Vous êtes sur la page 1sur 81

PCX Corporation

33 Pony Farm Road


Clayton, NC 27520
919-550-2800

ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS


STORE #XXXX – CITY, STATE

SAMPLE
REPORT Revision Control

Rev Number Rev Date Description Rev By

0 X-XX-2016 Release XXX

1 X-XX-2016 PE Comment & Review XXX & XXX


Implementation

2 X-XX-2016 FINAL XXX & XXX

1|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

Table of Contents

1. Executive Summary
2. Calculation Objective
3. Calculation Method – Software Used: ETAP Version
12.6.0
4. Protective Device Coordination – Design Basis

SAMPLE
5. Short Circuit Study - Design Basis
6. Conclusions – Arc Flash Hazard Analysis
7. References

Appendix A
Appendix B
Appendix C REPORT
ETAP One Line diagram
INPUT DATA and Assumptions
Coordination study report – including overcurrent
protective device settings
Appendix D Short Circuit results
Appendix E Arc Flash results
Appendix F Equipment Labels
Appendix G Reference Documents

2|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

1 Executive Summary
1.1 Results

An arc-flash hazard mitigation study was completed for Store #XXXX in City, State using the ETAP Electrical
Engineering Software Program by PCX Corporation. These are the key findings of this electrical engineering study:

A. Using the methodology prescribed in section 2, Zero (0) equipment buses within the plant were computed
with an arc flash hazard incident energy level greater than 40cal/cm2 at recommended settings for the
breakers in the system.
B. Two main breakers have setpoints available – Utility and Generator. All Main Switch Board (MSB)
settings were analyzed at the recommended settings for the two main breakers for this study.
C. The Main Switchboard MSB (Main Breaker Section) requires to be labeled for the worst case arc flash
hazard.
D. 208VAC panels have an energy level 0 arc flash hazard based on GE Spectra series Panelboards and
breakers when all CB are set to minimum instantaneous values, with the exception of panel LRX, which

SAMPLE
has an energy level 1 arc flash hazard.
E. The following 480VAC panel has an energy level 4 arc flash hazard:
i. MSB (Main Breaker)
F. Panels CHA1, CHA2, and CHB have been excluded from this study due to lack of field information.
G. Refer to Series rating document in appendix G (as required).

1.2 Recommendations
After reviewing the results of the Arc-Flash Hazard Analysis, the following actions are recommended:

REPORT
A. Utility main setpoints should be:
i. Long time pickup: 1 (1600A);
ii. Long time band: 1
iii. Short time pickup: 4 (6400A)
iv. Short time Band: Min (1)
v. I2t setpoint: OUT
vi. Instantaneous: 3 (4800A)
vii. Ground pickup: 0.4 (640A)
viii. Ground Band: 1
ix. Ground I2t: OUT

B. Generator main setpoints should be:


i. Long time pickup: FIXED (800A);
ii. Long time band: FIXED
iii. Short time pickup: FIXED (3940.65A)
iv. Short time Band: FIXED
v. I2t setpoint: IN
vi. Instantaneous: 5 (6305.04A)
vii. Ground pickup N/A
viii. Ground Band: N/A
ix. Ground I2t: N/A

3|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

C. MSB Distribution breakers should have the following instantaneous trip settings:
i. H1A: 5 (3162 A)
ii. H1P: MIN
iii. T1D: MIN
iv. DTA: 5 (3528.9 A)
v. MTB: MAX
vi. AHU1: MAX
vii. Baler: MAX
viii. Compactor: MAX
ix. Sub-Metering: MIN
x. Oven (Top): MIN
xi. Oven (Bottom): MIN
xii. PLM: MIN
xiii. UH (Vestibule): MIN
xiv. Water Heater: MIN

D. Ensure all other MCB Instantaneous settings are set to MINIMUM ensuring incident energy levels are
between categories 0-1.
E. Verify breaker settings on an annual basis to ensure arc flash hazard does not increase for the breakers

SAMPLE
identified in Appendix C: coordination study report.
F. Install the arc flash hazard study warning labels on applicable equipment throughout the store in
accordance with [2]. Whenever changes are made to the power system, subsequent studies may be
required to validate existing settings of devices.
G. Lower all 208VAC transformers to less than 125kva eliminating the requirement to include them in Arc
flash studies. NFPA70E, 2009 edition indicates that IEEE 1584 describes arc flash requirements for
3phase systems rated less than 240VAC. Section 4.2 of IEEE 1584 states “Equipment below 240 V need
not be considered unless it involves at least one 125 kVA or larger low impedance transformer in its

REPORT
immediate power supply.”
H. Update arc flash study every [5] years as described in NFPA70E, section 130.5.
I. Maintain an electrically safe work place. Insist that all electrical contractors and other outside construction
personnel servicing, maintaining, and/or making adjustments to energized power system equipment are
equipped with properly rated PPE based upon the results of this arc flash study prior to start of work.
J. Continue to perform routine preventive maintenance on all circuit breakers and electrical equipment as
recommended by [3] at regular service intervals.

2 Calculation Objective
ARC-FLASH HAZARD ANALYSIS – SCOPE:
Determine arc-flash incident energy levels and flash protection boundary distances based on the results of the
Short-Circuit and Coordination studies. To determine if the first upstream protective device de-energizes the arc
fault and if not identify any location where this may occur. Perform the analysis under worst-case arc-flash
conditions for all modes of operation. We received transformer available fault current information from the utility
and used the values provided by the utility. The values used are as follows:
1. KVA-500
2. Primary Voltage- 12,470
3. Secondary Voltage-480
4. Impedance-4.2 %
5. X/R- 3.69
6. Fuse-Cooper Bay-O-Net 60A

4|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

Identify all locations and equipment to be included in the arc-flash hazard analysis:

1. Include a copy of the facility one-line in the report.


2. Calculate the arcing fault current flowing through each branch for each fault location.
3. Determine the time required to clear the arcing fault current using the protective device settings
and associated trip curves.
4. Select the working distances based on system voltage and equipment class.
5. Calculate the incident energy at each fault location at the prescribed working distance.
6. Determine the hazard/risk category (HRC) for the estimated incident energy based on NFPA 70E 2009
Hazard/Risk Categories.
7. Calculate the flash protection boundary at each fault location based on energy at the boundary (EB) of 1.2
Cal/cm2.
8. Document the assessment in reports and one-line diagrams.
9. Furnish labels to be placed on each piece of equipment analyzed. Ship labels to be received by the General
Contractor by three weeks to Possession. (Not Included for this report)

Results of the arc-flash study shall be summarized in a final report containing the following:

1. Basis, method of hazard assessment, description, purpose, scope, and date of the study.

SAMPLE
2. Tabulations of the data used to model the system components and a corresponding one-line diagram.
3. Descriptions of the scenarios evaluated and identification of the scenario used to evaluate
equipment ratings.
4. Tabulations of equipment incident energies, hazard risk categories, and flash protection boundaries. The
tabulation shall identify and clearly note equipment that exceeds allowable Incident energy ratings.
5. Required arc-flash labels and installation instructions.
6. Conclusions and recommendations

REPORT
2.1 Objectives
The primary goals of this study were as follows:
1 To investigate existing arc flash hazard incident energy (IE) levels at the facility
2 To improve the coordination and selectivity between upstream and downstream overcurrent protective
devices at the plant, if possible, without compromising equipment protection boundaries and selective
coordination between upstream and downstream overcurrent protection devices.
3 To report all overcurrent protective devices with inadequate short circuit current interrupting ratings based
upon the computed available fault current.
4 Verify arc hazard levels at all panels 208VAC and above.

2.2 Methodology
Field data provided for the electrical power system at the facility was used to construct a digital computer model for
detailed electrical engineering analysis with the ETAP software program version 12.5.0. Some examples of the
typical field data required to perform this analysis include:
1 Motor Nameplate
2 Conductor Sizes and Lengths
3 Transformer Nameplate
4 Utility Thevenin Impedance
5 Breaker Ratings, Settings, and OEM Fuse Ratings and OEM Equipment Bus Short Circuit Rating

The ETAP computer model of the electrical one-line diagram of the store 0.48 kV and 0.208 kV secondary
distribution systems is shown in the one-line diagram.

The analysis includes a “Base” scenario based upon existing plant conditions and a revision with “minimum”
protective device pickup settings with modified device settings and ratings to provide the lowest possible arc flash

5|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

incident energy levels while achieving the best selective coordination between upstream and downstream
overcurrent protective devices without compromising existing equipment protection boundaries.

When a generator is included in the store, an alternate scenario is run for the generator supplied loads with the
main utility disconnected. In this instance the utility case resulted in a higher hazard energy level.

An arc-flash hazard analysis is an electrical engineering study’s main purpose to calculate the level of thermal
energy exposure to the personnel because of an electric arc-flash event [5]. Computed incident energy levels are
largely dependent upon the computed available fault current and device clearing times, which are produced by
short circuit current and protective device coordination studies.

Based upon the results of the arc flash hazard study, the rating of personal protective equipment (PPE) such as
gloves, arc-rated shirts and pants, eye protection, etc…can be properly selected for adequate personnel protection
as required by [5]. Note that there is a difference between fire-rated and arc-rated equipment. PPE needed for an
arc flash event should have an arc-rating and not just a fire-rated capability.

3 Calculation Method

SAMPLE
Arc Flash Analysis Process

IEEE 1584 establishes a nine-step process for gathering information and calculating arc flash hazards. The steps
are:

1. Collect Electrical System Data

REPORT
Collecting system data is the most difficult and time-intensive step in performing an arc flash hazard analysis, but
accurate information is vital to correctly calculating flash boundaries. A relatively small error at this point can
invalidate all further arc flash calculations. IEEE 1584-2002 lists the minimum information that should be gathered,
as shown in the table below. Information collected from facility's electrical system should be recorded and properly
documented on the one-line diagram or any other acceptable data collection database. The one-line diagram and
electrical database should be kept up to date as much as possible whenever modifications are made to the system
.

Component Required Information


SC contribution
Utility Initial voltage
X/R 3-phase
Nominal kVA
Primary Voltage
Transformers
Secondary Voltage
%Z Impedance
Size (AWG)
Length
Conductors Qty. per phase
Conductor material
Duct material

6|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

Model
Trip or sensor setting
Breakers
The following information is as it applies to the particular breaker:
Plug, LTPU, LTD, STPU, STD, and INST

Model
Fuses
Trip
Motors Nominal HP

2. Determine modes of operation


Many electrical systems, especially in smaller commercial facilities, have only a single mode of operation. In large
facilities, however, it is common to find a number of operating modes, possibly including: emergency modes in

SAMPLE
which only backup generators provide power; multiple utility sources or generators that are switched in or out; and
motors or portions of the system that may start or cease operation. All of these different modes cause changes in
current at various points in the system, altering incident energy and flash boundaries.

3. Determine bolted fault currents

REPORT
The bolted fault current is the current that would flow through a short circuit consisting of two conductors bolted
together. It is the maximum current available to flow through a short circuit. This information is used to calculate the
arc fault currents. Bolted fault currents should be determined for each piece of equipment likely to require
maintenance or inspection while energized. Information on the minimum bolted fault currents is also needed but
typically considered by assuming a minimum number of contributing sources to the fault. It is possible that the
worst-case incident energy will occur when the bolted fault current is at a minimum.

4. Determine arc fault currents


The current that flows through an arcing fault may be significantly less than the bolted fault current, due to greater
resistance (especially in low voltage equipment). Arc fault current calculations are based on voltage, bolted fault
current, conductor gap distance, and other factors. IEEE 1584 presents two formulas for calculating arc fault
currents, one for use with 0.208-1 kV systems, and the other for systems between 1 and 15 kV.

