Tk. 935.50
Rate per sqm. = Tk. 10,069.72

Say, Tk. 10,070 .00 Per sqm.

Item No.- 19.3


Manufacturing, supplying, fitting and fixing of ordinary type M.S. gate (double leaf) with 1 x 1/4"
F.I. bar, M.S. plate and 1.5" x 1.5" x 1/4" angle outer frame (without pocket gate)
excluding cost of paint.
Considering 1 No. of gate
Considering 10'-0" x 6'-8"= 66.67 sft. in two parts
(a) Cost of materials
(i) 1.5" x 1.5" x 1/4" angle for frame: @ 2.34 Ibs per rft.
2 x 2 x 6'-8"= 26.70 rft.
2 x 4 x 5'-0"= 40.00 rft.
66.70 rft.
Add wastage 5%= 3.34 rft.
= 70.04 rft.
= 163.89 Ibs. @ Tk. 28.34 Per Ib. = Tk. 4,644.64
(ii) 1.5" x 1/4" M.S. flat bar: @ 1.28 Ibs per rft.
2 x 5'-0"= 10.00 rft.
2 x 3'-4"= 6.70 rft.
2 x 2 x 4'-8.5" 18.80 rft.
35.50 rft.
Add wastage 5%= 1.775 rft.
= 37.28 rft.
= 47.72 Ibs. @ Tk. 25.40 Per Ib. = Tk. 1,212.09
(iii) 2" x 1/4" F.I. bar for rails: @ 1.7 Ibs per rft.
2 x 3.142 x 10'-0"/4= 15.71 rft.
Add wastage 5%= 0.79 rft.
16.50 rft.
= 28.05 Ibs. @ Tk. 25.40 Per Ib = Tk. 712.47
(iv) 1" x 1/4" F.I. bar : 0.85 Ib per rft.
2 x 2 x 9 x 1'-8"= 60.12 rft.
Add wastage 5%= 3.01 rft.
= 63.13 rft.
= 53.66 Ibs. @ Tk. 25.40 Per Ib. = Tk. 1,362.96
(v) 1/8" thick M.S. plate: @ 5.10 lbs per sft.
4 x 1'-0" x 1'-0"= 4.00 sft.
Analysis of PWD SoR 2014 for Civil Works 341

Add wastage 5%= 0.2 sft.


= 4.20 sft.
= 21.42 Ibs. @ Tk. 38.55 Per Ib. = Tk. 825.74
(vi) 1/4" thick M.S. plate as gusset plate
2 x 0-6" x 0'-6"= 0.50 sft.
Add wastage 5%= 0.03 sft.
= 0.53 sft.
= 5.41 Ibs. @ Tk. 38.55 Per Ib. = Tk. 208.56
(vii) 18 BWG M.S. plate: @ 2.04 Ibs per sft.
2 x 5'-0" x 3'-4"= 33.30 sft.
Add wastage 5%= 1.67 sft.
= 34.97 sft.
= 71.3388 Ibs. @ Tk. 38.55 Per Ib. = Tk. 2,750.11
(b) Fittings and consumables
(i) Locking arrangement 2 Nos. @ Tk. 229.00 each = Tk. 458.00
(ii) 1.5" dia heavy duty wheel 2 Nos. @ Tk. 145.00 each = Tk. 290.00
(iii) Clamp with huskel dumney 6 Nos. @ Tk. 120.00 each = Tk. 720.00
(iv) Clamp for rails 16 Nos. @ Tk. 28.00 each = Tk. 448.00
(v) Electrodes 160 Pc. @ Tk. 10.00 each = Tk. 1,600.00
(c) Making steel gate in work-shop
(i) Welder / fabricator 6 Nos. @ Tk. 423.00 each = Tk. 2,538.00
(ii) Helper 6 Nos. @ Tk. 304.00 each = Tk. 1,824.00
(iii) Ordinary labour 6 Nos. @ Tk. 245.00 each = Tk. 1,470.00
(d) Carrying materials to work-shop & gate to site L.S. = Tk. 367.50
Sub-total = Tk. 21,432.07
(e) Work-shop charges 10% = Tk. 2,143.21
Total = Tk. 23,575.28
(f) Ancillary work for fitting-fixing the gate:
(i) Making holes 6 Nos. @ Tk. 12.67 each = Tk. 76.02
(ii) Plain concrete: (1:2:4)
6 x 10" x 6" x 6"= 1.25 cft.
16'-0" x 6" x 4"= 2.67 cft.
2 x 4 x 6" x 4"= 1.33 cft.
5.25 cft. @ Tk. 17,637.01 Per % cft. = Tk. 925.94
(g) Labour charge for hoisting the gate in position
(i) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(ii) Mason helper 2 No. @ Tk. 304.00 each = Tk. 608.00
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 25,819.24
Profit 10.00% = Tk. 2,581.92
Overhead 3.50% = Tk. 903.67
= Tk. 29,304.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,705.57
Grand total = Tk. 31,010.40
Rate per sft. = Tk. 465.13
Rate per sqm. = Tk. 5,006.66
Say, Tk. 5,007 .00 Per sqm.
Item No.- 19.4
Manufacturing, supplying, fitting and fixing of ordinary type M.S. gate (double leaf)
with 1.5" x 1.5" x 1/4" M.S. angle box and channel.
Considering 1 No. of gate
Considering 13'-8" x 5'-2"= 70.67 sft. in two parts
(a) Cost of materials
(i) 1.5" x 1.5" x 1/4" angle for frame: @ 2.34 Ibs per rft.
2 x 2 x 2 x 6'-10"= 54.64 rft.
2 x 3 x 2 x 5'-2"= 62.04 rft.
= 116.68 rft.
Analysis of PWD SoR 2014 for Civil Works 342

Add wastage 5%= 5.83 rft.


= 122.51 rft.
= 286.67 Ibs. @ Tk. 28.34 Per Ib. = Tk. 8,124.23
(ii) 1" x 2" x 1" x 3/16" M.S. channel: @ 2.32 Ibs per rft.
Horizontal: 2 x 19 x 1'-3"= 47.50 rft.
450 inclined: 2 x 21 x 5'-2"(av)= 217.14 rft.
264.64 rft.
Add wastage 5%= 13.232 rft.
= 277.87 rft.
= 644.66 Ibs. @ Tk. 28.34 Per Ib. = Tk. 18,269.66
(iii) 2" x 1/4" F.I. bar for rails: @ 1.7 Ibs per rft.
2 x 3.142 x 13'-8"/4= 21.46 rft.
Add wastage 5%= 1.07 rft.
22.53 rft.
= 38.30 Ibs. @ Tk. 25.40 Per Ib = Tk. 972.82
(iv) 1/8" thick M.S. plate: @ 5.10 lbs per sft.
4 x 1'-0" x 1'-0"= 4.00 sft.
Add wastage 5%= 0.2 sft.
= 4.20 sft.
= 21.42 Ibs. @ Tk. 38.55 Per Ib. = Tk. 825.74
(b) Fittings and consumables
(i) Locking arrangement 2 Nos. @ Tk. 229.00 each = Tk. 458.00
(ii) 1.5" dia heavy duty wheel 2 Nos. @ Tk. 145.00 each = Tk. 290.00
(iii) Clamp with huskel dumney 6 Nos. @ Tk. 120.00 each = Tk. 720.00
(iv) Clamp for rails 8 Nos. @ Tk. 28.00 each = Tk. 224.00
(v) Electrodes 240 Pc. @ Tk. 10.00 each = Tk. 2,400.00
(c) Making steel gate in work-shop
(i) Welder / fabricator 5 Nos. @ Tk. 423.00 each = Tk. 2,115.00
(ii) Helper 5 Nos. @ Tk. 304.00 each = Tk. 1,520.00
(iii) Ordinary labour 5 Nos. @ Tk. 245.00 each = Tk. 1,225.00
(d) Carrying materials to work-shop & gate to site L.S. = Tk. 367.50
Sub-total = Tk. 37,511.95
(e) Work-shop charges 10% = Tk. 3,751.20
Total = Tk. 41,263.15
(f) Ancillary work for fitting-fixing the gate:
(i) Making holes 6 Nos. @ Tk. 12.67 each = Tk. 76.02
(ii) Plain concrete: (1:2:4)
6 x 10" x 6" x 6"= 1.25 cft.
22'-0" x 6" x 4"= 3.67 cft.
2 x 4 x 6" x 4"= 1.33 cft.
6.25 cft. @ Tk. 17,637.01 Per % cft. = Tk. 1,102.31
(g) Labour charge for hoisting the gate in position
(i) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(ii) Mason helper 2 No. @ Tk. 304.00 each = Tk. 608.00
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 43,683.48
Profit 10.00% = Tk. 4,368.35
Overhead 3.50% = Tk. 1,528.92
= Tk. 49,580.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,885.65
Grand total = Tk. 52,466.40
Rate per sft. = Tk. 742.41
Rate per sqm. = Tk. 7,991.30

Say, Tk. 7,991 .00 Per sqm.

Item No.- 19.5


Analysis of PWD SoR 2014 for Civil Works 343

Manufacturing, supplying, fitting and fixing of G.I. pipe gate excluding cost of painting.
Considering 1 No. of gate
Considering 10'-0" x 6'-8"= 66.67 sft. in two parts
(a) Cost of materials
(i) 1.5" dia G.I. pipe
2 x 4 x 5'-0"= 40.00 rft.
4 x 6'-8"= 26.67 rft.
= 66.67 rft.
Add wastage 5%= 3.33 rft.
= 70.00 rft. @ Tk. 169.31 Per rft. = Tk. 11,851.70
(ii) 3/4" dia G.I. pipe
Vertical post: 2 x 19 x 6'-8"= 253.33 rft.
Pocket gate: 2 x 2'-0"= 4.00 rft.
2 x 4'-5"= 8.83 rft.
1 x 2'-2"= 2.17 rft.
= 268.33 rft.
Add 5% wastage= 13.42 rft.
281.75 rft. @ Tk. 74.07 Per rft. = Tk. 20,869.22
(iii) 18 BWG M.S. plate for middle part: @ 2.04 lbs per sft.
2 x 5'-0" x 3'-4"= 33.33 sft.
Add wastage 5%= 1.67 sft.
= 35.00 sft.
= 71.40 Ibs. @ Tk. 38.55 Per Ib. = Tk. 2,752.47
(b) Fittings and consumables
(i) Locking arrangement 2 Nos. @ Tk. 229.00 each = Tk. 458.00
(ii) 5" long hinges 2 Nos. @ Tk. 38.00 each = Tk. 76.00
(iii) Clamp with huskel dumney 6 Nos. @ Tk. 120.00 each = Tk. 720.00
(iv) 5/8" dia M.S. socket bolt 2 Nos. @ Tk. 164.00 each = Tk. 328.00
(v) Electrodes 120 Pc. @ Tk. 10.00 each = Tk. 1,200.00
(c) Making steel gate in work-shop
(i) Welder / fabricator 4 Nos. @ Tk. 423.00 each = Tk. 1,692.00
(ii) Helper 4 Nos. @ Tk. 304.00 each = Tk. 1,216.00
(iii) Ordinary labour 4 Nos. @ Tk. 245.00 each = Tk. 980.00
(d) Carrying materials to work-shop & gate to site L.S. = Tk. 367.50
Sub-total = Tk. 42,510.89
(e) Work-shop charges 10% = Tk. 4,251.09
Total = Tk. 46,761.98
(f) Ancillary work for fitting-fixing the gate:
(i) Making holes 6 Nos. @ Tk. 12.67 each = Tk. 76.02
(ii) Plain concrete: (1:2:4)
6 x 10" x 6" x 6"= 1.25 cft. @ Tk. 17,637.01 Per % cft. = Tk. 220.46
(g) Labour charge for hoisting the gate in position
(i) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(ii) Mason helper 1 No. @ Tk. 304.00 each = Tk. 304.00
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 47,996.46
Profit 10.00% = Tk. 4,799.65
Overhead 3.50% = Tk. 1,679.88
= Tk. 54,475.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,170.56
Grand total = Tk. 57,646.55
Rate per sft. = Tk. 864.66
Rate per sqm. = Tk. 9,307.20

Say, Tk. 9,307 .00 Per sqm.

Item No.- 19.6


Analysis of PWD SoR 2014 for Civil Works 344

Manufacturing, supplying, fitting and fixing of rolling shutter made of 24 SWG G.P. sheet
excluding cost of painting.
Considering 1 No. rolling shutter
Considering 10'-0" x 6'-0"= 60 sft. of work
(a) Materials:
(i) 24 SWG G.P. sheet with 1/2" dia folding at the other end (@ 1 Ibs per rft.)
44 (2.75"+3.14 x 0.5"+3.14 x 0.375) x 10'-0"
= 121.00 sft.
Side patty: 2 x 10'-0" x 0'-3"= 5.00 sft.
126.00 sft.
Add 5% wastage= 6.05 sft.
132.05 sft.
= 132.05 lbs @ Tk. 41.04 Per Ib. = Tk. 5,419.33
(ii) 26 SWG cover sheet: @ 0.85 Ibs per sft.
6'-0" x 4'-0"= 24.0 sft.
Add 5% wastage= 1.2 sft.
25.2 sft.
= 21.42 Ibs. @ Tk. 38.55 Per Ib. = Tk. 825.74
(iii) 1.5" dia G.I. pipe 6.33 rft. @ Tk. 169.31 Per rft. = Tk. 1,071.73
(iv) 1" x 1" x 1/8" M.S. angle: @ 0.8 per rft.:
1 x 6'-0"= 6 rft.
= 4.8 lbs @ Tk. 28.34 Per Ib. = Tk. 136.03
(v) 1/4" thick M.S. plate: @ 10.21 lbs per sft.
Side guide: 2 x 2 x 4" x 10'-6"= 14.0 sft.
Mid guide: 2 x 6" x 10'-6"= 10.5 sft.
4 x 0'-2" x 0'-3"= 0.17 sft.
= 24.67 sft.
Add wastage 5%= 1.23 sft.
25.90 sft.
= 264.44 Ibs. @ Tk. 28.34 Per Ib = Tk. 7,494.23
(vi) 1" x 1/8" F.I. bar: @ 0.425 Ibs per rft.
Side guide channel: 2 x 2 x 10'-0"= 40 rft.
Mid guide channel: 2 x 10'-0"= 20 rft.
Guide channel to punkha:
2 x 2'-3"= 4.5 rft.
Guide channel to handle:
2 x 0'-9"= 1.5 rft.
= 66.0 rft.
Add 5% wastage= 3.3 rft.
69.3 rft.
= 29.4525 Ibs. @ Tk. 25.40 Per lb = Tk. 748.09
(vii) 1/8" thick M.S. plate for punkha & folded plate: @ 5.10 lbs per sft.
2 x 1'-3" x 1'-0"= 2.50 sft.
1 x 6'-0" x 0'-3"= 1.50 sft.
= 4.00 sft.
Add 5% wastage= 0.20 sft.
4.20 sft.
= 12.75 Ibs. @ Tk. 38.55 Per Ib. = Tk. 491.51
(b) Fittings, hardwares and consumables
(i) Best quality china made spring:
3 x 11'-0"= 33 rft. @ Tk. 24.00 Per rft. = Tk. 792.00
(ii) Spring box 3 Nos. @ Tk. 103.00 each = Tk. 309.00

(iii) Nut bolt, 1/2" dia maximum 2.5" long 18 Nos. @ Tk. 9.00 each = Tk. 162.00
(iv) Rivet:
Side patty= 176 Nos.
For fixing top tail= 9 Nos.
Analysis of PWD SoR 2014 for Civil Works 345

For fixing lower plate= 40 Nos.


= 225 Nos. @ Tk. 0.76 each = Tk. 171.00
For guide channel= 20 Nos. @ Tk. 1.14 each = Tk. 22.80
(v) 1" x 1/4" x 0'-9" clamps 8 Nos. @ Tk. 28.00 each = Tk. 224.00
(vi) Electrodes 30 Nos. @ Tk. 10.00 each = Tk. 300.00
(vii) Lubricant, greese: 1 Ibs. @ Tk. 56.00 Per Ib. = Tk. 56.00
(c) Labour:
Cutting, folding both sides, rolling, locking individual strip, stitching
or riveting side patty etc. 44 pcs. @ Tk. 14.70 Per piece = Tk. 646.80
Making other component of rolling shutter and assembling:
(i) Welder/fabricator 2 Nos. @ Tk. 423.00 each = Tk. 846.00
(ii) Welder helper 2 Nos. @ Tk. 304.00 each = Tk. 608.00
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(d) Carrying materials to work-shop and shutter to site L.S. = Tk. 367.50
Sub-total = Tk. 20,936.76
(e) Work-shop charges 10% = Tk. 2,093.68
Total = Tk. 23,030.44
(f) Ancillary work for fitting-fixing the gate:
(i) Making holes 8 Nos. @ Tk. 12.67 each = Tk. 101.36
(ii) Plain concrete: (1:2:4)
8 x 6" x 6" x 6"= 1.00 cft. @ Tk. 17,637.01 Per % cft. = Tk. 176.37
(iii) 1/2" plaster (1:4) to repair walls.
3 x 10'-0" x 1'-0"= 30 sft. @ Tk. 1,527.00 Per % sft. = Tk. 458.10
(g) Labour charge for hoisting and commissioning the gate in position
(i) Mason 0.5 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Mason helper 0.5 No. @ Tk. 304.00 each = Tk. 152.00
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
(iv) Welder/ fabricator 0.5 No. @ Tk. 423.00 each = Tk. 211.50
(v) Welder helper 0.5 No. @ Tk. 304.00 each = Tk. 152.00
Grand total = Tk. 24,598.77
Profit 10.00% = Tk. 2,459.88
Overhead 3.50% = Tk. 860.96
= Tk. 27,919.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,624.95
Grand total = Tk. 29,544.56
Rate per sft. = Tk. 492.41
Rate per sqm. = Tk. 5,300.30

Say, Tk. 5,300 .00 Per sqm.

Item No.- 19.7


Manufacturing, Supplying, fitting, fixing of ordinary type M.S. folding gate
For 1 No gate
Considering : 8'-6"X 7'-9" = 65.87 sft
(a) Cost of materials
(i) 40mm x 40mm x 6mm M.S. angle
2 x 2 x 7'-9"= 31 rft.
Add wastage 5%= 1.55 rft.
= 32.55 rft.
@ 2.33916 rft/lbs
= 76.140 Ibs. @ Tk. 28.34 Per Ib. = Tk. 2,157.81
(ii) 25mm x 25mm x 6mm M.S. angle
8 x 2 x 7'-9"= 124.00 rft.
2 x 2 x 2 x 1 '-10.5"= 14.96 rft.
2 x 2 x 2 x 1'-11"= 15.36 rft.
= 154.32 rft.
Add wastage 5%= 7.72 rft.
Analysis of PWD SoR 2014 for Civil Works 346

= 162.04 rft.
@ 1.489 rft/lbs
= 241.278 Ibs. @ Tk. 28.34 Per Ib. = Tk. 6,837.82
(iii) 12mm x 12mm M.S. Solid square bar
2 X 22 x 1'-10.5"= 82.5 rft.
2 X 22 x 1'-11"= 84.33 rft.
166.83 rft.
Add wastage 5%= 8.3415 rft.
= 175.1715 rft.
@ 0.851 rft/lbs
= 149.071 Ibs. @ Tk. 28.57 Per Ib. = Tk. 4,258.96
(b) Fittings and consumables:
i) Hinges 3" long 12.00 Nos @ Tk. 5.00 Each = Tk. 60.00
ii) Locking arrangement 2.00 Nos. @ Tk. 229.00 Each = Tk. 458.00
iii) Clamp (6" long) 6 Nos. @ Tk. 25.00 Each = Tk. 150.00
iv) Electrodes 200 Pc @ Tk. 10.00 Per pc = Tk. 2,000.00
(c) Making steel gate in work-shop
(i) Welder/ fabricator 6 Nos. @ Tk. 423.00 each = Tk. 2,538.00
(ii) Helper 5 Nos. @ Tk. 304.00 each = Tk. 1,520.00
(iii) Ordinary labour 5 Nos. @ Tk. 245.00 each = Tk. 1,225.00
(d) Carrying cost: materials & finished gate. L.S. = Tk. 50.00
Sub-total = Tk. 21,255.59
(e) Workshop charge 10% = Tk. 2,125.56
Total = Tk. 23,381.15
(f) Ancillary work for fitting-fixing the gate:
i) Making holes L.S. = Tk. 196.00
ii) Cost of CC (1:2:4):
6 x 10" x 6" x 6"= 1.25 cft @ Tk. 176.37 Per cft. = Tk. 220.46
(g) Labour for fitting-fixing the gate:
i) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
ii) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 25,037.61
Profit 10.00% = Tk. 2,503.76
Overhead 3.50% = Tk. 876.32
= Tk. 28,417.69
Add VAT with adjustment factor 1.0582 4.50% = Tk. 1,353.22
Grand total = Tk. 29,770.91
Rate per sft. = Tk. 451.96
Rate per sqm. = Tk. 4,864.90

Say, Tk. 4,865 .00 Per sqm.

DIVISION 20 : STAIR & VERANDAH RAILING AND NOSING


Item No.- 20.1
Supplying, fitting and fixing of stair railing of any height with square box made with 2 Nos.
3/4" x 3/4" x 1/8" angle welded with each other (excluding cost of wood for hand rail).
Considering 1 No. of railing
Considering 9'-9" x 2'-10"= 27.6 sft. exposed surface
(a) Materials:
(i) M.S. angle: 3/4" x 3/4" x 1/8" @ 0.60 lbs. per rft.
2 x 20 x 3'-1"= 122.3 rft.
Add wastage 5%= 6.12 rft.
= 128.42 rft.
= 77.052 Ibs. @ Tk. 28.34 Per Ib. = Tk. 2,183.65
(ii) 2" x 2" x 1/4" thick M.S. plate: @ 10.21 lbs per rft.
20 x 2" x 2"= 0.56 sft.
Analysis of PWD SoR 2014 for Civil Works 347

Add wastage 5%= 0.03 sft.


= 0.59 sft.
= 6.02 Ibs. @ Tk. 38.55 Per lb. = Tk. 232.07
(iii) 1.5" x 1/4" M.S. F.I. bar: @ 1.28 Ibs. per rft.
1 x 9'-9"= 9.75 rft.
Add wastage 5%= 0.49 rft.
= 10.24 rft.
= 13.11 lbs. @ Tk. 25.40 Per Ib. = Tk. 332.99
(b) Fittings, hardwares and consumables:
(i) Electrodes with electricity: 140.00 Nos. @ Tk. 10.00 each = Tk. 1,400.00
(c) Labour for fabrication and making square post
and railing support etc.
(i) Welder / fabricator 0.50 Nos. @ Tk. 423.00 each = Tk. 211.50
(ii) Welder helper 1.50 Nos. @ Tk. 304.00 each = Tk. 456.00
(iii) Ordinary labour 2.00 Nos. @ Tk. 245.00 each = Tk. 490.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 245.00
Sub-total = Tk. 5,551.21
(e) Work-shop charges: 10% = Tk. 555.12
Ttotal = Tk. 6,106.33
(f) Ancillary works for fitting-fixing the railing:
(i) Labour charge for cutting
2" x 2" x 6" size grooves 20 Nos @ Tk. 10.13 each = Tk. 202.60
(ii) CC (1:2:4): 20 x 2" x 2" x 6"= 0.28 cft. @ Tk. 17,637.01 Per % cft. = Tk. 49.38
(g) Labour charge for fitting fixing the stair railing
(i) Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(ii) Mason helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
(iii) Ordinary labour 0.50 No. @ Tk. 245.00 each = Tk. 122.50
(iv) Welder/fabricator 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(v) Welder helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
Grand total = Tk. 6,987.81
Profit 10.00% = Tk. 698.78
Overhead 3.50% = Tk. 244.57
= Tk. 7,931.16
Add VAT with adjustment factor 1.0582 5.50% = Tk. 461.60
Grand total = Tk. 8,392.76
Rate per sft. = Tk. 304.09
Rate per sqm. = Tk. 3,273.22

Say, Tk. 3,273 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 348

Item No.- 20.2


Supplying, fitting and fixing of stair railing of any height with square box made with 2 Nos. 1" x 1" x 3/16"
angle welded (full welding) with each other (excluding cost of wood for hand rail).
Considering 1 No. railing
Considering 9'-9" x 2'-10"= 27.6 sft. of work
(a) Materials:
(i) M.S. angle: 1" x 1" x 3/16" @ 1.16 lbs. per rft.
2 x 10 x 3'-1"= 61.67 rft.
Add wastage 5%= 3.08 rft.
= 64.75 rft.
= 75.11 Ibs. @ Tk. 28.34 Per Ib. = Tk. 2,128.62
(ii) 2" x 2" x 1/4" thick M.S. plate: @ 10.21 lbs per rft.
10 x 2" x 2"= 0.28 sft.
Add wastage 5%= 0.01 sft.
= 0.29 sft.
= 2.96 Ibs. @ Tk. 38.55 Per lb. = Tk. 114.11
(iii) 2" x 1/4" M.S. F.I. bar: @ 1.70 Ibs. per rft.
1 x 9'-9"= 9.75 rft.
Add wastage 5%= 0.49 rft.
= 10.24 rft.
= 17.41 lbs. @ Tk. 25.40 Per Ib. = Tk. 442.21
(b) Fittings, hardwares and consumables:
(i) Electrodes: 100.00 Nos. @ Tk. 10.00 each = Tk. 1,000.00
(ii) Nut-bolt screws etc. 0.25 kg @ Tk. 109.56 Per kg = Tk. 27.39
(c) Labour for fabrication and making square post
and railing-support F.I. bar etc.
(i) Welder / fabricator 0.75 Nos. @ Tk. 423.00 each = Tk. 317.25
(ii) Welder helper 1.50 Nos. @ Tk. 304.00 each = Tk. 456.00
(iii) Ordinary labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 245.00
Sub-total = Tk. 5,098.08
(e) Work-shop charges: 10% = Tk. 509.81
Total = Tk. 5,607.89
(f) Ancillary works & materials for fitting-fixing the railing:
(i) Labour charge for cutting: 2" x 2" x 6" size grooves
10 Nos @ Tk. 12.67 each = Tk. 126.70
(ii) CC (1:2:4): 10 x 2" x 2" x 6"= 0.14 cft. @ Tk. 17,637.01 Per % cft. = Tk. 24.69
(iii) C.T. wood plank:
2 x 10'-0" x 0'-9.5" x 1.25"= 1.65 cft. @ Tk. 4,500.00 Per cft. = Tk. 7,425.00
(g) Labour charge for fitting fixing the stair railing
(i) Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(ii) Mason helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
(iii) Ordinary labour 0.50 No. @ Tk. 245.00 each = Tk. 122.50
(iv) Welder/fabricator 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(v) Welder helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
Grand total = Tk. 13,813.78
Profit 10.00% = Tk. 1,381.38
Overhead 3.50% = Tk. 483.48
= Tk. 15,678.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 912.51
Grand total = Tk. 16,591.15
Rate per sft. = Tk. 601.13
Rate per sqm. = Tk. 6,470.56

Say, Tk. 6,471 .00 Per sqm.

Item No.- 20.3.1


Analysis of PWD SoR 2014 for Civil Works 349

Manufacturing, supplying, fitting and fixing G.I. pipe stair railing with the provision of 6" x 2.5"
hand rails (excluding cost of wood for hand rail) excluding cost of painting.
Considering 1 No. of railing
Considering 9'-9" x 2'-10"= 27.6 sft. of work
(a) Materials:
(i) 1/2" dia G.I. pipe:
10 x 3'-1"= 30.8 rft.
Add wastage 5%= 1.54 rft.
= 32.34 rft. @ Tk. 50.00 Per rft. = Tk. 1,617.00
(ii) 2" x 2" x 1/4" thick M.S. plate: @ 10.21 lbs per rft.
10 x 2" x 2"= 0.28 sft.
Add wastage 5%= 0.01 sft.
= 0.29 sft.
= 2.96 Ibs. @ Tk. 38.55 Per lb. = Tk. 114.11
(iii) 1.5" x 1/4" M.S. F.I. bar: @ 1.28 Ibs. per rft.
1 x 9'-9"= 9.75 rft.
Add wastage 5%= 0.49 rft.
= 10.24 rft.
= 13.11 lbs. @ Tk. 25.40 Per Ib. = Tk. 332.99
(b) Fittings, hardwares and consumables:
(i) Electrodes: 10.00 Nos. @ Tk. 10.00 each = Tk. 100.00
(c) Labour for fabrication and making post and railing support etc.
(i) Welder / fabricator 0.50 Nos. @ Tk. 423.00 each = Tk. 211.50
(ii) Welder helper 0.75 Nos. @ Tk. 304.00 each = Tk. 228.00
(iii) Ordinary labour 1.00 Nos. @ Tk. 245.00 each = Tk. 245.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 100.00
Sub-total = Tk. 2,948.60
(e) Work-shop charges: 10% = Tk. 294.86
Total = Tk. 3,243.46
(f) Ancillary works for fitting -fixing the railing:
(i) Labour charge for cutting: 2" x 2" x 6" size grooves
20 Nos @ Tk. 10.13 each = Tk. 202.60
(ii) CC (1:2:4): 20 x 2" x 2" x 6"= 0.28 cft. @ Tk. 17,637.01 Per % cft. = Tk. 49.38
(g) Labour charge for fitting fixing the stair railing at site
(i) Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(ii) Mason helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
(iii) Ordinary labour 0.50 No. @ Tk. 245.00 each = Tk. 122.50
(iv) Welder/fabricator 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(v) Welder helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
Grand total = Tk. 4,124.94
Profit 10.00% = Tk. 412.49
Overhead 3.50% = Tk. 144.37
= Tk. 4,681.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 272.49
Grand total = Tk. 4,954.29
Rate per sft. = Tk. 179.50
Rate per sqm. = Tk. 1,932.14

Say, Tk. 1,932 .00 Per sqm.


Item No.- 20.3.2
Manufacturing, supplying, fitting and fixing G.I. pipe stair railing with the provision of 4.5" x 2.5"
hand rail (excluding the cost of wood for hand rails) excluding cost of painting.
Considering 1 No. of railing
Clear G.I. pipe height 32.5" + hand rail 4.5" = clear height of railing = 37"
Considering 9'-9" x 3'-1"= 30.06 sft. of work
(a) Materials:
(i) 1/2" dia G.I. pipe
Analysis of PWD SoR 2014 for Civil Works 350

10 x 3'-2.5"= 32.08 rft.


Add wastage 5%= 1.60 rft.
= 33.68 rft. @ Tk. 50.00 Per rft. = Tk. 1,684.00
(ii) 2" x 2" x 1/4" thick M.S. plate: @ 10.21 lbs per rft.
10 x 2" x 2"= 0.27 sft.
Add wastage 5%= 0.01 sft.
= 0.28 sft.
= 2.86 Ibs. @ Tk. 38.55 Per lb. = Tk. 110.25
(iii) 1.5" x 1/4" M.S. F.I. bar: @ 1.28 Ibs. per rft.
1 x 9'-9"= 9.75 rft.
Add wastage 5%= 0.49 rft.
= 10.24 rft.
= 13.11 lbs. @ Tk. 25.40 Per Ib. = Tk. 332.99
(b) Fittings, hardwares and consumables:
(i) Electrodes with electricity: 50.00 Nos. @ Tk. 10.00 each = Tk. 500.00
(c) Labour for fabrication and making square post
and railing support etc.
(i) Welder / fabricator 1.00 Nos. @ Tk. 423.00 each = Tk. 423.00
(ii) Welder helper 2.00 Nos. @ Tk. 304.00 each = Tk. 608.00
(iii) Ordinary labour 2.00 Nos. @ Tk. 245.00 each = Tk. 490.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 245.00
Sub-total = Tk. 4,393.24
(e) Work-shop charges: 10% = Tk. 439.32
Total = Tk. 4,832.56
(f) Ancillary works for fitting-fixing the railing:
(i) Labour charge for cutting 2" x 2" x 6" size grooves
20 Nos. @ Tk. 12.67 each = Tk. 253.40
(ii) CC (1:2:4): 20 x 2" x 2" x 6" = 0.28 cft. @ Tk. 17,637.01 Per % cft. = Tk. 49.38
(g) Labour charge for fitting fixing the stair railing
(i) Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(ii) Mason helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
(iii) Ordinary labour 0.50 No. @ Tk. 245.00 each = Tk. 122.50
(iv) Welder/fabricator 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(v) Welder helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
Grand total = Tk. 5,764.84
Profit 10.00% = Tk. 576.48
Overhead 3.50% = Tk. 201.77
= Tk. 6,543.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 380.81
Grand total = Tk. 6,923.90
Rate per sft. = Tk. 230.34
Rate per sqm. = Tk. 2,479.38

Say, Tk. 2,479 .00 Per sqm.

Item No.- 20.4


Supplying, fitting and fixing of SS stair railing of any standard height with 2 mm thick 50mm dia pipe for hand-rail
Considering : 1X 11'-4" X 3'-2" = 35.92 sft
1 Cost of Materials
A) Cost of Pipe
a) 50 mm dia SS pipe
1 X 11'-4" = 11.33 rft
Add 5% wastage= 0.5665 "
11.90 rft @ Tk. 250.85 Per rft. = Tk. 2,985.12
b) 40 mm dia SS pipe
Vertical 3 X 3'-2" = 9.50 rft
Add 5% wastage= 0.475 "
Analysis of PWD SoR 2014 for Civil Works 351

9.98 rft @ Tk. 198.68 Per rft. = Tk. 1,982.83


c) 25 mm dia SS pipe
Horizontal 6 X 11'-4" = 68.00 rft
Add 5% wastage= 3.40 "
71.40 rft @ Tk. 136.19 Per rft. = Tk. 9,723.97
B Cost of fitting
a) 50 mm dia SS bend 1 Pcs @ Tk. 89.28 Each = Tk. 89.28
b) 50 mm dia end socket 1 Pcs @ Tk. 59.71 Each = Tk. 59.71
c) 40 mm dia end socket 3 Pcs @ Tk. 50.56 Each = Tk. 151.68
d) 25 mm dia socket 6 Pcs @ Tk. 38.57 Each = Tk. 231.42
C Cost of F. I. bar (50mm X 6mm)
3 X 2" = 0.5 rft
@ 1.178 kg/Rm
0.180 kg/Rm @ Tk. 56.00 Per Kg = Tk. 10.08
D 25mm long rowel bolt 3 Nos @ Tk. 8.56 Each = Tk. 25.68
E Welding Rod (Electrode) 100 Nos @ Tk. 10.00 Each = Tk. 1,000.00
2 Fabrication and making post of railing support etc.
i) Welder/Fabricator 1 No. @ Tk. 423.00 Each = Tk. 423.00
ii) Welder helper 2 No. @ Tk. 304.00 Each = Tk. 608.00
iii) Ordinary labour 2 No. @ Tk. 245.00 Each = Tk. 490.00
3 Carrying of Materials from market to work shop and workshop to site L.S. = Tk. 150.00
Total (A+B+C+D+E) = Tk. 17,930.77
4 Polishing work in/c all materials 10% = Tk. 1,793.08
Tk. 19,723.85

Profit 10.00% = Tk. 1,972.39


Overhead 3.50% = Tk. 627.58
= Tk. 22,323.82
Add VAT with adjustment factor 1.0582 4.50% = Tk. 1,063.04
Grand total = Tk. 23,386.86
Rate per sft. = Tk. 651.08
Rate per sqm. = Tk. 7,008.23

Say, Tk. 7,008 .00 Per sqm.

Item No.- 20.5.1


Manufacturing, supplying, fitting and fixing 1/2" dia G.I. pipe verandah
railing @ 5" c/c with 1.5" dia G.I. pipe hand rail.
Considering 1 No. of railing
Clear G.I. pipe height 35.5" + hand rail 1.5" = clear height of railing = 3'-1"
Considering 10'-0" x 3'-1"= 30.83 sft. of verandah railing
(a) Materials:
(i) 1/2" dia G.I. pipe
25 x 3'-2.5"= 80.21 rft.
Add wastage 5%= 4.01 rft.
= 84.22 rft. @ Tk. 50.00 Per rft. = Tk. 4,211.00
(ii) 1.5" dia G.I. pipe:
1 x 10'-6"= 10.5 rft.
Add wastage 5%= 0.53 rft.
= 11.03 rft. @ Tk. 140.00 Per rft. = Tk. 1,544.20
(iii) 2" x 2" x 1/4" M.S.plate: @ 10.2 Ibs. per rft.
25 x 2" x 2"= 0.694 sft.
Add wastage 5%= 0.03 sft.
= 0.724 sft.
= 7.38 lbs. @ Tk. 38.55 Per Ib. = Tk. 284.50
(b) Fittings, hardwares and consumables:
(i) Electrodes in/c electricity 25.00 Nos. @ Tk. 10.00 each = Tk. 250.00
Analysis of PWD SoR 2014 for Civil Works 352

(c) Labour for making verandah grill at workshop


(i) Welder / fabricator 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(ii) Welder helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
(iii) Ordinary labour 0.50 No. @ Tk. 245.00 each = Tk. 122.50
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 245.00
Sub-total = Tk. 6,914.95
(e) Work-shop charges: 10% = Tk. 691.50
Total = Tk. 7,606.45
(f) Ancillary works for fitting-fixing the verandah railing:
(i) Labour charge for cutting
2.5" x 2.5" x 3" size grooves 25 Nos @ Tk. 12.67 each = Tk. 316.75
(ii) CC (1:2:4):
27 x 2.5" x 2.5" x 3"= 0.29 cft. @ Tk. 17,637.01 Per % cft. = Tk. 51.15
(g) Labour charge for fitting-fixing the verandah railing
(i) Mason 0.10 No. @ Tk. 389.00 each = Tk. 38.90
(ii) Mason helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
(iii) Ordinary labour 0.25 No. @ Tk. 245.00 each = Tk. 61.25
(iv) Welder/fabricator 0.10 No. @ Tk. 423.00 each = Tk. 42.30
(v) Welder helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
Grand total = Tk. 8,268.80
Profit 10.00% = Tk. 826.88
Overhead 3.50% = Tk. 289.41
= Tk. 9,385.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 546.22
Grand total = Tk. 9,931.31
Rate per sft. = Tk. 322.13
Rate per sqm. = Tk. 3,467.41

Say, Tk. 3,467 .00 Per sqm.

Item No.- 20.5.2


Manufacturing, supplying, fitting and fixing 1/2" dia G.I. pipe verandah
railing @ 5" c/c with 2" dia G.I. pipe hand rail.
Considering 1 No. of railing
Clear G.I. pipe height 32.5" + hand rail 4.5" = clear height of railing = 3'-1"
Considering 10'-0" x 3'-1"= 30.83 sft. verandah railing
(a) Materials:
(i) 1/2" dia G.I. pipe
25 x 3'-2.5"= 80.21 rft.
Add wastage 5%= 4.01 rft.
= 84.22 rft. @ Tk. 50.00 Per rft. = Tk. 4,211.00
(ii) 2" dia G.I. pipe:
1 x 10'-6"= 10.5
Add wastage 5%= 0.53 rft.
= 11.03 rft. @ Tk. 175.00 Per rft. = Tk. 1,930.25
(iii) 2" x 2" x 1/4" M.S.plate: @ 10.2 Ibs. per rft.
25 x 2" x 2"= 0.694 sft.
Add wastage 5%= 0.03 sft.
= 0.724 sft.
= 7.38 lbs. @ Tk. 38.55 Per Ib. = Tk. 284.50
(b) Fittings, hardwares and consumables:
(i) Electrodes in/c electricity 25.00 Nos. @ Tk. 10.00 each = Tk. 250.00
(c) Labour for making verandah grill
(i) Welder / fabricator 0.50 No. @ Tk. 423.00 each = Tk. 211.50
(ii) Welder helper 1.00 No. @ Tk. 304.00 each = Tk. 304.00
(iii) Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 245.00
Analysis of PWD SoR 2014 for Civil Works 353

Sub-total = Tk. 7,681.25


(e) Work-shop charges: 10% = Tk. 768.13
Total = Tk. 8,449.38
(f) Ancillary works for fitting-fixing the verandah grill:
(i) Labour charge for cutting 2" x 2" x 6" size grooves
27 Nos @ Tk. 12.67 each = Tk. 342.09
(ii) CC (1:2:4):
27 x 2.5" x 2.5" x 3"= 0.29 cft. @ Tk. 17,637.01 Per % cft. = Tk. 51.15
(g) Labour charge for fitting-fixing the verandah grill
(i) Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(ii) Mason helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
(iii) Ordinary labour 0.50 No. @ Tk. 245.00 each = Tk. 122.50
(iv) Welder/fabricator 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(v) Welder helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
Grand total = Tk. 9,472.12
Profit 10.00% = Tk. 947.21
Overhead 3.50% = Tk. 331.52
= Tk. 10,750.85
Add VAT with adjustment factor 1.0582 5.50% = Tk. 625.71
Grand total = Tk. 11,376.56
Rate per sft. = Tk. 369.01
Rate per sqm. = Tk. 3,972.02

Say, Tk. 3,972 .00 Per sqm.

Item No.- 20.6


Manufacturing, supplying, fitting and fixing verandah railing with stainless steel pipes
Considering
1 x 18'-6" x 3'-10" = 70.85 70.85 sft.
2 x 1'-6" x 3' -10" = 11.49 11.49 sft.
82.34 sft.
(a) Materials:
(i) 50 mm dia SS pipe (2 mm thick)
1 x 18'-6" = 18.50 rft.
2 x 1'-9" = 3.5 rft.
22.00 rft.
Add wastage 5%= 1.10 rft.
23.10 rft. @ Tk. 250.85 rft. = Tk. 5,794.64
(ii) 20 mm dia SS pipe: (2 mm thick)
5 x 18'-6" = 92.50 rft.
2 x 5 x 1'-9" = 17.50 rft.
5 x 5 x 2 x 1'-5" = 6.25 rft.
116.25
Add wastage 5%= 5.81 rft.
= 122.06 rft. @ Tk. 93.91 rft. = Tk. 11,462.65
(iii) 25 mm dia SS. Pipe (2 mm thick)
5 x 4 x 1'-5" = 28.4 rft.
Add wastage 5%= 1.42 rft.
= 29.82 rft. @ Tk. 136.19 rft. = Tk. 4,061.19
(iv) 65 mm x 55 mm x 6 mm SS Plate 5 Nos. @ Tk. 552.47 each = Tk. 2,762.35
(v) 50 mm x 25 mm x 2 mm SS box:
5 x 2 x 3'-2" = 31.67 rft.
5 x 2 x 0'-8" = 6.67 rft.
38.34 rft.
Add wastage 5%= 1.92 rft.
40.26 rft. @ Tk. 256.57 rft. = Tk. 10,329.51
(vi) SS Cap 20.00 Nos. @ Tk. 263.53 each = Tk. 5,270.60
Analysis of PWD SoR 2014 for Civil Works 354

(vii) Carriage L.S. = Tk. 204.17


(viii) Fabrication, fitting-fixing including
welding, bending, making box 82.34 sft. @ Tk. 350.00 sft. = Tk. 28,819.00
(ix) Polishing 82.34 sft. @ Tk. 46.67 sft. = Tk. 3,842.81
Total = Tk. 72,546.92
Profit 10.00% = Tk. 7,254.69
Overhead 3.50% = Tk. 2,539.14
= Tk. 82,340.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4,792.31
Grand total = Tk. 87,133.06
Rate per sft. = Tk. 1,058.21
Rate per sqm. = Tk. 11,390.57

Say, Tk. 11,391 .00 Per sqm.

Item No.- 20.7.1


Providing 1.5" x 1.5" x 1/4" M.S. angle to the nosing of steps of stair case: one flight of
stair case with 10 steps 3'-6" wide.
Considering 10 steps
Total rft of nosing: 10 x 3'-6"= 35 rft.
(a) Cost of cutting @ 3 Nos. of grooves per steps
for fixing 1.5" x 1.5" x 3.5" size clamps
(i) Mason 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(b) Cost of CC (1:2:4) with smaller size of chips for fixing clamps:
30 x 1.5" x1.5" x3.5"= 0.14 cft. @ Tk. 17,637.01 Per % cft. = Tk. 24.69
(c) Cost of 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 Ibs. per rft.
10 x 3'-6"= 35 rft.
Add wastage 5%= 1.75 rft.
= 36.75 rft.
= 86.00 Ibs. @ Tk. 28.34 Per Ib. = Tk. 2,437.24
(d) Cost of 3/4" x 1/8" F.I. bar for clamps: @ 0.32 Ibs. per rft.
10 x 3 x 3"= 7.5 rft.
Add wastage 5%= 0.375 rft.
= 7.875 rft.
= 2.52 Ibs. @ Tk. 25.40 Per Ib. = Tk. 64.01
(e) Cutting charge of M.S. angle as per required measurement
in/c cost of T & P. 10 Nos. @ Tk. 6.13 each = Tk. 61.30
(f) Cost of welding of 3/4" x 1/8" F.I. bar for fixing one end with angle including
bifercating on the other end. 30 Nos. @ Tk. 6.13 each = Tk. 183.90
(g) Labour charge for fixing up the M.S. angle in the nosing of steps to
keep the angles in level and parallel with each of the steps properly
(i) Mason 0.5 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 3,336.89
Profit 10.00% = Tk. 333.69
Overhead 3.50% = Tk. 116.79
= Tk. 3,787.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 220.43
Grand total = Tk. 4,007.80
Rate per rft. = Tk. 114.51
Rate per rm. = Tk. 375.71

Say, Tk. 376 .00 Per rm.

Item No.- 20.7.2


Providing 1.25" x 1.25" x 1/4" M.S. angle to the nosing of steps of stair case:
Analysis of PWD SoR 2014 for Civil Works 355

one flight of stair case with 10 steps 3'-6" wide.


Considering 10 steps
Total rft of nosing: 10 x 3'-6"= 35 rft. of work
1. Cost of nosing work: Same as item No.157(a)
except cost of 1.5" x 1.5" x 1/4" size angle = Tk. 899.65
2. Cost of 1.25" x 1.25" x 1/4" angle: @ 1.91 Ibs per rft.
1 x 10 x 3' - 6"= 35 rft.
Add wastage 5%= 1.75 rft.
= 36.75 rft.
= 70.19 Ibs. @ Tk. 28.34 Per Ib. = Tk. 1,989.18
Total = Tk. 2,888.83
Profit 10.00% = Tk. 288.88
Overhead 3.50% = Tk. 101.11
= Tk. 3,278.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 190.83
Grand total = Tk. 3,469.65
Rate per rft. = Tk. 99.13
Rate per rm. = Tk. 325.25

Say, Tk. 325 .00 Per rm.

Item No.- 20.7.3


Providing 1" x 1" x 1/4" M.S. angle to the nosing of steps of stair case: one flight
of stair case with 10 steps 3'-6" wide.
Considering 10 steps
Total rft of nosing: 10 x 3'-6"= 35 rft. of work
1. Cost of nosing work: Same as item No. 157(a) except cost of 1.5" x 1.5" x 1/4" size angle = Tk. 899.65
2. Cost of 1" x 1" x 1/4" M.S. angle: @ 1.49 Ibs. per rft.
10 x 3'-6"= 35 rft.
Add wastage 5%= 1.75 rft.
= 36.75 rft.
= 54.76 Ibs. @ Tk. 28.34 Per Ib. = Tk. 1,551.90
Total = Tk. 2,451.55
Profit 10.00% = Tk. 245.16
Overhead 3.50% = Tk. 85.80
= Tk. 2,782.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 161.94
Grand total = Tk. 2,944.45
Rate per rft. = Tk. 84.13
Rate per rm. = Tk. 276.03

Say, Tk. 276 .00 Per rm.

Item No.- 20.7.4


Providing 1.5" x 1.5" x 1/4" brass angle to the nosing of steps of stair case:
one flight of stair case with 10 steps 3'-6" wide.
Considering 10 steps
Total rft of nosing: 10 x 3'-6"= 35 rft.
(a) Cost of nosing work: Same as item No. 157(a) except cost of 1.5" x 1.5" x 1/4" size angle = Tk. 899.65
(b) Cost of 1.5" x 1.5" x 1/4" brass
angle in/c 5% wastage 36.75 rft. @ Tk. 267.00 Per rft. = Tk. 9,812.25
Total = Tk. 10,711.90
Profit 10.00% = Tk. 1,071.19
Overhead 3.50% = Tk. 374.92
= Tk. 12,158.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 707.61
Grand total = Tk. 12,865.62
Analysis of PWD SoR 2014 for Civil Works 356

Rate per rft. = Tk. 367.59


Rate per rm. = Tk. 1,206.06

Say, Tk. 1,206 .00 Per rm.


Analysis of PWD SoR 2014 for Civil Works 357

DIVISION 21 : GRILL FENCING, BARBED WIRE FENCING


Item No.- 21.1
Manufacturing, supplying, fitting and fixing steel grill fencing in boundary wall with 1.25" x 1/4" F.I.
bars 6" c/c placed vertically and welding with 2 Nos. horizontal 1.25" x 1/4" F.I. bars etc excluding
cost of painting.
Considering 1 No. of steel grill fencing
Considering 8'-9" x 3'-1"= 26.98 sft. grill work
(a) Materials:
(i) 1.25" x 1/4" F.I. bars: @ 1.06 lbs per rft.
Vertical: 17 x 3'-1"= 52.42 rft.
Horizontal: 2 x 9'-9"= 19.5 rft.
= 71.92 rft.
Add wastage 5%= 3.60 rft.
= 75.52 rft.
= 80.05 Ibs. @ Tk. 25.40 Per lb. = Tk. 2,033.27
(b) Fittings, hardwares and consumables:
(i) Electrodes in/c electricity 15.00 Nos. @ Tk. 10.00 each = Tk. 150.00
(c) Labour for making fencing grill
(i) Welder / fabricator 1.00 No. @ Tk. 423.00 each = Tk. 423.00
(ii) Welder helper 1.00 No. @ Tk. 304.00 each = Tk. 304.00
(ii) Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 122.50
Sub-total = Tk. 3,277.77
(e) Work-shop charges: 10% = Tk. 327.78
Total = Tk. 3,605.55
(f) Ancillary works for fitting-fixing the grill fencing:
(i) Labour charge for cutting
3" x 3" x 6" size grooves 4 Nos @ Tk. 12.67 each = Tk. 50.68
(ii) CC (1:2:4):
4 x 3" x 3" x 6"= 0.13 cft. @ Tk. 17,637.01 Per % cft. = Tk. 22.93
(g) Labour charge for fitting-fixing the grill fencing
(i) Mason 0.50 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Mason helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
Grand total = Tk. 4,025.66
Profit 10.00% = Tk. 402.57
Overhead 3.50% = Tk. 140.90
= Tk. 4,569.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 265.93
Grand total = Tk. 4,835.06
Rate per sft. = Tk. 179.21
Rate per sqm. = Tk. 1,929.02

Say, Tk. 1,929 .00 Per sqm.

Item No.- 21.2


Supplying, fitting & fixing of steel grill fencing in boundary wall with 3/4" x 3/4" x 1/8" angle box
6" c/c placed vertically and welding with 2 Nos. horizontal 1" x 1" x 1/4" angle box, the whole
thing again welding with 1.5" x 1.5" x 1/4" M.S. angle box post @ 6'-0" c/c etc.
Considering 1 No. steel grill fencing
Considering 2 panels: 12'-1.5" x 3'-0"= 36.38 sft. fencing work
(a) Materials:
(i) 1.5" x 1.5" x 1/4" M.S. angle for box post: @ 2.34 Ibs. per rft.
@ 6'-0" c/c: 3 x 2 x 4'-6"= 27.00 rft.
Add wastage 5%= 1.35 rft.
= 28.35 rft.
= 66.34 Ibs. @ Tk. 28.34 Per lb. = Tk. 1,880.08
Analysis of PWD SoR 2014 for Civil Works 358

(ii) 1" x 1" x 1/4" M.S. angle box horizontally at top


and bottom.: @ 1.49 lbs per rft.
2 x 2 x 2 x 6'-0"= 48.00 rft.
Add wastage 5%= 2.40 rft.
= 50.40 rft.
= 75.10 lbs. @ Tk. 28.34 Per Ib. = Tk. 2,128.33
(iii) 3/4" x 3/4" x 1/4" M.S. angle for box: @ 0.585 lbs. per rft.
: 22 x 2 x 3'-0"= 132.00 rft.
Add wastage 5%= 6.60 rft.
= 138.60 rft.
= 81.08 lbs. @ Tk. 28.34 Per Ib. = Tk. 2,297.81
(b) Fittings, hardwares and consumables:
(i) Electrodes in/c electricity 140.00 Nos. @ Tk. 10.00 each = Tk. 1,400.00
(c) Labour for making grill fencing
(i) Welder / fabricator 3.00 Nos. @ Tk. 423.00 each = Tk. 1,269.00
(ii) Welder helper 3.00 Nos. @ Tk. 304.00 each = Tk. 912.00
(iii) Ordinary labour 3.00 Nos. @ Tk. 245.00 each = Tk. 735.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 367.50
Sub-total = Tk. 10,989.72
(e) Work-shop charges: 10% = Tk. 1,098.97
Total = Tk. 12,088.69
(f) Ancillary works for fitting-fixing the grill fencing:
(i) Labour charge for cutting
3" x 3" x 12" size grooves 4 Nos @ Tk. 24.50 each = Tk. 98.00
(ii) CC (1:2:4):
4 x 3" x 3" x 12"= 0.25 cft. @ Tk. 17,637.01 Per % cft. = Tk. 44.09
(g) Labour charge for fitting-fixing the grill fencing:
(i) Mason 0.50 No. @ Tk. 389.00 each = Tk. 194.50
(ii) Mason helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
Grand total = Tk. 12,577.28
Profit 10.00% = Tk. 1,257.73
Overhead 3.50% = Tk. 440.20
= Tk. 14,275.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 830.83
Grand total = Tk. 15,106.04
Rate per sft. = Tk. 415.23
Rate per sqm. = Tk. 4,469.54

Say, Tk. 4,470 .00 Per sqm.

Item No.- 21.3


Supplying, fitting & fixing of steel grill fencing with outer frame having 1.5" x 1.5" x 1/4" M.S. angle
and inner member having 1/4" dia M.S. rod placed 4.5" c/c diagonally on both directions.
Considering 1 No. steel grill fencing
Considering a panel of 7'-9" x 3'-3"= 25.19 sft. fencing work

(a) Materials:
(i) 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 Ibs. per rft.
2 x 3'-3"= 6.50 rft.
Horizontal: 2 x 7'-9"= 15.50 rft.
= 22 rft.
Add wastage 5%= 1.1 rft.
23.1 rft.
= 54.05 Ibs. @ Tk. 28.34 Per lb. = Tk. 1,531.78
(ii) 1/4" dia M.S. rod: @ 0.167 lbs. per rft.
20 x 3'-3"= 65.00 rft.
8 x 7'-9"= 62.00 rft.
Analysis of PWD SoR 2014 for Civil Works 359

127.00 rft.
Add wastage 5%= 6.35 rft.
= 133.35 rft.
= 22.27 lbs. @ Tk. 26.76 Per Ib. = Tk. 595.95
(b) Fittings, hardwares and consumables:
(i) Electrodes in/c electricity 35.00 Nos. @ Tk. 10.00 each = Tk. 350.00
(c) Labour for making grill fencing
(i) Welder / fabricator 1.00 No. @ Tk. 423.00 each = Tk. 423.00
(ii) Welder helper 1.00 No. @ Tk. 304.00 each = Tk. 304.00
(iii) Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 183.75
Sub-total = Tk. 3,633.48
(e) Work-shop charges: 10% = Tk. 363.35
Total = Tk. 3,996.83
(f) Labour charge for fitting-fixing the grill fencing:
(i) Welder / fabricator 0.50 No. @ Tk. 423.00 each = Tk. 211.50
(ii) Welder helper 0.50 No. @ Tk. 304.00 each = Tk. 152.00
Grand total = Tk. 4,360.33
Profit 10.00% = Tk. 436.03
Overhead 3.50% = Tk. 152.61
= Tk. 4,948.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 288.04
Grand total = Tk. 5,237.01
Rate per sft. = Tk. 207.90
Rate per sqm. = Tk. 2,237.84

Say, Tk. 2,238 .00 Per sqm.

Item No.- 21.4


Supplying, fitting & fixing of M.S. angle post made thorough welding of 2 nos.
1.5" x 1.5" x 1/4" M.S. angle.
Considering 1 No. steel post

(a) Materials:
(i) 1.5" x 1.5" x 1/4" M.S. angle for box post: @ 2.34 Ibs. per rft.
2 x 6'-3"= 12.5 rft.
Add wastage 5%= 0.63 rft.
= 13.13 rft.
= 30.72 Ibs. @ Tk. 28.34 Per lb. = Tk. 870.60
(ii) 1.5" x 1/4" M.S. plate: @ 10.20 lbs. per sft.
2 x 1.5" x 1.5"= 0.030 sft.
Add wastage 5%= 0.002 sft.
= 0.032 sft.
= 0.33 lbs. @ Tk. 38.55 Per Ib. = Tk. 12.72
(b) Fittings, hardwares and consumables:
(i) Electrodes in/c electricity 12.00 Nos. @ Tk. 10.00 each = Tk. 120.00
(c) Labour for making grill fencing
(i) Welder / fabricator 0.20 No. @ Tk. 423.00 each = Tk. 84.60
(ii) Welder helper 0.20 No. @ Tk. 304.00 each = Tk. 60.80
(iii) Ordinary labour 0.20 No. @ Tk. 245.00 each = Tk. 49.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 20.00
Sub-total = Tk. 1,217.72
(e) Work-shop charges: 10% = Tk. 121.77
Total = Tk. 1,339.49
(f) Labour charge for fitting-fixing the grill fencing:
(i) Mason 0.20 No. @ Tk. 389.00 each = Tk. 77.80
(ii) Mason helper 0.20 No. @ Tk. 304.00 each = Tk. 60.80
Analysis of PWD SoR 2014 for Civil Works 360

Grand total = Tk. 1,478.09


Profit 10.00% = Tk. 147.81
Overhead 3.50% = Tk. 51.73
= Tk. 1,677.63
Add VAT with adjustment factor 1.0582 5.50% = Tk. 97.64
Grand total = Tk. 1,775.27
Rate per rft. = Tk. 284.04
= Tk. 931.94

Say, Tk. 932 .00 Per rm.

Item No.- 21.5


Barbed wire fencing (7'-0" height) with RCC pillars 8'-0" c/c.
Considering 120' - 0" x 7' - 0"= 840 sft. of work
(a) 12 BWG barbed wire: @ 950 rft per cwt.
Horizontal: 8 x 120'-0"= 960 rft.
Diagonal: 15 x 2 x 10'-6"= 315 rft.
= 1275 rft.
= 1.34 cwt. @ Tk. 5,562.50 Per cwt. = Tk. 7,453.75
(b) G.I wire 2.00 kg. @ Tk. 110.00 Per kg. = Tk. 220.00
(c) Labour for stretching, tightening and binding barbed wire in position
(i) Skilled labour 2.5 Nos. @ Tk. 303.00 each = Tk. 757.50
(ii) Head mason 1 No. @ Tk. 493.00 each = Tk. 493.00
(d) Local carriage, storage, sundries etc. L.S. = Tk. 122.50
Total = Tk. 9,046.75
Profit 10.00% = Tk. 904.68
Overhead 3.50% = Tk. 316.64
= Tk. 10,268.07
Add VAT with adjustment factor 1.0582 5.50% = Tk. 597.61
Grand total = Tk. 10,865.68
Rate per sft. = Tk. 12.94
Rate per sqm. = Tk. 139.29

Say, Tk. 139 .00 Per sqm.

Item No.- 21.6


Barbed wire fencing (4'-6" height) with 4" av. dia best quality local bullah post 6'-0" c/c.
Considering 120' - 0" x 4' - 6"= 540 sft. of work
9 Nos. horizontal line of barbed wire with equal spacing & two nos of diagonal lines per bay.
(a) 12 BWG barbed wire: @ 950 rft per cwt.
Horizontal: 9 x 120'-0"= 1080 rft.
Diagonal: 20 x 2 x 7'-6"= 300 rft.
= 1380 rft.
= 1.45 cwt. @ Tk. 5,562.50 Per cwt. = Tk. 8,065.63
(b) Cost of nails and staples: 2 kg. @ Tk. 73.04 Per kg = Tk. 146.08
(c) Cost of G.I. Wire 2.25 kg. @ Tk. 110.00 Per kg = Tk. 247.50
(d) Labour for streching, tightening and binding barbed wire in position
(i) Carpenter 1.50 Nos. @ Tk. 423.00 each = Tk. 634.50
(ii) Skilled labour 2.50 Nos. @ Tk. 303.00 each = Tk. 757.50
(e) Local carriage, storage, sundries etc. L.S. = Tk. 183.75
Total = Tk. 10,034.96
Profit 10.00% = Tk. 1,003.50
Overhead 3.50% = Tk. 351.22
= Tk. 11,389.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 662.89
Grand total = Tk. 12,052.57
Rate per sft. = Tk. 22.32
Analysis of PWD SoR 2014 for Civil Works 361

Rate per sqm. = Tk. 240.25

Say, Tk. 240 .00 Per sqm.

Item No.- 21.7


Barbed wire fencing over brick wall/RCC member with 1.5" x 1.5" x 1/4" M.S. angle
post 2'-0" straight + 1'-6" inclined.
Considering 24'-0" x 3'-6"= 84 sft. of work
1. Barbed wire works:
(a) Cost of barbed wire: 12 BWG 2 ply 4 points; @ 950 rft. per cwt.
7 x 24'-0" + 49 x 4'-6"= 388.5 rft.
= 0.41 cwt. @ Tk. 5,562.50 Per cwt. = Tk. 2,280.63
(b) Cost of 18 SWG G.I. wire 1.00 kg @ Tk. 110.00 Per kg. = Tk. 110.00
(c) Labour for streching, tightening and binding barbed wire in position
(i) Skilled labour 1.50 Nos. @ Tk. 303.00 each = Tk. 454.50
(ii) Labour charge for fitting with M.S. angle post
(iii) Skilled labour 1.00 No. @ Tk. 303.00 each = Tk. 303.00
(d) Local carriage and storage L.S. = Tk. 61.25
(e) T & P and sundries L.S. = Tk. 61.25
2. M.S. Angle works:
(a) 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 lbs per rft.
4 x (1'-0" + 2'-0" + 1'-6")= 18.00 rft.
Add wastage 5%= 0.90 rft.
= 18.90 rft.
= 44.23 lbs. @ Tk. 28.34 Per lb. = Tk. 1,253.48
(b) Fabrication cost of angles:
(i) Welder / fabricator 0.25 No. @ Tk. 423.00 each = Tk. 105.75
(ii) Welder helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
(iii) Mason for fxing in position 0.25 No. @ Tk. 389.00 each = Tk. 97.25
(iv) Mason helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
(v) Local carriage and storage L.S. = Tk. 61.25
Total = Tk. 4,940.36
Profit 10.00% = Tk. 494.04
Overhead 3.50% = Tk. 172.91
= Tk. 5,607.31
Add VAT with adjustment factor 1.0582 5.50% = Tk. 326.35
Grand total = Tk. 5,933.66
Rate per sft. = Tk. 70.64
Rate per sqm. = Tk. 760.37

Say, Tk. 760 .00 Per sqm.

DIVISION 22 : MISCELLANEOUS ITEMS


Item No.- 22.1
Supplying fitting fixing 12 x 12 mm (base x height) thick triangular wooden bit instead
of putty for fixing glass panes
Analysis of PWD SoR 2014 for Civil Works 362

Considering 10 rft. of work


(a) 1/2" x 1/2"size wooden bit (garjan wood):
10'-0" x 0.5" x0. 5"= 0.02 cft.
Add wastage 10%= 0.002 cft.
= 0.022 cft. @ Tk. 2,000.0 Per cft. = Tk. 44.00
(b) Cost of nails = Tk. 7.30
(c) Labour charge for fitting and fixing
Carpenter 0.2 No. @ Tk. 423.00 each = Tk. 84.60
Total = Tk. 135.90
Profit 10.00% = Tk. 13.59
Overhead 3.50% = Tk. 4.76
= Tk. 154.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 8.98
Grand total = Tk. 163.23
Rate per rft. = Tk. 16.32
Rate per rm. = Tk. 53.55

Say, Tk. 54 .00 Per rm.

Item No.- 22.2


Supplying, fitting, fixing of 20mm dia Aluminium pipe curtain rail
Considering : 6'-0" = 6.00 rft
A) Cost of materials
i) Cost of pipe: 20 mm Aluminium pipe
Horizontal 1 x 6'-0"= 6.00 rft.
Add wastage 5%= 0.30 rft.
= 6.30 rft. @ Tk. 88.20 Per rft = Tk. 555.66
ii) Cost of fitting wheel 3 Nos. @ Tk. 43.26 Each = Tk. 129.78
iii) Royal plug screws etc. L.S. = Tk. 12.00
B) Labour Charge
i) Carpenter 1/8 No. @ Tk. 423.00 Per day = Tk. 52.88
ii) Carpenter helper 1/8 No. @ Tk. 304.00 Per day = Tk. 38.00
iii) Skilled Labour 1/4 No. @ Tk. 303.00 Per day = Tk. 60.00
Total = Tk. 848.32
Profit 10.00% = Tk. 84.83
Overhead 3.50% = Tk. 29.69
= Tk. 962.84
Add VAT with adjustment factor 1.0582 4.50% = Tk. 45.85
Grand total = Tk. 1,008.69
Rate per rt. = Tk. 168.12
Rate per rm. = Tk. 551.60

Say, Tk. 552 .00 Per rm.

Item No.- 22.3


Supplying, fitting-fixing 10 mm thick tempered glass door
Considering 1 x 3'-0" x 7'-0" = 21.00 sft.
A. Cost of Materials
i) Cost of 10 mm thick tempered glass
21.00 sft.
Add 3% wastage= 0.63 sft.
21.63 sft. @ Tk. 333.00 Per sft. = Tk. 7,202.79
ii) Floor mountain auto closure Taiwan origin 1 set @ Tk. 5,231.00 Per set = Tk. 5,231.00
ii) Clamping device top and bottom 2 Nos. @ Tk. 1,014.00 Each = Tk. 2,028.00
iv) Locking device 1 set @ Tk. 2,355.00 Per set = Tk. 2,355.00
v) Top hinge (Pivot) 1 set @ Tk. 1,043.00 Per set = Tk. 1,043.00
vi) Handle 1 set @ Tk. 2,293.00 Per set = Tk. 2,293.00
Analysis of PWD SoR 2014 for Civil Works 363

Total = Tk. 20,152.79


B. Labour cost for fitting and fixing:
i) Skilled Technician 1 No. @ Tk. 700.00 Each = Tk. 700.00
ii) Semi-Skilled Technician 1 No. @ Tk. 450.00 Each = Tk. 450.00
C. Scaffolding L.S. = Tk. 50.00
D. Local Carriage L.S. = Tk. 100.00
Total = Tk. 21,452.79
Profit 10.00% = Tk. 2,145.28
Overhead 3.50% = Tk. 750.85
= Tk. 24,348.92
Add VAT with adjustment factor 1.0582 4.50% = Tk. 1,159.47
Grand total = Tk. 25,508.39
Rate per sft. = Tk. 1,214.69
Rate per sqm. = Tk. 13,074.92

Say, Tk. 13,075 .00 Per sqm.

Item No.- 22.4


Supplying, fitting-fixing 10 mm thick clear glass partition with aluminium box

Considering : 1X 5'-0"X 7'-0" = 35.00 sft


A. Cost of Materials
i) Cost of 10 mm thick glass 35.00 sft.
Add 3% wastage= 1.05 sft.
36.05 sft. @ Tk. 180.00 Per sft. = Tk. 6,489.00
ii) 44mm x 44mm Aluminium box 5 rft @ Tk. 72.45 Per rft = Tk. 362.25
iii) Protector bit (Single) 17.00 rft @ Tk. 19.93 Per rft = Tk. 338.81
iv) Protector bit (Double) 17.00 rft @ Tk. 26.31 Per rft = Tk. 447.27
v) SS Screws 8 No. @ Tk. 1.91 Each = Tk. 15.28
vi) Silicon (1 piece 300 ml) 1 No. @ Tk. 312.19 Each = Tk. 312.19
vii) Rowel plug 8 No. @ Tk. 0.71 Each = Tk. 5.68
viii) Rivet 6 No. @ Tk. 4.62 Each = Tk. 27.72
Sub Total (A) = Tk. 7,998.20
B Labour cost 3.5 sft. @ Tk. 245.00 Per sft. = Tk. 857.50
Total = Tk. 8,855.70
Profit 10.00% = Tk. 885.57
Overhead 3.50% = Tk. 309.95
= Tk. 10,051.22
Add VAT with adjustment factor 1.0582 5.50% = Tk. 584.99
Grand total = Tk. 10,636.21
Rate per sft. = Tk. 303.89
Rate per sqm. = Tk. 3,271.07

Say, Tk. 3,271 .00 Per sqm.

Item No.- 22.5


Supplying fitting fixing Chittagong teak wood strip 62 mm x 25 mm x 20 mm for fixing
curtain rail for doors and windows.
Considering 4 rft. of work
(a) Chittagong teak wood:
1 x 4'-0" x 2.5" x 1" = 0.069 cft.
Add wastage 5%= 0.0035 cft.
0.073 cft. @ Tk. 4,500.0 Per rft. = Tk. 328.50
(b) Labour charge
(i) Carpenter 1/8 No. @ Tk. 423.00 each = Tk. 52.88
(ii) Helper 1/2 No. @ Tk. 304.00 each = Tk. 152.00
(c) Fitting, fixing, screws and polishing L.S. = Tk. 122.50
Analysis of PWD SoR 2014 for Civil Works 364

Total = Tk. 655.88


Profit 10.00% = Tk. 65.59
Overhead 3.50% = Tk. 22.96
= Tk. 744.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 43.33
Grand total = Tk. 787.76
Rate per rft. = Tk. 196.94
Rate per rm. = Tk. 646.16

Say, Tk. 646 .00 Per rm.

Item No.- 22.6


Supplying, fitting and fixing of vertical venetian blind of glass fibre fabrics
Considering 1 unit
Considering 1 x 8'-0" x 6'-0"= 48 sft. of work
1. Head rail, aluminium 8.2 rft. @ Tk. 8.34 Per rft. = Tk. 68.39
2. Rod tilt/hexagon aluminium rod 8 rft. @ Tk. 8.05 Per rft. = Tk. 64.40
3. End cap set/end closure set 2 sets @ Tk. 61.20 Per set = Tk. 122.40
4. Weight plate/weight bar 32 Nos. @ Tk. 9.23 each = Tk. 295.36
5. Link chain/weight chain 32.81 rft. @ Tk. 9.04 Per rft. = Tk. 296.60
6. Ball chain/plastic chain 39.34 rft. @ Tk. 8.99 Per rft. = Tk. 353.67
7. Plastic washer/fabricupper clip 32 Nos. @ Tk. 2.20 each = Tk. 70.40
8. Spacer (link)/plastic runner spring 8 rft. @ Tk. 7.41 Per rft. = Tk. 59.28
9' Handling cord/nylon cord 92.1 rft. @ Tk. 2.84 Per rft. = Tk. 261.56
10. Thread bar 1 No. @ Tk. 7.97 each = Tk. 7.97
11. Angle clip 3 Nos. @ Tk. 7.04 each = Tk. 21.12
12. Plastic runner 32 Nos. @ Tk. 3.32 each = Tk. 106.24
13. Glass fibre fabrics 48 sft. @ Tk. 88.62 Per sft. = Tk. 4,253.76
14. Angle 3 Nos. @ Tk. 4.17 each = Tk. 12.51
15. Fitting-fixing charge 48 sft. @ Tk. 3.15 Per sft. = Tk. 151.20
Total = Tk. 6,144.86
Profit 10.00% = Tk. 614.49
Overhead 3.50% = Tk. 215.07
= Tk. 6,974.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 405.92
Grand total = Tk. 7,380.34
Rate per sft. = Tk. 153.76
Rate per sqm. = Tk. 1,655.07

Say, Tk. 1,655 .00 Per sqm.

Item No.- 22.7


Supplying, fitting and fixing of horizontal venetian blind of aluminium foils/strips
Considering 1 unit
Considering 1 x 8'-0" x 6'-0"= 48 sft. of work
1. Head rail 8 rft. @ Tk. 6.22 Per rft. = Tk. 49.76
2. Bottom rail 8 rft. @ Tk. 4.05 Per rft. = Tk. 32.40
3. Aluminium strips 48 sft. @ Tk. 74.42 Per sft. = Tk. 3,572.16
4. Rod till/hexagon aluminium rod 8 rft. @ Tk. 5.43 Per rft. = Tk. 43.44
5. Gear box /tilter 2 Nos. @ Tk. 8.81 each = Tk. 17.62
6. Support and cord drum 4 Nos. @ Tk. 5.48 each = Tk. 21.92
7. Cord lock 4 Nos. @ Tk. 5.42 each = Tk. 21.68
8. Stop ring 6 Nos. @ Tk. 7.16 each = Tk. 42.96
9' Tassel 6 Nos. @ Tk. 4.22 each = Tk. 25.32
10. Ladder cord 118.42 rft. @ Tk. 3.14 Per rft. = Tk. 371.84
11. Stick / tilt wand 2 Nos. @ Tk. 7.87 each = Tk. 15.74
12. Bracket/metal intermediatebracket 4 Nos. @ Tk. 7.02 each = Tk. 28.08
Analysis of PWD SoR 2014 for Civil Works 365

13. Bottom cap/end cap for head rail 2 Nos. @ Tk. 9.97 each = Tk. 19.94
14. Tape holder 2 Nos. @ Tk. 5.51 each = Tk. 11.02
15. Steel washer 2 Nos. @ Tk. 7.44 each = Tk. 14.88
16. Head cap set 2 Nos. @ Tk. 11.89 each = Tk. 23.78
17. Handling cord 81.97 rft. @ Tk. 3.34 Per rft. = Tk. 273.78
18. Labour cost 48 sft. @ Tk. 2.72 Per sft. = Tk. 130.56
Total = Tk. 4,716.88
Profit 10.00% = Tk. 471.69
Overhead 3.50% = Tk. 165.09
= Tk. 5,353.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 311.59
Grand total = Tk. 5,665.25
Rate per sft. = Tk. 118.03
Rate per sqm. = Tk. 1,270.47

Say, Tk. 1,270 .00 Per sqm.

Item No.- 22.8


Supplying and fitting-fixing of steel iron rack: 24'-0" x 2'-3" x 14'-0"
Considering 24'-0" x 14'-0"= 336 sft. of work
1. 2" x 2" x 1/4" MS angle: @ 3.19 Ibs per rft.:
Angle post: 14 x 14'-0"= 196.00 rft.
7 x 8 x 2'-3"= 126.00 rft.
Horizontal: 8 x 2 x 24'-0"= 384.00 rft.
= 706.00 rft.
= 2252.14 Ibs. @ Tk. 28.34 Per Ibs = Tk. 63,825.65
2. 2.5" x 1/4" F.I. bar: @ 1.91 Ibs per rft.:
Horizontal bar: 8 x 3 x 24'-0"= 576.00 rft.
8 x 12 x 2'-3"= 216.00 rft.
= 792.00 rft.
= 1512.72 Ibs. @ Tk. 25.40 Per Ibs. = Tk. 38,423.09
3. 1.5" x 1/4" F.I. bar: @ 1.28 Ibs per rft.:
6 x 2 x 2 x 3'-3"= 78.00 rft.
= 99.84 Ibs. @ Tk. 25.40 Per Ibs = Tk. 2,535.94
4. 1/2" thick MS plate: 20.10 Ibs per rft.
8" dia cup: 14 x 3.142 x 8" x 6"= 14.66 sft.
14 x 3.142 x (0'-4")2= 4.88 sft.
Plate for bottom of the post:
14 x 1'-6" x 1'-6"= 31.50 sft.
= 51.04 sft.
= 1025.90 Ibs. @ Tk. 38.55 Per Ibs. = Tk. 39,548.45
= Tk. 144,333.13
Add wastage 5% = Tk. 7,216.66
= Tk. 151,549.79
5. Cost of CC (1:2:4) block:
14 x 1'-6" x 8" x 6" = 7.00 cft. @ Tk. 176.37 Per cft. = Tk. 1,234.59
6. Fabrication, fitting-fixing revetting, welding and hoisting including
cost of revets, bolts etc and painting,
local carriage complete 2223.00 kg. @ Tk. 40.40 Per kg. = Tk. 89,809.20
Total = Tk. 242,593.58
Profit 10.00% = Tk. 24,259.36
Overhead 3.50% = Tk. 8,490.78
= Tk. 275,343.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 16,025.28
Grand total = Tk. 291,369.00
Rate per sft. = Tk. 867.17
Rate per sqm. = Tk. 9,334.22
Analysis of PWD SoR 2014 for Civil Works 366

Say, Tk. 9,334 .00 Per sqm.

Item No.- 22.9


Supplying & fitting-fixing of uPVC plastic door/window frame (Chowkat): (size 2.13 m x 0.99m ) (for hollow shutter)
Considering 2 x 2.13 m + 0.99 m = 5.25 rm frame
1. Door frame: 5.25 rm @ Tk. 105 Per rm = Tk. 551.25
2. G.I. wall clamp 6 pcs. @ Tk. 13.20 Per pc. = Tk. 79.20
3. G.I. inner joint clamp 4 pcs. @ Tk. 13.02 Per pc. = Tk. 52.08
4. G.I. outer joint clamp 2 pcs. @ Tk. 11.22 Per pc. = Tk. 22.44
5. Revit 16 pcs. @ Tk. 1.10 Per pc. = Tk. 17.60
6. Wooden bit: Garjan 2.13 m @ Tk. 26.39 Per m = Tk. 56.21
7. Carpenter 1/4 No. @ Tk. 423.00 each = Tk. 105.75
8. Carpenter helper 1/4 No. @ Tk. 304.00 each = Tk. 76.00
9. Carrying LS = Tk. 122.50
Total = Tk. 1,083.03
Profit 10.00% = Tk. 108.30
Overhead 3.50% = Tk. 37.91
= Tk. 1,229.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 71.54
Grand total = Tk. 1,300.78
Rate per rm = Tk. 247.77
Say, Tk. 248 .00 Per rm.
Item No.- 22.10.1
Supplying and fitting-fixing uPVC hollow door shutter: (size 760 x 1980 mm)
Considering 1 No. shutter
1. Hollow shutter 1.4 sqm. @ Tk. 862.40 Per sqm = Tk. 1,207.36
2. Reinforcement 4.27 rm @ Tk. 25.44 Per rm = Tk. 108.63
3. Revit 36 pcs. @ Tk. 1.10 each = Tk. 39.60
4. S.S. Screw (40mm long) 24 pcs. @ Tk. 3.08 each = Tk. 73.92
5. S.S. Tower bolt 2 pcs. @ Tk. 56.00 each = Tk. 112.00
6. S.S. handle 2 pcs. @ Tk. 52.51 each = Tk. 105.02
7. G. I. inner joint clamp 2 pcs. @ Tk. 13.02 each = Tk. 26.04
8. S.S. Hinges 3 pcs. @ Tk. 47.32 each = Tk. 141.96
9 Lock 1 pc. @ Tk. 435.31 each = Tk. 435.31
10 Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
11 Carpentr helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
12 Fitting fixing charge LS. = Tk. 183.75
13 Carrying LS. = Tk. 98.00
Total = Tk. 2,713.34
Profit 10.00% = Tk. 271.33
Overhead 3.50% = Tk. 94.97
= Tk. 3,079.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 179.24
Grand total = Tk. 3,258.88

Say, Tk. 3,259 .00 each


Item No.- 22.10.2
Supplying and fitting-fixing uPVC solid door shutter: (size 760 x 2130 mm)
Considering 1 No. shutter
1. Solid shutter 1.47 sqm. @ Tk. 862.40 Per sqm = Tk. 1,267.73
2. Reinforcement 5.49 rm @ Tk. 25.44 Per rm = Tk. 139.67
3. Revit 36 pcs. @ Tk. 1.10 each = Tk. 39.60
4. S.S. Screw (40mm long) 24 pcs. @ Tk. 3.08 each = Tk. 73.92
5. S.S. Tower bolt 2 pcs. @ Tk. 56.00 each = Tk. 112.00
6. S.S. handle 2 pcs. @ Tk. 52.51 each = Tk. 105.02
7. G. I. inner joint clamp 2 pcs. @ Tk. 13.02 each = Tk. 26.04
Analysis of PWD SoR 2014 for Civil Works 367

8. S.S. Hinges 3 pcs. @ Tk. 47.32 each = Tk. 141.96


9 Lock 1 pc. @ Tk. 435.31 each = Tk. 435.31
10 Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
11 Carpentr helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
12 Fitting fixing charge LS. = Tk. 183.75
13. Carrying LS. = Tk. 98.00
Total = Tk. 2,804.75
Profit 10.00% = Tk. 280.48
Overhead 3.50% = Tk. 98.17
= Tk. 3,183.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 185.28
Grand total = Tk. 3,368.68

Say, Tk. 3,369 .00 each

Item No.- 22.10.3


Supplying and fitting-fixing uPVC hollow door shutter: (size 910 x 2130 mm)
Considering 1 No. shutter
1. Hollow shutter 1.64 sqm. @ Tk. 862.40 Per sqm = Tk. 1,414.34
2. Reinforcement 5.89 rm @ Tk. 25.44 Per rm = Tk. 149.84
3. Revit 36 pcs. @ Tk. 1.10 each = Tk. 39.60
4. S.S. Screw (40mm long) 24 pcs. @ Tk. 3.08 each = Tk. 73.92
5. S.S. Tower bolt 2 pcs. @ Tk. 56.00 each = Tk. 112.00
6. S.S. handle 2 pcs. @ Tk. 52.51 each = Tk. 105.02
7. G.I. inner joint clamp 2 pcs. @ Tk. 13.02 each = Tk. 26.04
8. S.S. Hinges 3 pcs. @ Tk. 47.32 each = Tk. 141.96
9 Lock 1 pc. @ Tk. 435.31 each = Tk. 435.31
10 Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
11 Carpentr helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
12 Fitting fixing charge LS. = Tk. 183.75
13. Carrying LS. = Tk. 98.00
Total = Tk. 2,961.53
Profit 10.00% = Tk. 296.15
Overhead 3.50% = Tk. 103.65
= Tk. 3,361.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 195.63
Grand total = Tk. 3,556.96

Say, Tk. 3,557 .00 each

Item No.- 22.10.4


Supplying and fitting-fixing uPVC solid door shutter: (size 990 x 2130 mm)
Considering 1 No. shutter
1. Hollow shutter 1.8 sqm. @ Tk. 862.40 Per sqm = Tk. 1,552.32
2. Reinforcement 6.04 rm @ Tk. 25.44 Per rm = Tk. 153.66
3. Revit 36 pcs. @ Tk. 1.10 each = Tk. 39.60
4. S.S. Screw (40mm long) 24 pcs. @ Tk. 3.08 each = Tk. 73.92
5. S.S. Tower bolt 2 pcs. @ Tk. 56.00 each = Tk. 112.00
6. S.S. handle 2 pcs. @ Tk. 52.51 each = Tk. 105.02
7. G.I. inner joint clamp 2 pcs. @ Tk. 13.02 each = Tk. 26.04
8. S.S. Hinges 3 pcs. @ Tk. 47.32 each = Tk. 141.96
9 Lock 1 pc. @ Tk. 435.31 each = Tk. 435.31
10 Carpenter 0.25 No. @ Tk. 423.00 each = Tk. 105.75
11 Carpentr helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
12 Fitting fixing charge LS. = Tk. 183.75
13. Carrying LS. = Tk. 61.25
Total = Tk. 3,066.58
Analysis of PWD SoR 2014 for Civil Works 368

Profit 10.00% = Tk. 306.66


Overhead 3.50% = Tk. 107.33
= Tk. 3,480.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 202.57
Grand total = Tk. 3,683.14

Say, Tk. 3,683 .00 each


Item No.- 22.11.1
Supplying and fitting-fixing uPVC plastic partion with hollow section: (size 2 m x 3 m)
Considering 1 No. partition of 6 sqm.
1. T-frame 9 rm @ Tk. 128.58 Per rm = Tk. 1,157.22
2. L-frame 10 rm @ Tk. 132.24 Per rm = Tk. 1,322.40
3. Hollow bit 28 rm @ Tk. 58.32 Per rm = Tk. 1,632.96
4. T-inner joint clamp 14 pcs. @ Tk. 8.50 each = Tk. 119.00
5. L-inner joint clamp 4 pcs. @ Tk. 12.88 each = Tk. 51.52
6. Revit 80 pcs. @ Tk. 1.10 each = Tk. 88.00
7. Screw 24 pcs. @ Tk. 1.59 each = Tk. 38.16
8. Rowel plug 24 pcs. @ Tk. 0.71 each = Tk. 17.04
9. Hollow section 6 sqm. @ Tk. 862.40 Per sqm = Tk. 5,174.40
10. Carpenter 4.5 Nos. @ Tk. 423.00 each = Tk. 1,903.50
11. Carpentr helper 1.5 Nos. @ Tk. 304.00 each = Tk. 456.00
12. Carrying LS. = Tk. 122.50
Total = Tk. 12,082.70
Profit 10.00% = Tk. 1,208.27
Overhead 3.50% = Tk. 422.89
= Tk. 13,713.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 798.16
Grand total = Tk. 14,512.02
Rate per sqm. = Tk. 2,418.67

Say, Tk. 2,419 .00 Per sqm

Item No.- 22.11.2


Supplying and fitting-fixing uPVC plastic partion with glass: (size 2 m x 3 m)
Considering 1 No. partition of 6 sqm.
1. T-frame 9 rm @ Tk. 128.58 Per rm = Tk. 1,157.22
2. L-frame 10 rm @ Tk. 132.24 Per rm = Tk. 1,322.40
3. Glass bit 28 rm @ Tk. 59.46 Per rm = Tk. 1,664.88
4. Round rubber bit 14 rm @ Tk. 18.37 Per rm = Tk. 257.18
5. Rubber bit 4 rm @ Tk. 7.68 Per rm = Tk. 30.72
6. T-inner joint clamp 80 pcs. @ Tk. 8.50 each = Tk. 680.00
7. L-inner joint clamp 24 pcs. @ Tk. 12.88 each = Tk. 309.12
8. Revit 24 pcs. @ Tk. 1.10 each = Tk. 26.40
9. Screw 6 pcs. @ Tk. 1.59 each = Tk. 9.54
10. Rowel plug 4.5 pcs. @ Tk. 0.71 each = Tk. 3.20
11. Adhesive 1.5 kg. @ Tk. 183.60 Per kg. = Tk. 275.40
12. 5 mm glass 6.00 sqm. @ Tk. 684.31 Per sqm. = Tk. 4,105.86
13. Carpenter 3 Nos. @ Tk. 423.00 each = Tk. 1,269.00
14. Carpenter helper 3 Nos. @ Tk. 304.00 each = Tk. 912.00
15. Carrying LS. = Tk. 122.50
Total = Tk. 12,145.42
Profit 10.00% = Tk. 1,214.54
Overhead 3.50% = Tk. 425.09
= Tk. 13,785.05
Add VAT with adjustment factor 1.0582 5.50% = Tk. 802.30
Grand total = Tk. 14,587.36
Rate per sqm. = Tk. 2,431.23
Analysis of PWD SoR 2014 for Civil Works 369

Say, Tk. 2,431 .00 Per sqm

Item No.- 22.12


uPVC door frame (chowkat) (For solid door)
Considering 7'-0" x 2'-6"size door = 16.50 rft. chowkat
1. Profile:
Partition frame 17 rft. @ Tk. 53.37 Per rft. = Tk.907.29
2. Re-inforcement:
Partition frame 14 rft. @ Tk. 25.60 Per rft. = Tk.358.40
3. Steel clamp (8") 6 Nos. @ Tk. 8.42 each = Tk.50.52
4. Carrying LS. = Tk.25.00
5. Carpenter 1 No. @ Tk. 423.00 each = Tk.423.00
6. Welding in/c electricity LS. = Tk. 73.50
Total = Tk.1,837.71
Profit 10.00% = Tk. 183.77
Overhead 3.50% = Tk. 64.32
= Tk. 2,085.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 121.40
Grand total = Tk. 2,207.20
Rate per rft. = Tk.133.77
Rate per rm. = Tk.438.90

Say, Tk. 439 .00 Per rm.

