Muzhil – 8 WIW

Tie Back & completion program


No. Content Item No.

1 1
General Well Information
2 2
Well History
3 4
Well status & Sketch
4 3
Tie Back objectives and highlights
5 Tie back operation & sequences 5

6 Clean out 9 5/8" casing & 7" liner 6

7 7” Scab Liner & Cement Program 7

8 Completion stg. To produce from Matulla 8


formation
Petrozenima commitment to health, safety and the environment is simply stated: no accidents, no
harm to people and no damage to the environment. Everybody who works for Petrozenima is
responsible for getting HSE right. Good HSE performance and the health, safety and security of
everyone who works for us are critical to the success of our business. It must also be remembered
that within Petrozenima no job is so important that we cannot take time to do it safely.

 Ensure all personnel adhere to, Total Safety man, Petrozenima and Contractor’s personal
protective equipment policies.
 While operations, hold abandon ship, H2S, fire drills, BOPE and accumulator tests weekly.
 Encourage all personnel to report any un-safe acts and/or spills.
 Report all pressure tests on the IADC report.
 Game plan operation sheet should prepare and distribute before any new jobs.
 All rig personnel should have appropriate safety training.
 All toxic and disposal to be boxed and hauled to SUCO for disposal.
1- General Well Information

Well Name Muzhil – 8 WIW


Country / Concession Egypt / South Abu Zenima concession Gulf of Suez area
Drilling Unit Admarine III
Y = 689,982 m N, X = 823,070 m E
Well Head coordinates
Long : 33° 77̕ 59.034” E , Lat. : 28° 544̒ 01.26” N

ORKB-MSL 92 ft

Water Depth 113 ft

Mud line 205 ft ORKB

30” Landing Ring 252.4 ft (47.4 ft below ML)


13-3/8” MLH 252.4 ft ORKB
9-5/8” MLH 254.6 ft ORKB
Mud line Suspension type VETCO GRAY

2- Well History

30” conductor (to 385 ft)

Ran 30” conductor with D46 to205 and free fall to 211 ft, drive to 224 ft and free fall to 242 ft, drove
to 385 ft Last BPF (160 – 170 – 195 – 200 – 200) ML @205 ft, L/R @252.4’

16” hole (F/385 – 4150 ft) Spud Mud @ 8.7 ppg, 9.2 SS KCL polymer mud

‐P/u 16” BHA (16” Reed new T41 Bit, With Ana drill GT MTR, ran in hole and drilling from 385’ to
2700 ft with 8.7-8.8 ppg spud mud, displace hole with 9 ppg polymer mud, continue drilling to 4092’
(csg point), circulate, spot 100 bbls hi vis pill on btm, wiper trip to conductor shoe, had 8 bph losses
ran back to bottom and spot 50 bbls LCM pill. Drilled to 4150 ft, circulated and swept hole with 100
bbls HVP. Spot 300 bbls HVP loaded with 40 ppb LCM (dynamic losses 4 bph, static 2 bph), pooh
and L/D BHA.

‐Ran 13 3/8” csg ( (4140 – 2827 ft) 35 its 72ppf, P110, BTC) & (72 jts , 68 ppf, K55, BTC) to
surface ,‐ MLH @ 252.4 ft, 4115 ft, CSG shoe @4140 ft, L/C @ 4057’. Circulate and had 4 bph
losses.‐Perform cmt job as follows. Pump 60 bbls preflush S.W, dropped btm plug, Mix& pump lead
slurry 490 bbls

@12.5 ppg, 100 bbls Tail slurry @15.8 ppg. Loaded first 50 bbls lead and tail slurry with 1.5 ppb ‐
Displace with 607 bbls MUD, had FDP 950 psi. Bump plug with 1450 psi, held 10 mints OK.

- Opened ports, had no cmt on surface.‐ Tried to close ports without success and finally tie back
with latch and lock tie back tool (emergency tie back tool).

12 1/4” hole ( F/4010 - 8993ft) ( 12.5 – 13.7ppg )– (ppg-SS - KCL - OBM)


P/U 12 1/4” Power Drive BHA with Ana drill GT Mtr- (0.1 RPG&7/8 lube) , 12 1/8” string stab & rih
and drilling without problems F/4140 ft –8720 ft, pooh and ran in hole with RAB rotary assembly and
drilled to 8993 ft. Pulled out of hole without problems.Logging: rih with (OBMI- BHC – GR), t0 8985ft
and recorded to 13 3/8” casing shoe.

