LIMESTONE CRUSHING SECTION:- Dated: 17-10-2014 Man power required

Material Mandays Actual Finish


Sr No. Work Descripion Responsibility availability required Start date Completion date Actual Start Date Date Work Status Fitter Welder Rigger Khalasi Gas Cutter Total Gang Agency Remarks Reason for work delaying

1.1 Apron conveyor

modification of discharge chute from apron conveyor to lime Awaiting Detail Drg. From Yamunanagar.
a
stone crusher 07 days 10/10/2014 16/10/14 B SPL
2 - DASS GANG
b fixing of CSK bolts for sppilage conveyor of appron feeder not availaible 2 days 17/10/14 18/10/14 16/10/2014 WIP 1 0 2 0 0 3 B 1 - JITENDER GANG
c fixing of scrapper pin for Sppillage conveyor available 1/2 days 10/10/2014 10/10/2014 13/10/2014 Completed 2 2 A SPL
d replacement of skirt board rubber for Sppilage conveyor available 1 day 10/10/2014 11/10/2014 12/10/2014 10/13/2014 Completed 1 0 1 0 0 2 A D.N Singh
e support fixing of discharge chute of Sppilage conveyor available 1 day 11/10/2014 11/10/2014 1 1 2 A SPL
f fixing of CSK Bolt of Apron conveyor discharge chute Not available 1 day 12/10/2014 12/10/2014 1 1 2 A SPL M16X50 supplied instead of M12X50, awaiting for material
Replacement of distributer box (4 nos.) of greasing system for it has been damaged at site, now same needs to be
g
Apron conveyor. Not available 2 days 13/10/2014 14/10/2014 1 1 1 3 A SPL
replaced.
h 100FN1-: installation of V belt as well as alingment of motor available 1 day 15/10/14 15/10/14 1 2 3 A SPL
i 100DC1-: erection of venting line available 3 days 16/10/14 18/10/14 1 1 1 1 4 A SPL
installation of Bags , headers, solenoide valve, air pipe line
j
(100DC-1) Available 2 days 19/10/14 20/10/14 1 1 2 1 5 A SPL

Not available clamping device is not showing in drawing however it


k pipeline support of Hydraulic power pack (additional 1 day 21/10/14 21/10/14 1 1 1 3 A SPL should be provided by supplier/ CPW. Date Can be
requirment) preponded as per availability of items.

l 100BC8-: installation of rubber, skirt board, All bolts, taper Available 2 days 6/10/2014 7/10/2014 1 1 2 J uttam construction
washers

2.1 100BC-1

a tightening of All nut bolts & fixing of taper washer available 2 days 6/10/2014 7/10/2014 C
4/10/2014 9/10/2014 COMPLETED 2 2 2 3 1 10
bearings checking & greasing of All pulleys, plumber blocks,
b
couplings available 2 days 8/10/2014 9/10/2014 C
c balance Welding to be done. available 2 days 10/10/2014 11/10/2014 1 1 2 C UTTAM
CONSTRUCTION
UTTAM
d fixing of CSK bolts for Discharge chute liner to be chacked 1 day 12/10/2014 12/10/2014 1 1 2 C
CONSTRUCTION
UTTAM
e balance work to be done of truss gallery available 3 days 13/10/2014 15/10/2014 1 1 1 1 4 C
CONSTRUCTION
UTTAM
f Belt laying & jointing available 2 days 15/10/14 16/10/14 1 4 2 7 C
CONSTRUCTION
UTTAM
g alignment of Drive unit available 2 days 17/10/14 18/10/14 11/10/2014 HOLD 1 1 3 2 7 C
CONSTRUCTION
h Modification of gantry available 2 days 10/15/2014 No Manpower 1 0 2 3 C UTTAM
CONSTRUCTION
i installation of Skirt boards,scrappers available 2 days 19/10/14 20/10/14 1 1 1 1 4 C UTTAM
CONSTRUCTION
2.2 100BC-2

a fixing of All nut bolts & taper washers available 2 days 4/10/2014 5/10/2014 1 D
4/10/2014 9/10/2014 COMPLETED 2 1 5
b bearings checking & greasing of All pulleys, plumber blocks, available 2 days 6/10/2014 7/10/2014 1 D
couplings

c erection & alignment of Drive unit available 2 days 8/10/2014 9/10/2014 12/10/2014 WIP 1 0 1 2 0 4 D Birender Yadav

d Balance welding to be done. available 2 days 10/10/2014 11/10/2014 17/10/2014 WIP 1 2 3 D UTTAM Stinger support welding
CONSTRUCTION
UTTAM
e belt laying and jointing. available 2 days 12/10/2014 13/10/2014 1 4 2 7 D CONSTRUCTION
UTTAM
g installation of discharge chute of Tripper conveyor available 2 days 1/10/2014 2/10/2014 1 1 1 1 4 C CONSTRUCTION
h instaltion of cable trolly available 3 days 14/10/14 16/10/14 4/10/2014 7/10/2014 COMPLETED 2 1 0 2 1 6 D
UTTAM
f installation of Skirt boards,scrappers available 1 days 17/10/14 17/10/14 1 1 1 1 4 D CONSTRUCTION
100BC-3 Erection and alinment of belt conveyor with UTTAM unable to start the job due to rain water logged in side the
2.3
accessories available 25 DAYS 10/10/2014 5/11/2014 1 1 1 1 4 E CONSTRUCTION tunnel
100BC4-Erection and alinment of belt conveyor with UTTAM unable to start the job due to heavy rain water logged in
2.4
accessories available 10 days 10/10/2014 19/10/14 1 1 2 2 6 F CONSTRUCTION side the tunnel
2.5 100DC2 - Erection of dust collector with accessories available 10 days 10/10/2014 20/10/14 17/10/2014 WIP 1 2 0 2 5 G 3 - IMRAN GANG
2 - Uttam Cons.
UTTAM
100FN2 -Erection of fan with accessories available 05 days 19/10/14 24/10/14 1 1 1 3 F
CONSTRUCTION
UTTAM
2.6 100BC4-: erection of plateform of Transfer tower available 4 DAYS 21/10/14 24/10/14 11/10/2014 WIP 1 0 0 1 0 2 G Welding is in progress.
CONSTRUCTION
2.7 100BC5 -

a erection and alingment of All gentry, structure support, short available 10 days 10/10/2014 19/10/14 11/10/2014 WIP 1 0 0 1 0 2 H UTTAM CONS. Welding is in progress.
supports, strinzer & idlers
UTTAM
b Welding of structure support available 3 days 10/10/2014 12/10/2014 8/10/2014 10/10/2014 COMPLETED 2 1 3
CONSTRUCTION
UTTAM
c installation of Head & tail end structure available 2 days 8/10/2014 9/10/2014 17/10/2014 WIP 1 0 0 1 2 I
CONSTRUCTION
UTTAM
d installation of Head frame pulleys available 1 day 10/10/2014 10/10/2014 1 1 1 1 4 I
CONSTRUCTION
UTTAM
e installation of All pulleys and erection of gravity takeup pulley available 3 days 11/10/2014 13/10/14 1 1 1 1 4 I
CONSTRUCTION
UTTAM
f ladder fixing of Transfer tower available 1/2 day 14/10/2014 14/11/2014 1 1 1 1 4 I
CONSTRUCTION
UTTAM
g erection & alignment of Drive unit available 2 days 22/10/14 23/10/14 1 1 1 1 4 H
CONSTRUCTION
UTTAM
h belt laying and jointing available 2 days 24/10/14 25/10/14 1 4 2 7 H
CONSTRUCTION
UTTAM
i erection of Diverting gate & discharge chute available 2 days 15/10/14 16/10/2014 1 1 1 1 4 I
CONSTRUCTION
UTTAM
j balance work of Ducting to be done available 5 day 26/10/2014 30/10/2014 1 1 1 1 4 H
CONSTRUCTION
UTTAM
k installation of Skirt boards,scrappers available 2 day 31/10/14 1/11/2014 1 1 1 1 1 H
erection and alingment of Rotary air lock of 200 DC-1with CONSTRUCTION
UTTAM
l available 1 day 17/10/14 17/10/14 1 1 1 1 4 I
drive CONSTRUCTION
UTTAM
m erection of Air pip line available 1 day 18/10/14 18/10/14 1 1 1 1 1 I
CONSTRUCTION
UTTAM
n erection of Expansion joint available 1/2day 19/10/14 19/10/14 1 1 1 1 1 I
CONSTRUCTION
UTTAM
o drive alingment of 200 FN-1 available 1day 20/10/14 20/10/14 1 1 1 1 1 I
CONSTRUCTION
2.9 200BC1 -:
UTTAM
a nut bolts tightning & fixing of taper washer available 1/2 days 21/10/14 21/10/14 1 1 2 I
CONSTRUCTION
UTTAM
b erection & alignment of Drive unit available 2 days 22/10/14 23/10/14 1 1 1 1 4 I
CONSTRUCTION
UTTAM
c belt laying and jointing available 2 days 24/10/14 25/10/14 1 2 2 5 I
CONSTRUCTION
Bearings checking & greasing of All pulleys, plumber blocks, UTTAM
d
couplings available 1 day 26/10/14 26/10/14 1 1 1 3 I CONSTRUCTION
UTTAM
e balance Welding to be done. available 1 day 27/10/14 27/10/14 10/10/2014 10/10/2014 COMPLETED 1 1 2 1 5 I CONSTRUCTION
UTTAM
f erection of Discharge chute available 2 days 28/10/14 29/10/14 12/10/2014 WIP 1 0 0 2 3 I Erection Completed. Welding work is in progress.
CONSTRUCTION
UTTAM
g duct connection of Bag filter available 2 days 30/10/14 31/10/14 11/10/2014 No Manpower 1 1 1 1 4 I
CONSTRUCTION
3 200BC2
a fixing and tightening of all nut bolts & taper washers available 1/2 days 1/11/2014 1/11/2014 1 1 2 I UTTAM
CONSTRUCTION
UTTAM
b erection & alignment of Drive unit available 2 days 2/11/2014 3/11/2014 1 1 1 1 4 I
CONSTRUCTION
bearings checking & greasing Of All pulleys, plumber blocks, UTTAM
c available 1 days 4/11/2014 4/11/2014 1 1 3 I
couplings CONSTRUCTION
UTTAM
d balance Welding to be done. available 2 days 5/11/2014 6/11/2014 10/10/2014 10/10/2014 COMPLETED 1 1 2 1 5 I CONSTRUCTION
UTTAM
e belt laying and jointing available 2 days 7/11/2014 8/11/2014 1 3 1 5 I CONSTRUCTION
UTTAM
f duct connecion of Bag filter available 2 days 9/11/2014 10/11/2014 1 1 1 1 4 I CONSTRUCTION
UTTAM
g installation of Skirt boards,scrappers available 1 days 11/11/2014 11/11/2014 1 1 1 1 4 I CONSTRUCTION
UTTAM
h duct connection of Bag filter available 1 days 12/11/2014 12/11/2014 1 1 1 1 4 I CONSTRUCTION
UTTAM Erection Completed. Welding work is in progress. (gang
i erection of Discharge chute available 2 days 13/11/14 14/11/14 11/10/2014 WIP 1 1 0 2 4 I CONSTRUCTION who are working in 200 BC2 discharge chute erection are
also working here)

