modification of discharge chute from apron conveyor to lime Awaiting Detail Drg. From Yamunanagar.
a
stone crusher 07 days 10/10/2014 16/10/14 B SPL
2 - DASS GANG
b fixing of CSK bolts for sppilage conveyor of appron feeder not availaible 2 days 17/10/14 18/10/14 16/10/2014 WIP 1 0 2 0 0 3 B 1 - JITENDER GANG
c fixing of scrapper pin for Sppillage conveyor available 1/2 days 10/10/2014 10/10/2014 13/10/2014 Completed 2 2 A SPL
d replacement of skirt board rubber for Sppilage conveyor available 1 day 10/10/2014 11/10/2014 12/10/2014 10/13/2014 Completed 1 0 1 0 0 2 A D.N Singh
e support fixing of discharge chute of Sppilage conveyor available 1 day 11/10/2014 11/10/2014 1 1 2 A SPL
f fixing of CSK Bolt of Apron conveyor discharge chute Not available 1 day 12/10/2014 12/10/2014 1 1 2 A SPL M16X50 supplied instead of M12X50, awaiting for material
Replacement of distributer box (4 nos.) of greasing system for it has been damaged at site, now same needs to be
g
Apron conveyor. Not available 2 days 13/10/2014 14/10/2014 1 1 1 3 A SPL
replaced.
h 100FN1-: installation of V belt as well as alingment of motor available 1 day 15/10/14 15/10/14 1 2 3 A SPL
i 100DC1-: erection of venting line available 3 days 16/10/14 18/10/14 1 1 1 1 4 A SPL
installation of Bags , headers, solenoide valve, air pipe line
j
(100DC-1) Available 2 days 19/10/14 20/10/14 1 1 2 1 5 A SPL
l 100BC8-: installation of rubber, skirt board, All bolts, taper Available 2 days 6/10/2014 7/10/2014 1 1 2 J uttam construction
washers
2.1 100BC-1
a tightening of All nut bolts & fixing of taper washer available 2 days 6/10/2014 7/10/2014 C
4/10/2014 9/10/2014 COMPLETED 2 2 2 3 1 10
bearings checking & greasing of All pulleys, plumber blocks,
b
couplings available 2 days 8/10/2014 9/10/2014 C
c balance Welding to be done. available 2 days 10/10/2014 11/10/2014 1 1 2 C UTTAM
CONSTRUCTION
UTTAM
d fixing of CSK bolts for Discharge chute liner to be chacked 1 day 12/10/2014 12/10/2014 1 1 2 C
CONSTRUCTION
UTTAM
e balance work to be done of truss gallery available 3 days 13/10/2014 15/10/2014 1 1 1 1 4 C
CONSTRUCTION
UTTAM
f Belt laying & jointing available 2 days 15/10/14 16/10/14 1 4 2 7 C
CONSTRUCTION
UTTAM
g alignment of Drive unit available 2 days 17/10/14 18/10/14 11/10/2014 HOLD 1 1 3 2 7 C
CONSTRUCTION
h Modification of gantry available 2 days 10/15/2014 No Manpower 1 0 2 3 C UTTAM
CONSTRUCTION
i installation of Skirt boards,scrappers available 2 days 19/10/14 20/10/14 1 1 1 1 4 C UTTAM
CONSTRUCTION
2.2 100BC-2
a fixing of All nut bolts & taper washers available 2 days 4/10/2014 5/10/2014 1 D
4/10/2014 9/10/2014 COMPLETED 2 1 5
b bearings checking & greasing of All pulleys, plumber blocks, available 2 days 6/10/2014 7/10/2014 1 D
couplings
c erection & alignment of Drive unit available 2 days 8/10/2014 9/10/2014 12/10/2014 WIP 1 0 1 2 0 4 D Birender Yadav
d Balance welding to be done. available 2 days 10/10/2014 11/10/2014 17/10/2014 WIP 1 2 3 D UTTAM Stinger support welding
CONSTRUCTION
UTTAM
e belt laying and jointing. available 2 days 12/10/2014 13/10/2014 1 4 2 7 D CONSTRUCTION
UTTAM
g installation of discharge chute of Tripper conveyor available 2 days 1/10/2014 2/10/2014 1 1 1 1 4 C CONSTRUCTION
h instaltion of cable trolly available 3 days 14/10/14 16/10/14 4/10/2014 7/10/2014 COMPLETED 2 1 0 2 1 6 D
UTTAM
f installation of Skirt boards,scrappers available 1 days 17/10/14 17/10/14 1 1 1 1 4 D CONSTRUCTION
100BC-3 Erection and alinment of belt conveyor with UTTAM unable to start the job due to rain water logged in side the
2.3
accessories available 25 DAYS 10/10/2014 5/11/2014 1 1 1 1 4 E CONSTRUCTION tunnel
100BC4-Erection and alinment of belt conveyor with UTTAM unable to start the job due to heavy rain water logged in
2.4
accessories available 10 days 10/10/2014 19/10/14 1 1 2 2 6 F CONSTRUCTION side the tunnel
2.5 100DC2 - Erection of dust collector with accessories available 10 days 10/10/2014 20/10/14 17/10/2014 WIP 1 2 0 2 5 G 3 - IMRAN GANG
2 - Uttam Cons.
