Vous êtes sur la page 1sur 7

IADC/SPE 98894

Large-Scale Feasibility Determination of Storing and Transporting a Cement Slurry


Below Deck Under Maritime Conditions
D. Doherty, SPE, C. Fanguy, SPE, and D.T. Mueller, SPE, BJ Services

Copyright 2006, IADC/SPE Drilling Conference


This paper will outline the 10-day slurry stability test that
This paper was prepared for presentation at the IADC/SPE Drilling Conference held in Miami, was undertaken aboard an offshore supply vessel. This test
Florida, U.S.A., 2123 February 2006.
was a large scale field trial, under anticipated storage
This paper was selected for presentation by an IADC/SPE Program Committee following
review of information contained in a proposal submitted by the author(s). Contents of the
conditions, of a 600-bbl quantity of pre-mixed cement slurry
paper, as presented, have not been reviewed by the International Association of Drilling stored in the liquid mud tanks of a working offshore supply
Contractors or Society of Petroleum Engineers and are subject to correction by the author(s).
The material, as presented, does not necessarily reflect any position of the IADC, SPE, their vessel. This paper will also discuss the testing results and
officers, or members. Electronic reproduction, distribution, or storage of any part of this paper
for commercial purposes without the written consent of the International Association of Drilling
conclusions drawn from the field trial.
Contractors and Society of Petroleum Engineers is prohibited. Permission to reproduce in print
is restricted to an abstract of not more than 300 words; illustrations may not be copied. The
abstract must contain conspicuous acknowledgment of where and by whom the paper was Introduction
presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A.,
fax 1.972.952.9435.
Driven by space and weight limitations for bulk cement on the
contracted rig the operator accepted an idea that was
Abstract considered unconventional by most. Would it be possible to
As the search for hydrocarbons in the Gulf of Mexico extends use LCP slurry to replace the enormous volume of bulk
deeper, so does the operators need for improved technology cement that would be necessary to cement their well? The
to meet the challenges associated with these increased depths. first string of pipe was a 20-inch casing, 133-ppf set at over
Several operators already have wells in the planning phase 12,000 ft. in a 26-inch open hole. The volume of cement
with projected depths in excess of 30,000 ft. Accordingly, the required to bring the top of cement to 6,000 ft. with 50%
casing programs will cause the well service companies to excess was over 7,500 sacks of cement. The rig had capacity
investigate alternate methods of accommodating the large for 6,000 ft3 (4,300 sacks) of cement. The second string of
cement volumes required to construct the well. pipe was to be 16-inch casing, 137.9 ppf set at over 17,000 ft.
The volume required to cement one of the larger casings The volume of cement for this string with the top of cement at
back to surface can exceed 20,000 sacks of cement. The 6,000 ft and 25% excess, was over 15,000 sacks or 3,000 bbl
conventional jack-up rigs that will be utilized to drill these at the design density. It must first be understood that in order
deep gas wells are generally limited to less than 10,000 ft3 of for the LCP slurry to be considered for use it must first be a
bulk storage. This bulk storage is generally divided between proven technology. Even though LCP slurry had been used in
barite, bentonite, and cement. There is an existing offshore hundreds of applications, the previous volume record was 750
infrastructure that is utilized daily to handle thousands of bbl. A test based on a large-scale field trial was developed to
barrels of liquid drilling mud. If a liquid cement premix demonstrate that the LCP would operationally satisfy all
(LCP) slurry could be maintained in boat tanks enduring technical and operational requirements.
maritime conditions for extended periods of time, it would
then be possible to perform a 30,000+-sack cement job from Slurry Design
an offshore supply vessel. It was known from the onset of this project that the 20-inch
In order for the LCP cement slurry to be considered as a cementing operation would be pumped in the traditional lead-
viable alternative to conventional cementing technology, it tail format. The final mud density was projected somewhere
would be necessary to determine: between 12-13.5 ppg. For the 20-inch casing, the lead slurry
Is the agitation system in the liquid mud tanks design density was to be equivalent to mud weight to avoid
sufficient to maintain large quantities of premixed exceeding the collapse rating of the 20-inch casing. The tail
cement slurry? slurry would be in the range of 15.0-16.5 ppg to provide
Can slurry maintenance be performed on the support and to anchor the casing. The final mud density for
slurry while it is in the liquid mud tanks? the 16-inch job would be in the range of 15-16.5 ppg and
would utilize a single density slurry design for the entire
What are the personnel requirements for liquid
operation. Based on these design parameters it was decided
slurry maintenance while at sea?
that a 15 ppg LCP could be utilized for the lead and tail
Can the boat transfer liquid cement at a high
slurries on the 20-inch casing string and a single slurry for the
enough rate to meet the job requirements?
16-inch casing string. The 15 ppg base slurry has the ability to
Could the density of the original premixed slurry be extended to 11.5 ppg, with the base suspension fluid, while
be increased and/or decreased in the boat tanks?
2 IADC/SPE 98894

