Vous êtes sur la page 1sur 5

IADC/SPE 98970

Deep Gas-Well Cementation: A Review of Risks and Design Basis for Use of a Liquid
Cement Premix for Large Offshore Cementing Operations
G. Benge, J. Darby, M. Peroyea, and T. Aguilar, ExxonMobil Development Co., and D. Mueller and D. Doherty, BJ Services

Copyright 2006, IADC/SPE Drilling Conference


casing string was to be set in a 26 inch open hole at a depth of
This paper was prepared for presentation at the IADC/SPE Drilling Conference held in Miami, over 12,000 ft. This was to be followed by a 16inch 137.9
Florida, U.S.A., 2123 February 2006.
ppf casing string set at approximately 17,000 ft in a 22-inch
This paper was selected for presentation by an IADC/SPE Program Committee following
review of information contained in a proposal submitted by the author(s). Contents of the
open hole.
paper, as presented, have not been reviewed by the International Association of Drilling To bring cement top to 6,000 ft, the volume for the
Contractors or Society of Petroleum Engineers and are subject to correction by the author(s).
The material, as presented, does not necessarily reflect any position of the IADC, SPE, their 20inch casing job with 50% excess would be approximately
officers, or members. Electronic reproduction, distribution, or storage of any part of this paper
for commercial purposes without the written consent of the International Association of Drilling
2,400 bbl or over 7,500 sacks of cement. The displacement
Contractors and Society of Petroleum Engineers is prohibited. Permission to reproduce in print volume for this string would be approximately 4,100 bbl. The
is restricted to an abstract of not more than 300 words; illustrations may not be copied. The
abstract must contain conspicuous acknowledgment of where and by whom the paper was 16-inch design also called for top of cement at 6,000 ft, with
presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A.,
fax 1.972.952.9435.
the cement volume being just over 3,000 bbl with a 25%
excess cement factor employed. At the anticipated density for
Abstract: this job, the cement volume would exceed 15,000 sacks.
The well was being drilled from a Tarzan class jack-
Large volume offshore cement jobs can present a number of up rig in 97 feet of water. The rig has approximately 6,000
challenges. Larger casing strings set to deeper depths have cubic feet of cement storage, enough for approximately 4,000
driven up the volume of cement jobs beyond the capacity of sacks of cement.
many rigs. A recent well design called for two cement jobs This paper discusses the design requirements for the
that would exceed 2,400 bbl. There were a number of options slurries, the risks associated with mixing and placing these
considered for dealing with these large cement jobs. These large volumes of cement, and the alternatives considered for
included spotting lift boats beside the rig, the use of a mixing and pumping the slurries. The discussion includes the
dedicated cementing vessel, the deployment of ocean going risks of mixing the cement slurries on the fly versus the use of
barges, spotting an additional jack up rig, or the use of a liquid a liquid cement premix, with its associated risks.
cement premix.
This paper discusses the risk analysis and Cement Design Requirements:
development plan that led to the selection of a liquid cement There were three primary drivers for the slurry designs on the
premix for the large volume jobs. The paper covers the design each of the casing jobs. These were density control, mixing
requirements of the jobs and addresses the risks associated rate and placement time.
with the available options. Information is provided on risks Density control was critical for the 20inch casing
associated with boat and barge stability, draft limits at job because of the risks of casing collapse. The 20inch, 133
available bulk facilities, deck load limits and logistics of ppf casing had a collapse rating of 1,600 psi. If the cement
alternative designs. Rig based pumping operations are were mixed above the designed 13.1 lbm/gal density, the
included with respect to logistics and timing issues related to differential pressure on the casing could be sufficient to cause
placing the entire operation on the rig. collapse.
These jobs were to be the largest liquid cement Density control was also required for consistent
premix jobs to date. Slurry stability and consistency were slurry behavior. Not mixing the cement to the proper density
major concerns on these jobs. These were addressed through could mean an unacceptable change in the thickening time.
full scale testing on the vessel. (The results of which are The large cement and displacement volumes required a very
summarized in SPE 988941.) The paper further covers the long thickening times for both job designs.
equipment requirements and mixing needs and compares the Mixing rate is directly related to the needed
selected option to that of a conventional cement job. thickening time of the slurry for the 20inch job. Mixing
2,250 bbl of lead at 10 bbl/min would require just under 4
Introduction: hours. At 15 bbl/min, this dropped to just over 2 hours.
The challenges presented by large volume cement jobs in an Coupled with the time to mix the tail slurry, in this case
offshore environment are driven by space limitations and another 30 minutes, and the 4,100 bbl of displacement at 15
weight restrictions. This project addressed the specific bbl/min, the minimum thickening time for the lead slurry
challenges of a Gulf of Mexico well where 20inch, 133 ppf would be approximately 10 hours. The 16inch casing job
2 IADC/SPE 98970