Ran 9 5/8” casing (F. Shoe – 2 jts 53.5# P-110, BTC – F. Collar with baffle plate- 110 jts 53.5 #,
P110, BTC – 102 jts 47#, P110, BTC) shoe @8985 ft, L/C @8898 ft, 9 5/8” M.L.H @254 ft, CTC
packer @4093 ft. Perform Cmt job,First stage: Pump 60 bbls Spacer well clean-II @14.5 ppg, 300
bbls cmt lead slurry @15 ppg, 100 bbls cmt tail slurry @16 ppg, drop shut off plug, 10 bbls Cmt
@16 ppg, 5 b bbls cmt well clean- II @14.5 ppg, displaced cmt with 665 bbls OBM, bumped plug
with 1500 psi and increased to 2800 psi and inflated CTC, dropped DV tool opening tool. Circulated,
had no spacer and no cement.

Had130bblslosses.Second stage cement: 50 bbls Well clean II @14.5 ppg, 183 bbls Cmt @16 ppg
dropped DV closing plug, pump 5 bbls cmt @16 ppg . Displace with291 bbls, pressure tested to
2500 psi. Opened ports and circulated 15 bbls contaminated spacer. Spotted 50 bbls 8ppb lingo
sulphonate, close MLH and test with 500 psi. Hold ok.

-8-1⁄2” hole ( F/8993 - 11901 ft) 9.5-9.7 ppg hydro guard

← P/u 8 1⁄2” BHA RSX616 PDC with power V vortex assembly. Drilling 8 1⁄2” hole 8993 ft –
10091 ft with 9.5 ppg WBM without problem, pooh to change Bit and BHA.- Pooh, p/u & M/U R.B
with power V and roller reamer and continue drilling f/10091 –10434 ft, pooh due to slow rop.- P/U &
M/U power V vortex assembly with security RSX616 PDC Bit RIH & drilling f/10434 - 11395 ft core
Point. - Pooh without problem.- Made up core assembly, ran in hole and cut core F/11395 – 11458
ft, pull out of hole, had back ream f/11432 – 11418 ft. continued pooh without problems. l/d core
assembly and recovered 62.5 ft with 99% recovery. -P/u vortex assembly and ran in hole, increased
m. wt to 9.8 ppg drilled F/11458 – 11606 ft, pulled out of hole and changed bit.- Rih with new bit and
rih, had tight spots @ 10510 , 10710 , 10723 , 10725 ft- Drilled 8 1⁄2” hole with power V vortex
assembly f/11606 – 11901 ft, circulated and pooh. - Ran logging tools. - Run#1 (HRLA – TDL –
APS – HNGS- SP) & tool hanged @11901 ft and logged hole.- Run #2(FMI-DSI-GR), tool stuck at
9260 ft, pooh to surface.- ran in hole with condition assembly to TD @11901, had tight spots
@10575 & 10600 ft. pull out of hole. - R/U slb Log and Rih with, (MDT – GR) to TD.- Pooh with
Schlumberger logging.7” liner.

Run 7” liner, (73 jts 29# BTC P110 + 14 ft pup jt), 7” liner shoe @ 11893’, L/C @ 11811’, top of 7”
liner @ 8555 ft.

-Performed cement job as follow:

-pump 50 bbls C.W with 4 bpm @1200 psi.-Mix & pump 50 bbls scavenger slurry @12.5 ppg .-
Pumped (Gneat+35% S.F), 145 bbls slurry batch mixed w/4 bpm @ 15.8 ppg @200-500 psi.

-dropped dart and displaced with 272 bbls mud (6- 3 bpm) 2170 psi, plug not pumped, bled of
pressure, no back flow.

- had 18 bbls losses.- Had 18 bbls losses while displacement, set ZXP, recovered 21 bbls
contaminated cmt +56 bbls contaminated C.W.
3- well status& sketch

M U Z H I L -8
W ELL BORE SKETCH
R I G : B e n n e v is
R K B -M S L 9 2 ft L a n d in g R in g @ 2 5 2 .4 f t
W .D 1 1 3 ft 1 3 3 /8 " M L H @ 2 5 4 ft
R K B -M L 2 0 5 ft 9 - 5 /8 " M L H @ ft

30" COND. @ 385 ft


500 ft CMT above B.plug

9 5/ 8” B.P.@ 1000 ft (Fast Drill)

9 5/ 8” DV @ 4047 ft MD

13 3/ 8" CSG @ 4140 ft

9- 5/ 8" P- 110, 53.5 PPF, BTC

7" TOL with ZXP packer @ 8555’ MD

9 5/ 8" CSG @ 8985 ft

7" Liner, 29 PPF, P- 110

10 ft CMT above BP

7” B.P. @ 11310 ft (Fast Drill)

Matulla perforated Zone


11410- 11432 ft (22 ft)

Landing collar @ 11811 ft (PBTD)

Legend
CMT
F a s t D r i l l B .P .
N o r m a l E S Z V B .P .
Vetco Gray Mud Liner Hanger
4- Tie back objectives and highlights

The objective of the Tie-back is to re-enter the well, complete tie-back string to surface and run
the injection completion string and perform injection test program. The well suspension status
was as follow:

Well MLH Type 30” Status 13 3/8” Status 9 5/8” Status 7” Status

MUZHIL -2 Vetco Gray 30” cut @ 200 ft 13 3/8” MLH @ 252.4 ft CORROSION CAP @ 254 Top 7” Liner@
8,555 ft
CORROSION CAP not FT ORKB
installed

5- Tie- back operation sequences:


Preliminary operations

1. Rig positioning over well Muzhil-8

2. Jump ROV to the Sea-bed. Inspect top of 30” cut conductor pipe.

Run the 30” CP tie back string

3. Rig up the conductor handling equipment. Check the tie back bell with overshot profile
ID (33”), OD (36”) and swallow length (4 ft)

P/U 36” x 30” tie back bell. M/U and RIH with the first joint of 30” CP (XLF connection 310 X-56)
Continue RIH with 30” CP tie back string Above the 30” stub (the 30” stub stick up should be
around 5 ft. above sea bed) Monitor with ROV when the tie back bell pass through the platform
funnels.
4. Lower the tie back bell over the 30” CP stub verifying that the swallow length is 3 ft. as per
tie back bell construction drawings, Slack off all the string weight.

Wei ght Mi n. Tensil e Ti e- bac NO OF


de Connection Be nBURST
di n COLLAP k
l b/ ft) LB
PSI
g S De pth
56 1.0 ” wt–310#X LF 2,770 1585 E 2,149,000200 6

5. Center 30” CP inside transition piece funnel and weld plates. Cold cut 30” CP above platform.

6. POOH and L/D 30” CP landing joints and cut off joint.
P/U & M/U 5"
7. Rig down conductor handling equipment.

13 3/8” casing tie back – 30” x 13 3/8” cement top job

8. P/U and M/U camera assembly and RIH on top of the 13 3/8” mud line hanger. Visual
inspection of the tie-back thread, flush same and repeat inspection. POOH and L/D camera
assembly.

9. If required, P/U and M/U wash out tool + 26” stab and RIH with 5” HWDP to the 13 3/8” mud
line hanger. Rotate slowly and circulate to clean the mud line hanger profile. Circulate until
return is clean. POOH and rack back. RIH camera assembly on top of the 13 3/8” mud line
hanger. Inspect the thread and circulate if necessary. POOH and L/D camera assy.

10. R/U 13 3/8” Swedge Circulation Head (13 3/8” BTC pin x 2” Weco Union) and rack back.

11. R/U casing handling and running equipment.

12. P/up 13 3/8” latch &lock Tie back tool already made up on 13 3/8” K-55 , BTC 68# pup joint.
Inspect the tie back tool seals. M/U the latch &lock tie back tool assembly with one joint of
13 3/8” casing and RIH.

13. Continue to RIH 13 3/8” latch &lock tie back tool on 13 3/8” casing to the top of the mud line
hanger@ 252.2 ft.

14. Before to stab into mud line hanger, P/U and M/U 13 3/8” Swedge Circulation Head.

Wei ght Connectio Bu rs Co ll Te n sil e MLH Cs g Nr. Of


Size Grade t apse Len
(l b/ f t) n Lb*1000 (ft MD) join
(psi psi gth
ts
(ft.)
13 3/8” k-55 68 BTC 3451 1943 1071 252 252 7
.

Weld two strips on 13 3/8” coupling between csg jts to avoid unscrew for any of it

15. Record P/U and S/O weight. Stab the tie-back tool into the casing hanger and engage it.

16. latch &lock tie back the 13 3/8” casing by as MLH Eng. Procedures as follow Stab the tool
in to the hanger body by slack 5 klbs, rotate the casing approximately one turn. Observe the
torque should be increase to 2000 lb ft, Apply 20 kips over pull over the string weight to
verify the tool has latched in, slack all csg weight.

17. Fill up the casing with water and check for hydraulic integrity. Perform 13 3/8” casing
pressure test at a maximum pressure of 500 psi.
18. L/D 13 3/8” Swedge Circulation Head.

19. R/U Cold Cutter equipment. Rough cut 13 3/8” casing above platform, R/D cold cutter
equipment.

20. L/D casing landing joint and cut off joint. R/D casing handling and running equipment

21. Center the 13 3/8” casing into 30” conductor pipe welding four centralizers at the spider
deck level.

22. R/U 2 7/8” handling equipment.

23. P/U and M/U 2 7/8” TBG mule shoe and 2 3/8” tubing and RIH in the annulus 30” x 13-3/8”
to the mud line landing ring.

24. Circulate through the two strings with sea water in case of :-

A- Have full return or partial return, perform direct cement job.in two stage:

Mix and pump 120 bbl 15.8 cement with LCM fiber till recover pure cement on surface.

B- Have no return:

Pump 150 bbls LCM material pill (100 lb/bbl coarse& med. material) wait on soaking, try to
circulate If got return perform cement job as previous case if no repeat LCM pill with
increasing concentration to 150 lb/bbl.

25. POOH and lay down the two 2 7/8” tubing strings.

26. R/U cold cutter equipment and perform 13 3/8” casing final cut.

27. Install 13 5/8” X 3000 psi Braden Head.

28. Perform pressure test of the casing head at 1000 psi for 15min. Check ID of the Casing
head with the 12 1/4” drift.

1. 9 5/8” casing tie back

29. P/U and M/U camera assembly and RIH on top of the 9-5/8” mud line hanger @ 254.6 ft.
ORKB Visual inspection of the tie-thread, flush same and repeat inspection. POOH and L/D
camera assembly.

30. P/U and M/U wash out tool and RIH with 5” HWDP to the 9 5/8” mud line hanger. Rotate
slowly and circulate to clean the mud line hanger profile. Circulate until return is clean.
POOH and rack back same.
31. RIH camera assembly on top of the 9 5/8” mud line hanger. Inspect the thread and
circulate (if necessary). POOH and L/D camera assembly.

32. R/U 9 5/8” Swedge Circulation Head (9 5/8” BTC Pin x 2” Weco Union) and rack back.

33. R/U casing handling and running equipment.

34. M/U and RIH 9 5/8” Stab-in latch & lock tie back tool already made up on 9 5/8” joint.
Inspect the latch & lock tie back tool seals. M/U the tie back tool assembly to one joint of 9
5/8” casing and RIH.

35. Continue to RIH 9 5/8” latch & lock tie back tool on 9 5/8” casing with 9-5/8” X 13-3/8” CTC
packer to the top of the mud line hanger @ 252.5 ft ORKB.

Burst Collapse Te nsile MLH - Cs g Nr.


Size Grade CSG Connectio PSI PSI
WT. n LB*100 F T. MD) M Of
0 joint
s
9 5/8” P-110 47 BTC 9439 5292 1494 254 254 7

Weld Four strips on 9 5/8 coupling between casing jts to avoid unscrew for any jt
while tie back operation

36. Before to stab into mud line hanger, P/U and M/U 9 5/8” Swedge Circulation Head.

37. Record P/U and S/O weight. Stab the tie-back tool into the casing hanger and engage it.
38. Latch &lock tie back the 9-5/8” casing by as Vetco Gray Eng. Procedures as follow Stab the
tool in to the hanger body by slack 5klbs,rotate the casing approximately one turn to the left.
Observe the torque should be increase to 2000 ft.lb, Apply 20 kips over pull over the string
weight to verify the tool has latched in, slack all casing weight and rotate the casing to the
left to make up the tie-back tool seals. Apply pressure, as per rig procedure, to the ID of the
9-5/8" casing to inflate CTC packer as per Weatherford Engineer procedure. Once a
satisfactory test is achieved, install surface equipment as required.

39. R/U cold cutter machine. Cut 9 5/8” casing. R/D cold cutter and L/D cut off landing joint. R/D
casing handling equipment.

40. Fill up the casing with water and check for hydraulic integrity. Perform 9 5/8” casing
pressure test at 1000 psi 15 minutes straight line.

41. L/D 9 5/8” Swedge Circulation Head.

42. Install and orient 13 5/8” x 11” x 3K psi tubing spool. Test the casing spool flange.
43. N/U riser and 13 5/8” X 5k BOP stack.

44. N/U 13 5/8” x 5K BOP stack. Pressure test BOP and spool adapter as per procedure.
POOH and L/D test plug.

6- Clean out 9 5/8” casing & 7" Liner

45. M/U and RIH with 8 1/2" mill tooth with IADC 117 on clean out BHA ON 5” DP.

46. RIH on top of cement plug @ 500 ft. MD ORKB. Tag it to confirm depth. Wash down last stand

47. Drill out cement plug from 500 to 1000 FT. MD ORKB with Sea water and Hi Viscous Sweeps.

N.B: sweep hole while drilling with Hi vis pill while cleaning

48. Cont. RIH Tag top of 7” liner @ 8,555 ft ORKB (run carefully across from below 13-3/8” casing
to top of liner)?

49. Circ. Pooh, L/D 8 ½” cleaning assy.

50. RIH and polish top of 7” liner and test top of liner to 3000 psi.

7- 7" Scab Liner

51. Run 7: Scab liner from 8,555 ft ORKB to +- 4000 ORKB ft and cement as per program.

52. M/U and RIH with 6”" mill tooth bit with IADC 217 OR 117 on clean out BHA on 3 1/2” & 5” DP
and clean out 7” scab liner and drill out cement & bridge plug at 11,300 ORKB.