exhibiting no tendency to settle or segregate. It also can be Vessel Selection


densified to 20 ppg with a weighting agent; once again, Since it had already been decided that an offshore supply
exhibiting no tendency to settle or segregate. The 15-ppg LCP vessel would carry the LCP and be the operation platform for
had been used quite frequently in the Gulf of Mexico (GOM) the job, it then became necessary to identify a suitable vessel.
but had never been placed in the storage tanks of an offshore Vessel requirements included: sufficient below deck storage
vessel. Since the LCP could possibly be spending three to capacity for the LCP, transfer capabilities from below deck to
seven days in the vessel before the job was pumped, it was this topside, sufficient topside deck loading capacity; draft
time frame, plus a safety margin, that the test was modeled. limitations and DP-II. DP-II provides the station keeping on
location by means of a satellite link and has 100% back up on
Test Overview the systems used to position the vessel, alleviating fears that
The actual test to determine slurry feasibility was designed to weather would hinder the project. The test vessel also had 3
parallel the actual job as closely as possible. The 15 ppg LCP separate and segregated mud systems, which would allow the
was to be mixed onshore at the bulk facility. The slurry would isolation of the liquid premix without risk of contamination
then be transported into the GOM; and subjected to the actual from another fluid being transported on the vessel. The vessel
conditions of maritime travel that it would experience during was equipped with two progressive cavity pumps that were
the cementing operation. The equipment used for the test mix each capable of 660 gpm @ 200 ft of head.
was to, parallel as closely as possible, the equipment to be The plan for the job was to have the progressive cavity
used on the actual job. The required time frame for pumps supply LCP to the suction manifolds of the downhole
transportation of the 15-ppg slurry was determined to be seven triplex pumps positioned on the deck of the supply vessel.
days. At the end of seven days, the slurry would then be This rate gave a 30% safety margin above the planned rate for
brought back to the dock and placed equally into two tanks. the job. Due to the downhole rate requirements, the test would
One tank would be cut back to 12.5 ppg, an arbitrary density have to determine if the boats pumps were adequate for the
picked to reflect a mid-range design density; and the other rate and pressure requirements. The total storage capacity of
tank would be weighted up to 16.5 ppg. the liquid mud system was 8,000 bbl, which was more than
double of any planned volume for liquid premix. This 8,000-
Test Data bbl liquid storage capacity equates to nearly 21,000 sacks of
The objective of the test was to collect data to determine cement based on the 15-ppg base slurry. In addition, the
whether or not the slurry could withstand the rigors and vessel had a dry storage capacity of 11,300 ft3. The dry
changing conditions that maritime travel would impart on the storage could be used for weighting material to bring the 15-
slurry. ppg slurry to 16.5 ppg as required. The feature that was the
most attractive on this particular vessel was the fan style
Test data to be gathered to include:
mixers that were permanently mounted inside of each liquid
Temperature data storage tank. Each tank was equipped with two submersible
Viscosity data fan style mixers, each operating at nearly 500 rpm, and
Density data theoretically capable of circulating the entire contents of the
Settling tendency tanks in less than 12 minutes.
Thickening time data LCP must be agitated on a regular basis to maintain
Gelation tendency optimal viscosity characteristics. The fan style mixers offered
Vessels capability to move the LCP good agitation and fluid movement, without imparting the
Logistical data severe shear conditions that would be experienced when
circulating with a standard centrifugal pump.
Temperature data was taken every six hours at five
different points to determine the effects of the external and Slurry Mixing
internal environment. The slurry was probed every six hours A suitable offshore supply vessel was identified and leased for
to determine if settling of solids was occurring, and finally the a ten day period. The vessel sailed to Port of Fourchon, the
rheologies were run on a Fann 35 at ambient temperature. site chosen for the blending of the LCP. The base gel
Upon conclusion of these tests the slurry was agitated, with suspension was prepared 24 hours prior to the arrival of the
permanently mounted fan mixers that are submerged in each vessel and was stored in a tank especially chosen for this task.
tank, for 30 minutes. All of the pertinent data was collected This tank minimizes the risk of degradation of the bio-
and analyzed to determine the effects of agitation on the polymers due to microbial action. Prior to hydration the base
slurry. Finally, a sample of the LCP was sent to the cement gel suspension is susceptible to contamination and pH
lab to verify thickening time. This was done on day one and variations. It must be mixed under controlled, but
every third day thereafter. Based on previous experience with manageable, conditions. The mix water is placed in a clean
the LCP it has been noted that thickening time will decrease as blender; and the pH is measured and adjusted as necessary.
the slurry ages. This decrease in thickening time is due to the The base gel is then added and allowed to hydrate. When
inherent reduction in the retarders effectiveness over time. fully hydrated and viscosity acceptable, the base gel was sent
Any acceleration in the thickening time reduction curve could to the storage tank to be monitored.
be a signal that the slurry was approaching the end of its As the mixing process progressed, close attention was
effective life. The thickening times were run at the anticipated given to the amount of time each step consumed. This
job temperature logistical information would be valuable when the volume of
IADC/SPE 98894 3

LCP to be produced for the actual operation was increased by ppg. The slurry was agitated for 30 minutes prior to the initial
a magnitude of four. The mixing process began when the data gathering being completed. Samples were then taken
vessel was ready to accept the LCP. The total batch would from the tanks and sent for laboratory analysis. The vessel
amount to 600 bbl of 15-ppg slurry. Two 120-bbl blenders, was released and headed to sea.
equipped with an eductor system, would accommodate the The plan was to travel at a high rate of speed to a point 50
introduction of the dry cement into the base fluid. The liquid miles offshore and secure the vessel to a platform or buoy.
suspension gel was transferred into one of the two blenders This would simulate the initial voyage of the LCP to the rig
and the additional liquid components were added. These and the resultant standby. After spending 12 hours on the
include the plasticizer, retarder, and free fluid control agent. buoy, the vessel would then traverse open water alternating
The additional components were homogenized for 20 minutes; between 12-hour periods of open water travel and standby.
and the rheology of the base fluid was measured and Since the only time the DP-II would be engaged would be at
compared to lab values. When homogenization was complete the rig during the job, it was decided not to include time on the
and the viscosity was at the designed values, the dry cement DP-II as a part of the test. The reason for this omission is that
blend was then added to the base fluid via a bulk line the only time the DP-II would actually be engaged would be
connected to a standard eductor system that re-circulated the when the LCP was being pumped into the wellbore. No
base fluid. The time to density was then recorded. Once the significant information could be obtained by using the DP-II
LCP was at the required density, the slurry was homogenized during the field trial.
for a minimum of 30 minutes. The homogenization period for Data was gathered every six hours both before and after
the LCP is critical. Experience with the LCP indicates that the slurry was agitated. Data gathered included:
improper homogenization can cause slurry longevity issues.
For this reason the base slurry is held to a viscosity standard of 1. Stability of the LCP using a probe
no more than a +/- 5% of the laboratory Fann 35 600 & 300 2. Density of LCP
values and no more than +/- 20% for the 6 & 3 values. If 3. Rheology at ambient temperature
these values are not within range additional homogenization is 4. Temperatures were recorded at these locations with a
required. Only one of six batches that were prepared for the laser type thermometer:
field trial required additional homogenization. Gulf of Mexico
As each batch was completed, and QA / QC checks were Top of Slurry
completed the LCP was transferred to its respective tank on Deck (Ambient)
the vessel. This task was accomplished with a high volume Below Deck Compartment
diaphragm pump. Void Adjacent to Liquid Mud Tanks
Liquid Storage Tank Modification There was considerable amount of speculation that the heat
A special riser with a hatch was built then attached to the lost from the surrounding environment would be excessive
manhole of that tank. The function of the riser was to allow and would cause longevity issues for the LCP. No data could
access to the tank in the event of rough seas where water be found to substantiate or alleviate these concerns. One
frequently covers the entire work deck. The riser elevated the reason for this lack of data is that liquid mud does not gel to
opening of the hatch three feet. The hatch on the riser was the point of becoming a solid when heated, as would a cement
built with quick connect style dogs to facilitate easy access. slurry. Therefore latent heat is of minimal concern to the
The only other modification deemed necessary was the drilling fluids industry. Fig 1 illustrates the effects of the
addition of a 2-inch chemical injection line. This line was external temperatures and their impact on the LCP. This field
installed in the advent that it became necessary to treat the trial was conducted late in the year and the data seems to
LCP during the field trial. The line was attached very near to suggest that heat was lost from the LCP and not the opposite.
the intake side of the lowest fan mixer in the tank and The GOM temperature was nearly 20F cooler than the initial
extended to inside the riser, just below the hatch. Because of temperature of the LCP. The temperature curve of the LCP
the position of the lower end of the injection line, it would be closely resembles the ambient temperature curve as well as the
possible to distribute treatment chemicals quickly and evenly GOM temperature curve.
throughout the tank by introducing them directly into the LCP Since the heat generated by the engines and the mixers in
as it passes through the fan mixer. the tanks appear to have little effect on slurry temperature, we
could predict that in the summer months the LCP temperature
Sea Trial would not rise much over the temperature of the GOM, or the
The sea trial was scheduled to last a total of 10 days. The first ambient temperature, whichever is greater. The rise in
seven days would be spent with the LCP at the 15-ppg density. temperature seen after agitation was due to the fact that the
At the end of 7 days, the slurry would be brought to the dock slurry was cooler near the surface than it was in the center of
and split evenly. The original tank would retain 300 bbls; and the tank and the warmer slurry was brought to the surface
300 bbls would be transferred to another tank, where the during agitation. Temperature was monitored at various
density would be decreased to 12.5 ppg. The original tank points in the agitation process to determine if the heat gain
would be weighted up to 16.5 ppg with a weighting agent. was from agitation. The gain in temperature did not come
The LCP occupied one tank once it was transferred into the from the agitation process, but a layering effect produced by
vessel. The total capacity of the tank chosen for the test was the slurry cooling at the top.
750 bbl. The total volume of LCP on board was 600 bbl of 15
4 IADC/SPE 98894