UTTAM
100FN2 -Erection of fan with accessories available 05 days 19/10/14 24/10/14 1 1 1 3 F
CONSTRUCTION
UTTAM
2.6 100BC4-: erection of plateform of Transfer tower available 4 DAYS 21/10/14 24/10/14 11/10/2014 WIP 1 0 0 1 0 2 G Welding is in progress.
CONSTRUCTION
2.7 100BC5 -
a erection and alingment of All gentry, structure support, short available 10 days 10/10/2014 19/10/14 11/10/2014 WIP 1 0 0 1 0 2 H UTTAM CONS. Welding is in progress.
supports, strinzer & idlers
UTTAM
b Welding of structure support available 3 days 10/10/2014 12/10/2014 8/10/2014 10/10/2014 COMPLETED 2 1 3
CONSTRUCTION
UTTAM
c installation of Head & tail end structure available 2 days 8/10/2014 9/10/2014 17/10/2014 WIP 1 0 0 1 2 I
CONSTRUCTION
UTTAM
d installation of Head frame pulleys available 1 day 10/10/2014 10/10/2014 1 1 1 1 4 I
CONSTRUCTION
UTTAM
e installation of All pulleys and erection of gravity takeup pulley available 3 days 11/10/2014 13/10/14 1 1 1 1 4 I
CONSTRUCTION
UTTAM
f ladder fixing of Transfer tower available 1/2 day 14/10/2014 14/11/2014 1 1 1 1 4 I
CONSTRUCTION
UTTAM
g erection & alignment of Drive unit available 2 days 22/10/14 23/10/14 1 1 1 1 4 H
CONSTRUCTION
UTTAM
h belt laying and jointing available 2 days 24/10/14 25/10/14 1 4 2 7 H
CONSTRUCTION
UTTAM
i erection of Diverting gate & discharge chute available 2 days 15/10/14 16/10/2014 1 1 1 1 4 I
CONSTRUCTION
UTTAM
j balance work of Ducting to be done available 5 day 26/10/2014 30/10/2014 1 1 1 1 4 H
CONSTRUCTION
UTTAM
k installation of Skirt boards,scrappers available 2 day 31/10/14 1/11/2014 1 1 1 1 1 H
erection and alingment of Rotary air lock of 200 DC-1with CONSTRUCTION
UTTAM
l available 1 day 17/10/14 17/10/14 1 1 1 1 4 I
drive CONSTRUCTION
UTTAM
m erection of Air pip line available 1 day 18/10/14 18/10/14 1 1 1 1 1 I
CONSTRUCTION
UTTAM
n erection of Expansion joint available 1/2day 19/10/14 19/10/14 1 1 1 1 1 I
CONSTRUCTION
UTTAM
o drive alingment of 200 FN-1 available 1day 20/10/14 20/10/14 1 1 1 1 1 I
CONSTRUCTION
2.9 200BC1 -:
UTTAM
a nut bolts tightning & fixing of taper washer available 1/2 days 21/10/14 21/10/14 1 1 2 I
CONSTRUCTION
UTTAM
b erection & alignment of Drive unit available 2 days 22/10/14 23/10/14 1 1 1 1 4 I
CONSTRUCTION
UTTAM
c belt laying and jointing available 2 days 24/10/14 25/10/14 1 2 2 5 I
CONSTRUCTION
Bearings checking & greasing of All pulleys, plumber blocks, UTTAM
d
couplings available 1 day 26/10/14 26/10/14 1 1 1 3 I CONSTRUCTION
UTTAM
e balance Welding to be done. available 1 day 27/10/14 27/10/14 10/10/2014 10/10/2014 COMPLETED 1 1 2 1 5 I CONSTRUCTION
UTTAM
f erection of Discharge chute available 2 days 28/10/14 29/10/14 12/10/2014 WIP 1 0 0 2 3 I Erection Completed. Welding work is in progress.
