Target Pekerjaan Main Bay - PT Nindya Karya

Tanggal 29 Okt. s/d 4 Nov. 2017


Volume Volume
No. Date Day Zone Description Rencana Realisasi
1 29-Oct Minggu 16 Backfill Scale Flume axis 10-15 -
2 29-Oct Minggu 20 Backfill Coiler Pit -
3 30-Oct Senin 12 Internal Wall 12.2 Utara 35.00 14.11
4 30-Oct Senin 13 External Wall Barat axis 5-6 22.40 19.49
5 30-Oct Senin 13 Perbaikan External Wall Timur -
6 30-Oct Senin 14 Internal Wall 38.71 26.54
7 30-Oct Senin 16 External Wall Barat axis 15-17 72.80 133.00
8 30-Oct Senin 16 Wall Scale Flume Y sect. 124.80 70.00
9 31-Oct Selasa 11 Middle Slab 25.20 63.00
10 31-Oct Selasa 13 Scale Flume Wall Barat 66.29 35.00
11 31-Oct Selasa 16 External Wall Timur axis 13-15 67.20 67.20
12 31-Oct Selasa 16 Bottom Slab axis 15-17 432.00 392.00
13 31-Oct Selasa 17 Block Foundation 17.1 Timur 85.41 70.00
14 1-Nov Rabu 16 External Wall Barat axis 13-15 61.60 99.96
15 2-Nov Kamis 13 External Wall Timur axis 4.5-6 elv. -4.00 m s/d -1.00 m 38.40 62.00
16 3-Nov Jumat 14 Block Foundation 212.02
17 3-Nov Jumat 18 Motor Foundation 420.00 98.00
18 3-Nov Jumat 19 Laminar Pit 19.3 56.23
19 3-Nov Jumat 20 Base Slab 687.78
20 4-Nov Sabtu 11 Beam 13.43
21 4-Nov Sabtu 20 External Wall Barat 73.73 -
22 2-Nov Kamis 20 Eksternal Wall NE Side 98.89
23 Kolom-kolom 39.50
2,533.00 1,288.69
Status Remark Reschedule

Done
Done (2/11)
Done (28/10)
Done (3/11) 3-Nov
Done
Done (3/11) 3-Nov
Done (31/10)
Done (1/11)
Done (30/10)
Done (1/11)
Done (4/11) 4-Nov
Done (1/11)
Done (1/11)
Done (3/11) 3-Nov
Done (30/10)

Done (2/11) Bertahap


5-Nov
8-Nov
7-Nov
Done (6/11) 6-Nov
Done (2/11)
Keterangan

Urgent!!
Urgent!!

Urgent!!
Urgent!!
459

Urgent!!

Urgent!!
Urgent!!

Urgent!!
Target Pekerjaan Main Bay - PT Nindya Karya
Tanggal 5 Nov. s/d 11 Nov. 2017
Vol.
No. Date Day Zone Description Vol. Plan Status PIC Foreman PIC SPV Remark
Realization
1 5-Nov Minggu 16 Bottom Slab axis 13-15 (Timur) 271.08 271.08 Late On sch Endar Syamsito Cast on 06/11
2 6-Nov Senin 16 Bottom Slab axis 13-15 (Barat) 213.90 Endar Syamsito
3 6-Nov Senin 17 Block Foundation Barat 17.2 89.96 89.96 Done on sch Unang Prapto
4 6-Nov Senin 20 External Wall Barat - Utara 73.73 176.57 Done on sch Lukman Didik 1 Cast
5 7-Nov Selasa 11 & 12 Beam 64.98 Habudin Eman
6 7-Nov Selasa 16 Botom Slab axis 10-13 (Barat) 189.66 Yoto Syamsito
7 7-Nov Selasa 19 Exterior Wall 19.3 axis 25-27 Barat 54.08 87.60 Faster on sch Ratemin Prapto
8 7-Nov Selasa 19 Exterior Wall 19.2 axis 23-25 Timur 66.56 Prapto
9 9-Nov Kamis 17 Block Foundation Barat 17.1 84.00 Unang Prapto
10 9-Nov Kamis 19 Laminar Pit 19.3 56.23 Ratemin Prapto
11 10-Nov Jumat 20 Bottom Slab 828.03 Eko Didik
12 10-Nov Jumat 14 Internal Wall (dekat CZ. 15) 20.50 Karmudi Andika
13 10-Nov Jumat 16 Backfill 16 Scale Flume Y sect. - Andri
14 10-Nov Jumat 19 Exterior Wall 19.1-19.2 axis 20-23 Barat 73.63 Alianto Prapto
6-Nov Senin 12 External Wall Timur Lanjutan - 59.22 Out Of Sch Badar Eman Cast on 06/11