Item No.- 22.13.1


6'-6" x 2'-6" size uPVC swing door shutter
Considering 1 No. swing door
1. 8 mm thick uPVC sheet 0.5 No. @ Tk. 1,475.64 Per pc. = Tk. 737.82
2. Profile:
(a) Partition frame 17 rft. @ Tk. 53.37 Per rft. = Tk. 907.29
(b) 4" New sash 18 rft. @ Tk. 136.66 Per rft. = Tk. 2,459.88
(c) Sliding glass bit 18 rft. @ Tk. 19.77 Per rft. = Tk. 355.86
3. Re-inforcement
Partition frame 14 rft. @ Tk. 25.60 Per rft. = Tk. 358.40
4. Rubber 36 rft. @ Tk. 6.73 Per rft. = Tk. 242.28
5. Accessories
(a) Screw LS. = Tk. 81.48
(b) Hinges 4 Nos. @ Tk. 46.33 each = Tk. 185.32
(c) Sitkani 2.00 pcs. @ Tk. 62.34 each = Tk. 124.68
(d) Handle 2 Nos. @ Tk. 50.65 each = Tk. 101.30
(e) Steel clamp 6 Nos. @ Tk. 8.42 each = Tk. 50.52
6. Carrying LS. = Tk. 122.50
7. Carpenter 1.25 Nos. @ Tk. 423.00 each = Tk. 528.75
8. Carpenter helper 1 No. @ Tk. 304.00 each = Tk. 304.00
9. Welding in/c electricity LS. = Tk. 735.00
Total = Tk. 7,295.08
Profit 10.00% = Tk. 729.51
Overhead 3.50% = Tk. 255.33
= Tk. 8,279.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 481.90
Grand total = Tk. 8,761.82

Say, Tk. 8,762 .00 each

Item No.- 22.13.2


7'-0" x 2'-6" size uPVC swing door shutter
Analysis of PWD SoR 2014 for Civil Works 370

Considering 1 No. swing door


1. 8 mm thick uPVC sheet 0.5 No. @ Tk. 1,475.64 Per pc. = Tk. 737.82
2. Profile:
(a) Partition frame 17 rft. @ Tk. 53.37 Per rft. = Tk. 907.29
(b) 4" New sash 19 rft. @ Tk. 136.66 Per rft. = Tk. 2,596.54
(c) Sliding glass bit 19 rft. @ Tk. 19.77 Per rft. = Tk. 375.63
3. Re-inforcement:
(a) Partition frame 16 rft. @ Tk. 25.60 Per rft. = Tk. 409.60
4. Rubber 38 rft. @ Tk. 6.73 Per rft. = Tk. 255.74
5. Accessories
(a) Screw LS. = Tk. 81.48
(b) Hinges 4 Nos. @ Tk. 46.33 each = Tk. 185.32
(c) Sitkani 2.00 pc. @ Tk. 62.34 each = Tk. 124.68
(d) Handle 2 Nos. @ Tk. 50.65 each = Tk. 101.30
(e) Steel clamp 6 Nos. @ Tk. 8.42 each = Tk. 50.52
6. Carrying LS. = Tk. 122.50
7. Carpenter 1.25 Nos. @ Tk. 423.00 each = Tk. 528.75
8. Carpenter helper 1 No. @ Tk. 304.00 each = Tk. 304.00
9. Welding in/c electricity LS. = Tk. 735.00
Total = Tk. 7,516.17
Profit 10.00% = Tk. 751.62
Overhead 3.50% = Tk. 263.07
= Tk. 8,530.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 496.50
Grand total = Tk. 9,027.36

Say, Tk. 9,027 .00 each

Item No.- 22.13.3


7'-0" x 3'-0" size uPVC swing door shutter
Considering 1 swing door
1. 8 mm thick PVC sheet 0.5 Nos. @ Tk. 1,475.64 Per pc. = Tk. 737.82
2. Profile:
(a) Partition frame 17 rft. @ Tk. 53.37 Per rft. = Tk. 907.29
(b) 4" New sash 20 rft. @ Tk. 136.66 Per rft. = Tk. 2,733.20
(c) Sliding glass bit 20 rft. @ Tk. 19.77 Per rft. = Tk. 395.40
3. Re-inforcement
Partition frame 18 rft. @ Tk. 25.60 Per rft. = Tk. 460.80
4. Rubber 40 rft. @ Tk. 6.73 Per rft. = Tk. 269.20
5. Accessories
(a) Screw LS. = Tk. 81.48
(b) Hinges 4 Nos. @ Tk. 46.33 each = Tk. 185.32
(c) Sitkani 2 pc. @ Tk. 62.34 each = Tk. 124.68
(d) Handle 2 Nos. @ Tk. 50.65 each = Tk. 101.30
(e) Steel clamp 6 Nos. @ Tk. 8.42 each = Tk. 50.52
6. Carrying LS. = Tk. 122.50
7. Carpenter 1.25 Nos. @ Tk. 423.00 each = Tk. 528.75
8. Carpenter helper 1 No. @ Tk. 304.00 each = Tk. 304.00
9. Welding in/c electricity LS. = Tk. 735.00
Total = Tk. 7,737.26
Profit 10.00% = Tk. 773.73
Overhead 3.50% = Tk. 270.80
= Tk. 8,781.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 511.11
Grand total = Tk. 9,292.90

Say, Tk. 9,293 .00 each


Analysis of PWD SoR 2014 for Civil Works 371

Item No.- 22.14


uPVC wall paneling with solid uPVC section
Considering 10'-0" x 10'-0"size = 100 sft.
1. Plastic wood
(3 mm thick sheet) 6 pcs. @ Tk. 666.14 Per pc. = Tk. 3,996.84
2. Accessories
(a) 2" screw 5 pack @ Tk. 109.65 Per pack = Tk. 548.25
(b) Wall bit (9/64) 2 pcs. @ Tk. 38.23 Per pc. = Tk. 76.46
(c) Super bit 1 pc. @ Tk. 154.86 Per pc. = Tk. 154.86
(d) Sun Star glue 3 liter @ Tk. 107.55 Per liter = Tk. 322.65
(e) Cloth 5 yrds. @ Tk. 16.48 Per yrd. = Tk. 82.40
(f) Tarpin 0.5 gallon @ Tk. 184.44 Per gallon = Tk. 92.22
(g) Super glue 4 Nos. @ Tk. 26.76 each Tk. 107.04
3. Labour
(a) Carpenter 4 Nos. @ Tk. 423.00 each = Tk. 1,692.00
(b) Carpenter helper 4 Nos. @ Tk. 304.00 each = Tk. 1,216.00
(c) Carrying L.S. = Tk. 367.50
Total = Tk. 8,656.22
Profit 10.00% = Tk. 865.62
Overhead 3.50% = Tk. 302.97
= Tk. 9,824.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 571.81
Grand total = Tk. 10,396.62
Rate per sft. = Tk. 103.97
Rate per sqm. = Tk. 1,119.13

Say, Tk. 1,119 .00 Per sqm.

Item No.- 22.15


uPVC fixed partition with 5mm clear glass
Considering 4'-0" x 4'-0" size = 16 sft.
1. Profile:
(a) Partition frame 17 rft. @ Tk. 53.37 Per rft. = Tk. 907.29
(b) Partition glass bit 16 rft. @ Tk. 8.94 Per rft. = Tk. 143.04
2. Re-inforcement
(a) Partition frame 14 rft. @ Tk. 25.60 Per rft. = Tk. 358.40
3. Rubber 32 rft. @ Tk. 6.73 Per rft. = Tk. 215.36
4. 5 mm clear glass 16.00 sft. @ Tk. 81.31 Per sft. = Tk. 1,300.96
5. Accessories
(a) Screw LS. = Tk. 74.72
(b) Steel clamp 6 Nos. @ Tk. 8.42 each = Tk. 50.52
6. Carrying LS. = Tk. 61.25
7. Carpenter 0.75 No. @ Tk. 423.00 each = Tk. 317.25
8. Carpenter helper 0.25 No. @ Tk. 304.00 each = Tk. 76.00
9. Welding in/c electricity LS. = Tk. 367.50
Total = Tk. 3,872.29
Profit 10.00% = Tk. 387.23
Overhead 3.50% = Tk. 135.53
= Tk. 4,395.05
Add VAT with adjustment factor 1.0582 5.50% = Tk. 255.80
Grand total = Tk. 4,650.85
Rate per sft. = Tk. 290.68
Rate per sqm. = Tk. 3,128.88

Say, Tk. 3,129 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 372

Item No.- 22.16.1


Solid uPVC sliding window with 5 mm clear glass
Considering 4'-0" x 4'-0"size = 16 sft.
1. Profile:
(a) Sliding frame 17 rft. @ Tk. 30.86 Per rft. = Tk. 524.62
(b) Sliding sash 24 rft. @ Tk. 36.08 Per rft. = Tk. 865.92
(c) Sliding glass bead 24 rft. @ Tk. 19.77 Per rft. = Tk. 474.48
(d) Sliding interlock 7 rft. @ Tk. 12.57 Per rft. = Tk. 87.99
2. Re-inforcement
(a) Sliding frame 14 rft. @ Tk. 25.82 Per rft. = Tk. 361.48
(b) Sliding sash 20 rft. @ Tk. 27.29 Per rft. = Tk. 545.80
3. Rubber 40 rft. @ Tk. 6.73 Per rft. = Tk. 269.20
4. Brush 30 rft. @ Tk. 9.13 Per rft. Tk. 273.90
5. 5 mm clear glass 15 sft. @ Tk. 81.31 Per sft. = Tk. 1,219.65
6. Accessories
(a) 1.5" screw L.S. = Tk. 36.75
(b) Lock 2 Nos. @ Tk. 31.17 each = Tk. 62.34
(c) Steel clamp 6 Nos. @ Tk. 8.42 each = Tk. 50.52
7 Others
(a) Carpenter 0.5 No. @ Tk. 423.00 each = Tk. 211.50
(b) Welding in/c electricity L.S. = Tk. 367.50
(c) Carrying L.S. = Tk. 61.25
Total = Tk. 5,412.90
Profit 10.00% = Tk. 541.29
Overhead 3.50% = Tk. 189.45
= Tk. 6,143.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 357.57
Grand total = Tk. 6,501.21
Rate per sft. = Tk. 406.33
Rate per sqm. = Tk. 4,373.74

Say, Tk. 4,374 .00 Per sqm.

Item No.- 22.16.2


uPVC sliding window without glass.
Considering 4'-0" x 4'-0"size = 16 sft.
1. Profile:
(a) Sliding frame 17 rft. @ Tk. 30.86 Per rft. = Tk. 524.62
(b) Sliding sash 24 rft. @ Tk. 36.08 Per rft. = Tk. 865.92
(c) Sliding glass bead 24 rft. @ Tk. 19.77 Per rft. = Tk. 474.48
(d) Sliding interlock 7 rft. @ Tk. 12.57 Per rft. = Tk. 87.99
2. Re-inforcement
(a) Sliding frame 14 rft. @ Tk. 25.82 Per rft. = Tk. 361.48
(b) Sliding sash 20 rft. @ Tk. 27.29 Per rft. = Tk. 545.80
3. Rubber 40 rft. @ Tk. 6.73 Per rft. = Tk. 269.20
4. Brush 30 rft. @ Tk. 9.13 Per rft. Tk. 273.90
5. Accessories
(a) 1.5" screw L.S. = Tk. 36.75
(b) Lock 2 Nos. @ Tk. 31.17 each = Tk. 62.34
(c) Steel clamp 6 Nos. @ Tk. 8.42 each = Tk. 50.52
6. Others
(a) Carpenter 0.5 No. @ Tk. 423.00 each = Tk. 211.50
(b) Welding in/c electricity L.S. = Tk. 367.50
(c) Carrying L.S. = Tk. 61.25
Total = Tk. 4,193.25
Profit 10.00% = Tk. 419.33
Overhead 3.50% = Tk. 146.76
Analysis of PWD SoR 2014 for Civil Works 373

= Tk. 4,759.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 277.00
Grand total = Tk. 5,036.34
Rate per sft. = Tk. 314.77
Rate per sqm. = Tk. 3,388.18

Say, Tk. 3,388 .00 Per sqm.

Item No.- 22.17


Solid uPVC false ceiling.
Considering 10'-0" x 10'-0"size = 100 sft. false ceiling
1. Plastic wood (6 mm thick) 4 pcs. @ Tk. 1,264.27 Per pc. = Tk. 5,057.08
2. Aluminium section & accessories
(a) 1" main Tee 2 pcs. @ Tk. 26.05 Per pc. = Tk. 52.10
(b) 1" cross Tee 1 pc. @ Tk. 22.62 Per pc. = Tk. 22.62
(c) 1" L-section 2 pcs. @ Tk. 22.72 Per pc. = Tk. 45.44
(d) Revit L.S. = Tk. 122.50
(e) G.1. wire 0.5 kg. @ Tk. 110.00 Per kg = Tk. 55.00
(f) 1.5" screw L.S. = Tk. 132.00
(g) Rowl plug 2 pack @ Tk. 18.43 Per pack Tk. 36.86
(h) Wall bit 2 Nos. @ Tk. 38.23 each = Tk. 76.46
3. Labour
(a) Carpenter 4 Nos. @ Tk. 423.00 each = Tk. 1,692.00
(b) Carpenter helper 4 Nos. @ Tk. 304.00 each = Tk. 1,216.00
(c) Carrying L.S. = Tk. 367.50
Total = Tk. 8,875.56
Profit 10.00% = Tk. 887.56
Overhead 3.50% = Tk. 310.64
= Tk. 10,073.76
Add VAT with adjustment factor 1.0582 5.50% = Tk. 586.30
Grand total = Tk. 10,660.06
Rate per sft. = Tk. 106.60
Rate per sqm. = Tk. 1,147.44

Say, Tk. 1,147 .00 Per sqm.


Item No.- 22.18
Supplying, fitting and fixing approved quality 190 mm x 190 mm size glass bricks in round stair wall
Break-up for 1 x 2'-6" x 2'-6" = 6.25 sft. area
1. Glass bricks 16.00 Nos.
Wastage 5% = 1 Nos.
17.00 Nos. @ Tk. 328.33 each = Tk. 5,581.61
3. White cement 10.00 kg @ Tk. 25.00 kg = Tk. 250.00
4. 1/4" dia M.S. Rod
2 x 3 x 4 x 2'-6" = 60 rft.
= 10.02 Ibs @ Tk. 26.76 Per Ib = Tk. 268.14
5. Scaffolding 6.25 sft. @ Tk. 7.20 Per sft. = Tk. 45.00
6. Labour charge 16.00 Nos. @ Tk. 29.18 each = Tk. 466.88
7. Local carriage, sundries, Tools and plant etc. L.S. = Tk. 30.63
Total = Tk. 6,642.26
Profit 10.00% = Tk. 664.23
Overhead 3.50% = Tk. 232.48
= Tk. 7,538.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 438.78
Grand total = Tk. 7,977.75
Rate per sft. = Tk. 1,276.44
Rate per sqm. = Tk. 13,739.60
Analysis of PWD SoR 2014 for Civil Works 374

Say Tk. 13,740 .00 per sqm.

Item No.- 22.19


Supplying, fitting and fixing 50 mm thick rock/glass wool padding
Break-up for panel: 1 x 12'-0" x 10'-0" = 120 sft. area
1. Glass wool in/c 5% wastage 126.00 sft. @ Tk. 197.48 per sft. = Tk. 24,882.48
2. Rubber gum (30 gm per sft.) 3.60 kg. @ Tk. 602.71 Per kg. = Tk. 2,169.76
3. Wire net in/c 5% wastage 126.00 sft. @ Tk. 18.00 per sft. = Tk. 2,268.00
4. Nails L.S. = Tk. 36.52
5. Fitting, fixing 120 sft. @ Tk. 25.97 Per sft. = Tk. 3,116.40
6. Tools and plant etc. L.S. = Tk. 102.08
Total = Tk. 32,575.24
Profit 10.00% = Tk. 3,257.52
Overhead 3.50% = Tk. 1,140.13
= Tk. 36,972.89
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,151.86
Grand total = Tk. 39,124.75
Rate per sft. = Tk. 326.04
Rate per sqm. = Tk. 3,509.49

Say Tk. 3,509 .00 per sqm.


Analysis of PWD SoR 2014 for Civil Works 375

DIVISION 23 : EXCAVATION OF TANK


Item No.- 23.1
Earth work in excavation of tanks of any dimension
Considering 1000 cft. of excavation work
23.1.1 For initial lead of 1000'-0" and lift of 5'-0"
(i) Ordinary labour 12.5 Nos. @ Tk. 245.00 each = Tk. 3,062.50
(ii) Sardar 1/2 No. @ Tk. 493.00 each = Tk. 246.50
(iii) Tools & plants (spade, busket) etc. L.S. = Tk. 36.75
Total = Tk. 3,345.75
Profit 10.00% = Tk. 334.58
Overhead 3.50% = Tk. 117.10
= Tk. 3,797.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 221.01
Grand total = Tk. 4,018.44
Rate per cft. = Tk. 4.02
Rate per cum. = Tk. 141.97

Say, Tk. 142 .00 Per cum.

23.1.2 For each additional lift of one foot beyond 5'-0" and upto 10'-0"
Considering 1000 cft. of excavation work
(i) Extra labour 1/2 No. @ Tk. 245.00 each = Tk. 122.50
Profit 10.00% = Tk. 12.25
Overhead 3.50% = Tk. 4.29
= Tk. 139.04
Add VAT with adjustment factor 1.0582 5.50% = Tk. 8.09
Grand total = Tk. 147.13
Rate per cft. = Tk. 0.15
Rate per cum. = Tk. 5.30

Say Tk. 5.30 Per cum.

23.1.3 For each additional lift of one foot beyond 10'-0" and upto 15'-0"
Considering 1000 cft. of excavation work
(i) Extra labour 3/4 No. @ Tk. 245.00 each = Tk. 183.75
Profit 10.00% = Tk. 18.38
Overhead 3.50% = Tk. 6.43
= Tk. 208.56
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12.14
Grand total = Tk. 220.70
Rate per cft. = Tk. 0.22
Rate per cum. = Tk. 7.77
Say Tk. 7.77 Per cum.

23.1.4 For each additional lift of one foot beyond 15'-0" and upto 20'-0"
Considering 1000 cft. of excavation work
(i) Extra labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Profit 10.00% = Tk. 24.50
Overhead 3.50% = Tk. 8.58
= Tk. 278.08
Add VAT with adjustment factor 1.0582 5.50% = Tk. 16.18
Grand total = Tk. 294.26
Rate per cft. = Tk. 0.29
Rate per cum. = Tk. 10.24
Say, Tk. 10.24 Per cum.
23.1.5 Extra each additional lead of 100'-0"
Analysis of PWD SoR 2014 for Civil Works 376

Considering 1000 cft. of excavation work


(i) Extra labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Profit 10.00% = Tk. 49.00
Overhead 3.50% = Tk. 17.15
= Tk. 556.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.37
Grand total = Tk. 588.52
Rate per cft. = Tk. 0.59
Rate per cum. = Tk. 20.84

Say Tk. 20.84 Per cum.

Item No.- 23.2.1


Bailing-out water using 1 cusec diesel operated pump set
Considering 1 day operation = 8 Hrs.
(i) Hire charge of pump including suction
and delivery pipe, connection, switch 1 day @ Tk. 1,030.95 Per day = Tk. 1,030.95
(ii) Fuel, lubricant, spares, maintenance etc. L.S. = Tk. 600.00
(iii) Pump operator 1 No. @ Tk. 423.00 Per day = Tk. 423.00
(iv) Helper 1 No. @ Tk. 304.00 Per day = Tk. 304.00
(v) Skilled labour for maintaining drainage 1 No. @ Tk. 303.00 Per day = Tk. 303.00
(vi) Provide drainage facilities and connection to discharge system L.S. = Tk. 250.00
(viii) Tools and plant, sundries etc. L.S. = Tk. 150.00
Tk. 3,060.95
Profit 10.00% = Tk. 306.10
Overhead 3.50% = Tk. 107.13
= Tk. 3,474.18
Add VAT with adjustment factor 1.0582 5.50% = Tk. 191.08
Grand total = Tk. 3,665.26
Rate per hour = Tk. 458.16

Say, Tk. 458 .00 Per hour

Item No.- 23.2.2


Bailing-out water using 1 cusec pump electricity operated pump set
Considering 1 day operation = 8 Hrs.
(i) Hire charge of pump including suction
and delivery pipe, connection, switch 1 day @ Tk. 760.00 Per day = Tk. 760.00
(ii) Electricity, lubricant, spares, maintenance etc. L.S. = Tk. 300.00
(iii) Pump operator 1 No. @ Tk. 423.00 Per day = Tk. 423.00
(iv) Helper 1 No. @ Tk. 304.00 Per day = Tk. 304.00
(v) Skilled labour for maintaining drainage 1 No. @ Tk. 303.00 Per day = Tk. 303.00
(vi) Provide drainage facilities and connection to discharge facilities L.S. = Tk. 250.00
(viii) Tools and plant, sundries etc. L.S. = Tk. 150.00
Tk. 2,490.00
Profit 10.00% = Tk. 249.00
Overhead 3.50% = Tk. 87.15
= Tk. 2,826.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 155.44
Grand total = Tk. 2,981.59
Rate per hour = Tk. 372.70

Say, Tk. 373 .00 Per hour

DIVISION 24 : ROAD AND PAVEMENT WORKS


Analysis of PWD SoR 2014 for Civil Works 377

Item No.- 24.1


Earth work in road embankment upto a lift of 5'-0"
Considering 1000 cft. of earth work
24.1.1 For initial lead of 1000'-0" and lift of 5'-0"
(i) Ordinary labour 10 Nos. @ Tk. 245.00 each = Tk. 2,450.00
(ii) Sardar 1/4 No. @ Tk. 493.00 each = Tk. 123.25
(iii) Tools & plant (spade, busket) etc. L.S. = Tk. 36.75
Total = Tk. 2,610.00
Profit 10.00% = Tk. 261.00
Overhead 3.50% = Tk. 91.35
= Tk. 2,962.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 172.41
Grand total = Tk. 3,134.76
Rate per cft. = Tk. 3.13
Rate per cum. = Tk. 110.54

Say, Tk. 111 .00 Per cum.


24.1.2 For additional lift of 3'-0", beyond 5'-0" upto 8'-0"
Considering 1000 cft. of erth work
(i) E/W upto 5'-0" lift Same as item No.183(a) = Tk. 2,610.00
(ii) Extra labour for additional lift 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
Total = Tk. 2,977.50
Profit 10.00% = Tk. 297.75
Overhead 3.50% = Tk. 104.21
= Tk. 3,379.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 196.69
Grand total = Tk. 3,576.15
Rate per cft. = Tk. 3.58
Rate per cum. = Tk. 126.43

Say, Tk. 126 .00 Per cum.

24.1.3 For additional lift of 3'-0", beyond 8'-0" upto 11'-0"


Considering 1000 cft. of earth work
(i) E/W upto 8'-0" lift: Same as item No. 183(b) = Tk. 2,977.50
(ii) Extra labour for additional lift 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
Total = Tk. 3,345.00
Profit 10.00% = Tk. 334.50
Overhead 3.50% = Tk. 117.08
= Tk. 3,796.58
Add VAT with adjustment factor 1.0582 5.50% = Tk. 220.96
Grand total = Tk. 4,017.54
Rate per cft. = Tk. 4.02
Rate per cum. = Tk. 141.97
Say, Tk. 142 .00 Per cum.

24.1.4 For additional lift of 3'-0", beyond 11'-0" upto 14'-0"


Considering 1000 cft. of earth work
(i) E/W upto 11'-0" lift: Same as item No. 183(c) = Tk. 3,345.00
(ii) Extra labour for additional lift 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
Total = Tk. 3,712.50
Profit 10.00% = Tk. 371.25
Overhead 3.50% = Tk. 129.94
= Tk. 4,213.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 245.24
Grand total = Tk. 4,458.93
Rate per cft. = Tk. 4.46
Analysis of PWD SoR 2014 for Civil Works 378

Rate per cum. = Tk. 157.50


Say, Tk. 158 .00 Per cum.
24.1.5 For additional lift of 3'-0", beyond 14'-0" upto 17'-0"
Considering 1000 cft. of earth work
(i) E/W upto 11'-0" lift: Same as item No. 183(d) = Tk. 3,712.50
(ii) Extra labour for addl. lift 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
Total = Tk. 4,080.00
Profit 10.00% = Tk. 408.00
Overhead 3.50% = Tk. 142.80
= Tk. 4,630.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 269.52
Grand total = Tk. 4,900.32
Rate per cft. = Tk. 4.90
Rate per cum. = Tk. 173.04

Say, Tk. 173 .00 Per cum.

24.1.6 For additional lift of 3'-0", beyond 17'-0" upto 20'-0"


Considering 1000 cft. of earth work
(i) E/W upto 11'-0" lift: Same as item No. 183(e) = Tk. 4,080.00
(ii) Extra labour for addl. lift 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
Total = Tk. 4,447.50
Profit 10.00% = Tk. 444.75
Overhead 3.50% = Tk. 155.66
= Tk. 5,047.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 293.79
Grand total = Tk. 5,341.70
Rate per cft. = Tk. 5.34
Rate per cum. = Tk. 188.58

Say, Tk. 189 .00 Per cum.

Item No.- 24.2.1


Earth work in box cutting upto 1'-0" depth
Considering 100 sft. of work
(i) Ordinary labour 1 Nos. @ Tk. 245.00 each = Tk. 245.00
(ii) Mason 1/8 No. @ Tk. 389.00 each = Tk. 48.63
Total = Tk. 293.63
Profit 10.00% = Tk. 29.36
Overhead 3.50% = Tk. 10.28
= Tk. 333.27
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.40
Grand total = Tk. 352.67
Rate per sft. = Tk. 3.53
Rate per sqm. = Tk. 38.00

Say, Tk. 38 .00 Per sqm.

Item No.- 24.2.1


Earth work in box cutting upto 1'-6" depth
Considering 100 sft. of work
(i) Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
(ii) Mason 1/8 No. @ Tk. 389.00 each = Tk. 48.63
Total = Tk. 416.13
Profit 10.00% = Tk. 41.61
Overhead 3.50% = Tk. 14.56
= Tk. 472.30
Analysis of PWD SoR 2014 for Civil Works 379

Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.49


Grand total = Tk. 499.79
Rate per sft. = Tk. 5.00
Rate per sqm. = Tk. 53.82

Say, Tk. 54 .00 Per sqm.

Item No.- 24.3


Turfing the side slopes and top of embankment
Considering 1000 sft. of work
1. Labour for cutting grass turf upto proper size, carrying and
placing it on the embankment side by side
(a) Ordinary labour 1 Nos. @ Tk. 245.00 each = Tk. 245.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
2. Watering the turf property & profusely at least twice a day and
guarding it from grazing animals for 7 days
(a) Ordinary labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
(b) Royalty or cost of the turf 1000 sft. @ Tk. 9.00 Per % sft. = Tk. 90.00
Total = Tk. 1,005.50
Profit 10.00% = Tk. 100.55
Overhead 3.50% = Tk. 35.19
= Tk. 1,141.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 66.42
Grand total = Tk. 1,207.66
Rate per sft. = Tk. 1.21
Rate per sqm. = Tk. 13.02

Say, Tk. 13 .00 Per sqm.


Item No.- 24.4
Single brick flat soling
Considering 100 sft. of work
(a) Bricks 300 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 2,250.00
(b) Fine sand 5 cft. @ Tk. 900.00 Per % cft. = Tk. 45.00
(c) Head mason 1/16 No. @ Tk. 493.00 each = Tk. 30.81
(d) Mason 1/4 No. @ Tk. 389.00 each = Tk. 97.25
(e) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(f) Local carriage, sundries, T & P L.S. = Tk. 122.50
Total = Tk. 2,848.56
Profit 10.00% = Tk. 284.86
Overhead 3.50% = Tk. 99.70
= Tk. 3,233.12
Add VAT with adjustment factor 1.0582 5.50% = Tk. 188.17
Grand total = Tk. 3,421.29
Rate per sft. = Tk. 34.21
Rate per sqm. = Tk. 368.24
Say, Tk. 368 .00 Per sqm.
Item No.- 24.5
Brick on end edge pavement in herring bone bond.
Considering 100 sft. of work
(a) Bricks 500 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 3,750.00
(b) Fine sand 10 cft. @ Tk. 900.00 Per % cft. = Tk. 90.00
(c) Head mason 1/16 No. @ Tk. 493.00 each = Tk. 30.81
(d) Mason 3/4 No. @ Tk. 389.00 each = Tk. 291.75
(e) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(f) Local carriage, sundries, T & P L.S. = Tk. 183.75
Total = Tk. 4,649.31
Profit 10.00% = Tk. 464.93
Analysis of PWD SoR 2014 for Civil Works 380

Overhead 3.50% = Tk. 162.73


= Tk. 5,276.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 307.12
Grand total = Tk. 5,584.09
Rate per sft. = Tk. 55.84
Rate per sqm. = Tk. 601.06

Say, Tk. 601 .00 Per sqm.

Item No.- 24.6


Double brick flat soling
Considering 100 sft. of work
(a) Bricks 600 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 4,500.00
(b) Fine sand 12 cft. @ Tk. 900.00 Per % cft. = Tk. 108.00
(c) Head mason 1/16 No. @ Tk. 493.00 each = Tk. 30.81
(d) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(e) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
(f) Local carriage, sundries, T & P L.S. = Tk. 122.50
Total = Tk. 5,756.31
Profit 10.00% = Tk. 575.63
Overhead 3.50% = Tk. 201.47
= Tk. 6,533.41
Add VAT with adjustment factor 1.0582 5.50% = Tk. 380.25
Grand total = Tk. 6,913.66
Rate per sft. = Tk. 69.14
Rate per sqm. = Tk. 744.22

Say, Tk. 744 .00 Per sqm.


Item No.- 24.7
Brick on end edging
Considering 100 rft. of work
(a) Bricks 250 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 1,875.00
(b) Fine sand 2 cft. @ Tk. 900.00 Per % cft. = Tk. 18.00
(c) Head mason 1/20 No. @ Tk. 493.00 each = Tk. 24.65
(d) Mason 1/4 No. @ Tk. 389.00 each = Tk. 97.25
(e) Skilled labour 3/4 No. @ Tk. 303.00 each = Tk. 227.25
(f) Local carriage, sundries, T & P L.S. = Tk. 122.50
Total = Tk. 2,364.65
Profit 10.00% = Tk. 236.47
Overhead 3.50% = Tk. 82.76
= Tk. 2,683.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 156.20
Grand total = Tk. 2,840.08
Rate per rft. = Tk. 28.40
Rate per rm. = Tk. 93.18
Say, Tk. 93 .00 Per rm.
Item No.- 24.8
Breaking picked Jhama & 1st class bricks or bats in/c cost of bricks.
Considering 100 cft. of work
24.8.1 For 100 cft. of works 2.5" - 1.5" size
(i) Bricks 850 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 6,375.00
(ii) Ordinary labour for breaking 3.5 Nos. @ Tk. 245.00 each = Tk. 857.50
Total = Tk. 7,232.50
Profit 10.00% = Tk. 723.25
Overhead 3.50% = Tk. 253.14
= Tk. 8,208.89
Add VAT with adjustment factor 1.0582 5.50% = Tk. 477.77
Analysis of PWD SoR 2014 for Civil Works 381

Grand total = Tk. 8,686.66


Rate per cft. = Tk. 86.87
Rate per cum. = Tk. 3,067.81
Say, Tk. 3,068 .00 Per cum.
24.8.2 For 100 cft. of works 1.5" - 1" size
Considering 100 cft. of work
(i) Bricks 850 Nos. @ Tk. 7,500.00 Per % 0 Nos. = Tk. 6,375.00
(ii) Ordinary labour for breaking 4.5 Nos. @ Tk. 245.00 each = Tk. 1,102.50
Total = Tk. 7,477.50
Profit 10.00% = Tk. 747.75
Overhead 3.50% = Tk. 261.71
= Tk. 8,486.96
Add VAT with adjustment factor 1.0582 5.50% = Tk. 493.95
Grand total = Tk. 8,980.91
Rate per cft. = Tk. 89.81
Rate per cum. = Tk. 3,171.64

Say, Tk. 3,172 .00 Per cum.


Item No.- 24.9
Labour for compacted water bound macadam base course
Consider 20'-0" x 10'-0" x 0'-6"= 100 cft. of work
1. Ordinary labour for spreading
in/c local carriage 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
2. Labour for hand packing 1/4 No. @ Tk. 245.00 each = Tk. 61.25
3. Labour for watering 1/2 No. @ Tk. 245.00 each = Tk. 122.50
4. Cost of sand for blinding 8 cft. @ Tk. 900.00 Per % cft. = Tk. 72.00
5. Labour for blinding 1/4 No. @ Tk. 245.00 each = Tk. 61.25
6. Head mason 1/16 No. @ Tk. 493.00 each = Tk. 30.81
7. Mason 1/4 No. @ Tk. 389.00 each = Tk. 97.25
8. Hire charge of 8 ton to 12 ton road
roller (two steel drum roller) 1/10 day @ Tk. 5,063.00 Per day = Tk. 506.30
9. Fuel & lubricants, spares,
maintenance, driver etc. 1/10 day @ Tk. 1,268.00 Per day = Tk. 126.80
Total = Tk. 1,445.66
Profit 10.00% = Tk. 144.57
Overhead 3.50% = Tk. 50.60
= Tk. 1,640.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 95.50
Grand total = Tk. 1,736.33
Rate per cft. = Tk. 17.36
Rate per cum. = Tk. 613.07

Say, Tk. 613 .00 Per cum.

Item No.- 24.10


Labour for compacted sub-base base course
Consider 10cum (353.15 cft.) of work
1. Bricks 2594 Nos. @ Tk. 7,500.00 per %0 = Tk. 19,455.00
2 Ordinary labour for breaking bricks 14 Nos. @ Tk. 245.00 each = Tk. 3,430.00
3 Labour for spreading
(a) Mason 1 Nos. @ Tk. 389.00 each = Tk. 389.00
(b) Labour 12 Nos. @ Tk. 245.00 each = Tk. 2,940.00
4 Labour for watering 1 3/4 No. @ Tk. 245.00 each = Tk. 428.75
5 Cost of sand (F.M = 0.8) 117.71 cft. @ Tk. 900.00 Per % cft. = Tk. 1,059.39
6 Hire charge of 8 ton to 12 ton road
roller (two steel drum roller) 0.06 day @ Tk. 5,063.00 Per day = Tk. 303.78
7 Fuel & lubricants, spares,
Analysis of PWD SoR 2014 for Civil Works 382

maintenance, driver etc. 0.06 day @ Tk. 1,268.00 Per day = Tk. 76.08
8 Local carries Sundries T & P etc. L. S. Tk. 50.00
Total = Tk. 28,132.00
Profit 10.00% = Tk. 2,813.20
Overhead 3.50% = Tk. 984.62
= Tk. 31,929.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,858.35
Grand total = Tk. 33,788.17
Rate per cft. = Tk. 95.68
Rate per cum. = Tk. 3,378.94
Say, Tk. 3,379 .00 Per cum.
Item No.- 24.11
2" compacted bitumenous carpeting (with stone chips / boulder)
Considering 100 sft. of work
(a) Cost of materials
(i) Boulder for stone chips 21 cft. @ Tk. 12,500.00 Per % cft. = Tk. 2,625.00
(ii) Bitumen 86 lbs. @ Tk. 29.63 Per Ib. = Tk. 2,548.18
(iii) Sand (F.M. 1.2) 4 cft. @ Tk. 1,700.00 Per % cft. = Tk. 68.00
(iv) Fire wood 2.5 Mnds. @ Tk. 194.00 Per mnds. = Tk. 485.00
Total (a) = Tk. 5,726.18
(b) Labour charges:
(i) For breaking stone chips 21 cft. @ Tk. 1,531.07 Per % cft. = Tk. 321.52
(ii) For heating & mixing stone
chips and bitumen 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(iii) For brooming & cleaning the base
Ordinary labour 1/2 No. @ Tk. 245.00 each = Tk. 122.50
(iv) Labour for spreading 1/2 No. @ Tk. 245.00 each = Tk. 122.50
(v) Skilled labour for levelling
& hand packing 1/2 No. @ Tk. 303.00 each = Tk. 151.50
(vi) Labour for sand blinding 1/4 No. @ Tk. 245.00 each = Tk. 61.25
(vii) Head mason 1/16 No. @ Tk. 493.00 each = Tk. 30.81
(viii) Mason 1/4 No. @ Tk. 389.00 each = Tk. 97.25
(ix) Sundries and T & P L.S. = Tk. 81.67
Total (c) = Tk. 1,479.00
(c) Roller charges:
(i) Hire charge of 8 ton to 12 ton
roller (two steel drum roller) 0.14 day @ Tk. 5,063.00 Per day = Tk. 708.82
(ii) Fuel & lubricants, spares,
maintenance, driver etc. 0.14 day @ Tk. 1,268.00 Per day = Tk. 177.52
Total (c) = Tk. 886.34
Total (a+b+c) = Tk. 8,091.52
Profit 10.00% = Tk. 809.15
Overhead 3.50% = Tk. 283.20
= Tk. 9,183.87
Add VAT with adjustment factor 1.0582 5.50% = Tk. 534.51
Grand total = Tk. 9,718.38
Rate per sft. = Tk. 97.18
Rate per sqm. = Tk. 1,046.05
Say, Tk. 1,046 .00 Per sqm.
Item No.- 24.12
1.5" compacted bitumenous carpeting (with stone chips/boulder)
Considering 100 sft. of work
(a) Cost of materials
(i) Boulder for stone chips 15.75 cft. @ Tk. 12,500.00 Per % cft. = Tk. 1,968.75
(ii) Bitumen 65 lbs. @ Tk. 29.63 Per Ib. = Tk. 1,925.95
(iii) Sand (F.M. 1.2) 4 cft. @ Tk. 1,700.00 Per % cft. = Tk. 68.00
(iv) Fire wood 2 Mnds. @ Tk. 194.00 Per mnd. = Tk. 388.00
Analysis of PWD SoR 2014 for Civil Works 383

Total (a) = Tk. 4,350.70


(b) Labour charges:
(i) For breaking stone chips 15.75 cft. @ Tk. 1,531.07 Per % cft. = Tk. 241.14
(ii) For heating & mixing stone
chips and bitumen 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(iii) For brooming & cleaning the base
Ordinary labour 1/2 Nos. @ Tk. 245.00 each = Tk. 122.50
(iv) Labour for spreading 1/2 No. @ Tk. 245.00 each = Tk. 122.50
(v) Skilled labour for levelling
& hand packing 1/2 No. @ Tk. 303.00 each = Tk. 151.50
(vi) Labour for sand blinding 1/4 No. @ Tk. 245.00 each = Tk. 61.25
(vii) Head mason 1/16 No. @ Tk. 493.00 each = Tk. 30.81
(viii) Mason 1/4 No. @ Tk. 389.00 each = Tk. 97.25
(ix) Sundries and T & P L.S. = Tk. 81.67
Total (b) = Tk. 1,398.62
(c) Roller charges
(i) Hire charge of 8 ton to 12 ton
roller (two steel drum roller) 0.14 day @ Tk. 5,063.00 Per day = Tk. 708.82
(ii) Fuel & lubricants, spares,
maintenance, driver etc. 0.14 day @ Tk. 1,268.00 Per day = Tk. 177.52
Total (c) = Tk. 886.34
Total (a+c+c) = Tk. 6,635.66
Profit 10.00% = Tk. 663.57
Overhead 3.50% = Tk. 232.25
= Tk. 7,531.48
Add VAT with adjustment factor 1.0582 5.50% = Tk. 438.34
Grand total = Tk. 7,969.82
Rate per sft. = Tk. 79.70
Rate per sqm. = Tk. 857.89

Say, Tk. 858 .00 Per sqm.

Item No.- 24.13


1" compacted bitumenous carpeting (with stone chips / boulder)
Considering 100 sft. of work
(a) Cost of materials
(i) Boulder for stone chips 10.5 cft. @ Tk. 12,500.00 Per % cft. = Tk. 1,312.50
(ii) Bitumen 45 lbs. @ Tk. 29.63 Per Ib. = Tk. 1,333.35
(iii) Sand (F.M. 1.2) 4 cft. @ Tk. 1,700.00 Per % cft. = Tk. 68.00
(iv) Fire wood 1.5 Mnds @ Tk. 194.00 Per mnd. = Tk. 291.00
Total (A) = Tk. 3,004.85
(b) Labour charges:
(i) For breaking stone chips 10.5 cft. @ Tk. 1,531.07 Per % cft. = Tk. 160.76
(ii) For heating & mixing
stone chips and bitumen 1 No. @ Tk. 245.00 each = Tk. 245.00
(iii) For brooming & cleaning the base
Ordinary labour 1/4 No. @ Tk. 245.00 each = Tk. 61.25
(iv) For spreading 1/4 No. @ Tk. 245.00 each = Tk. 61.25
(v) Skilled labour for levelling
& hand packing 1/2 No. @ Tk. 303.00 each = Tk. 151.50
(vi) Labour for sand blinding 1/4 No. @ Tk. 245.00 each = Tk. 61.25
(vii) Head mason 1/16 No. @ Tk. 493.00 each = Tk. 30.81
(viii) Mason 1/4 No. @ Tk. 389.00 each = Tk. 97.25
(ix) Sundries and T & P L.S. = Tk. 81.67
Total (B) = Tk. 950.74
(c) Roller charges
(i) Hire charge of 8 ton to 12 ton
Analysis of PWD SoR 2014 for Civil Works 384

roller (two steel drum roller) 0.14 day @ Tk. 5,063.00 Per day = Tk. 708.82
(ii) Fuel & lubricants, spares,
maintenance, driver etc. 0.14 day @ Tk. 1,268.00 Per day = Tk. 177.52
Total (C) = Tk. 886.34
Total (A+B+C) = Tk. 4,841.93
Profit 10.00% = Tk. 484.19
Overhead 3.50% = Tk. 169.47
= Tk. 5,495.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 319.85
Grand total = Tk. 5,815.44
Rate per sft. = Tk. 58.15
Rate per sqm. = Tk. 625.93

Say, Tk. 626 .00 Per sqm.

Item No.- 24.14


2" compacted bitumenous carpeting (with shingles)
Considering 100 sft. of work
1. Cost of bituminous work except cost of stone
chips & its breaking cost Same as item No. 190(a) = Tk. 5,145.00
2. Cost of shingles 21 cft. @ Tk. 8,100.00 Per % cft. = Tk. 1,701.00
Total = Tk. 6,846.00
Profit 10.00% = Tk. 684.60
Overhead 3.50% = Tk. 239.61
= Tk. 7,770.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 452.23
Grand total = Tk. 8,222.44
Rate per sft. = Tk. 82.22
Rate per sqm. = Tk. 885.02

Say, Tk. 885 .00 Per sqm.


Item No.- 24.15
1.5" compacted bitumenous carpeting (with shingles)
Considering 100 sft. of work
1. Cost of bituminous work except cost
of stone chips & its breaking cost Same as item No. 190(b) = Tk. 4,425.77
2. Cost of shingles 15.75 cft. @ Tk. 8,100.00 Per % cft. = Tk. 1,275.75
Total = Tk. 5,701.52
Profit 10.00% = Tk. 570.15
Overhead 3.50% = Tk. 199.55
= Tk. 6,471.22
Add VAT with adjustment factor 1.0582 5.50% = Tk. 376.63
Grand total = Tk. 6,847.85
Rate per sft. = Tk. 68.48
Rate per sqm. = Tk. 737.12

Say, Tk. 737 .00 Per sqm.


ITEM NO.- 24.16
1" compacted bitumenous carpeting (with shingles)
Considering 100 sft. of work
1. Cost of bituminous work except cost of
stone chips & its breaking cost Same as item No. 190(c) = Tk. 3,368.67
2. Cost of shingles 10.5 cft. @ Tk. 4,400.00 Per % cft. = Tk. 462.00
Total = Tk. 3,830.67
Profit 10.00% = Tk. 383.07
Overhead 3.50% = Tk. 134.07
= Tk. 4,347.81
Analysis of PWD SoR 2014 for Civil Works 385

Add VAT with adjustment factor 1.0582 5.50% = Tk. 253.05


Grand total = Tk. 4,600.86
Rate per sft. = Tk. 46.01
Rate per sqm. = Tk. 495.25

Say, Tk. 495 .00 Per sqm.

Item No. -24.17


Providing tack coat @ 15 Ibs per 100 sft.
Considering 100 sft. of work
(a) Cost of materials
(i) Bitumen 15 lbs. @ Tk. 29.63 Per Ib. = Tk. 444.45
(ii) Fire wood 1/4 Mds. @ Tk. 194.00 Per mnd. = Tk. 48.50
Total (a) = Tk. 492.95
(b) Labour charges:
(i) Skilled labour for heating
& laying bitumen 1/2 No. @ Tk. 303.00 each = Tk. 151.50
(ii) Sundries and T & P L.S. = Tk. 30.63
Total (c) Tk. 182.13
Total (a+b) = Tk. 675.08
Profit 10.00% = Tk. 67.51
Overhead 3.50% = Tk. 23.63
= Tk. 766.22
Add VAT with adjustment factor 1.0582 5.50% = Tk. 44.59
Grand total = Tk. 810.81
Rate per sft. = Tk. 8.11
Rate per sqm. = Tk. 87.30

Say, Tk. 87 .00 Per sqm.

Item No.- 24.18


Providing seal coat with 4 cft of sylhet sand mixed with 7.32 kg of bitumin.
Considering 100 sft. of work
(a) Cost of materials
(i) Bitumen 15 lbs. @ Tk. 29.63 Per Ib. = Tk. 444.45
(ii) Sylhet sand (F.M. 2.2) 4 cft. @ Tk. 3,000.00 Per % cft. = Tk. 120.00
(iii) Sand (F.M. 0.8) 3 cft. @ Tk. 900.00 Per % cft. = Tk. 27.00
(vi) Fire wood 1/2 Mnd. @ Tk. 194.00 Per mnd. = Tk. 97.00
Total (A) = Tk. 688.45
(b) Labour charges:
(i) Skilled labour for heating
& laying bitumen 1/2 No. @ Tk. 303.00 each = Tk. 151.50
(ii) Labour for spreading sand 1/5 No. @ Tk. 245.00 each = Tk. 49.00
(iii) Head mason 1/16 No. @ Tk. 493.00 each = Tk. 30.81
(iv) Mason 1/5 No. @ Tk. 389.00 each = Tk. 77.80
(v) Sundries and T & P L.S. = Tk. 49.00
Total (B) = Tk. 358.11
(c) Roller charges
(i) Hire charge of 8 ton to 12 ton
roller (two steel drum roller) 0.0625 day @ Tk. 5,063.00 Per day = Tk. 316.44
(ii) Fuel & lubricants, spares,
maintenance, driver etc. 0.0625 day @ Tk. 1,268.00 Per day = Tk. 79.25
Total (C) = Tk. 395.69
Total (a+b+c) = Tk. 1,442.25
Profit 10.00% = Tk. 144.23
Overhead 3.50% = Tk. 50.48
= Tk. 1,636.96
Analysis of PWD SoR 2014 for Civil Works 386

Add VAT with adjustment factor 1.0582 5.50% = Tk. 95.27


Grand total = Tk. 1,732.23
Rate per sft. = Tk. 17.32
Rate per sqm. = Tk. 186.43

Say, Tk. 186 .00 Per sqm.

Item No.- 24.19


Premixed bitumenous seal coat with 4 cft. of pea gravels per % sft.
Considering 100 sft. of work
(a) Cost of materials
(i) Bitumen 20 lbs. @ Tk. 29.63 Per Ib. = Tk. 592.60
(ii) Sand (F.M. 1.2) 3 cft. @ Tk. 1,700.00 Per % cft. = Tk. 51.00
(iii) Pea gravels 4 cft. @ Tk. 5,500.00 Per % cft. = Tk. 220.00
(iv) Fire wood 3/4 mnd. @ Tk. 194.00 Per mnd. = Tk. 145.50
Total (a) = Tk. 1,009.10
(b) Labour charges:
(i) Skilled labour for heating & laying mixture
of bitumen and pea-gravels 1/2 No. @ Tk. 303.00 each = Tk. 151.50
(ii) Labour for spreading sand 1/4 No. @ Tk. 245.00 each = Tk. 61.25
(iii) Mason for levelling and
hand packing 1/4 No. @ Tk. 389.00 each = Tk. 97.25
(iV) Labour for sand blinding 0.1 No. @ Tk. 245.00 each = Tk. 24.50
(v) Head mason 1/16 No. @ Tk. 493.00 each = Tk. 30.81
(vi) Sundries and T & P L.S. = Tk. 49.00
Total (b) Tk. 414.31
(c) Roller charges
(i) Hire charge of 8 ton to
12 ton roller 1/16 day @ Tk. 5,063.00 Per day = Tk. 316.44
(ii) Fuel & lubricants, spares,
maintenance, driver etc. 1/16 day @ Tk. 1,268.00 Per day = Tk. 79.25
Total (c) = Tk. 395.69
Total (a+b+c) = Tk. 1,819.10
Profit 10.00% = Tk. 181.91
Overhead 3.50% = Tk. 63.67
= Tk. 2,064.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 120.17
Grand total = Tk. 2,184.85
Rate per sft. = Tk. 21.85
Rate per sqm. = Tk. 235.19

Say, Tk. 235 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 387

Item No.- 24.20


Providing bitumenous painting with 4.54 kg of bitumin per 10 sqm. Road surface.
Considering 100 sft. of work
(a) Cost of materials
(i) Bitumen 10 lbs. @ Tk. 29.63 Per Ib. = Tk. 296.30
(ii) Sand (F.M. 1.2) 3 cft. @ Tk. 1,700.00 Per % cft. = Tk. 51.00
(iii) Fire wood 1/2 mnd. @ Tk. 194.00 Per mnd. = Tk. 97.00
Total (a) = Tk. 444.30
(b) Labour charges:
(i) Skilled labour for heating & laying mixture
of bitumen and pea-gravels 1/2 No. @ Tk. 303.00 each = Tk. 151.50
(ii) Labour for spreading sand 1/5 No. @ Tk. 245.00 each = Tk. 49.00
(iii) Head mason 1/16 No. @ Tk. 493.00 each = Tk. 30.81
(iv) Mason 1/5 No. @ Tk. 389.00 each = Tk. 77.80
(v) Sundries and T & P L.S. = Tk. 49.00
Total (b) Tk. 358.11
Total (a+b) = Tk. 802.41
Profit 10.00% = Tk. 80.24
Overhead 3.50% = Tk. 28.08
= Tk. 910.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 53.01
Grand total = Tk. 963.74
Rate per sft. = Tk. 9.64
Rate per sqm. = Tk. 103.76

Say, Tk. 104 .00 Per sqm.

Item No.- 24.21


Providing road marking in two course
Considering 100 sft. of work
1. Painter 1.00 No. @ Tk. 423.00 each = Tk. 423.00
2. Ordinary labour 1.00 No. @ Tk. 245.00 each = Tk. 245.00
3. Helper to painter 1.00 No. @ Tk. 304.00 each = Tk. 304.00
4. Synthetic anamel Paint 1.50 liter @ Tk. 310.00 Per liter = Tk. 465.00
5. Sealer 1.00 liter @ Tk. 149.00 Per liter = Tk. 149.00
6. Thinner 1.00 liter @ Tk. 140.00 Per liter = Tk. 140.00
7 T & P local carriege Sundries L.S. Tk. 100.00
Tk. 1,726.00
Profit 10.00% = Tk. 172.60
Overhead 3.50% = Tk. 60.41
= Tk. 1,959.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 114.02
Grand total = Tk. 2,073.03
Rate per sft. = Tk. 20.73
Rate per sqm. = Tk. 223.14

Say, Tk. 223 .00 Per sqm.

Item No.- 24.22


Expansion joint in RCC road
Considering 10 rft. long expansion joint
(a) Cost of materials
(i) 1/2" dia M.S. rod: @ 0.67 lbs per rft.
4 x 2'-0"= 8 rft.
= 5.63 lbs. @ Tk. 27.89 Per Ib. = Tk. 157.02
(ii) 3/4" dia PVC pipe
4 x 1'-0"= 4 rft. @ Tk. 4.97 Per rft. Tk. 19.88
Analysis of PWD SoR 2014 for Civil Works 388

(iii) Greese L.S. = Tk. 24.50


(iv) Cost of admixture of hot bitumen and sylhet sand (1:2),
finishing the top with bitumen, spreading
coarse sand over joints 10 rft. @ Tk. 36.75 Per rft. = Tk. 367.50
(b) Labour charges:
(i) Rod mistry 1/5 No. @ Tk. 421.00 each = Tk. 84.20
(ii) Helper to rod mistry 1/2 No. @ Tk. 304.00 each = Tk. 152.00
Total (A+B) = Tk. 805.10
Profit 10.00% = Tk. 80.51
Overhead 3.50% = Tk. 28.18
= Tk. 913.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 53.18
Grand total = Tk. 966.97
Rate per rft. = Tk. 96.70
Rate per rm. = Tk. 317.27

Say, Tk. 317 .00 Per rm.


Analysis of PWD SoR 2014 for Civil Works 389

DIVISION 25 : ARBORICULTURE WORK


Item No.- 25.1
Labour charge for scraping lawn surface upto 1.5" thick
Considering 1000 sft. of work
(a) Ordinary labour for scraping 1.75 Nos. @ Tk. 245.00 each = Tk. 428.75
(b) Ordinary labour for picking-up all sorts of
bricks, bats, rubbish etc. 1/3 No. @ Tk. 245.00 each = Tk. 81.67
(c) Tools & plant, incidental, sundries etc. L.S. = Tk. 39.20
Total = Tk. 549.62
Profit 10.00% = Tk. 54.96
Overhead 3.50% = Tk. 19.24
= Tk. 623.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 36.31
Grand total = Tk. 660.13
Rate per sft. = Tk. 0.66
Rate per sqm. = Tk. 7.10

Say, Tk. 7.1 0 Per sqm

Item No.- 25.2


Preparation of ground to make the scraped lawn fit for plantation
Considering 1000 sft. of work
(a) Labour charge for spading
up to 6" depth 4.5 Nos. @ Tk. 245.00 each = Tk. 1,102.50
(b) Tools & plant, incidental, sundries etc. L.S. = Tk. 61.25
Total = Tk. 1,163.75
Profit 10.00% = Tk. 116.38
Overhead 3.50% = Tk. 40.73
= Tk. 1,320.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 76.88
Grand total = Tk. 1,397.74
Rate per sft. = Tk. 1.40
Rate per sqm. = Tk. 15.07

Say, Tk. 15 .00 Per sqm.

Item No.- 25.3


Levelling and dressing the lawn areas to proper slope and grade.
Considering 1000 sft. of work
(a) Labour for spading up to 6" depth in/c
cutting earth, levelling-dressing etc. 1.25 Nos. @ Tk. 245.00 each = Tk. 306.25
(b) Tools & Plant, sundries, incidental etc. L.S. = Tk. 61.25
Total = Tk. 367.50
Profit 10.00% = Tk. 36.75
Overhead 3.50% = Tk. 12.86
= Tk. 417.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 24.28
Grand total = Tk. 441.39
Rate per sft. = Tk. 0.44
Rate per sqm. = Tk. 4.74

Say, Tk. 4.7 0 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 390

Item No.- 25.4


Supplying approved best quality ALLUVIAL LOAMY SILTY soil
Considering 180 cft. of soil
(a) Cost of silty soil in/c carrying by truck or any other means
in/c loading and unloading. 180 cft. @ Tk. 1,200.00 Per % cft. = Tk. 2,160.00
(b) Local carriage, storage and sundries L.S. = Tk. 245.00
Total = Tk. 2,405.00
Profit 10.00% = Tk. 240.50
Overhead 3.50% = Tk. 84.18
= Tk. 2,729.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 158.87
Grand total = Tk. 2,888.55
Rate per cft. = Tk. 16.05
Rate per cum. = Tk. 566.81

Say, Tk. 567 .00 Per cum.

Item No.- 25.5


Supplying approved best quality WELL DECOMPOSED COWDUNG.
Considering 180 cft. cowdung
(a) Cost of cowdung (1 trip) 180 cft. @ Tk. 2,000.00 Per % cft. = Tk. 3,600.00
(b) Carrying by truck or any other means
in/c loading & unloading etc 1 Trip @ Tk. 1,300.00 Per trip = Tk. 1,300.00
(c) Stacking at site, T&P, incidental, sundries etc. L.S. = Tk. 122.50
Total = Tk. 5,022.50
Profit 10.00% = Tk. 502.25
Overhead 3.50% = Tk. 175.79
= Tk. 5,700.54
Add VAT with adjustment factor 1.0582 5.50% = Tk. 331.78
Grand total = Tk. 6,032.32
Rate per cft. = Tk. 33.51
Rate per cum. = Tk. 1,183.41

Say, Tk. 1,183 .00 Per cum

Item No.- 25.6


Labour charge for spreading the alluvial loamy silty soil from the stack at site on the lawn surface.
Considering 100 cft. soil
(a) Labour charge for spading the lawn
surface as per requirement. 1 No. @ Tk. 245.00 each = Tk. 245.00
(b) Labour for levelling & dressing etc. complete as per
direction of officer-in-charge. 1/16 No. @ Tk. 245.00 each = Tk. 15.31
(c) Tools & plant, incidental, sundries etc. L.S. = Tk. 12.25
Total = Tk. 272.56
Profit 10.00% = Tk. 27.26
Overhead 3.50% = Tk. 9.54
= Tk. 309.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.01
Grand total = Tk. 327.37
Rate per cft. = Tk. 3.27
Rate per cum. = Tk. 115.48

Say, Tk. 115 .00 Per cum


Analysis of PWD SoR 2014 for Civil Works 391

Item No.- 25.7


Supplying and dibbling lawn grass of approved quality @ 1.5" - 2" apart.
Considering 100 sft. of work
(a) Cost of lawn grass 100 Sft. @ Tk. 35.00 Per % sft. = Tk. 35.00
(b) Ordinary labour for grass cutting to
proper size in/c washing etc. 0.1 No. @ Tk. 245.00 each = Tk. 24.50
(c) Ordinary labour for planting 0.75 No. @ Tk. 245.00 each = Tk. 183.75
(d) Ordinary labour for maintenance
upto 2 months 0.125 No. @ Tk. 245.00 each = Tk. 30.63
(e) Ordinary labour for
weeding weeds 0.1 No. @ Tk. 245.00 each = Tk. 24.50
(f) Urea fertilizer 1 Kg @ Tk. 20.00 Per kg. = Tk. 20.00
(g) Application of fertilizer L.S. = Tk. 2.45
Total = Tk. 320.83
Profit 10.00% = Tk. 32.08
Overhead 3.50% = Tk. 11.23
= Tk. 364.14
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.19
Grand total = Tk. 385.33
Rate per sft. = Tk. 3.85
Rate per sqm. = Tk. 41.44

Say, Tk. 41 .00 Per sqm.

Item No.- 25.8


Labour charge for mixing cowdung, alluvial loamy silty soil and excavated earth.
Considering 100 cft. of works
(a) Ordinary labour for mixing cowdung,
silty soil & excavated earth 1 No. @ Tk. 245.00 each = Tk. 245.00
(b) Tools & plant, incidental, sundries etc. L.S. = Tk. 8.17
Total = Tk. 253.17
Profit 10.00% = Tk. 25.32
Overhead 3.50% = Tk. 8.86
= Tk. 287.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 16.72
Grand total = Tk. 304.07
Rate per cft. = Tk. 3.04
Rate per cum. = Tk. 107.36

Say, Tk. 107 .00 Per cum.

Item No.- 25.9


Providing fitting and fixing bamboo jafry fencing by 3/4" size MULI BAMBOOO
split having 3" x 3" mesh horizontally and diagonally.
Considering 16'-0" x 3'-6" = 56 sft. of 3" x 3" size
16'-0" long muli bamboo
Available, 6 x 16'-0" = 96 rft. of split
Horizontally: 4 x 2 x 16'-0"= 128 rft.
Vertically: 16 x 2 x 3'-6"= 112 rft.
Diagonally: 64 x 2 x 4'-6"= 576 rft.
= 816 rft.
= 8.5 Nos. bamboo
(a) Cost of muli bamboo 8.5 Nos. @ Tk. 75.00 each = Tk. 637.50
(b) 18-22 BWG G.I. wire 1 Kg. @ Tk. 110.00 Per kg. = Tk. 110.00
(b) Barrack bamboo post
2.67 x 5'-0"= 13.35 Nos. @ Tk. 10.00 Per rft. = Tk. 133.50
(d) Ghorami 1.75 Nos. @ Tk. 397.00 each = Tk. 694.75
Analysis of PWD SoR 2014 for Civil Works 392

Total = Tk. 1,575.75


Profit 10.00% = Tk. 157.58
Overhead 3.50% = Tk. 55.15
= Tk. 1,788.48
Add VAT with adjustment factor 1.0582 5.50% = Tk. 104.09
Grand total = Tk. 1,892.57
Rate per sft. = Tk. 33.80
Rate per sqm. = Tk. 363.82

Say, Tk. 364 .00 Per sqm.

Item No.- 25.10


Providing fitting and fixing of 4'-0" long (height) and 20" dia Muli bamboo tree-guard
with 3/4" size best quality muli bamboo split having 3'' x 3'' square holes.
Considering 1 No. tree-guard
Bamboo split:
3.142 x 4 x 1'-8"= 21 rft.
Diagonally: 30 x 4'-6"= 135 rft.
Horizontally:
1 x 2 x 3.44 x 1'-8"= 10.48 rft.
= 166.48 rft.
No. of bamboo
(@ 96'-0" split per bamboo)= 1.73 Nos.
(a) Muli bamboo 1.73 Nos. @ Tk. 75.00 each = Tk. 129.75
(b) G.I. wire 0.1 Kg. @ Tk. 110.00 Per Kg. = Tk. 11.00
(c) Borrak bamboo post:
3 x 6'-0'' = 18 rft. @ Tk. 10.00 Per rft. = Tk. 180.00
(d) Labour (Gharami) 0.2 No. @ Tk. 397.00 each = Tk. 79.40
Total = Tk. 400.15
Profit 10.00% = Tk. 40.02
Overhead 3.50% = Tk. 14.01
= Tk. 454.18
Add VAT with adjustment factor 1.0582 5.50% = Tk. 26.43
Grand total = Tk. 480.61
Rate per No. = Tk. 480.61

Say, Tk. 481 .00 each

Item No.- 25.11


Earth-work in excavation 1'-6" x 1'-6" x 1'-6" size pits for plantation of plant
in/c cost of cowdung manure, loamy silty soil etc.
Considering 1'-6" x 1'-6" x 1'-6" size 10 Nos. pit = 33.8 cft. excavation
(a) Ordinary labour for excavation 0.5 No. @ Tk. 245.00 each = Tk. 122.50
(b) Cowdung manure
(@ 1cft. per pit) 10 cft. @ Tk. 31.39 Per cft. = Tk. 313.90
(c) Loamy silty soil
(@ 1.2 cft. Per pit) 10 cft. @ Tk. 13.36 Per cft. = Tk. 133.60
(d) Ordinary labour for mixing
cowdung, soil, earth etc. 0.125 No. @ Tk. 245.00 each = Tk. 30.63
(e) Borrak bamboo 30 rft. @ Tk. 10.00 Per rft. = Tk. 300.00
(f) Incidental, sundries L.S. = Tk. 16.33
Total = Tk. 916.96
Profit 10.00% = Tk. 91.70
Overhead 3.50% = Tk. 32.09
= Tk. 1,040.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 60.57
Analysis of PWD SoR 2014 for Civil Works 393

Grand total = Tk. 1,101.32


Rate per pit. = Tk. 110.13

Say, Tk. 110 .00 each

Item No.- 25.12


Preparation of FLOWER BEDS: Earth-work in excavation of Pits in 0.61 m / 2'-0"
depth for plantation of plants.
Considering 1 x 50'-0" x4'-0"= 200 sft. bed: 400 cft. excavation
(a) Ordinary labour for excavation 5.5 Nos. @ Tk. 245.00 each = Tk. 1,347.50
(b) Cost of silty soil (20% of soil) 80 cft. @ Tk. 13.36 Per cft. = Tk. 1,068.80
(c) Cost of cowdung (1/6 of soil) 66.67 cft. @ Tk. 31.39 Per cft. = Tk. 2,092.77
(d) Cost of mixing soil, cowdung
& cutted earth. 546.67 cft. @ Tk. 1.95 Per cft. = Tk. 1,066.01
(e) Tools & plant, incidentl, sundries etc. L.S. = Tk. 49.00
Total = Tk. 5,624.08
Profit 10.00% = Tk. 562.41
Overhead 3.50% = Tk. 196.84
= Tk. 6,383.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 371.52
Grand total = Tk. 6,754.85
Rate per sft. = Tk. 33.77
Rate per sqm. = Tk. 363.50

Say, Tk. 364 .00 Per sqm.

Item No.- 25.13


Preparation of Hedge beds in 0.3 m / 1'-0" depth for plantation of plants.
Considering 1 x 50'-0" x 1'-6" = 75 sft. Hedge: 75 cft. excavation
(a) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
(b) Loamy silty soil: 75 x 20%= 15 cft. @ Tk. 13.36 Per cft. = Tk. 200.40
(c) Cowdung manure: 75 x 1/6 = 12.5 cft. @ Tk. 31.39 Per cft. = Tk. 392.38
(d) Mixing cowdung,
silty soil & earth: 102.5 cft. @ Tk. 1.95 Per cft. = Tk. 199.88
(e) T ools & plant, incidental, sundries etc. L.S. = Tk. 24.50
Total = Tk. 1,062.16
Profit 10.00% = Tk. 106.22
Overhead 3.50% = Tk. 37.18
= Tk. 1,205.56
Add VAT with adjustment factor 1.0582 5.50% = Tk. 70.16
Grand total = Tk. 1,275.72
Rate per sft. = Tk. 17.01
Rate per sqm. = Tk. 183.10

Say, Tk. 183 .00 Per sqm.

Item No.- 25.14


Carrying and placing/stacking of all sorts of rubbish/debris, bricks, brick-bats, gravels, chips etc.
Considering 100 cft. of work
(a) Ordinary labour for carrying by head-load to a safe distance
not exceeding 200'-0" 1 Nos. @ Tk. 245.00 each = Tk. 245.00
(b) Tools and plant, sundries etc. L.S. = Tk. 16.33
Total = Tk. 261.33
Profit 10.00% = Tk. 26.13
Overhead 3.50% = Tk. 9.15
= Tk. 296.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.26
Analysis of PWD SoR 2014 for Civil Works 394

Grand total = Tk. 313.87


Rate per cft. = Tk. 3.14
Rate per cum. = Tk. 110.89

Say, Tk. 111 .00 Per cum.

Item No.- 25.15


Supplying Borrak bamboo: 4" dia & 40'-0" long.
Considering 1 No. bamboo
(a) Cost of borrak bamboo 1 No. @ Tk. 300.00 each = Tk. 300.00
(b) Carrying in/c stacking L.S. = Tk. 14.70
Total = Tk. 314.70
Profit 10.00% = Tk. 31.47
Overhead 3.50% = Tk. 11.01
= Tk. 357.18
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.79
Grand total = Tk. 377.97
Rate per No. = Tk. 377.97

Say, Tk. 378 .00 each

Item No.- 25.16


Supplying Borrak bamboo: 2" - 2.5" dia & 25'-0" long.
Considering 1 No. bamboo.
(a) Cost of borrak bamboo 1 No. @ Tk. 130.00 each = Tk. 130.00
(b) Carrying in/c stacking L.S. = Tk. 12.25
Total = Tk. 142.25
Profit 10.00% = Tk. 14.23
Overhead 3.50% = Tk. 4.98
= Tk. 161.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 9.40
Grand total = Tk. 170.86
Rate per No. = Tk. 170.86

Say, Tk. 171 .00 each

DIVISION 26 : SANITARY & WATER SUPPLY WORKS


Item No.- 26.1
Supplying, fitting & fixing Bangladeshi standard quality commode of following type "P" or "S" trap
Analysis of PWD SoR 2014 for Civil Works 395

in/c seat cover: or equivalent


26.1.1.1 White commode (Bangladeshi), size (mm) 465 x 340 x 415. wt: 14 kg.
Considering 1 No. of fixture
1. White commode: 1 No. @ Tk. 1,330.00 each = Tk. 1,330.00
2. Accessories:
(a) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,573.54
Profit 10.00% = Tk. 257.35
Overhead 3.50% = Tk. 90.07
= Tk. 2,920.96
Add VAT with adjustment factor 1.0582 5.50% = Tk. 170.00
Grand total = Tk. 3,090.96
Rate per No. = Tk. 3,090.96

Say, Tk. 3,091 .00 each

26.1.1.2 Coloured commode (Bangladeshi), size(mm) 465 x 340 x 415. wt.: 14 kg. or equivalent
Considering 1 No. of fixture
1. Coloured commode 1 No. @ Tk. 1,400.00 each = Tk. 1,400.00
2. Accessories:
(a) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,643.54
Profit 10.00% = Tk. 264.35
Overhead 3.50% = Tk. 92.52
= Tk. 3,000.41
Add VAT with adjustment factor 1.0582 5.50% = Tk. 174.63
Grand total = Tk. 3,175.04
Rate per No. = Tk. 3,175.04

Say, Tk. 3,175 .00 each

26.1.1.3 Special coloured commode (Bangladeshi), size(mm) 465 x 340 x 415. wt.: 14 kg.or equivalent
Considering 1 No. of fixture
1. Special coloured commode 1 No. @ Tk. 1,470.00 each = Tk. 1,470.00
2. Accessories:
(a) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
Analysis of PWD SoR 2014 for Civil Works 396

(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with Washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,713.54
Profit 10.00% = Tk. 271.35
Overhead 3.50% = Tk. 94.97
= Tk. 3,079.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 179.25
Grand total = Tk. 3,259.11
Rate per No. = Tk. 3,259.11

Say, Tk. 3,259 .00 each

Item No.- 26.2


Supplying fitting & fixing low-down (Bangladeshi) of following type & size on wall and
connecting with commode or pan: capacity 10 liter
26.2.1.1 White low-down (Bangladeshi), size (mm) 490 x 190 x 350. wt.: 14 kg.or equivalent
Considering 1 No. of fixture
1. White low-down 1 No. @ Tk. 1,240.00 each = Tk. 1,240.00
2. Accessories:
(a) 32 mm dia plastic pipe 1 No. @ Tk. 79.77 each = Tk. 79.77
3. Cost of fitting fixing materials:
(a) Clamp 2 Nos. @ Tk. 45.55 each = Tk. 91.10
(b) 50 mm rowel plug with screws 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(c) 75 mm screw, rowel plug & washer 3 Nos. @ Tk. 12.76 each = Tk. 38.28
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 1,744.89
Profit 10.00% = Tk. 174.49
Overhead 3.50% = Tk. 61.07
= Tk. 1,980.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 115.26
Grand total = Tk. 2,095.71
Rate per No. = Tk. 2,095.71

Say, Tk. 2,096 .00 each

26.2.1.2 Coloured low -down (Bangladeshi), size(mm) 490 x 190 x 350. wt.: 14 kg. or equivalent
Considering 1 No. of fixture
1. Coloured low-down 1 No. @ Tk. 1,550.00 each = Tk. 1,550.00
2. Accessories:
(a) 32 mm dia plastic pipe 1 No. @ Tk. 79.77 each = Tk. 79.77
3. Fitting fixing materials:
(a) Clamp 2 Nos. @ Tk. 45.55 each = Tk. 91.10
(i) 50 mm rowel plug with screws 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(ii) 75 mm screw, rowel plug 3 Nos. @ Tk. 12.76 each = Tk. 38.28
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 2,054.89
Profit 10.00% = Tk. 205.49
Overhead 3.50% = Tk. 71.92
= Tk. 2,332.30
Analysis of PWD SoR 2014 for Civil Works 397

Add VAT with adjustment factor 1.0582 5.50% = Tk. 135.74


Grand total = Tk. 2,468.04
Rate per No. = Tk. 2,468.04

Say, Tk. 2,468 .00 each

26.2.1.3 Special coloured low -down (Bangladeshi), size(mm) 490 x 190 x 350. wt.: 14 kg. or equivalent
Considering 1 No. of fixture
1. Special coloured low-down 1 No. @ Tk. 1,860.00 each = Tk. 1,860.00
2. Accessories:
(a) 32 mm dia plastic pipe 1 No. @ Tk. 79.77 each = Tk. 79.77
3. Fitting fixing materials:
(a) Clamp 2 Nos. @ Tk. 45.55 each = Tk. 91.10
(i) 50 mm rowel plug with screws 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(ii) 75 mm screw, rowel plug 3 Nos. @ Tk. 12.76 each = Tk. 38.28
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 2,364.89
Profit 10.00% = Tk. 236.49
Overhead 3.50% = Tk. 82.77
= Tk. 2,684.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 156.22
Grand total = Tk. 2,840.37
Rate per No. = Tk. 2,840.37

Say, Tk. 2,840 .00 each

Item No.- 26.3


Supplying, fitting & fixing (Bangladeshi) "P" or "S" combicloset
in/c flushing equipment: (BISF item No. 115A/415A or equivalent)
26.3.1.1 White combicloset (Bangladeshi), size (mm) 700 x 410 x 795. wt.: 31.5 kg. or equivalent
Considering 1 No. of fixture
1. White Combicloset 1 No. @ Tk. 3,622.50 each = Tk. 3,622.50
2. Accessories:
(a) Flushing equpment 1 No. @ Tk. 1,012.27 each = Tk. 1,012.27
(b) Seat-cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 6,029.81
Profit 10.00% = Tk. 602.98
Overhead 3.50% = Tk. 211.04
= Tk. 6,843.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 398.32
Grand total = Tk. 7,242.15
Rate per No. = Tk. 7,242.15

Say, Tk. 7,242 .00 each

26.3.1.2 Coloured combicloset (Bangladeshi), size(mm) 700 x 410 x 795. wt.: 31.5 kg. or equivalent
Analysis of PWD SoR 2014 for Civil Works 398

Considering 1 No. of fixture


1. Coloured combicloset: 1 No. @ Tk. 3,622.50 each = Tk. 3,622.50
2. Accessories:
(a) Flushing equipment 1 No. @ Tk. 1,012.27 each = Tk. 1,012.27
(b) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 6,029.81
Profit 10.00% = Tk. 602.98
Overhead 3.50% = Tk. 211.04
= Tk. 6,843.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 398.32
Grand total = Tk. 7,242.15
Rate per No. = Tk. 7,242.15

Say, Tk. 7,242 .00 each

26.3.1.3 Special coloured combicloset (Bangladeshi), size (mm) 700 x 410 x 795. wt.: 31.5 kg. or equivalent
Considering 1 No. of fixture
1. Special coloured combicloset: 1 No. @ Tk. 4,818.50 each = Tk. 4,818.50
2. Accessories:
(a) Flushing equipment 1 No. @ Tk. 1,012.27 each = Tk. 1,012.27
(b) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 7,225.81
Profit 10.00% = Tk. 722.58
Overhead 3.50% = Tk. 252.90
= Tk. 8,201.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 477.32
Grand total = Tk. 8,678.61
Rate per No. = Tk. 8,678.61

Say, Tk. 8,679 .00 each

26.3.2.1 White combicloset, size (mm) 700 x 370 x 795. wt.: 32.5 kg. or equivalent
Considering 1 No. of fixture
1. White Combicloset 1 No. @ Tk. 6,500.00 each = Tk. 6,500.00
2. Accessories:
(a) Flushing equpment 1 No. @ Tk. 1,012.27 each = Tk. 1,012.27
(b) Seat-cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
Analysis of PWD SoR 2014 for Civil Works 399

(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 8,907.31
Profit 10.00% = Tk. 890.73
Overhead 3.50% = Tk. 311.76
= Tk. 10,109.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 588.40
Grand total = Tk. 10,698.20
Rate per No. = Tk. 10,698.20

26.3.3.1 White combicloset, size (mm) 700 x 360 x 785. wt.: 36(+/-)36.5 kg. or equivalent
Considering 1 No. of fixture
1. White Combicloset 1 No. @ Tk. 10,500.00 each = Tk. 10,500.00
2. Accessories:
(a) Flushing equpment 1 No. @ Tk. 1,012.27 each = Tk. 1,012.27
(b) Seat-cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 12,907.31
Profit 10.00% = Tk. 1,290.73
Overhead 3.50% = Tk. 451.76
= Tk. 14,649.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 852.63
Grand total = Tk. 15,502.43
Rate per No. = Tk. 15,502.43

Say, Tk. 15,502 .00 each


Item No.- 26.4
Supplying, fitting & fixing (Bangladeshi) "P" or "S" combicloset in/c flushing equipment: (BISF Item No. 114/414 or equivalent)

26.4.1 White combicloset (Bangladeshi), size (mm) 725x360x840 42.7 kg.or equivalent
Considering 1 No. of fixture
1. White combicloset 1 No. @ Tk. 15,500.00 each = Tk. 15,500.00
2. Accessories:
(a) Flushing equipment 1 No. @ Tk. 883.29 each = Tk. 883.29
(b) Seat-cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Analysis of PWD SoR 2014 for Civil Works 400

Total = Tk. 17,778.33


Profit 10.00% = Tk. 1,777.83
Overhead 3.50% = Tk. 622.24
= Tk. 20,178.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,174.40
Grand total = Tk. 21,352.80
Rate per No. = Tk. 21,352.80

Say, Tk. 21,353 .00 each

26.4.2 Coloured combicloset (Bangladeshi), size (mm) 700 x 410 x 795. wt.: 34.5 kg.or equivalent
Considering 1 No. of fixture
1. Coloured combicloset: 1 No. @ Tk. 20,925.00 each = Tk. 20,925.00
2. Accessories:
(a) a) Flushing equipment 1 No. @ Tk. 883.29 each = Tk. 883.29
(b) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 23,203.33
Profit 10.00% = Tk. 2,320.33
Overhead 3.50% = Tk. 812.12
= Tk. 26,335.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,532.77
Grand total = Tk. 27,868.55
Rate per No. = Tk. 27,868.55

Say, Tk. 27,869 .00 each

26.4.3 Special coloured combicloset (Bangladeshi), size (mm) 700 x 410 x 795. wt.: 34.5 kg.or equivalent
Considering 1 No. of fixture
1. Special coloured combicloset: 1 No. @ Tk. 23,250.00 each = Tk. 23,250.00
2. Accessories:
(a) Flushing equipment 1 No. @ Tk. 883.29 each = Tk. 883.29
(b) Seat cover 1 No. @ Tk. 718.20 each = Tk. 718.20
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
(b) Nuts with washer 4 Nos. @ Tk. 22.21 each = Tk. 88.84
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 25,528.33
Profit 10.00% = Tk. 2,552.83
Overhead 3.50% = Tk. 893.49
= Tk. 28,974.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,686.35
Grand total = Tk. 30,661.00
Rate per No. = Tk. 30,661.00
Analysis of PWD SoR 2014 for Civil Works 401

Say, Tk. 30,661 .00 each

Item No.- 26.5


Supplying, fitting-fixing (Bangladeshi) long pan of following type:
26.5.1.1 White long pan (Bangladeshi), size(mm) 570 x 445 x 290. wt. 12 kg.or equivalent
Considering 1 No. of fixture
1. White long pan: 1 No. @ Tk. 1,147.00 each = Tk. 1,147.00
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,583.50
Profit 10.00% = Tk. 158.35
Overhead 3.50% = Tk. 55.42
= Tk. 1,797.27
Add VAT with adjustment factor 1.0582 5.50% = Tk. 104.60
Grand total = Tk. 1,901.87
Rate per No. = Tk. 1,901.87

Say, Tk. 1,902 .00 each

26.5.1.2 Coloured long pan (Bangladeshi), size (mm) 570 x 445 x 290. wt. 12 kg.or equivalent
Considering 1 No. of fixture
1. Coloured long pan: 1 No. @ Tk. 1,204.50 each = Tk. 1,204.50
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,641.00
Profit 10.00% = Tk. 164.10
Overhead 3.50% = Tk. 57.44
= Tk. 1,862.54
Add VAT with adjustment factor 1.0582 5.50% = Tk. 108.40
Grand total = Tk. 1,970.94
Rate per No. = Tk. 1,970.94
Say, Tk. 1,971 .00 each
26.5.1.3 Special coloured long pan (Bangladeshi), size (mm) 570 x 445 x 290. wt. 12 kg.or equivalent
Considering 1 No. of fixture
1. Special coloured long pan: 1 No. @ Tk. 1,265.00 each = Tk. 1,265.00
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Analysis of PWD SoR 2014 for Civil Works 402

Total = Tk. 1,701.50


Profit 10.00% = Tk. 170.15
Overhead 3.50% = Tk. 59.55
= Tk. 1,931.20
Add VAT with adjustment factor 1.0582 5.50% = Tk. 112.40
Grand total = Tk. 2,043.60
Rate per No. = Tk. 2,043.60

Say, Tk. 2,044 .00 each

26.5.2.1 White long pan (Bangladeshi), size(mm) 540 x 470 x 290. wt. 16 kg.or equivalent
Considering 1 No. of fixture
1. White long pan: 1 No. @ Tk. 1,387.00 each = Tk. 1,387.00
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,823.50
Profit 10.00% = Tk. 182.35
Overhead 3.50% = Tk. 63.82
= Tk. 2,069.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 120.46
Grand total = Tk. 2,190.13
Rate per No. = Tk. 2,190.13

Say, Tk. 2,190 .00 each

26.5.2.2 Coloured long pan (Bangladeshi), size (mm) 540 x 470 x 290. wt. 16 kg..or equivalent
Considering 1 No. of fixture
1. Coloured long pan: 1 No. @ Tk. 1,733.75 each = Tk. 1,733.75
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,170.25
Profit 10.00% = Tk. 217.03
Overhead 3.50% = Tk. 75.96
= Tk. 2,463.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 143.36
Grand total = Tk. 2,606.60
Rate per No. = Tk. 2,606.60

Say, Tk. 2,607 .00 each

26.5.2.3 Special coloured long pan (Bangladeshi), size (mm) 540 x 470 x 290. wt. 16 kg..or equivalent
Considering 1 No. of fixture
1. Special coloured long pan: 1 No. @ Tk. 2,080.50 each = Tk. 2,080.50
2. Fitting fixing materials:
(a) Cement mortar (1:4)
Analysis of PWD SoR 2014 for Civil Works 403

(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,517.00
Profit 10.00% = Tk. 251.70
Overhead 3.50% = Tk. 88.10
= Tk. 2,856.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 166.27
Grand total = Tk. 3,023.07
Rate per No. = Tk. 3,023.07

Say, Tk. 3,023 .00 each

Item No.- 26.6


26.6.1.1 White long pan (Bangladeshi), size 525x295x285 5.7kg.or equivalent
Considering 1 No. of fixture
1. White long pan: 1 No. @ Tk. 484.15 each = Tk. 484.15
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 920.65
Profit 10.00% = Tk. 92.07
Overhead 3.50% = Tk. 32.22
= Tk. 1,044.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 60.82
Grand total = Tk. 1,105.76
Rate per No. = Tk. 1,105.76

Say, Tk. 1,106 .00 each

26.6.2 Coloured long pan (Bangladeshi), size(mm) 560 x 290 x 270. wt. 7.1 kg. omitted
Considering 1 No. of fixture
1. Coloured long pan: 1 No. @ Tk. - each = Tk. -
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 436.50
Profit 10.00% = Tk. 43.65
Overhead 3.50% = Tk. 15.28
= Tk. 495.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 28.83
Grand total = Tk. 524.26
Rate per No. = Tk. 524.26
Analysis of PWD SoR 2014 for Civil Works 404

Say, Tk. 524 .00 each

26.6.3
Special coloured long pan (Bangladeshi), size (mm) 560 x 290 x 270. wt. 7.1 kg.or equivalent
omitted
Considering 1 No. of fixture
1. Special coloured long pan: 1 No. @ Tk. - each = Tk. -
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag. @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
3. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 436.50
Profit 10.00% = Tk. 43.65
Overhead 3.50% = Tk. 15.28
= Tk. 495.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 28.83
Grand total = Tk. 524.26
Rate per No. = Tk. 524.26

Say, Tk. 524 .00 each

Item No.- 26.7


Supplying, fitting and fixing plastic low-down
Break-up for 1 No. fixture
1. Plastic low-down 1.00 No. @ Tk. 1,066.59 Each = Tk. 1,066.59
2. 32 mm plastic pipe 1.00 No. @ Tk. 158.12 Each = Tk. 158.12
3. C.I. Bracket 1.00 Pair @ Tk. 113.45 per pair = Tk. 113.45
4. Screw, rowel plug, washer, putty etc. L.S. = Tk. 50.00
5. PVC connection pipe 1 No. @ Tk. 30.00 each = Tk. 30.00
6. Labour for fitting, fixing in position
(i) Plumber 0.25 Nos. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled Labour 0.50 Nos. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 1,679.66
Profit 10.00% = Tk. 167.97
Overhead 3.50% = Tk. 58.79
= Tk. 1,906.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 110.96
Grand total = Tk. 2,017.38

Say Tk. 2,017 .00 each


Item No.- 26.8
Supplying, fitting-fixing foot-rest (Bangladeshi): white or coloured,
size (mm) 260 x 227 x 25. wt.: 1 kg. or equivalent, 280x140x30,1.5kg
Considering 1 No. of fixture
1. White or coloured foot-rest: 1 No. @ Tk. 80.50 each = Tk. 80.50
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.05 bag. @ Tk. 440.00 Per bag = Tk. 22.00
(ii) Sand (F.M. 1.2) 0.25 cft. @ Tk. 1,700.00 Per % cft. = Tk. 4.25
3. Labour:
(a) Skilled labour 0.125 No. @ Tk. 303.00 each = Tk. 37.88
Total = Tk. 144.63
Profit 10.00% = Tk. 14.46
Overhead 3.50% = Tk. 5.06
Analysis of PWD SoR 2014 for Civil Works 405

= Tk. 164.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 9.55
Grand total = Tk. 173.70
Rate per No. = Tk. 173.70

Say, Tk. 174 .00 each

Item No.- 26.9


Supplying, fitting & fixing (Bangladeshi) wall-hung wash-basin of following type:
26.9.1.1 White w-basin (Bangladeshi), approx. size (mm) approx. 600x465x225, 14kg 580 x 445 x 235. wt.: 14 kg.or equivalent
Considering 1 No. of fixture
1. White wash-basin 1 No. @ Tk. 1,147.00 each = Tk. 1,147.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(b) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(c) CP chain with rubber plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(b) CI brakets 1 Pair @ Tk. 113.45 Per pair = Tk. 113.45
4. Labour:
(a) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(c) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 1,974.60
Profit 10.00% = Tk. 197.46
Overhead 3.50% = Tk. 69.11
= Tk. 2,241.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 130.44
Grand total = Tk. 2,371.61
Rate per No. = Tk. 2,371.61

Say, Tk. 2,372 .00 each

26.9.1.2 Coloured w-basin (Bangladeshi), size (mm) approx. 600x465x225, 14kg


Considering 1 No. of fixture
1. Coloured wash-basin 1 No. @ Tk. 1,212.00 each = Tk. 1,212.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(b) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(c) CP chain with rubber plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(b) CI brakets 1 Pair @ Tk. 113.45 Per pair = Tk. 113.45
4. Labour:
(a) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(c) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 2,039.60
Profit 10.00% = Tk. 203.96
Overhead 3.50% = Tk. 71.39
= Tk. 2,314.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 134.73
Grand total = Tk. 2,449.68
Analysis of PWD SoR 2014 for Civil Works 406

Rate per No. = Tk. 2,449.68

Say, Tk. 2,450 .00 each

26.9.1.3 Special coloured w-basin, (Bangladeshi) 204 size (mm) 5approx. 600x465x225, 14kg
1. Considering 1 No. of fixture
2. Special coloured wash-basin 1 No. @ Tk. 1,430.00 each = Tk. 1,430.00
(a) Accessories:
(b) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(d) CP chain with rubber plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(b) CI brakets 1 Pair @ Tk. 113.45 Per pair = Tk. 113.45
4. Labour:
(a) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(c) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 2,257.60
Profit 10.00% = Tk. 225.76
Overhead 3.50% = Tk. 79.02
= Tk. 2,562.38
Add VAT with adjustment factor 1.0582 5.50% = Tk. 149.13
Grand total = Tk. 2,711.51
Rate per No. = Tk. 2,711.51

Say, Tk. 2,712 .00 each

Item No.- 26.10.1


White w-basin(Bangladeshi), in/c pedastal size (mm) approx.656x510x845, 26kg 570 x 420 x 190. wt.: 10.4 kg.or equivalent
Considering 1 No. of fixture
1. White wash-basin 1 No. @ Tk. 4,000.00 each = Tk. 4,000.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(b) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(c) CP chain with rubber plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(b) CI brakets 1 Pair @ Tk. 113.45 Per pair = Tk. 113.45
4. Labour:
(a) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(c) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 4,827.60
Profit 10.00% = Tk. 482.76
Overhead 3.50% = Tk. 168.97
= Tk. 5,479.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 318.90
Grand total = Tk. 5,798.23
Rate per No. = Tk. 5,798.23

Say, Tk. 5,798 .00 each


Analysis of PWD SoR 2014 for Civil Works 407

Item No.- 26.10.2


Coloured w-basin (Bangladeshi), in/c pedastal size (mm) approx.656x510x845, 26kg
Considering 1 No. of fixture
1. Coloured wash-basin 1 No. @ Tk. 5,200.00 each = Tk. 5,200.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(b) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(c) CP chain with rubber plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(b) CI brakets 1 Pair @ Tk. 113.45 Per pair = Tk. 113.45
4. Labour:
(a) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(c) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 6,027.60
Profit 10.00% = Tk. 602.76
Overhead 3.50% = Tk. 210.97
= Tk. 6,841.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 398.17
Grand total = Tk. 7,239.50
Rate per No. = Tk. 7,239.50

Say, Tk. 7,240 .00 each

Item No.- 26.10.3


Special coloured w-basin (Bangladeshi), in/c pedastal size (mm) approx.656x510x845, 26kg
Considering 1 No. of fixture
1. Special coloured wash-basin 1 No. @ Tk. 6,000.00 each = Tk. 6,000.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(b) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(c) CP chain with rubber plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(b) CI brakets 1 Pair @ Tk. 113.45 Per pair = Tk. 113.45
4. Labour:
(a) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(c) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 6,827.60
Profit 10.00% = Tk. 682.76
Overhead 3.50% = Tk. 238.97
= Tk. 7,749.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 451.02
Grand total = Tk. 8,200.35
Rate per No. = Tk. 8,200.35

Say, Tk. 8,200 .00 each

Item No.- 26.11.1.1


White w-basin (Bangladeshi), in/c pedastal size (mm) approx. 650x485x870, 34kg 500 x 440 x 210. wt.: 7.6 kg.or equivalent
Considering 1 No. of fixture
Analysis of PWD SoR 2014 for Civil Works 408

1. White wash-basin 1 No. @ Tk. 7,200.00 each = Tk. 7,200.00


2. Accessories:
(a) a) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(b) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(c) CP chain with rubber plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(b) CI brakets 1 Pair @ Tk. 113.45 Per pair = Tk. 113.45
4. Labour:
(a) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(c) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 8,027.60
Profit 10.00% = Tk. 802.76
Overhead 3.50% = Tk. 280.97
= Tk. 9,111.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 530.29
Grand total = Tk. 9,641.62
Rate per No. = Tk. 9,641.62

Say, Tk. 9,642 .00 each

Item No.- 26.11.1.2


Coloured w-basin (Bangladeshi), in/c pedastal size (mm) approx. 650x485x870, 34kg
Considering 1 No. of fixture
1. Coloured wash-basin 1 No. @ Tk. 9,360.00 each = Tk. 9,360.00
2. Accessories
(a) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(b) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(c) CP chain with rubber plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(b) CI brakets 1 Pair @ Tk. 113.45 Per pair = Tk. 113.45
4. Labour:
(a) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(c) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 10,187.60
Profit 10.00% = Tk. 1,018.76
Overhead 3.50% = Tk. 356.57
= Tk. 11,562.93
Add VAT with adjustment factor 1.0582 5.50% = Tk. 672.97
Grand total = Tk. 12,235.90
Rate per No. = Tk. 12,235.90

Say, Tk. 12,236 .00 each

Item No.- 26.11.1.3


Special Coloured w-basin (Bangladeshi), in/c pedastal size (mm) approx. 650x485x870, 34kg
Considering 1 No. of fixture
1. Special coloured wash-basin 1 No. @ Tk. 10,800.00 each = Tk. 10,800.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
Analysis of PWD SoR 2014 for Civil Works 409

(b) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(c) CP chain with rubber plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(b) CI brakets 1 Pair @ Tk. 113.45 Per pair = Tk. 113.45
4. Labour:
(a) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(c) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 11,627.60
Profit 10.00% = Tk. 1,162.76
Overhead 3.50% = Tk. 406.97
= Tk. 13,197.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 768.10
Grand total = Tk. 13,965.43
Rate per No. = Tk. 13,965.43

Say, Tk. 13,965 .00 each


Item No. 26.12.1.1
Supplying, fitting-fixing Bangladeshi standard quality Pedestal of following type:
White Pedestal (Bangladeshi), size (mm) approx. 670x186x170, 6.5kg
Considering 1 No. of fixture
(a) White pedestal: 1 No. @ Tk. 763.00 each = Tk. 763.00
(b) Fitting fixing materials:
(i) 75 mm Rowel plug with screw 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
Total = Tk. 908.27
Profit 10.00% = Tk. 90.83
Overhead 3.50% = Tk. 31.79
= Tk. 1,030.89
Add VAT with adjustment factor 1.0582 5.50% = Tk. 60.00
Grand total = Tk. 1,090.89
Rate per No. = Tk. 1,090.89
Say, Tk. 1,091 .00 each
Item No. 26.12.1.2
Coloured pedestal (Bangladeshi), size(mm) approx. 670x186x170, 6.5kg
Considering 1 No. of fixture
(a) Coloured pedestal: 1 No. @ Tk. 801.00 each = Tk. 801.00
(b) Fitting fixing materials:
(i) 75 mm Rowel plug with screw 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
Total = Tk. 946.27
Profit 10.00% = Tk. 94.63
Overhead 3.50% = Tk. 33.12
= Tk. 1,074.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 62.51
Grand total = Tk. 1,136.53
Rate per No. = Tk. 1,136.53

Say, Tk. 1,137 .00 each


Analysis of PWD SoR 2014 for Civil Works 410

Item No. 26.12.1.3


Special coloured pedestal (Bangladeshi), size(mm) approx. 670x186x170, 6.5kg
Considering 1 No. of fixture
(a) Special coloured pedestal 1 No. @ Tk. 842.00 each = Tk. 842.00
(b) Fitting fixing materials:
(i) 75 mm Rowel plug with screw 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
Total = Tk. 987.27
Profit 10.00% = Tk. 98.73
Overhead 3.50% = Tk. 34.55
= Tk. 1,120.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 65.22
Grand total = Tk. 1,185.77
Rate per No. = Tk. 1,185.77

Say, Tk. 1,186 .00 each

Item No. 26.12.2.1


Supplying, fitting-fixing Bangladeshi standard quality Pedestal of following type:
White Pedestal (Bangladeshi), size (mm) approx. 670x186x170, 6.5kg
Considering 1 No. of fixture
(a) White pedestal: 1 No. @ Tk. 1,680.00 each = Tk. 1,680.00
(b) Fitting fixing materials:
(i) 75 mm Rowel plug with screw 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
Total = Tk. 1,825.27
Profit 10.00% = Tk. 182.53
Overhead 3.50% = Tk. 63.88
= Tk. 2,071.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 120.57
Grand total = Tk. 2,192.25
Rate per No. = Tk. 2,192.25
Say, Tk. 2,192 .00 each
Item No. 26.12.2.2
Coloured pedestal (Bangladeshi), size(mm) approx. 670x186x170, 6.5kg
Considering 1 No. of fixture
(a) Coloured pedestal: 1 No. @ Tk. 2,184.00 each = Tk. 2,184.00
(b) Fitting fixing materials:
(i) 75 mm Rowel plug with screw 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
Total = Tk. 2,329.27
Profit 10.00% = Tk. 232.93
Overhead 3.50% = Tk. 81.52
= Tk. 2,643.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 153.87
Grand total = Tk. 2,797.59
Rate per No. = Tk. 2,797.59

Say, Tk. 2,798 .00 each

Item No. 26.12.2.3


Analysis of PWD SoR 2014 for Civil Works 411

Special coloured pedestal (Bangladeshi), size(mm) approx. 670x186x170, 6.5kg


Considering 1 No. of fixture
(a) Special coloured pedestal 1 No. @ Tk. 2,520.00 each = Tk. 2,520.00
(b) Fitting fixing materials:
(i) 75 mm Rowel plug with screw 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
Total = Tk. 2,665.27
Profit 10.00% = Tk. 266.53
Overhead 3.50% = Tk. 93.28
= Tk. 3,025.08
Add VAT with adjustment factor 1.0582 5.50% = Tk. 176.06
Grand total = Tk. 3,201.14
Rate per No. = Tk. 3,201.14

Say, Tk. 3,201 .00 each

Item No.- 26.13.1.2


Supplying, fitting-fixing Bangladeshi standard quality wall-hung Urinal of following type:
White bowl urinal (Bangladeshi), size(mm) approx 485x360x290, 9.0kg wt.
Considering 1 No. of fixture
(a) White bowl urinal 1 No. @ Tk. 943.00 each = Tk. 943.00
(b) Accessories:
(i) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(ii) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) Fitting fixing materials:
(i) 75 mm rowel plug 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(d) Labour:
(i) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(ii) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 1,628.99
Profit 10.00% = Tk. 162.90
Overhead 3.50% = Tk. 57.01
= Tk. 1,848.90
Add VAT with adjustment factor 1.0582 5.50% = Tk. 107.61
Grand total = Tk. 1,956.51
Rate per No. = Tk. 1,956.51
Say, Tk. 1,957 .00 each
Item No.- 26.13.1.3
Coloured bowl urinal (Bangladeshi), size(mm) approx 485x360x290, 9.0kg
Considering 1 No. of fixture
(a) Coloured bowl urinal 1 No. @ Tk. 1,116.00 each = Tk. 1,116.00
(b) Accessories:
(i) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(ii) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) Fitting fixing materials:
(i) 75 mm rowel plug 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(d) Labour:
(i) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(ii) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 1,801.99
Profit 10.00% = Tk. 180.20
Overhead 3.50% = Tk. 63.07
= Tk. 2,045.26
Analysis of PWD SoR 2014 for Civil Works 412

Add VAT with adjustment factor 1.0582 5.50% = Tk. 119.04


Grand total = Tk. 2,164.30
Rate per No. = Tk. 2,164.30

Say, Tk. 2,164 .00 each

Item No.- 26.13.1.4


Special coloured bowl urinal (Bangladeshi), size(mm) approx 485x360x290, 9.0kg
Considering 1 No. of fixture
(a) Special coloured bowl rinal 1 No. @ Tk. 1,317.00 each = Tk. 1,317.00
(b) Accessories:
(i) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(ii) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) Fitting fixing materials:
(i) 75 mm rowel plug 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(d) Labour:
(i) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(ii) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 2,002.99
Profit 10.00% = Tk. 200.30
Overhead 3.50% = Tk. 70.10
= Tk. 2,273.39
Add VAT with adjustment factor 1.0582 5.50% = Tk. 132.31
Grand total = Tk. 2,405.70
Rate per No. = Tk. 2,405.70

Say, Tk. 2,406 .00 each

Item No.- 26.13.2.1


Supplying, fitting-fixing Bangladeshi standard quality wall-hung Urinal of following type:
White bowl urinal (Bangladeshi), size(mm) approx 445x3555x330, 10kg wt.
Considering 1 No. of fixture
(a) White bowl urinal 1 No. @ Tk. 1,440.00 each = Tk. 1,440.00
(b) Accessories:
(i) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(ii) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) Fitting fixing materials:
(i) 75 mm rowel plug 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(d) Labour:
(i) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(ii) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 2,125.99
Profit 10.00% = Tk. 212.60
Overhead 3.50% = Tk. 74.41
= Tk. 2,413.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 140.44
Grand total = Tk. 2,553.44
Rate per No. = Tk. 2,553.44

Say, Tk. 2,553 .00 each

Item No.- 26.13.2.2


Coloured bowl urinal (Bangladeshi), size(mm) approx 445x355x330, 10.0 kg 485x360x290, 9.0kg
Considering 1 No. of fixture
(a) Coloured bowl urinal 1 No. @ Tk. 1,872.00 each = Tk. 1,872.00
Analysis of PWD SoR 2014 for Civil Works 413

(b) Accessories:
(i) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(ii) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) Fitting fixing materials:
(i) 75 mm rowel plug 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(d) Labour:
(i) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(ii) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 2,557.99
Profit 10.00% = Tk. 255.80
Overhead 3.50% = Tk. 89.53
= Tk. 2,903.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 168.98
Grand total = Tk. 3,072.30
Rate per No. = Tk. 3,072.30

Say, Tk. 3,072 .00 each

Item No.- 26.13.2.3


Special coloured bowl urinal (Bangladeshi), size(mm) approx 445x355x330, 10.0 kg 485x360x290, 9.0kg
Considering 1 No. of fixture
(a) Special coloured bowl rinal 1 No. @ Tk. 2,160.00 each = Tk. 2,160.00
(b) Accessories:
(i) Grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(ii) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) Fitting fixing materials:
(i) 75 mm rowel plug 2 Nos. @ Tk. 12.76 each = Tk. 25.52
(d) Labour:
(i) Plumber 0.15 No. @ Tk. 440.00 each = Tk. 66.00
(ii) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 2,845.99
Profit 10.00% = Tk. 284.60
Overhead 3.50% = Tk. 99.61
= Tk. 3,230.20
Add VAT with adjustment factor 1.0582 5.50% = Tk. 188.00
Grand total = Tk. 3,418.20
Rate per No. = Tk. 3,418.20

Say, Tk. 3,418 .00 each

Item No.- 26.14.1


White flat/squatting urinal (Bangladeshi), size (mm) 510x380x 85 wt. 9.5 kg.or equivalent
Considering 1 No. of fixture
1. White flat/squatting urinal 1 No. @ Tk. 869.00 each = Tk. 869.00
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.2 bag @ Tk. 440.00 Per bag = Tk. 88.00
(ii) Sand (F.M. 1.2) 0.1 cft. @ Tk. 1,700.00 Per % cft. = Tk. 1.70
3. Labour:
(a) Plumber 0.2 No. @ Tk. 440.00 each = Tk. 88.00
(b) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,244.95
Profit 10.00% = Tk. 124.50
Analysis of PWD SoR 2014 for Civil Works 414

Overhead 3.50% = Tk. 43.57


= Tk. 1,413.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 82.24
Grand total = Tk. 1,495.26
Rate per No. = Tk. 1,495.26

Say, Tk. 1,495 .00 each

Item No.- 26.14.2


Coloured flat/squatting urinal (Bangladeshi), size (mm) 510x380x 85 wt. 9.5 kg..or equivalent
Considering 1 No. of fixture
1. Coloured flat/squatting urinal 1 No. @ Tk. 914.00 each = Tk. 914.00
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.2 bag @ Tk. 440.00 Per bag = Tk. 88.00
(ii) Sand (F.M. 1.2) 0.1 cft. @ Tk. 1,700.00 Per % cft. = Tk. 1.70
3. Labour:
(a) Plumber 0.2 No. @ Tk. 440.00 each = Tk. 88.00
(b) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,289.95
Profit 10.00% = Tk. 129.00
Overhead 3.50% = Tk. 45.15
= Tk. 1,464.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 85.21
Grand total = Tk. 1,549.31
Rate per No. = Tk. 1,549.31
Say, Tk. 1,549 .00 each
Item No.- 26.14.3
Special coloured flat/squatting urinal (Bangladeshi), size (mm) 510x380x 85 wt. 9.5 kg.

