Académique Documents
Professionnel Documents
Culture Documents
NUMBER
SH-06/2013
Version 2.0
Revision Record
Version Date Revision Details Author
1.0 7 November 2013 First Issue Ahmed Ibrahim Al Abri
Foreword
Although every effort has been made to ensure the accuracy of the data provided in this statement, Mazoon
Electricity Company SOAC (MZEC) does not accept any liability for the accuracy of the information
contained herein, and in particular neither MZEC nor its directors or its employees shall be under any
liability for any misstatement or opinion on which the recipient of this statement relies or seeks to rely.
Except to the extent that it is related to the work of the Authority for Electricity Regulation, Oman in the
matter of the MZEC Investment Period 2015 2020, no part of this document may be reproduced, stored in
a retrieval system, transmitted or further distributed in any form or means electronic, mechanical,
photocopying, recording or otherwise for any purpose other than with the written permission of MZEC.
Executive Summary
Purpose
The purpose of this pre-investment appraisal document (PIAD) is to find a suitable solution to ensure the
33 kV network supplying the Bediah area:
Removes and avoids overloaded situations and can accommodate expected future load growth.
Rectifies unacceptable customer voltages and maintains them within prescribed limits.
Meets required security of supply standards.
The present network does not comply with MZEC Distribution System Standards of Security (DSSS) both
in terms of substation firm capacity and circuit connectivity, is subject to complaints of low voltage in
some areas, and has insufficient capacity for predicted load increases, mainly in a large development area.
Moreover, MZEC will pay penalty of 2200 OMR/MW for each substation of non secure capacity.
PIAD SH-05/2013 is currently being prepared to ensure sufficient 132/33 kV substation capacity is
available for increasing loads in the area. It recommends establishment of a new Bediyah 132/33 kV
substation and indicates how new 33 kV circuits proposed below should be connected. Options for 33 kV
reinforcement presented below are based on this, but noting that 132 kV reinforcement is unlikely to be
completed before 2018.
Proposals are considered separately for the various issues to be resolved as follows:
Increase substation firm capacities at or near Al Wasil and Mintrib substations and avoid overload of
33 kV circuits
This is needed as existing substations are loaded above their firm capacity, and a large increase in capacity
is needed for a development area.
The following Options were considered:
Option 1
Reinforce Mintrib substation.
Establish new Al Shariq substation, supplied from the new Bediyah 132/33 kV substation proposed
in PIAD SH-05/2013, and reinforce it later.
Option 2
Establish new Al Shariq substation supplied from the existing Mudhairib 132/33 kV substation.
Reinforce Mintrib substation later.
Capital costs and net present value (NPV) analysis are summarised below.
Total Sche me NPV Capitalised NPV Capitalised Total NPV
MZEC Capital Total NPV
Option NPV Capital Cost Losses Losse s (inclusive 35 years
cost (to 2020)
(2014-2020) (up to 2020) (up to 2050) losses)
Option 1 OMR 4,460,500 OMR 3,591,237 OMR 1,628,873 OMR 6,935,847 OMR 5,220,110 OMR 10,527,084
Option 2 OMR 5,722,200 OMR 4,794,630 OMR 1,988,482 OMR 8,795,253 OMR 6,783,112 OMR 13,589,883
Option 1 has much lower capital cost and losses and therefore a much lower present value. It is the
recommended scheme as PIAD SH-05/2013.
Date of Issue: 10 December 2013 Page: 3 of 64
Version 2.0
Pre-investment Project Appraisal Project Number: SH-06/2013
Both schemes would provide more than sufficient capacity for the investment period.
Option 5 provides higher capacity, facilitates connection of additional 11 kV feeders, and provides better
voltage control and higher security of supply compared to Option 4. However, Option 4 is recommended
as it provides more than sufficient firm transformer capacity and increases security of supply to comply
with DSSS at much lower cost and present value compared to Option 5.
Improve voltage regulation at, and increase firm circuit capacity to, W Bani Khalid substation, and
increase network security of supply
The following Options were considered:
Option 6
Second 33 kV circuit to W Bani Khalid substation from the Hiyal tee feeder.
Option 7
Second 33 kV circuit to W Bani Khalid substation from Bediyah 132/33 kV substation.
Option 6 was rejected as it did not ensure satisfactory network voltages.
Option 7 adds a third feeder into an existing two-feeder ring network and adds telecontrol facilities at some
sites. It thereby reduces load supplied by each feeder with corresponding improvement in system voltage
and ensures compliance with DSSS. A temporary connection arrangement is included so that benefits can
be obtained in advance of full completion when the new circuit is connected to the new Bediyah 132/33 kV
substation in 2018.
Option 7 is therefore recommended. The estimated cost is OMR 1,591,829.
Overall recommendation
The recommended scheme is a combination of Options 1, 3, 4 and 7 as above.
A technical verification was undertaken, to confirm that the proposed reinforcement results in a system that
is practical to install, operate and maintain and ensure long term compliance with security standards.
Mazoon Electricity Company SAOC recommends that the recommended Options be authorised at a total
cost to the MZEC of OMR 7,413,579 and be carried out from 2014 to 2020 to achieve the outcomes and
benefits detailed in this Pre-Investment Appraisal Document.
Risks
The main risks with this project are:
The programme for design and delivery of the scheme is delayed.
The project must be driven to minimise delays to ensure early compliance with security standards
and provision of sufficient network capacity for new loads.
That the new 132/33 kV substation being proposed on PIAD SH-05-2013 is delayed.
Most of the recommended proposals below do not rely on this being available, but it is needed for
connection of the proposed new Al Shariq 33/11 kV substation. Therefore early engagement with
OETC is necessary.
Contents
REVISION RECORD ................................................................................................. 2
FOREWORD 3
CONTENTS 6
1 INTRODUCTION ................................................................................................ 8
1.1 Definition of project need ....................................................................................................................... 8
1.2 Current and planned situation............................................................................................................... 8
1.3 Load forecast and related issues ...........................................................................................................10
1.3.1 Basis ............................................................................................................................. 10
1.3.2 Substation loadings..................................................................................................... 10
The colour coding: ...................................................................................................................... 12
1.3.3 33 kV feeder loadings ................................................................................................. 13
1.3.4 Other 33 kV feeder issues .......................................................................................... 14
1.4 Base year .................................................................................................................................................15
1.5 Losses ......................................................................................................................................................15
1.5.1 Peak MW value before reinforcement ...................................................................... 15
1.5.2 Estimation of cost ....................................................................................................... 15
1.5.3 Estimation of net present value (NPV) ..................................................................... 16
2 PROPOSALS ..................................................................................................... 17
2.1 Proposed 132/33 kV substation reinforcement ....................................................................................17
2.2 To increase substation firm capacities at or near Al Wasil and Mintrib substations and to avoid
overload of Mintrib 2 and 3 33 kV circuits .......................................................................................................17
2.2.1 Requirement and list of options ................................................................................ 17
2.2.2 Option 1 - Reinforce Mintrib substation. Establish Al Shariq substation and reinforce
it later 19
2.2.3 Option 2 - Establish Al Shariq substation. Reinforce Mintrib substation later .. 23
2.2.4 Comparison of options ............................................................................................... 27
2.2.5 Recommended reinforcement.................................................................................... 27
2.3 To increase firm capacities at Lawrangh and Hiyal substations .......................................................28
2.3.1 Requirement and options ........................................................................................... 28
2.3.2 Option 3 - Uprate Lawrangh and Hiyal substations to 2 x 6 MVA ....................... 28
2.3.3 Recommended reinforcement.................................................................................... 31
2.4 To increase transformer firm capacity at W Bani Khalid substation ...............................................31
2.4.1 Requirement and list of options ................................................................................ 31
2.4.2 Option 4 - Add third 6 MVA transformer at W Bani Khalid substation. ............. 32
2.4.3 Option 5 - Reinforce W Bani Khalid substation to 2 x 20 MVA ............................ 35
2.4.4 Comparison of options ............................................................................................... 38
2.4.5 Recommended reinforcement.................................................................................... 39
2.5 To improve voltage regulation at, and increase firm circuit capacity to, W Bani Khalid substation, and
increase network security of supply ..................................................................................................................39
2.5.1 Requirement and list of options ................................................................................ 39
2.5.2 Option 6 - Second circuit to W Bani Khalid substation from the Hiyal tee feeder39
2.5.3 Option 7 - Second circuit to W Bani Khalid substation from Bediyah 132/33 kV
substation .................................................................................................................................... 41
3 RECOMMENDED SOLUTION.......................................................................... 45
3.1 Combination of options .........................................................................................................................45
3.2 Technical verification ............................................................................................................................46
3.2.1 Fault level .................................................................................................................... 46
3.2.2 Load flow analysis ...................................................................................................... 47
3.2.3 Compliance to DSSS requirements ........................................................................... 48
3.3 Indicative investment programme ........................................................................................................49
4 RECOMMENDATION....................................................................................... 50
5 AUTHORISATION ............................................................................................ 51
1 Introduction
1.1 Definition of project need
The drivers for the proposed reinforcement covered by this Pre-Investment Appraisal Document (PIAD)
are to:
Ensure the 33 kV networks supplying Mintrib, Al Wasil, Tawi Salim, Lawrange, Fashaga, W Bani
Khalid, Hiyal and Dhubaha 33/11 kV substations have sufficient capacity for expected future
loadings.
Overcome existing unacceptable low voltage and avoid it in the future.
Remedy the existing non-compliances with security of supply standards, and ensure compliance
into the future. Condition 31: Section 4(a) of the MZEC License states that the Licensee shall
plan and develop its distribution system in accordance with the approved Distribution System
Security Standards (DSSS). The security standards are shown in Table 1.
