Académique Documents
Professionnel Documents
Culture Documents
SAMPLE
REPORT Revision Control
1|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
Table of Contents
1. Executive Summary
2. Calculation Objective
3. Calculation Method – Software Used: ETAP Version
12.6.0
4. Protective Device Coordination – Design Basis
SAMPLE
5. Short Circuit Study - Design Basis
6. Conclusions – Arc Flash Hazard Analysis
7. References
Appendix A
Appendix B
Appendix C REPORT
ETAP One Line diagram
INPUT DATA and Assumptions
Coordination study report – including overcurrent
protective device settings
Appendix D Short Circuit results
Appendix E Arc Flash results
Appendix F Equipment Labels
Appendix G Reference Documents
2|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
1 Executive Summary
1.1 Results
An arc-flash hazard mitigation study was completed for Store #XXXX in City, State using the ETAP Electrical
Engineering Software Program by PCX Corporation. These are the key findings of this electrical engineering study:
A. Using the methodology prescribed in section 2, Zero (0) equipment buses within the plant were computed
with an arc flash hazard incident energy level greater than 40cal/cm2 at recommended settings for the
breakers in the system.
B. Two main breakers have setpoints available – Utility and Generator. All Main Switch Board (MSB)
settings were analyzed at the recommended settings for the two main breakers for this study.
C. The Main Switchboard MSB (Main Breaker Section) requires to be labeled for the worst case arc flash
hazard.
D. 208VAC panels have an energy level 0 arc flash hazard based on GE Spectra series Panelboards and
breakers when all CB are set to minimum instantaneous values, with the exception of panel LRX, which
SAMPLE
has an energy level 1 arc flash hazard.
E. The following 480VAC panel has an energy level 4 arc flash hazard:
i. MSB (Main Breaker)
F. Panels CHA1, CHA2, and CHB have been excluded from this study due to lack of field information.
G. Refer to Series rating document in appendix G (as required).
1.2 Recommendations
After reviewing the results of the Arc-Flash Hazard Analysis, the following actions are recommended:
REPORT
A. Utility main setpoints should be:
i. Long time pickup: 1 (1600A);
ii. Long time band: 1
iii. Short time pickup: 4 (6400A)
iv. Short time Band: Min (1)
v. I2t setpoint: OUT
vi. Instantaneous: 3 (4800A)
vii. Ground pickup: 0.4 (640A)
viii. Ground Band: 1
ix. Ground I2t: OUT
3|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
C. MSB Distribution breakers should have the following instantaneous trip settings:
i. H1A: 5 (3162 A)
ii. H1P: MIN
iii. T1D: MIN
iv. DTA: 5 (3528.9 A)
v. MTB: MAX
vi. AHU1: MAX
vii. Baler: MAX
viii. Compactor: MAX
ix. Sub-Metering: MIN
x. Oven (Top): MIN
xi. Oven (Bottom): MIN
xii. PLM: MIN
xiii. UH (Vestibule): MIN
xiv. Water Heater: MIN
D. Ensure all other MCB Instantaneous settings are set to MINIMUM ensuring incident energy levels are
between categories 0-1.
E. Verify breaker settings on an annual basis to ensure arc flash hazard does not increase for the breakers
SAMPLE
identified in Appendix C: coordination study report.
F. Install the arc flash hazard study warning labels on applicable equipment throughout the store in
accordance with [2]. Whenever changes are made to the power system, subsequent studies may be
required to validate existing settings of devices.
G. Lower all 208VAC transformers to less than 125kva eliminating the requirement to include them in Arc
flash studies. NFPA70E, 2009 edition indicates that IEEE 1584 describes arc flash requirements for
3phase systems rated less than 240VAC. Section 4.2 of IEEE 1584 states “Equipment below 240 V need
not be considered unless it involves at least one 125 kVA or larger low impedance transformer in its
REPORT
immediate power supply.”
H. Update arc flash study every [5] years as described in NFPA70E, section 130.5.
I. Maintain an electrically safe work place. Insist that all electrical contractors and other outside construction
personnel servicing, maintaining, and/or making adjustments to energized power system equipment are
equipped with properly rated PPE based upon the results of this arc flash study prior to start of work.
J. Continue to perform routine preventive maintenance on all circuit breakers and electrical equipment as
recommended by [3] at regular service intervals.
2 Calculation Objective
ARC-FLASH HAZARD ANALYSIS – SCOPE:
Determine arc-flash incident energy levels and flash protection boundary distances based on the results of the
Short-Circuit and Coordination studies. To determine if the first upstream protective device de-energizes the arc
fault and if not identify any location where this may occur. Perform the analysis under worst-case arc-flash
conditions for all modes of operation. We received transformer available fault current information from the utility
and used the values provided by the utility. The values used are as follows:
1. KVA-500
2. Primary Voltage- 12,470
3. Secondary Voltage-480
4. Impedance-4.2 %
5. X/R- 3.69
6. Fuse-Cooper Bay-O-Net 60A
4|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
Identify all locations and equipment to be included in the arc-flash hazard analysis:
Results of the arc-flash study shall be summarized in a final report containing the following:
1. Basis, method of hazard assessment, description, purpose, scope, and date of the study.
SAMPLE
2. Tabulations of the data used to model the system components and a corresponding one-line diagram.
3. Descriptions of the scenarios evaluated and identification of the scenario used to evaluate
equipment ratings.
4. Tabulations of equipment incident energies, hazard risk categories, and flash protection boundaries. The
tabulation shall identify and clearly note equipment that exceeds allowable Incident energy ratings.
5. Required arc-flash labels and installation instructions.
6. Conclusions and recommendations
REPORT
2.1 Objectives
The primary goals of this study were as follows:
1 To investigate existing arc flash hazard incident energy (IE) levels at the facility
2 To improve the coordination and selectivity between upstream and downstream overcurrent protective
devices at the plant, if possible, without compromising equipment protection boundaries and selective
coordination between upstream and downstream overcurrent protection devices.
3 To report all overcurrent protective devices with inadequate short circuit current interrupting ratings based
upon the computed available fault current.
4 Verify arc hazard levels at all panels 208VAC and above.
2.2 Methodology
Field data provided for the electrical power system at the facility was used to construct a digital computer model for
detailed electrical engineering analysis with the ETAP software program version 12.5.0. Some examples of the
typical field data required to perform this analysis include:
1 Motor Nameplate
2 Conductor Sizes and Lengths
3 Transformer Nameplate
4 Utility Thevenin Impedance
5 Breaker Ratings, Settings, and OEM Fuse Ratings and OEM Equipment Bus Short Circuit Rating
The ETAP computer model of the electrical one-line diagram of the store 0.48 kV and 0.208 kV secondary
distribution systems is shown in the one-line diagram.
The analysis includes a “Base” scenario based upon existing plant conditions and a revision with “minimum”
protective device pickup settings with modified device settings and ratings to provide the lowest possible arc flash
5|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
incident energy levels while achieving the best selective coordination between upstream and downstream
overcurrent protective devices without compromising existing equipment protection boundaries.
When a generator is included in the store, an alternate scenario is run for the generator supplied loads with the
main utility disconnected. In this instance the utility case resulted in a higher hazard energy level.
An arc-flash hazard analysis is an electrical engineering study’s main purpose to calculate the level of thermal
energy exposure to the personnel because of an electric arc-flash event [5]. Computed incident energy levels are
largely dependent upon the computed available fault current and device clearing times, which are produced by
short circuit current and protective device coordination studies.
Based upon the results of the arc flash hazard study, the rating of personal protective equipment (PPE) such as
gloves, arc-rated shirts and pants, eye protection, etc…can be properly selected for adequate personnel protection
as required by [5]. Note that there is a difference between fire-rated and arc-rated equipment. PPE needed for an
arc flash event should have an arc-rating and not just a fire-rated capability.
3 Calculation Method
SAMPLE
Arc Flash Analysis Process
IEEE 1584 establishes a nine-step process for gathering information and calculating arc flash hazards. The steps
are:
REPORT
Collecting system data is the most difficult and time-intensive step in performing an arc flash hazard analysis, but
accurate information is vital to correctly calculating flash boundaries. A relatively small error at this point can
invalidate all further arc flash calculations. IEEE 1584-2002 lists the minimum information that should be gathered,
as shown in the table below. Information collected from facility's electrical system should be recorded and properly
documented on the one-line diagram or any other acceptable data collection database. The one-line diagram and
electrical database should be kept up to date as much as possible whenever modifications are made to the system
.
6|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
Model
Trip or sensor setting
Breakers
The following information is as it applies to the particular breaker:
Plug, LTPU, LTD, STPU, STD, and INST
Model
Fuses
Trip
Motors Nominal HP
SAMPLE
which only backup generators provide power; multiple utility sources or generators that are switched in or out; and
motors or portions of the system that may start or cease operation. All of these different modes cause changes in
current at various points in the system, altering incident energy and flash boundaries.
REPORT
The bolted fault current is the current that would flow through a short circuit consisting of two conductors bolted
together. It is the maximum current available to flow through a short circuit. This information is used to calculate the
arc fault currents. Bolted fault currents should be determined for each piece of equipment likely to require
maintenance or inspection while energized. Information on the minimum bolted fault currents is also needed but
typically considered by assuming a minimum number of contributing sources to the fault. It is possible that the
worst-case incident energy will occur when the bolted fault current is at a minimum.
The time-current curves of upstream protective devices are the major factor in determining how long an arc-fault
will last. An effort should be made to determine the actual settings rather than relying on standard values, as these
may cause incident energy to vary greatly.
Another consideration when analyzing protective devices is that incident energy depends on both fault current and
time. Since protective devices are slower at lower currents, minimum fault currents often pose the worst-case arc
flash scenario as mentioned before.
SAMPLE
7. Establish working distances
The working distance is the distance from a potential arc source to a worker's face and chest. It is a critical quantity
REPORT
in determining the flash hazard boundary, as even an increase of a few inches in working distance can cause a
significant drop in incident energy. 18 inches is the working distance most commonly assumed in calculations, but
efforts should be made to determine actual working distances. Some usual working distances are shown in the
table below.
(1) E = 4.184(Cf)(En)(t/0.2)(610x/Dx)
Where E = incident energy in joules/cm2; Cf is a calculation factor (1.0 for voltages above 1 kV, and 1.5 for voltages
below 1 kV); En = normalized incident energy (from equation (2) below); t = arc duration in seconds; D = distance
8|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
SAMPLE
systems; G = arc gap in mm; Ia = predicted 3-phase arc fault current in kA
REPORT
The AFB is the distance at which incident energy exposure is about 1.2 cal/cm2, which is equivalent to the energy
required to cause the onset of a second-degree burn. The IEEE formula for calculating AFB is:
DB = [4.184(Cf)(En)(t/0.2)(610x/EB)]1/x
where EB is the desired incident energy at the boundary (usually 1.2 cal/cm2, but occasionally set at a value
matching proposed PPE rating), with other variables defined as for the incident energy equations above.
4.1 Discussion
The main objectives of the protective device coordination study are to prevent injury to personnel, to minimize
damage to system components, and to limit the extent and duration of service interruption whenever equipment
failure, human error, or adverse natural events occur on any portion of the electrical power system [4].
The term “selective coordination” simply implies that devices are carefully selected or adjusted to “trip” or operate
in a certain desired sequence during fault conditions, preferably beginning with the device closest to the fault
followed by the upstream protector(s). Using this methodology, extensive plant outages and safety hazards to
personnel and equipment can be avoided by localizing faults to the closest protective device [2].
Based on stated objectives, the settings of molded case circuit breakers (MCCB) and static trip units (STU) were
carefully analyzed and adjusted - wherever device adjustments were permissible - in order to obtain “selectivity”
9|P age
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
between upstream and downstream overcurrent protective devices without compromising equipment protective
boundaries, transformer inrush, and motor starting criteria.
This functional dependence between IF and IP is illustrated graphically in Fig. 2[7]. In this study, very few
opportunities for adjustments were possible due to the installation of mostly MCCB’s with fixed settings and fuses;
however, one coordination discrepancy can be corrected by making proper adjustments to the long time and
SAMPLE
instantaneous settings of the upstream device and is graphically illustrated in Appendix “E.”
REPORT
placed at a maximum pickup value). In addition, a “Recommended” case is included with revised settings required
to attain selective coordination, and most importantly, reduce arc flash hazard incident energy levels (Where
possible). Also shown are transformer inrush/damage curves, motor starting profile curves, cable and conductor
thermal curves, and a miniature section of the one-line diagram where the devices are taken from. These curves
and points are plotted to provide a visual, graphical representation of the existing equipment protection boundaries
for proper coordination and application of overcurrent protective devices.
5.1 Discussion
Short circuit current studies are performed to determine the magnitude of currents flowing throughout the
power systems at various time intervals after a “fault” or abnormal condition occurs [4], [6]. These currents
must be calculated in order to adequately specify electrical equipment bus withstand ratings and
overcurrent protective device interrupting duties.
Computer modeling using the ETAP Electrical Engineering software program by PCX was done by
expressing the per unit impedances of all relevant electrical power system components (i.e.,
Transformers, motors, cables, etc…) on a common 100 MVA base and using symmetrical components
theory to derive available fault current values at each specific bus.
The IEEE 1584 and NFPA 70E methodology only have equations to calculate the arc fault current for
three-phase bolted faults. It is likely that arc faults may initiate as line-to-ground faults, but the
methodology available makes the conservative assumption that the fault will quickly escalate to a three-
phase arc fault.
10 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
SAMPLE
5 Relay Instantaneous Trip Settings
The ½ Cycle Network is also preferred to as the “subtransient” impedance network, primarily because all
of the AC rotating machines are represented by their subtransient reactance (X”d), as indicated below:
REPORT
2 Utility X”
3 Induction Machines:
• >1000 Hp @1800 Rpm or Less X”D
• >250 Hp @ 3600 Rpm X”D
• All Other ≥50 Hp 1.2 X”D
6.1 Discussion
The ultimate goal of an arc-flash hazard analysis (AFHA) is to compute incident energy levels and arc flash
boundary distances at all relevant equipment locations in order to determine the thermal energy exposure to which
personnel can be exposed when performing energized work. The end-result is the proper selection of arc-rated
personal protective equipment (PPE), as prescribed by [5]. Incident energy (IE) level magnitudes, measured in
cal/cm2 or joules/cm2, are dependent upon the available 3-phase fault current computed at equipment buses, and
perhaps to an even greater degree, the actual total fault current clearing time of the upstream overcurrent
protective device(s).
Note that according to [1], arc flash hazard calculations pertain to three-phase
electrical power systems only. Single-phase power systems and equipment
encountered at the plant are not included in the arc flash calculations in this
study!
11 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
Wherever possible, the primary objective of the recommendations section of this study is to reduce or “mitigate”
incident energy levels by adjusting device trip settings to operate at or below the computed arcing fault current.
Personal protective clothing and equipment (PPE) hazard/risk categories 0-4 are specified in [5] with the intent of
limiting skin burn injuries to “survivable.” PPE category 4 is the highest of the hazard/risk categories recognized by
[5] and requires a minimum arc thermal performance exposure value (ATPV) of 40 cal/cm2 to limit the heat transfer
through the material or fabric to a second degree curable burn based upon the Stoll curve. Incident energy levels
computed above 40 cal/cm2 are preferred to as “hotspots” within this report and energized work at these locations
– If mitigation techniques are ineffective – should be strictly prohibited.
Please note that this is a formal incident energy study which determines the actual incident energy available at
each location. The choice to report the energy levels as “Categories” defined by NFPA 70E 2009 was made to
“easily” communicate the amount of incident energy available. The selection of the ATPV or EB rating of the PPE
should factor an additional safety factor above the calculated energy value to reduce any potential break open on
the material.
SAMPLE
A complete list of arc flash results based upon existing plant conditions are shown in Appendix “F” and
recommended changes are given in Section “1”
In addition, it has been well documented that a lack of timely electrical preventive maintenance and testing of
power circuit breakers could result over time in slower operating/tripping times leading to higher incident energy
levels [12]. Therefore, routine preventive maintenance testing of all plant protective relays and power circuit
breakers with solid-state trip devices is highly encouraged and recommended. The incident energy values
calculated in this study assume an “out-of-the-box” status for all circuit breakers. Their age and maintenance
REPORT
frequency has not been factored into the study.
Although higher available fault current levels can affect bus incident energy levels, the results of this study
demonstrates that long fault clearing times have an even greater impact on the incident energy calculation.
The arcing current variation (85% of original Ia) has been applied by default on all arc flash scenarios. The worst-
case incident energy (100% or 85% Ia) has been reported. Any location where the arcing current variation is a
major problem has been identified and recommendations made on how to mitigate the energy have been provided.
12 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
7 REFERENCES
7.1. Acknowledgements
Curtis Raymond Helfrich, PE provided his technical assistance in reviewing this ARC Flash Study.
7.2. Bibliography
1. IEEE Standard 1584, “IEEE Guide For Performing Arc-Flash Hazard Calculations,” 2002.
2. NFPA Standard 70, “National Electrical Code,” 2011.
3. International Electrical Testing Association (NETA), “Maintenance Testing Specifications For Electrical Power Distribution
Equipment And Systems,” 2005.
4. IEEE Standard 242 (Buff Book), “IEEE Recommended Practice for Protection and Coordination of Industrial and
Commercial Power Systems,” 1986.
5. NFPA Standard 70E, “Standard For Electrical Safety Requirements For Employee Workplaces,” 2009.
6. IEEE Standard 399 (Brown Book), “IEEE Recommended Practice for Industrial and Commercial Power Systems
Analysis,” 1990.
SAMPLE
7. Stevenson, William D, Jr., “Elements of Power System Analysis,” McGraw-Hill, Inc., 1982.
8. ANSI/IEEE Standard C37.04, “Standard Rating Structure for AC High Voltage Circuit Breakers Rated on a Symmetrical
Current Basis,” 1999.
9. ANSI/IEEE Standard C37.010, “Standard Application Guide for AC High Voltage Circuit Breakers Rated on a Symmetrical
Current Basis,” 1999.
10. ANSI/IEEE Standard C37.13, “Standard for Low-Voltage AC Circuit Breakers Used in Enclosures,” 1990.
11. ANSI/IEEE Standard C37.20.1, “Standard for Metal Enclosed Low-Voltage Power Circuit Breaker Switchgear,” 2002.
12. Neitzel, Dennis K., “Protective Devices Maintenance as It Applies To the Arc/Flash Hazard,” 2004.
REPORT
13 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
SAMPLE
REPORT
14 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
SAMPLE
REPORT
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
The incident energy has been conservatively estimated for most locations downstream from the main 1600 Amp circuit
breaker. Energy results for the 1600 Amp main circuit breaker compartment are not available since information on the
upstream primary side transformer protection is not available. An incident energy result projected based on a 1.5 sec
maximum exposure time has been provided. The actual incident energy value can be determined once the missing
information is obtained.
SAMPLE
City, State, zip Shreveport, LA 71129
Contact name John Doe
Phone XXX-XXX-XXXX
REPORT
Utility Company XXXX Power Co.
Contact Ernest Duncan
Address 6130 Union Ave.
City State Zip Shreveport, LA 71108
Email eduncan@xxxx.com
Phone XXX-XXX-XXXX
15 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
SAMPLE
REPORT
16 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
Project: STORE#XXXX ETAP Page: 1
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings
CB: CB-AHU1
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SFLA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 250 Cont. Amp: 250.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SF
Sensor: 250
Rating Plug: 225.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MAX
CB: CB-Baler
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
REPORT
Size: 30 Cont. Amp: 30.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 30
Rating Plug: 30.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MAX
Project: STORE#XXXX ETAP Page: 2
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings
CB: CB-Compactor
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 30 Cont. Amp: 30.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 30
Rating Plug: 30.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MAX
CB: CB-DTA
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SGLA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
REPORT
Size: 600 Cont. Amp: 600.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SG
Sensor: 600
Rating Plug: 450.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup 5
Project: STORE#XXXX ETAP Page: 3
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings
CB: CB-H1A
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SGLA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 400 Cont. Amp: 400.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SG
Sensor: 400
Rating Plug: 400.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup 5
CB: CB-H1P
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
REPORT
Size: 100 Cont. Amp: 100.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 100
Rating Plug: 100.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
Project: STORE#XXXX ETAP Page: 4
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings
CB: CB-MBU
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SS 1600 ETU Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 1600 Cont. Amp: 1600.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Entelliguard
Sensor: 1600 (LSIG)
Rating Plug: 1600.00
SAMPLE
Short-Time ST Pickup 4.000
ST Band 1 I^xt=OUT
INST Inst. Pickup 3.000
CB: CB-MTB
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SFLA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
REPORT
Size: 250 Cont. Amp: 250.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SF
Sensor: 250
Rating Plug: 200.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MAX
Project: STORE#XXXX ETAP Page: 5
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings
CB: CB-Oven(Bottom)
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 100 Cont. Amp: 100.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 70
Rating Plug: 70.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
CB: CB-Oven(Top)
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
REPORT
Size: 60 Cont. Amp: 60.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 40
Rating Plug: 40.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
Project: STORE#XXXX ETAP Page: 6
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings
CB: CB-PLM
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 30 Cont. Amp: 30.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 15
Rating Plug: 15.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
CB: CB-Sub-Metering
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SELA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
REPORT
Size: 30 Cont. Amp: 30.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 15
Rating Plug: 15.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
Project: STORE#XXXX ETAP Page: 7
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings
CB: CB-T1D
MFR: General Electric Tag #: 3-Phase kA: 0.00 Asym. (Calc.)
Model: SFLA Rating: 65 kA, 0.48 kV LG kA: 0.00 Asym. (Calc.)
Size: 250 Cont. Amp: 250.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SF
Sensor: 250
Rating Plug: 225.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
REPORT
Size: 60 Cont. Amp: 60.000 Base kV: 0.000 (Calc.)
LV Solid State Trip Device
MFR: General Electric
Model: Spectra RMS SE
Sensor: 50
Rating Plug: 50.00
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
Project: STORE#XXXX ETAP Page: 8
Location: City, State 12.6.0C Date: XX-XX-2016
Contract: Revision: Base
Engineer: XX
Filename: PCXXXXX Protective Device Settings
Phase Setting
Long-Time LT Pickup Fixed
LT Band Fixed
SAMPLE
Short-Time ST Pickup Fixed
ST Band Fixed I^xt=IN
INST Inst. Pickup MIN
REPORT
Amps X 10 MSB (Distribution) (Nom. kV=0.48, Plot Ref. kV=0.48)
.5 1 3 5 10 30 50 100 300 500 1K 3K 5K 10K
1K 1K
CB-H1A
300 300
CB-MTB
CB-MBG
100 100
50 CB-DTA 50
CB-T1D
30 30
CB-Oven(Bottom)
10 10
CB-PLM
SAMPLE
5 5
CB-Baler
Seconds
Seconds
3 3
CB-UH (Vestibule)
REPORT
1 1
CB-Sub-Metering
CB-H1P
.5 .5
.3 CB-Compactor .3
.1 .1
CB-Oven(Top)
.03 .03
CB-MBG
CB-Water Heater
.01 .01
CB-UH (Vestibule)
CB-H1A CB-H1P CB-T1D CB-DTA CB-MTB CB-AHU1 CB-Baler CB-Compactor CB-Sub-Metering CB-Oven(Top) CB-Oven(Bottom) CB-PLM
Amps X 10 MSB (Distribution) (Nom. kV=0.48, Plot Ref. kV=0.48) ETAP Star 12.6.0C
MBG COORDINATION
CB-H1P
500 500
CB-MTB
CB-MBU
100 100
50 50
CB-T1D
30 30
CB-AHU1
10 CB-PLM 10
SAMPLE
5 5
Seconds
Seconds
3 CB-UH (Vestibule) 3
CB-Sub-Metering
REPORT
1 1
CB-DTA
CB-Compactor
.5 .5
CB-Baler
.3 .3
CB-Water Heater
.1 CB-Oven(Bottom) .1
.03 .03
CB-MBU
CB-Water Heater
.01 .01
CB-UH (Vestibule)
CB-H1A CB-H1P CB-T1D CB-DTA CB-MTB CB-AHU1 CB-Baler CB-Compactor CB-Sub-Metering CB-Oven(Top) CB-Oven(Bottom) CB-PLM
Amps X 10 MSB (Distribution) (Nom. kV=0.48, Plot Ref. kV=0.48) ETAP Star 12.6.0C
MBU COORDINATION
SAMPLE
REPORT
17 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
Project: STORE#XXXX
ETAP Page: 1
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Short-Circuit Analysis
ANSI Standard
3-Phase Fault Currents
Number of Buses:
SAMPLE
Swing
1
V-Control
0
Load
28
Total
29
Number of Branches:
REPORT
XFMR2
2
Synchronous
Generator
XFMR3
Power
Grid
Reactor
Synchronous
Motor
Line/Cable
23
Induction
Machines
Impedance
Lumped
Load
Tie PD
Total
Total
28
Number of Machines: 0 1 0 3 3 7
Output Filename:
Project: STORE#XXXX
ETAP Page: 2
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Adjustments
Apply Individual
Tolerance Adjustments /Global Percent
SAMPLE
Cable Length: No
Apply Individual
Temperature Correction Adjustments /Global Degree C
REPORT
Project: STORE#XXXX
ETAP Page: 3
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
B-Oven(Top) Load 0.480 0.480 1 100.00 0.00
REPORT
B-UPS1 Sec Load 0.208 0.208 1 100.00 0.00
29 Buses Total
Line/Cable Length
SAMPLE
C-H1A 0.6MALN1 250 9.0 0 2 75 0.08600 0.05200 0.0000000
REPORT
C-L1U 0.6MCUN1 6 50.0 0 1 75 0.49000 0.06400 0.0000000
SAMPLE
Impedance Input Data
MSB Bus 0.01 0.01 0 % in 0.480 kV base and 100.0 MVA base
MSB Bus 2 0.01 0.01 0 % in 0.480 kV base and 100.0 MVA base
REPORT
Project: STORE#XXXX
ETAP Page: 6
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Branch Connections
Utility Transformer 2W XFMR B-Utility Primary B-Utility Secondary 161.63 824.30 840.00
SAMPLE
C-Compactor Cable MSB (Distribution) B-Compactor 14322.92 751.95 14342.64
C-L1D2 Line Cable B-T1D Sec Circuit Breaker L1D2 29.82 18.03 34.84
REPORT
C-L1D2 Load Cable Circuit Breaker L1D2 Panel L1D2-1 2782.91 1682.69 3252.09
C-MBU Cable B-Utility Secondary MSB (Main Breaker) 19.53 22.14 29.52
C-T1D Pri Cable MSB (Distribution) B-T1D Pri 28.13 19.92 34.47
C-UH (Vestibule) Cable MSB (Distribution) B-UH (Vestibule) 106.34 13.89 107.24
C-Water Heater Cable MSB (Distribution) B-Water Heater 43.40 12.37 45.13
MSB Bus Impedance MSB (Main Breaker) MSB (Distribution) 0.01 0.01 0.01
MSB Bus 2 Impedance MSB (Gen) MSB (Distribution) 0.01 0.01 0.01
% Impedance
Power Grid Connected Bus Rating 100 MVA Base
ID ID MVASC kV X/R R X
SAMPLE
REPORT
Project: STORE#XXXX
ETAP Page: 8
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
% Impedance
Induction Machine Connected Bus Rating X/R Ratio Machine Base
ID Qty ID HP/kW kVA kV RPM X"/R X'/R R X" X'
Motors
Load AHU1 1 B-AHU1 154.00 147.23 0.480 1800 9.66 9.66 2.07 20.00 50.00
Load Baler 1 B-Baler 10.45 11.65 0.480 1800 2.52 2.52 11.06 27.83 9999.00
Load Compactor 1 B-Compactor 10.45 11.65 0.480 1800 2.52 2.52 11.06 27.83 9999.00
SAMPLE
Total Connected Induction Motors ( = 3 ): 170.5 kVA
REPORT
Project: STORE#XXXX
ETAP Page: 9
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
% Imp.
Lumped Load Connected Bus Rating % Load Loading X/R Ratio (Machine Base) Loading
ID ID kVA kV MTR STAT kW kvar X"/R X'/R R X" X' kW kvar
Load DTA Panel DTA 328.0 0.480 100 0 278.8 172.8 2.38 2.38 8.403 20.00 50.00 0.00 0.00
Load H1A Panel H1A 286.0 0.480 100 0 243.1 150.7 2.38 2.38 8.403 20.00 50.00 0.00 0.00
Load MTB Panel MTB 130.0 0.480 100 0 110.5 68.5 2.38 2.38 8.403 20.00 50.00 0.00 0.00
SAMPLE
Total Connected Lumped Loads ( = 3 ): 744.0 kVA
REPORT
Project: STORE#XXXX
ETAP Page: 10
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SHORT-CIRCUIT REPORT
SAMPLE
MSB (Distribution) Total 0.00 4.319 -15.881 3.7 16.458
REPORT
Panel H1A MSB (Distribution) 0.26 0.615 -1.458 2.4 1.582
MSB (Main Breaker) MSB (Distribution) 0.00 2.531 -11.334 4.5 11.614
SAMPLE
B-Utility Secondary MSB (Main Breaker) 2.85 2.531 -11.335 4.5 11.614
MSB (Distribution) MSB (Main Breaker) 0.00 1.788 -4.546 2.5 4.885
REPORT
Project: STORE#XXXX
ETAP Page: 12
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
MSB (Distribution) Panel DTA 37.72 4.783 -8.877 1.9 10.084
REPORT
Project: STORE#XXXX
ETAP Page: 13
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
MSB (Distribution) Panel H1A 2.39 3.876 -14.112 3.6 14.635
REPORT
Project: STORE#XXXX
ETAP Page: 14
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
MSB (Distribution) Panel H1P 16.64 6.016 -13.731 2.3 14.991
REPORT
Project: STORE#XXXX
ETAP Page: 15
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
B-T1D Sec Panel L1D1-1 2.80 2.269 -7.280 3.2 7.626
REPORT
* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.
Project: STORE#XXXX
ETAP Page: 16
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
Panel L1D1-1 Panel L1D1-2 1.66 2.311 -7.161 3.1 7.525
REPORT
Project: STORE#XXXX
ETAP Page: 17
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
Circuit Breaker L1D2 Panel L1D2-1 50.96 2.599 -3.488 1.3 4.350
REPORT
* Indicates a fault current through a tie circuit breaker
If faulted bus is involved in loops formed by protection devices, the short-circuit contributions through these PDs will not be reported.
Project: STORE#XXXX
ETAP Page: 18
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
Panel L1D2-1 Panel L1D2-2 0.54 2.593 -3.465 1.3 4.328
REPORT
Project: STORE#XXXX
ETAP Page: 19
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
B-UPS1 Sec Panel L1U 37.04 1.635 -0.753 0.5 1.800
REPORT
Project: STORE#XXXX
ETAP Page: 20
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
Panel L1D1-1 Panel LRX 91.56 1.287 -0.367 0.3 1.338
REPORT
Project: STORE#XXXX
ETAP Page: 21
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
MSB (Distribution) Panel MTB 64.32 4.507 -5.120 1.1 6.822
REPORT
Project: STORE#XXXX
ETAP Page: 22
12.6.0C
Location: CIty, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
3-Phase Fault Currents: (Prefault Voltage = 100 % of the Bus Nominal Voltage)
MSB (Distribution) 0.480 MSB (Distribution) Switchboard 16.458 4.0 1.190 19.579 33.880
MSB (Main Breaker) 0.480 MSB (Main Breaker) Switchboard 16.458 4.0 1.190 19.579 33.880
SAMPLE
Panel DTA 0.480 Panel DTA Panelboard 11.895 2.0 1.040 12.369 20.213
Panel H1A 0.480 Panel H1A Panelboard 16.209 3.7 1.171 18.978 32.795
Panel H1P 0.480 Panel H1P Panelboard 14.991 2.4 1.070 16.034 26.890
Panel L1D1-1 0.208 Panel L1D1-1 Panelboard 7.626 3.3 1.136 8.661 14.891
Panel L1D1-2 0.208 Panel L1D1-2 Panelboard 7.525 3.1 1.127 8.481 14.554
Panel L1D2-1 0.208 Panel L1D2-1 Panelboard 4.350 1.3 1.009 4.391 6.748
Panel L1D2-2 0.208 Panel L1D2-2 Panelboard 4.328 1.3 1.009 4.368 6.708
REPORT
Panel L1U 0.208 Panel L1U Panelboard 1.800 0.5 1.000 1.800 2.549
Panel LRX 0.208 Panel LRX Panelboard 1.338 0.3 1.000 1.338 1.893
Panel MTB 0.480 Panel MTB Panelboard 7.508 1.2 1.006 7.556 11.468
3-Phase Fault Currents: (Prefault Voltage = 100 % of the Bus Nominal Voltage)
SAMPLE
CB-H1P MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
CB-T1D MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
CB-DTA MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
CB-Oven(Top) MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
CB-Sub-Metering MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
CB-Compactor MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
CB-Baler MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
REPORT
CB-AHU1 MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
CB-MTB MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
CB-Oven(Bottom) MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
CB-PLM MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
CB-UH (Vestibule) MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
CB-Water Heater MoldedFused 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
MSB (Main Breaker) 0.480 CB-MBU InsulUnfuse 16.458 4.0 1.000 16.458 0.480 20.00 65.000 65.000
Panel L1D1-1 0.208 CB-L1D1 Molded Case 7.626 3.3 1.107 8.440 0.240 50.00 10.000 10.000
CB-LRX Molded Case 7.626 3.3 1.107 8.440 0.240 50.00 10.000 10.000
Panel L1D2-1 0.208 CB-L1U Molded Case 4.350 1.3 1.000 4.350 0.240 50.00 10.000 10.000
SAMPLE
REPORT
18 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
Project: STORE#XXXX
ETAP Page: 1
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
IEEE 1584
ANSI Short-Circuit
Number of Buses:
SAMPLE
Swing
1
V-Control
0
Load
28
Total
29
REPORT
XFMR2 XFMR3 Reactor Line/Cable Impedance Tie PD Total
Number of Branches: 2 0 0 23 2 1 28
Number of Machines: 0 1 0 3 3 7
Output Filename:
Project: STORE#XXXX
ETAP Page: 2
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Adjustments
Apply Individual
Tolerance Adjustments /Global Percent
SAMPLE
Cable Length: No
Apply Individual
Temperature Correction Adjustments /Global Degree C
REPORT
Energy Levels
Level ID cal/cm²
Level 0 1.20
Level 1 4.00
Level 2 8.00
Level 3 25.00
Level 4 40.00
Project: STORE#XXXX
ETAP Page: 3
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
SAMPLE
B-Oven(Top) Load 0.480 0.480 1 100.00 0.00
REPORT
B-UPS1 Sec Load 0.208 0.208 1 100.00 0.00
29 Buses Total
MSB (Distribution) 0.480 Switchboard 32 1.473 10.000 3.500 1.000 0.100 0.0
MSB (Main Breaker) 0.480 Switchboard 32 1.473 10.000 3.500 1.000 0.100 0.0
Panel DTA 0.480 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0
Panel H1A 0.480 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0
Panel H1P 0.480 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0
SAMPLE
Panel L1D1-1 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0
Panel L1D1-2 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0
Panel L1D2-1 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0
Panel L1D2-2 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0
Panel L1U 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0
Panel LRX 0.208 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0
REPORT
Panel MTB 0.480 Panelboard 25 1.641 10.000 3.500 1.000 0.100 0.0
The Gap and X-Factors are not utilized if the theoretically derived Lee method was used to determine the incident energy and arc flash boundary .
The Lee method is used if the bus voltage and/or short-circuit parameters are outside the range covered by the IEEE 1584 empirical equations.
Project: STORE#XXXX
ETAP Page: 5
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Line/Cable Length
SAMPLE
C-DTA 0.6MALN1 300 235.0 0 2 75 0.07200 0.05100 0.0000000
REPORT
C-L1D2-2 0.6MALN1 250 3.0 0 2 75 0.08600 0.05200 0.0000000
SAMPLE
Impedance Input Data
MSB Bus 0.01 0.01 0 % in 0.480 kV base and 100.0 MVA base
REPORT
MSB Bus 2 0.01 0.01 0 % in 0.480 kV base and 100.0 MVA base
Project: STORE#XXXX
ETAP Page: 7
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Branch Connections
Utility Transformer 2W XFMR B-Utility Primary B-Utility Secondary 161.63 824.30 840.00
SAMPLE
C-DTA Cable MSB (Distribution) Panel DTA 367.19 260.09 449.97
C-L1D2 Line Cable B-T1D Sec Circuit Breaker L1D2 29.82 18.03 34.84
REPORT
C-L1D2 Load Cable Circuit Breaker L1D2 Panel L1D2-1 2782.91 1682.69 3252.09
C-MBU Cable B-Utility Secondary MSB (Main Breaker) 19.53 22.14 29.52
C-T1D Pri Cable MSB (Distribution) B-T1D Pri 28.13 19.92 34.47
C-UH (Vestibule) Cable MSB (Distribution) B-UH (Vestibule) 106.34 13.89 107.24
C-Water Heater Cable MSB (Distribution) B-Water Heater 43.40 12.37 45.13
MSB Bus Impedance MSB (Main Breaker) MSB (Distribution) 0.01 0.01 0.01
MSB Bus 2 Impedance MSB (Gen) MSB (Distribution) 0.01 0.01 0.01
% Impedance
Power Grid Connected Bus Rating 100 MVA Base
ID ID MVASC kV X/R R X
SAMPLE
REPORT
Project: STORE#XXXX
ETAP Page: 9
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
% Impedance
Induction Machine Connected Bus Rating X/R Ratio Machine Base
ID Qty ID HP/kW kVA kV RPM X"/R X'/R R X" X'
Motors
Load AHU1 1 B-AHU1 154.00 147.23 0.480 1800 9.66 9.66 2.07 20.00 50.00
Load Baler 1 B-Baler 10.45 11.65 0.480 1800 2.52 2.52 11.06 27.83 9999.00
Load Compactor 1 B-Compactor 10.45 11.65 0.480 1800 2.52 2.52 11.06 27.83 9999.00
SAMPLE
Total Connected Induction Motors ( = 3 ): 170.5 kVA
REPORT
Lumped Load Connected Bus Rating % Load Loading X/R Ratio % Imp. (Machine Base) Loading
ID ID kVA kV MTR STAT kW kvar X"/R X'/R R X" X' kW kvar
Load DTA Panel DTA 328.0 0.480 100 0 278.8 172.8 2.38 2.38 8.403 20.00 50.00 0.00 0.00
Load H1A Panel H1A 286.0 0.480 100 0 243.1 150.7 2.38 2.38 8.403 20.00 50.00 0.00 0.00
Load MTB Panel MTB 130.0 0.480 100 0 110.5 68.5 2.38 2.38 8.403 20.00 50.00 0.00 0.00
Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 24 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 16.458 Ia" = 9.536 FCT = 3.0 0.050 Incident Energy = 1.001
CB-AHU1
ID
Arc Fault at Device
Phase
Type
3Ph
REPORT
Type
LV CB
Individual Contribution
Bolted
(kA)
0.836
to Bus Arc Fault
Arcing
(kA)
0.484
FCT
(cycles)
Arcing
(kA)
9.536
FCT
(cycles)
3.0
3.0
CB-MBU
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
1.001
1.001
AFB
(ft)
1.77
Energy
Level*
Level 0
FCT = Total =
Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 24 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 16.458 Ia" = 9.536 FCT = 3.0 0.050 Incident Energy = 1.001
CB-MTB
ID
Arc Fault at Device
Phase
Type
3Ph
REPORT
Type
LV CB
Individual Contribution
Bolted
(kA)
0.683
to Bus Arc Fault
Arcing
(kA)
0.396
FCT
(cycles)
Arcing
(kA)
9.536
FCT
(cycles)
3.0
3.0
CB-MBU
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
1.001
1.001
AFB
(ft)
1.77
Energy
Level*
Level 0
FCT = Total =
Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 24 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 16.458 Ia" = 9.536 FCT = 3.0 0.050 Incident Energy = 1.001
ID
CB-UH (Vestibule)
Arc Fault at Device
Phase
Type
3Ph
REPORT
Type
LV CB
(kA)
Individual Contribution
Bolted
0.000
to Bus Arc Fault
Arcing
(kA)
0.000
FCT
(cycles)
Arcing
(kA)
9.536
FCT
(cycles)
3.0
3.0
CB-MBU
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
1.001
1.001
AFB
(ft)
1.77
Energy
Level*
Level 0
FCT = Total =
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 13
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 24 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 16.458 ¨Ia" = 8.106 FCT = 6987.5 116.459 Incident Energy = 1956.103
For Protective Device: Utility TX Fuse@ 85% Ia'' Energy Level* >Max.
=0.220 kA
Arc Flash Boundary = 303.15 ft
¨ CB-MBU
ID
Arc Fault at Device
Phase
Type
3Ph
REPORT
Type
LV CB
(kA)
Individual Contribution
Bolted
11.614
to Bus Arc Fault
Arcing
(kA)
5.720
FCT
(cycles)
3.0
Arcing
(kA)
8.106
FCT
(cycles)
6987.5
6987.5
Incident Energy
Protective Device ID
for FCT
Utility TX Fuse
Incident E
(cal/cm²)
1956.103
1956.103
AFB
(ft)
303.15
Energy
Level*
>Max.
FCT = Total =
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 14
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 18 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 11.895 Ia" = 7.605 FCT = 1.6 0.026 Incident Energy = 0.647
ID
Arc Fault at Device
Phase
Type REPORT
Type (kA)
Individual Contribution
Bolted
to Bus Arc Fault
Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 15
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 18 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 16.209 Ia" = 9.906 FCT = 1.5 0.025 Incident Energy = 0.822
ID
Arc Fault at Device
Phase
Type REPORT
Type (kA)
Individual Contribution
Bolted
to Bus Arc Fault
Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 16
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 18 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 14.991 Ia" = 9.267 FCT = 1.5 0.025 Incident Energy = 0.765
ID
Arc Fault at Device
Phase
Type REPORT
Type (kA)
Individual Contribution
Bolted
to Bus Arc Fault
Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 17
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 7.626 Ia" = 3.596 FCT = 1.5 0.025 Incident Energy = 0.275
CB-L1D1
ID
Arc Fault at Device
Phase
Type
3Ph
REPORT
Type
LV CB
(kA)
Individual Contribution
Bolted
7.626
to Bus Arc Fault
Arcing
(kA)
3.596
FCT
(cycles)
244.7
Arcing
(kA)
3.596
FCT
(cycles)
1.5
1.5
CB-T1D
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
0.275
0.275
AFB
(ft)
0.61
Energy
Level*
Level 0
FCT = Total =
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 18
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 7.525 Ia" = 3.562 FCT = 1.5 0.025 Incident Energy = 0.272
ID
Arc Fault at Device
Phase
Type REPORT
Type (kA)
Individual Contribution
Bolted
to Bus Arc Fault
Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 19
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 4.350 Ia" = 2.424 FCT = 1.5 0.025 Incident Energy = 0.179
CB-L1U
ID
Arc Fault at Device
Phase
Type
3Ph
REPORT
Type
LV CB
(kA)
Individual Contribution
Bolted
0.000
to Bus Arc Fault
Arcing
(kA)
0.000
FCT
(cycles)
Arcing
(kA)
2.424
FCT
(cycles)
1.5
1.5
CB-L1D2
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
0.179
0.179
AFB
(ft)
0.47
Energy
Level*
Level 0
FCT = Total =
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 20
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 4.328 Ia" = 2.416 FCT = 1.5 0.025 Incident Energy = 0.179
ID
Arc Fault at Device
Phase
Type REPORT
Type (kA)
Individual Contribution
Bolted
to Bus Arc Fault
Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 21
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 1.800 ¨Ia" = 1.109 FCT = 2.3 0.038 Incident Energy = 0.118
For Protective Device: CB-L1D2@ 85% Ia'' =1.109 kA Energy Level* Level 0
ID
Arc Fault at Device
Phase
Type REPORT
Type (kA)
Individual Contribution
Bolted
to Bus Arc Fault
Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 22
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Nominal kV = 0.208 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.208 = 100% of base kV Working Distance = 18 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 1.338 ¨Ia" = 0.901 FCT = 94.2 1.570 Incident Energy = 3.864
For Protective Device: CB-LRX@ 85% Ia'' =0.901 kA Energy Level* Level 1
ID
Arc Fault at Device
Phase
Type REPORT
Type (kA)
Individual Contribution
Bolted
to Bus Arc Fault
Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 23
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
Nominal kV = 0.480 Prefault Voltage = 100% of nominal bus kV System Grounding = Grounded
Base kV = 0.480 = 100% of base kV Working Distance = 18 inches
SAMPLE
(kA) (kA) (cycles) (Seconds) (cal/cm²)
Ibf" = 7.508 Ia" = 5.134 FCT = 1.5 0.025 Incident Energy = 0.404
ID
Arc Fault at Device
Phase
Type REPORT
Type (kA)
Individual Contribution
Bolted
to Bus Arc Fault
Arcing
(kA)
FCT
(cycles)
Arcing
(kA)
FCT
(cycles)
Incident Energy
Protective Device ID
for FCT
Incident E
(cal/cm²)
AFB
(ft)
Energy
Level*
* NFPA 70E 2009 Table 130.7(C)(11), Protective Clothing Characteristics, is used to determine the energy level (i.e. energy range).
¨ Arcing current variation was applied at this location.
Project: STORE#XXXX
ETAP Page: 24
12.6.0C
Location: City, ST Date: XX-XX-2016
Contract: PCXXXXX SN: PCX-CORP01
Engineer: XX Revision: Base
Study Case: SC Normal
Filename: PCXXXXX Config.: Normal
MSB (Main Breaker) 0.480 Switchboard 16.458 8.106 6987.547 1956.103 303.15 >Max.
Panel DTA 0.480 Panelboard 11.895 7.605 1.572 0.647 1.03 Level 0
Panel H1A 0.480 Panelboard 16.209 9.906 1.500 0.822 1.19 Level 0
SAMPLE
Panel H1P 0.480 Panelboard 14.991 9.267 1.500 0.765 1.14 Level 0
Panel L1D1-1 0.208 Panelboard 7.626 3.596 1.500 0.275 0.61 Level 0
Panel L1D1-2 0.208 Panelboard 7.525 3.562 1.500 0.272 0.61 Level 0
Panel L1D2-1 0.208 Panelboard 4.350 2.424 1.500 0.179 0.47 Level 0
Panel L1D2-2 0.208 Panelboard 4.328 2.416 1.500 0.179 0.47 Level 0
Panel L1U 0.208 Panelboard 1.800 1.109 2.291 0.118 0.36 Level 0
REPORT
Panel LRX 0.208 Panelboard 1.338 0.901 94.224 3.864 3.06 Level 1
Panel MTB 0.480 Panelboard 7.508 5.134 1.500 0.404 0.77 Level 0
Faulted Bus Fault Current Trip Device Arc Flash Incident Working
Gap Bolted Fault (kA) PD Arc Trip Open FCT Boundary Energy Distance Energy
ID Nom. kV Equip. Type (mm) Bus PD Fault (kA) Source Trip Device ID (cycle) (cycle) (cycle) (ft) (cal/cm²) (inches) Level
MSB (Distribution) 0.480 Switchboard 32 16.458 11.614 6.729 CB-MBU 3.00 0.00 3.00 1.8 1.0 24 Level 0
MSB (Main Breaker) 0.480 Switchboard 32 16.458 0.447 0.220 Utility TX Fuse 6987.55 0.00 6987.55 303.2 1956.1 24 >Max.
Panel DTA 0.480 Panelboard 25 11.895 10.084 6.447 CB-DTA 1.57 0.00 1.57 1.0 0.6 18 Level 0
Panel H1A 0.480 Panelboard 25 16.209 14.635 8.945 CB-H1A 1.50 0.00 1.50 1.2 0.8 18 Level 0
Panel H1P 0.480 Panelboard 25 14.991 14.991 9.267 CB-H1P 1.50 0.00 1.50 1.1 0.8 18 Level 0
Panel L1D1-1 0.208 Panelboard 25 7.626 3.305 1.558 CB-T1D 1.50 0.00 1.50 0.6 0.3 18 Level 0
Panel L1D1-2 0.208 Panelboard 25 7.525 3.261 1.544 CB-T1D 1.50 0.00 1.50 0.6 0.3 18 Level 0
Panel L1D2-1 0.208 Panelboard 25 4.350 4.350 2.424 CB-L1D2 1.50 0.00 1.50 0.5 0.2 18 Level 0
Panel L1D2-2 0.208 Panelboard 25 4.328 4.328 2.416 CB-L1D2 1.50 0.00 1.50 0.5 0.2 18 Level 0
Panel L1U 0.208 Panelboard 25 1.800 1.800 1.109 CB-L1D2 2.29 0.00 2.29 0.4 0.1 18 Level 0
Panel LRX 0.208 Panelboard 25 1.338 1.338 0.901 CB-LRX 94.22 0.00 94.22 3.1 3.9 18 Level 1
Panel MTB 0.480 Panelboard 25 7.508 6.822 4.664 CB-MTB 1.50 0.00 1.50 0.8 0.4 18 Level 0
PCX Corporation
33 Pony Farm Road
Clayton, NC 27520
919-550-2800
SAMPLE
REPORT
19 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State
Arc Flash and Shock Hazard Present Arc Flash and Shock Hazard Present
Appropriate PPE Required Appropriate PPE Required
Arc Flash Boundary (Dc) 1.8 ft Level 0 Arc Flash Boundary (Dc) 1.0 ft Level 0
Incident Energy (Ed) 1.0 cal/cm² Incident Energy (Ed) 0.6 cal/cm²
Working Distance 24.0 in Min. PPE Requirements Working Distance 18.0 in Min. PPE Requirements
Shock Hazard Exposure 480 VAC PPE Requirements have not been Shock Hazard Exposure 480 VAC PPE Requirements have not been
approved approved
Shock Hazard when covers removed Shock Hazard when covers removed
SAMPLE
Class 00 Insulating Gloves Class 00 Insulating Gloves
V-rating 500 VAC V-rating 500 VAC
Limited Approach Boundary 3.5 ft Limited Approach Boundary 3.5 ft
Restricted Approach Boundary 1.0 ft Restricted Approach Boundary 1.0 ft
Prohibited Approach Boundary 0.1 ft Prohibited Approach Boundary 0.1 ft
Source protective Device CB-MBU Source protective Device CB-DTA
Equipment MSB (Distribution) 02-11-2016 Equipment Panel DTA 02-11-2016
REPORT
Arc Flash and Shock Hazard Present
Appropriate PPE Required
Arc Flash Boundary (Dc) 303.2 ft
Incident Energy (Ed) 1956.1 cal/cm²
Working Distance 24.0 in
Arc Flash and Shock Hazard Present
Appropriate PPE Required
Arc Flash Boundary (Dc) 1.2 ft
Incident Energy (Ed) 0.8 cal/cm²
Working Distance 18.0 in
Level 0
SAMPLE
Class 00 Insulating Gloves Class 00 Insulating Gloves
V-rating 500 VAC V-rating 500 VAC
Limited Approach Boundary 3.5 ft Limited Approach Boundary 3.5 ft
Restricted Approach Boundary 1.0 ft Restricted Approach Boundary 1.0 ft
Prohibited Approach Boundary 0.1 ft Prohibited Approach Boundary 0.1 ft
Source protective Device CB-H1P Source protective Device CB-T1D
Equipment Panel H1P 02-11-2016 Equipment Panel L1D1-2 02-11-2016
REPORT
Arc Flash and Shock Hazard Present
Appropriate PPE Required
Arc Flash Boundary (Dc) 0.6 ft
Incident Energy (Ed) 0.3 cal/cm²
Working Distance 18.0 in
Level 0
SAMPLE
Class 00 Insulating Gloves Class 00 Insulating Gloves
V-rating 500 VAC V-rating 500 VAC
Limited Approach Boundary 3.5 ft Limited Approach Boundary 3.5 ft
Restricted Approach Boundary 1.0 ft Restricted Approach Boundary 1.0 ft
Prohibited Approach Boundary 0.1 ft Prohibited Approach Boundary 0.1 ft
Source protective Device CB-L1D2 Source protective Device CB-LRX
Equipment Panel L1D2-2 02-11-2016 Equipment Panel LRX 02-11-2016
REPORT
Arc Flash and Shock Hazard Present
Appropriate PPE Required
Arc Flash Boundary (Dc) 0.4 ft
Incident Energy (Ed) 0.1 cal/cm²
Working Distance 18.0 in
Level 0
SAMPLE
REPORT
20 | P a g e
ARC FLASH MITIGATION & DEVICE COORDINATION ANALYSIS
STORE #XXXX – City, State