Académique Documents
Professionnel Documents
Culture Documents
TRANSFER HOUSE 1
TRANSFER TOWER 2
CONVEYOR 1A & 1B
1 CHP
CONVEYOR 2A &2B
1 CHP
CONVEYOR 3A &3B
CONVEYOR 4A & 4B
CONVEYOR 5A & 5B
SECONDARY CRUSHER HOUSE
BOILER -I
STRUCTURAL
PRESSURE PART
ROTATING EQUIPMENTS
FUEL PATH
INSULATION
ESP
BOILER -II
STRUCTURAL
PRESSURE PART
ROTATING EQUIPMENTS
FUEL PATH
INSULATION
ESP
TG TO BOILER INTERCONNECTION
3 LP PIPING
LDO SYSTEM
PIPE RACK
FABRICATION & ERECTION OF PIPING
STRUCTURAL
TURBINE
TURBOGENERATOR
5 TG BUILDING
CONDENSER
AUXILLARIES
AC DUCTING WORK
STRUCTURAL
STRUCTURAL
WATER
EQUIPMENT ERECTION
WATER
7 TREATMENT
PLANT
FABRICATION & ERECTION OF PIPING
CHEMICAL HOUSE
WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 19
(HAZEMAG)
2 THERMAX 128
3 GPR 33
4 APT 20
5 SUVENDU SAHU 0
JOSEPH
6 12
CONSTRUCTIONS
7 ION EXCHANGE 4
CTIVITY REPORT (MECHANICAL- CPP) DATE-21.10.13
No activity
No activity
No activity
No activity
No activity
Completed
Completed
Completed
No activity
Completed
No activity
No activity
No activity
No activity
Erection of frame for generator air cooler & cleaning of air coolers
to complete.
No activity
No activity
No activity
No activity
No activity
Completed
Filling of material inside SSF is in progress.
No activity
No activity
DATE-21.10.13
PLANNED FOR REMARK
TOMORROW
Same to continue
Same to continue Refractory work started.
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
16mm plate to be fixed on TG
building for walkway.
No activity
Same to Continue.
Same to Continue.
Same to continue
No activity
No activity
No activity
No activity
Filling of material inside SSF to
continue.
No activity
No activity