CONSTRUCTION
UTTAM
g duct connection of Bag filter available 2 days 30/10/14 31/10/14 11/10/2014 No Manpower 1 1 1 1 4 I
CONSTRUCTION
3 200BC2
a fixing and tightening of all nut bolts & taper washers available 1/2 days 1/11/2014 1/11/2014 1 1 2 I UTTAM
CONSTRUCTION
UTTAM
b erection & alignment of Drive unit available 2 days 2/11/2014 3/11/2014 1 1 1 1 4 I
CONSTRUCTION
bearings checking & greasing Of All pulleys, plumber blocks, UTTAM
c available 1 days 4/11/2014 4/11/2014 1 1 3 I
couplings CONSTRUCTION
UTTAM
d balance Welding to be done. available 2 days 5/11/2014 6/11/2014 10/10/2014 10/10/2014 COMPLETED 1 1 2 1 5 I CONSTRUCTION
UTTAM
e belt laying and jointing available 2 days 7/11/2014 8/11/2014 1 3 1 5 I CONSTRUCTION
UTTAM
f duct connecion of Bag filter available 2 days 9/11/2014 10/11/2014 1 1 1 1 4 I CONSTRUCTION
UTTAM
g installation of Skirt boards,scrappers available 1 days 11/11/2014 11/11/2014 1 1 1 1 4 I CONSTRUCTION
UTTAM
h duct connection of Bag filter available 1 days 12/11/2014 12/11/2014 1 1 1 1 4 I CONSTRUCTION
UTTAM Erection Completed. Welding work is in progress. (gang
i erection of Discharge chute available 2 days 13/11/14 14/11/14 11/10/2014 WIP 1 1 0 2 4 I CONSTRUCTION who are working in 200 BC2 discharge chute erection are
also working here)
3.2 200WF2-: support fixing of discharge chute of Weigh feeder available 1 days 19/10/14 19/10/14 COMPLETED 1 1 1 1 4 B SPL
3.3 200WF3-: support fixing of discharge chute of Weigh feeder available 1 days 20/10/14 20/10/14 1 1 1 1 4 B SPL
3.4 200WF4-: support fixing of discharge chute of Weigh feeder available 1 days 23/10/14 23/10/14 1 1 1 1 4 B SPL
1 - Jitender Chauhan
a Proper adjustment of pin gate available 1 days 10/15/2014 10/15/2014 COMPLETED 1 0 2 0 0 3 2 - Dass Gang
3.5 200BC3-:
a fixing and tightening of nut bolts & taper washers available 1 days 2/11/2014 2/11/2014 1 1 2 H UTTAM
CONSTRUCTION
d bearings checking & greasing Of All pulleys, plumber blocks, available 2 days 3/11/2014 4/11/2014 1 1 1 3 H UTTAM
couplings CONSTRUCTION
UTTAM
b erection & alignment of Drive unit available 2 days 5/11/2014 6/11/2014 1 1 1 1 4 H
CONSTRUCTION
UTTAM
e balance Welding to be done available 2 days 7/11/2014 8/11/2014 1 1 2 H
CONSTRUCTION
UTTAM
f belt laying and jointing available 2 days 9/11/2014 10/11/2014 1 3 1 5 H
CONSTRUCTION
UTTAM
c installation of Skirt boards,scrappers available 2 days 11/11/2014 12/11/2014 1 1 1 1 4 H
CONSTRUCTION
3.6 200DC2 -:
c installtion of solinoide valve, hose pipe available 1 days 26/10/14 26/10/14 1 1 1 1 4 B SPL
3.7 200BC4-:
erection and alingment of All pulleys and structure fixing of
a
gravity takeup available 3 days 22/10/14 24/10/14 1 1 1 1 4 A SPL
b fixing and tightening of All nut bolts & taper washer available 1 days 25/10/14 25/10/14 15/10/2014 Completed 0 0 2 0 0 2 A Dass Gang
c erection & alignment of Drive unit available 2 days 28/101/14 29/10/14 1 1 2 A SPL
d installtion of Skirt boards and scrappers available 1 days 1/11/2014 1/11/2014 1 1 1 1 4 A SPL
3.9 300BC1-:
b fixing and tightening of All nut bolts & taper washers available 1 days 11/10/2014 11/10/2014 1 1 1 1 4 K SPL
c erection & alignment of Drive unit available 2 days 12/10/2014 13/10/14 1 1 1 1 4 K SPL
g erection of Discharge chute with flap valve 300FV1 available 1 days 17/10/14 17/10/14 8/10/2014 9/10/2014 COMPLETED 1 1 1 1 1 K SPL
Erection completion date of lime stone storage and Raw mill feeding section- 14/11/2014
RAW MILL-: Dated: 17-10-2014 Man power required
Material Mandays Actual Gang
Sr. NO. Limestone crushing section Responsibility availability required Start date Completion date Actual Start Date Completion Date Work Status Fitter Welder Rigger Khalasi Total Gang Name Remarks Reason for work delaying
a Fixing of inlet chute with double flap valve & caliberation chute. available 2 days 10/10/2014 11/10/2014 8/10/2014 9/10/2014 COMPLETED 1 1 1 1 4 2
b Liners gap to be adjusted as per drawing and fixing of Balance liner bolt. available 2 days 4/10/2014 5/10/2014 1 4 1 6 1
c fixing of Balance bolts of Diaphragm available 2 days 6/10/2014 7/10/2014 1 2 1 4 1
d Outlet spout erection & modification available 2 days 2/10/2014 3/10/2014 6/10/2014 COMPLETED 1 1 1 0 3 1 Scan - Ismail Supporting strcture fixing is in progress.
