Vous êtes sur la page 1sur 4

Part 4

38 TheStructuralEngineer Technical
December 2016 Temporary Works Toolkit

Temporary Works Toolkit


Part 4: The Temporary Works Toolkit is a series
of articles aimed primarily at assisting the
permanent works designer with temporary

An introduction works issues. Buildability – sometimes referred


to now as “construction method engineering” – is
not a new concept and one always recognised as

to backpropping vital to the realisation of one’s ideas; it ought to


be at the forefront of an engineer’s mind.

of flat slabs www.twforum.org.uk

Eur. Ing. Peter Pallett BSc, CEng, FICE, FCS


Above Ground Temporary Works Consultant, Pallett TemporaryWorks Ltd.

Introduction the mechanics of load transfer during proportional, each slab would effectively be
Backpropping of concrete slabs during construction of their designed structure. taking 50% of the applied load.
construction is a subject often misunderstood To quote a senior and respected engineer This is not correct, because the props will
in the industry. Regrettably, many permanent on whether concrete slabs get overstressed themselves be elastic members and need
works designers (PWDs) still consider the during construction: “It’s not a question of to shorten as they take load. So, if you have
subject as “not relevant and a contractor’s whether they crack, but by how much they the same two identical floor slabs, but now
issue”. crack!” separated by elastic props (Figure 1b), as the
This article explains the theory and The issue is really quite simple: nearly all load is applied to the top slab, the props have
background to backpropping and gives advice modern buildings are designed for imposed to physically shorten in order to transfer load
on the methods recommended to be adopted loads that represent only a small proportion to the lower slab.
for backpropping calculations. It looks at of the total design load. Many commercial The upper slab must now deflect more
the physics involved and how engineers and buildings have a ratio of imposed load to than the lower slab as the distance apart
designers can mitigate damage to concrete self-weight of 1:2.5, and apartment buildings is reducing. Thus, distribution of load will
slabs during construction. A second article, often less at 1:3.5. Hence, the self-weight of not be even – resulting in more load applied
giving worked examples, with solutions the next slab to be constructed cannot be to the upper slab. The theory predicts an
to reduce overloading flat slabs during taken on the recently completed slab, and approximate 70:30% split of the loads.
construction, will follow in the January issue. the construction loads need to be distributed When the three-dimensional deflected
The client and the PWD have legal to lower, already completed, floor slabs. This shape of a slab is considered, the movement
responsibilities to ensure that a structure transfer of load is known as “backpropping”. of the various members and their method of
can transfer any loads from backpropping. support becomes complex.
The Construction (Design and Management) The physics The simple assumptions discussed so
Regulations 2015 (CDM 2015) legal guidance The mechanics of how loads transfer through far take no account of the different physical
(L153)1 has very specific requirements for slabs is basic physics: within elastic limits stiffness of the completed floor slabs. Older
designers to control temporary works. the deflection of a slab is proportional to the floors are stiffer than newly constructed
The law also states that a structure has to total applied load on the slab – to carry load it ones; hence, they have different deflection
“be of such design … as to withstand any needs to deflect. properties. Further, no account is taken of
foreseeable loads which may be imposed on So, if you have two identical floor slabs the different stiffness of the backprops –
it” (CDM 2015 Reg. 19(2a))1. Backpropping separated by rigid (non-elastic) props aluminium members being less stiff than
during construction is a totally foreseeable (Figure 1a), applying a load to the top slab steel props. Another aspect of load transfer
load on the structure. Hence, designers have would cause both slabs to deflect by the is whether or not the backprops have been
to consider backpropping and understand same amount. Hence, as load/deflection is inserted with some residual load, i.e. as