53. Test Casing integrity to 3000 psi. POOH and L/D 6” cleaning assembly.

 Scrape the 7” casing till PBTD several times to clean same properly circulating at
max rate possible.
 Displace the well with completion fluid.
8. Re perforation operations & Equipment preparation:

8.1 Pre-Job Preparation:

 All completion assemblies to be checked compatible with the attached Sub-


assembly measuring sheets.
 All completion accessories to be checked against the proposal sketch and Material
and serial numbers to be recorded in the completion schematic.
 Completion engineer to check TBG size, weight, grade and material matches the
details of tubing stated in this design of services and has to be clear in the
completion schematic.
 TBG has to be drifted with API standard drift (2.867”).
 Completion procedures to be discussed in a pre-job meeting with all involved
parties prior to RIH.
 Confirm PKR setting depth against CBL to avoid setting against any CSG Collar.
 Test Control Line reel to 7500 PSI.
 Function test TRSSSV and make sure its operating correctly.
 Ensure that all non-essential personnel are clear of the loading area and make
announcement over rig PA system. Place barriers around gun loading area.
 Drift all the TCP tools with a 2” drift prior to make-up.
 Pick up and make-up lower TCP tool section consisting of 7” Test PKR, Safety Joint, and
Circulating valve in rig floor.
 Drift all tubular while RIH with a minimum of 2”,
 When running the test string, stabbing guides and tubing power tongs with integral back – up
must always be used. Connections requiring higher torque than the tubing are to be made up
with a back up tong on the collar or crossover to avoid over-torque on the tubing. Tubing
make up torque will be analyzed with Jam unit.
 Dope to be applied sparingly to pin only and string to be covered at all times when the
elevators are off.
 The driller or tool-pusher must be present on the rig floor at all times during testing operations
 All connections are to be made-up and checked using a computerized joint analyzer make-up
system.
 The Well Completion Supervisor will approve a running order of TCP assemblies prepared by
TCP Engineer and prepare tubing’s tally for the Driller to follow.
 All pressure operated test equipment settings will be reviewed by Service Company Eng.
Company Man And rig Tool-pusher prior to running equipment to ensure that casing burst,
tubing collapse and functions are all within the proper limits.
 Ensure that all contingency crossovers (i.e. slickline or logging) to top of STT are checked
before and make sure they screw together exactly.
Re-Perforation Intervals:
Perforation

From To Length , ft

11408 11432 24 FT

11455 11461 6 FT

11480 11498 18 FT

Total 48 FT
Depths to be confirmed after logs

 Safety Meeting to be held prior to start of TCP run, Drilling personnel and Service Company
Personnel to advice of planned operations etc.
 Safety Tool Box meetings to be held prior to any operation pertaining to lifting of equipment,
running string etc and should include Rig Crew and TCP specialist.
 Safety tool box meeting are to be held at each crew handover and documented
 Risk Assessment and JSA, documents should be developed/used in conjunction with all TCP
operations.
 TCP Specialist’s will be present and supervise at all times the lifting of TCP BHA equipment.
 Make up torques on rig floor have to be supervised by TCP Specialist who will advise Driller
and crew.
 Extreme care to be taken during all lifting operations and making up tools.
 The measurement between top of the gun and Radioactive marker is to be carefully
measured and allowing for packer to set.
 All necessary crossovers, circulating subs and IBOPs (without thread protectors), including
backups must be available on the rig floor ready for use.
 Ensure that the correct slips and elevators are available and clearly marked.
 Ensure all tubing, pup joints, tools and cross overs are drifted and measured on the rig (total
number of joints on board is to be recorded).
 Air operated elevators must not be used whilst picking up the bottom hole assembly or for
any other minor lifts.
 All equipment to be lifted on to the rig floor must be correctly stripped and equipped with
certified slings and tag lines attached.
 The TCP perforating specialist must be present and personally supervise all operations
involving handling of perforating equipment. The specialist shall also hold a safety briefing
with the rig crew before starting to make up the guns.
 Safety Tool Box Meetings to be held prior to any operation and documented.
 The running speed should be restricted to approximately 60 sec per joint.
 Ensure that all tools are drifted. Drift tools prior to picking up.
 Service Company must have available detailed sketches of all equipment run below the
rotary table in case fishing operations are required.
 Ensure that packer is not set across a casing collar.
 M/U TCP BHA referring to Halliburton tool string schematic and pick up and make up
procedures in attachment.

8.2 Installation Job Procedure:

1- Hold safety meeting reviewing P/U TCP guns.