e 300 DU7 Recirculation duct assembly available 17/10/2014 WIP 1 1 1 3 D.N. Singh
f Final alignment of auxiliary motor. available 2 days 3/10/2014 5/10/2014 12/10/2014 10/13/2014 COMPLETED 0 0 3 0 3 1 D.N. Singh
g Dismantling & Final alignment of main motor available 5 days 10/15/2014 10/19/2014 WIP 1 0 0 2 3 Scan - Ismail Motor dismantling completed.
Base frame alignment
h erection of Girth gear spray system. available 4days 8/10/2014 12/10/2014 11/10/2014 No Manpower 0 0 1 1 2 1
i fixing of dowel pin in Girth gear available 3 days Magnatic Drill Spair parts required
MR. ANAND & MR. SINHA
j Ducting joint for pre-heater fan to Mill inlet available 2 days 12/10/2014 13/10/14 10/10/2014 WIP 1 1 2 1 5 1 D.N. Singh
l Canvas cloth fixing between cyclone to classifier. available 2 days 15/10/2014 16/10/2014 1 1 1 1 4 1
m erection of duct from mill outlet spout to raw mill fan outlet duct. available 3 days 12/10/2014 14/10/14 1 1 1 3 6 2
m erection. Of duct from CA Fan outlet to bag house available 3 days 15/10/14 17/10/14 5/10/2014 9/10/2014 COMPLETED 1 1 1 1 4 2
p erection of Fresh air dampers from raw mill inlet to bag house inlet. available 2 days 10/10/2014 11/10/2014 1 1 1 1 4 3
r dressing of all false structure available 10 days after completion of all jobs
s 2nos. saddle fixing from preheater fan to bag house inlet duct. available 2 days 19/10/14 20/10/14 1 1 1 1 4 2
t removing of temporary lock of Expansion joints available 5 days 1 1 1 1 4 after completion of all jobs
v Fixing of Compressed & Water line for bag house. available 5 days 15/10/14 20/10/14 1 1 2 2 6
w connection of Lubrication pipline of main gear box. available 2 days 10/10/2014 11/10/2014 1 1 1 1 4
y Welding of hot air duct from preheater to bag house available 4 days 10/11/2014 10/15/2014 COMPLETED 1 1 1 3 D.N Singh
1 400DC2 BAG filter bag fixing,sol valves ,pressure swich fixing, work
klin feed bin areation bottom blower pipe line hader making with connection and two
2 nos of root blower400BL 3-4 mounting on civil foundation & alingment work
klin feed bin feeding close air slide blower pipe line header fabrication, erection & both
3 side discharge cone chute,flow control gate,pneumatic cylinder,manual gate,close air
slide connected to SFM and air slide 400AS12
4 Two nos of Root blower 400BL (1-2)Mounting on civil foundation ,aligment,and blowing
pipe line connected to open air slide areation hader( hader is already comleted)
Blending silo discharge air slide 400AS12 cloth fixing,erection,aligment and air slide fan
5 400FN6 Mounting,aligment,and areation blower pipe line connected to air slide
400AS12
SFM discharge chute connected to air slide and SFM venting Pipe line connected to
6 400DC2 bag filter inlet duct.
4 nos of Pnumatic slide gate and 4 nos of pnumatic butterfly valve. compressed air line
7 pipe hader making & connection work.
