OBRA: ADECUACIÓN DE TERRENO S.E.

YARABAMBA 500kV/200kV
CLIENTE: PROYECTOS DE INFRAESTRUCTURA DEL PERÚ SAC CRONOGRAMA DE MOVIMIENTO DE TIERRA - CURVA "S"
FECHA: 25 de enero del 2016

Mes NOVIEMBRE ´15 DICIEMBRE ´15 ENERO ´16 FEBRERO ´16 MARZO ´16
Parcial Contractual Parcial Proyectado % de W Sem. Sem 01 Sem 02 Sem 03 Sem 04 Sem 05 Sem 06 Sem 07 Sem 08 Sem 09 Sem 10 Sem 11 Sem 12 Sem 13 Sem 14 Sem 15 Sem 16 Sem 17 Sem 18
ITEM DESCRIPCIÓN UND Pesos Programado Real
(US$) (US$) completado Día Del 16.Nov Del 23.Nov Del 30.Nov Del 07.Dec Del 14.Dec Del 21.Dec Del 28.Dec Del 04.Jan Del 11.Jan Del 18.Jan Del 25.Jan Del 01.Feb Del 08.Feb Del 15.Feb Del 22.Feb Del 29.Feb Del 07.Mar Del 14.Mar
Día Al 22.Nov Al 29.Nov Al 06.Dec Al 13.Dec Al 20.Dec Al 27.Dec Al 03.Jan Al 10.Jan Al 17.Jan Al 24.Jan Al 31.Jan Al 07.Feb Al 14.Feb Al 21.Feb Al 28.Feb Al 06.Mar Al 13.Mar Al 20.Mar

ADECUACIÓN DEL TERRENO

1.00 MOVIMIENTOS DE TIERRA Glb 1,370,075.00 888,140.63 48.86% 88.03% 71.93% 35.1% Progr. 0.00% 0.00% 0.00% 9.65% 23.03% 33.57% 45.68% 57.21% 68.73% 80.25% 88.03% 90.33% 95.20% 100.00% 100.00% 100.00% 100.00% 100.00%

Actual. 0.00% 0.00% 0.00% 4.57% 17.69% 26.16% 34.27% 45.76% 55.75% 62.43% 71.93% 79.26% 89.23% 96.50% 99.41% 100.88% 100.88% 100.88%
Real 0.00% 0.00% 0.00% 4.57% 17.69% 26.16% 34.27% 45.76% 55.75% 62.43% 71.93% 71.93% 71.93% 71.93% 71.93% 71.93% 71.93% 71.93%
2.00 REVESTIMIENTO DE TALUD Glb 44,905.58 44,905.58 2.47% 0.00% 0.00% 0.0% Progr. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 75.00% 100.00% 100.00% 100.00%
Actual. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 25.00% 50.00% 75.00% 100.00% 100.00%
Real 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3.00 OBRAS DE CONTENCIÓN Glb 222,536.42 222,536.42 12.24% 98.58% 98.44% 12.1% Progr. 0.00% 0.00% 0.00% 0.00% 22.12% 44.23% 68.79% 83.43% 88.18% 92.19% 98.58% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Actual. 0.00% 0.00% 0.00% 4.77% 10.12% 48.47% 62.01% 64.33% 78.19% 86.35% 96.57% 99.81% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Real 0.00% 0.00% 0.00% 5.00% 10.40% 48.69% 63.79% 64.33% 78.19% 86.35% 98.44% 98.44% 98.44% 98.44% 98.44% 98.44% 98.44% 98.44%

VÍA DE ACCESO
4.00 MOVIMIENTOS DE TIERRA Glb 35,227.10 65,931.07 3.63% 19.88% 19.88% 0.7% Progr. 0.00% 0.00% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 30.34% 50.25% 61.34% 92.33% 100.00% 100.00% 100.00%
Actual. 0.00% 0.00% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 25.31% 50.25% 58.94% 94.06% 100.00% 100.00% 100.00%
Real 0.00% 0.00% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88% 19.88%
5.00 REVESTIMIENTO DE TALUD Glb 38,546.90 38,546.90 2.12% 0.00% 0.00% 0.0% Progr. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 48.52% 100.00% 100.00%
Actual. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 48.52% 100.00% 100.00%
Real 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

6.00 CONSTRUCCIÓN VÍA Glb 96,793.51 96,793.51 5.33% 0.00% 0.00% 0.0% Progr. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 7.68% 18.68% 74.74% 97.25% 100.00%
Actual. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 8.05% 0.00% 8.05% 10.95% 12.49% 74.74% 95.87% 100.00%
Real 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7.00 CANALES ESCALONADOS Y CABEZOTES Glb 8,782.36 8,782.36 0.48% 100.00% 0.00% 0.0% Progr. 0.00% 0.00% 0.00% 0.00% 5.53% 35.44% 58.57% 93.90% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Actual. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.53% 34.19% 69.52% 69.52% 75.62% 75.62% 75.62%
Real 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Programad
8.00 OBRAS DE CONTENCIÓN Glb 37,944.15 37,944.15 2.09% 100.00% 0.00% 0.0% Progr. 0.00% 0.00% 0.00% 0.00% 26.38% 46.38% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
o
Actual. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 24.99% 53.80% 82.61% 82.61% 94.99% 100.00% 100.00%
Real 0.00% Real
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

9.00 BADÉN Glb 72,377.42 72,377.42 3.98% 100.00% 45.83% 1.8% Progr. 0.00% 0.00% 0.00% 0.00% 16.67% 44.70% 69.15% 99.96% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Actual. 0.00% 0.00% 0.00% 7.64% 15.27% 15.27% 15.27% 15.27% 15.94% 19.44% 45.83% 91.14% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Real 0.00% 0.00% 0.00% 7.64% 15.27% 15.27% 15.27% 15.27% 15.94% 19.44% 45.83% 45.83% 45.83% 45.83% 45.83% 45.83% 45.83% 45.83%

10.00 MUROS EN GAVIONES Glb 30,301.60 30,301.60 1.67% 96.56% 26.46% 0.4% Progr. 0.00% 0.00% 0.00% 0.00% 0.00% 14.62% 30.06% 89.46% 89.67% 93.11% 96.56% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Actual. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 8.77% 13.15% 13.15% 13.15% 26.46% 97.56% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Real 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 8.77% 13.15% 13.15% 13.15% 26.46% 26.46% 26.46% 26.46% 26.46% 26.46% 26.46% 26.46%

11.00 CERRAMIENTO Glb 449,378.00 306,634.40 16.87% 47.13% 6.98% 1.2% Progr. 0.00% 0.00% 0.00% 0.00% 0.00% 5.80% 12.35% 21.04% 29.74% 38.43% 47.13% 55.83% 64.52% 73.22% 81.91% 90.61% 100.00% 100.00%
Actual. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.34% 3.02% 6.98% 13.88% 26.81% 42.33% 59.57% 81.12% 100.00% 100.00%
Real 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.34% 3.02% 6.98% 6.98% 6.98% 6.98% 6.98% 6.98% 6.98% 6.98%

12.00 OTROS Glb 4,738.80 4,738.80 0.26% 0.00% 5.00% 0.0% Progr. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
Actual. 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.00% 5.00% 5.00% 5.00% 50.45% 95.91% 100.00% 100.00% 100.00%
Real 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00% 5.00%