Another data set gathered was the slurry viscosity. As was stored at the bulk blending facility in the permanent bulk
with temperature, viscosity was also monitored every six tanks and was blown to the tank until the appropriate density
hours both before and after agitation. Viscosity data was was achieved. Density data for the 15-ppg slurry can be seen
gathered and plotted on both a log and linear scale. Based on in fig. 2.
these data, it was determined that the fluid exhibited properties
matching the modified power law model for fluid behavior. Sea Trial : Final 3 Days
Points plotted on the log/log plot produce a straight line, The two slurries were then subjected to 3 more days of sea
which indicates a match for power law fluid behavior. trials. Data was gathered following the same format set up for
Figs. 3-4 illustrate values for n & K that were calculated the 15-ppg base slurry. The 12.5 ppg slurry showed almost no
using the viscosity module of a current cementing wellbore solid settling and absolutely no density reduction. Calculated
simulator. Days 1-7 are plotted. The viscometer readings n and K values yielded results opposite the 15-ppg slurry.
used were those taken at midnight. Temperature data for The n value decreased which indicates the fluid moving away
points plotted can be seen in fig.1. (Note the increase in K from Newtonian flow behavior. The K value increased
after day 2.) K is the consistency index, an increase in K slightly indicating a possible increase in solids concentration.
could indicate gellation of the LCP. On day two an additional Although slight the slurry was actually gaining viscosity.
quantity of anti-settling agent was added to the LCP by means These same changes were seen in the n and K values for the
of the chemical addition line. The amount per/bbl was equal 16.5 ppg slurry. The 15.0 ppg slurry was weighted up to 16.5
to the amount that was originally blended into the LCP at the ppg on Dec 13 and pumped off the vessel on Dec 16, a 100-
blending facility. bbl sample was retained at the bulk blending facility for an
Being a polymer with a very high water requirement as additional eight days for evaluation. The slurry remained
well as high viscosity, it was important to determine if this pumpable with no settling or gelation.
additional amount of anti-settling agent could be added to the
tanks or would have to be incorporated into the original blend. Discussion
After the addition of the anti-settling agent, the K value A large-scale test was devised that which demonstrated that
increased which would indicate that the fluid was being LCP technology could be utilized by taking advantage of an
incorporated into the LCP and returning settled solids to the infrastructure being used primarily for the transport of liquid
mixture. The n value, which is the flow behavior index, drilling mud. It was the goal of this test was to ascertain if
indicates the slurry is becoming less Newtonian immediately LCP could withstand the rigors of maritime travel, as well as