Table 1: MZEC Distribution System Standards of Security
B 2 to 6 MW 3 Hours* No requirement
* For 11 kV networks in remote areas this restoration time may be extended by the time it
reasonably takes for a repair crew to reach the area with the outage as long as the total
restoration time will not exceed 6 hours.
** Planned outages are assumed to be restricted to the maintenance period when due to lower
ambient temperatures demand is reduced and equipment ratings enhanced.
It needs to be read in conjunction with PIAD SH-05/2013 which is being prepared alongside this PIAD. It
addresses the need for 132/33 kV substation reinforcement, and its recommendations are influenced by the
33 kV network issues addressed below.
7 km
New open point 2013
2.7 3.7
7 km
Hiyal Lawrangh
1 x 6 MVA 1 x 6 MVA
7 km
3 13 km
32 km
2013
13 km 11 km 1.5
2020
12 km
11 km 1 km
Mintrib
2 x 20 MVA
2013
22.4
Notes: 2020
59.6
All circuits are shown overhead, but there are
some short cable sections.
Street lighting 33 kV / LV transformers are not shown.
Lengths are rounded to nearest km.
Blue indicates proposal being considered separately.
Green indicates approved separate proposal.
2013
3.7 Indicates actual 2013 load / estimated 2020 load.
2020
6.2
Substation locations, existing circuit routes and main development areas are shown in Figure 2.
Some other 33/11 kV substations presently supplied by Mudhairib 132/33 kV substation will be transferred
to:
A new Ibra 132/33 kV substation 23 km north west of Mudhairib 132/33 kV substation (shown in
Figure 2) which should be commissioned in 2015.
A new Wadi Tayeen 132/33 kV substation in 2017. This is 50 km north of Mudhairib 132/33 kV
substation and is being proposed on PIAD SH-04/2013.
Green indicates
33 kV circuits
Black indicates
132 kV circuits
Yellow
indicates main
development
area
Existing Capacity
Ne w Capacity (MVA) Ye ar
(MVA)
Substation
Capacity Firm Capacity Firm Year of 2013 2014 2015 2016 2017 2018 2019 2020 Growth Comme nt
Transformer
Addition
Ye ar Fe ede r Ye ar Fe ede r
Conne cte d Dis connected
Is sue 1
Subs tations be ing transfe rre d to Ibra and Wadi
Mudhairib 2 x 125 125 63 70 77 86 96 107 119 133 Taye e n 132/33 kV substations by 2017 are not
include d.
Diversity Factor 1.00
Mintrib 2 x 20 20 22.4 25.8 29.6 34.1 39.2 45.1 51.8 59.6 15% Issue 2
Mintrib-2 2013
Mintrib-3 2013
Al Was il 2 x 6 6 6.0 6.5 7.0 7.6 8.2 8.8 9.5 10.3 8% Issue 3
Mintrib-1 2013
Tawi Salim 1 x 6 0 2 x 6 6 2014 1.5 1.7 1.8 2.0 2.2 2.4 2.7 2.9 10%
Mintrib-3 2013
Lawrangh 1 x 6 0 1.9 2.1 2.3 2.5 2.8 3.1 3.4 3.7 10% Issue 4
Mintrib-3 2013
Fashagah 1 x 1 0 0.4 0.4 0.4 0.4 0.5 0.5 0.5 0.5 3% Issue 5
Sooqah 2013
W Bani Khalid 2 x 6 6 4.5 4.8 5.2 5.5 5.9 6.3 6.8 7.2 7% Issue 6
Sooqah 2013
Hiyal 1 x 6 0 1.7 1.8 1.9 2.1 2.2 2.4 2.6 2.7 7% Issue 7
Sooqah 2013
Dhubaha 1 x 3 0 0.8 0.8 0.9 0.9 1.0 1.0 1.1 1.1 5% Issue 8
Sooqah 2013
Mudhairib Grid 2 x 20 20 13.8 15.5 17.3 19.4 21.7 24.3 27.2 30.5 12%
Not subject
to this PIAD
Ibra Hos pital 2 x 10 10 2.9 3.0 3.2 3.4 3.5 3.7 3.9 4.1 5%
Ibra MOD 1 x 6 0 0.9 0.9 0.9 0.9 0.9 0.9 1.0 1.0 1%
Mas roon 1 x 6 0 3.4 3.6 3.8 4.0 4.3 4.5 4.8 5.1 6%
The colour coding for substation loads throughout this report is as follows:
The substation is within firm capacity based on the transformers installed. The total load can be
Green
supplied when one of the transformers is out of service. (DSSS compliant)
The substation is outside its firm capacity, but still within the thermal rating of all the installed
transformers (DSSS non-compliant). When one transformer is out of service, the load needs to
Yellow be reduced. This can be achieved by transferring some load to neighbouring substations (via
the 11 kV system), or load shedding. The extent of the load reduction will depend on when the
outage occurs. This analysis considers only the maximum loads, as the worst-case.
Red The maximum installed capacity of the substation is exceeded at times of maximum demand.
The following substation issues are highlighted (related circuit issues are considered below):
Issue 1 Mudhairib 132/33 kV substation firm capacity
After transfers to planned and proposed 132/33 kV substations, load at Mudhairib 132/33 kV substation is
predicted to increase to 133 MVA in 2020 which exceeds firm capacity.
Year
Substation
2013 2014 2015 2016 2017 2018 2019 2020
Mintrib 5280 12672 21173 30949 42191 55120 69988 87086
Al Wasil No 1056 2196 3428 4758 6195 7747 9422
Tawi Salim No No No No No No No No
Lawrangh No 4598 5058 5564 6120 6732 7405 8146
Fashagah No No No No No No No No
W Bani Khalid No No No No No 685 1657 2697
Hiyal No No No 4582 4902 5246 5613 6006
Dhubaha No No No No No No No No
Total Penalty 5280 18326 28427 44522 57972 73978 92409 113357
Load
Mintrib-1 22.2 22.2 2013 6.0 6.5 7.0 7.6 8.2 8.8 9.5 10.3
Mintrib-2 22.2 22.2 2013 11.2 12.9 14.8 17.0 19.6 22.5 25.9 29.8
Mintrib-3 22.2 22.2 2013 14.6 16.6 18.9 21.6 24.6 28.0 31.9 36.4
Sooqah 22.2 22.2 2013 7.4 7.9 8.4 9.0 9.5 10.2 10.9 11.6
Issue 9
Issue 10
The colour coding for substation loads throughout this report is as follows:
Green The load on the feeder is less than 50% of the circuit rating.
The feeder load is greater than 50% of the circuit rating, but it does not exceed the
Yellow
thermal rating of the circuit.
Red The feeder load exceeds the thermal rating of the circuit.
Voltage
Loads Sooqah load Mudhairib 33 kV W Bani Khalid 33 kV W Bani Khalid 11 kV
2013 Included 28.3 kV (0.86 pu) 11.0 kV (1.00 pu)
33.8 kV (1.02 pu)
2020 Disconnected 27.4 kV (0.83 pu) 10.6 kV (0.96 pu)
This shows the most optimistic situation with 33 kV voltage at Mudhairib 132/33 kV substation set to
+ 2 % and with 33/11 kV transformers at W Bani Khalid 33/11 kV substation manually tapped to 10 %
tap to give maximum boost. In 2020, even with Sooqah substation load disconnected, 33 kV volt-drop is
19 %, and 11 kV busbar voltage 8 % lower than the required 11.5 kV. High volt-drop in 11 kV circuits
adds to this situation. Even lower voltages will occur in the abnormal situations that Sooqah substation is
supplied from this circuit or during an outage of the 33 kV feeder to Tawi Salim substation.
Issue 12 Second 33 kV circuit to Hiyal substation
Hiyal substation is supplied on a single 33 kV circuit. Load will exceed 2 MW and will therefore require a
second circuit to ensure restoration of supply following circuit outages within the 3 hours specified by
DSSS.
Issue 13 Second 33 kV circuit to Lawrangh substation
Lawrangh substation is supplied on a single 33 kV circuit. Load will exceed 2 MW and will therefore
require a second circuit to ensure restoration of supply following circuit outages within the 3 hours
specified by DSSS.
Issue 14 Second 33 kV circuit to W Bani Khalid substation
W Bani Khalid substation is supplied on a single 33 kV circuit. Load exceeds 2 MW and therefore a
second circuit is required to ensure restoration of supply following circuit outages within the 3 hours or 15
minutes specified by DSSS.
Issue 15 Insufficient firm 33 kV circuit capacity
Outage of the Sooqah 33 kV feeder from Mudhairib 132/33 kV substation causes loss of supply to an
aggregate demand of 7.4 MW in 2013 (excluding the Sooqah substation load which will be transferred) and
11.5 MW in 2020. This load is in Class C (6 20 MW) of DSSS which requires restoration in 15 minutes
which is not possible.
Similarly, outage of the Mintrib 3 33 kV feeder from Mudhairib 132/33 kV substation causes loss of supply
to an aggregate demand of 3.4 MW in 2013 and 6.6 MW in 2020. This assumes no loss of supply at
Mintrib substation for this outage as transformers there should normally operate in parallel; at present they
do not as explained above. Once load lost exceeds 6 MW, DSSS requires restoration within 15 minutes
which is not possible.
1.5 Losses
1.5.1 Peak MW value before reinforcement
Network studies using and network configuration as above (i.e. after completion of existing planned
reinforcement) indicate total losses in the 33 kV network shown in Figure 1 of 3.7 MW at 2014 loadings at
the time of network peak loading.