For systems between 0.208 and 1 kV:

lg Ia = K + 0.662(lg Ibf) + 0.0966(V) + 0.000526(G) + 0.5588(V)(lg Ibf) - 0.00304(G)(lg Ibf)


For systems between 1 and 15 kV:

lg Ia = 0.00402 + 0.983(lg Ibf)


where Ia = arc fault current in kA; K = -0.153 for open-air arcs and -0.097 for enclosed arcs; Ibf = 3-phase bolted
fault current in kA; V = voltage in kV; G = conductor gap in mm

5. Determine protective device characteristics and duration of arcs


7|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

The time-current curves of upstream protective devices are the major factor in determining how long an arc-fault
will last. An effort should be made to determine the actual settings rather than relying on standard values, as these
may cause incident energy to vary greatly.

Another consideration when analyzing protective devices is that incident energy depends on both fault current and
time. Since protective devices are slower at lower currents, minimum fault currents often pose the worst-case arc
flash scenario as mentioned before.

6. Document voltages and equipment classes


Voltage and equipment class determine what equation should be used to find the flash boundary, as well as the
bus gap distances required by the equations. Systems operating at <1 kV use a different equation than those
operating between 1 kV and 15 kV.

SAMPLE
7. Establish working distances
The working distance is the distance from a potential arc source to a worker's face and chest. It is a critical quantity

REPORT
in determining the flash hazard boundary, as even an increase of a few inches in working distance can cause a
significant drop in incident energy. 18 inches is the working distance most commonly assumed in calculations, but
efforts should be made to determine actual working distances. Some usual working distances are shown in the
table below.

Equipment class Working distance


Low-voltage switchgear 24"
15 kV/5 kV switchgear 36"
Low-voltage MCCs and panel boards 18"
Cables 18"

8. Determine incident energies


Incident energy is defined in NFPA 70E as "the amount of energy impressed on a surface, a certain distance from
the source, generated during an electrical arc event." In an arc flash hazard study, the "surface" is the worker's
body at the assumed working distance. Incident energy is expressed in calories/cm2. IEEE 1584-2002 uses the
following formulas (which are also part of NFPA 70E annex D):

(1) E = 4.184(Cf)(En)(t/0.2)(610x/Dx)
Where E = incident energy in joules/cm2; Cf is a calculation factor (1.0 for voltages above 1 kV, and 1.5 for voltages
below 1 kV); En = normalized incident energy (from equation (2) below); t = arc duration in seconds; D = distance

8|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

from arc in mm; x = distance exponent (see table below)

Equipment Type D (Distance Exponent)


Open air 2.0
Low-voltage (.208-1 kV) switchgear 1.473
High-voltage (1-15 kV) switchgear 0.973
Low-voltage MCCs and panels 1.641
Cables 2.0

(2) lg En = K1 + K2 + 1.081(lg Ia) + 0.0011(G)


where En = energy normalized for distance of 610 mm and arc duration of 0.2 seconds, in joules/cm2; K1 = -0.792
for open-air arcs and -0.555 for enclosed arcs; K2 = 0 for ungrounded/high-Z systems and -0.113 for grounded

SAMPLE
systems; G = arc gap in mm; Ia = predicted 3-phase arc fault current in kA

9. Determine the Arc Flash Boundary (AFB)

REPORT
The AFB is the distance at which incident energy exposure is about 1.2 cal/cm2, which is equivalent to the energy
required to cause the onset of a second-degree burn. The IEEE formula for calculating AFB is:

DB = [4.184(Cf)(En)(t/0.2)(610x/EB)]1/x
where EB is the desired incident energy at the boundary (usually 1.2 cal/cm2, but occasionally set at a value
matching proposed PPE rating), with other variables defined as for the incident energy equations above.

4 PROTECTIVE DEVICE COORDINATION STUDY

4.1 Discussion
The main objectives of the protective device coordination study are to prevent injury to personnel, to minimize
damage to system components, and to limit the extent and duration of service interruption whenever equipment
failure, human error, or adverse natural events occur on any portion of the electrical power system [4].

The term “selective coordination” simply implies that devices are carefully selected or adjusted to “trip” or operate
in a certain desired sequence during fault conditions, preferably beginning with the device closest to the fault
followed by the upstream protector(s). Using this methodology, extensive plant outages and safety hazards to
personnel and equipment can be avoided by localizing faults to the closest protective device [2].

Based on stated objectives, the settings of molded case circuit breakers (MCCB) and static trip units (STU) were
carefully analyzed and adjusted - wherever device adjustments were permissible - in order to obtain “selectivity”

9|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

between upstream and downstream overcurrent protective devices without compromising equipment protective
boundaries, transformer inrush, and motor starting criteria.

4.2 Coordination Discrepancies


Coordination discrepancies are best shown graphically by TCC’s which overlap creating an incorrect device
tripping sequence. The undesired operation of circuit breakers and can be modified simply by adjusting trip settings
to greater than the computed fault current levels (And vice-versa). This operation is preferred to as “blocking” and
is represented mathematically by the following expressions:
1 |IF| > |Ip| : Trip (1)
2 |IF| < |Ip| : Do Not Trip (Block) (2)
3 Where:
4 IF = Fault Current
5 IP = Pick-Up Current

This functional dependence between IF and IP is illustrated graphically in Fig. 2[7]. In this study, very few
opportunities for adjustments were possible due to the installation of mostly MCCB’s with fixed settings and fuses;
however, one coordination discrepancy can be corrected by making proper adjustments to the long time and

SAMPLE
instantaneous settings of the upstream device and is graphically illustrated in Appendix “E.”

Trip Curves and Settings


Time-current characteristic tripping curves (TCC’s) of all applicable fuses, and circuit breakers found in this study
are provided in “Appendix B.” The curves are plotted on log-log scale and shown for a “Base” Case, which may
represent existing plant overcurrent device settings configured to yield a worst-case scenario (i.e. with settings

REPORT
placed at a maximum pickup value). In addition, a “Recommended” case is included with revised settings required
to attain selective coordination, and most importantly, reduce arc flash hazard incident energy levels (Where
possible). Also shown are transformer inrush/damage curves, motor starting profile curves, cable and conductor
thermal curves, and a miniature section of the one-line diagram where the devices are taken from. These curves
and points are plotted to provide a visual, graphical representation of the existing equipment protection boundaries
for proper coordination and application of overcurrent protective devices.

5 Short Circuit Study – Design Basis

5.1 Discussion
Short circuit current studies are performed to determine the magnitude of currents flowing throughout the
power systems at various time intervals after a “fault” or abnormal condition occurs [4], [6]. These currents
must be calculated in order to adequately specify electrical equipment bus withstand ratings and
overcurrent protective device interrupting duties.

Computer modeling using the ETAP Electrical Engineering software program by PCX was done by
expressing the per unit impedances of all relevant electrical power system components (i.e.,
Transformers, motors, cables, etc…) on a common 100 MVA base and using symmetrical components
theory to derive available fault current values at each specific bus.

The IEEE 1584 and NFPA 70E methodology only have equations to calculate the arc fault current for
three-phase bolted faults. It is likely that arc faults may initiate as line-to-ground faults, but the
methodology available makes the conservative assumption that the fault will quickly escalate to a three-
phase arc fault.
10 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

5.2 Utility Source Impedance Information


Data on Utility Transformer can be provided by ETAP if necessary.

5.3 ANSI/IEEE Fault Current Report


ETAP provides two short current calculation methods based on either ANSI/IEEE or IEC (European)
Industry Standards. The following summarizes the ANSI/IEEE short-circuit current method based upon
[8], [9], [10], [11]:

5.3.1 ½ Cycle Network


This network impedance is used to compute the momentary short circuit current and protective device
duties at ½ cycle after the fault occurs. This fault current is used to validate the following:

Device Type Duty


1 HV CB Closing & Latching Rating
2 LV CB Interrupting Rating
3 Fuse Interrupting Rating
4 SWGR/MCC Bus Bracing Rating

SAMPLE
5 Relay Instantaneous Trip Settings

The ½ Cycle Network is also preferred to as the “subtransient” impedance network, primarily because all
of the AC rotating machines are represented by their subtransient reactance (X”d), as indicated below:

Machine Type Short Circuit Impedance


1 Turbo-Generator X”D

REPORT
2 Utility X”
3 Induction Machines:
• >1000 Hp @1800 Rpm or Less X”D
• >250 Hp @ 3600 Rpm X”D
• All Other ≥50 Hp 1.2 X”D

6 ARC FLASH HAZARD ANALYSIS

6.1 Discussion
The ultimate goal of an arc-flash hazard analysis (AFHA) is to compute incident energy levels and arc flash
boundary distances at all relevant equipment locations in order to determine the thermal energy exposure to which
personnel can be exposed when performing energized work. The end-result is the proper selection of arc-rated
personal protective equipment (PPE), as prescribed by [5]. Incident energy (IE) level magnitudes, measured in
cal/cm2 or joules/cm2, are dependent upon the available 3-phase fault current computed at equipment buses, and
perhaps to an even greater degree, the actual total fault current clearing time of the upstream overcurrent
protective device(s).

Note that according to [1], arc flash hazard calculations pertain to three-phase
electrical power systems only. Single-phase power systems and equipment
encountered at the plant are not included in the arc flash calculations in this
study!

11 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

Wherever possible, the primary objective of the recommendations section of this study is to reduce or “mitigate”
incident energy levels by adjusting device trip settings to operate at or below the computed arcing fault current.

Personal protective clothing and equipment (PPE) hazard/risk categories 0-4 are specified in [5] with the intent of
limiting skin burn injuries to “survivable.” PPE category 4 is the highest of the hazard/risk categories recognized by
[5] and requires a minimum arc thermal performance exposure value (ATPV) of 40 cal/cm2 to limit the heat transfer
through the material or fabric to a second degree curable burn based upon the Stoll curve. Incident energy levels
computed above 40 cal/cm2 are preferred to as “hotspots” within this report and energized work at these locations
– If mitigation techniques are ineffective – should be strictly prohibited.

Please note that this is a formal incident energy study which determines the actual incident energy available at
each location. The choice to report the energy levels as “Categories” defined by NFPA 70E 2009 was made to
“easily” communicate the amount of incident energy available. The selection of the ATPV or EB rating of the PPE
should factor an additional safety factor above the calculated energy value to reduce any potential break open on
the material.

6.2 Arc Flash Results

SAMPLE
A complete list of arc flash results based upon existing plant conditions are shown in Appendix “F” and
recommended changes are given in Section “1”

In addition, it has been well documented that a lack of timely electrical preventive maintenance and testing of
power circuit breakers could result over time in slower operating/tripping times leading to higher incident energy
levels [12]. Therefore, routine preventive maintenance testing of all plant protective relays and power circuit
breakers with solid-state trip devices is highly encouraged and recommended. The incident energy values
calculated in this study assume an “out-of-the-box” status for all circuit breakers. Their age and maintenance

REPORT
frequency has not been factored into the study.

Although higher available fault current levels can affect bus incident energy levels, the results of this study
demonstrates that long fault clearing times have an even greater impact on the incident energy calculation.

The arcing current variation (85% of original Ia) has been applied by default on all arc flash scenarios. The worst-
case incident energy (100% or 85% Ia) has been reported. Any location where the arcing current variation is a
major problem has been identified and recommendations made on how to mitigate the energy have been provided.

12 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

7 REFERENCES

7.1. Acknowledgements
Curtis Raymond Helfrich, PE provided his technical assistance in reviewing this ARC Flash Study.

7.2. Bibliography
1. IEEE Standard 1584, “IEEE Guide For Performing Arc-Flash Hazard Calculations,” 2002.
2. NFPA Standard 70, “National Electrical Code,” 2011.
3. International Electrical Testing Association (NETA), “Maintenance Testing Specifications For Electrical Power Distribution
Equipment And Systems,” 2005.
4. IEEE Standard 242 (Buff Book), “IEEE Recommended Practice for Protection and Coordination of Industrial and
Commercial Power Systems,” 1986.
5. NFPA Standard 70E, “Standard For Electrical Safety Requirements For Employee Workplaces,” 2009.
6. IEEE Standard 399 (Brown Book), “IEEE Recommended Practice for Industrial and Commercial Power Systems
Analysis,” 1990.

