Vous êtes sur la page 1sur 11

Society of Petroleum Engineers

SPE 26334

Recovery of Attic Oil Through Horizontal Drilling


E.J. Martins and N.J. Larez, Maraven S.A., and W.G. Lesso Jr., Anadrill Schlumberger
SPE Members

Copyright 1993, Society of Petroleum Engineers, Inc.

This paper was prepared for presentation at the 68th Annual Technical Conference and Exhibition of the Society of Petroleum Engineers held in Houston, Texas, 3-6 October 1993.

This paper was selected for presentation by an SPE Program Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper,
as presented, have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material, as presented, does not necessarily reflect
any position of the Society of Petroleum Engineers, its officers, or members. Papers presented at SPE meetings are subject to pUblication review by Editorial Committees of the Society
of Petroleum Engineers. Permission to copy is restricted to an abstract of not more than 300 words. Illustrations may not be copied. The abstract should contain conspicuous acknowledgment
of where and by whom the paper is presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A. Telex, 163245 SPEUT.

Abstract recovery of most of the remaining reserves in a cost


effective manner. The experience gained on this well is
The production of moderate-sized oil reservoirs, wedged serving as the basis for other horizontal projects in Lake
up against major faults, frequently leaves residual Maracaibo and other parts of Venezuela.
hydrocarbons towards the top of the trapping mechanism
involved. The beds are usually dipping at a high angle.
Recovery of this attic oil in geologically complex reservoirs Introduction
with conventional vertical or directional wells is, in general,
not cost effective because of the reduced vertical column Various trapping mechanisms have allowed migrating oil to
of oil in place and the ease of water coning. This situation accumulate Into reservoirs where size would be defined by
exists in several Bloque I, Lake Maracaibo, Venezuela the extent of the trap and porous rock below it. These
reservoirs that have produced oil over the past 40 years. reservoirs, upon discovery and production, yield
A horizontal drainhole was planned, drilled and produced hydrocarbons and pressure in a pattern depending on the
in one of these attic sections parallel to a large fault to location of the wells and their perforations. The result after
recover a higher percentage of the remaining reserves. many years of production is an influx of water consolidating
The location was identified using 30 seismic and confirmed hydrocarbons towards the top of the trap and thus causing
with reservoir modeling and historical data. In addition, a small pockets of oil to be isolated from each other. This is
pilot was drilled near the heel of the well to confirm the attic oil. This, coupled with an uneven oil-water contact,
sand location. The first attempt to land a horizontal makes further exploitation difficult. The reduced vertical
drainhole missed the sand due to the complexity of the height of pay, lower reservoir pressures, and greater
geologic structure. A timely assessment of geologic and relative permeability of water to oil result in new wells,
geometric data yielded a new model of the sand location. which attempt to tap these hydrocarbons, not findin9 much
This, coupled with geo-steering techniques, allowed a to produce or watering out quickly upon production. A
second drainhole to successfully follow the sand in oil for large percentage of oil in place is then left as being
more than 1100 ft. The well was completed with 7" casing uneconomic to recover.
having a slotted section along the drainhole. Initial tests
showed 2400 BOPO. This was an eight-fold increase as This scenario has developed in Bloque I, Lake Maracaibo,
compared to several vertical wells in the same reservoir. Venezuela. A series of massive faults has allowed oil to
accumulate. Production from the 1950's to the present day
The project was an overall success. Costs and time spent have reduced reservoir pressures and brought the oj(-
in drilling and completion were within expectations. This water contact up. A fault, named the Icotea, has a
paper will show that coordination of the project through an vertical displacement exceeding 2,000 ft with several
Integrated team consisting of the operator's and the smaller faults nearby. Large amounts of oil have been
various contractor's personnel was key in producing this produced. In one region, VLA-8, 42 million barrels have
result. Based on the first six month's production been produced from 118 million estimated barrels of
performance, the well has paid for itself, and it will allow reserves in place. Figure 1 shows the location of the