2 Proposals
2.1 Proposed 132/33 kV substation reinforcement
Issue 1 is resolved separately in PIAD SH-05/2013 which considers the impact of 132/33 kV substation
reinforcement on 33 kV reinforcements proposed below as they influence the decision of whether to
reinforce the existing 132/33 kV substation or establish another. It recommends:
Establishment of a new Bediyah 132/33 kV substation to be used to supply the new Al Shariq
33/11 kV substation and a new 33 kV circuit to W Bani Khalid substation proposed below.
The new 33 kV Mintrib feeder proposed below should be connected to Mudhairib 132/33 kV
substation.
This is the basis for options for 33 kV reinforcement presented below, but noting that 132 kV
reinforcement is unlikely to be completed before 2018.
Green indicates
33 kV circuits
Black indicates
132 kV circuits
Yellow
indicates main
development
area
This also shows the assumed location of the new Bediyah 132/33 kV substation being proposed on PIAD
SH-05/2013.
Table 6 summarises loads and firm capacities at Al Wasil and Mintrin 33/11 kV substations.
Table 6 Al Wasil and Mintrib substation loads and firm capacities
This indicates an additional 40 MVA of firm capacity would be sufficient until after summer 2019 when
additional capacity would be needed, assuming predicted load increases materialise.
The following options to provide an additional 40 MVA of firm substation capacity and an additional
20 MVA later should be considered and these are described below:
Option 1
Reinforce Mintrib substation.
Establish Al Shariq substation and reinforce it later.
Option 2
Establish Al Shariq substation.
Reinforce Mintrib substation later.
Figure 4 Additional 20 MVA transformer at Mintrib substation, new 2 x 20 MVA Al Shariq substation (with 3rd
transformer later), transfer of Tawi Salim feeder as Option1
11 kV work to facilitate load transfers needed to keep substations within firm capacity will be minimised
by strategic connection of new loads, and nominal amounts are included in the cost estimate.
New Infrastructure Requirement
Table 7 summarises the main equipment needed.
Assessment
This proposal provides an additional 20 MVA of firm substation capacity by 2016, another 20 MVA in
2018 and another 20 MVA in 2020. This is sufficient to overcome existing n-1 substation overload
situations and provide for planned load increases as shown in Table 8. This also indicates the required load
transfers between 33/11 kV substations; in reality, as most of the new load will be for new development,
most transfers will be avoided by managed allocation of new 11 kV feeders between Mintrib and Al Shariq
substations.
Al Wasil substation remains loaded above firm capacity until 2018. This could be avoided by connecting
Al Shariq substation initially to Mudhairib 132/33 kV substation. PIAD SH-05/2013 indicates this would
be at much higher cost and losses, so proposes connection to Bediyah 132/33 kV substation. Potential
overloads can be managed by 11 kV load transfers.
Table 8 - Option 1 - Substation loading after reinforcement
Existing Capacity
Ne w Capacity (MVA) Ye ar
(MVA)
Substation
Capacity Firm Capacity Firm Year of 2013 2014 2015 2016 2017 2018 2019 2020 Growth Comme nt
Transformer
Addition
Ye ar Fe ede r Ye ar Fe ede r
Conne cte d Dis connected
Mintrib 2 x 20 20 3 x 20 40 2016 22.4 25.8 29.6 34.1 39.2 32.1 36.9 34.4 15% 13 MW to Al Shariq 2018
Mintrib-2 2013 8 MW to Al Shariq 2020
Mintrib-3 2013
Mintrib New 2016
Al Was il 2 x 6 6 6.0 6.5 7.0 7.6 8.2 4.8 5.2 5.6 8% 4 MW to Al Shariq 2018
Mintrib-1 2013
Table 9 indicates feeder loading after reinforcement. Values > 50 % of rating (shown yellow) after 2016
are acceptable because:
Load
Mintrib-1 22.2 22.2 2013 6.0 6.5 7.0 7.6 8.2 4.8 5.2 5.6
Mintrib-2 22.2 22.2 2013 11.2 12.9 14.8 11.4 13.1 10.7 12.3 11.5
Mintrib-3 22.2 22.2 2013 14.6 16.6 18.9 15.9 18.0 10.7 12.3 11.4
Sooqah 22.2 22.2 2013 7.4 7.9 8.4 9.0 9.5 10.2 10.9 11.6
Mintrib New 22.2 22.2 2020 0.0 0.0 0.0 11.4 13.1 10.7 12.3 11.5
An incidental benefit of this proposal is that it creates an interconnector between Mudhairib and Bediyah
132/33 kV substations. This will provide some increase in security of supply with opportunities for
restoration of load during double outages at these substations.
Capital cost
The estimated cost is OMR 4,460,500 as detailed in Appendix A. Appendix B and Table 10 show the
spend profile.
Table 10 Capital investment stream for Option 1
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on inve stment
0
0
1,519,000 151,900 911,400 379,750 75,950 Transformer at Mintrib
1,941,000 194,100 1,164,600 485,250 97,050 Two transformers at Al Shariq + transfer Tawi Salam
595,000 59,500 357,000 178,500 3rd transformer at Al Shariq
405,500 15,190 91,140 57,385 124,055 54,475 45,405 17,850 Contingency (10%) on MZEC costs
System losses
Table 11 shows peak losses.
Table 11 Peak system losses with reinforcement as Option 1
Table 12 and Appendix B show the cost and NPV of these losses.
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Overall NPV
Appendix B and Table 13 show the overall NPV analysis.
Table 13 NPV with reinforcement as Option 1
Total Cost stream 167,090 1,002,540 964,133 1,786,672 938,068 933,412 743,254
Net Present Value : 5,220,110 Omani Rial For investment period to 2020 only
Net Present Value : 10,527,084 Omani Rial Including 30 years of losses, capped at 2020 value
Figure 5 New 3 x 20 MVA Al Shariq substation (and additional 20 MVA transformer at Mintrib substation later) as
Option 2
11 kV work to facilitate load transfers needed to keep substations within firm capacity will be minimised
by strategic connection of new loads, and nominal amounts are included in the cost estimate.
New Infrastructure Requirement
Table 14 summarises the main equipment needed.
No. / km No. / km
Equipment
2016 2020
12 km 3 km 33 kV cable.
54 km 21 km 33 kV overhead.
1 km 1 km 11 kV cable.
8 km 8 km 11 kV overhead.
1 Civil work for 3 x 20 MVA substation.
1 Civil work for upgrading 2 x 20 to 3 x 20 MVA substation.
3 1 33 kV circuit breakers.
1 11 kV switchboard at Al Shariq comprising 3 incoming, 2
bus-section, 2 auxiliary transformer, 3 capacitor and 15
feeder breakers.
11 kV switchboard at Mintrib comprising 1 incoming, 2 for
1
cable bus-section, 1 capacitor and 8 feeder breakers.
3 1 20 MVA 33/11 kV transformers.
2 Auxiliary transformers.
3 1 7 MVAr capacitor banks.
Additionally, four 33 kV feeder circuit breakers will be required at Mudhairib 132/33 kV substation. These
are excluded above and in the cost estimate because existing breakers will be released when Ibra 132/33 kV
substation is commissioned in 2015.
Assessment
This proposal provides an additional 40 MVA of firm substation capacity by 2016 and an additional
20 MVA in 2020. This is sufficient to overcome existing n-1 substation overload situations and provide for
planned load increases as shown in Table 15. This also indicates the required load transfers between
33/11 kV substations; in reality, as most of the new load will be for new development, most transfers will
be avoided by managed allocation of new 11 kV feeders between Mintrib and Al Shariq substations.
Table 15 - Option 2 - Substation loading after reinforcement
Existing Capacity
Ne w Capacity (MVA) Ye ar
(MVA)
Substation
Capacity Firm Capacity Firm Year of 2013 2014 2015 2016 2017 2018 2019 2020 Growth Comme nt
Transformer
Addition
Ye ar Fe ede r Ye ar Fe ede r
Conne cte d Dis connected
Mintrib 2 x 20 20 3 x 20 40 2020 22.4 25.8 29.6 13.1 15.0 17.3 19.9 30.9 15% 21 MW to Bidiyah 2016
Mintrib-2 2013 8 MW from Bidiyah 2020
Mintrib-3 2013
Mintrib New 2020
Al Was il 2 x 6 6 6.0 6.5 7.0 4.4 4.7 5.1 5.5 5.9 8% 3.2 MW to Bidiyah 2016
Mintrib-1 2013
Bidiyah 3 x 20 40 24.2 27.6 31.5 36.0 33.1 14% 21 MW from Mintrib 2016
Bidiyah 1 2016 3.2 MW from Al Wasil 2016
Bidiyah 2 2016 8 MW to Mintrib 2020
Bidiyah 3 2016
Table 16 indicates feeder loading after reinforcement. Values > 50 % of rating (shown yellow) after 2016
are mostly acceptable because:
The Sooqah feeder is a single radial feeder as explained in Paragraph 1.3.3.
Mintrib 2 and 3 and Mintrib New feeders share the load at Mintrib, Tawi Salim and Lawrangh
substations, and any two feeders have sufficient capacity for this load. However, the Tawi Salim
and Lawrangh substation loads supplied from the Mintrib 3 feeder will ultimately limit capacity at
Mintrib substation.
Al Shariq 1, 2 and 3 feeders share the load at Al Shariq substation, and any two feeders have
sufficient capacity for this load.