SAMPLE
7. Stevenson, William D, Jr., “Elements of Power System Analysis,” McGraw-Hill, Inc., 1982.
8. ANSI/IEEE Standard C37.04, “Standard Rating Structure for AC High Voltage Circuit Breakers Rated on a Symmetrical
Current Basis,” 1999.
9. ANSI/IEEE Standard C37.010, “Standard Application Guide for AC High Voltage Circuit Breakers Rated on a Symmetrical
Current Basis,” 1999.
10. ANSI/IEEE Standard C37.13, “Standard for Low-Voltage AC Circuit Breakers Used in Enclosures,” 1990.
11. ANSI/IEEE Standard C37.20.1, “Standard for Metal Enclosed Low-Voltage Power Circuit Breaker Switchgear,” 2002.
12. Neitzel, Dennis K., “Protective Devices Maintenance as It Applies To the Arc/Flash Hazard,” 2004.

REPORT

13 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

Appendix A: ETAP One-Line diagram


A one-line diagram was generated for the Store #XXXX for analysis purposes. The worst case
analysis drawing is attached showing the AFH for each bus and panel.

SAMPLE
REPORT

14 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
SAMPLE
REPORT
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

Appendix B: INPUT DATA & Assumptions


In instances where credible data was not supplied or available, valid engineering assumptions for the ETAP computer model
were made based upon the specific application and professional engineering experience and judgment. The following are
known assumptions for this study:

The incident energy has been conservatively estimated for most locations downstream from the main 1600 Amp circuit
breaker. Energy results for the 1600 Amp main circuit breaker compartment are not available since information on the
upstream primary side transformer protection is not available. An incident energy result projected based on a 1.5 sec
maximum exposure time has been provided. The actual incident energy value can be determined once the missing
information is obtained.

Customer Store #XXXX

Address 544 Industrial Loop

SAMPLE
City, State, zip Shreveport, LA 71129
Contact name John Doe
Phone XXX-XXX-XXXX

REPORT
Utility Company XXXX Power Co.
Contact Ernest Duncan
Address 6130 Union Ave.
City State Zip Shreveport, LA 71108
Email eduncan@xxxx.com
Phone XXX-XXX-XXXX

General Contractor XXXX Construction


Contact Justin Wells
Address 1102 S. Happy Hollow Rd.
City State Zip Fayetteville, AR 72701
Email jwells@xxxx.com
Phone XXX-XXX-XXX

15 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

Appendix C: Coordination study report – including overcurrent


protective device settings

SAMPLE
REPORT

16 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
Project: STORE#XXXX ETAP Page: 1
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings

CB: CB-AHU1
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SFLA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 250 Cont. Amp: 250.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SF
Sensor: 250
Rating Plug: 225.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed

SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MAX

CB: CB-Baler
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)

REPORT
Size: 30 Cont. Amp: 30.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 30
Rating Plug: 30.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MAX
Project: STORE#XXXX ETAP Page: 2
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings

CB: CB-Compactor
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 30 Cont. Amp: 30.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 30
Rating Plug: 30.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed

SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MAX

CB: CB-DTA
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SGLA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)

REPORT
Size: 600 Cont. Amp: 600.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SG
Sensor: 600
Rating Plug: 450.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup 5
Project: STORE#XXXX ETAP Page: 3
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings

CB: CB-H1A
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SGLA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 400 Cont. Amp: 400.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SG
Sensor: 400
Rating Plug: 400.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed

SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup 5

CB: CB-H1P
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)

REPORT
Size: 100 Cont. Amp: 100.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 100
Rating Plug: 100.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
Project: STORE#XXXX ETAP Page: 4
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings

CB: CB-MBU
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SS 1600 ETU Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 1600 Cont. Amp: 1600.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Entelliguard
Sensor: 1600 (LSIG)
Rating Plug: 1600.00

Phase Setting Ground Setting


Long-Time LT Pickup 1.000 Ground Pickup 0.400
LT Band 1 Ground Band 1 I^xt=OUT

SAMPLE
Short-Time ST Pickup 4.000
ST Band 1 I^xt=OUT
INST Inst. Pickup 3.000

CB: CB-MTB
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SFLA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)

REPORT
Size: 250 Cont. Amp: 250.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SF
Sensor: 250
Rating Plug: 200.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MAX
Project: STORE#XXXX ETAP Page: 5
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings

CB: CB-Oven(Bottom)
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 100 Cont. Amp: 100.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 70
Rating Plug: 70.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed

SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN

CB: CB-Oven(Top)
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)

REPORT
Size: 60 Cont. Amp: 60.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 40
Rating Plug: 40.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
Project: STORE#XXXX ETAP Page: 6
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings

CB: CB-PLM
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 30 Cont. Amp: 30.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 15
Rating Plug: 15.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed

SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN

CB: CB-Sub-Metering
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)

REPORT
Size: 30 Cont. Amp: 30.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 15
Rating Plug: 15.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
Project: STORE#XXXX ETAP Page: 7
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings

CB: CB-T1D
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SFLA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 250 Cont. Amp: 250.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SF
Sensor: 250
Rating Plug: 225.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed

SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN

CB: CB-UH (Vestibule)


MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)

REPORT
Size: 60 Cont. Amp: 60.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 50
Rating Plug: 50.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
Project: STORE#XXXX ETAP Page: 8
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings

CB: CB-Water Heater


MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 100 Cont. Amp: 100.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 70
Rating Plug: 70.00

Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed

SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN

REPORT
Amps X 10 MSB (Distribution) (Nom. kV=0.48, Plot Ref. kV=0.48)
.5 1 3 5 10 30 50 100 300 500 1K 3K 5K 10K
1K 1K
CB-H1A

500 CB-AHU1 500

300 300
CB-MTB
CB-MBG

100 100

50 CB-DTA 50
CB-T1D

30 30

CB-Oven(Bottom)

10 10
CB-PLM

SAMPLE
5 5
CB-Baler
Seconds

Seconds
3 3

CB-UH (Vestibule)

REPORT
1 1
CB-Sub-Metering
CB-H1P
.5 .5

.3 CB-Compactor .3

.1 .1
CB-Oven(Top)

.05 CB-Water Heater .05

.03 .03

CB-MBG

CB-Water Heater

.01 .01
CB-UH (Vestibule)
CB-H1A CB-H1P CB-T1D CB-DTA CB-MTB CB-AHU1 CB-Baler CB-Compactor CB-Sub-Metering CB-Oven(Top) CB-Oven(Bottom) CB-PLM

.5 1 3 5 10 30 50 100 300 500 1K 3K 5K 10K

Amps X 10 MSB (Distribution) (Nom. kV=0.48, Plot Ref. kV=0.48) ETAP Star 12.6.0C

MBG COORDINATION

Project: STORE#XXXX Date: XX-XX-2016


Location: City, ST SN: PCX-CORP01
Contract: PCXXXXX Rev: Base
Engineer: XX Fault: Phase
Filename:
Amps X 10 MSB (Distribution) (Nom. kV=0.48, Plot Ref. kV=0.48)
.5 1 3 5 10 30 50 100 300 500 1K 3K 5K 10K
1K 1K

CB-H1P
500 500

300 CB-H1A 300

CB-MTB
CB-MBU
100 100

50 50
CB-T1D
30 30

CB-AHU1

10 CB-PLM 10

SAMPLE
5 5
Seconds

Seconds
3 CB-UH (Vestibule) 3
CB-Sub-Metering

REPORT
1 1

CB-DTA
CB-Compactor
.5 .5

CB-Baler
.3 .3

CB-Water Heater

.1 CB-Oven(Bottom) .1

.05 CB-Oven(Top) .05

.03 .03

CB-MBU

CB-Water Heater

.01 .01
CB-UH (Vestibule)
CB-H1A CB-H1P CB-T1D CB-DTA CB-MTB CB-AHU1 CB-Baler CB-Compactor CB-Sub-Metering CB-Oven(Top) CB-Oven(Bottom) CB-PLM

.5 1 3 5 10 30 50 100 300 500 1K 3K 5K 10K

Amps X 10 MSB (Distribution) (Nom. kV=0.48, Plot Ref. kV=0.48) ETAP Star 12.6.0C

MBU COORDINATION

Project: STORE#XXXX Date: XX-XX-2016


Location: City, ST SN: PCX-CORP01
Contract: PCXXXXX Rev: Base
Engineer: XX Fault: Phase
Filename:
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

Appendix D: Short Circuit results

SAMPLE
REPORT

17 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
Project: STORE#XXXX
ETAP Page: 1
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Electrical Transient Analyzer Program

Short-Circuit Analysis

ANSI Standard
3-Phase Fault Currents

Number of Buses:
SAMPLE
Swing
1
V-Control
0
Load
28
Total
29

Number of Branches:

REPORT
XFMR2
2

Synchronous
Generator
XFMR3

Power
Grid
Reactor

Synchronous
Motor
Line/Cable

23

Induction
Machines
Impedance

Lumped
Load
Tie PD

Total
Total

28

Number of Machines: 0 1 0 3 3 7

System Frequency: 60.00 Hz

Unit System: English

Project Filename: PCXXXXX

Output Filename:
Project: STORE#XXXX
ETAP Page: 2
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Adjustments

Apply Individual
Tolerance Adjustments /Global Percent

Transformer Impedance: Yes Individual

Reactor Impedance: Yes Individual

Overload Heater Resistance: No

Transmission Line Length: No

SAMPLE
Cable Length: No

Apply Individual
Temperature Correction Adjustments /Global Degree C

Transmission Line Resistance: Yes Individual

Cable Resistance: Yes Individual

REPORT
Project: STORE#XXXX
ETAP Page: 3
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Bus Input Data

Bus Initial Voltage


ID Type Nom. kV Base kV Sub-sys %Mag. Ang.

B-AHU1 Load 0.480 0.480 1 100.00 0.00

B-Baler Load 0.480 0.480 1 1.00 0.00

B-Compactor Load 0.480 0.480 1 100.00 0.00

B-Oven(Bottom) Load 0.480 0.480 1 100.00 0.00

SAMPLE
B-Oven(Top) Load 0.480 0.480 1 100.00 0.00

B-PLM Load 0.480 0.480 1 100.00 0.00

B-Sub-Metering Load 0.480 0.480 1 100.00 0.00

B-T1D Pri Load 0.480 0.480 1 100.00 0.00

B-T1D Sec Load 0.208 0.208 1 100.00 0.00

B-UH (Vestibule) Load 0.480 0.480 1 100.00 0.00

B-UPS1 Pri Load 0.208 0.208 1 100.00 0.00

REPORT
B-UPS1 Sec Load 0.208 0.208 1 100.00 0.00

B-Utility Primary SWNG 13.200 12.470 1 94.47 0.00

B-Utility Secondary Load 0.480 0.480 1 100.00 0.00

B-Water Heater Load 0.480 0.480 1 100.00 0.00

Circuit Breaker L1D2 Load 0.208 0.208 1 100.00 0.00

MSB (Distribution) Load 0.480 0.480 1 1.00 0.00

MSB (Gen) Load 0.480 0.480 1 100.00 0.00

MSB (Main Breaker) Load 0.480 0.480 1 100.00 0.00

Panel DTA Load 0.480 0.480 1 100.00 0.00

Panel H1A Load 0.480 0.480 1 100.00 0.00

Panel H1P Load 0.480 0.480 1 100.00 0.00

Panel L1D1-1 Load 0.208 0.208 1 100.00 0.00

Panel L1D1-2 Load 0.208 0.208 1 1.00 0.00

Panel L1D2-1 Load 0.208 0.208 1 100.00 0.00

Panel L1D2-2 Load 0.208 0.208 1 100.00 0.00

Panel L1U Load 0.208 0.208 1 100.00 0.00

Panel LRX Load 0.208 0.208 1 100.00 0.00

Panel MTB Load 0.480 0.480 1 100.00 0.00

29 Buses Total

All voltages reported by ETAP are in % of bus Nominal kV.


Base kV values of buses are calculated and used internally by ETAP .
Project: STORE#XXXX
ETAP Page: 4
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Line/Cable Input Data

Ohms or Siemens/1000 ft per Conductor (Cable) or per Phase (Line)

Line/Cable Length

ID Library Size Adj. (ft) % Tol. #/Phase T (°C) R X Y


C-AHU1 0.6MCUN1 4/0 290.0 0 1 75 0.06300 0.05100 0.0000000

C-Baler 0.6MCUN1 10 270.0 0 1 75 1.20000 0.06300 0.0000000

C-Compactor 0.6MCUN1 10 275.0 0 1 75 1.20000 0.06300 0.0000000

C-DTA 0.6MALN1 300 235.0 0 2 75 0.07200 0.05100 0.0000000

SAMPLE
C-H1A 0.6MALN1 250 9.0 0 2 75 0.08600 0.05200 0.0000000

C-H1P 1.0MALN1 1 12.0 0 1 75 0.25000 0.05700 0.0000000

C-L1D1-1 0.6MALN1 300 5.0 0 1 75 0.07200 0.05100 0.0000000

C-L1D1-2 0.6MALN1 300 3.0 0 1 75 0.07200 0.05100 0.0000000

C-L1D2 Line 0.6MALN1 250 3.0 0 2 75 0.08600 0.05200 0.0000000

C-L1D2 Load 0.6MALN1 250 280.0 0 2 75 0.08600 0.05200 0.0000000

C-L1D2-2 0.6MALN1 250 3.0 0 2 75 0.08600 0.05200 0.0000000

REPORT
C-L1U 0.6MCUN1 6 50.0 0 1 75 0.49000 0.06400 0.0000000

C-LRX 0.6MALN1 4 160.0 0 1 75 0.51000 0.06000 0.0000000

C-MBU 0.6MCUN1 300 60.0 0 6 75 0.04500 0.05100 0.0000000

C-MTB 0.6MALN1 250 260.0 0 1 75 0.08600 0.05200 0.0000000

C-Oven(Bottom) 0.6MCUN1 2 275.0 0 1 75 0.20000 0.05700 0.0000000

C-Oven(Top) 0.6MCUN1 8 275.0 0 1 75 0.78000 0.06500 0.0000000

C-PLM 0.6MCUN1 12 5.0 0 1 75 2.00000 0.06800 0.0000000

C-Sub-Metering 0.6MCUN1 12 5.0 0 1 75 2.00000 0.06800 0.0000000

C-T1D Pri 0.6MALN1 300 9.0 0 1 75 0.07200 0.05100 0.0000000

C-UH (Vestibule) 0.6MCUN1 6 5.0 0 1 75 0.49000 0.06400 0.0000000

C-UPS1 0.6MCUN1 6 40.0 0 1 75 0.49000 0.06400 0.0000000

C-Water Heater 0.6MCUN1 2 5.0 0 1 75 0.20000 0.05700 0.0000000

Line / Cable resistances are listed at the specified temperatures.


Project: STORE#XXXX
ETAP Page: 5
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

2-Winding Transformer Input Data

Transformer Rating Z Variation % Tap Setting Adjusted


ID MVA Prim. kV Sec. kV %Z X/R + 5% - 5% % Tol. Prim. Sec. %Z

T1D 0.150 0.480 0.208 4.00 3.45 0 0 0 2.500 2.500 4.0000

Utility Transformer 0.500 12.470 0.480 4.20 5.10 0 0 0 0 0 4.2000

SAMPLE
Impedance Input Data

Impedance Positive Sequence Impedanc


ID R X Y Unit

MSB Bus 0.01 0.01 0 % in 0.480 kV base and 100.0 MVA base

MSB Bus 2 0.01 0.01 0 % in 0.480 kV base and 100.0 MVA base

REPORT
Project: STORE#XXXX
ETAP Page: 6
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Branch Connections

CKT/Branch Connected Bus ID % Impedance, Pos. Seq., 100 MVAb


ID Type From Bus To Bus R X Z Y

T1D 2W XFMR B-T1D Pri B-T1D Sec 779.97 2690.91 2801.67

Utility Transformer 2W XFMR B-Utility Primary B-Utility Secondary 161.63 824.30 840.00

C-AHU1 Cable MSB (Distribution) B-AHU1 792.97 641.93 1020.23

C-Baler Cable MSB (Distribution) B-Baler 14062.50 738.28 14081.87

SAMPLE
C-Compactor Cable MSB (Distribution) B-Compactor 14322.92 751.95 14342.64

C-DTA Cable MSB (Distribution) Panel DTA 367.19 260.09 449.97

C-H1A Cable MSB (Distribution) Panel H1A 16.80 10.16 19.63

C-H1P Cable MSB (Distribution) Panel H1P 130.21 29.69 133.55

C-L1D1-1 Cable B-T1D Sec Panel L1D1-1 83.21 58.94 101.97

C-L1D1-2 Cable Panel L1D1-1 Panel L1D1-2 49.93 35.36 61.18

C-L1D2 Line Cable B-T1D Sec Circuit Breaker L1D2 29.82 18.03 34.84

REPORT
C-L1D2 Load Cable Circuit Breaker L1D2 Panel L1D2-1 2782.91 1682.69 3252.09

C-L1D2-2 Cable Panel L1D2-1 Panel L1D2-2 29.82 18.03 34.84

C-L1U Cable B-UPS1 Sec Panel L1U 5662.91 739.65 5711.01

C-LRX Cable Panel L1D1-1 Panel LRX 18860.95 2218.94 18991.02

C-MBU Cable B-Utility Secondary MSB (Main Breaker) 19.53 22.14 29.52

C-MTB Cable MSB (Distribution) Panel MTB 970.49 586.81 1134.10

C-Oven(Bottom) Cable MSB (Distribution) B-Oven(Bottom) 2387.15 680.34 2482.21

C-Oven(Top) Cable MSB (Distribution) B-Oven(Top) 9309.90 775.82 9342.17

C-PLM Cable MSB (Distribution) B-PLM 434.03 14.76 434.28

C-Sub-Metering Cable MSB (Distribution) B-Sub-Metering 434.03 14.76 434.28

C-T1D Pri Cable MSB (Distribution) B-T1D Pri 28.13 19.92 34.47

C-UH (Vestibule) Cable MSB (Distribution) B-UH (Vestibule) 106.34 13.89 107.24

C-UPS1 Cable Panel L1D2-1 B-UPS1 Pri 4530.33 591.72 4568.81

C-Water Heater Cable MSB (Distribution) B-Water Heater 43.40 12.37 45.13

MSB Bus Impedance MSB (Main Breaker) MSB (Distribution) 0.01 0.01 0.01

MSB Bus 2 Impedance MSB (Gen) MSB (Distribution) 0.01 0.01 0.01

UPS1 Tie Switch B-UPS1 Pri B-UPS1 Sec


Project: STORE#XXXX
ETAP Page: 7
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Power Grid Input Data

% Impedance
Power Grid Connected Bus Rating 100 MVA Base
ID ID MVASC kV X/R R X

Utility B-Utility Primary 58.727 12.470 3.69 44.53977 164.35170

Total Connected Power Grids (= 1 ): 58.727 MVA

SAMPLE
REPORT
Project: STORE#XXXX
ETAP Page: 8
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Induction Machine Input Data

% Impedance
Induction Machine Connected Bus Rating X/R Ratio Machine Base
ID Qty ID HP/kW kVA kV RPM X"/R X'/R R X" X'

Motors
Load AHU1 1 B-AHU1 154.00 147.23 0.480 1800 9.66 9.66 2.07 20.00 50.00

Load Baler 1 B-Baler 10.45 11.65 0.480 1800 2.52 2.52 11.06 27.83 9999.00

Load Compactor 1 B-Compactor 10.45 11.65 0.480 1800 2.52 2.52 11.06 27.83 9999.00

SAMPLE
Total Connected Induction Motors ( = 3 ): 170.5 kVA

REPORT
Project: STORE#XXXX
ETAP Page: 9
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Lumped Load Input Data

Lumped Load Motor Loads Static Loads

% Imp.
Lumped Load Connected Bus Rating % Load Loading X/R Ratio (Machine Base) Loading
ID ID kVA kV MTR STAT kW kvar X"/R X'/R R X" X' kW kvar
Load DTA Panel DTA 328.0 0.480 100 0 278.8 172.8 2.38 2.38 8.403 20.00 50.00 0.00 0.00

Load H1A Panel H1A 286.0 0.480 100 0 243.1 150.7 2.38 2.38 8.403 20.00 50.00 0.00 0.00

Load MTB Panel MTB 130.0 0.480 100 0 110.5 68.5 2.38 2.38 8.403 20.00 50.00 0.00 0.00

SAMPLE
Total Connected Lumped Loads ( = 3 ): 744.0 kVA

REPORT
Project: STORE#XXXX
ETAP Page: 10
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

SHORT-CIRCUIT REPORT

3-phase fault at bus: MSB (Distribution)

Prefault voltage = 0.480 = 100.00 % of nominal bus kV ( 0.480 kV)


= 100.00 % of base ( 0.480 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

SAMPLE
MSB (Distribution) Total 0.00 4.319 -15.881 3.7 16.458

B-AHU1 MSB (Distribution) 7.09 0.128 -0.826 6.5 0.836

B-Baler MSB (Distribution) 5.35 0.019 -0.042 2.2 0.046

B-Compactor MSB (Distribution) 5.45 0.019 -0.042 2.2 0.046

Panel DTA MSB (Distribution) 6.43 0.719 -1.561 2.2 1.718

REPORT
Panel H1A MSB (Distribution) 0.26 0.615 -1.458 2.4 1.582

Panel H1P MSB (Distribution) 0.00 0.000 0.000 999.9 0.000

Panel MTB MSB (Distribution) 6.44 0.288 -0.619 2.1 0.683

B-Oven(Bottom) MSB (Distribution) 0.00 0.000 0.000 999.9 0.000

B-Oven(Top) MSB (Distribution) 0.00 0.000 0.000 999.9 0.000

B-PLM MSB (Distribution) 0.00 0.000 0.000 999.9 0.000

B-Sub-Metering MSB (Distribution) 0.00 0.000 0.000 999.9 0.000

B-T1D Pri MSB (Distribution) 0.00 0.000 0.000 999.9 0.000

B-UH (Vestibule) MSB (Distribution) 0.00 0.000 0.000 999.9 0.000

B-Water Heater MSB (Distribution) 0.00 0.000 0.000 999.9 0.000

MSB (Main Breaker) MSB (Distribution) 0.00 2.531 -11.334 4.5 11.614

MSB (Gen) MSB (Distribution) 0.00 0.000 0.000 999.9 0.000

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer


* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.
Project: STORE#XXXX
ETAP Page: 11
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

3-phase fault at bus: MSB (Main Breaker)

Prefault voltage = 0.480 = 100.00 % of nominal bus kV ( 0.480 kV)


= 100.00 % of base ( 0.480 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

MSB (Main Breaker) Total 0.00 4.319 -15.881 3.7 16.458

SAMPLE
B-Utility Secondary MSB (Main Breaker) 2.85 2.531 -11.335 4.5 11.614

MSB (Distribution) MSB (Main Breaker) 0.00 1.788 -4.546 2.5 4.885

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer


* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.

REPORT
Project: STORE#XXXX
ETAP Page: 12
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

3-phase fault at bus: Panel DTA

Prefault voltage = 0.480 = 100.00 % of nominal bus kV ( 0.480 kV)


= 100.00 % of base ( 0.480 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

Panel DTA Total 0.00 5.487 -10.554 1.9 11.895

SAMPLE
MSB (Distribution) Panel DTA 37.72 4.783 -8.877 1.9 10.084

Load DTA Panel DTA 100.00 0.704 -1.677 2.4 1.819

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer


* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.

REPORT
Project: STORE#XXXX
ETAP Page: 13
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

3-phase fault at bus: Panel H1A

Prefault voltage = 0.480 = 100.00 % of nominal bus kV ( 0.480 kV)


= 100.00 % of base ( 0.480 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

Panel H1A Total 0.00 4.491 -15.574 3.5 16.209

SAMPLE
MSB (Distribution) Panel H1A 2.39 3.876 -14.112 3.6 14.635

Load H1A Panel H1A 100.00 0.614 -1.462 2.4 1.586

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer


* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.

REPORT
Project: STORE#XXXX
ETAP Page: 14
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

3-phase fault at bus: Panel H1P

Prefault voltage = 0.480 = 100.00 % of nominal bus kV ( 0.480 kV)


= 100.00 % of base ( 0.480 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

Panel H1P Total 0.00 6.016 -13.731 2.3 14.991

SAMPLE
MSB (Distribution) Panel H1P 16.64 6.016 -13.731 2.3 14.991

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer


* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.

REPORT
Project: STORE#XXXX
ETAP Page: 15
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

3-phase fault at bus: Panel L1D1-1

Prefault voltage = 0.208 = 100.00 % of nominal bus kV ( 0.208 kV)


= 100.00 % of base ( 0.208 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

Panel L1D1-1 Total 0.00 2.269 -7.280 3.2 7.626

SAMPLE
B-T1D Sec Panel L1D1-1 2.80 2.269 -7.280 3.2 7.626

Panel L1D1-2 Panel L1D1-1 0.00 0.000 0.000 999.9 0.000

Panel LRX Panel L1D1-1 0.00 0.000 0.000 999.9 0.000

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer

REPORT
* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.
Project: STORE#XXXX
ETAP Page: 16
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

3-phase fault at bus: Panel L1D1-2

Prefault voltage = 0.208 = 100.00 % of nominal bus kV ( 0.208 kV)


= 100.00 % of base ( 0.208 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

Panel L1D1-2 Total 0.00 2.311 -7.161 3.1 7.525

SAMPLE
Panel L1D1-1 Panel L1D1-2 1.66 2.311 -7.161 3.1 7.525

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer


* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.

REPORT
Project: STORE#XXXX
ETAP Page: 17
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

3-phase fault at bus: Panel L1D2-1

Prefault voltage = 0.208 = 100.00 % of nominal bus kV ( 0.208 kV)


= 100.00 % of base ( 0.208 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

Panel L1D2-1 Total 0.00 2.599 -3.488 1.3 4.350

SAMPLE
Circuit Breaker L1D2 Panel L1D2-1 50.96 2.599 -3.488 1.3 4.350

Panel L1D2-2 Panel L1D2-1 0.00 0.000 0.000 999.9 0.000

B-UPS1 Pri Panel L1D2-1 0.00 0.000 0.000 999.9 0.000

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer

REPORT
* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.
Project: STORE#XXXX
ETAP Page: 18
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

3-phase fault at bus: Panel L1D2-2

Prefault voltage = 0.208 = 100.00 % of nominal bus kV ( 0.208 kV)


= 100.00 % of base ( 0.208 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

Panel L1D2-2 Total 0.00 2.593 -3.465 1.3 4.328

SAMPLE
Panel L1D2-1 Panel L1D2-2 0.54 2.593 -3.465 1.3 4.328

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer


* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.

REPORT
Project: STORE#XXXX
ETAP Page: 19
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

3-phase fault at bus: Panel L1U

Prefault voltage = 0.208 = 100.00 % of nominal bus kV ( 0.208 kV)


= 100.00 % of base ( 0.208 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

Panel L1U Total 0.00 1.635 -0.753 0.5 1.800

SAMPLE
B-UPS1 Sec Panel L1U 37.04 1.635 -0.753 0.5 1.800

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer


* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.

REPORT
Project: STORE#XXXX
ETAP Page: 20
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

3-phase fault at bus: Panel LRX

Prefault voltage = 0.208 = 100.00 % of nominal bus kV ( 0.208 kV)


= 100.00 % of base ( 0.208 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

Panel LRX Total 0.00 1.287 -0.367 0.3 1.338

SAMPLE
Panel L1D1-1 Panel LRX 91.56 1.287 -0.367 0.3 1.338

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer


* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.

REPORT
Project: STORE#XXXX
ETAP Page: 21
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

3-phase fault at bus: Panel MTB

Prefault voltage = 0.480 = 100.00 % of nominal bus kV ( 0.480 kV)


= 100.00 % of base ( 0.480 kV)

Contribution 1/2 Cycle


From Bus To Bus %V kA kA Imag. kA Symm.
ID ID From Bus Real Imaginary /Real Magnitude

Panel MTB Total 0.00 4.786 -5.785 1.2 7.508

SAMPLE
MSB (Distribution) Panel MTB 64.32 4.507 -5.120 1.1 6.822

Load MTB Panel MTB 100.00 0.279 -0.665 2.4 0.721

NACD Ratio = 1.00

# Indicates a fault current contribution from a three-winding transformer


* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.

REPORT
Project: STORE#XXXX
ETAP Page: 22
12.6.0C
Location: CIty, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Momentary Duty Summary Report

3-Phase Fault Currents: (Prefault Voltage = 100 % of the Bus Nominal Voltage)

Bus Device Momentary Duty Device Capability


Symm. X/R Asymm. Asymm. Symm. Asymm. Asymm.
ID kV ID Type kA rms Ratio M.F. kA rms kA Peak kA rms kA rms kA Peak

MSB (Distribution) 0.480 MSB (Distribution) Switchboard 16.458 4.0 1.190 19.579 33.880

MSB (Main Breaker) 0.480 MSB (Main Breaker) Switchboard 16.458 4.0 1.190 19.579 33.880

SAMPLE
Panel DTA 0.480 Panel DTA Panelboard 11.895 2.0 1.040 12.369 20.213

Panel H1A 0.480 Panel H1A Panelboard 16.209 3.7 1.171 18.978 32.795

Panel H1P 0.480 Panel H1P Panelboard 14.991 2.4 1.070 16.034 26.890

Panel L1D1-1 0.208 Panel L1D1-1 Panelboard 7.626 3.3 1.136 8.661 14.891

Panel L1D1-2 0.208 Panel L1D1-2 Panelboard 7.525 3.1 1.127 8.481 14.554

Panel L1D2-1 0.208 Panel L1D2-1 Panelboard 4.350 1.3 1.009 4.391 6.748

Panel L1D2-2 0.208 Panel L1D2-2 Panelboard 4.328 1.3 1.009 4.368 6.708

REPORT
Panel L1U 0.208 Panel L1U Panelboard 1.800 0.5 1.000 1.800 2.549

Panel LRX 0.208 Panel LRX Panelboard 1.338 0.3 1.000 1.338 1.893

Panel MTB 0.480 Panel MTB Panelboard 7.508 1.2 1.006 7.556 11.468

Method: IEEE - X/R is calculated from separate R & X networks.


Protective device duty is calculated based on total fault current.
The multiplication factors for high voltage circuit-breaker and high voltage bus momentary duty (asymmetrical and crest values) are calculated based on system X/R.

* Indicates a device with momentary duty exceeding the device capability


Project: STORE#XXXX
ETAP Page: 23
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Interrupting Duty Summary Report

3-Phase Fault Currents: (Prefault Voltage = 100 % of the Bus Nominal Voltage)

Bus Device Interrupting Duty Device Capability


CPT Symm. X/R Adj. Sym. Test Rated Adjusted
ID kV ID Type (Cy) kA rms Ratio M.F. kA rms kV PF Int. Int.
MSB (Distribution) 0.480 CB-H1A MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

SAMPLE
CB-H1P MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

CB-T1D MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

CB-DTA MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

CB-Oven(Top) MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

CB-Sub-Metering MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

CB-Compactor MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

CB-Baler MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

REPORT
CB-AHU1 MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

CB-MTB MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

CB-Oven(Bottom) MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

CB-PLM MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

CB-UH (Vestibule) MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

CB-Water Heater MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

MSB (Main Breaker) 0.480 CB-MBU InsulUnfuse 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000

Panel DTA 0.480 11.895 2.0

Panel H1A 0.480 16.209 3.7

Panel H1P 0.480 14.991 2.4

Panel L1D1-1 0.208 CB-L1D1 Molded Case 7.626 3.3 1.107 8.440 0.240 50.00 10.000 10.000

CB-LRX Molded Case 7.626 3.3 1.107 8.440 0.240 50.00 10.000 10.000

Panel L1D1-2 0.208 7.525 3.1

Panel L1D2-1 0.208 CB-L1U Molded Case 4.350 1.3 1.000 4.350 0.240 50.00 10.000 10.000

Panel L1D2-2 0.208 4.328 1.3

Panel L1U 0.208 1.800 0.5

Panel LRX 0.208 1.338 0.3

Panel MTB 0.480 7.508 1.2

Method: IEEE - X/R is calculated from separate R & X networks.


HV CB interrupting capability is adjusted based on bus nominal voltage
Short-circuit multiplying factor for LV Molded Case and Insulated Case Circuit Breakers is calculated based on asymmetrical current.
Generator protective device duty is calculated based on maximum through fault current. Other protective device duty is calculated based on total fault current.
* Indicates a device with interrupting duty exceeding the device capability
** Indicates that the circuit breaker has been flagged as a generator circuit breaker. However, ETAP could not detect a single path, without a transformer, to the specified generator.
Therefore, this circuit breaker is treated as a regular circuit breaker in short-circuit calculations.
+ The prefault voltage exceeds the rated maximum kV limit of the circuit breaker - The rated interrupting kA must be derated.
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

Appendix E: Arc Flash results

SAMPLE
REPORT

18 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
Project: STORE#XXXX
ETAP Page: 1
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Electrical Transient Analyzer Program

Arc Flash Analysis

IEEE 1584
ANSI Short-Circuit

Number of Buses:
SAMPLE
Swing
1
V-Control
0
Load
28
Total
29

REPORT
XFMR2 XFMR3 Reactor Line/Cable Impedance Tie PD Total
Number of Branches: 2 0 0 23 2 1 28

Synchronous Power Synchronous Induction Lumped


Generator Grid Motor Machines Load Total

Number of Machines: 0 1 0 3 3 7

System Frequency: 60.00 Hz

Unit System: English

Project Filename: PCXXXXX

Output Filename:
Project: STORE#XXXX
ETAP Page: 2
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Adjustments

Apply Individual
Tolerance Adjustments /Global Percent

Transformer Impedance: Yes Individual

Reactor Impedance: Yes Individual

Overload Heater Resistance: No

Transmission Line Length: No

SAMPLE
Cable Length: No

Apply Individual
Temperature Correction Adjustments /Global Degree C

Transmission Line Resistance: Yes Individual

Cable Resistance: Yes Individual

REPORT
Energy Levels

NFPA 70E 2009

Level ID cal/cm²

Level 0 1.20

Level 1 4.00

Level 2 8.00

Level 3 25.00

Level 4 40.00
Project: STORE#XXXX
ETAP Page: 3
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Bus Input Data

Bus Initial Voltage


ID Type Nom. kV Base kV Sub-sys %Mag. Ang.

B-AHU1 Load 0.480 0.480 1 100.00 0.00

B-Baler Load 0.480 0.480 1 1.00 0.00

B-Compactor Load 0.480 0.480 1 100.00 0.00

B-Oven(Bottom) Load 0.480 0.480 1 100.00 0.00

SAMPLE
B-Oven(Top) Load 0.480 0.480 1 100.00 0.00

B-PLM Load 0.480 0.480 1 100.00 0.00

B-Sub-Metering Load 0.480 0.480 1 100.00 0.00

B-T1D Pri Load 0.480 0.480 1 100.00 0.00

B-T1D Sec Load 0.208 0.208 1 100.00 0.00

B-UH (Vestibule) Load 0.480 0.480 1 100.00 0.00

B-UPS1 Pri Load 0.208 0.208 1 100.00 0.00

REPORT
B-UPS1 Sec Load 0.208 0.208 1 100.00 0.00

B-Utility Primary SWNG 13.200 12.470 1 94.47 0.00

B-Utility Secondary Load 0.480 0.480 1 100.00 0.00

B-Water Heater Load 0.480 0.480 1 100.00 0.00

Circuit Breaker L1D2 Load 0.208 0.208 1 100.00 0.00

MSB (Distribution) Load 0.480 0.480 1 1.00 0.00

MSB (Gen) Load 0.480 0.480 1 100.00 0.00

MSB (Main Breaker) Load 0.480 0.480 1 100.00 0.00

Panel DTA Load 0.480 0.480 1 100.00 0.00

Panel H1A Load 0.480 0.480 1 100.00 0.00

Panel H1P Load 0.480 0.480 1 100.00 0.00

Panel L1D1-1 Load 0.208 0.208 1 100.00 0.00

Panel L1D1-2 Load 0.208 0.208 1 1.00 0.00

Panel L1D2-1 Load 0.208 0.208 1 100.00 0.00

Panel L1D2-2 Load 0.208 0.208 1 100.00 0.00

Panel L1U Load 0.208 0.208 1 100.00 0.00

Panel LRX Load 0.208 0.208 1 100.00 0.00

Panel MTB Load 0.480 0.480 1 100.00 0.00

29 Buses Total

All voltages reported by ETAP are in % of bus Nominal kV.


Base kV values of buses are calculated and used internally by ETAP .
Project: STORE#XXXX
ETAP Page: 4
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Bus Arc Flash Input Data

Faulted Bus Arc Flash Ratings Limited Approach Boundary (ft)


Avail. Protection
ID Nom. kV Equip. Type Gap (mm) X Factor Exp. Movable Fixed Circuit Restricted Prohibited cal/cm²

MSB (Distribution) 0.480 Switchboard 32 1.473 10.000 3.500 1.000 0.100 0.0

MSB (Main Breaker) 0.480 Switchboard 32 1.473 10.000 3.500 1.000 0.100 0.0

Panel DTA 0.480 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0

Panel H1A 0.480 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0

Panel H1P 0.480 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0

SAMPLE
Panel L1D1-1 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0

Panel L1D1-2 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0

Panel L1D2-1 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0

Panel L1D2-2 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0

Panel L1U 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0

Panel LRX 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0

REPORT
Panel MTB 0.480 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0

The Gap and X-Factors are not utilized if the theoretically derived Lee method was used to determine the incident energy and arc flash boundary .
The Lee method is used if the bus voltage and/or short-circuit parameters are outside the range covered by the IEEE 1584 empirical equations.
Project: STORE#XXXX
ETAP Page: 5
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Line/Cable Input Data

Ohms or Siemens/1000 ft per Conductor (Cable) or per Phase (Line)

Line/Cable Length

ID Library Size Adj. (ft) % Tol. #/Phase T (°C) R X Y


C-AHU1 0.6MCUN1 4/0 290.0 0 1 75 0.06300 0.05100 0.0000000

C-Baler 0.6MCUN1 10 270.0 0 1 75 1.20000 0.06300 0.0000000

C-Compactor 0.6MCUN1 10 275.0 0 1 75 1.20000 0.06300 0.0000000

SAMPLE
C-DTA 0.6MALN1 300 235.0 0 2 75 0.07200 0.05100 0.0000000

C-H1A 0.6MALN1 250 9.0 0 2 75 0.08600 0.05200 0.0000000

C-H1P 1.0MALN1 1 12.0 0 1 75 0.25000 0.05700 0.0000000

C-L1D1-1 0.6MALN1 300 5.0 0 1 75 0.07200 0.05100 0.0000000

C-L1D1-2 0.6MALN1 300 3.0 0 1 75 0.07200 0.05100 0.0000000

C-L1D2 Line 0.6MALN1 250 3.0 0 2 75 0.08600 0.05200 0.0000000

C-L1D2 Load 0.6MALN1 250 280.0 0 2 75 0.08600 0.05200 0.0000000

REPORT
C-L1D2-2 0.6MALN1 250 3.0 0 2 75 0.08600 0.05200 0.0000000

C-L1U 0.6MCUN1 6 50.0 0 1 75 0.49000 0.06400 0.0000000

C-LRX 0.6MALN1 4 160.0 0 1 75 0.51000 0.06000 0.0000000

C-MBU 0.6MCUN1 300 60.0 0 6 75 0.04500 0.05100 0.0000000

C-MTB 0.6MALN1 250 260.0 0 1 75 0.08600 0.05200 0.0000000

C-Oven(Bottom) 0.6MCUN1 2 275.0 0 1 75 0.20000 0.05700 0.0000000

C-Oven(Top) 0.6MCUN1 8 275.0 0 1 75 0.78000 0.06500 0.0000000

C-PLM 0.6MCUN1 12 5.0 0 1 75 2.00000 0.06800 0.0000000

C-Sub-Metering 0.6MCUN1 12 5.0 0 1 75 2.00000 0.06800 0.0000000

C-T1D Pri 0.6MALN1 300 9.0 0 1 75 0.07200 0.05100 0.0000000

C-UH (Vestibule) 0.6MCUN1 6 5.0 0 1 75 0.49000 0.06400 0.0000000

C-UPS1 0.6MCUN1 6 40.0 0 1 75 0.49000 0.06400 0.0000000

C-Water Heater 0.6MCUN1 2 5.0 0 1 75 0.20000 0.05700 0.0000000

Line / Cable resistances are listed at the specified temperatures.


Project: STORE#XXXX
ETAP Page: 6
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

2-Winding Transformer Input Data

Transformer Rating Z Variation % Tap Setting Adjusted


ID MVA Prim. kV Sec. kV %Z X/R + 5% - 5% % Tol. Prim. Sec. %Z

T1D 0.150 0.480 0.208 4.00 3.45 0 0 0 2.500 2.500 4.0000

Utility Transformer 0.500 12.470 0.480 4.20 5.10 0 0 0 0 0 4.2000

SAMPLE
Impedance Input Data

Impedance Positive Sequence Impedanc


ID R X Y Unit

MSB Bus 0.01 0.01 0 % in 0.480 kV base and 100.0 MVA base

REPORT
MSB Bus 2 0.01 0.01 0 % in 0.480 kV base and 100.0 MVA base
Project: STORE#XXXX
ETAP Page: 7
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Branch Connections

CKT/Branch Connected Bus ID % Impedance, Pos. Seq., 100 MVAb


ID Type From Bus To Bus R X Z Y

T1D 2W XFMR B-T1D Pri B-T1D Sec 779.97 2690.91 2801.67

Utility Transformer 2W XFMR B-Utility Primary B-Utility Secondary 161.63 824.30 840.00

C-AHU1 Cable MSB (Distribution) B-AHU1 792.97 641.93 1020.23

C-Baler Cable MSB (Distribution) B-Baler 14062.50 738.28 14081.87

C-Compactor Cable MSB (Distribution) B-Compactor 14322.92 751.95 14342.64

SAMPLE
C-DTA Cable MSB (Distribution) Panel DTA 367.19 260.09 449.97

C-H1A Cable MSB (Distribution) Panel H1A 16.80 10.16 19.63

C-H1P Cable MSB (Distribution) Panel H1P 130.21 29.69 133.55

C-L1D1-1 Cable B-T1D Sec Panel L1D1-1 83.21 58.94 101.97

C-L1D1-2 Cable Panel L1D1-1 Panel L1D1-2 49.93 35.36 61.18

C-L1D2 Line Cable B-T1D Sec Circuit Breaker L1D2 29.82 18.03 34.84

REPORT
C-L1D2 Load Cable Circuit Breaker L1D2 Panel L1D2-1 2782.91 1682.69 3252.09

C-L1D2-2 Cable Panel L1D2-1 Panel L1D2-2 29.82 18.03 34.84

C-L1U Cable B-UPS1 Sec Panel L1U 5662.91 739.65 5711.01

C-LRX Cable Panel L1D1-1 Panel LRX 18860.95 2218.94 18991.02

C-MBU Cable B-Utility Secondary MSB (Main Breaker) 19.53 22.14 29.52

C-MTB Cable MSB (Distribution) Panel MTB 970.49 586.81 1134.10

C-Oven(Bottom) Cable MSB (Distribution) B-Oven(Bottom) 2387.15 680.34 2482.21

C-Oven(Top) Cable MSB (Distribution) B-Oven(Top) 9309.90 775.82 9342.17

C-PLM Cable MSB (Distribution) B-PLM 434.03 14.76 434.28

C-Sub-Metering Cable MSB (Distribution) B-Sub-Metering 434.03 14.76 434.28

C-T1D Pri Cable MSB (Distribution) B-T1D Pri 28.13 19.92 34.47

C-UH (Vestibule) Cable MSB (Distribution) B-UH (Vestibule) 106.34 13.89 107.24

C-UPS1 Cable Panel L1D2-1 B-UPS1 Pri 4530.33 591.72 4568.81

C-Water Heater Cable MSB (Distribution) B-Water Heater 43.40 12.37 45.13

MSB Bus Impedance MSB (Main Breaker) MSB (Distribution) 0.01 0.01 0.01

MSB Bus 2 Impedance MSB (Gen) MSB (Distribution) 0.01 0.01 0.01

UPS1 Tie Switch B-UPS1 Pri B-UPS1 Sec


Project: STORE#XXXX
ETAP Page: 8
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Power Grid Input Data

% Impedance
Power Grid Connected Bus Rating 100 MVA Base
ID ID MVASC kV X/R R X

Utility B-Utility Primary 58.727 12.470 3.69 44.53977 164.35170

Total Connected Power Grids (= 1 ): 58.727 MVA

SAMPLE
REPORT
Project: STORE#XXXX
ETAP Page: 9
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Induction Machine Input Data

% Impedance
Induction Machine Connected Bus Rating X/R Ratio Machine Base
ID Qty ID HP/kW kVA kV RPM X"/R X'/R R X" X'

Motors
Load AHU1 1 B-AHU1 154.00 147.23 0.480 1800 9.66 9.66 2.07 20.00 50.00

Load Baler 1 B-Baler 10.45 11.65 0.480 1800 2.52 2.52 11.06 27.83 9999.00

Load Compactor 1 B-Compactor 10.45 11.65 0.480 1800 2.52 2.52 11.06 27.83 9999.00

SAMPLE
Total Connected Induction Motors ( = 3 ): 170.5 kVA

Lumped Load Input Data

Lumped Load Motor Loads Static Loads

REPORT
Lumped Load Connected Bus Rating % Load Loading X/R Ratio % Imp. (Machine Base) Loading
ID ID kVA kV MTR STAT kW kvar X"/R X'/R R X" X' kW kvar

Load DTA Panel DTA 328.0 0.480 100 0 278.8 172.8 2.38 2.38 8.403 20.00 50.00 0.00 0.00

Load H1A Panel H1A 286.0 0.480 100 0 243.1 150.7 2.38 2.38 8.403 20.00 50.00 0.00 0.00

Load MTB Panel MTB 130.0 0.480 100 0 110.5 68.5 2.38 2.38 8.403 20.00 50.00 0.00 0.00

Total Connected Lumped Loads ( = 3 ): 744.0 kVA


Project: STORE#XXXX
ETAP Page: 10
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: MSB (Distribution)
Solution Method: 1/2 Cycle

Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 24 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 16.458 Ia" = 9.536 FCT = 3.0 0.050 Incident Energy = 1.001

Fault Clearing Time = 3.0 0.050 Total Incident Energy = 1.001

For Protective Device: CB-MBU@ Ia'' =6.729 kA Energy Level* Level 0

Arc Flash Boundary = 1.77 ft

CB-AHU1
ID
Arc Fault at Device

Phase
Type

3Ph
REPORT
Type

LV CB
Individual Contribution

Bolted
(kA)

0.836
to Bus Arc Fault

Arcing
(kA)

0.484
FCT
(cycles)
Arcing
(kA)

9.536
FCT
(cycles)
3.0

3.0
CB-MBU
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)

1.001

1.001
AFB
(ft)

1.77
Energy
Level*

Level 0
FCT = Total =

CB-Baler 3Ph LV CB 0.046 0.026 9.536 3.0 CB-MBU 1.001

FCT = 3.0 Total = 1.001 1.77 Level 0

CB-Compactor 3Ph LV CB 0.046 0.026 9.536 3.0 CB-MBU 1.001

FCT = 3.0 Total = 1.001 1.77 Level 0

CB-DTA 3Ph LV CB 1.718 0.996 9.536 3.0 CB-MBU 1.001

FCT = 3.0 Total = 1.001 1.77 Level 0

CB-H1A 3Ph LV CB 1.582 0.917 9.536 3.0 CB-MBU 1.001

FCT = 3.0 Total = 1.001 1.77 Level 0

CB-H1P 3Ph LV CB 0.000 0.000 9.536 3.0 CB-MBU 1.001

FCT = 3.0 Total = 1.001 1.77 Level 0


Project: STORE#XXXX
ETAP Page: 11
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: MSB (Distribution)
Solution Method: 1/2 Cycle

Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 24 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 16.458 Ia" = 9.536 FCT = 3.0 0.050 Incident Energy = 1.001

Fault Clearing Time = 3.0 0.050 Total Incident Energy = 1.001

For Protective Device: CB-MBU@ Ia'' =6.729 kA Energy Level* Level 0

Arc Flash Boundary = 1.77 ft

CB-MTB
ID
Arc Fault at Device

Phase
Type

3Ph
REPORT
Type

LV CB
Individual Contribution

Bolted
(kA)

0.683
to Bus Arc Fault

Arcing
(kA)

0.396
FCT
(cycles)
Arcing
(kA)

9.536
FCT
(cycles)
3.0

3.0
CB-MBU
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)

1.001

1.001
AFB
(ft)

1.77
Energy
Level*

Level 0
FCT = Total =

CB-Oven(Bottom) 3Ph LV CB 0.000 0.000 9.536 3.0 CB-MBU 1.001

FCT = 3.0 Total = 1.001 1.77 Level 0

CB-Oven(Top) 3Ph LV CB 0.000 0.000 9.536 3.0 CB-MBU 1.001

FCT = 3.0 Total = 1.001 1.77 Level 0

CB-PLM 3Ph LV CB 0.000 0.000 9.536 3.0 CB-MBU 1.001

FCT = 3.0 Total = 1.001 1.77 Level 0

CB-Sub-Metering 3Ph LV CB 0.000 0.000 9.536 3.0 CB-MBU 1.001

FCT = 3.0 Total = 1.001 1.77 Level 0

CB-T1D 3Ph LV CB 0.000 0.000 9.536 3.0 CB-MBU 1.001

FCT = 3.0 Total = 1.001 1.77 Level 0


Project: STORE#XXXX
ETAP Page: 12
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: MSB (Distribution)
Solution Method: 1/2 Cycle

Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 24 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 16.458 Ia" = 9.536 FCT = 3.0 0.050 Incident Energy = 1.001

Fault Clearing Time = 3.0 0.050 Total Incident Energy = 1.001

For Protective Device: CB-MBU@ Ia'' =6.729 kA Energy Level* Level 0

Arc Flash Boundary = 1.77 ft

ID

CB-UH (Vestibule)
Arc Fault at Device

Phase
Type

3Ph
REPORT
Type

LV CB
(kA)
Individual Contribution

Bolted

0.000
to Bus Arc Fault

Arcing
(kA)

0.000
FCT
(cycles)
Arcing
(kA)

9.536
FCT
(cycles)
3.0

3.0
CB-MBU
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)

1.001

1.001
AFB
(ft)

1.77
Energy
Level*

Level 0
FCT = Total =

CB-Water Heater 3Ph LV CB 0.000 0.000 9.536 3.0 CB-MBU 1.001

FCT = 3.0 Total = 1.001 1.77 Level 0

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 13
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: MSB (Main Breaker)
Solution Method: 1/2 Cycle

Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 24 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 16.458 ¨Ia" = 8.106 FCT = 6987.5 116.459 Incident Energy = 1956.103

Fault Clearing Time = 6987.5 116.459 Total Incident Energy = 1956.103

For Protective Device: Utility TX Fuse@ 85% Ia'' Energy Level* >Max.
=0.220 kA
Arc Flash Boundary = 303.15 ft

¨ CB-MBU
ID
Arc Fault at Device

Phase
Type

3Ph
REPORT
Type

LV CB
(kA)
Individual Contribution

Bolted

11.614
to Bus Arc Fault

Arcing
(kA)

5.720
FCT
(cycles)
3.0
Arcing
(kA)

8.106
FCT
(cycles)
6987.5

6987.5
Incident Energy

Protective Device ID
for FCT
Utility TX Fuse
Incident E
(cal/cm²)

1956.103

1956.103
AFB
(ft)

303.15
Energy
Level*

>Max.
FCT = Total =

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 14
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: Panel DTA
Solution Method: 1/2 Cycle

Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 18 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 11.895 Ia" = 7.605 FCT = 1.6 0.026 Incident Energy = 0.647

Fault Clearing Time = 1.6 0.026 Total Incident Energy = 0.647

For Protective Device: CB-DTA@ Ia'' =6.447 kA Energy Level* Level 0

Arc Flash Boundary = 1.03 ft

ID
Arc Fault at Device

Phase
Type REPORT
Type (kA)
Individual Contribution

Bolted
to Bus Arc Fault

Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 15
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: Panel H1A
Solution Method: 1/2 Cycle

Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 18 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 16.209 Ia" = 9.906 FCT = 1.5 0.025 Incident Energy = 0.822

Fault Clearing Time = 1.5 0.025 Total Incident Energy = 0.822

For Protective Device: CB-H1A@ Ia'' =8.945 kA Energy Level* Level 0

Arc Flash Boundary = 1.19 ft

ID
Arc Fault at Device

Phase
Type REPORT
Type (kA)
Individual Contribution

Bolted
to Bus Arc Fault

Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 16
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: Panel H1P
Solution Method: 1/2 Cycle

Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 18 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 14.991 Ia" = 9.267 FCT = 1.5 0.025 Incident Energy = 0.765

Fault Clearing Time = 1.5 0.025 Total Incident Energy = 0.765

For Protective Device: CB-H1P@ Ia'' =9.267 kA Energy Level* Level 0

Arc Flash Boundary = 1.14 ft

ID
Arc Fault at Device

Phase
Type REPORT
Type (kA)
Individual Contribution

Bolted
to Bus Arc Fault

Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 17
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: Panel L1D1-1
Solution Method: 1/2 Cycle

Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 7.626 Ia" = 3.596 FCT = 1.5 0.025 Incident Energy = 0.275

Fault Clearing Time = 1.5 0.025 Total Incident Energy = 0.275

For Protective Device: CB-T1D@ Ia'' =1.558 kA Energy Level* Level 0

Arc Flash Boundary = 0.61 ft

CB-L1D1
ID
Arc Fault at Device

Phase
Type

3Ph
REPORT
Type

LV CB
(kA)
Individual Contribution

Bolted

7.626
to Bus Arc Fault

Arcing
(kA)

3.596
FCT
(cycles)
244.7
Arcing
(kA)

3.596
FCT
(cycles)
1.5

1.5
CB-T1D
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)

0.275

0.275
AFB
(ft)

0.61
Energy
Level*

Level 0
FCT = Total =

CB-LRX 3Ph LV CB 0.000 0.000 3.596 1.5 CB-T1D 0.275

FCT = 1.5 Total = 0.275 0.61 Level 0

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 18
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: Panel L1D1-2
Solution Method: 1/2 Cycle

Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 7.525 Ia" = 3.562 FCT = 1.5 0.025 Incident Energy = 0.272

Fault Clearing Time = 1.5 0.025 Total Incident Energy = 0.272

For Protective Device: CB-T1D@ Ia'' =1.544 kA Energy Level* Level 0

Arc Flash Boundary = 0.61 ft

ID
Arc Fault at Device

Phase
Type REPORT
Type (kA)
Individual Contribution

Bolted
to Bus Arc Fault

Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 19
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: Panel L1D2-1
Solution Method: 1/2 Cycle

Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 4.350 Ia" = 2.424 FCT = 1.5 0.025 Incident Energy = 0.179

Fault Clearing Time = 1.5 0.025 Total Incident Energy = 0.179

For Protective Device: CB-L1D2@ Ia'' =2.424 kA Energy Level* Level 0

Arc Flash Boundary = 0.47 ft

CB-L1U
ID
Arc Fault at Device

Phase
Type

3Ph
REPORT
Type

LV CB
(kA)
Individual Contribution

Bolted

0.000
to Bus Arc Fault

Arcing
(kA)

0.000
FCT
(cycles)
Arcing
(kA)

2.424
FCT
(cycles)
1.5

1.5
CB-L1D2
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)

0.179

0.179
AFB
(ft)

0.47
Energy
Level*

Level 0
FCT = Total =

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 20
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: Panel L1D2-2
Solution Method: 1/2 Cycle

Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 4.328 Ia" = 2.416 FCT = 1.5 0.025 Incident Energy = 0.179

Fault Clearing Time = 1.5 0.025 Total Incident Energy = 0.179

For Protective Device: CB-L1D2@ Ia'' =2.416 kA Energy Level* Level 0

Arc Flash Boundary = 0.47 ft

ID
Arc Fault at Device

Phase
Type REPORT
Type (kA)
Individual Contribution

Bolted
to Bus Arc Fault

Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 21
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: Panel L1U
Solution Method: 1/2 Cycle

Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 1.800 ¨Ia" = 1.109 FCT = 2.3 0.038 Incident Energy = 0.118

Fault Clearing Time = 2.3 0.038 Total Incident Energy = 0.118

For Protective Device: CB-L1D2@ 85% Ia'' =1.109 kA Energy Level* Level 0

Arc Flash Boundary = 0.36 ft

ID
Arc Fault at Device

Phase
Type REPORT
Type (kA)
Individual Contribution

Bolted
to Bus Arc Fault

Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 22
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: Panel LRX
Solution Method: 1/2 Cycle

Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 1.338 ¨Ia" = 0.901 FCT = 94.2 1.570 Incident Energy = 3.864

Fault Clearing Time = 94.2 1.570 Total Incident Energy = 3.864

For Protective Device: CB-LRX@ 85% Ia'' =0.901 kA Energy Level* Level 1

Arc Flash Boundary = 3.06 ft

ID
Arc Fault at Device

Phase
Type REPORT
Type (kA)
Individual Contribution

Bolted
to Bus Arc Fault

Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 23
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Arc Flash Analysis


1/2 Cycle Calculation Method
Arc Fault at Bus: Panel MTB
Solution Method: 1/2 Cycle

Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 18 inches

Bus Arc Flash Results


Total Bolted Total Arcing Fault Clearing Time

SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)

Ibf" = 7.508 Ia" = 5.134 FCT = 1.5 0.025 Incident Energy = 0.404

Fault Clearing Time = 1.5 0.025 Total Incident Energy = 0.404

For Protective Device: CB-MTB@ Ia'' =4.664 kA Energy Level* Level 0

Arc Flash Boundary = 0.77 ft

ID
Arc Fault at Device

Phase
Type REPORT
Type (kA)
Individual Contribution

Bolted
to Bus Arc Fault

Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy

Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*

* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 24
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal

Incident Energy Summary

Total Fault Arc-Flash Analysis Results


Bus Current (kA) FCT Incident E Energy
AFB
ID Nom. kV Type Bolted Arcing (cycles) (cal/cm²) (ft) Level
MSB (Distribution) 0.480 Switchboard 16.458 9.536 3.000 1.001 1.77 Level 0

MSB (Main Breaker) 0.480 Switchboard 16.458 8.106 6987.547 1956.103 303.15 >Max.

Panel DTA 0.480 Panelboard 11.895 7.605 1.572 0.647 1.03 Level 0

Panel H1A 0.480 Panelboard 16.209 9.906 1.500 0.822 1.19 Level 0

SAMPLE
Panel H1P 0.480 Panelboard 14.991 9.267 1.500 0.765 1.14 Level 0

Panel L1D1-1 0.208 Panelboard 7.626 3.596 1.500 0.275 0.61 Level 0

Panel L1D1-2 0.208 Panelboard 7.525 3.562 1.500 0.272 0.61 Level 0

Panel L1D2-1 0.208 Panelboard 4.350 2.424 1.500 0.179 0.47 Level 0

Panel L1D2-2 0.208 Panelboard 4.328 2.416 1.500 0.179 0.47 Level 0

Panel L1U 0.208 Panelboard 1.800 1.109 2.291 0.118 0.36 Level 0

REPORT
Panel LRX 0.208 Panelboard 1.338 0.901 94.224 3.864 3.06 Level 1

Panel MTB 0.480 Panelboard 7.508 5.134 1.500 0.404 0.77 Level 0

Summary - Arc Flash Hazard Calculations

Faulted Bus Fault Current Trip Device Arc Flash Incident Working
Gap Bolted Fault (kA) PD Arc Trip Open FCT Boundary Energy Distance Energy
ID Nom. kV Equip. Type (mm) Bus PD Fault (kA) Source Trip Device ID (cycle) (cycle) (cycle) (ft) (cal/cm²) (inches) Level

MSB (Distribution) 0.480 Switchboard 32 16.458 11.614 6.729 CB-MBU 3.00 0.00 3.00 1.8 1.0 24 Level 0

MSB (Main Breaker) 0.480 Switchboard 32 16.458 0.447 0.220 Utility TX Fuse 6987.55 0.00 6987.55 303.2 1956.1 24 >Max.

Panel DTA 0.480 Panelboard 25 11.895 10.084 6.447 CB-DTA 1.57 0.00 1.57 1.0 0.6 18 Level 0

Panel H1A 0.480 Panelboard 25 16.209 14.635 8.945 CB-H1A 1.50 0.00 1.50 1.2 0.8 18 Level 0

Panel H1P 0.480 Panelboard 25 14.991 14.991 9.267 CB-H1P 1.50 0.00 1.50 1.1 0.8 18 Level 0

Panel L1D1-1 0.208 Panelboard 25 7.626 3.305 1.558 CB-T1D 1.50 0.00 1.50 0.6 0.3 18 Level 0

Panel L1D1-2 0.208 Panelboard 25 7.525 3.261 1.544 CB-T1D 1.50 0.00 1.50 0.6 0.3 18 Level 0

Panel L1D2-1 0.208 Panelboard 25 4.350 4.350 2.424 CB-L1D2 1.50 0.00 1.50 0.5 0.2 18 Level 0

Panel L1D2-2 0.208 Panelboard 25 4.328 4.328 2.416 CB-L1D2 1.50 0.00 1.50 0.5 0.2 18 Level 0

Panel L1U 0.208 Panelboard 25 1.800 1.800 1.109 CB-L1D2 2.29 0.00 2.29 0.4 0.1 18 Level 0

Panel LRX 0.208 Panelboard 25 1.338 1.338 0.901 CB-LRX 94.22 0.00 94.22 3.1 3.9 18 Level 1

Panel MTB 0.480 Panelboard 25 7.508 6.822 4.664 CB-MTB 1.50 0.00 1.50 0.8 0.4 18 Level 0
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

Appendix F: Equipment labels

SAMPLE
REPORT

19 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
Arc Flash and Shock Hazard Present Arc Flash and Shock Hazard Present
Appropriate PPE Required Appropriate PPE Required
Arc Flash Boundary (Dc) 1.8 ft Level 0 Arc Flash Boundary (Dc) 1.0 ft Level 0
Incident Energy (Ed) 1.0 cal/cm² Incident Energy (Ed) 0.6 cal/cm²
Working Distance 24.0 in Min. PPE Requirements Working Distance 18.0 in Min. PPE Requirements
Shock Hazard Exposure 480 VAC PPE Requirements have not been Shock Hazard Exposure 480 VAC PPE Requirements have not been
approved approved
Shock Hazard when covers removed Shock Hazard when covers removed

SAMPLE
Class 00 Insulating Gloves Class 00 Insulating Gloves
V-rating 500 VAC V-rating 500 VAC
Limited Approach Boundary 3.5 ft Limited Approach Boundary 3.5 ft
Restricted Approach Boundary 1.0 ft Restricted Approach Boundary 1.0 ft
Prohibited Approach Boundary 0.1 ft Prohibited Approach Boundary 0.1 ft
Source protective Device CB-MBU Source protective Device CB-DTA
Equipment MSB (Distribution) 02-11-2016 Equipment Panel DTA 02-11-2016

REPORT
Arc Flash and Shock Hazard Present
Appropriate PPE Required
Arc Flash Boundary (Dc) 303.2 ft
Incident Energy (Ed) 1956.1 cal/cm²
Working Distance 24.0 in
Arc Flash and Shock Hazard Present
Appropriate PPE Required
Arc Flash Boundary (Dc) 1.2 ft
Incident Energy (Ed) 0.8 cal/cm²
Working Distance 18.0 in
Level 0

Min. PPE Requirements


Shock Hazard Exposure 480 VAC Shock Hazard Exposure 480 VAC PPE Requirements have not been
approved
Shock Hazard when covers removed Shock Hazard when covers removed
Class 00 Insulating Gloves Class 00 Insulating Gloves
V-rating 500 VAC
Exceeds Max. PPE Arc Rating V-rating 500 VAC
Limited Approach Boundary 3.5 ft Limited Approach Boundary 3.5 ft
Restricted Approach Boundary 1.0 ft Restricted Approach Boundary 1.0 ft
Prohibited Approach Boundary 0.1 ft Prohibited Approach Boundary 0.1 ft
Source protective Device Utility TX Fuse Source protective Device CB-H1A
Equipment MSB (Main Breaker) 02-11-2016 Equipment Panel H1A 02-11-2016
Arc Flash and Shock Hazard Present Arc Flash and Shock Hazard Present
Appropriate PPE Required Appropriate PPE Required
Arc Flash Boundary (Dc) 1.1 ft Level 0 Arc Flash Boundary (Dc) 0.6 ft Level 0
Incident Energy (Ed) 0.8 cal/cm² Incident Energy (Ed) 0.3 cal/cm²
Working Distance 18.0 in Min. PPE Requirements Working Distance 18.0 in Min. PPE Requirements
Shock Hazard Exposure 480 VAC PPE Requirements have not been Shock Hazard Exposure 208 VAC PPE Requirements have not been
approved approved
Shock Hazard when covers removed Shock Hazard when covers removed

SAMPLE
Class 00 Insulating Gloves Class 00 Insulating Gloves
V-rating 500 VAC V-rating 500 VAC
Limited Approach Boundary 3.5 ft Limited Approach Boundary 3.5 ft
Restricted Approach Boundary 1.0 ft Restricted Approach Boundary 1.0 ft
Prohibited Approach Boundary 0.1 ft Prohibited Approach Boundary 0.1 ft
Source protective Device CB-H1P Source protective Device CB-T1D
Equipment Panel H1P 02-11-2016 Equipment Panel L1D1-2 02-11-2016

REPORT
Arc Flash and Shock Hazard Present
Appropriate PPE Required
Arc Flash Boundary (Dc) 0.6 ft
Incident Energy (Ed) 0.3 cal/cm²
Working Distance 18.0 in
Level 0

Min. PPE Requirements


Arc Flash and Shock Hazard Present
Appropriate PPE Required
Arc Flash Boundary (Dc) 0.5 ft
Incident Energy (Ed) 0.2 cal/cm²
Working Distance 18.0 in
Level 0

Min. PPE Requirements


Shock Hazard Exposure 208 VAC PPE Requirements have not been Shock Hazard Exposure 208 VAC PPE Requirements have not been
approved approved
Shock Hazard when covers removed Shock Hazard when covers removed
Class 00 Insulating Gloves Class 00 Insulating Gloves
V-rating 500 VAC V-rating 500 VAC
Limited Approach Boundary 3.5 ft Limited Approach Boundary 3.5 ft
Restricted Approach Boundary 1.0 ft Restricted Approach Boundary 1.0 ft
Prohibited Approach Boundary 0.1 ft Prohibited Approach Boundary 0.1 ft
Source protective Device CB-T1D Source protective Device CB-L1D2
Equipment Panel L1D1-1 02-11-2016 Equipment Panel L1D2-1 02-11-2016
Arc Flash and Shock Hazard Present Arc Flash and Shock Hazard Present
Appropriate PPE Required Appropriate PPE Required
Arc Flash Boundary (Dc) 0.5 ft Level 0 Arc Flash Boundary (Dc) 3.1 ft Level 1
Incident Energy (Ed) 0.2 cal/cm² Incident Energy (Ed) 3.9 cal/cm²
Working Distance 18.0 in Min. PPE Requirements Working Distance 18.0 in Min. PPE Requirements
Shock Hazard Exposure 208 VAC PPE Requirements have not been Shock Hazard Exposure 208 VAC PPE Requirements have not been
approved approved
Shock Hazard when covers removed Shock Hazard when covers removed

SAMPLE
Class 00 Insulating Gloves Class 00 Insulating Gloves
V-rating 500 VAC V-rating 500 VAC
Limited Approach Boundary 3.5 ft Limited Approach Boundary 3.5 ft
Restricted Approach Boundary 1.0 ft Restricted Approach Boundary 1.0 ft
Prohibited Approach Boundary 0.1 ft Prohibited Approach Boundary 0.1 ft
Source protective Device CB-L1D2 Source protective Device CB-LRX
Equipment Panel L1D2-2 02-11-2016 Equipment Panel LRX 02-11-2016

REPORT
Arc Flash and Shock Hazard Present
Appropriate PPE Required
Arc Flash Boundary (Dc) 0.4 ft
Incident Energy (Ed) 0.1 cal/cm²
Working Distance 18.0 in
Level 0

Min. PPE Requirements


Arc Flash and Shock Hazard Present
Appropriate PPE Required
Arc Flash Boundary (Dc) 0.8 ft
Incident Energy (Ed) 0.4 cal/cm²
Working Distance 18.0 in
Level 0

Min. PPE Requirements


Shock Hazard Exposure 208 VAC PPE Requirements have not been Shock Hazard Exposure 480 VAC PPE Requirements have not been
approved approved
Shock Hazard when covers removed Shock Hazard when covers removed
Class 00 Insulating Gloves Class 00 Insulating Gloves
V-rating 500 VAC V-rating 500 VAC
Limited Approach Boundary 3.5 ft Limited Approach Boundary 3.5 ft
Restricted Approach Boundary 1.0 ft Restricted Approach Boundary 1.0 ft
Prohibited Approach Boundary 0.1 ft Prohibited Approach Boundary 0.1 ft
Source protective Device CB-L1D2 Source protective Device CB-MTB
Equipment Panel L1U 02-11-2016 Equipment Panel MTB 02-11-2016
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800

Appendix G: Reference Documents

SAMPLE
REPORT

20 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State

Vous aimerez peut-être aussi