2- Get the Guns from TCP Basket using Rig crane and position them on the catwalk.
3- Start picking up Gun # 1 using the air wench and put it inside the mouse hole.
4- Remove the gun cap and tide the Gun lifting sub.
5- Use 2 7/8” Elevator to get the gun from the mouse hole to run inside the hole.
6- Use the 4 ½” Slips and Gun safety clamp to support the gun before opening the
elevator.
7- Get the second gun from the catwalk to the mouse hole and get off the gun cap and tide
8- The lifting sub and get the gun using elevator and position it above the gun in hole and
start tiding the two guns together.
9- After that pick up the guns with the elevator and remove the slips and the gun safety
clamp.
10- RIH with guns and put the slips and safety clamp and repeat the steps until running all
guns.
11- Make sure that all the assemblies above firing head was drifted with its suitable drift.
12- Pick up and make up the Down Hole perforation string as per the attached sheet
(Completion Schematic).
13- Hold safety meeting discussing the operations before P/U the completion
subassemblies.
14- Start connecting all the completion BHA as per attached schematic diagram M/U 3-
1/2” EUE TBG Joints as per Halliburton completion schematic.
15-Install Radio Active bead by the TCP engineer on location.
16-M/U 3-1/2” EUE GR Nipple size: 2.56” as per schematic.
17-M/U 3-1/2” EUE perforated pup joint.
18-M/U 3-1/2” EUE GF Nipple size: 2.56”.
19-M/U 3-1/2” EUE TBG joints, quantity as per proposed in Halliburton completion
schematic.
20-M/U 7” x 3-1/2” EUE PHL packer.
21-M/U 3-1/2” EUE TBG joint.
22-M/U 3-1/2” EUE SSD, Size: 2.75”, Type: GL.
23-M/U 3-1/2” EUE TBG joint.
24-M/U 3-1/2” EUE X-Nipple, Size: 2.81”.
25-R/U Slick line with test plug and set inside X-Nipple.
26-Pressure tests the string with 3000 psi for 15 minutes.
27-POOH with slick line and test plug and R/D
28-Continue RIH with completion assembly as proposed schematic.
29-M/U 3-1/2” EUE TBG joints, Quantity 39.
30-M/U 3-1/2” EUE Expansion Joint, Keyed type in open position.
31-M/U quantity 1, 3-1/2” EUE TBG joint.
32-R/U Slick line with test plug and set inside X-Nipple.
33-Pressure tests the string with 3000 psi for 15 minutes.
34-POOH with slick line and test plug and R/D
35-Continue RIH with completion assembly as proposed schematic.
36-MU 3-1/2” TBG joints as per proposed schematic till reach TRSSSV.
37-M/U TRSSSV assembly and connect the control line reel to the TRSSSV.
38-Apply pressure in the control line reel to open 2.81” TRSSSV while RIH.
39-M/U 3-1/2” EUE TBG joints until reach with TCP guns on depth.
40-Keep the sting under tension.
41-R/U Slick line with test plug and set inside X-Nipple.
42-Pressure tests the string with 3000 psi for 15 minutes.
43-POOH with slick line and test plug and R/D
44-R/U E/L and RIH with GR-CCL and correlate guns depth using RADIO ACTIVE BEAD
(Ref. Logs are open hole log and CAST-V). POH and R/D HLS.
45-Space out the guns and packer depths.
Notes:

 Short Pup joints to be available to space out.


 Don’t M/U the tubing hanger to the string during this step till perform all the
correlation required and confirm the space out PUP JTs lengths.

46- L/D the excess tubing joints and do the space out calculation required.
47-Make up the tubing hanger with the space out PUP Jts required to the 3 ½” running tool
in the top of hanger and torque connection to thread manufacture’s minimum make up
torque.
48-Open THS side outlets and slowly lower the tubing hanger in the THS and complete
land it, be sure that at this step the guns are positioned against the required perforation
interval.
49-Check that the tubing hanger has fully landed by measuring the distance from DF to
THF. Observe paint mark via SOV.
50- Pull the string 5 FT to make the expansion joint semi closed after setting PHL packer.
51-Hold safety meeting to discuss the R/U and the operations of S/L.
52-R/U Slick line with test plug and set inside X-Nipple.
53-Pressure tests the string with 3000 psi for 15 minutes.
54-POOH with slick line and test plug and R/D.
55-S/L RIH and retrieve 2.813” PXX- Plug (Lock mandrel and prong), POOH.
56-S/L, RIH W/ 2.56" Check Valve and set same at GF-Nipple below the Packer,
POOH and L/D S/L.
57-Pressure up the tubing string to 500 psi/10 min and then increase gradually to
3000 psi for 15 min’s to set Packer. (Follow Hall. Engineer instructions)
Note:

Annulus side to be kept open in all TBG. Pressure tests to monitor annulus for return.

58-Take 10 KIBS over pull to check the setting of the packer.