presented similar challenges. The preliminary design called Spotting the cement units and associated bulk equipment on
for 16.5 lbm/gal slurry. Volumes for this job would be in the rig deck would have been possible, but due to the space
excess of 3,000 bbl with a displacement volume of required, no equipment could be moved onto the deck until the
approximately 3,400 bbl. At 10 bpm, the mixing time for the pipe had been run and the deck prepared. The hole would be
lead slurry would be 6 hours, reducing to 3 1/2 hours at 15 circulated while the cement units and bulk equipment were
bpm. A 6hour displacement at 10 bpm would yield a moved to the deck, followed by transfer of the cement into the
minimum pump time requirement of over 12 hours for the lead tanks. It was estimated that at best this would take 12 hours to
slurry. accomplish.
An alternative to this would be placing the cement
Operational Alternatives: units and associated equipment on the rig and running the
Mixing on the Fly - All alternatives except the liquid cement casing off a supply vessel. This would eliminate the delays
premix share the same "mix on the fly" limitations and risks associated with the cement equipment, though would
associated with proper density control. These risks include complicate casing running.
proper cement delivery to assure consistent density control
and coordination of bulk material movement during the job. Ocean Going Barge Barges have been used for large
While it is possible to mix the 13.1 lbm/gal lead at 8 cement jobs in many operations, though they do require
10 bpm with a single unit, density control usually suffers.2 relatively protected waters and have a limited weather
To reduce the risks of density variation, and give sufficient window. The ballast control on a barge can be a challenge and
redundancy on location, at least three cement units were must be continuously monitored. Station keeping for a barge
considered necessary to properly mix the lead slurry. Even if also presented a maritime challenge, and even with multiple
one cement unit suffered mechanical failure, it should still be tug support, a 200 ft safety encroachment distance between the
possible to mix this slurry at a sufficient rate. The 16.5 drilling rig and the barge was anticipated. The large number
lbm/gal slurry presented more challenges because if one unit of cement storage tanks placed on the barge would require a
failed, it was felt two units would be able to maintain a mixing separate and extensive material delivery and air handling
rate of 10 bpm, but probably not 15. system. The limited weather window, the requirement for
Mixing on the fly also requires excellent bulk additional attending vessels, and the need for an extensive top
delivery of the dry mix. This would require the bulk tanks be side bulk handling system eliminated this option from further
in close proximity to the cement units. This could require consideration.
careful design of the placement of the cement units and the
bulk equipment. Lift Boats Use of lift boats to place the cement and
Material movement during cement mixing and additional cementing units was carefully considered. Due to
pumping was also a consideration for the job. For the 13.1 the limited deck space on the boats, two lift boats would have
ppg system, at 10 bpm, the amount of cement and water being been required to hold all of the bulk storage and cementing
moved is 5,500 pounds a minute and at 15 bpm, it is 8,250 units. The weight of the cement and equipment meant the lift
pounds a minute. The job would be designed for 15 bpm, thus boats could not be preloaded prior to jacking up on location.
any mix on the fly option had to consider the safety and This would have required additional boats to transport the
stability of moving over 2.5 tons of material a minute. For the materials, and additional crane time to place the cement units
16inch string, the material movement would increase to and bulk cans.
6,900 pounds a minute at 10 bpm, and over 10,000 pounds per The lift boats offered very good stability and a good
minute at 15 bpm. operating weather window. There were some weather
concerns as there would be an extended period of time
Use of Liquid Cement Premix: required to place the units and bulk equipment and transfer the
An alternative to the conventional mixing of the slurry would cement and water to the boats. While this could be done off of
be through the use of a liquid cement premix. This option the critical path, it would mean the lift boats would be on
takes the critical step of mixing the cement off the critical location for an extended period of time.
path, and eliminates concerns over density control. This A major drawback of the lift boats was the need to tie
option also eases concerns over bulk material transfer, as the up one side of the rig for at least a week prior to the job.
only material being moved is a liquid. The total weight being While considered possible, this limitation was deemed
moved does not change, but the material movement challenges unacceptable in the final analysis. The risks associated with
are greatly reduced. tying up an access point to the rig were considered higher than
using a dedicated cement vessel for the job, thus in spite of the
Logistics Options - Conventional Mixing: improved weather capability, lift boats were not considered
further.
Pump the job from the rig The first option for any cement
job is to determine if that job can be performed with the Additional jack up Spotting an additional jack up rig for
existing systems on the rig. Rig bulk systems are not sized for the cementing job would allow the best weather window of
the very large jobs required for this well. This requires any of the alternatives. However, there are inherent dangers
spotting additional bulk handling equipment on the deck. with bringing in an additional rig in such close proximity to
As noted, at least three additional cement units above another rig. The volume of cement anticipated for the 20inch
the one on the rig were considered necessary for these jobs. and 16inch casing cementation would exceed the bulk
IADC/SPE 98970 3