8 silo inside cone venting fan 400FN9 and venting duct erection work
9 silo out side two nos inspection door and cone inspection door fixing work
air slide fan 400FN3 Mounting,alingment and areation blower pipe line connection to
10 hexgonal hader
Close Air Slide 400 AS2 to 400AS5 & parallel distributor blower pipe line fabrication and
1 erection
3 SILO top bag filter400DC1 inlet venting duct connected to 400BE1 work
4 silo top bucket elevator 400BE1 discharge Chute connected to 400AS1 air slide
silo top parallel distributer with close air slide areation blower pipe line connection work
5 and air slide fan fixing with alingment work
400DC1 bag filter bag fixing,sol valves,hader com air line connection,inlet duct
6 connected to silo socket
1 Venting connection
2 Bucket elevator casing alignment, casing locking & top hood lifting and aligment work
Drive arrngement for Aux & main drive,drive platform, shifting,lifting, erection,and
3 aligment work
4 steel cord belt ,shifting, lifting,and belt jointing device fixing work
Avilable 10 _ _ 10-Oct
Avilable 4 _ _
Avilable 4 _ _
Mr. Rajiv and Mr. Ankit
Avilable 10 _ _ 10-Oct
Available 1 _
Available 2 _
1 1 1 2
1 1 1 2
WIP 1 1 1 1
WIP 1 1 1 1
HOLD 1 1 1 2
1 1 1 2
1 1 1 2
1 1 1 2
1 1 1 2
1 1 1 2
WIP 1 1 2 2
No Manpower 1 1
1 1 1 2
1 1 1 2
1 1 1 2
1 1 1 2
WIP 1 1 1 1
1 1 2 2
1 3 4
1 1 3
1 1 3
ired:-
Total Gang Gang Name Remarks
5 1-GANG
5 1-GANG
5 2-GANG
5 1-GANG
5 1-GANG
5 1-GANG
5 1-GANG
2 No Manpower
5 1-GANG
5 1-GANG
5 1-GANG
5 1-GANG
4 GANG-3 Scan-Ismail
6 GANG-3
8 GANG-3
5 GANG-3
5 GANG-3
Reason for work delaying
PREHEATER & KILN SECTION:- Dated: 17-10-2014 Man power required:-
Sr. No. Work Descripion Responsibiliy Material Days required. Start date Completion date Actual Start date Actual Completion date Work Status Fitter Welder Rigger Khalasi Gas Cutter Total TEAM Gang Name Remarks.
availability
4 Downcomer support structure erection. 3 02.10.2014 04.10.2014 12.10.2014 WIP 1 1 5 2 9 Gang - C D.N. Singh
Down comer duct finishing work and expansion joint 2 - Jitendra Gang
6 modification work. 8 12.10.2014 19.10.2014 12.10.2014 WIP 0 2 0 1 3 Gang -C 1 - Nepali worker
7 Downcomer duct hinged support erection 4 09.10.2014 12.10.2014 1 2 2 2 8 Gang - B Rigging extra
11 Guide vane erection at cyclone 1 5 20.10.2014 24.10.2014 11.10.2014 15.10.2014 Completed 1 1 2 0 1 5 Gang -C
12 Actuator erection work at inlet hood 3 11.10.2014 13.10.2014 03.10.2014 11.10.2014 Completed 2 1 1 1 1 6 Gang - A &
Gang D
13 Airslide erection at preheater top 6 25.10.2014 30.10.2014 1 1 5 2 9 Frontage not available due to UCPL work
balance.
14 Meal pipe modification at 3 rd cyclone. 7 13.10.2014 19.10.2014 04.10.2014 08.10.2014 Completed 1 1 0 2 4 Gang - B
15 Meal pipe dismantling & welding from 1st to 3rd & CV 5 20.10.2014 24.10.2014 8.10.2014 WIP 1 1 2 0 1 5 Gang - B Jitendra Gang Meal pipe dismantling completed, Welding
furnace work is in progress
17 9 Nos pocking hole cover to be fix. Not available. 2 08.10.2014 10.10.2014 1 1 2 4 Gang - A Awaiting material
18 Calciner duct rectification & welding 7 02.10.2014 08.10.2014 01.10.2014 14.10.2014 Completed 0 2 0 1 0 3 Gang - B
Kiln
1 Kiln inlet seal pneumatic cylinder to be fix Not available. 3 15.10.2014 17.10.2014 1 1 0 2 4 Gang - A Nipple, connector and valve yet to received