59-S/L RIH and retrieve 2.56” check valve, POOH and R/D S/L.
60-Tight all lock down screws properly.
61-Hold safety meeting before testing the annulus.
62-Pressure test annuals with 750 PSI, for 10 min.
63-Remove the landing joint and TBG. HGR running tool.
64-Install the 3” BPV in the tubing hanger.
65-Hold safety meeting to discuss the operations of N/D BOP and N/U X-mass tree.
66-N/D the BOP stack
67-R/U X-mass tree
68-Hold safety meeting before testing the X-mass tree.
69-Replace BPV with TWCV & Pressure test X mass-tree to 3000 psi/15 min's
against TWCV. Chart test and witnessed by Petrozenima DSV and
Service Company Supervisor.
70-Retrieve the TWCV.
71-Hold safety meeting to discuss the R/U and the operations of nitrogen displacement.
72-Open TRSSSV.
73-R/U Slick line and RIH to open the SSD valve.
74-R/D Slick line.
75-R/U N2 pump and start displace tubing with nitrogen to achieve under-balance.
76-R/U Slick line and RIH to close the SSD valve.
77-A pressure test annual with 750 PSI, for 10 min to make sure SSD is closed.
78-R/D Slick line.
79-Bleed off nitrogen pressure in the tubing side to zero.
80-Perform General Safety Meeting Attended By All Rig Personnel.
81-Pressure up the annulus side above the packer, 500 PSI.
82-Inform all Personnel Including Radio-Room of Intention to Perforate.
83-Install calibrated pressure gauge on KWV.
84-Remove Tree cab. Keep LMV close. Open SV & UMV.
85-Hang the 1.25” detonating bar above LMV.
86-Open LMV and drop the 1.25” mechanical firing bar; then close all tree
valves and install tree cab flange.
87-Keep SV close and record WHSIP from KWV gauge.

Notes:
 Time delay for the firing head is about 15 minutes.
 Slick line to be ready in case required to RIH and fishing the firing bar.
 Call Cairo office (Petrozenima & Halliburton) in case of we are going to fish
the bar.

88- If there is no indication of firing, R/U Slick line with PCE and pressure test same
to 3000 psi for 15 min against X-mass tree valves.
89- S/L, RIH with 1.25" Bar fishing tool (15/16” Sucker Rod thread) with the
recommended slick line too
l string and RIH to fish the bar.
90- If the bar depth is the mechanical firing head depth and there is no indication for
firing on the end of
the bar.
91- Wait for firing indication.
92- If succeeded to fire the guns mechanically, go to next step. If failed consult with
Cairo office for the contingency plan.
93- Monitor the well for 30 minutes.
94- R/U Slick line with PCE and pressure test same to CITHP for 15 min.
95- S/L, RIH with 2.25” shifting tool and work on mechanical gun release to release
the guns and drop it in.
rate hole. Continue RIH to below the bottom shot and confirm release of the
guns.
96- Muzhil-8 Sampling and Injectivity test will follow.

Notes:

 Annulus side to be kept open in all TBG. Pressure tests to monitor annulus for return.
 One person should be dedicated to monitor the annulus returns at all steps while
pumping down the tubing.
 Ensure that the tubing is full prior to test the string.
 measure the distance from rig RKB to THAF, All measurements should be referenced to
ORKB report RKB correction and mention it in the first completion report.

 Take all precautions and monitor H2S or LEL gases if any

 Clean all tanks before mixing any completion fluid


 Monitor and observe well is full during all completion operations and record losses if any
 While RIH completion stg. put Limited Qty of Tbg dope on pin only by using soft painting
brush (don’t put any dope on the Box).

9 Contingency

As per the highlighted comments above.


Proposed COMPLETI ON I NSTALLATION
Customer: PETROZENIMA Completion Type: Casing: Size Weight Grade Thread
Field: MUZHIL Completion Eng.: Upper: 9 5/8" 53.5# P-110
Well No : MUZHIL-8 Date: Lower:
Co. Man: Ticket No.: Liner: 7" 29# P-110
Tubing: Size Weight Grade Thread
Upper:
Lower:
Completion Fluid:
BHP
BHT
U.B

Perforation I nt. (11408-11432) 24 FT,(11455-11461) 6 ft,(11480-11498) 18 ft


Item No. of Min ID Max OD Length Depth
Description of I tem Comment
No J oints (In) (In) (FEET) To Top

