DAILY ACTIVITY REPORT

SL NO. PACKAGE EQUIPMENT CENTRE

PRIMARY CRUSHER/COAL SHED

TRANSFER HOUSE 1

TRANSFER TOWER 2

CONVEYOR 1A & 1B

1 CHP
CONVEYOR 2A &2B

1 CHP

CONVEYOR 3A &3B

CONVEYOR 4A & 4B

CONVEYOR 5A & 5B
SECONDARY CRUSHER HOUSE

BOILER -I

STRUCTURAL

PRESSURE PART
ROTATING EQUIPMENTS

HOT AIR PATH

COLD AIR PATH


FLUE GAS PATH

FUEL PATH

INSULATION

ESP

BOILER -II

STRUCTURAL
PRESSURE PART

ROTATING EQUIPMENTS

2 BOILER & ESP

HOT AIR DUCTING

COLD AIR DUCTING


FLUE GAS DUCTING

FUEL PATH

INSULATION

ESP
TG TO BOILER INTERCONNECTION

RAW WATER PUMP HOUSE

CLARIFIED WATER PUMP HOUSE

CW AND ACW PUMP HOUSE

UTILITY WATER PUMP HOUSE


COMPRESSOR HOUSE

3 LP PIPING

FIRE FIGHTING SYSTEM

LDO SYSTEM

PIPE RACK
FABRICATION & ERECTION OF PIPING

FANS ,GEAR BOXES,PROPELLER SHAFT &


STRUCTURALS

COOLING DISTRIBUTION PIPE LINES


4 TOWER DRIFT ELIMINATORS & SPLASH GUARDS

DECK RAILING WORK.

STRUCTURAL
TURBINE

TURBOGENERATOR

5 TG BUILDING
CONDENSER

AUXILLARIES

FABRICATION & ERECTION OF PIPING


LUBE OIL SYSTEM

AC DUCTING WORK

STRUCTURAL

ERECTION OF EMBEDED PLATES & OPENING


6 ASH SILO
ASH HANDLING EQUIPMENT

ASH TRANFER PIPE LINE

STRUCTURAL

WATER
EQUIPMENT ERECTION

WATER
7 TREATMENT
PLANT
FABRICATION & ERECTION OF PIPING

CHEMICAL HOUSE

WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 19
(HAZEMAG)
2 THERMAX 128
3 GPR 33
4 APT 20
5 SUVENDU SAHU 0
JOSEPH
6 12
CONSTRUCTIONS

7 ION EXCHANGE 4
CTIVITY REPORT (MECHANICAL- CPP) DATE-21.10.13

No activity

No activity

Erection of diagonal beams connecting main columns is in


progress. Rework on the main columns of Transfer Tower-2
completed. Fabrication & welding of staircase column completed.
Alignment work completed and welding in progress. Tie members
of Main Column structures being erected.

No activity
No activity

Foundation work 3B is in progress. Erection of gallery of 3A


completed.

Assembly of gallery started. Welding of platform for the erection


of upper half of the column is in progress.Alingment of columns of
TR-5,TR-6 completed. Erection & welding of tie beam & floor
beams of TR-6 & TR-5 is in progress. Unloading of gallery materials
completed.

Assembly work of Structures & final welding completed.


Casting of half portion of 17.0 M slab completed.

Final painting work in progress.

No activity
Completed

Completed

Completed
No activity

Completed

Insulation work at SA FAN duct is in progress.Insulation of outlet


duct of ESP connecting to ID FAN is in progress. Insulation of
remaining pipes in furnace is in progress.Insulation of PA duct
started. Insulation of by pass ducts from BAC started. Insulation
work at PA & SA FAN is in progress.

No activity

Fixing of net in pent house for insulation. Final painting work in


progress. Erection of monorail support structure & monorail for ID
FAN completed & welding is in progress. Erection of monorail
support structure & monorail for PA FAN & SA FAN is in progress.
Drain piping work started. Welding of supporting structures in
progress. Refractory work in furnace zone is in progress.

Erection of expanion bellow in ID Fan -4 was taken up.Erection of


ID FAN-3 completed & alignment completed. ID FAN-4 alingnment
is in progress. Erection & alignment of rotor of PA FAN-3 & 4
completed. Erection of rotor of SA FAN-3 & SA FAN-4 completed &
alingnment is in progress.

Erection & welding of PA Duct connecting to windbox completed .


Ducting from PA line to MDC is in progress.Ducting from PA AIR
line to Wind box is in progress .Erection of PA FAN to APH
connecting duct completed & final welding is in progress. Erection
of duct connecting APH to ESP completed & welding in progress.

Erection & welding of secondary air duct fitting work in


progress .Ducting work from SA FAN to APH is in progress.Erection
of damper & silenser for SA Fan completed.
Fabrication & Assembly of man hole in APH .Erection of ID FAN
inlet ducting is in prorgess. Refractory work inside furnace zone
started.Erection of economiser casing completed & Welding of
economiser casing to complete. Erection of 4th ID-Fan Ducting
taken up.

Welding of chute connection to drag chain feeder of coal bunker


is in progress.MDC welding in progress. Erection & welding of
MDC Bypass to ash seperator completed. Fixing of ceramic
cyclones pipes in MDC completed.Erection of MDC bypass lineis in
progress. Erection of air slide in MDC is in progress.

Insulation work to be taken up.