TOTAL (CD) 2,411,606.842 1,817,632.846 100% 51.38%

% COMPLETADO

A % AVANCE PROGRAMADO Programado 0.00% 0.00% 0.72% 5.43% 15.93% 26.68% 39.17% 50.45% 58.17% 65.81% 71.92% 75.38% 79.95% 84.57% 89.60% 95.98% 99.85% 100.00%
Actualizado 43.31% 51.38% 60.02% 69.57% 77.72% 84.14% 93.97% 100.09% 100.31%
B % AVANCE ACTUAL Real 0.00% 0.00% 0.72% 3.87% 11.25% 20.07% 26.03% 31.78% 38.44% 43.31% 51.38%
OBRA: ADECUACIÓN DE TERRENO S.E. YARABAMBA 500kV/200kV
CLIENTE: PROYECTOS DE INFRAESTRUCTURA DEL PERÚ SAC 119,321.04 Del 16.Nov 119.00 Del 14.Mar
CRONOGRAMA DE EJECUCIÓN
NOVIEMBRE ´15 DICIEMBRE ´15 ENERO ´16 FEBRERO ´16 MARZO ´14 NOVIEMBRE ´15 DICIEMBRE ´15 ENERO ´16 FEBRERO ´16 MARZO ´14
Sem 01 Sem 02 Sem 03 Sem 04 Sem 05 Sem 06 Sem 07 Sem 08 Sem 09 Sem 10 Sem 11 Sem 12 Sem 13 Sem 14 Sem 15 Sem 16 Sem 17 Sem 18 Sem 01 Sem 02 Sem 03 Sem 04 Sem 05 Sem 06 Sem 07 Sem 08 Sem 09 Sem 10 Sem 11 Sem 12 Sem 13 Sem 14 Sem 15 Sem 16 Sem 17 Sem 18
METRADOS METRADOS METRADOS
ITEM DESCRIPCIÓN UND P.U. PRESUPUESTO Del 16.Nov Del 23.Nov Del 30.Nov Del 07.Dec Del 14.Dec Del 21.Dec Del 28.Dec Del 04.Jan Del 11.Jan Del 18.Jan Del 25.Jan Del 01.Feb Del 08.Feb Del 15.Feb Del 22.Feb Del 29.Feb Del 07.Mar Del 14.Mar VARIACION Del 11.Nov Del 18.Nov Del 25.Nov Del 02.Dec Del 09.Dec Del 16.Dec Del 23.Dec Del 30.Dec Del 06.Jan Del 13.Jan Del 20.Jan Del 27.Jan Del 03.Feb Del 10.Feb Del 17.Feb Del 24.Feb Del 02.Mar Del 09.Mar
CONTRATO REALES REAL
Al 22.Nov Al 29.Nov Al 06.Dec Al 13.Dec Al 20.Dec Al 27.Dec Al 03.Jan Al 10.Jan Al 17.Jan Al 24.Jan Al 31.Jan Al 07.Feb Al 14.Feb Al 21.Feb Al 28.Feb Al 06.Mar Al 13.Mar Al 20.Mar Al 17.Nov Al 24.Nov Al 01.Dec Al 08.Dec Al 15.Dec Al 22.Dec Al 29.Dec Al 05.Jan Al 12.Jan Al 19.Jan Al 26.Jan Al 02.Feb Al 09.Feb Al 16.Feb Al 23.Feb Al 01.Mar Al 08.Mar Al 15.Mar
ADECUACIÓN DEL TERRENO (VER PLANO PE-
-
MAMO-00005-S-04-K4250)
1.00 MOVIMIENTOS DE TIERRA 1,370,075.00 888,140.63 0.0% 0.0% 0.0% 6.6% 29.8% 48.3% 62.8% 70.2% 77.7% 85.2% 90.1% 91.3% 95.6% 100.0% 100.0% 100.0% 100.0% 100.0%
DESBROCE Ó DESCAPOTE H=0,30 m.
1.1 INCLUYE: CARGUE, RETIRO Y LIMPIEZA.
m3 16,200.00 15,427.85 3.58 57,996.00 55,231.70 15,427.85 14,400.00 1,027.85 - - - - 0.93 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 desbroce ó descapote h=0,30 m. incluye: cargue, retiro y limpieza.
EXPLANACIÓN EN CORTE EN MATERIAL
1.2 COMÚN. MEDIDO EN BANCO.
m3 118,100.00 112,506.04 4.74 559,794.00 533,278.63 112,506.04 7,200.00 15,840.00 12,960.00 14,400.00 17,280.00 17,280.00 17,280.00 10,266.04 - - - - 0.06 0.20 0.32 0.45 0.60 0.76 0.91 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 explanación en corte en material común. medido en banco.
EXPLANACIÓN EN LLENO CON MATERIAL DE
1.3 EXCAVACIÓN. MEDIDO EN BANCO EN SU m3 10,500.00 13,215.92 9.46 99,330.00 125,022.60 13,215.92 2,160.00 2,160.00 2,160.00 2,160.00 2,160.00 2,160.00 255.92 - - - - - - - 0.16 0.33 0.49 0.65 0.82 0.98 1.00 1.00 1.00 1.00 1.00 1.00 explanación en lleno con material de excavación. medido en banco en su posición final.
POSICIÓN FINAL.
EXPLANACIÓN EN CORTE EN ROCA. MEDIDO 3,000.00 2,400.00 1,415.00
1.4 m3 40,000.00 6,815.00 13.38 535,200.00 91,184.70 6,815.00 - - - - - 0.44 0.79 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 explanación en corte en roca. medido en banco
EN BANCO
EXPLANACIÓN EN LLENO CON MATERIAL DE 1,992.37
1.5 PRÉSTAMO. MEDIDO EN BANCO m3 5,500.00 3,896.45 21.41 117,755.00 83,422.99 3,896.45 1,904.08 - - - - - - - - - - - - - 0.49 1.00 1.00 1.00 1.00 1.00 explanación en lleno con material de préstamo. medido en banco
2.00 REVESTIMIENTO DE TALUD 44,905.58 44,905.58 - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 75.0% 100.0% 100.0% 100.0%

PROTECCIÓN DE TALUDES EN MALLA


ELECTROSOLDADA Y CONCRETO LANZADO
E=0,05 m. INCLUYE: TRASLAPOS DE LA
MALLA, ADITIVOS, SEPARADORES, TUBERÍA
2.1 m2 2,161.00 2,161.00 20.78 44,905.58 44,905.58 2,161.00 1,620.75 540.25 - - - - - - - - - - - - - - - 0.75 1.00 1.00 1.00
PVC Y DEMÁS ACTIVIDADES Y/O ACCESORIOS
NECESARIOS PARA LA CORRECTA
EJECUCIÓN. VER NOTAS 9 Y 10 EN HOJA 1 DE
PLANO N° PE-MAMO-00005-S-04-K4250