storage capacity of the additional jack up rig requiring vessel had the capacity to transfer liquids from the storage
additional cement storage tanks with, once again, separate tanks up to the deck at a rate of 880 gpm (20.9 bpm).
bulk material delivery and air handling systems. Like the lift The liquid premix does not eliminate the use of a
boats, this option would also tie up the side of the rig for an dedicated vessel, but does reduce the amount of equipment
extended period of time. Finally, the high cost of this option required on the deck to a skid-mounted frac unit and liquid
coupled with the lack of any short-term contract options additive kit. Because there would be no mixing of the slurry
quickly eliminated it as a viable alternative. on the vessel, the operational weather window for the boat
should be larger than that for a dedicated cement boat.
Dedicated cement boat - Most offshore large volume cement Further, the stability issues would be improved, as only liquids
jobs utilize a dedicated cement vessel. While there are would be transferred on the vessel.
concerns regarding the operating weather window, vessels
equipped with dynamic positioning capabilities were
considered acceptable for the project. Liquid Premix Risks:
Several risks were identified with the cement boat While there appeared to be several operational advantages to
option. First was the ability to contract a vessel of sufficient the liquid cement premix option, there remained several risks
size to accommodate the cement and three cement units (two associated with this option. These risks included:
primaries, one back up) required for the job. The largest of the
offshore supply vessels have a total internal bulk storage This would be the largest application of the liquid
capacity of approximately 11,000 cubic feet in two segregated cement premix to date
bulk systems. Combining the bulk storage capacity of the Slurry stability, both of the base mix at 15.0 lbm/gal,
vessel with that of the rig raises the total bulk storage capacity the diluted mix at 13.1 lbm/gal, and the 16.5 lbm/gal
to 17,000 cubic feet. Any additional cement bulk storage slurries
capacity would be placed topside. The use of vertical storage Slurry stability in the boat tanks and if the tanks on
tanks topside was eliminated as an option due to a deck the boat were appropriate for the premix
loading limitation of 1,000 lbs/ft2 and vessel center of gravity Effects of agitation in the tanks over long periods of
considerations. It was determined that 1,200 cubic foot time
horizontal bulk storage tanks would be placed topside should The marine effects of heave on the stability of the
additional cement storage capacity be required. While minor, premix which could not be simulated in large scale
there were concerns for boat stability during the mixing on land
operation and the need to maintain constant ballast control. Ability to mix very large volumes of the slurry at the
The automatic ballast control systems available on offshore supply base
many boats were considered sufficient to address this risk.
Heat transfer from the vessel's mechanical equipment
Using the dedicated vessel to mix on the fly the cement for the
to the liquid premix
20inch and 16inch casings would have the risks associated
Uses of the liquid premix at low temperatures
with conducting three cement mixing operations
normally higher well temperatures are required for
simultaneously, two on the vessel, one on the rig.
consistent setting properties.
An additional consideration was which offshore
service point(s) had sufficient channel depth to accommodate Ability to accurately add the enhancer while pumping
a supply vessel of this size. Dulac, Berwick and Port of the job
Fourchon, Louisiana were all considered as possible service
points, but only Port of Fourchon was deep enough to allow Project Management:
movement of the fully loaded vessel from the bulk facility. The volume for these jobs would exceed the experience base
Using a dedicated cement vessel with the mix on the by several times. Prior to the project, the largest volume
fly process was considered the lowest risk of any of the applied in the field was approximately 750 bbl.3-6 This project
would require 3 4 times this volume.
alternatives and would be used as the primary back-up if the
To address the project concerns, a dedicated team of
testing on the liquid premix was not successful.
operator and service company personnel was selected and
assembled and charged with the task of identifying and
Logistics Options Liquid Cement Premix:
mitigating the risks associated with the large-scale application
Unlike the other options, the liquid cement premix alternative
of the liquid premix.
offered the only choice where the mixing of the cement was
The team established expectations for all aspects of the
taken off line. The liquid cement premix de-couples the
job. These included:
cement mixing from cement operation, allowing the slurry to
be mixed at the offshore bulk facility a week or more before
the actual cementing operation. As noted, by using the vessel selection with attention to available tankage,
premix, there were no concerns over density control or mixing mixing system, liquid deliverability and draft
rate. This would assure consistent slurry properties for the full requirements
job, and eliminate concerns over blend quality. bulk plant capabilities and associated water access
The only variable in its placement would be the selection of engineering and field personnel
ability to deliver the liquid premix to the pumps, and to quality control monitoring and testing protocols
properly proportion the liquid enhancer into the system. The pumping equipment and liquid enhancer addition
4 IADC/SPE 98970