Considering 1 No. of fixture


1. Special Coloured flat/squatting urinal 1 No. @ Tk. 959.00 each = Tk. 959.00
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.2 bag @ Tk. 440.00 Per bag = Tk. 88.00
(ii) Sand (F.M. 1.2) 0.1 cft. @ Tk. 1,700.00 Per % cft. = Tk. 1.70
3. Labour:
(a) Plumber 0.2 No. @ Tk. 440.00 each = Tk. 88.00
(b) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,334.95
Profit 10.00% = Tk. 133.50
Overhead 3.50% = Tk. 46.72
= Tk. 1,515.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 88.18
Grand total = Tk. 1,603.35
Rate per No. = Tk. 1,603.35

Say, Tk. 1,603 .00 each


Item No.- 26.15.1
Supplying, fitting-fixing Bangladeshi standard quality sink of following type:
White porcelain sink (Bangladeshi), size (mm) 635 x 480 x 195, wt. 19.5 kg 625 x 490 x 224. wt. 19.5 kg. or equivalent
Considering 1 No. of fixture
1. White porcelain Sink 1 No. @ Tk. 1,535.94 each = Tk. 1,535.94
2. Accessories:
(a) CP grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
Analysis of PWD SoR 2014 for Civil Works 415

(b) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) CP chain with plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) CI braket: heavy type 1 Pair @ Tk. 138.05 Per pair = Tk. 138.05
(b) Cement mortar (1:4):
(i) Cement 0.015 bag. @ Tk. 440.00 Per bag = Tk. 6.60
(ii) Sand 0.075 cft. @ Tk. 1,700.00 Per % cft. = Tk. 1.28
4. Labour:
(a) Plumber 0.2 No. @ Tk. 440.00 each = Tk. 88.00
(b) Skilled labour 0.3 No. @ Tk. 303.00 each = Tk. 90.90
Total = Tk. 2,345.07
Profit 10.00% = Tk. 234.51
Overhead 3.50% = Tk. 82.08
= Tk. 2,661.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 154.91
Grand total = Tk. 2,816.57
Rate per No. = Tk. 2,816.57

Say, Tk. 2,817 .00 each

Item No.- 26.15.2


Coloured porcelain sink (Bangladeshi), size (mm) 635 x 480 x 195, wt. 19.5 kg 625 x 490 x 224. wt. 19.5 kg. or equivalent
Considering 1 No. of fixture
1. Coloured porcelain sink 1 No. @ Tk. 2,125.00 each = Tk. 2,125.00
2. Accessories:
(a) CP grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(b) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) CP chain with plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) CI braket: heavy type 1 Pair @ Tk. 138.05 Per pair = Tk. 138.05
(b) Cement mortar (1:4):
(i) Cement 0.015 bag. @ Tk. 440.00 Per bag = Tk. 6.60
(ii) Sand 0.075 cft. @ Tk. 1,700.00 Per % cft. = Tk. 1.28
4. Labour:
(a) Plumber 0.2 No. @ Tk. 440.00 each = Tk. 88.00
(b) Skilled labour 0.3 No. @ Tk. 303.00 each = Tk. 90.90
Total = Tk. 2,934.13
Profit 10.00% = Tk. 293.41
Overhead 3.50% = Tk. 102.69
= Tk. 3,330.23
Add VAT with adjustment factor 1.0582 5.50% = Tk. 193.82
Grand total = Tk. 3,524.05
Rate per No. = Tk. 3,524.05

Say, Tk. 3,524 .00 each

Item No.- 26.16


Stainless steel single bowl sink (Singapore/M'Asia), size(mm) 450 x 1050
Considering 1 No. of fixture
1. Stainless steel single bowl sink 1 No. @ Tk. 2,596.49 each = Tk. 2,596.49
2. Accessories:
(a) CP grating with brass coupling 1 No. @ Tk. 277.75 each = Tk. 277.75
(b) 32 mm dia PVC waste pipe 1 No. @ Tk. 158.12 each = Tk. 158.12
(c) CP chain with plug 1 No. @ Tk. 48.43 each = Tk. 48.43
3. Fitting fixing materials:
(a) CI braket: heavy type 1 Pair @ Tk. 138.05 Per pair = Tk. 138.05
(b) Cement mortar (1:4):
Analysis of PWD SoR 2014 for Civil Works 416

(i) Cement 0.015 bag. @ Tk. 440.00 Per bag = Tk. 6.60
(ii) Sand 0.075 cft. @ Tk. 1,700.00 Per % cft. = Tk. 1.28
4. Labour:
(a) Plumber 0.2 No. @ Tk. 440.00 each = Tk. 88.00
(b) Skilled labour 0.3 No. @ Tk. 303.00 each = Tk. 90.90
Total = Tk. 3,405.62
Profit 10.00% = Tk. 340.56
Overhead 3.50% = Tk. 119.20
= Tk. 3,865.38
Add VAT with adjustment factor 1.0582 5.50% = Tk. 224.97
Grand total = Tk. 4,090.35
Rate per No. = Tk. 4,090.35

Say, Tk. 4,090 .00 each

Item No.- 26.17


Stainless steel double bowl sink (Singapore/M'Asia)
Considering 1 No. of fixture
1. Stainless steel double bowl sink 1 No. @ Tk. 4,906.22 each = Tk. 4,906.22
2. Accessories:
(a) CP grating with brass coupling 2 Nos. @ Tk. 277.75 each = Tk. 555.50
(b) 40 mm dia PVC waste pipe 1 No. @ Tk. 316.24 each = Tk. 316.24
(c) CP chain with plug 2 Nos. @ Tk. 48.43 each = Tk. 96.86
3. Fitting fixing materials:
(a) CI braket: heavy type 3 Nos. @ Tk. 69.03 each = Tk. 207.09
(b) Cement mortar (1:4):
(i) Cement 0.022 bag. @ Tk. 440.00 Per bag = Tk. 9.68
(ii) Sand 0.12 cft. @ Tk. 1,700.00 Per % cft. = Tk. 2.04
4. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.4 No. @ Tk. 303.00 each = Tk. 121.20
Total = Tk. 6,324.83
Profit 10.00% = Tk. 632.48
Overhead 3.50% = Tk. 221.37
= Tk. 7,178.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 417.81
Grand total = Tk. 7,596.49
Rate per No. = Tk. 7,596.49

Say, Tk. 7,596 .00 each

Item No.- 26.18


Supply and fitting-fixing best quality mirror of following type:
Unframed mirror, size (mm) 450 x 600 x 5.
Considering 1 No. of fixture
(a) Unframed mirror 1 No. @ Tk. 492.00 each = Tk. 492.00
(b) Fitting fixing materials:
(i) Plastic cap 4 Nos. @ Tk. 13.61 each = Tk. 54.44
(ii) Rowel plug and screw 4 Nos. @ Tk. 6.38 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
Total = Tk. 654.56
Profit 10.00% = Tk. 65.46
Overhead 3.50% = Tk. 22.91
= Tk. 742.93
Add VAT with adjustment factor 1.0582 5.50% = Tk. 43.24
Analysis of PWD SoR 2014 for Civil Works 417

Grand total = Tk. 786.17


Rate per No. = Tk. 786.17

Say, Tk. 786 .00 each


Item No.- 26.19
Unframed mirror, size (mm) 450 x 350 x 5.
Considering 1 No. of fixture
(a) Unframed mirror 1 No. @ Tk. 336.00 each = Tk. 336.00
(b) Fitting fixing materials:
(i) Plastic cap 4 Nos. @ Tk. 13.61 each = Tk. 54.44
(ii) Rowel plug and screw 4 Nos. @ Tk. 6.38 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 517.26
Profit 10.00% = Tk. 51.73
Overhead 3.50% = Tk. 18.10
= Tk. 587.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 34.17
Grand total = Tk. 621.26
Rate per No. = Tk. 621.26
Say, Tk. 621 .00 each

Item No.- 26.20


Supply and fitting-fixing glas shelf:
236/A Super quality coloured glass shelf of size (mm) 600 x 125 x 5 mm thick
Considering 1 No. of fixture
(a) Steel frame with brakets 1 No. @ Tk. 586.08 each = Tk. 586.08
(b) Glass shelf 1 No. @ Tk. 326.00 each = Tk. 326.00
(c) Fitting fixing materials:
(i) Rowel plug and screw 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(d) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 1,047.62
Profit 10.00% = Tk. 104.76
Overhead 3.50% = Tk. 36.67
= Tk. 1,189.05
Add VAT with adjustment factor 1.0582 5.50% = Tk. 69.20
Grand total = Tk. 1,258.25
Rate per No. = Tk. 1,258.25

Say, Tk. 1,258 .00 each

Item No.- 26.21


Medium quality white glass shelf of size (mm) 600 x 125 x 5 mm thick
Considering 1 No. of fixture
(a) Steel frame with brakets 1 No. @ Tk. 305.00 each = Tk. 305.00
(b) Glass shelf 1 No. @ Tk. 133.00 each = Tk. 133.00
(c) Fitting fixing materials:
(i) Rowel plug and screw 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(d) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Analysis of PWD SoR 2014 for Civil Works 418

Total = Tk. 573.54


Profit 10.00% = Tk. 57.35
Overhead 3.50% = Tk. 20.07
= Tk. 650.96
Add VAT with adjustment factor 1.0582 5.50% = Tk. 37.89
Grand total = Tk. 688.85
Rate per No. = Tk. 688.85
Say, Tk. 689 .00 each
Item No.- 26.22
Supply and fitting-fixing towel rail of following sizes:
Super quality CP towel rail of size(mm) 600 x 20 mm dia.
Considering 1 set of item

(a) Super quality CP towel rail 1 No. @ Tk. 417.44 each = Tk. 417.44
(b) Fitting fixing materials:
(i) Rowel plug and screw 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(c) Labour:
(i) Plumber 0.04 No. @ Tk. 440.00 each = Tk. 17.60
(ii) Skilled labour 0.08 No. @ Tk. 303.00 each = Tk. 24.24
(iii) Ordinary labour 0.15 No. @ Tk. 245.00 each = Tk. 36.75
Total = Tk. 530.27
Profit 10.00% = Tk. 53.03
Overhead 3.50% = Tk. 18.56
= Tk. 601.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 35.03
Grand total = Tk. 636.89
Rate per No. = Tk. 636.89

Say, Tk. 637 .00 each


Item No.- 26.23
Medium quality CP towel rail of size(mm) 600 x 20 mm dia.
Considering 1 set of item
(a) Medium quality CP towel rail 1 No. @ Tk. 330.00 each = Tk. 330.00
(b) Fitting fixing materials:
(i) Rowel plug and screw 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(c) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
Total = Tk. 446.84
Profit 10.00% = Tk. 44.68
Overhead 3.50% = Tk. 15.64
= Tk. 507.16
Add VAT with adjustment factor 1.0582 5.50% = Tk. 29.52
Grand total = Tk. 536.68
Rate per No. = Tk. 536.68

Say, Tk. 537 .00 each

Item No.- 26.24.1


Supplying, fitting-fixing toilet paper holder of following type:
BISF White porcelain toilet paper holder (Bangladeshi), size(mm) 150 x 150 x 126.or equivalent
Considering 1 No. of fixture

1. White porcelain toilet paper holder 1 No. @ Tk. 126.00 each = Tk. 126.00
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
Analysis of PWD SoR 2014 for Civil Works 419

(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
3. Labour:
(a) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(b) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(c) Ordinary labour 0.01 No. @ Tk. 245.00 each = Tk. 2.45
Total = Tk. 159.85
Profit 10.00% = Tk. 15.99
Overhead 3.50% = Tk. 5.59
= Tk. 181.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10.56
Grand total = Tk. 191.99
Rate per No. = Tk. 191.99

Say, Tk. 192 .00 each

Item No.- 26.24.2


BISF Special colour porcelain toilet paper holder (Bangladeshi), size (mm) 150 x 150 x 126. or equivalent
Considering 1 No. of fixture
1. Special Coloure paper holder 1 No. @ Tk. 155.00 each = Tk. 155.00
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
3. Labour:
(a) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(b) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(c) Ordinary labour 0.01 No. @ Tk. 245.00 each = Tk. 2.45
Total = Tk. 188.85
Profit 10.00% = Tk. 18.89
Overhead 3.50% = Tk. 6.61
= Tk. 214.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12.48
Grand total = Tk. 226.83
Rate per No. = Tk. 226.83

Say, Tk. 227 .00 each

Item No.- 26.25.1


Supplying, fitting-fixing toilet paper holder of following type:
White porcelain toilet paper holder (Bangladeshi), size(mm) 150 x 150 x 126.or equivalent
Considering 1 No. of fixture

1. White porcelain toilet paper holder 1 No. @ Tk. 450.00 each = Tk. 450.00
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
3. Labour:
(a) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(b) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(c) Ordinary labour 0.01 No. @ Tk. 245.00 each = Tk. 2.45
Total = Tk. 483.85
Profit 10.00% = Tk. 48.39
Overhead 3.50% = Tk. 16.93
= Tk. 549.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 31.96
Grand total = Tk. 581.13
Analysis of PWD SoR 2014 for Civil Works 420

Rate per No. = Tk. 581.13

Say, Tk. 581 .00 each

Item No.- 26.25.2


Special colour porcelain toilet paper holder (Bangladeshi), size (mm) 150 x 150 x 126. or equivalent
Considering 1 No. of fixture
1. Special Coloure paper holder 1 No. @ Tk. 585.00 each = Tk. 585.00
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
3. Labour:
(a) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(b) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(c) Ordinary labour 0.01 No. @ Tk. 245.00 each = Tk. 2.45
Total = Tk. 618.85
Profit 10.00% = Tk. 61.89
Overhead 3.50% = Tk. 21.66
= Tk. 702.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 40.88
Grand total = Tk. 743.28
Rate per No. = Tk. 743.28

Say, Tk. 743 .00 each


Analysis of PWD SoR 2014 for Civil Works 421

Item No.- 26.25.2


Stainless steel toilet paper holder
Considering 1 No. of fixture
(a) Stainless steel toilet paper holder 1 No. @ Tk. 270.96 each = Tk. 270.96
(b) Fitting fixing materials:
(i) Rowel plug with screw 4 Nos. @ Tk. 6.38 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
Total = Tk. 337.78
Profit 10.00% = Tk. 33.78
Overhead 3.50% = Tk. 11.82
= Tk. 383.38
Add VAT with adjustment factor 1.0582 5.50% = Tk. 22.31
Grand total = Tk. 405.69
Rate per No. = Tk. 405.69

Say, Tk. 406 .00 each

Item No.- 26.25.3


238/C1 CP iron toilet paper holder with plastic holder rod
Considering 1 No. of fixture
(a) CP iron toilet paper holder 1 No. @ Tk. 216.02 each = Tk. 216.02
(b) Fitting fixing materials:
(i) Rowel plug with screw 4 Nos. @ Tk. 6.38 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
Total = Tk. 282.84
Profit 10.00% = Tk. 28.28
Overhead 3.50% = Tk. 9.90
= Tk. 321.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.68
Grand total = Tk. 339.70
Rate per No. = Tk. 339.70

Say, Tk. 340 .00 each

Item No.- 26.26.1


CP soap tray
Considering 1 No. of fixture
(a) CP soap tray 1 No. @ Tk. 124.00 each = Tk. 124.00
(b) Fitting fixing materials:
(i) Rowel plug with screw 4 Nos. @ Tk. 6.38 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
Total = Tk. 175.67
Profit 10.00% = Tk. 17.57
Overhead 3.50% = Tk. 6.15
= Tk. 199.39
Add VAT with adjustment factor 1.0582 5.50% = Tk. 11.60
Grand total = Tk. 210.99
Rate per No. = Tk. 210.99

Say, Tk. 211 .00 each


Item No.- 26.26.2
Analysis of PWD SoR 2014 for Civil Works 422

Porcelain soap tray: white


Considering 1 No. of fixture
(a) Porcelain soap tray: white 1 No. @ Tk. 215.59 each = Tk. 215.59
(b) Fitting fixing materials:
(i) Rowel plug with screw 4 Nos. @ Tk. 6.38 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
Total = Tk. 267.26
Profit 10.00% = Tk. 26.73
Overhead 3.50% = Tk. 9.35
= Tk. 303.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.65
Grand total = Tk. 320.99
Rate per No. = Tk. 320.99

Say, Tk. 321 .00 each

Item No.- 26.26.3


Porcelain soap tray: colored
Considering 1 No. of fixture
(a) Porcelain soap tray: colored 1 No. @ Tk. 260.62 each = Tk. 260.62
(b) Fitting fixing materials:
(i) Rowel plug with screw 4 Nos. @ Tk. 6.38 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
Total = Tk. 312.29
Profit 10.00% = Tk. 31.23
Overhead 3.50% = Tk. 10.93
= Tk. 354.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.63
Grand total = Tk. 375.08
Rate per No. = Tk. 375.08

Say, Tk. 375 .00 each

Item No.- 26.26.4


Stainless steel soap tray
Considering 1 No. of fixture
(a) Stainless steel soap tray 1 No. @ Tk. 227.11 each = Tk. 227.11
(b) Fitting fixing materials:
(i) Rowel plug with screw 4 Nos. @ Tk. 6.38 each = Tk. 25.52
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
Total = Tk. 278.78
Profit 10.00% = Tk. 27.88
Overhead 3.50% = Tk. 9.76
= Tk. 316.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.42
Grand total = Tk. 334.84
Rate per No. = Tk. 334.84

Say, Tk. 335 .00 each


Item No.- 26.27
Supplying, fitting-fixing floor-grating of following type:
Analysis of PWD SoR 2014 for Civil Works 423

125 mm dia stainless steel floor-grating

1. 125 mm dia stainless steel grating 1 No. @ Tk. 114.24 each = Tk. 114.24
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
3. Labour:
(a) Skilled labour 0.15 No. @ Tk. 303.00 each = Tk. 45.45
Total = Tk. 164.94
Profit 10.00% = Tk. 16.49
Overhead 3.50% = Tk. 5.77
= Tk. 187.20
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10.90
Grand total = Tk. 198.10
Rate per No. = Tk. 198.10

Say, Tk. 198 .00 each

Item No.- 26.28


62 mm dia stainless steel floor-grating
Considering 1 No. of fixture
1. 62 mm dia stainless steel grating 1 No. @ Tk. 85.27 each = Tk. 85.27
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag. @ Tk. 440.00 Per bag = Tk. 4.40
(ii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
3. Labour:
(a) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
Total = Tk. 120.82
Profit 10.00% = Tk. 12.08
Overhead 3.50% = Tk. 4.23
= Tk. 137.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 7.98
Grand total = Tk. 145.11
Rate per No. = Tk. 145.11

Say, Tk. 145 .00 each

Item No.- 26.29


150 x 150 mm size plastic-grating with hinged cover
Considering 1 No. of fixture
1. Plastic-grating 1 No. @ Tk. 187.18 each = Tk. 187.18
2. Fitting fixing materials:
(a) Solvent cement 13.5 grm. @ Tk. 1.63 Per grm. = Tk. 22.01
(b) Cement mortar (1:4):
(i) Cement 0.02 bag. @ Tk. 440.00 Per bag = Tk. 8.80
(ii) Sand (F.M. 1.2) 0.1 cft. @ Tk. 1,700.00 Per % cft. = Tk. 1.70
3. Labour:
(a) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(b) Skilled labour 0.15 No. @ Tk. 303.00 each = Tk. 45.45
Total = Tk. 287.14
Profit 10.00% = Tk. 28.71
Overhead 3.50% = Tk. 10.05
= Tk. 325.90
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.97
Grand total = Tk. 344.87
Analysis of PWD SoR 2014 for Civil Works 424

Rate per No. = Tk. 344.87

Say, Tk. 345 .00 each

Item No.- 26.30


Supplying fitting and fixing of 100 mm/ 4" dia cast iron rain water down pipe
Considering 6' ft. long 7 pc.= 42 rft.
1. Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
2. Helper to plumber 2 Nos. @ Tk. 304.00 each = Tk. 608.00
3. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
4. Scaffolding L.S. = Tk. 240.00
5. Cost of pipe 42 rft. @ Tk. 2,095.26 Per pc (6'-0") = Tk. 14,666.82
6. Fittings, clamp, nails etc. 25% = Tk. 3,666.71
Total = Tk. 19,866.53
Profit 10.00% = Tk. 1,986.65
Overhead 3.50% = Tk. 695.33
= Tk. 22,548.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,312.35
Grand total = Tk. 23,860.86
Rate per rft. = Tk. 568.12
Rate per meter = Tk. 1,864.00

Say, Tk. 1,864 .00 Per rm

Item No.- 26.31


Supplying, fitting fixing of 100 mm/4" dia u-PVC rain water down pipe.
Considering 60 rft.of work
1. Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
2. Helper to plumber 2 Nos. @ Tk. 304.00 each = Tk. 608.00
3. Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
4. Scaffolding L.S. = Tk. 360.00
5. Cost of u-PVC pipe 60 rft. @ Tk. 104.19 Per rft. = Tk. 6,251.40
6. Fittings, clamp nails etc. 30% = Tk. 1,875.42
Total = Tk. 9,779.82
Profit 10.00% = Tk. 977.98
Overhead 3.50% = Tk. 342.29
= Tk. 11,100.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 646.04
Grand total = Tk. 11,746.13
Rate per rft. = Tk. 195.77
Rate per rm. = Tk. 642.32

Say, Tk. 642 .00 Per rm

Item No. -26.32


Supplying, fitting & fixing of soil, waste and ventilation pipe of following type (cement mortar jointing)
50 mm dia HCI, single hub pipe
Considering 3 x 1.83 m= 5.49 meter work
(a) 50 mm dia 1.8 m long HCI pipe: 3 Nos. @ Tk. 1,005.10 each = Tk. 3,015.30
(b) Fittings:
(i) Bend/45O bend/ off-set/cowel etc. 1 No. @ Tk. 221.36 each = Tk. 221.36
(ii) Tee/T-Y/Y(50 x 50 mm) 1 No. @ Tk. 626.35 each = Tk. 626.35
(c) Jointing & fixing materials
(i) Hem 25 gm. @ Tk. 1.84 Per gm. = Tk. 46.00
(ii) Cement 0.02 bag. @ Tk. 440.00 Per bag. = Tk. 8.80
(iii) Sand (F.M. 1.2) 0.05 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.85
(iv) Clamp 3 Nos. @ Tk. 32.80 each = Tk. 98.40
Analysis of PWD SoR 2014 for Civil Works 425

(v) Rowel plug & screw 6 Nos. @ Tk. 22.83 each = Tk. 136.98
(vi) Scaffolding 18 rft. @ Tk. 2.26 Per rft. = Tk. 40.68
(d) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 4,397.32
Profit 10.00% = Tk. 439.73
Overhead 3.50% = Tk. 153.91
= Tk. 4,990.96
Add VAT with adjustment factor 1.0582 5.50% = Tk. 290.48
Grand total = Tk. 5,281.44
Rate per rm. = Tk. 962.01

Say, Tk. 962 .00 Per rm

Item No. -26.33


100 mm dia HCI, single hub pipe
Considering 3 x 1.83 m= 5.49 meter work
(a) 100 mm dia 1.83 m long HCI pipe: 3 Nos. @ Tk. 2,095.26 each = Tk. 6,285.78
(b) Fittings:
(i) Bend/45O bend/off-set/cowel etc. 1 No. @ Tk. 450.08 each = Tk. 450.08
(ii) Tee/T-Y/Y(100 x 100/50 mm) 1 No. @ Tk. 788.83 each = Tk. 788.83
(c) Jointing & fixing materials
(i) Hem 50 gm. @ Tk. 1.84 Per gm. = Tk. 92.00
(ii) Cement 0.04 bag. @ Tk. 440.00 Per bag. = Tk. 17.60
(iii) Sand (F.M. 1.2) 0.1 cft. @ Tk. 1,700.00 Per % cft. = Tk. 1.70
(iv) Clamp 3 Nos. @ Tk. 43.73 each = Tk. 131.19
(v) Rowel plug & screw 6 Nos. @ Tk. 22.83 each = Tk. 136.98
(vi) Scaffolding 18 rft. @ Tk. 2.26 Per rft. = Tk. 40.68
(d) Labour:
(i) Plumber 0.3 No. @ Tk. 440.00 each = Tk. 132.00
(ii) Skilled labour 0.6 No. @ Tk. 303.00 each = Tk. 181.80
(iii) Ordinary labour 0.12 No. @ Tk. 245.00 each = Tk. 29.40
Total = Tk. 8,288.04
Profit 10.00% = Tk. 828.80
Overhead 3.50% = Tk. 290.08
= Tk. 9,406.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 547.49
Grand total = Tk. 9,954.41
Rate per rm. = Tk. 1,813.19

Say, Tk. 1,813 .00 Per rm

Item No. -26.34


150 mm diaHCI, single hub pipe
Considering 3 x 1.83 m = 5.49 meter work
(a) 150 mm dia 1.8 m long HCI pipe: 3 Nos. @ Tk. 2,899.65 each = Tk. 8,698.95
(b) Fittings:
(i) Bend/45O bend/off-set/cowel 1 No. @ Tk. 1,013.81 each = Tk. 1,013.81
(ii) Tee/T-Y/Y 1 No. @ Tk. 1,424.70 each = Tk. 1,424.70
(c) Jointing & fixing materials
(i) Hem 75 gm. @ Tk. 1.84 Per gm. = Tk. 138.00
(ii) Cement 0.06 bag. @ Tk. 440.00 Per bag. = Tk. 26.40
(iii) Sand (F.M. 1.2) 0.3 cft. @ Tk. 1,700.00 Per % cft. = Tk. 5.10
(iv) Clamp 3 Nos. @ Tk. 54.66 each = Tk. 163.98
(v) Rowel plug & screw 6 Nos. @ Tk. 28.53 each = Tk. 171.18
Analysis of PWD SoR 2014 for Civil Works 426

(vi) Scaffolding 36 rft. @ Tk. 2.26 Per rft. = Tk. 81.36


(d) Labour:
(i) Plumber 0.3 No. @ Tk. 440.00 each = Tk. 132.00
(ii) Skilled labour 0.6 No. @ Tk. 303.00 each = Tk. 181.80
(iii) Ordinary labour 0.12 No. @ Tk. 245.00 each = Tk. 29.40
Total = Tk. 12,066.68
Profit 10.00% = Tk. 1,206.67
Overhead 3.50% = Tk. 422.33
= Tk. 13,695.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 797.10
Grand total = Tk. 14,492.78
Rate per rm. = Tk. 2,639.85

Say, Tk. 2,640 .00 Per rm

Item No. -26.35


50 mm dia uPVC pipe
Considering 20 rft. long one pipe
(a) 50 mm dia 20'-0" long pipe: 20 rft. @ Tk. 44.84 each = Tk. 896.80
(b) Fittings:
(i) Bend/45O bend/off-set/cowel 1 No. @ Tk. 136.44 each = Tk. 136.44
(ii) Tee/T-Y/Y 1 No. @ Tk. 209.24 each = Tk. 209.24
(c) Jointing & fixing materials
(i) Solvent cement 20 gm. @ Tk. 1.63 Per gm. = Tk. 32.60
(ii) Clamp 8 Nos. @ Tk. 10.93 each = Tk. 87.44
(iii) Rowel plug & screw 16 Nos. @ Tk. 8.56 each = Tk. 136.96
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(iii) Ordinary labour 0.8 No. @ Tk. 245.00 each = Tk. 196.00
Total = Tk. 2,263.68
Profit 10.00% = Tk. 226.37
Overhead 3.50% = Tk. 79.23
= Tk. 2,569.28
Add VAT with adjustment factor 1.0582 5.50% = Tk. 149.53
Grand total = Tk. 2,718.81
Rate per ft. = Tk. 135.94
Rate per rm. = Tk. 446.02

Say, Tk. 446 .00 Per rm

Item No.- 26.36


100 mm dia uPVC pipe
Considering 20 rft. long one pipe
(a) 100 mm dia 20'-0" long pipe: 20 rft. @ Tk. 104.19 each = Tk. 2,083.80
(b) Fittings:
(i) Bend/45O bend/off-set/cowel 1 No. @ Tk. 292.00 each = Tk. 292.00
(ii) Tee/T-Y/Y 1 No. @ Tk. 457.94 each = Tk. 457.94
(c) Jointing & fixing materials
(i) Solvent cement 54 gm. @ Tk. 1.63 Per gm. = Tk. 88.02
(ii) Clamp 4 Nos. @ Tk. 14.58 each = Tk. 58.32
(iii) Rowel plug & screw 8 Nos. @ Tk. 11.41 each = Tk. 91.28
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.75 No. @ Tk. 440.00 each = Tk. 330.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Analysis of PWD SoR 2014 for Civil Works 427

Total = Tk. 3,749.56


Profit 10.00% = Tk. 374.96
Overhead 3.50% = Tk. 131.23
= Tk. 4,255.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 247.69
Grand total = Tk. 4,503.44
Rate per ft. = Tk. 225.17
Rate per rm. = Tk. 738.78

Say, Tk. 739 .00 Per rm

Item No.- 26.37


150 mm dia uPVC Pipe
Considering 20 rft. long one pipe
(a) 150 mm dia 20'-0" long pipe: 20 rft. @ Tk. 135.99 each = Tk. 2,719.80
(b) Fittings:
(i) Bend/45O bend/off-set/cowel etc. 1 No. @ Tk. 494.55 each = Tk. 494.55
(ii) Tee/T-Y/Y 1 No. @ Tk. 1,048.44 each = Tk. 1,048.44
(c) Jointing & fixing materials
(i) Solvent cement 120 gm. @ Tk. 1.63 Per gm. = Tk. 195.60
(ii) Clamp 4 Nos. @ Tk. 14.58 each = Tk. 58.32
(iii) Rowel plug & screw 8 Nos. @ Tk. 14.27 each = Tk. 114.16
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 5,444.07
Profit 10.00% = Tk. 544.41
Overhead 3.50% = Tk. 190.54
= Tk. 6,179.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 359.63
Grand total = Tk. 6,538.65
Rate per ft. = Tk. 326.93
Rate per rm. = Tk. 1,072.66

Say, Tk. 1,073 .00 Per rm

Item No.- 26.38


Supplying, fitting & fixing installation and testing of Water-Supply pipe of following sizes:
26.38.1 12 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 12 mm dia G.I. pipe: 20 rft. @ Tk. 53.61 Per rft. = Tk. 1,072.20
(b) Fittings:
(i) Elbow 1 No. @ Tk. 23.59 each = Tk. 23.59
(ii) Tee 1 No. @ Tk. 26.24 each = Tk. 26.24
(iii) Nipple 1 No. @ Tk. 19.79 each = Tk. 19.79
(iv) Plug 1 No. @ Tk. 15.82 each = Tk. 15.82
(v) Socket 1 No. @ Tk. 18.79 each = Tk. 18.79
(c) Jointing & fixing materials
(i) Teflon tape 2.1 gm. @ Tk. 1.82 Per gm. = Tk. 3.82
(ii) Clamp 2 Nos. @ Tk. 14.58 each = Tk. 29.16
(iii) Rowel plug & screw 4 Nos. @ Tk. 5.71 each = Tk. 22.84
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
(ii) Skilled labour 0.375 No. @ Tk. 303.00 each = Tk. 113.63
Analysis of PWD SoR 2014 for Civil Works 428

(iii) Ordinary labour 0.325 No. @ Tk. 245.00 each = Tk. 79.63
Total = Tk. 1,525.71
Profit 10.00% = Tk. 152.57
Overhead 3.50% = Tk. 53.40
= Tk. 1,731.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 100.79
Grand total = Tk. 1,832.47
Rate per rft. = Tk. 91.62
Rate Per rm = Tk. 300.61

Say, Tk. 301 .00 Per rm

26.38.2 20 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 20 mm dia G.I. pipe: 20 rft. @ Tk. 74.07 Per rft. = Tk. 1,481.40
(b) Fittings:
(i) Elbow 1 No. @ Tk. 30.07 each = Tk. 30.07
(ii) Tee 1 No. @ Tk. 40.99 each = Tk. 40.99
(iii) Nipple 0.5 No. @ Tk. 28.22 each = Tk. 14.11
(iv) Plug 0.5 No. @ Tk. 19.69 each = Tk. 9.85
(v) Reducer 1 No. @ Tk. 34.83 each = Tk. 34.83
(vi) Socket 1 No. @ Tk. 24.01 each = Tk. 24.01
(c) Jointing & fixing materials
(i) Teflon tape 3.2 gm. @ Tk. 1.82 Per gm. = Tk. 5.82
(ii) Clamp 2 Nos. @ Tk. 7.29 each = Tk. 14.58
(iii) Rowel plug & screw 4 Nos. @ Tk. 5.71 each = Tk. 22.84
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
(ii) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,976.95
Profit 10.00% = Tk. 197.70
Overhead 3.50% = Tk. 69.19
= Tk. 2,243.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 130.59
Grand total = Tk. 2,374.43
Rate per rft. = Tk. 118.72
Rate per rm. = Tk. 389.52

Say, Tk. 390 .00 Per rm

26.38.3 25 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 25 mm dia G.I. pipe: 20 rft. @ Tk. 99.61 Per rft. = Tk. 1,992.20
(b) Fittings:
(i) Elbow 1 No. @ Tk. 38.66 each = Tk. 38.66
(ii) Tee 1 No. @ Tk. 46.27 each = Tk. 46.27
(iii) Nipple 1 No. @ Tk. 36.70 each = Tk. 36.70
(iv) Plug 1 No. @ Tk. 25.27 each = Tk. 25.27
(v) Reducer 1 No. @ Tk. 48.42 each = Tk. 48.42
(vi) Socket 1 No. @ Tk. 37.93 each = Tk. 37.93
(c) Jointing & fixing materials
(i) Teflon tape 4.2 gm. @ Tk. 1.82 Per gm. = Tk. 7.64
(ii) Clamp 2 Nos. @ Tk. 9.11 each = Tk. 18.22
(iii) Rowel plug & screw 4 Nos. @ Tk. 7.13 each = Tk. 28.52
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
Analysis of PWD SoR 2014 for Civil Works 429

(d) Labour:
(i) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
(ii) Skilled labour 0.25 No. @ Tk. 303.00 each = Tk. 75.75
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,578.28
Profit 10.00% = Tk. 257.83
Overhead 3.50% = Tk. 90.24
= Tk. 2,926.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 170.32
Grand total = Tk. 3,096.67
Rate per rft. = Tk. 154.83
Rate per rm = Tk. 508.00
Say, Tk. 508 .00 Per rm

26.38.4 32 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 32 mm dia G.I. pipe: 20 rft. @ Tk. 124.90 Per rft. = Tk. 2,498.00
(b) Fittings:
(i) Elbow 1 No. @ Tk. 65.28 each = Tk. 65.28
(ii) Tee 1 No. @ Tk. 87.50 each = Tk. 87.50
(iii) Nipple 0.5 No. @ Tk. 63.52 each = Tk. 31.76
(iv) Plug 0.5 No. @ Tk. 38.43 each = Tk. 19.22
(v) Reducer 1 No. @ Tk. 72.29 each = Tk. 72.29
(vi) Socket 1 No. @ Tk. 61.52 each = Tk. 61.52
(c) Jointing & fixing materials
(i) Teflon tape 5.2 gm. @ Tk. 1.82 Per gm. = Tk. 9.46
(ii) Clamp 2 Nos. @ Tk. 9.11 each = Tk. 18.22
(iii) Rowel plug & screw 4 Nos. @ Tk. 7.13 each = Tk. 28.52
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 3,265.97
Profit 10.00% = Tk. 326.60
Overhead 3.50% = Tk. 114.31
= Tk. 3,706.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 215.74
Grand total = Tk. 3,922.62
Rate per rft. = Tk. 196.13
Rate per rm = Tk. 643.50
Say, Tk. 644 .00 Per rm

26.38.5 40 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 40 mm dia G.I. pipe: 20 rft. @ Tk. 169.31 Per rft. = Tk. 3,386.20
(b) Fittings:
(i) Elbow 1 No. @ Tk. 81.73 each = Tk. 81.73
(ii) Tee 1 No. @ Tk. 103.49 each = Tk. 103.49
(iii) Nipple 1 No. @ Tk. 69.22 each = Tk. 69.22
(iv) Plug 1 No. @ Tk. 48.61 each = Tk. 48.61
(v) Reducer 1 No. @ Tk. 103.23 each = Tk. 103.23
(vi) Socket 1 No. @ Tk. 64.90 each = Tk. 64.90
(c) Jointing & fixing materials
(i) Teflon tape 6.3 gm. @ Tk. 1.82 Per gm. = Tk. 11.47
(ii) Clamp 2 Nos. @ Tk. 9.11 each = Tk. 18.22
(iii) Rowel plug & screw 4 Nos. @ Tk. 7.13 each = Tk. 28.52
Analysis of PWD SoR 2014 for Civil Works 430

(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20


(d) Labour:
(i) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 4,412.29
Profit 10.00% = Tk. 441.23
Overhead 3.50% = Tk. 154.43
= Tk. 5,007.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 291.47
Grand total = Tk. 5,299.42
Rate per rft. = Tk. 264.97
Rate per rm = Tk. 869.37

Say, Tk. 869 .00 Per rm

26.38.6 50 mm dia G.I. pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 50 mm dia G.I. pipe: 20 rft. @ Tk. 197.33 Per rft. = Tk. 3,946.60
(b) Fittings:
(i) Elbow 1 No. @ Tk. 115.59 each = Tk. 115.59
(ii) Tee 1 No. @ Tk. 162.01 each = Tk. 162.01
(iii) Nipple 1 No. @ Tk. 91.15 each = Tk. 91.15
(iv) Plug 1 No. @ Tk. 60.91 each = Tk. 60.91
(v) Reducer 1 No. @ Tk. 105.56 each = Tk. 105.56
(vi) Socket 1 No. @ Tk. 97.92 each = Tk. 97.92
(c) Jointing & fixing materials
(i) Teflon tape 8.2 gm. @ Tk. 1.82 Per gm. = Tk. 14.92
(ii) Clamp (F.I. bar) 2 Nos. @ Tk. 27.33 each = Tk. 54.66
(iii) Rowel plug & screw 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 5,496.76
Profit 10.00% = Tk. 549.68
Overhead 3.50% = Tk. 192.39
= Tk. 6,238.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 363.11
Grand total = Tk. 6,601.94
Rate per rft. = Tk. 330.10
Rate per rm. = Tk. 1,083.06

Say, Tk. 1,083 .00 Per rm


Analysis of PWD SoR 2014 for Civil Works 431

26.38.7 62 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 62 mm dia G.I. pipe: 20 rft. @ Tk. 277.79 Per rft. = Tk. 5,555.80
(b) Fittings:
(i) Elbow 1 No. @ Tk. 196.98 each = Tk. 196.98
(ii) Tee 1 No. @ Tk. 223.18 each = Tk. 223.18
(iii) Nipple 1 No. @ Tk. 155.88 each = Tk. 155.88
(iv) Plug 1 No. @ Tk. 91.75 each = Tk. 91.75
(v) Reducer 1 No. @ Tk. 144.45 each = Tk. 144.45
(vi) Socket 1 No. @ Tk. 133.32 each = Tk. 133.32
(c) Jointing & fixing materials
(i) Teflon tape 10.5 gm. @ Tk. 1.82 Per gm. = Tk. 19.11
(ii) Clamp (F.I. bar) 2 Nos. @ Tk. 27.33 each = Tk. 54.66
(iii) Rowel plug & screw 4 Nos. @ Tk. 8.56 each = Tk. 34.24
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
(iii) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 7,819.07
Profit 10.00% = Tk. 781.91
Overhead 3.50% = Tk. 273.67
= Tk. 8,874.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 516.51
Grand total = Tk. 9,391.16
Rate per rft. = Tk. 469.56
Rate per rm. = Tk. 1,540.63
Say, Tk. 1,541 .00 Per rm
26.38.8 75 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 rft. long one pipe
(a) 75 mm dia G.I. pipe: 20 rft. @ Tk. 330.99 Per rft. = Tk. 6,619.80
(b) Fittings:
(i) Elbow 1 No. @ Tk. 352.01 each = Tk. 352.01
(ii) Tee 1 No. @ Tk. 400.01 each = Tk. 400.01
(iii) Nipple 1 No. @ Tk. 239.50 each = Tk. 239.50
(iv) Plug 1 No. @ Tk. 156.54 each = Tk. 156.54
(v) Reducer 1 No. @ Tk. 216.85 each = Tk. 216.85
(vi) Socket 1 No. @ Tk. 194.56 each = Tk. 194.56
(c) Jointing & fixing materials
(i) Teflon tape 12.5 gm. @ Tk. 1.82 Per gm. = Tk. 22.75
(ii) Clamp (F.I. bar) 2 Nos. @ Tk. 36.44 each = Tk. 72.88
(iii) Rowel plug & screw 4 Nos. @ Tk. 11.41 each = Tk. 45.64
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 0.75 No. @ Tk. 440.00 each = Tk. 330.00
(ii) Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
(iii) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 9,640.24
Profit 10.00% = Tk. 964.02
Overhead 3.50% = Tk. 337.41
= Tk. 10,941.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 636.82
Grand total = Tk. 11,578.49
Rate per rft. = Tk. 578.92
Rate per rm. = Tk. 1,899.44
Say, Tk. 1,899 .00 Per rm
26.38.9 100 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Analysis of PWD SoR 2014 for Civil Works 432

Considering 20 rft. long one pipe


(a) 100 mm dia G.I. pipe: 20 rft. @ Tk. 433.02 Per rft. = Tk. 8,660.40
(b) Fittings:
(i) Elbow 1 No. @ Tk. 487.23 each = Tk. 487.23
(ii) Tee 1 No. @ Tk. 538.84 each = Tk. 538.84
(iii) Nipple 1 No. @ Tk. 354.18 each = Tk. 354.18
(iv) Plug 1 No. @ Tk. 307.75 each = Tk. 307.75
(v) Reducer 1 No. @ Tk. 336.88 each = Tk. 336.88
(vi) Socket 1 No. @ Tk. 344.21 each = Tk. 344.21
(c) Jointing & fixing materials
(i) Teflon tape 16.75 gm. @ Tk. 1.82 Per gm. = Tk. 30.49
(ii) Clamp (F.I. bar) 2 Nos. @ Tk. 45.55 each = Tk. 91.10
(iii) Rowel plug & screw 4 Nos. @ Tk. 14.27 each = Tk. 57.08
(iv) Scaffolding 20 rft. @ Tk. 2.26 Per rft. = Tk. 45.20
(d) Labour:
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
(iii) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 12,789.36
Profit 10.00% = Tk. 1,278.94
Overhead 3.50% = Tk. 447.63
= Tk. 14,515.93
Add VAT with adjustment factor 1.0582 5.50% = Tk. 844.84
Grand total = Tk. 15,360.77
Rate per rft. = Tk. 768.04
Rate per rm. = Tk. 2,519.94

Say, Tk. 2,520 .00 Per rm

Item No.- 26.39


26.39.1 1/2" or 12 mm dia uPVC pipe for plumbing purpose
Considering 20 rft. long 6 Nos. pipe = 120 rft. work
(a) 12 mm dia uPVC pipe 120 rft. @ Tk. 13.45 Per rft. = Tk. 1,614.00
(b) Fittings:
(i) 12 mm uPVC plain Tee 10 Nos. @ Tk. 17.55 each = Tk. 175.50
(ii) 12 mm uPVC plain elbow 25 Nos. @ Tk. 16.57 each = Tk. 414.25
(iii) 12 mm uPVC faucet elbow 5 Nos. @ Tk. 21.06 each = Tk. 105.30
(iv) 12 mm uPVC plain socket 6 Nos. @ Tk. 11.58 each = Tk. 69.48
(v) 12 mm uPVC thread plug 5 Nos. @ Tk. 11.11 each = Tk. 55.55
(c) Jointing & fixing materials
(i) Solvent cement for jointing 400 gm. @ Tk. 1.63 Per gm. = Tk. 652.00
(d) Labour:
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
(iii) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 4,622.08
Profit 10.00% = Tk. 462.21
Overhead 3.50% = Tk. 161.77
= Tk. 5,246.06
Add VAT with adjustment factor 1.0582 5.50% = Tk. 305.33
Grand total = Tk. 5,551.39
Rate per rft. = Tk. 46.26
Rate per rm. = Tk. 151.78

Say, Tk. 152 .00 Per rm


26.39.2 3/4" or 19 mm dia uPVC pipe for plumbing purpose
Considering 20 rft. long 3.5 Nos. pipe = 70 rft. work
Analysis of PWD SoR 2014 for Civil Works 433

The costing is based on one distribution line from upper tank to 4th & 4th floor toilet of a 5 storied building
(a) 19 mm dia uPVC pipe 70 rft. @ Tk. 23.30 Per rft. = Tk. 1,631.00
(b) Fittings:
(i) 19 mm uPVC plain Tee 5 Nos. @ Tk. 25.61 each = Tk. 128.05
(ii) 19 mm uPVC plain elbow 10 Nos. @ Tk. 20.90 each = Tk. 209.00
(iii) 19 mm uPVC plain socket 4 Nos. @ Tk. 15.18 each = Tk. 60.72
(iv) 19 x 12 mm uPVC round Tee 5 Nos. @ Tk. 28.38 each = Tk. 141.90
(v) 19 x 12 mm uPVC round elbow 10 Nos. @ Tk. 30.64 each = Tk. 306.40
(c) Jointing & fixing materials
(i) Solvent cement 50 gm. @ Tk. 1.63 Per gm. = Tk. 81.50
(d) Labour:
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(iii) Labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 3,546.57
Profit 10.00% = Tk. 354.66
Overhead 3.50% = Tk. 124.13
= Tk. 4,025.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 234.28
Grand total = Tk. 4,259.64
Rate per rft. = Tk. 60.85
Rate per rm. = Tk. 199.65

Say, Tk. 200 .00 Per rm

26.39.3 1" or 25 mm dia uPVC pipe for plumbing purpose


Considering 20 rft. long one pipe
The costing is based on one distribution line from upper tank to 5th floor toilet of a 5 storied building
(a) 25 mm dia uPVC pipe 20 rft. @ Tk. 28.08 Per rft. = Tk. 561.60
(b) Fittings:
(i) 25 x 19 mm round. Tee 2 Nos. @ Tk. 49.52 each = Tk. 99.04
(c) Jointing & fixing materials
(i) Solvent cement 25 gm. @ Tk. 1.63 Per gm. = Tk. 40.75
(d) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,085.39
Profit 10.00% = Tk. 108.54
Overhead 3.50% = Tk. 37.99
= Tk. 1,231.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 71.70
Grand total = Tk. 1,303.62
Rate per rft. = Tk. 65.18
Rate per rm. = Tk. 213.86

Say, Tk. 214 .00 Per rm

26.39.4 1.25" or 32 mm dia uPVC pipe for plumbing purpose


Considering 20 rft. long one pipe
(a) 32 mm dia uPVC pipe 20 rft. @ Tk. 34.90 Per rft. = Tk. 698.00
(b) Fittings:
(i) 32 mm uPVC plain Tee 2 Nos. @ Tk. 75.47 each = Tk. 150.94
(ii) 32 mm uPVC socket 2 Nos. @ Tk. 60.13 each = Tk. 120.26
(iii) 32 mm uPVC elbow 2 Nos. @ Tk. 59.65 each = Tk. 119.30
(c) Jointing & fixing materials
(i) Solvent cement 35 gm. @ Tk. 1.63 Per gm. = Tk. 57.05
Analysis of PWD SoR 2014 for Civil Works 434

(d) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 1,407.05
Profit 10.00% = Tk. 140.71
Overhead 3.50% = Tk. 49.25
= Tk. 1,597.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 92.95
Grand total = Tk. 1,689.96
Rate per rft. = Tk. 84.50
Rate per rm. = Tk. 277.24

Say, Tk. 277 .00 Per rm

26.39.5 1.5" or 37 mm dia uPVC pipe for plumbing purpose


Considering 20 rft. long one pipe
(a) 37 mm dia uPVC pipe 20 rft. @ Tk. 45.76 Per rft. = Tk. 915.20
(b) Fittings:
(i) 37 mm uPVC plain Tee 1 No. @ Tk. 99.51 each = Tk. 99.51
(ii) 37 mm uPVC socket 2 Nos. @ Tk. 61.59 each = Tk. 123.18
(iii) 37 mm uPVC elbow 2 Nos. @ Tk. 83.86 each = Tk. 167.72
(c) Jointing & fixing materials
(i) Solvent cement 50 gm. @ Tk. 1.63 Per gm. = Tk. 81.50
(d) Labour:
(i) a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 1,648.61
Profit 10.00% = Tk. 164.86
Overhead 3.50% = Tk. 57.70
= Tk. 1,871.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 108.90
Grand total = Tk. 1,980.07
Rate per rft. = Tk. 99.00
Rate per rm. = Tk. 324.82

Say, Tk. 325 .00 Per rm

26.39.6 60 mm dia uPVC pipe for plumbing purpose


Considering 20 rft. long one pipe
(a) 60 mm dia pipe 20 rft. @ Tk. 47.82 Per rft. = Tk. 956.40
(b) Fittings:
(i) 60 mm Tee 1 No. @ Tk. 161.04 each = Tk. 161.04
(ii) 60 mm socket 2 Nos. @ Tk. 89.83 each = Tk. 179.66
(iii) 60 mm elbow 2 Nos. @ Tk. 131.61 each = Tk. 263.22
(c) Jointing & fixing materials
(i) Solvent cement 65 gm @ Tk. 1.63 Per gm. = Tk. 105.95
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Plumber helper 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(e) Local carriage, sundries etc. L.S. = Tk. 49.00
Total = Tk. 2,086.77
Profit 10.00% = Tk. 208.68
Overhead 3.50% = Tk. 73.04
= Tk. 2,368.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 137.85
Grand total = Tk. 2,506.34
Rate per rft. = Tk. 125.32
Analysis of PWD SoR 2014 for Civil Works 435

Rate per rm. = Tk. 411.17

Say, Tk. 411 .00 Per rm

26.39.7 75 mm dia uPVC pipe for plumbing purpose


Considering 1 piece of 20 rft work
(a) 75 mm dia pipe 20 rft. @ Tk. 74.52 Per rft. = Tk. 1,490.40
(b) Fittings:
(i) 75 mm Tee 1 No. @ Tk. 188.52 each = Tk. 188.52
(ii) 75 mm socket 2 Nos. @ Tk. 120.12 each = Tk. 240.24
(iii) 75 mm elbow 2 Nos. @ Tk. 157.72 each = Tk. 315.44
(c) Jointing & fixing materials
(i) Solvent cement 70 gm @ Tk. 1.63 Per gm. = Tk. 114.10
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Plumber helper 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(e) Local carriage, sundries etc. L.S. = Tk. 49.00
Total = Tk. 2,769.20
Profit 10.00% = Tk. 276.92
Overhead 3.50% = Tk. 96.92
= Tk. 3,143.04
Add VAT with adjustment factor 1.0582 5.50% = Tk. 182.93
Grand total = Tk. 3,325.97
Rate per rft. = Tk. 166.30
Rate per rm. = Tk. 545.63

Say, Tk. 546 .00 Per rm

26.39.8 88 mm dia uPVC pipe for plumbing purpose


Considering 20 rft. long one pipe
(a) 88 mm dia pipe 20 rft. @ Tk. 68.57 Per rft. = Tk. 1,371.40
(b) Fittings:
(i) 88 mm Tee 1 No. @ Tk. 411.06 each = Tk. 411.06
(ii) 88 mm socket 2 Nos. @ Tk. 200.91 each = Tk. 401.82
(iii) 88 mm elbow 2 Nos. @ Tk. 316.22 each = Tk. 632.44
(c) Jointing & fixing materials
(i) Solvent cement 100 gm @ Tk. 1.63 Per gm. = Tk. 163.00
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Plumber helper 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(e) Local carriage, sundries etc. L.S. = Tk. 68.60
Total = Tk. 3,419.82
Profit 10.00% = Tk. 341.98
Overhead 3.50% = Tk. 119.69
= Tk. 3,881.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 225.91
Grand total = Tk. 4,107.40
Rate per rft. = Tk. 205.37
Rate per rm. = Tk. 673.82

Say, Tk. 674 .00 Per rm

26.39.9 114 mm dia uPVC pipe for plumbing purpose


Considering 20 rft. long one pipe
(a) 114 mm dia pipe 20 rft. @ Tk. 85.76 Per rft. = Tk. 1,715.20
(b) Fittings:
(i) 114 mm Tee 1 No. @ Tk. 753.93 each = Tk. 753.93
Analysis of PWD SoR 2014 for Civil Works 436

(ii) 114 mm socket 2 Nos. @ Tk. 290.63 each = Tk. 581.26


(iii) 114 mm elbow 2 Nos. @ Tk. 476.13 each = Tk. 952.26
(c) Jointing & fixing materials
(i) Solvent cement 140 gm @ Tk. 1.63 Per gm. = Tk. 228.20
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Plumber helper 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(e) Local carriage, sundries etc. L.S. = Tk. 68.60
Total = Tk. 4,670.95
Profit 10.00% = Tk. 467.10
Overhead 3.50% = Tk. 163.48
= Tk. 5,301.53
Add VAT with adjustment factor 1.0582 5.50% = Tk. 308.55
Grand total = Tk. 5,610.08
Rate per rft. = Tk. 280.50
Rate per rm. = Tk. 920.32

Say, Tk. 920 .00 Per rm

Item No.- 26.40


26.40.1 1/2" or 12 mm dia CPVC pipe for plumbing purpose
Considering 20 rft. long 6 Nos. pipe = 120 rft. work
(a) 12 mm dia CPVC pipe 120 rft. @ Tk. 33.91 Per rft. = Tk. 4,069.20
(b) Fittings:
(i) 12 mm CPVC plain Tee 10 Nos. @ Tk. 29.76 each = Tk. 297.60
(ii) 12 mm CPVC plain elbow 25 Nos. @ Tk. 24.42 each = Tk. 610.50
(iii) 12 mm CPVC faucet elbow 5 Nos. @ Tk. 28.73 each = Tk. 143.65
(iv) 12 mm CPVC plain socket 6 Nos. @ Tk. 19.41 each = Tk. 116.46
(v) 12 mm CPVC thread plug 5 Nos. @ Tk. 13.02 each = Tk. 65.10
(c) Jointing & fixing materials
(i) Solvent cement for jointing 400 gm. @ Tk. 1.63 Per gm. = Tk. 652.00
(d) Labour:
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
(iii) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 7,490.51
Profit 10.00% = Tk. 749.05
Overhead 3.50% = Tk. 262.17
= Tk. 8,501.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 494.81
Grand total = Tk. 8,996.54
Rate per rft. = Tk. 74.97
Rate per rm. = Tk. 245.98

Say, Tk. 246 .00 Per rm

26.40.2 3/4" or 19 mm dia CPVC pipe for plumbing purpose


Considering 20 rft. long 3.5 Nos. pipe = 70 rft. work
The costing is based on one distribution line from upper tank to 4th & 4th floor toilet of a 5 storied building
(a) 19 mm dia CPVC pipe 70 rft. @ Tk. 41.81 Per rft. = Tk. 2,926.70
(b) Fittings:
(i) 19 mm CPVC plain Tee 5 Nos. @ Tk. 64.61 each = Tk. 323.05
(ii) 19 mm CPVC plain elbow 10 Nos. @ Tk. 48.59 each = Tk. 485.90
(iii) 19 mm CPVC plain socket 4 Nos. @ Tk. 32.37 each = Tk. 129.48
(iv) 19 x 12 mm CPVC round Tee 5 Nos. @ Tk. 58.57 each = Tk. 292.85
(v) 19 x 12 mm CPVC round elbow 10 Nos. @ Tk. 88.47 each = Tk. 884.70
(c) Jointing & fixing materials
Analysis of PWD SoR 2014 for Civil Works 437

(i) Solvent cement 50 gm. @ Tk. 1.63 Per gm. = Tk. 81.50
(d) Labour:
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(iii) Labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 6,112.18
Profit 10.00% = Tk. 611.22
Overhead 3.50% = Tk. 213.93
= Tk. 6,937.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 403.76
Grand total = Tk. 7,341.09
Rate per rft. = Tk. 104.87
Rate per rm. = Tk. 344.08

Say, Tk. 344 .00 Per rm

26.40.3 1" or 25 mm dia CPVC pipe for plumbing purpose


Considering 20 rft. long one pipe
The costing is based on one distribution line from upper tank to 5th floor toilet of a 5 storied building
(a) 25 mm dia CPVC pipe 20 rft. @ Tk. 55.94 Per rft. = Tk. 1,118.80
(b) Fittings:
(i) 25 x 19 mm round. Tee 2 Nos. @ Tk. 123.68 each = Tk. 247.36
(c) Jointing & fixing materials
(i) Solvent cement 25 gm. @ Tk. 1.63 Per gm. = Tk. 40.75
(d) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 1,790.91
Profit 10.00% = Tk. 179.09
Overhead 3.50% = Tk. 62.68
= Tk. 2,032.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 118.30
Grand total = Tk. 2,150.98
Rate per rft. = Tk. 107.55
Rate per rm. = Tk. 352.87

Say, Tk. 353 .00 Per rm

26.40.4 1.25" or 32 mm dia CPVC pipe for plumbing purpose


Considering 20 rft. long one pipe
(a) 32 mm dia CPVC pipe 20 rft. @ Tk. 74.51 Per rft. = Tk. 1,490.20
(b) Fittings:
(i) 32 mm CPVC plain Tee 2 Nos. @ Tk. 193.15 each = Tk. 386.30
(ii) 32 mm CPVC socket 2 Nos. @ Tk. 91.04 each = Tk. 182.08
(iii) 32 mm CPVC elbow 2 Nos. @ Tk. 152.32 each = Tk. 304.64
(c) Jointing & fixing materials
(i) Solvent cement 35 gm. @ Tk. 1.63 Per gm. = Tk. 57.05
(d) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 2,681.77
Profit 10.00% = Tk. 268.18
Overhead 3.50% = Tk. 93.86
= Tk. 3,043.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 177.15
Grand total = Tk. 3,220.96
Analysis of PWD SoR 2014 for Civil Works 438

Rate per rft. = Tk. 161.05


Rate per rm. = Tk. 528.41

Say, Tk. 528 .00 Per rm

26.40.5 1.5" or 37 mm dia CPVC pipe for plumbing purpose


Considering 20 rft. long one pipe
(a) 37 mm dia CPVC pipe 20 rft. @ Tk. 98.79 Per rft. = Tk. 1,975.80
(b) Fittings:
(i) 37 mm CPVC plain Tee 1 No. @ Tk. 282.84 each = Tk. 282.84
(ii) 37 mm CPVC socket 2 Nos. @ Tk. 140.40 each = Tk. 280.80
(iii) 37 mm CPVC elbow 2 Nos. @ Tk. 207.19 each = Tk. 414.38
(c) Jointing & fixing materials
(i) Solvent cement 50 gm. @ Tk. 1.63 Per gm. = Tk. 81.50
(d) Labour:
(i) a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 3,296.82
Profit 10.00% = Tk. 329.68
Overhead 3.50% = Tk. 115.39
= Tk. 3,741.89
Add VAT with adjustment factor 1.0582 5.50% = Tk. 217.78
Grand total = Tk. 3,959.67
Rate per rft. = Tk. 197.98
Rate per rm. = Tk. 649.57
Say, Tk. 650 .00 Per rm

26.40.6 50 mm dia CPVC pipe for plumbing purpose


Considering 20 rft. long one pipe
(a) 50 mm dia pipe 20 rft. @ Tk. 142.34 Per rft. = Tk. 2,846.80
(b) Fittings:
(i) 50 mm Tee 1 No. @ Tk. 586.60 each = Tk. 586.60
(ii) 50 mm socket 2 Nos. @ Tk. 286.67 each = Tk. 573.34
(iii) 50 mm elbow 2 Nos. @ Tk. 466.09 each = Tk. 932.18
(c) Jointing & fixing materials
(i) Solvent cement 65 gm @ Tk. 1.63 Per gm. = Tk. 105.95
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Plumber helper 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(e) Local carriage, sundries etc. L.S. = Tk. 49.00
Total = Tk. 5,465.37
Profit 10.00% = Tk. 546.54
Overhead 3.50% = Tk. 191.29
= Tk. 6,203.20
Add VAT with adjustment factor 1.0582 5.50% = Tk. 361.03
Grand total = Tk. 6,564.23
Rate per rft. = Tk. 328.21
Rate per rm. = Tk. 1,076.86
Say, Tk. 1,077 .00 Per rm
Item No.- 26.41
26.41.1 1/2" or 12 mm dia ABS pipe for plumbing purpose
Considering 20 rft. long 6 Nos. pipe = 120 rft. work
(a) 12 mm dia ABS pipe 120 rft. @ Tk. 55.39 Per rft. = Tk. 6,646.80
(b) Fittings:
(i) 12 mm ABS plain Tee 10 Nos. @ Tk. 40.83 each = Tk. 408.30
(ii) 12 mm ABS plain elbow 25 Nos. @ Tk. 34.66 each = Tk. 866.50
(iii) 12 mm ABS faucet elbow 5 Nos. @ Tk. 34.66 each = Tk. 173.30
Analysis of PWD SoR 2014 for Civil Works 439

(iv) 12 mm ABS plain socket 6 Nos. @ Tk. 24.46 each = Tk. 146.76
(v) 12 mm ABS thread plug 5 Nos. @ Tk. 270.82 each = Tk. 1,354.10
(c) Jointing & fixing materials
(i) Adhesive solution for jointing 400 gm. @ Tk. 3.09 Per gm. = Tk. 1,236.00
(d) Labour:
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
(iii) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 12,367.76
Profit 10.00% = Tk. 1,236.78
Overhead 3.50% = Tk. 432.87
= Tk. 14,037.41
Add VAT with adjustment factor 1.0582 5.50% = Tk. 816.99
Grand total = Tk. 14,854.40
Rate per rft. = Tk. 123.79
Rate per rm. = Tk. 406.15

Say, Tk. 406 .00 Per rm

26.41.2 3/4" or 19 mm dia ABS pipe for plumbing purpose


Considering 20 rft. long 3.5 Nos. pipe = 70 rft. work
The costing is based on one distribution line from upper tank to 4th & 4th floor toilet of a 5 storied building
(a) 19 mm dia ABS pipe 70 rft. @ Tk. 63.77 Per rft. = Tk. 4,463.90
(b) Fittings:
(i) 19 mm ABS plain Tee 5 Nos. @ Tk. 82.36 each = Tk. 411.80
(ii) 19 mm ABS plain elbow 10 Nos. @ Tk. 64.30 each = Tk. 643.00
(iii) 19 mm ABS plain socket 4 Nos. @ Tk. 41.76 each = Tk. 167.04
(iv) 19 x 12 mm ABS round Tee 5 Nos. @ Tk. 24.30 each = Tk. 121.50
(v) 19 x 12 mm ABS round elbow 10 Nos. @ Tk. 139.72 each = Tk. 1,397.20
(c) Jointing & fixing materials
(i) Adhesive solution for jointing 50 gm. @ Tk. 3.09 Per gm. = Tk. 154.50
(d) Labour:
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(iii) Labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 8,346.94
Profit 10.00% = Tk. 834.69
Overhead 3.50% = Tk. 292.14
= Tk. 9,473.77
Add VAT with adjustment factor 1.0582 5.50% = Tk. 551.38
Grand total = Tk. 10,025.15
Rate per rft. = Tk. 143.22
Rate per rm. = Tk. 469.90
Say, Tk. 470 .00 Per rm
26.41.3 1" or 25 mm dia ABS pipe for plumbing purpose
Considering 20 rft. long one pipe
The costing is based on one distribution line from upper tank to 5th floor toilet of a 5 storied building
(a) 25 mm dia ABS pipe 20 rft. @ Tk. 84.21 Per rft. = Tk. 1,684.20
(b) Fittings:
(i) 25 x 19 mm round. Tee 2 Nos. @ Tk. 40.74 each = Tk. 81.48
(c) Jointing & fixing materials
(i) Adhesive solution for jointing 25 gm. @ Tk. 3.09 Per gm. = Tk. 77.25
(d) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 2,226.93
Analysis of PWD SoR 2014 for Civil Works 440

Profit 10.00% = Tk. 222.69


Overhead 3.50% = Tk. 77.94
= Tk. 2,527.56
Add VAT with adjustment factor 1.0582 5.50% = Tk. 147.11
Grand total = Tk. 2,674.67
Rate per rft. = Tk. 133.73
Rate per rm. = Tk. 438.77

Say, Tk. 439 .00 Per rm

26.41.4 1.25" or 32 mm dia ABS pipe for plumbing purpose


Considering 20 rft. long one pipe
(a) 32 mm dia ABS pipe 20 rft. @ Tk. 125.99 Per rft. = Tk. 2,519.80
(b) Fittings:
(i) 32 mm ABS plain Tee 2 Nos. @ Tk. 257.86 each = Tk. 515.72
(ii) 32 mm ABS socket 2 Nos. @ Tk. 67.84 each = Tk. 135.68
(iii) 32 mm ABS elbow 2 Nos. @ Tk. 208.07 each = Tk. 416.14
(c) Jointing & fixing materials
(i) Adhesive solution for jointing 35 gm. @ Tk. 3.09 Per gm. = Tk. 108.15
(d) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 3,956.99
Profit 10.00% = Tk. 395.70
Overhead 3.50% = Tk. 138.49
= Tk. 4,491.18
Add VAT with adjustment factor 1.0582 5.50% = Tk. 261.39
Grand total = Tk. 4,752.57
Rate per rft. = Tk. 237.63
Rate per rm. = Tk. 779.66

Say, Tk. 780 .00 Per rm

26.41.5 1.5" or 37 mm dia ABS pipe for plumbing purpose


Considering 20 rft. long one pipe
(a) 37 mm dia ABS pipe 20 rft. @ Tk. 162.49 Per rft. = Tk. 3,249.80
(b) Fittings:
(i) 37 mm ABS plain Tee 1 No. @ Tk. 364.54 each = Tk. 364.54
(ii) 37 mm ABS socket 2 Nos. @ Tk. 180.70 each = Tk. 361.40
(iii) 37 mm ABS elbow 2 Nos. @ Tk. 297.92 each = Tk. 595.84
(c) Jointing & fixing materials
(i) Adhesive solution for jointing 50 gm. @ Tk. 3.09 Per gm. = Tk. 154.50
(d) Labour:
(i) a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 4,987.58
Profit 10.00% = Tk. 498.76
Overhead 3.50% = Tk. 174.57
= Tk. 5,660.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 329.47
Grand total = Tk. 5,990.38
Rate per rft. = Tk. 299.52
Rate per rm. = Tk. 982.73

Say, Tk. 983 .00 Per rm

26.41.6 50 mm dia ABS pipe for plumbing purpose


Analysis of PWD SoR 2014 for Civil Works 441

Considering 20 rft. long one pipe


(a) 50 mm dia pipe 20 rft. @ Tk. 263.86 Per rft. = Tk. 5,277.20
(b) Fittings:
(i) 50 mm Tee 1 No. @ Tk. 798.83 each = Tk. 798.83
(ii) 50 mm socket 2 Nos. @ Tk. 393.72 each = Tk. 787.44
(iii) 50 mm elbow 2 Nos. @ Tk. 634.92 each = Tk. 1,269.84
(c) Jointing & fixing materials
(i) Adhesive solution for jointing 65 gm @ Tk. 3.09 Per gm. = Tk. 200.85
(d) Labour:
(i) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(ii) Plumber helper 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(e) Local carriage, sundries etc. L.S. = Tk. 49.00
Total = Tk. 8,754.66
Profit 10.00% = Tk. 875.47
Overhead 3.50% = Tk. 306.41
= Tk. 9,936.54
Add VAT with adjustment factor 1.0582 5.50% = Tk. 578.32
Grand total = Tk. 10,514.86
Rate per rft. = Tk. 525.74
Rate per rm. = Tk. 1,724.95

Say, Tk. 1,725 .00 Per rm


Item No.- 26.42
Supplying, fitting & laying pipes of following type for depth to invert:
26.42.1 100 mm dia HCI
Considering 3 x 1.83 m= 5.49 m work
1. 100 mm dia 1.83 m long HCI pipe: 3 Nos. @ Tk. 2,095.26 each = Tk. 6,285.78
2. Jointing materials
(a) Hem 1.35 sqm. @ Tk. 27.36 Per sqm.. = Tk. 36.94
(b) Cement mortar (1:4)
(i) Cement 0.2 bag. @ Tk. 440.00 Per bag. = Tk. 88.00
(ii) Sand (F.M. 1.2) 0.52 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.84
3. Excavation 72.75 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 165.26
4. Bedding by sand (F.M. 1.2) 12.78 cft. @ Tk. 1,700.00 Per cft. = Tk. 217.26
5. Labour:
(a) Plumber 0.2 No. @ Tk. 440.00 each = Tk. 88.00
(b) Skilled labour 0.4 No. @ Tk. 303.00 each = Tk. 121.20
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 7,133.78
Profit 10.00% = Tk. 713.38
Overhead 3.50% = Tk. 249.68
= Tk. 8,096.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 471.24
Grand total = Tk. 8,568.08
Rate per rm. = Tk. 1,560.67
Say, Tk. 1,561 .00 Per rm
26.42.2 150 mm dia HCI
Considering 3 x 1.83 m =5.49 m work
1. 150 mm dia 1.8 m long HCI pipe: 3 Nos. @ Tk. 2,899.65 each = Tk. 8,698.95
2. Jointing materials
(a) Hem 1.35 sqm. @ Tk. 27.36 Per sqm. = Tk. 36.94
(b) Cement mortar (1:4)
(i) Cement 0.20 bag. @ Tk. 440.00 Per bag. = Tk. 88.00
(ii) Sand (F.M. 1.2) 0.52 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.84
3. Excavation 64.63 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 146.81
4. Bedding by sand (F.M. 1.2) 10.95 cft. @ Tk. 1,700.00 Per cft. = Tk. 186.15
5. Labour:
Analysis of PWD SoR 2014 for Civil Works 442

(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00


(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 9,549.69
Profit 10.00% = Tk. 954.97
Overhead 3.50% = Tk. 334.24
= Tk. 10,838.90
Add VAT with adjustment factor 1.0582 5.50% = Tk. 630.83
Grand total = Tk. 11,469.73
Rate per rm. = Tk. 2,089.20

Say, Tk. 2,089 .00 Per rm

Item No.- 26.43


26.43.1 100 mm dia uPVC
Considering 20 rft. long 1 No. pipe
(a) 100 mm dia 20'-0" long uPVC pipe: 20 rft. @ Tk. 104.19 Per rft. = Tk. 2,083.80
(b) Jointing materials
(i) Solvent cement 54 gm @ Tk. 1.63 Per gm. = Tk. 88.02
(c) Excavation 26.13 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 59.36
(d) Bedding by sand (F.M. 1.2) 9.88 cft. @ Tk. 1,700.00 Per cft. = Tk. 167.96
(e) Labour:
(i) Plumber 0.2 No. @ Tk. 440.00 each = Tk. 88.00
(ii) Skilled labour 0.4 No. @ Tk. 303.00 each = Tk. 121.20
(iii) Ordinary labour 0.8 No. @ Tk. 245.00 each = Tk. 196.00
Total = Tk. 2,804.34
Profit 10.00% = Tk. 280.43
Overhead 3.50% = Tk. 98.15
= Tk. 3,182.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 185.25
Grand total = Tk. 3,368.17
Rate per rft. = Tk. 168.41
Rate Per rm. = Tk. 552.55

Say, Tk. 553 .00 Per rm

26.43.2 150 mm dia uPVC


Considering 20 rft. long 1 No. pipe
(a) 150 mm dia 20'-0" long uPVC pipe: 20 rft. @ Tk. 135.99 Per rft. = Tk. 2,719.80
(b) Jointing materials
(i) Solvent cement 120 gm @ Tk. 1.63 Per gm. = Tk. 195.60
(c) Excavation 72.04 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 163.64
(d) Bedding by sand (F.M. 1.2) 12.36 cft. @ Tk. 1,700.00 Per cft. = Tk. 210.12
(e) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 3,673.16
Profit 10.00% = Tk. 367.32
Overhead 3.50% = Tk. 128.56
= Tk. 4,169.04
Add VAT with adjustment factor 1.0582 5.50% = Tk. 242.64
Grand total = Tk. 4,411.68
Rate per rft. = Tk. 220.58
Rate Per rm. = Tk. 723.72

Say, Tk. 724 .00 Per rm


Analysis of PWD SoR 2014 for Civil Works 443

Item No.- 26.44


26.44.1 150 mm dia RCC pipe made of stone chips, thickness 40 mm
Considering 1.83 m long 3 Nos. pipe = 5.49 m work
1. 150 mm dia 1.83 m long RCC pipe: 3 Nos. @ Tk. 1,017.00 each = Tk. 3,051.00
2. Jointing materials
(a) Hem 1.35 sqm. @ Tk. 27.36 Per sqm.. = Tk. 36.94
(b) Cement mortar (1:4)
(i) Cement 0.2 bag. @ Tk. 440.00 Per bag. = Tk. 88.00
(ii) Sand (F.M. 1.2) 0.52 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.84
3. excavation 72.75 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 165.26
4. Bedding by sand (F.M. 1.2) 12.78 cft. @ Tk. 1,700.00 Per cft. = Tk. 217.26
5. Labour:
(a) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 3,951.30
Profit 10.00% = Tk. 395.13
Overhead 3.50% = Tk. 138.30
= Tk. 4,484.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 261.02
Grand total = Tk. 4,745.75
Rate per rm. = Tk. 864.44

Say, Tk. 864 .00 Per rm

26.44.2 225 mm dia RCC pipe made of stone chips, thickness 40 mm


Considering 1.83 m long 3 Nos. pipe = 5.49 m work
1. 225 mm dia 1.83 m long RCC pipe: 3 Nos. @ Tk. 1,575.00 each = Tk. 4,725.00
2. Jointing materials
(a) Hem 1.75 sqm. @ Tk. 27.36 Per sqm.. = Tk. 47.88
(b) Cement mortar (1:4)
(i) Cement 0.31 bag. @ Tk. 440.00 Per bag. = Tk. 136.40
(ii) Sand (F.M. 1.2) 0.8 cft. @ Tk. 1,700.00 Per % cft. = Tk. 13.60
3. Excavation 137.73 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 312.86
4. Bedding by sand (F.M. 1.2) 18.0 cft. @ Tk. 1,700.00 Per cft. = Tk. 306.00
5. Babour:
(a) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 6,158.24
Profit 10.00% = Tk. 615.82
Overhead 3.50% = Tk. 215.54
= Tk. 6,989.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 406.80
Grand total = Tk. 7,396.40
Rate per rm. = Tk. 1,347.25

Say, Tk. 1,347 .00 Per rm

26.44.3 300 mm dia RCC pipe made of stone chips, thickness 50 mm


Considering 1.83 m long 3 Nos. pipe = 5.49 m work
1. 300 mm dia 1.83 m long RCC pipe: 3 Nos. @ Tk. 2,743.00 each = Tk. 8,229.00
2. Jointing materials
(a) Hem 2.19 sqm. @ Tk. 27.36 Per sqm.. = Tk. 59.92
(b) Cement mortar (1:4)
(i) Cement 0.4 bag. @ Tk. 440.00 Per bag. = Tk. 176.00
Analysis of PWD SoR 2014 for Civil Works 444

(ii) Sand (F.M. 1.2) 1 cft. @ Tk. 1,700.00 Per % cft. = Tk. 17.00
3. Excavation 175.16 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 397.89
4. Bedding by sand (F.M. 1.2) 21.96 cft. @ Tk. 1,700.00 Per cft. = Tk. 373.32
5. Labour:
(a) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(b) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(c) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 10,114.63
Profit 10.00% = Tk. 1,011.46
Overhead 3.50% = Tk. 354.01
= Tk. 11,480.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 668.15
Grand total = Tk. 12,148.25
Rate per rm. = Tk. 2,212.80

Say, Tk. 2,213 .00 Per rm

26.44.4 375 mm dia RCC pipe made of stone chips, thickness 50 mm


Considering 1.83 m long 3 Nos. pipe = 5.49 m work
1. 375 mm dia 1.83 m long RCC pipe: 3 Nos. @ Tk. 3,580.00 each = Tk. 10,740.00
2. Jointing materials
(a) Hem 2.73 sqm. @ Tk. 27.36 Per sqm.. = Tk. 74.69
(b) Cement mortar (1:4)
(i) Cement 0.47 bag. @ Tk. 440.00 Per bag. = Tk. 206.80
(ii) Sand (F.M. 1.2) 1.18 cft. @ Tk. 1,700.00 Per % cft. = Tk. 20.06
3. Excavation 217.89 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 494.95
4. Bedding by sand (F.M. 1.2) 26.3 cft. @ Tk. 1,700.00 Per cft. = Tk. 447.10
5. Labour:
(a) Plumber 0.5 No. @ Tk. 440.00 each = Tk. 220.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(c) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 12,996.60
Profit 10.00% = Tk. 1,299.66
Overhead 3.50% = Tk. 454.88
= Tk. 14,751.14
Add VAT with adjustment factor 1.0582 5.50% = Tk. 858.53
Grand total = Tk. 15,609.67
Rate per rm. = Tk. 2,843.29
Say, Tk. 2,843 .00 Per rm
Item No.- 26.45
4" or 110 mm dia uPVC 8 bar waste pipe
Considering 120 rft. work (80' + 40') work
The costing of waste water down pipe - fittings based one one main line connected
from 5th floor to ground floor of a 5 storied building
(a) 110 mm dia uPVC pipe 80 rft. @ Tk. 82.23 Per rft. = Tk. 6,578.40
(b) 32 mm dia uPVC pipe 40 rft. @ Tk. 34.90 Per rft. = Tk. 1,396.00
(c) Fittings:
(i) 4" dia uPVC door Tee (back) 5 Nos. @ Tk. 400.73 each = Tk. 2,003.65
(ii) 4" dia uPVC plain bend 900 1 No. @ Tk. 207.72 each = Tk. 207.72
(iii) 4" dia uPVC long trap 5 Nos. @ Tk. 414.83 each = Tk. 2,074.15
(iv) 4" dia uPVC round grating 5 Nos. @ Tk. 319.79 each = Tk. 1,598.95
(v) 4" dia uPVC vent cowl 1 No. @ Tk. 108.29 each = Tk. 108.29
(vi) 1.25" dia uPVC plain bend 900 5 Nos. @ Tk. 62.29 each = Tk. 311.45
(d) Jointing & fixing materials
(i) Solvent cement for jointing 600 gm. @ Tk. 1.63 Per gm. = Tk. 978.00
(e) Labour:
(i) Plumber 2 Nos. @ Tk. 440.00 each = Tk. 880.00
Analysis of PWD SoR 2014 for Civil Works 445

(ii) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00


(iii) Ordinary labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(f) Scaffolding and sundries L.S. = Tk. 269.50
Total = Tk. 17,502.11
Profit 10.00% = Tk. 1,750.21
Overhead 3.50% = Tk. 612.57
= Tk. 19,864.89
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,156.16
Grand total = Tk. 21,021.05
Rate per rft. = Tk. 175.18
Rate per rm. = Tk. 574.77

Say, Tk. 575 .00 Per rm


Item No.- 26.46
26.46.1 150 mm dia uPVC pipe for underground laying
Considering 20 rft. long one pipe
(a) 150 mm uPVC pipe: 20 rft. @ Tk. 135.99 Per rft. = Tk. 2,719.80
(b) Jointing materials
(i) Solvent cement 50 gm @ Tk. 1.63 Per gm. = Tk. 81.50
(c) Excavation 62.5 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 141.97
(d) Bedding by sand (F.M. 0.8) 38.8 cft. @ Tk. 1,419.46 Per cft. = Tk. 550.75
(e) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 3,878.02
Profit 10.00% = Tk. 387.80
Overhead 3.50% = Tk. 135.73
= Tk. 4,401.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 256.17
Grand total = Tk. 4,657.72
Rate per rft. = Tk. 232.89
Rate Per rm. = Tk. 764.11

Say, Tk. 764 .00 Per rm

26.46.2 200 mm dia uPVC for underground laying


Considering 20 rft. long one pipe
(a) 200 mm uPVC pipe: 20 rft. @ Tk. 289.14 Per rft. = Tk. 5,782.80
(b) Jointing materials
(i) Solvent cement 50 gm @ Tk. 1.63 Per gm. = Tk. 81.50
(c) Excavation 87.5 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 198.76
(d) Bedding by sand (F.M. 0.8) 67.5 cft. @ Tk. 1,419.46 Per cft. = Tk. 958.14
(e) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 7,405.20
Profit 10.00% = Tk. 740.52
Overhead 3.50% = Tk. 259.18
= Tk. 8,404.90
Add VAT with adjustment factor 1.0582 5.50% = Tk. 489.17
Grand total = Tk. 8,894.07
Rate per rft. = Tk. 444.70
Rate Per rm. = Tk. 1,459.06
Say, Tk. 1,459 .00 Per rm
Analysis of PWD SoR 2014 for Civil Works 446

26.46.3 250 mm dia uPVC for underground laying


Considering 20 rft. long one pipe
(a) 250 mm uPVC pipe: 20 rft. @ Tk. 419.11 Per rft. = Tk. 8,382.20
(b) Jointing materials
(i) Solvent cement 330 gm @ Tk. 1.63 Per gm. = Tk. 537.90
(c) Excavation 87.5 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 198.76
(d) Bedding by sand (F.M. 0.8) 52.5 cft. @ Tk. 1,419.46 Per cft. = Tk. 745.22
(e) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 10,248.08
Profit 10.00% = Tk. 1,024.81
Overhead 3.50% = Tk. 358.68
= Tk. 11,631.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 676.97
Grand total = Tk. 12,308.54
Rate per rft. = Tk. 615.43
Rate Per rm. = Tk. 2,019.23
Say, Tk. 2,019 .00 Per rm

26.46.4 uPVC waste pipe 280 mm dia wall thickness 6.9 mm - 8.6 mm for underground laying.
Considering 20 rft. long one pipe
(a) 280 mm uPVC pipe: 20 rft. @ Tk. 525.55 Per rft. = Tk. 10,511.00
(b) Jointing materials
(i) Solvent cement 330 gm @ Tk. 1.63 Per gm. = Tk. 537.90
(c) Excavation 87.5 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 198.76
(d) Bedding by sand (F.M. 0.8) 52.5 cft. @ Tk. 1,419.46 Per cft. = Tk. 745.22
(e) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 12,499.38
Profit 10.00% = Tk. 1,249.94
Overhead 3.50% = Tk. 437.48
= Tk. 14,186.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 825.69
Grand total = Tk. 15,012.49
Rate per rft. = Tk. 750.62
Rate Per rm. = Tk. 2,462.78
Say, Tk. 2,463 .00 Per rm

26.46.5 uPVC waste pipe 315 mm dia wall thickness 7.7 mm - 9.7 mm for underground laying
Considering 20 rft. long one pipe
(a) 315 mm uPVC pipe: 20 rft. @ Tk. 755.23 Per rft. = Tk. 15,104.60
(b) Jointing materials
(i) Solvent cement 330 gm @ Tk. 1.63 Per gm. = Tk. 537.90
(c) Excavation 87.5 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 198.76
(d) Bedding by sand (F.M. 0.8) 52.5 cft. @ Tk. 1,419.46 Per cft. = Tk. 745.22
(e) Labour:
(i) Plumber 0.25 No. @ Tk. 440.00 each = Tk. 110.00
(ii) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 17,092.98
Profit 10.00% = Tk. 1,709.30
Overhead 3.50% = Tk. 598.25
= Tk. 19,400.53
Analysis of PWD SoR 2014 for Civil Works 447

Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,129.13


Grand total = Tk. 20,529.66
Rate per rft. = Tk. 1,026.48
Rate Per rm. = Tk. 3,367.88

Say, Tk. 3,368 .00 Per rm

Item No.- 26.47


Supplying, fitting-fixing of G.I. Union of following sizes:
26.47.1 12 mm dia G.I. Union
Considering 1 No. of fixture
(a) 12 mm dia G.I. Union 1 No. @ Tk. 40.00 each = Tk. 40.00
(b) Fitting fixing materials:
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.075 No. @ Tk. 303.00 each = Tk. 22.73
(iii) Ordinary labour 0.05 No. @ Tk. 245.00 each = Tk. 12.25
Total = Tk. 86.94
Profit 10.00% = Tk. 8.69
Overhead 3.50% = Tk. 3.04
= Tk. 98.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5.74
Grand total = Tk. 104.41
Rate per No. = Tk. 104.41

Say, Tk. 104 .00 each

26.47.2 20 mm dia G.I. Union


Considering 1 No. of fixture
(a) 20 mm dia G.I. Union 1 No. @ Tk. 60.00 each = Tk. 60.00
(b) Fitting fixing materials:
(i) Teflon tape 0.8 rft. @ Tk. 1.82 Per rft. = Tk. 1.46
(c) Labour:
(i) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(ii) Skilled labour 0.08 No. @ Tk. 303.00 each = Tk. 24.24
(iii) Ordinary labour 0.06 No. @ Tk. 245.00 each = Tk. 14.70
Total = Tk. 113.60
Profit 10.00% = Tk. 11.36
Overhead 3.50% = Tk. 3.98
= Tk. 128.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 7.50
Grand total = Tk. 136.44
Rate per No. = Tk. 136.44

Say, Tk. 136 .00 each

26.47.3 25 mm dia G.I. Union


Considering 1 No. of fixture
(a) 25 mm dia G.I. Union 1 No. @ Tk. 72.00 each = Tk. 72.00
(b) Fitting fixing materials:
(i) Teflon tape 1.05 rft. @ Tk. 1.82 Per rft. = Tk. 1.91
(c) Labour:
(i) Plumber 0.04 No. @ Tk. 440.00 each = Tk. 17.60
(ii) Skilled labour 0.09 No. @ Tk. 303.00 each = Tk. 27.27
(iii) Ordinary labour 0.07 No. @ Tk. 245.00 each = Tk. 17.15
Total = Tk. 135.93
Analysis of PWD SoR 2014 for Civil Works 448

Profit 10.00% = Tk. 13.59


Overhead 3.50% = Tk. 4.76
= Tk. 154.28
Add VAT with adjustment factor 1.0582 5.50% = Tk. 8.98
Grand total = Tk. 163.26
Rate per No. = Tk. 163.26

Say, Tk. 163 .00 each

26.47.4 32 mm dia G.I. Union


Considering 1 No. of fixture
(a) 32 mm dia G.I. Union 1 No. @ Tk. 95.00 each = Tk. 95.00
(b) Fitting fixing materials:
(i) Teflon tape 1.3 rft. @ Tk. 1.82 Per rft. = Tk. 2.37
(c) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
(iii) Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 174.17
Profit 10.00% = Tk. 17.42
Overhead 3.50% = Tk. 6.10
= Tk. 197.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 11.51
Grand total = Tk. 209.20
Rate per No. = Tk. 209.20

Say, Tk. 209 .00 each

26.47.5 40 mm dia G.I. Union


Considering 1 No. of fixture
(a) 40 mm dia G.I. Union 1 No. @ Tk. 140.00 each = Tk. 140.00
(b) Fitting fixing materials:
(i) Teflon tape 1.58 rft. @ Tk. 1.82 Per rft. = Tk. 2.88
(c) Labour:
(i) Plumber 0.06 No. @ Tk. 440.00 each = Tk. 26.40
(ii) Skilled labour 0.11 No. @ Tk. 303.00 each = Tk. 33.33
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 251.61
Profit 10.00% = Tk. 25.16
Overhead 3.50% = Tk. 8.81
= Tk. 285.58
Add VAT with adjustment factor 1.0582 5.50% = Tk. 16.62
Grand total = Tk. 302.20
Rate per No. = Tk. 302.20

Say, Tk. 302 .00 each

26.47.6 50 mm dia G.I. Union


Considering 1 No. of fixture
(a) 50 mm dia G.I. Union 1 No. @ Tk. 190.00 each = Tk. 190.00
(b) Fitting fixing materials:
(i) Teflon tape 2.05 rft. @ Tk. 1.82 Per rft. = Tk. 3.73
(c) Labour:
(i) Plumber 0.07 No. @ Tk. 440.00 each = Tk. 30.80
(ii) Skilled labour 0.12 No. @ Tk. 303.00 each = Tk. 36.36
(iii) Ordinary labour 0.15 No. @ Tk. 245.00 each = Tk. 36.75
Total = Tk. 297.64
Analysis of PWD SoR 2014 for Civil Works 449

Profit 10.00% = Tk. 29.76


Overhead 3.50% = Tk. 10.42
= Tk. 337.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.66
Grand total = Tk. 357.48
Rate per No. = Tk. 357.48

Say, Tk. 357 .00 each

26.47.7 62 mm dia G.I. Union


Considering 1 No. of fixture
(a) 62 mm dia G.I. Union 1 No. @ Tk. 420.00 each = Tk. 420.00
(b) Fitting fixing materials:
(i) Teflon tape 2.62 rft. @ Tk. 1.82 Per rft. = Tk. 4.77
(c) Labour:
(i) Plumber 0.09 No. @ Tk. 440.00 each = Tk. 39.60
(ii) Skilled labour 0.14 No. @ Tk. 303.00 each = Tk. 42.42
(iii) Ordinary labour 0.17 No. @ Tk. 245.00 each = Tk. 41.65
Total = Tk. 548.44
Profit 10.00% = Tk. 54.84
Overhead 3.50% = Tk. 19.20
= Tk. 622.48
Add VAT with adjustment factor 1.0582 5.50% = Tk. 36.23
Grand total = Tk. 658.71
Rate per No. = Tk. 658.71

Say, Tk. 659 .00 each

26.47.8 75 mm dia G.I. Union


Considering 1 No. of fixture
(a) 75 mm dia G.I. Union 1 No. @ Tk. 550.00 each = Tk. 550.00
(b) Fitting fixing materials:
(i) Teflon tape 3.13 rft. @ Tk. 1.82 Per rft. = Tk. 5.70
(c) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.175 No. @ Tk. 303.00 each = Tk. 53.03
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 701.73
Profit 10.00% = Tk. 70.17
Overhead 3.50% = Tk. 24.56
= Tk. 796.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 46.35
Grand total = Tk. 842.81
Rate per No. = Tk. 842.81

Say, Tk. 843 .00 each

26.47.9 100 mm dia G.I. Union


Considering 1 No. of fixture
(a) 100 mm dia G.I. Union 1 No. @ Tk. 800.00 each = Tk. 800.00
(b) Fitting fixing materials:
(i) Teflon tape 4.19 rft. @ Tk. 1.82 Per rft. = Tk. 7.63
(c) Labour:
(i) Plumber 0.115 No. @ Tk. 440.00 each = Tk. 50.60
(ii) Skilled labour 0.19 No. @ Tk. 303.00 each = Tk. 57.57
(iii) Ordinary labour 0.225 No. @ Tk. 245.00 each = Tk. 55.13
Total = Tk. 970.93
Analysis of PWD SoR 2014 for Civil Works 450

Profit 10.00% = Tk. 97.09


Overhead 3.50% = Tk. 33.98
= Tk. 1,102.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 64.14
Grand total = Tk. 1,166.14
Rate per No. = Tk. 1,166.14

Say, Tk. 1,166 .00 each

Item No.- 26.48


Supplying, fitting-fixing of Valves of following types:
26.48.1 12 mm dia Gate Valve
Considering 1 No. of fixture
(a) 12 mm dia Gate Valve 1 No. @ Tk. 220.00 each = Tk. 220.00
(b) Fitting fixing materials:
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.075 No. @ Tk. 303.00 each = Tk. 22.73
(iii) Ordinary labour 0.05 No. @ Tk. 245.00 each = Tk. 12.25
Total = Tk. 266.94
Profit 10.00% = Tk. 26.69
Overhead 3.50% = Tk. 9.34
= Tk. 302.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.63
Grand total = Tk. 320.60
Rate per No. = Tk. 320.60

Say, Tk. 321 .00 each

26.48.2 20 mm dia Gate Valve


Considering 1 No. of fixture
(a) 20 mm dia Gate Valve 1 No. @ Tk. 380.00 each = Tk. 380.00
(b) Fitting fixing materials:
(i) Teflon tape 0.8 rft. @ Tk. 1.82 Per rft. = Tk. 1.46
(c) Labour:
(i) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(ii) Skilled labour 0.08 No. @ Tk. 303.00 each = Tk. 24.24
(iii) Ordinary labour 0.06 No. @ Tk. 245.00 each = Tk. 14.70
Total = Tk. 433.60
Profit 10.00% = Tk. 43.36
Overhead 3.50% = Tk. 15.18
= Tk. 492.14
Add VAT with adjustment factor 1.0582 5.50% = Tk. 28.64
Grand total = Tk. 520.78
Rate per No. = Tk. 520.78

Say, Tk. 521 .00 each

26.48.3 25 mm dia Gate Valve


Considering 1 No. of fixture
(a) 25 mm dia Gate Valve 1 No. @ Tk. 450.00 each = Tk. 450.00
(b) Fitting fixing materials:
(i) Teflon tape 1.05 rft. @ Tk. 1.82 Per rft. = Tk. 1.91
(c) Labour:
(i) Plumber 0.04 No. @ Tk. 440.00 each = Tk. 17.60
(ii) Skilled labour 0.09 No. @ Tk. 303.00 each = Tk. 27.27
Analysis of PWD SoR 2014 for Civil Works 451

(iii) Ordinary labour 0.07 No. @ Tk. 245.00 each = Tk. 17.15
Total = Tk. 513.93
Profit 10.00% = Tk. 51.39
Overhead 3.50% = Tk. 17.99
= Tk. 583.31
Add VAT with adjustment factor 1.0582 5.50% = Tk. 33.95
Grand total = Tk. 617.26
Rate per No. = Tk. 617.26

Say, Tk. 617 .00 each

26.48.4 32 mm dia Gate Valve


Considering 1 No. of fixture
(a) 32 mm dia Gate Valve 1 No. @ Tk. 650.00 each = Tk. 650.00
(b) Fitting fixing materials:
(i) Teflon tape 1.32 rft. @ Tk. 1.82 Per rft. = Tk. 2.40
(c) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
(iii) Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 729.20
Profit 10.00% = Tk. 72.92
Overhead 3.50% = Tk. 25.52
= Tk. 827.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 48.17
Grand total = Tk. 875.81
Rate per No. = Tk. 875.81

Say, Tk. 876 .00 each

26.48.5 40 mm dia Gate Valve


Considering 1 No. of fixture
(a) 40 mm dia Gate Valve 1 No. @ Tk. 700.00 each = Tk. 700.00
(b) Fitting fixing materials:
(i) Teflon tape 1.58 rft. @ Tk. 1.82 Per rft. = Tk. 2.88
(c) Labour:
(i) Plumber 0.06 No. @ Tk. 440.00 each = Tk. 26.40
(ii) Skilled labour 0.11 No. @ Tk. 303.00 each = Tk. 33.33
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 811.61
Profit 10.00% = Tk. 81.16
Overhead 3.50% = Tk. 28.41
= Tk. 921.18
Add VAT with adjustment factor 1.0582 5.50% = Tk. 53.61
Grand total = Tk. 974.79
Rate per No. = Tk. 974.79

Say, Tk. 975 .00 each

26.48.6 50 mm dia Gate Valve


Considering 1 No. of fixture
(a) 50 mm dia Gate Valve 1 No. @ Tk. 1,250.00 each = Tk. 1,250.00
(b) Fitting fixing materials:
(i) Teflon tape 2.05 rft. @ Tk. 1.82 Per rft. = Tk. 3.73
(c) Labour:
(i) Plumber 0.07 No. @ Tk. 440.00 each = Tk. 30.80
(ii) Skilled labour 0.12 No. @ Tk. 303.00 each = Tk. 36.36
Analysis of PWD SoR 2014 for Civil Works 452

(iii) Ordinary labour 0.15 No. @ Tk. 245.00 each = Tk. 36.75
Total = Tk. 1,357.64
Profit 10.00% = Tk. 135.76
Overhead 3.50% = Tk. 47.52
= Tk. 1,540.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 89.68
Grand total = Tk. 1,630.60
Rate per No. = Tk. 1,630.60

Say, Tk. 1,631 .00 each

26.48.7 62 mm dia Gate Valve


Considering 1 No. of fixture
(a) 62 mm dia Gate Valve 1 No. @ Tk. 2,600.00 each = Tk. 2,600.00
(b) Fitting fixing materials:
(i) Teflon tape 2.62 rft. @ Tk. 1.82 Per rft. = Tk. 4.77
(c) Labour:
(i) Plumber 0.09 No. @ Tk. 440.00 each = Tk. 39.60
(ii) Skilled labour 0.14 No. @ Tk. 303.00 each = Tk. 42.42
(iii) Ordinary labour 0.17 No. @ Tk. 245.00 each = Tk. 41.65
Total = Tk. 2,728.44
Profit 10.00% = Tk. 272.84
Overhead 3.50% = Tk. 95.50
= Tk. 3,096.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 180.24
Grand total = Tk. 3,277.02
Rate per No. = Tk. 3,277.02

Say, Tk. 3,277 .00 each

26.48.8 75 mm dia Gate Valve


Considering 1 No. of fixture
(a) 75 mm dia Gate Valve 1 No. @ Tk. 3,500.00 each = Tk. 3,500.00
(b) Fitting fixing materials:
(i) Teflon tape 3.13 rft. @ Tk. 1.82 Per rft. = Tk. 5.70
(c) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.175 No. @ Tk. 303.00 each = Tk. 53.03
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 3,651.73
Profit 10.00% = Tk. 365.17
Overhead 3.50% = Tk. 127.81
= Tk. 4,144.71
Add VAT with adjustment factor 1.0582 5.50% = Tk. 241.23
Grand total = Tk. 4,385.94
Rate per No. = Tk. 4,385.94

Say, Tk. 4,386 .00 each

26.48.9 100 mm dia Gate Valve


Considering 1 No. of fixture
(a) 100 mm dia Gate Valve 1 No. @ Tk. 5,800.00 each = Tk. 5,800.00
(b) Fitting fixing materials:
(i) Teflon tape 4.19 rft. @ Tk. 1.82 Per rft. = Tk. 7.63
(c) Labour:
(i) Plumber 0.115 No. @ Tk. 440.00 each = Tk. 50.60
(ii) Skilled labour 0.19 No. @ Tk. 303.00 each = Tk. 57.57
Analysis of PWD SoR 2014 for Civil Works 453

(iii) Ordinary labour 0.225 No. @ Tk. 245.00 each = Tk. 55.13
Total = Tk. 5,970.93
Profit 10.00% = Tk. 597.09
Overhead 3.50% = Tk. 208.98
= Tk. 6,777.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 394.43
Grand total = Tk. 7,171.43
Rate per No. = Tk. 7,171.43

Say, Tk. 7,171 .00 each

Item No.- 26.49


26.49.1 12 mm dia Glove Valve
Considering 1 No. of fixture
(a) 12 mm dia Glove Valve 1 No. @ Tk. 219.93 each = Tk. 219.93
(b) Fitting fixing materials:
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.075 No. @ Tk. 303.00 each = Tk. 22.73
(iii) Ordinary labour 0.05 No. @ Tk. 245.00 each = Tk. 12.25
Total = Tk. 266.87
Profit 10.00% = Tk. 26.69
Overhead 3.50% = Tk. 9.34
= Tk. 302.90
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.63
Grand total = Tk. 320.53
Rate per No. = Tk. 320.53

Say, Tk. 321 .00 each

26.49.2 20 mm dia Glove Valve


Considering 1 No. of fixture
(a) 20 mm dia Glove Valve 1 No. @ Tk. 324.45 each = Tk. 324.45
(b) Cost of fitting fixing materials:
(i) Teflon tape 0.8 rft. @ Tk. 1.82 Per rft. = Tk. 1.46
(c) Labour:
(i) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(ii) Skilled labour 0.08 No. @ Tk. 303.00 each = Tk. 24.24
(iii) Ordinary labour 0.06 No. @ Tk. 245.00 each = Tk. 14.70
Total = Tk. 378.05
Profit 10.00% = Tk. 37.81
Overhead 3.50% = Tk. 13.23
= Tk. 429.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 24.97
Grand total = Tk. 454.06
Rate per No. = Tk. 454.06

Say, Tk. 454 .00 each

26.49.3 25 mm dia Glove Valve


Considering 1 No. of fixture
(a) 25 mm dia Glove Valve 1 No. @ Tk. 563.10 each = Tk. 563.10
(b) Fitting fixing materials:
(i) Teflon tape 1.05 rft. @ Tk. 1.82 Per rft. = Tk. 1.91
(c) Labour:
(i) Plumber 0.04 No. @ Tk. 440.00 each = Tk. 17.60
Analysis of PWD SoR 2014 for Civil Works 454

(ii) Skilled labour 0.09 No. @ Tk. 303.00 each = Tk. 27.27
(iii) Ordinary labour 0.07 No. @ Tk. 245.00 each = Tk. 17.15
Total = Tk. 627.03
Profit 10.00% = Tk. 62.70
Overhead 3.50% = Tk. 21.95
= Tk. 711.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 41.42
Grand total = Tk. 753.10
Rate per No. = Tk. 753.10

Say, Tk. 753 .00 each

26.49.4 32 mm dia Glove Valve


Considering 1 No. of fixture
(a) 32 mm dia Glove Valve 1 No. @ Tk. 877.97 each = Tk. 877.97
(b) Fitting fixing materials:
(i) Teflon tape 1.32 rft. @ Tk. 1.82 Per rft. = Tk. 2.40
(c) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
(iii) Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 957.17
Profit 10.00% = Tk. 95.72
Overhead 3.50% = Tk. 33.50
= Tk. 1,086.39
Add VAT with adjustment factor 1.0582 5.50% = Tk. 63.23
Grand total = Tk. 1,149.62
Rate per No. = Tk. 1,149.62

Say, Tk. 1,150 .00 each

26.49.5 40 mm dia Glove Valve


Considering 1 No. of fixture
(a) 40 mm dia Glove Valve 1 No. @ Tk. 1,014.63 each = Tk. 1,014.63
(b) Fitting fixing materials:
(i) Teflon tape 1.58 rft. @ Tk. 0.30 Per rft. = Tk. 0.47
(c) Labour:
(i) Plumber 0.06 No. @ Tk. 440.00 each = Tk. 26.40
(ii) Skilled labour 0.11 No. @ Tk. 303.00 each = Tk. 33.33
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 1,123.83
Profit 10.00% = Tk. 112.38
Overhead 3.50% = Tk. 39.33
= Tk. 1,275.54
Add VAT with adjustment factor 1.0582 5.50% = Tk. 74.24
Grand total = Tk. 1,349.78
Rate per No. = Tk. 1,349.78

Say, Tk. 1,350 .00 each

26.49.6 50 mm dia Globe Valve


Considering 1 No. of fixture
(a) 50 mm dia Glove Valve 1 No. @ Tk. 1,574.58 each = Tk. 1,574.58
(b) Fitting fixing materials:
(i) Teflon tape 2.05 rft. @ Tk. 1.82 Per rft. = Tk. 3.73
(c) Labour:
(i) Plumber 0.07 No. @ Tk. 440.00 each = Tk. 30.80
Analysis of PWD SoR 2014 for Civil Works 455

(ii) Skilled labour 0.12 No. @ Tk. 303.00 each = Tk. 36.36
(iii) Ordinary labour 0.15 No. @ Tk. 245.00 each = Tk. 36.75
Total = Tk. 1,682.22
Profit 10.00% = Tk. 168.22
Overhead 3.50% = Tk. 58.88
= Tk. 1,909.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 111.12
Grand total = Tk. 2,020.44
Rate per No. = Tk. 2,020.44

Say, Tk. 2,020 .00 each

26.49.7 62 mm dia Globe Valve


Considering 1 No. of fixture
(a) 62 mm dia Glove Valve 1 No. @ Tk. 2,653.14 each = Tk. 2,653.14
(b) Fitting fixing materials:
(i) Teflon tape 2.62 rft. @ Tk. 1.82 Per rft. = Tk. 4.77
(c) Labour:
(i) Plumber 0.09 No. @ Tk. 440.00 each = Tk. 39.60
(ii) Skilled labour 0.14 No. @ Tk. 303.00 each = Tk. 42.42
(iii) Ordinary labour 0.17 No. @ Tk. 245.00 each = Tk. 41.65
Total = Tk. 2,781.58
Profit 10.00% = Tk. 278.16
Overhead 3.50% = Tk. 97.36
= Tk. 3,157.10
Add VAT with adjustment factor 1.0582 5.50% = Tk. 183.75
Grand total = Tk. 3,340.85
Rate per No. = Tk. 3,340.85

Say, Tk. 3,341 .00 each

26.49.8 75 mm dia Globe Valve


Considering 1 No. of fixture
(a) 75 mm dia Glove Valve 1 No. @ Tk. 3,663.35 each = Tk. 3,663.35
(b) Fitting fixing materials:
(i) Teflon tape 3.13 rft. @ Tk. 1.82 Per rft. = Tk. 5.70
(c) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.175 No. @ Tk. 303.00 each = Tk. 53.03
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 3,815.08
Profit 10.00% = Tk. 381.51
Overhead 3.50% = Tk. 133.53
= Tk. 4,330.12
Add VAT with adjustment factor 1.0582 5.50% = Tk. 252.02
Grand total = Tk. 4,582.14
Rate per No. = Tk. 4,582.14

Say, Tk. 4,582 .00 each

26.49.9 100 mm dia Globe Valve


Considering 1 No. of fixture
(a) 100 mm dia Glove Valve 1 No. @ Tk. 5,056.60 each = Tk. 5,056.60
(b) Fitting fixing materials:
(i) Teflon tape 4.19 rft. @ Tk. 1.82 Per rft. = Tk. 7.63
(c) Labour:
Analysis of PWD SoR 2014 for Civil Works 456

(i) Plumber 0.115 No. @ Tk. 440.00 each = Tk. 50.60


(ii) Skilled labour 0.19 No. @ Tk. 303.00 each = Tk. 57.57
(iii) Ordinary labour 0.225 No. @ Tk. 245.00 each = Tk. 55.13
Total = Tk. 5,227.53
Profit 10.00% = Tk. 522.75
Overhead 3.50% = Tk. 182.96
= Tk. 5,933.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 345.32
Grand total = Tk. 6,278.56
Rate per No. = Tk. 6,278.56

Say, Tk. 6,279 .00 each

Item No.- 26.50


26.50.1 12 mm dia Check Valve
Considering 1 No. of fixture
(a) 12 mm dia Check Valve 1 No. @ Tk. 250.00 each = Tk. 250.00
(b) Fitting fixing materials:
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.075 No. @ Tk. 303.00 each = Tk. 22.73
(iii) Ordinary labour 0.05 No. @ Tk. 245.00 each = Tk. 12.25
Total = Tk. 296.94
Profit 10.00% = Tk. 29.69
Overhead 3.50% = Tk. 10.39
= Tk. 337.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.61
Grand total = Tk. 356.63
Rate per No. = Tk. 356.63
Say, Tk. 357 .00 each
26.50.2 20 mm dia Check Valve
Considering 1 No. of fixture
(a) 20 mm dia Check Valve 1 No. @ Tk. 300.00 each = Tk. 300.00
(b) Fitting fixing materials:
(i) Teflon tape 0.8 rft. @ Tk. 1.82 Per rft. = Tk. 1.46
(c) Labour:
(i) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(ii) Skilled labour 0.08 No. @ Tk. 303.00 each = Tk. 24.24
(iii) Ordinary labour 0.06 No. @ Tk. 245.00 each = Tk. 14.70
Total = Tk. 353.60
Profit 10.00% = Tk. 35.36
Overhead 3.50% = Tk. 12.38
= Tk. 401.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 23.36
Grand total = Tk. 424.70
Rate per No. = Tk. 424.70

Say, Tk. 425 .00 each

26.50.3 25 mm dia Check Valve


Considering 1 No. of fixture
(a) 25 mm dia Check Valve 1 No. @ Tk. 450.00 each = Tk. 450.00
(b) Fitting fixing materials:
(i) Teflon tape 1.05 rft. @ Tk. 1.82 Per rft. = Tk. 1.91
(c) Labour:
(i) Plumber 0.04 No. @ Tk. 440.00 each = Tk. 17.60
Analysis of PWD SoR 2014 for Civil Works 457

(ii) Skilled labour 0.09 No. @ Tk. 303.00 each = Tk. 27.27
(iii) Ordinary labour 0.07 No. @ Tk. 245.00 each = Tk. 17.15
Total = Tk. 513.93
Profit 10.00% = Tk. 51.39
Overhead 3.50% = Tk. 17.99
= Tk. 583.31
Add VAT with adjustment factor 1.0582 5.50% = Tk. 33.95
Grand total = Tk. 617.26
Rate per No. = Tk. 617.26

Say, Tk. 617 .00 each

26.50.4 32 mm dia Check Valve


Considering 1 No. of fixture
(a) 32 mm dia Check Valve 1 No. @ Tk. 650.00 each = Tk. 650.00
(b) Fitting fixing materials:
(i) Teflon tape 1.32 rft. @ Tk. 1.82 Per rft. = Tk. 2.40
(c) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
(iii) Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 729.20
Profit 10.00% = Tk. 72.92
Overhead 3.50% = Tk. 25.52
= Tk. 827.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 48.17
Grand total = Tk. 875.81
Rate per No. = Tk. 875.81

Say, Tk. 876 .00 each


26.50.5 40 mm dia Check Valve
Considering 1 No. of fixture
(a) 40 mm dia Check Valve 1 No. @ Tk. 750.00 each = Tk. 750.00
(b) Fitting fixing materials:
(i) Teflon tape 1.58 rft. @ Tk. 1.82 Per rft. = Tk. 2.88
(c) Labour:
(i) Plumber 0.06 No. @ Tk. 440.00 each = Tk. 26.40
(ii) Skilled labour 0.11 No. @ Tk. 303.00 each = Tk. 33.33
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 861.61
Profit 10.00% = Tk. 86.16
Overhead 3.50% = Tk. 30.16
= Tk. 977.93
Add VAT with adjustment factor 1.0582 5.50% = Tk. 56.92
Grand total = Tk. 1,034.85
Rate per No. = Tk. 1,034.85

Say, Tk. 1,035 .00 each

26.50.6 50 mm dia Check Valve


Considering 1 No. of fixture
(a) 50 mm dia Check Valve 1 No. @ Tk. 1,250.00 each = Tk. 1,250.00
(b) Fitting fixing materials:
(i) Teflon tape 2.05 rft. @ Tk. 1.82 Per rft. = Tk. 3.73
(c) Labour:
(i) Plumber 0.07 No. @ Tk. 440.00 each = Tk. 30.80
(ii) Skilled labour 0.12 No. @ Tk. 303.00 each = Tk. 36.36
Analysis of PWD SoR 2014 for Civil Works 458

(iii) Ordinary labour 0.15 No. @ Tk. 245.00 each = Tk. 36.75
Total = Tk. 1,357.64
Profit 10.00% = Tk. 135.76
Overhead 3.50% = Tk. 47.52
= Tk. 1,540.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 89.68
Grand total = Tk. 1,630.60
Rate per No. = Tk. 1,630.60

Say, Tk. 1,631 .00 each

26.50.7 62 mm dia Check Valve


Considering 1 No. of fixture
(a) 62 mm dia Check Valve 1 No. @ Tk. 2,200.00 each = Tk. 2,200.00
(b) Fitting fixing materials:
(i) Teflon tape 2.62 rft. @ Tk. 1.82 Per rft. = Tk. 4.77
(c) Labour:
(i) Plumber 0.09 No. @ Tk. 440.00 each = Tk. 39.60
(ii) Skilled labour 0.14 No. @ Tk. 303.00 each = Tk. 42.42
(iii) Ordinary labour 0.17 No. @ Tk. 245.00 each = Tk. 41.65
Total = Tk. 2,328.44
Profit 10.00% = Tk. 232.84
Overhead 3.50% = Tk. 81.50
= Tk. 2,642.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 153.81
Grand total = Tk. 2,796.59
Rate per No. = Tk. 2,796.59

Say, Tk. 2,797 .00 each


26.50.8 75 mm dia Check Valve
Considering 1 No. of fixture
(a) 75 mm dia Check Valve 1 No. @ Tk. 3,050.00 each = Tk. 3,050.00
(b) Fitting fixing materials:
(i) Teflon tape 3.13 rft. @ Tk. 1.82 Per rft. = Tk. 5.70
(c) Labour:
(i) Plumber 0.1 No. @ Tk. 440.00 each = Tk. 44.00
(ii) Skilled labour 0.175 No. @ Tk. 303.00 each = Tk. 53.03
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 3,201.73
Profit 10.00% = Tk. 320.17
Overhead 3.50% = Tk. 112.06
= Tk. 3,633.96
Add VAT with adjustment factor 1.0582 5.50% = Tk. 211.50
Grand total = Tk. 3,845.46
Rate per No. = Tk. 3,845.46

Say, Tk. 3,845 .00 each

26.50.9 100 mm dia Check Valve


Considering 1 No. of fixture
(a) 100 mm dia Check Valve 1 No. @ Tk. 5,000.00 each = Tk. 5,000.00
(b) Fitting fixing materials:
(i) Teflon tape 4.19 rft. @ Tk. 1.82 Per rft. = Tk. 7.63
(c) Labour:
(i) Plumber 0.115 No. @ Tk. 440.00 each = Tk. 50.60
(ii) Skilled labour 0.19 No. @ Tk. 303.00 each = Tk. 57.57
(iii) Ordinary labour 0.225 No. @ Tk. 245.00 each = Tk. 55.13
Analysis of PWD SoR 2014 for Civil Works 459

Total = Tk. 5,170.93


Profit 10.00% = Tk. 517.09
Overhead 3.50% = Tk. 180.98
= Tk. 5,869.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 341.58
Grand total = Tk. 6,210.58
Rate per No. = Tk. 6,210.58

Say, Tk. 6,211 .00 each

Item No.- 26.51


26.51.1 12 mm dia Float Valve
Considering 1 No. of fixture
(a) 12 mm dia Float Valve 1 No. @ Tk. 234.22 each = Tk. 234.22
(b) Fitting fixing materials:
(i) Teflon tape 0.27 rft. @ Tk. 1.82 Per rft. = Tk. 0.49
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.075 No. @ Tk. 303.00 each = Tk. 22.73
(iii) Ordinary labour 0.05 No. @ Tk. 245.00 each = Tk. 12.25
Total = Tk. 280.69
Profit 10.00% = Tk. 28.07
Overhead 3.50% = Tk. 9.82
= Tk. 318.58
Add VAT with adjustment factor 1.0582 5.50% = Tk. 18.54
Grand total = Tk. 337.12
Rate per No. = Tk. 337.12
Say, Tk. 337 .00 each
26.51.2 20 mm dia Float Valve
Considering 1 No. of fixture
(a) 20 mm dia Float Valve 1 No. @ Tk. 317.10 each = Tk. 317.10
(b) Fitting fixing materials:
(i) Teflon tape 0.27 rft. @ Tk. 1.82 Per rft. = Tk. 0.49
(c) Labour:
(i) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(ii) Skilled labour 0.08 No. @ Tk. 303.00 each = Tk. 24.24
(iii) Ordinary labour 0.06 No. @ Tk. 245.00 each = Tk. 14.70
Total = Tk. 369.73
Profit 10.00% = Tk. 36.97
Overhead 3.50% = Tk. 12.94
= Tk. 419.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 24.42
Grand total = Tk. 444.06
Rate per No. = Tk. 444.06

Say, Tk. 444 .00 each

26.51.3 25 mm dia Float Valve


Considering 1 No. of fixture
(a) 25 mm dia Float Valve 1 No. @ Tk. 348.93 each = Tk. 348.93
(b) Fitting fixing materials:
(i) Teflon tape 0.27 rft. @ Tk. 1.82 Per rft. = Tk. 0.49
(c) Labour:
(i) Plumber 0.04 No. @ Tk. 440.00 each = Tk. 17.60
(ii) Skilled labour 0.09 No. @ Tk. 303.00 each = Tk. 27.27
(iii) Ordinary labour 0.07 No. @ Tk. 245.00 each = Tk. 17.15
Total = Tk. 411.44
Analysis of PWD SoR 2014 for Civil Works 460

Profit 10.00% = Tk. 41.14


Overhead 3.50% = Tk. 14.40
= Tk. 466.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.18
Grand total = Tk. 494.16
Rate per No. = Tk. 494.16

Say, Tk. 494 .00 each

26.51.4 32 mm dia Float Valve


Considering 1 No. of fixture
(a) 32 mm dia Float Valve 1 No. @ Tk. 618.07 each = Tk. 618.07
(b) Fitting fixing materials:
(i) Teflon tape 0.27 rft. @ Tk. 1.82 Per rft. = Tk. 0.49
(c) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
(iii) Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 695.36
Profit 10.00% = Tk. 69.54
Overhead 3.50% = Tk. 24.34
= Tk. 789.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 45.93
Grand total = Tk. 835.17
Rate per No. = Tk. 835.17

Say, Tk. 835 .00 each

26.51.5 40 mm dia Float Valve


Considering 1 No. of fixture
(a) 40 mm dia Float Valve 1 No. @ Tk. 817.36 each = Tk. 817.36
(b) Fitting fixing materials:
(i) Teflon tape 0.27 rft. @ Tk. 1.82 Per rft. = Tk. 0.49
(c) Labour:
(i) Plumber 0.06 No. @ Tk. 440.00 each = Tk. 26.40
(ii) Skilled labour 0.11 No. @ Tk. 303.00 each = Tk. 33.33
(iii) Ordinary labour 0.2 No. @ Tk. 245.00 each = Tk. 49.00
Total = Tk. 926.58
Profit 10.00% = Tk. 92.66
Overhead 3.50% = Tk. 32.43
= Tk. 1,051.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 61.21
Grand total = Tk. 1,112.88
Rate per No. = Tk. 1,112.88

Say, Tk. 1,113 .00 each

Item No.- 26.52


Supplying, fitting fixing drainage pipe fittings of following type:
26.52.1 100 mm dia HCI trap
Considering 1 No. of fixture
1. 100 mm dia HCI trap: 1 No. @ Tk. 766.03 each = Tk. 766.03
2. Jointing materials
(a) Hem 50 gm. @ Tk. 1.84 Per gm. = Tk. 92.00
(b) Cement mortar (1:4)
(i) Cement 0.008 bag. @ Tk. 440.00 Per bag. = Tk. 3.52
(ii) Sand (F.M. 1.2) 0.02 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.34
Analysis of PWD SoR 2014 for Civil Works 461

3. Labour:
(a) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(b) Skilled labour 0.06 No. @ Tk. 303.00 each = Tk. 18.18
(c) Ordinary labour 0.124 No. @ Tk. 245.00 each = Tk. 30.38
Total = Tk. 923.65
Profit 10.00% = Tk. 92.37
Overhead 3.50% = Tk. 32.33
= Tk. 1,048.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 61.02
Grand total = Tk. 1,109.37
Rate per No. = Tk. 1,109.37

Say, Tk. 1,109 .00 each

26.52.2 100 x 100 or 100 x 50 mm dia HCI Y or T-Y cleanout


Considering 1 No. of fixture
1. 100 x 100 or 100 x 50 mm
dia HCI Y or T-Y 1 No. @ Tk. 749.58 each = Tk. 749.58
2. Jointing materials
(a) Hem 100 gm. @ Tk. 1.84 Per gm. = Tk. 184.00
(b) Cement mortar (1:4)
(i) Cement 0.016 bag. @ Tk. 440.00 Per bag. = Tk. 7.04
(ii) Sand (F.M. 1.2) 0.04 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.68
3. Labour:
(a) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(b) Skilled labour 0.1 No. @ Tk. 303.00 each = Tk. 30.30
(c) Ordinary labour 0.19 No. @ Tk. 245.00 each = Tk. 46.55
Total = Tk. 1,040.15
Profit 10.00% = Tk. 104.02
Overhead 3.50% = Tk. 36.41
= Tk. 1,180.58
Add VAT with adjustment factor 1.0582 5.50% = Tk. 68.71
Grand total = Tk. 1,249.29
Rate per No. = Tk. 1,249.29

Say, Tk. 1,249 .00 each

26.52.3 150 x 150 or 150 x 100 mm dia HCI Y or T-Y cleanout


Considering 1 No. of fixture
1. 100 x 100 or 150 x 100 mm dia
HCI Y or T-Y cleanout 1 No. @ Tk. 1,139.22 each = Tk. 1,139.22
2. ii. Cost of jointing
(a) Hem 50 gm. @ Tk. 1.84 Per gm. = Tk. 92.00
(b) Cement mortar (1:4)
(i) Cement 0.008 bag. @ Tk. 440.00 Per bag. = Tk. 3.52
(ii) Sand (F.M. 1.2) 0.02 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.34
3. Labour:
(a) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(b) Skilled labour 0.07 No. @ Tk. 303.00 each = Tk. 21.21
(c) Ordinary labour 0.162 No. @ Tk. 245.00 each = Tk. 39.69
Total = Tk. 1,309.18
Profit 10.00% = Tk. 130.92
Overhead 3.50% = Tk. 45.82
= Tk. 1,485.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 86.48
Grand total = Tk. 1,572.40
Rate per No. = Tk. 1,572.40
Analysis of PWD SoR 2014 for Civil Works 462

Say, Tk. 1,572 .00 each

26.52.4 50 mm dia HCI trap


Considering 1 No. of fixture
1. 50 mm dia HCI trap 1 No. @ Tk. 1,094.02 each = Tk. 1,094.02
2. Jointing materials
(a) Hem 25 gm. @ Tk. 1.84 Per gm. = Tk. 46.00
(b) Cement mortar (1:4)
(i) Cement 0.004 bag. @ Tk. 440.00 Per bag. = Tk. 1.76
(ii) Sand (F.M. 1.2) 0.01 cft. @ Tk. 1,700.00 Per % cft. = Tk. 0.17
3. Labour:
(a) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(b) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(c) Ordinary labour 0.095 No. @ Tk. 245.00 each = Tk. 23.28
Total = Tk. 1,191.38
Profit 10.00% = Tk. 119.14
Overhead 3.50% = Tk. 41.70
= Tk. 1,352.22
Add VAT with adjustment factor 1.0582 5.50% = Tk. 78.70
Grand total = Tk. 1,430.92
Rate per No. = Tk. 1,430.92

Say, Tk. 1,431 .00 each

Item No.- 26.53


26.53.1 50 mm dia plastic Y or T-Y cleanout
Considering 1 No. of fixture
(a) 50 mm dia plastic
Y or T-Y cleanout 1 No. @ Tk. 340.88 each = Tk. 340.88
(b) Jointing materials
(i) Solvent cement 10 gm. @ Tk. 1.84 Per gm. = Tk. 18.40
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(iii) Ordinary labour 0.095 No. @ Tk. 245.00 each = Tk. 23.28
Total = Tk. 408.71
Profit 10.00% = Tk. 40.87
Overhead 3.50% = Tk. 14.30
= Tk. 463.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.00
Grand total = Tk. 490.88
Rate per No. = Tk. 490.88

Say, Tk. 491 .00 each

26.53.2 100 mm dia plastic "P" or "S" trap


Considering 1 No. of fixture
(a) 100 mm dia plastic trap 1 No. @ Tk. 360.62 each = Tk. 360.62
(b) Jointing materials
(i) Solvent cement 27 gm. @ Tk. 1.63 Per gm. = Tk. 44.01
(c) Labour:
(i) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(ii) Skilled labour 0.07 No. @ Tk. 303.00 each = Tk. 21.21
(iii) Ordinary labour 0.162 No. @ Tk. 245.00 each = Tk. 39.69
Total = Tk. 478.73
Profit 10.00% = Tk. 47.87
Analysis of PWD SoR 2014 for Civil Works 463

Overhead 3.50% = Tk. 16.76


= Tk. 543.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 31.62
Grand total = Tk. 574.98
Rate per No. = Tk. 574.98
Say, Tk. 575 .00 each
26.53.3 100 mm dia plastic "Y" or "T-Y" cleanout
Considering 1 No. of fixture
(a) 100 mm dia plastic
Y or "T-Y" cleanout 1 No. @ Tk. 426.58 each = Tk. 426.58
(b) Jointing Materials
(i) Solvent cement 27 gm. @ Tk. 1.63 Per gm. = Tk. 44.01
(c) Labour:
(i) Plumber 0.045 No. @ Tk. 440.00 each = Tk. 19.80
(ii) Skilled labour 0.09 No. @ Tk. 303.00 each = Tk. 27.27
(iii) Ordinary labour 0.161 No. @ Tk. 245.00 each = Tk. 39.45
Total = Tk. 557.11
Profit 10.00% = Tk. 55.71
Overhead 3.50% = Tk. 19.50
= Tk. 632.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 36.80
Grand total = Tk. 669.12
Rate per No. = Tk. 669.12
Say, Tk. 669 .00 each
26.53.4 50 mm dia plastic "P" or "S" trap
Considering 1 No. of fixture
(a) 50 mm dia plastic trap 1 No. @ Tk. 342.30 each = Tk. 342.30
(b) Jointing materials
(i) Solvent cement 10 gm. @ Tk. 1.63 Per gm. = Tk. 16.30
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(iii) Ordinary labour 0.095 No. @ Tk. 245.00 each = Tk. 23.28
Total = Tk. 408.03
Profit 10.00% = Tk. 40.80
Overhead 3.50% = Tk. 14.28
= Tk. 463.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 26.95
Grand total = Tk. 490.06
Rate per No. = Tk. 490.06

Say, Tk. 490 .00 each


Item No.- 26.54
Supplying, fitting fixing Faucets of following type:
26.54.1 12 mm CP bib cock
Considering 1 No. of fixture
(a) 12 mm CP bib cock 1 No. @ Tk. 517.64 each = Tk. 517.64
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ Tk. 1.82 Per rft. = Tk. 0.55
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(iii) Ordinary labour 0.095 No. @ Tk. 245.00 each = Tk. 23.28
Total = Tk. 567.62
Profit 10.00% = Tk. 56.76
Overhead 3.50% = Tk. 19.87
= Tk. 644.25
Analysis of PWD SoR 2014 for Civil Works 464

Add VAT with adjustment factor 1.0582 5.50% = Tk. 37.50


Grand total = Tk. 681.75
Rate per No. = Tk. 681.75
Say, Tk. 682 .00 each

26.54.2 12 mm special quality CP bib cock


Considering 1 No. of fixture
(a) 12 mm special quality CP bib cock 1 No. @ Tk. 834.91 each = Tk. 834.91
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ Tk. 1.82 Per rft. = Tk. 0.55
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(iii) Ordinary labour 0.095 No. @ Tk. 245.00 each = Tk. 23.28
Total = Tk. 884.89
Profit 10.00% = Tk. 88.49
Overhead 3.50% = Tk. 30.97
= Tk. 1,004.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 58.45
Grand total = Tk. 1,062.80
Rate per No. = Tk. 1,062.80

Say, Tk. 1,063 .00 each


26.54.3 12 mm twin in one bib cock
Considering 1 No. of fixture
(a) 12 mm special quality CP bib cock 1 No. @ Tk. 1,580.00 each = Tk. 1,580.00
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ Tk. 1.82 Per rft. = Tk. 0.55
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(iii) Ordinary labour 0.095 No. @ Tk. 245.00 each = Tk. 23.28
Total = Tk. 1,629.98
Profit 10.00% = Tk. 163.00
Overhead 3.50% = Tk. 57.05
= Tk. 1,850.03
Add VAT with adjustment factor 1.0582 5.50% = Tk. 107.67
Grand total = Tk. 1,957.70
Rate per No. = Tk. 1,957.70

Say, Tk. 1,958 .00 each


Item No.- 26.55
26.55.1 12 mm CP medium quality pillar cock
Considering 1 No. of fixture
(a) 12 mm CP medium
quality pillar cock 1 No. @ Tk. 649.72 each = Tk. 649.72
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ Tk. 1.82 Per rft. = Tk. 0.55
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(iii) Ordinary labour 0.095 No. @ Tk. 245.00 each = Tk. 23.28
Total = Tk. 699.70
Profit 10.00% = Tk. 69.97
Overhead 3.50% = Tk. 24.49
= Tk. 794.16
Add VAT with adjustment factor 1.0582 5.50% = Tk. 46.22
Analysis of PWD SoR 2014 for Civil Works 465

Grand total = Tk. 840.38


Rate per No. = Tk. 840.38
Say, Tk. 840 .00 each

26.55.2 12 mm CP special heavy duty pillar cock


Considering 1 No. of fixture
(a) 12 mm CP heavy duty pillar cock 1 No. @ Tk. 764.43 each = Tk. 764.43
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ Tk. 1.82 Per rft. = Tk. 0.55
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(iii) Ordinary labour 0.095 No. @ Tk. 245.00 each = Tk. 23.28
Total = Tk. 814.41
Profit 10.00% = Tk. 81.44
Overhead 3.50% = Tk. 28.50
= Tk. 924.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 53.80
Grand total = Tk. 978.15
Rate per No. = Tk. 978.15

Say, Tk. 978 .00 each


Item No.- 26.56
26.56.1 12 mm CP concealed fixed sink cock
Considering 1 No. of fixture
(a) 12 mm CP conealed
fixed sink cock 1 No. @ Tk. 716.50 each = Tk. 716.50
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ Tk. 1.82 Per rft. = Tk. 0.55
(c) labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(iii) Ordinary labour 0.095 No. @ Tk. 245.00 each = Tk. 23.28
Total = Tk. 766.48
Profit 10.00% = Tk. 76.65
Overhead 3.50% = Tk. 26.83
= Tk. 869.96
Add VAT with adjustment factor 1.0582 5.50% = Tk. 50.63
Grand total = Tk. 920.59
Rate per No. = Tk. 920.59

Say, Tk. 921 .00 each

26.56.2 12 mm CP concealed moving sink cock


Considering 1 No. of fixture
(a) 12 mm CP concealed
moving sink cock 1 No. @ Tk. 742.86 each = Tk. 742.86
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ Tk. 1.82 Per rft. = Tk. 0.55
(c) Labour:
(i) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(ii) Skilled labour 0.06 No. @ Tk. 303.00 each = Tk. 18.18
(iii) Ordinary labour 0.124 No. @ Tk. 245.00 each = Tk. 30.38
Total = Tk. 805.17
Profit 10.00% = Tk. 80.52
Overhead 3.50% = Tk. 28.18
= Tk. 913.87
Analysis of PWD SoR 2014 for Civil Works 466

Add VAT with adjustment factor 1.0582 5.50% = Tk. 53.19


Grand total = Tk. 967.06
Rate per No. = Tk. 967.06

Say, Tk. 967 .00 each

Item No.- 26.57.1


CP basin mixture
Considering 1 No. of fixture
(a) CP basin mixture 1 No. @ Tk. 1,823.01 each = Tk. 1,823.01
(b) Fitting-fixing materials
(i) Teflon tape 0.04 rft. @ Tk. 1.82 Per rft. = Tk. 0.07
(c) Labour:
(i) Plumber 0.06 No. @ Tk. 440.00 each = Tk. 26.40
(ii) Skilled labour 0.12 No. @ Tk. 303.00 each = Tk. 36.36
(iii) Ordinary labour 0.248 No. @ Tk. 245.00 each = Tk. 60.76
Total = Tk. 1,946.60
Profit 10.00% = Tk. 194.66
Overhead 3.50% = Tk. 68.13
= Tk. 2,209.39
Add VAT with adjustment factor 1.0582 5.50% = Tk. 128.59
Grand total = Tk. 2,337.98
Rate per No. = Tk. 2,337.98

Say, Tk. 2,338 .00 each

Item No.- 26.57.2


CP single handle basin mixture
Considering 1 No. of fixture
(a) CP single handle basin mixture 1 No. @ Tk. 1,485.97 each = Tk. 1,485.97
(b) Fitting-fixing materials
(i) Teflon tape 0.4 rft. @ Tk. 1.82 Per rft. = Tk. 0.73
(c) Labour:
(i) Plumber 0.06 No. @ Tk. 440.00 each = Tk. 26.40
(ii) Skilled labour 0.12 No. @ Tk. 303.00 each = Tk. 36.36
(iii) Ordinary labour 0.248 No. @ Tk. 245.00 each = Tk. 60.76
Total = Tk. 1,610.22
Profit 10.00% = Tk. 161.02
Overhead 3.50% = Tk. 56.36
= Tk. 1,827.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 106.37
Grand total = Tk. 1,933.97
Rate per No. = Tk. 1,933.97

Say, Tk. 1,934 .00 each

Item No.- 26.58


CP shower mixture in/c shower head only
Considering 1 No. of fixture
(a) CP shower mixture 1 No. @ Tk. 2,648.68 each = Tk. 2,648.68
(b) Fitting-fixing materials
(i) Teflon tape 0.5 rft. @ Tk. 1.82 Per rft. = Tk. 0.91
(c) Labour:
(i) Plumber 0.09 No. @ Tk. 440.00 each = Tk. 39.60
(ii) Skilled labour 0.156 No. @ Tk. 303.00 each = Tk. 47.27
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 2,834.46
Analysis of PWD SoR 2014 for Civil Works 467

Profit 10.00% = Tk. 283.45


Overhead 3.50% = Tk. 99.21
= Tk. 3,217.12
Add VAT with adjustment factor 1.0582 5.50% = Tk. 187.24
Grand total = Tk. 3,404.36
Rate per No. = Tk. 3,404.36

Say, Tk. 3,404 .00 each

Item No.- 26.59


CP shower mixture in/c shower head and faucet
Considering 1 No. of fixture
(a) CP shower mixture 1 No. @ Tk. 3,866.37 each = Tk. 3,866.37
(b) Fitting-fixing materials
(i) Teflon tape 0.5 rft. @ Tk. 1.82 Per rft. = Tk. 0.91
(c) Labour:
(i) Plumber 0.09 No. @ Tk. 440.00 each = Tk. 39.60
(ii) Skilled labour 0.156 No. @ Tk. 303.00 each = Tk. 47.27
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 4,052.15
Profit 10.00% = Tk. 405.22
Overhead 3.50% = Tk. 141.83
= Tk. 4,599.20
Add VAT with adjustment factor 1.0582 5.50% = Tk. 267.68
Grand total = Tk. 4,866.88
Rate per No. = Tk. 4,866.88

Say, Tk. 4,867 .00 each

Item No.- 26.60


CP bath-tub mixture with shower head only
Considering 1 No. of fixture
(a) CP bath-tub mixture 1 No. @ Tk. 4,068.67 each = Tk. 4,068.67
(b) Fitting-fixing materials
(i) Teflon tape 0.5 rft. @ Tk. 1.82 Per rft. = Tk. 0.91
(c) Labour:
(i) Plumber 0.09 No. @ Tk. 440.00 each = Tk. 39.60
(ii) Skilled labour 0.156 No. @ Tk. 303.00 each = Tk. 47.27
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
Total = Tk. 4,254.45
Profit 10.00% = Tk. 425.45
Overhead 3.50% = Tk. 148.91
= Tk. 4,828.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 281.04
Grand total = Tk. 5,109.85
Rate per No. = Tk. 5,109.85

Say, Tk. 5,110 .00 each

Item No.- 26.61


CP self closing pillar cock
Considering 1 No. of fixture
(a) CP self closing pillar cock 1 No. @ Tk. 734.04 each = Tk. 734.04
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ Tk. 1.82 Per rft. = Tk. 0.55
(c) Labour:
(i) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
Analysis of PWD SoR 2014 for Civil Works 468

(ii) Skilled labour 0.07 No. @ Tk. 303.00 each = Tk. 21.21
(iii) Ordinary labour 0.162 No. @ Tk. 245.00 each = Tk. 39.69
Total = Tk. 808.69
Profit 10.00% = Tk. 80.87
Overhead 3.50% = Tk. 28.30
= Tk. 917.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 53.42
Grand total = Tk. 971.28
Rate per No. = Tk. 971.28

Say, Tk. 971 .00 each

Item No.- 26.62


Supply and fitting-fixing stop cocks of following types:
26.62.1 12 mm stop cock (brass) for surface mount (ordinary type)
Considering 1 No. of fixture
(a) 12 mm stop cock (brass) for surface
mount (ordinary type) 1 No. @ Tk. 229.54 each = Tk. 229.54
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 255.34
Profit 10.00% = Tk. 25.53
Overhead 3.50% = Tk. 8.94
= Tk. 289.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 16.87
Grand total = Tk. 306.68
Rate per No. = Tk. 306.68

Say, Tk. 307 .00 each

26.62.2 12 mm surface mount medium quality CP stop cock


Considering 1 No. of fixture
(a) 12 mm CP medium
quality stop cock 1 No. @ Tk. 292.28 each = Tk. 292.28
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 318.08
Profit 10.00% = Tk. 31.81
Overhead 3.50% = Tk. 11.13
= Tk. 361.02
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.01
Grand total = Tk. 382.03
Rate per No. = Tk. 382.03

Say, Tk. 382 .00 each

26.62.3 12 mm CP surface mount special quality stop cock


Considering 1 No. of fixture
(a) 12 mm CP surface mount
Analysis of PWD SoR 2014 for Civil Works 469

special quality stop cock 1 No. @ Tk. 739.70 each = Tk. 739.70
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 765.50
Profit 10.00% = Tk. 76.55
Overhead 3.50% = Tk. 26.79
= Tk. 868.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 50.57
Grand total = Tk. 919.41
Rate per No. = Tk. 919.41

Say, Tk. 919 .00 each

26.62.4 Angle stop cock (concealed)


Considering 1 No. of fixture
(a) Stop cock (concealed) 1 No. @ Tk. 822.09 each = Tk. 822.09
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 847.89
Profit 10.00% = Tk. 84.79
Overhead 3.50% = Tk. 29.68
= Tk. 962.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 56.01
Grand total = Tk. 1,018.37
Rate per No. = Tk. 1,018.37

Say, Tk. 1,018 .00 each

26.62.5 Stop cock concealed (medium)


Considering 1 No. of fixture
(a) Stop cock concealed (medium) 1 No. @ Tk. 870.95 each = Tk. 870.95
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 896.75
Profit 10.00% = Tk. 89.68
Overhead 3.50% = Tk. 31.39
= Tk. 1,017.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 59.24
Grand total = Tk. 1,077.06
Rate per No. = Tk. 1,077.06

Say, Tk. 1,077 .00 each

26.62.6 Stop cock concealed (heavy)


Considering 1 No. of fixture
Analysis of PWD SoR 2014 for Civil Works 470

(a) Stop cock concealed (heavy) 1 No. @ Tk. 952.15 each = Tk. 952.15
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 977.95
Profit 10.00% = Tk. 97.80
Overhead 3.50% = Tk. 34.23
= Tk. 1,109.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 64.60
Grand total = Tk. 1,174.58
Rate per No. = Tk. 1,174.58

Say, Tk. 1,175 .00 each

Item No.- 26.63


26.63.1 12 mm CP surface mounted angle stop cock
Considering 1 No. of fixture
(a) 12 mm CP surface
mounted angle stop cock 1 No. @ Tk. 630.95 each = Tk. 630.95
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 656.75
Profit 10.00% = Tk. 65.68
Overhead 3.50% = Tk. 22.99
= Tk. 745.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 43.38
Grand total = Tk. 788.80
Rate per No. = Tk. 788.80
Say, Tk. 789 .00 each
26.63.2 12 mm CP medium quality surface & heavy type fancy angle stop cock
Considering 1 No. of fixture
(a) 12 mm CP surface & heavy
type fancy angle stop cock 1 No. @ Tk. 662.98 each = Tk. 662.98
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 688.78
Profit 10.00% = Tk. 68.88
Overhead 3.50% = Tk. 24.11
= Tk. 781.77
Add VAT with adjustment factor 1.0582 5.50% = Tk. 45.50
Grand total = Tk. 827.27
Rate per No. = Tk. 827.27
Say, Tk. 827 .00 each
26.63.3 12 mm surface special heavy type angle stop cock
Considering 1 No. of fixture
(a) 12 mm surface special heavy
Analysis of PWD SoR 2014 for Civil Works 471

type angle stop cock 1 No. @ Tk. 636.47 each = Tk. 636.47
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 662.27
Profit 10.00% = Tk. 66.23
Overhead 3.50% = Tk. 23.18
= Tk. 751.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 43.75
Grand total = Tk. 795.43
Rate per No. = Tk. 795.43

Say, Tk. 795 .00 each


26.63.4 12 mm CP concealed mount angle stop cock
Considering 1 No. of fixture
(a) 12 mm CP concealed
mount angle stop cock 1 No. @ Tk. 512.50 each = Tk. 512.50
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 538.30
Profit 10.00% = Tk. 53.83
Overhead 3.50% = Tk. 18.84
= Tk. 610.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 35.56
Grand total = Tk. 646.53
Rate per No. = Tk. 646.53

Say, Tk. 647 .00 each


26.63.5 Medium concealed angle stop cock
Considering 1 No. of fixture
(a) 12 mm CP medium
concealed angle stop cock 1 No. @ Tk. 636.47 each = Tk. 636.47
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 662.27
Profit 10.00% = Tk. 66.23
Overhead 3.50% = Tk. 23.18
= Tk. 751.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 43.75
Grand total = Tk. 795.43
Rate per No. = Tk. 795.43

Say, Tk. 795 .00 each


26.63.6 Special concealed heavy type angle stop cock
Considering 1 No. of fixture
(a) Special concealed heavy
Analysis of PWD SoR 2014 for Civil Works 472

type angle stop cock 1 No. @ Tk. 766.53 each = Tk. 766.53
(b) Fitting-fixing materials
(i) Teflon tape 0.53 rft. @ Tk. 1.82 Per rft. = Tk. 0.96
(c) Labour:
(i) Plumber 0.0125 No. @ Tk. 440.00 each = Tk. 5.50
(ii) Skilled labour 0.025 No. @ Tk. 303.00 each = Tk. 7.58
(iii) Ordinary labour 0.048 No. @ Tk. 245.00 each = Tk. 11.76
Total = Tk. 792.33
Profit 10.00% = Tk. 79.23
Overhead 3.50% = Tk. 27.73
= Tk. 899.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 52.34
Grand total = Tk. 951.63
Rate per No. = Tk. 951.63
Say, Tk. 952 .00 each
Item No.- 26.64
Groove cutting in brick work, RCC floor etc. and cement mortaring after laying pipe
26.64.1 Groove size: 40 x 40 mm (for laying 12 to 20 mm dia pipe)
Considering 3 meter long groove
(a) Labour cutting and filling groove
(i) Plumber 0.06 No. @ Tk. 440.00 each = Tk. 26.40
(ii) Skilled labour 0.12 No. @ Tk. 303.00 each = Tk. 36.36
(iii) Ordinary labour 0.248 No. @ Tk. 245.00 each = Tk. 60.76
(b) Cement mortar (1:4)
(i) Cement 0.024 bag @ Tk. 440.00 Per bag = Tk. 10.56
(ii) Sand (F.M. 1.2) 0.12 cft. @ Tk. 1,700.00 Per % cft. = Tk. 2.04
Total = Tk. 123.52
Profit 10.00% = Tk. 12.35
Overhead 3.50% = Tk. 4.32
= Tk. 140.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 8.16
Grand total = Tk. 148.35
Rate per rm. = Tk. 49.45

Say, Tk. 49 .00 Per rm.


26.64.2 Groove size: 75 x 75 mm (for laying 25 to 40 mm dia pipe)
Considering 3 meter long groove
(a) Labour for cutting and filling groove
(i) Plumber 0.09 No. @ Tk. 440.00 each = Tk. 39.60
(ii) Skilled labour 0.156 No. @ Tk. 303.00 each = Tk. 47.27
(iii) Ordinary labour 0.4 No. @ Tk. 245.00 each = Tk. 98.00
(b) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 440.00 Per bag = Tk. 44.00
(ii) Sand (F.M. 1.2) 0.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 8.50
Total = Tk. 184.87
Profit 10.00% = Tk. 18.49
Overhead 3.50% = Tk. 6.47
= Tk. 209.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12.21
Grand total = Tk. 222.04
Rate per rm. = Tk. 74.01

Say, Tk. 74 .00 Per rm.

Item No.- 26.65


Supply and fitting-fixing cleanging shower for ablution including holder
26.65.1 Fixed type 100 mm CP shower rose
Analysis of PWD SoR 2014 for Civil Works 473

Considering 1 No. of fixture


(a) Fixed type 100 mm CP
cleanging shower rose 1 No. @ Tk. 435.21 each = Tk. 435.21
(b) Fitting-fixing materials
(i) Teflon tape 0.27 rft. @ Tk. 1.82 Per rft. = Tk. 0.49
(ii) Rowel plug & screw 4 Nos. @ Tk. 5.71 each = Tk. 22.84
(c) Labour:
(i) Plumber 0.025 No. @ Tk. 440.00 each = Tk. 11.00
(ii) Skilled labour 0.05 No. @ Tk. 303.00 each = Tk. 15.15
(iii) Ordinary labour 0.095 No. @ Tk. 245.00 each = Tk. 23.28
Total = Tk. 507.97
Profit 10.00% = Tk. 50.80
Overhead 3.50% = Tk. 17.78
= Tk. 576.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 33.56
Grand total = Tk. 610.11
Rate per No. = Tk. 610.11

Say, Tk. 610 .00 each


26.65.2 Moving type 100 mm CP shower rose
Considering 1 No. of fixture
(a) Moving type 100 mm CP
cleanging shower rose 1 No. @ Tk. 652.79 each = Tk. 652.79
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ Tk. 1.82 Per rft. = Tk. 0.55
(ii) Rowel plug & screw 4 Nos. @ Tk. 5.71 each = Tk. 22.84
(c) Labour:
(i) Plumber 0.115 No. @ Tk. 440.00 each = Tk. 50.60
(ii) Skilled labour 0.19 No. @ Tk. 303.00 each = Tk. 57.57
(iii) Ordinary labour 0.225 No. @ Tk. 245.00 each = Tk. 55.13
Total = Tk. 839.48
Profit 10.00% = Tk. 83.95
Overhead 3.50% = Tk. 29.38
= Tk. 952.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 55.45
Grand total = Tk. 1,008.26
Rate per No. = Tk. 1,008.26

Say, Tk. 1,008 .00 each

Item No.- 26.66


Supply and fitting-fixing cleanging shower for ablution including holder
26.66.1 CP Moving hand shower
Considering 1 No. of fixture
(a) Fixed type 100 mm
CP shower rose 1 No. @ Tk. 2,126.03 each = Tk. 2,126.03
(b) Ftting-fixing materials
(i) Teflon tape 0.3 rft. @ Tk. 1.82 Per rft. = Tk. 0.55
(c) Labour:
(i) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(ii) Skilled labour 0.06 No. @ Tk. 303.00 each = Tk. 18.18
(iii) Ordinary labour 0.124 No. @ Tk. 245.00 each = Tk. 30.38
Total = Tk. 2,188.34
Profit 10.00% = Tk. 218.83
Overhead 3.50% = Tk. 76.59
= Tk. 2,483.76
Add VAT with adjustment factor 1.0582 5.50% = Tk. 144.56
Analysis of PWD SoR 2014 for Civil Works 474

Grand total = Tk. 2,628.32


Rate per No. = Tk. 2,628.32

Say, Tk. 2,628 .00 each


26.66.2 CP Moving push shower
Considering 1 No. of fixture
(a) Moving type 100 mm
CP shower rose 1 No. @ Tk. 685.90 each = Tk. 685.90
(b) Fitting-fixing materials
(i) Teflon tape 0.3 rft. @ Tk. 1.82 Per rft. = Tk. 0.55
(c) Labour:
(i) Plumber 0.03 No. @ Tk. 440.00 each = Tk. 13.20
(ii) Skilled labour 0.06 No. @ Tk. 303.00 each = Tk. 18.18
(iii) Ordinary labour 0.124 No. @ Tk. 245.00 each = Tk. 30.38
Total = Tk. 748.21
Profit 10.00% = Tk. 74.82
Overhead 3.50% = Tk. 26.19
= Tk. 849.22
Add VAT with adjustment factor 1.0582 5.50% = Tk. 49.43
Grand total = Tk. 898.65
Rate per No. = Tk. 898.65

Say, Tk. 899 .00 each

Item No.- 26.67


Supply and fitting and installation of over-head water-tank of following type:
26.67.1 Food-grade plastic over-head water-tank
1000 liter capacity food-grade plastic over-head water-tank
Considering 1 No. of fixture
(a) 1000 liter water-tank 1 No. @ Tk. 9,800.00 each = Tk. 9,800.00
(b) Carrying up to site L.S. = Tk. 245.00
(c) Fitting-fixing materials
(i) Teflon tape 4.2 rft. @ Tk. 1.82 Per rft. = Tk. 7.64
(ii) Nipple with jam-nuts 4 Nos. @ Tk. 25.00 each = Tk. 100.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00
Total = Tk. 11,140.64
Profit 10.00% = Tk. 1,114.06
Overhead 3.50% = Tk. 389.92
= Tk. 12,644.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 735.93
Grand total = Tk. 13,380.55
Rate per No. = Tk. 13,380.55

Say, Tk. 13,381 .00 each


26.67.2 1500 liter capacity food-grade plastic over-head water-tank
Considering 1 No. of fixture
(a) 1500 liter water-tank 1 No. @ Tk. 14,700.00 each = Tk. 14,700.00
(b) Carrying up to site L.S. = Tk. 306.25
(c) Fitting-fixing materials
(i) Teflon tape 4.2 rft. @ Tk. 1.82 Per rft. = Tk. 7.64
(ii) Nipple with jam-nuts 4 Nos. @ Tk. 66.14 each = Tk. 264.56
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Analysis of PWD SoR 2014 for Civil Works 475

(iii) Ordinary labour 1 No. @ Tk. 245.00 each = Tk. 245.00


Total = Tk. 16,266.45
Profit 10.00% = Tk. 1,626.65
Overhead 3.50% = Tk. 569.33
= Tk. 18,462.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,074.53
Grand total = Tk. 19,536.96
Rate per No. = Tk. 19,536.96

Say, Tk. 19,537 .00 each


Analysis of PWD SoR 2014 for Civil Works 476

26.67.3 2000 liter capacity food-grade plastic over-head water-tank


Considering 1 No. of fixture
(a) 2000 liter water-tank 1 No. @ Tk. 19,600.00 each = Tk. 19,600.00
(b) Carrying up to site L.S. = Tk. 367.50
(c) Fitting-fixing materials
(i) Teflon tape 4.2 rft. @ Tk. 1.82 Per rft. = Tk. 7.64
(ii) Nipple with jam-nuts 4 Nos. @ Tk. 66.14 each = Tk. 264.56
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
(iii) Ordinary labour 2 No. @ Tk. 245.00 each = Tk. 490.00
Total = Tk. 21,472.70
Profit 10.00% = Tk. 2,147.27
Overhead 3.50% = Tk. 751.54
= Tk. 24,371.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,418.45
Grand total = Tk. 25,789.96
Rate per No. = Tk. 25,789.96

Say, Tk. 25,790 .00 each

Item No.- 26.68


26.68.1 Food-grade plastic internal mini water tank for the use in kitchen, bathroom & toilet for
emergency storage and supply of water: 150 liter capacity
Considering 1 No. of fixture
(a) 150 liter plastic water tank 1 No. @ Tk. 1,950.00 each = Tk. 1,950.00
(b) Carrying up to site L.S. = Tk. 122.50
(c) Fitting-fixing materials
(i) Teflon tape 4.2 rft. @ Tk. 1.82 Per rft. = Tk. 7.64
(ii) 3/4" dia ball cock 1 No. @ Tk. 231.50 each = Tk. 231.50
(iii) 3/4" dia pipe with jam-nuts 1 No. @ Tk. 122.37 each = Tk. 122.37
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Total = Tk. 3,177.01
Profit 10.00% = Tk. 317.70
Overhead 3.50% = Tk. 111.20
= Tk. 3,605.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 209.87
Grand total = Tk. 3,815.78
Rate per No. = Tk. 3,815.78

Say, Tk. 3,816 .00 each

26.68.2 Food-grade plastic internal mini water tank for the use in kitchen, bathroom & toilet for
emergency storage and supply of water: 300 liter capacity
Considering 1 No. of fixture
(a) 300 literplastic water tank 1 No. @ Tk. 3,690.00 each = Tk. 3,690.00
(b) Carrying up to site L.S. = Tk. 183.75
(c) Fitting-fixing materials
(i) Teflon tape 4.2 rft. @ Tk. 1.82 Per rft. = Tk. 7.64
(ii) 3/4" dia ball cock 1 No. @ Tk. 231.50 each = Tk. 231.50
(iii) Nipple with jam-nuts 1 No. @ Tk. 122.37 each = Tk. 122.37
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Total = Tk. 4,978.26
Analysis of PWD SoR 2014 for Civil Works 477

Profit 10.00% = Tk. 497.83


Overhead 3.50% = Tk. 174.24
= Tk. 5,650.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 328.85
Grand total = Tk. 5,979.18
Rate per No. = Tk. 5,979.18

Say, Tk. 5,979 .00 each

26.68.3 Food-grade plastic internal mini water tank for the use in kitchen, bathroom & toilet for
emergency storage and supply of water: 500 liter capacity
Considering 1 No. of fixture
(a) 500 liter plastic water tank 1 No. @ Tk. 5,000.00 each = Tk. 5,000.00
(b) Carrying up to site L.S. = Tk. 458.15
(c) Fitting-fixing materials
(i) Teflon tape 4.2 rft. @ Tk. 1.82 Per rft. = Tk. 7.64
(ii) 3/4" dia ball cock 1 No. @ Tk. 231.50 each = Tk. 231.50
(iii) Nipple with jam-nuts 1 No. @ Tk. 122.37 each = Tk. 122.37
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Total = Tk. 6,562.66
Profit 10.00% = Tk. 656.27
Overhead 3.50% = Tk. 229.69
= Tk. 7,448.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 433.52
Grand total = Tk. 7,882.14
Rate per No. = Tk. 7,882.14

Say, Tk. 7,882 .00 each

Item No.- 26.69


26.69.1 Food-grade foreign made stainless steel water tank: 500 liter capacity
Considering 1 No. of fixture
(a) 500 liter stainless steel water tank 1 No. @ Tk. 7,640.93 each = Tk. 7,640.93
(b) Carrying up to site L.S. = Tk. 122.50
(c) Ffitting-fixing materials
(i) 1/2" ball cock 1 No. @ Tk. 231.50 Per rft. = Tk. 231.50
(ii) 1/2" G.I. pipe with jum-nuts 1 No. @ Tk. 80.42 each = Tk. 80.42
(iii) Other small fittings in/c out-let pipe & flange etc. L.S. = Tk. 183.75
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 0.75 No. @ Tk. 440.00 each = Tk. 330.00
(ii) Skilled labour 1.5 Nos. @ Tk. 303.00 each = Tk. 454.50
Total = Tk. 9,043.60
Profit 10.00% = Tk. 904.36
Overhead 3.50% = Tk. 316.53
= Tk. 10,264.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 597.40
Grand total = Tk. 10,861.89
Rate per No. = Tk. 10,861.89

Say, Tk. 10,862 .00 each


Analysis of PWD SoR 2014 for Civil Works 478

26.69.2 Food-grade foreign made stainless steel water tank: 1000 liter capacity
Considering 1 No. of fixture
(a) 1000 liter stainless steel water tank 1 No. @ Tk. 14,036.63 each = Tk. 14,036.63
(b) Carrying up to site L.S. = Tk. 183.75
(c) Ffitting-fixing materials
(i) 1/2" ball cock 1 No. @ Tk. 231.50 Per rft. = Tk. 231.50
(ii) 1/2" dia G.I. pipe with jum-nuts 1 No. @ Tk. 80.42 each = Tk. 80.42
(iii) Other small fittings in/c out-let pipe & flange etc. L.S. = Tk. 245.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(ii) Skilled labour 2 Nos. @ Tk. 303.00 each = Tk. 606.00
Total = Tk. 15,823.30
Profit 10.00% = Tk. 1,582.33
Overhead 3.50% = Tk. 553.82
= Tk. 17,959.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,045.26
Grand total = Tk. 19,004.71
Rate per No. = Tk. 19,004.71

Say, Tk. 19,005 .00 each

26.69.3 Food-grade foreign made stainless steel water tank: 2000 liter capacity
Considering 1 No. of fixture
(a) 2000 liter stainless steel water tank 1 No. @ Tk. 24,056.59 each = Tk. 24,056.59
(b) Carrying L.S. = Tk. 367.50
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 No. @ Tk. 231.50 Per rft. = Tk. 231.50
(ii) 1/2" dia G.I. pipe with jum-nuts 1 No. @ Tk. 80.42 each = Tk. 80.42
(iii) Other small fittings in/c out-let pipe & flange etc. L.S. = Tk. 367.50
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1.5 No. @ Tk. 440.00 each = Tk. 660.00
(ii) Skilled labour 3 Nos. @ Tk. 303.00 each = Tk. 909.00
Total = Tk. 26,672.51
Profit 10.00% = Tk. 2,667.25
Overhead 3.50% = Tk. 933.54
= Tk. 30,273.30
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,761.94
Grand total = Tk. 32,035.24
Rate per No. = Tk. 32,035.24

Say, Tk. 32,035 .00 each

26.69.4 Food-grade foreign made stainless steel water tank: 4000 liter capacity
Considering 1 No. of fixture
(a) 4000 liter stainless steel tank 1 No. @ Tk. 49,191.06 each = Tk. 49,191.06
(b) Carrying up to site L.S. = Tk. 612.50
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 No. @ Tk. 231.50 Per rft. = Tk. 231.50
(ii) 1/2" dia G.I. pipe with jum-nuts 1 No. @ Tk. 80.42 each = Tk. 80.42
(iii) Other small fittings in/c out-let pipe & flange etc. L.S. = Tk. 490.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 2 No. @ Tk. 440.00 each = Tk. 880.00
(ii) Skilled labour 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00
Total = Tk. 52,697.48
Profit 10.00% = Tk. 5,269.75
Overhead 3.50% = Tk. 1,844.41
= Tk. 59,811.64
Analysis of PWD SoR 2014 for Civil Works 479

Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,481.10


Grand total = Tk. 63,292.74
Rate per No. = Tk. 63,292.74

Say, Tk. 63,293 .00 each

26.69.5 Food-grade foreign made stainless steel water tank: 6000 liter capacity
Considering 1 No. of fixture
(a) 6000 liter stainless steel water tank 1 No. @ Tk. 53,481.79 each = Tk. 53,481.79
(b) Carrying up to site L.S. = Tk. 735.00
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 No. @ Tk. 231.50 Per rft. = Tk. 231.50
(ii) Over-flow 1/2" dia
(iii) G.I. pipe with jum-nuts 1 No. @ Tk. 80.42 each = Tk. 80.42
(iv) Other small fittings in/c out-let pipe & flange etc. L.S. = Tk. 612.50
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 2 No. @ Tk. 440.00 each = Tk. 880.00
(ii) Skilled labour 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00
Total = Tk. 57,233.21
Profit 10.00% = Tk. 5,723.32
Overhead 3.50% = Tk. 2,003.16
= Tk. 64,959.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,780.72
Grand total = Tk. 68,740.41
Rate per No. = Tk. 68,740.41

Say, Tk. 68,740 .00 each

Item No.- 26.70


Food-grade ferro-cement water tank: 400 Gallon capacity
Considering 1 No. of fixture
(a) 400 gallon capacty ferro-cement
water tank in/c installation 1 No. @ Tk. 6,320.90 each = Tk. 6,320.90
(b) Carrying (for Dhaka city) L.S. = Tk. 245.00
Total = Tk. 6,565.90
Profit 10.00% = Tk. 656.59
Overhead 3.50% = Tk. 229.81
= Tk. 7,452.30
Add VAT with adjustment factor 1.0582 5.50% = Tk. 433.73
Grand total = Tk. 7,886.03
Rate per No. = Tk. 7,886.03

Say, Tk. 7,886 .00 each

Item No.- 26.71


Supplying, fitting-fixing flexible plastic connection pipe of following sizes:
12 mm dia 450 mm long plastic connection pipe
Considering 1'-6" long 1 No. pipe
(a) 12 mm dia 450 mm long pipe 1 No. @ Tk. 48.74 each = Tk. 48.74
(b) Labour:
(i) Plumber 0.005 No. @ Tk. 440.00 each = Tk. 2.20
(ii) Skilled labour 0.01 No. @ Tk. 303.00 each = Tk. 3.03
Total = Tk. 53.97
Profit 10.00% = Tk. 5.40
Overhead 3.50% = Tk. 1.89
= Tk. 61.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3.57
Analysis of PWD SoR 2014 for Civil Works 480

Grand total = Tk. 64.83


Rate Per No. = Tk. 64.83

Say, Tk. 65 .00 each

Item No.- 26.72


12 mm dia 600 mm long plastic connection pipe
Considering 2'-0" long 1 No. pipe
(a) 12 mm dia 600 mm long pipe 1 No. @ Tk. 57.62 each = Tk. 57.62
(b) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.01 No. @ Tk. 303.00 each = Tk. 3.03
Total = Tk. 82.65
Profit 10.00% = Tk. 8.27
Overhead 3.50% = Tk. 2.89
= Tk. 93.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5.46
Grand total = Tk. 99.27
Rate Per No. = Tk. 99.27

Say, Tk. 99 .00 each

Item No.- 26.73


12 mm dia 450 mm long metal cover connection pipe
Considering 1'-6" long 1 No. pipe
(a) 12 mm dia 450 mm long pipe 1 No. @ Tk. 266.46 each = Tk. 266.46
(b) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.01 No. @ Tk. 303.00 each = Tk. 3.03
Total = Tk. 291.49
Profit 10.00% = Tk. 29.15
Overhead 3.50% = Tk. 10.20
= Tk. 330.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.26
Grand total = Tk. 350.10
Rate Per No. = Tk. 350.10

Say, Tk. 350 .00 each

Item No.- 26.74


12 mm dia 600 mm long metal cover connection pipe
Considering 2'-0" long 1 No. pipe
(a) 12 mm dia 450 mm long pipe 1 No. @ Tk. 307.52 each = Tk. 307.52
(b) Labour:
(i) Plumber 0.05 No. @ Tk. 440.00 each = Tk. 22.00
(ii) Skilled labour 0.01 No. @ Tk. 303.00 each = Tk. 3.03
Total = Tk. 332.55
Profit 10.00% = Tk. 33.26
Overhead 3.50% = Tk. 11.64
= Tk. 377.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 21.97
Grand total = Tk. 399.42
Rate Per No. = Tk. 399.42
Say, Tk. 399 .00 each

INSPECTION PIT & SOAK WELL


Item No.- 26.75
Analysis of PWD SoR 2014 for Civil Works 481

Construction of Inspection pit of following dimension


26.75.1 Inspection pit of internal size: 450 x 450 mm & depth 450 to 600 mm (av. 525 mm)
for single 6" dia size RCC pipes
Considering 1 No. pit
1. Earth-work:
1 x 3-4" x 3'-4" x 2'-3"= 24.95 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 56.68
2. Brick-flat soling:
1 x 3'-2" x 3'-2"= 10.04 sft. @ Tk. 2,744.25 Per % sft. = Tk. 275.52
3. C.C. (1:3:6) on soling:
1 x 3'-2" x 3'-2" x 0'-3"= 2.51 cft. @ Tk. 14,713.64 Per % cft. = Tk. 369.31
4. C.C. (1:3:6) for invert:
1 x 1'-6" x 1'-6" x 0'-2"= 0.38 cft. @ Tk. 14,713.64 Per % cft. = Tk. 55.91
5. Brick-work (1:6):
2 x (3'-2" + 1'-6") x 1'-9" x 0'-10"= 13.57 cft. @ Tk. 12,557.68 Per % cft. = Tk. 1,704.08
6. 12 mm plaster with n.c.f.:
4 x (1'-6" x 1'- 6") + 1' - 6" x 1'- 6"= 12.75 sft. @ Tk. 1,906.00 Per % sft. = Tk. 243.02
7. Labour for making invert & side back-filling:
a) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
b) Skilled labour 0.125 No. @ Tk. 303.00 each = Tk. 37.88
c) Ordinary labour 0.25 No. @ Tk. 245.00 each = Tk. 61.25
Total = Tk. 2,858.65
Profit 10.00% = Tk. 285.87
Overhead 3.50% = Tk. 100.05
= Tk. 3,244.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 188.84
Grand total = Tk. 3,433.41
Rate per No. = Tk. 3,433.41

Say, Tk. 3,433 .00 each

26.75.2 Inspection pit of internal size: 525 x 525 mm & depth 675 to 825 mm (av. 750 mm)
for single 9" dia size RCC or 300 mm plastic/PVC pipes
Considering 1 No. pit
1. Earth-work:
1 x 3-7" x 3'-7" x 3'-0"= 38.45 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 87.34
2. Brick-flat soling:
1 x 3'-5" x 3'-5"= 11.7 sft. @ Tk. 2,744.25 Per % sft. = Tk. 321.08
3. C.C. (1:3:6) on soling:
1 x 3'-5" x 3'-5" x 0'-3"= 2.92 cft. @ Tk. 14,713.64 Per % cft. = Tk. 429.64
4. C.C. (1:3:6) for invert:
1 x 1'-9" x 1'-9" x 0'-2"= 0.51 cft. @ Tk. 14,713.64 Per % cft. = Tk. 75.04
5. Brick-work (1:6):
2 x (3'-5" + 1'-9") x 2'-6" x 0'-10"= 21.46 cft. @ Tk. 12,557.68 Per % cft. = Tk. 2,694.88
6. 12 mm plaster with n.c.f.:
4 x (1'-9" x 2'-6") + 1'-9" x 1'-9"= 20.56 sft. @ Tk. 1,906.00 Per % sft. = Tk. 391.87
7. Extra labour for making invert & side back-filling:
a) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
b) Skilled labour 0.2 No. @ Tk. 303.00 each = Tk. 60.60
c) Ordinary labour 0.235 No. @ Tk. 245.00 each = Tk. 57.58
Total = Tk. 4,173.03
Profit 10.00% = Tk. 417.30
Overhead 3.50% = Tk. 146.06
= Tk. 4,736.39
Add VAT with adjustment factor 1.0582 5.50% = Tk. 275.66
Grand total = Tk. 5,012.05
Rate per No. = Tk. 5,012.05
Analysis of PWD SoR 2014 for Civil Works 482

Say, Tk. 5,012 .00 each

26.75.3 Inspection pit of internal size: 600 x 600 mm & depth 750 to 900 mm (av. 825 mm)
for single 12" dia size RCC or 375 mm plastic/PVC pipes
Considering 1 No. pit
1. Earth-work:
1 x 3'-11" x 3'-11" x 3'-3"= 49.94 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 113.44
2. Brick-flat soling:
1 x 3'-8" x 3'-8"= 13.47 sft. @ Tk. 2,744.25 Per % sft. = Tk. 369.65
3. C.C. (1:3:6) on soling:
1 x 3'-8" x 3'-8" x 0'-3"= 3.37 cft. @ Tk. 14,713.64 Per % cft. = Tk. 495.85
4. C.C. (1:3:6) for invert:
1 x 2'-0" x 2'-0" x 0'-2"= 0.67 cft. @ Tk. 14,713.64 Per % cft. = Tk. 98.58
5. Brick-work (1:6):
2 x (3'-8" + 2'-0") x 2'-9" x 0'-10"=
31.19 cft. @ Tk. 12,557.68 Per % cft. = Tk. 3,916.74
6. 12 mm plaster with n.c.f.:
4 x (2'-0" x 2'-9") + 2'-6" x 2'-6"= 28.25 sft. @ Tk. 1,906.00 Per % sft. = Tk. 538.45
7. Extra labour for making invert & side back-filling:
(a) Plumber 0.14 No. @ Tk. 440.00 each = Tk. 61.60
(b) Skilled labour 0.23 No. @ Tk. 303.00 each = Tk. 69.69
(c) Ordinary labour 0.27 No. @ Tk. 245.00 each = Tk. 66.15
Total = Tk. 5,730.15
Profit 10.00% = Tk. 573.02
Overhead 3.50% = Tk. 200.56
= Tk. 6,503.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 378.52
Grand total = Tk. 6,882.25
Rate per No. = Tk. 6,882.25

Say, Tk. 6,882 .00 each

26.75.4 Master-pit of Size: 600 x 500 mm & average depth 750 mm for Septic tank.
Considering 1 No. pit
1. Earth-work:
1 x 2'-3" x 4'-0" x 3'-0"= 27.96 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 63.51
2. Brick-flat soling:
1 x 3'-8" x 2'-6"= 9.175 sft. @ Tk. 2,744.25 Per % sft. = Tk. 251.78
3. C.C. (1:3:6) on soling:
1 x 1'-6" x 2'-0" x 0'-3"= 0.94 cft. @ Tk. 14,713.64 Per % cft. = Tk. 138.31
4. C.C. (1:3:6) for channel making:
1 x 1'-6" x 2'-6" x 0'-4"= 1.24 cft. @ Tk. 14,713.64 Per % cft. = Tk. 182.45
5. Brick-work (1:6):
2 x 1'-8" x 2'-2" x 0'-10"= 6.02 cft.
1 x 3' - 8" x 2' - 2" x 10" = 6.61 cft.
12.63 cft. @ Tk. 12,557.68 Per % cft. = Tk. 1,586.03
6. 12 mm plaster with n.c.f.:
(2' - 0" + 1' - 8" + 1' - 8") x 2' - 2" = 11.5661 sft.
(2' - 6" + 2' - 6" + 3' - 8") x 1' - 0" = 8.67 sft.
1' - 6" x 2' - 6" = 3.75 sft.
23.99 sft. @ Tk. 1,906.00 Per % sft. = Tk. 457.25
7. Extra labour for making channel & back-fill to side:
(a) Plumber 0.125 No. @ Tk. 440.00 each = Tk. 55.00
(b) Skilled labour 0.125 No. @ Tk. 303.00 each = Tk. 37.88
(c) Ordinary labour 0.125 No. @ Tk. 245.00 each = Tk. 30.63
8. Reinforcement: 3/8" dia M.S. rod
4 x 2' -6" x 0.375 Ibs/rft. = 3.75 Ibs
Analysis of PWD SoR 2014 for Civil Works 483

4 x 3' - 8" x 0.375Ib/rft = 5.505 Ibs


9.255 Ibs @ Tk. 30.93 Per Ibs. = Tk. 286.26
Total = Tk. 3,089.10
Profit 10.00% = Tk. 308.91
Overhead 3.50% = Tk. 108.12
= Tk. 3,506.13
Add VAT with adjustment factor 1.0582 5.50% = Tk. 204.06
Grand total = Tk. 3,710.19
Rate per No. = Tk. 3,710.19

Say, Tk. 3,710 .00 each

Item No.- 26.76


Construction and placing RCC pit covers on pit
26.76.1 900 x 900 x 75 mm size pit cover
Considering 1 No. pit cover
1. R.C.C. (1:2:4) for slab:
3'-2" x 3'-2" x 0'-3"= 2.51 cft. @ Tk. 17,255.06 Per % cft. = Tk. 433.10
2. 1% re-inforcement in/c fabrication 12.3 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 380.44
3. 12 mm plaster with n.c.f.:
4 x 3'-2" x 0'-3" + 3'-2" x 3'-2"= 13.22 sft. @ Tk. 1,906.00 Per % sft. = Tk. 251.97
4. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 1,090.01
Profit 10.00% = Tk. 109.00
Overhead 3.50% = Tk. 38.15
= Tk. 1,237.16
Add VAT with adjustment factor 1.0582 5.50% = Tk. 72.00
Grand total = Tk. 1,309.16
Rate per No. = Tk. 1,309.16

Say, Tk. 1,309 .00 each

26.76.2 1025 x 1025 x 75 mm size pit cover


Considering 1 No. pit cover
1. R.C.C. (1:2:4) for slab:
1 x 3'-5" x 3'-5" x 0'-3" = 2.92 cft. @ Tk. 17,255.06 Per % cft. = Tk. 503.85
2. 1% re-inforcement in/c fabrication 14.31 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 442.61
3. 12 mm plaster with n.c.f.:
4 x 3'-5" x 0'-3" + 3'-5" x 3'-5" = 15.12 sft. @ Tk. 1,906.00 Per % sft. = Tk. 288.19
4. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 1,259.15
Profit 10.00% = Tk. 125.92
Overhead 3.50% = Tk. 44.07
= Tk. 1,429.14
Add VAT with adjustment factor 1.0582 5.50% = Tk. 83.18
Grand total = Tk. 1,512.32
Rate per No. = Tk. 1,512.32

Say, Tk. 1,512 .00 each


26.76.3 1100 x 1100 x 75 mm size pit cover
Considering 1 No. pit cover
1. R.C.C. (1:2:4) for slab:
1 x 3'-8" x 3'-8" x 0'-3"= 3.37 cft. @ Tk. 17,255.06 Per % cft. = Tk. 581.50
2. 1% re-inforcement in/c fabrication 16.51 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 510.65
3. 12 mm plaster with n.c.f.:
Analysis of PWD SoR 2014 for Civil Works 484

4 x 3'-8" x 0'-3" + 3'-8" x 3'-8"= 17.14 sft. @ Tk. 1,906.00 Per % sft. = Tk. 326.69
4. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 1,443.34
Profit 10.00% = Tk. 144.33
Overhead 3.50% = Tk. 50.52
= Tk. 1,638.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 95.34
Grand total = Tk. 1,733.53
Rate per No. = Tk. 1,733.53

Say, Tk. 1,734 .00 each

Item No.- 26.77


26.77.1 1100 x 1100 x 75 mm size pit cover with 18" dia C.I. man-hole cover.
Considering 1 No. pit cover with man-hole cover
1. R.C.C. (1:2:4) for slab:
1 x (3'-2" x 3'-2"- 0.785 x 1'-6" x 1'-6") x 0'-3" =
2.07 cft. @ Tk. 17,255.06 Per % cft. = Tk. 357.18
2. 1% re-inforcement in/c fabrication 10.14 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 313.63
3. 12 mm plaster with n.c.f.:
4 x (3'-2" x 0'-3" + 3'-2" x 3'-2" - 0.785 x 1'-6" x 1'-6") =
13.22 sft. @ Tk. 1,906.00 Per % sft. = Tk. 251.97
4. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
5. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 1,974.12
Profit 10.00% = Tk. 197.41
Overhead 3.50% = Tk. 69.09
= Tk. 2,240.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 130.41
Grand total = Tk. 2,371.03
Rate per No. = Tk. 2,371.03

Say, Tk. 2,371 .00 each

26.77.2 1050 x 1050 x 75 mm size pit cover with 18" dia C.I. man-hole cover.
Considering 1 No. pit cover with man-hole cover
1. R.C.C. (1:2:4) for slab:
1 x (3'-5" x 3'-5"- 0.785 x 1'-6" x 1'-6") x 0'-3" =
2.48 cft. @ Tk. 17,255.06 Per % cft. = Tk. 427.93
2. 1% re-inforcement in/c fabrication 12.15 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 375.80
3. 12 mm plaster with n.c.f.:
4 x (3'-5" x 0'-3" + 3'-5" x 3'-5" - 0.785 x 1'-6" x 1'-6") =
13.35 sft. @ Tk. 1,906.00 Per % sft. = Tk. 254.45
4. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
5. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 2,109.52
Profit 10.00% = Tk. 210.95
Overhead 3.50% = Tk. 73.83
= Tk. 2,394.30
Add VAT with adjustment factor 1.0582 5.50% = Tk. 139.35
Grand total = Tk. 2,533.65
Rate per No. = Tk. 2,533.65
Analysis of PWD SoR 2014 for Civil Works 485

Say, Tk. 2,534 .00 each

26.77.3 1100 x 1100 x 75 mm size pit cover with 18" dia C.I. man-hole cover.
Considering 1 No. pit cover with man-hole cover
1. R.C.C. (1:2:4) for slab:
1 x (3'-8" x 3'-8"- 0.785 x 1'-6" x 1'-6") x 0'-3" =
2.93 cft. @ Tk. 17,255.06 Per % cft. = Tk. 505.57
2. 1% re-inforcement in/c fabrication 14.36 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 444.15
3. 12 mm plaster with n.c.f.:
4 x (3'-8" x 0'-3" + 3'-8" x 3'-8" - 0.785 x 1'-6" x 1'-6") =
15.37 sft. @ Tk. 1,906.00 Per % sft. = Tk. 292.95
4. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
5. Extra labour for placing pit cover
Ordinary labour 0.1 No. @ Tk. 245.00 each = Tk. 24.50
Total = Tk. 2,294.01
Profit 10.00% = Tk. 229.40
Overhead 3.50% = Tk. 80.29
= Tk. 2,603.70
Add VAT with adjustment factor 1.0582 5.50% = Tk. 151.54
Grand total = Tk. 2,755.24
Rate per No. = Tk. 2,755.24

Say, Tk. 2,755 .00 each

Item No.- 26.78


26.78.1 450 x 450 mm and depth 450 - 600 mm, average 525 mm for single 150 mm dia RCC pipes and 400 mm
dia PVC pipe with pitcover and 450 mm dia C.I. Man-hole cover
Item No. 241/A1 + 242/B1 = Tk. 5,804
Say, Tk. 5,804 .00 each

26.78.2 520 x 525 mm and depth 675 - 825 mm, average 750 mm for single 225 mm dia RCC pipes and 400 mm
dia PVC pipe with pitcover and 450 mm dia C.I. Man-hole cover
Item No. 241/A2 + 242/B2 = Tk. 7,546
Say, Tk. 7,546 .00 each

26.78.3 600 x 600 mm and depth 750 - 900 mm, average 825 mm for single 300 mm dia RCC pipes and 400 mm
dia PVC pipe with pitcover and 450 mm dia C.I. Man-hole cover
Item No. 241/A3 + 242/B3 = Tk. 9,637.00
Say, Tk. 9,637 .00 each

Item No.- 26.79


Construction of septic tank of following sizes:
26.79.1 Septic tank of 200 users excluding master-pit
Considering 1 No. septic tank
1. Earth-work:
1 x 25-2" x 10'-8" x 6'-9" = 1812.81 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 4,117.94
2. Brick-flat soling:
1 x 24'-8" x 10'-2" = 250.89 sft. @ Tk. 2,744.25 Per % sft. = Tk. 6,885.05
3. 6" R. C.C. (1:2:4) on soling:
1 x 24'-8" x 10'-2" x 0'-6" = 125.45 cft. @ Tk. 17,255.06 Per % cft. = Tk. 21,646.47
4. 5" thick R.C.C.(1:2"4) lining
2 x (23'-0" + 6'-0") x 6'-8" x 5" = 162.48 cft. @ Tk. 17,255.06 Per % cft. = Tk. 28,036.02
5. Tie beam (1:2:4)
1 x 9" x 9" x 7'-0" = 3.94 cft @ Tk. 17,255.06 Per % cft. = Tk. 679.85
6. R.C.C. in roof slab
Analysis of PWD SoR 2014 for Civil Works 486

1 x 24' - 8" x 8' - 6" x 4" = 69.20 cft. @ Tk. 17,255.06 Per % cft. = Tk. 11,940.50
7. Formwork 230.00 sft. @ Tk. 35.48 Per sft. = Tk. 8,160.40
8. Brick-work (1:6):
2 x 24'-8" x 2'-0" x 10" = 81.90 cft.
2 x 24'-8" x 1'-0" x 5" = 20.72 cft.
2 x (24'-8" + 6'-10") x 6'-8" x 10" 348.8 cft.
Total = 451.42 cft. @ Tk. 12,557.68 Per % cft. = Tk. 56,687.88
9. 5" thick brick-work (1:6)
6'-0" x 4'-5" = 26.52 sft.
6'-0" x 5'-6" = 33.00 sft.
59.52 sft. @ Tk. 6,175.43 Per % sft. = Tk. 3,675.62
10. 12 mm plaster with n.c.f.:
Floor: 1 x 22' - 2" x 6' - 0" = 133.02 sft.
Walls:2x(22'-2"+ 5'-11") x 6'-7.5" = 371.78 sft.
Tie: 1 x 6' - 0" x 2' - 7" = 15.48 sft.
Outside: 2x(24'-8"+ 8'-6")x1'-6" = 99.51 sft.
619.79 sft. @ Tk. 1,906.00 Per % sft. = Tk. 11,813.20
11. RCC Tees 2 Nos. @ Tk. 436.03 each = Tk. 872.06
12. 40 grade re-inforcement & fabrication 1212.00 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 37,487.16
13. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 3 Nos. @ Tk. 1,026.84 each = Tk. 3,080.52
14. Side filling, dressing, inside cleaning etc. L.S. = Tk. 1,225.00
Total = Tk. 196,307.67
Profit 10.00% = Tk. 19,630.77
Overhead 3.50% = Tk. 6,870.77
= Tk. 222,809.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12,967.72
Grand total = Tk. 235,776.93
Rate per No. = Tk. 235,776.93

Say, Tk. 235,777 .00 each

26.79.2 Septic tank of 100 users excluding master-pit


Considering 1 No. septic tank
1. Earth-work:
1 x 20-5" x 8'-10" x 6'-0" = 1081.85 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 2,457.51
2. Brick-flat soling
1 x 19'-11" x 8'-4" = 165.93 sft. @ Tk. 2,744.25 Per % sft. = Tk. 4,553.53
3. 6" R. C.C. (1:2:4) on soling:
1 x 19'-11" x 8'-4" x 0'-6" = 82.97 cft. @ Tk. 17,255.06 Per % cft. = Tk. 14,316.52
4. 5" thick R.C.C.(1:2"4) lining
2 x (18'-3" + 4'-2") x 7'-0" x 5" = 131.83 cft. @ Tk. 17,255.06 Per % cft. = Tk. 22,747.35
5. Tie beam (1:2:4)
1 x 9" x 9" x 5'-2" = 2.91 cft @ Tk. 17,255.06 Per % cft. = Tk. 502.12
6. R.C.C. in roof slab
1 x 19' - 11" x 6' - 8" x 4" = 43.85 cft. @ Tk. 17,255.06 Per % cft. = Tk. 7,566.34
7. Formwork 145.00 sft. @ Tk. 35.48 Per sft. = Tk. 5,144.60
8. Brick-work (1:6):
2 x 19'-11" x 2'-0" x 10" = 66.13 cft.
2 x 19'-11" x 1'-0" x 5" = 16.73 cft.
2 x (19'-11" + 5'-0") x 6'-8" = 332.43 cft.
Total = 415.29 cft. @ Tk. 12,557.68 Per % cft. = Tk. 52,150.79
9. 5" thick brick-work (1:6)
4'-2" x 4'-5" = 18.43 sft.
4'-2" x 5'-2" = 21.56 sft.
39.99 sft. @ Tk. 6,175.43 Per % sft. = Tk. 2,469.55
10. 12 mm plaster with n.c.f.:
Analysis of PWD SoR 2014 for Civil Works 487

Floor: 1 x 17' - 5" x 4' - 2" = 72.64 sft.