3.00 OBRAS DE CONTENCIÓN 222,536.42 222,536.42 - 0.0% 0.0% 0.0% 0.0% 22.1% 44.2% 68.8% 83.4% 88.2% 92.2% 98.6% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
3.1 CONSTRUCCIÓN MURO TIPO 1. INCLUYE: EXCAVA ml 5.00 5.00 453.25 2,266.25 2,266.25 5.00 5.00 - - - - - - - - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00
3.2 CONSTRUCCIÓN MURO TIPO 2. INCLUYE: EXCAVA ml 5.00 5.00 663.95 3,319.75 3,319.75 5.00 3.67 1.33 - - - - - - - - - - - 0.73 1.00 1.00 1.00 1.00 1.00 1.00 1.00
3.3 CONSTRUCCIÓN MURO TIPO 3. INCLUYE: EXCAVA ml 9.00 9.00 1,862.04 16,758.36 16,758.36 9.00 2.67 6.33 - - - - - - - - - - 0.30 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
3.4 CONSTRUCCIÓN MURO TIPO 4. INCLUYE: EXCAVA ml 6.00 6.00 1,699.55 10,197.30 10,197.30 6.00 3.67 2.33 - - - - - - - - - 0.61 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
3.5 CONSTRUCCIÓN MURO TIPO 5. INCLUYE: EXCAVA ml 25.00 25.00 5,906.01 147,650.25 147,650.25 25.00 8.33 8.33 8.33 - - - - - 0.33 0.67 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
3.6 CONSTRUCCIÓN MURO TIPO 6. INCLUYE: EXCAVA ml 13.00 13.00 3,257.27 42,344.51 42,344.51 13.00 1.67 10.00 1.33 - - - - - - - 0.13 0.90 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
VÍA DE ACCESO (VER PLANO PE-MAMO-00005-S-04-K4251) 0.00 -
4.00 MOVIMIENTOS DE TIERRA 35,227.10 65,931.07 - 0.0% 0.0% 29.1% 29.1% 29.1% 29.1% 29.1% 29.1% 29.1% 29.1% 29.1% 40.4% 71.7% 86.2% 97.3% 100.0% 100.0% 100.0%
4.1 DESBROCE Ó DESCAPOTE E=0,30 m. INCLUYE: m3 1,597.00 2,752.90 3.58 5,717.26 9,855.38 2,752.90 825.87 1,927.03 - - - 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 1.00 1.00 1.00 1.00 1.00 1.00 1.00
4.2 EXPLANACIÓN EN CORTE EN MATERIAL COMÚN. m3 5,140.00 6,118.69 4.74 24,363.60 29,002.59 6,118.69 2,141.54 2,769.23 1,207.92 - - - 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.80 1.00 1.00 1.00 1.00 1.00
4.3 EXPLANACIÓN EN LLENO CON MATERIAL DE EXC m3 544.00 2,861.85 9.46 5,146.24 27,073.10 2,861.85 167.63 2,160.00 534.22 - - - - - - - - - - - - - - 0.06 0.81 1.00 1.00 1.00
5.00 REVESTIMIENTO DE TALUD 38,546.90 38,546.90 - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 48.5% 100.0% 100.0%
5.1 PROTECCIÓN DE TALUDES EN MALLA ELECTROSO m2 1,855.00 1,855.00 20.78 38,546.90 38,546.90 1,855.00 900.00 955.00 - - - - - - - - - - - - - - - - 0.49 1.00 1.00
6.00 CONSTRUCCIÓN VÍA 96,793.51 96,793.51 - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 7.7% 18.7% 74.7% 97.2% 100.0%
6.1 MATERIAL DE BASE GRANULAR E=0,15 m. m3 787.00 787.00 21.40 16,841.80 16,841.80 787.00 787.00 - - - - - - - - - - - - - - - - 1.00 1.00 1.00
6.2 MATERIAL DE SUB-BASE GRANULAR E=0,20 m. m3 1,048.00 1,048.00 21.40 22,427.20 22,427.20 1,048.00 838.78 209.22 - - - - - - - - - - - - - - - - 0.80 1.00 1.00
6.3 CUNETA TIPO 1 EN VÍA. m 1,414.00 1,414.00 24.48 34,614.72 34,614.72 1,414.00 652.62 652.62 108.77 - - - - - - - - - - - - - - - - 0.46 0.92 1.00
6.4 POCETAS. un 15.00 15.00 195.26 2,928.90 2,928.90 15.00 15.00 - - - - - - - - - - - - - - - 1.00 1.00 1.00 1.00
6.5 TUBERÍA DE CONCRETO Ø 10". m 167.00 167.00 89.05 14,871.35 14,871.35 167.00 83.50 83.50 - - - - - - - - - - - - - - 0.50 1.00 1.00 1.00 1.00
6.6 ENROCADO DE PROTECCIÓN. m3 7.00 7.00 138.42 968.94 968.94 7.00 2.00 5.00 - - - - - - - - - - - - - - - 0.29 1.00 1.00 1.00
6.7 CONCRETO f'c 21 MPa DESCARGA DE TUBERÍA. m3 4.80 4.80 146.75 704.40 704.40 4.80 4.80 - - - - - - - - - - - - - - - - 1.00 1.00 1.00
6.8 CONCRETO f'c 21 MPa ATRAQUE DE TUBERÍA. m3 14.30 14.30 146.75 2,098.53 2,098.53 14.30 14.30 - - - - - - - - - - - - - - - - 1.00 1.00 1.00
6.9 ARENILLA PARA COLECTOR. m3 9.70 9.70 34.55 335.14 335.14 9.70 9.70 - - - - - - - - - - - - - - - - - 1.00 1.00
6.10 LLENO CON MATERIAL COMPACTADO PARA COL m3 77.00 77.00 13.02 1,002.54 1,002.54 77.00 77.00 - - - - - - - - - - - - - - - - - 1.00 1.00
7.00 CANALES ESCALONADOS Y CABEZOTES 8,782.36 8,782.36 - 0.0% 0.0% 0.0% 0.0% 5.5% 35.4% 58.6% 93.9% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
7.1 CANAL ESCALONADO 1. INCLUYE: EXCAVACIÓN, un 1.00 1.00 2,141.12 2,141.12 2,141.12 1.00 1.00 - - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
7.2 CANAL ESCALONADO 2. INCLUYE: EXCAVACIÓN, un 1.00 1.00 4,063.26 4,063.26 4,063.26 1.00 0.50 0.50 - - - - - - - 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
7.3 CONSTRUCCIÓN CABEZOTES. INCLUYE ENROC un 3.00 3.00 535.66 1,606.98 1,606.98 3.00 2.00 1.00 - - - - - - - - 0.67 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
7.4 DESVIO Y CONFORMACIÓN DE CANALES EN TIE ml 50.00 50.00 19.42 971.00 971.00 50.00 25.00 25.00 - - - - - 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
8.00 OBRAS DE CONTENCIÓN 37,944.15 37,944.15 - 0.0% 0.0% 0.0% 0.0% 26.4% 46.4% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
8.1 CONSTRUCCIÓN MURO TIPO 1. INCLUYE: EXCAV ml 6.80 6.80 579.69 3,941.89 3,941.89 6.80 6.80 - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
8.2 CONSTRUCCIÓN MURO TIPO 2. INCLUYE: EXCAV ml 15.00 15.00 1,896.52 28,447.80 28,447.80 15.00 3.20 4.00 7.80 - - - - - 0.21 0.48 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
8.3 CONSTRUCCIÓN MURO TIPO 3. INCLUYE: EXCA ml 7.60 7.60 730.85 5,554.46 5,554.46 7.60 7.60 - - - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.00 BADÉN 72,377.42 72,377.42 - 0.0% 0.0% 0.0% 0.0% 16.7% 44.7% 69.2% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
9.1 CONFORMACIÓN DEL CAUCE DEL RÍO. m2 800.00 800.00 0.60 480.00 480.00 800.00 800.00 - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.2 TRANSICIÓN ANCHO TROCHA EXISTENTE. gl 1.00 1.00 3,050.35 3,050.35 3,050.35 1.00 1.00 - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.3 EXCAVACIONES. m3 280.00 280.00 1.84 515.20 515.20 280.00 280.00 - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.4 CONCRETO f'c=35 MPa. m3 185.00 185.00 171.53 31,733.05 31,733.05 185.00 15.00 20.00 20.00 130.00 - - - - - 0.08 0.19 0.30 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.5 CONCRETO CICLÓPEO f'c=21 MPa. m3 95.00 95.00 127.60 12,122.00 12,122.00 95.00 25.00 45.00 25.00 - - - - - 0.26 0.74 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.6 ACERO DE REFUERZO. INCLUYE PASADORES EN kg 12,420.00 12,420.00 1.78 22,107.60 22,107.60 12,420.00 6,210.00 6,210.00 - - - - - - 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.7 PINTURA DE TRÁFICO COLOR BLANCO (TTP-115F m2 10.00 10.00 2.94 29.40 29.40 10.00 10.00 - - - - - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.8 CAMA DE PIEDRA REDONDEADA DE Ø10,0m A Ø2 m3 66.00 66.00 33.27 2,195.82 2,195.82 66.00 66.00 - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.9 PASA LOSA EN TUBERÍA PVC Ø2". ml 120.00 120.00 1.20 144.00 144.00 120.00 50.00 50.00 20.00 - - - - - 0.42 0.83 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
10.00 MUROS EN GAVIONES 30,301.60 30,301.60 - 0.0% 0.0% 0.0% 0.0% 0.0% 14.6% 30.1% 89.5% 89.7% 93.1% 96.6% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
10.1 CONSTRUCCIÓN MUROS EN GAVIONES, INCLUYE: m3 300.00 300.00 88.58 26,574.00 26,574.00 300.00 50.00 50.00 200.00 - - - - - - 0.17 0.33 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
10.2 RELLENO ESPALDAR, CONSISTE EN RELLENAR E m3 250.00 250.00 13.04 3,260.00 3,260.00 250.00 5.00 5.00 80.00 80.00 80.00 - - - - - - - - 0.02 0.04 0.36 0.68 1.00 1.00 1.00 1.00 1.00 1.00 1.00
10.3 GEOTEXTIL NT 1600 O EQUIVALENTE. m2 280.00 280.00 1.67 467.60 467.60 280.00 150.00 130.00 - - - - - - - 0.54 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
11.00 CERRAMIENTO 449,378.00 306,634.40 - 0.0% 0.0% 0.0% 0.0% 0.0% 5.8% 12.3% 21.0% 29.7% 38.4% 47.1% 55.8% 64.5% 73.2% 81.9% 90.6% 100.0% 100.0%
11.1 CONSTRUCCIÓN CERRAMIENTO PERIMETRAL. EL ml 1,700.00 1,160.00 264.34 449,378.00 306,634.40 1,160.00 67.25 75.98 100.87 100.87 100.87 100.87 100.87 100.87 100.87 100.87 100.87 108.94 - - - - - - 0.06 0.12 0.21 0.30 0.38 0.47 0.56 0.65 0.73 0.82 0.91 1.00 1.00
12.00 OTROS 4,738.80 4,738.80 - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
12.10 CUNETA DE CORONACION, INCLUYE EXCAVACI ml 330.00 330.00 14.36 4,738.80 4,738.80 330.00 330.00 - - - - - - - - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00
-

2,411,606.84 1,817,632.85
2,411,606.84
2,411,606.84
-
1,817,632.85 - - 13,107.52 85,680.00 190,678.63 195,463.16 227,110.41 204,977.51 140,209.63 138,978.92 111,029.09 62,929.74 82,977.37 84,067.49 91,418.06 115,908.72 70,433.92 2,662.67
GG 535,930.74 22.22% 2,547,450.97 31,262.63 31,262.63 45,768.33 126,082.14 242,281.00 247,575.89 282,598.96 258,105.14 186,428.46 185,066.46 154,135.22 100,905.10 123,091.22 124,297.62 132,432.28 159,535.36 109,209.76 7,412.79
Utilidad 257,246.75 10.67% 2,547,450.97 865,532.09 796,588.75 565,028.14 320,301.99
-

2,547,450.97 2,547,450.97 320,478.48 778,978.88 716,929.87 508,525.33 222,538.41


- -

-65,733.38
OBRA: ADECUACIÓN DE TERRENO S.E. YARABAMBA 500kV/200kV
CLIENTE: PROYECTOS DE INFRAESTRUCTURA DEL PERÚ SAC
CRONOGRAMA DE EJECUCIÓN
NOVIEMBRE ´15 DICIEMBRE ´15 ENERO ´16 FEBRERO ´16 MARZO ´14 NOVIEMBRE ´15 DICIEMBRE ´15 ENERO ´16 FEBRERO ´16 MARZO ´14
Sem 01 Sem 02 Sem 03 Sem 04 Sem 05 Sem 06 Sem 07 Sem 08 Sem 09 Sem 10 Sem 11 Sem 12 Sem 13 Sem 14 Sem 15 Sem 16 Sem 17 Sem 18 Sem 19 Sem 01 Sem 02 Sem 03 Sem 04 Sem 05 Sem 06 Sem 07 Sem 08 Sem 09 Sem 10 Sem 11 Sem 12 Sem 13 Sem 14 Sem 15 Sem 16 Sem 17 Sem 18
METRADOS
ITEM DESCRIPCIÓN UND Del 16.Nov Del 23.Nov Del 30.Nov Del 07.Dec Del 14.Dec Del 21.Dec Del 28.Dec Del 04.Jan Del 11.Jan Del 18.Jan Del 25.Jan Del 01.Feb Del 08.Feb Del 15.Feb Del 22.Feb Del 29.Feb Del 07.Mar Del 14.Mar Del 21.Mar VARIACION Del 16.Nov Del 23.Nov Del 30.Nov Del 07.Dec Del 14.Dec Del 21.Dec Del 28.Dec Del 04.Jan Del 11.Jan Del 18.Jan Del 25.Jan Del 01.Feb Del 08.Feb Del 15.Feb Del 22.Feb Del 29.Feb Del 07.Mar Del 14.Mar
REALES
Al 22.Nov Al 29.Nov Al 06.Dec Al 13.Dec Al 20.Dec Al 27.Dec Al 03.Jan Al 10.Jan Al 17.Jan Al 24.Jan Al 31.Jan Al 07.Feb Al 14.Feb Al 21.Feb Al 28.Feb Al 06.Mar Al 13.Mar Al 20.Mar Al 27.Mar Al 22.Nov Al 29.Nov Al 06.Dec Al 13.Dec Al 20.Dec Al 27.Dec Al 03.Jan Al 10.Jan Al 17.Jan Al 24.Jan Al 31.Jan Al 07.Feb Al 14.Feb Al 21.Feb Al 28.Feb Al 06.Mar Al 13.Mar Al 20.Mar
ADECUACIÓN DEL TERRENO (VER PLANO PE-
MAMO-00005-S-04-K4250)
1.00 MOVIMIENTOS DE TIERRA 0.0% 0.0% 0.0% 4.7% 24.7% 43.0% 54.5% 64.8% 71.6% 75.6% 82.5% 86.8% 94.4% 100.4% 102.4% 103.4% 103.4% 103.4%
DESBROCE Ó DESCAPOTE H=0,30 m. INCLUYE:
1.1 m3 15,427.85 15,427.85 2,790.24 3,919.44 808.10 838.41 4,087.92 1,297.44 914.92 367.00 404.39 0.00 - - - 0.18 0.43 0.49 0.54 0.81 0.89 0.95 0.97 1.00 1.00 1.00 1.00 1.00 1.00 1.00
CARGUE, RETIRO Y LIMPIEZA.
EXPLANACIÓN EN CORTE EN MATERIAL COMÚN.
1.2 m3 112,506.04 112,506.04 5,491.52 14,973.97 7,767.10 10,969.79 16,955.00 17,725.92 5,850.67 8,224.70 5,446.15 5,446.15 5,446.15 5,446.15 2,762.75 0.00 - - - 0.05 0.18 0.25 0.35 0.50 0.66 0.71 0.78 0.83 0.88 0.93 0.98 1.00 1.00 1.00
MEDIDO EN BANCO.
EXPLANACIÓN EN LLENO CON MATERIAL DE
1.3 EXCAVACIÓN. MEDIDO EN BANCO EN SU m3 13,215.92 13,215.92 3,000.00 4,302.00 4,000.00 1,913.92 - - - - - - - - - - 0.23 0.55 0.86 1.00 1.00 1.00 1.00 1.00 1.00
POSICIÓN FINAL.
EXPLANACIÓN EN CORTE EN ROCA. MEDIDO EN 342.54 2,353.11 2,652.97 1,275.64
1.4 BANCO
m3 6,815.00 7,402.00 527.74 250.00 -587.00 - - - 0.05 0.40 0.78 0.97 1.05 1.05 1.05 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09
EXPLANACIÓN EN LLENO CON MATERIAL DE
1.5 PRÉSTAMO. MEDIDO EN BANCO
m3 3,896.45 3,896.45 2,086.08 1,810.37 - - - - - - - - - - - - - 0.54 1.00 1.00 1.00 1.00 1.00
2.00 REVESTIMIENTO DE TALUD - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 25.0% 50.0% 75.0% 100.0% 100.0%
PROTECCIÓN DE TALUDES EN MALLA
ELECTROSOLDADA Y CONCRETO LANZADO
E=0,05 m. INCLUYE: TRASLAPOS DE LA MALLA,
ADITIVOS, SEPARADORES, TUBERÍA PVC Y
2.1 DEMÁS ACTIVIDADES Y/O ACCESORIOS
m2 2,161.00 2,161.00 540.25 540.25 540.25 540.25 - - - - - - - - - - - - - - 0.25 0.50 0.75 1.00 1.00
NECESARIOS PARA LA CORRECTA EJECUCIÓN.
VER NOTAS 9 Y 10 EN HOJA 1 DE PLANO N° PE-
MAMO-00005-S-04-K4250