TSE60_38-41 Temporary works part 4.indd 38 17/11/2016 12:41


www.thestructuralengineer.org

39

S Figure 1
Floor slabs separated by props
than two levels was unnecessary, as the load
just didn’t get distributed to the lowest level.
while striking the falsework to that slab,
a designer has no idea where the weight
The detailed research was written up for of the slab and any imposed load is being
industry use by the Concrete Structures supported. Is it transferred to the building’s
Group in CS140: Guide to Flat Slab Formwork columns/walls? Is it carried by the reprops?
and Falsework3. Is it distributed between various supports?
Early striking of soffit formwork and There have been major collapses of such
falsework was a key issue and the research structures with props “left in place” without an
introduced a new method of considering early understanding of how much load was being
a) Rigid props
striking of slabs. Research was also published transferred and to where!
on a more accurate method of predicting It is therefore an important rule of thumb in
the concrete strength required – based on backpropping calculations that the formwork/
determination of crack width, as opposed to falsework to a recently cast slab be struck
earlier methods based on a simple ratio of completely; the new slab is allowed to take
loads4–6. up its instantaneous deflection under self-
weight, and only then has a designer the
Methodology confidence that the floor self-weight is now
b) Elastic props If you leave propping in under a slab that has being transferred directly to the permanent
just been cast, such as installing “reprops” supports of the columns/walls, etc. Hence,
any loads transferred through this floor
pre-tensioned props which would push the from construction of higher floors will all be
floor above upwards, decreasing its load,
while at the same time increasing the load "It is an important “additional loading” to that already on the
slab.
into the lower floor. The nomenclature usually
used for backpropping relating to the varying
rule of thumb in This rule of thumb does not preclude the
use of, say, two sets of formwork/falsework
stiffness is shown in Figure 2.
backpropping without any backpropping being used. This
is a common technique used in developing
Research
In the 1990s, industry concerns were
calculations that countries as sets of equipment leapfrog
up the building. The Concrete Society’s
formulated into a research project,
culminating in full-scale trials at the European
the formwork/ formwork Worked Example 77 highlights the
limits of such a technique and illustrates the
Concrete Building Project (ECBP) which
were completed in 1998. The research, led
falsework to a significant role of the PWD in accepting that
loads greater than designed are being applied
by Prof. Andrew Beeby, University of Leeds,
was published in 2000 in a Building Research
recently cast regularly during construction.
Consider the general arrangement of
Establishment Report (BR 394 Task 4)2. It
demonstrated that it is the supporting slab
slab be struck construction of a concrete slab, with its soffit
formwork and grid of supporting falsework
below the falsework that takes the majority completely" legs standing on the previously cast floor.
of the load when backpropping. It further When the fresh concrete is placed, does
confirmed that backpropping through more the load distributed into the supporting slab

 Figure 2
Diagrammatic
representation
One level of Two levels of
of backpropping Stiffness backpropping Load backpropping

Slab to be cast

Falsework wp

Supporting slab (1) Ss1

Backprops Sb wb1
Lower slab (2) Ss2
Backprops (when fitted) Sb wb2
Lower slab (3) Ss3
Any preload to props is PP

TSE60_38-41 Temporary works part 4.indd 39 17/11/2016 12:41



Part 4

40 TheStructuralEngineer Technical
December 2016 Temporary Works Toolkit

act as a distributed load, or as individual be used in calculations for assessing the predict the load transfer, knowing the
point loads from each of the falsework legs? amount of backpropping necessary. stiffness of the slabs and the stiffness of the
Further, the grid of backprops below the Worked examples of backpropping backpropping. It considers deflection of the
supporting slab, transferring load to lower calculations using Method 1, including system in two dimensions only.
floors, will rarely be at the same centres as “What if?” scenarios, are published in the Refer to CS1403 for more detailed
the falsework legs (only about a third of the separate booklet with the Concrete Society information on this method.
load is transferred); hence, the concrete formwork guide7.
supporting slab will also have an influence The percentages of load transmitted Method 3
on load transfer. through lower supports for a falsework This method, using simplified equations, is
Thinking in three dimensions complicates cast with no backpropping, with one level given in detail in CS1403 and Section 5.4.2.5 of
backpropping calculations still further. It backpropped, and then with two levels of the Concrete Society formwork guide9.
is more usual for designers to simplify the backpropping, are shown in Table 1. The The equation for two levels of inserted
approach and regard the applied loads from table assumes elastic backprops and, backprops is reproduced below; it assumes
the formwork/falsework as a distributed where there are two levels of backpropping, that the slabs have been struck individually,
load applied to the supporting slab. that they are identical, i.e. exactly above and have taken up their deflected shape,
There are four methods by which each other on the floor plan. prior to installation of the backpropping. The
designers can complete backpropping It is important to state that the distributed analysis assumes that the structure is in two
calculations. load applied on the existing floor slabs is dimensions only, and that to calculate the
additional to the load already supported by loads in backpropping the slabs will be at
Method 1 the floor at the time considered. Designers least twice the stiffness of any backpropping
Based on the University of Leeds research2, will be aware that this method gives loads introduced.
this method (also reproduced in Clause in backpropping significantly less than This makes and (see Fig. 2)
19.3.4 of BS 59758 and in Section 5.4.2.3 previously assumed for rigid backprops.
of the Concrete Society formwork guide9) The corollary being that more load is For two levels of backprops, as shown
uses a simple assumption about the required to be carried by the supporting on the right hand side of Fig. 2:
percentage of load transferred through the slab with the realistic assumption of elastic
supporting slab(s). backprops. Load in top backprops is
The method is generally conservative,
and recommendations on percentages for Method 2 (1)
either one or two levels of backpropping This method uses the equations established
are given. This is the method most likely to by the University of Leeds research2 to

Load in lower backprops is


Table 1: Method 1 percentage of load transfer for flat slabs less than 350mm thick
(2)
No One level of Two levels of
Location Load backprops backprops backprops
fitted
On slab In prop On slab In prop Method 4
This method is a more accurate
New slab cast wp 100% 100% 100%
determination by using a three-dimensional
on falsework 100% 100% 100% representation of the equations in Method
100% 70% wp 65% wp 2. It introduces deflection coefficients and
Supporting slab – –
allows for the location of the slab and its
wb1 deflected shape. Edge panels will behave
Backprops None – 30% wp – 35% wp
differently to internal panels of the slab, etc.
The calculation is presented as an Excel®
Lower slab (2) – 30% wp 23% wp –
spreadsheet on a CD-ROM with CS1403.
The spreadsheet allows selection of
Backprops wb2 None None – 12% wp interior panels, edge panels, corner panels
or panels supported on four sides by walls/
Lower slab (3) – – – 12% wp – beams. The stiffness of the concrete slabs
and backpropping can be varied, and
Notes: props can be preloaded. The output gives
1) Assumes all floors are of similar construction and have similar stiffness at time considered a “loading factor”, a “cracking factor” and
2) Assumes lower and supporting slabs have been struck and have taken up their deflected shape an “effective deflection factor”. If all are
and are carrying their own weight
less than unity, then the limits are safe for
3) The distribution is that percentage of the applied load onto the supporting slab. Each floor slab will
also have to carry its own self weight and any imposed construction loads already on the floor
striking. If any factor is greater than unity,
then reference must be made to the PWD –
4) Determination of the characteristic strength of the slabs to carry the applied loads is not
considered the philosophy of loading a slab to above its
5) All floors are suspended floors and Method 1 slabs are flat slabs design service load is extensively discussed
in Annex E of CS1403.

TSE60_38-41 Temporary works part 4.indd 40 17/11/2016 12:41


www.thestructuralengineer.org

41

With one level of backpropping loads, once the arrangement of the falsework erection has commenced before installing
The previously cast floor slab is now and the backpropping is known, is to use the the backprops, the supporting slab will
the supporting slab for the next level of CS140 spreadsheet3. already be supporting this construction load.
construction, as shown on the left-hand side The load in the two levels of backprops
of Fig. 2. With two levels of backpropping Wb1 and Wb2 may be estimated from Method
The temporary works coordinator Three previously cast floor slabs are now 1, Table 1, Method 3 (using Equations 1 and
(TWC) will need to establish whether the the supports for the new slab, with the 2), or be calculated using another method,
supporting slab has sufficient capacity at most recently cast slab being the critical obviously requiring knowledge of the relative
its very early age to support the self-weight supporting slab, as shown on the right-hand stiffness; the accurate method to predict
of the temporary works and possibly some side of Fig. 2. the loads being to use the Method 4 CS140
imposed construction operations load at The TWC will need to first establish spreadsheet3. The load imposed on the
the time considered. As the supporting slab whether this supporting slab has sufficient supporting slab (1) will be the difference
matures, its capacity should increase up “spare capacity” at its very early age to Wp – Wb1. This loading often governs the
to its design service load capacity. Note support the self-weight of the temporary speed of construction at this critical stage.
that the supporting slab should always works and some imposed construction The TWC must ensure that both the
be considered to take the weight of the operations load at the time considered. As supporting slab (1) and the lower slabs (2)
formwork and falsework for the next slab. the supporting slab matures, its capacity and (3) have each gained sufficient strength
This overcomes the onerous requirement should increase up to its design service load before casting the new slab.
to place the backprops in position before capacity. The supporting slab should always
formwork can be moved vertically up the be considered to take the weight of the Conclusion
building. The intention should be to install formwork and falsework for the next slab. The conclusion from this paper is that all
the backpropping at the earliest available This overcomes the onerous requirement PWDs, as competent designers, need to
opportunity. to place the backprops in position before be aware of the implications of specifying
The load in the backprops Wb1 may be formwork can be moved vertically up the design loads, and understand the effects
estimated from Method 1 (Table 1), or be building. on their slabs during construction caused
calculated using a simplified Method 3 In the backpropping calculations for by load transfers between floors through
equation. The additional load imposed on construction of the new slab, the temporary backprops. It highlights the coordination
the supporting slab will be the difference works designer (TWD) will need to establish needed between the PWD, the TWD and the
Wp – Wb1. This loading is often critical and can the total load during construction Wp. This TWC to ensure safe construction.
govern the speed of construction. The TWC will include the self-weight of the new slab, A second article, to be published in
must ensure that both the supporting slab but with no super imposed construction January 2017, will discuss the research
and the lower slab (2) have gained sufficient load. The self-weight of the falsework and results, give a worked example, and
strength before casting the new slab. formwork may not necessarily be carried demonstrate how to reduce overloading of
The more accurate method to predict the through to the backprops, because if flat slabs during construction.

References

E1 Health and Safety Executive (2015) L153: Managing E5 British Cement Association (2001) Best practice
health and safety in construction: Construction (Design guide No. 4 for in situ concrete frame buildings: Early
and Management) Regulations 2015 – Guidance on striking and improved backpropping (BCA ref. 97.505),
Regulations, Sudbury, UK: HSE Books Crowthorne, UK: BCA

E2 Beeby A.W. (2000) BR 394: A radical redesign of the in E6 Beeby A.W. (2001) ‘Criteria for the loading of slabs
situ concrete frame process, Task 4: Early striking of during construction’, Proc. ICE – Struct. Build.,
formwork and forces in backprops, London, UK: University 146 (2), pp. 195–202
of Leeds and Building Research Establishment Ltd
E7 Concrete Society (2012) CS169: Formwork – a
E3 Concrete Structures Group (2003) CS140: Guide to guide to good practice (3rd ed.). Worked Examples,
flat slab formwork and falsework, Crowthorne, UK: Camberley, UK: Concrete Society
Concrete Society (Guide includes backpropping Excel
spreadsheet on CD-ROM) E8 British Standards Institution (2011) BS5975:
2008+A1:2011 Code of practice for temporary
E4 British Cement Association (2000) Best practice guide works procedures and the permissible stress design of
No. 1 for in situ concrete frame buildings: Early age falsework, London, UK: BSI
strength assessment of concrete on site
(BCA ref. 97.503), Crowthorne, UK: BCA E9 Concrete Society (2012) CS030: Formwork – a
guide to good practice (3rd ed.), Camberley, UK:
Concrete Society

TSE60_38-41 Temporary works part 4.indd 41 17/11/2016 12:41

Vous aimerez peut-être aussi