Table 16 - Option 2 33 kV feeder loading after reinforcement
Load
Mintrib-1 22.2 22.2 2013 6.0 6.5 7.0 4.4 4.7 5.1 5.5 5.9
Mintrib-2 22.2 22.2 2013 11.2 12.9 14.8 6.5 7.5 8.6 9.9 10.3
Mintrib-3 22.2 22.2 2013 14.6 16.6 18.9 11.1 12.5 14.1 16.0 16.9
Sooqah 22.2 22.2 2013 7.4 7.9 8.4 9.0 9.5 10.2 10.9 11.6
Mintrib New 22.2 22.2 2020 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.3
Al Shariq 1 22.2 22.2 2016 0.0 0.0 0.0 8.1 9.2 10.5 12.0 11.0
Al Shariq 2 22.2 22.2 2016 0.0 0.0 0.0 8.1 9.2 10.5 12.0 11.0
Al Shariq 3 22.2 22.2 2016 0.0 0.0 0.0 8.1 9.2 10.5 12.0 11.0
Capital cost
The estimated cost is OMR 5,722,200 as detailed in Appendix A. Appendix B and Table 17 show the
spend profile.
Table 17 Capital investment stream for Option 2
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on investment
-
-
3,726,000 372,600 2,235,600 931,500 186,300 Establishment of Al Shariq substation
1,476,000 147,600 885,600 369,000 73,800 Reinforcement of Mintrib substation
520,200 37,260 223,560 93,150 33,390 88,560 36,900 7,380 Contingency (10%) on MZEC costs
System losses
Table 18 shows peak losses.
Table 18 Peak system losses with reinforcement as Option 2
Table 19 and Appendix B show the cost and NPV of these losses.
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Overall NPV
Appendix B and Table 20 show the overall NPV analysis.
Table 20 NPV with reinforcement as Option 2
Total Cost stream 409,860 2,459,160 1,339,714 753,690 1,485,397 1,053,863 782,644
Net Present Value : 6,783,112 Omani Rial For investment period to 2020 only
Net Present Value : 13,589,883 Omani Rial Including 30 years of losses, capped at 2020 value
Option 1 has much lower capital cost and losses and therefore a much lower present value.
No. / km No. / km
Equipment
Hiyal Lawrangh
3 Outdoor 33 kV isolators.
3 Outdoor 33 kV motorized isolators.
1 set 1 set 33 kV transformer fuses.
1 1 6 MVA, 33/11 kV transformers.
2 2 11 kV outdoor air break switches.
1 1 3 MVAr capacitor bank.
1 1 Extend substation earthing.
1 Auxiliary building for SCADA & DC system.
1 Telecoms and SCADA equipment.
1 km 1 km 33 kV overhead.
Assessment
This proposal provides 6 MVA of firm substation capacity at each site as shown in Table 23. This is more
than sufficient for the investment period.
Table 23 - Option 3 - Substation loading after reinforcement
Existing Capacity
Ne w Capacity (MVA) Ye ar
(MVA)
Substation
Capacity Firm Capacity Firm Year of 2013 2014 2015 2016 2017 2018 2019 2020 Growth Comme nt
Transformer
Addition
Ye ar Fe ede r Ye ar Fe ede r
Conne cte d Dis connected
Lawrangh 1 x 6 0 2 x 6 6 2016 1.9 2.1 2.3 2.5 2.8 3.1 3.4 3.7 10%
Mintrib-3 2013
Hiyal 1 x 6 0 2 x 6 6 2016 1.7 1.8 1.9 2.1 2.2 2.4 2.6 2.7 7%
Sooqah 2013
Motorised incoming and bus-section isolators with telecontrol at Lawrangh substation will increase overall
33 kV security of supply. Remote operation of these isolators will be a requirement when the aggregate
related feeder load exceeds 6 MW and DSSS requires restoration in 15 minutes.
Capital cost
The estimated cost is OMR 727,100 as detailed in Appendix A. Appendix B and Table 24 show the spend
profile.
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on investment
-
-
661,000 66,100 396,600 165,250 33,050 Substation reinforcements
66,100 6,610 39,660 16,525 3,305 Contingency (10%) on MZEC costs
- - - -
NPV
Appendix B and Table 25 show the overall NPV analysis. The cost of losses is not included as this is only
needed to facilitate comparison of options and only one option is proposed.
Table 25 NPV with reinforcement as Option 3
Cost of Losses - - - - - - -
Figure 7 Additional 6 MVA transformer at W Bani Khalid substation as Option 4 (Option 3 proposals also shown)
No. / km Equipment
4 Outdoor 33 kV motorized isolators.
1 set 33 kV transformer fuses.
1 6 MVA, 33/11 kV transformer.
2 11 kV outdoor air break switches.
1 11 kV auto-recloser.
1 3 MVAr capacitor bank.
1 Auxiliary building for SCADA & DC system.
1 Telecoms and SCADA equipment.
1 Extend substation earthing.
1 km 11 kV cable.
5 km 11 kV overhead.
Assessment
Addition of a third 6 MVA transformer (with associated alterations, switchgear, etc.) will increase firm
capacity to 12 MVA which is sufficient as shown in Table 27.
Table 27 - Option 4 - Substation loading after reinforcement
Existing Capacity
New Capacity (MVA) Year
(MVA)
Substation
Capacity Firm Capacity Firm Ye ar of 2013 2014 2015 2016 2017 2018 2019 2020 Growth Comme nt
Transforme r
Addition
Year Fe eder Year Fe eder
Connected Disconne cte d
W Bani Khalid 2 x 6 6 3 x 6 12 2016 4.5 4.8 5.2 5.5 5.9 6.3 6.8 7.2 7%
Sooqah 2013
Motorised incoming and bus-section isolators with telecontrol will increase overall 33 kV security of
supply. Remote operation of these isolators is a requirement as DSSS requires restoration in 15 minutes.
Capital cost
The estimated cost is OMR 634,150 as detailed in Appendix A. Appendix B and Table 28 show the spend
profile.
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on investment
-
-
576,500 57,650 345,900 144,125 28,825 Substation reinforcements
57,650 5,765 34,590 14,413 2,883 Contingency (10%) on MZEC costs
- - - -
NPV
Appendix B and Table 29 show the overall NPV analysis. Costs for losses are not included as circuit losses
will be the same as those for Option 5, and transformer losses will be very similar for both Options 4 and 5.
Table 29 NPV with reinforcement as Option 4
Cost of Losses - - - - - - -
W Bani Khalid
2 x 6 MVA
Reinforce to 2 x 20 MVA 2016
2013
New circuit being proposed 4.5
on PIAD SH-04/2013 2020
7.2
T
2013
Sooqah 4.2
12 km
2 x 6 MVA 2020
5.9
0 km 0 km 0.4
2013 being proposed on 2020
0.8 0.5
PIAD SH-04/2013
Dhubaha 2020
1.1 Fashagah
1 x 3 MVA 4 km 1 x 1 MVA
7 km Lawrangh
3 km
1 x 6 MVA
2013
1.7 1 km
Reinforce to
Hiyal
7 km
2020
2.7
2 x 6 MVA 2016
1 x 6 MVA
2013
Reinforce to 1.9
T
2 x 6 MVA 2016 2020
3.7
7 km
3 13 km
32 km
2013
13 km 11 km 1.5
2020
12 km
11 km 1 km
Notes: Mintrib
All circuits are shown overhead, but there are 2 x 20 MVA
some short cable sections. 2013
22.4
Street lighting 33 kV / LV transformers are not shown. 2020
Figure 8 Replace 2 x 6 MVA transformers at W Bani Khalid substation with 2 x 20 MVA as Option 5 (Option 3 proposals
also shown)
No. / km Equipment
5 Outdoor 33 kV circuit breakers.
2 20 MVA, 33/11 kV transformers.
11 kV switchboard comprising 2 incoming, 1 bus-
1 section, 2 auxiliary transformer, 2 capacitor and 6
feeder breakers.
2 5 MVAr capacitor bank.
2 500 kVA auxiliary transformers.
1 Telecoms and SCADA equipment.
1 DC system for CB tripping.
1 Substation earthing.
1 km 11 kV cable.
5 km 11 kV overhead.
Assessment
Replacement 2 x 20 MVA transformers will increase firm capacity to 20 MVA which is sufficient as
shown in Table 31.
Table 31 - Option 5 - Substation loading after reinforcement
Existing Capacity
New Capacity (MVA) Year
(MVA)
Substation
Capacity Firm Capacity Firm Ye ar of 2013 2014 2015 2016 2017 2018 2019 2020 Growth Comme nt
Transforme r
Addition
Year Fe eder Year Fe eder
Connected Disconne cte d
W Bani Khalid 2 x 6 6 2 x 20 20 2016 4.5 4.8 5.2 5.5 5.9 6.3 6.8 7.2 7%
Sooqah 2013
Installed switchgear and protection will to allow transformers to operate in parallel, so transformer faults
will no longer result in loss of supply.
Additional 11 kV feeder breakers will be available for future connections.
Automatic voltage control will provide improved voltage control compared to the present off-load manual
control assisted by capacitor switching.
Telecontrol of 33 kV circuit breakers will increase overall 33 kV security of supply. Remote operation is a
requirement as DSSS requires restoration in 15 minutes.
Capital cost
The estimated cost is OMR 1,359,600 as detailed in Appendix A. Appendix B and Table 32 show the
spend profile.
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on investment
-
-
1,236,000 123,600 741,600 309,000 61,800 Substation reinforcements
123,600 12,360 74,160 30,900 6,180 Contingency (10%) on MZEC costs
- - - -
NPV
Appendix B and Table 33 show the overall NPV analysis. Costs for losses are not included as circuit losses
will be the same as those for Option 4, and transformer losses will be very similar for both Options 4 and 5.
Table 33 NPV with reinforcement as Option 5
Cost of Losses - - - - - - -
2.5 To improve voltage regulation at, and increase firm circuit capacity to,
W Bani Khalid substation, and increase network security of supply
2.5.1 Requirement and list of options
Proposals here address Issues 11, 14 and 15 detailed above, i.e.:
Unsatisfactory voltage at W Bani Khalid substation.