3.00 OBRAS DE CONTENCIÓN - 0.0% 0.0% 0.0% 5.0% 10.4% 48.7% 63.8% 64.3% 78.2% 86.3% 98.4% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
3.1 CONSTRUCCIÓN MURO TIPO 1. INCLUYE: EXCAVACI ml 5.00 5.00 0.25 - 0.25 3.50 0.75 - - 0.25 - - - - 0.05 0.05 0.10 0.80 0.95 0.95 0.95 0.95 1.00 1.00 1.00 1.00 1.00 1.00 1.00 95% 4.75 4.75 0.00
3.2 CONSTRUCCIÓN MURO TIPO 2. INCLUYE: EXCAVACI ml 5.00 5.00 0.25 - 0.25 2.25 - 2.00 - 0.25 - - - - 0.05 0.05 0.10 0.55 0.55 0.95 0.95 0.95 1.00 1.00 1.00 1.00 1.00 1.00 1.00 95% 4.75 4.75 0.00
3.3 CONSTRUCCIÓN MURO TIPO 3. INCLUYE: EXCAVACI ml 9.00 9.00 0.45 - 0.45 4.05 - - - 3.80 0.25 - - - - 0.05 0.05 0.10 0.55 0.55 0.55 0.55 0.97 1.00 1.00 1.00 1.00 1.00 1.00 1.00 55% 4.95 4.95 0.00
3.4 CONSTRUCCIÓN MURO TIPO 4. INCLUYE: EXCAVACI ml 6.00 6.00 0.30 0.36 0.30 2.34 - - - 2.45 0.25 - - - - 0.05 0.11 0.16 0.55 0.55 0.55 0.55 0.96 1.00 1.00 1.00 1.00 1.00 1.00 1.00 55% 3.30 3.30 0.00
3.5 CONSTRUCCIÓN MURO TIPO 5. INCLUYE: EXCAVACI ml 25.00 25.00 1.25 1.50 11.00 2.50 - 5.00 2.50 1.00 0.25 - - - - 0.05 0.11 0.55 0.65 0.65 0.85 0.95 0.99 1.00 1.00 1.00 1.00 1.00 1.00 1.00 95% 23.75 23.75 0.00
3.6 CONSTRUCCIÓN MURO TIPO 6. INCLUYE: EXCAVACI ml 13.00 13.00 0.65 0.78 5.72 1.30 0.26 - 1.04 3.00 0.25 - - - - 0.05 0.11 0.55 0.65 0.67 0.67 0.75 0.98 1.00 1.00 1.00 1.00 1.00 1.00 1.00 75% 9.75 9.75 0.00
VÍA DE ACCESO (VER PLANO PE-MAMO-00005-S-04-K4251) -
4.00 MOVIMIENTOS DE TIERRA - 0.0% 0.0% 29.1% 29.1% 29.1% 29.1% 29.1% 29.1% 29.1% 29.1% 29.1% 35.0% 71.7% 85.4% 97.9% 100.0% 100.0% 100.0%
4.1 DESBROCE Ó DESCAPOTE E=0,30 m. INCLUYE: CA m3 2,752.90 2,752.90 825.87 1000.00 927.03 - - - 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.66 1.00 1.00 1.00 1.00 1.00 1.00
4.2 EXPLANACIÓN EN CORTE EN MATERIAL COMÚN. m3 6,118.69 6,118.69 2,141.54 2769.23 1207.92 - - - 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.80 1.00 1.00 1.00 1.00 1.00
4.3 EXPLANACIÓN EN LLENO CON MATERIAL DE EXCAV m3 2,861.85 2,861.85 2448.00 413.85 - - - - - - - - - - - - - - - 0.86 1.00 1.00 1.00
5.00 REVESTIMIENTO DE TALUD - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 48.5% 100.0% 100.0%
5.1 PROTECCIÓN DE TALUDES EN MALLA ELECTROSOLDm2 1,855.00 1,855.00 900.00 955.00 - - - - - - - - - - - - - - - - 0.49 1.00 1.00
6.00 CONSTRUCCIÓN VÍA - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 8.1% 0.0% 8.1% 11.0% 12.5% 74.7% 95.9% 100.0%
6.1 MATERIAL DE BASE GRANULAR E=0,15 m. m3 787.00 787.00 787.00 - - - - - - - - - - - - - - - - 1.00 1.00 1.00
6.2 MATERIAL DE SUB-BASE GRANULAR E=0,20 m. m3 1,048.00 1,048.00 838.78 209.22 - - - - - - - - - - - - - - - - 0.80 1.00 1.00
6.3 CUNETA TIPO 1 EN VÍA. m 1,414.00 1,414.00 652.62 652.62 108.77 - - - - - - - - - - - - - - - - 0.46 0.92 1.00
6.4 POCETAS. un 15.00 15.00 4.50 10.50 - - - - - - - - - - - 0.30 - 0.30 0.30 0.30 1.00 1.00 1.00
6.5 TUBERÍA DE CONCRETO Ø 10". m 167.00 167.00 66.80 16.70 83.50 - - - - - - - - - - - 0.40 - 0.40 0.40 0.50 1.00 1.00 1.00
6.6 ENROCADO DE PROTECCIÓN. m3 7.00 7.00 7.00 - - - - - - - - - - - 1.00 - 1.00 1.00 1.00 1.00 1.00 1.00
6.7 CONCRETO f'c 21 MPa DESCARGA DE TUBERÍA. m3 4.80 4.80 4.80 - - - - - - - - - - - - - - 1.00 1.00 1.00 1.00 1.00
6.8 CONCRETO f'c 21 MPa ATRAQUE DE TUBERÍA. m3 14.30 14.30 14.30 - - - - - - - - - - - - - - 1.00 1.00 1.00 1.00 1.00
6.9 ARENILLA PARA COLECTOR. m3 9.70 9.70 9.70 - - - - - - - - - - - - - - - - - - 1.00
6.10 LLENO CON MATERIAL COMPACTADO PARA COLEC m3 77.00 77.00 77.00 - - - - - - - - - - - - - - - - - - 1.00
7.00 CANALES ESCALONADOS Y CABEZOTES - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 5.5% 34.2% 69.5% 69.5% 75.6% 75.6% 75.6%
7.1 CANAL ESCALONADO 1. INCLUYE: EXCAVACIÓN, CO un 1.00 - 1.00 - - - - - - - - - - - - - - - - - -
7.2 CANAL ESCALONADO 2. INCLUYE: EXCAVACIÓN, CO un 1.00 1.00 0.50 0.50 - - - - - - - - - - - - - 0.50 1.00 1.00 1.00 1.00 1.00
7.3 CONSTRUCCIÓN CABEZOTES. INCLUYE ENROCAD un 3.00 3.00 2.00 1.00 - - - - - - - - - - - - - - 0.67 0.67 1.00 1.00 1.00
7.4 DESVIO Y CONFORMACIÓN DE CANALES EN TIERR ml 50.00 50.00 25.00 25.00 - - - - - - - - - - - - 0.50 1.00 1.00 1.00 1.00 1.00 1.00
8.00 OBRAS DE CONTENCIÓN - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 25.0% 53.8% 82.6% 82.6% 95.0% 100.0% 100.0%
8.1 CONSTRUCCIÓN MURO TIPO 1. INCLUYE: EXCAVAC ml 6.80 6.80 2.50 2.50 1.80 - - - - - - - - - - - - - 0.37 0.74 0.74 1.00 1.00 1.00
8.2 CONSTRUCCIÓN MURO TIPO 2. INCLUYE: EXCAVAC ml 15.00 15.00 5.00 5.00 5.00 - - - - - - - - - - - - 0.33 0.67 1.00 1.00 1.00 1.00 1.00
8.3 CONSTRUCCIÓN MURO TIPO 3. INCLUYE: EXCAVA ml 7.60 7.60 5.00 2.60 - - - - - - - - - - - - - - - - 0.66 1.00 1.00
9.00 BADÉN - 0.0% 0.0% 0.0% 7.6% 15.3% 15.3% 15.3% 15.3% 15.9% 19.4% 45.8% 91.1% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