Walls: 2 x (17' - 5" + 4'-1") x 6' - 7.5" = 284.66 sft.
Tie: 1 x 4' -0" x 2' - 7" = 8.68 sft.
Outside: 2 x (19'-11" + 6'-8") x 1'-6" = 79.74 sft.
445.72 sft. @ Tk. 1,906.00 Per % sft. = Tk. 8,495.42
11. RCC Tees 2 Nos. @ Tk. 436.03 each = Tk. 872.06
12. 40 grade re-inforcement & fabrication 883.00 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 27,311.19
13. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 3 Nos. @ Tk. 1,026.84 each = Tk. 3,080.52
14. Side filling, dressing, inside cleaning etc. L.S. = Tk. 980.00
Total = Tk. 152,647.50
Profit 10.00% = Tk. 15,264.75
Overhead 3.50% = Tk. 5,342.66
= Tk. 173,254.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10,083.61
Grand total = Tk. 183,338.52
Rate per No. = Tk. 183,338.52

Say, Tk. 183,339 .00 each

26.79.3 Septic tank of 50 users excluding master-pit


Considering 1 No. septic tank
1. Earth-work:
1 x 14'-0" x 8'-10" x 6'-5" = 793.64 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,802.82
2. Brick-flat soling
1 x 13'-6" x 8'-4" = 112.46 sft. @ Tk. 2,744.25 Per % sft. = Tk. 3,086.18
3. 6" R. C.C. (1:2:4) on soling:
1 x 13'-6" x 8'-4" x 0'-6" = 56.23 cft. @ Tk. 17,255.06 Per % cft. = Tk. 9,702.52
4. 5" thick R.C.C.(1:2"4) lining
2 (11'-10" + 4' - 2") x 6' - 4" x 5" = 85.08 cft. @ Tk. 17,255.06 Per % cft. = Tk. 14,680.61
5. Tie beam (1:2:4)
1 x 9" x 9" x 5'-0" = 2.81 cft @ Tk. 17,255.06 Per % cft. = Tk. 484.87
6. R.C.C. in roof slab
1 x 13' - 6" x 6' - 8" x 4" = 29.71 cft. @ Tk. 17,255.06 Per % cft. = Tk. 5,126.48
7. Formwork 140.00 sft. @ Tk. 35.48 Per sft. = Tk. 4,967.20
8. Brick-work (1:6):
2 x 13'-6" x 2'-0" x 10" = 44.82 cft.
2 x 13'-6" x 1'-0" x 5" = 11.34 cft.
2 x (13'-6" + 5'-0") x 6'-0" x 10" = 184.26 cft.
Total = 240.42 cft. @ Tk. 12,557.68 Per % cft. = Tk. 30,191.17
9. 5" thick brick-work (1:6)
4'-2" x 4'-1" = 17.01 sft.
4'-2" x 4'-10" = 20.14 sft.
37.15 sft. @ Tk. 6,175.43 Per % sft. = Tk. 2,294.17
10. 12 mm plaster with n.c.f.:
Floor: 1 x 11' - 0" x 4' - 2" = 45.87 sft.
Walls: 2 x (11' - 0" + 4'-1") x 6' - 3.5" = 189.71 sft.
Tie: 1 x 2' - 7" x 4' - 2" = 10.76 sft.
Outside: 2 x (13'-6" + 6'-8") x 1'-6" = 60.51 sft.
306.85 sft. @ Tk. 1,906.00 Per % sft. = Tk. 5,848.56
11. RCC Tees 2 Nos. @ Tk. 436.03 each = Tk. 872.06
12. 40 grade re-inforcement & fabrication 587.00 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 18,155.91
13. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 3 Nos. @ Tk. 1,026.84 each = Tk. 3,080.52
14. Side filling, dressing, inside cleaning etc. L.S. = Tk. 857.50
Total = Tk. 101,150.57
Profit 10.00% = Tk. 10,115.06
Analysis of PWD SoR 2014 for Civil Works 488

Overhead 3.50% = Tk. 3,540.27


= Tk. 114,805.90
Add VAT with adjustment factor 1.0582 5.50% = Tk. 6,681.82
Grand total = Tk. 121,487.72
Rate per No. = Tk. 121,487.72

Say, Tk. 121,488 .00 each

26.79.4 Septic tank of 30 users excluding master-pit


Considering 1 No. septic tank
1. Earth-work:
1 x 12'-0" x 7'-2" x 6'-1.5" = 526.56 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,196.12
2. Brick-flat soling
1 x 11'-6" x 6'-8" = 76.71 sft. @ Tk. 2,744.25 Per % sft. = Tk. 2,105.11
3. 6" R. C.C. (1:2:4) on soling:
1 x 11'-6" x 6'-8" x 0'-6" = 37.38 cft. @ Tk. 17,255.06 Per % cft. = Tk. 6,449.94
4. 5" thick R.C.C.(1:2"4) lining
2 (9'-10" + 2' - 6") x 5' - 8" x 5" = 58.73 cft. @ Tk. 17,255.06 Per % cft. = Tk. 10,133.90
5. Tie beam (1:2:4)
1 x 9" x 9" x 3'-6" = 1.97 cft @ Tk. 17,255.06 Per % cft. = Tk. 339.92
6. R.C.C. in roof slab
1 x 11' - 6" x 5' - 0" x 4" = 18.98 cft. @ Tk. 17,255.06 Per % cft. = Tk. 3,275.01
7. Formwork 70.00 sft. @ Tk. 35.48 Per sft. = Tk. 2,483.60
8. Brick-work (1:6):
2 x 11' - 6" x 2'-0" x 10" = 38.18 cft.
2 x 11' - 6" x 1'-0" x 5" = 9.66 cft.
2 x (11' - 6" + 3' - 2") x 5' - 8" x 10" = 138.08 cft.
Total = 185.92 cft. @ Tk. 12,557.68 Per % cft. = Tk. 23,347.24
9. 5" thick brick-work (1:6)
1 x 2' - 6" x 3'-5" = 8.55 sft. @ Tk. 6,175.43 Per % sft. = Tk. 528.00
10. 12 mm plaster with n.c.f.:
Floor: 1 x 9' - 0" x 2' - 6" = 22.50 sft.
Walls: 2 x (9' - 0" + 2'-1") x 5' - 8" = 125.65 sft.
Tie: 1 x 2' - 7" x 2' - 5" = 6.24 sft.
Outside: 2 x (11'-6" + 5'-0") x 1'-6" = 49.50 sft.
203.89 sft. @ Tk. 1,906.00 Per % sft. = Tk. 3,886.14
11. RCC Tees 2 Nos. @ Tk. 436.03 each = Tk. 872.06
12. 40 grade re-inforcement & fabrication 432.00 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 13,361.76
13. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 2 Nos. @ Tk. 1,026.84 each = Tk. 2,053.68
14. Side filling, dressing, inside cleaning etc. L.S. = Tk. 735.00
Total = Tk. 70,767.48
Profit 10.00% = Tk. 7,076.75
Overhead 3.50% = Tk. 2,476.86
= Tk. 80,321.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4,674.77
Grand total = Tk. 84,995.86
Rate per No. = Tk. 84,995.86

Say, Tk. 84,996 .00 each

26.79.5 Septic tank of 20 users excluding master-pit


Considering 1 No. septic tank
1. Earth-work:
1 x 11'-0" x 7'-2" x 6'-1.5" = 482.68 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,096.45
2. Brick-flat soling
1 x 10'-6" x 6'-6" = 68.25 sft. @ Tk. 2,744.25 Per % sft. = Tk. 1,872.95
Analysis of PWD SoR 2014 for Civil Works 489

3. 6" R. C.C. (1:2:4) on soling:


1 x 10'-6" x 6'-6" x 0'-6" = 34.13 cft. @ Tk. 17,255.06 Per % cft. = Tk. 5,889.15
4. 5" thick R.C.C.(1:2:4) lining
2 x (8'-10" + 2'-6") x 5' - 8" x 5" = 53.96 cft. @ Tk. 17,255.06 Per % cft. = Tk. 9,310.83
5. Tie beam (1:2:4)
1 x 9" x 9" x 3'-6" = 1.97 cft @ Tk. 17,255.06 Per % cft. = Tk. 339.92
6. R.C.C. in roof slab
1 x 10' - 6" x 6' - 8" x 4" = 23.11 cft. @ Tk. 17,255.06 Per % cft. = Tk. 3,987.64
7. Formwork 80.00 sft. @ Tk. 35.48 Per sft. = Tk. 2,838.40
8. Brick-work (1:6):
2 x 10'-6" x 2'-0" x 10" = 34.86 cft.
2 x 10'-6" x 1'-0" x 5" = 8.82 cft.
2 x (10'-6" + 3' - 2") x 5'-8" x 10" = 128.66 cft.
Total = 172.34 cft. @ Tk. 12,557.68 Per % cft. = Tk. 21,641.91
9' 5" thick brick-work (1:6)
2'-6" x 3'-5" = 8.55 sft. @ Tk. 6,175.43 Per % sft. = Tk. 528.00
10. 12 mm plaster with n.c.f.:
Floor: 1 x 8' - 0" x 2' - 6" = 20.00 sft.
Walls: 2 x (8' - 0" + 2'-5") x 5' - 8" = 118.16 sft.
Tie: 1 x 2' - 7" x 2' - 5" = 6.24 sft.
Outside: 2 x (10'-6" + 5'-0") x 1'-6" = 46.50 sft.
190.90 sft. @ Tk. 1,906.00 Per % sft. = Tk. 3,638.55
11. RCC Tees 2 Nos. @ Tk. 436.03 each = Tk. 872.06
12. 40 grade re-inforcement & fabrication 389.00 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 12,031.77
13. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 2 Nos. @ Tk. 1,026.84 each = Tk. 2,053.68
14. Side filling, dressing, inside cleaning etc. L.S. = Tk. 612.50
Total = Tk. 66,713.81
Profit 10.00% = Tk. 6,671.38
Overhead 3.50% = Tk. 2,334.98
= Tk. 75,720.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4,406.99
Grand total = Tk. 80,127.16
Rate per No. = Tk. 80,127.16

Say, Tk. 80,127 .00 each

26.79.6 Septic tank of 10 users excluding master-pit


Considering 1 No. septic tank
1. Earth-work:
1 x 9'-0" x 5'-6" x 4'-9" = 235.13 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 534.12
2. Brick-flat soling:
1 x 8'-6" x 5'-0" = 42.5 sft. @ Tk. 2,744.25 Per % sft. = Tk. 1,166.31
3. 6" R. C.C. (1:2:4) on soling:
1 x 8'-6" x 5'-0" x 0'-6" = 21.25 cft. @ Tk. 17,255.06 Per % cft. = Tk. 3,666.70
4. 5" thick R.C.C.(1:2:4) lining
2 x 6'-0" x 4' - 0" x 5" = 20.16 cft.
2 x 2'-6" x 4' - 3.5" x 5" = 9.01 cft.
29.17 cft. @ Tk. 17,255.06 Per % cft. = Tk. 5,033.30
5. Tie beam (1:2"4)
1 x 9" x 9" x 3'-0" = 1.69 cft @ Tk. 17,255.06 Per % cft. = Tk. 291.61
6. R.C.C. in roof slab
1 x 8' - 6" x 5' - 0" x 4" = 14.03 cft. @ Tk. 17,255.06 Per % cft. = Tk. 2,420.88
7. Formwork 52.00 sft. @ Tk. 35.48 Per sft. = Tk. 1,844.96
8. 10" thick Brick-work (1:6):
2 x 8'-6" x 4'-0" x 0'-10" = 56.44 cft.
2 x 3'-4" x 4'-0" x 0'-10" = 22.11 cft.
Analysis of PWD SoR 2014 for Civil Works 490

Total = 78.55 cft. @ Tk. 12,557.68 Per % cft. = Tk. 9,864.06


9. 5" thick brick-work (1:6)
1 x 1'-5" x 2'-6" = 3.55 sft. @ Tk. 6,175.43 Per % sft. = Tk. 219.23
10. 12 mm thic plaster with n.c.f.:
Floor: 1 x 6' - 0" x 2' - 6" = 15.00 sft.
Walls: 2 x 5' - 11" x 4' - 0" = 47.36 sft.
2 x 2' - 5" x 4' - 0" = 19.36 sft.
Tie: 1 x 2' - 7" x 2' - 5" = 6.24 sft.
Outside: 2 x (8'-6" + 5'-0") x 1'-6" = 40.50 sft.
128.46 sft. @ Tk. 1,906.00 Per % sft. = Tk. 2,448.45
11. RCC Tees 2 Nos. @ Tk. 436.03 each = Tk. 872.06
12. 40 grade re-inforcement & fabrication 249.00 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 7,701.57
13. 18" dia water sealed heavy type C.I. man-hole cover with locking
14. arrangement in/c making holes. 2 Nos. @ Tk. 1,026.84 each = Tk. 2,053.68
Side filling, dressing, inside cleaning etc. L.S. = Tk. 612.50
Total = Tk. 38,729.43
Profit 10.00% = Tk. 3,872.94
Overhead 3.50% = Tk. 1,355.53
= Tk. 43,957.90
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,558.39
Grand total = Tk. 46,516.29
Rate per No. = Tk. 46,516.29

Say, Tk. 46,516 .00 each

Item No.- 26.80


Construction of Soak-well of following sizes:
26.80.1 Soak-well for 200 users
Considering 1 No. soak-well
1. Earth-work: 795.78 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,807.68
2. R.C.C. (1:2:4) in curb well with 1.25% re-inforcement
(excluding cost of re-inforcement) 14.78 cft. @ Tk. 17,255.06 Per % cft. = Tk. 2,550.30
3. 10" Honeycomb brick-work (1:6) in cement mortar
(87.57% of solid b/work). 113.95 cft. @ Tk. 10,996.76 Per % cft. = Tk. 12,530.81
4. 10" solid brick-work (1:6) 117.75 cft. @ Tk. 12,557.68 Per % cft. = Tk. 14,786.67
5. R.C.C. (1:2:4) in curb well with 1.25% re-inforcement
(excluding cost of reinforcement) 11.52 cft. @ Tk. 17,255.06 Per % cft. = Tk. 1,987.78
6. 40 grade re-inforcement &
fabrication 1.25% 161.09 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 4,982.51
7. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
8. Supply and filling graded
khoa and sand. 295 cft. @ Tk. 81.05 Per cft. = Tk. 23,909.75
Total = Tk. 63,582.34
Profit 10.00% = Tk. 6,358.23
Overhead 3.50% = Tk. 2,225.38
= Tk. 72,165.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4,200.13
Grand total = Tk. 76,366.08
Rate per No. = Tk. 76,366.08

Say, Tk. 76,366 .00 each

26.80.2 Soak-well for 100 users


Considering 1 No. soak-well
1. Earth-work: 699 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,587.83
2. R.C.C. (1:2:4) in curb well with 1.25% reinforcement
Analysis of PWD SoR 2014 for Civil Works 491

(excluding cost of reinforcement) 13.51 cft. @ Tk. 17,255.06 Per % cft. = Tk. 2,331.16
3. 10" Honeycomb brick-work (1:6) in cement mortar
(87.57% of solid b/work). 104.18 cft. @ Tk. 10,996.76 Per % cft. = Tk. 11,456.42
4. 10" solid brick-work (1:6) 107.66 cft. @ Tk. 12,557.68 Per % cft. = Tk. 13,519.60
5. R.C.C. (1:2:4) in curb well with 1.25% re-inforcement
(excluding cost of re-inforcement) 9.86 cft. @ Tk. 17,255.06 Per % cft. = Tk. 1,701.35
6. 40 grade reinforcement &
fabrication 1.25% 143.14 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 4,427.32
7. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
8. Supply and filling graded
khoa and sand. 251 cft. @ Tk. 81.05 Per cft. = Tk. 20,343.55
Total = Tk. 56,394.07
Profit 10.00% = Tk. 5,639.41
Overhead 3.50% = Tk. 1,973.79
= Tk. 64,007.27
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,725.29
Grand total = Tk. 67,732.56
Rate per No. = Tk. 67,732.56

Say, Tk. 67,733 .00 each

26.80.3 Soak-well for 50 users


Considering 1 No. soak-well
1. Earth-work: 608.9 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,383.17
2. R.C.C. (1:2:4) in curb well with 1.25% reinforcement
(excluding cost of reinforcement) 12.24 cft. @ Tk. 17,255.06 Per % cft. = Tk. 2,112.02
3. 10" Honeycomb brick-work (1:6) in cement
mortar (87.57% of solid b/work). 94.4 cft. @ Tk. 10,996.76 Per % cft. = Tk. 10,380.94
4. 10" solid brick-work (1:6) 97.56 cft. @ Tk. 12,557.68 Per % cft. = Tk. 12,251.27
5. R.C.C. (1:2:4) in curb well with 1.25% reinforcement
(excluding cost of reinforcement) 8.32 cft. @ Tk. 17,255.06 Per % cft. = Tk. 1,435.62
6. 40 grade reinforcement &
fabrication 1.25% 125.93 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 3,895.01
7. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
8. Supply and filling graded
khoa and sand. 188.4 cft. @ Tk. 81.05 Per cft. = Tk. 15,269.82
Total = Tk. 47,754.69
Profit 10.00% = Tk. 4,775.47
Overhead 3.50% = Tk. 1,671.41
= Tk. 54,201.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,154.59
Grand total = Tk. 57,356.16
Rate per No. = Tk. 57,356.16

Say, Tk. 57,356 .00 each

Item No.- 26.81


Soak-well (small sizes)
26.81.1 Soak-well for 30 users
26.81.1 Soak-well for 20 to 30 users
Considering 1 No. soak-well
1. Earth-work: 525.02 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,192.62
2. R.C.C. (1:2:4) in curb well with 1.25% reinforcement
(excluding cost of reinforcement) 10.98 cft. @ Tk. 17,255.06 Per % cft. = Tk. 1,894.61
3. 10" Honeycomb brick-work (1:6) in cement mortar
Analysis of PWD SoR 2014 for Civil Works 492

(87.57% of solid b/work). 84.68 cft. @ Tk. 10,996.76 Per % cft. = Tk. 9,312.06
4. 10" solid brick-work (1:6) 87.45 cft. @ Tk. 12,557.68 Per % cft. = Tk. 10,981.69
5. R.C.C. (1:2:4) in curb well with 1.5% re-inforcement
(excluding cost of reinforcement) 6.92 cft. @ Tk. 17,255.06 Per % cft. = Tk. 1,194.05
6. 40 grade reinforcement &
fabrication 1.25% 109.64 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 3,391.17
7. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
8. Supply and filling graded
khoa and sand. 144.24 cft. @ Tk. 81.05 Per cft. = Tk. 11,690.65
Total = Tk. 40,683.69
Profit 10.00% = Tk. 4,068.37
Overhead 3.50% = Tk. 1,423.93
= Tk. 46,175.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,687.49
Grand total = Tk. 48,863.48
Rate per No. = Tk. 48,863.48

Say, Tk. 48,863 .00 each

26.81.2 Soak-well for 10 users


Considering 1 No. soak-well
1. Earth-work: 375.9 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 853.89
2. R.C.C. (1:2:4) in curb well with 1.25% reinforcement
(excluding cost of reinforcement) 8.44 cft. @ Tk. 17,255.06 Per % cft. = Tk. 1,456.33
3. 10" Honeycomb brick-work (1:6) in cement mortar
(87.57% of solid b/work). 65.09 cft. @ Tk. 10,996.76 Per % cft. = Tk. 7,157.79
4. 10" solid brick-work (1:6) 67.26 cft. @ Tk. 12,557.68 Per % cft. = Tk. 8,446.30
5. R.C.C. (1:2:4) in curb well with 1.5% reinforcement
(excluding cost of reinforcement) 4.5 cft. @ Tk. 17,255.06 Per % cft. = Tk. 776.48
6. 40 grade reinforcement &
fabrication 1.25% 79.26 Ibs. @ Tk. 30.93 Per Ibs. = Tk. 2,451.51
7. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 No. @ Tk. 1,026.84 each = Tk. 1,026.84
8. Supply and filling graded
khoa and sand. 73.59 cft. @ Tk. 81.05 Per cft. = Tk. 5,964.47
Total = Tk. 28,133.61
Profit 10.00% = Tk. 2,813.36
Overhead 3.50% = Tk. 984.68
= Tk. 31,931.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,858.45
Grand total = Tk. 33,790.10
Rate per No. = Tk. 33,790.10
Say, Tk. 33,790 .00 each

Item No.- 26.82


Supply and installation of Reverse Osmosis Water Purifier (Japan/ Korea/ Taiwan) for drinking purpose:
26.82.1 Water purification volume: 50 gallon per day
Water reserve capacity: 11 liter
Model No.: TW-1250
Considering 1 No. water purifier
1. Cost of purifier complete set 1 No. @ Tk. 16,998.58 each = Tk. 16,998.58
2. Installation charge excluding
cost of pipe line 1 No. @ Tk. 339.97 each = Tk. 339.97
3. Carriage, incidental, sundries etc. L.S. = Tk. 410.83
Total = Tk. 17,749.38
Profit 10.00% = Tk. 1,774.94
Analysis of PWD SoR 2014 for Civil Works 493

Overhead 3.50% = Tk. 621.23


= Tk. 20,145.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,172.49
Grand total = Tk. 21,318.04
Rate per No. = Tk. 21,318.04

Say, Tk. 21,318 .00 each

26.82.2 Water purification volume: 75 gallon per day (Without meter)


Water reserve capacity: 10 liter
Model No.: TY-B99-528
Considering 1 No. water purifier
1. Cost of purifier complete set 1 No. @ Tk. 20,063.85 each = Tk. 20,063.85
2. Installation charge excluding
cost of pipe line 1 No. @ Tk. 401.28 each = Tk. 401.28
3. Carriage, incidental, sundries etc. = Tk. 547.78
Total = Tk. 21,012.91
Profit 10.00% = Tk. 2,101.29
Overhead 3.50% = Tk. 735.45
= Tk. 23,849.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,388.07
Grand total = Tk. 25,237.72
Rate per No. = Tk. 25,237.72
Say, Tk. 25,238 .00 each

26.82.3 Water purification volume: 75 gallon per day (With meter)


Water reserve capacity: 11 liter
Model No.: THC-1500
Considering 1 No. water purifier
1. Cost of purifier complete set 1 No. @ Tk. 21,205.04 each = Tk. 21,205.04
2. Installation charge excluding
cost of pipe line 1 No. @ Tk. 424.10 each = Tk. 424.10
3. Carriage, incidental, sundries etc. L.S. = Tk. 547.78
Total = Tk. 22,176.92
Profit 10.00% = Tk. 2,217.69
Overhead 3.50% = Tk. 776.19
= Tk. 25,170.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,464.97
Grand total = Tk. 26,635.77
Rate per No. = Tk. 26,635.77
Say, Tk. 26,636 .00 each
26.82.4 Water purification volume: 100 gallon per day
Water reserve capacity: 17 liter
Model No.: CW-929 CAR (hot, cold & warm options)
Considering 1 No. water purifier
1. Cost of purifier complete set 1 No. @ Tk. 63,809.24 each = Tk. 63,809.24
2. Installation charge excluding
cost of pipe line 1 No. @ Tk. 957.14 each = Tk. 957.14
3. Carriage, incidental, sundries etc. = Tk. 1,369.44
Total = Tk. 66,135.82
Profit 10.00% = Tk. 6,613.58
Overhead 3.50% = Tk. 2,314.75
= Tk. 75,064.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4,368.81
Grand total = Tk. 79,432.96
Rate per No. = Tk. 79,432.96
Analysis of PWD SoR 2014 for Civil Works 494

Say, Tk. 79,433 .00 each

Item No.- 26.83


Water Dispenser: 50 liter capacity
Considering 1 No. water Dispenser
1. Cost of Dispenser complete set 1 No. @ Tk. 3,500.00 each = Tk. 3,500.00
2. Installation 1 No. @ Tk. 50.00 each = Tk. 50.00
3. Carriage, incidental, sundries etc. = Tk. 106.23
Total = Tk. 3,656.23
Profit 10.00% = Tk. 365.62
Overhead 3.50% = Tk. 127.97
= Tk. 4,149.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 241.52
Grand total = Tk. 4,391.34
Rate per No. = Tk. 4,391.34

Say, Tk. 4,391 .00 each

Item No.- 26.84


Punching / cutting hole in RCC floor for sanitary works
Break-up for 6" dia 1 hole
1. Skilled labour 1.00 Nos. @ Tk. 303.00 each = Tk. 303.00
2. Ordinary labour 0.50 Nos. @ Tk. 245.00 each = Tk. 122.50
3. Tools and plant, sundries etc. L.S. = Tk. 20.42
4. Mending good the damages L.S. = Tk. 108.21
Tk. 554.13
Profit 10.00% = Tk. 55.41
Overhead 3.50% = Tk. 19.39
= Tk. 628.93
Add VAT with adjustment factor 1.0582 5.50% = Tk. 36.60
Grand total = Tk. 665.53

Say Tk. 666 .00 Per hole

DIVISION 27 : DEEP TUBE-WELL


SINKING OF 38 mm DIA TEST AND OBSERVATION WELL

Item No.- 27.1


Mobilization: Transportation of materials, equipments, tools and plants and boring rig to work site.
Considering mobilization for 1 set
Transportation of materials, equipments, tools and
plants, boring rigs to work site for sinking
38 mm test and observation well. L.S. = Tk. 5,856.91
Profit 10.00% = Tk. 585.69
Overhead 3.50% = Tk. 204.99
= Tk. 6,647.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 386.90
Total = Tk. 7,034.49

Say, Tk. 7,034 .00 Per set


Analysis of PWD SoR 2014 for Civil Works 495

Item No.- 27.2.1


Boring by using 100 mm dia cutter
(a) Considering 0 meter to 50 meter
Cost for boring including all equipment, accessories,
labours and materials along with
insurance coverage of risks 50 meter @ Tk. 128.00 Per meter = Tk. 6,400.00
Profit 10.00% = Tk. 640.00
Overhead 3.50% = Tk. 224.00
= Tk. 7,264.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 422.77
Total = Tk. 7,686.77

Rate Per meter (from 0 m to 50 m) = Tk. 153.74

Say, Tk. 154 .00 Per rm

Item No.- 27.2.2


Boring by using 100 mm dia cutter
Considering 50 m to 100 m
(a) Rate for 0 m to 50 m = Tk. 153.74
(b) Add for 50 m to 100 m 15% = Tk. 23.06
Total = Tk. 176.80
Rate Per meter (50 m to 100 m) = Tk. 176.80

Say, Tk. 177 .00 Per rm

Item No.- 27.2.3


Boring by using 100 mm dia cutter
Considering 100 m to 152 m
(a) Rate for 50 m to 100 m = Tk. 176.80
(b) Add for 100 m to 152 m 15% = Tk. 26.52
Total = Tk. 203.32
Rate Per meter (100 m to 152 m) = Tk. 203.32

Say, Tk. 203 .00 Per rm


Analysis of PWD SoR 2014 for Civil Works 496

Item No.- 27.2.4


Boring by using 100 mm dia cutter
Considering 152 m to 200 m
(a) Rate for 100 m to 152 m = Tk. 203.32
(b) Add for 152 m to 200 m 15% = Tk. 30.50
Total = Tk. 233.82
Rate Per meter (152 m to 200 m) = Tk. 233.82

Say, Tk. 234 .00 Per rm

Item No.- 27.2.5


Boring by using 100 mm dia cutter
Considering 200 to 250 m
(a) Rate for 152 m to 200 m = Tk. 233.82
(b) Add for 200 m to 250 m 15% = Tk. 35.07
Total = Tk. 268.89
Rate Per meter (200 m to 250 m) = Tk. 268.89

Say, Tk. 269 .00 Per rm

Item No.- 27.2.6


Boring by using 100 mm dia cutter
Beyond 250 m
(a) Rate for 200 m to 250 m = Tk. 268.89
(b) Add for Beyond 250 m 15% = Tk. 40.33
Total = Tk. 309.22
Rate Per meter (beyond 250 m) = Tk. 309.22

Say, Tk. 309 .00 Per rm

Item No.- 27.3.1


Supplying and installation of Hand pump No. 6
Hand Pump No.6
Considering 1 set
(a) Best quality heavy type
Hand Pump No. 6 1 set @ Tk. 2,182.00 Per set = Tk. 2,182.00
(b) Labour cost L.S. = Tk. 98.00
Total = Tk. 2,280.00
Profit 10.00% = Tk. 228.00
Overhead 3.50% = Tk. 79.80
= Tk. 2,587.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 150.61
Grand total = Tk. 2,738.41
Rate per set = Tk. 2,738.41

Say, Tk. 2,738 .00 Per set

Item No.- 27.3.2


Supplying and lowering of 38 mm dia tube well pipe
38 mm dia G.I. pipe
Considering 1 meter
(a) 38 mm dia G.I. pipe 1 meter @ Tk. 486.41 Per meter = Tk. 486.41
(b) Labour for fitting, fixing, lowering in/c coverage of risk and solution L.S. = Tk. 67.38
(c) Carriage L.S. = Tk. 12.25
Total = Tk. 566.04
Profit 10.00% = Tk. 56.60
Overhead 3.50% = Tk. 19.81
Analysis of PWD SoR 2014 for Civil Works 497

= Tk. 642.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 37.39
Grand total = Tk. 679.84
Rate per rm = Tk. 679.84

Say, Tk. 680 .00 Per rm

Item No.- 27.3.3


Supplying and lowering of 38 mm dia PVC tube well pipe
38 mm dia PVC pipe
Considering 1 meter
(a) 38 mm dia water grade PVC pipe
including carriage 1 meter @ Tk. 95.65 Per meter = Tk. 95.65
(b) Labour for fitting, fixing, lowering
in/c coverage of risk and solution L.S. = Tk. 22.05
Total = Tk. 117.70
Profit 10.00% = Tk. 11.77
Overhead 3.50% = Tk. 4.12
= Tk. 133.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 7.78
Grand total = Tk. 141.37
Rate per rm = Tk. 141.37

Say, Tk. 141 .00 Per rm

Item No.- 27.3.4


Supplying and lowering of 38 mm dia PVC strainer
38 mm dia PVC Strainer
Considering 1 meter
(a) 36 mm dia water grade PVC
strainer in/c carriage 1 meter @ Tk. 111.80 Per meter = Tk. 111.80
(b) Making slot & cleaning 1 meter @ Tk. 9.80 Per meter = Tk. 9.80
(c) Labour for fitting, fixing, lowering
in/c coverage of risk and solution L.S. = Tk. 24.50
Total = Tk. 146.10
Profit 10.00% = Tk. 14.61
Overhead 3.50% = Tk. 5.11
= Tk. 165.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 9.65
Grand total = Tk. 175.47
Rate per rm = Tk. 175.47

Say, Tk. 175 .00 Per rm

Item No.- 27.3.5


Supplying and installation of 38 mm dia socketed adopter
38 mm dia socketed adopter
Considering 1 No.
(a) 38 mm dia socketed adopter 1 No. @ Tk. 60.18 each = Tk. 60.18
(b) Labour for fitting, fixing, lowering in/c coverage of risk and solution = Tk. 12.25
Total = Tk. 72.43
Profit 10.00% = Tk. 7.24
Overhead 3.50% = Tk. 2.54
= Tk. 82.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4.78
Grand total = Tk. 86.99
Rate each. = Tk. 86.99
Analysis of PWD SoR 2014 for Civil Works 498

Say, Tk. 87 .00 each.

Item No.- 27.3.6


Supplying and istallation of best quality 38 mm dia PVC cap.
Best quality 38 mm dia PVC cap.
Considering 1 No.
(a) Best quality 38 mm dia PVC cap. 1 No. @ Tk. 43.00 each = Tk. 43.00
(b) Labour for fitting, fixing, lowering in/c coverage of risk and solution L.S. = Tk. 12.25
Total = Tk. 55.25
Profit 10.00% = Tk. 5.53
Overhead 3.50% = Tk. 1.93
= Tk. 62.71
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3.65
Grand total = Tk. 66.36
Rate each. = Tk. 66.36

Say, Tk. 66 .00 each.


Item No.- 27.3.7
Supplying, fitting fixing obsevation well inside the housing pipe of the deep tube well: 100'-0" depth
Considering 1 No.
(a) Cost of 38 mm dia G.I. Pipe 100 rft. @ Tk. 169.31 each = Tk. 16,931.00
(b) Cost of fittings and labour for fitting, fixing, lowering in/c coverage of risk and solution L.S. = Tk. 1,225.00
Total = Tk. 18,156.00
Profit 10.00% = Tk. 1,815.60
Overhead 3.50% = Tk. 635.46
= Tk. 20,607.06
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,199.35
Grand total = Tk. 21,806.41
Rate each. = Tk. 21,806.41
Say, Tk. 21,806 .00 each.
Item No.- 27.3.8
Supplying, fitting fixing tube-well log describing technical information of the tube-well as
per instruction and direction of the engineer in charge.
Considering 1 No.
(a) Cost of plate/pillar 1 No. @ Tk. 980.00 each = Tk. 980.00
(b) Cost of writing information L.S. = Tk. 840.00
(c) Cost of fittings and labour for erection or fitting, fixing etc. L.S. = Tk. 560.00
Total = Tk. 2,380.00
Profit 10.00% = Tk. 238.00
Overhead 3.50% = Tk. 83.30
= Tk. 2,701.30
Add VAT with adjustment factor 1.0582 5.50% = Tk. 157.22
Grand total = Tk. 2,858.52
Rate each. = Tk. 2,858.52

Say, Tk. 2,859 .00 each.

Item No.- 27.3.9


Filling the top 0.6 meter of the bore hole around the top pipe with a sanitary seal of concrete
of proportion (1:2:4):
0.24 cft. Tk. 176.37 Per cft. = Tk. 42.33
Profit 10.00% = Tk. 4.23
Overhead 3.50% = Tk. 1.48
= Tk. 48.04
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2.80
Total = Tk. 50.84
Analysis of PWD SoR 2014 for Civil Works 499

Say, Tk. 51 .00 each

Item No.- 27.4


Complete development of the tube well to obtain sand and turbidity free water at a satisfactory yield
27.4.1 Cost for wells up to 200 m depth: sample of water
must be taken from 3 aquifier level from
1 test tube-wells 1 Nos. @ Tk. 5,150.37 Per bore = Tk. 5,150.37
Profit 10.00% = Tk. 515.04
Overhead 3.50% = Tk. 180.26
= Tk. 5,845.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 340.22
Total = Tk. 6,185.89

27.4.1.1 Development using 1 test tube-wells Say, Tk. 6,186 .00 LS

27.4.1.2 Development using 2 test tube-wells 150% = Say, Tk. 9,279 .00 LS

27.4.1.3 Development using 3 test tube-wells 200% = Say, Tk. 12,372 .00 LS

27.4.2 Extra cost for test tube-well beyond 200 m depth

27.4.2.1 For 1 test tube-wells 115% Say, Tk. 35.57 Per meter

27.4.2.2 For 2 test tube-wells 115% Say, Tk. 53.35 Per meter

27.4.2.3 For 3 test tube-wells 115% Say, Tk. 71.14 Per meter

Item No.- 27.5


Furnishing design of the production well by testing of water and soil samples collected
from the observation well in/c test for Arsenic from BRTC, BUET/reputed laboratory etc.

27.5.1 Taking consideration of 1 No. Test bore


(1) Cost for furnishing design of tube well L.S. = Tk. 14,000.00
(2) Testing of water collected from the test bore:
(i) pH/Hydrogen ion density 1 test @ Tk. 259.00 Per test = Tk. 259.00
(ii) Carbondioxide (CO2) 1 test @ Tk. 259.00 Per test = Tk. 259.00
(iii) Chlorine (Cl) 1 test @ Tk. 534.00 Per test = Tk. 534.00
(iv) Fluorine (Fl) 1 test @ Tk. 509.00 Per test = Tk. 509.00
(v) Iron (Fe) 1 test @ Tk. 634.00 Per test = Tk. 634.00
(vi) Manganese (Mn) 1 test @ Tk. 692.00 Per test = Tk. 692.00
(vii) Nitrate-Nitrogen (NO3-N) 1 test @ Tk. 505.00 Per test = Tk. 505.00
(viii) Total alkalinity 1 test @ Tk. 250.00 Per test = Tk. 250.00
(ix) Total hardness 1 test @ Tk. 519.00 Per test = Tk. 519.00
(x) Arsenic (As) 1 test @ Tk. 1,034.00 Per test = Tk. 1,034.00
(xi) Turbidity 1 test @ Tk. 265.00 Per test = Tk. 265.00
Tk. 5,460.00
(xii) Sieve analysis for sand 3 tests @ Tk. 1,123.00 Per test = Tk. 3,369.00
from different layer
(3) Maintaining the bore holes and tools and plants etc. at site untill
satisfactory results are obtained from laboratory, filling and sealing
the bore holes 1 No. @ Tk. 4,000.00 Per test bore = Tk. 4,000.00
Total = Tk. 26,829.00
Profit 10.00% = Tk. 2,682.90
Overhead 3.50% = Tk. 939.02
= Tk. 30,450.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,772.27
Grand total = Tk. 32,223.19
Analysis of PWD SoR 2014 for Civil Works 500

Say, Tk. 32,223 .00 each

27.5.2 Taking consideration of 2 Nos. Test bore

(1) Cost for furnishing design of tube-well considering 2 bore = Tk. 18,666.67
(2) Testing of water collected from 2 test bore = Tk. 10,920.00
(3) Sieve analysis for sand
from different layers 6 tests @ Tk. 1,123.00 Per test = Tk. 6,738.00
(3) Maintaining the bore holes and tools and plants etc. at site untill
satisfactory results are obtained from laboratory, filling and sealing
the bore holes 2 No. @ Tk. 4,000.00 Per test bore = Tk. 8,000.00
Tk. 44,324.67
Profit 10.00% = Tk. 4,432.47
Overhead 3.50% = Tk. 1,551.36
= Tk. 50,308.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,928.01
Grand total = Tk. 53,236.51

Say, Tk. 53,237 .00 each

27.5.3 Taking consideration of 3 Nos. Test bore

(1) Cost for furnishing design of tube-well considering 3 bore = Tk. 28,000.01
(2) Testing of water collected from 3 test bore = Tk. 16,380.00
(3) Sieve analysis for sand
from different layers 9 tests @ Tk. 1,123.00 Per test = Tk. 10,107.00
(3) Maintaining the bore holes and tools and plants etc. at site untill
satisfactory results are obtained from laboratory, filling and sealing
the bore holes 3 No. @ Tk. 4,000.00 Per test bore = Tk. 12,000.00
Tk. 66,487.01
Profit 10.00% = Tk. 6,648.70
Overhead 3.50% = Tk. 2,327.05
= Tk. 75,462.76
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4,392.01
Grand total = Tk. 79,854.77

Say, Tk. 79,855 .00 each

Item No.- 27.6


Disinfection of the well by using minimum 3 kg of bleaching powder
(a) Cost for disinfection using bleaching powder
including the cost of bleaching powder L.S. = Tk. 316.00
Profit 10.00% = Tk. 31.60
Overhead 3.50% = Tk. 11.06
= Tk. 358.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.87
Total = Tk. 379.53

Say, Tk. 380 .00 each


Analysis of PWD SoR 2014 for Civil Works 501

PRODUCTION WELL

Item No.- 27.7


Preparation, packing, transportation of complete boring equipments, installation of drilling rig with
accessories and other necessary arrangements for installation of one complete tube well
27.7.1 Mobilization of complete set of boring rig
etc. for sinking up to 100 meter depth LS. = Tk. 29,392.65
Profit 10.00% = Tk. 2,939.27
Overhead 3.50% = Tk. 1,028.74
= Tk. 33,360.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,941.62
Total = Tk. 35,302.28

Say Tk. 35,302 .00 per set

27.7.2 Mobilization of complete set of boring rig


etc. for sinking up to 200 meter depth: = Tk. 37,823.87
Say Tk. 37,824 .00 per set

27.7.3 Mobilization of complete set of boring rig


etc. for sinking up to 200 meter depth: = Tk. 40,345.46
Say, Tk. 40,345 .00 per set

Item No.- 27.8


Preparation and making gravel pack around the tube well fixtures (Shrouding the annular space
between the tube-well fixtures with pea-gravels)
Considering 2.8 cum
(a) Cost of pea-gravels including
20% for caving and siltation 3.36 cum. @ Tk. 1,942.33 each = Tk. 6,526.23
(b) Labour for screening out the larger
and smaller size of peagravels 1.0 No. @ Tk. 245.00 each = Tk. 245.00
(c) Labour for packing of peagravels with care:
Skilled labour 1.0 No. @ Tk. 303.00 Per liter = Tk. 303.00
(d) Local carriage, T & P L.S. = Tk. 122.50
Total = Tk. 7,196.73
Profit 10.00% = Tk. 719.67
Overhead 3.50% = Tk. 251.89
= Tk. 8,168.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 475.40
Grand total = Tk. 8,643.69
Rate per cum. = Tk. 3,087.03

Say, Tk. 3,087 .00 Per cum.

Item No.- 27.9


Making sanitary seal by RCC work with brick chips (1:1.5:3) complete excluding the cost of
reinforcement and its fabrication up to a minimum depth of 6 meter.
Rate per cum: Same as item No 52(a): item for R.C.C. work with brick
chips (1:1.5:3) in footings of column, raft & floor slab at
plinth level = Tk. 7,982.00
Say, Tk. 7,982 .00 Per cum.
Analysis of PWD SoR 2014 for Civil Works 502

ANALYSIS FOR INSTALLATION OF 50 mm x 125 mm DIA SHROUDED


PRODUCTION WELL WITH PVC PIPE

Item No.- 27.10.1


325 mm dia boring
Considering 0 m to 50 m
Cost for boring including all equipment, accessories,
labours and materials along
with insurance coverage of risks 50 meter @ Tk. 624.24 Per meter = Tk. 31,212.00
Profit 10.00% = Tk. 3,121.20
Overhead 3.50% = Tk. 1,092.42
= Tk. 35,425.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,061.81
Total = Tk. 37,487.43
Rate Per meter (from 0 m to 50 m) = Tk. 749.75

Say, Tk. 750 .00 Per rm

Item No.- 27.10.2


325 mm dia boring
Considering 50 m to 100 m
(a) Rate for 0 m to 50 m = Tk. 749.75
(b) Add for 50 m to 100 m 15% = Tk. 112.46
Total = Tk. 862.21
Rate Per meter (50 m to 100 m) = Tk. 862.21

Say, Tk. 862 .00 Per rm

Item No.- 27.10.3


325 mm dia boring
Considering 100 m to 152 m
(a) Rate for 50 m to 100 m = Tk. 862.21
(b) Add for 100 m to 152 m 15% = Tk. 129.33
Total = Tk. 991.54
Rate Per meter (100 m to 152 m) = Tk. 991.54

Say, Tk. 992 .00 Per rm

Item No.- 27.10.4


325 mm dia boring
d) Considering 152 m to 200 m
(a) Rate for 100 m to 152 m = Tk. 991.54
(b) Add for 152 m to 200 m 15% = Tk. 148.73
Total = Tk. 1,140.27
Rate Per meter (152 m to 200 m) = Tk. 1,140.27

Say, Tk. 1,140 .00 Per rm


Item No.- 27.10.5
325 mm dia boring
Considering 200 m to 250 m
(a) Rate for 152 m to 200 m = Tk. 1,140.27
(b) Add for 200 m to 250 m 15% = Tk. 171.04
Total = Tk. 1,311.31
Rate Per meter (200 m to 250 m) = Tk. 1,311.31

Say, Tk. 1,311 .00 Per rm


Item No.- 27.10.6
Analysis of PWD SoR 2014 for Civil Works 503

325 mm dia boring


Beyond 250 m
(a) Rate for 200 m to 250 m = Tk. 1,311.31
(b) Add for beyond 250 m 15% = Tk. 196.70
Total = Tk. 1,508.01
Rate Per meter (beyond 250 m) = Tk. 1,508.01

Say, Tk. 1,508 . 00 Per rm

Item No.- 27.11.1


Supplying 50 mm dia uPVC cap
Considering 1 No.
(a) 50 mm dia uPVC cap 1 No. @ Tk. 55.00 each = Tk. 55.00
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 74.60
Profit 10.00% = Tk. 7.46
Overhead 3.50% = Tk. 2.61
= Tk. 84.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4.93
Grand total = Tk. 89.60
Rate each. = Tk. 89.60

Say, Tk. 90 .00 each.

Item No.- 27.11.2


Supplying 50 mm dia uPVC tube well pipe and blank pipe
Considering 1 meter
(a) 50 mm dia C-grade uPVC pipe 1 meter @ Tk. 135.21 Per meter = Tk. 135.21
(b) Carriage of materials L.S. = Tk. 16.33
Total = Tk. 151.54
Profit 10.00% = Tk. 15.15
Overhead 3.50% = Tk. 5.30
= Tk. 171.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10.01
Grand total = Tk. 182.00
Rate per rm. = Tk. 182.00

Say, Tk. 182 .00 Per rm.

Item No.- 27.11.3


Supplying 50 mm dia uPVC Strainer
Considering 1 meter
(a) 50 mm dia C-grade uPVC pipe 1 meter @ Tk. 135.21 Per meter = Tk. 135.21
(b) Making slot
and cleaning 1 meter @ Tk. 29.40 Per meter = Tk. 29.40
(c) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 184.21
Profit 10.00% = Tk. 18.42
Overhead 3.50% = Tk. 6.45
= Tk. 209.08
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12.17
Grand total = Tk. 221.25
Rate per rm. = Tk. 221.25
Say, Tk. 221 .00 Per rm.
Item No.- 27.11.4
Supplying 50 mm x 125 mm uPVC reducer
Analysis of PWD SoR 2014 for Civil Works 504

Considering 1 No. 1 No.


(a) Best quality uPVC
50 mm x 125 mm reducer 1 No. @ Tk. 486.00 each = Tk. 486.00
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 505.60
Profit 10.00% = Tk. 50.56
Overhead 3.50% = Tk. 17.70
= Tk. 573.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 33.40
Grand total = Tk. 607.26
Rate per rm. = Tk. 607.26

Say, Tk. 607 .00 Per rm.

Item No.- 27.11.5


Supplying 125 mm dia uPVC housing pipe
Considering 1 meter
(a) 125 mm dia C-grade
PVC housing pipe 1 meter @ Tk. 593.00 Per meter = Tk. 593.00
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 612.60
Profit 10.00% = Tk. 61.26
Overhead 3.50% = Tk. 21.44
= Tk. 695.30
Add VAT with adjustment factor 1.0582 5.50% = Tk. 40.47
Grand total = Tk. 735.77
Rate per rm. = Tk. 735.77

Say, 736 .00 Per rm.

Item No.- 27.11.6


Supplying centralizer made with 12 mm dia M.S. rod of approved design
Considering 1 No.
(a) 1 set centralizer consists of four leaves:
12 mm dia M.S. rod:
4 x 3'-0"+2*3.14*0.5=15'-3" 9.1 Ibs @ Tk. 27.89 Per meter = Tk. 253.80
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 49.00
Total = Tk. 302.80
Profit 10.00% = Tk. 30.28
Overhead 3.50% = Tk. 10.60
= Tk. 343.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.00
Grand total = Tk. 363.68
Rate each. = Tk. 363.68

Say, Tk. 364 .00 each.


Item No.- 27.12
Complete installation of tubewell (fixture)
Considering for 100 meter
(a) Material cost
(i) PVC tape 3 Nos. @ Tk. 91.85 each = Tk. 275.55
(ii) PVC solution/gum 2 Nos. @ Tk. 601.83 each = Tk. 1,203.66
(iii) Cost of fuel 10 Liter @ Tk. 83.81 Per liter = Tk. 838.10
(iv) Iron screws etc L.S. = Tk. 171.50
(b) Labour cost in/c coverage of risk
(i) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(ii) Foreman helper 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00
Analysis of PWD SoR 2014 for Civil Works 505

(iii) Skilled labour 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00


Total = Tk. 5,479.81
Profit 10.00% = Tk. 547.98
Overhead 3.50% = Tk. 191.79
= Tk. 6,219.58
Add VAT with adjustment factor 1.0582 5.50% = Tk. 361.99
Grand total = Tk. 6,581.57
Rate per rm. = Tk. 65.82

Say, Tk. 66 .00 Per rm.

Item No.- 27.13


Complete development of the tube well (for 50 mm x 125 mm tube-well) by air compressor and
pump of suitable capacity by alternate surging and pumping untill satisfactory yield, sand free
water and the turbidity condotions is reached.
27.13.1 Development of tube well for depth up to 200 m. L.S. = Tk. 18,573.48
Profit 10.00% = Tk. 1,857.35
Overhead 3.50% = Tk. 650.07
= Tk. 21,080.90
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,226.93
Total = Tk. 22,307.83

Say, Tk. 22,308 .00 each

27.13.2 Development of tube well for the depth beyond 200 m: = Tk. 28,256.80

Say, Tk. 28,257 . 00 each

Item No.- 27.14


Long term pumping test of the well by required capacity pump including drawdown and
recovery test etc. complete
Considering 72 hrs.
(a) Hire charge of pump in/c
spare and maintenance 72 hrs @ Tk. 230.24 Per hour = Tk. 16,577.28
(b) Fuel for pump: petrol
@ 2.5 liter per hour 180 liter @ Tk. 83.81 Per liter = Tk. 15,085.80
(c) Foreman: @ 1 No. per 8 hrs 9 Nos. @ Tk. 567.00 each = Tk. 5,103.00
(c) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(d) Local carriage, T & P L.S. = Tk. 416.50
Total = Tk. 39,000.58
Profit 10.00% = Tk. 3,900.06
Overhead 3.50% = Tk. 1,365.02
= Tk. 44,265.66
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,576.31
Grand total = Tk. 46,841.97
Rate per hour = Tk. 650.58
Say, Tk. 651 .00 Per hour.
Item No.- 27.15
Disinfection of the tube well
Cost for disinfection of the tube well including supply of all the
materials and other necessary cost as per specification
(for 50 mm x 125 mm tube-well) L.S. = Tk. 920.45
Profit 10.00% = Tk. 92.05
Overhead 3.50% = Tk. 32.22
= Tk. 1,044.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 60.80
Grand total = Tk. 1,105.52
Analysis of PWD SoR 2014 for Civil Works 506

Say, Tk. 1,106 .00 each

Item No.- 27.16


Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(b) Skilled labour 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00
(c) Local carriage, T & P L.S. = Tk. 183.75
Total = Tk. 1,962.75
Profit 10.00% = Tk. 196.28
Overhead 3.50% = Tk. 68.70
= Tk. 2,227.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 129.66
Grand total = Tk. 2,357.39
Rate per rm. = Tk. 23.57

Say, Tk. 24 .00 Per rm.

Item No.- 27.17


Protective top cover
Considering for 1 job
(a) 150 mm dia and 4 mm
thick M.S. pipe 1 meter @ Tk. 1,952.98 Per meter = Tk. 1,952.98
(b) 4 mm thick 200 mm dia plate 1 No. @ Tk. 987.20 each = Tk. 987.20
(c) Welding and other cost as necessary L.S. = Tk. 245.00
Total = Tk. 3,185.18
Profit 10.00% = Tk. 318.52
Overhead 3.50% = Tk. 111.48
= Tk. 3,615.18
Add VAT with adjustment factor 1.0582 5.50% = Tk. 210.41
Grand total = Tk. 3,825.59

Say, Tk. 3,826 .00 each

ANALYSIS FOR INSTALLATION OF 75 mm x 150 mm DIA SHROUDED


PRODUCTION WELL WITH PVC PIPE

Item No.- 27.18.1


350 mm dia boring
Considering 0 m to 50 meter
Cost for boring including all equipment,
accessories, labours and materials along
with insurance coverage of risks 50 meter @ Tk. 659 Per meter = Tk. 32,950.00
Profit 10.00% = Tk. 3,295.00
Overhead 3.50% = Tk. 1,153.25
= Tk. 37,398.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,176.62
Grand total = Tk. 39,574.87
Rate Per meter (from 0 m to 50 m) = Tk. 791.50

Say, Tk. 792 .00 Per rm


Item No.- 27.18.2
350 mm dia boring
Considering 50 m to 100 m
(a) Rate for 0 m to 50 m = Tk. 791.50
(b) Add for 50 m to 100 m 15% = Tk. 118.73
Analysis of PWD SoR 2014 for Civil Works 507

Total = Tk. 910.23


Rate Per meter (50 m to 100 m) = Tk. 910.23

Say, Tk. 910 .00 Per rm

Item No.- 27.18.3


350 mm dia boring
Considering 100 m to 152 m
(a) Rate for 50 m to 100 m = Tk. 910.23
(b) Add for 100 m to 152 m 15% = Tk. 136.53
Total = Tk. 1,046.76
Rate Per meter (100 m to 152 m) = Tk. 1,046.76

Say, Tk. 1,047 .00 Per rm

Item No.- 27.18.4


350 mm dia boring
Considering 152 m to 200 m
(a) Rate for 100 m to 152 m = Tk. 1,046.76
(b) Add for 152 m to 200 m 15% = Tk. 157.01
Total = Tk. 1,203.77
Rate Per meter (152 m to 200 m) = Tk. 1,203.77

Say, Tk. 1,204 .00 Per rm

Item No.- 27.18.5


350 mm dia boring
Considering 200 m to 250 m
(a) Rate for 152 m to 200 m = Tk. 1,203.77
(b) Add for 200 m to 250 m 15% = Tk. 180.57
Total = Tk. 1,384.34
Rate Per meter (200 m to 250 m) = Tk. 1,384.34

Say, Tk. 1,384 .00 Per rm

Item No.- 27.18.6


350 mm dia boring
Beyond 250 m
(a) Rate for 200 m to 250 m = Tk. 1,384.34
(b) Add for beyond 250 m 15% = Tk. 207.65
Total = Tk. 1,591.99
Rate Per meter (beyond 250 m) = Tk. 1,591.99

Say, Tk. 1,592 .00 Per rm

Item No.- 27.19.1


Supplying 75 mm dia uPVC cap
Considering 1 No.
(a) 75 mm dia uPVC cap 1 No. @ Tk. 82.50 each = Tk. 82.50
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 102.10
Profit 10.00% = Tk. 10.21
Overhead 3.50% = Tk. 3.57
= Tk. 115.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 6.74
Grand total = Tk. 122.62
Rate each. = Tk. 122.62
Analysis of PWD SoR 2014 for Civil Works 508

Say, Tk. 123 .00 each.

Item No.- 27.19.2


Supplying 75 mm dia uPVC tube well pipe and blank pipe
Considering 1 meter
(a) 75 mm dia C-grade uPVC pipe 1 meter @ Tk. 240.17 Per meter = Tk. 240.17
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 259.77
Profit 10.00% = Tk. 25.98
Overhead 3.50% = Tk. 9.09
= Tk. 294.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 17.16
Grand total = Tk. 312.00
Rate per rm. = Tk. 312.00

Say, Tk. 312 .00 Per rm.

Item No.- 27.19.3


Supplying 75 mm dia uPVC strainer
Considering 1 meter
(a) 75 mm dia C-grade uPVC pipe 1 meter @ Tk. 240.17 Per meter = Tk. 240.17
(b) Cost of making slot and cleaning 1 meter @ Tk. 29.40 Per meter = Tk. 29.40
(c) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 289.17
Profit 10.00% = Tk. 28.92
Overhead 3.50% = Tk. 10.12
= Tk. 328.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 19.10
Grand total = Tk. 347.31
Rate per rm. = Tk. 347.31

Say, Tk. 347 .00 Per rm.

Item No.- 27.19.4


Supplying 75 mm x 150 mm uPVC reducer
Considering 1 No.
(a) 75 x 150 mm uPVC reducer 1 No. @ Tk. 621.00 each = Tk. 621.00
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 640.60
Profit 10.00% = Tk. 64.06
Overhead 3.50% = Tk. 22.42
= Tk. 727.08
Add VAT with adjustment factor 1.0582 5.50% = Tk. 42.32
Grand total = Tk. 769.40
Rate each. = Tk. 769.40

Say, Tk. 769 .00 each.

Item No.- 27.19.5


Supplying 150 mm dia uPVC housing pipe
Considering 1 meter
(a) 150 mm dia C-grade
uPVC housing pipe 1 meter @ Tk. 774.00 Per meter = Tk. 774.00
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 793.60
Analysis of PWD SoR 2014 for Civil Works 509

Profit 10.00% = Tk. 79.36


Overhead 3.50% = Tk. 27.78
= Tk. 900.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 52.42
Grand total = Tk. 953.16
Rate per rm. = Tk. 953.16

Say, 953 .00 Per rm.

Item No.- 27.19.6


Supplying centralizer made with 12 mm dia M.S. rod of approved design
Considering 1 No.
(a) 1 set centralizer consists of four leaves:
12 mm dia M.S. rod:
4 x 3'-0"+2*3.14*0.5=15'-3" 9.1 Ibs @ Tk. 27.89 Per meter = Tk. 253.80
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 49.00
Total = Tk. 302.80
Profit 10.00% = Tk. 30.28
Overhead 3.50% = Tk. 10.60
= Tk. 343.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.00
Grand total = Tk. 363.68
Rate each. = Tk. 363.68

Say, Tk. 364 .00 each.

Item No.- 27.20


Complete installation of tubewell (Fixture)
Considering for 100 meter
(a) Material cost
(i) PVC tape 3 Nos. @ Tk. 91.85 each = Tk. 275.55
(ii) PVC solution / gum 3 Nos. @ Tk. 601.83 each = Tk. 1,805.49
(iii) Cost of fuel 12.5 Liter @ Tk. 83.81 Per liter = Tk. 1,047.63
(iv) Iron screws etc = Tk. 70.00
(b) Labour cost in/c coverage of risk
(i) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(ii) Foreman helper 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00
(iii) Skilled labour 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00
Total = Tk. 6,189.67
Profit 10.00% = Tk. 618.97
Overhead 3.50% = Tk. 216.64
= Tk. 7,025.28
Add VAT with adjustment factor 1.0582 5.50% = Tk. 408.88
Grand total = Tk. 7,434.16
Rate per rm. = Tk. 74.34

Say, Tk. 74 .00 Per rm.


Analysis of PWD SoR 2014 for Civil Works 510

Item No.- 27.21


Complete development of the tube well (75 mm x 150 mm tube-well) by air compressor and pump
of suitable capacity by alternate surging and pumping untill satisfactory yield, sand free
water and the turbidity condotions is reached.
27.21.1 Development of tube well for depth up to 200 m. L.S. = Tk. 23,637.15
Profit 10.00% = Tk. 2,363.72
Overhead 3.50% = Tk. 827.30
= Tk. 26,828.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,561.43
Total = Tk. 28,389.60

Say, Tk. 28,390 .00 each

27.21.2 Development of tube well for the depth beyond 200 m: = Tk. 34,067.52
Say, Tk. 34,068 .00 each

Item No.- 27.22


Long term pumping test of the well by required capacity pump including drawdown and recovery
test etc. complete
Considering 72 hrs.
(a) Hire charge of pump in/c
spare and maintenance 72 hrs @ Tk. 287.80 Per hour = Tk. 20,721.60
(b) Fuel for pump:
@ 3.33 liter per hour 240 liter @ Tk. 83.81 Per liter = Tk. 20,114.40
(c) Foreman: @ 1 No. per 8 hrs 9 Nos. @ Tk. 567.00 each = Tk. 5,103.00
(d) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(e) Local carriage, T & P L.S. = Tk. 612.50
Total = Tk. 48,369.50
Profit 10.00% = Tk. 4,836.95
Overhead 3.50% = Tk. 1,692.93
= Tk. 54,899.38
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,195.20
Grand total = Tk. 58,094.58
Rate per hour = Tk. 806.87

Say, Tk. 807 .00 Per hour.

Item No.- 27.23


Disinfection of the tube well
Cost for disinfection of the tube well including supply of
all the materials and other necessary cost as per
specification (for 75 mm x 150 mm tube-well) L.S. = Tk. 1,117.69
Profit 10.00% = Tk. 111.77
Overhead 3.50% = Tk. 39.12
= Tk. 1,268.58
Add VAT with adjustment factor 1.0582 5.50% = Tk. 73.83
Grand total = Tk. 1,342.41

Say, Tk. 1,342 .00 each

Item No.- 27.24


Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(b) Skilled labour 5 Nos. @ Tk. 303.00 each = Tk. 1,515.00
(c) Local carriage, T & P L.S. = Tk. 245.00
Total = Tk. 2,327.00
Analysis of PWD SoR 2014 for Civil Works 511

Profit 10.00% = Tk. 232.70


Overhead 3.50% = Tk. 81.45
= Tk. 2,641.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 153.72
Grand total = Tk. 2,794.87
Rate per rm. = Tk. 27.95

Say, Tk. 28 .00 Per rm.

Item No.- 27.25


Protective top cover
Considering for 1 job
(a) 200 mm dia and 5 mm
thick M.S. pipe 1 meter @ Tk. 2,900.27 Per meter = Tk. 2,900.27
(b) 5 mm thick 250 mm dia plate 1 No. @ Tk. 1,158.86 each = Tk. 1,158.86
(c) Welding and other cost as necessary L.S. = Tk. 367.50
Total = Tk. 4,426.63
Profit 10.00% = Tk. 442.66
Overhead 3.50% = Tk. 154.93
= Tk. 5,024.22
Add VAT with adjustment factor 1.0582 5.50% = Tk. 292.41
Grand total = Tk. 5,316.63

Say, Tk. 5,317 .00 each

ANALYSIS FOR INSTALLATION OF 100 mm x 200 mm DIA SHROUDED


PRODUCTION WELL WITH uPVC PIPE

Item No.- 27.26.1


400 mm dia boring
Considering 0 m to 50 m
Cost for boring including all equipment,
accessories, labours and materials along
with insurance coverage of risks 50 meter @ Tk. 693.60 Per meter = Tk. 34,680.00
Profit 10.00% = Tk. 3,468.00
Overhead 3.50% = Tk. 1,213.80
= Tk. 39,361.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,290.90
Total = Tk. 41,652.70

Rate Per meter (from 0 m to 50 m) = Tk. 833.05

Say, Tk. 833 .00 Per rm

Item No.- 27.26.2


400 mm dia boring
Considering 50 m to 100 m
(a) Rate for 0 m to 50 m = Tk. 833.05
(b) Add for 50 m to 100 m 15% = Tk. 124.96
Total = Tk. 958.01
Rate Per meter (50 m to 100 m) = Tk. 958.01

Say, Tk. 958 .00 Per rm


Analysis of PWD SoR 2014 for Civil Works 512

Item No.- 27.26.3


400 mm dia boring
Considering 100 m to 152 m
(a) Rate for 50 m to 100 m = Tk. 958.01
(b) Add for 100 m to 152 m 15% = Tk. 143.70
Total = Tk. 1,101.71
Rate Per meter (100 m to 152 m) = Tk. 1,101.71

Say, Tk. 1,102 .00 Per rm

Item No.- 27.26.4


400 mm dia boring
Considering 152 m to 200 m
(a) Rate for 100 m to 152 m = Tk. 1,101.71
(b) Add for 152 m to 200 m 15% = Tk. 165.26
Total = Tk. 1,266.97
Rate Per meter (152 m to 200 m) = Tk. 1,266.97

Say, Tk. 1,267 .00 Per rm


Item No.- 27.26.5
400 mm dia boring
Considering 200 m to 250 m
(a) Rate for 152 m to 200 m = Tk. 1,266.97
(b) Add for 200 m to 250 m 15% = Tk. 190.05
Total = Tk. 1,457.02
Rate Per meter (200 m to 250 m) = Tk. 1,457.02

Say, Tk. 1,457 .00 Per rm

Item No.- 27.26.6


400 mm dia boring
Beyond 250 m
(a) Rate for 200m to 250 m = Tk. 1,457.02
(b) Add for beyond 250 m 15% = Tk. 218.55
Total = Tk. 1,675.57
Rate Per meter (beyond 250 m) = Tk. 1,675.57

Say, Tk. 1,676 .00 Per rm

Item No.- 27.27.1


Supplying 100 mm dia uPVC cap
Considering 1 No.
(a) 100 mm dia uPVC cap 1 No. @ Tk. 144.91 each = Tk. 144.91
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 164.51
Profit 10.00% = Tk. 16.45
Overhead 3.50% = Tk. 5.76
= Tk. 186.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 10.87
Grand total = Tk. 197.59
Rate each. = Tk. 197.59

Say, Tk. 198 .00 each.


Analysis of PWD SoR 2014 for Civil Works 513

Item No.- 27.27.2


Supplying 100 mm dia uPVC tube well pipe and blank pipe
Considering 1 meter
(a) 100 mm dia C-gradeuPVC pipe 1 meter @ Tk. 373.13 Per meter = Tk. 373.13
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 392.73
Profit 10.00% = Tk. 39.27
Overhead 3.50% = Tk. 13.75
= Tk. 445.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 25.94
Grand total = Tk. 471.69
Rate per rm. = Tk. 471.69

Say, Tk. 472 .00 Per rm.

Item No.- 27.27.3


Supplying 100 mm dia uPVC strainer
Considering 1 meter
(a) 100 mm dia C-grade
uPVC pipe strainer 1 meter @ Tk. 373.13 Per meter = Tk. 373.13
(b) Making slot and cleaning 1 meter @ Tk. 29.40 Per meter = Tk. 29.40
(c) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 422.13
Profit 10.00% = Tk. 42.21
Overhead 3.50% = Tk. 14.77
= Tk. 479.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 27.88
Grand total = Tk. 506.99
Rate per rm. = Tk. 506.99

Say, Tk. 507 .00 Per rm.

Item No.- 27.27.4


Supplying 100 mm x 200 mm uPVC reducer
Considering 1 No.
(a) 100 x 200 mm uPVC reducer 1 No. @ Tk. 697.00 each = Tk. 697.00
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 716.60
Profit 10.00% = Tk. 71.66
Overhead 3.50% = Tk. 25.08
= Tk. 813.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 47.34
Grand total = Tk. 860.68
Rate per rm. = Tk. 860.68

Say, Tk. 861 .00 each.


Item No.- 27.27.5
Supplying 200 mm dia uPVC housing pipe
Considering 1 meter
(a) 200 mm dia C-grade
uPVC housing pipe 1 meter @ Tk. 650.00 Per meter = Tk. 650.00
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 669.60
Profit 10.00% = Tk. 66.96
Overhead 3.50% = Tk. 23.44
= Tk. 760.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 44.23
Analysis of PWD SoR 2014 for Civil Works 514

Grand total = Tk. 804.23


Rate per rm. = Tk. 804.23

Say, 804 .00 Per rm.

Item No.- 27.27.6


Supplying centralizer made with 12 mm dia M.S. rod of approved design
Considering 1 No.
(a) 1 set centralizer consists of four leaves:
12 mm dia M.S. rod:
4 x 3'-0"+2*3.14*0.5=15'-3" 9.1 Ibs @ Tk. 27.89 Per meter = Tk. 253.80
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 49.00
Total = Tk. 302.80
Profit 10.00% = Tk. 30.28
Overhead 3.50% = Tk. 10.60
= Tk. 343.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.00
Grand total = Tk. 363.68
Rate each. = Tk. 363.68

Say, Tk. 364 .00 each.

Item No.- 27.28


Complete installation of tubewell (Fixture)
Considering for 100 meter
(a) Material cost
(i) uPVC tape 3 Nos. @ Tk. 91.85 each = Tk. 275.55
(ii) uPVC solution / gum 3 Nos. @ Tk. 601.83 each = Tk. 1,805.49
(iii) Cost of fuel 15 Liter @ Tk. 83.81 Per liter = Tk. 1,257.15
(iv) Cost of iron screws etc L.S. = Tk. 171.50
(b) Labour cost in/c coverage of risk
(i) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(ii) Foreman helper 5 Nos. @ Tk. 303.00 each = Tk. 1,515.00
(iii) Skilled labour 5 Nos. @ Tk. 303.00 each = Tk. 1,515.00
Total = Tk. 7,106.69
Profit 10.00% = Tk. 710.67
Overhead 3.50% = Tk. 248.73
= Tk. 8,066.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 469.45
Grand total = Tk. 8,535.54
Rate per rm. = Tk. 85.36

Say, Tk. 85 .00 Per rm.


Item No.- 27.29
Complete development of the tube well (for 100 mm x 200 mm tube-well) by air compressor and
pump of suitable capacity by alternate surging and pumping untill satisfactory yield, sand
free water and the turbidity condotions is reached.

27.29.1 Development of tube well for depth up to 200 m. L.S. = Tk. 29,243.18
Profit 10.00% = Tk. 2,924.32
Overhead 3.50% = Tk. 1,023.51
= Tk. 33,191.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,931.75
Total = Tk. 35,122.76
Say, Tk. 35,123 .00 each
27.29.2 Development of tube well for the depth beyond 200 m: = Tk. 42,147.31
Analysis of PWD SoR 2014 for Civil Works 515

Say, Tk. 42,147 .00 each

Item No.- 27.30


Long term pumping test of the well by required capacity pump including drawdown and recovery
test etc. complete
Considering 72 hrs.
(a) Hire charge of pump in/c
spare and maintenance 72 hrs @ Tk. 287.80 Per hour = Tk. 20,721.60
(b) Fuel for pump:
@ 3.75 liter per hour 270 liter @ Tk. 83.81 Per liter = Tk. 22,628.70
(c) Foreman: @ 1 No. per 8 hrs 9 Nos. @ Tk. 567.00 each = Tk. 5,103.00
(d) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(e) Local carriage, T & P L.S. = Tk. 796.25
Total = Tk. 51,067.55
Profit 10.00% = Tk. 5,106.76
Overhead 3.50% = Tk. 1,787.36
= Tk. 57,961.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,373.43
Grand total = Tk. 61,335.10
Rate per hour = Tk. 851.88

Say, Tk. 852 .00 Per hour.

Item No.- 27.31


Disinfection of the tube well
Cost for disinfection of the tube well including supply of all the
materials and other necessary cost as per specification
(for 100 x 200 mm tube-well) L.S. = Tk. 1,314.93
Profit 10.00% = Tk. 131.49
Overhead 3.50% = Tk. 46.02
= Tk. 1,492.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 86.86
Total = Tk. 1,579.30

Say, Tk. 1,579 .00 each

Item No.- 27.32


Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(b) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(c) Local carriage, T & P L.S. = Tk. 245.00
Total = Tk. 2,630.00
Profit 10.00% = Tk. 263.00
Overhead 3.50% = Tk. 92.05
= Tk. 2,985.05
Add VAT with adjustment factor 1.0582 5.50% = Tk. 173.73
Grand total = Tk. 3,158.78
Rate per rm. = Tk. 31.59

Say, Tk. 32 .00 Per rm.


Analysis of PWD SoR 2014 for Civil Works 516

Item No.- 27.33


Protective top cover
Considering for 1 job
(a) 300 mm dia and 6 mm thick M.S. pipe 1 meter @ Tk. 5,037.14 Per meter = Tk. 5,037.14
(b) 6 mm thick 350 mm dia plate 1 No. @ Tk. 1,400.80 each = Tk. 1,400.80
(c) Welding and other cost as necessary L.S. = Tk. 612.50
Total = Tk. 7,050.44
Profit 10.00% = Tk. 705.04
Overhead 3.50% = Tk. 246.77
= Tk. 8,002.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 465.74
Grand total = Tk. 8,467.99

Say, Tk. 8,468 .00 each

ANALYSIS FOR INSTALLATION OF 150 mm x 200 mm DIA SHROUDED


PRODUCTION WELL WITH uPVC PIPE

Item No.- 27.34.1


600 mm dia boring
a) Considering 0 m to 50 meter
Cost for boring including all equipment,
accessories, labours and materials along
with insurance coverage of risks 50 meter @ Tk. 849 Per meter = Tk. 42,450.00
Profit 10.00% = Tk. 4,245.00
Overhead 3.50% = Tk. 1,485.75
= Tk. 48,180.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,804.17
Total = Tk. 50,984.92

Rate Per meter (from 0 m to 50 m) = Tk. 1,019.70

Say, Tk. 1,020 .00 Per rm

Item No.- 27.34.2


600 mm dia boring
Considering 50 m to 100 m
(a) Rate for 0 m to 50 m = Tk. 1,019.70
(b) Add for 50 m to 100 m 15% = Tk. 152.96
Total = Tk. 1,172.66
Rate Per meter (50 m to 100 m) = Tk. 1,172.66

Say, Tk. 1,173 .00 Per rm

Item No.- 27.34.3


600 mm dia boring
Considering 100 m to 152 m
(a) Rate for 50 m to 100 m = Tk. 1,172.66
(b) Add for 100 m to 152 m 15% = Tk. 175.90
Total = Tk. 1,348.56
Rate Per meter (100 m to 152 m) = Tk. 1,348.56

Say, Tk. 1,349 . 00 Per rm


Analysis of PWD SoR 2014 for Civil Works 517

Item No.- 27.34.4


600 mm dia boring
Considering 152 m to 200 m
(a) Rate for 100 m to 152 m = Tk. 1,348.56
(b) Add for 152 m to 200 m 15% = Tk. 202.28
Total = Tk. 1,550.84
Rate Per meter (152 m to 200 m) = Tk. 1,550.84

Say, Tk. 1,551 .00 Per rm

Item No.- 27.34.5


600 mm dia boring
Considering 200 m to 250 m
(a) Rate for 152 m to 200 m = Tk. 1,550.84
(b) Add for 200 m to 250 m 15% = Tk. 232.63
Total = Tk. 1,783.47
Rate Per meter (200 m to 250 m) = Tk. 1,783.47

Say, Tk. 1,783 .00 Per rm

Item No.- 27.34.6


600 mm dia boring
Beyond 250 m
(a) Rate for 200 m to 250 m = Tk. 1,783.47
(b) Add for beyond 250 m 15% = Tk. 267.52
Total = Tk. 2,050.99
Rate Per meter (beyond 250 m) = Tk. 2,050.99

Say, Tk. 2,051 .00 Per rm

Item No.- 27.35.1


Supplying 150 mm dia uPVC cap
Considering 1 No.
(a) 150 mm dia uPVC cap 1 No. @ Tk. 375.07 each = Tk. 375.07
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 394.67
Profit 10.00% = Tk. 39.47
Overhead 3.50% = Tk. 13.81
Tk. 447.95
VAT 5.50% = Tk. 24.64
Grand total = Tk. 472.59
Rate each. = Tk. 472.59
Say, Tk. 473 .00 each.
Item No.- 27.35.2
Supplying 150 mm dia uPVC tube well pipe and blank pipe
Considering 1 meter
(a) 150 mm dia C-gradeuPVC pipe 1 meter @ Tk. 848.00 Per meter = Tk. 848.00
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 867.60
Profit 10.00% = Tk. 86.76
Overhead 3.50% = Tk. 30.37
= Tk. 984.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 57.31
Grand total = Tk. 1,042.04
Rate per rm. = Tk. 1,042.04
Say, Tk. 1,042 .00 Per rm.
Item No.- 27.35.3
Analysis of PWD SoR 2014 for Civil Works 518

Supplying 150 mm dia uPVC strainer


Considering 1 meter
(a) 150 mm dia C-grade uPVC pipe 1 meter @ Tk. 848.00 Per meter = Tk. 848.00
(b) Making slot and cleaning 1 meter @ Tk. 36.75 Per meter = Tk. 36.75
(c) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 904.35
Profit 10.00% = Tk. 90.44
Overhead 3.50% = Tk. 31.65
= Tk. 1,026.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 59.74
Grand total = Tk. 1,086.18
Rate per rm. = Tk. 1,086.18

Say, Tk. 1,086 .00 Per rm.

Item No.- 27.35.4


Supplying 150 mm x 200 mm uPVC reducer
Considering 1 No.
(a) 150 x 200 mm uPVC reducer 1 No. @ Tk. 807.00 each = Tk. 807.00
(b) Carriage of materials L.S. = Tk. 24.50
Total = Tk. 831.50
Profit 10.00% = Tk. 83.15
Overhead 3.50% = Tk. 29.10
= Tk. 943.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 54.93
Grand total = Tk. 998.68
Rate each. = Tk. 998.68

Say, Tk. 999 .00 each.

Item No.- 27.35.5


Supplying 200 mm dia uPVC housing pipe
Considering 1 meter
(a) 200 mm dia C-grade
uPVC housing pipe 1 meter @ Tk. 1,369.17 Per meter = Tk. 1,369.17
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 1,388.77
Profit 10.00% = Tk. 138.88
Overhead 3.50% = Tk. 48.61
= Tk. 1,576.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 91.74
Grand total = Tk. 1,668.00
Rate per rm. = Tk. 1,668.00

Say, 1668 .00 Per rm.

Item No.- 27.35.6


Supplying centralizer made with 12 mm dia M.S. rod of approved design
Considering 1 No.
(a) 1 set centralizer consists of four leaves:
12 mm dia M.S. rod:
4 x 3'-0"+2*3.14*0.5=15'-3" 9.1 Ibs @ Tk. 27.89 Per meter = Tk. 253.80
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 49.00
Total = Tk. 302.80
Profit 10.00% = Tk. 30.28
Overhead 3.50% = Tk. 10.60
Analysis of PWD SoR 2014 for Civil Works 519

= Tk. 343.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.00
Grand total = Tk. 363.68
Rate each. = Tk. 363.68

Say, Tk. 364 .00 each.

Item No.- 27.36


Complete installation of 150 mm dia uPVC tube well (fixture)
Considering for 100 meter
(a) Material cost
(i) uPVC Tape 4 Nos. @ Tk. 91.85 each = Tk. 367.40
(ii) uPVC solution / gum 4 Nos. @ Tk. 601.83 each = Tk. 2,407.32
(iii) Cost of fuel 20 Liter @ Tk. 83.81 Per liter = Tk. 1,676.20
(iv) Cost of iron screws etc. L.S. = Tk. 19.60
(b) Labour cost in/c coverage of risk
(i) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(ii) Foreman helper 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00
(iii) Skilled labour 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00
Total = Tk. 7,461.52
Profit 10.00% = Tk. 746.15
Overhead 3.50% = Tk. 261.15
= Tk. 8,468.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 492.89
Grand total = Tk. 8,961.71
Rate per rm. = Tk. 89.62

Say, Tk. 90 .00 Per rm.

Item No.- 27.37


Complete development of the tube well (for 150 x 200 mm tube-well) by air compressor and
pump of suitable capacity by alternate surging and pumping untill satisfactory yield, sand
free water and the turbidity condotions is reached.

27.37.1 Development of tube well for depth up to 200 m. L.S. = Tk. 34,814.71
Profit 10.00% = Tk. 3,481.47
Overhead 3.50% = Tk. 1,218.51
= Tk. 39,514.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,299.79
Total = Tk. 41,814.48

Say, Tk. 41,814 .00 each

27.37.2 Development of tube well for the depth beyond 200 m: = Tk. 47,389.74
Say, Tk. 47,390 .00 each

Item No.- 27.38


Long term pumping test of the well by required capacity pump including drawdown and
recovery test etc. complete
Considering 72 hrs.
(a) Hire charge of pump in/c
spare and maintenance 72 hrs @ Tk. 335.77 Per hour = Tk. 24,175.44
(b) Fuel: @ 4.375 liter per hour 315 liter @ Tk. 83.81 Per liter = Tk. 26,400.15
(c) Foreman: @ 1 No. per 8 hrs 9 Nos. @ Tk. 567.00 each = Tk. 5,103.00
(d) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(e) Local carriage, T & P L.S. = Tk. 857.50
Total = Tk. 58,354.09
Analysis of PWD SoR 2014 for Civil Works 520

Profit 10.00% = Tk. 5,835.41


Overhead 3.50% = Tk. 2,042.39
= Tk. 66,231.89
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,854.76
Grand total = Tk. 70,086.65
Rate per hour = Tk. 973.43

Say, Tk. 973 .00 Per hour.


