Académique Documents
Professionnel Documents
Culture Documents
P
recast, prestressed concrete girders are often used in
the construction of medium-span bridges1 with span
lengths varying from 12m (40ft) to 54m (177ft).
The precast concrete girders are cast in a casting yard and
then transported to the site, where they are erected using
mechanical cranes (Fig.1). Pretensioning offers a cost-ef-
fective solution compared with posttensioning by obviating
the need for bursting and spalling reinforcing steel in the
end zones.
ronmental classifications. These solutions were obtained The 28-day concrete compressive strength for the
from a parametric analysis based on the concrete service precast, prestressed concrete girders varied from 40 to
load stress limits in AASHTO LRFD specifications. 50MPa (5800 to 7200psi) for normalweight concrete.
The analysis was first conducted for regular HL93 live
loads and was then extended to HL93 increased by 50% The optimal number of 15mm diameter (0.6in.) pre-
(HL931.5),5 a live load that more realistically represents stressing strands was determined based on the service
the actual complex truck weights, axle configurations, and load stress limits in the initial (release) stage.
truck weight populations.6 The implication of increasing
the design live loads on the precast concrete girder size The optimal girder spacing S was determined based on
and spacing was examined, and alternative girder configu- the concrete service load stress limits in the final stage
rations based on increasing the 28-day concrete strength for a girder spacing range of 1.1m < S 3m
were presented. This helped optimize the design of precast, (3.6ft < S 9.9ft) and a topping slab thickness
prestressed concrete bridge girders subjected to increased of 200mm (8in.) for HL93 live load and 250mm
live loads.5 Application of the optimized solution was il- (10in.) for HL93 live load increased by 50%.
lustrated with a comprehensive numerical example.
The parametric service load stress analysis was con-
Assumptions ducted using computer software based on AASHTO
LRFD specifications.
The following assumptions were used for the paramet-
ric studies performed for AASHTO TypeII to modified Identification of parameters
TypeVI girders (Fig.3) for bridge structures of span
lengths from 12m (39ft) to 54m (177ft): The main parameters involved in the design of precast,
prestressed concrete girders are the span length L, the
200 mm
t slab
Edge 1 Edge
Spacing S 2
Spacing S 3
Spacing S 4
Spacing S 5
distance distance
Le Le
Figure 2. Typical cross section of a bridge structure that contains precast, prestressed concrete girders. Note: The girder spacing and edge distance are usually set
based on practical limits: 1.1m (3.6ft) < S 3m (9.9ft); Le 1.1m (3.6ft); 20cm (8in.) tslab 25cm (10in.); 40MPa (5800psi) fc' 50MPa (7200psi).
fc' = 28-day concrete compressive strength; Le = distance from centerline of exterior girder to edge of slab; S = girder spacing; tslab = thickness of concrete slab.
girder size, the 28-day concrete compressive strength f c' , 28-day concrete compressive
the prestressing strand size, the design loads (mainly live strength
load), the concrete service load stress limits, and the girder
spacing S. Practical ranges of these parameters are defined The 28-day concrete strength f c' for the precast, pre-
as follows. stressed concrete girders varied from 40to 50MPa (5800
to 7200psi) in increments of 5MPa (700psi) for nor-
Span length and girder size malweight concrete. A 28-day concrete strength f c' of
50 MPa is highly recommended2 (as shown in the para-
The girder size is a function of the girder design span metric analysis later). However, lower strengths were also
length L. Commonly used AASHTO TypeII to VI girders considered because they provide a basis of comparison
were adopted in this paper (Fig.2) for span lengths of 12m and, contrary to U.S. practice, 50 MPa may be difficult to
(39ft) to 45m (148ft) in addition to a modified girder that achieve on a consistent basis in some locations.2
was introduced for span lengths up to 54m (177ft). Fig-
ure3 shows the girder dimensions and section properties of The concrete strength at release f ci' was taken as 0.8 f c'
TypesII to modified VI girders. (commonly used for the concrete strength range consid-
ered):2
Based on a simple span, the following span length ranges
were adopted for each girder type: f ci' = 32MPa (4600psi) for f c' = 40MPa (5800psi)
TypeII: 12m L < 20m (39ft L < 66ft) f ci' = 36MPa (5200psi) for f c' = 45MPa (6500psi)
TypeIII: 18m L < 26 m (59ft L < 85ft) f ci' = 40MPa (5800psi) for f c' = 50MPa (7200psi)
TypeV: 30m L < 38m (98 ft L < 125ft) The prestressing steel area was based on 15mm (0.6in.)
diameter, low-relaxation strands where the area per strand
TypeVI: 36m L < 45m (118ft L < 148ft) Astrand was 140mm2 (0.217in.2). The minimum tensile
strength fpu was 1860MPa (270ksi). The jacking strength
Modified TypeVI: 42m L < 54m fpj was taken as 75% of fpu, which is equal to 1395MPa
(138ft L < 177ft) (202.5ksi).2,4 The strand distribution was based on a
75mm (3in.) cover to exposed surfaces (measured from
The span length ranges were set for the maximum live load the centerline of the strand to the edge of the exposed
HL93 1.5 and 28-day concrete strength f c' of 50MPa surface) and 50mm (2in.) spacing measured between the
(7200psi), and their upper bound could be extended for the centerline of strands elsewhere.2,4
smaller HL93 loading.2
Section properties
Girder
2 4
type Ybot, m Anc, m Icg, m
II 0.4 0.24 0.021
(4) III 0.52 0.36 0.053
IV 0.63 0.51 0.11
V 0.81 0.65 0.22
VI 0.92 0.7 0.31
VIM 1.08 0.81 0.52
Figure 3. AASHTO TypeII to TypeVI girders commonly used for medium-span bridges in addition to a modified TypeVI girder that was specifically developed for the
new Khalifa Port project in Abu Dhabi, United Arab Emirates. Note: Designed according to British Standards.7,8 All dimensions are in millimeters. Anc = area of the pre-
stressed concrete girder; Icg = moment of inertia of precast concrete girder; L = span length; Ybot = distance from neutral axis of precast concrete girder to the bottom
fiber. 1mm = 0.0394in.; 1m = 3.28ft.
Allowable compressive
28-day concrete strength Normal environments Aggressive environments Extremely aggressive
stress at 28 days
fc' , MPa (e )T = 0.5 fci' , MPa (e )T = 0.25 fci' , MPa environments (e )T = 0
(e )C = 0.6 fc' , MPa
40 3.16 1.58 0 24
45 3.35 1.68 0 27
50 3.54 1.77 0 30
Note: fci' = concrete compressive strength at release; (e)C = allowable concrete service load compressive stress in the final stage; (e)T = allowable
concrete service load tensile stress in the final stage. 1MPa = 145psi.
The upper and lower bounds of the girder spacing S (St)nc = top-fiber noncomposite section modulus
(centerline to centerline of girder, Fig.2) were set at 3m
(9.9ft) and 1.1m (3.6ft), respectively. This girder spacing (i)T = allowable concrete service load tensile stress at
range of 1.1m < S 3m and the constant slab thickness of release (Table1)
200mm (8in.) for HL93 live load and 250mm (10in.) for
1.5 HL93 (Fig.2) allowed the AASHTO LRFD specifica- Based on Eq.(1) and (2), the maximum number of prestress-
tions live load distribution factor formulas to be used. The ing strands was determined for the range of parameters defined
maximum spacing of 3m was provided so that the 200mm in this paper: 12m L 54m (39ft L 177ft), TypeII to
thick (for HL93 live load) and the 250 mm thick (for 1.5 modified VI girders (Fig.3), and f c' of 40MPa (5800psi),
HL93 live load) concrete slabs were not overreinforced. 45MPa (6500psi), and 50MPa (7200psi). The governing
The edge distance Le (that is, the distance from the center- stresses in the initial stage were compressive stresses in the
line of the exterior girder to the edge of the slab) was lim- bottom fiber of the concrete section in the midspan region as
ited to 1.1m for similar reasons in the overhangs (Fig.2). the precompressed tensile zone was subjected to self-weight
dead load only at transfer (Eq.[1]). Tensile stresses at transfer
Optimization of the design were then checked using Eq.(2). Stresses in the girder end
zones10 were controlled by debonding (shielding) of strands
In addition to the range of key parameters previously according to AASHTO LRFD specifications (the maximum
defined, the maximum number of prestressing strands and number of strands that could be debonded per girder was
girder spacing were determined based on the concrete 25% of the total number of strands and 40% of the number of
service load stress limits in the initial stage and in the final strands in a row) and/or using harped strands (a maximum of
stage, respectively. six strands per girder were harped based on common practice
to avoid providing special anchoring systems and bulky form-
work to resist the vertical component of the prestress force).
The parametric analysis was conducted using computer plotted in Fig.4 as a function of the span length L for the
software based on AASHTO LRFD specifications for span length range (12m L 54m [39ft L 177ft]),
the span lengths (Fig.3) considered in multiples of 1m for AASHTO TypeII to modified TypeVI girders as a
(3.3ft). Initial prestress losses (elastic shortening) were function of the 28-day concrete strength range ( f c' equal
directly calculated. Consequently, the maximum number to 40MPa [5800psi], 45MPa [6500psi], and 50MPa
of strands that could be accommodated per girder was [7200psi]).
The spacing S between girders depends on the design span The parametric analysis for selecting the maximum girder
length L, the 28-day concrete strength f c' , the applied dead spacing was conducted for span lengths (Fig.3)
and live loads, and the allowable concrete stresses. In this (12m L 54m [39ft L 177ft]) in increments of 1m
paper, the parametric analysis for the girder spacing was (3.3ft) using computer software based on AASHTO LRFD
performed based on the maximum number of strands that specifications. Final prestress losses (creep, shrinkage, and
was determined in the initial stage (Fig.4). The girder steel relaxation) were directly calculated by the software
spacing was maximized based on the serviceability check based on AASHTO LRFD specifications approximate
for the maximum tensile stress in the positive moment method without accounting for elastic gain (elastic gains
region in the final stage. This bottom-fiber tensile stress usually help reducing losses by 3% to 4%). Live load dis-
check was performed based on AASHTO LRFD specifica- tribution factors were conservatively calculated based on
tions serviceIII load combination using Eq.(3) as follows: AASHTO equations, though they could be more accurately
determined based on grillage models11 considering the true
bridge geometry. Composite dead loads were assumed to
1 e M ncdl M
F + + + cdl (3) be equally distributed among the number of girders.12
Anc ( Sb ) nc ( Sb )nc ( Sb )c
M The optimal girder spacing as a function of the span length
+ ( 0.8 ) LL + I ( e )T was plotted for TypeII to modified VI girders for f c'
( Sb )c equal to 40MPa (5800psi) (Fig.5), f c' equal to 45MPa
(6500psi) (Fig.6), and f c' equal to 50MPa (7200psi)
where (Fig.7). Each figure contains two charts, one for HL93
live loads4 and the other for 1.5 HL93 live loads.5 Each
F = effective prestress force after total losses chart includes plots for the environmental classifications
'
noted in this paper; for example, (e)T of 0.5 f c (6 f c )
'
'
Mncdl = noncomposite dead load moment for a normal environment, (e)T of 0.25 f c (3 f c' ) for an
aggressive environment, and (e)T of zero for an extremely
Mcdl = composite dead load moments aggressive environment.
MLL+I = live load moment plus impact The charts developed from the parametric study may also
serve as design aids because they allow determining the
(Sb)c = bottom-fiber composite section modulus precast concrete girder configurations and prestressing
strand distributions for a wide range of bridge lengths, live
()T = allowable concrete service load tensile stress in the loads, concrete strengths, and service load stress limits by
final stage interpolation.
45 to 50 20 30 0.25 fc' to 0 10 15 45 17 25
40 to 50 45 70 0.5 fc' to 0 20 25 50 15 22
The effect of increasing the concrete strength f c' on the Last, the effect of increasing the design live load by 50%
girder spacing S was examined first. Based on the charts, on the girder spacing was examined.
it was shown that increasing f c' from 40 to 45MPa (5800
to 6500psi), and from 45 to 50MPa (7200psi) would in- From Fig.5 ( f c' equal to 40MPa [5800psi]), the girder
crease S by approximately 20% for HL93 and 1.5 HL93 spacing S would reduce by 20% if the design live load
live loads. This implies that the increase is about 40% if f c' was increased from HL93 to 1.5 HL93. From Fig.6 ( f c'
is increased from 40 to 50MPa. Those increases were de- equal to 45MPa [6500psi]) the reduction in girder spacing
termined as average values based on the ratios of the ordi- S was 17%, and from Fig.7 ( f c' of 50MPa [7200psi])
nates of the plots from Fig.5, 6, and 7, for HL93 live load it was 15%. These percentages were computed based on
and for 1.5 HL93 live load. Table3 lists the increases in average values of the chart ordinates.
girder spacing (maximum and average values).
As for the case of reducing the allowable concrete ser-
Effect of reducing the allowable vice load tensile stress (e)T, the effect of increasing the
concrete service load tensile stress live load could be compensated by increasing the 28-day
concrete strength by 5MPa (700psi); that is, the girder
The effect of reducing the allowable concrete service load spacing for f c' of 40MPa (5800psi) and HL93 live load
tensile stress (e)T from 0.5 f c' (6 f c' ) (normal environ- was almost comparable to the case where f c' was 45MPa
ment) to 0.25 f c' (3 f c' ) (aggressive environment) and (6500psi) with a 1.5HL93 live load (within 5%), and
zero (extremely aggressive environment) on the girder the girder spacing for f c' of 45MPa and HL93 live load
spacing S was also examined. The graphs in Fig.5, 6, and was almost comparable to the case where f c' was 50MPa
7 show that reducing the tensile stress from 0.5 f c' to (7200psi) with a 1.5HL93 live load (also within 5%).
0.25 f c' and from 0.25 f c' to zero necessitated reduc-
ing the girder spacing by an average of about 10%. The Effect of reducing the allowable
greatest reductions in spacing occurred at the greatest span concrete service load tensile stress
lengths. and increasing the design live load
Alternatively, the girder spacing can be maintained by in- The worst-case scenario was encountered when the design
creasing the 28-day concrete strength by 5MPa (700psi). live load was increased by 50% (from HL934 to 1.5
For example f c' can be increased from 40 to 45MPa (5800 HL935) and the allowable concrete service load tensile
and 6500psi) or 45 to 50 MPa (7200psi) if (e)T is reduced stress (e)T was reduced from 0.5 f c' (6 f c' ) (normal en-
from 0.5 f c' (6 f c' ) to 0.25 f c' (3 f c' ), or 0.25 f c' to vironment) to 0.25 f c' (3 f c' ) (aggressive environment)
zero. and to zero (extremely aggressive environment).
as a function of the 28-day concrete strength, design live girders were also required to comply with the edge
load, and environmental classification. Table4 summarizes distance limits (Fig.2).
results, which are discussed as follows:
If the live load was increased to 1.5 HL93 live
For f c' of 40MPa (5800psi), HL93 live load, (e)T of load, S reduced to 1.65m (5.45ft) for f c' of 40MPa
0.5 f c' (6 f c' ) (normal conditions), the girder spac- (5800psi), for example, seven girders. If f c' was
ing S was 2.3m (7.6ft). For an 11.2m (37ft) width, increased to 50MPa (7200psi), S increased to 2.35m
five TypeVI girders with an edge distance Le of 1m (7.8ft), for example, five girders (same as for normal
(3.3ft) were required (Fig.2). For f c' of 45MPa conditions).