Target minggu ini (5 Nov - 11 Nov) 2,086.33 684.43


13 Wall Barat 22.40
16 External Wa 61.60

16 External Wa 67.20

17 Column 12.73

20 Wall Timur 61.2324


17 Block Foun 85.41
20 Kolom Sela 10.1548
Target Pekerjaan Main Bay - PT Nindya Karya
Tanggal 3 Nov. s/d 11 Nov. 2017
Volume Volume
No. Date Day Zone Description Status PIC Foreman PIC SPV
Rencana Realisasi
1 3-Nov Jumat 13 External Wall Barat axis 5-6 22.40 19.49 Done on sch Eko Encu
2 3-Nov Jumat 14 Internal Wall 38.71 26.54 Done on sch Karmudi Andika
3 3-Nov Jumat 16 External Wall Barat axis 13-15 61.60 99.96 Done on sch Yoto Syamsito
4 3-Nov Jumat 16 Wall Scale Flume Y sect. 54.80 50.00 Done on sch Yoto Syamsito
5 4-Nov Sabtu 13 Scale Flume Wall Timur 66.29 66.29 Done on sch Eko Encu
Habudin,
6 4-Nov Sabtu 16 External Wall Timur axis 13-15 67.20 67.20 Done on sch Syamsito
Jubaidi

7 4-Nov Sabtu 16 External Wall Barat axis 10-13 elv. -4.00 s/d -1.00 m 57.60 125.98 Faster on sch Karmudi Syamsito

8 5-Nov Minggu 16 Bottom Slab axis 13-15 (Timur) 271.08 271.08 Late On sch Endar Syamsito
9 6-Nov Senin 16 Bottom Slab axis 13-15 (Barat) 213.90 Endar Syamsito
10 6-Nov Senin 17 Block Foundation Barat 17.2 89.96 89.96 Done on sch Unang Prapto
11 6-Nov Senin 20 External Wall Barat Utara 73.73 115.21 Done on sch Lukman Didik

12 7-Nov Selasa 11 Beam 64.98 Habudin Eman


13 7-Nov Selasa 16 Botom Slab axis 10-13 (Barat) 189.66 Yoto Syamsito
14 7-Nov Selasa 19 Exterior Wall 19.3 axis 25-27 Barat (25-26) 54.08 87.60 Faster on sch Ratemin Prapto
15 7-Nov Selasa 19 Exterior Wall 19.2 axis 23-25 Timur 66.56 Prapto
16 9-Nov Kamis 17 Block Foundation Barat 17.1 84.00 Unang Prapto
17 9-Nov Kamis 19 Laminar Pit 19.3 56.23 Ratemin Prapto
18 10-Nov Jumat 20 Bottom Slab 828.03 Eko Didik
19 10-Nov Jumat 14 Internal Wall (dekat CZ. 15) 20.50 Karmudi Andika
20 10-Nov Jumat 16 Backfill 16 Scale Flume Y sect. - Andri
21 10-Nov Jumat 19 Exterior Wall 19.1 axis 20-23 Barat 73.63 Alianto Prapto
4-Nov Sabtu 13 Column (Elv. -4.0 up to -1.0) @4 pcs - 12.13 Out Of Sch Encu
6-Nov Senin 12 External Wall Timur Lanjutan 59.22 Out Of Sch Eman

Target minggu ini (3 nov - 11 nov) 2,454.93 1,090.66


Equip. Remark

TC Close check list Jumat 11.00


1 CP Close check list Jumat 11.00
1 CP Check list Jumat 15.00
1 CP Done Jumat 13.00
1 CP Check list pertama Jumat 15.00
1 CP Check list pertama Jumat 15.00

1 CP Check list pertama Jumat 15.00, kurang support

1 CP Check list pertama Sabtu 10.00


2 CP Check list pertama Sabtu 10.00
1 CP Check list pertama Senin 10.00
1 CP Check list pertama Sabtu 10.00, kurang perkuatan
tie rod, verticality
TC Check list pertama Selasa 15.00
1 CP Check list pertama Senin 10.00 (Barat)
1 CP Check list pertama Senin 10.00
1 CP Check list pertama Senin 10.00
1 CP Check list Kamis 10.00
1 CP Check list pertama Kamis 10.00
4 CP Check list pertama Kamis 15.00
TC Check list Jumat 10.00
Prioritas CZ 20, 16 Y minggu selesai
2 CP Check list pertama Rabu 10.00
13 Wall Barat 22.40
16 External Wa 61.60

16 External Wa 67.20

20 Wall Barat 56.0628

17 Column 12.73

20 Wall Timur 61.2324


17 Block Foun 85.41
20 Kolom Sela 10.1548
Target Pekerjaan Main Bay - PT Nindya Karya
Tanggal 3 Nov. s/d 11 Nov. 2017
Volume
No. Date Day Zone Description Rencana

1 3-Nov Jumat 13 External Wall Barat axis 5-6 22.40


2 3-Nov Jumat 14 Internal Wall 38.71
3 3-Nov Jumat 16 External Wall Barat axis 13-15 61.60
4 3-Nov Jumat 16 Wall Scale Flume Y sect. 54.80
5 4-Nov Sabtu 13 Scale Flume Wall Timur 66.29
6 4-Nov Sabtu
16 External Wall Timur axis 13-15 67.20
7 4-Nov Sabtu
16 External Wall Barat axis 10-13 elv. -4.00 s/d -1.00 m 57.60
8 5-Nov Minggu 16 Bottom Slab axis 13-15 (Timur) 271.08
9 6-Nov Senin 16 Bottom Slab axis 13-15 (Barat) 213.90
10 6-Nov Senin 17 Block Foundation Barat 17.2 89.96
11 6-Nov Senin 20 External Wall Barat 73.73

12 7-Nov Selasa 11 Beam 64.98


13
7-Nov Selasa 16 Botom Slab axis 10-13 (Barat) 189.66
14 7-Nov Selasa 19 Exterior Wall 19.3 axis 25-27 Barat (25-26) 54.08
15 7-Nov Selasa 19 Exterior Wall 19.2 axis 23-25 Timur 66.56
7-Nov Selasa 13 Internal Column
7-Nov Selasa 18 Internal Column 18.1 @2 pcs
16 9-Nov Kamis 17 Block Foundation Barat 17.1 4.20
17 9-Nov Kamis 19 Laminar Pit 19.3 56.23
18 10-Nov Jumat 20 Bottom Slab 828.03
19 10-Nov Jumat 14 Internal Wall (dekat CZ. 15) 20.50
20 10-Nov Jumat 16 Backfill 16 Scale Flume Y sect. -
21 10-Nov Jumat 19 Exterior Wall 19.1 axis 20-23 Barat 73.63
11-Nov Sabtu 12 Middle Beam
11-Nov Sabtu 11 Wall Roller Table
11-Nov Sabtu 15 External Wall utara
11-Nov Sabtu 16 Bottom Slab axis 10-13 (Barat)
11-Nov Sabtu 18 Internal Column 18.2 @2 pcs
11-Nov Sabtu 17 Block Foundation 17.2 Timur up to -3.6
4-Nov Sabtu 13 Column (Elv. -4.0 up to -1.0) @4 pcs -
6-Nov Senin 12 External Wall Timur Lanjutan

Target minggu ini (3 nov - 11 nov) 2,375.13


Volume Volume
Rencana Status PIC Foreman PIC SPV Equip.
Realisasi
Tambahan
19.49 Done on sch Eko Encu TC
26.54 Done on sch Karmudi Encu 1 CP
99.96 Done on sch Yoto Syamsito 1 CP
50.00 Done on sch Yoto Syamsito 1 CP
66.29 Done on sch Eko Encu 1 CP
Habudin,
Done on sch Syamsito 1 CP
67.20 Jubaidi

Faster on sch Karmudi Syamsito 1 CP


125.98
271.08 Endar Syamsito 1 CP
Endar Syamsito 2 CP
89.96 Unang Prapto 1 CP
115.21 Lukman Didik 1 CP

Habudin Eman TC

Yoto Syamsito 1 CP
87.60 Faster on sch Ratemin Prapto 1 CP
Prapto 1 CP
Encu TC
Wewe TC
Unang Prapto 1 CP
Ratemin Prapto 1 CP
Eko Didik 4 CP
Karmudi Andika TC
Andri
Alianto Prapto 2 CP
Eman
Eman
Andika
Syamsito
Wewe TC
Prapto
12.13 Out Of Sch Encu
59.22 Out Of Sch Eman

- 1,090.66
Remark

Close check list Jumat 11.00


Close check list Jumat 11.00
Check list Jumat 15.00
Done Jumat 13.00
Check list pertama Jumat 15.00
Check list pertama Jumat 15.00

Check list pertama Jumat 15.00, kurang


support
Check list pertama Sabtu 10.00
Check list pertama Sabtu 10.00
Check list pertama Senin 10.00
Check list pertama Sabtu 10.00, kurang
perkuatan tie rod, verticality
Check list pertama Selasa 15.00

Check list pertama Senin 10.00 (Barat)


Check list pertama Senin 10.00
Check list pertama Senin 10.00

Check list Kamis 10.00


Check list pertama Kamis 10.00
Check list pertama Kamis 15.00
Check list Jumat 10.00
Prioritas CZ 20, 16 Y minggu selesai
Check list pertama Rabu 10.00
13 Wall Barat 22.40
16 External Wa 61.60

16 External Wa 67.20

20 Wall Barat 56.0628

17 Column 12.73

20 Wall Timur 61.2324


17 Block Foun 85.41
20 Kolom Sela 10.1548
Target Pekerjaan Main Bay - PT Nindya Karya
Tanggal 12 Nov. s/d 18 Nov. 2017
Volume Volume
No. Date Day Zone Description Rencana Realisasi
13-Nov Senin 15 Internal Column @3 pcs & Staircase 7.28
13-Nov Senin 18 Motor Foundation Block F3-F7 683.93
13-Nov Senin 17 Block Foundation 17.1 Timur up to -3.6 130.96
14-Nov Selasa 15 External Wall selatan 71.60
14-Nov Selasa 16 Y section to Tunnel 31.90
14-Nov Selasa 20 Bottom Slab NE Side (Sect. 20.4 Part 2) 100.98
14-Nov Selasa 14 Middle Slab Timur 67.02
15-Nov Rabu 16 Bottom Slab axis 12-13 (Barat) samping Y sect. 69.60
17-Nov Jumat 14 Block Foundation -1 124.90
17-Nov Jumat 15 External Wall Barat 183.15

Target minggu ini (12 nov - 18 nov) 1,471.32 -


Status PIC Foreman PIC SPV Equip. Remark

Andika
Wewe
Prapto
Andika
Syamsito
Didik
Prapto
Syamsito
Andika
Andika
13 Wall Barat 22.40
16 External Wa 61.60

16 External Wa 67.20

20 Wall Barat 56.0628

17 Block Foun 85.41


20 Kolom Sela 10.1548
Target Pekerjaan Main Bay - PT Nindya Karya
Tanggal 19 Nov. s/d 25 Nov. 2017
Volume Volume
No. Date Day Zone Description Rencana Realisasi
1 24-Nov Jumat 14 Block Foundation -2 152.76
24-Nov Jumat 14 Exterior Wall -4.0 up to -1.0 125.40
19-Nov Minggu 16 Bottom Slab axis 10-11 Barat samping Y Sect. 53.36
25-Nov Minggu 16 Bottom Slab axis 11-12 Barat atas Y sect. 75.40

Target minggu ini (19 nov - 25 nov) 406.92 -


Status PIC Foreman PIC SPV Equip. Remark

Andika
Andika
Syamsito
Syamsito