COMPANY CONFIDENTIAL

TECHNICAL DEPARTMENT MEETING

Meeting No: 01 Document stored:/pc

Subject:
TRX-Expansion

Date/Time: Place:
January 02, 2008 @ 11:00 TP Regional Office, Lahore
File No.: From:
20080102 Minutes by Shoaib Rehman.

Participants: Distribution:

Naeem_ul_Haq, NSN Participants list+


Idress Bralas, NSN
Faisal Mehmood, NSN Shafqat Shan, TP
Wajhat Asif, NSN Abdul Haseeb Chaudhry, TP
Junaid Farooq, TP
Kashif Anwar, TP Fitaw Amlak, TP
Abdul Ghaffar, TP Muhammad Kamal, TP
Sharjeel Ahmad, TP Mubeen-ul-Hassan, TP
Shoaib Rehman, TP Adnan Zafar, NSN

Waqas Manzoor, TP
Usama Rehman Bhatti, TP

PURPOSE

This purpose of this meeting is to discuss the plans and procedures for TRX
Expansion for the year 2008.

AGENDA

 Plans for TRX Expansion in the year 2008.


 Issues and Procedures
 Action points from the last meeting to be revised.
 Delays and plans to catch up.
 Blocking (Escalation) issues

TRX_Expansion_Plans 1/3
COMPANY CONFIDENTIAL

AP/WK ISSUES Raised Responsible Due Date Status

01/01 Resource for


Database Creation

TP asked from NSN that Abdul Naeem, NSN January 9, Naeem from NSN will update
there should be a Ghaffar 2008 TP within a week. He further
dedicated resource of added that currently Nauman
database creation in is responsible for database
central region for TRX creation. [Week01]
Expansions.

02/01 TimeLine for


creation of database

NSN will create a TP NSN Ongoing OPEN


database before 24 [Week01]
Hour and engineer will
leave the site after
hardware installation
and verification.

03/01 TRX Expansion


Reporting

There will be daily


reporting about the TRX NSN Abdul Ghaffar Ongoing OPEN.
Expansion, after that TP [Week01]
RF will monitor the
stats for 48 hours.

If any issue is found it


will be reported to NSN
for Rectification.

04/01 Priority sites for


Expansions

Abdul Ghaffar will email


the priority expansions NSN TP Ongoing OPEN
cells to NSN. It is [Week01]
mutually decided that
this priority sites will be
mail to NSN 1 week
before scheduling for
next 2 weeks.

TRX_Expansion_Plans 2/3
COMPANY CONFIDENTIAL

05/01 Issues related to


Operations

It is mutually decided
that all dismantling of NSN/TP NSN O&M Ongoing OPEN.
equipments (CU, FCU, [Week01]
and DUAMCO) should
be done by NSN O&M.

06/01 Relocation of TRX

It is decided that
operations will remove TP Operation Ongoing OPEN.
the operative TRX from [Week01]
the ON-Air site and they
will install it on
requested segmented.

07/01 Problematic cells

NSN claims that 85 TP NSN Ongoing OPEN


problematic cells will be [Week01]
resolved by Monday
January 07, 2008.

08/01 Configuration Issue

NSN informs that errors


should be avoided on NSN TP RF Ongoing OPEN
actual site configuration [Week01]
sheet sent by TP RF.

Next TRX Expansion meeting # 2

To be decided….

At 2nd floor Telenor Office, Lahore

Minutes approved by:

Telenor Pakistan: ____________________ NSN: ____________________

Date: ____________________ Date: ___________________

TRX_Expansion_Plans 3/3