Académique Documents
Professionnel Documents
Culture Documents
EEN339: Internship
Authored by:
Raghad Jz Abuolwan 1045560
Supervised by:
Dr.Montasir Qasymeh
September 3, 2017
Alrakha cont general transport LLC
Galaxy advanced general contracting LLC
Abu Dhabi, United Arab Emirates Starting Date of Internship: 2nd, July
2017
End Date of Internship:10th, July 2017
Number of Internship Days:30 Days
Total Number of Hours: 240
1
Faculty supervisor Company supervisor
———————– ———————–
2
1 Acknowledgements
This 6-week internship period was such a profitable opportunity for gaining
professional experience. I would like to take this opportunity to thank the ca-
reer development department in Abu Dhabi University (ADU) for arranging
this internship for me. Also, i would like to extend my deepest appreciation
to Eng. shereen shokri who, despite being busy with finalizing phase 1 of the
project, taught me from her valued experience. Finally, i would like to thank
dr.Montasir Qasymeh for his valuable guidance and advice throughout this
internship.
3
2 Weekly Timetable
This section is dedicated to schedule and list the learning activities that have
been done through the 6-week internship training as follows:
4
Figure 3: The schedule of the Third Week of Internship
5
Figure 5: The schedule of the Fifth Week of Internship
6
3 Introduction
3.1 Executive Summary of the Internship
In completion of my Undergraduate degree in Electrical Engineer, I was
assigned to complete my Summer Internship (2017) with Al-rakha cont gen-
eral transport LLC. Al-Rakha group has been providing an outstanding and
timely general contracting and construction management services in contract-
ing projects assigned by clients for 25 years. I received my 6-week internship
training in Ansam Project shown in Fig. 7, which is currently under-
construction of phase 1 in Yas Island. The finished four residential buildings
in the project are built on the Andalusian Style, which includes 540 studios,
1-BR, 2-BR, and 3-BR units. [5]
7
trained by the electrical department of Galaxy General Contracting under
the supervision of Engineer Shereen Shokri. She is a senior engineer who is
responsible for following up with the work done by other engineers, verifying
their designs conformity with the allowable engineering practices, carrying
out the cabling and load calculations, ordering the requisite electrical equip-
ment, and submitting documents for ADDC inspections.
The Learning activities of this internship are as follows:
2. Life and Safety systems design inside the building (Fire Alarm
and central Battery Systems).
• Transformer Room
8
Contents
1 Acknowledgements 3
2 Weekly Timetable 4
3 Introduction 7
3.1 Executive Summary of the Internship . . . . . . . . . . . . . . 7
5 Internship Activities 14
5.1 Safety Induction . . . . . . . . . . . . . . . . . . . . . . . . . . 14
5.1.1 Bus Bar . . . . . . . . . . . . . . . . . . . . . . . . . . 15
5.2 The Electrical Substation . . . . . . . . . . . . . . . . . . . . 17
5.2.1 Dry Type Substation Transformers . . . . . . . . . . . 18
5.2.2 High Voltage Room . . . . . . . . . . . . . . . . . . . . 20
5.2.3 Low Voltage Panel . . . . . . . . . . . . . . . . . . . . 22
5.2.4 Secondary Distribution System: Low Voltage Trans-
former . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
5.2.5 Wall Mounted Electrical Room SMDB . . . . . . . . . 26
5.3 Single Line Diagram of the Project . . . . . . . . . . . . . . . 30
5.3.1 Determining the Suitable Size of Cable for Electrical
Installation . . . . . . . . . . . . . . . . . . . . . . . . 30
5.4 Power and Light Schematics . . . . . . . . . . . . . . . . . . . 34
5.5 Circuit Breakers . . . . . . . . . . . . . . . . . . . . . . . . . . 39
5.6 Take off . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
5.7 Low Current Systems: Life and Safety Systems Design inside
the building . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
5.7.1 Clear Agent Suppression System . . . . . . . . . . . . . 47
5.8 Low Current and Security Systems Design . . . . . . . . . . . 48
7 Conclusion 50
9
List of Figures
1 The schedule of the First Week of Internship . . . . . . . . . . 4
2 The schedule of the Second Week of Internship . . . . . . . . . 4
3 The schedule of the Third Week of Internship . . . . . . . . . 5
4 The schedule of the Fourth Week of Internship . . . . . . . . . 5
5 The schedule of the Fifth Week of Internship . . . . . . . . . . 6
6 The schedule of the Sixth Week of Internship . . . . . . . . . . 6
7 Ansam Project . . . . . . . . . . . . . . . . . . . . . . . . . . 7
8 The organizational Chart of Al-rakha cont general transport
LLC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
9 Safety Helmet/ High visibility vest . . . . . . . . . . . . . . . 14
10 Bus Bar Trunking and a Cable Tray . . . . . . . . . . . . . . . 15
11 A Bus Bar Riser from the Main Distribution Board in JA-12 . 16
12 Bus Bar Trunking and a Cable Tray . . . . . . . . . . . . . . . 16
13 Bus Bar Trunking System . . . . . . . . . . . . . . . . . . . . 17
14 The Dry Type Transformer in the Transformer Room of JA-12 19
15 The Dry Type Transformer in the Transformer Room of JA-12 20
16 The route of the ADDC cable to the HV Room . . . . . . . . 21
17 The International Safety Symbol for High Voltage Indication
for Electrical Substation that Transforms the distribution High
Voltage to Usable Voltages . . . . . . . . . . . . . . . . . . . . 21
18 The connection Between the Main Distribution Boards and
the Low Voltage Room in JA-12 . . . . . . . . . . . . . . . . . 22
19 Ring Incomer 1 in the Low Voltage Panel/ what is fed to the
Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
20 Ring Incomer 2 in the Low Voltage Panel/ What leaves the
Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
21 The Low Voltage Panel/switch-gear . . . . . . . . . . . . . . . 23
22 The Outgoing from Transformer into the Low Voltage Panel . 24
23 The Current Transformer Used to Measuring the Current . . . 24
24 The Nameplate of the Step-down Transformer . . . . . . . . . 25
25 The Sub-main Distribution Board . . . . . . . . . . . . . . . . 26
26 Installation Details of a Wall Mounted SMDB . . . . . . . . . 27
27 Ratings of the MCCB . . . . . . . . . . . . . . . . . . . . . . 28
28 A Central Battery that can be Found in Electrical Rooms . . 29
29 Self-contained Lighting for Exit/Escape Points . . . . . . . . . 30
10
30 Maximum Allowable Voltage Drop comparison between ser-
vice connection and the utilization points . . . . . . . . . . . . 31
31 Maximum Allowable Voltage Drop comparison between ser-
vice connection and the utilization points . . . . . . . . . . . . 31
32 ELECTRICAL SCHEMATIC DIAGRAM (JA-12)-SHEET 1
OF 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
33 ELECTRICAL SCHEMATIC DIAGRAM (JA-12)-SHEET 2
OF 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
34 The Lighting Socket-outlet Legends . . . . . . . . . . . . . . . 34
35 Second Floor Light System Layout for JA-12 . . . . . . . . . . 35
36 Second Floor Power System Layout for JA-12 with the Power
System Legend . . . . . . . . . . . . . . . . . . . . . . . . . . 36
37 The Load Schedule of the Final Distribution Board of FLat
(203) in Building JA-12 . . . . . . . . . . . . . . . . . . . . . 37
38 The Load Schedule of the Final Distribution Board of studio
(208) in Building JA-12 . . . . . . . . . . . . . . . . . . . . . 37
39 Ring circuit/ socket wiring . . . . . . . . . . . . . . . . . . . . 38
40 Radial circuit/ socket wiring . . . . . . . . . . . . . . . . . . . 38
41 An Electrical Circuit Breaker Panel of a Studio in JA-10 . . . 41
42 An MCCB with an External Operated Handler . . . . . . . . 41
43 An MCCB with an External Operated Handler . . . . . . . . 42
44 Fire Alarm System and Voice Evacuation System in Building
JA-12 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
45 Fire Alarm System Riser including the System Components
that are installed in Building JA-12 . . . . . . . . . . . . . . . 45
46 2 Core Shielded Fire Resistant Cable . . . . . . . . . . . . . . 46
47 Class A Wiring to the FACP . . . . . . . . . . . . . . . . . . . 47
48 Class B Wiring to the FACP . . . . . . . . . . . . . . . . . . . 47
49 The Clean Agent for Extinguishing Fire in Electrical Systems 48
50 Low Current Cable . . . . . . . . . . . . . . . . . . . . . . . . 49
11
4 Description of the Company and the Project
Al-Rakha Group is a cluster of companies that form one of the front-runner
companies in the construction industry in the UAE. Al Rakha General Con-
tracting Company WLL started out as a single company in 1986, which has
joined 4 other companies on the part of creating a group. [6]
Al-rakha group arranged transportation and carpentry and aluminum divi-
sions in order to be complementary to their construction services in 1999.
The transport division of the group is concerned with providing well-timed
delivery of the construction materials and tools to the site. Figure 8 shows
the hierarchical organizational chart of Al-Rakha Group where the groups
with higher positions are at the top, while individuals working for them
are beneath them. On the head of the organizational chart, the project di-
rectors, administrative director, and the transport department head can be
seen. Following up with project budget and schedule is the responsibilities of
the project directors. The projects budget, cost reduction, business planing
are under the responsibilities of the administrative director. The transport
department is concerned with providing timely and effective transportation
to projects and employees. The MEP project manager Mr. Mohammed
Al bick, who is responsible for interns, manages the electrical-mechanical-
pluming part of the project. Beneath his supervision comes the engineering,
planning engineer, construction manager, and the quality supervisor.
There are two senior engineers for Galaxy Advanced General Contract-
ing: an electrical senior engineer Ms.sheeren shokri, and mechanical senior
engineer Mr. Mohammed Badr. The senior engineers verify the electrical
and mechanical drawings drawn by the AutoCad Operators.
12
y
pan Pro
m
file
Co
Al Rakha Group Al Rakha Group
Co
file
Constructing Dreams...
m
Since 1986 p a P ro
ny
13
14
5.1.1 Bus Bar
Bus Bars are conductors assembled for collecting electrical currents coming
from a incomer feeder and distributing it to out-coming feeders in the low
voltage panel shown in Figure 11. One of the fundamental considerations in
the design of Electrical Power Distribution systems is space, which is occupied
by the electrical equipment and cabling, and the cost of installation. Hence,
Bus bar trunking installations are preferred to cabling system. In Bus Bar
Trunking systems (BBT) depicted in Figure 10, bus bars are enclosed in
high protective aluminum/copper enclosures that are essential for relegating
animals such as rodents. Bus bar trunking system reduces the number of
circuits required for power distribution in a building. Bus Bar riser, shown
in Figure 11, starts from the main distribution board in the Low Voltage
(LV) Panel and rises to all floors making a single circuit, whereas cabling
system requires a circuit for each floor. This justifies the reason for choosing
bus bar trunking system over cabling system that not only reduce the cost
but also reduces the requisite space for installation. [24]
15
Figure 11: A Bus Bar Riser from the Main Distribution Board in JA-12
16
5.2 The Electrical Substation
17
5.2.1 Dry Type Substation Transformers
The design of the main electrical room in any building of Ansam Project
(Phase 1) uses two substation dry type transformers shown in Figure 14.
The insulation material of this type of transformers is a non-liquid dry ma-
terial. The high voltage side of the transformer meets the high voltage cable
extended by the ADDC has a low current as a result of the high secondary
distribution voltage (V α I). A single core transformer has a pair of 3 phase
cables and a neutral cable that can be seen in Figure 15. 4 core transformers
have 11 cables where 3 pairs of them are phase cables, and the other two
cables are neutral cables. The voltage at this side of the transformer is low;
hence, the current is magnified to 630 A for a single core transformer. The
stepped down voltage is then supplied to the low voltage panel where power
is distributed by a bus bar. [19] The advantages of the Dry type substation
transformer are as follows:
• Eliminates the possibility of having oil leakage which makes dry type
more environmental friendly than oil type transformers.