2 Graphite lubricator arrangement fixing. 5 03.10.2014 07.10.2014 15.10.2014 WIP 1 1 1 1 1 5 Gang - A Jitendra Gang
3 Support roller bearing housing oil tray modification 2 02.10.2014 Completed 1 2 1 4 Gang -C
5 Girth gear guard rectification work. 8 18.10.2014 25.10.2014 1 1 2 2 6 Gang - A Hold due to Drg req.
16 Kiln feed bucket elevator - 400 BE 2 30 10.10.2014 10.11.2014 1 1 4 2 8 Gang F Not AV.
Cooler
Six nos of air blaster cylinder fixing,ss tubing
connection,sol valves control pannel mounting and
1 Availability 6 2-Oct 7-Oct 9-Oct Completed 1 0 1 1 3 GANG 1
compressed air pipe line connection to sol valves
control pannel
4 Fans motor alignment is
completed & rest 2 fans motor
2 Six nos of cooling fan motor aligment work Availability 12 2-Oct 13-Oct HOLD 1 1 1 1 4 GANG 1 SCAN - Birender yadav
alignment will be started after
engicon decision.
Six no. of cooling fan duct modification then
3 connected to fan outlet flexible joint & balance Availability 8 8-Oct 15-Oct 13-Oct WIP 1 1 1 3 GANG 1 SCAN - Birender yadav 500 FN13, 500 FN11 Work is
welding work,And cooler inlet hood expnsion joint completed
outside angle full welding work
4 centralised grease lubrication system male connector Availability 1 11-Oct 11-Oct 7-Oct 12-Oct Completed 1 1 0 1 3 GANG 1
connected to roller bearing block.
5 Clinker braker discharge chute shifting & erection Availability 4 14-Oct 17-Oct 10-Oct WIP 1 1 1 1 4 GANG 1 SCAN - Birender yadav Material Shifted.
No progress
Cooler discharge flap valve 14 nos of pneumatic
6 Availability 7 18-Oct 24-Oct 10-Oct 16-Oct Completed 1 1 1 1 4 GANG 1 SCAN - Birender yadav PU tube male Connector is not
cylinder fixing and compressed air pipe line available. Rest work completed.
connection to PU tube pipe work.
7 Clinker braker drive motor aligment & v-belt fixing Availability 1 24-Oct 24-Oct 1 2 GANG 1
work
Mr. Rajiv paithya & Mr. Ankit rajgarhia
8 Grate Cooler air blaster control panel frame mounting Availability 1 5-Oct 6-Oct Completed 1 1 1 1 4 GANG 1
DPC-1
1 DPC-1 Gallery structer ,top pannel material shifting Availability 16 12-Oct 27-Oct 17/10/2014 WIP 1 1 1 2 5 Gang 2 & Material shifting in progress.
and aligment work. Rigging Gang
2 DPC-1 Rail frame fixing work and hand rail fixing work Availability 7 28-Oct 3-Nov 1 1 1 2 5 Gang 2
4 Head sprocket erection & aligment work Availabity 4 29-Oct 1-Nov 1 1 1 2 5 Gang 1
5 DPC-1 bucket chain erection work Availabity 5 1-Nov 5-Nov 1 1 1 2 5 Gang 1& 2
7 Drive arrngement erection and aligment work Availabity 5 6-Nov 10-Nov 1 1 2 2 6 Gang 1
DPC-2
2 Alignment of head frame and tail frame Available 3 16-Oct 18-Oct 1 1 2 2 6 Gang 4
3 Erection of short post with aligment work Available 4 22-Oct 26-Oct 1 1 2 2 6 Gang 4
8 Discharge hood and chute fixing work Available 3 9-Nov 12-Nov 1 1 2 2 6 Gang 4
k Mix duct Calciner & C.V. Furnance available 15 12/10/2014 14/10/14 6/10/2014 WIP 4 1 7 0 1 13
Mr. Ashish Tiwari
Gang2
Gang 4
Gang 3
Gang 4
Gang 3
Gang1
Gang 4
Gang 1
Gang3
Work in progress by using insulation
Gang 2
block of 100 mm & 25 mm thk. Due
to insulation block 125 mm
unavailability.
Gang1
Ram ujagir &
co.
Gang3
Gang3
Work is pending due to kiln tip
anchor unavailability
Gang2
COAL MILL SECTION:- Dated: 17-10-2014 Man power required.
Completion Actual Start date Actual Completion Gas
Sr. No. Work Descripion Responsibiliy Material availability Days required. Start date Work Status Fitter Welder Rigger Khalasi Total Team Gang Name Remarks. Reason for work delaying
date date Cutter
1 Seprator drive alignment avail. 1 30.09.2014 9.10.2014 10.10.2014 Completed 1 1 1 1 0 4 Gang - A Client checking balance.
2 F.K.Pump drive alignment avail. 3 2.10.2014 6.10.2014 2.10.2014 6.10.2014 1 1 1 1 Gang - A Released for half grouting
4 Booster fan alignment avail. 3 3.10.2014 5.10.2014 16.10.2014 WIP 1 0 1 0 2 Gang - B Birender Yadav Coupling Fitting is under progress
5 1100 RVF6,7 &8 spocket fixing & drive alignment avail. 1 6.10.2014 6.10.2014 4.10.2014 6.10.2014 Completed 1 1 1 1 Gang - C
6 Coal dosing pipe line welding & erection avail. 2 7.10.2014 8.10.2014 4.10.2014 WIP 0 1 0 1 2 Gang -C Birender Yadav
7 Blower to F.K.Pump pipe line support avail. 1 7.10.2014 8.10.2014 1 1 1 Gang -C Due to non Av. of flooring(UCPL)
11 C02 inertization system cylinder installation avail. 3 10.10.2014 12.10.14 1 1 2 Gang -C Due to non Av. of flooring(UCPL)
12 Hot air duct structure avail. 8 13.10.2014 20.10.14 8.10.2014 WIP 1 2 3 4 0 10 Pearlcem Engineering
13 Hot air duct material shifting & erection avail. 15 10.10.2014 24.10.14 11.10.2014 WIP 1 2 2 2 0 7 Gang -C Pearlcem Engineering
Mr. Ankit rajgarhia & Mr. Rajiv paithya
14 Fine coal bin rupture disc avail. 1 9.10.2014 9.10.2014 6.10.2014 6.10.2014 Completed 1 1 1 1
15 Fixing of Fine coal bin load cell avail. 3 10.10.2014 12.10.14 1 1 1 1 4 Gang - A
16 Fixing of Raw coal hopper load cell avail. 2 13.10.14 14.10.14 1 1 1 1 Gang - B
18 All chute & duct support avail. 4 10.10.2014 13.10.2014 Completed 1 1 1 1 Gang - B
19 1100 DU 7 duct support avail. 2 Due to non AV. ofcoal mill shed (UCPL)
22 2 nos expention joint cloth changing Not avail. 1 21.10.14 21.10.14 Gang -C Due to wrong erection damaged
1 1 1 2
23 Bag filter hose clamp fixing Not avail. 1 21.10.14 21.10.14 Gang - A Received clamps size are small
24 1100 DC 2 rupture disc flange (Explotion door) avail. 2 14.10.2014 15.10.14 7.10.2014 8.10.2014 Completed 1 1 0 1 3 Gang - A
25 Bag filter bag & cages fixing avail. 5 14.10.14 19.10.14 1 1 1 1 Gang - B
Gang - D
All 3 nos. hoppeer setting 9 10.10.2014 18.10.2014 13/10/2014 WIP 0 2 0 2 0 4 1- Dass Gang Running Welding work in progress.
1 1- D.N Singh
Erection of hopper discharge chute 500CH 12A,13A & 22A 2 25.10.2014 26.10.2014 1 1 2 1 5
8
Inlet duct rectification & erection work with support 15 10.10.2014 25.10.2014 13/10/2014 WIP 1 1 7 1 10 Scan- Ismail
14
Erection & aligment of E tube rapping system 4 04.11.2014 07.11.2014 1 1 2 1 5 Subject to availability OF Anvil plate
20
Erection,fit up & welding of casing baffle plate,ladder & rungs 10 4.11.2014 13.11.2014 1 1 2 1 5
24
Finishing Date:-13.11.2014
GRINDING UNIT SECTION:- Dated: 17-10-2014 Man power required
Completion Actual Start Actual
Sr No. Work Description Responsibility Material availability Mandays required Start date date Date Completion Date Work Status Fitter Welder Rigger Khalasi Gas Cutter Total Gang Agency Remarks
IMPULSTUBE,FLOW
TRANSMETER AND
PIEZOMETRIC RING NOT
23 INSTRUMENTS WORK IN COOLER. AVAILABLE RECEIVED AT SITE AS
MENTION IN PACKING
LIST
TRAY WORK FROM CCR TO COAL MILL THROUGH ESP FAN AND COAL