1 Tubing Hanger
2 3 3 1/2" EUE TBG. joint 2.992 3.950 250.000 0.000 PETROZENIMA TO SUPPLY
3 3 1/2" EUE Flow Coupling 2.880 4.520 5.010 250.000 HALLIBURTON HCT TO SUPPLY
4 3 1/2" EUE TRSSSV, Size: 281", Well Star 2.81 5.20 4.65 255.010 HALLIBURTON HCT TO SUPPLY
5 3 1/2" EUE Flow Coupling 2.880 4.520 5.010 259.660 HALLIBURTON HCT TO SUPPLY
6 3 1/2" EUE TBG. joint 2.992 3.950 9504.658 264.670 PETROZENIMA TO SUPPLY
7 3 1/2" EUE Expansio Joint, Keyed, 10 FT Stroke 2.910 5.030 12.000 9769.328 HALLIBURTON HCT TO SUPPLY
8 39 3 1/2" EUE TBG. joint 2.992 3.950 1170.000 9781.328 PETROZENIMA TO SUPPLY
9 3 1/2" EUE X-Nipple, Size: 2.81" 2.810 4.500 1.200 10951.328 HALLIBURTON HCT TO SUPPLY
10 1 3 1/2" EUE TBG. joint 2.992 3.950 30.000 10952.528 PETROZENIMA TO SUPPLY
11 3-1/2" EUE SSD, Size: 2.75", GL Type 2.750 4.500 3.500 10982.528 HALLIBURTON HCT TO SUPPLY
12 1 3 1/2" EUE TBG. joint 2.992 3.950 30.000 10986.028 PETROZENIMA TO SUPPLY
13 7" x 3-1/2" PHL Packer, 23-29 # 2.850 5.980 5.933 11016.028 HALLIBURTON HCT TO SUPPLY
14 4 3 1/2" EUE TBG. joint 2.992 3.950 120.000 11021.960 PETROZENIMA TO SUPPLY
15 3 1/2" EUE GF Nipple, Size: 2.56" 2.560 4.500 1.260 11141.960 HALLIBURTON HCT TO SUPPLY
16 1 3 1/2" EUE Perforated Pup Joint, 10 FT 2.990 4.500 10.000 11143.220 HALLIBURTON HCT TO SUPPLY
17 3 1/2" EUE GR Nipple, Size: 2.56" 2.440 4.500 1.260 11153.220 HALLIBURTON HCT TO SUPPLY
18 2 7/8" RADIO ACTIVE SUB 2.440 3.670 0.440 11154.480 HALLIBURTON TCP TO SUPPLY

19 RADIO ACTIVE BEAD 2.440 3.670 1.400 11154.920 PETROZENIMA TO SUPPLY


20 3 2 7/8" EUE TBG. joint 2.992 3.950 93.000 11156.320 PETROZENIMA TO SUPPLY
21 1 2 7/8" EUE Tubing JOINT 2.440 3.670 30.000 11249.320 HALLIBURTON TCP TO SUPPLY

22 5" VERTICAL SHOCK ABSORBER 2.300 5.000 3.520 11279.320 HALLIBURTON TCP TO SUPPLY

23 1 2 7/8" EUE Tubing JOINT 2.440 3.670 30.000 11282.840 HALLIBURTON TCP TO SUPPLY

24 2 7/8" Mechanical TBG Release 2.250 3.670 1.800 11312.840 HALLIBURTON TCP TO SUPPLY
25 1 2 7/8" EUE TBG. JOINT 2.440 3.670 30.000 11314.640 HALLIBURTON TCP TO SUPPLY

26 2 7/8" EUE Ported Depris Sub 2.990 3.750 2.230 11344.640 HALLIBURTON TCP TO SUPPLY

27 1 2 7/8" EUE TBG. JOINT 2.440 2.875 30.000 11346.870 HALLIBURTON TCP TO SUPPLY

28 1 2 7/8" EUE pup. JOINT 1.990 2.875 10.000 11376.870 HALLIBURTON TCP TO SUPPLY

29 1 2 7/8" EUE HEAVY WALL PUP JOINT W/ NO GO 1.560 2.875 4.570 11386.870 HALLIBURTON TCP TO SUPPLY

30 3-3/8" Mechanical Firing Head N/A 3.375 0.500 11391.440 HALLIBURTON TCP TO SUPPLY

31 4 5/8" T.C.P GUN SAFETY SPACER N/A 4.625 16.060 11391.940 HALLIBURTON TCP TO SUPPLY

32 TOP SHOT N/A 4.625 11408.000 HALLIBURTON TCP TO SUPPLY

33 4 5/8" TCP GUN 5 SPF, EXTRA DP,HMX (48 ft Loaded) N/A 4.625 90.000 HALLIBURTON TCP TO SUPPLY

34 BOTTOM SHOT N/A 4.625 11498.000 HALLIBURTON TCP TO SUPPLY

35 BLANK GUN N/A 3.375 0.180 11498.180 HALLIBURTON TCP TO SUPPLY

36 2.00 Extended Delay element N/A 3.380 2.200 11500.380 HALLIBURTON TCP TO SUPPLY

37 TIME DELAY FIRING HEAD N/A 3.380 1.850 11502.230 HALLIBURTON TCP TO SUPPLY

38 ported Nose Plug N/A 2.875 0.590 11502.820 HALLIBURTON TCP TO SUPPLY

GENERAL REMARKS:-
* ALL LENGTHESACCORDING TO TUBING HEAD SPOOL.
* THE RADIO ACTIVE BEED MARKER DEPTH IS ------- ORKB.
* THE FISH LENGTH IS.
* PETROZENIMA TO SUPPLY 2 7/8", 31/2" ELEVATORSAND SLIPS.
* THE TRUE DIMENSIONS WILL BE REVIEWED AND CONFIRMED BY THE COMPLETION ENGINEER.
* TUBING END @ +/- MT
* PETROZENIMA to supply 2 7/8" EUE TubingJ oints (---- EA)& 23/8" TBG. J OINT (1EA)

proposed completion sketch before dropping the guns