MINUTES OF MEETING HELD BETWEEN M/S GE INDIA INDUSTRIAL PVT LTD

AND M/S L &T . DATED ON 28.12.2017 220/33kV

RAMAGUNDAM SS

Members Present:

M/S LARSEN & TOUBRO LTD. M/S GEIPL.

Mr. YASWANTH (TESTING INCHARGE.) Mr. SUMAN B Y (Relay Engg.)


Mr. JAYA PRAKASH.R (SAS Engg.)

The following work has been done as on date.

*C&R Panel Job status.

M/s.GE representative reported to the site on 11thDEC 2017 and completed the following works,

BAY Panel Serial No. Installation Relay Ref. Relay SL. No. Status
REF/NAME panel
LINE DIFFERENTIAL AA2C17001437 Scheme Check, Relay
B1737!/GA17027 PROTECTION (L90) Configuration &Testing
220 KV - Completed including all functional checks
Feeder 1 CRP 201/EV0153/201 BCU & BACKUP 34205986 and Trips logics were
RP PROTECTION (C264) Completed, Panel
Commissioned.
B1737!/GA17027 LINE DIFFERENTIAL AA2C17001439 Scheme Check, Relay
- PROTECTION (L90) Configuration &Testing
220 KV 201/EV0154/202 Completed including all functional checks
Feeder 2 CRP RP BCU & BACKUP 34205984 and Trips logics were
PROTECTION (C264) Completed, Panel
Commissioned.

DIFFERENTIAL Scheme Check, Relay


B1737!/GA17027 Completed PROTECTION (T60) ABHC17000972 Configuration &Testing
- including all functional checks
220 KV 203/EV0155/203 REF 34205981 and Trips logics were
Trafo 1 CRP RP PROTECTION(P141) Completed, Panel
Commissioned.

BACKUP_C264 34205978
DIFFERENTIAL Scheme Check, Relay
220 KV BI612!/GA15008- PROTECTION (T60) ABHC17000971 Configuration &Testing
Trafo 2 CRP 203/EVO107/203 REF 34205980 including all functional checks
RP Completed PROTECTION(P141) and Trips logics were
BI612!/GA15008- Completed , Panel
203/EVO106/206 Commissioned.
CP BACKUP 34205983
PROTECTION (C264)
B1737!/GA17027 Scheme Check, Relay
- Configuration &Testing
220 KV BCRP 205/EV0152/205 Completed BCU 34205982 including all functional checks
RP PROTECTION(C264) and Trips logics were
Completed, Panel
BACKUP 34205979 Commissioned.
PROTECTION(P141)

R PHASE RELAY 34191558 Scheme Check, Relay


B1737!/GA17027 Completed Configuration &Testing
220 KV BBRP - including all functional checks
Y PHASE RELAY 34191559
210/EV0151/2BB and Trips logics were
RP Completed, Panel
B PHASE RELAY 34191560
Commissioned.

220 KV B1737!/GA17027 Completed SECURE PREMIER Scheme Check, Metering


INCOMER - 100 checking and configuration is
TARIFF 211/EV0157/TM completed
METERING P
PANEL

B1737!/GA17027 Completed DATA 34102318 Scheme Check, Configuration


SAS PANEL - CONCENTRATOR(C2 done, checked events of all
10.2/EV0158/X0 64) the relays OF 220 KV through
1 event logger

TIME SYNCH B1737!/GA17027 Completed SERTEL GPS-H/17/25-02 Scheme Check Done,Time


EQUIPMENT - synched to all the relays of
PANEL 10.2/EV0158/X0 220kV with GPS
14 RECIEVER,GPS Antenna
connected and found working
OK.
RELAY TYPE MODEL NO NO OF RELAYS

L90 L90T03HKHFBLH6DLXXN67567UXXW7H 2

T60 T60T03HKHFBLH6DM8NP67U67W5F 2

P141 P141916A6M0510J 6

C264 C264MB1M6910023504000030111N10 5

 The Above mentioned relays (Annexure: 1) are configured and Logics Checked as per
scheme.
 Numerical Relays protection functions are successfully tested with relay test kit and the
same was witnessed by M/s. L&T,M/s RFCL &M/s EIL.
 All protection relay settings installed in the relays are provided by M/s. L&T and its Test
reports hardcopies are submitted to M/s. L&T.
 All Auxiliary relays functions are tested and Tripping circuits are healthy and found ok.
 Scheme check of 220 kV Panels found OK.
 All Backup relays were tested for Directional and Non Directional Protection and tested
with TOC and IOC.
 All relays were tested with the protections like Overfrequency,Under Frequency
Overvoltage and Over current protections.
 All wiring issues in Panel have been rectified and Put Relay on service.
 Settings has been changed in C264 as per customer requirement.
 LED’s are configured in C264 as per the Customer requirement.
 Synchrocheck is configured in BCU because of customer need.
 Logics are changed as per scheme and customer need.
 CT and VT ratios has been put as per customer requirement .
 UR setup, C264 Software’s, MICOM S1 Agile installed in customer laptop.
 Relay project backups has been submitted to M/s. L&T.
 M/s GE representative left from site on 28thDEC 2017.

PENDING POINTS: