CHEMICALS
1 Cera polymer latex kg 234.00
2 Cera Latex SBR Ltr 253.13
3 Cera bond EP (Base 0.65+Hardner0.35) kg 450.00
4 Cera lockset Kg 150.00
5 Murexin Primer Kg 119.40
6 Murexin Sealing Compound Kg 122.40
7 Ardex Superflex Kg 31.00
8 Boscolastic Kg 57.05
9 Cloropyoriphos Ltr 239.20
10 Holdtite Kg 247.00
11 Araldite with hardner set 660.00
12 Bitoplast Kg 73.28
13 Solvent cement Ltr 312.60
14 HCl acid Ltr 18.22
15 HY - 150 - 330 ml foil Kit 1600.00
16 Turpentine Ltr 32.00
17 Phenyl(Germ free) ltr 86.50
18 Thinner ltrs 47.25
19 Soap oil ltr 65.81
ALUMINIUM ACCESSORIES
1 Aluminium Extrusions Kg 153.18
2 PVC foam sheet ( Forex sheet) Sqm 1360.00
3 GP rubber big Kg 103.00
4 GP rubber small Kg 103.00
5 Cobra Hinges Nos 59.63
6 Ventilator Louvers Nos 545.63
7 Weather Strip 9mm thick , 50 m Per roll Nos 185.63
8 Latch Nos 60.00
9 Door lock with handle Nos 410.00
10 SS Door handle Nos 410.00
11 Aluminium angle (38X25X2)mm Kg 189.28
12 Weather strip 6mm Roll 195.00
13 4 mm Plain Glass Sqm 265.15
14 5 mm Plain Glass Sqm 326.19
15 10mm Toughened Glass Sqm 1550.00
16 Toughened clear glass 6mm, 2090X990 Sqm 8216.13
17 Frosted glass Sqm 1200.00
18 Pin Headed Glass 4mm Sqm 180.00
SIL MATERIALS
1 Main door frame Nos 2968.25
2 Main door architrave Nos 1484.13
3 Main door shutter Nos 5936.50
4 BR door frame Nos 2936.25
5 BR door architrave Nos 1468.13
6 BR door shutter Nos 5872.50
7 Toilet door frame Nos 2728.50
8 Toilet door architrave Nos 1364.25
9 Toilet door shutter Nos 5457.00
10 Door handle Set 450.00
11 Door lock Nos 256.00
12 Cylinder both side key Nos 235.00
13 Cylinder one side key (snib turn) Nos 235.00
14 Brass hinges Nos 109.00
15 Brassscrews for hinges Nos 1.00
16 Tower bolt 8" Nos 125.00
17 Door stopper brass painted Nos 64.00
18 Door viewer Nos 18.00
SAFETY ITEMS
1 Yellow Helmet Nos 45.00
2 Blue Helmet Nos 45.00
3 White Helmet Nos 45.00
4 Barricading Tape Mtr 1.00
5 Safety Googles with side mesh Nos 20.48
6 safety belt Nos 65.00
7 Leather Hand Gloves 14" Pairs 20.00
8 Rubber Hand Gloves 14" Pairs 21.75
9 Dust mask cloth type Nos 4.50
10 Button Shoes Nos 74.07
11 Safety shoe for Engineers Pairs 601.88
12 Safety shoe for Tradesmen Pairs 303.75
13 PVC Gumboot Pairs 101.25
14 Ear plug Nos 20.25
15 Safety net Sqm 132.75
C CLASS
1 PVC Tile beading - 8mm Mtr 20.50
2 PVC tile beading - 6mm Mtr 20.50
3 Tile spacers 2mm Nos 0.23
4 Tile spacers 3mm Nos 0.38
5 Silicon Black Nos 95.00
6 Silicon white Nos 85.00
7 Silicon clear Nos 85.00
8 Wheel Barrows Nos 1973.77
9 Old Cloth Nos 9.83
10 Coconut broom stick Nos 5.01
11 Bombay broom Nos 16.42
12 Plastic Mug Nos 9.00
13 G I Bucket 10 ltr Nos 63.35
14 G I Bucket 20 ltr Nos 96.50
15 Plastic can 10 litre Nos 36.40
16 Plastic can 20 litre capacity Nos 72.80
17 Plastic Bucket 20ltr capacity Nos 35.00
18 PVC Tank ltr 2.40
19 Barrel Empty 20 ltrs Nos 42.85
20 Cotton mop Gala Nos 173.00
21 Shuttering oil Ltrs 75.00
22 Room freshner Nos 85.00
23 Floor wiper Nos 65.00
24 M.S.Wire brush with handle Nos 12.75
Sl.N
o Machnery Name Make Model No Rate Remarks
1 Angle grinder 4"
Makita MT 954 3432.00
Bosch GWS - 6 - 100 2856.00
Hitachi PDA - 100D 4200.00
Hitachi G10 SK - 3 4300.00
2 Hoist with Accessories Esquire 205475.00
Sand siever with 0.5 HP motor 48"
lengthx27" dia , electrically operated with
3 0.5 HP Motor 19500.00
4 Hand Planner Machine Bosch GHO - 10 - 82 5346.00
31 Platform weighing scale with scale Blue Bird BBL 6901 5600.00
32 Weighing Machine cap. 10 Kg GEE BEE 333 2540.00
No.of persons
Description of works/ Phase I 6 Phase II 6 Phase III 6
Sl.no Category of workers months months months Remarks
2 MC 4 MC 4 MC
House keeping, External
2 FC 2 FC 2 FC
C
Barricading - Carpenter 1 2 0
D
Helper 2 4 0
Total 40 56 42
Area considered for the Analysis - 1,50,000sft viz, two towers with 4 apartments each per Floor
2 Plastering 2 MC
Water proofing Activities like ponding, Tile screed
3 curing,etc 2 MC
2 Wall Plastering
1 Shuttering 3 Sft
2 Reinforcement 4 Kg
5 Plastering 5 Sft
Earthwork Excavation
Concreting
20cum per mason + helper
Reinforcement
For Slab
170 kg per 1 fitter + 1.5 helper
For Footing
200 kg per 1 fitter + 1.5 helper
Formwork
Fixing & removal
For Slab
7sqm per 1 carpenter + 1.5 helper
For Footings
5sqm per 1 carpenter + 1.5 helper
Starter fixing
5 nos of starters (1 carpenter + 1 helper)
Making
Beam sides
60sqft per Carpenter+ Helper
Column boxes
2.8sqm per Carpenter+Helper
Starter
5 Nos per Carpenter+ Helper
Blockwork
6sqm - 8sqm per mason + 1.5 helper
(1sqm of blockwork = 12.5nos of 8" block)
Plastering
Internal plastering 10sqm
External plastering 12sqm
Ceiling plastering 10 -12 sqm
Tiling
Wall tiling 5 - 6sqm
Floor tiling 8sqm
Granite Works
Granite flooring 7sqm
Granite coping fixing 40rft (1 mason + 1helper)
Granite moulding 100rft (1 mason + 1helper)
W/B counter fixing os(full counter-1500mm X 600mm)
W/B counter fixing nos(half counter-900mm X 600mm)
Skirting Fitting 20rmt
Joint filling 90sft
Limit of Chemical contents for Portable Water
5
Skirting near Door frames
2 Mason, 2 Helper
460
Chipped tile, Hollow tile removing and Cerabond application, cerabond
6
1 bag - Rs.250 250
7 Pop removal
2 Mason, 2 FC
440
SIPL - 6 Helpers
600
10
Miscellaneous item
1526580.00
Total cost for 198 apartments(i.e.343951.64: SBA)
4.44
Cost/SBA