201
References and illustrations at end of paper.
2 RECOVERING ATTIC OIL THROUGH HORIZONTAL DRILLING seE 26334

region and wells drilled. Virgin reservoir pressures of 3200 the exact location of the C-7 reservoir. Seismic lines have
psi have fallen to 1800 psi in some parts of the area. been merged into a database for the area. New lines
Production has come from three sand groups, the C-5, C- were interpolated with 3D processing along the azimuth of
6, and C-7. Figure 2 shows recent three month average the fault and perpendicular to it. ihis enabled project
production of several wells in the region. Most wells have planners to get a feel for the stratigraphy. The
watered out and have been shut in. Production modeling perpendicular lines were viewed about every 500 feet
confirmed that significant oil remains near the fault. along the fault line and intended drainhole azimuth. One of
Recently drilled wells broke to water either immediately these plots is shown in figure 4.
upon being put on production or within two months.
Three different pilot hole options were considered (figure
A new production approach was needed. In early 1992 a 5). A 55 degree pilot near the heel of three proposed
project was started to model and review the economics of horizontal paths was selected as a compromise of location
using a horizontal drainhole to capture a significant and cost. This further reflects the complex nature of the.
percentage of the remaining reserves while delaying water stratigraphy and uncertainties in the actual location of the
breakthrough as long as possible. The idea was to rely on Icotea fault along the path and irregularities in the oil water
a lower drawdown pressure during production to avoid contact. The resolution of these issues was the prime
water coning. The drainhole would have to be precisely objective of the pilot. From a drilling standpoint,
placed in the sand close to the fault, in a non-watered-out directional experience gained from a higher angle pilot
section, and as far above the water as possible. All of would help in horizontal operations, since no directional
this was complicated by the sand dip varying from 30 to 45 wells had been drilled in this field.
degrees caused by the proximity of the fault. The
procedures used to plan, execute, evaluate, complete The well path trajectory would be geo-steered with an
and produce this project are the subject of this paper. MWD system. The formation would be evaluated in real-
time while drilling using a gamma ray and 2 mHz dual
resistivity tool. Density and neutron porosity data would
The Geological Model be recorded in downhole memory for later retrieval.
Precision directional control in both the pilot and drainhole
The attic in the VLA-8 region is comprised of a strongly would be achieved using an adjustable bent housing
faulted area sealed on the west by the major structural steerable system. Figure 6 shows the basic BHA and drill
features of the Maracaibo basin. This is the Icotea fault string design to be used in the high angle sections. Due
which runs generally on a north-south pattern. The to depleated formation pressures, a low density PHPA
reservoir is limited by an oil-water contact estimated at mud system was selected to provide improved cuttings
7118 ft SS as the sand dips down towards the east. The transport in high angle sections.
region is separated from other regions on the north and
south by normal faults (figure 3). This structure has been The drilling log data program would be supplemented by
interpreted as a high dip faulted monocline striking conventional wireline logs designed to gain critical
northeast to southwest. The productive sands in this area information concerning high angle drilling. Among standard
are C-6 and C-7. Each have been divided into three formation evaluation logs, a rock mechanics sonic evaluation
intervals -- Superior, Medium and Lower respectively. The would be made to determine formation mechanical
C-7 reservoir in particular is made up of massive sand stability. This is a prerequisite for horizontal operations.
packages with thicknesses varying between 60 and 200 ft,
which represents a complex fluvial delta model. The plan called for 9 5/8" casing to be set at the beginning
of a safety tangent section to allow flexibility in decisions
The C-7 is formed by seven sedimentary units which are concerning the final trajectory. Maintaining flexibility in the
part of a series of channels and meandering bars generally plan was a key strategy of the project. Further flexibility
oriented north-south throughout the field. This reservoir was planned so that the drainhole could be completed
has produced with a high water cut for more than 30 years with either a fully cemented and perforated liner or simply
which has increased sharply in recent years. The large with a slotted liner.
water production is due to a very active water drive and
historically high drawdown pressures to which the wells
have been subjected. Further exploitation of these sands Cross-Discipline Coordination
with vertical wells drilled in the crest of the structure would
have the same limitation and would not guarantee A multi-discipline group was formed to coordinate
significant recovery. operations, analyze information coming from the well, and
properly execute modifications to the plan. The team was
The fact is that large amounts of oil remain, and these can made up of specialists from geology, engineering and
not be produced by normal means. Thus, the field is an field operations groups of the operator and personnel
ideal candidate for horizontal drainhole exploitation. from the various service companies. The team would meet
on a scheduled daily basis and be available 24 hrs a day
during critical operations. A mission control center was
Well Design established as a focal point for the variety of data
acquired. There geologic and directional plots could be
A review of seismic data showed the complexity of the merged and reviewed with newly incoming data by' the
field and begged the question for additional information on team. Variations in stratigraphy required flexibility in

