Académique Documents
Professionnel Documents
Culture Documents
SEQUENCE (PDD)
INTRODUCTION
There are several reasons which lead to delay in project completion, out of all, one main
reason is delay in deliverable processing i.e., submission & review documents. Most of the
project cycles start with a list of deliverables but without a sequence of submission of the
same, means without a direction to move, leading to overlapping of activities and more
interdependences.
Submittals are documents that must accompany items being sent, such as sample materials,
plans, drawings, documents etc. Submittals typically require a response from the recipient, so
it is necessary to organize and track when, and whether a response has been received.
Hence Project Design Deliverables (PDD) is developed as a solution to Organize Transmittals
(Documents/Drawings) received from contractors/consultants during different phases of an
EPC (Engineering, Procurement & Construction) projects, which gives proper direction to the
stakeholders from the beginning, to reduce inter discipline dependency, avoid overlapping
of activities, provide a list of deliverables, sequence of activities etc...
PDD attempts to provide a list and sequencing of the engineering documents/ drawings
required during different phases of a Project which will benefit both client and Contractor in
performing planned activities through timely submission & review of deliverables. This helps in
ensuring improved quality and completion of Project in time. The successful implementation
begins with a detailed understanding the specific challenges and requirements of the
project.
INTRODUCTION
The PDD will cover the contractor transmittal submission sequence for
the following types of project
Pipeline projects,
Tankage projects,
Building projects,
Substation projects,
Pressure Vessels (Separators, Heaters) projects,
Fire and Gas System projects,
DCS & ESD Modification Works projects,
CCTV Projects,
Fencing projects,
Fire water System projects,
Flare Projects,
Air Compressor system projects
AIM
Doc/Dwg Dependency
S. No PROJECT DESIGN DELIVERABLES:
EXAMPLE
3-E Site Survey Drawings/Document Doc/Dwg Independent
4-E Drawings for Protection of Under Ground Facilities Dwg. Independent
5-E Area Classification Drawing Dwg. Independent
6-E Identifation of reserved Electrical Feeders for the Project Doc. Independent
7-E Design Datasheet for LT Power Cable, Control Cable & Earthing Doc. Independent
Cables
8-E Design Datasheet for MICS Cable Doc. Independent
9-E Design Datasheet for 440V LV Switchboard Doc. Independent
10-E Design Datasheet for Induction Motors Doc. Independent
11-E Design Datasheet for MOV Actuator Doc. Independent
Project Design Deliverable Check List 12-E Design Datasheet for MOV Isolators Doc. Independent
13-E Design Datasheet for Flame Proof DB/Junction Box Doc. Independent
Tankage Projects 14-E
15-E
Design Datasheet for Local Control Stations
Load List
Doc.
Doc.
Independent
3-MP/ 7-MP
16-E Illumination Calculation Doc. 2-MP/ 14-E
Electrical 17-E Single Line & Schematic Diagram of 440 volt Network Dwg. 14-E
18-E Single Line Diagram for lighting Distribution Board Dwg. 14-E
19-E Single Line Diagram for Power Distribution Board Dwg. 14-E
20-E List-Cable Sizing calculation Doc. 15-E,16-E,
17-E,18-E,
19-E
21-E List-LV & Control Cable Schedule Doc. 15-E,16-E,
17-E,18-E,
19-E
22-E Earthing Calculation Doc. 15-E,16-E,
17-E,18-E,
19-E
23-E Lightning Calculation Dwg. 9-E,10-E, 11-E,
12-E,13-E,14-E
24-E LCS Wiring Dwg. 7-MP
25-E Overall Lighting Layout Dwg. 15-E
26-E Overall Cable Layout Dwg. 20-E
27-E Overall Plot Plan-Earthing Layout Dwg. 22-E
28-E Lightning Protection Layout Dwg. 23-E
29-E Vendor Datasheet, Drawing s for LV Switchgear Doc/Dwg 9-E,17-E
30-E Vendor Datasheet, Drawing s for Lighting DB Doc/Dwg 18-E
31-E Vendor Datasheet, Drawing s for Power DB Doc/Dwg 19-E
32-E Doc/Dwg 19-E,20-E
Vendor Datasheet, for Cables
33-E Doc/Dwg 22-E.23-E
Vendor Datasheet, Drawing s for Earthing & Lightning Materials
34-E Doc/Dwg 3MP/9MP
Vendor Datasheet, Drawing s for CP system
IMPLEMENTATION
During the Sequencing process we identify the document relationship
among the different discipline documents. These documents are well-
arranged based on their logical relationships. Most of them are linked to
at least one predecessor and one successor.
SEQUENCING FUNDAMENTALS WE ASSUME FOR PREPARATION.
Sequencing can be stuck-up by
P&ID, Layouts, load details etc.
Necessary Vendor Dependencies
Optional Dependencies
External Dependencies
IMPLEMENTATION
DOCUMENT SEQUENCING TECHNIQUES
During the implementation we illustrate in details the dependent relationships among all project
documents and, consequently, the order is being generated in our software for the predecessor
and the successor document.