:SGSIA/PROINTEC Action

:Completed
SUIVI DELAIS EQUIPEMENTS Date:2017/03/10
:Not yet happened

Fabrication Remaining days Start Manufacture EX-Works


Item Name Equipment Brand Fabrication Time Shipping Time Installation sur chantier Action to mitigate delay
Status before fabrication Date Date

Generator - Batch 1(2 sets) 12/01/2017 61 02/03/2017

Generator - Batch 2(2 sets) 17/01/2017 75 09/03/2017

24/01/2017 75 09/04/2017 Factory Vist done (2017/1/12)


Groupes
1
Electrogenes
YES N/A 27/10/2016 85 75% Every generator is already manufactured. Formerly scheduled dates modified due to
logisitcs issues. Departure dates of the following batches to be confirmed.
Generator - Batch 3(6 sets, 2+2+2) 24/01/2017 60 25/03/2017

24/01/2017 60 25/03/2017

Generator - Batch 4(6 sets) 21/02/2017 60 22/04/2017

2 MV Switchboard Schneider YES N/A 30/11/2016 90 22/02/2017 50 13/04/2017 Test scheduled for 07/03/2017

14/01/2017 38 21/02/2017
Transformer - Batch 1(8 sets, 4+4 sets)
25/01/2017 46 12/03/2017
3 Legrand YES N/A 23/09/2016 112 84% Factory Visit on 19/12/2016, done
Transformer - Batch 2(8 sets) 01/02/2017 35 08/03/2017

Transformer - Batch 3(9 sets) 11/02/2017 37 20/03/2017

4 Electricité MV Cable - Batch 1(Internal 8000m) YES N/A 05/11/2016 61 12/01/2017 50 03/03/2017
CABELTE
5 MV Cable - Batch 2(External 25000m) YES N/A 27/01/2017 57 25/03/2017 50 14/05/2017

CT1, CT6, CT7. 9 Panel board test scheduled for 07/02/2017. Shipment will be organized
Main Distribution Panel Board- Batch 1(9 units) 07/02/2017 47 26/03/2017 26% afterwards

Main Distribution Panel Board- Batch 2(3 units) 07/03/2017 30 06/04/2017

6 Main Distribution Panel Board- Batch 3(8 units) Legrand YES N/A 13/11/2016 160 20/03/2017 30 19/04/2017

Main Distribution Panel Board- Batch 4(8 units) 07/04/2017 30 07/05/2017

Main Distribution Panel Board- Batch 5(6 units) 07/04/2017 30 07/05/2017

CT1, CT6, CT7. 3 panel board Test scheduled for 07/02/2017. The rest of the panels are
Distribution Panel Board(2nd&3rd)-Batch 1(150 units) 07/02/2017 44 23/03/2017 being prepared for shipment.

Distribution Panel Board(2nd&3rd)-Batch 2(250 units) 27/02/2017 30 29/03/2017


7 Legrand YES N/A 13/11/2016 160
Distribution Panel Board(2nd&3rd)-Batch 3(343 units) 20/03/2017 30 19/04/2017

Distribution Panel Board(2nd&3rd)-Batch 4(190 units) 07/04/2017 30 07/05/2017

28/03/2017 -Test in Bologne (Italy)


8 UPS Emerson YES N/A 13/01/2017 94 17/04/2017 30 17/05/2017
Battery manufacture finishes on 22/05/2017

35 CTA - Batch 1 28/02/2017 28 28/03/2017

35 CTA - Batch 2 01/03/2017 28 29/03/2017


Carrier YES N/A 22/12/2016 90
35 CTA - Batch 3 15/03/2017 28 12/04/2017

35 CTA - Batch 4 30/04/2017 28 28/05/2017


HVAC
8 FCU Aermec YES N/A 15/12/2016 39 23/01/2017 31 23/02/2017

9 Air Condition Pump(Primary ) KSB YES N/A 13/12/2016 87 10/03/2017 28 07/04/2017


Test dates required at the end of last year.
10 Air Condition Pump(secondary,tertiary) KSB YES N/A 13/12/2016 87 10/03/2017 28 07/04/2017

11 Chiller & Heat Pump Trane YES N/A 16/12/2016 94 20/03/2017 28 17/04/2017 Test dates required at the end of last year.

19 ULV Fire Alarm System (FAS) Honeywell YES N/A 15/11/2016 90 13/02/2017 28 13/03/2017 50% of equipment expected on-site on 10-01-2017

Engineering phase ongoing. Some approvals are required to start manufacturing phase
29 ULV Building Management System (BMS) Siemens NO ?¿ ¿? 90 04/03/2017 28 01/04/2017
(CTA, Heat/chill producers…)

36 HAVC Computer Room Air Conditioner Emerson Not Yet Approved (59) 14/01/2017 110 04/05/2017 28 01/06/2017 Rejected and preparing re-submission

37 Gas Fire Protection KOMTES Not Yet Approved (82) 22/12/2016 60 20/02/2017 28 20/03/2017 Approved with comments, resubmitted on 31th of Dec
Plomberie
38 Sanitary Aquacontrol Not Yet Approved (40) 02/02/2017 120 02/06/2017 28 30/06/2017 SGSIA sent a letter to start procurement process.