PS-DC-202-500-0016
Sheet 1 of 12
Ramagundam NTPC Ref no RGM /1/TS/2/004
Plant area: TURBINE
PROCEDURE FOR CONDENSER FLOOD TEST AND VACUUM TIGHTNESS TEST
SLNO
2.0 OBJECTIVE
3.0 PROPOSAL
8.0 METHOD
1.2 Condenser : -
1.5 Plant item completion list for mechanical, Electrical and C & I to
be prepared at site.
Signatures
NTPC BHEL
Station: NTPC- BHEL Ref No.PS-DC-202-500-0016
Sheet 3 of 12
Ramagundam NTPC Ref no RGM /1/TS/2/004
Plant area: TURBINE
PROCEDURE FOR CONDENSER FLOOD TEST AND VACUUM TIGHTNESS TEST
SLNO STATUS
2.0 OBJECTIVE:
Signatures
NTPC BHEL
Station: NTPC- BHEL Ref No.PS-DC-202-500-0016
Sheet 4 of 12
Ramagundam NTPC Ref no RGM /1/TS/2/004
Plant area: TURBINE
PROCEDURE FOR CONDENSER FLOOD TEST AND VACUUM TIGHTNESS TEST
SLNO STATUS
Signatures
NTPC BHEL
Station: NTPC- BHEL Ref No.PS-DC-202-500-0016
Sheet 5 of 12
Ramagundam NTPC Ref no RGM /1/TS/2/004
Plant area: TURBINE
PROCEDURE FOR CONDENSER FLOOD TEST AND VACUUM TIGHTNESS TEST
SLNO STATUS
4.6 Availability of Man Power and T & P for leak detection and
attending.
4.8 Availability of dewatering pump near test area and a pit for
dewatering.
Signatures
NTPC BHEL
Station: NTPC- BHEL Ref No.PS-DC-202-500-0016
Sheet 6 of 12
Ramagundam NTPC Ref no RGM /1/TS/2/004
Plant area: TURBINE
PROCEDURE FOR CONDENSER FLOOD TEST AND VACUUM TIGHTNESS TEST
SLNO STATUS
5.1 Ensure the availability of first Aid Box near the test area
5.2 Ensure that the personnel deployed to check the system leakage
are provided with required safety gears, such as helmets, safety
belts etc.
5.4 Ensure the test area is clean and devoid of obstruction and the
required flooring completed.
Signatures
NTPC BHEL
Station: NTPC- BHEL Ref No.PS-DC-202-500-0016
Sheet 7 of 12
Ramagundam NTPC Ref no RGM /1/TS/2/004
Plant area: TURBINE
PROCEDURE FOR CONDENSER FLOOD TEST AND VACUUM TIGHTNESS TEST
SLNO STATUS
6.1 The personnel for this operation shall be well aware of the layout
of this system.
6.4 During the test, all precautions to be taken at local and remote to
observe the running CEP, Vacuum pump and any tend in
increase in bearing temperature or vibration should be
communicated to control room for appropriate follow up action.
Signatures
NTPC BHEL
Station: NTPC- BHEL Ref No.PS-DC-202-500-0016
Sheet 8 of 12
Ramagundam NTPC Ref no RGM /1/TS/2/004
Plant area: TURBINE
PROCEDURE FOR CONDENSER FLOOD TEST AND VACUUM TIGHTNESS TEST
SLNO STATUS
7.1.6 Make up water line to condenser for filling the condenser steam
space.
7.1.9 Locking of all the hangers of drain flash tanks and connected pipe
Lines in vaccum system.
Signatures
NTPC BHEL
Station: NTPC- BHEL Ref No.PS-DC-202-500-0016
Sheet 9 of 12
Ramagundam NTPC Ref no RGM /1/TS/2/004
Plant area: TURBINE
PROCEDURE FOR CONDENSER FLOOD TEST AND VACUUM TIGHTNESS TEST
SLNO STATUS
7.1.13 The piping & tanks under vacuum system are not to be insulated
including at welding joints and flange joints, manholes, root
valves, stubs etc.
7.2.3 CEP trial run completed with required interlock and protections.
(The list of minimum interlocks and protections to be mutually
prepared at site).
7.2.9 Gland sealing water lines for valves coming under vacuum
system are completed.
Signatures
NTPC BHEL
Station: NTPC- BHEL Ref No.PS-DC-202-500-0016
Sheet 10 of 12
Ramagundam NTPC Ref no RGM /1/TS/2/004
Plant area: TURBINE
PROCEDURE FOR CONDENSER FLOOD TEST AND VACUUM TIGHTNESS TEST
SLNO STATUS
8.0 METHOD:
8.1.2 Check for leakages in the system after every 1 M rise in water
level.
8.1.4 Check the leakages upto 1 M above tube nest and maintain this
level during this test.
8.1.6 After the completion of leak test, clean hot well and release the
jack bolts of condenser springs.
8.2.4 Start one seal steam exhauster fan and both vacuum pumps.
8.2.5 After achieving about 0.2 kg/cm2 vacuum, charge seal steam to
turbine glands. Downstream parameters to be maintained are:
Pressure : 0.01 KSC and temp > 160oC
Signatures
NTPC BHEL
Station: NTPC- BHEL Ref No.PS-DC-202-500-0016
Sheet 11 of 12
Ramagundam NTPC Ref no RGM /1/TS/2/004
Plant area: TURBINE
PROCEDURE FOR CONDENSER FLOOD TEST AND VACUUM TIGHTNESS TEST
SLNO STATUS
8.2.6 Check system for air ingress points if proper vacuum is not
achieved and same shall be rectified.
8.2.7 Stop one vacuum pump when desired vacuum is achieved and
stabilised. However, if with one vacuum pump, vacuum is not
holding then check for air ingress and attend the leakages.
Signatures
NTPC BHEL
Station: NTPC- BHEL Ref No.PS-DC-202-500-0016
Sheet 12 of 12
Ramagundam NTPC Ref no RGM /1/TS/2/004
Plant area: TURBINE
PROCEDURE FOR CONDENSER FLOOD TEST AND VACUUM TIGHTNESS TEST
SLNO STATUS
9.3 After achieving the required vacuum, stop both vacuum pumps
and record the rate of fall of vacuum for 10 minutes. The rate of
fall of vacuum should be 2 to 3 mm of Hg per minute.
9.4 After attending all the leakages, total hogging time taken for
achieving full vacuum shall be noted down by running each
vacuum pump separately one by one and by running both the
vacuum pumps together.
Signatures
NTPC BHEL
PROCEDURE FOR CONDENSER FLOOD TEST
AND VACUUM TIGHTNESS TEST
PROJECT RAMAGUNDAM 500 MW, UNIT - 7
COPY NO:
ISSUED TO :
00 KJ MKS KB 22.09.2003