18
Figure 14: The Dry Type Transformer in the Transformer Room of JA-12
19
Figure 15: The Dry Type Transformer in the Transformer Room of JA-12
20
Figure 16: The route of the ADDC cable to the HV Room
Figure 17: The International Safety Symbol for High Voltage Indication for
Electrical Substation that Transforms the distribution High Voltage to Us-
able Voltages
21
5.2.3 Low Voltage Panel
In order to distribute power throughout the building, the High Voltage should
be stepped down to a usable 3 phase voltage (415 v) and fed into the low volt-
age (LV) switch-gear. As illustrated in Figure 18, there are two sub-main
distribution boards SMDB-GAS, SMDB-GBS feeding parts A and B of
the ground floor of the building, an emergency sub-main distribution board
ESMDB-G, and a capacitor bank (150KVA) for power factor correction. In
this project, the sub-main distribution boards (SMDB-GBA SMDB-GAS)
are not supplied by the two bus bars; instead, they are connected to the main
distribution boards through cables underneath the LV trench. Bus bar risers
deliver electricity to the electric rooms (Sub-main Distribution Boards) in
each floor, and cable trays deliver electricity from the main electrical room
to the loads in the ground floor. The emergency sub-main distribution board
(ESMDB-G) is fed from a spare generator in addition to the main distribu-
tion board (MDB-G2). The Emergency sub-main distribution board assure
the continuity of supply in case of interruption or failure in the supply of the
main distribution board.
Figure 18: The connection Between the Main Distribution Boards and the
Low Voltage Room in JA-12
The low voltage panel divides up the electric supply fed from an incomer
bus between branch circuits and provides protective devices such as: MCCB,
MCB, and HRC fuses. One of the main components of the low voltage panel
is the Low Voltage (LV) switch-gear. Current Transformers (CT) are in-
strument transformers used in electrical power distribution systems for mea-
22
Figure 19: Ring Incomer 1 in the Figure 20: Ring Incomer 2 in the
Low Voltage Panel/ what is fed to Low Voltage Panel/ What leaves
the Panel the Panel
23
Figure 22: The Outgoing from Transformer into the Low Voltage Panel
24
5.2.4 Secondary Distribution System: Low Voltage Transformer
Metal nameplates are mounted on the shields of power and distribution trans-
formers for providing essential information about its installation and opera-
tion either by printing or by stamping it on the metal. Figure 24 shows the
stamped nameplate of the step-down transformer, which is shown in Figure
14, located in the Main Electrical Room of Each Building. The manufac-
turer, serial number, and the year of manufacture are the most fundamental
and basic requisite information provided by any nameplate. [4]
25
5.2.5 Wall Mounted Electrical Room SMDB
Usually, Sub Main Distribution Boards (SM-DB) are installed in a different
location from the Main Distribution Boards (MDB) and the distribution
switch-gear. There are a number of design standards that facilitates the
design of electrical rooms, which does not necessarily imply that the judgment
of an experienced engineer can be over-ridden. Final Distribution boards in
each floor should be supplied by at least from a single panel in the electrical
room, and each panel is fed from a single feeder. Water sprinklers shall not
be installed in electrical rooms; instead, clear agent suppression systems are
employed for protection of fire hazards. Lightening in the electrical room
should have reachable switches in addition to wiring at least one light to the
emergency panel. [17]
26
The electrical rooms (SMDB-GA) and (SMDB-GB) in Ansam Project
are separated from the Low voltage panel as per the regulations of electrical
room design where an emergency lightening battery is installed. Sub-main
distribution boards can be either supplied through a cable trench or PVC
duct pipes. In some cases, electrical rooms panels are fed from the bus bar
trunking that begins from the bus bar riser in the main electrical room. The
schematic diagram of the Sub-main Distribution Board (SM-DB) is shown in
Figure 25. Sub Main Distribution Boards are enclosed in a Electro-galvanized
steel sheet that should have a thickness of at least 2mm by specifications. [18]
27
choose an isolator material that can withstand the short circuit current while
protecting the bus bar from moisture. [18]
The feeder incoming to the sub-main distribution board from the main
distribution board is usually protected by a 400A tri-pole (TP) MCCB, on
the other hand, a 125 A TP MCCB is installed for Final Distribution Boards
(FDB) protection as illustrated in Figure 27. The ratings of the MCCBs
can be varied upon the design. It can be seen from the electric schematics
sheets, for ansam project, that a 160 A is installed in the feeder from the Main
Distribution Board (MDB) and the sub-main Distribution Boards (SM-DB).
The feeder from each SMDB to a FDB is protected with a 63 A MCCB.
28
Central Battery systems provide an applicable and cost effective emer-
gency lighting solution that is alternative for self-contained lights in medium
to large projects. An example of self-contained lightnings can be seen in
exit/escape points. In case of power outage in a building, the central battery
switches on lighting automatically. Self-contained lightnings are suitable for
small projects. The advantages of central battery systems over self-contained
lighting are as follows:
• Better illumination.
29
Figure 29: Self-contained Lighting for Exit/Escape Points
30
The construction of the cable is a simply a conductor made from copper
or aluminum and insulated with PVC, XLPE, or EPR. Another physical
characteristic of cables is the number of cores. A 2 core cable (Line, Neutral)
does not require earth connection unlike 3 core cables (line, neutral, earth)
[16].
An important factor in the selection of cable size is the allowable voltage
drop (MVD). The table shown in Figure 30 shows the values of the allowable
voltage drop percentages for lighting, heating, and power loads. Motors
Maximum Voltage Drop should not exceed 5 percent in the steady state,
since the start up current of motors is 5 to 7 times higher than the full
load current under steady state condition. Hence, if motor operates at 8
percent, the maximum voltage drop may reach up to 40 percent in the start
up condition. [20]
31
2
GENERAL NOTES:-
LEGEND :
KEYPLAN
JA-12
32
01 ISSUED FOR APPROVAL R.K APR.16
00 ISSUED FOR APPROVAL AD DEC.15
No. REVISION APP'D DATE
CLIENT
PROJECT MANAGEMENT
CONSULTANT
MAIN CONTRACTOR
MEP CONTRACTOR:
GALAXY ADVANCED
GENERAL CONT. CO. LLC.
TEL: +971 2 6151600 , FAX: +971 2 6651670
P.O.Box: 39226, Abu Dhabi, UAE
E-mail: info@galaxy-uae.com
Website: www.galaxymep.com
DRAWING TITLE:
REF
A0
NO.
2
GENERAL NOTES:-
LEGEND :
KEYPLAN
JA-12
33
01 ISSUED FOR APPROVAL R.K APR.16
00 ISSUED FOR APPROVAL AD DEC.15
No. REVISION APP'D DATE
CLIENT
PROJECT MANAGEMENT
CONSULTANT
MAIN CONTRACTOR
MEP CONTRACTOR:
GALAXY ADVANCED
GENERAL CONT. CO. LLC.
TEL: +971 2 6151600 , FAX: +971 2 6651670
P.O.Box: 39226, Abu Dhabi, UAE
E-mail: info@galaxy-uae.com
Website: www.galaxymep.com
DRAWING TITLE:
REF
A0
NO.
5.4 Power and Light Schematics
Figures 35 and 36 show the lighting and the power systems layout of the
second floor of building JA-12. The load schedules of the final distribution
boards that include the lighting and power loads of flats and studios were
included in this activity. The total load (Kw) is greater in flats than in
studios. The reason for this is mainly because flat have a remarkably larger
area than studios, which results into more lighting socket outlets, Fan coil
units (FCU)s, and water heaters loads. In this project, dish-washers and gas
meters are loads included in the design and installation of flats only. The
purpose of this activity was to compare the load schedules of flats/studios in
the second floor in JA-12 with the drawing shown in Figures 40 and ??, dif-
ferentiate between the classes of socket connections, circuit types, and finally
the conformity of the schematics with the load schedules of flats/studios in
this floor.
34
35
Scanned by CamScanner
Figure 36: Second Floor Power System Layout for JA-12 with the Power
System Legend
Figure 37: The Load Schedule of the Final Distribution Board of FLat (203)
in Building JA-12
Figure 38: The Load Schedule of the Final Distribution Board of studio (208)
in Building JA-12
37
used for heating/cooling in residual buildings. The Motor Control Center
(MCC) is an assembly of one or more enclosed sections that control motor
unit in a building.