202
SEE 26334 E MARTINS. N. LAREZ and W. LESSO. JR. 3

directional targeting. The group had to come to a degrees from the pilot; it flattened out, and eventually
consensus on actions to be taken while drilling. Mission started dipping down. A 6 degree/100 ft build to 95
control was linked to the rig, which was about 20 miles degrees was planned with an intersection of the sand
away by phone, fax and data transmission. Fax with target point at 6380 ft (tvd). This was 996 ft along the
discussions by voice proved to be the most effective. project azimuth of 16 degrees. Various markers along the
way down to C-7 Superior were selected that could be
found with either the LWD gamma ray or resistivity
Pilot Operations sensors. The idea was to verify the approach to horizontal
with these anomalies and adjust the trajectory accordingly.
One conclusion of the pre-drilling planning was that there
was considerable uncertainty surrounding the location and The final build to horizontal began. Early correlations came
quality of the C-7 sands. The objective of the pilot was to in slightly shallow, indicating a higher dip than expected.
determine the course for the drainhole. The pilot, including The trend continued until the point where the C-7 was now
the vertical section, first build, and tangent section through projected to be more than 50 ft shallower. The wellbore
the C-7 series was drilled in 13 days. The first build was would penetrate through the sand into the water leg which
planned for 6 de~rees/1 00 ft. This would be similar to would render the drainhole useless. This, in fact,
curve rates used In the high angle section. One purpose happened. The team had to develop a tactic to deal with
of this was to test directional drilling tools and techniques. this local geologic anomaly. The wellbore was turned up in
Several different bits were also tested. These included an attempt to find the bottom of the oil leg of the sand.
IADC 437 and 519 roller cone bits and two soft formation Inclination reached 100 degrees. The bottom was found,
PDC bits. While these bits were not exactly matched to and the hole was plugged back. Data indicated that the
the formation for maximum rate of penetration, they would formation dip was the expected five degrees. A fault was
provide two workable alternatives in high-angle drilling. suspected but was not supported by seismic or other
Thus, after drillinQ the pilot hole, it was learned that a 1.5 data. The team began an in-depth review of drilling and
degree bent hOUSing motor would deliver 7-9 degrees/100 formation data. Resolution was not forthcoming.
ft of build. Also, the PDC bits would be difficult to steer
but could deliver good rates of penetration when rotated. A possible solution came from the effects of azimuthal
Steel bearing roller cone bits were effective in avoiding changes and the high transverse dips relative to the well
bearing failure due to rotary drilling with the bent housing. path. As azimuth varied, the path moved towards or away
Problems were noted with maintaining bit gauge and bit from the fault. A move towards the fault, which occurred in
tooth gauge which adversely affected steering. the just completed operation, resulted in penetration
lower in the sand package. This was due to the beds
The pilot penetrated two promising sections of the C-7. dipping up towards the fault at an estimated 35 degrees.
The shallower one, the C-7 Superior, was an excellent Figure 8 IS the horizontal plot of the well path trajectories.
show. The sand was 144 ft thick consisting of 62 ft of oil on It shows that the azimuth changes were relatively small, but
top of 82 ft of water. A volumetric interpretation of the the effect was significant on the sand location. Other minor
sand is shown in figure 7. This corresponded to a true variations in dip caused the picture to become quite
vertical thickness of 41 ft of oil and 54 ft of water. Rock complex. A model was worked out that could be used on
mechanical properties computed from sonic 10Q data a second attempt. This evaluation took place in the five
indicated that the sand would be stable for a hOrizontal days needed to plug back the first drainhole and sidetrack
wellbore to be drilled through. for the start of the second. It was here that cohesive
teamwork among geologists, engineers and directional
Suitable well bore stability is represented in the form of a drillers paid off.
safe mud weight window. 1 The lower boundary is the
minimum mud weight to prevent sloughing, while the As in the first wellbore, early correlations would be used
upper limit is the maximum mud weight before losses. to determine the position of the well path with respect to
The window narrows as wellbore angle increases. At 90 the formations. These correlations again indicated high
degrees, a window must exist in order to realistically formation dips. Computations were made to correct for
expect to drill. The analysis for the C-7 Superior is also the azimuthal changes, and a pattern was locked onto. This
shown in figure 7. The window is shown for wellbore indicated that the landing would be successful. The path
inclinations of 50 and 90 degrees. The safe window width entered the top of the sand at 6750 ft with an inclination of
is about 15 ppg in the oil leg of the sand and slightly less 87.6 degrees. This finished the first phase of the
in the water section. Reduction of the window due to navigation. The second phase would be to steer within
increasing inclination is minimal. The decision was made to the sand, staying as far away from the oil-water contact as
proceed with a drainhole. The pilot was plugged back, possible.
9 5/8" casing was set, and new targets selected.
The pilot hole log across the sand would be the key map
for navigating the drainhole. The gamma ray and resistivity
Dralnhole Operations measurements from the LWD tool would be the indicators.
Updating Models and Steering Decisions This data from the pilot log is shown in figure 9. Small
changes in sandlshaliness are labeled as markers "a" thru
The project team correlated the pilot log data with nearby "k". The team would attempt to determine elevation in the
wells, specifically VLA-929, 462 and 417. The correlation sand from these markers as the drainhole progressed.
indicated that the C-7 Superior was dipping up about 5

