Vous êtes sur la page 1sur 1

DAILY PROGRESS CHART

DATE : 20-DEC-2017 SERIAL NO: 03


S.No Bus Depo Stone Soiling DPC Formwork Steel Framing/Reinforcement Concreting Curing Block Masonary Plaster Work Flooring Finishes Paint Work Electrical Plumbing Misseleneous

Reinforcement for walls


Concrete of Bed Backfilling in
1 Fuel Tank distribution Bars & Plinth Beams
Completed Progress
Started

Formwork for Roof Beams and Reinforcement for Beams and Concreting for ledge
2 Masjid
Slabs In Progress Slabs In Progress completed (2.5 cum)

Lean Concreting for Floors


Stone Soiling In Reinforcement for Columns
3 Admin Block in Progress (80%) upto (18
Progress (80%) (50%) In Progress
cum)

Block Masonary for Walls


4 Cafeteria
Started (upto 15%)

Concreting to be done for


5 Maintainence Block
Plinth Beams

Formwork for Plinth Beams to be


6 Driver's Waiting Area
Completed today

Vous aimerez peut-être aussi