ID Task Name Duration Start Finish 13 May '13 Jun '13 Jul '

7 14 21 28 5 12 19 26 2 9 16 23 30
1 KIEHI'S @ THE DUBAI MALL 55 days Apr 22 '13 Jun 29 '13
2 Pre-construction works 43 days Apr 22 '13 Jun 13 '13
3 General 2 days Apr 22 '13 Apr 23 '13
4 Work order confirmation 1 day Apr 22 '13 Apr 22 '13
5 Kick off meeting 1 day Apr 23 '13 Apr 23 '13
6 Shop drawing submission & approval 19 days Apr 24 '13 May 18 '13
7 Preparation of shop drawing for submission 14 days Apr 24 '13 May 12 '13
8 Submission of shop drawings 1 day May 12 '13 May 13 '13
9 Approval for shop drawings 4 days May 13 '13 May 18 '13
10 Material sample submission & approval 15 days Apr 24 '13 May 13 '13
11 Preparation of sample for submission 10 days Apr 24 '13 May 6 '13
12 Submission of samples 1 day May 6 '13 May 7 '13
13 Approval for samples 4 days May 7 '13 May 13 '13
14 Procurement & production of joinery works 30 days May 7 '13 Jun 13 '13
15 Procurement & production of joinery works 30 days May 7 '13 Jun 13 '13
16 Authority approval 15 days Apr 24 '13 May 13 '13
17 Preparation of documents for submission 7 days Apr 24 '13 May 2 '13
18 Submission of documents 1 day May 2 '13 May 4 '13
19 Approval for documents 7 days May 4 '13 May 13 '13
20 Construction works 48 days Apr 30 '13 Jun 29 '13
21 Priliminaries 2 days Apr 30 '13 May 2 '13
22 Site mobilisation 1 day Apr 30 '13 May 1 '13
23 Site survey & marking layout 1 day May 1 '13 May 2 '13
24 Civil works 2 days May 2 '13 May 5 '13
25 Cement sand screed on floor 2 days May 2 '13 May 5 '13
26 Mep 1st & 2nd fix 13 days May 5 '13 May 21 '13
27 Conduting & wiring 8 days May 5 '13 May 15 '13
28 AC ducting works 8 days May 5 '13 May 15 '13
29 Cable tray & trunking 8 days May 8 '13 May 19 '13
30 DB installation 5 days May 15 '13 May 21 '13
31 Gypsum cladding,partition & ceiling 11 days May 19 '13 Jun 2 '13
32 Wall partition framework 3 days May 22 '13 May 26 '13
33 Ceiling framework 3 days May 19 '13 May 22 '13
34 Inspection for ceiling closure 1 day May 26 '13 May 27 '13
35 Gypsum boarding,taping & jointing 4 days May 27 '13 Jun 2 '13
36 Wall & Floor finishes 8 days Jun 2 '13 Jun 11 '13

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: keigh dubai mall
Progress Rolled Up Milestone Group By Summary
Date: Apr 24 '13
Milestone Rolled Up Progress Deadline
Summary Split

Page 1
ID Task Name Duration Start Finish 13 May '13 Jun '13 Jul '
7 14 21 28 5 12 19 26 2 9 16 23 30
37 Brick wall cladding 2 days Jun 2 '13 Jun 4 '13
38 Installation of timber flooring 4 days Jun 6 '13 Jun 11 '13
39 Installation of mosaic tiles 1 day Jun 6 '13 Jun 8 '13
40 Painting works 6 days Jun 2 '13 Jun 9 '13
41 Primer & stucco application 4 days Jun 2 '13 Jun 6 '13
42 Painting for all areas 2 days Jun 6 '13 Jun 9 '13
43 Shop front & signage works 8 days Jun 6 '13 Jun 16 '13
44 Installation of shop front bulkhead, signage support & signage
3 days Jun 6 '13 Jun 10 '13
45 Install black roller curtain 3 days Jun 10 '13 Jun 13 '13
46 Installation of polycarbonate roller shutter 3 days Jun 10 '13 Jun 13 '13
47 Installation of decorative frames 5 days Jun 6 '13 Jun 12 '13
48 Installation of door & ironmongery 3 days Jun 12 '13 Jun 16 '13
49 Fixture installation 5 days Jun 13 '13 Jun 19 '13
50 Joinery works 5 days Jun 13 '13 Jun 19 '13
51 MEP final fix 11 days Jun 9 '13 Jun 23 '13
52 Grills & diffusers fixing 3 days Jun 9 '13 Jun 12 '13
53 Switches & sockets fixing 3 days Jun 12 '13 Jun 16 '13
54 Light fixing 2 days Jun 17 '13 Jun 18 '13
55 Installation of sanitary wares 2 days Jun 17 '13 Jun 18 '13
56 FF & FA devices fixing 3 days Jun 19 '13 Jun 23 '13
57 Testing,commissioning & final works 5 days Jun 23 '13 Jun 29 '13
58 Testing & comissioning 2 days Jun 23 '13 Jun 25 '13
59 Final cleaning & snagging 1 day Jun 25 '13 Jun 26 '13
60 Authority inspection 1 day Jun 26 '13 Jun 27 '13
61 Completion & handover 1 day Jun 27 '13 Jun 29 '13

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: keigh dubai mall
Progress Rolled Up Milestone Group By Summary
Date: Apr 24 '13
Milestone Rolled Up Progress Deadline
Summary Split

Page 2