24 CRUSHER 15-Nov AVAILABLE
25 TRAY WORK IN ESP TOP AND INSTRUMENTATION WORK IN ESP 22-Nov AVAILABLE
26 IO TERMINATION AND CJB TERMINATION IN CCR . AVAILABLE AVAILABLE
27 IO TERMINATION AND CJB TERMINATION IN LC3 . AVAILABLE AVAILABLE
28 CABLE LAYING FROM LC3 TO BLENDING SILO. AVAILABLE AVAILABLE
29 CABLE LAYING FROM LC3 TO RAWMILL INSTRUMENTS. AVAILABLE AVAILABLE
30 CABLE LAYING FROM LC3 TO RAWMILL DAMPERS. AVAILABLE AVAILABLE
31 CABLE LAYING FROM COALMILL INSTRUMENTS AND 0 LVL MOTORS. AVAILABLE AVAILABLE
32 CABLE LAYING FROM CCR TO BOOSTER FAN AND ITS DAMPER. AVAILABLE AVAILABLE
33 CABLE LAYING FROM CCR TO PH ,COOLER AND ESP INSTRUMENTS. AVAILABLE AVAILABLE
34 CABLE LAYING FROM CCR TO LC4, LC3 BAGHOUSE FAN AND LC2 . AVAILABLE AVAILABLE
35 TRAY WORK FROM COOLER TO CSP AVAILABLE AVAILABLE
MECH DATE NOT
36 ADDITIVE CRUSHER TRAY WORK AND LPBS FIXING AVAILABLE AVAILABLE
37 TRAY WORK AND LPBS FIXING IN PACKER BUILDING AVAILABLE AVAILABLE
38 TRAY WORK AND LPBS FIXING IN PACKER FOR TRUCK LOADER AVAILABLE AVAILABLE
39 CABLE LAYING IN CSP BUILDING AVAILABLE AVAILABLE
40 CABLE LAYING IN PACKER BUILDING AVAILABLE AVAILABLE
MECH DATE NOT
41 TRAY WORK IN COALMILL DUMPHOPPER AND STORAGE AVAILABLE AVAILABLE
42 CABLE TRAY WORK IN LC5 CABLE CELLER 20-Nov AVAILABLE
43 PANEL ERECTION IN LC5 AND TRANSFORMER ERECTION WITH BUS DUCT 20-Nov AVAILABLE
44 CABLE TRAY WORK FROM LC5 CABLE CELLER TO PACKER BUILDING 20-Nov AVAILABLE
45 CEMENT MILL HOUSE TRAY WORK LPBS, CJB FIXING 20-Nov AVAILABLE
46 CEMENT MILL FEEDING TRAY WORK AND LPBS ,CJB FIXING. 20-Nov AVAILABLE
47 CABLE LAYING FOR ALL LOAD CENTER FOR PLC (OFC) 2-Dec AVAILABLE
48 CABLE LAYING FOR LC5 AVAILABLE
49 TRAY WORK AND LPBS FIXING FOR CEMENT SILO AVAILABLE
50 CABLE LAYING WORK FOR CEMENT SILO AVAILABLE
51 LOOP TESTING IN RAWMILL,BLENDING SILO, BAGHOUSE AVAILABLE AVAILABLE
52 LOOP TESTING IN CRUSHER SECTION AVAILABLE AVAILABLE
53 LOOP TESTING IN COALMILL SECTION AVAILABLE AVAILABLE
54 COMMISIONING FOR COALMILL AVAILABLE AVAILABLE
55 LOOP TESTING IN PH KILN,COOLER SECTION AVAILABLE AVAILABLE
56 COMMISIONING PYRO SECTION AVAILABLE AVAILABLE
57 IO TERMINATION IN PACKER BUILDING AVAILABLE
58 IO TERMINATION IN LC5 AVAILABLE
59 LOOP TESTING IN CEMENTMILL AVAILABLE
60 CEMENTMILL COMISIONING AVAILABLE
61 OIL FILTERATION FOR ALL 6 TRANSFORMER AVAILABLE AVAILABLE
62 COMMISIONING FOR RAWMILL AVAILABLE AVAILABLE
REQUIRED
GANG 5 CAN 5BE
HELPERS
USED AS
MISSCELANIOUS
WORK
DAYS REQUIRED MAN POWER
START DATE FINISH DATE SECTION Work status GANG
FOR ERECTION REQUIRED
7 11-Oct 18-Oct RAWMILL WIP 2 GANG 1
GANG 5 &
4 15-Oct 19-Oct RAWMILL WIP 5 GANG 3
5 12-Oct 17-Oct RAWMILL completed 2 GANG 2
7 18-Oct 24-Oct RAWMILL 2 GANG 2
2 HELPER JOSEPH
3 ELECTRICIAN GANG 2 RAJA
4 HELPER REQUIRED
5 ELECTRICIAN GANG 3 GANESH
6 HELPER ANIL
7 HELPER REQUIRED
8 HELPER REQUIRED
9 HELPER REQUIRED
10 FITTER GANG 4 RAMNARESH
11 HELPER REQUIRED
12 HELPER RAJESH
13 FITTER/ELEC. GANG 5 MEENU
14 ELECTRICIAN RATAN
REMARKS