Phase
Neutral
32A MCB Earth
Earth
Neutral
Phase [Line]
Spur
Phase
20A MCB Neutral
Earth
Earth
Neutral
Phase [Line]
Spur
38
5.5 Circuit Breakers
A circuit breaker is a protective device that trips causing distribution in the
continuity of current when potentially higher currents, than its rated value,
flow through them. There is a wide variation for circuit breakers utilization
as it can be used for protection in residential, industrial, and in distributional
systems. Circuit breaker selection is dependant on the type of application
where the maximum short circuit current is determined by the rating of the
transformer. [20]
For calculating the current break size for a circuit breaker, the following
equation is used:
p
P = (3) ∗ V ∗ I ∗ cosφ
P
I=p ∗ 1.25
(3) ∗ (V ) ∗ (cosφ)
Miniature circuit breakers (MCB) are used in applications where the rated
current is less than 100 A. This type of circuit breakers is considered as final
distribution products, which are connected to branch circuits wired to the
electrical circuit breaker panel. Generally, lighting is protected with a 10 A
MCB. Fan Coil Units (FCU), Optical Network Units (ONU), Gas Cookers,
Water Heaters, Washing Machines, and spares are connected to 20 A rated
MCB. The Available ratings of MCBs are as follows:
39
MCB Available Ratings
16 A
20 A
25 A
32 A
40 A
50 A
63 A
While Miniature circuit breakers are more suited for low current appli-
cations and lightening, the moulded case circuit breakers in heavy current
circuits. The current ratings of the MCCBs can reach up to 2500 A. [14]
40
Figure 41: An Electrical Circuit Breaker Panel of a Studio in JA-10
41
Figure 43: An MCCB with an External Operated Handler
42
Fire Alarm Control Panels, as the name implies, are digital controllers that
control all devices connected to it. [19]
The riser diagram of the Fire Alarm System in building JA-12, depicted
in Figure 45, shows the wiring of devices located in 8 floors, roof, and ground
floor to the Fire Alarm Control Panel (FACP) based in the building man-
agement system (BMS) room. There are two classes of wiring devices to the
FACP: Class A, and Class B illustrated in Figures 48 and 47 respectively.
43
GENERAL NOTES:-
JA-12
LEGEND :
10
8
11
7
12 5
13 2
14
15
32
KEYPLAN
16
33 N
31
34
17
30
47
35 JA-12
44
18
46
29
19
36
45
28
20 37
27
38
21 26
22 40
24
44
PROJECT MANAGEMENT
41
43
23
CONSULTANT
42
MAIN CONTRACTOR
MEP CONTRACTOR:
GALAXY ADVANCED
GENERAL CONT. CO. LLC.
TEL: +971 2 6151600 , FAX: +971 2 6651670
P.O.Box: 39226, Abu Dhabi, UAE
E-mail: info@galaxy-uae.com
Website: www.galaxymep.com
Figure 44: Fire Alarm System and Voice Evacuation System in Building
NAME DRAWING No.
DESIGNED N/A
DEVELOPED N/A
CHECKED ENG.OMAR PROJECT No.
COORDINATED ENG.SABA
139
VERIFIED ENG.SHEREEN. SHOKRY
DRAWN MOHAN GANGA SCALE 1:100
APPROVED ENG.ADEL DAHER DATE
REF
A0
NO.
GENERAL NOTES:-
LEGEND :
JA-12
45
00 ISSUED FOR CIVIL DEFENCE APPROVAL AD 06-04-2016
No. REVISION APP'D DATE
CLIENT
PROJECT MANAGEMENT
CONSULTANT
MAIN CONTRACTOR
MEP CONTRACTOR:
GALAXY ADVANCED
GENERAL CONT. CO. LLC.