3.2 200WF2-: support fixing of discharge chute of Weigh feeder available 1 days 19/10/14 19/10/14 COMPLETED 1 1 1 1 4 B SPL

a Proper adjustment of pin gate available 1 days 10/13/2014 10/13/2014 1 0 2 0 0 3

3.3 200WF3-: support fixing of discharge chute of Weigh feeder available 1 days 20/10/14 20/10/14 1 1 1 1 4 B SPL

a Proper adjustment of pin gate available 1 days 10/14/2014 10/14/2014 COMPLETED 1 0 2 0 0 3

b duct connection of Bag filter available 1 days 21/10/14 21/10/14 1 1 1 1 4 B SPL

c installation & alignment of Drive available 1 days 22/10/14 22/10/14 1 1 1 1 4 B SPL

3.4 200WF4-: support fixing of discharge chute of Weigh feeder available 1 days 23/10/14 23/10/14 1 1 1 1 4 B SPL
1 - Jitender Chauhan
a Proper adjustment of pin gate available 1 days 10/15/2014 10/15/2014 COMPLETED 1 0 2 0 0 3 2 - Dass Gang

b installation and alingment of drive. available 1 days 24/10/14 24/10/14 1 1 1 1 4 B SPL

3.5 200BC3-:
a fixing and tightening of nut bolts & taper washers available 1 days 2/11/2014 2/11/2014 1 1 2 H UTTAM
CONSTRUCTION
d bearings checking & greasing Of All pulleys, plumber blocks, available 2 days 3/11/2014 4/11/2014 1 1 1 3 H UTTAM
couplings CONSTRUCTION
UTTAM
b erection & alignment of Drive unit available 2 days 5/11/2014 6/11/2014 1 1 1 1 4 H
CONSTRUCTION
UTTAM
e balance Welding to be done available 2 days 7/11/2014 8/11/2014 1 1 2 H
CONSTRUCTION
UTTAM
f belt laying and jointing available 2 days 9/11/2014 10/11/2014 1 3 1 5 H
CONSTRUCTION
UTTAM
c installation of Skirt boards,scrappers available 2 days 11/11/2014 12/11/2014 1 1 1 1 4 H
CONSTRUCTION
3.6 200DC2 -:

a balance work to be done of ducting available 1 days 25/10/14 25/10/14 1 1 1 1 4 B SPL

c installtion of solinoide valve, hose pipe available 1 days 26/10/14 26/10/14 1 1 1 1 4 B SPL

d installation of Air pipline available 1 days 27/10/14 27/10/14 1 1 1 1 1 B SPL

e erection of Expansion joint available 1 days 28/10/14 28/10/14 1 1 1 3 B SPL

f alingment of drive. available 1 days 29/10/14 29/10/14 1 1 1 1 4 B SPL

3.7 200BC4-:
erection and alingment of All pulleys and structure fixing of
a
gravity takeup available 3 days 22/10/14 24/10/14 1 1 1 1 4 A SPL

b fixing and tightening of All nut bolts & taper washer available 1 days 25/10/14 25/10/14 15/10/2014 Completed 0 0 2 0 0 2 A Dass Gang

bearings checking & greasing Of All pulleys, plumber block,


e
couplings available 2 days 26/10/14 27/10/14 1 1 1 3 A SPL

c erection & alignment of Drive unit available 2 days 28/101/14 29/10/14 1 1 2 A SPL

f belt laying and jointing available 2 days 30/10/14 31/10/14 1 4 2 7 A SPL

d installtion of Skirt boards and scrappers available 1 days 1/11/2014 1/11/2014 1 1 1 1 4 A SPL

3.9 300BC1-:

a installaion of Head frame available 1 days 10/10/2014 10/10/2014 1 1 1 1 4 K SPL

b fixing and tightening of All nut bolts & taper washers available 1 days 11/10/2014 11/10/2014 1 1 1 1 4 K SPL

c erection & alignment of Drive unit available 2 days 12/10/2014 13/10/14 1 1 1 1 4 K SPL

d installation of Skirt boards, scrappers available 1 days 14/10/14 14/10/14 1 1 1 1 4 K SPL


bearings checking & greasing of All pulleys, plumber blocks,
e available 1 days 15/10/14 15/10/14 1 1 1 3 K SPL
couplings
f belt laying and jointing available 1 days 16/10/14 16/10/14 1 4 2 7 K SPL

g erection of Discharge chute with flap valve 300FV1 available 1 days 17/10/14 17/10/14 8/10/2014 9/10/2014 COMPLETED 1 1 1 1 1 K SPL

h Material Shifting In Sections. WIP 3 3 UTTAM CONS.

Note:- Total gang required :- Uttam construction- 08 nos, SPL- 02 NOS

Erection completion date of lime stone storage and Raw mill feeding section- 14/11/2014
RAW MILL-: Dated: 17-10-2014 Man power required
Material Mandays Actual Gang
Sr. NO. Limestone crushing section Responsibility availability required Start date Completion date Actual Start Date Completion Date Work Status Fitter Welder Rigger Khalasi Total Gang Name Remarks Reason for work delaying

a Fixing of inlet chute with double flap valve & caliberation chute. available 2 days 10/10/2014 11/10/2014 8/10/2014 9/10/2014 COMPLETED 1 1 1 1 4 2
b Liners gap to be adjusted as per drawing and fixing of Balance liner bolt. available 2 days 4/10/2014 5/10/2014 1 4 1 6 1
c fixing of Balance bolts of Diaphragm available 2 days 6/10/2014 7/10/2014 1 2 1 4 1

d Outlet spout erection & modification available 2 days 2/10/2014 3/10/2014 6/10/2014 COMPLETED 1 1 1 0 3 1 Scan - Ismail Supporting strcture fixing is in progress.

e 300 DU7 Recirculation duct assembly available 17/10/2014 WIP 1 1 1 3 D.N. Singh

f Final alignment of auxiliary motor. available 2 days 3/10/2014 5/10/2014 12/10/2014 10/13/2014 COMPLETED 0 0 3 0 3 1 D.N. Singh

g Dismantling & Final alignment of main motor available 5 days 10/15/2014 10/19/2014 WIP 1 0 0 2 3 Scan - Ismail Motor dismantling completed.
Base frame alignment

h erection of Girth gear spray system. available 4days 8/10/2014 12/10/2014 11/10/2014 No Manpower 0 0 1 1 2 1

i fixing of dowel pin in Girth gear available 3 days Magnatic Drill Spair parts required
MR. ANAND & MR. SINHA

j Ducting joint for pre-heater fan to Mill inlet available 2 days 12/10/2014 13/10/14 10/10/2014 WIP 1 1 2 1 5 1 D.N. Singh

k Anchor bolt fixing of cyclone support available 1 day 13/10/14 13/10/14 1 1 1 1 4 1

l Canvas cloth fixing between cyclone to classifier. available 2 days 15/10/2014 16/10/2014 1 1 1 1 4 1

m erection of duct from mill outlet spout to raw mill fan outlet duct. available 3 days 12/10/2014 14/10/14 1 1 1 3 6 2

m erection. Of duct from CA Fan outlet to bag house available 3 days 15/10/14 17/10/14 5/10/2014 9/10/2014 COMPLETED 1 1 1 1 4 2

o erection of Actuators for all dampers. available 3 days 17/10/2014 19/10/14 1 1 1 1 4 1

p erection of Fresh air dampers from raw mill inlet to bag house inlet. available 2 days 10/10/2014 11/10/2014 1 1 1 1 4 3

q Slide support to be free from duct. available 1 day 18/10/14 18/10/14 1 1 1 1 4 2

r dressing of all false structure available 10 days after completion of all jobs

s 2nos. saddle fixing from preheater fan to bag house inlet duct. available 2 days 19/10/14 20/10/14 1 1 1 1 4 2

t removing of temporary lock of Expansion joints available 5 days 1 1 1 1 4 after completion of all jobs

u Balance welding of all ducts. available 10days 10/10/2014 19/10/14 3 3 6

v Fixing of Compressed & Water line for bag house. available 5 days 15/10/14 20/10/14 1 1 2 2 6

w connection of Lubrication pipline of main gear box. available 2 days 10/10/2014 11/10/2014 1 1 1 1 4

Manpower is shifdted to main motor base frame


x Installation of Torsion Shaft available 2 days 10/15/2014 10/16/2014 No Manpower 1 0 0 1 2 alignment.

y Welding of hot air duct from preheater to bag house available 4 days 10/11/2014 10/15/2014 COMPLETED 1 1 1 3 D.N Singh

Note:- Total gang required :- 03 NOS(Scan).

Erection completion date of Raw mill section section- 20/10/2014


BLENDING SILO SECTION:- Dated: 17-10-2014
Sr.No. WORK DISCRIPTION

BLENDING SILO INSIDE

1 400DC2 BAG filter bag fixing,sol valves ,pressure swich fixing, work

klin feed bin areation bottom blower pipe line hader making with connection and two
2 nos of root blower400BL 3-4 mounting on civil foundation & alingment work
klin feed bin feeding close air slide blower pipe line header fabrication, erection & both
3 side discharge cone chute,flow control gate,pneumatic cylinder,manual gate,close air
slide connected to SFM and air slide 400AS12

4 Two nos of Root blower 400BL (1-2)Mounting on civil foundation ,aligment,and blowing
pipe line connected to open air slide areation hader( hader is already comleted)
Blending silo discharge air slide 400AS12 cloth fixing,erection,aligment and air slide fan
5 400FN6 Mounting,aligment,and areation blower pipe line connected to air slide
400AS12
SFM discharge chute connected to air slide and SFM venting Pipe line connected to
6 400DC2 bag filter inlet duct.

4 nos of Pnumatic slide gate and 4 nos of pnumatic butterfly valve. compressed air line
7 pipe hader making & connection work.