9.1 CONFORMACIÓN DEL CAUCE DEL RÍO. m2 800.00 800.00 800.00 - - - - - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.2 TRANSICIÓN ANCHO TROCHA EXISTENTE. gl 1.00 1.00 1.00 - - - - - - - - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.3 EXCAVACIONES. m3 280.00 280.00 168.00 84.00 28.00 - - - - - - - - - - 0.60 0.90 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.4 CONCRETO f'c=35 MPa. m3 185.00 185.00 80.00 105.00 - - - - - - - - - - - 0.43 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.5 CONCRETO CICLÓPEO f'c=21 MPa. m3 95.00 95.00 0.00 45.00 50.00 - - - - - - - - - - - - 0.47 1.00 1.00 1.00 1.00 1.00 1.00
9.6 ACERO DE REFUERZO. INCLUYE PASADORES EN kg 12,420.00 12,420.00 3,105.00 3,105.00 869.40 2,236.00 3,104.60 - - - - 0.25 0.50 0.50 0.50 0.50 0.50 0.57 0.75 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.7 PINTURA DE TRÁFICO COLOR BLANCO (TTP-115F TI m2 10.00 10.00 10.00 - - - - - - - - - - - - - 1.00 1.00 1.00 1.00 1.00 1.00
9.8 CAMA DE PIEDRA REDONDEADA DE Ø10,0m A Ø20, m3 66.00 66.00 19.80 36.00 10.20 - - - - - - - - - - 0.30 0.85 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.9 PASA LOSA EN TUBERÍA PVC Ø2". ml 120.00 120.00 16.80 40.00 63.20 - - - - - - - - - - 0.14 0.47 1.00 1.00 1.00 1.00 1.00 1.00 1.00
10.00 MUROS EN GAVIONES - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 8.8% 13.2% 13.2% 13.2% 26.5% 97.6% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
10.1 CONSTRUCCIÓN MUROS EN GAVIONES, INCLUYE: E m3 300.00 300.00 30.00 15.00 45.00 210.00 - - - - - - - 0.10 0.15 0.15 0.15 0.30 1.00 1.00 1.00 1.00 1.00 1.00 1.00
10.2 RELLENO ESPALDAR, CONSISTE EN RELLENAR EL m3 250.00 250.00 0.00 200.00 50.00 - - - - - - - - - - - - 0.80 1.00 1.00 1.00 1.00 1.00 1.00
10.3 GEOTEXTIL NT 1600 O EQUIVALENTE. m2 280.00 280.00 28.00 200.00 52.00 - - - - - - - - - - - 0.10 0.81 1.00 1.00 1.00 1.00 1.00 1.00
11.00 CERRAMIENTO - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.3% 3.0% 7.0% 13.9% 26.8% 42.3% 59.6% 81.1% 100.0% 100.0%
11.1 CONSTRUCCIÓN CERRAMIENTO PERIMETRAL. EL P ml 1,160.00 1,160.00 4.00 31.00 46.00 80.00 150.00 180.00 200.00 250.00 219.00 - - - - - - - - - 0.00 0.03 0.07 0.14 0.27 0.42 0.60 0.81 1.00 1.00
12.00 OTROS - 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 5.0% 5.0% 5.0% 5.0% 50.5% 95.9% 100.0% 100.0% 100.0%
12.10 CUNETA DE CORONACION, INCLUYE EXCAVACION ml 330.00 330.00 16.50 0.00 150.00 150.00 13.50 - - - - - - - - - - 0.05 0.05 0.05 0.05 0.50 0.96 1.00 1.00 1.00
-
OBRA: ADECUACIÓN DE TERRENO S.E. YARABAMBA 500kV/200kV
CLIENTE: PROYECTOS DE INFRAESTRUCTURA DEL PERÚ SAC Del 16.Nov 119.00 Del 14.Mar
CRONOGRAMA DE EJECUCIÓN
NOVIEMBRE ´15 DICIEMBRE ´15 ENERO ´16 FEBRERO ´16 MARZO ´14 NOVIEMBRE ´15 DICIEMBRE ´15 ENERO ´16 FEBRERO ´16 MARZO ´14
Sem 01 Sem 02 Sem 03 Sem 04 Sem 05 Sem 06 Sem 07 Sem 08 Sem 09 Sem 10 Sem 11 Sem 12 Sem 13 Sem 14 Sem 15 Sem 16 Sem 17 Sem 18 Sem 01 Sem 02 Sem 03 Sem 04 Sem 05 Sem 06 Sem 07 Sem 08 Sem 09 Sem 10 Sem 11 Sem 12 Sem 13 Sem 14 Sem 15 Sem 16 Sem 17 Sem 18
METRADOS METRADOS PRESUPUEST METRADOS
ITEM DESCRIPCIÓN UND P.U. Del 16.Nov Del 23.Nov Del 30.Nov Del 07.Dec Del 14.Dec Del 21.Dec Del 28.Dec Del 04.Jan Del 11.Jan Del 18.Jan Del 25.Jan Del 01.Feb Del 08.Feb Del 15.Feb Del 22.Feb Del 29.Feb Del 07.Mar Del 14.Mar VARIACION Del 11.Nov Del 18.Nov Del 25.Nov Del 02.Dec Del 09.Dec Del 16.Dec Del 23.Dec Del 30.Dec Del 06.Jan Del 13.Jan Del 20.Jan Del 27.Jan Del 03.Feb Del 10.Feb Del 17.Feb Del 24.Feb Del 02.Mar Del 09.Mar
CONTRATO REALES O REAL
Al 22.Nov Al 29.Nov Al 06.Dec Al 13.Dec Al 20.Dec Al 27.Dec Al 03.Jan Al 10.Jan Al 17.Jan Al 24.Jan Al 31.Jan Al 07.Feb Al 14.Feb Al 21.Feb Al 28.Feb Al 06.Mar Al 13.Mar Al 20.Mar Al 17.Nov Al 24.Nov Al 01.Dec Al 08.Dec Al 15.Dec Al 22.Dec Al 29.Dec Al 05.Jan Al 12.Jan Al 19.Jan Al 26.Jan Al 02.Feb Al 09.Feb Al 16.Feb Al 23.Feb Al 01.Mar Al 08.Mar Al 15.Mar
ADECUACIÓN DEL TERRENO (VER PLANO PE-
MAMO-00005-S-04-K4250) -
1.00 MOVIMIENTOS DE TIERRA 1,370,075.00 888,140.63 - - - 0.05 0.25 0.43 0.55 0.65 0.72 0.76 0.82 0.82 0.82 0.82 0.82 0.82 0.82 0.82
DESBROCE Ó DESCAPOTE H=0,30 m.
1.1 INCLUYE: CARGUE, RETIRO Y LIMPIEZA.
m3 16,200.00 15,427.85 3.58 57,996.00 55,231.70 15,023.46 2,790.24 3,919.44 808.10 838.41 4,087.92 1,297.44 914.92 367.00 -404.39 - - - 0.18 0.43 0.49 0.54 0.81 0.89 0.95 0.97 0.97 0.97 0.97 0.97 0.97 0.97 0.97
EXPLANACIÓN EN CORTE EN MATERIAL
1.2 COMÚN. MEDIDO EN BANCO. m3 118,100.00 112,506.04 4.74 559,794.00 533,278.63 87,958.67 5,491.52 14,973.97 7,767.10 10,969.79 16,955.00 17,725.92 5,850.67 8,224.70 -24,547.37 - - - 0.05 0.18 0.25 0.35 0.50 0.66 0.71 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78
EXPLANACIÓN EN LLENO CON MATERIAL DE
1.3 EXCAVACIÓN. MEDIDO EN BANCO EN SU m3 10,500.00 13,215.92 9.46 99,330.00 125,022.60 7,302.00 3,000.00 4,302.00 -5,913.92 - - - - - - - - - 0.23 0.55 0.55 0.55 0.55 0.55 0.55 0.55 0.55
POSICIÓN FINAL.

1.4
EXPLANACIÓN EN CORTE EN ROCA. MEDIDO
m3 40,000.00 6,815.00 13.38 535,200.00 91,184.70 7,402.00 342.54 2,353.11 2,652.97 1,275.64 527.74 250.00 587.00 - - - 0.05 0.40 0.78 0.97 1.05 1.05 1.05 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09
EN BANCO
EXPLANACIÓN EN LLENO CON MATERIAL DE
1.5 m3 5,500.00 3,896.45 21.41 117,755.00 83,422.99 - -3,896.45 - - - - - - - - - - - - - - - - - -
PRÉSTAMO. MEDIDO EN BANCO
2.00 REVESTIMIENTO DE TALUD 44,905.58 44,905.58 - - - - - - - - - - - - - - - - - - -

PROTECCIÓN DE TALUDES EN MALLA


ELECTROSOLDADA Y CONCRETO LANZADO
E=0,05 m. INCLUYE: TRASLAPOS DE LA
MALLA, ADITIVOS, SEPARADORES, TUBERÍA
2.1 PVC Y DEMÁS ACTIVIDADES Y/O ACCESORIOS
m2 2,161.00 2,161.00 20.78 44,905.58 44,905.58 - -2,161.00 - - - - - - - - - - - - - - - - - -
NECESARIOS PARA LA CORRECTA
EJECUCIÓN. VER NOTAS 9 Y 10 EN HOJA 1 DE
PLANO N° PE-MAMO-00005-S-04-K4250