The primary offshore liquid cement premix blending plant The large scale testing was significant because the
in use was a dedicated facility located in Dulac, Louisiana, successful results of the test gave sufficient confidence in the
however the draft requirements of the vessel did not allow for system, and the ability to maintain the slurry within the design
the use of the Dulac site. Additional mixing and storage tanks requirements, to plan for its use on the two large cement jobs
would be required at any other blending facility. The Port of on the well.
Fourchon was chosen as the site for the preparation of the Following the decision, two final risk factors were
liquid cement premix. This temporary mixing plant would be identified and evaluated. These were the use of the system at
placed at the existing offshore bulk plant and supply base. All the low temperatures expected on the 20inch job, and the
laboratory testing of the liquid cement premix would take ability to properly meter the enhancer into the system. These
place in Broussard, Louisiana. related risks were particularly important for the 20inch job
because the lower temperatures would require higher
Slurry Stability There were several issues identified with concentrations of the enhancer.
respect to slurry stability. There was considerable data
available on the stability of the 15.0 lbm/gal system that forms Use of liquid premix at low temperatures The 20
the basis for most of the liquid premix systems. From this inch cement job would call for the top of the liquid cement
base slurry, the cement is either diluted or weighted up on premix to set at a depth of 6,000 ft and a temperature of
location to match well requirements. approximately 130 deg F. The system can have difficulty
For the 20inch casing operation, the initial planning building strength at low temperatures, though for this casing
called for a variety of slurry densities to be tested. 12.5 job, this was not considered a major risk. The operations
lbm/gal, 13.0 lbm/gal, and 13.5 lbm/gal slurries were all tested required a good shoe test, but due to other operations on the
under the engineering guidelines put forth in the initial well, the casing would not be reentered for at least three days.
requirements. (By the time interval depth was reached, a final To lower the risk on the 20inch job further, a
slurry density of 13.1 lbm/gal was to be used.) A large-scale conventional tail system was designed and pumped with the
boat test was developed where 600 bbl of 15.0 lbm/gal slurry cementing unit on the rig. The resulting design called for 150
was to be mixed and maintained in the boat tanks for one bbl of tail cement pumped at a density of 16.2 lbm/gal.
week. At the end of the initial test, the 600 bbls of liquid
cement premix would be split. One batch would then be Addition of the enhancer The final area of concern was
diluted to 12.5 lbm/gal, the other weighted to 16.5 lbm/gal and the ability to accurately add the liquid enhancer to the slurry
tested for stability for an additional three days. The objectives prior to pumping in the well. The liquid cement premix
of the test were: requires either enhancement or higher temperatures to set.
The cement for the 20-inch job would not be exposed to high
Identify any issues with slurry settling temperatures, thus accurate addition of an enhancer would be
Prove that density changes to the liquid premix can essential.
be made on board the offshore vessel The liquid enhancer is a synergistic two-part system.
Confirm the ability of the mixers on the boat to Part one has been proven to have no effect on thickening time
properly condition the slurry by itself on the liquid cement premix. Part two could
Evaluate any effects of slurry mixing in the tank to accelerate the thickening time when added to the slurry
include effects of shear and temperature containing part one. For this reason there were concerns about
adding the total enhancer package directly to the tanks on the
Evaluate the efficiency of the boat's mud discharge
vessel. If there were any delays to the job, this would have
system in handling the liquid premix
left the enhanced cement system in the boat tanks, which was
Determine if the diluted slurry was stable over long
deemed an unacceptable risk. This required adding the
term or if the cement would require dilution
enhancer on the fly, and would be accomplished by use of the
immediately before the job
same liquid additive proportioning and control system used for
Determine the stability of the 16.5 lbm/gal system to fracturing and foamed cementing operations.
be used on the 16inch casing job The system consists of a computer-controlled pump
metering the enhancer into the suction side of the pumps. The
The results of the test indicated excellent slurry flow rate was monitored and controlled by use of a Coriolis-
stability for both the base slurry and the diluted/weighted type mass flow meter. These meters have been used in many
systems for the duration of the test. This was an important operations and have been shown to be highly reliable and very
finding because it would allow pre-dilution of the slurry to the accurate in this type of application.7
desired density well in advance of the 20inch casing job.
Had the system not been stable, the advantage of the liquid Discussion:
premix would have been greatly reduced as the job would The goal of the evaluation was to determine acceptable
have still required mixing, or diluting large volumes of slurry alternatives to performing very large cement jobs in an
on the fly. offshore environment. The project identified two main areas
of concern: the ability to mix large volumes of cement at an
accurate density, and the ability to perform that operation at a
IADC/SPE 98970 5