8 silo inside cone venting fan 400FN9 and venting duct erection work

9 silo out side two nos inspection door and cone inspection door fixing work

air slide fan 400FN3 Mounting,alingment and areation blower pipe line connection to
10 hexgonal hader

BLENDING SILO TOP

Close Air Slide 400 AS2 to 400AS5 & parallel distributor blower pipe line fabrication and
1 erection

2 SILO top bag filter 400DC1 welding work

3 SILO top bag filter400DC1 inlet venting duct connected to 400BE1 work

4 silo top bucket elevator 400BE1 discharge Chute connected to 400AS1 air slide

silo top parallel distributer with close air slide areation blower pipe line connection work
5 and air slide fan fixing with alingment work
400DC1 bag filter bag fixing,sol valves,hader com air line connection,inlet duct
6 connected to silo socket

BLENDING SILO BUCKET ELEVATOR 400BE1

1 Venting connection

2 Bucket elevator casing alignment, casing locking & top hood lifting and aligment work

Drive arrngement for Aux & main drive,drive platform, shifting,lifting, erection,and
3 aligment work

4 steel cord belt ,shifting, lifting,and belt jointing device fixing work

5 bucket fixing work

6 Gravity take up arrangement fixinig with aligment work

Finishing Date of Blending silo : - 08.11.2014

Total gang required:- 03


4
MATERIAL No. of days
Responsibility START DATE FINISH DATE Actual Start Date
AVAILABILITY req.

Avilable 1 14-Oct 15-Oct

Avilable 12 15-Oct 27-Oct

Avilable 4 15-Oct 19-Oct 10-Oct

Avilable 6 28-Nov 3-Nov 15-Oct

Avilable 10 _ _ 10-Oct

Avilable 5 20/10/2014 25/10/2014

Avilable 4 4-Nov 8-Nov

Avilable 4 _ _

Avilable 4 _ _
Mr. Rajiv and Mr. Ankit

Avilable 4 26-Nov 30-Oct

Avilable 10 _ _ 10-Oct

Avilable 2 15-Oct 17-Oct 11-Oct

Available 1 _

Available 2 _

Available 3 15-Oct 18-Oct


Mr. socket is not availabe 2 20-Oct 22-Oct

Available 3 10.10.2014 12.10.2014 13/10/2014

Available 10 13.10.2014 22.10.2014

Available 3 23.10.2014 25.10.2014

Available 12 26.10.2014 06.11.2014

Available 2 07.11.2014 08.11.2014


Man Power required:-
Actual Finish Work Status Fitter Welder Rigger Khalasi
Date

1 1 1 2

1 1 1 2

WIP 1 1 1 1

WIP 1 1 1 1

HOLD 1 1 1 2

1 1 1 2

1 1 1 2

1 1 1 2

1 1 1 2

1 1 1 2

WIP 1 1 2 2

No Manpower 1 1

1 1 1 2

1 1 1 2

1 1 1 2
1 1 1 2

WIP 1 1 1 1

1 1 2 2

1 3 4

1 1 3

1 1 3
ired:-
Total Gang Gang Name Remarks

5 1-GANG

5 1-GANG

3 - Jitendra gang Welding Machine is repaired & welding


4 2-GANG 1 - Dass gang cable is damaged.

4 1-GANG 3 - Birender Yadav


1- Dass gang
Work is on hold due to non availability of
5 1-GANG welding machine.

5 2-GANG

5 1-GANG

5 1-GANG

5 1-GANG

5 1-GANG

6 1-GANG Ravindra Kumar

2 No Manpower

5 1-GANG

5 1-GANG

5 1-GANG
5 1-GANG

4 GANG-3 Scan-Ismail

6 GANG-3

8 GANG-3

5 GANG-3

5 GANG-3
Reason for work delaying
PREHEATER & KILN SECTION:- Dated: 17-10-2014 Man power required:-
Sr. No. Work Descripion Responsibiliy Material Days required. Start date Completion date Actual Start date Actual Completion date Work Status Fitter Welder Rigger Khalasi Gas Cutter Total TEAM Gang Name Remarks.
availability

Header pipe yet to received. Rest of work


1 Instrumentation pipe fixing on bottom cone of cyclones 5 01.10.2014 04.10.2014 11.10.2014 HOLD 1 1 2 0 4 Gang - A completed.
2 - Scan Ismail
2 Airblaster accessories fixing for all cyclones & calciner. 5 05.10.2014 09.10.2014 11.10.2014 WIP 1 0 1 2 1 5 Gang - A
1 - D.N singh

3 Retainer ring fixing at 3,2 and 1 st cyclones. 7 03.10.2014 09.10.2014 1 3 3 7 Gang - B

4 Downcomer support structure erection. 3 02.10.2014 04.10.2014 12.10.2014 WIP 1 1 5 2 9 Gang - C D.N. Singh

5 Downcomer duct pending work at top. 6 06.10.2014 11.10.2014 1 0 0 2 0 3 Gang -C

Down comer duct finishing work and expansion joint 2 - Jitendra Gang
6 modification work. 8 12.10.2014 19.10.2014 12.10.2014 WIP 0 2 0 1 3 Gang -C 1 - Nepali worker

7 Downcomer duct hinged support erection 4 09.10.2014 12.10.2014 1 2 2 2 8 Gang - B Rigging extra

8 Gas analyser fixing at inlet hood. 4 10.10.2014 13.10.14 1 2 2 1 6 Gang - A

Assembling completed, due to rain work is


9 Bag filter erection along with fan. 3 14.10.2014 16.10.2014 07.10.2014 HOLD 0 1 6 2 0 9 Gang - A on hold.
Frontage not available due to UCPL work
10 Ducting erection for bagfiler. 7 25.10.2014 31.10.2014 1 1 4 2 8 Gang -C balance.

11 Guide vane erection at cyclone 1 5 20.10.2014 24.10.2014 11.10.2014 15.10.2014 Completed 1 1 2 0 1 5 Gang -C

12 Actuator erection work at inlet hood 3 11.10.2014 13.10.2014 03.10.2014 11.10.2014 Completed 2 1 1 1 1 6 Gang - A &
Gang D

13 Airslide erection at preheater top 6 25.10.2014 30.10.2014 1 1 5 2 9 Frontage not available due to UCPL work
balance.

14 Meal pipe modification at 3 rd cyclone. 7 13.10.2014 19.10.2014 04.10.2014 08.10.2014 Completed 1 1 0 2 4 Gang - B

15 Meal pipe dismantling & welding from 1st to 3rd & CV 5 20.10.2014 24.10.2014 8.10.2014 WIP 1 1 2 0 1 5 Gang - B Jitendra Gang Meal pipe dismantling completed, Welding
furnace work is in progress

16 Finishing work at 2nd cyclones 2 17.10.2014 WIP 1 1 2 1 5 Gang - B Jitendra Gang

17 9 Nos pocking hole cover to be fix. Not available. 2 08.10.2014 10.10.2014 1 1 2 4 Gang - A Awaiting material

18 Calciner duct rectification & welding 7 02.10.2014 08.10.2014 01.10.2014 14.10.2014 Completed 0 2 0 1 0 3 Gang - B

Kiln

1 Kiln inlet seal pneumatic cylinder to be fix Not available. 3 15.10.2014 17.10.2014 1 1 0 2 4 Gang - A Nipple, connector and valve yet to received

2 Graphite lubricator arrangement fixing. 5 03.10.2014 07.10.2014 15.10.2014 WIP 1 1 1 1 1 5 Gang - A Jitendra Gang

3 Support roller bearing housing oil tray modification 2 02.10.2014 Completed 1 2 1 4 Gang -C

Nipple for conacting to housing yet to


4 Water cooling system assembling. Not available. 3 10.10.2014 12.10.2014 1 0 2 3 Gang - A received.

5 Girth gear guard rectification work. 8 18.10.2014 25.10.2014 1 1 2 2 6 Gang - A Hold due to Drg req.

It can be preponded based on increasing of


6 TA Duct damper erection (INCLUDING MODIFICATION) 8 25.10.2014 01.11.2014 1 1 1 2 5 Gang - B man power
It can be preponded based on increasing of
7 Handrail and ladder erection. 5 08.10.2014 12.10.2014 1 1 4 2 8 Gang - D man power
It can be preponded based on increasing of
8 Duct trestle welding work 5 12.10.2014 16.10.2014 2 2 4 Gang - D man power
It can be preponded based on increasing of
9 TA Duct support structure fabrication and erection 8 17.10.2014 24.10.2014 1 1 2 2 6 Gang - D
man power

10 Anubar sensor fixing. 1 20.10.2014 20.10.2014 1 0 0 1 2 Gang - A Material yet to received.

Man force required.It can be preponded


11 Total finishing work at preheater and kiln. 7 26.10.2014 01.11.2014 0 2 2 2 6 Gang - A
based on increasing of man power

12 Burner platform-structure erection 8 10.10.2014 17.10.2014 1 2 2 2 7 Gang E

13 Burner platform - Piping work 8 18.10.2014 25.10.2014 1 2 2 2 7 Gang E


Man force required.It can be preponded
based on increasing of man power
14 Burner erection 6 26.10.2014 31.10.2014 1 1 4 2 8 Gang E

15 Day oil tank connections 3 01.11.2014 03.11.2014 1 1 2 2 6 Gang F

16 Kiln feed bucket elevator - 400 BE 2 30 10.10.2014 10.11.2014 1 1 4 2 8 Gang F Not AV.

18 Coal conveying 20 18.10.2014 1 1 3 3 8 Gang G AV. Gulam surver ( Ismail )gang.

FINISHING DATE:- 10.11.2014 27

TEAM REQUIRED FROM M/s SCAN :- 05

TEAM REQUIRED FROM M/s UTTAM CONS.:- 01

TEAM REQUIRED FROM MR. ISMAIL :- 01

TOTAL GANGS REQUIRED :- 07


Reason for work delaying

Due to shortage of welding m/c work is


getting delayed.

Due to shortage of welding m/c work is


getting delayed.

Due to less manpower & rain fall.