3.00 OBRAS DE CONTENCIÓN 222,536.42 222,536.42 - - - - 0.05 0.10 0.49 0.64 0.64 0.78 0.86 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
3.1 CONSTRUCCIÓN MURO TIPO 1. INCLUYE: EXCAV ml 5.00 5.00 453.25 2,266.25 2,266.25 4.75 0.25 - 0.25 3.50 0.75 - - -0.25 - - - 0.05 0.05 0.10 0.80 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95
3.2 CONSTRUCCIÓN MURO TIPO 2. INCLUYE: EXCAV ml 5.00 5.00 663.95 3,319.75 3,319.75 4.75 0.25 - 0.25 2.25 - 2.00 - -0.25 - - - 0.05 0.05 0.10 0.55 0.55 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95
3.3 CONSTRUCCIÓN MURO TIPO 3. INCLUYE: EXCAV ml 9.00 9.00 1,862.04 16,758.36 16,758.36 8.75 0.45 - 0.45 4.05 - - - 3.80 -0.25 - - - 0.05 0.05 0.10 0.55 0.55 0.55 0.55 0.97 0.97 0.97 0.97 0.97 0.97 0.97 0.97
3.4 CONSTRUCCIÓN MURO TIPO 4. INCLUYE: EXCAV ml 6.00 6.00 1,699.55 10,197.30 10,197.30 5.75 0.30 0.36 0.30 2.34 - - - 2.45 -0.25 - - - 0.05 0.11 0.16 0.55 0.55 0.55 0.55 0.96 0.96 0.96 0.96 0.96 0.96 0.96 0.96
3.5 CONSTRUCCIÓN MURO TIPO 5. INCLUYE: EXCAV ml 25.00 25.00 5,906.01 147,650.25 147,650.25 24.75 1.25 1.50 11.00 2.50 - 5.00 2.50 1.00 -0.25 - - - 0.05 0.11 0.55 0.65 0.65 0.85 0.95 0.99 0.99 0.99 0.99 0.99 0.99 0.99 0.99
3.6 CONSTRUCCIÓN MURO TIPO 6. INCLUYE: EXCAV ml 13.00 13.00 3,257.27 42,344.51 42,344.51 12.75 0.65 0.78 5.72 1.30 0.26 - 1.04 3.00 -0.25 - - - 0.05 0.11 0.55 0.65 0.67 0.67 0.75 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98
VÍA DE ACCESO (VER PLANO PE-MAMO-00005-S-04-K4251) 0.00 -
4.00 MOVIMIENTOS DE TIERRA 35,227.10 65,836.47 - - - 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29
4.1 DESBROCE Ó DESCAPOTE E=0,30 m. INCLUYE: m3 1,597.00 2,752.90 3.58 5,717.26 9,855.38 825.87 825.87 -1,927.03 - - 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30
4.2 EXPLANACIÓN EN CORTE EN MATERIAL COMÚN m3 5,140.00 6,118.69 4.74 24,363.60 29,002.59 2,141.54 2,141.54 -3,977.15 - - 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35
4.3 EXPLANACIÓN EN LLENO CON MATERIAL DE EX m3 544.00 2,851.85 9.46 5,146.24 26,978.50 - -2,851.85 - - - - - - - - - - - - - - - - - -
5.00 REVESTIMIENTO DE TALUD 38,546.90 38,546.90 - - - - - - - - - - - - - - - - - - -
5.1 m2
PROTECCIÓN DE TALUDES EN MALLA ELECTROSO 1,855.00 1,855.00 20.78 38,546.90 38,546.90 - -1,855.00 - - - - - - - - - - - - - - - - - -
6.00 CONSTRUCCIÓN VÍA 96,793.51 96,793.51 - - - - - - - - - - - - - - - - - - -
6.1 MATERIAL DE BASE GRANULAR E=0,15 m. m3 787.00 787.00 21.40 16,841.80 16,841.80 - -787.00 - - - - - - - - - - - - - - - - - -
6.2 MATERIAL DE SUB-BASE GRANULAR E=0,20 m. m3 1,048.00 1,048.00 21.40 22,427.20 22,427.20 - -1,048.00 - - - - - - - - - - - - - - - - - -
6.3 CUNETA TIPO 1 EN VÍA. m 1,414.00 1,414.00 24.48 34,614.72 34,614.72 - -1,414.00 - - - - - - - - - - - - - - - - - -
6.4 POCETAS. un 15.00 15.00 195.26 2,928.90 2,928.90 - -15.00 - - - - - - - - - - - - - - - - - -
6.5 TUBERÍA DE CONCRETO Ø 10". m 167.00 167.00 89.05 14,871.35 14,871.35 - -167.00 - - - - - - - - - - - - - - - - - -
6.6 ENROCADO DE PROTECCIÓN. m3 7.00 7.00 138.42 968.94 968.94 - -7.00 - - - - - - - - - - - - - - - - - -
6.7 CONCRETO f'c 21 MPa DESCARGA DE TUBERÍA. m3 4.80 4.80 146.75 704.40 704.40 - -4.80 - - - - - - - - - - - - - - - - - -
6.8 CONCRETO f'c 21 MPa ATRAQUE DE TUBERÍA. m3 14.30 14.30 146.75 2,098.53 2,098.53 - -14.30 - - - - - - - - - - - - - - - - - -
6.9 ARENILLA PARA COLECTOR. m3 9.70 9.70 34.55 335.14 335.14 - -9.70 - - - - - - - - - - - - - - - - - -
6.10 LLENO CON MATERIAL COMPACTADO PARA CO m3 77.00 77.00 13.02 1,002.54 1,002.54 - -77.00 - - - - - - - - - - - - - - - - - -
7.00 CANALES ESCALONADOS Y CABEZOTES 8,782.36 8,782.36 - - - - - - - - - - - - - - - - - - -
7.1 CANAL ESCALONADO 1. INCLUYE: EXCAVACIÓN, un 1.00 1.00 2,141.12 2,141.12 2,141.12 - -1.00 - - - - - - - - - - - - - - - - - -
7.2 CANAL ESCALONADO 2. INCLUYE: EXCAVACIÓN, un 1.00 1.00 4,063.26 4,063.26 4,063.26 - -1.00 - - - - - - - - - - - - - - - - - -
7.3 CONSTRUCCIÓN CABEZOTES. INCLUYE ENRO un 3.00 3.00 535.66 1,606.98 1,606.98 - -3.00 - - - - - - - - - - - - - - - - - -
7.4 DESVIO Y CONFORMACIÓN DE CANALES EN TI ml 50.00 50.00 19.42 971.00 971.00 - -50.00 - - - - - - - - - - - - - - - - - -
8.00 OBRAS DE CONTENCIÓN 37,944.15 37,944.15 - - - - - - - - - - - - - - - - - - -
8.1 CONSTRUCCIÓN MURO TIPO 1. INCLUYE: EXCAV ml 6.80 6.80 579.69 3,941.89 3,941.89 - -6.80 - - - - - - - - - - - - - - - - - -
8.2 CONSTRUCCIÓN MURO TIPO 2. INCLUYE: EXCAV ml 15.00 15.00 1,896.52 28,447.80 28,447.80 - -15.00 - - - - - - - - - - - - - - - - - -
8.3 CONSTRUCCIÓN MURO TIPO 3. INCLUYE: EXCA ml 7.60 7.60 730.85 5,554.46 5,554.46 - -7.60 - - - - - - - - - - - - - - - - - -
9.00 BADÉN 72,377.42 72,377.42 - - - - 0.08 0.15 0.15 0.15 0.15 0.16 0.19 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46
9.1 CONFORMACIÓN DEL CAUCE DEL RÍO. m2 800.00 800.00 0.60 480.00 480.00 800.00 800.00 - - - - - - - - - 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
9.2 TRANSICIÓN ANCHO TROCHA EXISTENTE. gl 1.00 1.00 3,050.35 3,050.35 3,050.35 - -1.00 - - - - - - - - - - - - - - - - - -
9.3 EXCAVACIONES. m3 280.00 280.00 1.84 515.20 515.20 252.00 168.00 84.00 -28.00 - - - - - - - - - 0.60 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90
9.4 CONCRETO f'c=35 MPa. m3 185.00 185.00 171.53 31,733.05 31,733.05 80.00 80.00 -105.00 - - - - - - - - - - 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43
9.5 CONCRETO CICLÓPEO f'c=21 MPa. m3 95.00 95.00 127.60 12,122.00 12,122.00 - - -95.00 - - - - - - - - - - - - - - - - - -
9.6 ACERO DE REFUERZO. INCLUYE PASADORES E kg 12,420.00 12,420.00 1.78 22,107.60 22,107.60 9,315.40 3,105.00 3,105.00 869.40 2,236.00 -3,104.60 - - - 0.25 0.50 0.50 0.50 0.50 0.50 0.57 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
9.7 PINTURA DE TRÁFICO COLOR BLANCO (TTP-115F m2 10.00 10.00 2.94 29.40 29.40 - -10.00 - - - - - - - - - - - - - - - - - -
9.8 CAMA DE PIEDRA REDONDEADA DE Ø10,0m A Ø m3 66.00 66.00 33.27 2,195.82 2,195.82 55.80 19.80 36.00 -10.20 - - - - - - - - - 0.30 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85
9.9 PASA LOSA EN TUBERÍA PVC Ø2". ml 120.00 120.00 1.20 144.00 144.00 56.80 16.80 40.00 -63.20 - - - - - - - - - 0.14 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47
10.00 MUROS EN GAVIONES 30,301.60 30,301.60 - - - - - - - 0.09 0.13 0.13 0.13 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26
10.1 m3
CONSTRUCCIÓN MUROS EN GAVIONES, INCLUYE: 300.00 300.00 88.58 26,574.00 26,574.00 90.00 30.00 15.00 45.00 -210.00 - - - - - - 0.10 0.15 0.15 0.15 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30
10.2 RELLENO ESPALDAR, CONSISTE EN RELLENAR Em3 250.00 250.00 13.04 3,260.00 3,260.00 - - -250.00 - - - - - - - - - - - - - - - - - -
10.3 GEOTEXTIL NT 1600 O EQUIVALENTE. m2 280.00 280.00 1.67 467.60 467.60 28.00 28.00 -252.00 - - - - - - - - - - 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
11.00 CERRAMIENTO 449,378.00 306,634.40 - - - - - - - - - 0.00 0.03 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
11.1 CONSTRUCCIÓN CERRAMIENTO PERIMETRAL. ELml 1,700.00 1,160.00 264.34 449,378.00 306,634.40 81.00 4.00 31.00 46.00 -1,079.00 - - - - - - - - 0.00 0.03 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
12.00 OTROS 4,738.80 4,738.80 - - - - - - - - - - 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
12.10 CUNETA DE CORONACION, INCLUYE EXCAVACI ml 330.00 330.00 14.36 4,738.80 4,738.80 16.50 16.50 - -313.50 - - - - - - - - - 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
-