203
4 RECOVERING ATTIC OIL THROUGH HORIZONTAL DRILLING SPE 26334

A five degree up-dip was expected so penetration


through the first few markers was anticipated based on the Production Results
entry angle mentioned above. As the path went into the
sand, angle was built up to 96.6 degrees. Markers "a" thru The well was brought in initially with a 318" choke. This was
"f" were penetrated with a turn-around section in "f" opened to 1/2", 3/4" and 1" over the course of 16 days.
indicating that the path was going up into He". The labeled The final test resulted in 2456 BOPO. Figure 12 shows the
log for the drainhole is also shown in figure 9. This was not production test profile. Water production was less than 2
a clear cut interpretation. The further away from the pilot percent. It was decided to produce the well on a 5/8"
that the drainhole went, the more suspect the analysis choke. The well has averaged 1400 BOPO for the five
became. Towards the end of the drainhole with several months time up to the wnting of this paper. Water
hundred feet of oil sand, it was decided to steer production has risen to 4%. The production history is
aggressively upwards. The idea was that it would be shown in figure 13. The well has paid for itself and is a .
better to drill out into the shale above rather than into the commercial success.
water below. Inclination was maintained between 95 and
96 degrees. A correlation was made that indicated travel
up thru members "d", "c", "b" and "a" and finally out of the Conclusions
sand and into the shale above. This interpretation was
made using the LWO data in real-time. The path was Horizontal drilling in sand/shale sequences where there is a
steered down and back into the sand. Another form of production problem such as water coning is most
correlation data was used effectively at this point. successful when the drainhole is geo-steered. In other
Sedimentology facies within the sand were correlated words, targets of opportunity as spotted from real-time
which also indicated that the path was nearing the top of drilling logs must be taken advantage of. The C-7
the sand. This exit and subsequent reentry served a very Superior sand was the explicit target, not a geometric
useful purpose in verifying the effectiveness of these two point defined by a TVO, Northing and Easting. The
navi~ation techniques. The drainhole trajectories are shown trajectory was adjusted to follow it. The operator's
in figure 10. The drainhole reached its planned procedures have to allow rapid approval of changing
displacement with 1112 ft of net pay sand. target locations. The service companies have to be able
to respond with BHA's and drilling procedures to hit a
moving target.
Completion and Production Decisions
A team representing the various disciplines needed to
Final correlations indicated that the closest approach of the execute this project was formed. This resulted in timely
drainhole to the water leg of the C-7 Superior was 18 ft. decisions on subjects from trajectory modifications and
This distance allowed the completion design to center drilling operations to the completion design.
around using slotted casing in the productive zone. There