COOLER, DPC1, DPC2:- Dated: 17-10-2014 Man power required.
Sr. No. Work Description Responsibiliy Material Days Start Date Finish Date Actual Start Actual Completion Work Status Fitter Welder Rigger Khalasi Total Gang Gang Name Remarks Reason for work delaying
Availability Required date date

Cooler
Six nos of air blaster cylinder fixing,ss tubing
connection,sol valves control pannel mounting and
1 Availability 6 2-Oct 7-Oct 9-Oct Completed 1 0 1 1 3 GANG 1
compressed air pipe line connection to sol valves
control pannel
4 Fans motor alignment is
completed & rest 2 fans motor
2 Six nos of cooling fan motor aligment work Availability 12 2-Oct 13-Oct HOLD 1 1 1 1 4 GANG 1 SCAN - Birender yadav
alignment will be started after
engicon decision.
Six no. of cooling fan duct modification then
3 connected to fan outlet flexible joint & balance Availability 8 8-Oct 15-Oct 13-Oct WIP 1 1 1 3 GANG 1 SCAN - Birender yadav 500 FN13, 500 FN11 Work is
welding work,And cooler inlet hood expnsion joint completed
outside angle full welding work
4 centralised grease lubrication system male connector Availability 1 11-Oct 11-Oct 7-Oct 12-Oct Completed 1 1 0 1 3 GANG 1
connected to roller bearing block.

5 Clinker braker discharge chute shifting & erection Availability 4 14-Oct 17-Oct 10-Oct WIP 1 1 1 1 4 GANG 1 SCAN - Birender yadav Material Shifted.
No progress
Cooler discharge flap valve 14 nos of pneumatic
6 Availability 7 18-Oct 24-Oct 10-Oct 16-Oct Completed 1 1 1 1 4 GANG 1 SCAN - Birender yadav PU tube male Connector is not
cylinder fixing and compressed air pipe line available. Rest work completed.
connection to PU tube pipe work.
7 Clinker braker drive motor aligment & v-belt fixing Availability 1 24-Oct 24-Oct 1 2 GANG 1
work
Mr. Rajiv paithya & Mr. Ankit rajgarhia

8 Grate Cooler air blaster control panel frame mounting Availability 1 5-Oct 6-Oct Completed 1 1 1 1 4 GANG 1

DPC-1

1 DPC-1 Gallery structer ,top pannel material shifting Availability 16 12-Oct 27-Oct 17/10/2014 WIP 1 1 1 2 5 Gang 2 & Material shifting in progress.
and aligment work. Rigging Gang

2 DPC-1 Rail frame fixing work and hand rail fixing work Availability 7 28-Oct 3-Nov 1 1 1 2 5 Gang 2

3 DPC-1 stranger support fixing work Availabity 4 25-Oct 28-Oct 1 1 1 2 5 Gang 1

4 Head sprocket erection & aligment work Availabity 4 29-Oct 1-Nov 1 1 1 2 5 Gang 1

5 DPC-1 bucket chain erection work Availabity 5 1-Nov 5-Nov 1 1 1 2 5 Gang 1& 2

6 DPC -1 Bucket fixing work Availabity 8 5-Nov 12-Nov 1 2 4 7 Gang 2 & 3

7 Drive arrngement erection and aligment work Availabity 5 6-Nov 10-Nov 1 1 2 2 6 Gang 1

DPC-1 Discharge hood and discharge chute,divering


8 gate,venting line connection erection work Availabity 7 1-Nov 8-Nov 1 1 2 2 6 Gang 3

9 DPC -1 RAIL gurd fixing work Avaiabity 5 9-Nov 13-Nov 1 1 2 2 6 Gang 3

DPC-1 Skart bord fixing for cooler discharge flap valve


10 Availabity 6 14-Nov 19-Nov 1 1 2 2 6 Gang 3
chute

DPC-2

clinker silo roof concrete slab not


1 Placement Head frame and tail frame with sproket Available 2 15-Oct 16-Oct 1 1 2 2 6 Gang 4
completed UCPL civil scope

2 Alignment of head frame and tail frame Available 3 16-Oct 18-Oct 1 1 2 2 6 Gang 4

3 Erection of short post with aligment work Available 4 22-Oct 26-Oct 1 1 2 2 6 Gang 4

4 Erection straingers with rail Available 6 26-Oct 31-Oct 1 1 2 2 6 Gang 4

Drive arrngement motor ,gearbox,platform lifting,


5 erection and aligment work. Available 8 1-Nov 8-Nov 1 1 2 2 6 Gang 4

6 Fixing of Chain assembly Available 5 9-Nov 13-Nov 1 1 2 2 6 Gang 1&2

7 Bucket fixing Available 3 14-Nov 17-Nov 1 1 2 2 6 Gang 1&2

8 Discharge hood and chute fixing work Available 3 9-Nov 12-Nov 1 1 2 2 6 Gang 4

Finishing Date of Blending silo : - 19.11.2014

Total gang required:- 04(Scan)


REFRACTORY:- Dated:- 17-10-2014 MAN POWER REQUIRED
Sr No. Sections:- Responsibility Material Days required Start date Completion date Actual Start Actual Finish Work Status Mason Welder Helper Cutter Supervisor Total
availability Date Date

a Cyclone 1st available 12 10/10/2014 11/10/2014 1 1 2 1 1 6

b Cyclone 11nd available 12 4/10/2014 5/10/2014 1 4 1 1 7

c Cyclone 111rd available 10 6/10/2014 7/10/2014 1 2 1 1 5

d Cyclone 1Vth available 12 8/10/2014 10-20-2014 8/10/2014 WIP 4 1 9 1 1 16

e Cyclone Vth available 10 Completed 2 0 1 1 1 5

f Kiln Inlet available 8 8/10/2014 12/10/2014 1 1 1 1 1 5

g RISER DUCT-1 available 10 1 1 1 1 1 5

h RISER DUCT-2 available 9 12/10/2014 13/10/14 1 1 1 3 1 7

i RISER DUCT-3 available 8 13/10/14 13/10/14 1 1 1 1 1 5

j RISER DUCT-4 available 7 15/10/2014 16/10/2014 5/10/2014 WIP 2 0 6 0 0 8

k Mix duct Calciner & C.V. Furnance available 15 12/10/2014 14/10/14 6/10/2014 WIP 4 1 7 0 1 13
Mr. Ashish Tiwari

l Pre Calciner available 12 15/10/14 17/10/14 1 1 1 1 1 5

m cyclone 5th Meal pipe available 3 17/10/2014 19/10/14 1 3 1 5

n cyclone 4th Meal pipe available 3 10/10/2014 11/10/2014 1 1 1 1 1 5

o cyclone 3rd Meal pipe available 3 18/10/14 18/10/14 1 1 1 1 1 5

p cyclone 2nd Meal pipe available 4 1 1 1 1 1

q cyclone 1st Meal pipe available 4 19/10/14 20/10/14 1 1 1 1 1 2

r TA Duct available 10 WIP 1 0 6 0 1 8

s Kiln available 15 Completed 3 3 1

t Kiln Out let Hood available 8 Completed 1 1 1 1 1

u Cooler available 13 5/10/2014 Completed 1 1 1 1 1

v Insulation of Ducts available 75 1

w Compressed air line available 17/10/14 18/10/14 1 1 1 1 1 4


50
x Water Line available 19/10/14 20/10/14 1 1 1 1 1 4

xi Material Shifting to cyclones, cv furnace available WIP 7 1 8


and TAD
Gang Gang Remarks Reason for work delaying
Name

Gang2

Gang 4

Gang 3

Gang 4

Gang 3

Gang1

Gang 4

Gang 1

Gang3
Work in progress by using insulation
Gang 2
block of 100 mm & 25 mm thk. Due
to insulation block 125 mm
unavailability.
Gang1
Ram ujagir &
co.

Gang3

after completion of all jobs

Gang1 after completion of all jobs

Gang3
Work is pending due to kiln tip
anchor unavailability

Gang2
COAL MILL SECTION:- Dated: 17-10-2014 Man power required.
Completion Actual Start date Actual Completion Gas
Sr. No. Work Descripion Responsibiliy Material availability Days required. Start date Work Status Fitter Welder Rigger Khalasi Total Team Gang Name Remarks. Reason for work delaying
date date Cutter

1 Seprator drive alignment avail. 1 30.09.2014 9.10.2014 10.10.2014 Completed 1 1 1 1 0 4 Gang - A Client checking balance.

2 F.K.Pump drive alignment avail. 3 2.10.2014 6.10.2014 2.10.2014 6.10.2014 1 1 1 1 Gang - A Released for half grouting

4 Booster fan alignment avail. 3 3.10.2014 5.10.2014 16.10.2014 WIP 1 0 1 0 2 Gang - B Birender Yadav Coupling Fitting is under progress

5 1100 RVF6,7 &8 spocket fixing & drive alignment avail. 1 6.10.2014 6.10.2014 4.10.2014 6.10.2014 Completed 1 1 1 1 Gang - C

6 Coal dosing pipe line welding & erection avail. 2 7.10.2014 8.10.2014 4.10.2014 WIP 0 1 0 1 2 Gang -C Birender Yadav

7 Blower to F.K.Pump pipe line support avail. 1 7.10.2014 8.10.2014 1 1 1 Gang -C Due to non Av. of flooring(UCPL)

8 Venturi conveyor system avail. 5 8.10.2014 12.10.2014 8.10.2014 Completed 1 1 1 2 Gang - B

9 1 nos linear actuvatar fixing avail. 1 05.10.14 05.10.14 Gang - A

Replacing of bend due to leakage from


10 Lubrication pipe line bend changing avail. 2 08.10.14 09.10.14 1 1 Gang - A
joints

11 C02 inertization system cylinder installation avail. 3 10.10.2014 12.10.14 1 1 2 Gang -C Due to non Av. of flooring(UCPL)

12 Hot air duct structure avail. 8 13.10.2014 20.10.14 8.10.2014 WIP 1 2 3 4 0 10 Pearlcem Engineering

13 Hot air duct material shifting & erection avail. 15 10.10.2014 24.10.14 11.10.2014 WIP 1 2 2 2 0 7 Gang -C Pearlcem Engineering
Mr. Ankit rajgarhia & Mr. Rajiv paithya

14 Fine coal bin rupture disc avail. 1 9.10.2014 9.10.2014 6.10.2014 6.10.2014 Completed 1 1 1 1

15 Fixing of Fine coal bin load cell avail. 3 10.10.2014 12.10.14 1 1 1 1 4 Gang - A

16 Fixing of Raw coal hopper load cell avail. 2 13.10.14 14.10.14 1 1 1 1 Gang - B

17 Main gear box coupling(Replacement) Not avail. 2 1 1 1 1 Gang - A

18 All chute & duct support avail. 4 10.10.2014 13.10.2014 Completed 1 1 1 1 Gang - B

19 1100 DU 7 duct support avail. 2 Due to non AV. ofcoal mill shed (UCPL)