high rate which dictates the use of multiple cementing units 3. Merritt, J.W., "Premixed Cement Slurry Solves Problems
and bulk equipment. Space limitations led to placing the Associated With Conventional Oilwell Cementing," paper
mixing operation off the rig, which decreases the operability SPE 93897, presented at the 2005 Production and
window due to weather concerns. The solution to these risks Operations Symposium, Oklahoma City, OK, 17-19
were to move the cement mixing operation to shore and April, 2005
completely away from the rig operations.
By using the liquid cement premix, and taking the 4. Rae, Phil and Johnston, Neil, "Liquid Cement Premix
slurry mixing variable out of the critical path, the ancual job Introduces New Solutions to Conventional Cementing
would be able to concentrate only on pumping the slurry into Problems," paper IADC/SPE 35086 presented at the
the well. This allowed use of fracturing pump equipment for IADC/SPE Drilling Conference, New Orleans, LA, 12-15
cementing operations, thus further reducing the number of March, 1996
pumping units. The fracturing pumps also used an existing,
proven liquid proportioning system for the addition of the 5. Anderson, J.W., Buchanan, A.I., and Susanto, A., "New
enhancer. Technology Eliminates Bulking in Cementing
Operations," paper SPE 36478 presented at the SPE
Conclusions: Annual Technical Conference and Exhibition, Denver,
CO, 6-9 October, 1996.
1. The risk analysis demonstrated liquid cement premix can
be readily adapted to large, complex cement jobs. 6. Anderson, J.W., Buchanan, A.I. and Susanto, A., "New
Technology Improves Cement Slurry Design," paper SPE
2. The boat testing demonstrated the stability of the base 36973 presented at the Asia Pacific Oil and Gas
premix as well as a diluted slurry and a weighted slurry for Conference, Adelaide, Australia, 28-31 October, 1996.
extended periods of time.
7. Judge, Robert A and Benge, Glen, "Advances in Metering
3. The use of the fracturing pump and associated liquid and Control Technology Improves Design and Execution
additive system proved very effective for the high rate of Foamed Cement Jobs," paper IADC/SPE 47831
cementing operation. presented at the IADC/SPE Asia Drilling Conference,
Jakarta, Indonesia, 7-9 September 1998
4. The use of the liquid cement premix removes the risks
associated with mixing on the fly.

5. Slurry quality control was taken out of the critical path by


the use of liquid cement premix.

6. Preplanning, preparation, and personnel selection, etc were


key areas of evaluation for the process.

References:

1. Fanguy, C.J., Doherty, D.H. and Mueller, D. T., "Large


Scale Feasibility Determination of Storing and
Transporting a Liquid Pre-mixed Cement Slurry Below
Deck Under Maritime Conditions," paper IADC/SPE
98894 presented at the 2006 IADC/SPE Drilling
Conference, Miami, FL 21-23 February, 2006.

2. Benge, Glen, "A New Technique for Evaluating Field


Cement Mixing," paper IADC/SPE 27522 presented at
the IADC/SPE Drilling Conference, Dallas, TX 15-18
February 1994

Vous aimerez peut-être aussi