The need for a second 33 kV circuit to W Bani Khalid substation for DSSS compliance.
The need to improve security of supply in the 33 kV network supplying Dhubaha, Hiyal, W Bani
Khalid, Fashagah, Lawrangh and Tawi Salim substations, noting that reconnecting Tawi Salim
substation to the new Bediyah 132/33 kV substation as Option 1 has already provided some
improvement.
Options to deal with the above are:
Option 6
Second circuit to W Bani Khalid substation from the Hiyal tee feeder.
Option 7
Second circuit to W Bani Khalid substation from Bediyah 132/33 kV substation.
2.5.2 Option 6 - Second circuit to W Bani Khalid substation from the Hiyal tee feeder
Description
As shown in Figure 9 (which also shows the Option 1, 3 and 4 proposals detailed above) this scheme:
Provides the necessary second 33 kV circuit to W Bani Khalid substation by teeing to the Hiyal tee
circuit, a route length of about 19 km. This is the closest alternative to the existing supply.
Closes the existing normal open point near Lawrangh substation.
Introduces a new 33 kV normal open point.
Motorises 33 kV isolators and adds telecontrol at Hiyal and Tawi Salim substations (not shown on
Figure 9).
W Bani Khalid
2 x 6 MVA
Reinforce to 3 x 6 MVA 2016
2013
0 km 0 km 0.4
2013 being proposed on 2020
0.8 0.5
PIAD SH-04/2013
Dhubaha 2020
1.1
4 km Fashagah
1 x 3 MVA 4 km 1 x 1 MVA
7 km Lawrangh
16 km 3 km
1 x 6 MVA
2013 New open point Reinforce to
Hiyal 1.7 1 km
7 km 1 x 6 MVA
2020
2.7
2 x 6 MVA 2016
Close open point
Reinforce to 2013
1.9
2 x 6 MVA 2016 T 2020
3.7
7 km
3 13 km
32 km
New open point 2013
13 km 11 km 1.5
2020
12 km
11 km 1 km
24 km Mintrib 5 km
Figure 9 Second 33 kV feeder W Bani Khalid substation from Hiyal tee circuit as Option 6 (Option 1, 3 and 4 proposals
also shown)
Assessment
With this option, two connected feeders from 132/33 kV substations supply Dhubaha, Hiyal, W Bani
Khalid, Fashagah, Lawrangh and Tawi Salim substations. The aggregate load in 2020 is 18.1 MW which is
within the capacity of each circuit. There would therefore be no overloads even under worst single outage
conditions.
Date of Issue: 10 December 2013 Page: 40 of 64
Version 2.0
Pre-investment Project Appraisal Project Number: SH-06/2013
All supplies could probably be restored by remote switching for any 33 kV circuit fault within the 15
minutes specified in DSSS (depending on the extent of switching needed). Exceptions are faults affecting
the teed circuits to Dhubaha and Fashagh substations; each is under 2 MW and it is assumed the less
onerous Class A standard of DSSS applies, requiring only restoration in repair time which is possible.
However, circuit lengths and corresponding volt-drops are high. Voltages under normal running conditions
are just acceptable, but they are not under outage conditions. E.G. in 2020 during outage of the incoming
circuit to Tawi Salim substation, 11 kV voltage at Tawi Salim substation reduces to 10.5 kV instead of the
required 11.5 kV.
As this situation is unacceptable the Option is rejected.
2.5.3 Option 7 - Second circuit to W Bani Khalid substation from Bediyah 132/33 kV
substation
Description
As shown in Figure 10 (which also shows the Option 1, 3 and 4 proposals detailed above) this scheme:
Provides the necessary second 33 kV circuit to W Bani Khalid substation from the new Bidiyah
132/33 kV substation. This is the closest alternative to the existing supply after the Hiyal tee
circuit considered in Option 6.
Includes a short normally open teed connection between the new circuit above and the Tawi Salim
Lawrangh 33 kV circuit.
Closes the existing normal open point near Lawrangh substation.
Introduces additional 33 kV normal open points.
It cannot be completed until 2018 when the new Bediyah 132/33 kV substation is commissioned.
Therefore a short additional 33 kV circuit connection is included to connect temporarily to the new Mintrib
feeder proposed in Option 1.
Part of the new circuit should be of tower construction in the mountainous section of the route.
W Bani Khalid
2 x 6 MVA
Reinforce to 3 x 6 MVA and
new 33 kV circuit 2016
39 km
2013
New circuit being proposed 4.5 T
on PIAD SH-04/2013 2020
7.2 New open point
2013
Sooqah 4.2
12 km
2 x 6 MVA 2020
5.9
0 km 0 km 0.4
2013 being proposed on 2020
0.8 0.5
PIAD SH-04/2013
Dhubaha 2020 1.1 Fashagah
1 x 3 MVA 4 km 1 x 1 MVA
7 km
New open point Lawrangh
20 km 3 km
1 x 6 MVA
2013
13 km 11 km 1.5
2020
12 km
11 km 1 km
New open
24 km point 2018 Mintrib 5 km
Add third 20 MVA 2 x 20 MVA
2013
Figure 10 Second 33 kV feeder to W Bani Khalid substation from Bediyah 132/33 kV substation as Option 7 (Option 1, 3
and 4 proposals also shown)
Assessment
With this option, ultimately and temporarily, three connected feeders from 132/33 kV substations (one
from Mudhairib and two from Bediyah) will supply Dhubaha, Hiyal, W Bani Khalid, Fashagah, Lawrangh
and Tawi Salim substations. The aggregate load in 2020 is 18.1 MW which is within the capacity of each
circuit. There would therefore be no overloads even under worst single outage conditions or even for some
double outage situations.
Volt-drops in the 33 kV feeders reduce as the load in and feeding length of each is reduced. The short
connection between the new circuit to W Bani Khalid substation and the Tawi Salim Lawrangh 33 kV
circuit provides additional network security and flexibility and an improvement in voltage at Tawi Salim
substation during single outage conditions which would otherwise reduce to 29.4 kV at 2020 loadings.
All supplies can be restored by remote switching for any 33 kV circuit fault within the 15 minutes specified
in DSSS. Exceptions are faults affecting the teed circuits to Dhubaha and Fashagh substations; each is
under 2 MW and it is assumed the less onerous Class A standard of DSSS applies, requiring only
restoration in repair time.
The temporary 33 kV connection to the new 33 kV circuit to Mintrib will provide some improvement in
voltage at W Bani Khalid minimising customer complaints until the full scheme is completed in 2018. It
cannot remain loaded as it reduces the circuit capacity available at Mintrib substation, and will therefore
run open after the final connection to Bediyah 132/33 kV substation is made. It will then provide another
interconnection between Mudhairib and Bediyah 132/33 kV substations. This will provide further increase
in security of supply with additional opportunities for restoration of load during double outages at these
substations.
Capital cost
The estimated cost is OMR 1,591,829 as detailed in Appendix A. Appendix B and Table 36 show the
spend profile.
Table 36 Capital investment stream for Option 7
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on investment
-
-
1,336,875 133,688 802,125 334,219 66,844 New 33 kV circuit with temporary connection
133,687 13,369 80,212 33,422 6,684 Contingency (10%) on MZEC costs
110,243 11,024 66,146 27,561 5,512 Final connection of new 33 kV circuit to Bediyah 132/33 kV substation
11,024 1,102 6,614 2,756 551 Contingency (10%) on MZEC costs
NPV
Appendix B and Table 37 show the overall NPV analysis. The cost of losses is not included as this is only
needed to facilitate comparison of options and only one option is proposed.
Cost of Losses - - - - - - -
3 Recommended solution
3.1 Combination of options
The recommended solution to the issues detailed above is a combination of the recommended Options 1, 3,
4 and 7 as illustrated in Figure 11 below which is a simplification of Figure 10 above.
39 km
2013
New circuit being proposed 4.5 W Bani Khalid
T
on PIAD SH-04/2013 2020
7.2
3 x 6 MVA
2013
Sooqah 4.2
12 km
2 x 6 MVA 2020
5.9
0 km 0 km 0.4
2013 being proposed on 2020
0.8 0.5
PIAD SH-04/2013
Dhubaha 2020
1.1 Fashagah
1 x 3 MVA 4 km 1 x 1 MVA
7 km
20 km 3 km
2013
1.7
Lawrangh
1 km
Hiyal 2020 2 x 6 MVA
7 km 2.7
2 x 6 MVA 2013
1.9
T 2020
3.7
7 km 0.1 km
3 13 km
32 km
2013
13 km 11 km 1.5
2020
12 km
11 km 1 km
24 km Mintrib 5 km
Notes: 3 x 20 MVA 5 km
Blue indicates proposal being considered separately. 2013
22.4
Green indicates approved separate proposal. 2020
Issue Resolved by
Issue 1 Mudhairib 132/33 kV substation firm capacity PIAD SH-05-2013
Issue 2 Mintrib 33/11kV substation firm capacity Option 1
Issue 3 Al Wasil 33/11kV substation firm capacity Option 1
Issue 4 Lawrangh 33/11kV substation firm capacity Option 3
Issue 5 Fashagah 33/11kV substation firm capacity Does not require resolution
Issue 6 W Bani Khalid 33/11kV substation firm capacity Option 4
Issue 7 Hiyal 33/11kV substation firm capacity Option 3
Issue 8 Dhubaha 33/11kV substation firm capacity Does not require resolution
Issue 9 Mintrib 2 and 3 33 kV circuit capacities Option 1
Issue 10 Sooqah 33 kV circuit capacity Does not require resolution
Issue 11- Excessive 33 kV volt-drop Option 7
Issue 12 Second 33 kV circuit to Hiyal substation Option 3
Issue 13 Second 33 kV circuit to Lawrangh substation Option 3
Issue 14 Second 33 kV circuit to W Bani Khalid substation Option 7
Issue 15 Insufficient firm 33 kV circuit capacity Options 7 and 1
Figure 14 W Bani Khalid substation voltage under normal running conditions and 2020 loads
Figure 15 W Bani Khalid substation voltage under n-1 running conditions and 2020 loads
Indicative capital
Project period Brief description of works expenditure
(OMR)
Nov 2013 Internal approvals. 0
Nov Dec 2013 Submission and regulatory approval. 0
Jan 2014 April 2014 Survey, planning approvals, tender document. 0
Tender Board review, reply, tendering, open bids, analysis
May - Dec 2014 845,148
and awarding + mobilisation.