20 All actuaor alignment & welding avail. 2 14.10.2014 15.10.2014 1 1 1 1 Gang - A

21 1100 FN4 impeller key fixing avail. 1 07.10.14 07.10.14 1 1 1 1 Gang - A

22 2 nos expention joint cloth changing Not avail. 1 21.10.14 21.10.14 Gang -C Due to wrong erection damaged
1 1 1 2
23 Bag filter hose clamp fixing Not avail. 1 21.10.14 21.10.14 Gang - A Received clamps size are small

24 1100 DC 2 rupture disc flange (Explotion door) avail. 2 14.10.2014 15.10.14 7.10.2014 8.10.2014 Completed 1 1 0 1 3 Gang - A

25 Bag filter bag & cages fixing avail. 5 14.10.14 19.10.14 1 1 1 1 Gang - B

Gang - D

FINISHING DATE :-24.10.2014

TOTAL TEAM REQ.:-4 (SCAN)


ESP SECTION:- Dated: 16-10-2014 Man Power required:-
Material Man days Actual Start Actual Completion
Sr. No. Work Descripion Responsibiliy availability required. Start date Completion date Date Date Work Status Fitter Welder Rigger Khalasi Grinder Supervisor Total Gang Gang Name Remarks. Reason for work delaying

All 3 nos. hoppeer setting 9 10.10.2014 18.10.2014 13/10/2014 WIP 0 2 0 2 0 4 1- Dass Gang Running Welding work in progress.
1 1- D.N Singh

All 3 nos hopper welding 8 13.10.2014 21.10.2014 6 6 12


2

Hopper inside Spidadr pipe fixing 6 19.10.2014 24.10.2014 1 1 2 1 5


3

Erection & alignment of 500 CC1 2 19.10.2014 20.10.2014 1 1 2 1 5


4

Erection & alignment of 500 CC1 drive 1 21.10.2014 21.10.2014 1 1 2 1 5


5

Erection & alignment of 500 CC2 3 22.10.2014 24.10.2014 1 1 2 1 5


6 UCPL Structural platform required

Erection & alignment of 500 CC2 drive 1 25.10.2014 25.10.2014 1 1 2 1 5


7

Erection of hopper discharge chute 500CH 12A,13A & 22A 2 25.10.2014 26.10.2014 1 1 2 1 5
8

Erection of 500 RAV 1,2,3 1 27.10.2014 27.10.2014 1 1 2 1 5


9

Mr. Ankit rajgarhia & Mr. Ashok ram


Erection of 500 RAV 1,2,3 discharge chute 500 CH12B,13B & 22B 2 28.10.2014 29.10.2014 1 1 2 1 5
10

Erection of 500CC1 discharge chute 500 CH 14 1 30.10.2014 30.10.2014 1 1 2 1 5


11

Erection of 500CC2 discharge chute 500 CH 15 1 26.10.2014 26.10.2014 1 1 2 1 5


12

Hopper by pass chute 2 27.10.2014 28.10.2014 1 1 2 1 5


13

Inlet duct rectification & erection work with support 15 10.10.2014 25.10.2014 13/10/2014 WIP 1 1 7 1 10 Scan- Ismail
14

Erection & alignmnt of purge air system 3 29.10.2014 31.10.2014 1 1 2 1 5


15

Erection of monorail with structure 4 31.10.2014 3.11.2014 1 1 2 1 5


16

Alignment & welding of TR sets 3 26.10.2014 28.10.2014 1 1 1 1 4


17

Alignment of support insulator 2 29.10.2014 30.10.2014 1 1 2 1 5


18

Erection & aligment of collecting plate rapping system 8 31.10.2014 07.11.2014 1 1 2 1 5


19

Erection & aligment of E tube rapping system 4 04.11.2014 07.11.2014 1 1 2 1 5 Subject to availability OF Anvil plate
20

Checking of E tube straightness 2 08.11.2014 09.11.2014 1 1 1 1 4


21

Fixing of guide frame to E tube 2 08.11.2014 09.11.2014


22

Alignment of E tube w.r.t collecting plates 4 09.11.2014 12.11.2014


23

Erection,fit up & welding of casing baffle plate,ladder & rungs 10 4.11.2014 13.11.2014 1 1 2 1 5
24

Fixing of mechanical interlock & warning brackets 5 5.11.2014 9.11.2014 1 1 2 1 5


25

Air leak test 3 2.11.2014 4.11.2014


26

Balance Welding works 10.10.2014 1.11.2014 6 6


27

TOTAL SCAN TEAM REQ.:-3team +1 Rigging gang

Finishing Date:-13.11.2014
GRINDING UNIT SECTION:- Dated: 17-10-2014 Man power required
Completion Actual Start Actual
Sr No. Work Description Responsibility Material availability Mandays required Start date date Date Completion Date Work Status Fitter Welder Rigger Khalasi Gas Cutter Total Gang Agency Remarks

1.1 CLINKER EXTRACTION AND FEEDING SECTION

ERECTION OF MS HOPPER AT OUTLET OF CLINKER


a
SILO (8 NOS) 02 Days
b ERECTION OF PIN GATE(8 NOS) 01 days
c ERECTION OF CHUTE FROM CS TO RF 03 days
d ERECTION OF RECIPROCATING FEEDERES(8NOS) 07 days
e ERECTION OF CHUTE FROM RECIPROCATING
FEEDER TO BELT CONVEYOR 03 days
BELT CONV.600BC1
Checking of Civil foundation and marking of center
f line 1 day
g Laveling of foundation 1 day
h erection of short post and straingers 02 days
i Erection of haed pully,tail pully and snub pully with
frame 03 days
j Fixing of deCk plate 02 day
k Fixing of idler with frame
l Fixing of Couplings 01 day
m Belt laying and valcanization 03 days
n Drive alignment of conveyor 02 Days
o Skirt fixing 02 days
p Hood fixing
q Discharge chute fixing from 600BC1 to 600BC3 01 day
BELT CONV.600BC2
Checking of Civil foundation and marking of center
r line 1 day
s Laveling of foundation 1 day
t erection of short post and straingers 02 days
u Erection of haed pully,tail pully and snub pully with
frame 02 days
v Fixing of deCk plate 01 day
w Fixing of idler with frame
x Fixing of Couplings 01 day
y Belt laying and valcanization 03 days
z Drive alignment of conveyor 02 Days
Skirt fixing 02 days
Hood fixing
Discharge chute fixing from 600BC2 to 600BC3 01 day
BELT CONV.600BC4
Checking of Civil foundation and marking of center
line 1 day
Laveling of foundation 1 day
Realese for half grouting 02 Days
erection of short post and straingers 02 days
Erection of haed pully,tail pully and snub pully with
frame 02 days
Fixing of deCk plate 01 day
Fixing of idler with frame
Fixing of Couplings 01 day
Belt laying and valcanization 03 days
Drive alignment of conveyor 02 Days
Skirt fixing 02 days
Hood fixing
Discharge chute fixing from 600BC4 to 600BC3 01 day
BELT CONV.600BC3
Checking of Civil foundation and marking of center
line 1 day
Laveling of foundation 1 day
Erection of vertical structure 05 dys
Realese for half grouting 04 days
Erection of gantry 06 days
erection of short post and straingers 03 days
Erection of haed pully,tail pully and snub pully with
frame
Fixing of dek plate 01 day
Fixing of idler with frame 03 days
Fixing of Couplings 02 Days
Belt laying and valcanization 02 days
Drive alignment of conveyor
Skirt fixing 01 day
Hood fixing 1 day
Discharge chute fixing 01 day
Erection of trasfer tower 04 days
ERECTION OF DIVERTING GATE 1 days
ERECTION OF CHUTE FROM 600BC3 TO 600BC6 01 day
Erection of bagfilter with comlete assembly 07 days
CHUTE FROM BF TO 600BC3 01 day
ERECTION OF BAGFILTER FAN 06 days
DRIVE ALIGNMENT 01day
FIXING OF EXPANSION JOINT 01 day
ERECTION OF FAN DISCHARGE DUCT
ERECTION OF DUCT 600DU6 10 days
ERECTION OF DAMPER
ERECTION OF EXPANSION JOINT
ERECTION OF DUCT
ERECTION OF DUCT
ERECTION OF DUCT
ERECTION OF DUCT
REVERSIBLE BELT ON THE TOP OF CLINKER AND
GYPSUM HOPPER
Checking of Civil foundation and marking of center 1 day
line
Laveling of foundation 1 day
Realese for half grouting 02 Days
erection of short post and straingers 02 days
Erection of haed pully,tail pully and snub pully with
frame 02 days
Fixing of deCk plate 01 day
Fixing of idler with frame
Fixing of Couplings 01 day
Belt laying and valcanization 03 days
Drive alignment of conveyor 02 Days
Skirt fixing 02 days
Hood fixing
ERECTION OF CHUTE
FIXING OF HIGH LEVEL INDICATOR ON HOPPER 01 day
FIXING OF LOW LEVEL INDICATOR ON HOPPER 01 day
FIXING OF PIN GATE AT THE BOTTOM OF CLINKER
AND GYPSUM HOPPER 01 day
FIXING OF SLIDE GATE AT THE BOTTOM OF FLYASH
HOPPER 01 day
CHUTE FROM CLINKER,GYPSUM, FLYASH HOPPER 02 Days
ERECTION OF WEIGH FEEDER FOR CLINKER,
GYPSUM ,FLYASH AND ITS ALIGNMENT 06 days
ERECTION OF CHUTE FROM CLINKER, GYPSUM
,FLYASH WEIGH FEEDER TO 800BC1 05 days
Erection of bagfilter with comlete assembly 06 days
RAL fixing o1 day
ERECTION OF BAGFILTER FAN 05 days
DISCHARGE DUCT FROM FAN OUTLET 01 day
EXPANSION JOINT INSTALLATION
ERECTION OF DUCT WITH EXPANSION JOINT 600EJ5
AND DAMPER
ERECTION 600DA3
OF DEDUSTING DUCT FOR CLINKER 2 days
HOPPER 10 days
ERECTION OF MANUAL BUTTERFLY DAMPER FOR
600DU8
ERECTION OF DEDUSTING DUCT FOR CLINKER
HOPPER
ERECTION OF MANUAL BUTTERFLY DAMPER FOR
600DU9
ERECTION OF DEDUSTING DUCT FOR CLINKER
HOPPER
ERECTION OF MANUAL BUTTERFLY DAMPER FOR
600DU10-
Mill feeding belt conv.
Checking of Civil foundation and marking of center 1 day
line
Laveling of foundation 1 day
Erection of supporting structure and gantry 10 days
Realese for half grouting 04 Days
erection of short post and straingers 04 days
Erection of haed pully,tail pully and snub pully with
frame 02 days
Fixing of deCk plate 02 day
Fixing of idler with frame
Fixing of Couplings 01 day
Belt laying and valcanization 03 days
Drive alignment of conveyor 03 Days
Skirt fixing 02 days
Hood fixing
GYPSUM,FLY ASH STORAGE AND CRUSHING &
FEEDING SECTION
ERECTION OF MS HOPPER FOR GYPSUM 03 days
INSTALLATION OF PIN GATE BELOW MS HOPPER
ERECTION OF CHUTE FROM GYPSUM HOPPER TO
RECIPROCATING FEEDER 01 day
ERECTION OF RECIPROCATING FEEDER 02 days
BELT CONV.
Checking of Civil foundation and marking of center
line 01 day
Laveling of foundation 01 day
Erection of supporting structure and gantry 10 days
Realese for half grouting 03 days
erection of short post and straingers 02 days
Erection of haed pully,tail pully and snub pully with
frame 02 days
Fixing of deCk plate 02 days
Fixing of idler with frame
Fixing of Couplings 01 day
Belt laying and valcanization 03 days
Drive alignment of conveyor 03 days
Skirt fixing 01 day
Hood fixing 01 day
ERECTION OF CHUTE FROM RECIPROCATING
FEEDER TO CONV 700BC1 02 day
ERECTION OF IMPACTOR
CHECKING OF CENTRE
MARKING OF CIVIL FOUNDATION
LINE AND ELEVATION 01 day
CHECKING 01 day
ERECTION OF BASE FRAME FOR IMPACTOR 01 day
ALIGNMENT OF IMPACTOR
RELEASE FOR HALF GROUTING 03 days
ERECTION OF BASE FRAME FOR MOTOR 01 Day
CHECKING,ALIGNMENT WORK AND RELEASE FOR
HALF GROUTING
ERECTION OF MOTOR WITH DRIVE PULLEY 02 Days
INSTALLATION OF V-BELT
FINAL ALIGNMENT 01 day
BELT CONV.
Checking of Civil foundation and marking of center
line 1 day
Laveling of foundation 1 day
Erection supporting structure and gantry 10 days
Realese for half grouting 02 Days
erection of short post and straingers 02 days
Erection of haed pully,tail pully and snub pully with
frame 02 days
Fixing of deCk plate 01 day
Fixing of idler with frame
Fixing of Couplings 01 day
Belt laying and valcanization 03 days
Drive alignment of conveyor 02 Days
Skirt fixing 02 days
Hood fixing
ERECTION OF CHUTE FROM IMPACTOR TO 700BC2 02 Days
ERECTION OF CHUTE FROM 700BC2 TO 600BC2 01 day
INSTALLATION OF SLIDE GATE BELOW RCC FLYASH
HOPPER 01 day
ERECTION OF SCREW FEEDER AND ITS ALIGNMENT 04 days
CHUTE FROM FLYASH HOPPER TO SCREW FEEDER 02 dyas
BUCKET ELEVATOR 700BE1
CHECKING
MARKING OF OF CENTRE
CIVIL FOUNDATION
LINE AND ELEVATION 1days
CHECKING
Boot casing erection & alignment 2 days
Half grouting of boot casing 4 days
Erection and alignment of casing 07 days
Erection and alignment head casing 3 days
Drive erection and alignment of drive 5 days
Belt fixing 7 days
Bucket fixing 10 days
CHUTE FROM 700SF1 TO BUCKET ELEVATOR 3 days
CHUTE FROM 700BE1 TO 600HP9 WITH EXP JOINT
700EJ3 3 days
ERECTION WORK FOR BAGFILTER 10 days
RAL FITTING
CHUTE FROM BF TO SCREW FEEDER 2 days
ERECTION OF BAGFILTER FAN AND ITS ALIGNMENT 07 days
Inlet outlet duct for bagfilter 06 days
DISCHARGE DUCT FROM FAN OUTLET 01 days
DISCHARGE CHUTE FROM 800BC1 01 day