were two problems that had to be dealt with. First, the The high transverse dip, 35 degrees up towards the Icotea
open hole below the 9 5/8" shoe which contained gas fault, resulted in azimuth controf being critical. This was not
sections, had to be hydraulically sealed from oil accounted for in the original plan and it resulted in the
production. Second, there were concerns that the slotted abandonment of the first drainhole. The team was
section might not be able to slide to TO. The slotted effective in resolving this problem and designing a
section needed to be centralized to avoid plugging a large successful recovery.
proportion of the slots.
To effect solutions to these two problems, it was decided Future Plans
to set 7" casing to surface, rather than as a liner with its
associated liner hanger,. Casing would provide pushing There are a large number of fields similar to VLA-8 in a
power to get to TO. It would also provide excellent mature area such as Lake Maracaibo. This new capability
Isolation from the gas. Slotted 7" pipe with 96 0.02" by has led to the generation of new prospects by the three
1.75" slots per foot would be placed In the bottom 1300 ft Venezuelan operating companies both In the Lake and on
of the hole. The casing string was run in the hole without land. Several of these prospects will have been drilled
incident. It remained to isolate cement flow from the by the time this paper is published.
slotted pipe and to direct it up the annulus between the 7"
and 9 5/8" casings. An inflatable external casing packer
(ECP) was placed above the slotted section along with a Acknowledgements
port collar. Cement was then pumped, without affecting
the slotted section, 1500 ft above the 9 5/8" shoe. This The authors would like to note that they were only
provided the hydraulic seal needed. members of a larger team and recognize those who
contributed to the success of this project. This project
The low reservoir pressure (1200 psi) required artificial lift involved a different style of working for many people and
for production. 3 1/2" tubing was run with two gas lift their extra efforts should be applauded. We also would
mandrels at 3838 ft and 5838 ft. A sketch of the completion like to thank the management of Maraven and
design is shown in figure 11. The well was now ready for Schlumberger for encouraging such a project and
production. permission to publish the results.

204
SPE 26334 E. MARTINS, N. LAREZ and W. LESSQ. JR. 5

References
1. Bruce,S., MA Mechanical Stability LogM, SPElIADC
19942, SPElIADC Drilling Conference, February 1990.

Figure 1
Location of the VLA-8 Region in Bloque 1 of Lake Maracaibo. Venezuela
Showing the Location of the Horizontal Project and Nearby Wells.

205
1500

1000

~
~ 500 oil

o
VLA VLA VLA VLA
VLA VLA VLA VLA 1035
137 417 462 545 546 459 798 HZ
o
.",.,.,.;'
................
'.".,.,-",
500 ,........." ,.......
I.,.,.,.,
I'0"0"'"
..,.".,.,-
.........,
>.".,.".,
'
t:;-:;::;.,,:;.'
'
I\) ...............
..'.,.,.,.,
".,.,." '
o ..............'
..............
m '.,.,.,.,
...........,..
1000 ,.".,.,.,
'.... ,." .... '
'.",.,.,.",
........,......
'.,.,.,.,
.................
,.".".,.,
t:;":;.":;":;~
...........
,.,.,."., ,..
water
~ .................
I.,.,.,."
....,.....-
,"!':'!:.:!:.!-
o
ifi 1500
a:I

2000

2500 (fluid productions based on average of most recently


avaliable three months data)
Figure 3
A Model of the Geologic Structure for the VLA-8 Region of
Bloque 1 in Lake Maracaibo, Venezuela.
Figure 2
Average Production from Nearby VLA-8 Region wells. including the
VLA-1035 Horizontal Well.
VERTICAL PLAN Maraven. S.A.
Proyecto Horizontal C-7
PLANE OF PROPOSAL VLA1035
16.0 0 Bloque 1

2000
HORIZONTAL PLAN
4000

2500
3500

3000 6470 (tvd)


TO
3000
2500

2000
Q)
~-
3500 ~ 1500
.<::
~ t::
0 1000
.<:: Z
Ci. 4000
CD
0 500

~ 0
~I
N
I ~?
.~-,~

?"f"
... ..
.~ ~ 1~~~1 .~~ ~~~ ~W~;:I
._-...~- if, ...
_, t, , __
CD
>
CD
4500 0 500 1000
East (feet)
1500 2000

2
f-

5000

5SOO

6000

6500
I
Pilot Pilot
1 3
7000 1--0
500 500 1000 1500 2000
2500 3000 3500

Displacement (feet)

Figure 4
A West to East Seismic Line Interpolated from 3D Data Crossing Figure 5
the VLA-1 035 Well Profile. The Drainhole is Oriented into the Trajectory Plot of the Various Pilot Options Considered
Page. Components of the Icotea Fault System are Shown. Note
the High Dip Angle of the Target C-7 Where the Well was Drilled.
SPE 26334 E. MARTINS, N, LAREZ and W, LESSQ, JR. 9

2'25
BOSOft
2000 TO Orainhola 2

1875 Plan Una

1750

'825

,sao

'375

1250
Figure 8
Horizontal Trajectory Plot for VLA-1035 of Planned
i' 1125 vs, Actual Well Paths. Note the Relatively SIi9ht Changes
~
in Azimuth that had Major Effects on PosItion In the Sand.
'000
.&:
1::
0 875
Z
750
~ Up-dip
625 direction
35
sao

375

250

'25

III Sholo

o SandyShoio

Drainhole D-
+-
Figure 9

The Pilot and Drainhole Trajectory Sketches with


Labeled Markers. "a" through "k" In the pilot and
"a" through "f" in the drainhole.

Pilot

209
11- RECOVERING ATTIC Oil THROUGH HORIZONTAL DRILLING seE 26334

5400
5400ft KOP

~ 5700

~
-
.I::
a.
~6000
cti
u
8050ft
:e Orainhole 2 TO
Q)
> 6300
Q)
::::l
7276ft 8044ft
~ Orainhole 1 TO
Planned TO

6600

6900
7493ft Pilot TO

7200
300 o 300 600 900 1200
1500 1800 2100
11-23-1992
2400
Displacement (feet)

Figure 10
Vertical Trajectory Plot of Planned vs Actual Well Paths,
Showing Variations in Orainhole Elevations.

13 31S" at 2504'

,._..J----l'---- 31/2" tubing

Gas Lift
Mandrels
3838' and
5838'
9 SIS" at 6062'

Hydraulic
Retrievable
Packer

7"
casing to
TO at 8050'

Figure 11
Sketch of the Completion Design for VLA-1 035.
210
SEE 26334 E MARTINS, N, LAREZ and W, LESSO, JR 11

2500

2000

~
~ 1500
:::::.
.0
e
:=
o
1000
u:
500

o..L...--------+--~f_----__+_----~
3/8" 1/2" 3/4" 1"
Choke Size

Figure 12
Production Test Profile for VLA-1 035,

1600

1400

1200 oil
>-
~ 1000
...
Q)
C- 800
"tJ
'5
u: 600
-J
co 400
co
200
water
0
0 20 40 60 80 100 120 140
Days Since Initial Production (Dec 92 to May 93)

Figure 13
Recent Production for VLA-1 035,

211

Vous aimerez peut-être aussi