Vous êtes sur la page 1sur 49

1

CODE OF ETHICS AND


PROFESSIONAL
CONDUCT
PMP® Certification Training

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
2

OVERVIEW

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
3

Code of Ethics and Professional Conduct


• Vision and Applicability

• Responsibility

• Respect

• Fairness

• Honesty

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
4

Code of Ethics and Professional Conduct


• Not in the PMBOK Guide:
• Project Management Professional (PMP) Handbook

• https://www.pmi.org/about/ethics/code

• Scroll down, click download to your computer, then click save

• About 18 of the 200 exam questions may address ethics and


professional conduct.

• Two standards:
• Aspirational
• Mandatory

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
5

1.0 VISION AND


APPLICABILITY

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
6

1.1 Vision and Purpose


• As practitioners of project management, we:
• Are committed to doing what is right and honorable
• Set high standards for ourselves
• Aspire to meet the standards in all aspects of our lives

• The purpose of the code describes the expectations that


we have for our ourselves and our fellow practitioners
globally.

• It articulates the ideals to which we aspire and the


behaviors that are mandatory in our professional and in
our volunteer roles.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
7

Ethical Application
• The ethical application of project management requires
that project managers:
• Obtain the authority necessary to manage the project

• Handle an unrealistic schedule problem upfront

• Do the right thing and stand up for the right process

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
8

1.2 Persons to Whom the Code Applies

• All PMI members.

• Non-members who meet one or more of the following


criteria:
• Hold a PMI certificate

• Apply to commence a PMI certification process

• Serve PMI in a volunteer capacity

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
9

Regarding PMP Certification


• The applicant will not let anyone cheat on the application
or the PMP exam.

• The applicant will not let anyone copy PMP exam


materials or perform other illegal behavior.

• The applicant will not disclose questions on the PMP


exam.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
10

1.3 Structure of the Code


• Four values were identified as most important to the
project management community.

• The Code of Ethics and Professional Conduct is divided


into sections that contain standards of conduct that are
aligned with those four values.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
11

1.4 Values that Support this Code


• Responsibility

• Respect

• Fairness

• Honesty

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
12

1.5 Aspirational and Mandatory Conduct

• Code of Conduct includes two types of standards:


• Aspirational standards
• Mandatory standards

• Aspirational standards not easily defined but we strive to


meet them.

• Mandatory standards offer firm requirements and may


limit or prohibit certain behavior.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
13

2.0 RESPONSIBILITY

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
14

2.1 Description
• Responsibility is our duty to take ownership of:

• The decisions we make or fail to make

• The actions we take or fail to take

• The consequences that result

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
15

2.2 Responsibility: Aspirational Standards


• The project management professional will make decisions
based on the best interests of the company and the team,
as well as society and the environment.
• The PM will only take assignments for which they are
qualified.
• If the PM is given a project to manage that is beyond their
qualifications or experience, they will make sure the
sponsor knows of any gaps in qualifications before
accepting the assignment.
• The PM acknowledges their own errors, takes ownership
and make corrections promptly.
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
16

2.3 Responsibility: Mandatory Standards


• Respect confidentiality requirements and protect
proprietary information, including obeying copyright laws.
• Uphold policies, rules, regulations and laws.

• If you witness or become aware of unethical or illegal


behavior, you will report it to management and to those
affected.
• Report violations of PMI’s Code of Ethics and
Professional Conduct only with factual proof of the
violation.
• Pursue disciplinary actions for retaliation.
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
17

3.0 RESPECT

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
18

3.1 Description
• Respect is our duty to show a high regard for ourselves,
for others, and for the resources entrusted to us.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
19

3.2 Respect: Aspirational Standards


• The project management professional will maintain an
attitude of mutual cooperation.
• The PM is informed about the customs and norms of
others, avoids disrespectful behavior, and respects
cultural differences.
• The PM respects others, and listens to their point of view.
• The PM is direct in dealing individuals concerning conflict.
• The PM conducts himself or herself professionally.
• The PM does not gossip or say things that could damage
another person’s reputation, and confronts those that
engage in this behavior.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
20

3.3 Respect: Mandatory Standards


• The project management professional engages in good
faith negotiations.

• The PM does not use power or position to influence


others for personal benefit.

• The PM does not act in an abusive manner toward others

• The PM respects the property rights of others.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
21

4.0 FAIRNESS

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
22

4.1 Description
• Fairness is our duty to make decisions and act impartially
and objectively.

• Our conduct must be free from competing self interest,


prejudice, and favoritism.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
23

4.2 Fairness: Aspirational Standards


• The project management professional demonstrates
transparency in decision making.

• The PM regularly reexamines his or her impartiality and


objectivity, and takes corrective action.

• The PM provides equal access to information, when


authorized.

• The PM makes opportunities equally available to qualified


candidates.
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
24

4.3 Fairness: Mandatory Standards


• The project management professional proactively and fully
discloses real or potential conflicts of interest.

• if there is a real or potential conflict of interest the PM refrains


from engaging in the decision making process or otherwise
attempting to influence outcomes,

• The PM does not hire or fire, reward or punish, award or deny


contracts based on personal considerations, including but not
limited to favoritism, nepotism, bribery, or prejudice,

• The PM does not discriminate against others, based on but not


limited to, gender, race, age, religion, disability, nationality, or
sexual orientation.

• The PM applies organizational rules without favoritism or


prejudice.
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
25

5.0 HONESTY

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
26

5.1 Description
• Honesty is our duty to understand the truth and act in a
truthful manner, both in our communications and in our
conduct.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
27

5.2 Honesty: Aspirational Standards


• The project management professional always seeks to
understand the truth.

• The PM is truthful in all communications and conduct.

• The PM provides accurate and timely information.

• The PM make commitments and promises in good faith.

• The PM creates an environment that encourages honesty.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
28

5.3 Honesty: Mandatory Standards


• The project management professional does not engage in
or condone behavior that is designed to deceive others.
• Including but not limited to, making misleading or false statements,
stating half-truths, providing information out of context or
withholding information that, if known, would render our statements
as misleading or incomplete.

• The PM does not act dishonestly for personal gain or


advantage.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
29

SAMPLE QUESTIONS

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
30

How to read Practice Questions


• Read last sentence first, then read the entire paragraph.

• Read the answers, starting with D and go through A.

• Choose 50/50 – eliminate two choices

• Then choose the answer

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
31

• You recently joined a new company as a project manager. While


reviewing the procurement plans for a project you will be taking
over, you see that the company is considering using one of the
most expensive manufacturers to provide equipment required
for the project. At your previous employer, you used a different
supplier for the same equipment and paid significantly less.
Without telling your boss, you now call that supplier for a quote.
Have you violated the rule of keeping proprietary information
confidential?

A. Maybe. You need to talk to your boss first


B. No. There is no harm in sharing the information with your
current employer, because you are no longer working for
your old employer
C. Yes. The supply source is proprietary information and you
should not contact the supplier
D. You have not violated any rule

Answer: D
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
32

A vendor that was not selected for a contract awarded by


your company has asked why their bid was not selected.
What should you do?

A. Share only the winning bid with the vendor


B. Provide information to the vendor about the areas where
their bid did not meet the defined vendor selection criteria
C. Share all the bids with the vendor
D. Decline the request citing confidentiality

Answer: B

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
33

During a project meeting, the engineering lead tells you he


never makes formal change requests to implement changes
on the development environment servers. He simply asks
one of the IT system administrators to load new code when
it is ready; what do you do?

A. Rollback all the changes


B. Rebuild the development environment
C. Notify the project stakeholders
D. Create a change request for each change the
engineering lead implemented

Answer: C
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
34

The project you are managing has had many customer-


requested requirements changes. Communication and
control of the main supplier was a challenge as well; nearly
all of this supplier’s deliverables were late, resulting in cost
increases of 32% and delays of 2.5 months. No deliverables
from any other supplier were late. While preparing closeout
documentation, you discover that the unreliable supplier is a
company owned by the senior director's brother. What do
you do?

A. Freeze the requirements for the remainder of the project


B. Notify the appropriate management immediately of a
potential conflict of interest
C. Call the supplier and complain about their performance
D. Begin the process to fire the supplier

Answer: B

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
35

As a project manager based at the customer location for a


performing organization, you build rapport with a customer
manager. As the project progresses, the manager asks you to
make certain changes to the project scope and wants this to be
handled on an informal basis. You should:

A. Contact your manager in your organization and ask for this work to
be done without payment, as a goodwill gesture
B. Comply with the manager's request because it is important to
continue to maintain a good relationship with the manager
C. Refuse to take up any changes since the manager has asked you
to do it informally
D. Explain to the manager that you would need to formally document
these as part of project scope change and put it through the
change management process

Answer: D

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
36

• You are hired by a company to work as a project manager


in a foreign country. You discover that you must pay
kickbacks to the officials there to get licenses for your
project. What should you do?

A. Offer kickbacks but inform your management


B. Resign from project
C. Offer kickbacks but document them in cost
management plan
D. Refuse to pay kickbacks

Answer: D

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
37

Homework
1. Read the PMI Code of Ethics & Professional Conduct in
the Handbook PDF file, see table of contents (p37).
https://www.pmi.org/about/ethics/code

2. Take the Focus Area Test: Professional and Social


Responsibility. PMTraining.com/ Take A Test/ p4

3. Read Chapters1-3 from PMBOK guide 5th edition.

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
38

Discussion, Questions and Answers

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
39

EXTRA ETHICS
QUESTIONS

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
40

• Your project sponsor has just handed you a project


schedule that has been developed by your executive
management team and tells you that these are the dates
you must hit. However, the project scope and requirements
have not been finalized. What should you do?

A. Fast Track the project


B. Inform sponsor that you cannot commit to those dates
until appropriate estimating has been done
C. Refuse the project
D. Crash the Project

Answer: B

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
41

You are the project manager of a project executing work


under a contract signed with a buyer organization. Just after
the project has started, you notice that the buyer
organization had made a mistake in the financial terms, and
your organization stands to benefit considerably from this
oversight. What should your stance be?

A. Do not take any action, a contract is a binding and legal


document
B. Discuss with your management on how you could gain a
bonus due to the increased revenue your company stands to
gain
C. Informally check with your counterpart in the buyer
organization to see if they have noticed this error
D. Bring the error to the notice of the buyer organization and
have an amendment made to the contract since this was in
good faith

Answer: D
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
42

What should you do as a senior project manager if the PMP


certification claimed by a recently recruited project manager
does not appear in the PMI website?

A. Advise your new recruit to complete his certification


B. Report to the PMI
C. Report to the sponsor
D. Request more information from the new recruit

Answer: D

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
43

Your manufacturing project is contractually required to


complete on a specific date. No additional funding or work is
permitted beyond that date. You have just discovered a
quality problem that affects less than one percent of the
product produced by this project. Identifying the cause and
implementing corrective action will cause the project to
complete after the contract deadline. What do you do?

A. Compress the schedule


B. Fast track the project
C. Notify the stakeholders
D. Do nothing

Answer: C
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
44

You are a certified PMP and you have been contacted by PMI
as part of an investigation they are conducting into
allegations of improper conduct by your manager, who is
also a PMP. A complaint has been filed stating that your
manager has received bribes related to a large procurement
contract on another project. PMI has asked if you would be
able to provide information regarding this situation. What
should you do?

A. Confront your manager


B. Send PMI project documentation and emails related to the
allegations to assist with their investigation
C. Notify the appropriate management immediately
D. Do nothing, citing a conflict of interest

Answer: C
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
45

You have recently taken over a project from a PMP-certified


project manager who has been removed from the project
due to incompetence and lack of skills. When you happen to
meet him outside your building, he starts loudly criticizing
you for taking his project. He even goes so far as to suggest
that your religion played a part in your selection by the
management. What should you do first?

A. Report to Project Management Institute (PMI)


B. Report to the customer
C. Report to your management
D. Report to the Police

Answer: A
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
46

You are just about to present your project's status to your


company's executive team. Just as you are leaving your
desk for the meeting, one of your resources hands you an
updated report on the progress of a critical deliverable. As
you are walking to the conference room, you review the
report and notice that there is an error in it. What do you do?

A. Do not report on that part of the project


B. Disclose that you have just discovered that there is an error
in some of the information that you had intended to present,
and only present the information that you know to be true
C. Cancel the meeting
D. Present the information as-it-is and revise it in the meeting
minutes, which will be sent after 2 days

Answer: B
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
47

You are in the 10th month of a yearlong project and are about to
deliver the main product. You have already received 75% of the
total payment from the client, You just received a fax from the
client saying that they are wrapping up their operations in the
region due to a change in the government which decided to close
them due to fraud allegations. You are shocked and call your boss
to get confirmation. He also received the same news from other
sources, and he asks you to terminate the project and release the
team. What must you do?

A. Update lessons learned, release payments of your suppliers, pay


all the employees and relieve them from their duties
B. Release payments, check the termination clause in contract, and
relieve employees from their duties
C. Release payments of your suppliers, pay all the employees and
relieve them from their duties
D. Close all project documents, release payments of your suppliers,
pay all the employees and relieve them from their duties

Answer: B
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
48

• Your project team is having a dispute with a vendor about


whether a specific task is within the scope of the project.
The scope statement does not provide implementation-
level details that could resolve this dispute. There is no
WBS because the project sponsor insisted that the project
be started right away without pausing to create standard
project planning documentation, who is at fault?

A. The Project Manager


B. The Project Sponsor
C. The Project Stakeholders
D. The Project Vendor

Answer: A
© 2017, PM Training. All rights reserved.
PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.
49

• You are a project manager, contracted by an investment bank to run a large


IT project, which is expected to last 15 months. While developing the charter,
you discover several regulatory requirements have not been addressed in
the business case. Failure to meet these requirements could result in legal
action against the company. Implementing the technology to comply with
the regulations could exceed the budget and scope of the project, which
could lead to the cancellation of the project, what should you do?

A. Disclose the discovery to the project sponsor and stakeholders


immediately

B. Track this as a risk

C. Wait until project is 25% complete, when you have a better idea of
what resources and funding could be allocated to addressing these
requirements

D. Write up a Scope change request for the work

Answer: A

© 2017, PM Training. All rights reserved.


PMI, the PMI logo, PMP, the PMP logo, and PMBOK are registered marks of Project Management Institute.

Vous aimerez peut-être aussi