Start of the work, ordering of major equipment items,
Jan 2015 Dec 2019 4,366,598
execution of the major works.
Jan 2016 Feb 2020 Commissioning & testing + handover. 1,831,154
Release of the retention money for work completed in
Feb 2016 157,595
2015.
Release of the retention money for work completed in
Feb 2017 67,566
2016.
Release of the retention money for work completed in
Feb 2018 78,948
2017.
Release of the retention money for work completed in
Feb 2019 31,477
2018.
Release of the retention money for work completed in
Feb 2020 35,093
2019.
Total expenditure by MZEC 7,413,579
4 Recommendation
Mazoon Electricity Company SAOC recommends that the series of reinforcements described in paragraph
3.1 be authorised at a total cost to the MZEC of OMR 7,413,579 (made up as Option 1 OMR 4,460,500,
Option 3 OMR 727,100, Option 4 OMR 634,150 and Option 7 OMR 1,591,829) and be carried out
from 2014 to 2020 to achieve the outcomes and benefits detailed in this Pre-Investment Appraisal
Document.
5 Authorisation
The following signatures are duly sought in line with company delegations of authority.
Prepared by Planning Engineer We confirm that we have completed and checked this
project appraisal and we are satisfied with its content.
Signature Date
Reviewed by Head of Planning I confirm that I have completed and checked this project
appraisal and I am satisfied with its content.
Signature Date
Final Revision Planning and Regulatory I confirm that I have reviewed this project appraisal and I
Affairs Manager am satisfied with its content.
Signature Date
Final Revision Sharqiyah Senior Operations I confirm that I have reviewed this project appraisal and I
Manager am satisfied with its content.
Signature Date
Final Revision Projects Manager I confirm that this investment can be delivered as per the
cost estimated and within the stipulated time frame.
Signature Date
Hassan Abdawani Zahir Al Abri Majid Al Busaidi Hamed Al Jassasi Biju Joseph
CIC Chairman CIC Deputy Chairman CIC member CIC member CIC member
Signature Signature Signature Signature Signature
Cables
33 kV Cables Cost per km Subtotal OMR 225,000 Subtotal OMR 300,000 Subtotal OMR 75,000
33kV cable 3c 300mm2 (Easy terrain) 64,000 OMR - OMR - OMR -
33kV cable 3c 300mm2 (Moderate terrain) 75,000 3 OMR 225,000 4 OMR 300,000 1 OMR 75,000
33kV cable 3c 300mm2 (Hard terrain) 83,000 OMR - OMR - OMR -
11kV Cables Cost per km Subtotal OMR 53,000 Subtotal OMR 53,000 Subtotal OMR -
11kV cable 3c 240 mm2 (Easy terrain) 40,000 OMR - OMR - OMR -
11kV cable 3c 240mm2 (Moderate terrain) 53,000 1 OMR 53,000 1 OMR 53,000 OMR -
11kV cable 3c 240mm2 (Hard terrain) 60,000 OMR - OMR - OMR -
11kV cable 3c 185mm2 (Easy terrain) 38,000 OMR - OMR - OMR -
11kV cable 3c 185mm2 (Moderate terrain) 45,000 OMR - OMR - OMR -
11kV cable 3c 185mm2 (Hard terrain) 50,000 OMR - OMR - OMR -
Overhead Lines
132 kV Overhead Lines Cost per km Subtotal OMR - Subtotal OMR - Subtotal OMR -
33 kV Overhead Lines Cost per km Subtotal OMR 420,000 Subtotal OMR 153,000 Subtotal OMR 51,000
Upgrading 33kV Wolf to Panther 200mm2 8,500 OMR - OMR - OMR -
33kV Panther 200mm2 ACSR on w ood poles (Easy terrain) 17,000 OMR - 9 OMR 153,000 3 OMR 51,000
33kV Panther 200mm2 ACSR on w ood poles (Moderate terrain) 20,000 21 OMR 420,000 OMR - OMR -
33kV Panther 200mm2 ACSR on w ood poles (Hard terrain) 22,000 OMR - OMR - OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Easy terrain) 16,000 OMR - OMR - OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Moderate terrain) 19,000 OMR - OMR - OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Hard terrain) 21,000 OMR - OMR - OMR -
2
33kV Panther 200 mm ACSR on 33kV S.C. Tow ers (Easy terrain) 25,000 OMR - OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV S.C. Tow ers (Moderate terrain) 29,412 OMR - OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV S.C. Tow ers (Hard terrain) 32,353 OMR - OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV D.C. Tow ers (Easy terrain) 35,000 OMR - OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV D.C. Tow ers (Moderate terrain) 41,176 OMR - OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV D.C. Tow ers (Hard terrain) 45,294 OMR - OMR - OMR -
OMR - OMR - OMR -
33kV double circuit on 132kV Tow ers 77,601 OMR - OMR - OMR -
33 kV Pole mounted Air Break Sw itch 4,000 OMR - OMR - OMR -
11kV Overhead Lines Cost per km Subtotal OMR 85,000 Subtotal OMR 102,000 Subtotal OMR 85,000
11kV Wolf 150mm2 ACSR (Easy terrain) 15,000 OMR - OMR - OMR -
11kV Wolf 150mm2 ACSR (Moderate terrain) 17,000 5 OMR 85,000 6 OMR 102,000 5 OMR 85,000
11kV Wolf 150mm2 ACSR (Hard terrain) 19,000 OMR - OMR - OMR -
11kV Booster transformer 40,000 OMR - OMR - OMR -
11kV Capacitors (Pole mounted) 600 kVar 3,000 OMR - OMR - OMR -
11kV Capacitors (Pole mounted) 900 kVar 4,000 OMR - OMR - OMR -
Substations
Grid Substation Subtotal OMR - Subtotal OMR - Subtotal OMR -
Primary Substation Subtotal OMR 736,000 Subtotal OMR 1,333,000 Subtotal OMR 384,000
Civil Works / and general fit-out
Civil Works f or 1 x 6 MVA 62,000 OMR - OMR - OMR -
Civil Works f or 2 x 6 MVA 83,000 OMR - OMR - OMR -
Civil Works f or upgrading to 3 x 6 MVA 100,000 OMR - OMR - OMR -
Civil Works f or a SCADA / LV / Control building 50,000 OMR - OMR - OMR -
Civil Works f or 1 x 20 MVA OMR - OMR - OMR -
Civil Works f or 2 x 20 MVA 200,000 OMR - OMR - OMR -
Civil Works f or 3 x 20 MVA 300,000 OMR - 1 OMR 300,000 OMR -
Civil Works f or upgrading to 3 x 20 MVA 200,000 1 OMR 200,000 OMR - OMR -
OMR - OMR - OMR -
OMR - OMR - OMR -
33 kV Sw itchgear
33kV TX CB Bays (indoor) 35,000 OMR - OMR - OMR -
33kV Incoming Feeder CB (indoor) 32,000 OMR - OMR - OMR -
33kV Outgoing Feeder (indoor) 30,000 OMR - OMR - OMR -
33kV Bus Section/Bus Coupler CB Bays (indoor) 32,000 OMR - OMR - OMR -
33kV CB incl. 3-ph VT+ Control (outdoor) 30,000 1 OMR 30,000 2 OMR 60,000 1 OMR 30,000
33kV Bus Section/Bus Coupler CB Bays (outdoor AB sw itch) 3,500 OMR - OMR - OMR -
33kV Air Break Sw itch including remote operation (outdoor) 8,000 1 OMR 8,000 2 OMR 16,000 1 OMR 8,000
OMR - OMR - OMR -
OMR - OMR - OMR -
OMR - OMR - OMR -
11 kV Sw itchgear
11kV TX incoming CB (indoor) 20,000 1 OMR 20,000 3 OMR 60,000 OMR -
11kV Bus Section/Bus Coupler CB Bays (indoor) 15,000 OMR - 2 OMR 30,000 OMR -
11kV Outgoing Feeder (indoor) 12,000 11 OMR 132,000 22 OMR 264,000 OMR -
11V TX incoming CB (indoor) - 31.5kA 23,000 OMR - OMR - OMR -
11kV Bus Section/Bus Coupler CB Bays (indoor) - 31.5kA 17,250 OMR - OMR - OMR -
11kV Outgoing Feeder (indoor) - 31.5kA 13,800 OMR - OMR - OMR -
11kV Sectionaliser (outdoor AB sw itch) 3,500 OMR - OMR - OMR -
11kV Auto-recloser (Outdoor) 15,500 OMR - OMR - OMR -
11kV Ring Main Unit w ith remote control (outdoor) 15,500 OMR - OMR - OMR -
OMR - OMR - OMR -
OMR - OMR - OMR -
Transf ormers
20MVA 33/11kV 150,000 1 OMR 150,000 2 OMR 300,000 1 OMR 150,000
10MVA 33/11kV 100,000 OMR - OMR - OMR -
6MVA 33/11kV 80,000 OMR - OMR - OMR -
23MVA Booster Transf ormer 100,000 OMR - OMR - OMR -
500kVA, 11/0.415 kV Auxiliary Transf ormer 5,500 OMR - 2 OMR 11,000 OMR -
3 MVA 11kV Booster Transformer 40,000 OMR - OMR - OMR -
OMR - OMR - OMR -
Cables
33 kV Cables Cost per km Subtotal OMR 900,000 Subtotal OMR 225,000