1.2 CEMENT MILL SECTION


CEMENT MILL SHIFTING available 8/10/2014 10/10/2014 Completed 13 13 Uttam Cons.
CEMENT MILL LIFTING available 17/10/2014 10
CHECKING OF CIVIL FOUNDATION 1 days
MARKING OF CENTRE
MICROCHIPPING LINE
OF FOUNDATION AND PACKING
Plate 5 days
ERECTION OF BASE PLATE 1days
SHIFTING THE MILL 07 DAYS
ALIGNMENT OF BASE PLATE 3days
RELEASE FOR HALF GROUT 5days
FINAL ALIGNMENT OF BASE PLATE 5days
PLACEMENT OF BEARING HOUSING 03days
ALIGNMENT OF HOUSING
BEARING SCRAPPING WORK FOR BLUE MATCHING 7 days
ERECTION OF BEARING 1 days
ERECTION OF SHELL 7days
FIXING OF INLET AND OUTLET HEADER 7 days
ALIGNMENT OF MILL 4 days
GROUND ASSEMBLY OF GIRTH GEAR 3 days
ERECTION OF GIRTH GEAR 5 days
ALIGNMENT OF GIRTH GERAR 5 days
ERECTION OF PINION 5days
PINION ALIGNMENT
LINER FIXING 12 DAYS
CHECKING OF CIVIL FOUNDATION 3 days
MARKING OF CENTRE LINE
MICROCHIPPING OF FOUNDATION
INSTALLATION OF LUBRICATION PUMP FOR
TRUNION BEARING
CHECKING OF CIVIL FOUNDATION 3 days
MARKING OF CENTRE LINE
MICROCHIPPING OF FOUNDATION
INSTALLATION OF LUBRICATION PUMP FOR GIRTH
GEAR AND PINION
CHECKING OF CIVIL FOUNDATION 7 days
MICROCHIPPING OF FOUNDATION
INITIAL ALIGNMENT OF GEARBOX
HALF GROUTING
FINAL ALIGNMENT OF GEARBOX
CHECKING OF CIVIL FOUNDATION 7 days
MICROCHIPPING OF FOUNDATION
ERECTION OF MAIN MOTOR AND ITS ALIGNMENT
CHECKING OF CIVIL FOUNDATION 7 days
MICROCHIPPING OF FOUNDATION
ERECTION OF AUXILIARY GEAR BOX AND ITS
ALIGNMENT
CHECKING OF CIVIL FOUNDATION
MICROCHIPPING
ERECTION OF FOUNDATION
OF AUXILIARY MOTOR AND ITS
ALIGNMENT
CHECKING OF CIVIL FOUNDATION
MICROCHIPPING OF FOUNDATION
ERECTION OF CLASSIFIER 7 days
CHECKING OF CIVIL FOUNDATION
MICROCHIPPING OF FOUNDATION
ERECTION OF CENTRALIZED LUBRICATION SYSTEM
PIPE LINE CONNECTION AND FITTING
CHECKING OF CIVIL FOUNDATION 07 days
MICROCHIPPING OF FOUNDATION
ERECTION OF CYCLONE AND ITS ALIGNMENT
FITTING OF ROTARY VANE FEEDER AT THE BOTTOM
CYCLONE 2days

CEMENT MILL CLASSIFIER FAN ERECTION


CHECKING OF CIVIL FOUNDATION 2 DAYS
MICROCHIPPING
ERECTION OF FOUNDATION
OF CASING PEDASTAL AND ITS
ALIGNMENT 06 DAYS
ERECTION OF DE,NDE BEARING HOUSING
ERECTION OF IMPELLER WITH SHAFT WITH CONE
AND ITS ALIGNMENT 3 DAYS
CONE GAP CHECKING AND SETTING 01 DAY
DRIVE INSTALLATION AND ITS ALIGNMENT 05 DAY
CEMENT MILL CA FAN ERECTION 17 DAY
CHECKING OF CIVIL FOUNDATION 3 DAYS
MICROCHIPPING
ERECTION OF FOUNDATION
OF CASING PEDASTAL AND ITS
ALIGNMENT 2 DAYS
HALF GRAUTING 4DAYS
ERECTION OF DE,NDE BEARING HOUSING 5 DAY
ERECTION OF IMPELLER WITH SHAFT WITH CONE
AND ITS ALIGNMENT
CONE GAP CHECKING AND SETTING
DRIVE INSTALLATION AND ITS ALIGNMENT
BUCKET ELEVATOR
GROUND ASSEMBLY OF CASING AND ITS PLUMB
CHECKING 1 DAY
CHECKING OF CIVIL FOUNDATION
MICROCHIPPING OF FOUNDATION
ERECTION OF BOOT CASING AND ITS ALIGNMENT 04 DAY
ERECTION OF ASSEMBLED CASING UP TO REQUIRED
LEVEL AND ITS PLUMB CHECKING 15 DAYS
ERECTION OF HEAD CASING AND ITS ALIGNMENT 03 DAYS
DRIVE ALIGNMENT WORK 04 DAYS
FIXING OF BELT 02 DAY
BUCKET FIXING 07 DAYS
AIR SLIDE FEEDING TO CLASSIFIER 7DAYS
Laying of airslide
placement of blower
pipe line connection with valve
Venting line connection
ERECTION OF CHUTE FEEDING TO CLASSIFIER 01 DAY
ERECTION OF CHUTE FROM MILL DISCHARGE TO
AIR SLIDE 800AS1 02 DAYS
AIR SLIDE FOR MILL OUTLET 07 DAYS
Laying of airslide
pipe line connection with valve
Venting line connection
CHECKING OF CIVIL FOUNDATION
MICROCHIPPING OF FOUNDATION
ERECTION OF NIB TRAP BLOWER
INSTALLATION OF SLIDE GATE BELOW NIB TRAP
ERECTION OF CHUTE FEEDING TO ELEVATOR
AIR SLIDE FOR FEEDING TO CEMENT SILO 07 DAYS
Laying of airslide
pipe line connection with valve
Venting line connection
placement of blower

ERECTION OF CHUTE FEEDING TO BUCKET ELEVATOR


INSTALLATION OF SCREW SAMPLER
COURSE RETURN BELT CONV
Checking of Civil foundation and marking of center 01 DAY
line
Laveling of foundation
erection of short post and straingers 08 DAYS
Erection of haed pully,tail pully and snub pully with
frame
Fixing of deCk plate
Fixing of idler with frame
Fixing of Couplings
Belt laying and valcanization
Drive alignment of conveyor
Skirt fixing
Hood fixing
ERECTION OF CHUTE 03 DAYS