Item No.- 27.39
Disinfection of the tube well
Cost for disinfection of the tube well including supply of all the materials and
other necessary cost as per specification (for 150 x 200 mm tube-well) L.S. = Tk. 1,577.91
Profit 10.00% = Tk. 157.79
Overhead 3.50% = Tk. 55.23
= Tk. 1,790.93
Add VAT with adjustment factor 1.0582 5.50% = Tk. 104.23
Total = Tk. 1,895.16

Say, Tk. 1,895 .00 each

Item No.- 27.40


Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(b) Skilled labour 9 No. @ Tk. 303.00 each = Tk. 2,727.00
(c) Local carriage, T & P L.S. = Tk. 306.25
Total = Tk. 3,600.25
Profit 10.00% = Tk. 360.03
Overhead 3.50% = Tk. 126.01
= Tk. 4,086.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 237.83
Grand total = Tk. 4,324.12
Rate per rm. = Tk. 43.24

Say, Tk. 43 .00 per rm

Item No.- 27.41


Protective top cover
Considering for 1 job
(a) 300 mm dia and 6 mm
thick M.S. pipe 1 meter @ Tk. 5,037.14 Per meter = Tk. 5,037.14
(b) 6 mm thick 350 mm
dia M.S. plate 1 No. @ Tk. 1,296.74 each = Tk. 1,296.74
(c) Welding and other cost as necessary L.S. = Tk. 612.50
Total = Tk. 6,946.38
Profit 10.00% = Tk. 694.64
Overhead 3.50% = Tk. 243.12
= Tk. 7,884.14
Add VAT with adjustment factor 1.0582 5.50% = Tk. 458.86
Grand total = Tk. 8,343.00

Say, Tk. 8,343 .00 each

ANALYSIS FOR INSTALLATION OF 150 mm x 300 mm DIA SHROUDED


PRODUCTION WELL WITH G.I. PIPE

Item No.- 27.42.1


Analysis of PWD SoR 2014 for Civil Works 521

600 mm dia boring


a) Considering 0 m to 50 meter
Cost for boring including all equipment,
accessories, labours and materials along
with insurance coverage of risks 50 meter @ Tk. 849 Per meter = Tk. 42,450.00
Profit 10.00% = Tk. 4,245.00
Overhead 3.50% = Tk. 1,485.75
= Tk. 48,180.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,804.17
Total = Tk. 50,984.92
Rate Per meter (from 0 m to 50 m) = Tk. 1,019.70

Say, Tk. 1,020 .00 Per rm

Item No.- 27.42.2


600 mm dia boring
Considering 50 m to 100 m
(a) Rate for 0 m to 50 m = Tk. 1,019.70
(b) Add for 50 m to 100 m 15% = Tk. 152.96
Total = Tk. 1,172.66
Rate Per meter (50 m to 100 m) = Tk. 1,172.66

Say, Tk. 1,173 .00 Per rm

Item No.- 27.42.3


600 mm dia boring
Considering 100 m to 152 m
(a) Rate for 50 m to 100 m = Tk. 1,172.66
(b) Add for 100 m to 152 m 15% = Tk. 175.90
Total = Tk. 1,348.56
Rate Per meter (100 m to 152 m) = Tk. 1,348.56

Say, Tk. 1,349 .00 Per rm

Item No.- 27.42.4


600 mm dia boring
Considering 152 m to 200 m
(a) Rate for 100 m to 152 m = Tk. 1,348.56
(b) Add for 152 m to 200 m 15% = Tk. 202.28
Total = Tk. 1,550.84
Rate Per meter (152 m to 200 m) = Tk. 1,550.84

Say, Tk. 1,551 .00 Per rm


Item No.- 27.42.5
600 mm dia boring
Considering 200 m to 250 m
(a) Rate for 152 m to 200 m = Tk. 1,550.84
(b) Add for 200 m to 250 m 15% = Tk. 232.63
Total = Tk. 1,783.47
Rate Per meter (200 m to 250 m) = Tk. 1,783.47

Say, Tk. 1,783 .00 Per rm


Item No.- 27.42.6
600 mm dia boring
Beyond 250 m
(i) Rate for 200m to 250 m = Tk. 1,783.47
(ii) Add for beyond 250 m 15% = Tk. 267.52
Analysis of PWD SoR 2014 for Civil Works 522

Total = Tk. 2,050.99


Rate Per meter (beyond 250 m) = Tk. 2,050.99

Say, Tk. 2,051 .00 Per rm

Item No.- 27.43.1


Supplying 150 mm dia M.S. cap
Considering 1 No.
(a) 6 mm thick 150 mm dia M.S. cap 1 No. @ Tk. 990.23 each = Tk. 990.23
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 1,009.83
Profit 10.00% = Tk. 100.98
Overhead 3.50% = Tk. 35.34
= Tk. 1,146.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 66.71
Grand total = Tk. 1,212.86
Rate each. = Tk. 1,212.86

Say, Tk. 1,213 .00 each.

Item No.- 27.43.2


Supplying 150 mm dia 4.85 mm thick tube well pipe and blank G.I. pipe
Considering 1 meter
(a) 150 mm dia 4.85 mm thick G.I. Pipe 1 meter @ Tk. 2,462.63 Per meter = Tk. 2,462.63
(b) Carriage of materials L.S. = Tk. 61.25
Total = Tk. 2,523.88
Profit 10.00% = Tk. 252.39
Overhead 3.50% = Tk. 88.34
= Tk. 2,864.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 166.72
Grand total = Tk. 3,031.33
Rate per rm. = Tk. 3,031.33

Say, Tk. 3,031 .00 Per rm.

Item No.- 27.43.3.1


i) Supplying 150 mm dia stainless steel strainer of continuous slot (bridge type or equivalent)
having 28.84 kg per meter.
Considering 6.1 meter
(a) 150 mm dia stainless steel strainer 6.1 meter @ Tk. 12,117.41 Per meter = Tk. 73,916.20
(b) 12 mm dia M.S. rod 47.30 Ibs. @ Tk. 27.89 Per Ib. = Tk. 1,319.20
(c) Local carriage, welding & other necessary cost L.S. = Tk. 294.00
Total = Tk. 75,529.40
Profit 10.00% = Tk. 7,552.94
Overhead 3.50% = Tk. 2,643.53
= Tk. 85,725.87
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4,989.33
Grand total = Tk. 90,715.20
Rate per rm. = Tk. 14,871.34

Say, Tk. 14,871 .00 Per rm.


Item No.- 27.43.3.2
ii) Supplying 150 mm dia 2.5 mm thick stainless steel bridge type strainer
Considering 6.1 meter
(a) 150 mm dia 2.5 mm thick stainless
steel bridge type strainer 6.1 meter @ Tk. 8,644.03 Per meter = Tk. 52,728.58
(b) 12 mm dia M.S. rod 47.30 Ibs. @ Tk. 27.89 Per Ib. = Tk. 1,319.20
Analysis of PWD SoR 2014 for Civil Works 523

(c) Local carriage, welding & other necessary cost L.S. = Tk. 294.00
Total = Tk. 54,341.78
Profit 10.00% = Tk. 5,434.18
Overhead 3.50% = Tk. 1,901.96
= Tk. 61,677.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,589.72
Grand total = Tk. 65,267.64
Rate per rm. = Tk. 10,699.61

Say, Tk. 10,700 .00 Per rm.

Item No.- 27.43.4


Supplying 150 mm x 300 mm dia 6 mm thick M.S. reducer.
Considering 1 No.
(a) 150 x 300 mm dia M.S. reducer 1 No. @ Tk. 2,800.00 each = Tk. 2,800.00
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 2,922.50
Profit 10.00% = Tk. 292.25
Overhead 3.50% = Tk. 102.29
= Tk. 3,317.04
Add VAT with adjustment factor 1.0582 5.50% = Tk. 193.06
Grand total = Tk. 3,510.10
Rate each. = Tk. 3,510.10

Say, Tk. 3,510 .00 each.

Item No.- 27.43.5


Supplying 300 mm dia 6 mm thick M.S. housing pipe (welded)
Considering 1 meter
(a) 300 mm dia 6 mm thick
M.S. housing pipe 1 meter @ Tk. 5,037.14 Per meter = Tk. 5,037.14
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 5,159.64
Profit 10.00% = Tk. 515.96
Overhead 3.50% = Tk. 180.59
= Tk. 5,856.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 340.84
Grand total = Tk. 6,197.03
Rate per rm. = Tk. 6,197.03

Say, Tk. 6,197 .00 Per rm.

Item No.- 27.43.6


Supplying 300 mm dia 6 mm thick M.S. housing pipe (seamless)
Considering 1 meter
(a) 300 mm dia 6 mm thick
M.S. housing pipe 1 meter @ Tk. 8,178.48 Per meter = Tk. 8,178.48
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 8,300.98
Profit 10.00% = Tk. 830.10
Overhead 3.50% = Tk. 290.53
= Tk. 9,421.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 548.35
Grand total = Tk. 9,969.96
Rate per rm. = Tk. 9,969.96
Analysis of PWD SoR 2014 for Civil Works 524

Say, Tk. 9,970 .00 Per rm.

Item No.- 27.43.7


Supplying centralizer made with 12 mm dia M.S. rod of approved design
Considering 1 No.
(a) 1 set centralizer consists of four leaves:
12 mm dia M.S. rod:
4 x 3'-0"+2*3.14*0.5=15'-3" 9.1 Ibs @ Tk. 27.89 Per meter = Tk. 253.80
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 49.00
Total = Tk. 302.80
Profit 10.00% = Tk. 30.28
Overhead 3.50% = Tk. 10.60
= Tk. 343.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.00
Grand total = Tk. 363.68
Rate each. = Tk. 363.68

Say, Tk. 364 .00 each.

Item No.- 27.43.8


Supplying 350 mm dia M.S. cap of 6 mm thick.
Considering 1 No.
(a) 350 mm dia 6 mm
thick M.S. cap. 1 No. @ Tk. 1,400.80 each = Tk. 1,400.80
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 294.00
Total = Tk. 1,694.80
Profit 10.00% = Tk. 169.48
Overhead 3.50% = Tk. 59.32
= Tk. 1,923.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 111.96
Grand total = Tk. 2,035.56
Rate each. = Tk. 2,035.56

Say, Tk. 2,036 .00 each.

Item No.- 27.44


Complete installation of tube well fixtures
Considering 107 meter for 1 No. tube-well
(a) Filling the pit with slurry in/c preparation of slurry L.S. = Tk. 1,960.00
(b) Lowering the bail plug, strainer, 150 mm dia G.I. Pipe
and 300 mm dia M.S. housing
pipe in/c coverage of risk 107 meter @ Tk. 93.10 Per meter = Tk. 9,961.70
(c) Verticality test 2 times @ Tk. 1,470.00 Per time = Tk. 2,940.00
(d) Necessary welding, cutting, jointing, levelling in/c cost of
electrodes, welding set, electricity connection fees, tools and plants etc. L.S. = Tk. 5,390.00
(e) Cost for filling the peagravels 28 cum. @ Tk. 43.24 Per cum = Tk. 1,210.72
(f) Final anchoring the tubewell in/c supply of joint,
concrete, brick work etc. L.S. = Tk. 9,800.00
Total = Tk. 31,262.42
Profit 10.00% = Tk. 3,126.24
Overhead 3.50% = Tk. 1,094.18
= Tk. 35,482.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,065.14
Grand total = Tk. 37,547.98
Rate per rm. = Tk. 350.92

Say, Tk. 351 .00 Per rm.


Analysis of PWD SoR 2014 for Civil Works 525

Item No.- 27.45


Complete development of the tube well by air compressor and pump of suitable capacity by alternate
surging and pumping untill satisfactory yield, sand free water and the turbidity condotions is reached.
27.45.1 Development of tube well for depth up to 200 m. L.S. = Tk. 34,814.71
Profit 10.00% = Tk. 3,481.47
Overhead 3.50% = Tk. 1,218.51
= Tk. 39,514.69
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,299.79
Grand total = Tk. 41,814.48

Say, Tk. 41,814 .00 each

27.45.2 Development of tube well for the depth beyond 200 m: = Tk. 47,389.74

Say, Tk. 47,390 .00 each

Item No.- 27.46


Long term pumping test of the well by required capacity pump including drawdown and
recovery test etc. complete
Considering 72 hrs.
(a) Hire charge of pump in/c
spare and maintenance 72 hrs @ Tk. 359.75 Per hour = Tk. 25,902.00
(b) Fuel for pump:
@ 4.375 liter per hour 315 liter @ Tk. 83.81 Per liter = Tk. 26,400.15
(c) Foreman: @ 1 No. per 8 hrs 9 Nos. @ Tk. 567.00 each = Tk. 5,103.00
(d) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(e) Local carriage, T & P L.S. = Tk. 857.50
Total = Tk. 60,080.65
Profit 10.00% = Tk. 6,008.07
Overhead 3.50% = Tk. 2,102.82
= Tk. 68,191.54
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,968.82
Grand total = Tk. 72,160.36
Rate per hour = Tk. 1,002.23

Say, Tk. 1,002 .00 Per hour.

Item No.- 27.47


Disinfection of the tube well
Cost for disinfection of the tube well including supply of all the
materials and other necessary cost as per specification L.S. = Tk. 1,610.81
Profit 10.00% = Tk. 161.08
Overhead 3.50% = Tk. 56.38
= Tk. 1,828.27
Add VAT with adjustment factor 1.0582 5.50% = Tk. 106.41
Total = Tk. 1,934.68
Say, Tk. 1,935 .00 each
Item No.- 27.48
Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter 100 meter
(a) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(b) Skilled labour 9 No. @ Tk. 303.00 each = Tk. 2,727.00
(c) Local carriage, T & P L.S. = Tk. 306.25
Total = Tk. 3,600.25
Profit 10.00% = Tk. 360.03
Overhead 3.50% = Tk. 126.01
Analysis of PWD SoR 2014 for Civil Works 526

= Tk. 4,086.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 237.83
Grand total = Tk. 4,324.12
Rate per rm. = Tk. 43.24

Say, Tk. 43 .00 Per rm.

ANALYSIS FOR INSTALLATION OF 200 mm x 400 mm DIA SHROUDED


PRODUCTION WELL WITH G.I. PIPE

Item No.- 27.49.1


800 mm dia boring
a) Considering 0 m to 50 m
Cost for boring including all equipment,
accessories, labours and materials along
with insurance coverage of risks 50 meter @ Tk. 947 Per meter = Tk. 47,350.00
Profit 10.00% = Tk. 4,735.00
Overhead 3.50% = Tk. 1,657.25
= Tk. 53,742.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,127.85
Total = Tk. 56,870.10

Rate Per meter (from 0 m to 50 m) = Tk. 1,137.40

Say, Tk. 1,137 .00 Per m


Item No.- 27.49.2
600 mm dia boring
Considering 50 m to 100 m
(a) Rate for 0 m to 50 m = Tk. 1,137.40
(b) Add for 50 m to 100 m 15% = Tk. 170.61
Total = Tk. 1,308.01
Rate Per meter (50 m to 100 m ) = Tk. 1,308.01

Say, Tk. 1,308 .00 Per rm


Item No.- 27.49.3
600 mm dia boring
Considering 100 m to 152 m
(a) Rate for 50 m to 100 m = Tk. 1,308.01
(b) Add for 100 m to 152 m 15% = Tk. 196.20
Total = Tk. 1,504.21
Rate Per meter (100 m to 152 m) = Tk. 1,504.21

Say, Tk. 1,504 .00 Per rm


Item No.- 27.49.4
600 mm dia boring
Considering 152 m to 200 m
(a) Rate for 100 m to 152 m = Tk. 1,504.21
(b) Add for 152 m to 200 m 15% = Tk. 225.63
Total = Tk. 1,729.84
Rate Per meter (152 m to 200 m) = Tk. 1,729.84

Say, Tk. 1,730 .00 Per rm


Item No.- 27.49.5
600 mm dia boring
Considering 200 m to 250 m
(a) Rate for 152 m to 200 m = Tk. 1,729.84
(b) Add for 200 m to 250 m 15% = Tk. 259.48
Analysis of PWD SoR 2014 for Civil Works 527

Total = Tk. 1,989.32


Rate Per meter (200 m to 250 m) = Tk. 1,989.32

Say, Tk. 1,989 .00 Per rm

Item No.- 27.49.6


600 mm dia boring
f) Beyond 250 m
(i) Rate for 200m to 250 m = Tk. 1,989.32
(ii) Add for beyond 250 m 15% = Tk. 298.40
Total = Tk. 2,287.72
Rate Per meter (beyond 250 m) = Tk. 2,287.72

Say, Tk. 2,288 .00 Per rm

Item No.- 27.50.1


Supplying 200 mm dia M.S. cap
Considering 1 No.
(a) 6 mm thick 200 mm
dia M.S. cap 1 No. @ Tk. 1,296.74 each = Tk. 1,296.74
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 1,316.34
Profit 10.00% = Tk. 131.63
Overhead 3.50% = Tk. 46.07
= Tk. 1,494.04
Add VAT with adjustment factor 1.0582 5.50% = Tk. 86.95
Grand total = Tk. 1,580.99
Rate each. = Tk. 1,580.99

Say, Tk. 1,581 .00 each.

Item No.- 27.50.2


Supplying 200 mm dia 6 mm thick tube well pipe and blank G.I. pipe
Considering 1 meter
(a) 200 mm dia 6 mm
thick G.I. pipe 1 meter @ Tk. 5,770.75 Per meter = Tk. 5,770.75
(b) Carriage of materials L.S. = Tk. 61.25
Total = Tk. 5,832.00
Profit 10.00% = Tk. 583.20
Overhead 3.50% = Tk. 204.12
= Tk. 6,619.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 385.25
Grand total = Tk. 7,004.57
Rate per rm. = Tk. 7,004.57

Say, Tk. 7,005 .00 Per rm.


Item No.- 27.50.3.1
Supplying 200 mm dia stainless steel strainer of continuous slot having 28.84 kg per meter.
Considering 6.1 meter
(a) 200 mm dia stainless
steel strainer 6.1 meter @ Tk. 13,856.05 Per meter = Tk. 84,521.91
(b) 12 mm dia M.S. rod 47.08 Ibs. @ Tk. 27.89 Per Ib = Tk. 1,313.06
(c) Local carriage, welding & other necessary cost L.S. = Tk. 367.50
Total = Tk. 86,202.47
Profit 10.00% = Tk. 8,620.25
Overhead 3.50% = Tk. 3,017.09
= Tk. 97,839.81
Analysis of PWD SoR 2014 for Civil Works 528

Add VAT with adjustment factor 1.0582 5.50% = Tk. 5,694.37


Grand total = Tk. 103,534.18
Rate per rm. = Tk. 16,972.82

Say, Tk. 16,973 .00 Per rm.

Item No.- 27.50.3.2


Supplying 200 mm dia 2.5 mm thick stainless steel bridge type strainer
Considering 6.1 meter
(a) 200 mm dia 2.5 mm thick stainless
steel bridge type strainer 6.1 meter @ Tk. 8,831.97 Per meter = Tk. 53,875.02
(b) 12 mm dia M.S. rod 47.30 Ibs. @ Tk. 27.89 Per Ib = Tk. 1,319.20
(c) Local carriage, welding & other necessary cost L.S. = Tk. 367.50
Total = Tk. 55,561.72
Profit 10.00% = Tk. 5,556.17
Overhead 3.50% = Tk. 1,944.66
= Tk. 63,062.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,670.30
Grand total = Tk. 66,732.85
Rate per rm. = Tk. 10,939.81

Say, Tk. 10,940 .00 Per rm.

Item No.- 27.50.4


Supplying 200 mm x 400 mm dia 6 mm thick M.S. reducer.
Considering 1 No. reducer
(a) 200 x 400 mm
dia M.S. reducer 1 No. @ Tk. 10,823.91 each = Tk. 10,823.91
(b) Carriage of materials L.S. = Tk. 98.00
Total = Tk. 10,921.91
Profit 10.00% = Tk. 1,092.19
Overhead 3.50% = Tk. 382.27
= Tk. 12,396.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 721.48
Grand total = Tk. 13,117.85
Rate each. = Tk. 13,117.85

Say, Tk. 13,118 .00 each.

Item No.- 27.50.5


(i) Supplying 400 mm dia 6 mm thick M.S. housing pipe (welded)
Considering 1 meter
(a) 400 mm dia 6 mm
thick M.S. housing pipe 1 meter @ Tk. 9,017.14 Per meter = Tk. 9,017.14
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 9,139.64
Profit 10.00% = Tk. 913.96
Overhead 3.50% = Tk. 319.89
= Tk. 10,373.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 603.75
Grand total = Tk. 10,977.24
Rate per rm. = Tk. 10,977.24

Say, Tk. 10,977 .00 Per rm.

Item No.- 27.50.6


(ii) Supplying 400 mm dia 6 mm thick M.S. housing pipe (seamless)
Analysis of PWD SoR 2014 for Civil Works 529

Considering 1 meter
(a) 400 mm dia 6 mm
thick M.S. housing pipe 1 meter @ Tk. 11,042.23 Per meter = Tk. 11,042.23
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 11,164.73
Profit 10.00% = Tk. 1,116.47
Overhead 3.50% = Tk. 390.77
= Tk. 12,671.97
Add VAT with adjustment factor 1.0582 5.50% = Tk. 737.52
Grand total = Tk. 13,409.49
Rate per rm. = Tk. 13,409.49

Say, Tk. 13,409 .00 Per rm.

Item No.- 27.50.7


Supplying centralizer made with 12 mm dia M.S. rod of approved design
Considering 1 No.
(a) 1 set centralizer consists of four leaves:
12 mm dia M.S. rod:
4 x 3'-0"+2*3.14*0.5=15'-3" 9.1 Ibs @ Tk. 27.89 Per meter = Tk. 253.80
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 49.00
Total = Tk. 302.80
Profit 10.00% = Tk. 30.28
Overhead 3.50% = Tk. 10.60
= Tk. 343.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.00
Grand total = Tk. 363.68
Rate each. = Tk. 363.68

Say, Tk. 364 .00 each.


Item No.- 27.50.8
Supplying 450 mm dia M.S. cap of 6 mm thick.
Considering 1 No.
(a) Best quality 450 mm dia
6 mm thick M.S. cap. 1 No. @ Tk. 1,400.80 each = Tk. 1,400.80
(b) Carriage, welding, fabrication and other necessary cost etc. L.S. = Tk. 245.00
Total = Tk. 1,645.80
Profit 10.00% = Tk. 164.58
Overhead 3.50% = Tk. 57.60
= Tk. 1,867.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 108.72
Grand total = Tk. 1,976.70
Rate each. = Tk. 1,976.70
Say, Tk. 1,977 .00 each.
Item No.- 27.51
Complete installation of tube well fixtures
Considering 107 meter of 1 No. tube-well:
(a) Filling the pit with slurry in/c preparation of slurry L.S. = Tk. 1,633.33
(b) Lowering the bail plug, strainer, 150 mm dia G.I. pipe
and 300 mm dia M.S. housing
pipe in/c coverage of risk 107 meter @ Tk. 98.00 Per meter = Tk. 10,486.00
(c) Verticality test 2 times @ Tk. 1,470.00 Per time = Tk. 2,940.00
(d) Necessary welding, cutting, jointing, levelling in/c cost of
electrodes, welding set, electricity connection fees, tools and plants etc. L.S. = Tk. 8,085.00
(e) Cost for filling the peagravels 28 cum. @ Tk. 43.24 Per cum = Tk. 1,210.72
(f) Final anchoring the tubewell in/c supply of joint, concrete,
brick work etc. L.S. = Tk. 9,800.00
Analysis of PWD SoR 2014 for Civil Works 530

Total = Tk. 34,155.05


Profit 10.00% = Tk. 3,415.51
Overhead 3.50% = Tk. 1,195.43
= Tk. 38,765.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,256.22
Grand total = Tk. 41,022.21
Rate per rm. = Tk. 383.39

Say, Tk. 383 .00 Per rm.

Item No.- 27.52


Complete development of the tube well by air compressor and pump of suitable capacity by alternate
surging and pumping untill satisfactory yield, sand free water and the turbidity condotions is reached.
27.52.1 Development of tube well for depth up to 200 m. L.S. = Tk. 32,177.78
Profit 10.00% = Tk. 3,217.78
Overhead 3.50% = Tk. 1,126.22
= Tk. 36,521.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,125.60
Grand total = Tk. 38,647.38

Say, Tk. 38,647 .00 each

27.52.2 Development of tube well for the depth beyond 200 m: = Tk. 43,194.13
Say, Tk. 43,194 .00 each

Item No.- 27.53


Long term pumping test of the well by required capacity pump including drawdown and recovery test etc. complete
Considering 72 hrs.
(a) Hire charge of pump in/c
spare and maintenance 72 hrs @ Tk. 359.75 Per hour = Tk. 25,902.00
(b) Fuel for pump:
@ 4.8 liter per hour 345 liter @ Tk. 83.81 Per liter = Tk. 28,914.45
(c) Foreman: @ 1 No. per 8 hrs 9 Nos. @ Tk. 567.00 each = Tk. 5,103.00
(d) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(e) Local carriage, T & P L.S. = Tk. 857.50
Total = Tk. 62,594.95
Profit 10.00% = Tk. 6,259.50
Overhead 3.50% = Tk. 2,190.82
= Tk. 71,045.27
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4,134.91
Grand total = Tk. 75,180.18
Rate per hour = Tk. 1,044.17
Say, Tk. 1,044 .00 Per hour.
Item No.- 27.54
Disinfection of the tube well
Cost for disinfection of the tube well including supply of
all the materials and other necessary cost as per
specification L.S. = Tk. 1,840.90
Profit 10.00% = Tk. 184.09
Overhead 3.50% = Tk. 64.43
= Tk. 2,089.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 121.61
Total = Tk. 2,211.03

Say, Tk. 2,211 .00 each

Item No.- 27.55


Analysis of PWD SoR 2014 for Civil Works 531

Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(b) Skilled labour 9 No. @ Tk. 303.00 each = Tk. 2,727.00
(c) Local carriage, T & P L.S. = Tk. 306.25
Total = Tk. 3,600.25
Profit 10.00% = Tk. 360.03
Overhead 3.50% = Tk. 126.01
= Tk. 4,086.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 237.83
Grand total = Tk. 4,324.12
Rate per rm. = Tk. 43.24

Say, Tk. 43 .00 per rm.

ANALYSIS FOR INSTALLATION OF 50 mm x 150 mm DIA SHROUDED


PRODUCTION WELL WITH G.I. PIPE

Item No.- 27.56.1


325 mm dia boring
a) Considering 0 m to 50 m
Cost for boring including all equipment,
accessories, labours and materials along
with insurance coverage of risks 50 meter @ Tk. 624.24 Per meter = Tk. 31,212.00
Profit 10.00% = Tk. 3,121.20
Overhead 3.50% = Tk. 1,092.42
= Tk. 35,425.62
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,061.81
Total = Tk. 37,487.43
Rate Per meter (from 0 m to 50 m) = Tk. 749.75

Say, Tk. 750 .00 Per rm


Item No.- 27.56.2
325 mm dia boring
Considering 50 m to 100 m
(a) Rate for 0 m to 50 m = Tk. 749.75
(b) Add for 50 m to 100 m 15% = Tk. 112.46
Total = Tk. 862.21
Rate Per meter (50 m to 100 m) = Tk. 862.21

Say, Tk. 862 .00 Per rm


Item No.- 27.56.3
325 mm dia boring
Considering 100 m to 152 m
(a) Rate for 50 m to 100 m = Tk. 862.21
(b) Add for 100 m to 152 m 15% = Tk. 129.33
Total = Tk. 991.54
Rate Per meter (100 m to 152 m) = Tk. 991.54

Say, Tk. 992 .00 Per rm

Item No.- 27.56.4


325 mm dia boring
Considering 152 m to 200 m
(a) Rate for 100 m to 152 m = Tk. 991.54
(b) Add for 152 m to 200 m 15% = Tk. 148.73
Analysis of PWD SoR 2014 for Civil Works 532

Total = Tk. 1,140.27


Rate Per meter (152 m to 200 m) = Tk. 1,140.27

Say, Tk. 1,140 .00 Per rm

Item No.- 27.56.5


325 mm dia boring
Considering 200 m to 250 m
(a) Rate for 152 m to 200 m = Tk. 1,140.27
(b) Add for 200 m to 250 m 15% = Tk. 171.04
Total = Tk. 1,311.31
Rate Per meter (200 m to 250 m) = Tk. 1,311.31

Say, Tk. 1,311 .00 Per rm

Item No.- 27.56.6


325 mm dia boring
Beyond 250 m
(a) Rate for 200m to 250 m = Tk. 1,311.31
(b) Add for beyond 250 m 15% = Tk. 196.70
Total = Tk. 1,508.01
Rate Per meter (beyond 250 m) = Tk. 1,508.01

Say, Tk. 1,508 .00 Per rm

Item No.- 27.57.1


Supplying 150 mm dia M.S. cap
Considering 1 No.
(a) 6 mm thick 150 mm
dia M.S. cap 1 No. @ Tk. 990.23 each = Tk. 990.23
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 1,009.83
Profit 10.00% = Tk. 100.98
Overhead 3.50% = Tk. 35.34
= Tk. 1,146.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 66.71
Grand total = Tk. 1,212.86
Rate each. = Tk. 1,212.86

Say, Tk. 1,213 .00 each.

Item No.- 27.57.2


Supplying 50 mm dia 4.85 mm thick tube well pipe and blank G.I. pipe
Considering 1 meter
(a) 50 mm dia 4.85 mm
thick G.I. pipe 1 meter @ Tk. 647.44 Per meter = Tk. 647.44
(b) Carriage of materials L.S. = Tk. 61.25
Total = Tk. 708.69
Profit 10.00% = Tk. 70.87
Overhead 3.50% = Tk. 24.80
= Tk. 804.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 46.81
Grand total = Tk. 851.17
Rate per rm. = Tk. 851.17

Say, Tk. 851 .00 Per rm.


Analysis of PWD SoR 2014 for Civil Works 533

Item No.- 27.57.3.1


Supplying 50 mm dia stainless steel strainer of continuous slot (bridge type or equivalent)
having 28.84 kg per meter.
Considering 6.1 meter
(a) 50 mm dia
stainless steel strainer 6.1 meter @ Tk. 4,549.91 Per meter = Tk. 27,754.45
(b) 12 mm dia M.S. rod 47.30 Ibs. @ Tk. 27.89 Per Ib. = Tk. 1,319.20
(c) Local carriage, welding & other necessary cost L.S. = Tk. 294.00
Total = Tk. 29,367.65
Profit 10.00% = Tk. 2,936.77
Overhead 3.50% = Tk. 1,027.87
= Tk. 33,332.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,939.97
Grand total = Tk. 35,272.26
Rate per rm. = Tk. 5,782.34

Say, Tk. 5,782 .00 Per rm.

Item No.- 27.57.3.2


Supplying 50 mm dia 2.5 mm thick stainless steel bridge type strainer
Considering 6.1 meter
(a) 50 mm dia 2.5 mm thick stainless
steel bridge type strainer 6.1 meter @ Tk. 4,549.91 Per meter = Tk. 27,754.45
(b) 12 mm dia M.S. rod 47.30 Ibs. @ Tk. 27.89 Per Ib. = Tk. 1,319.20
(c) Local carriage, welding & other necessary cost L.S. = Tk. 294.00
Total = Tk. 29,367.65
Profit 10.00% = Tk. 2,936.77
Overhead 3.50% = Tk. 1,027.87
= Tk. 33,332.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,939.97
Grand total = Tk. 35,272.26
Rate per rm. = Tk. 5,782.34

Say, Tk. 5,782 .00 Per rm.

Item No.- 27.57.4


Supplying 50 mm x 150 mm dia 6 mm thick M.S. reducer.
Considering 1 No.
(a) 50 x 150 mm dia M.S. reducer 1 No. @ Tk. 1,865.73 each = Tk. 1,865.73
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 1,988.23
Profit 10.00% = Tk. 198.82
Overhead 3.50% = Tk. 69.59
= Tk. 2,256.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 131.34
Grand total = Tk. 2,387.98
Rate each. = Tk. 2,387.98

Say, Tk. 2,388 .00 each.

Item No.- 27.57.5


Supplying 150 mm dia 6 mm thick M.S. housing pipe (welded)
Considering 1 meter
(a) 150 mm dia 6 mm
thick M.S. housing pipe 1 meter @ Tk. 2,549.97 Per meter = Tk. 2,549.97
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 2,672.47
Analysis of PWD SoR 2014 for Civil Works 534

Profit 10.00% = Tk. 267.25


Overhead 3.50% = Tk. 93.54
= Tk. 3,033.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 176.54
Grand total = Tk. 3,209.80
Rate per rm. = Tk. 3,209.80

Say, 3210 .00 Per rm.

Item No.- 27.57.6


Supplying 150 mm dia 6 mm thick M.S. housing pipe (seamless)
Considering 1 meter
(a) 150 mm dia 6 mm
thick M.S. housing pipe 1 meter @ Tk. 2,639.54 Per meter = Tk. 2,639.54
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 2,762.04
Profit 10.00% = Tk. 276.20
Overhead 3.50% = Tk. 96.67
= Tk. 3,134.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 182.45
Grand total = Tk. 3,317.36
Rate per rm. = Tk. 3,317.36

Say, 3317 .00 Per rm.


Item No.- 27.57.7
Supplying centralizer made with 12 mm dia M.S. rod of approved design
Considering 1 No.
(a) 1 set centralizer consists of four leaves:
12 mm dia M.S. rod:
4 x 3'-0"+2*3.14*0.5=15'-3" 9.1 Ibs @ Tk. 27.89 Per meter = Tk. 253.80
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 49.00
Total = Tk. 302.80
Profit 10.00% = Tk. 30.28
Overhead 3.50% = Tk. 10.60
= Tk. 343.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.00
Grand total = Tk. 363.68
Rate each. = Tk. 363.68
Say, 364 .00 each.
Item No.- 27.57.8
Supplying 150 mm dia M.S. cap of 6 mm thick.
Considering 1 No.
(a) Best quality 150 mm
dia 6 mm thick M.S. cap. 1 No. @ Tk. 990.23 each = Tk. 990.23
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 294.00
Total = Tk. 1,284.23
Profit 10.00% = Tk. 128.42
Overhead 3.50% = Tk. 44.95
= Tk. 1,457.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 84.83
Grand total = Tk. 1,542.43
Rate each. = Tk. 1,542.43

Say, 1542 .00 each.

Item No.- 27.58


Complete installation of tube well fixtures
Analysis of PWD SoR 2014 for Civil Works 535

Considering 107 meter of 1 No. tube-well:


(a) Filling the pit with slurry in/c preparation of slurry L.S. = Tk. 1,960.00
(b) Lowering the bail plug, strainer, 50 mm dia G.I. pipe and
150 mm dia M.S. housing
pipe in/c coverage of risk 107 meter @ Tk. 93.10 Per meter = Tk. 9,961.70
(c) Verticality test 2 times @ Tk. 1,470.00 Per time = Tk. 2,940.00
(d) Necessary welding, cutting, jointing, levelling in/c cost of
electrodes, welding set, electricity connection fees, tools and plants etc. L.S. = Tk. 5,390.00
(e) Cost for filling the peagravels 28 cum. @ Tk. 43.24 Per cum = Tk. 1,210.72
(f) Final anchoring the tubewell in/c supply of joint, concrete,
brick work etc. L.S. = Tk. 9,800.00
Total = Tk. 31,262.42
Profit 10.00% = Tk. 3,126.24
Overhead 3.50% = Tk. 1,094.18
= Tk. 35,482.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,065.14
Grand total = Tk. 37,547.98
Rate per rm. = Tk. 350.92

Say, Tk. 351 .00 Per rm.

Item No.- 27.59


Complete development of the tube well by air compressor and pump of suitable capacity by alternate
surging and pumping untill satisfactory yield, sand free water and the turbidity condotions is reached.
27.59.1 Development of tube well for depth up to 200 m. L.S. = Tk. 18,573.48
Profit 10.00% = Tk. 1,857.35
Overhead 3.50% = Tk. 650.07
= Tk. 21,080.90
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,226.93
Total = Tk. 22,307.83

Say, Tk. 22,308 .00 each

27.59.2 Development of tube well for the depth beyond 200 m: = Tk. 25,282.21

Say, Tk. 25,282 .00 each


Analysis of PWD SoR 2014 for Civil Works 536

Item No.- 27.60


Long term pumping test of the well by required capacity pump including drawdown and
recovery test etc. complete
Considering 72 hrs.
(a) Hire charge of pump in/c
spare and maintenance 72 hrs @ Tk. 230.24 Per hour = Tk. 16,577.28
(b) Fuel for pump:
@ 4.375 liter per hour 315 liter @ Tk. 83.81 Per liter = Tk. 26,400.15
(c) Foreman: @ 1 No. per 8 hrs 9 Nos. @ Tk. 567.00 each = Tk. 5,103.00
(d) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(e) Local carriage, T & P L.S. = Tk. 416.50
Total = Tk. 50,314.93
Profit 10.00% = Tk. 5,031.49
Overhead 3.50% = Tk. 1,761.02
= Tk. 57,107.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,323.71
Grand total = Tk. 60,431.15
Rate per hour = Tk. 839.32

Say, Tk. 839 .00 Per hour.

Item No.- 27.61


Disinfection of the tube well
(a) Cost for disinfection of the tube well including supply
of all the materials and other necessary
cost as per specification L.S. = Tk. 920.45
Profit 10.00% = Tk. 92.05
Overhead 3.50% = Tk. 32.22
= Tk. 1,044.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 60.80
Total = Tk. 1,105.52

Say, Tk. 1,106 .00 each

Item No.- 27.62


Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(b) Skilled labour 4 Nos. @ Tk. 303.00 each = Tk. 1,212.00
(c) Local carriage, T & P L.S. = Tk. 306.25
Total = Tk. 2,085.25
Profit 10.00% = Tk. 208.53
Overhead 3.50% = Tk. 72.98
= Tk. 2,366.76
Add VAT with adjustment factor 1.0582 5.50% = Tk. 137.75
Grand total = Tk. 2,504.51
Rate per rm. = Tk. 25.05
Say, Tk. 25 .00 Per rm.
ANALYSIS FOR INSTALLATION OF 75 mm x 150 mm DIA SHROUDED
PRODUCTION WELL WITH G.I. PIPE

Item No. -27.63.1


350 mm dia boring
a) Considering 0 m to 50 m
Cost for boring including all equipment, accessories, labours and materials along with insurance coverage of risks
50 meter @ Tk. 658.9 Per meter = Tk. 32,945.00
Profit 10.00% = Tk. 3,294.50
Analysis of PWD SoR 2014 for Civil Works 537

Overhead 3.50% = Tk. 1,153.08


= Tk. 37,392.58
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,176.29
Total = Tk. 39,568.87

Rate Per meter (from 0 m to 50 m) = Tk. 791.38

Say, Tk. 791 .00 Per rm

Item No.- -27.63.2


350 mm dia boring
Considering 50 m to 100 m
(a) Rate for 0 m to 50 m = Tk. 791.38
(b) Add for 50 m to 100 m 15% = Tk. 118.71
Total = Tk. 910.09
Rate Per meter (50 m to 100 m) = Tk. 910.09

Say, Tk. 910 .00 Per rm

Item No. -27.63.3


350 mm dia boring
Considering 100 m to 152 m
(a) Rate for 50 m to 100 m = Tk. 910.09
(b) Add for 100 m to 152 m 15% = Tk. 136.51
Total = Tk. 1,046.60
Rate Per meter (100 m to 152 m) = Tk. 1,046.60

Say, Tk. 1,047 .00 Per rm

Item No. -27.63.4


350 mm dia boring
Considering 152 m to 200 m
(a) Rate for 100 m to 152 m = Tk. 1,046.60
(b) Add for 152 m to 200 m 15% = Tk. 156.99
Total = Tk. 1,203.59
Rate Per meter (152 m to 200 m) = Tk. 1,203.59
Say, Tk. 1,204 .00 Per rm

Item No. -27.63.5


350 mm dia boring
Considering 200 m to 250 m
(a) Rate for 152 m to 200 m = Tk. 1,203.59
(b) Add for 200 m to 250 m 15% = Tk. 180.54
Total = Tk. 1,384.13
Rate Per meter (200 m to 250 m) = Tk. 1,384.13
Say, Tk. 1,384 .00 Per rm

Item No. -27.63.6


350 mm dia boring
Beyond 250 m
(a) Rate for 200m to 250 m = Tk. 1,384.13
(b) Add for beyond 250 m 15% = Tk. 207.62
Total = Tk. 1,591.75
Rate Per meter (beyond 250 m) = Tk. 1,591.75
Say, Tk. 1,592 .00 Per rm
Item No. -27.64.1
Supplying 150 mm dia M.S. cap
Analysis of PWD SoR 2014 for Civil Works 538

Considering 1 No.
(a) 6 mm thick 150 mm
dia M.S. cap 1 No. @ Tk. 990.23 each = Tk. 990.23
(b) Carriage of materials L.S. = Tk. 16.33
Total = Tk. 1,006.56
Profit 10.00% = Tk. 100.66
Overhead 3.50% = Tk. 35.23
= Tk. 1,142.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 66.49
Grand total = Tk. 1,208.94
Rate each. = Tk. 1,208.94

Say, Tk. 1,209 .00 each.

Item No. -27.64.2


Supplying 75 mm dia 4.85 mm thick tube well pipe and blank G.I. pipe
Considering 1 meter
(a) 75 mm dia 4.85 mm
thick G.I. pipe 1 meter @ Tk. 1,085.98 Per meter = Tk. 1,085.98
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 1,105.58
Profit 10.00% = Tk. 110.56
Overhead 3.50% = Tk. 38.70
= Tk. 1,254.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 73.03
Grand total = Tk. 1,327.87
Rate per rm. = Tk. 1,327.87

Say, Tk. 1,328 .00 Per rm.

Item No.- 27.64.3.1


Supplying 75 mm dia stainless steel strainer of continuous slot having 28.84 kg per meter.
Considering 6.1 meter
(a) 75 mm dia
stainless steel strainer 6.1 meter @ Tk. 6,179.02 Per meter = Tk. 37,692.02
(b) 12 mm dia M.S. rod 47.30 Ibs. @ Tk. 27.89 Per Ib. = Tk. 1,319.20
(c) Local carriage, welding & other necessary cost L.S. = Tk. 367.50
Total = Tk. 39,378.72
Profit 10.00% = Tk. 3,937.87
Overhead 3.50% = Tk. 1,378.26
= Tk. 44,694.85
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,601.28
Grand total = Tk. 47,296.13
Rate Per rm.. = Tk. 7,753.46

Say, Tk. 7,753 .00 Per rm.

Item No.- 27.64.3.2


ii) Supplying 75 mm dia 2.5 mm thick stainless steel bridge type strainer
Considering 6.1 meter
(a) 75 mm dia 2.5 mm thick stainless
steel bridge type strainer 6.1 meter @ Tk. 6,179.02 Per meter = Tk. 37,692.02
(b) 12 mm dia M.S. rod 47.30 Ibs. @ Tk. 27.89 Per Ib. = Tk. 1,319.20
(c) Local carriage, welding & other necessary cost L.S. = Tk. 367.50
Total = Tk. 39,378.72
Profit 10.00% = Tk. 3,937.87
Overhead 3.50% = Tk. 1,378.26
Analysis of PWD SoR 2014 for Civil Works 539

= Tk. 44,694.85
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,601.28
Grand total = Tk. 47,296.13
Rate per rm. = Tk. 7,753.46

Say, Tk. 7,753 .00 Per rm.

Item No.- 27.64.4


Supplying 75 mm x 150 mm dia 6 mm thick M.S. reducer.
Considering 1 No.
(a) 75 x 150 mm dia M.S. reducer 1 No. @ Tk. 4,179.70 each = Tk. 4,179.70
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 4,302.20
Profit 10.00% = Tk. 430.22
Overhead 3.50% = Tk. 150.58
= Tk. 4,883.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 284.20
Grand total = Tk. 5,167.20
Rate each. = Tk. 5,167.20

Say, Tk. 5,167 .00 each.


Item No.- 27.64.5
Supplying 150 mm dia 6 mm thick M.S. housing pipe (welded)
Considering 1 meter
(a) 150 mm dia 6 mm
thick M.S. housing pipe 1 meter @ Tk. 2,549.97 Per meter = Tk. 2,549.97
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 2,672.47
Profit 10.00% = Tk. 267.25
Overhead 3.50% = Tk. 93.54
= Tk. 3,033.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 176.54
Grand total = Tk. 3,209.80
Rate per rm. = Tk. 3,209.80

Say, 3210 .00 Per rm.

Item No.- 27.64.6


Supplying 150 mm dia 6 mm thick M.S. housing pipe (seamless)
Considering 1 meter
(a) 150 mm dia 6 mm
thick M.S. housing pipe 1 meter @ Tk. 2,639.54 Per meter = Tk. 2,639.54
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 2,762.04
Profit 10.00% = Tk. 276.20
Overhead 3.50% = Tk. 96.67
= Tk. 3,134.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 182.45
Grand total = Tk. 3,317.36
Rate per rm. = Tk. 3,317.36

Say, 3317 .00 Per rm.


Item No.- 27.64.7
Supplying centralizer made with 12 mm dia M.S. rod of approved design
Considering 1 No.
(a) 1 set centralizer consists of four leaves:
Analysis of PWD SoR 2014 for Civil Works 540

12 mm dia M.S. rod:


4 x 3'-0"+2*3.14*0.5=15'-3" 9.1 Ibs @ Tk. 27.89 Per meter = Tk. 253.80
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 49.00
Total = Tk. 302.80
Profit 10.00% = Tk. 30.28
Overhead 3.50% = Tk. 10.60
= Tk. 343.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.00
Grand total = Tk. 363.68
Rate each. = Tk. 363.68

Say, 364 .00 each.

Item No.- 27.64.8


Supplying 150 mm dia M.S. cap of 6 mm thick.
Considering 1 No. 1 No.
(a) Cost of best quality 150 mm
dia 6 mm thick M.S. cap. 1 No. @ Tk. 990.23 each = Tk. 990.23
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 294.00
Total = Tk. 1,284.23
Profit 10.00% = Tk. 128.42
Overhead 3.50% = Tk. 44.95
= Tk. 1,457.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 84.83
Grand total = Tk. 1,542.43
Rate each. = Tk. 1,542.43

Say, Tk. 1,542 .00 each.

Item No.- 27.65


Complete installation of tube well fixtures
Considering 107 meter of 1 No. tube-well
(a) Filling the pit with slurry in/c preparation of slurry L.S. = Tk. 1,960.00
(b) Lowering the bail plug, strainer, 50 mm dia G.I. pipe
and 150 mm dia M.S. housing
pipe in/c coverage of risk 107 meter @ Tk. 93.10 Per meter = Tk. 9,961.70
(c) Verticality test 2 times @ Tk. 1,470.00 Per time = Tk. 2,940.00
(d) Necessary welding, cutting, jointing, levelling in/c cost of
electrodes, welding set, electricity connection fees, tools and plants etc. L.S. = Tk. 5,390.00
(e) Cost for filling the peagravels 28 cum. @ Tk. 68.66 Per cum = Tk. 1,922.48
(f) Final anchoring the tubewell in/c supply
of joint, concrete, brick work etc. L.S. = Tk. 8,166.67
Total = Tk. 30,340.85
Profit 10.00% = Tk. 3,034.09
Overhead 3.50% = Tk. 1,061.93
= Tk. 34,436.87
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,004.26
Grand total = Tk. 36,441.13
Rate per rm. = Tk. 340.57

Say, Tk. 341 .00 Per rm.

Item No.- 27.66


Complete development of the tube well by air compressor and pump of suitable capacity by alternate
surging and pumping untill satisfactory yield, sand free water and the turbidity condotions is reached.
27.66.1 Development of tube well for depth up to 200 m. L.S. = Tk. 23,637.15
Profit 10.00% = Tk. 2,363.72
Analysis of PWD SoR 2014 for Civil Works 541

Overhead 3.50% = Tk. 827.30


= Tk. 26,828.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,561.43
Total = Tk. 28,389.60

Say, Tk. 28,390 .00 each

27.66.2 Development of tube well for the depth beyond 200 m: = Tk. 32,174.88

Say, Tk. 32,175 .00 each

Item No.- 27.67


Long term pumping test of the well by required capacity pump including drawdown and
recovery test etc. complete
Considering 72 hrs.
(a) Hire charge of pump in/c
spare and maintenance 72 hrs @ Tk. 359.75 Per hour = Tk. 25,902.00
(b) Fuel for pump:
@ 4.375 liter per hour 240 liter @ Tk. 83.81 Per liter = Tk. 20,114.40
(c) Foreman: @ 1 No. per 8 hrs 9 Nos. @ Tk. 567.00 each = Tk. 5,103.00
(d) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(e) Local carriage, T & P L.S. = Tk. 857.50
Total = Tk. 53,794.90
Profit 10.00% = Tk. 5,379.49
Overhead 3.50% = Tk. 1,882.82
= Tk. 61,057.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,553.59
Grand total = Tk. 64,610.80
Rate per hour = Tk. 897.37

Say, Tk. 897 .00 Per hour.

Item No.- 27.68


Disinfection of the tube well
Cost for disinfection of the tube well including
supply of all the materials and other necessary
cost as per specification L.S. = Tk. 1,117.69
Profit 10.00% = Tk. 111.77
Overhead 3.50% = Tk. 39.12
= Tk. 1,268.58
Add VAT with adjustment factor 1.0582 5.50% = Tk. 73.83
Total = Tk. 1,342.41

Say, Tk. 1,342 .00 each

Item No.- 27.69


Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(b) Skilled labour 5 Nos. @ Tk. 303.00 each = Tk. 1,515.00
(c) Local carriage, T & P L.S. = Tk. 306.25
Total = Tk. 2,388.25
Profit 10.00% = Tk. 238.83
Overhead 3.50% = Tk. 83.59
= Tk. 2,710.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 157.76
Grand total = Tk. 2,868.43
Analysis of PWD SoR 2014 for Civil Works 542

Rate per rm. = Tk. 28.68

Say, Tk. 29 .00 Per rm.

ANALYSIS FOR INSTALLATION OF 100 mm x 200 mm DIA SHROUDED


PRODUCTION WELL WITH G.I. PIPE

Item No.- 27.70.1


400 mm dia boring
a) Considering 0 m to 50 m
Cost for boring including all equipment,
accessories, labours and materials along
with insurance coverage of risks 50 meter @ Tk. 693.60 Per meter = Tk. 34,680.00
Profit 10.00% = Tk. 3,468.00
Overhead 3.50% = Tk. 1,213.80
= Tk. 39,361.80
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,290.90
Total = Tk. 41,652.70
Rate Per meter (from 0 m to 50 m) = Tk. 833.05

Say, Tk. 833 .00 Per rm

Item No.- 27.70.2


400 mm dia boring
Considering 50 m to 100 m
(a) Rate for 0 m to 50 m = Tk. 833.05
(b) Add for 50 m to 100 m 15% = Tk. 124.96
Total = Tk. 958.01
Rate Per meter (50 m to 100 m) = Tk. 958.01

Say, Tk. 958 .00 Per rm


ITEM No.- 27.70.3
400 mm dia boring
Considering 100 m to 152 m
(a) Rate for 50 m to 100 m = Tk. 958.01
(b) Add for 100 m to 152 m 15% = Tk. 143.70
Total = Tk. 1,101.71
Rate Per meter (100 m to 152 m) = Tk. 1,101.71

Say, Tk. 1,102 .00 Per rm


Item No.- 27.70.4
400 mm dia boring
Considering 152 m to 200 m
(a) Rate for 100 m to 152 m = Tk. 1,101.71
(b) Add for 152 m to 200 m 15% = Tk. 165.26
Total = Tk. 1,266.97
Rate Per meter (152 m to 200 m) = Tk. 1,266.97

Say, Tk. 1,267 .00 Per rm


Item No.- 27.70.5
400 mm dia boring
Considering 200 m to 250 m
(a) Rate for 152 m to 200 m = Tk. 1,266.97
(b) Add for 200 m to 250 m 15% = Tk. 190.05
Total = Tk. 1,457.02
Rate Per meter (200 m to 250 m) = Tk. 1,457.02
Analysis of PWD SoR 2014 for Civil Works 543

Say, Tk. 1,457 .00 Per rm

Item No.- 27.70.6


400 mm dia boring
Beyond 250 m
(a) Rate for 200 m to 250 m = Tk. 1,457.02
(b) Add for beyond 250 m 15% = Tk. 218.55
Total = Tk. 1,675.57
Rate Per meter (beyond 250 m) = Tk. 1,675.57

Say, Tk. 1,676 .00 Per rm

Item No.- 27.71.1


Supplying 150 mm dia M.S. cap
Considering 1 No.
(a) Best quality 6 mm thick
150 mm dia M.S. cap 1 No. @ Tk. 990.23 each = Tk. 990.23
(b) Carriage of materials L.S. = Tk. 19.60
Total = Tk. 1,009.83
Profit 10.00% = Tk. 100.98
Overhead 3.50% = Tk. 35.34
= Tk. 1,146.15
Add VAT with adjustment factor 1.0582 5.50% = Tk. 66.71
Grand total = Tk. 1,212.86
Rate each. = Tk. 1,212.86

Say, Tk. 1,213 .00 each.

Item No.- 27.71.2


Supplying 100 mm dia 6 mm thick tube well pipe and blank G.I. pipe
Considering 1 meter
(a) 100 mm dia 6 mm
thick G.I. pipe 1 meter @ Tk. 1,420.74 Per meter = Tk. 1,420.74
(b) Carriage of materials L.S. = Tk. 61.25
Total = Tk. 1,481.99
Profit 10.00% = Tk. 148.20
Overhead 3.50% = Tk. 51.87
= Tk. 1,682.06
Add VAT with adjustment factor 1.0582 5.50% = Tk. 97.90
Grand total = Tk. 1,779.96
Rate per rm. = Tk. 1,779.96

Say, Tk. 1,780 .00 Per rm.

Item No.- 27.71.3.1


Supplying 100 mm dia stainless steel strainer of continuous slot having 28.84 kg per meter.
Considering 6.1 meter
(a) 100 mm dia stainless steel
continuous slot strainer 6.1 meter @ Tk. 5,546.52 Per meter = Tk. 33,833.77
(b) 12 mm dia M.S. rod 47.30 Ibs. @ Tk. 27.89 Per Ib. = Tk. 1,319.20
(c) Local carriage, welding & other necessary cost L.S. = Tk. 367.50
Total = Tk. 35,520.47
Profit 10.00% = Tk. 3,552.05
Overhead 3.50% = Tk. 1,243.22
= Tk. 40,315.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,346.42
Analysis of PWD SoR 2014 for Civil Works 544

Grand total = Tk. 42,662.16


Rate per rm. = Tk. 6,993.80

Say, Tk. 6,994 .00 Per rm.

Item No.- 27.71.3.2


Supplying 100 mm dia 2.5 mm thick stainless steel bridge type strainer
Considering 6.1 meter
(a) 100 mm dia 2.5 mm thick stainless
steel bridge type strainer 6.1 meter @ Tk. 5,546.52 Per meter = Tk. 33,833.77
(b) 12 mm dia M.S. rod 47.30 Ibs. @ Tk. 27.89 Per Ib. = Tk. 1,319.20
(c) Local carriage, welding & other necessary cost L.S. = Tk. 367.50
Total = Tk. 35,520.47
Profit 10.00% = Tk. 3,552.05
Overhead 3.50% = Tk. 1,243.22
= Tk. 40,315.74
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,346.42
Grand total = Tk. 42,662.16
Rate per rm. = Tk. 6,993.80

Say, Tk. 6,994 .00 Per rm.

Item No.- 27.71.4


Supplying 100 mm x 200 mm dia 6 mm thick M.S. reducer.
Considering 1 No.
(a) 100 x 200 mm
dia M.S. reducer 1 No. @ Tk. 4,586.39 each = Tk. 4,586.39
(b) Carriage of materials L.S. = Tk. 98.00
Total = Tk. 4,684.39
Profit 10.00% = Tk. 468.44
Overhead 3.50% = Tk. 163.95
= Tk. 5,316.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 309.44
Grand total = Tk. 5,626.22
Rate each. = Tk. 5,626.22

Say, Tk. 5,626 .00 each.

Item No.- 27.71.5


Supplying 200 mm dia 6 mm thick M.S. housing pipe (Welded)
Considering 1 meter
(a) 200 mm dia 6 mm
thick M.S. housing pipe 1 meter @ Tk. 2,900.27 Per meter = Tk. 2,900.27
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 3,022.77
Profit 10.00% = Tk. 302.28
Overhead 3.50% = Tk. 105.80
= Tk. 3,430.85
Add VAT with adjustment factor 1.0582 5.50% = Tk. 199.68
Grand total = Tk. 3,630.53
Rate per rm. = Tk. 3,630.53

Say, Tk. 3,631 .00 Per rm.

Item No.- 27.71.6


Supplying 200 mm dia 6 mm thick M.S. housing pipe (Seamless)
Considering 1 meter
Analysis of PWD SoR 2014 for Civil Works 545

(a) 200 mm dia 6 mm


thick M.S. housing pipe 1 meter @ Tk. 3,200.93 Per meter = Tk. 3,200.93
(b) Carriage of materials L.S. = Tk. 122.50
Total = Tk. 3,323.43
Profit 10.00% = Tk. 332.34
Overhead 3.50% = Tk. 116.32
= Tk. 3,772.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 219.54
Grand total = Tk. 3,991.63
Rate per rm. = Tk. 3,991.63

Say, Tk. 3,992 .00 Per rm.

Item No.- 27.71.7


Supplying centralizer made with 12 mm dia M.S. rod of approved design
Considering 1 No.
(a) 1 set centralizer consists of four leaves:
10 mm dia M.S. rod
4 x 3'-0"=12'-0" 4.512 Ibs @ Tk. 27.89 Per meter = Tk. 125.84
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 49.00
Total = Tk. 174.84
Profit 10.00% = Tk. 17.48
Overhead 3.50% = Tk. 6.12
= Tk. 198.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 11.55
Grand total = Tk. 209.99
Rate each. = Tk. 209.99

Say, Tk. 210 .00 each.

Item No.- 27.71.8


Supplying 200 mm dia M.S. cap of 6 mm thick.
Considering 1 No.
(a) 200 mm dia 6 mm thick M.S. cap. 1 No. @ Tk. 1,400.80 each = Tk. 1,400.80
(b) Carriage, welding, fabrication and other necessary cost L.S. = Tk. 389.00
Total = Tk. 1,789.80
Profit 10.00% = Tk. 178.98
Overhead 3.50% = Tk. 62.64
= Tk. 2,031.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 118.23
Grand total = Tk. 2,149.65
Rate each. = Tk. 2,149.65

Say, Tk. 2,150 .00 each.


Analysis of PWD SoR 2014 for Civil Works 546

Item No.- 27.72


Complete installation of tube well fixtures
Considering 107 meter of 1 No. tube-well:
(a) Filling the pit with slurry in/c preparation of slurry L.S. = Tk. 1,633.33
(b) Lowering the bail plug, strainer, 50 mm dia G.I. pipe and
150 mm dia M.S. housing
pipe in/c coverage of risk 107 meter @ Tk. 98.00 Per meter = Tk. 10,486.00
(c) Verticality test 2 times @ Tk. 1,470.00 Per time = Tk. 2,940.00
(d) Necessary welding, cutting, jointing, levelling in/c cost of
electrodes, welding set, electricity connection fees, tools and plants etc. L.S. = Tk. 8,085.00
(e) Cost for filling the pea-gravels 28 cum. @ Tk. 43.24 Per cum = Tk. 1,210.72
(f) Final anchoring the tubewell in/c supply of joint,
concrete, brick work etc. L.S. = Tk. 9,800.00
Total = Tk. 34,155.05
Profit 10.00% = Tk. 3,415.51
Overhead 3.50% = Tk. 1,195.43
= Tk. 38,765.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,256.22
Grand total = Tk. 41,022.21
Rate per rm. = Tk. 383.39

Say, Tk. 383 .00 Per rm.


Item No.- 27.73
Complete development of the tube well by air compressor and pump of suitable capacity by alternate
surging and pumping untill satisfactory yield, sand free water and the turbidity conditions is reached.
27.73.1 Development of tube well for depth up to 200 m. L.S. = Tk. 29,243.18
Profit 10.00% = Tk. 2,924.32
Overhead 3.50% = Tk. 1,023.51
= Tk. 33,191.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,931.75
Total = Tk. 35,122.76
Say, Tk. 35,123 .00 each

27.73.2 Development of tube well for the depth beyond 200 m: = Tk. 39,805.79
Say, Tk. 39,806 .00 each
Item No.- 27.74
Long term pumping test of the well by required capacity pump including drawdown and recovery
test etc. complete
Considering 72 hrs.
1. Hire charge of pump in/c
spare and maintenance 72 hrs @ Tk. 359.75 Per hour = Tk. 25,902.00
2. Fuel for pump:
@ 4.375 liter per hour 270 liter @ Tk. 83.81 Per liter = Tk. 22,628.70
3. Foreman: @ 1 No. per 8 hrs 9 Nos. @ Tk. 567.00 each = Tk. 5,103.00
4. Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
5. Local carriage, T & P L.S. = Tk. 857.50
Total = Tk. 56,309.20
Profit 10.00% = Tk. 5,630.92
Overhead 3.50% = Tk. 1,970.82
= Tk. 63,910.94
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,719.68
Grand total = Tk. 67,630.62
Rate per hour = Tk. 939.31

Say, Tk. 939 .00 Per hour.

Item No.- 27.75


Analysis of PWD SoR 2014 for Civil Works 547

Disinfection of the tube well


Cost for disinfection of the tube well including supply of all the
materials and other necessary cost as per specification L.S. = Tk. 1,314.93
Profit 10.00% = Tk. 131.49
Overhead 3.50% = Tk. 46.02
= Tk. 1,492.44
Add VAT with adjustment factor 1.0582 5.50% = Tk. 86.86
Grand total = Tk. 1,579.30

Say, Tk. 1,579 .00 each

Item No.- 27.76


Filling the bore hole around the well from top to the shrouding to G.L. as per specification
Considering 100 meter
(a) Foreman 1 No. @ Tk. 567.00 each = Tk. 567.00
(b) Skilled labour 6 Nos. @ Tk. 303.00 each = Tk. 1,818.00
(c) Local carriage, T & P L.S. = Tk. 306.25
Total = Tk. 2,691.25
Profit 10.00% = Tk. 269.13
Overhead 3.50% = Tk. 94.19
= Tk. 3,054.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 177.78
Grand total = Tk. 3,232.35
Rate per rm. = Tk. 32.32

Say, Tk. 32 .00 Per rm.

ANALYSIS FOR INSTALLATION OF 40 MM DIA uP.V.C. HAND TUBE WEL

Item No.- 27.77.1


Supplying, fitting & fixing 40 mm dia "D" uPVC pipe having wall thickness 2.5 mm to 3.00 mm
including sinking
Up to 60 m depth
Considering 1 rft.
(a) 40 mm dia uPVC pipe 1 rft. @ Tk. 32.57 Per rft. = Tk. 14.00
(b) Labour for sinking and other costs L.S. = Tk. 24.50
Total = Tk. 38.50
Profit 10.00% = Tk. 3.85
Overhead 3.50% = Tk. 1.35
= Tk. 43.70
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2.54
Grand total = Tk. 46.24
Rate per rm. = Tk. 151.71

Say, Tk. 152 .00 Per rm.

Item No.- 27.77.2


Beyond 60 m depth
Considering 1 rft.
(i) Cost of 40 mm dia uPVC pipe 1 rft. @ Tk. 32.57 Per rft. = Tk. 32.57
(ii) Labour cost for sinking and other costs L.S. = Tk. 36.75
Total = Tk. 69.32
Profit 10.00% = Tk. 6.93
Overhead 3.50% = Tk. 2.43
= Tk. 78.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4.58
Grand total = Tk. 83.26
Analysis of PWD SoR 2014 for Civil Works 548

Rate per rm. = Tk. 273.18

Say, Tk. 273 .00 Per rm.


Item No.- 27.78
Supplying and sinking Five Star / equivalent brand PVC strainer 3 m long
Considering 3 m long 1 No. strainer
(a) Cost of 40 mm dia strainer 1 No. @ Tk.263.00 each = Tk. 160.00
(b) Labour cost for sinking
and other costs 10 rft @ Tk.24.50 Per rft. = Tk. 245.00
Total = Tk. 405.00
Profit 10.00% = Tk. 40.50
Overhead 3.50% = Tk. 14.18
= Tk. 459.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 26.75
Grand total = Tk. 486.43
Rate each. = Tk. 486.43

Say, Tk. 486 .00 each.


Item No.- 27.79
Supplying, fitting and fixing No. 6 Pump with 2'-0" long G.I. pipe
Considering 1 No. pump 1 No.
(a) Pump in/c necessary fittings 1 No. @ Tk. 2,277.00 each = Tk. 2,277.00
(b) 40 mm dia G.I. pipe 2 rft @ Tk. 169.31 Per rft. = Tk. 338.62
Total = Tk. 775.00
Profit 10.00% = Tk. 77.50
Overhead 3.50% = Tk. 27.13
= Tk. 879.63
Add VAT with adjustment factor 1.0582 5.50% = Tk. 51.20
Grand total = Tk. 930.83
Rate each. = Tk. 930.83

Say, Tk. 931 .00 each.


Item No.- 27.80
Construction of Platform
Considering 1.40 m x 1.00 m size platform and 1 m long drain
1. Cost for making platform
(a) Earth cutting 0.67 cum @ Tk. 80.22 Per cum = Tk. 53.75
(b) Sand filling 0.26 cum @ Tk. 501.28 Per cum = Tk. 130.33
(c) Brick work (1:6) 0.29 cum. @ Tk. 4,434.74 Per cum = Tk. 1,286.07
(d) C.C. (1:2:4) 0.24 cum @ Tk. 6,228.51 Per cum = Tk. 1,494.84
(e) 12 mm plaster (1:4) in/c n.c.f. 2.00 sqm. @ Tk. 205.16 Per sqm. = Tk. 410.32
2. Cost for making drain
(a) Earth cutting 0.06 cum @ Tk. 80.22 Per cum = Tk. 4.81
(b) Brick work (1:6) 0.06 cum @ Tk. 4,434.74 Per cum = Tk. 266.08
(c) 12 mm plaster (1:4) in/c n.c.f. 0.7 sqm @ Tk. 205.16 Per sqm. = Tk. 143.61
Total = Tk. 3,789.81
Profit 10.00% = Tk. 378.98
Overhead 3.50% = Tk. 132.64
= Tk. 4,301.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 250.35
Grand total = Tk. 4,551.78
Rate each. = Tk. 4,551.78

Say, Tk. 4,552 .00 each.


ANALYSIS FOR DEEP SET HAND OPERATED TUBE WELL

Item No.- 27.81.1


Analysis of PWD SoR 2014 for Civil Works 549

Supplying and sinking of 50 mm dia water grade uPVC pipe having wall thickness 2.5 mm to 3.00 mm
for tube well including fitting fixing.
Considering 1 rft.
(a) 50 mm dia uPVC pipe 1 rft. @ Tk. 78.32 Per rft. = Tk. 78.32
(b) Labour for sinking and other costs L.S. = Tk. 24.50
Total = Tk. 102.82
Profit 10.00% = Tk. 10.28
Overhead 3.50% = Tk. 3.60
= Tk. 116.70
Add VAT with adjustment factor 1.0582 5.50% = Tk. 6.79
Grand total = Tk. 123.49
Rate per rm. = Tk. 405.17

Say, Tk. 405 .00 Per rm.

Item No.- 27.81.2


Supplying and sinking of 40 mm dia water grade uPVC pipe having wall thickness 2.5 mm to 3.00 mm
for tube well including fitting, fixing
Considering 1 rft.
(a) 40 mm dia uPVC pipe 1 rft. @ Tk. 32.57 Per rft. = Tk. 32.57
(b) Labour for sinking and other costs L.S. = Tk. 24.50
Total = Tk. 57.07
Profit 10.00% = Tk. 5.71
Overhead 3.50% = Tk. 2.00
= Tk. 64.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3.77
Grand total = Tk. 68.55
Rate per rm. = Tk. 224.91

Say, Tk. 225 .00 Per rm.

Item No.- 27.81.3


Supplying and sinking 3 m long uPVC strainer
Considering 3 m long 1 No. strainer
(a) 40 mm dia strainer 1 No. @ Tk.263.00 each = Tk. 263.00
(b) Labour cost for sinking
and other costs 10 rft @ Tk.24.50 Per rft. = Tk. 100.00
Total = Tk. 363.00
Profit 10.00% = Tk. 36.30
Overhead 3.50% = Tk. 12.71
= Tk. 412.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 23.98
Grand total = Tk. 435.99
Rate each. = Tk. 435.99

Say, Tk. 436 .00 each.

Item No.- 27.82


Supplying, fitting and fixing of deep set (Hand) tube well pump with all necessary fittings.
Considering 1 No. pump
A. Materials:
(a) No. 6 pump with nut and bolts 1 No. @ Tk. 2,277.00 each = Tk. 2,277.00
(b) 50 mm dia G.I. pipe 2 rft @ Tk. 197.33 Per rft. = Tk. 394.66
(c) 50 x 40 mm socket (reducer) 1 No. @ Tk. 62.86 each = Tk. 62.86
(d) 4'-0" long cylinder 1 No. @ Tk. 168.05 each = Tk. 168.05
(e) 40 mm dia nipple 1 No. @ Tk. 99.69 each = Tk. 99.69
(f) 3/8" dia M.S. rod 18.81 Ibs. @ Tk. 27.89 Per lb = Tk. 524.61
Analysis of PWD SoR 2014 for Civil Works 550

(g) Tie foot ball 1 No. @ Tk. 30.00 each = Tk. 30.00
(h) Tie planger 1 pair @ Tk. 59.84 Per pair = Tk. 59.84
((i) 3/8" dia socket 3 No. @ Tk. 15.33 each = Tk. 45.99
(j) 3/8" dia nut 4 No. @ Tk. 14.00 each = Tk. 56.00
(k) Solution (big size) 1 No. @ Tk. 283.00 each = Tk. 283.00
(l) Tape 2 No. @ Tk. 22.00 each = Tk. 44.00
Sub total (A) = Tk. 4,045.70
(B) Workshop charge for cutting M.S. rod in suitable
size threaded and necessary welding L.S = Tk. 490.00
(C) Labour cost
(a) Plumber 1 No. @ Tk. 440.00 each = Tk. 440.00
(b) Skilled labour 1 No. @ Tk. 303.00 each = Tk. 303.00
Sub total (C) = Tk. 300.00
Total (A+B+C) = Tk. 4,835.70
Profit 10.00% = Tk. 483.57
Overhead 3.50% = Tk. 169.25
= Tk. 5,488.52
Add VAT with adjustment factor 1.0582 5.50% = Tk. 319.44
Grand total = Tk. 5,807.96
Rate each. = Tk. 5,807.96

Say, Tk. 5,808 .00 each.


Analysis of PWD SoR 2014 for Civil Works 551

DIVISION 28 : GAS CONNECTION WORKS


PART-A (LOW PRESSURE LINE)
Item No.- 28.1.1
Installation of 50 PSI API 5L, Grade-B ERW M.S. Pipe line for supplying
Titas Gas. 75 mm ND (88.90 mm O.D) M.S. pipe.
Considering 100 rft. of pipe line
(a) Materials:
(i) Cost of pipe 100 rft. @ Tk. 272.12 Per rft = Tk. 27,212.00
(ii) Cost of tape: 4" x 400'-0" 1.0 Roll @ Tk. 5,323.13 Per roll = Tk. 5,323.13
(iii) Cost of primer 1.136 liter @ Tk. 267.33 Per liter = Tk. 303.69
(b) Labour:
(i) Cutting trenches
100'-0" x 1'-6" x 3'-0"= 450.00 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,022.21
(ii) Laying and back-filling in/c levelling the top
surface with excavated earth 100 rft. @ Tk. 11.39 Per rft. = Tk. 1,139.00
(iii) Skilled labour for applying primer, wrapping the
pipe with tap in/c scrapping 100 rft. @ Tk. 7.58 Per rft. = Tk. 758.00
(iv) Carrying from Titas Gas store to work side in/c loading & unloading L.S. = Tk. 367.50
Total = Tk. 36,125.53
Incidental charges 10.00% = Tk. 3,612.55
Profit 10.00% = Tk. 3,612.55
Overhead 3.50% = Tk. 126.44
= Tk. 43,477.07
Add VAT with adjustment factor 1.0582 5.50% = Tk. 2,530.41
Grand total = Tk. 46,007.48
Rate per rft. = Tk. 460.07
Rate per rm = Tk. 1,509.49

Say, Tk. 1,509 .00 Per rm.


Item No.- 28.1.2
Installation of 50 PSI API 5L, Grade-B ERW M.S. Pipe line for supplying
Titas Gas. 50 mm ND (60.30 mm O.D) M.S. pipe.
Considering 100 rft. of pipe line
(a) Materials:
(i) Cost of pipe 100 rft. @ Tk. 163.28 Per rft = Tk. 16,328.00
(ii) Cost of tape: 2" x 200'-0" 3.0 Roll @ Tk. 1,145.93 Per roll = Tk. 3,437.79
(iii) Cost of primer 0.757 liter @ Tk. 267.33 Per liter = Tk. 202.37
(b) Labour:
(i) Cutting trenches:
100'-0" x 1'-6" x 3'-0"= 450.00 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,022.21
(ii) Laying and back-filling in/c levelling the top
surface with excavated earth 100 rft. @ Tk. 11.39 Per rft. = Tk. 1,139.00
(iii) Skilled labour for applying primer, wrapping the
pipe with tap in/c scrapping 100 rft. @ Tk. 7.58 Per rft. = Tk. 758.00
(iv) Carrying from Titas Gas store to work side in/c loading & unloading L.S. = Tk. 367.50
Total = Tk. 23,254.87
Incidental charges 10.00% = Tk. 2,325.49
Profit 10.00% = Tk. 2,325.49
Overhead 3.50% = Tk. 81.39
= Tk. 27,987.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,628.89
Grand total = Tk. 29,616.13
Rate per rft. = Tk. 296.16
Rate per rm = Tk. 971.70
Say, Tk. 972 .00 Per rm.
Item No.- 28.1.3
Analysis of PWD SoR 2014 for Civil Works 552

Installation of 50 PSI API 5L, Grade-B ERW M.S. Pipe line for supplying
Titas Gas 25 mm ND (33.40 mm O.D) M.S. pipe.
Considering 100 rft. of pipe line
(a) Materials:
(i) Cost of pipe 100 rft. @ Tk. 122.37 Per rft = Tk. 12,237.00
(ii) Cost of tape: 2" x 200'-0" 1.5 Roll @ Tk. 1,145.93 Per roll = Tk. 1,718.90
(iii) Cost of primer 0.65 liter @ Tk. 267.33 Per liter = Tk. 173.76
(b) Labour:
(i) Cutting trenches:
100'-0" x 1'-6" x 3'-0"= 450.00 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,022.21
(ii) Laying and back-filling in/c levelling the top
surface with excavated earth 100 rft. @ Tk. 11.39 Per rft. = Tk. 1,139.00
(iii) Skilled labour for applying primer, wrapping the
pipe with tap in/c scrapping 100 rft. @ Tk. 7.58 Per rft. = Tk. 758.00
(iv) Carrying from Titas Gas store to work side in/c loading & unloading L.S. = Tk. 367.50
Total = Tk. 17,416.37
Incidental charges 10.00% = Tk. 1,741.64
Profit 10.00% = Tk. 1,741.64
Overhead 3.50% = Tk. 60.96
= Tk. 20,960.61
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,219.93
Grand total = Tk. 22,180.54
Rate per rft. = Tk. 221.81
Rate per rm = Tk. 727.76

Say, Tk. 728 .00 Per rm.

Item No.- 28.1.4


Installation of 50 PSI API 5L, Grade-B ERW M.S. Pipe line for supplying
Titas Gas 20 mm ND (26.7 mm O.D) M.S. pipe.
Considering 100 rft. of pipe line
(a) Materials:
(i) Cost of pipe 100 rft. @ Tk. 51.30 Per rft = Tk. 5,130.00
(ii) Cost of tape: 2" x 200'-0" 1.25 Roll @ Tk. 1,145.93 Per roll = Tk. 1,432.41
(iii) Cost of primer 0.57 liter @ Tk. 267.33 Per liter = Tk. 152.38
(b) Labour:
(i) Cutting trenches:
100'-0" x 1'-6" x 3'-0"= 450.00 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 1,022.21
(ii) Laying and back-filling in/c levelling the top
surface with excavated earth 100 rft. @ Tk. 11.39 Per rft. = Tk. 1,139.00
(iii) Skilled labour for applying primer, wrapping the pipe
with tap in/c scrapping 100 rft. @ Tk. 7.58 Per rft. = Tk. 758.00
(iv) Carrying from Titas Gas store to work side in/c loading & unloading L.S. = Tk. 367.50
Total = Tk. 10,001.50
Incidental charges 10.00% = Tk. 1,000.15
Profit 10.00% = Tk. 1,000.15
Overhead 3.50% = Tk. 35.01
= Tk. 12,036.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 700.55
Grand total = Tk. 12,737.36
Rate per rft. = Tk. 127.37
Rate per rm = Tk. 417.90

Say, Tk. 418 .00 Per rm.

Item No.- 28.2


Sand filling the trench with sand of F.M. 0.8
Analysis of PWD SoR 2014 for Civil Works 553

Considering: 100'-0" x 1'-6" x 1'-0"= 150 cft.


(a) Sand in/c 30% for compaction 195 cft. @ Tk. 900.00 Per % cft. = Tk. 1,755.00
(b) Labour for watering, levelling
& compaction etc. 1.00 No. @ Tk. 245.00 each = Tk. 245.00
(c) Local carriage & sundries L.S. = Tk. 147.00
Total = Tk. 2,147.00
Incidental charges 10.00% = Tk. 214.70
Profit 10.00% = Tk. 214.70
Overhead 3.50% = Tk. 7.51
= Tk. 2,583.91
Add VAT with adjustment factor 1.0582 5.50% = Tk. 150.39
Grand total = Tk. 2,734.30
Rate per cft.. = Tk. 18.23
Rate per cum = Tk. 643.79

Say, Tk. 644 .00 Per cum.

Item No.- 28.3.1


Providing Butt welding joint to M.S. pipe: 75 mm ND (88.90 mm O.D.)
(a) Cost of welding as per Titas gas rate L.S. = Tk. 130.22
Incidental charges 10.00% = Tk. 13.02
Profit 10.00% = Tk. 13.02
Overhead 3.50% = Tk. 0.46
= Tk. 156.72
Add VAT with adjustment factor 1.0582 5.50% = Tk. 9.12
Total = Tk. 165.84

Say, Tk. 166 .00 Per joint.

Item No.- 28.3.2


Providing Butt welding joint to M.S. pipe: 50 mm ND (60.30 mm O.D.)
(a) Cost of welding as per Titas Gas rate L.S. = Tk. 110.66
Incidental charges 10.00% = Tk. 11.07
Profit 10.00% = Tk. 11.07
Overhead 3.50% = Tk. 0.39
= Tk. 133.19
Add VAT with adjustment factor 1.0582 5.50% = Tk. 7.75
Total = Tk. 140.94

Say, Tk. 141 .00 Per joint.

Item No.- 28.3.3


Providing Butt welding joint to M.S. pipe: 25 mm ND (33.40 mm O.D.)
(a) Cost of welding as per Titas Gas rate L.S. = Tk. 86.72
Incidental charges 10.00% = Tk. 8.67
Profit 10.00% = Tk. 8.67
Overhead 3.50% = Tk. 0.30
= Tk. 104.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 6.07
Total = Tk. 110.43

Say, Tk. 110 .00 Per joint.


Analysis of PWD SoR 2014 for Civil Works 554

Item No.- 28.3.4


Providing Butt welding joint to M.S. pipe: 20 mm ND (26.70 mm O.D.)
(a) Cost of welding as per Titas Gas rate L.S. = Tk. 74.19
Incidental charges 10.00% = Tk. 7.42
Profit 10.00% = Tk. 7.42
Overhead 3.50% = Tk. 0.26
= Tk. 89.29
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5.20
Total = Tk. 94.49

Say, Tk. 94 .00 Per joint.

Item No.- 28.4.1


Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 x 50 x 50 mm N.D. Tee CD 40
Considering 1 No. Tee
(a) Equal Tee (as per Titas Gas rate) = Tk. 201.35
(b) Carrying charge L.S. = Tk. 5.00
Total = Tk. 206.35
Incidental charges 10.00% = Tk. 20.64
Profit 10.00% = Tk. 20.64
Overhead 3.50% = Tk. 0.72
= Tk. 248.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 14.45
Grand total = Tk. 262.80

Say, Tk. 263 .00 each

Item No.- 28.4.2


Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 x 50 x 25 mm N.D. Tee CD 40
Considering 1 No. Tee
(a) Reducing Tee (as per Titas Gas rate) = Tk. 224.61
(b) Carrying charge L.S. = Tk. 5.00
Total = Tk. 229.61
Incidental charges 10.00% = Tk. 22.96
Profit 10.00% = Tk. 22.96
Overhead 3.50% = Tk. 0.80
= Tk. 276.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 16.08
Grand total = Tk. 292.41

Say, Tk. 292 .00 each

Item No.- 28.4.3


Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 25 x 25 x 25 mm N.D. Tee CD 40
Considering 1 No. Tee
(a) Equal Tee (as per Titas Gas rate) = Tk. 127.62
(b) Carrying charge L.S. = Tk. 12.25
Total = Tk. 139.87
Incidental charges 10.00% = Tk. 13.99
Profit 10.00% = Tk. 13.99
Overhead 3.50% = Tk. 0.49
= Tk. 168.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 9.80
Grand total = Tk. 178.14

Say, Tk. 178 .00 each


Item No.- 28.4.4
Analysis of PWD SoR 2014 for Civil Works 555

Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 mm x 90o mm Elbow
Considering 1 No. elbow
(a) Elbow (as per Titas Gas rate) = Tk. 164.93
(b) Carrying charge L.S. = Tk. 12.25
Total = Tk. 177.18
Incidental charges 10.00% = Tk. 17.72
Profit 10.00% = Tk. 17.72
Overhead 3.50% = Tk. 0.62
= Tk. 213.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12.41
Grand total = Tk. 225.65

Say, Tk. 226 .00 each

Item No.- 28.4.5


Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 25 mm x 90o mm Elbow
Considering 1 No. elbow
(a) Elbow (as per Titas Gas rate) = Tk. 47.84
(b) Carrying charge L.S. = Tk. 12.25
Total = Tk. 60.09
Incidental charges 10.00% = Tk. 6.01
Profit 10.00% = Tk. 6.01
Overhead 3.50% = Tk. 0.21
= Tk. 72.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 4.21
Grand total = Tk. 76.53

Say, Tk. 77 .00 each


Item No.- 28.4.6
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 mm x 45o mm Elbow
Considering 1 No. elbow
(a) Elbow (as per Titas Gas rate) = Tk. 71.12
(b) Carrying charge L.S. = Tk. 12.25
Total = Tk. 83.37
Incidental charges 10.00% = Tk. 8.34
Profit 10.00% = Tk. 8.34
Overhead 3.50% = Tk. 0.29
= Tk. 100.34
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5.84
Grand total = Tk. 106.18

Say, Tk. 106 .00 each


Item No.- 28.4.7
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 x 25 mm Reducer CD 40
Considering 1 No. reducer
(a) Reducer (as per Titas Gas rate) = Tk. 78.86
(b) Carrying charge L.S. = Tk. 12.25
Total = Tk. 91.11
Incidental charges 10.00% = Tk. 9.11
Profit 10.00% = Tk. 9.11
Overhead 3.50% = Tk. 0.32
= Tk. 109.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 6.38
Grand total = Tk. 116.03
Say, Tk. 116 .00 each
Item No.- 28.4.8
Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 20 mm Plug/Socket
Analysis of PWD SoR 2014 for Civil Works 556

Considering 1 No. plug/socket


(a) Plug/socket (as per Titas Gas rate) = Tk. 197.96
(b) Carrying charge L.S. = Tk. 12.25
Total = Tk. 210.21
Incidental charges 10.00% = Tk. 21.02
Profit 10.00% = Tk. 21.02
Overhead 3.50% = Tk. 0.74
= Tk. 252.99
Add VAT with adjustment factor 1.0582 5.50% = Tk. 14.72
Grand total = Tk. 267.71

Say, Tk. 268 .00 each

Item No.- 28.4.9


Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 x 20 mm Saddle
Considering 1 No. saddle
(a) Saddle (as per Titas Gas rate) = Tk. 173.19
(b) Carrying charge L.S. = Tk. 12.25
Total = Tk. 185.44
Incidental charges 10.00% = Tk. 18.54
Profit 10.00% = Tk. 18.54
Overhead 3.50% = Tk. 0.65
= Tk. 223.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12.99
Grand total = Tk. 236.16

Say, Tk. 236 .00 each

Item No.- 28.4.10


Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 50 mm dia End Cap CD 40
Considering 1 No. end cap
(a) End cap (as per Titas Gas rate) = Tk. 73.65
(b) Carrying charge L.S. = Tk. 12.25
Total = Tk. 85.90
Incidental charges 10.00% = Tk. 8.59
Profit 10.00% = Tk. 8.59
Overhead 3.50% = Tk. 0.30
= Tk. 103.38
Add VAT with adjustment factor 1.0582 5.50% = Tk. 6.02
Grand total = Tk. 109.40

Say, Tk. 109 .00 each

Item No.- 28.4.11


Supplying different sizes Tee, Elbow, Reducer, Plug, Socket: 25 mm dia End Cap CD 40
Considering 1 No. end cap
(a) End cap (as per Titas Gas rate) = Tk. 64.90
(b) Carrying charge L.S. = Tk. 12.25
Total = Tk. 77.15
Incidental charges 10.00% = Tk. 7.72
Profit 10.00% = Tk. 7.72
Overhead 3.50% = Tk. 0.27
= Tk. 92.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5.40
Grand total = Tk. 98.26
Analysis of PWD SoR 2014 for Civil Works 557

Say, Tk. 98 .00 each

Item No.- 28.5.1


Supplying different sizes Valve Tee, Service Tee: 50 x 50 x 50mm N.D. Tee
Considering 1 No. equal Tee
(a) Equal Tee (as per Titas Gas rate) = Tk. 14,079.19
(b) Carrying, welding & fitting-fixing L.S. = Tk. 1,960.00
Total = Tk. 16,039.19
Incidental charges 10.00% = Tk. 1,603.92
Profit 10.00% = Tk. 1,603.92
Overhead 3.50% = Tk. 56.14
= Tk. 19,303.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,123.46
Grand total = Tk. 20,426.63

Say, Tk. 20,427 .00 each

Item No.- 28.5.2


Supplying different sizes Valve Tee, Service Tee: 50 x 50 x 25 mm N.D.Tee CD 40
Considering 1 No. Tee
(a) Tee (as per Titas Gas rate) = Tk. 224.61
(b) Carrying, welding & fitting-fixing L.S. = Tk. 1,715.00
Total = Tk. 1,939.61
Incidental charges 10.00% = Tk. 193.96
Profit 10.00% = Tk. 193.96
Overhead 3.50% = Tk. 6.79
= Tk. 2,334.32
Add VAT with adjustment factor 1.0582 5.50% = Tk. 135.86
Grand total = Tk. 2,470.18

Say, Tk. 2,470 .00 each

Item No.- 28.5.3


Supplying different sizes Valve Tee, Service Tee: 25 x 25 x 25 mm Service Tee CD 40
Considering 1 No. Tee
(a) Service Tee (as per Titas Gas rate) = Tk. 1,503.33
(b) Carrying, welding & fitting-fixing L.S. = Tk. 1,225.00
Total = Tk. 2,728.33
Incidental charges 10.00% = Tk. 272.83
Profit 10.00% = Tk. 272.83
Overhead 3.50% = Tk. 9.55
= Tk. 3,283.54
Add VAT with adjustment factor 1.0582 5.50% = Tk. 191.11
Grand total = Tk. 3,474.65

Say, Tk. 3,475 .00 each

Item No.- 28.5.4


Supplying different sizes Valve Tee, Service Tee: 50 x 25 mm Service Tee CD 40
Considering 1 No. Tee
(a) Service Tee (as per Titas Gas rate) = Tk. 2,817.40
(b) Carrying, welding & fitting-fixing L.S. = Tk. 980.00
Total = Tk. 3,797.40
Incidental charges 10.00% = Tk. 379.74
Profit 10.00% = Tk. 379.74
Overhead 3.50% = Tk. 13.29
Analysis of PWD SoR 2014 for Civil Works 558

= Tk. 4,570.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 265.99
Grand total = Tk. 4,836.16

Say, Tk. 4,836 .00 each

Item No.- 28.6


Supplying & fitting-fixing in position different dia I/F all complete in all respect
as per specification of Titas Gas T & D Co. Ltd.
Considering 1 No.
(a) 50 mm dia insulation kits 1 No. @ Tk. 1,831.67 each = Tk. 1,831.67
(b) 50 mm flange W/N 150 R/F 2 Nos. @ Tk. 752.74 each = Tk. 1,505.48
(c) 5/8" x 3" long nut-bolt
with washer 4 Nos. @ Tk. 95.61 each = Tk. 382.44
(d) Carrying, welding & fitting-fixing L.S. = Tk. 1,470.00
Total = Tk. 5,189.59
Incidental charges 10.00% = Tk. 518.96
Profit 10.00% = Tk. 518.96
Overhead 3.50% = Tk. 18.16
= Tk. 6,245.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 363.50
Grand total = Tk. 6,609.17

Say, Tk. 6,609 .00 each


Item No.- 28.7
Construction of 5'-0" x 5'-0" x 5'-0" size O.D. standard size valve pit in/c providing standard M.S.
sheet cover as per drawing approved by Titas Gas T&D Co. Ltd. (3'-4" x 3'-4" x 4'-4.5" inside clear)
Considering 1 No.
(a) Materials:
(i) Valve pit as per Titas Gas
T&D Co. Ltd. design 1 No. @ Tk. 15,154.70 each = Tk. 15,154.70
(ii) M.S. sheet cover supplied by Titas
Gas T&D Co. Ltd. 1 No. @ Tk. 13,492.37 each = Tk. 13,492.37
(b) Masonry pit
(i) Earth cutting 405.00 cft. @ Tk. 2,271.58 Per % 0 cft. = Tk. 919.99
(ii) Brick flat soling 33.99 sft. @ Tk. 2,744.25 Per % sft. = Tk. 932.77
(iii) Plain concrete (1:3:6) 33.99 sft. @ Tk. 2,022.78 Per % sft. = Tk. 687.54
(iv) Brick-work (1:6) 62.26 cft. @ Tk. 12,557.68 Per % cft. = Tk. 7,818.41
(v) Plaster with n.c.f. 163.83 sft. @ Tk. 1,906.00 Per % sft. = Tk. 3,122.60
(vi) 38 mm patent stone flooring (1:2:4) 11.09 sft. @ Tk. 1,548.62 Per % sft. = Tk. 171.74
(vii) Sand filling (F.M. 0.8) 275.51 cft. @ Tk. 1,419.46 Per % cft. = Tk. 3,910.75
(viii) Fitting-fixing & carrying of pit-cover L.S. = Tk. 3,675.00
(c) Labour for loading-unloading L.S. = Tk. 245.00
Total = Tk. 50,130.87
Incidental charges 10.00% = Tk. 5,013.09
Profit 10.00% = Tk. 5,013.09
Overhead 3.50% = Tk. 175.46
= Tk. 60,332.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 3,511.41
Grand total = Tk. 63,843.92

Say, Tk. 63,844 .00 each


Item No.- 28.8
Testing and purging pipe line
Considering 1 meter
(a) Testing & purging as per Titas Gas rate = Tk. 18.97
Incidental charges 10.00% = Tk. 1.90
Analysis of PWD SoR 2014 for Civil Works 559

Profit 10.00% = Tk. 1.90


Overhead 3.50% = Tk. 0.07
= Tk. 22.84
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1.33
Total = Tk. 24.17

Say, Tk. 24 .00 Per rm

Item No.- 28.9.1


Supplying & fitting-fixing 50 mm N.D. ball valve class 150 RF 2" dia.
Considering 1 No.
(a) 50 mm ND dia ball
valve class 150 RF. 1 No. @ Tk. 7,000.40 each = Tk. 7,000.40
(b) 50 mm flange W/N 150 R.F. 2 Nos. @ Tk. 752.74 each = Tk. 1,505.48
(c) 50 mm dia gaskit 2 Nos. @ Tk. 242.85 each = Tk. 485.70
(d) 5/8" x 3" nut-bolt 8 Nos. @ Tk. 92.18 each = Tk. 737.44
(e) Labour for fitting-fixing, necessary welding in/c transportation L.S. = Tk. 2,450.00
Total = Tk. 12,179.02
Incidental charges 10.00% = Tk. 1,217.90
Profit 10.00% = Tk. 1,217.90
Overhead 3.50% = Tk. 42.63
= Tk. 14,657.45
Add VAT with adjustment factor 1.0582 5.50% = Tk. 853.08
Grand total = Tk. 15,510.53

Say, Tk. 15,511 .00 each

Item No.- 28.9.2


Supplying & fitting-fixing 25 mm N.D. ball valve Ball class 150 R.F. 1" dia.
Considering 1 No.
(a) 25 mm ND dia ball valve
class 150 R.F. 1 No. @ Tk. 4,540.80 each = Tk. 4,540.80
(b) 25 mm dia flange W/N 150 R.F. 2 Nos. @ Tk. 369.06 each = Tk. 738.12
(c) 25 mm dia gaskit (asbestos) 2 Nos. @ Tk. 39.67 each = Tk. 79.34
(d) 1/2" x 2.5" nut-bolt 8 Nos. @ Tk. 29.35 each = Tk. 234.80
(e) Labour for fitting-fixing, necessary welding in/c transportation L.S. = Tk. 2,450.00
Total = Tk. 8,043.06
Incidental charges 10.00% = Tk. 804.31
Profit 10.00% = Tk. 804.31
Overhead 3.50% = Tk. 28.15
= Tk. 9,679.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 563.38
Grand total = Tk. 10,243.21

Say, Tk. 10,243 .00 each

Item No.- 28.10


Cutting and permanent re-installment of pucca road (rigid & flexible)
28.10.1 Bitumenous road:
Considering 100 sft.
(I) Cutting & permanent re-installment of road L.S. = Tk. 4,201.75
Incidental charges 10.00% = Tk. 420.18
Profit 10.00% = Tk. 420.18
Overhead 3.50% = Tk. 14.71
= Tk. 5,056.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 294.31
Total = Tk. 5,351.13
Analysis of PWD SoR 2014 for Civil Works 560

Rate per sft. = Tk. 53.51


Rate per sqm. = Tk. 575.98

Say, Tk. 576 .00 Per sqm.