after the addition of the anti-settling agent. Viscosity data the associated logistics, without losing the value for which it
indicates a gradual thinning of the 15 ppg LCP over the 7-day was intended. The test vessel required very little in the way of
period. The post-agitation density of the LCP remained a modifications because of the similarity of drilling mud and
constant 15 ppg until day 5 with a gradual decrease to 14.9 cement in its liquid state. Pending a successful test it would
ppg on day 7. then be possible for the appropriate vessel to transport,
maintain, and deliver the equivalent of tens-of-thousands of
Sea Trial : Day 8 sacks of cement to a rig in one run.
The vessel returned from offshore on day eight to the bulk The major areas of concern were addressed and the
blending facility, where the slurry was split into two tanks. evaluation was structured in such a way as to find any
This was accomplished by using the vessels progressive weaknesses in the system prior to implementing the
cavity pump. The slurry was pumped via the discharge system technology in a full scale operation, which would first be the
that is used to deliver liquid mud to the rig. The slurry is execution of the aforementioned 20-inch job. Since an LCP
pulled from the bottom of the liquid mud tank through a 12- had never been intentionally placed in the liquid mud tanks of
inch suction line, discharged through the pump, and then on to an offshore vessel, there was no prior history to rely upon. The
the discharge manifold on the deck of the vessel. A 3-inch end result of this full scale field trial was the decision to
hose was connected to the manifold and run into the top of the employ the LCP in a large volume 20-inch casing cementing
tank that the new slurry would occupy. This tank was also operation.
fitted with a riser to prevent seawater contamination. It must
be noted, that during the transfer, the maximum rate of the Conclusions
vessels progressive cavity pump was tested. It was 1. The test demonstrated liquid cement premix could be
determined that at 80% capacity the pump could transfer fluid, readily adapted to large, complex cement jobs with
on deck, 240 gpm faster than what was required for the actual the use of existing, properly equipped offshore
job vessels.
Upon completion of splitting the volume of LCP, liquid
2. The test demonstrated the stability of the base premix
suspension gel was added to the first tank in the amount of 18
as well as diluted slurry and weighted slurry for
gpb in order to reduce the density from 15 ppg to 12.5 ppg.
extended periods of time and the effects of the low
With this task complete, a weighting agent was then
frequency vibration and heave produced by the vessel
introduced to the remaining tank. This was accomplished by
were minimal.
utilizing the same circulating system previously mentioned
and circulating the 15-ppg LCP back into the tank. The 3. Temperature effects from the vessels equipment
weighting agent would be introduced through a standard below deck were not as pronounced as first
eductor system mounted on the riser. The weighting agent presumed.
IADC/SPE 98894 5