ERECTION WORK FOR BAGFILTER 10 DAYS


RAL FITTING
COMPRESSED AIR PIPING WORK
CHUTE ERECTION AT THE OUTLET- INLET DUCT FOR
800DC1 10DAYS
ERECTION WORK FOR BAGFILTER O6 DAYS
RAL FITTING
COMPRESSED AIR PIPING WORK
CHUTE ERECTION AT THE OUTLET 800DC1 01 DAYS
INLET AND OUTLET DUCT FOR BAGFILTER 800DC2 05 DAYS
CHECKING OF CIVIL FOUNDATION
MICROCHIPPING OF FOUNDATION 06 DAYS
ERECTION OF FAN
DRIVE ALIGNMENT AND CHECKING
ERECTION OF DISCHARGE DUCT OF 800FN4 01 DAYS
CHECKING OF CIVIL FOUNDATION 05 DAYS
MICROCHIPPING OF FOUNDATION
ERECTION OF FAN
DRIVE ALIGNMENT AND CHECKING
ERECTION OF DISCHARGE DUCT OF 800FN4 01 DAY
ERECTION OF DUCT WITH EXP JOINT 800EJ9 01 DAY

BUCKET ELEVATOR(CEMENT SILO) 01 DAY


CHECKING OF CIVIL FOUNDATION
MICROCHIPPING OF FOUNDATION
ERECTION OF BOOT CASING AND ITS ALIGNMENT 02 DAYS
ERECTION OF ASSEMBLED CASING ON BOOT
CASING AND ITS PLUMB CHECKING AN HALF
GROUTING
ERECTION OF ASSEMBLED CASING UP TO REQUIRED
LEVEL AND ITS PLUMB CHECKING 15 DAYS
ERECTION OF HEAD CASING AND ITS ALIGNMENT 03 DAYS
DRIVE ALIGNMENT WORK 04 DAYS
FIXING OF BELT 04 DAYS
BUCKET FIXING 07 DAYS
Airslide for Cement Silo 07 DAYS
Laying of airslide
pipe line connection with valve
Venting line connection
placement of blower
AIRSLIDE FEEDING TO 900CS1
Laying of airslide 07 DAYS
pipe line connection with valve
Venting line connection
placement of blower
FIXING OF DIVERTOR GATE AT THE OUTLET OF B/E 02 DAYS
CHUTE FROM DIVERTOR GATE TO AIR SLIDE 900AS1 01 DAY
CHUTE FROM DIVERTOR GATE TO AIR SLIDE 900AS4 01 DAY
CHUTE FROM AIR SLIDE 900AS4 TO CEMENT SILO
900CS2 01 DAY
CHUTE FROM AIR SLIDE 900AS1 TO CEMENT SILO
900CS1 01 DAY
CHECKING OF CIVIL FOUNDATION 05 DAYS
MICROCHIPPING OF FOUNDATION
ERECTION OF FAN
DRIVE ALIGNMENT AND CHECKING
CHECKING OF CIVIL FOUNDATION 05 DAYS
MICROCHIPPING OF FOUNDATION
ERECTION OF FAN
DRIVE ALIGNMENT AND CHECKING
ERECTION OF DISCHARGE DUCT OF 800FN4 02 DAYS
ERECTION WORK FOR BAGFILTER 07 DAYS
RAL FITTING
COMPRESSED AIR PIPING WORK
CHECKING OF CIVIL FOUNDATION 05 DAYS
MICROCHIPPING OF FOUNDATION
ERECTION OF FAN
DRIVE ALIGNMENT AND CHECKING
ERECTION WORK FOR BAGFILTER 07 DAYS
RAL FITTING
INLET OUTLET DUCT ERECTION OF BAGFILTER 08 DAYS
ERECTION OF OUTLET CHUTE FROM BF 900DC2 01 DAY
FITTING OF HIGH LEVEL INDICATOR 02 DAYS
FITTING OF SILO PILOT 02 DAYS
FITTING OF SILO FEED SOCKET 02 DAYS
FITTING OF SILO INSPECTION DOOR AT THE TOP 01 DAY
FITTING OF SILO AIR BALANCE VALVE AT THE TOP 01 DAY
FITTING OF HIGH LEVEL INDICATOR 01 DAY
FITTING OF SILO PILOT 01DAY
FITTING OF SILO FEED SOCKET 01 DAY
FITTING OF SILO INSPECTION DOOR AT THE TOP 01 DAY
FITTING OF SILO AIR BALANCE VALVE AT THE TOP 01 DAY
INSTALLATION OF SILO OPEN AIR SLIDE WITH
PIPELINE WORK 20 DAYS
INSTALLATION OF SILO OPEN AIR SLIDE WITH
PIPELINE WORK 15 DAYS
ERECTION OF INLET BOX 17 DAYS
ERECTION OF 2 NOS OF MANUAL CUT OFF GATE
ERECTION OF 2 NOS OF DISCHARGE SECTION
ERECTION OF 2 NOS OF PNEUMATIC CUT OFF GATE
ERECTION OF 2 NOS OF FLOW CONTROL GATE
ERECTION OF DISCHARGE CHUTE FROM INLET BOX
ERECTION DISCHARGE SECTION
ERECTION OF PNEUMATIC CUT OFF GATE
ERECTION OF CHUTE FROM INLET BOX TO 900AS3
ERECTION OF FLOW CONTROL GATE
FIXING OF DIVERTOR GATE AT THE OUTLET OF INLET
BOX
AIR SLIDE FEEDING TO PACKING PLANT ELEVATOR
Laying of airslide 07 DAYS
placement of blower
pipe line connection with valve
Venting line connection
placement of blower
pipe line connection with valve
Venting line connection
BUCKET ELEVATOR (PACKING PLANT)
CHECKING OF CIVIL FOUNDATION 01DAY
MICROCHIPPING OF FOUNDATION
ERECTION OF BOOT CASING AND ITS ALIGNMENT 03 DAYS
ERECTION OF ASSEMBLED CASING ON BOOT
CASING AND ITS PLUMB CHECKING
ERECTION OF ASSEMBLED CASING UP TO REQUIRED
LEVEL AND ITS PLUMB CHECKING 08 DAYS
ERECTION OF HEAD CASING 03 DAYS
DRIVE ALIGNMENT WORK 04 DAYS
FIXING OF BELT 03 DAYS
BUCKET FIXING 06 DAYS
ERECTION DISCHARGE CHUTE FROM 900AS3 02 DAYS
ERECTION DISCHARGE CHUTE FROM BUCKET
ELEVATOR 900BE2 02 DAYS
ERECTION OF FEED BIN 07 DAYS
INSTALLATION OF LOAD CELL 03 DAYS
ERECTION DISCHARGE CHUTE FROM VIBRATING
SCREEN O/L 03 DAYS
ERECTION OF BLOWER 03 DAYS
PIPING WORK BETWEEN BLOWER AND FEED BIN 03 DAYS
ERECTION OF MANUAL CUT OFF GATE AT BIN O/L
ERECTION OF INLET BOX
ERECTION OF PNEUMATIC CUT OFF GATE
ERECTION OF ROTO PACKER AND ITS ALIGNMENT 07 DAYS
ERECTION OF ROLLER WAYS AND ITS ALIGNMENT
ERECTION OF BELT CONV 900BC1
Fixing of Couplings 03 DAYS
Belt laying and valcanization
Drive alignment of conveyor
ERECTION OF SPIRAL CHUTE 04 DAYS
Air slide 07 DAYS
Laying of airslide
placement of blower
pipe line connection with valve
Venting line connection
ERECTION WORK FOR BAGFILTER
RAL FITTING
COMPRESSED AIR PIPING WORK
BUCKET ELEVATOR (BULK LOADING)
CHECKING OF CIVIL FOUNDATION 01 DAY
MICROCHIPPING OF FOUNDATION
ERECTION OF BOOT CASING AND ITS ALIGNMENT 03 DAYS
ERECTION OF ASSEMBLED CASING ON BOOT
CASING AND ITS PLUMB CHECKING
ERECTION OF ASSEMBLED CASING UP TO REQUIRED
LEVEL AND ITS PLUMB CHECKING 07 DAYS
ERECTION OF HEAD CASING 03 DAYS
DRIVE ALIGNMENT WORK 03 DAYS
FIXING OF BELT 03 DAYS
BUCKET FIXING 05 DAYS
ERECTION OF CHUTE FROM B/E TO BIN 01 DAY
ERECTION OF CHUTE FROM BIN TO PNEUMATIC
CUT OFF GATE 02 DAYS
ERECTION OF CHUTE FROM PNEUMATIC CUT OFF
GATE TO BULK LOADING SPOUT 02 DAYS
ERECTION OF BULK LOADING SPOUT 07 DAYS
Air slide
Laying of airslide
placement of blower
pipe line connection with valve
Venting line connection
CHUTE FROM 900AS6 TO 900BE3 02 DAYS
Reason for work delaying
ELECTRICAL :- DATED:- 17-10-2014
CIVIL FRONT
S.NO ACTIVITY MATERIAL STATUS
STATUS
1 LC3 CABEL CELLER TRAY WORK AVAILABLE AVAILABLE
TRAY WORK FROM LC3 TO RAWMILL 0 LVL,RAWMILL
2 AVAILABLE AVAILABLE
FAN,LUBRICATION UNIT,AUX DRIVE,GIRTH GEAR
3 LPBS AND CJB FIXING 0 LVL. AVAILABLE AVAILABLE
TRAY WORK AT 9 MTR LVL AND CLASIFIER LVL AND LPBS CJB FIXING
4 AVAILABLE AVAILABLE
IN RAWMILL.
TRAY WORK AN LPBS AND CJB FIXING FROM RAWMILL INLET TO
5 AVAILABLE AVAILABLE
100BC5 TAIL END