(6500psi), though the girder spacing S increased to
2.65m (8.75ft), the number of girders remained at For f c' of 40MPa (5800psi), HL93 live load and
five to satisfy the edge distance limits (Fig.2). If f c' (e)T equal to zero (extremely aggressive condi-
was increased to 50MPa (7200psi), the number of tions), S was equal to 1.85m (6.1ft) (for example, six
girders reduced to four with S equal to 3m (9.93ft). girders). For f c' of 45MPa (6500psi), S increased to
2.25m (7.4ft), (for example, five girders, which is
If the live load was increased to 1.5 HL93 live the same as for normal conditions). For f c' of 50MPa
load, S reduced to 1.9m (6.2ft) for f c' of 40MPa (7200psi), though S increased to 2.55m (8.4ft), five
(5800psi), (for example, six TypeVI girders with Le girders were also required to comply with the edge
of 0.85m [2.8ft]). For f c' of 45MPa (6500psi), S distance limits (Fig.2).
increased to 2.25m (7.45ft) (for example, five girders,
which is the same as for normal conditions). For f c' If the live load was increased to 1.5 HL93 live load, S
of 50MPa (7200psi), though S increased to 2.55m reduced to 1.4m (4.63ft) (for example, eight girders). For
(8.4ft), five girders were also required to comply with f c' of 50MPa (7200psi), S increased to 2m (6.6ft) and
the edge distance limits (Fig.2). the number of girders reduced to six.
'
For f c of 40MPa (5800psi), HL93 live load and The numerical application illustrated the benefits of in-
(e)T of 0.25 f c' (3 f c' ) (aggressive conditions), creasing the concrete strength f c' on the design of precast
S was equal to 2m (6.6ft) (for example, six gird- concrete girders subjected to increased live loads. Based
ers). For f c' of 45MPa (6500psi), S increased to on HL93 live load, it was shown that increasing f c' to
2.45m (8.1ft), (for example, five girders, which is 50MPa (7200psi) reduced the number of girders by one.
the same as for normal conditions). For f c' of 50MPa This effect was more noticeable when the live load was
(7200psi), though S increased to 2.8m (9.2ft), five increased to 1.5 HL935 and the environmental classifica-
tion was set as extremely aggressive, where (e)T was equal spans measured between centerlines of piers, the total
to zero, as the number of girders reduced from eight for f c' number of spans in all three bridges was 90 (25 + 25 + 40),
of 40MPa (5800psi) to six for f c' of 50 MPa (7200psi). and the total number of modified TypeVI precast concrete
girders was 905. If f c' was increased to 50MPa (7200psi),
Practical application the modified TypeVI girder spacing would increase to
2.55m (8.4ft). For example, the number of girders could
The numerical application was based on data taken from a be reduced by about 20%, a savings of 180girders. Alter-
recently completed project in the Middle East13 that com- natively, the smaller TypeVI girders could have been used
prised a 1000m long (3300ft), 28.9m wide (94.8ft) main based at the same spacing of 2m. This clearly illustrates
bridge; a 1000m long (3300ft), 27.5m wide (90.2ft) the cost and time savings benefits of increasing the con-
utility bridge; and a 1640m long (5380ft), 12m wide crete strength.
(39ft) trestle bridge (Fig.8) subdivided into 40m (130ft)
spans measured between centerlines of piers and designed Conclusion
according to British Standards7,8 using a concrete cylinder
strength f c' of 41.7MPa (6000psi). It was shown in the AASHTO HL93 live loads do not always represent the
numerical example that for extremely aggressive environ- actual traffic conditions for bridge design, especially in
mental conditions and 1.5 HL93 live load, AASHTO regions where the enforcement characteristics on truck
TypeVI girders spaced 1.4m (4.6ft) were required for f c' weight distributions are more stringent.6 Increasing live
of 40MPa (5800psi), and the spacing S increased to 2m loads (1.5HL93), required a reduction of the girder
(6.6ft) for f c' of 50MPa (7200psi). However, 90tonne spacing by 20%. This reduction in girder spacing could
(200kip), modified TypeVI girders were fabricated instead be compensated by increasing the concrete strength f c' by
to match the larger girder spacing of 2m (6.6ft) that was approximately 5MPa (700psi). A more severe situation
presented in the original design.13 Based on 40m (130ft) was encountered when the live load was increased and the
Furthermore, the design aids provided in this paper not 9. Gergess, A., and R. Sen. 2013. Design of Precast
only set up the basis for optimization but also helped re- Bridge Girders Made Continuous under Increased
duce trial and error in predicting the precast concrete girder Live Loads. PCI Journal (Spring).
size and spacing for a wide range of bridge live loads
and configurations. Such information paves the way for 10. Russell, B. W., and N. H. Burns. 1993. Design Guide-
more rigorous investigations on the effects of new trends lines for Transfer, Development and Debonding of
of bridge design live loads that could be soon adopted in Large Diameter Seven Wire Strands in Pretensioned
design specifications. Concrete Girders. Research report 1210-5F. Austin,
Tex.: Center for Transportation Research, University
Acknowledgments of Texas at Austin.
The authors are indebted to Miroslav Tepavcevic, technical 11. Hambley, E. C. 1991. Bridge Deck Behavior. 2nd ed.
director of Al-Meraikhi Industrial Complex in the United London, UK, and New York, NY: E & FN Spon, an
Arab Emirates (www.almgroup.ae) for sharing informa- imprint of Chapman and Hall.
tion on its innovative precast, prestressed concrete girder
fabrication techniques. They thank Khaled Al-Sayed from 12. FDOT (Florida Department of Transportation). 2010.
Archirodon Construction for his great assistance, and due Florida Department of Transportation Structural
acknowledgment is also given to Abu Dhabi Ports Co., cli- Design Guidelines. Tallahassee, FL: FDOT Structural
ent for Khalifa Port Bridges project. Design Office.
4. AASHTO. 2010. LRFD Bridge Design Specifications. f c' = 28-day concrete compressive strength
5th ed. Washington, DC: AASHTO.
f ci' = concrete strength at release
5. Abu Dhabi Municipality. 2008. Structural Design Re-
quirements for Bridges. Municipality of Abu Dhabi. fpj = jacking strength
www.adm.gov.ae.
fpu = minimum tensile strength.
6. Sivakumar, B., and F. Sheikh Ibrahim. 2007. En-
hancement of Bridge Live Loads Using Weigh-in-Mo- Icg = moment of inertia of precast concrete girder
tion Data. Bridge Structures 3 (34): pp. 193204.
L = span length
7. BSI (British Standards Institute) 2006. Steel, Concrete
and Composite Bridges Part 2: Specification for
S = girder spacing
American Association of State Highway and Trans- This paper was reviewed in accordance with the
portation Officials (AASHTO) design live loads are Precast/Prestressed Concrete Institutes peer-review
sometimes increased as directed by relevant authorities process.
to reflect actual traffic conditions. A 50% increase is
adopted in some regions of the Middle East based on Reader comments
comparisons of AASHTO LRFD specifications HL93
live loads with the British Standards HA + HB live Please address any reader comments to journal@pci
loads. Even in some U.S. jurisdictions, the AASHTO .org or Precast/Prestressed Concrete Institute, c/o PCI
live loads may not represent modern truck configura- Journal, 200 W. Adams St., Suite 2100, Chicago, IL
tions. This paper examines the effects of increasing 60606. J
AASHTO LRFD specifications HL93 live loads on