4. The test demonstrated that although the agitation in 2. Merritt, J.W.: "Premixed Cement Slurry Solves Problems
the vessels tanks is more than adequate for the LCP, Associated With Conventional Oilwell Cementing," paper
highly viscous fluids with a high water requirement SPE 93897, presented at the 2005 Production and
could not be injected directly into the tank and Operations Symposium, Oklahoma City, OK, 17-19
incorporated into the mixture efficiently. April, 2005

Acknowledgements 3. Rae, Phil and Johnston, N.: "Liquid Cement Premix


The authors wish to thank the field operations personnel in Introduces New Solutions to Conventional Cementing
Houma and Port of Fourchon for their support in this field Problems," paper IADC/SPE 35086 presented at the
trial. The authors also wish to thank Ms. Issa Mendez for her IADC/SPE Drilling Conference, New Orleans, LA, 12-15
assistance in the preparation of this manuscript and to the March, 1996
management of BJ Services for permission to publish this
paper. 4. Anderson, J.W., Buchanan, A.I., and Susanto, A.: "New
Technology Eliminates Bulking in Cementing
Nomenclature Operations," paper SPE 36478 presented at the SPE
GOM =Gulf of Mexico Annual Technical Conference and Exhibition, Denver,
LCP =liquid cement pre-mix CO, 6-9 October 1996.
gpm =gallons per minute
bbl =barrels 5. Judge, Robert A and Benge, G.: "Advances in Metering
gpb =gallons per barrel and Control Technology Improves Design and Execution
K =consistency index lbf - secn of Foamed Cement Jobs," paper IADC/SPE 47831
n =flow behavior index (dimensionless) presented at the IADC/SPE Asia Drilling Conference,
ppf =pound per foot Jakarta, Indonesia, 7-9 September 1998.
ppg =pounds per gallon
DP =dynamic positioning

References

1. Benge, G., Darby, J., Peroyea, M., Aquilar, T., Mueller,


D. T., Doherty, D. R.: "Deep Gas Well Cementation: A
Review of Risks and Design Basis for use of a Liquid
Cement Premix for Large Offshore Cementing
Operations," paper IADC/SPE 98970 presented at the
2006 IADC/SPE Drilling Conference, Miami, FL 21-23
February, 2006.
6 IADC/SPE 98894

90

85

80

75

70

65

60

55
0 1 2 3 4 5 6 7 8
Mid. Temp. before agitation
Mid. Temp after agitation
GOM Temperature
Noon Deck Temp
Empty Tank on Bottom
Noon below deck Temp

Fig.1 Temperature effects on base slurry (days vs. F)

15.15

15.1

15.05

15
Density

14.95

14.9

14.85

14.8

14.75
0 1 2 3 4 5 6 7 8
Mid. Density
Days before agitation
Mid. Density after agitation

Fig. 2 Density days 1-7


IADC/SPE 98894 7

0.5800

0.5750

0.5700

0.5650

0.5600

0.5550

0.5500

0.5450

0.5400

0.5350
0 1 2 3 4 5 6 7 8

Fig. 3 n (days vs. flow behavior index)

0.1200

0.1100

0.1000

0.0900

0.0800

0.0700

0.0600
0 1 2 3 4 5 6 7 8

Fig. 4 - K (days vs. consistency index)

Vous aimerez peut-être aussi