Assembly of pent house structure is in progress. Emitting


electrode erection completed. Erection of 2nd & 4th field hopper
completed final welding of hopper is in progress. Erection of
chequered plates on the roof completed.Pent house roof sheeting
work is in progress. Fabrication of 5th field hopper completed & to
be erected.Erection of monorail support columns started & is in
progress.
Fabrication of Connecting walkway completed. fixing of bolts on
the beam TG building completed

Erection of 2 nos of pumps completed.Asssembly of fittings to the


outlet header is in progress. Laying of pipe line from raw water
pump house to chemical house completed.

Placing of pumps & motors

Erection of rails on the the girder completed & fixing is in progress.


Alingment of crane girder is to complete.Fabrication of reducer for
cooling water inlet is in progress. Erection of Crane Gantry beams
for EOT crane complete. Erection of east side runner for side
sheeting work complete.west side runner erection to start after
erection of EOT Crane.Assembly of EOT crane is in progress.

No activity as monitoring basin Civil work yet to start.


Assembly of outlet line of dryer connecting to receiver tank is in
progress. Erection of globe valves inside compressor house for
conveying air compressor completed & erection of pipe
connecting valve to compressor is in progress. Erection of pipe
rack support connecting to main pipe rack completed. Fabrication
of Pipelines in progress. Erection of instrument air compresed air
pipe near boiler & doubling of pipes on pipe rack is under process.

No activity

Civil foundation work has started.

Fabrication of remaining cable rack & erection is in progress. Final


welding of pipe rack connecting beams completed. Erection of
columns & connecting beam for pipe rack connecting from main
pipe rack to DM Plant to complete.
Painting of 1600NB pipe is in progress. Laying of 350NB pipe
completed .CT MAKE UP Piping from clarified water pump house
to main pipe rack is completed. Erection & welding of 80 NB DM
make up line in the road crossing area is in progress. Fabrication of
reducer for CW suction line is in progress.

All materials shifted close to Cooling Tower.

No activity

No activity

Railing work in progress .

Fixing of handrailing in staircase completed final finishing work to


be completed. Roof sheeting of staircase head room completed &
side sheeting to start. Erection of Side runner at 23m level for
head room is in progress.
Cleaning of tubine rotor started.Shifting of turbine assembly
materials to the TG Deck is in progress. Upper casing of turbine
was erected with exhaust hood upper part for the assembly.

Erection of frame for generator air cooler & cleaning of air coolers
to complete.

Final welding of hotwell to condenser is in progress.

Allignment of CEP is in progress.

Fabrication of boiler feed pump delivery line in progress.


Fabrication & assembly of pipe valves connecting condensate float
tank is in progress.Segrigation of piping material for assembly is in
progress.
Fabrication & Erection of lube oil pipe line & pipe supports is in
progress.

No activity

No activity

No activity

No activity

No activity

Completed
Filling of material inside SSF is in progress.

No activity

Sheeting work completed.

No activity
DATE-21.10.13
PLANNED FOR REMARK
TOMORROW

Hoppers, railings & chutes for feeder breaker


No activity awaited at site. Party has been followed up.

No activity Transfer Chutes awaited at Site

Grouting of foundation bolt to


be completed

Follow up on for Short Post and stringers for


No activity inclined ramp.
No activity Idler frames & Idler not received at site.

Civil foundation work yet to be completed

Trussel fabrication completed & gallery to be


received.party not despatching further materials
despite of repeated reminders. Rigorous followup
Same to continue required as party is not able to provide any
evidence of work in progress.WITHOUT GALLERY
IT IS NOW UNSAFE TO HOLD THE ERECTED
TRUSSELS FOR LONG.

Erection work to start after


transfer house -2 erection
completion.
Civil work to continue. Civil work yet to be completed

All fabrication scraps being cut


for use & house keeping work
to continue. Painting work to
continue.
Same to continue

Same to continue
Same to continue Refractory work started.

Same to continue

Balance Erection work awaiting completion of fan


Same to continue foundation.

Same to continue
Same to continue

Same to continue

Same to continue
16mm plate to be fixed on TG
building for walkway.

Fabrication & erection of


Piping work to continue.
Laying of pipe from raw water
pump house to chemical house
to start.

Fabrication of Suction line to Since brick work is in progress,Erection of pumps


start. is not started.

Fixing of rail to continue. Alignment of base frame to be taken after


Erection of EOT crane. erection of suction line to pump.
Same to continue

No activity

Civil foundation work started.fabricated tank


Same to continue received at site.

Allingment of columns for DM


plant to continue. Erection of
cable rack support in the
vertical portion of columns to
start.
Same to continue

Civil work yet to be completed & mobilisation to


be started by Paltech.Paltech to mobilise site by
Same to continue 15/9/13. Civil work not yet completed. Expected
completion by 30/10/13.

Shifting completed same as above

Shifting completed. same as above

West side railing work of cooling tower staircase


to be taken up after completion of deck railing.

Fixing of side runner to


continue.
Erection Work In progress with supervision of
Same to Continue. BHEL Representatives.

Same to Continue.

Same to Continue.

Same to continue

Approval given by IBR for all pressure line


No activity erection & welding.
Same to continue

Materials indented for supply of cooling water to


No activity A.C.Units

No activity

No activity

No activity

No activity
Filling of material inside SSF to
continue.

No activity

No activity