33kV cable 3c 300mm2 (Easy terrain) 64,000 OMR - OMR -
33kV cable 3c 300mm2 (Moderate terrain) 75,000 12 OMR 900,000 3 OMR 225,000
33kV cable 3c 300mm2 (Hard terrain) 83,000 OMR - OMR -
11kV Cables Cost per km Subtotal OMR 53,000 Subtotal OMR 53,000
11kV cable 3c 240 mm2 (Easy terrain) 40,000 OMR - OMR -
11kV cable 3c 240mm2 (Moderate terrain) 53,000 1 OMR 53,000 1 OMR 53,000
11kV cable 3c 240mm2 (Hard terrain) 60,000 OMR - OMR -
11kV cable 3c 185mm2 (Easy terrain) 38,000 OMR - OMR -
11kV cable 3c 185mm2 (Moderate terrain) 45,000 OMR - OMR -
11kV cable 3c 185mm2 (Hard terrain) 50,000 OMR - OMR -
Overhead Lines
132 kV Overhead Lines Cost per km Subtotal OMR - Subtotal OMR -
33 kV Overhead Lines Cost per km Subtotal OMR 1,080,000 Subtotal OMR 420,000
Upgrading 33kV Wolf to Panther 200mm2 8,500 OMR - OMR -
33kV Panther 200mm2 ACSR on w ood poles (Easy terrain) 17,000 OMR - OMR -
33kV Panther 200mm2 ACSR on w ood poles (Moderate terrain) 20,000 54 OMR 1,080,000 21 OMR 420,000
33kV Panther 200mm2 ACSR on w ood poles (Hard terrain) 22,000 OMR - OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Easy terrain) 16,000 OMR - OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Moderate terrain) 19,000 OMR - OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Hard terrain) 21,000 OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV S.C. Tow ers (Easy terrain) 25,000 OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV S.C. Tow ers (Moderate terrain) 29,412 OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV S.C. Tow ers (Hard terrain) 32,353 OMR - OMR -
2
33kV Panther 200 mm ACSR on 33kV D.C. Tow ers (Easy terrain) 35,000 OMR - OMR -
2
33kV Panther 200 mm ACSR on 33kV D.C. Tow ers (Moderate terrain) 41,176 OMR - OMR -
2
33kV Panther 200 mm ACSR on 33kV D.C. Tow ers (Hard terrain) 45,294 OMR - OMR -
OMR - OMR -
33kV double circuit on 132kV Tow ers 77,601 OMR - OMR -
33 kV Pole mounted Air Break Sw itch 4,000 OMR - OMR -
11kV Overhead Lines Cost per km Subtotal OMR 136,000 Subtotal OMR 136,000
11kV Wolf 150mm2 ACSR (Easy terrain) 15,000 OMR - OMR -
11kV Wolf 150mm2 ACSR (Moderate terrain) 17,000 8 OMR 136,000 8 OMR 136,000
11kV Wolf 150mm2 ACSR (Hard terrain) 19,000 OMR - OMR -
11kV Booster transf ormer 40,000 OMR - OMR -
11kV Capacitors (Pole mounted) 600 kVar 3,000 OMR - OMR -
11kV Capacitors (Pole mounted) 900 kVar 4,000 OMR - OMR -
Substations
Grid Substation Subtotal OMR - Subtotal OMR -
33 kV Sw itchgear
33kV TX CB Bays (indoor) 35,000 OMR - OMR -
33kV Incoming Feeder CB (indoor) 32,000 OMR - OMR -
33kV Outgoing Feeder (indoor) 30,000 OMR - OMR -
33kV Bus Section/Bus Coupler CB Bays (indoor) 32,000 OMR - OMR -
33kV CB incl. 3-ph VT+ Control (outdoor) 30,000 3 OMR 90,000 1 OMR 30,000
33kV Bus Section/Bus Coupler CB Bays (outdoor AB sw itch) 3,500 OMR - OMR -
33kV Air Break Sw itch including remote operation (outdoor) 8,000 3 OMR 24,000 1 OMR 8,000
OMR - OMR -
OMR - OMR -
OMR - OMR -
11 kV Sw itchgear
11kV TX incoming CB (indoor) 20,000 3 OMR 60,000 1 OMR 20,000
11kV Bus Section/Bus Coupler CB Bays (indoor) 15,000 2 OMR 30,000 2 OMR 30,000
11kV Outgoing Feeder (indoor) 12,000 20 OMR 240,000 9 OMR 108,000
11V TX incoming CB (indoor) - 31.5kA 23,000 OMR - OMR -
11kV Bus Section/Bus Coupler CB Bays (indoor) - 31.5kA 17,250 OMR - OMR -
11kV Outgoing Feeder (indoor) - 31.5kA 13,800 OMR - OMR -
11kV Sectionaliser (outdoor AB sw itch) 3,500 OMR - OMR -
11kV Auto-recloser (Outdoor) 15,500 OMR - OMR -
11kV Ring Main Unit w ith remote control (outdoor) 15,500 OMR - OMR -
OMR - OMR -
OMR - OMR -
Transformers
20MVA 33/11kV 150,000 3 OMR 450,000 1 OMR 150,000
10MVA 33/11kV 100,000 OMR - OMR -
6MVA 33/11kV 80,000 OMR - OMR -
23MVA Booster Transformer 100,000 OMR - OMR -
500kVA, 11/0.415 kV Auxiliary Transformer 5,500 2 OMR 11,000 OMR -
3 MVA 11kV Booster Transf ormer 40,000 OMR - OMR -
OMR - OMR -
Cables
33 kV Cables Cost per km Subtotal OMR - Subtotal OMR - Subtotal OMR -
33kV cable 3c 300mm2 (Easy terrain) 64,000 OMR - OMR - OMR -
33kV cable 3c 300mm2 (Moderate terrain) 75,000 OMR - OMR - OMR -
33kV cable 3c 300mm2 (Hard terrain) 83,000 OMR - OMR - OMR -
11kV Cables Cost per km Subtotal OMR - Subtotal OMR 53,000 Subtotal OMR 53,000
11kV cable 3c 240 mm2 (Easy terrain) 40,000 OMR - OMR - OMR -
11kV cable 3c 240mm2 (Moderate terrain) 53,000 OMR - 1 OMR 53,000 1 OMR 53,000
11kV cable 3c 240mm2 (Hard terrain) 60,000 OMR - OMR - OMR -
11kV cable 3c 185mm2 (Easy terrain) 38,000 OMR - OMR - OMR -
11kV cable 3c 185mm2 (Moderate terrain) 45,000 OMR - OMR - OMR -
11kV cable 3c 185mm2 (Hard terrain) 50,000 OMR - OMR - OMR -
Overhead Lines
132 kV Overhead Lines Cost per km Subtotal OMR - Subtotal OMR - Subtotal OMR -
33 kV Overhead Lines Cost per km Subtotal OMR 40,000 Subtotal OMR - Subtotal OMR -
Upgrading 33kV Wolf to Panther 200mm2 8,500 OMR - OMR - OMR -
33kV Panther 200mm2 ACSR on w ood poles (Easy terrain) 17,000 OMR - OMR - OMR -
33kV Panther 200mm2 ACSR on w ood poles (Moderate terrain) 20,000 2 OMR 40,000 OMR - OMR -
33kV Panther 200mm2 ACSR on w ood poles (Hard terrain) 22,000 OMR - OMR - OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Easy terrain) 16,000 OMR - OMR - OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Moderate terrain) 19,000 OMR - OMR - OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Hard terrain) 21,000 OMR - OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV S.C. Tow ers (Easy terrain) 25,000 OMR - OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV S.C. Tow ers (Moderate terrain) 29,412 OMR - OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV S.C. Tow ers (Hard terrain) 32,353 OMR - OMR - OMR -
33kV Panther 200 mm2 ACSR on 33kV D.C. Tow ers (Easy terrain) 35,000 OMR - OMR - OMR -
2
33kV Panther 200 mm ACSR on 33kV D.C. Tow ers (Moderate terrain) 41,176 OMR - OMR - OMR -
2
33kV Panther 200 mm ACSR on 33kV D.C. Tow ers (Hard terrain) 45,294 OMR - OMR - OMR -
OMR - OMR - OMR -
33kV double circuit on 132kV Tow ers 77,601 OMR - OMR - OMR -
33 kV Pole mounted Air Break Sw itch 4,000 OMR - OMR - OMR -
11kV Overhead Lines Cost per km Subtotal OMR - Subtotal OMR 85,000 Subtotal OMR 85,000
11kV Wolf 150mm2 ACSR (Easy terrain) 15,000 OMR - OMR - OMR -
11kV Wolf 150mm2 ACSR (Moderate terrain) 17,000 OMR - 5 OMR 85,000 5 OMR 85,000
11kV Wolf 150mm2 ACSR (Hard terrain) 19,000 OMR - OMR - OMR -
11kV Booster transf ormer 40,000 OMR - OMR - OMR -
11kV Capacitors (Pole mounted) 600 kVar 3,000 OMR - OMR - OMR -
11kV Capacitors (Pole mounted) 900 kVar 4,000 OMR - OMR - OMR -
Substations
Grid Substation Subtotal OMR - Subtotal OMR - Subtotal OMR -
Primary Substation Subtotal OMR 621,000 Subtotal OMR 438,500 Subtotal OMR 1,098,000
Civil Works / and general f it-out
Civil Works f or 1 x 6 MVA 62,000 2 OMR 124,000 OMR - OMR -
Civil Works f or 2 x 6 MVA 83,000 OMR - OMR - OMR -
Civil Works f or upgrading to 3 x 6 MVA 100,000 OMR - 1 OMR 100,000 OMR -
Civil Works f or a SCADA / LV / Control building 50,000 1 OMR 50,000 1 OMR 50,000 OMR -
Civil Works f or 1 x 20 MVA OMR - OMR - OMR -
Civil Works f or 2 x 20 MVA 200,000 OMR - OMR - 1 OMR 200,000
Civil Works f or 3 x 20 MVA 300,000 OMR - OMR - OMR -
Civil Works f or upgrading to 3 x 20 MVA 200,000 OMR - OMR - OMR -
OMR - OMR - OMR -
OMR - OMR - OMR -
33 kV Sw itchgear