TEL: +971 2 6151600 , FAX: +971 2 6651670
P.O.Box: 39226, Abu Dhabi, UAE
E-mail: info@galaxy-uae.com
Website: www.galaxymep.com
DRAWING TITLE:
FIRE ALARM
SYSTEM RISER DIAGRAM
( JA-12 )
Location :-BMS Control Room
Figure 45: Fire Alarm System Riser including the System Components that
COORDINATED ENG.SABA
139
VERIFIED ENG.SHEREEN. SHOKRY
DRAWN NASIR SCALE 1 : 100
APPROVED ENG.ADEL DAHER DATE 06-04-2016
REF
YAS-JA-KHA-2600-DG-005054
A0
NO.
In class A wiring, the shielded fire resistant cable consists of a pair of
wires (-) and ( +) that is connects the FACP to each device in parallel. At
the end of the resistor wire, the positive and negative of the last device is
connected back to the FACP creating a loop. The advantage of this class
of connection is that the safe devices remain connected to the FACP even
in the presence of a faulty device existing in the loop. The reason for this
lies in the reverse connection from the last device in the resistor wire to the
FACP where devices are fed with power from two directions.
Devices are powered from one direction in case of class B wiring. In case
a fault occurs on a device in the line, the devices after will be disconnected
from the Fire Alarm Control Panel (FACP). An available example of class B
wiring is the Sounder with strobe. Devices connected in Class A are shown
in Figure 45 which are as follows:
• Smoke detectors.
• Heat detectors.
• Break glass.
46
Figure 47: Class A Wiring to the FACP
47
Figure 49: The Clean Agent for Extinguishing Fire in Electrical Systems
48
Figure 50: Low Current Cable
49
engineers get their work done. Interns are assigned to a department where
they have the freedom to approach several engineers and ask for tasks.
First and foremost, the responsibilities of electrical engineers has been
explained in accordance to their job title. A junior engineer is responsible
for preparing the low voltage, high voltage panels schedule, and site visits.
The conformity of electric devices installations to the national electric codes is
checked by the site electrical engineer. Site engineers responsibilities include
equipment testing after installation and before inspections. The work of
junior engineers and site engineers is supervised by the senior engineer who
acts as reference for others and checks their work. Also, a senior electrical
engineer checks electrical schematics submitted by other engineers, draws
various electric schematics, and prepares inspection documents. In addition,
the responsibilities of a contractor, consultant, and project manager towards
the completion of the project and serving the client were explained.
In terms of electrical designing tools, a brief introduction to the Auto-
CAD for checking electrical schematics was given by the electrical engineer
graphic designer in which he has shown how they used predefined functions in
excel to prepare the load schedules. Several electrical schematics for power,
lighting, low current systems were introduced. I feel like this internship has
given me an overall description of electrical engineering profession since it
introduced me to submittals, take offs, and inspections in addition to other
technical knowledge and skills. Furthermore, we were encouraged by the en-
gineers to go further in-depth research after being introduced to each electric
component. Some essential calculation that are important for electrical engi-
neering as load schedules, current break size selection, and cost estimations
have been studied.
It is important for electrical engineering to recognize the international
standards and designing requirements, which will facilitate creating designs
that are within the acceptable engineering practices. Documents such sub-
mittals can be used as a reference for this purpose.
7 Conclusion
This 6-week internship has been a flourishing experience for me as a fresh
graduate in electrical engineering in which i learned technical skills as well
as professional mannerism. I have learned that employees should show such
a governed attitude and actions in the workplace, even under pressure, as it
50
may affect the quality of their colleagues work. What have been introduced
to me through this internship is a complementary of the previously gained
knowledge from power distribution and power protection system courses that
will hopefully be made use of in my future career.
51
References
[1] ”cable size calculation”,. [Online]. Available:
http://www.authorstream.com/Presentation/
rajamrperfect-2898394-cable-size-calculation/
52
[9] What is a “Clean Agent”?. 2013. [Online]. Available: http://www.
approvedprotection.com/what-is-clean-agents/
[16] ”What is the difference between 2 core and 3 core cable ”. [Online].
Available: http://www.factorylux.com/lighting-knowledge-base/
what-difference-between-2-core-3-core-cable-flex/
53
[20] ”Maximum voltage drop limit”. [Online]. Available: http:
//www.electrical-installation.org/enwiki/Maximum_voltage_
drop_limit
54