28.10.2 R.C.C. Road:


Considering 100 sft.
(i) Cutting & permanent re-installment of road L.S. = Tk. 6,284.25
Incidental charges 10.00% = Tk. 628.43
Profit 10.00% = Tk. 628.43
Overhead 3.50% = Tk. 22.00
= Tk. 7,563.11
Add VAT with adjustment factor 1.0582 5.50% = Tk. 440.18
Grand total = Tk. 8,003.29
Rate per sft. = Tk. 80.03
Rate per sqm. = Tk. 861.44

Say, Tk. 861 .00 Per sqm.

Part - B (Domestic & Commercial line)

Item No.- 28.11.1


Installation of commercial and domestic house line
3/4" dia G.I. pipe line
Considering 1 rft. of work
(a) G.I. pipe 1 rft. @ Tk. 60.80 Per rft. = Tk. 60.80
(b) Fittings L.S. = Tk. 9.27
(c) Labour: L.S. = Tk. 7.96
Total = Tk. 78.03
Incidental charges 10.00% = Tk. 7.80
Profit 10.00% = Tk. 7.80
Overhead 3.50% = Tk. 0.27
= Tk. 93.90
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5.47
Grand total = Tk. 99.37
Rate per rft. = Tk. 99.37
Rate per rm. = Tk. 326.03

Say, Tk. 326 .00 Per rm.

Item No.- 28.11.2


Installation of commercial and domestic house line
1/2" dia G.I. pipe line
Considering 1 rft. of work
(a) G.I. pipe 1 rft. @ Tk. 51.25 Per rft. = Tk. 51.25
(b) Fittings L.S. = Tk. 13.09
(c) Labour L.S. = Tk. 7.96
Total = Tk. 72.30
Incidental charges 10.00% = Tk. 7.23
Profit 10.00% = Tk. 7.23
Overhead 3.50% = Tk. 0.25
= Tk. 87.01
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5.06
Grand total = Tk. 92.07
Rate per rft. = Tk. 92.07
Rate per rm. = Tk. 302.08
Analysis of PWD SoR 2014 for Civil Works 561

Say, Tk. 302 .00 Per rm.

Item No.- 28.12.1


Supplying and fitting-fixing one way gas stop cock
12 x 6 mm dia one way gas stop cock
Considering 1 No.
(a) Heavy type gas stop cock 1 No. @ Tk. 167.83 each = Tk. 167.83
(b) Labour: L.S. = Tk. 12.25
Total = Tk. 180.08
Incidental charges 10.00% = Tk. 18.01
Profit 10.00% = Tk. 18.01
Overhead 3.50% = Tk. 0.63
= Tk. 216.73
Add VAT with adjustment factor 1.0582 5.50% = Tk. 12.61
Grand total = Tk. 229.34

Say, Tk. 229 .00 each

Item No.- 28.12.2


Supplying and fitting-fixing one way gas stop cock
20 x 20 mm dia one way gas stop cock
Considering 1 No.
(a) Heavy type gas stop cock 1 No. @ Tk. 268.31 each = Tk. 268.31
(b) Labour L.S. = Tk. 19.60
Total = Tk. 287.91
Incidental charges 10.00% = Tk. 28.79
Profit 10.00% = Tk. 28.79
Overhead 3.50% = Tk. 1.01
= Tk. 346.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 20.17
Grand total = Tk. 366.67

Say, Tk. 367 .00 each

Item No.- 28.13


Testing and purging the house line properly as per specification of the Titas Gas T&D Co. Ltd.
Considering 1 meter of work
(a) Testing & purging the house line L.S. = Tk. 12.25
Incidental charges 10.00% = Tk. 1.23
Profit 10.00% = Tk. 1.23
Overhead 3.50% = Tk. 0.04
= Tk. 14.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 0.86
Total = Tk. 15.61
Rate per rm. = Tk. 15.61

Say, Tk. 16 .00 Per rm..

DIVISION 29 : TERMITE TREATMENT WORKS


Item No.- 29.1
Spraying Anti-termite chemical mixed water on the sides & bottom of foundation
trench and over plinth filling
Considering 100 sqm. of work
(1 liter DURS BAN 20EC to be mixed with 19 liters of pure water)
to be sprayed @ 5 liters solution per sqm of soil
Analysis of PWD SoR 2014 for Civil Works 562

(a) DURS BAN 20EC 25 liter @ Tk. 654.73 Per liter = Tk. 16,368.25
(b) Labour 1.50 Nos. @ Tk. 245.00 each = Tk. 367.50
(c) Skilled technician 0.25 No. @ Tk. 700.00 each = Tk. 175.00
(d) T & P and hand spray L.S. = Tk. 7.45
(e) Local carriage L.S. = Tk. 39.20
Total = Tk. 16,957.40
Profit 10.00% = Tk. 1,695.74
Overhead 3.50% = Tk. 593.51
= Tk. 19,246.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,120.17
Grand total = Tk. 20,366.82
Rate per sqm. = Tk. 203.67

Say, Tk. 204 .00 Per sqm.

Item No.- 29.2


Extra cost for using anti-termite chemicals in brick-works (6:1) in foundation
Considering 100 cft. of work
For 4 bags of cement mixing = 100 liters of solution.Chemical required = 5.00 liters
(a) DURS BAN 20EC 5 liter @ Tk. 654.73 Per liter = Tk. 3,273.65
(b) Skilled labour 0.50 No. @ Tk. 303.00 each = Tk. 151.50
(c) Skilled technician 0.125 Nos. @ Tk. 700.00 each = Tk. 87.50
(d) T & P, sundries L.S. = Tk. 18.62
(e) Local carriage L.S. = Tk. 7.35
Total = Tk. 3,538.62
Profit 10.00% = Tk. 353.86
Overhead 3.50% = Tk. 123.85
= Tk. 4,016.33
Add VAT with adjustment factor 1.0582 5.50% = Tk. 233.75
Grand total = Tk. 4,250.08
Rate per cft.. = Tk. 42.50
Rate per cum. = Tk. 1,500.89

Say, Tk. 1,501 .00 Per cum.

Item No.- 29.3


Extra cost for anti-termite treatment of the back-fill in foundation trenches both outside and inside.
Considering 100 sqm. of work
(7.5 liters of emulsion mixture to be sprayed per sqm)
Chemical required = 37.5 liters
(a) DURS BAN 20EC 37.5 liter @ Tk. 654.73 Per liter = Tk. 24,552.38
(b) Skilled labour 2.00 Nos. @ Tk. 303.00 each = Tk. 606.00
(c) Skilled technician 0.25 No. @ Tk. 700.00 each = Tk. 175.00
(d) T & P, sundries & sprayer L.S. = Tk. 59.58
(e) Local carriage L.S. = Tk. 39.20
Total = Tk. 25,432.16
Profit 10.00% = Tk. 2,543.22
Overhead 3.50% = Tk. 890.13
= Tk. 28,865.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,680.00
Grand total = Tk. 30,545.51
Rate per sqm. = Tk. 305.46

Say, Tk. 305 .00 Per sqm.

Item No.- 29.4


Termite treatment in existing structures by making downwardly slanted holes at a depth of 9"
Analysis of PWD SoR 2014 for Civil Works 563

from the existing finished F.L./G.L. inside and outside the building and applying the
emulsion of anti-termite chemicals DURSBAN 20EC to be mixed with water
at 1:19 ratio into the holes @ 25 ml per hole in/c mending good the damages.
Considering 100 holes
(a) DURS BAN 20EC 1.25 liter @ Tk. 654.73 Per liter = Tk. 818.41
(b) Labour for cutting holes 100 holes @ Tk. 12.25 Per hole = Tk. 1,225.00
(c) C.C. (1:2:4):
100 x 1/2 x 1/2 x 9"= 1.56 cft. @ Tk. 176.37 Per cft. = Tk. 275.14
(d) Labour for preparing & applying
(i) Skilled labour 2.00 Nos. @ Tk. 303.00 each = Tk. 606.00
(ii) Skilled technician 0.25 No. @ Tk. 700.00 each = Tk. 175.00
(e) T & P, sundries, drilling machine & sprayer L.S. = Tk. 39.72
(f) Local carriage L.S. = Tk. 78.40
Total = Tk. 3,217.67
Profit 10.00% = Tk. 321.77
Overhead 3.50% = Tk. 112.62
= Tk. 3,652.06
Add VAT with adjustment factor 1.0582 5.50% = Tk. 212.55
Grand total = Tk. 3,864.61
Rate per hole. = Tk. 38.65

Say, Tk. 39 .00 Per hole.

Item No.- 29.5


Trench treatment for protecting against incoming termite by making trench around existing
buildings/strucures at a depth of 2'-6" from G.L. and applying anti-termite chemicals
DURSBAN 20EC solution mix with water, at the ratio 1:19 in three layers
in/c earth filling in the trench etc.
Considering 100 rft. of work
(5 liters of emulsified solution to be sprayed per sqm. in three layers, in 1'-6" width trench.)
(a) DURS BAN 20EC 5.25 liter @ Tk. 654.73 Per liter = Tk. 3,437.33
(b) E/ work in excv. trench
100'-0" x 1'-6" x 2'-6"= 375 cft. @ Tk. 2.27 Per cft. = Tk. 851.25
(c) Labour for preparing & applying solution
(i) Skilled labour 2.00 Nos. @ Tk. 303.00 each = Tk. 606.00
(ii) Skilled technician 0.25 No. @ Tk. 700.00 each = Tk. 175.00
(c) T & P, sundries, & sprayer L.S. = Tk. 19.60
(d) Local carriage L.S. = Tk. 39.20
Total = Tk. 5,128.38
Profit 10.00% = Tk. 512.84
Overhead 3.50% = Tk. 179.49
= Tk. 5,820.71
Add VAT with adjustment factor 1.0582 5.50% = Tk. 338.77
Grand total = Tk. 6,159.48
Rate per rft. = Tk. 61.59
Rate per rm. = Tk. 202.08
Say, Tk. 202 .00 Per rm.
Item No.- 29.6
Fumigation treatment against mosquitoes, flies, spiders, silverfish, cockroaches,
lizards and other harmful pests inside the buildings etc.
Considering 10' x 10' x 10'= 1000 cft. inside volume of room
(a) Hire charge of spray machine in/c transportation and mobilization etc. = Tk. 245.00
(b) NEOCIDOL-60 200 ml @ Tk. 125.90 Per % ml = Tk. 251.80
(c) Skilled labour 0.20 No. @ Tk. 303.00 each = Tk. 60.60
(d) Skilled technician 0.05 No. @ Tk. 700.00 each = Tk. 35.00
(e) Scaffolding, T&P and sundries etc. L.S. = Tk. 12.25
Total = Tk. 359.65
Analysis of PWD SoR 2014 for Civil Works 564

Profit 10.00% = Tk. 35.97


Overhead 3.50% = Tk. 12.59
= Tk. 408.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 23.76
Grand total = Tk. 431.97
Rate per cft.. = Tk. 0.43
Rate per cum. = Tk. 15.19

Say, Tk. 15 .00 Per cum.

Item No.- 29.7


Anti-termite treatment of all wooden door frames, windows, wood panelling etc. by using
DURSBAN 20EC emulsion at the ratio of 1:19 (DURSBAN 20EC and Kerosene).
Considering 100 sft. of work
(i) DURSBAN 20EC 0.5 liter @ Tk. 654.73 Per liter = Tk. 327.37
(ii) Kerosene 9.5 liter @ Tk. 68.00 Per liter = Tk. 646.00
(iii) Brush L.S. = Tk. 10.00
(iv) Painter 0.33 No. @ Tk. 423.00 each = Tk. 139.59
(v) Scaffolding, T&P and sundries, local carriage etc. L.S. = Tk. 24.50
Total = Tk. 1,147.46
Profit 10.00% = Tk. 114.75
Overhead 3.50% = Tk. 40.16
= Tk. 1,302.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 75.80
Grand total = Tk. 1,378.17
Rate per sft.. = Tk. 13.78
Rate per sqm = Tk. 148.33

Say, Tk. 148 .00 Per sqm.


Item No.- 29.8
Anti-termite treatment of electric and telephone system by inserting a plugging material
(cotton. foam etc.) with anti-termite chemical DURSBAN 20EC etc.
Considering 8 switch-board in/c wires & cable
(a) DURASBAN 20EC 0.8 liter @ Tk. 654.73 Per liter = Tk. 523.78
(b) Skilled labour 1.00 No. @ Tk. 303.00 each = Tk. 303.00
(c) Skilled technician 1.00 No. @ Tk. 700.00 each = Tk. 700.00
(d) Cost of plugging materials L.S. = Tk. 36.75
Total = Tk. 1,563.53
Profit 10.00% = Tk. 156.35
Overhead 3.50% = Tk. 54.72
= Tk. 1,774.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 103.28
Grand total = Tk. 1,877.88
Rate per switch-board = Tk. 234.74

Say, Tk. 235 .00 Per board


Item No.- 29.9
Destruction of termite nests
Considering 1 No. nest.
(a) Earth-work in excavation
1 x 1 m x 1.5 m x 1.5 m = 2.25 cum. @ Tk. 80.22 Per cum. = Tk. 180.50
(b) Cost of DURSBAN 20EC 1.10 liter @ Tk. 654.73 Per liter = Tk. 720.20
(c) Skilled Technician 0.25 No. @ Tk. 700.00 each = Tk. 175.00
(d) Skilled labour 0.5 No. @ Tk. 303.00 each = Tk. 151.50
Total = Tk. 1,227.20
Profit 10.00% = Tk. 122.72
Overhead 3.50% = Tk. 42.95
Analysis of PWD SoR 2014 for Civil Works 565

= Tk. 1,392.87
Add VAT with adjustment factor 1.0582 5.50% = Tk. 81.07
Grand total = Tk. 1,473.94
Rate each.. = Tk. 1,473.94

Say, Tk. 1,474 .00 each nest.

DIVISION 30 : CONCRETE HOLLOW BLOCK AND PAVING STONE


Item No.- 30.1
70 mm thick non-load bearing partition wall with concrete hollow block:
cement : lime : sand (1 : 1 : 6)
Consideration 100 sft. of work
(a) Material
(i) 70 mm block (390 x 70 x 190 mm)
in/c wastage 116 Nos. @ Tk. 21.23 Per block = Tk. 2,462.68
(ii) Cement 0.4 bag @ Tk. 440.00 Per bag = Tk. 176.00
(iii) Lime 11.25 kg. @ Tk. 19.00 Per kg. = Tk. 213.75
(iv) Sand (F.M. 1.2) 3.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 51.00
Analysis of PWD SoR 2014 for Civil Works 566

(v) Transportation of block 116 Nos. @ Tk. 3.18 each = Tk. 368.88
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary Labour 2.5 Nos. @ Tk. 245.00 each = Tk. 612.50
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc LS. = Tk. 122.50
Total = Tk. 4,625.61
Profit 10.00% = Tk. 462.56
Overhead 3.50% = Tk. 161.90
= Tk. 5,250.07
Add VAT with adjustment factor 1.0582 5.50% = Tk. 305.56
Grand total = Tk. 5,555.63
Rate per sft. = Tk. 55.56
30.1.1 Ground floor Rate per sqm. = Tk. 598.05

Say, Tk. 598 .00 Per sqm.

30.1.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft.) Per sqm = Tk. 24.82
30.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 33.10
30.1.4 Add for each addl floor for 10th floor and above (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 41.37

Item No.- 30.2


70 mm thick non-load bearing partition wall with concrete hollow block:
cement : sand (1 : 6) with mortar mix.
Consideration 100 sft. of work
(a) Material
(i) 70 mm block (390 x 70 x 190 mm)
in/c wastage 116 Nos. @ Tk. 21.23 Per block = Tk. 2,462.68
(ii) Cement 0.5 bag @ Tk. 440.00 Per bag = Tk. 220.00
(iii) Mortar mix 0.015 liter @ Tk. 244.42 Per liter = Tk. 3.67
(iv) Sand (F.M. 1.2) 3.80 cft. @ Tk. 1,700.00 Per % cft. = Tk. 64.60
(v) Transportation of block 116 Nos. @ Tk. 3.18 each = Tk. 368.88
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary Labour 2.5 Nos. @ Tk. 245.00 each = Tk. 612.50
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc LS. = Tk. 122.50
Total = Tk. 4,473.13
Profit 10.00% = Tk. 447.31
Overhead 3.50% = Tk. 156.56
= Tk. 5,077.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 295.49
Grand total = Tk. 5,372.49
Rate per sft. = Tk. 53.72
30.2.1 Ground floor Rate per sqm. = Tk. 578.24

Say, Tk. 578 .00 Per sqm.

30.2.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft.) Per sqm = Tk. 24.82
30.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 33.10
30.2.4 Add for each addl floor for 10th floor and above (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 41.37

Item No.- 30.3


90 mm thick non-load bearing partition wall with concrete hollow block:
cement : lime : sand (1 : 1 : 6)
Analysis of PWD SoR 2014 for Civil Works 567

Consideration for 100 sft.


(a) Material
(i) 90 mm block (390 x 90 x 190 mm)
in/c wastage 116 Nos. @ Tk. 24.00 Per block = Tk. 2,784.00
(ii) Cement 0.5 bag @ Tk. 440.00 Per bag = Tk. 220.00
(iii) Lime 11.25 kg. @ Tk. 19.00 Per kg. = Tk. 213.75
(iv) Sand (F.M. 1.2) 3.80 cft. @ Tk. 1,700.00 Per % cft. = Tk. 64.60
(v) Transportation of block 116 Nos. @ Tk. 3.14 each = Tk. 364.24
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary Labour 2.75 Nos. @ Tk. 245.00 each = Tk. 673.75
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc LS. = Tk. 122.50
Total = Tk. 5,061.14
Profit 10.00% = Tk. 506.11
Overhead 3.50% = Tk. 177.14
= Tk. 5,744.39
Add VAT with adjustment factor 1.0582 5.50% = Tk. 334.33
Grand total = Tk. 6,078.72
Rate per sft. = Tk. 60.79
30.3.1 Ground floor Rate per sqm. = Tk. 654.34

Say, Tk. 654 .00 Per sqm.

30.3.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft.) Per sqm = Tk. 24.82
30.3.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 33.10
30.3.4 Add for each addl floor for 10th floor and above (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 41.37

Item No.- 30.4


90 mm thick non-load bearing partition wall with concrete hollow block:
cement : sand (1 : 6) with mortar mix.
Consideration 100 sft. of work
(a) Material
(i) 90 mm block (390 x 90 x 190 mm)
in/c wastage 116 Nos. @ Tk. 24.00 Per block = Tk. 2,784.00
(ii) Cement 0.6 bag @ Tk. 440.00 Per bag = Tk. 264.00
(iii) Mortar mix 0.018 liter @ Tk. 244.42 Per liter = Tk. 4.40
(iv) Sand (F.M. 1.2) 4.50 cft. @ Tk. 1,700.00 Per % cft. = Tk. 76.50
(v) Transportation of block 116 Nos. @ Tk. 3.14 each = Tk. 364.24
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary Labour 2.75 Nos. @ Tk. 245.00 each = Tk. 673.75
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc LS. = Tk. 122.50
Total = Tk. 4,907.69
Profit 10.00% = Tk. 490.77
Overhead 3.50% = Tk. 171.77
= Tk. 5,570.23
Add VAT with adjustment factor 1.0582 5.50% = Tk. 324.19
Grand total = Tk. 5,894.42
Rate per sft. = Tk. 58.94
30.4.1 Ground floor Rate per sqm. = Tk. 634.43

Say, Tk. 634 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 568

30.4.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft.) Per sqm = Tk. 24.82
30.4.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 33.10
30.4.4 Add for each addl floor for 10th floor and above (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 41.37

Item No.- 30.5


140 mm thick non-load bearing external wall with concrete hollow block:
cement : lime : sand (1 : 1 : 6)
Consideration 100 sft. of work
(a) Material
(i) 140 mm block (390 x 140 x 190 mm)
in/c wastage 116 Nos. @ Tk. 33.46 Per block = Tk. 3,881.36
(ii) Cement 0.7 bag @ Tk. 440.00 Per bag = Tk. 308.00
(iii) Lime 15 kg. @ Tk. 19.00 Per kg. = Tk. 285.00
(iv) Sand (F.M. 1.2) 4.40 cft. @ Tk. 1,700.00 Per % cft. = Tk. 74.80
(v) Transportation of block 116 Nos. @ Tk. 6.84 each = Tk. 793.44
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
(iii) Ordinary Labour 3.25 Nos. @ Tk. 245.00 each = Tk. 796.25
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc LS. = Tk. 122.50
Total = Tk. 7,074.15
Profit 10.00% = Tk. 707.42
Overhead 3.50% = Tk. 247.60
= Tk. 8,029.17
Add VAT with adjustment factor 1.0582 5.50% = Tk. 467.31
Grand total = Tk. 8,496.48
Rate per sft. = Tk. 84.96
30.5.1 Ground floor Rate per sqm. = Tk. 914.51

Say, Tk. 915 .00 Per sqm.

30.5.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft.) Per sqm = Tk. 33.10
30.5.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.5.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 49.65

Item No.- 30.6


140 mm thick non-load bearing external wall with concrete hollow block:
cement : sand (1 : 6) with mortar mix.
Consideration 100 sft. of work
(a) Material
(i) 140 mm block (390 x 140 x 190 mm)
in/c wastage 116 Nos. @ Tk. 33.46 Per block = Tk. 3,881.36
(ii) Cement 0.8 bag @ Tk. 440.00 Per bag = Tk. 352.00
(iii) Mortar mix 0.024 liter @ Tk. 244.42 Per liter = Tk. 5.87
(iv) Sand (F.M. 1.2) 6.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 102.00
(iv) Transportation of block 116 Nos. @ Tk. 6.84 each = Tk. 793.44
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
(iii) Ordinary Labour 3.25 Nos. @ Tk. 245.00 each = Tk. 796.25
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc. LS. = Tk. 122.50
Total = Tk. 6,866.22
Profit 10.00% = Tk. 686.62
Overhead 3.50% = Tk. 240.32
= Tk. 7,793.16
Analysis of PWD SoR 2014 for Civil Works 569

Add VAT with adjustment factor 1.0582 5.50% = Tk. 453.57


Grand total = Tk. 8,246.73
Rate per sft. = Tk. 82.47
30.6.1 Ground floor Rate per sqm. = Tk. 887.71

Say, Tk. 888 .00 Per sqm.

30.6.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft.) Per sqm = Tk. 33.10
30.6.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.6.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 49.65

Item No.- 30.7


140 mm thick load bearing wall with concrete hollow block:
cement : lime : sand (1 : 1 : 6)
Consideration 100 sft. of work
(a) Material
(i) 140 mm block (390 x 140 x 190 mm)
in/c wastage 116 Nos. @ Tk. 48.75 Per block = Tk. 5,655.00
(ii) Cement 0.7 bag @ Tk. 440.00 Per bag = Tk. 308.00
(iii) Lime 15 kg. @ Tk. 19.00 Per kg. = Tk. 285.00
(iv) Sand (F.M. 1.2) 4.40 cft. @ Tk. 1,700.00 Per % cft. = Tk. 74.80
(v) Transportation of block 116 Nos. @ Tk. 6.84 each = Tk. 793.44
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
(iii) Ordinary Labour 3.25 Nos. @ Tk. 245.00 each = Tk. 796.25
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc. LS. = Tk. 122.50
Total = Tk. 8,847.79
Profit 10.00% = Tk. 884.78
Overhead 3.50% = Tk. 309.67
= Tk. 10,042.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 584.47
Grand total = Tk. 10,626.71
Rate per sft. = Tk. 106.27
30.7.1 Ground floor Rate per sqm. = Tk. 1,143.89

Say, Tk. 1,144 .00 Per sqm.

30.7.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft.) Per sqm = Tk. 33.10
30.7.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.7.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 49.65

Item No.- 30.8


140 mm thick load bearing wall with concrete hollow block:
cement : sand (1 : 6) with mortar mix.
Consideration of 100 sft. of work
(a) Material
(i) 140 mm block (390 x 140 x 190 mm)
in/c wastage 116 Nos. @ Tk. 48.75 Per block = Tk. 5,655.00
(ii) Cement 0.8 bag @ Tk. 440.00 Per bag = Tk. 352.00
(iii) Mortar mix 0.024 liter @ Tk. 244.42 Per liter = Tk. 5.87
(iv) Sand (F.M. 1.2) 6.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 102.00
(v) Transportation of block 116 Nos. @ Tk. 6.84 each = Tk. 793.44
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
Analysis of PWD SoR 2014 for Civil Works 570

(iii) Ordinary Labour 3.25 Nos. @ Tk. 245.00 each = Tk. 796.25
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc. LS. = Tk. 122.50
Total = Tk. 8,639.86
Profit 10.00% = Tk. 863.99
Overhead 3.50% = Tk. 302.40
= Tk. 9,806.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 570.73
Grand total = Tk. 10,376.98
Rate per sft. = Tk. 103.77
30.8.1 Ground floor Rate per sqm. = Tk. 1,116.98

Say, Tk. 1,117 .00 Per sqm.

30.8.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft.) Per sqm = Tk. 33.10
30.8.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.8.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 49.65

Item No.- 30.9


190 mm thick load bearing wall with concrete hollow block:
cement : lime : sand (1 : 1 : 6)
Consideration of 100 sft. of work
(a) Material
(i) 190 mm block (390 x 190 x 190 mm)
in/c wastage 116 Nos. @ Tk. 59.61 Per block = Tk. 6,914.76
(ii) Cement 0.75 bag @ Tk. 440.00 Per bag = Tk. 330.00
(iii) Lime 15 kg. @ Tk. 19.00 Per kg. = Tk. 285.00
(iv) Sand (F.M. 1.2) 4.70 cft. @ Tk. 1,700.00 Per % cft. = Tk. 79.90
(v) Transportation of block 116 Nos. @ Tk. 6.84 each = Tk. 793.44
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
(iii) Ordinary Labour 3.5 Nos. @ Tk. 245.00 each = Tk. 857.50
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc. LS. = Tk. 122.50
Total = Tk. 10,195.90
Profit 10.00% = Tk. 1,019.59
Overhead 3.50% = Tk. 356.86
= Tk. 11,572.35
Add VAT with adjustment factor 1.0582 5.50% = Tk. 673.52
Grand total = Tk. 12,245.87
Rate per sft. = Tk. 122.46
30.9.1 Ground floor Rate per sqm. = Tk. 1,318.16

Say, Tk. 1,318 .00 Per sqm.

30.9.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.9.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % sft.) Per sqm = Tk. 49.65
30.9.4 Add for each addl floor for 10th floor and above (@ 1.75 Nos. lab. per % sft.) Per sqm = Tk. 57.92

Item No.- 30.10


190 mm thick load bearing wall with concrete hollow block:
cement : sand (1 : 6) with mortar mix.
Consideration of 100 sft. of work
(a) Material
(i) 190 mm block (390 x 190 x 190 mm)
in/c wastage 116 Nos. @ Tk. 59.61 Per block = Tk. 6,914.76
Analysis of PWD SoR 2014 for Civil Works 571

(ii) Cement 0.85 bag @ Tk. 440.00 Per bag = Tk. 374.00
(iii) Mortar mix 0.026 liter @ Tk. 244.42 Per liter = Tk. 6.35
(iv) Sand (F.M. 1.2) 7.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 119.00
(v) Transportation of block 116 Nos. @ Tk. 6.84 each = Tk. 793.44
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1.5 Nos. @ Tk. 389.00 each = Tk. 583.50
(iii) Ordinary Labour 3.5 Nos. @ Tk. 245.00 each = Tk. 857.50
(c) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(d) Local carriage, curing & sundries etc. LS. = Tk. 122.50
Total = Tk. 10,000.35
Profit 10.00% = Tk. 1,000.04
Overhead 3.50% = Tk. 350.01
= Tk. 11,350.40
Add VAT with adjustment factor 1.0582 5.50% = Tk. 660.60
Grand total = Tk. 12,011.00
30.10.1 Ground floor Rate per sft. = Tk. 120.11
Rate per sqm. = Tk. 1,292.86

Say, Tk. 1,293 .00 Per sqm.

30.10.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft.) Per sqm = Tk. 41.37
30.10.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % sft.) Per sqm = Tk. 49.65
30.10.4 Add for each addl floor for 10th floor and above (@ 1.75 Nos. lab. per % sft.) Per sqm = Tk. 57.92

Item No.- 30.11


Supplying, carrying and placing of 150 mm concrete ceiling block on perfectly leveled shutter
as per direction of the engineer-in-charge.
Consideration of 100 Nos.
(a) Material
(i) 150 mm ceiling block
(600 x 200 x 150 mm) 102 Nos. @ Tk. 56.41 Per block = Tk. 5,753.82
(ii) Transportation of block 102 Nos. @ Tk. 7.60 each = Tk. 775.20
(b) Ordinary Labour
(i) Lifting & placing on shutter 102 Nos. @ Tk. 6.13 each = Tk. 625.26
(ii) Local carriage, sundries etc. 102 Nos. @ Tk. 2.45 each = Tk. 249.90
Total = Tk. 7,404.18
Profit 10.00% = Tk. 740.42
Overhead 3.50% = Tk. 259.15
= Tk. 8,403.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 489.11
Grand total = Tk. 8,892.86
30.11.1 Ground floor Rate each. = Tk. 88.93

Say, Tk. 89 .00 each.

30.11.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % pc.) each = Tk. 3.08
30.11.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % pc.) each = Tk. 3.84
30.11.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % pcs.) each = Tk. 4.61

Item No.- 30.12


Supplying, carrying and placing of 200 mm concrete ceiling block on perfectly leveled shutter
as per direction of the engineer-in-charge.
Consideration of 100 Nos.
(a) Material
(i) 200 mm ceiling block
(600 m x 200 x 200 mm) 102 Nos. @ Tk. 81.75 Per block = Tk. 8,338.50
Analysis of PWD SoR 2014 for Civil Works 572

(ii) Transportation of block 102 Nos. @ Tk. 7.60 each = Tk. 775.20
(b) Ordinary Labour
(i) Lifting & placing on shutter 102 Nos. @ Tk. 6.13 each = Tk. 625.26
(ii) Local carriage, sundries etc. 102 Nos. @ Tk. 2.45 each = Tk. 249.90
Total = Tk. 9,988.86
Profit 10.00% = Tk. 998.89
Overhead 3.50% = Tk. 349.61
= Tk. 11,337.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 659.85
Grand total = Tk. 11,997.21
30.12.1 Ground floor Rate each. = Tk. 119.97
Say, Tk. 120 .00 each.

30.12.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % pc.) each = Tk. 3.84
30.12.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % pc.) each = Tk. 6.92
30.12.4 Add for each addl floor for 6th floor to 9th floor (@ 1.75 No. lab. per % pc.) each = Tk. 8.07

Item No.- 30.13


Minimum total 10 mm thick plaster (1:5) applied in two coats on outer surface of external
wall with specified external plaster mix.
Consideration of 100 sft. of work
(a) Material
(i) Cement 0.65 bag @ Tk. 440.00 Per bag = Tk. 286.00
(ii) Sand 4.1 cft. @ Tk. 1,700.00 Per % cft. = Tk. 69.70
(iii) External plaster mix 0.086 liter @ Tk. 249.19 Per liter = Tk. 21.43
(b) Labour for 2 coats
(i) Mason (1.5 x 1 No.) 1.5 No. @ Tk. 389.00 each = Tk. 583.50
(ii) Ordinary Labour 1.5 Nos. @ Tk. 245.00 each = Tk. 367.50
(c) Washing of sand, local carriage, scaffolding, curing & sundries etc. L.S. = Tk. 245.00
Total = Tk. 1,573.13
Profit 10.00% = Tk. 157.31
Overhead 3.50% = Tk. 55.06
= Tk. 1,785.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 103.92
Grand total = Tk. 1,889.42
Rate per sft. = Tk. 18.89
30.13.1 Ground floor Rate per sqm. = Tk. 203.33
Say, Tk. 203 .00 Per sqm.
30.13.2 Add for each addl. floor up to 5th floor (1/3 lab. per % sft.) Per sqm = Tk. 11.03
30.13.3 Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft.) Per sqm = Tk. 16.55
30.13.4 Add for each addl. floor above 9th floor (2/3 lab. per % sft.) Per sqm = Tk. 22.07

Item No.- 30.14.1


Supplying and placing 60 mm thick grey Uni-block for Walk Way on 50 mm stabilized sand base:
compressive strength 15N/mm2
Consideration of 100 sft. of work
(a) Material
(i) 60 mm grey uni-block
(222 x 110 x 60 mm) 388 Nos. @ Tk. 9.62 Per block = Tk. 3,732.56
(ii) Sand 30.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 510.00
(iii0 Transportation of block 388 Nos. @ Tk. 1.79 each = Tk. 694.52
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary Labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(c) Tools & machinery 100 sft. @ Tk. 2.45 Per sft. = Tk. 245.00
(d) Local carriage, storage & sundries etc. LS. = Tk. 73.50
Analysis of PWD SoR 2014 for Civil Works 573

Total = Tk. 6,183.88


Profit 10.00% = Tk. 618.39
Overhead 3.50% = Tk. 216.44
= Tk. 7,018.71
Add VAT with adjustment factor 1.0582 5.50% = Tk. 408.50
Grand total = Tk. 7,427.21
Rate per sft. = Tk. 74.27
Rate per sqm. = Tk. 799.44

Say, Tk. 799 .00 Per sqm.

Item No.- 30.14.2


Supplying and placing 60 mm colored Uni-block for Walk Way on 50 mm stabilized sand base:
compressive strength 15N/mm2
Consideration of 100 sft of work
(a) Material
(i) 60 mm colored uni-block
(222 x 110 x 60 mm) 388 Nos. @ Tk. 14.00 Per block = Tk. 5,432.00
(ii) Sand 30.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 510.00
(iii) Transportation of block 388 Nos. @ Tk. 1.79 each = Tk. 694.52
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary Labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(c) Tools & machinery 100 sft. @ Tk. 2.45 Per sft. = Tk. 245.00
(d) Local carriage, storage & sundries etc. LS. = Tk. 73.50
Total = Tk. 7,883.32
Profit 10.00% = Tk. 788.33
Overhead 3.50% = Tk. 275.92
= Tk. 8,947.57
Add VAT with adjustment factor 1.0582 5.50% = Tk. 520.76
Grand total = Tk. 9,468.33
Rate per sft. = Tk. 94.68
Rate per sqm. = Tk. 1,019.14

Say, Tk. 1,019 .00 Per sqm.

Item No.- 30.15.1


Supplying and placing 60 mm grey Uni-block for major walk-way, car porch on 50 mm stabilized
sand base: compressive strength 49 N/mm2
Consideration of 100 sft. of work.
(a) Material
9i) 60 mm grey uni-block
(222 x 110 x 60 mm) 388 Nos. @ Tk. 15.23 Per block = Tk. 5,909.24
(ii) Sand 30.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 510.00
(iii) Transportation of block 388 Nos. @ Tk. 1.79 each = Tk. 694.52
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary Labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(c) Tools & machinery 100 sft. @ Tk. 2.45 Per sft. = Tk. 245.00
(d0 Local carriage, storage & sundries etc. LS. = Tk. 73.50
Total = Tk. 8,360.56
Profit 10.00% = Tk. 836.06
Overhead 3.50% = Tk. 292.62
= Tk. 9,489.24
Add VAT with adjustment factor 1.0582 5.50% = Tk. 552.28
Analysis of PWD SoR 2014 for Civil Works 574

Grand total = Tk. 10,041.52


Rate per sft. = Tk. 100.42
Rate per sqm. = Tk. 1,080.92

Say, Tk. 1,081 .00 Per sqm.

Item No.- 30.15.2


Supplying and placing 60 mm colored Uni-block for major walk way, car porch on 50 mm
stabilized sand base: compressive strength 49N/mm2
Consideration of 100 sft. work
(a) Material
(i) 60 mm colored uni-block
(222 x 110 x 60 mm) 388 Nos. @ Tk. 16.71 Per block = Tk. 6,483.48
(ii) Sand 30.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 510.00
(iii) Transportation of block 388 Nos. @ Tk. 1.79 each = Tk. 694.52
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary Labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(c) Tools & machinery 100 sft. @ Tk. 2.45 Per sft. = Tk. 245.00
(d) Local carriage, storage & sundries etc. LS. = Tk. 73.50
Total = Tk. 8,934.80
Profit 10.00% = Tk. 893.48
Overhead 3.50% = Tk. 312.72
= Tk. 10,141.00
Add VAT with adjustment factor 1.0582 5.50% = Tk. 590.22
Grand total = Tk. 10,731.22
Rate per sft. = Tk. 107.31
Rate per sqm. = Tk. 1,155.08

Say, Tk. 1,155 .00 Per sqm.

Item No.- 30.16.1


Supplying and placing 80 mm grey Uni-block for bus terminal, minor road, industrial yard on 50 mm
stabilized sand base: compressive strength 49N/mm2
Consideration of 100 sft. of work
(a) Material
(i) 80 mm grey uni-block
(222 x 110 x 80 mm) 388 Nos. @ Tk. 20.19 Per block = Tk. 7,833.72
(ii) Sand 30.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 510.00
(iii) iii) Transportation of block 388 Nos. @ Tk. 1.79 each = Tk. 694.52
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary Labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(c) Tools & machinery 100 sft. @ Tk. 2.45 Per sft. = Tk. 245.00
(d) Local carriage, storage & sundries etc. LS. = Tk. 73.50
Total = Tk. 10,285.04
Profit 10.00% = Tk. 1,028.50
Overhead 3.50% = Tk. 359.98
= Tk. 11,673.52
Add VAT with adjustment factor 1.0582 5.50% = Tk. 679.41
Grand total = Tk. 12,352.93
Rate per sft. = Tk. 123.53
Rate per sqm. = Tk. 1,329.68

Say, Tk. 1,330 .00 Per sqm.


Analysis of PWD SoR 2014 for Civil Works 575

Item No.- 30.16.2


Supplying and placing 80 mm colored Uni-block for bus terminal, minor road, industrial yard on 50 mm
stabilized sand base: compressive strength 49N/mm2
Consideration of 100 sft. of work
(a) Material
(i) 80 mm colored uni-block
(222 x 110 x 80 mm) 388 Nos. @ Tk. 25.39 Per block = Tk. 9,851.32
(ii) Sand 30.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 510.00
(iii) Transportation of block 388 Nos. @ Tk. 1.79 each = Tk. 694.52
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 1 No. @ Tk. 389.00 each = Tk. 389.00
(iii) Ordinary Labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(d) Tools & machinery 100 sft. @ Tk. 2.45 Per sft. = Tk. 245.00
(e) Local carriage, storage & sundries etc. LS. = Tk. 73.50
Total = Tk. 12,302.64
Profit 10.00% = Tk. 1,230.26
Overhead 3.50% = Tk. 430.59
= Tk. 13,963.49
Add VAT with adjustment factor 1.0582 5.50% = Tk. 812.69
Grand total = Tk. 14,776.18
Rate per sft. = Tk. 147.76
Rate per sqm. = Tk. 1,590.49

Say, Tk. 1,590 .00 Per sqm.

Item No.- 30.17.1


Supplying and placing grey Rectangular-block on 50 mm stabilized sand base:
compressive strength 15N/mm2
Consideration of 100 sft. of work
(a) Material
(i) Grey rec-block
(200 x 100 x 60 mm) 474 Nos. @ Tk. 18.05 Per block = Tk. 8,555.70
(ii) Sand 30.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 510.00
(iii) Transportation of block 474 Nos. @ Tk. 1.79 each = Tk. 848.46
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 0.75 No. @ Tk. 389.00 each = Tk. 291.75
(iii) Ordinary Labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(c) Local carriage, storage & sundries etc. LS. = Tk. 73.50
Total = Tk. 10,818.71
Profit 10.00% = Tk. 1,081.87
Overhead 3.50% = Tk. 378.65
= Tk. 12,279.23
Add VAT with adjustment factor 1.0582 5.50% = Tk. 714.66
Grand total = Tk. 12,993.89
Rate per sft. = Tk. 129.94
Rate per sqm. = Tk. 1,398.67

Say, Tk. 1,399 .00 Per sqm.

Item No.- 30.17.2


Supplying and placing colored Rec-block on 50 mm stabilized sand base:
compressive strength 15N/mm2
Consideration of 100 sft. work
(a) Material
Analysis of PWD SoR 2014 for Civil Works 576

(i) Colored rec-block


(200 x 100 x 60 mm) 474 Nos. @ Tk. 21.42 Per block = Tk. 10,153.08
(ii) Sand 30.00 cft. @ Tk. 1,700.00 Per % cft. = Tk. 510.00
(iii) Transportation of block 474 Nos. @ Tk. 1.79 each = Tk. 848.46
(b) Labour
(i) Head mason 0.1 No. @ Tk. 493.00 each = Tk. 49.30
(ii) Mason 0.75 No. @ Tk. 389.00 each = Tk. 291.75
(iii) Ordinary Labour 2 Nos. @ Tk. 245.00 each = Tk. 490.00
(c) Local carriage, storage & sundries etc. LS. = Tk. 73.50
Total = Tk. 12,416.09
Profit 10.00% = Tk. 1,241.61
Overhead 3.50% = Tk. 434.56
= Tk. 14,092.26
Add VAT with adjustment factor 1.0582 5.50% = Tk. 820.18
Grand total = Tk. 14,912.44
Rate per sft. = Tk. 149.12
Rate per sqm. = Tk. 1,605.13

Say, Tk. 1,605 .00 Per sqm.

Item No.- 30.18.1


Suplying and placing grey engraved cement concrete tiles (250 x 250 mm) with cement mortar (1:4)
Consideration of 100 sft. work
(a) Materials
(i) Grey engraved tiles
in/c wastage 105 sft. @ Tk. 40.57 Per sft. = Tk. 4,259.85
(ii) Cement 1.10 bags @ Tk. 440.00 Per bag = Tk. 484.00
(iii) Sand 5.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 93.50
(iv) Transportation 105 sft. @ Tk. 1.65 Per sft. = Tk. 173.25
(b) Labour
(i) Mason 2 Nos. @ Tk. 389.00 each = Tk. 778.00
(ii) Ordinary Labour 4 Nos. @ Tk. 245.00 each = Tk. 980.00
(c) Local carriage, storage & sundries etc. L.S. = Tk. 98.00
(d) Tools & machinery 100 sft. @ Tk. 2.45 Per sft. = Tk. 245.00
Total = Tk. 7,111.60
Profit 10.00% = Tk. 711.16
Overhead 3.50% = Tk. 248.91
= Tk. 8,071.67
Add VAT with adjustment factor 1.0582 5.50% = Tk. 469.78
Grand total = Tk. 8,541.45
Rate per sft. = Tk. 85.41
30.18.1.1 Ground floor Rate per sqm. = Tk. 919.35

Say, Tk. 919 .00 Per sqm.

30.18.1.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.18.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.18.1.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92

Item No.- 30.18.2


Suplying and placing colored engraved cement concrete tiles (250 x 250 mm) with cement mortar (1:4)
Consideration of 100 sft. work
(a) Materials
(i) Colored engraved tiles
in/c wastage 105 sft. @ Tk. 49.14 Per sft. = Tk. 5,159.70
(ii) Cement 1.10 bags @ Tk. 440.00 Per bag = Tk. 484.00
(iii) Sand 5.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 93.50
Analysis of PWD SoR 2014 for Civil Works 577

(iv) Transportation 100 sft. @ Tk. 1.65 Per sft. = Tk. 165.00
(b) Labour
(i) Mason 2 Nos. @ Tk. 389.00 each = Tk. 778.00
(ii) Ordinary Labour 4 Nos. @ Tk. 245.00 each = Tk. 980.00
(c) Local carriage, storage & sundries etc. L.S. = Tk. 98.00
(d) Tools & machinery 100 sft. @ Tk. 2.45 Per sft. = Tk. 245.00
Total = Tk. 8,003.20
Profit 10.00% = Tk. 800.32
Overhead 3.50% = Tk. 280.11
= Tk. 9,083.63
Add VAT with adjustment factor 1.0582 5.50% = Tk. 528.68
Grand total = Tk. 9,612.31
Rate per sft. = Tk. 96.12
30.18.2.1 Ground floor Rate per sqm. = Tk. 1,034.64

Say, Tk. 1,035 .00 Per sqm.

30.18.2.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.18.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.18.2.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92

Item No.- 30.19.1


225 mm thick wall with concrete solid block (215 x 100 x 65) mm with cement mortar (1:6)
Consideration of 100 sft. of work
(a) Materials
(i) Solid bloc for 225 mm
thick wall in/c wastage 1110 Nos. @ Tk. 7.98 each = Tk. 8,857.80
(ii) Cement 3.00 bags @ Tk. 440.00 Per bag = Tk. 1,320.00
(iii) Sand 22.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 382.50
(iv) Transportation 1110 Nos. @ Tk. 1.64 each = Tk. 1,820.40
(b) Labour
(i) block work in/c screening sand 100 sft. @ Tk. 11.69 Per sft. = Tk. 1,169.00
(ii) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(iii) Labour for local carriage and sundries etc. 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 13,852.20
Profit 10.00% = Tk. 1,385.22
Overhead 3.50% = Tk. 484.83
= Tk. 15,722.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 915.05
Grand total = Tk. 16,637.30
Rate per sft. = Tk. 166.37
30.19.1.1 Ground floor Rate per sqm. = Tk. 1,790.81

Say, Tk. 1,791 .00 Per sqm.

30.19.1.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.19.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.19.1.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92

Item No.- 30.19.2


112 mm thick wall with concrete solid block (215 x 100 x 65) mm with cement mortar (1:6)
Consideration of 100 sft. work
(a) Materials
(i) Solid bloc for 112 mm
thick wall in/c wastage 560 Nos. @ Tk. 7.98 each = Tk. 4,468.80
(ii) Cement 1.00 bag @ Tk. 440.00 Per bag = Tk. 440.00
(iii) Sand 7.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 127.50
Analysis of PWD SoR 2014 for Civil Works 578

(iv) Transportation 560 Nos. @ Tk. 1.64 each = Tk. 918.40


(b) Labour
(i) Block work in/c screening sand & curing 100 sft. @ Tk. 7.77 Per sft. = Tk. 777.00
(ii) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(iii) Labour for local carriage, sundries etc. 0.5 No. @ Tk. 245.00 each = Tk. 122.50
Total = Tk. 7,034.20
Profit 10.00% = Tk. 703.42
Overhead 3.50% = Tk. 246.20
= Tk. 7,983.82
Add VAT with adjustment factor 1.0582 5.50% = Tk. 464.67
Grand total = Tk. 8,448.49
Rate per sft. = Tk. 84.48
30.19.2.1 Ground floor Rate per sqm. = Tk. 909.34

Say, Tk. 909 .00 Per sqm.

30.19.2.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.19.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.19.2.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92

Item No.- 30.20.1


Providing cladding work in facing in superstructure with 200 x 90 x 38 mm size concrete solid
cladding pested with 20 mm thick cement mortar (1:4): Grey
Consideration of 100 sft. work
(a) Materials
(i) Grey cladding block in/c wastage 480 Nos. @ Tk. 12.19 each = Tk. 5,851.20
(ii) Cement 2.60 bags @ Tk. 440.00 Per bag = Tk. 1,144.00
(iii) Sand 16.25 cft. @ Tk. 1,700.00 Per % cft. = Tk. 276.25
(iv) Transportation 480 Nos. @ Tk. 2.01 each = Tk. 964.80
(b) Labour
(i) Block work in/c screening sand & curing 100 sft. @ Tk. 14.95 Per sft. = Tk. 1,495.00
(ii) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(iii) Tools and machinery 100 sft. @ Tk. 2.45 Per sft. Tk. 245.00
(iv) Labour for local carriage, sundries etc. 0.75 No. @ Tk. 245.00 each = Tk. 183.75
Total = Tk. 10,340.00
Profit 10.00% = Tk. 1,034.00
Overhead 3.50% = Tk. 361.90
= Tk. 11,735.90
Add VAT with adjustment factor 1.0582 5.50% = Tk. 683.04
Grand total = Tk. 12,418.94
Rate per sft. = Tk. 124.19
30.20.1.1 Ground floor Rate per sqm. = Tk. 1,336.78

Say, Tk. 1,337 .00 Per sqm.

30.20.1.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.20.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.20.1.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92

Item No.- 30.20.2


Providings cladding work in facing in superstructure with 200 x 92x 38 mm size concrete
solid cladding pested with 20 mm thick cement mortar (1:4): Colored
Consideration of 100 sft. work
(a) Materials
(i) Colored cladding block in/c wastage 480 Nos. @ Tk. 8.96 each = Tk. 4,300.80
(ii) Cement 2.60 bags @ Tk. 440.00 Per bag = Tk. 1,144.00
(iii) Sand 16.25 cft. @ Tk. 1,700.00 Per % cft. = Tk. 276.25
Analysis of PWD SoR 2014 for Civil Works 579

(iv) Transportation 480 Nos. @ Tk. 2.01 each = Tk. 964.80


(b) Labour
(i) Cladding work in/c screening sand 100 sft. @ Tk. 14.95 Per sft. = Tk. 1,495.00
(ii) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(iii) Tools and machinery 100 sft. @ Tk. 2.45 Per sft. Tk. 245.00
(iv) Labour for local carriagesundries etc. 0.75 No. @ Tk. 245.00 each = Tk. 183.75
Total = Tk. 8,789.60
Profit 10.00% = Tk. 878.96
Overhead 3.50% = Tk. 307.64
= Tk. 9,976.20
Add VAT with adjustment factor 1.0582 5.50% = Tk. 580.62
Grand total = Tk. 10,556.82
Rate per sft. = Tk. 105.57
30.20.2.1 Ground floor Rate per sqm. = Tk. 1,136.36

Say, Tk. 1,136 .00 Per sqm.

30.20.2.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.20.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.20.2.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92

Item No.- 30.20.3


Providing cladding work in facing in superstructure with 400 x 100 x 50 mm size concrete
split cladding pested with 20 mm thick cement mortar (1:4): Grey
Consideration of 100 sft. work
(a) Materials
(i) Grey split cladding block in/c wastage 220 Nos. @ Tk. 16.61 each = Tk. 3,654.20
(ii) Cement 2.60 bags @ Tk. 440.00 Per bag = Tk. 1,144.00
(iii) Sand 16.25 cft. @ Tk. 1,700.00 Per % cft. = Tk. 276.25
(iv) Transportation 220 Nos. @ Tk. 2.49 each = Tk. 547.80
(b) Labour
(i) Cladding work in/c screening sand & curing 100 sft. @ Tk. 19.06 Per sft. = Tk. 1,906.00
(ii) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(iii) Tools and machinery 100 sft. @ Tk. 2.45 Per sft. Tk. 245.00
(iv) Labour for local carriagesundries etc. 0.75 No. @ Tk. 245.00 each = Tk. 183.75
Total = Tk. 8,137.00
Profit 10.00% = Tk. 813.70
Overhead 3.50% = Tk. 284.80
= Tk. 9,235.50
Add VAT with adjustment factor 1.0582 5.50% = Tk. 537.52
Grand total = Tk. 9,773.02
Rate per sft. = Tk. 97.73
30.20.3.1 Ground floor Rate per sqm. = Tk. 1,051.97

Say, Tk. 1,052 .00 Per sqm.

30.20.3.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.20.3.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.20.3.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92

Item No.- 30.20.4


Providing cladding work in facing in superstructure with 400 x 100 x 50 mm size concrete
Split cladding pested with 20 mm thick cement mortar (1:4): Colored
Consideration of 100 sft. work
(a) Materials
(i) Colored split cladding block 220 Nos. @ Tk. 18.65 each = Tk. 4,103.00
(ii) Cement 2.60 bags @ Tk. 440.00 Per bag = Tk. 1,144.00
Analysis of PWD SoR 2014 for Civil Works 580

(iii) Sand 16.25 cft. @ Tk. 1,700.00 Per % cft. = Tk. 276.25
(iv) Transportation 220 Nos. @ Tk. 2.49 each = Tk. 547.80
(b) Labour
(i) Cladding work in/c screening
sand & nominal curing 100 sft. @ Tk. 19.06 Per sft. = Tk. 1,906.00
(ii) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(iii) Tools and machinery 100 sft. @ Tk. 2.45 Per sft. Tk. 245.00
(iv) Labour for local carriage sundries etc. 0.75 No. @ Tk. 245.00 each = Tk. 183.75
Total = Tk. 8,585.80
Profit 10.00% = Tk. 858.58
Overhead 3.50% = Tk. 300.50
= Tk. 9,744.88
Add VAT with adjustment factor 1.0582 5.50% = Tk. 567.16
Grand total = Tk. 10,312.04
Rate per sft. = Tk. 103.12
30.20.4.1 Ground floor Rate per sqm. = Tk. 1,109.98

Say, Tk. 1,110 .00 Per sqm.

30.20.4.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.20.4.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.20.4.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92

Item No.- 30.20.5


Providing facial cladding work in facing in superstructure with 420 x 330 x 15 mm size
concrete facial cladding pested with 20 mm thick cement mortar (1:4): Colored
Consideration of 100 sft. work
(a) Materials
(i) Colored facial cladding block 67 Nos. @ Tk. 30.62 each = Tk. 2,051.54
(ii) Cement 2.00 bags @ Tk. 440.00 Per bag = Tk. 880.00
(iii) Sand 12.5 cft. @ Tk. 1,700.00 Per % cft. = Tk. 212.50
(iv) Transportation 67 Nos. @ Tk. 2.49 each = Tk. 166.83
(b) Labour
(i) Cladding work in/c screening sand & curing 100 sft. @ Tk. 14.95 Per sft. = Tk. 1,495.00
(ii) Scaffolding 25 sft. @ Tk. 7.20 Per sft. = Tk. 180.00
(iii) Tools and machinery 100 sft. @ Tk. 2.45 Per sft. Tk. 245.00
(iv) Labour for local carriagesundries etc. 0.75 No. @ Tk. 245.00 each = Tk. 183.75
Total = Tk. 5,414.62
Profit 10.00% = Tk. 541.46
Overhead 3.50% = Tk. 189.51
= Tk. 6,145.59
Add VAT with adjustment factor 1.0582 5.50% = Tk. 357.68
Grand total = Tk. 6,503.27
Rate per sft. = Tk. 65.03
30.20.5.1 Ground floor Rate per sqm. = Tk. 699.98

Say, Tk. 700 .00 Per sqm.

30.20.5.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft.) Per sqm = Tk. 31.28
30.20.5.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 Nos. lab. per % sft.) Per sqm = Tk. 39.10
30.20.5.4 Add for each addl floor for 10th floor and above (@ 1.5 Nos. lab. per % sft.) Per sqm = Tk. 46.92

Item No.- 30.21.1


Providing 418 x 330 x 17 mm red/brown color roof tiles on prefabricated truss
Consideration of 100 Nos.
(a) Materials
(i) Red/brown color concrete
Analysis of PWD SoR 2014 for Civil Works 581

roof tiles in/c wastage 102.0 Nos. @ Tk. 41.07 each = Tk. 4,189.14
(ii) J-hook with nut & washer 60.00 Nos. @ Tk. 9.00 each = Tk. 540.00
(iii) Transportation 102 Nos. @ Tk. 3.00 each = Tk. 306.00
(b) Labour
(i) Lifting & placing on shutter 102.0 Nos. @ Tk. 2.45 Per sft. = Tk. 249.90
(c) Tools and machinery for 102.0 Nos. @ Tk. 3.68 Per sft. Tk. 375.36
Total = Tk. 5,660.40
Profit 10.00% = Tk. 566.04
Overhead 3.50% = Tk. 198.11
= Tk. 6,424.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 373.92
Grand total = Tk. 6,798.47
Rate each. = Tk. 67.98

Say, Tk. 68 .00 sqm

Item No.- 30.21.2


Providing 418 x 330 x 17 mm Oriental red/Ruset gold/Mehagany color roof tiles on prefabricated truss
Consideration of 100 Nos.
(a) Materials
(i) Oriental red/Ruset/Mehagany color concrete
roof tiles in/c wastage 102 Nos. @ Tk. 37.01 each = Tk. 3,775.02
(ii) J-hook with nut & washer 60.00 Nos. @ Tk. 9.00 each = Tk. 540.00
(iii) Transportation 102 Nos. @ Tk. 3.00 each = Tk. 306.00
(b) Labour
(i) Lifting & placing on shutter 102 Nos. @ Tk. 2.45 Per sft. = Tk. 249.90
(c) Tools and machinery for 102 Nos. @ Tk. 3.68 Per sft. Tk. 375.36

Total = Tk. 5,246.28


Profit 10.00% = Tk. 524.63
Overhead 3.50% = Tk. 183.62
= Tk. 5,954.53
Add VAT with adjustment factor 1.0582 5.50% = Tk. 346.56
Grand total = Tk. 6,301.09
Rate each. = Tk. 63.01

Say, Tk. 63 .00 sqm.

Item No.- 30.21.3


Providing 418 x 330 x 17 mm Antique red color roof tiles on pre-fabricated truss
Consideration of 100 Nos.
(a) Materials
(i) Antique red color concrete roof tiles 102 Nos. @ Tk. 42.65 each = Tk. 4,350.30
(ii) J-hook with nut & washer 60.00 Nos. @ Tk. 9.00 each = Tk. 540.00
(iii) Transportation 102 Nos. @ Tk. 3.00 each = Tk. 306.00
(b) Labour
(i) Lifting & placing on shutter 102 Nos. @ Tk. 2.45 Per sft. = Tk. 249.90
(c) Tools and machinery for 102 Nos. @ Tk. 2.45 Per sft. Tk. 249.90
Total = Tk. 5,696.10
Profit 10.00% = Tk. 569.61
Overhead 3.50% = Tk. 199.36
= Tk. 6,465.07
Add VAT with adjustment factor 1.0582 5.50% = Tk. 376.27
Grand total = Tk. 6,841.34
Rate each. = Tk. 68.41

Say, Tk. 68 .00 sqm.


Analysis of PWD SoR 2014 for Civil Works 582

Item No.- 30.21.4


Providing 418 x 330 x 17 mm green color roof tiles on prefabricated truss
Consideration of 100 Nos.
(a) Materials
(i) Green red color concrete
roof tiles in/c wastag 102 Nos. @ Tk. 46.40 each = Tk. 4,732.80
(ii) J-hook with nut & washer 60.00 Nos. @ Tk. 9.00 each = Tk. 540.00
(iii) Transportation 102 Nos. @ Tk. 3.00 each = Tk. 306.00
(b) Labour
(i) Lifting & placing on shutter 100 Nos. @ Tk. 2.45 Per sft. = Tk. 245.00
(c) Tools and machinery for 100 Nos. @ Tk. 2.45 Per sft. Tk. 245.00
Total = Tk. 6,068.80
Profit 10.00% = Tk. 606.88
Overhead 3.50% = Tk. 212.41
= Tk. 6,888.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 400.89
Grand total = Tk. 7,288.98
Rate each. = Tk. 72.89

Say, Tk. 73 .00 sqm.

Item No.- 30.22


Supplying and placing of concrete kerb stone (K3) as per direction of the engineer in charge
Consideration of 100 Nos.
(a) Materials
(i) Kerb-stone (600 x 300 x 100/60 mm) 100 Nos. @ Tk. 121.66 each = Tk. 12,166.00
(ii) Cement for pointing & jointing 1.50 bags @ Tk. 440.00 Per bag = Tk. 660.00
(iii) Transportation 100 Nos. @ Tk. 27.12 each = Tk. 2,712.00
(b) Labour
(i) Local carriage & placing 100 Nos. @ Tk. 7.35 each = Tk. 735.00
Total = Tk. 16,273.00
Profit 10.00% = Tk. 1,627.30
Overhead 3.50% = Tk. 569.56
= Tk. 18,469.86
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,074.96
Grand total = Tk. 19,544.82
Rate each. = Tk. 195.45

Say, Tk. 195 .00 sqm .


Analysis of PWD SoR 2014 for Civil Works 583

DIVISION 31: SUB-SOIL INVESTIGATION WORK


Except in special cases as deemed by the authority Sub-soil exploration and testing to be executed only by the PWD enlisted agencies
according to the advice of the design office in regards to the number of bore-holes, number and types of tests mentioning .

Item No.- 31.1


Mobilization and demobilization of boring equipment and man-power: at site within 20 km from district
Head Quarters (drilling rig comprising drilling pipe, drop hammer, tripod, pulley,
chain, wrange, sample collection devices etc tools and plant; tripol for
temporary camp, 8-10 men work-force)
Considering 1 No. site
(a) Truck fare in/c loading and unloading (both ways) 2 way 1000.00 L.S. = Tk. 2,000.00
(b) Camp at site L.S. = Tk. 1,053.00
(c) Conveyance for man-power
(2 x 8 Nos.) 16 Nos. @ Tk. 63.00 each = Tk. 1,008.00
(c) Wages for man power
(i) Foreman: 1 No. x (1/2 + 1/2) 1 manday @ Tk. 670.00 each = Tk. 670.00
(ii) Rig operators: 1 No. x (1/2 + 1/2) 1 manday @ Tk. 603.00 each = Tk. 603.00
(iii) Helper to rig operators:
6 Nos. x (1/2 + 1/2) 6 mandays @ Tk. 375.00 each = Tk. 2,250.00
(iv) Incidental, sundries etc. L.S. = Tk. 161.70
Total = Tk. 7,745.70
Profit 10.00% = Tk. 774.57
Overhead 3.50% = Tk. 271.10
= Tk. 8,791.37
Add VAT with adjustment factor 1.0582 5.50% = Tk. 511.67
Grand total = Tk. 9,303.04
Rate per site = Tk. 9,303.04

Say, Tk. 9,303 .00 Per site

Item No.- 31.2 Field vist, BH Coordinate settings and inspection of sampling and samples by the Geo-tech. Expert / Engineer
Considering 1 No. site
Field visit and(a)inspection of sampling and samples by the Geo-tech. Expert / Engineer in/c
3 Conv unit
& DA, 1438 = Tk. 4,314.00
(b) Setting location & Cordinates of BH in X,Y,Z from
surveyer
datum 0.25 day 1200 300
Helper to surveyer 0.25 day 750 187.5
Profit 10.00% = Tk. 431.40
Overhead 3.50% = Tk. 150.99
= Tk. 5,383.89
Add VAT with adjustment factor 1.0582 5.50% = Tk. 313.35
Total = Tk. 5,697.24
Rate per site = Tk. 5,697.24

Say, Tk. 5,697 .00 Per site

Item No.- 31.3


31.3.1 Installation of boring equipment at site: dry ground condition to submerged field of water
depth up to 750 mm
Considering 1 point
(i) Foreman (1 x 1/32) 0.03 manday @ Tk. 670.00 each = Tk. 20.10
(ii) Rig operators (1 x 1/16) 0.06 manday @ Tk. 603.00 each = Tk. 36.18
(iii) Helper to rig operators (6 x 1/16) 0.38 mandays @ Tk. 375.00 each = Tk. 142.50
(iv) Incidental, sundries, consumables etc. L.S. = Tk. 500.00
Total = Tk. 698.78
Profit 10.00% = Tk. 69.88
Overhead 3.50% = Tk. 24.46
= Tk. 793.12
Analysis of PWD SoR 2014 for Civil Works 584

Add VAT with adjustment factor 1.0582 5.50% = Tk. 46.16


Grand total = Tk. 839.28
Rate per point = Tk. 839.28
Say, Tk. 839 .00 Per point

31.3.2 Installation of boring equipment at site: For depth of water above 750 mm and up to 1500 mm
Considering 1 point
(a) Man-power
(i) Foreman (1 x 1/16) 0.06 manday @ Tk. 670.00 each = Tk. 40.20
(ii) Rig operators (1 x 1/8) 0.13 manday @ Tk. 603.00 each = Tk. 78.39
(iii) Skilled labour (6 x 1/8) 0.75 mandays @ Tk. 375.00 each = Tk. 281.25
(iv) Unskilled labour (2 x 1/8) 0.25 manday @ Tk. 245.00 each = Tk. 61.25
(b) Material
(i) Bamboo for platform (using 6 times) 268 rft. @ Tk. 12.00 Per rft. = Tk. 536.00
(ii) Wooden plank (using 6times)
10 x 8'-0" x 12" x 1.5"= 12 cft. @ Tk. 470.00 Per cft. = Tk. 940.00
(iii) Rope (using 4 times) 8 kg. @ Tk. 45.00 Per kg. = Tk. 90.00
(iv) Hire charge of small boat 1 No. @ Tk. 688.00 Tk. 688.00
in/c boatman & helper, 1 No. @ Tk. 700.00 Per day = Tk. 700.00
(v) Tools & plant, sundries, consumables, local carrying 4 No. Tk. 245.00 L.S. = Tk. 980.00
Total = Tk. 4,395.09
Profit 10.00% = Tk. 439.51
Overhead 3.50% = Tk. 153.83
= Tk. 4,988.43
Add VAT with adjustment factor 1.0582 5.50% = Tk. 290.33
Grand total = Tk. 5,278.76
Re-use to other bore point 0.8 Rate per point = Tk. 4,223.01

Say, Tk. 4,223 .00 Per point

31.3.3 Installation of boring equipment at site: For depth of water above 1500 mm (stagnant water)
Considering 1 point
(a) Man-power
(i) Foreman (1 x 1/16) 0.06 manday @ Tk. 670.00 each = Tk. 40.20
(ii) Rig operators (1 x 1/8) 0.13 manday @ Tk. 603.00 each = Tk. 78.39
(iii) Skilled labour (6 x 1/8) 0.75 mandays @ Tk. 375.00 each = Tk. 281.25
(iv) Unskilled labour (2 x 1/8) 0.25 manday @ Tk. 245.00 each = Tk. 61.25
(b) Material
(i) Bamboo for platform (using 6 times) 260 rft. @ Tk. 12.00 each = Tk. 520.00
(ii) Wooden plank (using 6 times)
15 x 8'-0" x 12" x 1.5"= 15 cft. @ Tk. 470.00 Per cft. = Tk. 1,175.00
(iii) Rope (using 4 times) 20 kg. @ Tk. 45.00 Per kg. = Tk. 225.00
(iv) Hire charge of small boat 1 no Tk. 688.00
in/c boatman & helper. 1 No. @ Tk. 700.00 Per day = Tk. 700.00
(v) Drum (defects free, using 8 times) 22 Nos. @ Tk. 995.00 each = Tk. 2,736.25
(vi) Tools & plant, anchor, sundries, consumables, local carrying4 uni Tk. 245.00 = Tk. 980.00
Total = Tk. 6,797.34
Profit 10.00% = Tk. 679.73
Overhead 3.50% = Tk. 237.91
= Tk. 7,714.98
Add VAT with adjustment factor 1.0582 5.50% = Tk. 449.02
Grand total = Tk. 8,164.00
Re-use to other bore point 0.7 Rate per point = Tk. 5,714.80

Say, Tk. 5,715 .00 Per point


Item No.- 31.4
31.4.1 Boring 100 mm dia bore-hole by wash boring method: 0 to 15 meter
Analysis of PWD SoR 2014 for Civil Works 585

(a) Hire charge of boring rig 0.4 day @ Tk. 2,750.00 Per day = Tk. 1,100.00
(b) Wages for man power
(i) Foreman
(1 x 20% per day x 0.4 day) 0.08 manday @ Tk. 670.00 each = Tk. 53.60
(ii) Rig operator
(1 x 30% per day x 0.4 day) 0.12 manday @ Tk. 603.00 each = Tk. 72.36
(iii) Helper to rig operators
(5 x 50% per day x 0.4 day) 1.00 mandays @ Tk. 375.00 each = Tk. 375.00
Total = Tk. 1,600.96
Profit 10.00% = Tk. 160.10
Overhead 3.50% = Tk. 56.03
= Tk. 1,817.09
Add VAT with adjustment factor 1.0582 5.50% = Tk. 105.76
Grand total = Tk. 1,922.85
Rate per meter = Tk. 213.65

Say, Tk. 214 .00 Per rm

31.4.2 Boring 100 mm dia bore-hole by wash boring method: 15 meter to 25 meter

(a) Hire charge of boring rig 0.44 day @ Tk. 2,750.00 Per day = Tk. 1,210.00
(b) Wages for man power
(i) Foreman
(1 x 20% per day x 0.4 4day) 0.09 manday @ Tk. 670.00 each = Tk. 60.30
(ii) Rig operator
(1 x 30% per day x 0.44 day) 0.13 manday @ Tk. 603.00 each = Tk. 78.39
(iii) Helper to rig operators
(5 x 50% per day x 0.44 day) 1.10 mandays @ Tk. 375.00 each = Tk. 412.50
Total = Tk. 1,761.19
Profit 10.00% = Tk. 176.12
Overhead 3.50% = Tk. 61.64
= Tk. 1,998.95
Add VAT with adjustment factor 1.0582 5.50% = Tk. 116.34
Grand total = Tk. 2,115.29
Rate per meter = Tk. 235.03

Say, Tk. 235 .00 Per rm

31.4.3 Boring 100 mm dia bore-hole by wash boring method: 25 meter to 35 meter

(a) Hire charge of boring rig 0.45 days @ Tk. 2,750.00 Per day = Tk. 1,237.50
(b) Wages for man power
(i) Foreman
(1 x 20% per day x 0.45day) 0.090 manday @ Tk. 670.00 each = Tk. 60.30
(ii) Rig operator
(1 x 30% per day x 0.45 day) 0.135 manday @ Tk. 603.00 each = Tk. 81.41
(iii) Helper to rig operators
(5 x 50% per day x 0.45day) 1.13 manday @ Tk. 375.00 each = Tk. 423.75
Total = Tk. 1,802.96
Profit 10.00% = Tk. 180.30
Overhead 3.50% = Tk. 63.10
= Tk. 2,046.36
Add VAT with adjustment factor 1.0582 5.50% = Tk. 119.10
Grand total = Tk. 2,165.46
Rate per meter = Tk. 240.61
Analysis of PWD SoR 2014 for Civil Works 586

Say, Tk. 241 .00 Per rm

31.4.4 Boring 100 mm dia bore-hole by wash boring method: 35 meter to 45 meter

(a) Hire charge of boring rig 0.46 day @ Tk. 2,750.00 Per day = Tk. 1,265.00
(b) Wages for man power
(i) Foreman 0.092 manday @ Tk. 670.00 each = Tk. 61.64
(1 x 20% per day x 0.46day)
(ii) Rig operator 0.138 manday @ Tk. 603.00 each = Tk. 83.21
(1 x 30% per day x 0.46 day)
(iii) Helper to rig operators 1.15 mandays @ Tk. 375.00 each = Tk. 431.25
(5 x 50% per day x 0.46day) Total = Tk. 1,841.10
Profit 10.00% = Tk. 184.11
Overhead 3.50% = Tk. 64.44
= Tk. 2,089.65
Add VAT with adjustment factor 1.0582 5.50% = Tk. 121.62
Grand total = Tk. 2,211.27
Rate per meter = Tk. 245.70

Say, Tk. 246 .00 Per rm

31.4.5 Boring 100 mm dia bore-hole by wash boring method: 45m & above

(a) Hire charge of boring rig 0.48 day @ Tk. 2,750.00 Per day = Tk. 1,320.00
(b) Wages for man power
(i) Foreman 0.10 manday @ Tk. 670.00 each = Tk. 67.00
(1 x 20% per day x 0.48day)
(ii) Rig operator 0.14 manday @ Tk. 603.00 each = Tk. 84.42
(1 x 30% per day x 0.48 day)
(iii) Helper to rig operators 1.20 manday @ Tk. 375.00 each = Tk. 450.00
(5 x 50% per day x 0.48day) Total = Tk. 1,921.42
Profit 10.00% = Tk. 192.14
Overhead 3.50% = Tk. 67.25
= Tk. 2,180.81
Add VAT with adjustment factor 1.0582 5.50% = Tk. 126.93
Grand total = Tk. 2,307.74
Rate per meter = Tk. 256.42

Say, Tk. 256 .00 Per rm

Item No.- 31.5


Execution of SPT (ASTM D-1586 - 84, Hammer: 140 + 2 Ibs / 63.5 + 1 kg, Height of fall: 30" + 1" / 760 mm +
25 mm): in/c withdrawing drilling pipe from the bore-hole and fixing the steel cap with the drilling pipe and
again placing the drilling pipe with cap into the bore-hole up to layer of interest SPT to be executed at 1.5 m interval
[SPT to be executed in each layer of interest.]
31.5.1 SPT @ 1500 mm interval: For 0 to 15 meter
Considering 6 points SPT execution in 0.4 day
(i) Foreman
(1 x 30% per day x 0.4 day) 0.12 manday @ Tk. 670.00 each = Tk. 80.40
(ii) Rig operators
(1 x 30% per day x 0.4 day) 0.12 manday @ Tk. 603.00 each = Tk. 72.36
(iii) Helper to rig operators
(6 x 30% per day x 0.4 day) 0.72 manday @ Tk. 375.00 each = Tk. 270.00
(iv) Incidental, sundries etc. L.S. = Tk. 24.50
Total = Tk. 447.26
Profit 10.00% = Tk. 44.73
Overhead 3.50% = Tk. 15.65
Analysis of PWD SoR 2014 for Civil Works 587

= Tk. 507.64
Add VAT with adjustment factor 1.0582 5.50% = Tk. 29.55
Grand total = Tk. 537.19
Rate per point = Tk. 89.53

Say, Tk. 90 .00 Per point

31.5.2 SPT @ 1500 mm interval: For 15 meter to 25 meter


Considering 6 points SPT execution in 0.44 day
(i) Foreman
(1 x 30% per day x 0.44 day) 0.13 manday @ Tk. 670.00 each = Tk. 87.10
(ii) Rig operators
(1 x 30% per day x 0.44 day) 0.13 manday @ Tk. 603.00 each = Tk. 78.39
(iii) Helper to rig operators
(6 x 30% per day x 0.44) 0.79 manday @ Tk. 375.00 each = Tk. 296.25
(iv) Incidental, sundries etc. L.S. = Tk. 36.75
Total = Tk. 498.49
Profit 10.00% = Tk. 49.85
Overhead 3.50% = Tk. 17.45
= Tk. 565.79
Add VAT with adjustment factor 1.0582 5.50% = Tk. 32.93
Grand total = Tk. 598.72
Rate per point = Tk. 99.79

Say, Tk. 100 .00 Per point


31.5.3 SPT @ 1500 mm interval: For 25 meter to 35 meter
Considering 6 points SPT execution in 0.48 day
(i) Foreman (1 x 30% per day x 0.48 day) 0.14 manday @ Tk. 670.00 each = Tk. 93.80
(ii) Rig operators
(1 x 30% per day x 0.48 day) 0.14 manday @ Tk. 603.00 each = Tk. 84.42
(iii) Helper to rig operators
(6 x 30% per day x 0.48 day) 0.86 mandays @ Tk. 375.00 each = Tk. 322.50
(iv) Incidental, sundries etc. L.S. = Tk. 36.75
Total = Tk. 537.47
Profit 10.00% = Tk. 53.75
Overhead 3.50% = Tk. 18.81
= Tk. 610.03
Add VAT with adjustment factor 1.0582 5.50% = Tk. 35.50
Grand total = Tk. 645.53
Rate per point = Tk. 107.59

Say, Tk. 108 .00 Per point

31.5.4 SPT @ 1500 mm interval: For 35 meter to 45 meter


Considering 6 points SPT execution in 0.53 day
(i) Foreman (1 x 35% per day x 0.53 day) 0.19 manday @ Tk. 670.00 each = Tk. 127.30
(ii) Rig operators
(1 x 35% per day x 0.53 day) 0.19 manday @ Tk. 603.00 each = Tk. 114.57
(iii) Helper to rig operators
(6 x 35% per day x 0.53 day) 1.11 manday @ Tk. 375.00 each = Tk. 416.25
(iv) Incidental, sundries etc. L.S. = Tk. 36.75
Total = Tk. 694.87
Profit 10.00% = Tk. 69.49
Overhead 3.50% = Tk. 24.32
= Tk. 788.68
Add VAT with adjustment factor 1.0582 5.50% = Tk. 45.90
Grand total = Tk. 834.58
Analysis of PWD SoR 2014 for Civil Works 588

Rate per point = Tk. 139.10

Say, Tk. 139 .00 Per point

31.5.5 SPT @ 1500 mm interval: For 45 meter & above


Considering 6 points SPT execution in 0.58 day
(i) Foreman (1 x 40% per day x 0.58 day) 0.35 manday @ Tk. 670.00 each = Tk. 234.50
(ii) Rig operators
(1 x 40% per day x 0.58 day) 0.28 manday @ Tk. 603.00 each = Tk. 168.84
(iii) Helper to rig operators
(6 x 40% per day x 0.58 day) 1.68 mandays @ Tk. 375.00 each = Tk. 630.00
(iv) Incidental, sundries etc. L.S. = Tk. 36.75
Total = Tk. 1,070.09
Profit 10.00% = Tk. 107.01
Overhead 3.50% = Tk. 37.45
= Tk. 1,214.55
Add VAT with adjustment factor 1.0582 5.50% = Tk. 70.69
Grand total = Tk. 1,285.24
Rate per point = Tk. 214.21

Say, Tk. 214 .00 Per point

Item No.- 31.6


Collection of undisturbed soil samples in 75 mm tube from cohesive layer in/c preservation,
and transportation: (ASTM D-1587-83)
Considering 1 No. sample
(i) Collection, preservation, transportation and incidental charges L.S. = Tk. 93.80
Profit 10.00% = Tk. 9.38
Overhead 3.50% = Tk. 3.28
= Tk. 106.46
Add VAT with adjustment factor 1.0582 5.50% = Tk. 6.20
Total = Tk. 112.66
Rate per sample = Tk. 112.66

Say, Tk. 113 .00 Per sample

Item No.- 31.7


Collection of disturbed soil samples in 75 mm tube from cohesive layer in/c preservation,
and transportation. (ASTM D-1587-84)
Considering 1 No. sample

(i) Collection, preservation, transportation and incidental charges L.S. = Tk. 80.40
Profit 10.00% = Tk. 8.04
Overhead 3.50% = Tk. 2.81
= Tk. 91.25
Add VAT with adjustment factor 1.0582 5.50% = Tk. 5.31
Total = Tk. 96.56
Rate per sample = Tk. 96.56

Say, Tk. 97 .00 Per sample

Item No.- 31.8


Plate load test
Mobilization, demobilization, arrangement of plates for loading and all
other required materials, execution of tests, recording the data,
preparation and submission of test report
(if desired by S.E. Design Circle) L.S. = Tk. 16,250.00
Analysis of PWD SoR 2014 for Civil Works 589

Profit 10.00% = Tk. 1,625.00


Overhead 3.50% = Tk. 568.75
= Tk. 18,443.75
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,073.44
Total = Tk. 19,517.19

Say, Tk. 19,517 .00 Per test

Item No.- 31.9


Preparation, writing and submission of report on sub-soil investigation
Considering for 1 site
(a) Foundation Engineer 1 man day @ Tk. 2,156.00 Each = Tk. 2,156.00
(b) Computer operator for data entry,
composition and result presentation etc. 3 man day @ Tk. 1,500.00 Each = Tk. 4,500.00
(c) Paper, spiral binding, consumable articles
and submission of report to
the officer-in-charge etc. 8 copies @ Tk. 256.79 Per copy = Tk. 2,054.32
Total = Tk. 8,710.32
Profit 10.00% = Tk. 871.03
Overhead 3.50% = Tk. 304.86
= Tk. 9,886.21
Add VAT with adjustment factor 1.0582 5.50% = Tk. 575.39
Grand total Tk. 10,461.60

Say, Tk. 10,462 .00 Per site


31.32 General Sub - Soil investigation by exploratory borings ,
mobilization ,collection samples Testings & Reports etc. in numbers as required.