6 PANEL SHIFTING TO LC3 AND ERECTION 15-Oct AVAILABLE

7 IO TERMINATION AND CJB TERMINATION IN LC1 AND CRUSHER AVAILABLE AVAILABLE


8 IO TERMINATION AND CJB TERMINATION IN LC2 AVAILABLE AVAILABLE
CABLE LAYING FROM LC3 TO RAWMILL HOUSE AND RAWMILL
9 AVAILABLE AVAILABLE
FEEDING
10 IO TERMINATION AND CJB TERMINATION IN LC4 . AVAILABLE AVAILABLE
MOTOR CONNECTION AND GLANDING IN FIELD AND PANEL SIDE
11 AVAILABLE AVAILABLE
WITH GLAND PLATE HOLES
TRAY CONNECTION BETWEEN LC3 AND BLENDING SILO,
12 25-Oct AVAILABLE
PREHEATER, LPBS FIXING IN BLENDING SILO.
13 TRAY WORK FROM LC3 TO LC1 AND TUNNEL 26-Oct AVAILABLE
14 TRAY WORK FROM LC3 TO CCR 31-Oct AVAILABLE
15 LC3 TRANSFORMER ERECTION 1-Nov AVAILABLE
16 GLAND AND TERMINATION IN LC3 RELATED AREA. 1-Nov AVAILABLE
17 CABLE LAYING FROM LC3 TO RAWMILL ,CONVEYORS ,LC1 AND TUNNEL AVAILABLE AVAILABLE
TRAY WORK FROM LC3 TO BOOSTER FAN AND LPBS CJB FIXING FOR
18 31-Oct AVAILABLE
PH FAN AND BOOSTER FAN
TRAY WORK FOR BAG HOUSE AND RAWMILL DAMPERS AND MAIN CABLE
19 GALLARY TO LC2 31-Oct AVAILABLE
20 TRAY WORK AND INSTRUMENTS WORK IN PH KILN AVAILABLE
21 TRAY WORK AND INSTRUMENTS AT COAL MILL HOUSE AND 0 LVL. 5-Nov AVAILABLE
TRAY WORK AND INSTRUMENTS WORK IN RAWMILL ,RAWMILL FEEDING
22 AND BAGHOUSE. AVAILABLE AVAILABLE

IMPULSTUBE,FLOW
TRANSMETER AND
PIEZOMETRIC RING NOT
23 INSTRUMENTS WORK IN COOLER. AVAILABLE RECEIVED AT SITE AS
MENTION IN PACKING
LIST
TRAY WORK FROM CCR TO COAL MILL THROUGH ESP FAN AND COAL
24 CRUSHER 15-Nov AVAILABLE
25 TRAY WORK IN ESP TOP AND INSTRUMENTATION WORK IN ESP 22-Nov AVAILABLE
26 IO TERMINATION AND CJB TERMINATION IN CCR . AVAILABLE AVAILABLE
27 IO TERMINATION AND CJB TERMINATION IN LC3 . AVAILABLE AVAILABLE
28 CABLE LAYING FROM LC3 TO BLENDING SILO. AVAILABLE AVAILABLE
29 CABLE LAYING FROM LC3 TO RAWMILL INSTRUMENTS. AVAILABLE AVAILABLE
30 CABLE LAYING FROM LC3 TO RAWMILL DAMPERS. AVAILABLE AVAILABLE
31 CABLE LAYING FROM COALMILL INSTRUMENTS AND 0 LVL MOTORS. AVAILABLE AVAILABLE
32 CABLE LAYING FROM CCR TO BOOSTER FAN AND ITS DAMPER. AVAILABLE AVAILABLE
33 CABLE LAYING FROM CCR TO PH ,COOLER AND ESP INSTRUMENTS. AVAILABLE AVAILABLE
34 CABLE LAYING FROM CCR TO LC4, LC3 BAGHOUSE FAN AND LC2 . AVAILABLE AVAILABLE
35 TRAY WORK FROM COOLER TO CSP AVAILABLE AVAILABLE
MECH DATE NOT
36 ADDITIVE CRUSHER TRAY WORK AND LPBS FIXING AVAILABLE AVAILABLE
37 TRAY WORK AND LPBS FIXING IN PACKER BUILDING AVAILABLE AVAILABLE
38 TRAY WORK AND LPBS FIXING IN PACKER FOR TRUCK LOADER AVAILABLE AVAILABLE
39 CABLE LAYING IN CSP BUILDING AVAILABLE AVAILABLE
40 CABLE LAYING IN PACKER BUILDING AVAILABLE AVAILABLE
MECH DATE NOT
41 TRAY WORK IN COALMILL DUMPHOPPER AND STORAGE AVAILABLE AVAILABLE
42 CABLE TRAY WORK IN LC5 CABLE CELLER 20-Nov AVAILABLE
43 PANEL ERECTION IN LC5 AND TRANSFORMER ERECTION WITH BUS DUCT 20-Nov AVAILABLE
44 CABLE TRAY WORK FROM LC5 CABLE CELLER TO PACKER BUILDING 20-Nov AVAILABLE
45 CEMENT MILL HOUSE TRAY WORK LPBS, CJB FIXING 20-Nov AVAILABLE
46 CEMENT MILL FEEDING TRAY WORK AND LPBS ,CJB FIXING. 20-Nov AVAILABLE
47 CABLE LAYING FOR ALL LOAD CENTER FOR PLC (OFC) 2-Dec AVAILABLE
48 CABLE LAYING FOR LC5 AVAILABLE
49 TRAY WORK AND LPBS FIXING FOR CEMENT SILO AVAILABLE
50 CABLE LAYING WORK FOR CEMENT SILO AVAILABLE
51 LOOP TESTING IN RAWMILL,BLENDING SILO, BAGHOUSE AVAILABLE AVAILABLE
52 LOOP TESTING IN CRUSHER SECTION AVAILABLE AVAILABLE
53 LOOP TESTING IN COALMILL SECTION AVAILABLE AVAILABLE
54 COMMISIONING FOR COALMILL AVAILABLE AVAILABLE
55 LOOP TESTING IN PH KILN,COOLER SECTION AVAILABLE AVAILABLE
56 COMMISIONING PYRO SECTION AVAILABLE AVAILABLE
57 IO TERMINATION IN PACKER BUILDING AVAILABLE
58 IO TERMINATION IN LC5 AVAILABLE
59 LOOP TESTING IN CEMENTMILL AVAILABLE
60 CEMENTMILL COMISIONING AVAILABLE
61 OIL FILTERATION FOR ALL 6 TRANSFORMER AVAILABLE AVAILABLE
62 COMMISIONING FOR RAWMILL AVAILABLE AVAILABLE

NOTE:- Subject to availability of front

REQUIRED
GANG 5 CAN 5BE
HELPERS
USED AS
MISSCELANIOUS
WORK
DAYS REQUIRED MAN POWER
START DATE FINISH DATE SECTION Work status GANG
FOR ERECTION REQUIRED
7 11-Oct 18-Oct RAWMILL WIP 2 GANG 1

5 19-Oct 23-Oct RAWMILL 2 GANG 1

1 24-Oct 24-Oct RAWMILL 2 GANG 1

5 13-Oct 18-Oct RAWMILL 3 GANG 4

7 19-Oct 25-Oct RAWMILL 3 GANG 4

GANG 5 &
4 15-Oct 19-Oct RAWMILL WIP 5 GANG 3
5 12-Oct 17-Oct RAWMILL completed 2 GANG 2
7 18-Oct 24-Oct RAWMILL 2 GANG 2

15 20-Oct 4-Nov RAWMILL 5 GANG 3

10 25-Oct 5-Nov COALMILL 2 GANG 2

8 20-Oct 27-Oct RAWMILL 2 GANG 5

6 25-Oct 31-Oct RAWMILL 2 GANG 1

9 26-Oct 3-Nov RAWMILL 3 GANG 4


6 1-Nov 6-Nov RAWMILL 2 GANG 1
4 28-Oct 2-Nov RAWMILL 3 GANG 5
6 3-Nov RAWMILL 2 GANG 5
7 5-Nov 11-Nov RAWMILL 5 GANG 3

3 4-Nov 6-Nov PH 3 GANG 4

3 7-Nov 9-Nov RAWMILL 2 GANG 1


8 10-Nov 17-Nov PH 3 GANG 1
6 7-Nov 12-Nov COALMILL 2 GANG 4
6 13-Nov 18-Nov RAWMILL 2 GANG 4

6 18-Nov 23-Nov COOLER 2 GANG 1

8 19-Nov 27-Nov COALMILL 3 GANG 4


5 24-Nov 29-Nov ESP 3 GANG 1
10 6-Nov 15-Nov KILN 2 GANG 2
12 16-Nov 27-Nov RAWMILL 2 GANG 2
6 12-Nov 16-Nov RAWMILL 5 GANG 3
2 17-Nov 18-Nov RAWMILL 5 GANG 3
3 19-Nov 21-Nov RAWMILL 5 GANG 3
4 22-Nov 25-Nov COALMILL 5 GANG 3
2 26-Nov 27-Nov PH 5 GANG 3
5 28-Nov 2-Dec PH 5 GANG 3
5 3-Dec 7-Dec RAWMILL 12 ALL GANGS
6 28-Nov 2-Dec CSP 3 GANG 4
3 30-Nov 2-Dec RAWMILL 2 GANG 1
3 PACKER 2 GANG 1
2 PACKER 2 GANG 1
3 8-Dec 10-Dec CSP 5 GANG 3
3 PACKER 5 GANG 3
8 8-Dec 15-Dec COALMILL 2 GANG 4
8 CEMENTMILL 3 GANG 4
9 CEMENTMILL 3 GANG 1
5 CEMENTMILL 2 GANG 4
12 CEMENTMILL 3 GANG 1
12 CEMENTMILL 3 GANG 4
6 14-Dec 19-Dec RAWMILL 5 GANG 3
18 CEMENTMILL 5 GANG 3
8 CEMENTMILL 3 GANG 1
6 CEMENTMILL 5 GANG 3
6 28-Nov 3-Dec RAWMILL 2 GANG 2
2 4-Dec 5-Dec RAWMILL 2 GANG 2
4 6-Dec 10-Dec COALMILL 2 GANG 2
15 15-Dec 30-Dec COALMILL 2 GANG 5
6 11-Dec 17-Dec KILN 2 GANG 2
20 25-Dec 15-Jan KILN 2 GANG 5
6 CEMENTMILL 2 GANG 2
15 CEMENTMILL 2 GANG 2
10 CEMENTMILL 2 GANG 2
15 CEMENTMILL 2 GANG 2
12 10-Dec 22-Dec RAWMILL 2 GANG 5
12 15-Dec 23-Dec RAWMILL 2 GANG 5

SR.NO. DEG. GANG NAME

1 FITTER GANG 1 SONU

2 HELPER JOSEPH
3 ELECTRICIAN GANG 2 RAJA
4 HELPER REQUIRED
5 ELECTRICIAN GANG 3 GANESH
6 HELPER ANIL
7 HELPER REQUIRED
8 HELPER REQUIRED
9 HELPER REQUIRED
10 FITTER GANG 4 RAMNARESH
11 HELPER REQUIRED
12 HELPER RAJESH
13 FITTER/ELEC. GANG 5 MEENU
14 ELECTRICIAN RATAN
REMARKS

30 mtr. Cable tray laying & cable tray angle.

R I/O Panel shifting & erection.