Vous êtes sur la page 1sur 6

METRADO DE EXCAVACION ZAPATAS

OBRA : ESTRUCTURAS HINOSTROZA ELEMENTO: ZAPATAS


LUGAR : HUANCAYO - JUNIN FECHA : ENERO 2006

TOTAL
LONGITUDES DE ZAPATA
DESCRIPCION F'C CANTIDAD (m)
(km/cm) LARGO ANCHO ALTO PARCIAL.

Z-1 100 4 1.20 1.20 1.40 8.06 32.59


Z-2 100 2 1.00 1.00 1.40 2.80
Z-3 100 6 1.60 0.80 1.40 10.75
Z-4 100 7 1.40 0.80 1.40 10.98

TOTAL EXCAVACION EN ZAPATAS (M3) 32.59


METRADO DE EXCAVACION CIMIENTOS CORRIDOS

OBRA : ESTRUCTURAS HINOSTROZA ELEMENTO:CIMIENTOS


LUGAR : HUANCAYO - JUNIN FECHA : ENERO 2006

TOTAL
LONGITUDES DE CIMIENTOS
DESCRIPCION F'C CANTIDAD (m)
(km/cm) LARGO ANCHO ALTO PARCIAL.

EJE A-A
ENTRE 1-2 100 1 4.38 0.40 0.60 1.05
ENTRE 2-3 100 1 2.25 0.40 0.60 0.54
ENTRE 3-4 100 1 1.90 0.60 0.80 0.91
ENTRE 4-5 100 1 0.35 0.60 0.80 0.17
ENTRE 5-6 100 1 1.65 0.60 0.80 0.79
ENTRE 6-7 100 1 2.42 0.40 0.60 0.58

EJE 7-7
ENTRE A-B 100 1 4.17 0.40 0.60 1.00
ENTRE B-C 100 1 2.43 0.60 0.80 1.17

EJE C-C
ENTRE 1-2 100 1 2.78 0.60 0.80 1.33
ENTRE 2-3 100 1 0.80 0.60 0.80 0.38
ENTRE 3-4 100 1 1.90 0.60 0.80 0.91
ENTRE 4-5 100 1 0.55 0.60 0.80 0.26
ENTRE 5-6 100 1 1.75 0.60 0.80 0.84
ENTRE 6-7 100 1 1.23 0.60 0.80 0.59

EJE 1-1
ENTRE B-C 100 1 1.30 0.40 0.60 0.31
ENTRE B-C 100 1 0.90 0.40 0.60 0.22

EJE 3-3
ENTRE A-B 100 1 4.05 0.40 0.60 0.97

EJE 4-4
ENTRE A-B 100 1 2.35 0.60 0.80 1.13

EJE 5-5
ENTRE A-B 100 1 2.48 0.60 0.80 1.19
100 1 1.05 0.40 0.30 0.13

EJE 6-6
ENTRE A-B 100 1 1.55 0.40 0.60 0.37
100 1 1.60 0.40 0.60 0.38

EJE B-B
ENTE 3-4 100 1 2.32 0.40 0.60 0.56
ENTE 5-6 100 1 0.92 0.40 0.30 0.11
100 1 0.93 0.40 0.30 0.11

ENTRE A-B
ENTRE 3-4 100 1 2.40 0.40 0.60 0.58
100 1 0.35 0.40 0.60 0.08
100 1 0.38 0.40 0.60 0.09
ENTRE 4-5 100 1 2.45 0.40 0.60 0.59

ENTRE B-C
ENTRE 1-2 100 1 1.60 0.40 0.60 0.38
ENTRE 2-3 100 1 1.35 0.40 0.60 0.32

TOTAL VOLUMEN EXCAVADO = 18.06


METRADO DE EXCAVACION ZAPATAS

OBRA : ESTRUCTURAS HINOSTROZA ELEMENTO: ZAPATAS


LUGAR : HUANCAYO - JUNIN FECHA : ENERO 2006

TOTAL
LONGITUDES DE ZAPATA
DESCRIPCION F'C CANTIDAD (m)
(km/cm) LARGO ANCHO ALTO PARCIAL.

Z-1 100 4 1.20 1.20 0.70 4.03 16.30


Z-2 100 2 1.00 1.00 0.70 1.40
Z-3 100 6 1.60 0.80 0.70 5.38
Z-4 100 7 1.40 0.80 0.70 5.49

TOTAL EXCAVACION EN ZAPATAS (M3) 16.30


METRADO DE RELLENOS CIMIENTOS CORRIDOS

OBRA : ESTRUCTURAS HINOSTROZA ELEMENTO:CIMIENTOS


LUGAR : HUANCAYO - JUNIN FECHA : ENERO 2006

TOTAL
LONGITUDES DE CIMIENTOS
DESCRIPCION F'C CANTIDAD (m)
(km/cm) LARGO ANCHO ALTO PARCIAL.

EJE A-A
ENTRE 1-2 100 1 4.38 0.25 0.25 0.27
ENTRE 2-3 100 1 2.25 0.25 0.25 0.14
ENTRE 3-4 100 1 1.90 0.45 0.25 0.21
ENTRE 4-5 100 1 0.35 0.45 0.25 0.04
ENTRE 5-6 100 1 1.65 0.45 0.25 0.19
ENTRE 6-7 100 1 2.42 0.25 0.25 0.15

EJE 7-7
ENTRE A-B 100 1 4.17 0.25 0.25 0.26
ENTRE B-C 100 1 2.43 0.45 0.25 0.27

EJE C-C
ENTRE 1-2 100 1 2.78 0.45 0.25 0.31
ENTRE 2-3 100 1 0.80 0.45 0.25 0.09
ENTRE 3-4 100 1 1.90 0.45 0.25 0.21
ENTRE 4-5 100 1 0.55 0.45 0.25 0.06
ENTRE 5-6 100 1 1.75 0.45 0.25 0.20
ENTRE 6-7 100 1 1.23 0.45 0.25 0.14

EJE 1-1
ENTRE B-C 100 1 1.30 0.25 0.25 0.08
ENTRE B-C 100 1 0.90 0.25 0.25 0.06

EJE 3-3
ENTRE A-B 100 1 4.05 0.25 0.25 0.25

EJE 4-4
ENTRE A-B 100 1 2.35 0.45 0.25 0.26

EJE 5-5
ENTRE A-B 100 1 2.48 0.45 0.25 0.28
100 1 1.05 0.25 0.25 0.07

EJE 6-6
ENTRE A-B 100 1 1.55 0.25 0.25 0.10
100 1 1.60 0.25 0.25 0.10

EJE B-B
ENTE 3-4 100 1 2.32 0.25 0.25 0.15
ENTE 5-6 100 1 0.92 0.25 0.25 0.06
100 1 0.93 0.25 0.25 0.06

ENTRE A-B
ENTRE 3-4 100 1 2.40 0.25 0.25 0.15
100 1 0.35 0.25 0.25 0.02
100 1 0.38 0.25 0.25 0.02
ENTRE 4-5 100 1 2.45 0.25 0.25 0.15

ENTRE B-C
ENTRE 1-2 100 1 1.60 0.25 0.25 0.10
ENTRE 2-3 100 1 1.35 0.25 0.25 0.08

TOTAL VOLUMEN RELLENO = 4.54

EXCA 32.59 18.06 50.65


RELLENO 16.30 4.54 26.05
ELIMINACION 30.76