31.32.1 Bore Hole depth 0 to 15m per bore 1 Tk. 7,222.50 each = Tk. 7,222.50
15 Total = Tk. 7,222.50
f=samplecollection , test, report 2.25 Profit 10.00% = Tk. 722.25
boring/m Tk. 214 Overhead 3.50% = Tk. 252.79
= Tk. 8,197.54
Add VAT with adjustment factor 1.0582 5.50% = Tk. 477.11
Grand total Tk. 8,674.65

Say, Tk. 8,675 .00 Per bore

31.32.2 Bore Hole depth 0 to 18m per bore 1 LS Tk. 7,583.63 each = Tk. 7,583.63
Total = Tk. 7,583.63
Tk. 7,222.50 Profit 10.00% = Tk. 758.36
f=1.05 1.05 Overhead 3.50% = Tk. 265.43
= Tk. 8,607.42
Add VAT with adjustment factor 1.0582 5.50% = Tk. 500.96
Grand total Tk. 9,108.38

Say, Tk. 9,108 .00 Per bore

31.32.3 Bore Hole depth 0 to 20m per bore 1 LS Tk. 9,461.48 each = Tk. 9,461.48
20 Total = Tk. 9,461.48
Tk. 7,222.50 Profit 10.00% = Tk. 946.15
1.31 Overhead 3.50% = Tk. 331.15
= Tk. 10,738.78
Add VAT with adjustment factor 1.0582 5.50% = Tk. 625.01
Grand total Tk. 11,363.79

Say, Tk. 11,364 .00 Per bore


Analysis of PWD SoR 2014 for Civil Works 590

31.32.4 Bore Hole depth 0 to 25m per bore 1 LS Tk. 11,353.77 each = Tk. 11,353.77
25 Total = Tk. 11,353.77
Tk. 7,222.50 Profit 10.00% = Tk. 1,135.38
1.572 Overhead 3.50% = Tk. 397.38
= Tk. 12,886.53
Add VAT with adjustment factor 1.0582 5.50% = Tk. 750.01
Grand total Tk. 13,636.54

Say, Tk. 13,637 .00 Per bore

31.32.5 Bore Hole depth 0 to 30m per bore 1 LS Tk. 13,624.52 each = Tk. 13,624.52
30 Total = Tk. 13,624.52
Tk. 7,222.50 Profit 10.00% = Tk. 1,362.45
1.8864 Overhead 3.50% = Tk. 476.86
= Tk. 15,463.83
Add VAT with adjustment factor 1.0582 5.50% = Tk. 900.01
Grand total Tk. 16,363.84

Say, Tk. 16,364 .00 Per bore

31.32.6 Bore Hole depth 0 to 35m per bore 1 Tk. 16,349.43 each = Tk. 16,349.43
35 Total = Tk. 16,349.43
Tk. 7,222.50 Profit 10.00% = Tk. 1,634.94
2.26368 Overhead 3.50% = Tk. 572.23
= Tk. 18,556.60
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,080.01
Grand total Tk. 19,636.61

Say, Tk. 19,637 .00 Per bore

31.32.7 Bore Hole depth 0 to 40m per bore 1 Tk. 19,619.31 each = Tk. 19,619.31
40 Total = Tk. 19,619.31
Tk. 7,222.50 Profit 10.00% = Tk. 1,961.93
2.716416 Overhead 3.50% = Tk. 686.68
= Tk. 22,267.92
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,296.02
Grand total Tk. 23,563.94

Say, Tk. 23,564 .00 Per bore

31.32.8 Bore Hole depth 0 to 45m per bore 1 Tk. 23,543.18 each = Tk. 23,543.18
45 Total = Tk. 23,543.18
Tk. 7,222.50 Profit 10.00% = Tk. 2,354.32
3.2596992 Overhead 3.50% = Tk. 824.01
= Tk. 26,721.51
Add VAT with adjustment factor 1.0582 5.50% = Tk. 1,555.22
Grand total Tk. 28,276.73

Say, Tk. 28,277 .00 Per bore


Analysis of PWD SoR 2014 for Civil Works 591
Analysis of PWD SoR 2014 for Civil Works 592
Analysis of PWD SoR 2014 for Civil Works 593
Analysis of PWD SoR 2014 for Civil Works 594
Analysis of PWD SoR 2014 for Civil Works 595
Analysis of PWD SoR 2014 for Civil Works 596
Analysis of PWD SoR 2014 for Civil Works 597
Analysis of PWD SoR 2014 for Civil Works 598
Analysis of PWD SoR 2014 for Civil Works 599
Analysis of PWD SoR 2014 for Civil Works 600
Analysis of PWD SoR 2014 for Civil Works 601
Analysis of PWD SoR 2014 for Civil Works 602
Analysis of PWD SoR 2014 for Civil Works 603
Analysis of PWD SoR 2014 for Civil Works 604
Analysis of PWD SoR 2014 for Civil Works 605
Analysis of PWD SoR 2014 for Civil Works 606
Analysis of PWD SoR 2014 for Civil Works 607
Analysis of PWD SoR 2014 for Civil Works 608
Analysis of PWD SoR 2014 for Civil Works 609
Analysis of PWD SoR 2014 for Civil Works 610
Analysis of PWD SoR 2014 for Civil Works 611
Analysis of PWD SoR 2014 for Civil Works 612
Analysis of PWD SoR 2014 for Civil Works 613
Analysis of PWD SoR 2014 for Civil Works 614
Analysis of PWD SoR 2014 for Civil Works 615
Analysis of PWD SoR 2014 for Civil Works 616
Analysis of PWD SoR 2014 for Civil Works 617
Analysis of PWD SoR 2014 for Civil Works 618
Analysis of PWD SoR 2014 for Civil Works 619
Analysis of PWD SoR 2014 for Civil Works 620
Analysis of PWD SoR 2014 for Civil Works 621
Analysis of PWD SoR 2014 for Civil Works 622
Analysis of PWD SoR 2014 for Civil Works 623
Analysis of PWD SoR 2014 for Civil Works 624
Analysis of PWD SoR 2014 for Civil Works 625
Analysis of PWD SoR 2014 for Civil Works 626
Analysis of PWD SoR 2014 for Civil Works 627
Analysis of PWD SoR 2014 for Civil Works 628
Analysis of PWD SoR 2014 for Civil Works 629
Analysis of PWD SoR 2014 for Civil Works 630
Analysis of PWD SoR 2014 for Civil Works 631
Analysis of PWD SoR 2014 for Civil Works 632
Analysis of PWD SoR 2014 for Civil Works 633
Analysis of PWD SoR 2014 for Civil Works 634
Analysis of PWD SoR 2014 for Civil Works 635
Analysis of PWD SoR 2014 for Civil Works 636
Analysis of PWD SoR 2014 for Civil Works 637
Analysis of PWD SoR 2014 for Civil Works 638
Analysis of PWD SoR 2014 for Civil Works 639
Analysis of PWD SoR 2014 for Civil Works 640
Analysis of PWD SoR 2014 for Civil Works 641
Analysis of PWD SoR 2014 for Civil Works 642
Analysis of PWD SoR 2014 for Civil Works 643
Analysis of PWD SoR 2014 for Civil Works 644
Analysis of PWD SoR 2014 for Civil Works 645
Analysis of PWD SoR 2014 for Civil Works 646
Analysis of PWD SoR 2014 for Civil Works 647
Analysis of PWD SoR 2014 for Civil Works 648
Analysis of PWD SoR 2014 for Civil Works 649
Analysis of PWD SoR 2014 for Civil Works 650
Analysis of PWD SoR 2014 for Civil Works 651
Analysis of PWD SoR 2014 for Civil Works 652
Analysis of PWD SoR 2014 for Civil Works 653
Analysis of PWD SoR 2014 for Civil Works 654
Analysis of PWD SoR 2014 for Civil Works 655
Analysis of PWD SoR 2014 for Civil Works 656
Analysis of PWD SoR 2014 for Civil Works 657
Analysis of PWD SoR 2014 for Civil Works 658
Analysis of PWD SoR 2014 for Civil Works 659
Analysis of PWD SoR 2014 for Civil Works 660
Analysis of PWD SoR 2014 for Civil Works 661
Analysis of PWD SoR 2014 for Civil Works 662
Analysis of PWD SoR 2014 for Civil Works 663
Analysis of PWD SoR 2014 for Civil Works 664
Analysis of PWD SoR 2014 for Civil Works 665
Analysis of PWD SoR 2014 for Civil Works 666
Analysis of PWD SoR 2014 for Civil Works 667
Analysis of PWD SoR 2014 for Civil Works 668
Analysis of PWD SoR 2014 for Civil Works 669
Analysis of PWD SoR 2014 for Civil Works 670
Analysis of PWD SoR 2014 for Civil Works 671
Analysis of PWD SoR 2014 for Civil Works 672
Analysis of PWD SoR 2014 for Civil Works 673
Analysis of PWD SoR 2014 for Civil Works 674
Analysis of PWD SoR 2014 for Civil Works 675
Analysis of PWD SoR 2014 for Civil Works 676
Analysis of PWD SoR 2014 for Civil Works 677
Analysis of PWD SoR 2014 for Civil Works 678
Analysis of PWD SoR 2014 for Civil Works 679
Analysis of PWD SoR 2014 for Civil Works 680
Analysis of PWD SoR 2014 for Civil Works 681
Analysis of PWD SoR 2014 for Civil Works 682
Analysis of PWD SoR 2014 for Civil Works 683
Analysis of PWD SoR 2014 for Civil Works 684
Analysis of PWD SoR 2014 for Civil Works 685
Analysis of PWD SoR 2014 for Civil Works 686
Analysis of PWD SoR 2014 for Civil Works 687
Analysis of PWD SoR 2014 for Civil Works 688
Analysis of PWD SoR 2014 for Civil Works 689
Analysis of PWD SoR 2014 for Civil Works 690
Analysis of PWD SoR 2014 for Civil Works 691
Analysis of PWD SoR 2014 for Civil Works 692
Analysis of PWD SoR 2014 for Civil Works 693
Analysis of PWD SoR 2014 for Civil Works 694
Analysis of PWD SoR 2014 for Civil Works 695
Analysis of PWD SoR 2014 for Civil Works 696
Analysis of PWD SoR 2014 for Civil Works 697
Analysis of PWD SoR 2014 for Civil Works 698
Analysis of PWD SoR 2014 for Civil Works 699
Analysis of PWD SoR 2014 for Civil Works 700
Analysis of PWD SoR 2014 for Civil Works 701
Analysis of PWD SoR 2014 for Civil Works 702
Analysis of PWD SoR 2014 for Civil Works 703
Analysis of PWD SoR 2014 for Civil Works 704
Analysis of PWD SoR 2014 for Civil Works 705
Analysis of PWD SoR 2014 for Civil Works 706
Analysis of PWD SoR 2014 for Civil Works 707
Analysis of PWD SoR 2014 for Civil Works 708
Analysis of PWD SoR 2014 for Civil Works 709
Analysis of PWD SoR 2014 for Civil Works 710
Analysis of PWD SoR 2014 for Civil Works 711
Analysis of PWD SoR 2014 for Civil Works 712
Analysis of PWD SoR 2014 for Civil Works 713
Analysis of PWD SoR 2014 for Civil Works 714
Analysis of PWD SoR 2014 for Civil Works 715
Analysis of PWD SoR 2014 for Civil Works 716
Analysis of PWD SoR 2014 for Civil Works 717
Analysis of PWD SoR 2014 for Civil Works 718
Analysis of PWD SoR 2014 for Civil Works 719
Analysis of PWD SoR 2014 for Civil Works 720
Analysis of PWD SoR 2014 for Civil Works 721
Analysis of PWD SoR 2014 for Civil Works 722
Analysis of PWD SoR 2014 for Civil Works 723
Analysis of PWD SoR 2014 for Civil Works 724
Analysis of PWD SoR 2014 for Civil Works 725
Analysis of PWD SoR 2014 for Civil Works 726
Analysis of PWD SoR 2014 for Civil Works 727
Analysis of PWD SoR 2014 for Civil Works 728
Analysis of PWD SoR 2014 for Civil Works 729
Analysis of PWD SoR 2014 for Civil Works 730
Analysis of PWD SoR 2014 for Civil Works 731
Analysis of PWD SoR 2014 for Civil Works 732
Analysis of PWD SoR 2014 for Civil Works 733
Analysis of PWD SoR 2014 for Civil Works 734
Analysis of PWD SoR 2014 for Civil Works 735
Analysis of PWD SoR 2014 for Civil Works 736
Analysis of PWD SoR 2014 for Civil Works 737
Analysis of PWD SoR 2014 for Civil Works 738
Analysis of PWD SoR 2014 for Civil Works 739

Add 09.21.1 09.21.2 09.21.3 after09.20.3


14.05.14
Analysis of PWD SoR 2014 for Civil Works 740
Analysis of PWD SoR 2014 for Civil Works 741
Analysis of PWD SoR 2014 for Civil Works 742
Analysis of PWD SoR 2014 for Civil Works 743

in/c 10% intelectual charges


Y=187754e-.194x x, nos pile Y -0.194*x e^(-.194*x)
1 154645.1 -0.194 0.8236579
2 127374.6 -0.388 0.67841234
3 104913.1 -0.582 0.55877969
4 86412.52 -0.776 0.46024331
5 71174.36 -0.97 0.37908304
Analysis of PWD SoR 2014 for Civil Works 744

6 58623.32 -1.164 0.31223474


7 48285.56 -1.358 0.25717461
8 39770.78 -1.552 0.2118239
9 32757.52 -1.746 0.17447043
10 26980.99 -1.94 0.14370395
11 22223.11 -2.134 0.11836289
12 18304.24 -2.328 0.09749053
13 15076.43 -2.522 0.08029885
14 12417.82 -2.716 0.06613878
15 10228.04 -2.91 0.05447573
16 8424.403 -3.104 0.04486937
17 6938.826 -3.298 0.03695701
18 5715.219 -3.492 0.03043993
19 4707.385 -3.686 0.02507209
20 3877.275 -3.88 0.02065083
21 3193.548 -4.074 0.01700922
22 2630.391 -4.268 0.01400977
Analysis of PWD SoR 2014 for Civil Works 745
Analysis of PWD SoR 2014 for Civil Works 746
Analysis of PWD SoR 2014 for Civil Works 747
Analysis of PWD SoR 2014 for Civil Works 748
Analysis of PWD SoR 2014 for Civil Works 749
Analysis of PWD SoR 2014 for Civil Works 750
Analysis of PWD SoR 2014 for Civil Works 751
Analysis of PWD SoR 2014 for Civil Works 752
Analysis of PWD SoR 2014 for Civil Works 753
Analysis of PWD SoR 2014 for Civil Works 754
Analysis of PWD SoR 2014 for Civil Works 755
Analysis of PWD SoR 2014 for Civil Works 756
Analysis of PWD SoR 2014 for Civil Works 757
Analysis of PWD SoR 2014 for Civil Works 758
Analysis of PWD SoR 2014 for Civil Works 759
Analysis of PWD SoR 2014 for Civil Works 760
Analysis of PWD SoR 2014 for Civil Works 761
Analysis of PWD SoR 2014 for Civil Works 762
Analysis of PWD SoR 2014 for Civil Works 763
Analysis of PWD SoR 2014 for Civil Works 764
Analysis of PWD SoR 2014 for Civil Works 765
Analysis of PWD SoR 2014 for Civil Works 766
Analysis of PWD SoR 2014 for Civil Works 767
Analysis of PWD SoR 2014 for Civil Works 768
Analysis of PWD SoR 2014 for Civil Works 769
Analysis of PWD SoR 2014 for Civil Works 770
Analysis of PWD SoR 2014 for Civil Works 771
Analysis of PWD SoR 2014 for Civil Works 772
Analysis of PWD SoR 2014 for Civil Works 773
Analysis of PWD SoR 2014 for Civil Works 774
Analysis of PWD SoR 2014 for Civil Works 775
Analysis of PWD SoR 2014 for Civil Works 776
Analysis of PWD SoR 2014 for Civil Works 777
Analysis of PWD SoR 2014 for Civil Works 778
Analysis of PWD SoR 2014 for Civil Works 779
Analysis of PWD SoR 2014 for Civil Works 780
Analysis of PWD SoR 2014 for Civil Works 781
Analysis of PWD SoR 2014 for Civil Works 782
Analysis of PWD SoR 2014 for Civil Works 783
Analysis of PWD SoR 2014 for Civil Works 784
Analysis of PWD SoR 2014 for Civil Works 785
Analysis of PWD SoR 2014 for Civil Works 786
Analysis of PWD SoR 2014 for Civil Works 787
Analysis of PWD SoR 2014 for Civil Works 788
Analysis of PWD SoR 2014 for Civil Works 789
Analysis of PWD SoR 2014 for Civil Works 790
Analysis of PWD SoR 2014 for Civil Works 791
Analysis of PWD SoR 2014 for Civil Works 792
Analysis of PWD SoR 2014 for Civil Works 793
Analysis of PWD SoR 2014 for Civil Works 794
Analysis of PWD SoR 2014 for Civil Works 795
Analysis of PWD SoR 2014 for Civil Works 796
Analysis of PWD SoR 2014 for Civil Works 797
Analysis of PWD SoR 2014 for Civil Works 798
Analysis of PWD SoR 2014 for Civil Works 799
Analysis of PWD SoR 2014 for Civil Works 800
Analysis of PWD SoR 2014 for Civil Works 801
Analysis of PWD SoR 2014 for Civil Works 802
Analysis of PWD SoR 2014 for Civil Works 803
Analysis of PWD SoR 2014 for Civil Works 804
Analysis of PWD SoR 2014 for Civil Works 805
Analysis of PWD SoR 2014 for Civil Works 806
Analysis of PWD SoR 2014 for Civil Works 807
Analysis of PWD SoR 2014 for Civil Works 808
Analysis of PWD SoR 2014 for Civil Works 809
Analysis of PWD SoR 2014 for Civil Works 810
Analysis of PWD SoR 2014 for Civil Works 811
Analysis of PWD SoR 2014 for Civil Works 812
Analysis of PWD SoR 2014 for Civil Works 813
Analysis of PWD SoR 2014 for Civil Works 814
Analysis of PWD SoR 2014 for Civil Works 815
Analysis of PWD SoR 2014 for Civil Works 816
Analysis of PWD SoR 2014 for Civil Works 817
Analysis of PWD SoR 2014 for Civil Works 818
Analysis of PWD SoR 2014 for Civil Works 819
Analysis of PWD SoR 2014 for Civil Works 820
Analysis of PWD SoR 2014 for Civil Works 821
Analysis of PWD SoR 2014 for Civil Works 822
Analysis of PWD SoR 2014 for Civil Works 823
Analysis of PWD SoR 2014 for Civil Works 824
Analysis of PWD SoR 2014 for Civil Works 825
Analysis of PWD SoR 2014 for Civil Works 826
Analysis of PWD SoR 2014 for Civil Works 827
Analysis of PWD SoR 2014 for Civil Works 828
Analysis of PWD SoR 2014 for Civil Works 829
Analysis of PWD SoR 2014 for Civil Works 830
Analysis of PWD SoR 2014 for Civil Works 831
Analysis of PWD SoR 2014 for Civil Works 832
Analysis of PWD SoR 2014 for Civil Works 833
Analysis of PWD SoR 2014 for Civil Works 834
Analysis of PWD SoR 2014 for Civil Works 835
Analysis of PWD SoR 2014 for Civil Works 836
Analysis of PWD SoR 2014 for Civil Works 837
Analysis of PWD SoR 2014 for Civil Works 838
Analysis of PWD SoR 2014 for Civil Works 839
Analysis of PWD SoR 2014 for Civil Works 840
Analysis of PWD SoR 2014 for Civil Works 841
Analysis of PWD SoR 2014 for Civil Works 842
Analysis of PWD SoR 2014 for Civil Works 843
Analysis of PWD SoR 2014 for Civil Works 844
Analysis of PWD SoR 2014 for Civil Works 845
Analysis of PWD SoR 2014 for Civil Works 846
Analysis of PWD SoR 2014 for Civil Works 847
Analysis of PWD SoR 2014 for Civil Works 848
Analysis of PWD SoR 2014 for Civil Works 849
Analysis of PWD SoR 2014 for Civil Works 850
Analysis of PWD SoR 2014 for Civil Works 851
Analysis of PWD SoR 2014 for Civil Works 852
Analysis of PWD SoR 2014 for Civil Works 853
Analysis of PWD SoR 2014 for Civil Works 854
Analysis of PWD SoR 2014 for Civil Works 855
Analysis of PWD SoR 2014 for Civil Works 856
Analysis of PWD SoR 2014 for Civil Works 857
Analysis of PWD SoR 2014 for Civil Works 858
Analysis of PWD SoR 2014 for Civil Works 859
Analysis of PWD SoR 2014 for Civil Works 860
Analysis of PWD SoR 2014 for Civil Works 861
Analysis of PWD SoR 2014 for Civil Works 862
Analysis of PWD SoR 2014 for Civil Works 863
Analysis of PWD SoR 2014 for Civil Works 864
Analysis of PWD SoR 2014 for Civil Works 865
Analysis of PWD SoR 2014 for Civil Works 866
Analysis of PWD SoR 2014 for Civil Works 867
Analysis of PWD SoR 2014 for Civil Works 868
Analysis of PWD SoR 2014 for Civil Works 869
Analysis of PWD SoR 2014 for Civil Works 870
Analysis of PWD SoR 2014 for Civil Works 871
Analysis of PWD SoR 2014 for Civil Works 872
Analysis of PWD SoR 2014 for Civil Works 873
Analysis of PWD SoR 2014 for Civil Works 874
Analysis of PWD SoR 2014 for Civil Works 875
Analysis of PWD SoR 2014 for Civil Works 876
Analysis of PWD SoR 2014 for Civil Works 877
Analysis of PWD SoR 2014 for Civil Works 878
Analysis of PWD SoR 2014 for Civil Works 879
Analysis of PWD SoR 2014 for Civil Works 880
Analysis of PWD SoR 2014 for Civil Works 881
Analysis of PWD SoR 2014 for Civil Works 882
Analysis of PWD SoR 2014 for Civil Works 883
Analysis of PWD SoR 2014 for Civil Works 884
Analysis of PWD SoR 2014 for Civil Works 885
Analysis of PWD SoR 2014 for Civil Works 886
Analysis of PWD SoR 2014 for Civil Works 887
Analysis of PWD SoR 2014 for Civil Works 888
Analysis of PWD SoR 2014 for Civil Works 889
Analysis of PWD SoR 2014 for Civil Works 890
Analysis of PWD SoR 2014 for Civil Works 891
Analysis of PWD SoR 2014 for Civil Works 892
Analysis of PWD SoR 2014 for Civil Works 893
Analysis of PWD SoR 2014 for Civil Works 894
Analysis of PWD SoR 2014 for Civil Works 895
Analysis of PWD SoR 2014 for Civil Works 896
Analysis of PWD SoR 2014 for Civil Works 897
Analysis of PWD SoR 2014 for Civil Works 898
Analysis of PWD SoR 2014 for Civil Works 899
Analysis of PWD SoR 2014 for Civil Works 900
Analysis of PWD SoR 2014 for Civil Works 901
Analysis of PWD SoR 2014 for Civil Works 902
Analysis of PWD SoR 2014 for Civil Works 903
Analysis of PWD SoR 2014 for Civil Works 904
Analysis of PWD SoR 2014 for Civil Works 905
Analysis of PWD SoR 2014 for Civil Works 906
Analysis of PWD SoR 2014 for Civil Works 907
Analysis of PWD SoR 2014 for Civil Works 908
Analysis of PWD SoR 2014 for Civil Works 909
Analysis of PWD SoR 2014 for Civil Works 910
Analysis of PWD SoR 2014 for Civil Works 911
Analysis of PWD SoR 2014 for Civil Works 912
Analysis of PWD SoR 2014 for Civil Works 913
Analysis of PWD SoR 2014 for Civil Works 914
Analysis of PWD SoR 2014 for Civil Works 915
Analysis of PWD SoR 2014 for Civil Works 916
Analysis of PWD SoR 2014 for Civil Works 917
Analysis of PWD SoR 2014 for Civil Works 918
Analysis of PWD SoR 2014 for Civil Works 919
Analysis of PWD SoR 2014 for Civil Works 920
Analysis of PWD SoR 2014 for Civil Works 921
Analysis of PWD SoR 2014 for Civil Works 922
Analysis of PWD SoR 2014 for Civil Works 923
Analysis of PWD SoR 2014 for Civil Works 924
Analysis of PWD SoR 2014 for Civil Works 925
Analysis of PWD SoR 2014 for Civil Works 926
Analysis of PWD SoR 2014 for Civil Works 927
Analysis of PWD SoR 2014 for Civil Works 928
Analysis of PWD SoR 2014 for Civil Works 929
Analysis of PWD SoR 2014 for Civil Works 930
Analysis of PWD SoR 2014 for Civil Works 931
Analysis of PWD SoR 2014 for Civil Works 932
Analysis of PWD SoR 2014 for Civil Works 933
Analysis of PWD SoR 2014 for Civil Works 934
Analysis of PWD SoR 2014 for Civil Works 935
Analysis of PWD SoR 2014 for Civil Works 936
Analysis of PWD SoR 2014 for Civil Works 937
Analysis of PWD SoR 2014 for Civil Works 938
Analysis of PWD SoR 2014 for Civil Works 939
Analysis of PWD SoR 2014 for Civil Works 940
Analysis of PWD SoR 2014 for Civil Works 941
Analysis of PWD SoR 2014 for Civil Works 942
Analysis of PWD SoR 2014 for Civil Works 943
Analysis of PWD SoR 2014 for Civil Works 944
Analysis of PWD SoR 2014 for Civil Works 945
Analysis of PWD SoR 2014 for Civil Works 946
Analysis of PWD SoR 2014 for Civil Works 947
Analysis of PWD SoR 2014 for Civil Works 948
Analysis of PWD SoR 2014 for Civil Works 949
Analysis of PWD SoR 2014 for Civil Works 950
Analysis of PWD SoR 2014 for Civil Works 951
Analysis of PWD SoR 2014 for Civil Works 952
Analysis of PWD SoR 2014 for Civil Works 953
Analysis of PWD SoR 2014 for Civil Works 954
Analysis of PWD SoR 2014 for Civil Works 955
Analysis of PWD SoR 2014 for Civil Works 956
Analysis of PWD SoR 2014 for Civil Works 957
Analysis of PWD SoR 2014 for Civil Works 958
Analysis of PWD SoR 2014 for Civil Works 959
Analysis of PWD SoR 2014 for Civil Works 960
Analysis of PWD SoR 2014 for Civil Works 961
Analysis of PWD SoR 2014 for Civil Works 962
Analysis of PWD SoR 2014 for Civil Works 963
Analysis of PWD SoR 2014 for Civil Works 964
Analysis of PWD SoR 2014 for Civil Works 965
Analysis of PWD SoR 2014 for Civil Works 966
Analysis of PWD SoR 2014 for Civil Works 967
Analysis of PWD SoR 2014 for Civil Works 968
Analysis of PWD SoR 2014 for Civil Works 969
Analysis of PWD SoR 2014 for Civil Works 970
Analysis of PWD SoR 2014 for Civil Works 971
Analysis of PWD SoR 2014 for Civil Works 972
Analysis of PWD SoR 2014 for Civil Works 973
Analysis of PWD SoR 2014 for Civil Works 974
Analysis of PWD SoR 2014 for Civil Works 975
Analysis of PWD SoR 2014 for Civil Works 976
Analysis of PWD SoR 2014 for Civil Works 977
Analysis of PWD SoR 2014 for Civil Works 978
Analysis of PWD SoR 2014 for Civil Works 979
Analysis of PWD SoR 2014 for Civil Works 980
Analysis of PWD SoR 2014 for Civil Works 981
Analysis of PWD SoR 2014 for Civil Works 982
Analysis of PWD SoR 2014 for Civil Works 983
Analysis of PWD SoR 2014 for Civil Works 984
Analysis of PWD SoR 2014 for Civil Works 985
Analysis of PWD SoR 2014 for Civil Works 986
Analysis of PWD SoR 2014 for Civil Works 987
Analysis of PWD SoR 2014 for Civil Works 988
Analysis of PWD SoR 2014 for Civil Works 989
Analysis of PWD SoR 2014 for Civil Works 990
Analysis of PWD SoR 2014 for Civil Works 991
Analysis of PWD SoR 2014 for Civil Works 992
Analysis of PWD SoR 2014 for Civil Works 993
Analysis of PWD SoR 2014 for Civil Works 994
Analysis of PWD SoR 2014 for Civil Works 995
Analysis of PWD SoR 2014 for Civil Works 996
Analysis of PWD SoR 2014 for Civil Works 997
Analysis of PWD SoR 2014 for Civil Works 998
Analysis of PWD SoR 2014 for Civil Works 999
Analysis of PWD SoR 2014 for Civil Works 1000
Analysis of PWD SoR 2014 for Civil Works 1001
Analysis of PWD SoR 2014 for Civil Works 1002
Analysis of PWD SoR 2014 for Civil Works 1003
Analysis of PWD SoR 2014 for Civil Works 1004
Analysis of PWD SoR 2014 for Civil Works 1005
Analysis of PWD SoR 2014 for Civil Works 1006
Analysis of PWD SoR 2014 for Civil Works 1007
Analysis of PWD SoR 2014 for Civil Works 1008
Analysis of PWD SoR 2014 for Civil Works 1009
Analysis of PWD SoR 2014 for Civil Works 1010
Analysis of PWD SoR 2014 for Civil Works 1011
Analysis of PWD SoR 2014 for Civil Works 1012
Analysis of PWD SoR 2014 for Civil Works 1013
Analysis of PWD SoR 2014 for Civil Works 1014
Analysis of PWD SoR 2014 for Civil Works 1015
Analysis of PWD SoR 2014 for Civil Works 1016
Analysis of PWD SoR 2014 for Civil Works 1017
Analysis of PWD SoR 2014 for Civil Works 1018
Analysis of PWD SoR 2014 for Civil Works 1019
Analysis of PWD SoR 2014 for Civil Works 1020
Analysis of PWD SoR 2014 for Civil Works 1021
Analysis of PWD SoR 2014 for Civil Works 1022
Analysis of PWD SoR 2014 for Civil Works 1023
Analysis of PWD SoR 2014 for Civil Works 1024
Analysis of PWD SoR 2014 for Civil Works 1025
Analysis of PWD SoR 2014 for Civil Works 1026
Analysis of PWD SoR 2014 for Civil Works 1027
Analysis of PWD SoR 2014 for Civil Works 1028
Analysis of PWD SoR 2014 for Civil Works 1029
Analysis of PWD SoR 2014 for Civil Works 1030
Analysis of PWD SoR 2014 for Civil Works 1031
Analysis of PWD SoR 2014 for Civil Works 1032
Analysis of PWD SoR 2014 for Civil Works 1033
Analysis of PWD SoR 2014 for Civil Works 1034
Analysis of PWD SoR 2014 for Civil Works 1035
Analysis of PWD SoR 2014 for Civil Works 1036
Analysis of PWD SoR 2014 for Civil Works 1037
Analysis of PWD SoR 2014 for Civil Works 1038
Analysis of PWD SoR 2014 for Civil Works 1039
Analysis of PWD SoR 2014 for Civil Works 1040
Analysis of PWD SoR 2014 for Civil Works 1041
Analysis of PWD SoR 2014 for Civil Works 1042
Analysis of PWD SoR 2014 for Civil Works 1043
Analysis of PWD SoR 2014 for Civil Works 1044
Analysis of PWD SoR 2014 for Civil Works 1045
Analysis of PWD SoR 2014 for Civil Works 1046
Analysis of PWD SoR 2014 for Civil Works 1047
Analysis of PWD SoR 2014 for Civil Works 1048
Analysis of PWD SoR 2014 for Civil Works 1049
Analysis of PWD SoR 2014 for Civil Works 1050
Analysis of PWD SoR 2014 for Civil Works 1051
Analysis of PWD SoR 2014 for Civil Works 1052
Analysis of PWD SoR 2014 for Civil Works 1053
Analysis of PWD SoR 2014 for Civil Works 1054
Analysis of PWD SoR 2014 for Civil Works 1055
Analysis of PWD SoR 2014 for Civil Works 1056
Analysis of PWD SoR 2014 for Civil Works 1057
Analysis of PWD SoR 2014 for Civil Works 1058
Analysis of PWD SoR 2014 for Civil Works 1059
Analysis of PWD SoR 2014 for Civil Works 1060
Analysis of PWD SoR 2014 for Civil Works 1061
Analysis of PWD SoR 2014 for Civil Works 1062
Analysis of PWD SoR 2014 for Civil Works 1063
Analysis of PWD SoR 2014 for Civil Works 1064
Analysis of PWD SoR 2014 for Civil Works 1065
Analysis of PWD SoR 2014 for Civil Works 1066
Analysis of PWD SoR 2014 for Civil Works 1067
Analysis of PWD SoR 2014 for Civil Works 1068
Analysis of PWD SoR 2014 for Civil Works 1069
Analysis of PWD SoR 2014 for Civil Works 1070
Analysis of PWD SoR 2014 for Civil Works 1071
Analysis of PWD SoR 2014 for Civil Works 1072
Analysis of PWD SoR 2014 for Civil Works 1073
Analysis of PWD SoR 2014 for Civil Works 1074
Analysis of PWD SoR 2014 for Civil Works 1075
Analysis of PWD SoR 2014 for Civil Works 1076
Analysis of PWD SoR 2014 for Civil Works 1077
Analysis of PWD SoR 2014 for Civil Works 1078
Analysis of PWD SoR 2014 for Civil Works 1079
Analysis of PWD SoR 2014 for Civil Works 1080
Analysis of PWD SoR 2014 for Civil Works 1081
Analysis of PWD SoR 2014 for Civil Works 1082
Analysis of PWD SoR 2014 for Civil Works 1083
Analysis of PWD SoR 2014 for Civil Works 1084
Analysis of PWD SoR 2014 for Civil Works 1085
Analysis of PWD SoR 2014 for Civil Works 1086
Analysis of PWD SoR 2014 for Civil Works 1087
Analysis of PWD SoR 2014 for Civil Works 1088
Analysis of PWD SoR 2014 for Civil Works 1089
Analysis of PWD SoR 2014 for Civil Works 1090
Analysis of PWD SoR 2014 for Civil Works 1091
Analysis of PWD SoR 2014 for Civil Works 1092
Analysis of PWD SoR 2014 for Civil Works 1093
Analysis of PWD SoR 2014 for Civil Works 1094
Analysis of PWD SoR 2014 for Civil Works 1095
Analysis of PWD SoR 2014 for Civil Works 1096
Analysis of PWD SoR 2014 for Civil Works 1097
Analysis of PWD SoR 2014 for Civil Works 1098
Analysis of PWD SoR 2014 for Civil Works 1099
Analysis of PWD SoR 2014 for Civil Works 1100
Analysis of PWD SoR 2014 for Civil Works 1101
Analysis of PWD SoR 2014 for Civil Works 1102
Analysis of PWD SoR 2014 for Civil Works 1103
Analysis of PWD SoR 2014 for Civil Works 1104
Analysis of PWD SoR 2014 for Civil Works 1105
Analysis of PWD SoR 2014 for Civil Works 1106
Analysis of PWD SoR 2014 for Civil Works 1107
Analysis of PWD SoR 2014 for Civil Works 1108
Analysis of PWD SoR 2014 for Civil Works 1109
Analysis of PWD SoR 2014 for Civil Works 1110
Analysis of PWD SoR 2014 for Civil Works 1111
Analysis of PWD SoR 2014 for Civil Works 1112
Analysis of PWD SoR 2014 for Civil Works 1113
Analysis of PWD SoR 2014 for Civil Works 1114
Analysis of PWD SoR 2014 for Civil Works 1115
Analysis of PWD SoR 2014 for Civil Works 1116
Analysis of PWD SoR 2014 for Civil Works 1117
Analysis of PWD SoR 2014 for Civil Works 1118
Analysis of PWD SoR 2014 for Civil Works 1119
Analysis of PWD SoR 2014 for Civil Works 1120
Analysis of PWD SoR 2014 for Civil Works 1121
Analysis of PWD SoR 2014 for Civil Works 1122
Analysis of PWD SoR 2014 for Civil Works 1123
Analysis of PWD SoR 2014 for Civil Works 1124
Analysis of PWD SoR 2014 for Civil Works 1125
Analysis of PWD SoR 2014 for Civil Works 1126
Analysis of PWD SoR 2014 for Civil Works 1127
Analysis of PWD SoR 2014 for Civil Works 1128
Analysis of PWD SoR 2014 for Civil Works 1129
Analysis of PWD SoR 2014 for Civil Works 1130
Analysis of PWD SoR 2014 for Civil Works 1131
Analysis of PWD SoR 2014 for Civil Works 1132
Analysis of PWD SoR 2014 for Civil Works 1133
Analysis of PWD SoR 2014 for Civil Works 1134
Analysis of PWD SoR 2014 for Civil Works 1135
Analysis of PWD SoR 2014 for Civil Works 1136
Analysis of PWD SoR 2014 for Civil Works 1137
Analysis of PWD SoR 2014 for Civil Works 1138
Analysis of PWD SoR 2014 for Civil Works 1139
Analysis of PWD SoR 2014 for Civil Works 1140
Analysis of PWD SoR 2014 for Civil Works 1141
Analysis of PWD SoR 2014 for Civil Works 1142
Analysis of PWD SoR 2014 for Civil Works 1143
Analysis of PWD SoR 2014 for Civil Works 1144
Analysis of PWD SoR 2014 for Civil Works 1145
Analysis of PWD SoR 2014 for Civil Works 1146
Analysis of PWD SoR 2014 for Civil Works 1147
Analysis of PWD SoR 2014 for Civil Works 1148
Analysis of PWD SoR 2014 for Civil Works 1149
Analysis of PWD SoR 2014 for Civil Works 1150
Analysis of PWD SoR 2014 for Civil Works 1151
Analysis of PWD SoR 2014 for Civil Works 1152
Analysis of PWD SoR 2014 for Civil Works 1153
Analysis of PWD SoR 2014 for Civil Works 1154
Analysis of PWD SoR 2014 for Civil Works 1155
Analysis of PWD SoR 2014 for Civil Works 1156
Analysis of PWD SoR 2014 for Civil Works 1157
Analysis of PWD SoR 2014 for Civil Works 1158
Analysis of PWD SoR 2014 for Civil Works 1159
Analysis of PWD SoR 2014 for Civil Works 1160
Analysis of PWD SoR 2014 for Civil Works 1161
Analysis of PWD SoR 2014 for Civil Works 1162
Analysis of PWD SoR 2014 for Civil Works 1163
Analysis of PWD SoR 2014 for Civil Works 1164
Analysis of PWD SoR 2014 for Civil Works 1165
Analysis of PWD SoR 2014 for Civil Works 1166
Analysis of PWD SoR 2014 for Civil Works 1167
Analysis of PWD SoR 2014 for Civil Works 1168
Analysis of PWD SoR 2014 for Civil Works 1169
Analysis of PWD SoR 2014 for Civil Works 1170
Analysis of PWD SoR 2014 for Civil Works 1171
Analysis of PWD SoR 2014 for Civil Works 1172
Analysis of PWD SoR 2014 for Civil Works 1173
Analysis of PWD SoR 2014 for Civil Works 1174
Analysis of PWD SoR 2014 for Civil Works 1175
Analysis of PWD SoR 2014 for Civil Works 1176
Analysis of PWD SoR 2014 for Civil Works 1177
Analysis of PWD SoR 2014 for Civil Works 1178
Analysis of PWD SoR 2014 for Civil Works 1179
Analysis of PWD SoR 2014 for Civil Works 1180
Analysis of PWD SoR 2014 for Civil Works 1181
Analysis of PWD SoR 2014 for Civil Works 1182
Analysis of PWD SoR 2014 for Civil Works 1183
Analysis of PWD SoR 2014 for Civil Works 1184
Analysis of PWD SoR 2014 for Civil Works 1185
Analysis of PWD SoR 2014 for Civil Works 1186
Analysis of PWD SoR 2014 for Civil Works 1187
Analysis of PWD SoR 2014 for Civil Works 1188
Analysis of PWD SoR 2014 for Civil Works 1189
Analysis of PWD SoR 2014 for Civil Works 1190
Analysis of PWD SoR 2014 for Civil Works 1191
Analysis of PWD SoR 2014 for Civil Works 1192
Analysis of PWD SoR 2014 for Civil Works 1193
Analysis of PWD SoR 2014 for Civil Works 1194
Analysis of PWD SoR 2014 for Civil Works 1195
Analysis of PWD SoR 2014 for Civil Works 1196
Analysis of PWD SoR 2014 for Civil Works 1197
Analysis of PWD SoR 2014 for Civil Works 1198
Analysis of PWD SoR 2014 for Civil Works 1199
Analysis of PWD SoR 2014 for Civil Works 1200
Analysis of PWD SoR 2014 for Civil Works 1201
Analysis of PWD SoR 2014 for Civil Works 1202
Analysis of PWD SoR 2014 for Civil Works 1203
Analysis of PWD SoR 2014 for Civil Works 1204
Analysis of PWD SoR 2014 for Civil Works 1205
Analysis of PWD SoR 2014 for Civil Works 1206
Analysis of PWD SoR 2014 for Civil Works 1207
Analysis of PWD SoR 2014 for Civil Works 1208
Analysis of PWD SoR 2014 for Civil Works 1209
Analysis of PWD SoR 2014 for Civil Works 1210
Analysis of PWD SoR 2014 for Civil Works 1211
Analysis of PWD SoR 2014 for Civil Works 1212
Analysis of PWD SoR 2014 for Civil Works 1213
Analysis of PWD SoR 2014 for Civil Works 1214
Analysis of PWD SoR 2014 for Civil Works 1215
Analysis of PWD SoR 2014 for Civil Works 1216
Analysis of PWD SoR 2014 for Civil Works 1217
Analysis of PWD SoR 2014 for Civil Works 1218
Analysis of PWD SoR 2014 for Civil Works 1219
Analysis of PWD SoR 2014 for Civil Works 1220
Analysis of PWD SoR 2014 for Civil Works 1221
Analysis of PWD SoR 2014 for Civil Works 1222
Analysis of PWD SoR 2014 for Civil Works 1223
Analysis of PWD SoR 2014 for Civil Works 1224
Analysis of PWD SoR 2014 for Civil Works 1225
Analysis of PWD SoR 2014 for Civil Works 1226
Analysis of PWD SoR 2014 for Civil Works 1227
Analysis of PWD SoR 2014 for Civil Works 1228
Analysis of PWD SoR 2014 for Civil Works 1229
Analysis of PWD SoR 2014 for Civil Works 1230
Analysis of PWD SoR 2014 for Civil Works 1231
Analysis of PWD SoR 2014 for Civil Works 1232
Analysis of PWD SoR 2014 for Civil Works 1233
Analysis of PWD SoR 2014 for Civil Works 1234
Analysis of PWD SoR 2014 for Civil Works 1235
Analysis of PWD SoR 2014 for Civil Works 1236
Analysis of PWD SoR 2014 for Civil Works 1237
Analysis of PWD SoR 2014 for Civil Works 1238
Analysis of PWD SoR 2014 for Civil Works 1239
Analysis of PWD SoR 2014 for Civil Works 1240
Analysis of PWD SoR 2014 for Civil Works 1241
Analysis of PWD SoR 2014 for Civil Works 1242
Analysis of PWD SoR 2014 for Civil Works 1243
Analysis of PWD SoR 2014 for Civil Works 1244
Analysis of PWD SoR 2014 for Civil Works 1245
Analysis of PWD SoR 2014 for Civil Works 1246
Analysis of PWD SoR 2014 for Civil Works 1247
Analysis of PWD SoR 2014 for Civil Works 1248
Analysis of PWD SoR 2014 for Civil Works 1249
Analysis of PWD SoR 2014 for Civil Works 1250
Analysis of PWD SoR 2014 for Civil Works 1251
Analysis of PWD SoR 2014 for Civil Works 1252
Analysis of PWD SoR 2014 for Civil Works 1253
Analysis of PWD SoR 2014 for Civil Works 1254
Analysis of PWD SoR 2014 for Civil Works 1255
Analysis of PWD SoR 2014 for Civil Works 1256
Analysis of PWD SoR 2014 for Civil Works 1257
Analysis of PWD SoR 2014 for Civil Works 1258
Analysis of PWD SoR 2014 for Civil Works 1259
Analysis of PWD SoR 2014 for Civil Works 1260
Analysis of PWD SoR 2014 for Civil Works 1261
Analysis of PWD SoR 2014 for Civil Works 1262
Analysis of PWD SoR 2014 for Civil Works 1263
Analysis of PWD SoR 2014 for Civil Works 1264
Analysis of PWD SoR 2014 for Civil Works 1265
Analysis of PWD SoR 2014 for Civil Works 1266
Analysis of PWD SoR 2014 for Civil Works 1267
Analysis of PWD SoR 2014 for Civil Works 1268
Analysis of PWD SoR 2014 for Civil Works 1269
Analysis of PWD SoR 2014 for Civil Works 1270
Analysis of PWD SoR 2014 for Civil Works 1271
Analysis of PWD SoR 2014 for Civil Works 1272
Analysis of PWD SoR 2014 for Civil Works 1273
Analysis of PWD SoR 2014 for Civil Works 1274
Analysis of PWD SoR 2014 for Civil Works 1275
Analysis of PWD SoR 2014 for Civil Works 1276
Analysis of PWD SoR 2014 for Civil Works 1277
Analysis of PWD SoR 2014 for Civil Works 1278
Analysis of PWD SoR 2014 for Civil Works 1279

in/c 10% intelectual charges


105%
162377 162377
133743 148060
110159 135426
90733 124253
74733 114349
Analysis of PWD SoR 2014 for Civil Works 1280

61554 105550
50700 97714
41759 90720
34395 84461
28330 78848
23334 73802
19219 69253
15830 65144
13039 61422
10739 58043
8846 54968
7286 52163
6001 49599
4943 47248
4071 45090
3353 43102
2762 41268
Analysis of PWD SoR 2014 for Civil Works 1281
Analysis of PWD SoR 2014 for Civil Works 1282
Analysis of PWD SoR 2014 for Civil Works 1283
Analysis of PWD SoR 2014 for Civil Works 1284
Analysis of PWD SoR 2014 for Civil Works 1285
Analysis of PWD SoR 2014 for Civil Works 1286
Analysis of PWD SoR 2014 for Civil Works 1287
Analysis of PWD SoR 2014 for Civil Works 1288
Analysis of PWD SoR 2014 for Civil Works 1289
Analysis of PWD SoR 2014 for Civil Works 1290
Analysis of PWD SoR 2014 for Civil Works 1291
Analysis of PWD SoR 2014 for Civil Works 1292
Analysis of PWD SoR 2014 for Civil Works 1293
Analysis of PWD SoR 2014 for Civil Works 1294
Analysis of PWD SoR 2014 for Civil Works 1295
Analysis of PWD SoR 2014 for Civil Works 1296
Analysis of PWD SoR 2014 for Civil Works 1297
Analysis of PWD SoR 2014 for Civil Works 1298
Analysis of PWD SoR 2014 for Civil Works 1299
Analysis of PWD SoR 2014 for Civil Works 1300
Analysis of PWD SoR 2014 for Civil Works 1301
Analysis of PWD SoR 2014 for Civil Works 1302
Analysis of PWD SoR 2014 for Civil Works 1303
Analysis of PWD SoR 2014 for Civil Works 1304
Analysis of PWD SoR 2014 for Civil Works 1305
Analysis of PWD SoR 2014 for Civil Works 1306
Analysis of PWD SoR 2014 for Civil Works 1307
Analysis of PWD SoR 2014 for Civil Works 1308
Analysis of PWD SoR 2014 for Civil Works 1309
Analysis of PWD SoR 2014 for Civil Works 1310
Analysis of PWD SoR 2014 for Civil Works 1311
Analysis of PWD SoR 2014 for Civil Works 1312
Analysis of PWD SoR 2014 for Civil Works 1313
Analysis of PWD SoR 2014 for Civil Works 1314
Analysis of PWD SoR 2014 for Civil Works 1315
Analysis of PWD SoR 2014 for Civil Works 1316
Analysis of PWD SoR 2014 for Civil Works 1317
Analysis of PWD SoR 2014 for Civil Works 1318
Analysis of PWD SoR 2014 for Civil Works 1319
Analysis of PWD SoR 2014 for Civil Works 1320
Analysis of PWD SoR 2014 for Civil Works 1321
Analysis of PWD SoR 2014 for Civil Works 1322
Analysis of PWD SoR 2014 for Civil Works 1323
Analysis of PWD SoR 2014 for Civil Works 1324
Analysis of PWD SoR 2014 for Civil Works 1325
Analysis of PWD SoR 2014 for Civil Works 1326
Analysis of PWD SoR 2014 for Civil Works 1327
Analysis of PWD SoR 2014 for Civil Works 1328
Analysis of PWD SoR 2014 for Civil Works 1329
Analysis of PWD SoR 2014 for Civil Works 1330
Analysis of PWD SoR 2014 for Civil Works 1331
Analysis of PWD SoR 2014 for Civil Works 1332
Analysis of PWD SoR 2014 for Civil Works 1333
Analysis of PWD SoR 2014 for Civil Works 1334
Analysis of PWD SoR 2014 for Civil Works 1335
Analysis of PWD SoR 2014 for Civil Works 1336
Analysis of PWD SoR 2014 for Civil Works 1337
Analysis of PWD SoR 2014 for Civil Works 1338
Analysis of PWD SoR 2014 for Civil Works 1339
Analysis of PWD SoR 2014 for Civil Works 1340
Analysis of PWD SoR 2014 for Civil Works 1341
Analysis of PWD SoR 2014 for Civil Works 1342
Analysis of PWD SoR 2014 for Civil Works 1343
Analysis of PWD SoR 2014 for Civil Works 1344
Analysis of PWD SoR 2014 for Civil Works 1345
Analysis of PWD SoR 2014 for Civil Works 1346
Analysis of PWD SoR 2014 for Civil Works 1347
Analysis of PWD SoR 2014 for Civil Works 1348
Analysis of PWD SoR 2014 for Civil Works 1349
Analysis of PWD SoR 2014 for Civil Works 1350
Analysis of PWD SoR 2014 for Civil Works 1351
Analysis of PWD SoR 2014 for Civil Works 1352
Analysis of PWD SoR 2014 for Civil Works 1353
Analysis of PWD SoR 2014 for Civil Works 1354
Analysis of PWD SoR 2014 for Civil Works 1355
Analysis of PWD SoR 2014 for Civil Works 1356
Analysis of PWD SoR 2014 for Civil Works 1357
Analysis of PWD SoR 2014 for Civil Works 1358
Analysis of PWD SoR 2014 for Civil Works 1359
Analysis of PWD SoR 2014 for Civil Works 1360
Analysis of PWD SoR 2014 for Civil Works 1361
Analysis of PWD SoR 2014 for Civil Works 1362
Analysis of PWD SoR 2014 for Civil Works 1363
Analysis of PWD SoR 2014 for Civil Works 1364
Analysis of PWD SoR 2014 for Civil Works 1365
Analysis of PWD SoR 2014 for Civil Works 1366
Analysis of PWD SoR 2014 for Civil Works 1367
Analysis of PWD SoR 2014 for Civil Works 1368
Analysis of PWD SoR 2014 for Civil Works 1369
Analysis of PWD SoR 2014 for Civil Works 1370
Analysis of PWD SoR 2014 for Civil Works 1371
Analysis of PWD SoR 2014 for Civil Works 1372
Analysis of PWD SoR 2014 for Civil Works 1373
Analysis of PWD SoR 2014 for Civil Works 1374
Analysis of PWD SoR 2014 for Civil Works 1375
Analysis of PWD SoR 2014 for Civil Works 1376
Analysis of PWD SoR 2014 for Civil Works 1377
Analysis of PWD SoR 2014 for Civil Works 1378
Analysis of PWD SoR 2014 for Civil Works 1379
Analysis of PWD SoR 2014 for Civil Works 1380
Analysis of PWD SoR 2014 for Civil Works 1381
Analysis of PWD SoR 2014 for Civil Works 1382
Analysis of PWD SoR 2014 for Civil Works 1383
Analysis of PWD SoR 2014 for Civil Works 1384
Analysis of PWD SoR 2014 for Civil Works 1385
Analysis of PWD SoR 2014 for Civil Works 1386
Analysis of PWD SoR 2014 for Civil Works 1387
Analysis of PWD SoR 2014 for Civil Works 1388
Analysis of PWD SoR 2014 for Civil Works 1389
Analysis of PWD SoR 2014 for Civil Works 1390
Analysis of PWD SoR 2014 for Civil Works 1391
Analysis of PWD SoR 2014 for Civil Works 1392
Analysis of PWD SoR 2014 for Civil Works 1393
Analysis of PWD SoR 2014 for Civil Works 1394
Analysis of PWD SoR 2014 for Civil Works 1395
Analysis of PWD SoR 2014 for Civil Works 1396
Analysis of PWD SoR 2014 for Civil Works 1397
Analysis of PWD SoR 2014 for Civil Works 1398
Analysis of PWD SoR 2014 for Civil Works 1399
Analysis of PWD SoR 2014 for Civil Works 1400
Analysis of PWD SoR 2014 for Civil Works 1401
Analysis of PWD SoR 2014 for Civil Works 1402
Analysis of PWD SoR 2014 for Civil Works 1403
Analysis of PWD SoR 2014 for Civil Works 1404
Analysis of PWD SoR 2014 for Civil Works 1405
Analysis of PWD SoR 2014 for Civil Works 1406
Analysis of PWD SoR 2014 for Civil Works 1407
Analysis of PWD SoR 2014 for Civil Works 1408
Analysis of PWD SoR 2014 for Civil Works 1409
Analysis of PWD SoR 2014 for Civil Works 1410
Analysis of PWD SoR 2014 for Civil Works 1411
Analysis of PWD SoR 2014 for Civil Works 1412
Analysis of PWD SoR 2014 for Civil Works 1413
Analysis of PWD SoR 2014 for Civil Works 1414
Analysis of PWD SoR 2014 for Civil Works 1415
Analysis of PWD SoR 2014 for Civil Works 1416
Analysis of PWD SoR 2014 for Civil Works 1417
Analysis of PWD SoR 2014 for Civil Works 1418
Analysis of PWD SoR 2014 for Civil Works 1419
Analysis of PWD SoR 2014 for Civil Works 1420
Analysis of PWD SoR 2014 for Civil Works 1421
Analysis of PWD SoR 2014 for Civil Works 1422
Analysis of PWD SoR 2014 for Civil Works 1423
Analysis of PWD SoR 2014 for Civil Works 1424
Analysis of PWD SoR 2014 for Civil Works 1425
Analysis of PWD SoR 2014 for Civil Works 1426
Analysis of PWD SoR 2014 for Civil Works 1427
Analysis of PWD SoR 2014 for Civil Works 1428
Analysis of PWD SoR 2014 for Civil Works 1429
Analysis of PWD SoR 2014 for Civil Works 1430
Analysis of PWD SoR 2014 for Civil Works 1431
Analysis of PWD SoR 2014 for Civil Works 1432
Analysis of PWD SoR 2014 for Civil Works 1433
Analysis of PWD SoR 2014 for Civil Works 1434
Analysis of PWD SoR 2014 for Civil Works 1435
Analysis of PWD SoR 2014 for Civil Works 1436
Analysis of PWD SoR 2014 for Civil Works 1437
Analysis of PWD SoR 2014 for Civil Works 1438
Analysis of PWD SoR 2014 for Civil Works 1439
Analysis of PWD SoR 2014 for Civil Works 1440
Analysis of PWD SoR 2014 for Civil Works 1441
Analysis of PWD SoR 2014 for Civil Works 1442
Analysis of PWD SoR 2014 for Civil Works 1443
Analysis of PWD SoR 2014 for Civil Works 1444
Analysis of PWD SoR 2014 for Civil Works 1445
Analysis of PWD SoR 2014 for Civil Works 1446
Analysis of PWD SoR 2014 for Civil Works 1447
Analysis of PWD SoR 2014 for Civil Works 1448
Analysis of PWD SoR 2014 for Civil Works 1449
Analysis of PWD SoR 2014 for Civil Works 1450
Analysis of PWD SoR 2014 for Civil Works 1451
Analysis of PWD SoR 2014 for Civil Works 1452
Analysis of PWD SoR 2014 for Civil Works 1453
Analysis of PWD SoR 2014 for Civil Works 1454
Analysis of PWD SoR 2014 for Civil Works 1455
Analysis of PWD SoR 2014 for Civil Works 1456
Analysis of PWD SoR 2014 for Civil Works 1457
Analysis of PWD SoR 2014 for Civil Works 1458
Analysis of PWD SoR 2014 for Civil Works 1459
Analysis of PWD SoR 2014 for Civil Works 1460
Analysis of PWD SoR 2014 for Civil Works 1461
Analysis of PWD SoR 2014 for Civil Works 1462
Analysis of PWD SoR 2014 for Civil Works 1463
Analysis of PWD SoR 2014 for Civil Works 1464
Analysis of PWD SoR 2014 for Civil Works 1465
Analysis of PWD SoR 2014 for Civil Works 1466
Analysis of PWD SoR 2014 for Civil Works 1467
Analysis of PWD SoR 2014 for Civil Works 1468
Analysis of PWD SoR 2014 for Civil Works 1469
Analysis of PWD SoR 2014 for Civil Works 1470
Analysis of PWD SoR 2014 for Civil Works 1471
Analysis of PWD SoR 2014 for Civil Works 1472
Analysis of PWD SoR 2014 for Civil Works 1473
Analysis of PWD SoR 2014 for Civil Works 1474
Analysis of PWD SoR 2014 for Civil Works 1475
Analysis of PWD SoR 2014 for Civil Works 1476
Analysis of PWD SoR 2014 for Civil Works 1477
Analysis of PWD SoR 2014 for Civil Works 1478
Analysis of PWD SoR 2014 for Civil Works 1479
Analysis of PWD SoR 2014 for Civil Works 1480
Analysis of PWD SoR 2014 for Civil Works 1481
Analysis of PWD SoR 2014 for Civil Works 1482
Analysis of PWD SoR 2014 for Civil Works 1483
Analysis of PWD SoR 2014 for Civil Works 1484
Analysis of PWD SoR 2014 for Civil Works 1485
Analysis of PWD SoR 2014 for Civil Works 1486
Analysis of PWD SoR 2014 for Civil Works 1487
Analysis of PWD SoR 2014 for Civil Works 1488
Analysis of PWD SoR 2014 for Civil Works 1489
Analysis of PWD SoR 2014 for Civil Works 1490
Analysis of PWD SoR 2014 for Civil Works 1491
Analysis of PWD SoR 2014 for Civil Works 1492
Analysis of PWD SoR 2014 for Civil Works 1493
Analysis of PWD SoR 2014 for Civil Works 1494
Analysis of PWD SoR 2014 for Civil Works 1495
Analysis of PWD SoR 2014 for Civil Works 1496
Analysis of PWD SoR 2014 for Civil Works 1497
Analysis of PWD SoR 2014 for Civil Works 1498
Analysis of PWD SoR 2014 for Civil Works 1499
Analysis of PWD SoR 2014 for Civil Works 1500
Analysis of PWD SoR 2014 for Civil Works 1501
Analysis of PWD SoR 2014 for Civil Works 1502
Analysis of PWD SoR 2014 for Civil Works 1503
Analysis of PWD SoR 2014 for Civil Works 1504
Analysis of PWD SoR 2014 for Civil Works 1505
Analysis of PWD SoR 2014 for Civil Works 1506
Analysis of PWD SoR 2014 for Civil Works 1507
Analysis of PWD SoR 2014 for Civil Works 1508
Analysis of PWD SoR 2014 for Civil Works 1509
Analysis of PWD SoR 2014 for Civil Works 1510
Analysis of PWD SoR 2014 for Civil Works 1511
Analysis of PWD SoR 2014 for Civil Works 1512
Analysis of PWD SoR 2014 for Civil Works 1513
Analysis of PWD SoR 2014 for Civil Works 1514
Analysis of PWD SoR 2014 for Civil Works 1515
Analysis of PWD SoR 2014 for Civil Works 1516
Analysis of PWD SoR 2014 for Civil Works 1517
Analysis of PWD SoR 2014 for Civil Works 1518
Analysis of PWD SoR 2014 for Civil Works 1519
Analysis of PWD SoR 2014 for Civil Works 1520
Analysis of PWD SoR 2014 for Civil Works 1521
Analysis of PWD SoR 2014 for Civil Works 1522
Analysis of PWD SoR 2014 for Civil Works 1523
Analysis of PWD SoR 2014 for Civil Works 1524
Analysis of PWD SoR 2014 for Civil Works 1525
Analysis of PWD SoR 2014 for Civil Works 1526
Analysis of PWD SoR 2014 for Civil Works 1527
Analysis of PWD SoR 2014 for Civil Works 1528
Analysis of PWD SoR 2014 for Civil Works 1529
Analysis of PWD SoR 2014 for Civil Works 1530
Analysis of PWD SoR 2014 for Civil Works 1531
Analysis of PWD SoR 2014 for Civil Works 1532
Analysis of PWD SoR 2014 for Civil Works 1533
Analysis of PWD SoR 2014 for Civil Works 1534
Analysis of PWD SoR 2014 for Civil Works 1535
Analysis of PWD SoR 2014 for Civil Works 1536
Analysis of PWD SoR 2014 for Civil Works 1537
Analysis of PWD SoR 2014 for Civil Works 1538
Analysis of PWD SoR 2014 for Civil Works 1539
Analysis of PWD SoR 2014 for Civil Works 1540
Analysis of PWD SoR 2014 for Civil Works 1541
Analysis of PWD SoR 2014 for Civil Works 1542
Analysis of PWD SoR 2014 for Civil Works 1543
Analysis of PWD SoR 2014 for Civil Works 1544
Analysis of PWD SoR 2014 for Civil Works 1545
Analysis of PWD SoR 2014 for Civil Works 1546
Analysis of PWD SoR 2014 for Civil Works 1547
Analysis of PWD SoR 2014 for Civil Works 1548
Analysis of PWD SoR 2014 for Civil Works 1549
Analysis of PWD SoR 2014 for Civil Works 1550
Analysis of PWD SoR 2014 for Civil Works 1551
Analysis of PWD SoR 2014 for Civil Works 1552
Analysis of PWD SoR 2014 for Civil Works 1553
Analysis of PWD SoR 2014 for Civil Works 1554
Analysis of PWD SoR 2014 for Civil Works 1555
Analysis of PWD SoR 2014 for Civil Works 1556
Analysis of PWD SoR 2014 for Civil Works 1557
Analysis of PWD SoR 2014 for Civil Works 1558
Analysis of PWD SoR 2014 for Civil Works 1559
Analysis of PWD SoR 2014 for Civil Works 1560
Analysis of PWD SoR 2014 for Civil Works 1561
Analysis of PWD SoR 2014 for Civil Works 1562
Analysis of PWD SoR 2014 for Civil Works 1563
Analysis of PWD SoR 2014 for Civil Works 1564
Analysis of PWD SoR 2014 for Civil Works 1565
Analysis of PWD SoR 2014 for Civil Works 1566
Analysis of PWD SoR 2014 for Civil Works 1567
Analysis of PWD SoR 2014 for Civil Works 1568
Analysis of PWD SoR 2014 for Civil Works 1569
Analysis of PWD SoR 2014 for Civil Works 1570
Analysis of PWD SoR 2014 for Civil Works 1571
Analysis of PWD SoR 2014 for Civil Works 1572
Analysis of PWD SoR 2014 for Civil Works 1573
Analysis of PWD SoR 2014 for Civil Works 1574
Analysis of PWD SoR 2014 for Civil Works 1575
Analysis of PWD SoR 2014 for Civil Works 1576
Analysis of PWD SoR 2014 for Civil Works 1577
Analysis of PWD SoR 2014 for Civil Works 1578
Analysis of PWD SoR 2014 for Civil Works 1579
Analysis of PWD SoR 2014 for Civil Works 1580
Analysis of PWD SoR 2014 for Civil Works 1581
Analysis of PWD SoR 2014 for Civil Works 1582
Analysis of PWD SoR 2014 for Civil Works 1583
Analysis of PWD SoR 2014 for Civil Works 1584
Analysis of PWD SoR 2014 for Civil Works 1585
Analysis of PWD SoR 2014 for Civil Works 1586
Analysis of PWD SoR 2014 for Civil Works 1587
Analysis of PWD SoR 2014 for Civil Works 1588
Analysis of PWD SoR 2014 for Civil Works 1589
Analysis of PWD SoR 2014 for Civil Works 1590
Analysis of PWD SoR 2014 for Civil Works 1591
Analysis of PWD SoR 2014 for Civil Works 1592
Analysis of PWD SoR 2014 for Civil Works 1593
Analysis of PWD SoR 2014 for Civil Works 1594
Analysis of PWD SoR 2014 for Civil Works 1595
Analysis of PWD SoR 2014 for Civil Works 1596
Analysis of PWD SoR 2014 for Civil Works 1597
Analysis of PWD SoR 2014 for Civil Works 1598
Analysis of PWD SoR 2014 for Civil Works 1599
Analysis of PWD SoR 2014 for Civil Works 1600
Analysis of PWD SoR 2014 for Civil Works 1601
Analysis of PWD SoR 2014 for Civil Works 1602
Analysis of PWD SoR 2014 for Civil Works 1603
Analysis of PWD SoR 2014 for Civil Works 1604
Analysis of PWD SoR 2014 for Civil Works 1605
Analysis of PWD SoR 2014 for Civil Works 1606
Analysis of PWD SoR 2014 for Civil Works 1607
Analysis of PWD SoR 2014 for Civil Works 1608
Analysis of PWD SoR 2014 for Civil Works 1609
Analysis of PWD SoR 2014 for Civil Works 1610
Analysis of PWD SoR 2014 for Civil Works 1611
Analysis of PWD SoR 2014 for Civil Works 1612
Analysis of PWD SoR 2014 for Civil Works 1613
Analysis of PWD SoR 2014 for Civil Works 1614
Analysis of PWD SoR 2014 for Civil Works 1615
Analysis of PWD SoR 2014 for Civil Works 1616
Analysis of PWD SoR 2014 for Civil Works 1617
Analysis of PWD SoR 2014 for Civil Works 1618
Analysis of PWD SoR 2014 for Civil Works 1619
Analysis of PWD SoR 2014 for Civil Works 1620
Analysis of PWD SoR 2014 for Civil Works 1621
Analysis of PWD SoR 2014 for Civil Works 1622
Analysis of PWD SoR 2014 for Civil Works 1623
Analysis of PWD SoR 2014 for Civil Works 1624
Analysis of PWD SoR 2014 for Civil Works 1625
Analysis of PWD SoR 2014 for Civil Works 1626
Analysis of PWD SoR 2014 for Civil Works 1627
Analysis of PWD SoR 2014 for Civil Works 1628
Analysis of PWD SoR 2014 for Civil Works 1629
Analysis of PWD SoR 2014 for Civil Works 1630
Analysis of PWD SoR 2014 for Civil Works 1631
Analysis of PWD SoR 2014 for Civil Works 1632
Analysis of PWD SoR 2014 for Civil Works 1633
Analysis of PWD SoR 2014 for Civil Works 1634
Analysis of PWD SoR 2014 for Civil Works 1635
Analysis of PWD SoR 2014 for Civil Works 1636
Analysis of PWD SoR 2014 for Civil Works 1637
Analysis of PWD SoR 2014 for Civil Works 1638
Analysis of PWD SoR 2014 for Civil Works 1639
Analysis of PWD SoR 2014 for Civil Works 1640
Analysis of PWD SoR 2014 for Civil Works 1641
Analysis of PWD SoR 2014 for Civil Works 1642
Analysis of PWD SoR 2014 for Civil Works 1643
Analysis of PWD SoR 2014 for Civil Works 1644
Analysis of PWD SoR 2014 for Civil Works 1645
Analysis of PWD SoR 2014 for Civil Works 1646
Analysis of PWD SoR 2014 for Civil Works 1647
Analysis of PWD SoR 2014 for Civil Works 1648
Analysis of PWD SoR 2014 for Civil Works 1649
Analysis of PWD SoR 2014 for Civil Works 1650
Analysis of PWD SoR 2014 for Civil Works 1651
Analysis of PWD SoR 2014 for Civil Works 1652
Analysis of PWD SoR 2014 for Civil Works 1653
Analysis of PWD SoR 2014 for Civil Works 1654
Analysis of PWD SoR 2014 for Civil Works 1655
Analysis of PWD SoR 2014 for Civil Works 1656
Analysis of PWD SoR 2014 for Civil Works 1657
Analysis of PWD SoR 2014 for Civil Works 1658
Analysis of PWD SoR 2014 for Civil Works 1659
Analysis of PWD SoR 2014 for Civil Works 1660
Analysis of PWD SoR 2014 for Civil Works 1661
Analysis of PWD SoR 2014 for Civil Works 1662
Analysis of PWD SoR 2014 for Civil Works 1663
Analysis of PWD SoR 2014 for Civil Works 1664
Analysis of PWD SoR 2014 for Civil Works 1665
Analysis of PWD SoR 2014 for Civil Works 1666
Analysis of PWD SoR 2014 for Civil Works 1667
Analysis of PWD SoR 2014 for Civil Works 1668
Analysis of PWD SoR 2014 for Civil Works 1669
Analysis of PWD SoR 2014 for Civil Works 1670
Analysis of PWD SoR 2014 for Civil Works 1671
Analysis of PWD SoR 2014 for Civil Works 1672
Analysis of PWD SoR 2014 for Civil Works 1673
Analysis of PWD SoR 2014 for Civil Works 1674
Analysis of PWD SoR 2014 for Civil Works 1675
Analysis of PWD SoR 2014 for Civil Works 1676
Analysis of PWD SoR 2014 for Civil Works 1677
Analysis of PWD SoR 2014 for Civil Works 1678
Analysis of PWD SoR 2014 for Civil Works 1679
Analysis of PWD SoR 2014 for Civil Works 1680
Analysis of PWD SoR 2014 for Civil Works 1681
Analysis of PWD SoR 2014 for Civil Works 1682
Analysis of PWD SoR 2014 for Civil Works 1683
Analysis of PWD SoR 2014 for Civil Works 1684
Analysis of PWD SoR 2014 for Civil Works 1685
Analysis of PWD SoR 2014 for Civil Works 1686
Analysis of PWD SoR 2014 for Civil Works 1687
Analysis of PWD SoR 2014 for Civil Works 1688
Analysis of PWD SoR 2014 for Civil Works 1689
Analysis of PWD SoR 2014 for Civil Works 1690
Analysis of PWD SoR 2014 for Civil Works 1691
Analysis of PWD SoR 2014 for Civil Works 1692
Analysis of PWD SoR 2014 for Civil Works 1693
Analysis of PWD SoR 2014 for Civil Works 1694
Analysis of PWD SoR 2014 for Civil Works 1695
Analysis of PWD SoR 2014 for Civil Works 1696
Analysis of PWD SoR 2014 for Civil Works 1697
Analysis of PWD SoR 2014 for Civil Works 1698
Analysis of PWD SoR 2014 for Civil Works 1699
Analysis of PWD SoR 2014 for Civil Works 1700
Analysis of PWD SoR 2014 for Civil Works 1701
Analysis of PWD SoR 2014 for Civil Works 1702
Analysis of PWD SoR 2014 for Civil Works 1703
Analysis of PWD SoR 2014 for Civil Works 1704
Analysis of PWD SoR 2014 for Civil Works 1705
Analysis of PWD SoR 2014 for Civil Works 1706
Analysis of PWD SoR 2014 for Civil Works 1707
Analysis of PWD SoR 2014 for Civil Works 1708
Analysis of PWD SoR 2014 for Civil Works 1709
Analysis of PWD SoR 2014 for Civil Works 1710
Analysis of PWD SoR 2014 for Civil Works 1711
Analysis of PWD SoR 2014 for Civil Works 1712
Analysis of PWD SoR 2014 for Civil Works 1713
Analysis of PWD SoR 2014 for Civil Works 1714
Analysis of PWD SoR 2014 for Civil Works 1715
Analysis of PWD SoR 2014 for Civil Works 1716
Analysis of PWD SoR 2014 for Civil Works 1717
Analysis of PWD SoR 2014 for Civil Works 1718
Analysis of PWD SoR 2014 for Civil Works 1719
Analysis of PWD SoR 2014 for Civil Works 1720
Analysis of PWD SoR 2014 for Civil Works 1721
Analysis of PWD SoR 2014 for Civil Works 1722
Analysis of PWD SoR 2014 for Civil Works 1723
Analysis of PWD SoR 2014 for Civil Works 1724
Analysis of PWD SoR 2014 for Civil Works 1725
Analysis of PWD SoR 2014 for Civil Works 1726
Analysis of PWD SoR 2014 for Civil Works 1727
Analysis of PWD SoR 2014 for Civil Works 1728
Analysis of PWD SoR 2014 for Civil Works 1729
Analysis of PWD SoR 2014 for Civil Works 1730
Analysis of PWD SoR 2014 for Civil Works 1731
Analysis of PWD SoR 2014 for Civil Works 1732
Analysis of PWD SoR 2014 for Civil Works 1733
Analysis of PWD SoR 2014 for Civil Works 1734
Analysis of PWD SoR 2014 for Civil Works 1735
Analysis of PWD SoR 2014 for Civil Works 1736
Analysis of PWD SoR 2014 for Civil Works 1737
Analysis of PWD SoR 2014 for Civil Works 1738
Analysis of PWD SoR 2014 for Civil Works 1739
Analysis of PWD SoR 2014 for Civil Works 1740
Analysis of PWD SoR 2014 for Civil Works 1741
Analysis of PWD SoR 2014 for Civil Works 1742
Analysis of PWD SoR 2014 for Civil Works 1743
Analysis of PWD SoR 2014 for Civil Works 1744
Analysis of PWD SoR 2014 for Civil Works 1745
Analysis of PWD SoR 2014 for Civil Works 1746
Analysis of PWD SoR 2014 for Civil Works 1747
Analysis of PWD SoR 2014 for Civil Works 1748
Analysis of PWD SoR 2014 for Civil Works 1749
Analysis of PWD SoR 2014 for Civil Works 1750
Analysis of PWD SoR 2014 for Civil Works 1751
Analysis of PWD SoR 2014 for Civil Works 1752
Analysis of PWD SoR 2014 for Civil Works 1753
Analysis of PWD SoR 2014 for Civil Works 1754
Analysis of PWD SoR 2014 for Civil Works 1755
Analysis of PWD SoR 2014 for Civil Works 1756
Analysis of PWD SoR 2014 for Civil Works 1757
Analysis of PWD SoR 2014 for Civil Works 1758
Analysis of PWD SoR 2014 for Civil Works 1759
Analysis of PWD SoR 2014 for Civil Works 1760
Analysis of PWD SoR 2014 for Civil Works 1761
Analysis of PWD SoR 2014 for Civil Works 1762
Analysis of PWD SoR 2014 for Civil Works 1763
Analysis of PWD SoR 2014 for Civil Works 1764
Analysis of PWD SoR 2014 for Civil Works 1765
Analysis of PWD SoR 2014 for Civil Works 1766
Analysis of PWD SoR 2014 for Civil Works 1767
Analysis of PWD SoR 2014 for Civil Works 1768
Analysis of PWD SoR 2014 for Civil Works 1769
Analysis of PWD SoR 2014 for Civil Works 1770
Analysis of PWD SoR 2014 for Civil Works 1771
Analysis of PWD SoR 2014 for Civil Works 1772
Analysis of PWD SoR 2014 for Civil Works 1773
Analysis of PWD SoR 2014 for Civil Works 1774
Analysis of PWD SoR 2014 for Civil Works 1775
Analysis of PWD SoR 2014 for Civil Works 1776
Analysis of PWD SoR 2014 for Civil Works 1777
Analysis of PWD SoR 2014 for Civil Works 1778
Analysis of PWD SoR 2014 for Civil Works 1779
Analysis of PWD SoR 2014 for Civil Works 1780
Analysis of PWD SoR 2014 for Civil Works 1781
Analysis of PWD SoR 2014 for Civil Works 1782
Analysis of PWD SoR 2014 for Civil Works 1783
Analysis of PWD SoR 2014 for Civil Works 1784
Analysis of PWD SoR 2014 for Civil Works 1785
Analysis of PWD SoR 2014 for Civil Works 1786
Analysis of PWD SoR 2014 for Civil Works 1787
Analysis of PWD SoR 2014 for Civil Works 1788
Analysis of PWD SoR 2014 for Civil Works 1789
Analysis of PWD SoR 2014 for Civil Works 1790
Analysis of PWD SoR 2014 for Civil Works 1791
Analysis of PWD SoR 2014 for Civil Works 1792
Analysis of PWD SoR 2014 for Civil Works 1793
Analysis of PWD SoR 2014 for Civil Works 1794
Analysis of PWD SoR 2014 for Civil Works 1795
Analysis of PWD SoR 2014 for Civil Works 1796
Analysis of PWD SoR 2014 for Civil Works 1797
Analysis of PWD SoR 2014 for Civil Works 1798
Analysis of PWD SoR 2014 for Civil Works 1799
Analysis of PWD SoR 2014 for Civil Works 1800
Analysis of PWD SoR 2014 for Civil Works 1801
Analysis of PWD SoR 2014 for Civil Works 1802
Analysis of PWD SoR 2014 for Civil Works 1803
Analysis of PWD SoR 2014 for Civil Works 1804
Analysis of PWD SoR 2014 for Civil Works 1805
Analysis of PWD SoR 2014 for Civil Works 1806
Analysis of PWD SoR 2014 for Civil Works 1807
Analysis of PWD SoR 2014 for Civil Works 1808
Analysis of PWD SoR 2014 for Civil Works 1809
Analysis of PWD SoR 2014 for Civil Works 1810
Analysis of PWD SoR 2014 for Civil Works 1811
Analysis of PWD SoR 2014 for Civil Works 1812
Analysis of PWD SoR 2014 for Civil Works 1813
Analysis of PWD SoR 2014 for Civil Works 1814
Analysis of PWD SoR 2014 for Civil Works 1815
Analysis of PWD SoR 2014 for Civil Works 1816
Analysis of PWD SoR 2014 for Civil Works 1817
Analysis of PWD SoR 2014 for Civil Works 1818
Analysis of PWD SoR 2014 for Civil Works 1819
Analysis of PWD SoR 2014 for Civil Works 1820
Analysis of PWD SoR 2014 for Civil Works 1821
Analysis of PWD SoR 2014 for Civil Works 1822
Analysis of PWD SoR 2014 for Civil Works 1823
Analysis of PWD SoR 2014 for Civil Works 1824
Analysis of PWD SoR 2014 for Civil Works 1825
Analysis of PWD SoR 2014 for Civil Works 1826
Analysis of PWD SoR 2014 for Civil Works 1827
Analysis of PWD SoR 2014 for Civil Works 1828
Analysis of PWD SoR 2014 for Civil Works 1829
Analysis of PWD SoR 2014 for Civil Works 1830
Analysis of PWD SoR 2014 for Civil Works 1831
Analysis of PWD SoR 2014 for Civil Works 1832
Analysis of PWD SoR 2014 for Civil Works 1833
Analysis of PWD SoR 2014 for Civil Works 1834
Analysis of PWD SoR 2014 for Civil Works 1835
Analysis of PWD SoR 2014 for Civil Works 1836
Analysis of PWD SoR 2014 for Civil Works 1837
Analysis of PWD SoR 2014 for Civil Works 1838
Analysis of PWD SoR 2014 for Civil Works 1839
Analysis of PWD SoR 2014 for Civil Works 1840
Analysis of PWD SoR 2014 for Civil Works 1841
Analysis of PWD SoR 2014 for Civil Works 1842
Analysis of PWD SoR 2014 for Civil Works 1843
Analysis of PWD SoR 2014 for Civil Works 1844
Analysis of PWD SoR 2014 for Civil Works 1845
Analysis of PWD SoR 2014 for Civil Works 1846
Analysis of PWD SoR 2014 for Civil Works 1847
Analysis of PWD SoR 2014 for Civil Works 1848
Analysis of PWD SoR 2014 for Civil Works 1849
Analysis of PWD SoR 2014 for Civil Works 1850
Analysis of PWD SoR 2014 for Civil Works 1851
Analysis of PWD SoR 2014 for Civil Works 1852
Analysis of PWD SoR 2014 for Civil Works 1853
Analysis of PWD SoR 2014 for Civil Works 1854
Analysis of PWD SoR 2014 for Civil Works 1855
Analysis of PWD SoR 2014 for Civil Works 1856
Analysis of PWD SoR 2014 for Civil Works 1857
Analysis of PWD SoR 2014 for Civil Works 1858
Analysis of PWD SoR 2014 for Civil Works 1859
Analysis of PWD SoR 2014 for Civil Works 1860
Analysis of PWD SoR 2014 for Civil Works 1861
Analysis of PWD SoR 2014 for Civil Works 1862
Analysis of PWD SoR 2014 for Civil Works 1863
Analysis of PWD SoR 2014 for Civil Works 1864
Analysis of PWD SoR 2014 for Civil Works 1865
Analysis of PWD SoR 2014 for Civil Works 1866
Analysis of PWD SoR 2014 for Civil Works 1867
Analysis of PWD SoR 2014 for Civil Works 1868
Analysis of PWD SoR 2014 for Civil Works 1869
Analysis of PWD SoR 2014 for Civil Works 1870
Analysis of PWD SoR 2014 for Civil Works 1871
Analysis of PWD SoR 2014 for Civil Works 1872
Analysis of PWD SoR 2014 for Civil Works 1873
Analysis of PWD SoR 2014 for Civil Works 1874
Analysis of PWD SoR 2014 for Civil Works 1875
Analysis of PWD SoR 2014 for Civil Works 1876
Analysis of PWD SoR 2014 for Civil Works 1877
Analysis of PWD SoR 2014 for Civil Works 1878
Analysis of PWD SoR 2014 for Civil Works 1879
Analysis of PWD SoR 2014 for Civil Works 1880
Analysis of PWD SoR 2014 for Civil Works 1881
Analysis of PWD SoR 2014 for Civil Works 1882
Analysis of PWD SoR 2014 for Civil Works 1883
Analysis of PWD SoR 2014 for Civil Works 1884
Analysis of PWD SoR 2014 for Civil Works 1885
Analysis of PWD SoR 2014 for Civil Works 1886
Analysis of PWD SoR 2014 for Civil Works 1887
Analysis of PWD SoR 2014 for Civil Works 1888
Analysis of PWD SoR 2014 for Civil Works 1889
Analysis of PWD SoR 2014 for Civil Works 1890
Analysis of PWD SoR 2014 for Civil Works 1891
Analysis of PWD SoR 2014 for Civil Works 1892
Analysis of PWD SoR 2014 for Civil Works 1893
Analysis of PWD SoR 2014 for Civil Works 1894
Analysis of PWD SoR 2014 for Civil Works 1895
Analysis of PWD SoR 2014 for Civil Works 1896
Analysis of PWD SoR 2014 for Civil Works 1897
Analysis of PWD SoR 2014 for Civil Works 1898
Analysis of PWD SoR 2014 for Civil Works 1899
Analysis of PWD SoR 2014 for Civil Works 1900
Analysis of PWD SoR 2014 for Civil Works 1901
Analysis of PWD SoR 2014 for Civil Works 1902
Analysis of PWD SoR 2014 for Civil Works 1903
Analysis of PWD SoR 2014 for Civil Works 1904
Analysis of PWD SoR 2014 for Civil Works 1905
Analysis of PWD SoR 2014 for Civil Works 1906
Analysis of PWD SoR 2014 for Civil Works 1907
Analysis of PWD SoR 2014 for Civil Works 1908
Analysis of PWD SoR 2014 for Civil Works 1909
Analysis of PWD SoR 2014 for Civil Works 1910
Analysis of PWD SoR 2014 for Civil Works 1911
Analysis of PWD SoR 2014 for Civil Works 1912
Analysis of PWD SoR 2014 for Civil Works 1913
Analysis of PWD SoR 2014 for Civil Works 1914
Analysis of PWD SoR 2014 for Civil Works 1915
Analysis of PWD SoR 2014 for Civil Works 1916
Analysis of PWD SoR 2014 for Civil Works 1917
Analysis of PWD SoR 2014 for Civil Works 1918
Analysis of PWD SoR 2014 for Civil Works 1919
Analysis of PWD SoR 2014 for Civil Works 1920
Analysis of PWD SoR 2014 for Civil Works 1921
Analysis of PWD SoR 2014 for Civil Works 1922
Analysis of PWD SoR 2014 for Civil Works 1923
Analysis of PWD SoR 2014 for Civil Works 1924
Analysis of PWD SoR 2014 for Civil Works 1925
Analysis of PWD SoR 2014 for Civil Works 1926
Analysis of PWD SoR 2014 for Civil Works 1927
Analysis of PWD SoR 2014 for Civil Works 1928
Analysis of PWD SoR 2014 for Civil Works 1929
Analysis of PWD SoR 2014 for Civil Works 1930
Analysis of PWD SoR 2014 for Civil Works 1931
Analysis of PWD SoR 2014 for Civil Works 1932
Analysis of PWD SoR 2014 for Civil Works 1933
Analysis of PWD SoR 2014 for Civil Works 1934
Analysis of PWD SoR 2014 for Civil Works 1935
Analysis of PWD SoR 2014 for Civil Works 1936
Analysis of PWD SoR 2014 for Civil Works 1937
Analysis of PWD SoR 2014 for Civil Works 1938
Analysis of PWD SoR 2014 for Civil Works 1939
Analysis of PWD SoR 2014 for Civil Works 1940
Analysis of PWD SoR 2014 for Civil Works 1941
Analysis of PWD SoR 2014 for Civil Works 1942
Analysis of PWD SoR 2014 for Civil Works 1943
Analysis of PWD SoR 2014 for Civil Works 1944
Analysis of PWD SoR 2014 for Civil Works 1945
Analysis of PWD SoR 2014 for Civil Works 1946
Analysis of PWD SoR 2014 for Civil Works 1947
Analysis of PWD SoR 2014 for Civil Works 1948
Analysis of PWD SoR 2014 for Civil Works 1949
Analysis of PWD SoR 2014 for Civil Works 1950
Analysis of PWD SoR 2014 for Civil Works 1951
Analysis of PWD SoR 2014 for Civil Works 1952
Analysis of PWD SoR 2014 for Civil Works 1953
Analysis of PWD SoR 2014 for Civil Works 1954
Analysis of PWD SoR 2014 for Civil Works 1955
Analysis of PWD SoR 2014 for Civil Works 1956
Analysis of PWD SoR 2014 for Civil Works 1957
Analysis of PWD SoR 2014 for Civil Works 1958
Analysis of PWD SoR 2014 for Civil Works 1959
Analysis of PWD SoR 2014 for Civil Works 1960
Analysis of PWD SoR 2014 for Civil Works 1961
Analysis of PWD SoR 2014 for Civil Works 1962
Analysis of PWD SoR 2014 for Civil Works 1963
Analysis of PWD SoR 2014 for Civil Works 1964
Analysis of PWD SoR 2014 for Civil Works 1965
Analysis of PWD SoR 2014 for Civil Works 1966
Analysis of PWD SoR 2014 for Civil Works 1967
Analysis of PWD SoR 2014 for Civil Works 1968
Analysis of PWD SoR 2014 for Civil Works 1969
Analysis of PWD SoR 2014 for Civil Works 1970
Analysis of PWD SoR 2014 for Civil Works 1971
Analysis of PWD SoR 2014 for Civil Works 1972
Analysis of PWD SoR 2014 for Civil Works 1973
Analysis of PWD SoR 2014 for Civil Works 1974
Analysis of PWD SoR 2014 for Civil Works 1975
Analysis of PWD SoR 2014 for Civil Works 1976
Analysis of PWD SoR 2014 for Civil Works 1977
Analysis of PWD SoR 2014 for Civil Works 1978
Analysis of PWD SoR 2014 for Civil Works 1979
Analysis of PWD SoR 2014 for Civil Works 1980
Analysis of PWD SoR 2014 for Civil Works 1981
Analysis of PWD SoR 2014 for Civil Works 1982
Analysis of PWD SoR 2014 for Civil Works 1983
Analysis of PWD SoR 2014 for Civil Works 1984
Analysis of PWD SoR 2014 for Civil Works 1985
Analysis of PWD SoR 2014 for Civil Works 1986
Analysis of PWD SoR 2014 for Civil Works 1987
Analysis of PWD SoR 2014 for Civil Works 1988
Analysis of PWD SoR 2014 for Civil Works 1989
Analysis of PWD SoR 2014 for Civil Works 1990
Analysis of PWD SoR 2014 for Civil Works 1991
Analysis of PWD SoR 2014 for Civil Works 1992
Analysis of PWD SoR 2014 for Civil Works 1993
Analysis of PWD SoR 2014 for Civil Works 1994
Analysis of PWD SoR 2014 for Civil Works 1995
Analysis of PWD SoR 2014 for Civil Works 1996
Analysis of PWD SoR 2014 for Civil Works 1997
Analysis of PWD SoR 2014 for Civil Works 1998
Analysis of PWD SoR 2014 for Civil Works 1999
Analysis of PWD SoR 2014 for Civil Works 2000
Analysis of PWD SoR 2014 for Civil Works 2001
Analysis of PWD SoR 2014 for Civil Works 2002
Analysis of PWD SoR 2014 for Civil Works 2003
Analysis of PWD SoR 2014 for Civil Works 2004
Analysis of PWD SoR 2014 for Civil Works 2005
Analysis of PWD SoR 2014 for Civil Works 2006
Analysis of PWD SoR 2014 for Civil Works 2007
Analysis of PWD SoR 2014 for Civil Works 2008
Analysis of PWD SoR 2014 for Civil Works 2009
Analysis of PWD SoR 2014 for Civil Works 2010
Analysis of PWD SoR 2014 for Civil Works 2011
Analysis of PWD SoR 2014 for Civil Works 2012
Analysis of PWD SoR 2014 for Civil Works 2013
Analysis of PWD SoR 2014 for Civil Works 2014
Analysis of PWD SoR 2014 for Civil Works 2015
Analysis of PWD SoR 2014 for Civil Works 2016
Analysis of PWD SoR 2014 for Civil Works 2017
Analysis of PWD SoR 2014 for Civil Works 2018
Analysis of PWD SoR 2014 for Civil Works 2019
Analysis of PWD SoR 2014 for Civil Works 2020
Analysis of PWD SoR 2014 for Civil Works 2021
Analysis of PWD SoR 2014 for Civil Works 2022
Analysis of PWD SoR 2014 for Civil Works 2023
Analysis of PWD SoR 2014 for Civil Works 2024
Analysis of PWD SoR 2014 for Civil Works 2025
Analysis of PWD SoR 2014 for Civil Works 2026
Analysis of PWD SoR 2014 for Civil Works 2027
Analysis of PWD SoR 2014 for Civil Works 2028
Analysis of PWD SoR 2014 for Civil Works 2029
Analysis of PWD SoR 2014 for Civil Works 2030
Analysis of PWD SoR 2014 for Civil Works 2031
Analysis of PWD SoR 2014 for Civil Works 2032
Analysis of PWD SoR 2014 for Civil Works 2033
Analysis of PWD SoR 2014 for Civil Works 2034
Analysis of PWD SoR 2014 for Civil Works 2035
Analysis of PWD SoR 2014 for Civil Works 2036
Analysis of PWD SoR 2014 for Civil Works 2037
Analysis of PWD SoR 2014 for Civil Works 2038
Analysis of PWD SoR 2014 for Civil Works 2039
Analysis of PWD SoR 2014 for Civil Works 2040
Analysis of PWD SoR 2014 for Civil Works 2041
Analysis of PWD SoR 2014 for Civil Works 2042
Analysis of PWD SoR 2014 for Civil Works 2043
Analysis of PWD SoR 2014 for Civil Works 2044
Analysis of PWD SoR 2014 for Civil Works 2045
Analysis of PWD SoR 2014 for Civil Works 2046
Analysis of PWD SoR 2014 for Civil Works 2047
Analysis of PWD SoR 2014 for Civil Works 2048
Analysis of PWD SoR 2014 for Civil Works 2049
Analysis of PWD SoR 2014 for Civil Works 2050
Analysis of PWD SoR 2014 for Civil Works 2051
Analysis of PWD SoR 2014 for Civil Works 2052
Analysis of PWD SoR 2014 for Civil Works 2053
Analysis of PWD SoR 2014 for Civil Works 2054
Analysis of PWD SoR 2014 for Civil Works 2055
Analysis of PWD SoR 2014 for Civil Works 2056
Analysis of PWD SoR 2014 for Civil Works 2057
Analysis of PWD SoR 2014 for Civil Works 2058
Analysis of PWD SoR 2014 for Civil Works 2059
Analysis of PWD SoR 2014 for Civil Works 2060
Analysis of PWD SoR 2014 for Civil Works 2061
Analysis of PWD SoR 2014 for Civil Works 2062
Analysis of PWD SoR 2014 for Civil Works 2063
Analysis of PWD SoR 2014 for Civil Works 2064
Analysis of PWD SoR 2014 for Civil Works 2065
Analysis of PWD SoR 2014 for Civil Works 2066
Analysis of PWD SoR 2014 for Civil Works 2067
Analysis of PWD SoR 2014 for Civil Works 2068
Analysis of PWD SoR 2014 for Civil Works 2069
Analysis of PWD SoR 2014 for Civil Works 2070
Analysis of PWD SoR 2014 for Civil Works 2071
Analysis of PWD SoR 2014 for Civil Works 2072
Analysis of PWD SoR 2014 for Civil Works 2073
Analysis of PWD SoR 2014 for Civil Works 2074
Analysis of PWD SoR 2014 for Civil Works 2075
Analysis of PWD SoR 2014 for Civil Works 2076
Analysis of PWD SoR 2014 for Civil Works 2077
Analysis of PWD SoR 2014 for Civil Works 2078
Analysis of PWD SoR 2014 for Civil Works 2079
Analysis of PWD SoR 2014 for Civil Works 2080
Analysis of PWD SoR 2014 for Civil Works 2081
Analysis of PWD SoR 2014 for Civil Works 2082
Analysis of PWD SoR 2014 for Civil Works 2083
Analysis of PWD SoR 2014 for Civil Works 2084
Analysis of PWD SoR 2014 for Civil Works 2085
Analysis of PWD SoR 2014 for Civil Works 2086
Analysis of PWD SoR 2014 for Civil Works 2087
Analysis of PWD SoR 2014 for Civil Works 2088
Analysis of PWD SoR 2014 for Civil Works 2089
Analysis of PWD SoR 2014 for Civil Works 2090
Analysis of PWD SoR 2014 for Civil Works 2091
Analysis of PWD SoR 2014 for Civil Works 2092
Analysis of PWD SoR 2014 for Civil Works 2093
Analysis of PWD SoR 2014 for Civil Works 2094
Analysis of PWD SoR 2014 for Civil Works 2095
Analysis of PWD SoR 2014 for Civil Works 2096
Analysis of PWD SoR 2014 for Civil Works 2097
Analysis of PWD SoR 2014 for Civil Works 2098
Analysis of PWD SoR 2014 for Civil Works 2099
Analysis of PWD SoR 2014 for Civil Works 2100
Analysis of PWD SoR 2014 for Civil Works 2101
Analysis of PWD SoR 2014 for Civil Works 2102
Analysis of PWD SoR 2014 for Civil Works 2103
Analysis of PWD SoR 2014 for Civil Works 2104
Analysis of PWD SoR 2014 for Civil Works 2105
Analysis of PWD SoR 2014 for Civil Works 2106
Analysis of PWD SoR 2014 for Civil Works 2107
Analysis of PWD SoR 2014 for Civil Works 2108
Analysis of PWD SoR 2014 for Civil Works 2109
Analysis of PWD SoR 2014 for Civil Works 2110
Analysis of PWD SoR 2014 for Civil Works 2111
Analysis of PWD SoR 2014 for Civil Works 2112
Analysis of PWD SoR 2014 for Civil Works 2113
Analysis of PWD SoR 2014 for Civil Works 2114
Analysis of PWD SoR 2014 for Civil Works 2115
Analysis of PWD SoR 2014 for Civil Works 2116
Analysis of PWD SoR 2014 for Civil Works 2117
Analysis of PWD SoR 2014 for Civil Works 2118
Analysis of PWD SoR 2014 for Civil Works 2119
Analysis of PWD SoR 2014 for Civil Works 2120
Analysis of PWD SoR 2014 for Civil Works 2121
Analysis of PWD SoR 2014 for Civil Works 2122
Analysis of PWD SoR 2014 for Civil Works 2123
Analysis of PWD SoR 2014 for Civil Works 2124
Analysis of PWD SoR 2014 for Civil Works 2125
Analysis of PWD SoR 2014 for Civil Works 2126
Analysis of PWD SoR 2014 for Civil Works 2127
Analysis of PWD SoR 2014 for Civil Works 2128
Analysis of PWD SoR 2014 for Civil Works 2129
Analysis of PWD SoR 2014 for Civil Works 2130
Analysis of PWD SoR 2014 for Civil Works 2131
Analysis of PWD SoR 2014 for Civil Works 2132
Analysis of PWD SoR 2014 for Civil Works 2133
Analysis of PWD SoR 2014 for Civil Works 2134
Analysis of PWD SoR 2014 for Civil Works 2135
Analysis of PWD SoR 2014 for Civil Works 2136
Analysis of PWD SoR 2014 for Civil Works 2137
Analysis of PWD SoR 2014 for Civil Works 2138
Analysis of PWD SoR 2014 for Civil Works 2139
Analysis of PWD SoR 2014 for Civil Works 2140
Analysis of PWD SoR 2014 for Civil Works 2141
Analysis of PWD SoR 2014 for Civil Works 2142
Analysis of PWD SoR 2014 for Civil Works 2143
Analysis of PWD SoR 2014 for Civil Works 2144
Analysis of PWD SoR 2014 for Civil Works 2145
Analysis of PWD SoR 2014 for Civil Works 2146
Analysis of PWD SoR 2014 for Civil Works 2147
Analysis of PWD SoR 2014 for Civil Works 2148
Analysis of PWD SoR 2014 for Civil Works 2149
Analysis of PWD SoR 2014 for Civil Works 2150
Analysis of PWD SoR 2014 for Civil Works 2151
Analysis of PWD SoR 2014 for Civil Works 2152
Analysis of PWD SoR 2014 for Civil Works 2153
Analysis of PWD SoR 2014 for Civil Works 2154
Analysis of PWD SoR 2014 for Civil Works 2155
Analysis of PWD SoR 2014 for Civil Works 2156
Analysis of PWD SoR 2014 for Civil Works 2157
Analysis of PWD SoR 2014 for Civil Works 2158
Analysis of PWD SoR 2014 for Civil Works 2159
Analysis of PWD SoR 2014 for Civil Works 2160
Analysis of PWD SoR 2014 for Civil Works 2161
Analysis of PWD SoR 2014 for Civil Works 2162
Analysis of PWD SoR 2014 for Civil Works 2163
Analysis of PWD SoR 2014 for Civil Works 2164
Analysis of PWD SoR 2014 for Civil Works 2165
Analysis of PWD SoR 2014 for Civil Works 2166
Analysis of PWD SoR 2014 for Civil Works 2167
Analysis of PWD SoR 2014 for Civil Works 2168
Analysis of PWD SoR 2014 for Civil Works 2169
Analysis of PWD SoR 2014 for Civil Works 2170
Analysis of PWD SoR 2014 for Civil Works 2171
Analysis of PWD SoR 2014 for Civil Works 2172
Analysis of PWD SoR 2014 for Civil Works 2173
Analysis of PWD SoR 2014 for Civil Works 2174
Analysis of PWD SoR 2014 for Civil Works 2175
Analysis of PWD SoR 2014 for Civil Works 2176
Analysis of PWD SoR 2014 for Civil Works 2177
Analysis of PWD SoR 2014 for Civil Works 2178
Analysis of PWD SoR 2014 for Civil Works 2179
Analysis of PWD SoR 2014 for Civil Works 2180
Analysis of PWD SoR 2014 for Civil Works 2181
Analysis of PWD SoR 2014 for Civil Works 2182
Analysis of PWD SoR 2014 for Civil Works 2183
Analysis of PWD SoR 2014 for Civil Works 2184
Analysis of PWD SoR 2014 for Civil Works 2185
Analysis of PWD SoR 2014 for Civil Works 2186
Analysis of PWD SoR 2014 for Civil Works 2187
Analysis of PWD SoR 2014 for Civil Works 2188
Analysis of PWD SoR 2014 for Civil Works 2189
Analysis of PWD SoR 2014 for Civil Works 2190
Analysis of PWD SoR 2014 for Civil Works 2191
Analysis of PWD SoR 2014 for Civil Works 2192
Analysis of PWD SoR 2014 for Civil Works 2193
Analysis of PWD SoR 2014 for Civil Works 2194
Analysis of PWD SoR 2014 for Civil Works 2195
Analysis of PWD SoR 2014 for Civil Works 2196
Analysis of PWD SoR 2014 for Civil Works 2197
Analysis of PWD SoR 2014 for Civil Works 2198
Analysis of PWD SoR 2014 for Civil Works 2199

Vous aimerez peut-être aussi