33kV TX CB Bays (indoor) 35,000 OMR - OMR - OMR -
33kV Incoming Feeder CB (indoor) 32,000 OMR - OMR - OMR -
33kV Outgoing Feeder (indoor) 30,000 OMR - OMR - OMR -
33kV Bus Section/Bus Coupler CB Bays (indoor) 32,000 OMR - OMR - OMR -
33kV CB incl. 3-ph VT+ Control (outdoor) 30,000 OMR - OMR - 5 OMR 150,000
33kV Bus Section/Bus Coupler CB Bays (outdoor AB sw itch) 3,500 OMR - OMR - OMR -
33kV Air Break Sw itch including remote operation (outdoor) 8,000 8 OMR 64,000 5 OMR 40,000 OMR -
OMR - OMR - OMR -
OMR - OMR - OMR -
OMR - OMR - OMR -
11 kV Sw itchgear
11kV TX incoming CB (indoor) 20,000 OMR - OMR - 2 OMR 40,000
11kV Bus Section/Bus Coupler CB Bays (indoor) 15,000 OMR - OMR - 1 OMR 15,000
11kV Outgoing Feeder (indoor) 12,000 OMR - OMR - 10 OMR 120,000
11V TX incoming CB (indoor) - 31.5kA 23,000 OMR - OMR - OMR -
11kV Bus Section/Bus Coupler CB Bays (indoor) - 31.5kA 17,250 OMR - OMR - OMR -
11kV Outgoing Feeder (indoor) - 31.5kA 13,800 OMR - OMR - OMR -
11kV Sectionaliser (outdoor AB sw itch) 3,500 4 OMR 14,000 2 OMR 7,000 OMR -
11kV Auto-recloser (Outdoor) 15,500 OMR - 1 OMR 15,500 OMR -
11kV Ring Main Unit w ith remote control (outdoor) 15,500 OMR - OMR - OMR -
OMR - OMR - OMR -
OMR - OMR - OMR -
Transformers
20MVA 33/11kV 150,000 OMR - OMR - 2 OMR 300,000
10MVA 33/11kV 100,000 OMR - OMR - OMR -
6MVA 33/11kV 80,000 2 OMR 160,000 1 OMR 80,000 OMR -
23MVA Booster Transformer 100,000 OMR - OMR - OMR -
500kVA, 11/0.415 kV Auxiliary Transformer 5,500 OMR - OMR - 2 OMR 11,000
3 MVA 11kV Booster Transf ormer 40,000 OMR - OMR - OMR -
OMR - OMR - OMR -
Option 7
Asset
Item Description Unit Cost Units Required Total Cost
Cables
33 kV Cables Cost per km Subtotal OMR 688,000
33kV cable 3c 300mm2 (Easy terrain) 64,000 1 OMR 64,000
33kV cable 3c 300mm2 (Moderate terrain) 75,000 5 OMR 375,000
33kV cable 3c 300mm2 (Hard terrain) 83,000 3 OMR 249,000
11kV Cables Cost per km Subtotal OMR -
Overhead Lines
132 kV Overhead Lines Cost per km Subtotal OMR -
132 kV line (double circuit) 77,601 OMR -
33 kV Overhead Lines Cost per km Subtotal OMR 759,118
Upgrading 33kV Wolf to Panther 200mm2 8,500 OMR -
33kV Panther 200mm2 ACSR on w ood poles (Easy terrain) 17,000 5 OMR 85,000
33kV Panther 200mm2 ACSR on w ood poles (Moderate terrain) 20,000 24 OMR 480,000
33kV Panther 200mm2 ACSR on w ood poles (Hard terrain) 22,000 OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Easy terrain) 16,000 OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Moderate terrain) 19,000 OMR -
33kV Wolf 150mm2 ACSR on w ood poles (Hard terrain) 21,000 OMR -
33kV Panther 200 mm2 ACSR on 33kV S.C. Tow ers (Easy terrain) 25,000 OMR -
33kV Panther 200 mm2 ACSR on 33kV S.C. Tow ers (Moderate terrain) 29,412 OMR -
33kV Panther 200 mm2 ACSR on 33kV S.C. Tow ers (Hard terrain) 32,353 6 OMR 194,118
33kV Panther 200 mm2 ACSR on 33kV D.C. Tow ers (Easy terrain) 35,000 OMR -
33kV Panther 200 mm2 ACSR on 33kV D.C. Tow ers (Moderate terrain) 41,176 OMR -
33kV Panther 200 mm2 ACSR on 33kV D.C. Tow ers (Hard terrain) 45,294 OMR -
OMR -
33kV double circuit on 132kV Tow ers 77,601 OMR -
33 kV Pole mounted Air Break Sw itch 4,000 OMR -
Substations
Miscellaneous Subtotal OMR -
TOTAL COST OF OPTION: OMR 1,447,118
Option 7
Appendix B1 Option 1
1. Capital Inve stme nt Stream
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on investment
0
0
1,519,000 151,900 911,400 379,750 75,950 Transformer at Mintrib
1,941,000 194,100 1,164,600 485,250 97,050 Two transformers at Al Shariq + transfer Tawi Salam
595,000 59,500 357,000 178,500 3rd transformer at Al Shariq
405,500 15,190 91,140 57,385 124,055 54,475 45,405 17,850 Contingency (10%) on MZEC costs
2. Capitalised Losses
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Total Cost stream 167,090 1,002,540 964,133 1,786,672 938,068 933,412 743,254
Net Pre sent Value : 5,220,110 Omani Rial For investment period to 2020 only
Net Pre sent Value : 10,527,084 Omani Rial Including 30 years of losses, capped at 2020 value
Discount Rate = 6.0%
Appendix B2 Option 2
1. Capital Investment Stream
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on investment
-
-
3,726,000 372,600 2,235,600 931,500 186,300 Establishment of Al Shariq substation
1,476,000 147,600 885,600 369,000 73,800 Reinforcement of Mintrib substation
520,200 37,260 223,560 93,150 33,390 88,560 36,900 7,380 Contingency (10%) on MZEC costs
2. Capitalised Losses
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Total Cost stream 409,860 2,459,160 1,339,714 753,690 1,485,397 1,053,863 782,644
Net Present Value : 6,783,112 Omani Rial For investment period to 2020 only
Net Present Value : 13,589,883 Omani Rial Including 30 years of losses, capped at 2020 value
Discount Rate = 6.0%
Appendix B3 Option 3
1. Capital Investment Stream
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on investment
-
-
661,000 66,100 396,600 165,250 33,050 Substation reinforcements
66,100 6,610 39,660 16,525 3,305 Contingency (10%) on MZEC costs
- - - -
2. Capitalised Losses
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Cost of Losses - - - - - - -
Appendix B4 Option 4
1. Capital Investment Stream
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on investment
-
-
576,500 57,650 345,900 144,125 28,825 Substation reinforcements
57,650 5,765 34,590 14,413 2,883 Contingency (10%) on MZEC costs
- - - -
2. Capitalised Losses
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Cost of Losses - - - - - - -
Appendix B5 Option 5
1. Capital Investment Stream
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on investment
-
-
1,236,000 123,600 741,600 309,000 61,800 Substation reinforcements
123,600 12,360 74,160 30,900 6,180 Contingency (10%) on MZEC costs
- - - -
2. Capitalised Losses
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Cost of Losses - - - - - - -
Appendix B6 Option 7
1. Capital Investment Stream
Capital Cost (OMR) 2014 2015 2016 2017 2018 2019 2020 Comments on investment
-
-
1,336,875 133,688 802,125 334,219 66,844 New 33 kV circuit with temporary connection
133,687 13,369 80,212 33,422 6,684 Contingency (10%) on MZEC costs
110,243 11,024 66,146 27,561 5,512 Final connection of new 33 kV circuit to Bediyah 132/33 kV substation
11,024 1,102 6,614 2,756 551 Contingency (10%) on MZEC costs
2. Capitalised Losses
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Cost of Losses - - - - - - -
2: Location New 33/11 kV substation and associated 11 and 33 kV cables and overhead lines in the Al Shariq
area. Also, alterations to existing substations within existing sites.
Additional 33 kV circuits in surrounding areas.
5: Flood risk map Flood risk map exists for the area: does not exist
Flood risk map does not exist for location of the new asset and/or for an area of [2 km]
around the new asset: assessment of flood risk based on height above wadi bed
6: Flood risk mitigation No specific measures needed, but normal foundations should be used ensuring that all
measures equipment is slightly raised above surrounding land levels
10: Infrastructure that Development plans have been checked up to: (not Available)
may affect flood flows
New asset will be more than [2 km] from dams, culvert,
main roads, drainage system and/or other infrastructure / buildings that may affect flood
flows: