Académique Documents
Professionnel Documents
Culture Documents
TABLE OF CONTENTS
EXECUTIVE SUMMARY
o 8 intersections are due for some type of upgrade between now and 2011.
o Traffic signal upgrades have not been budgeted and planned for based on the 20-year
life expectancy of the traffic signal hardware.
• Staff plans to address deficiencies by:
o Implementing a work order system in 2008.
o Implementing a regularly scheduled preventative maintenance program in 2007.
o Requesting a total of $257,500 in additional funding to the Traffic Signal Upgrade
Project over the next 5 years. The Traffic Signal Upgrade Project will:
Complete 3 traffic signal upgrades by upgrading the controller cabinet.
Perform 2 complete traffic signal upgrades of City-owned intersections.
Perform 3 complete traffic signal upgrades to the three University of Illinois
traffic signals maintained by the City. The University would be billed for this
work.
Three City-owned intersections that are due for upgrades will not be addressed.
The Kirby Avenue signals were chosen based on public benefit based on the fact
that Kirby is a major commuter route.
Install UPS at 25 intersections.
Complete 3 interconnected signal systems consisting of 18 intersections.
o Tracking time demands for traffic signal timing to determine what re-timing cycle is
feasible at current staffing levels and evaluating whether that is acceptable.
o Moving forward with projects budgeted in the CIP over the next 5 years, including:
Replacement of First and Green traffic signals in 2011.
Replacement of Fourth and University traffic signals in 2011.
Study of the 10 intersection Downtown that will result in approved design
concepts and an implementation plan.
Study of the intersection of Fourth and Daniel.
Installation of new traffic signals at the Duncan/Curtis and Mattis/Curtis
intersections.
o Submitting requests for funding through the CIP process for:
Left turn lanes and replacement of traffic signals at the Kirby/State and
First/Windsor intersections.
New traffic signal installations at the Bradley/McKinley, Kirby/Crescent and
Bradley/Duncan intersections.
1.0 PURPOSE
The purpose of the Traffic Signal Master Plan is to provide a comprehensive evaluation of
the City’s traffic signal system. There are three tasks associated with the Master Plan.
2.1 Introduction.
The traffic signal system is one of the key components of the City’s transportation system.
The basic function of a traffic signal is to assign the right-of-way to vehicles and
pedestrians at busy intersections, enhancing the safe operation of the City’s street network
and reducing the potential for
crashes.
The traffic signal system does not include improvements to intersections that are often
designed and constructed in conjunction with traffic signals as part of a project. These
additional improvements include pavement related to the addition of left or right turn lanes,
storm sewer or pavement related to the realignment of the curb around corners, the
installation of sidewalks or sidewalk ramps, and new pavement markings and signs. These
other improvements become part of other City systems once the project is completed.
3.0 BACKGROUND
Two of these 66 traffic signals are Fire Station Signals. These signals are located at the
intersection of the fire station driveway with a City street and provide protection to fire
equipment responding to and returning from an emergency call.
Some of these 66 City-owned signals include a private driveway or street that is opposite a
City street. The cost sharing arrangements for these locations vary and are outlined in
agreements between the City and the property owner negotiated and approved at the time of
the installation of the traffic signal.
There are also 31 intersections where a City street and/or private drive intersects a State
route. Of these, five are the sole responsibility of the City as a result of conditions agreed
upon by the City and State at the time of installation. The installations were all related to
development. For the remaining 26 intersections, the costs associated with the traffic
signals are divided proportionally by the number of approaches under the jurisdiction of
each agency. The projects to install or replace the equipment are managed by IDOT and
funding is shared between the City and IDOT. Maintenance services are provided by the
City, with IDOT reimbursing the City for their proportional share of the costs.
The locations of the various situations outlined above appear in Exhibit 1 of Appendix A.
3.1.4 Interconnect
In order for traffic signals to be simultaneously programmed and consistently work
together, they must be interconnected. This connection is usually through a physical wire or
fiber optic cable that connects the traffic signals at several intersections along a specific
street. The City also has two interconnects that utilize wireless technologies. The
intersections all communicate with a master controller, which acts as a hub for
communicating with the various signals in the group, similar to a network server with
individual desktop computers.
The master controller has several functions. It tells the individual intersections when to run
various signal timing plans. It can register the emergency vehicle preemption call from one
intersection and direct the other intersections to respond accordingly. It ensures that the
clocks at each intersection are in synch with one another so that coordinated timing plans
operate as intended. Through the use of software and a phone connection, it serves as the
point of contact from the office for investigating reports of malfunctions and to make
changes to timing plans. It can also be programmed to call the office computer and report
on the operation of intersections on a regular basis.
Standard Comment
Video detection Provide detection without compromising integrity of
pavement. Can be serviced without extended lane closures.
Emergency vehicle pre-emption Provides priority to fire equipment.
Light Emitting Diode (LED) Have measured about a 75% savings in power consumption
signal indications over incandescent bulbs. Longer life cycle reduced service
calls.
Enhanced grounding system Provides additional protection from lighting strikes.
Electrical service installation Reduces clutter at intersection and provide power to
additions intersection lighting.
Street lighting photocell location Provided on cabinet to help with testing/troubleshooting
lighting problems.
Combination mast arms Provide intersection lighting.
Uninterruptible Power Supply Maintains signal operation or all-red flash during power
(UPS) outages.
Lower right signal indications for Improves signal visibility when sun is directly behind mast
east-west streets arm mounted signals in morning and evening.
Interconnection with adjacent Maintains integrity of coordinated signal timings. Provides
traffic signals communication back to Public Works.
For the purposes of this master plan the life of a traffic signal
installation is estimated to be about 40 years. This is based on the
anticipated life of mast arms, foundations, and electrical conduit.
At the 20-year mark, the remainder of the above ground and
electrical equipment has met the end of its useful life and should be
replaced to maintain reliability through the second 20-year period. Example of an 40+ year old traffic
signal post.
The reality of these life cycles depends on advances in technology,
changes in design practices, and changes in traffic volumes and patterns. Any of these areas
could shorten the effective life of portions of, or the entire, installation, especially change to
traffic volumes as the result of development. As an example, it is anticipated that a project will
need to improve the intersection of First Street and Windsor Road because it has become
inadequate for the increased traffic along Windsor Road, as well as increases anticipated from
the development of the University’s Research Park and other developments to the south in
Savoy.
Conditions were rated for all traffic signal installations over 15 years old. In general, the
ratings were based on the following:
A map illustrating where these signals are located is included in Exhibit 3 of Appendix A and
the individual intersection summary sheets are included in Appendix B. Some general
observations of the results are:
In the late 1980’s and 1990’s, IDOT participated in a federal program referred to as Operation
Green Light, which provided funds to upgrade or rehabilitate traffic signals. This program
funded a large portion of the costs of various traffic signal projects in Champaign along State
routes, with IDOT and the City funding a small percentage. Operation Green Light has since
been discontinued and the current practice is to upgrade signals when there is a safety issue, or
as part of a larger scale projects such as road projects or intersection projects changing the
geometry of the intersection.
3.4.1 1994 Traffic Signal Master Plan Study Session – July 12, 1994.
Council reviewed and approved the list of the top 20 needed improvements to existing
signalized intersections, as well as a list of ten locations in the City that were potential locations
for new traffic signals. Council also directed staff to continue to let traffic signal projects
compete for funding in the capital improvements plan on their own merits and construct signals
in conjunction with road projects.
3.4.2 1994 Traffic Signal Master Plan Adoption – Council Bill 94-214.
On August, 2, 1994, Council adopted the 1994 Traffic Signal Master Plan.
3.4.3 Approval of Contracts for Projects Included the 1994 Master Plan – Various.
Since 1994, Council has approved various Council Bills, approving contracts for engineering
and construction of various traffic signal projects outlined in the 1994 master plan (some were
part of larger road projects). Of the replacement 20 projects identified in the 1994 master plan,
9 have been completed. Of the 10 new signal locations identified in the 1994 master plan, 8
have been installed. These locations are listed in the following table:
In addition, Council approved various agreements between the City and IDOT regarding cost
share arrangements on projects to install or replace traffic signals along State routes within the
City.
The agreement outlines the level of maintenance required of the City, the cost sharing
arrangements for energy costs related to traffic signal installations along State routes, details
regarding billing, signal timing development and implementation, pavement markings and
emergency vehicle preemption.
The City of Champaign was the lead agency in renegotiating several key points of the
agreement relative to the past maintenance agreements:
• Under the current agreement, the State pays 100% of its share of the energy costs, which
are determined by the number of approaches under the jurisdiction of IDOT; under
previous agreements the local agencies were responsible for all energy costs.
• A multiplier for wages was added to include direct and indirect labor costs, retirement,
social security, health, hospitalization and life insurance, holidays, vacation, sick leave
and workers compensation; resulting in the City being able to bill IDOT at a higher rate
than under previous maintenance agreements.
• The standards for maintenance were changed to more closely reflect what is required for
modern signal equipment; the old agreement was based on what was required for
equipment from 1980, which is now obsolete.
• The length of the maintenance agreement was reduced from 20 years to 10 years; this
was based on the fact that signal technology continues to evolve and the terms of the
agreement need to be revisited more than once every 20 years.
The purpose of this section is to outline current job duties of the various personnel associated
with traffic signals and outline the funding levels for traffic signal activities.
4.1.1 Personnel
The vast majority of current activities are carried out by the Traffic and Lighting Section of
Engineering and a Civil Engineer II. The exception would be the management of larger scale
projects that may include traffic signal replacements or installations. In these cases, the
personnel described below are often asked for input, to review plans, and/or to set up the
intersection settings once the traffic signal is installed.
Electrical Technicians
The City has four electrical technicians responsible for the maintenance of traffic signals and
street lighting. All four work on traffic signals at one time or another. Taking into account
time off for vacation, sick leave, training, and breaks, each electrical technician accounts for
1,580 regular working hours. The Engineering Division timesheet program reports from the
last two full fiscal years indicate that between 50% and 60% of this available work time is
devoted to traffic signals.
identifying how many recurring tasks are completed and includes descriptions of work
performed. The shortcoming of the system is that the amount of hours spent on various types of
work is not available. In lieu of available information, annual hours spent on various activities
have been estimated using available information and estimates provided by staff regarding
various work activities for use in later sections.
The Institute of
Transportation Engineers
(ITE) guidelines for
electrical technician
staffing are in the
neighborhood of one
technician for every 40 to
50 traffic signals. This
number depends on the
complexity of the
intersections and the level
of maintenance desired.
Champaign’s staffing
level for electrical
technicians is between
75% and 95% of ITE
guidelines.
In addition to supervisory and administrative duties related to traffic signals, the supervisor
position is currently responsible for the diagnostics and repair of controllers and other
electronic devices located in the controller cabinet. This person also tests incoming equipment,
participates in plan review for traffic signals, programs traffic signal timings and occasionally
works in the field with the technicians to return equipment to normal operation.
ITE refers to the person responsible for these duties as a Traffic Signal Engineer and estimates
that one full time traffic signal engineer per 100 signals is sufficient. Champaign’s staffing
level for Traffic Signal (Engineer) Supervisor is about half of the ITE recommended level.
These duties can be characterized as support activities. In the ITE guidelines, these duties are
not mentioned in any of the descriptions for traffic signal personnel. It is estimated that
approximately 20% of the Traffic and Lighting Technician’s time is dedicated to traffic signals.
Civil Engineer II
A Civil Engineer II is assigned to traffic signal related work activities. The duties of this
position include:
• managing engineering design consultants and contractors for traffic signal replacement and
traffic signal installation projects
• developing and maintaining traffic signal timings
• performing traffic signal warrant studies
• developing the traffic signal master plan
• providing input as requested on development issues related to traffic signals
• investigating complaints related to signal timings
• working with the Traffic and Lighting Supervisor to identify upgrade and design
modification projects.
It is estimated that approximately 25 to 30% of the Civil Engineer II’s time is dedicated to
traffic signal related work, consisting of both capital improvement projects and traffic signal
operational items such as traffic signal timing development.
The time spent on traffic signal projects varies year to year, depending on the scope of active
projects. Some years the percentage of available staff time has been much lower due to time
demands on other projects or work activities. Until the last few months, time spent on traffic
signals timings and addressing traffic signal issues outside of capital improvement projects was
not tracked individually, but instead was included in the general description of traffic
management, which also included Traffic Service Requests. These two work activities are now
tracked separately, which will allow for future evaluations of Civil Engineer II time spent on
traffic signal operations.
ITE refers to the engineer level staff as a Traffic Engineer. Under the ITE model the traffic
engineer is responsible for traffic signal design, keeping equipment up with technology, signal
timing plans, and administration of signal installations and maintenance. ITE estimates that one
traffic engineer can properly operate and maintain 75 to 100 traffic signals. A survey of 23
cites conducted by ITE found an average of one traffic engineer per 76 signals. Champaign’s
staffing level for Traffic (Civil II) Engineer is about between 25% and 30% of the ITE
recommended level.
4.1.2 Budget
The potential annual funding resources for traffic signals are outlined in the following table.
Table 4-1 Estimated Funding for Traffic Signals1 FY 2006-2007
Line Item Description Amount
02-0702-63002 Traffic Signals - Materials $38,840
02-0702-74001 Utilities – Power2 $71,000
02-0702-74002 Utilities – Phone $1,900
02-0702-512 Electrical Standby3 $17,000
2
02-0702-511 Electrical OT $10,000
02-0702-750 Repair and Maintenance Services $2,500
4
02-0702-720 Miscellaneous Contractual $0
23-0700-0087 Traffic Signal Upgrade CIP Project $136,510
5
Estimated Electrical Technician Staffing Costs $132,209
5
Estimated Staffing Costs $55,623
Estimated Equipment Usage Costs5 $44,480
Total $510,062
1
Outlines maintenance and upgrade funding; does not include individual one-time funding from CIP projects to
install or rehabilitate traffic signals. Traffic Signal Upgrade Project funding level varies from year to year.
2
The line items for electricity and overtime include funding for both traffic signals and street lighting. The
electricity budget is updated annually with the previous year’s expenditures serving as the basis for the funding
level. The amounts shown here only reflect anticipated costs related to traffic signals.
3
Electrical Standby provides an on-call electrician on weekends. The IDOT maintenance agreement calls for
skilled maintenance personnel available for emergency calls.
4
Misc. Contractual is generally used for pavement marking contracts and boring work or painting for street
lighting. It is also available for painting of traffic signals or other work that would be contracted out. This is not
anticipated to be used for traffic signals.
5
Based on IDOT Billing Rate. These costs are funded through several line items that include funding for the
entire Traffic & Lighting Section. The funding directly related to traffic signals for these items is not identifiable.
The operating budget for Traffic and Lighting is updated annually. From year to year,
depending on the needs and priorities identified for the section, the budgeted amount in a given
line item may fluctuate, but generally the operating budget as a whole is relatively stable.
Several of these line items include funding related to street lighting and/or traffic signs and
markings; for those line items, only the portion anticipated for use on traffic signals is shown in
the table. Also, funds can be transferred from one line item to another to address unforeseen
needs during the course of the fiscal year.
4.2 Maintenance.
An effective maintenance program is essential to the successful performance of any traffic
control system. A poorly maintained traffic signal system can compromise the safe and
efficient movement of traffic. As is the case with most equipment, signal systems that are
neglected will likely perform inefficiently and experience premature failure, which could lead
to traffic delay or be a contributing factor in traffic crashes.
The City maintains 106 traffic signals. Of these, 66 are City-owned, 37 are IDOT or IDOT-
City traffic signals, and three are University of Illinois traffic signals. For all of these signals,
the City provides two types of maintenance: response maintenance and preventative
maintenance. Incurred costs associated with IDOT and University traffic signals are billed to
those entities based upon maintenance agreements.
The staff hour estimates in this report are based on a combination of available billing
information, timesheet reports and entries in the Traffic and Lighting Activity Manager.
Because the Activity Manager does not track the number of hours it takes to perform various
tasks and is also dependent upon the information entered, this information was estimated by
staff.
A breakdown of the electrical technician hours spent maintaining the 106 traffic signals the City
is currently responsible for is outlined in the following table:
The City’s purchase of equipment for the maintenance of all traffic signals the City maintains
whether they are the City’s, IDOT’s or the University’s, is funded by the operating budget of
the Traffic and Lighting Section of the Engineering Division. This consists of one line item
(Traffic Signals 02-0702-63002) with an annual amount around $35,000 available. This
amount can be adjusted on an annual basis and, if needed, funds can be transferred from other
line items, as identified in Section 4.1.2.
repairs are tracked, and the responsible party is billed for the costs.
This procedure results in an accurate record of costs associated with response maintenance
related to traffic accidents since the start of FY 01-02. The information was summarized to
calculate the staff hours and annual costs associated with traffic accidents over the last 5 years.
The City is often times reimbursed for these costs. However, the reimbursement is not returned
to the operating budget; they are considered general revenues. The operating budget absorbs
the costs of repairs from crashes. In cases of controller cabinet or mast arm damage, Traffic
and Lighting may work with the City’s Risk Manager to fund the repairs, as the cost of these
items is significant enough that the operating budget may not be able to absorb the costs.
Activities such as cabinet inspections, cabinet cleaning, and hardware maintenance are
performed, but occur as staff availability permits rather than on a calendar interval. The amount
of preventative maintenance performed in a given year is dependent on amount of staff time
spent on response maintenance calls and street lighting work.
4.2.3 Electricity
Ameren IP currently provides electrical service for traffic signals through 91 separate service
connections. The following table illustrates the annual estimated electrical costs billed to the
City for traffic signals:
The electricity costs of each traffic signal installation vary from one to another depending on
the size of the intersection, the equipment present at that location, and whether intersection
lighting and/or other street lighting are included on the same electrical service. Each service
connection is billed individually. In addition to the energy charges, there is also a service
connection fee for each. In order to minimize service connection costs, it is to the City’s
benefit to combine service connections when possible.
For each new traffic signal installation, energy use is metered to determine the amount of
electricity used over a set time period to calculate an unmetered service billing rate. The
information is shared with the utility company and an agreed upon monthly charge for the
intersection is established.
The electricity costs are funded through the Utilities – Power line item in the Traffic & Lighting
operating budget (02-0702-74001). Additional information regarding the calculation of the
electrical costs is included in Appendix C.
The following table illustrates the annual estimated phone charges for these services:
Additional information regarding the calculation of the phone charge estimates is included in
Appendix C.
Maintenance tasks for IDOT intersections are tracked in the activity manager and a summary is
prepared for each activity. In addition to the activity manager information the sheet includes a
detail of the staff time spent, equipment used, and materials utilized along with a total cost.
The cost sharing arrangements for this work are outlined in Exhibit A of the maintenance
agreement, which is included in Appendix C of this report. In general, the costs for individual
intersections are shared proportionally based on the number of approaches under the
jurisdiction of each agency.
As of 2006, there are five intersections that are exceptions to this arrangement, where the City
is responsible for 100% of the costs. In all five cases, the traffic signal was installed as a result
of new development, where the development required the traffic signal installation. The State
does not pay for costs associated with private benefit signals.
Based on available information for 2005, the City spent 400 hours on maintenance of traffic
signals located along State routes. The following table outlines the costs associated with annual
maintenance of traffic signals along State routes, and the corresponding share of those costs for
the City and IDOT.
Cost sharing for electricity follows the same model with one exception. IDOT does not
currently share in the costs associated with intersection lighting installed at the request of the
City. In order to handle this, an agreed upon amount of $5 per street light is deducted monthly
from the total for that intersection before the cost share proportions are applied. The following
table is an estimate of the annual costs associated with electricity for traffic signals along State
routes, and the corresponding share of those costs for the City and IDOT.
For maintenance and phone charges related to interconnected signal systems, the costs are
shared in proportion to the total approaches maintained by each agency within the
interconnected system. The following table is an estimate of the annual costs associated with
phone connections for interconnected signal systems along State routes, and the corresponding
share of those costs for the City and IDOT.
Table 4-8 Phone Service Costs for Signals on State Routes (2005)
Total Amount Billed to City/Paid to SBC $1,080
City’s Share of Costs $540
IDOT’s Share of Costs $540
The following table is a summary of the annual amount billed to IDOT. This estimate is based
on information from calendar year 2005:
Maintenance tasks associated with the three University-owned intersections are tracked and
summarized following same process used for IDOT signals. Based on the billing information
from the past three calendar years, approximately 30 to 40 hours of regular staff hours are spent
annually maintaining these traffic signals.
The maintenance costs associated with maintaining these intersections are the sole
responsibility of the University. The University independently provides power to the traffic
signals. The following table summarizes the annual amounts billed to the University for the
past three calendar years:
Using ITE estimates, it takes about 20 to 25 staff hours per intersection to conduct a retiming
project. The steps in signal timing are outlined below:
• Traffic Data Collection
• Intersection Data Collection
• Input information into traffic signal coordination software (e.g. Synchro)
• Run analysis and adjust based on experience
• Review
• Implement
• Field monitoring (driving) and field adjustments
• Documentation
Again using ITE estimates, traffic signal retiming costs are relatively small – ranging from
$500 to $3,000 per intersection. Traffic signal retiming is also very cost effective, producing
benefit to cost ratios as high as 40 to 1.
ITE recommends that signal timing should be considered at least every three years. In addition,
the following changes also warrant retiming of traffic signals:
• Addition of a signal or upgrade of an existing signal.
This work is currently performed by the Civil Engineer II and the Traffic and Lighting
Supervisor. To date, this activity has been performed when project management, supervisory,
neighborhood traffic issues and other work items considered a higher priority allow. In the last
6 years, 99 of the 106 traffic signals maintained by the City have been timed and coordinated.
The remaining 7 signals have been timed, but are isolated and are therefore not part of a
coordinated system.
On average, 15 traffic signals have been retimed each year. North Prospect Avenue has been
revisited several times during that period. At the conclusion of 2006, 86 of the 99 coordinated
traffic signals will have timing plans that are over three years old, including 34 intersections
with timings over five years old.
ITE estimates that it will take one traffic engineer to properly operate and maintain every 75 to
100 traffic signals. Currently about 25% - 30% of the Civil Engineer II’s time is dedicated to
traffic signal related work. It is estimated that less than 10% is currently allocated to signal
timing.
As the City grows, traffic patterns change, and the distances citizens are traveling within the
City increase, the need to keep traffic signal timings updated will become more pressing.
The staff hour estimates in this section are based on a combination the information in the
Activity Manager and staff estimates. The Activity manager does not track hours for the
various tasks. The quantity of various tasks was taken from the Activity Manager combined
with staff estimates of time to complete a type of task. Based on this estimating procedure,
over the last two years an average of 1,505 hours of Electrical Technician staff hours were
utilized on these activities. The following table provides a breakdown of those hours:
Currently, the materials for this work are purchased using funds from the Traffic Signal line
item in the Traffic and Lighting operating budget and the Traffic Signal Upgrade CIP project.
The total funding remains constant while the percentage assigned to each category may vary
from year to year and is dependent upon the funding needs associated with general
maintenance, repairs, fiscal obligation for IDOT initiated projects along State routes, and staff
availability.
In addition, all 10 of the older downtown installations have had partial upgrades, with
replacement of all of the above ground equipment. Due to the condition of the underground
conduits at these locations, some in excess of 50 years old, only portions of the deteriorating
wiring systems were able to be replaced. In order to replace the wiring, new conduit would
need to be installed. Signal indications were relocated to street light poles where possible to
improve signal visibility. In addition, this had the added advantage of removing street clutter
and reducing the number of fixed objects that could potentially be struck, including large
above-ground concrete foundations. The visibility will be improved further with the
installation of mast arms when the signals are replaced. Although these were not complete
upgrades, they are worth mentioning as an effort to keep the aging signals in the Downtown
area operating safely and as reliably as possible until replacement projects can be funded.
It is estimated that one to two intersections can be upgraded per year with current staffing
levels. Utilizing recent cost information for materials, a full upgrade of a typical four-approach
intersection is approximately $50,200.
Funding for design modification projects is dependent upon the funding demands of general
maintenance, the number of knockdowns, and obligations to projects along State routes.
Design modifications related to safety or recurring problems receive priority over projects such
as interconnect, updating technologies and signal upgrades.
1996 through 2005, CIP projects accounted for the replacement of 8 traffic signals and the
installation of traffic signals at 17 new locations, many of which were related to new
development. In addition, the City had cost shares for the replacement of 8 traffic signals and 5
new installations along State routes.
Each project has its own set of design issues that impact the cost of the project. The scope of
work surrounding a traffic signal installation is dependent upon the age of the existing
infrastructure, existing and projected traffic volumes and movements, the presence and location
of utilities, available City rights-of-way vs. right-of-way that must be purchased, and impacts to
adjacent properties. In addition, zoning plays a role as traffic signals are generally considered
an asset in commercial areas but are sometimes viewed as invasive in residential areas, leading
to a great deal more public participation and concern. All of these factors impact the cost.
Because of these variables, it is not possible to reliably allocate a long term annual amount for
the rehabilitation and installation of traffic signals. Nor is it possible to predict what a “typical
installation” would cost. The only way to truly identify likely costs for a traffic signal
installation is through an Intersection Design Study and/or a Phase I Preliminary Design Study.
The following table summarizes the cost ranges experienced for various types of studies and
projects involving traffic signals:
An IDS generally takes only a cursory look at grade issues along the intersection. It does not
evaluate pavement, sidewalk, drainage or other infrastructure conditions, it does not address
grade issues with adjacent properties that may arise from widening, and it does not identify
potential utility conflicts. Obvious concerns may be noted on the IDS or in the corresponding
memorandum, but the full impact of these items on the cost of the improvements is not known.
Occasionally, the scope of an IDS may be expanded to take a look at grades if it is evident this
is a significant design issue.
IDS’s are currently prepared by engineering consultants and cost between $16,000 and $20,000.
In the past, IDS’s have been funded as the initial step of the CIP project that actually installs the
traffic signals. Construction budgets are not reliable until and IDS is prepared, reviewed, and
approved.
The other funding mechanism currently available is the Intersection Design Study Project
(Project 453). The IDS project was created to address situations where a preliminary budget
number is needed to program the project into the CIP. There are currently only two IDS’s
planned for and funded by this project (Fourth and Daniel; Columbia & Neil), both in fiscal
year 2007.
In addition to this project, the Downtown Signal Study (Project 452) funded in 2007 will
prepare IDS’s for 10 intersections in the Downtown area.
All of the items included in a Phase I study are part of the design process. The Phase I/Phase II
approach simply divides the activities into two parts. The Phase I portion can be performed
prior to allocating funding for the construction of the project. Phase II builds upon that
information and also prepares detailed plans and specifications for contracts to be bid for
construction.
During Phase I, the City can decide how to address construction issues. If feasible, phased
approaches to construction can be decided upon, different design alternatives can be considered
and public input sought. At the conclusion of Phase I, the City has determined the timing and
types of improvements that will be constructed. The engineering consultant then prepares an
estimate of cost. This estimate of cost is based on significantly more information than one
based on an IDS, and is therefore more accurate.
As examples, this approach was utilized for the Prospect and Green intersection in 2002 at a
cost of about $45,000 and for the Kirby and State intersection in 2005 at a cost of about
$70,000. As of April 2006, no other Phase I Design Studies appear in the CIP.
The cost of a traffic signal replacement varies greatly from project to project and is dependent
on the amount of geometric changes needed to accommodate traffic and meet current design
standards. For example, the total cost for the Prospect-Green project, a straightforward signal
replacement without geometric changes, was $324,000 in 2002. On the other end of the
spectrum, the recently completed IDS for the First & Windsor intersection, including significant
widening to accommodate traffic growth resulting from the development of the University’s
Research Park, estimated the cost of the improvements at over $3 million.
The evaluation of an intersection for new traffic signals may occur as a result of a citizen
request, staff suggestion, or as part of a traffic impact analysis required of a proposed
development. There are two levels of new traffic signal installation projects, intersection
improvement projects and traffic signal projects.
These projects typically include the traffic signal installation along with the addition of left
turn lanes and widening of the intersection to accommodate larger vehicles. Widening
projects usually include storm sewer and sidewalks. Significant pavement rehabilitation or
replacement may also be involved. The installations could also include the addition of right
turn or additional through lanes, sidewalk and sidewalk ramps. Intersection improvement
projects usually require the acquisition of right-of-way.
In some cases, changes to the vertical alignment of the road may also be necessary to satisfy
design standards. This involves flattening of rises and dips in the road alignment to
improve visibility, reduce abrupt changes of pavement grades across streets, and/or drainage
as traffic approaches or travels through the intersection.
On the other end of the range, the recently completed IDS for the Bradley-Staley
intersection, which is a scenario involving widening, pavement replacement, grade issues
along Bradley and with adjacent properties, estimated the cost of that project at between
$2.5 and $3 million for one intersection in 2006 dollars.
There are currently no intersection improvement projects fully funded in the CIP. The
Bradley-Staley intersection is partially funded, with the bulk of funding appearing in 2013.
Traffic signal projects consist mostly of electrical work, with a small percentage of concrete
work for minor curb or sidewalk modification. Because they are smaller in scope, a signal
installation that falls into this category can be completed in a shorter timeframe than
installations categorized as intersection improvement projects or traffic signal replacement
projects.
The purchase and installation of all traffic signal equipment is included as part of the
construction contract. In some cases, where the project timeline has been accelerated, the
City purchases the combination mast arms in a separate bid prior to the bid process for
construction. Doing so allows the project to remain on schedule while accommodating the
10 to 15 week lead times for mast arm fabrication and delivery.
There have really only been two such projects, with both occurring in the last 3 years. The
Neil-Town Center project was completed in 2004 at a total project cost of $336,500. The
Duncan-Windsor project was completed in 2005 at a total project cost of $242,143. The
cost differential between the two is related tot the size of the intersections (Neil-Town
Center intersection has 3 approaches with 5 lanes while the Windsor-Duncan intersection
has all 3-lane approaches) and the amount of concrete work included (Neil-Town Center
required some median work and a larger amount of sidewalk modification).
There are currently two projects funded in the CIP that may fall into this category: The
Fourth-Bradley Project (Project 450) in 2008 and the Town Center-Moreland project in
2012.
District 5 maintains a list of intersections that would benefit from upgrade or replacement
and submits the list to Program Development on an annual basis, updating it with input
from the City. The current list includes the intersections of Prospect Avenue with
University Avenue and with Church Street. These intersections compete with other
intersections in the District for funding.
For each project, the City and IDOT enter into an intergovernmental agreement outlining
the cost participation of each agency. In many cases, federal funding (available to IDOT,
but not the City) covers 80% of the costs for these projects, with the City and IDOT
splitting the remaining 20% of the costs proportionally based on the number of approaches
under the jurisdiction of each agency. Additional costs, associated with items included at
the request of the City (emergency vehicle preemption or street lighting as examples), are at
100% cost to the City. In addition, the City also pays for a portion of the engineering costs
associated with the project, typically calculated as 15% of the City’s share of construction.
As an example, IDOT will upgrade the Neil Street (U.S. Route 45) and Windsor Road
traffic signals in 2006. The project will replace all electrical wiring and above ground
equipment such as the controller cabinet, mast arms, signal posts, and signal heads along
with some median removal work and replacement of pavement markings. The total cost of
the project is anticipated to be $274,850 with the City’s share of the cost anticipated to be
$12,305.
The City’s share of these projects is funded through the CIP. The IDOT-City Traffic Signal
Upgrade Project (Project 0087) was created to pay for the City’s share of smaller scale
projects such as the Neil-Windsor project, with an annual funding level of $42,000. If
funding remains after obligations to projects on State routes have been addressed, the
remaining dollars are used to purchase equipment for upgrades or design modification
projects at City-owned intersections.
In general, the cost to the City for most IDOT projects is between $10,000 and $20,000 per
intersection. Generally, the State provides notice of upcoming projects well in advance,
allowing accommodations for funding to be handled through the CIP process for larger
scale projects where the City’s share would be above the budgeted amount.
5.4 Interconnect.
Of the 106 traffic signals maintained by the City, 49 are interconnected with established
communication back to Public Works. City standards include interconnect as part of a
signal installation. The goal is to have remote communication to all 106 traffic signals the
City maintains.
5.6 Frequency of Crash Analyses for Existing and Proposed Signalized Intersections.
This is currently handled through the Champaign-Urbana Urbanized Transportation Study
(CUUATS). CUUATS publishes a Selected Crash Intersection Location Report for every
two years of crash data. The report is used as a preliminary review of all intersections. City
staff reviews the report and conduct additional analysis to confirm the conclusions.
The most recent report includes crash data up to 2002. Crash data is provided by IDOT and
is lagging behind. In addition, once data is received from IDOT, it is another year or so
before the report is published due to demands for CUUATS staff time. CUUATS reports
that the report preparation requires between 240 and 280 hours of staff time.
An annual amount of about 1,200 electrical technician staff hours has been estimated for
scheduled preventative maintenance activities. The estimate was based on projections for
various tasks and may be adjusted once the program is up and established. Additional
information regarding how these estimates were developed is included in Appendix D. It is
anticipated that up to an additional 800 staff hours may be necessary to address issues found
during these scheduled activities. In addition, Traffic & Lighting Supervisor, Traffic &
Lighting Technician, and Civil Engineer II hours will be necessary to develop schedules,
checklists, and track progress.
6.4.1 Upgrades
The life cycle of most traffic signal equipment (the signal heads, posts, pedestrian
pushbuttons, etc.) is 20 years. In order to maintain a reliable traffic signal system, the
traffic signal equipment at an intersection needs to be replaced around the 20-year mark
through an upgrade. The current estimate of in-house upgrade capacity is one large
intersection or two smaller or three-approach intersections in a given year. A full upgrade
of a large intersection was estimated to take about 305 staff hours to complete. This
estimate was used to develop the schedule for upgrades over the next five years. Time and
materials will be tracked so that time and funding needs for upgrades can be refined as the
program moves forward. The traffic signal upgrades planned for the next five years are
outlined in the following table:
At the end of the 5-year planning period two traffic signals will be past due for an upgrade.
In addition, the next two 5-year planning periods (2012-2016 and 2017-2021) will each
require the upgrade of about 15 traffic signals, or an average of 3 per year. The experience
and knowledge gained over the next five years will be used to evaluate whether these
upgrades can be performed with City staff under current staffing levels.
6.4.2 Interconnect.
The City’s long term goal is to have all traffic signals interconnected with communications
between the systems and Public Works. Interconnection of traffic signals has three major
benefits:
• It maintains the integrity of coordinated traffic signal timings (all but 7 of the 106
traffic signals are part of a coordinated system) by ensuring the intersections in a
system are operating in-synch with one another.
• It improves the overall reliability of the signals through automatic reporting of errors
and alarms back to Public Works.
• It improves efficiency by allowing for the monitoring of operations and
investigation of reported controller problems remotely.
Over the next five years, staff will establish three additional interconnect systems totaling
18 intersections. The following table outlines the schedule and locations for interconnect
projects over the next five years:
Interconnect is also included as part of road projects and/or traffic signal projects when
practical.
Over the next five years, staff will install 25 UPS systems (5 per year), coordinating
installations with traffic signal upgrades where possible. Materials for each UPS system are
estimated to cost about $2,500 for an annual cost of $12,500 and each installation is
estimated to require about 12 staff hours. The following table identifies the 25 intersections
that are scheduled to receive UPS systems over the next 5 years.
The installation of a UPS system is also a City standard for all new traffic signal
installations and replacements.
The Institute of Transportation Engineers recommends retiming traffic signals every three
years. Re-timing signals every three years is not realistic given the time demands of other
responsibilities on staff at the current level of staffing. The goal over the next five years is
to collect information that can be used to determine what is a realistic re-timing cycle under
current staffing and if that cycle is acceptable.
Over the next five years, the Civil Engineer II and Traffic and Lighting Supervisor will:
• Re-time at least one signal system per year.
• Track staff hours related to retiming traffic signals to develop a per intersection
estimate of staff hours required for retiming.
• Investigate data collection and data entry alternatives (e.g. intern/co-op hours).
• Evaluate whether the City’s signal timing needs can be met under current staffing
levels.
Staff will also submit requests for funding for three intersections through the Capital
Improvements Plan Process:
• Bradley & Duncan
• Kirby & Crescent
• Bradley & McKinley
There are also intersections that could potentially become future candidates for traffic signal
installations within the next 5 to 15 years depending on the rate of development on the
edges of the City. These intersections are generally the intersection of mile section roads
located along Staley Road, Rising Road, and Olympian Drive. The requests for funding
would be handled through the CIP process.
Over the last 10 years, the number of traffic signals that are 100% City owned has more
than doubled (from 31 to 66). In addition, many signals have been added along IDOT
routes, with the City providing maintenance through an agreement with the State.
During this same time, staffing related to traffic signals has remained constant. The
replacement of several aging street lighting systems and aging traffic signal installations,
along with advances in traffic signal technology, have allowed the City to continue to
maintain its growing system with the same amount of staff. It is not clear if this trend can
continue.
The implementation and evaluation of several of the elements of the master plan over the
next five years will allow the City to determine the capacity of current staff and determine
how best to maintain the traffic signal system at an acceptable level into the future.
Current Conditions: The overall condition of the intersection is poor. The electrical
wiring and conduit is over 40 years old. Wiring failures and crushed conduit have
necessitated the use of overhead wiring to several signal heads. The intersection does not
have mast arms and the pavement and infrastructure are in need of replacement. The
signal heads and posts were replaced in 2003 as an interim measure.
Crash History: This intersection was a SCIL for 24 of the 26 years from 1976 through
2002. It will not likely be a SCIL starting in 2004 due to interim safety enhancements
implemented in fall 2003 (split phasing) and revised in fall 2005 (3-lane cross section).
Prior to 2003, the predominant crash pattern at the intersection was turning crashes
related to visibility of on-coming traffic; a situation created by the four-lane cross section.
Split phasing was implemented in 2003 to address this issue on an interim bases and
greatly reduced turning crashes (2 in 2004) by providing a protected only left turn. In
2005, Green Street was re-striped to 3-lanes, providing a dedicated left turn lane and
improving the visibility of on-coming traffic. This allowed the split phasing to be
removed. Since going back to standard operation in July 2005 (through March 2006)
there has been 1 Turning crash at the intersection and 8 total reported crashes.
The remaining safety issue at the intersection appears to be signal visibility. Of the 8
crashes reported from July 2005-March 2006, 5 crashes have involved red light running,
with signal visibility of post-mounted traffic signal a potential cause. Installation of mast
arm mounted signal heads would improve signal visibility and would reduce
unintentional red light running.
Current Status: Funded as part of Campus Improvement (Project 477) scheduled for
construction in 2011.
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Condition: The overall condition of the intersection is poor. Portions of the
electrical wiring were replaced in 2003 but the conduit is over 40 years old and electrical
junction boxes are located in the street. The intersection does not have mast arms or left
turn phasing. Signal heads and signal posts were replaced in 2004 and, when possible,
were relocated to improve signal visibility until replacement and installation of mast
arms. The intersection has minor geometric deficiencies, with the north and south legs
offset and an island located on the north leg separating the northbound right turn and
through movements.
The predominant crash patterns at this intersection are angle and turning crashes,
accounting for 52 of the 61 crashes (85%). Conditions related to these types of crashes
are signal visibility of the post-mounted signals and possibly the lack of a protected left
turn phase. The odd geometry of the intersection may also play a role.
Current Status: Funded by the Fourth and University Traffic Signal project (Project
359), currently scheduled for construction in 2011 (Project 359). This project funds the
construction of the traffic signal equipment, not the geometric improvements, which will
be funded through the Eastside Streetscape Project (Project 407). The two projects will
need to be coordinated.
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Condition: All ten of these intersections are in poor condition. The traffic
signal equipment was installed between 1953 and 1963. The conduit and, in most cases,
the electrical wiring are over 40 years old with junction boxes located in the street. The
intersections do not have mast arms. Over the last 3 years, signal posts and signal heads
were replaced to improve signal visibility and allow for the installation of LED’s to
reduce power consumption. In 2004, the signal posts and bases were painted black to
match the new signals installed at Main & Neil and First & University. These
improvements are mostly cosmetic and are intended to be interim enhancements to bridge
the gap until the installations can be completely replaced.
Crash History: See the individual intersection assessments at the end of this Appendix
for details of the crash history of these intersections. In general, all but two (Randolph &
Church, State & Church) of these ranked in the top ten for highest 2002 crash rate among
the signalized intersections evaluated by CUUATS. In addition, the predominant crash
types at many of the intersections are angle crashes. The lack of mast arm mounted
traffic signal indications over the street can be a contributing factor to angle crashes.
Current Status: The Downtown Traffic Signal Rehabilitation Project (Project 452) is
funded through the Downtown TIF over the next 10 years, beginning with the
recommended study of the intersections in 2006. Funding for design and construction of
traffic signal replacements currently appears in 2007, 2009, 2011 and 2014 ($55,000 for
design and $275,000 for construction).
Current Condition: The overall condition of this intersection is poor. The traffic signal
equipment was installed in 1983 and the signal hardware is original to the installation.
The signal hardware is 3 years past due for replacement. The intersection does not have
left turn lanes or left turn phasing on Kirby Avenue. The mast arms are aluminum, which
are no longer used and have a tendency to age quicker than steel. Video detection was
installed in 2003 to replace failing loop detectors and the controller cabinet was replaced
to accommodate the video detection.
Left turning traffic on Kirby creates congestion at this intersection, which is the highest
volume intersection without dedicated left turn lanes. With redevelopment of the site on
the north side of Kirby and potential redevelopment on the south side, traffic volumes are
likely to increase at this intersection.
Crash History: This intersection was a SCIL for 1999 and 2000.
The predominant crash pattern at the intersection is eastbound turning (44%) and angle
(38%) crashes. The cause of the turning crashes is most likely the absence of left turn
lanes and phasing. The development on the north side of the intersection will likely
increase left turns, which may in turn increase the number of crashes.
Current Status: Funded by the Kirby and State Project (Project 374) currently
scheduled for construction in 2007.
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Condition: The overall condition of this intersection is poor mainly due to
geometric deficiencies. The intersection does not have left turn lanes and operates under
split phasing for Windsor Road. The split phasing was implemented in 1995 to address a
safety issue related left turning crashes (one of which resulted in a fatality). It was
intended to be an interim measure until left turn lanes could be constructed as part of an
intersection project. Under the current conditions delays along First Street can approach
3 minutes per vehicle in the PM peak according to CUUATS information.
The traffic signal was installed in 1993 and all traffic signal hardware is original to the
installation. The intersection will be due for an upgrade in 2013. The mast arms are in
good condition but do not have intersection lighting.
Crash History: The intersection has a safe operating history over the last 5 years.
Current Status: Funded by the Windsor and First Intersection Improvement Project
(Project 195).
Currently the construction of improvements to the north leg of the intersection, which
serves as the main entrance into the University’s South Research Park, are funded for
2008. Prior to the start of design, an intergovernmental agreement between the
University and the City will be necessary.
The improvements to the other three legs of the intersection are currently unfunded. The
University and the City are working to identify potential funding sources to aid in
financing the improvements.
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Condition: The overall condition of this intersection is poor. The traffic signal
equipment was installed in 1968. The signal posts, wiring, conduit and foundations are
original to the installation. The signal heads are smaller than current standard. The
intersection does not have mast arms.
Current Status: The Intersection Design Study project (Project 453) provides funding
to conduct an Intersection Design Study in 2006.
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Condition: The overall condition of this intersection is fair. The intersection is
6 years past due for an upgrade. The traffic signal was installed in 1980. The mast arms,
signal posts, signal heads, wiring and conduit are original to the installation and are now
26 years old. Video detection was added to the north and south approaches in 2005 to
replace failing in-pavement loops. The east and west approaches remain under loop
detection, which were replaced around 2000.
Crash History: This intersection has been a SCIL every year from 1994 through 2002.
The number of crashes in 2003 and 2004 were about half the number seen on an annual
basis the previous three years.
The predominant crash patterns at the intersection are angle and turning crashes,
accounting for 86% of the crashes. The predominant directions of travel for vehicles
involved have been northbound and eastbound. Several factors may play a role in the
crash pattern: drivers unfamiliar with the area, the proximity of this intersection with the
Neil and Anthony intersection (225 feet), and a horizontal curve just north of the
intersection.
Current Status: An upgrade is funded for 2006 through the Traffic Signal Upgrade
Project (Project 87). The upgrade will include the wiring for future pedestrian
indications.
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Condition: The overall condition of the intersection is poor based on the
condition of the cabinet. The traffic signal equipment was installed in 1988. The mast
arms, signal posts, signal heads, wiring and conduit are original to the installation. The
cabinet has been damaged by mice the condition of its wiring is questionable. The loop
detection on Anthony is operational but suspect. There is no intersection lighting.
In 2003, the east leg was re-striped to provide dual left turn lanes for traffic turning from
Anthony onto southbound Mattis.
A crash pattern could not be established. The increase in 2004 could be a statistical
anomaly or related to an increase in traffic volumes.
Current Status: An upgrade is funded for 2008 through the Traffic Signal Upgrade
Project (Project 87).
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Condition: The overall condition of this intersection is fair. The traffic signal
equipment was installed in 1987. Most of the traffic signal equipment is original to the
installation and will be due for an upgrade in 2007. New detector loops were installed on
Interstate Drive as part of a City project in 2001.
The installation has many design features that do not meet the City’s standards. The
cabinet and cabinet wiring are not standard. There are currently the minimum 2 signal
indications per direction allowed by the MUTCD for northbound and southbound traffic
with unreliable motion sensor detection on Mattis. A dual mast arm, which is also
nonstandard, was used at this intersection. There is a right turn lane of substandard
length for northbound traffic turning onto Interstate that does not include a right turn
overlap. The intersection also lacks a southbound left turn lane for traffic turning onto
Interstate Drive.
The predominant crash pattern at the intersection is southbound rear end crashes,
accounting for 6 of the 10 total crashes and 6 of the 8 rear end crashes. The motion
sensor detection, a lack of advance detection to extend the green indication, and the lack
of a left turn lane may be contributing factors.
Prior to the upgrade, the status of development activities in the area should be checked to
see if development of the land directly to the west that would impact the intersection is
anticipated in the near future. In addition, a turning movement count should be
performed at the intersection to assess the need for a southbound left turn lane and the
crash history should be examined to make sure the intersection is still operating safely.
Current Status: An upgrade is funded for 2008 through the Traffic Signal Upgrade
Project (Project 87).
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Condition: The overall condition of this intersection is good. The traffic signal
equipment was installed in 1986. The signal heads were replaced around 2000. Video
detection was installed in 2003 to provide fully actuated control. The mast arms are
original to the installation and are in good condition but do not have street lighting.
The predominant crash types at the intersection were turning (23 of 52 – 44%) and rear
end (19 of 51 – 43%) crashes. The intersection is one of the busiest in the City. The
volume of traffic is directly related to the number of crashes. At peak periods the
northbound through movement and the southbound left turn movement compete for green
time. The southbound left turn averages more than 175 vehicles per hour through out the
day with peaks approaching 250 to 300. However, there is not room at this intersection
to add capacity through the addition of lanes without significant right-of-way acquisition.
Current Status: A cabinet replacement is funded for 2007 through the Traffic Signal
Upgrade Project (Project 87).
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Condition: The overall condition of these signals is good. The traffic signal
equipment was installed in 1985. The signal hardware was replaced in 2005 and the
intersection was painted black. The mast arms and conduit are original to the installation.
The only detection present at these intersections is for the left turn arrows for traffic
turning from Green Street onto Randolph and State.
Current Status: Cabinet replacements are funded for 2007 through the Traffic Signal
Upgrade Project (Project 87).
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Condition: The overall condition of this intersection is good. The traffic signal
equipment was installed in 1991. The signal hardware is original to the installation and is
due for replacement in 2011. The mast arms are in good condition.
Crash History: The intersection has appeared as a SCIL for 1996 and 2002.
The predominant crash pattern at this intersection is southbound rear end crashes,
accounting for 10 of the 13 rear end crashes (77%) and 10 of the 22 total crashes (45%).
A contributing factor could be the proximity of the I-74 westbound ramp (435 feet to the
south) and possibly confusion regarding the signal indications at the two intersections.
Current Status: Nothing planned for 2007-2011 planning period. This intersection
would be upgraded in the next five-year planning period (2012-2016).
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Conditions: The overall condition of the intersection is good. The traffic
signal equipment was installed in 1988. The signal equipment is original to the
installation and will be due for replacement in 2008. The detector loops in the pavement
are operational but are suspect. The preemption at this intersection is activated be a
pushbutton in the Fire Station located on the southeast corner.
Recommendation: The signal hardware is due for replacement in 2008. Given the safe
operating history, condition of the signal hardware and needs for upgrades elsewhere,
defer the upgrade until the 20012-2016 planning period.
Current Status: Nothing planned for 2007-2011 planning period. This intersection
would be upgraded in the next five-year planning period (2012-2016).
City of Champaign
Traffic Signal Master Plan
Intersection Summary Sheet
Current Condition: The overall condition of this intersection is fair, due to the lack of
mast arms. The traffic signal equipment was installed in 1971. The traffic signal posts
and signal heads were replaced in 2000. However, the conduit and wiring are original to
the installation. The intersection only has detection on the side street and the loop
detectors are suspect. The intersection does not have mast arms but rather has median
mounted signals on Kirby. The intersection does not have left turn lanes.
The predominant crash type at the intersection is turning, accounting for 15 of the 31
crashes (48%). The most common cause of this type of crash on streets with four lanes is
the visibility of oncoming traffic in the curb lane due to the presence of an oncoming
vehicle in the travel lane. This is due to the lack of left turn lanes at the intersection.
Current Condition: The overall condition of this intersection is good. This is a private
benefit signal on a State route that has become the responsibility of the City by default.
The signal is part of a fiber optic closed loop system that includes signals on Springfield
Avenue and Mattis Avenue. The interconnect wiring and cabinet were upgraded by an
IDOT interconnect project in 2003. As part of an overlay project along Springfield
Avenue, IDOT replaced the detector loops in 2004. Also in 2004, the City swapped out
the signal posts and heads for newer equipment transplanted from downtown signals
(which were changed to black hardware).
Recommendation: The safe operating history indicates that the intersection geometry is
fine in its current configuration. The equipment had been upgraded. No actions are
recommended at this time.
Current Condition: The overall condition of these intersections is poor. These two
intersections are controlled by one controller. The traffic signal equipment was installed
in 1963. The electrical wiring and conduit and foundations are over 40 years old. The
intersection does not have mast arms. The signal indications and posts were replaced in
2004 as an interim measure until a replacement project can be funded.
These intersections are located in an area of downtown Champaign that is starting to see
significant redevelopment. The driveway that is the south leg of the intersection does not
have signal indications for it and the property has seen more activity in the last couple of
years. Walnut Street transitions from one-way northbound traffic to two-way traffic at
this intersection. Redevelopment near Market and Washington has increased pedestrian
activity but the intersection does not have any pedestrian indications or pushbuttons and
the current installation cannot be modified to include them due to its age.
Crash History: Market & Washington has a safe operating history. Walnut &
Washington was a SCIL in 2002.
Current Condition: The overall condition of this intersection is poor. The traffic signal
equipment was installed in 1963. The wiring and conduit are over 40 years old. The
intersection does not have mast arms, left turn lanes, or left turn phasing. Most of the
signal heads are original to the installation.
Crash History: This intersection was a SCIL in 1999, 2000 and 2001.
The predominant crash types at the intersection are angle (14 of 34 – 41%) crashes.
Signal visibility of post mounted traffic signals are a contributing factor to angle crashes,
and rear end crashes (of which there were 10 – 29%). The lack of turn lanes is a
contributing factor to turning crashes, which accounted for 5 crashes (15%).
Current Condition: The overall condition of this intersection is poor. These two
intersections are controlled by one controller. The traffic signal equipment was installed
in 1963. The electrical wiring and conduit are over 40 years old. The intersection does
not have mast arms. In 2004, the signal posts and signal heads were replaced with larger
signal indications including LED’s and black signal heads. The signal posts were also
painted black in 2004.
The westbound left turn onto Neil Street is very busy most of the day and backs up
through Walnut at times. The current setup (one controller) limits options for dealing
with this problem.
Crash History: Neil & University has been a SCIL every year since 1992 except for
2000. Walnut & University was a SCIL in 1998.
The predominant crash type at both intersections is the angle crash. Signal visibility
related to the lack of mast arms is a contributing factor to angle crashes.
Current Conditions: The overall condition of these intersections is poor. The traffic
signal equipment was installed in 1953 at Randolph and in 1963 at State. Most of the
equipment is over 40 years old. The signal heads and signal posts were replaced in 2005
and some were relocated to improve visibility in the interim.
Crash History: Randolph & Church was a SCIL in 2000, 2001 and 2002. State and
Church was a SCIL in 1999, 2000, 2001 and 2002.
The predominant crash type at both intersections is the angle crash. Signal visibility
related to the lack of mast arms is a contributing factor to angle crashes.
Current Conditions: The overall condition of these intersections is poor. The traffic
signal equipment was installed in 1955 at Randolph and in 1963 at State. The wiring and
conduit is over 40 years old. In 2004, the signal posts and signal heads were replaced
with larger signal indications including LED’s and black signal heads. The signal posts
were painted black.
Crash History: Randolph & University was a SCIL in 2001 and 2002. State and
University was a SCIL in 1998, 1999, 2001 and 2002.
The predominant crash type at this intersection is the angle crash (41 of 63 for 65%).
Signal visibility of post mounted signals could be a contributing factor.
The predominant crash type at this intersection is the turning crash (16 of 34 for 47%).
Current Condition: The overall condition of the intersection is poor. The traffic signal
equipment was installed in 1955. The wiring and conduit are over 40 years old. The
intersection does not have mast arms. The signal equipment on the southwest corner is
mounted over a vault. The signal heads, posts, electrical service and controller were
replaced in 2003. The signal posts were painted black in 2004.
The predominant crash types at this intersection are angle and turning crashes.
*The purpose of this is to show the proportion of equiavent value spent on City intersections using the billing rate
charged to outside agencies as the basis for comparison. This may not reflect acutal costs to the City.
Summary
Revenue from
Estimated Upfront Costs Reimbursement Net Cost to City
Traffic Signals (02-0702-63002) $38,840 $4,360 $34,480
Repair and Maintenance Services (02-0702-750) $2,500 $500 $2,500
Miscellaneous Contractual (02-0702-720) $0 $0 $0
Utilities - Power (02-0702-63002) $71,000 $32,000 $39,000
Utilities - Phone (02-0702-74002) $1,900 $540 $1,360
Electrical Standby (02-0702-512) $17,000 $0 $17,000
Electrical OT (02-0702-511) $10,000 $1,995 $8,005
Regular Electrical Technician Staff Hours (Estimat $132,209 $14,680 $121,866
Other Staff Time (Estimated) $55,623 $0 $55,623
Equipment Usage - Vehicles (Estimated) $44,480 $5,129 $39,352
Grand Totals $373,552 $59,204 $319,186
Estimated Cost Per Signal Maintained $3,524
Prepared 5/06 by CBS
Annual Electrical Technician Traffic Signal Hours
Annual Hours
Response Maintenance
Accident Response 119
Lamp Changes 400
Power failure responses 48
Preemption issues 68
Repairing/replacing failed hardware 176
Total 811
Notes:
Contractor costs are associated with accidents requiring the replacement of a traffic signal mast arm.
The City is reimbursed for these costs. However the Traffic & Lighting Budget is not, and must absorb these costs.
Signal posts knockdowns account for most of the incidents. The costs for repairing range from $500 to $1,500 in general.
Cabinet knockdowns are the most costly from both a material and man-hour perspective. A cabinet knowckdown is around $7,000 to repair.
Mast arm damage requires the use of a contractor because a line truck is necessary to set the equipment. Mast arm replacement is around $6,000.
Electricity Charges Summary
DATE:
5287,1(0$,17(1$1&( $&&,'(17'$0$*(
&2175$&7255(3$,56 081,&,3$/,7<0$,17(1$1&(
MATERIALS $0.00
TOTAL COST $0.00
LESS THIRD PARTY CLAIMS $0.00
NET COST $0.00
PERCENTAGE STATE SHARE 100% PAY $0.00
Revenues
Contingency* To be requested upon MP approval $ 25,000 $ 25,000 $ 25,000 $ 25,000
Total Revenues $ 136,510 $ 148,900 $ 87,700 $ 101,200 $ 87,700
Intersection (20-year mark) Upgrade Work 2007 2008 2009 2010 2011
Various State-City Intersections LED installations (grant funded) $ 70,551
Randolph & Green (2005) FC $ 9,200
State & Green (2005) FC $ 9,200
Mattis & Kirby (2006) FC $ 9,200
Mattis & Interstate (2007) H, FC, D, P $ 45,200
Mattis & Anthony (2008) H, FC, D, P $ 45,200
Upgrades
Kirby & Fourth* (2003) H, FC, D, P $ 50,200
Kirby & First* (2009) H, FC, D, P $ 50,200
Kirby & Oak* (2009) H, FC, D, P $ 50,200
Upgrade Total $ 98,151 $ 90,400 $ 50,200 $ 50,200 $ 50,200
Intersections 2007 2008 2009 2010 2011
With Upgrade: Randolph & Green, State & Green, Mattis & Kirby $ 7,500
With Upgrade: Mattis & Anthony, Interstate $ 5,000
With Upgrade: Kirby & Fourth* $ 2,500
With Upgrade: Kirby & First* $ 2,500
With Upgrade: Kirby & Oak* $ 2,500
UPS Only: Mattis & Windsor, Neil & Green $ 5,000
UPS Only:Mattis & Bloomington, Bradley, Paula $ 7,500
UPS Only:Kirby & Neil, Prospect; Bradley & CFD, Clayton $ 10,000
UPS Locations
UPS Only: Windsor & Prospect, Galen; Prospect & Bloom., Town Center $ 10,000
UPS Only:Bradley & State, Randolph, Neil, Market $ 10,000
Alt. UPS Only: Springfield & Neil, Randolph, State, Prospect, Mattis
UPS Total $ 12,500 $ 12,500 $ 12,500 $ 12,500 $ 12,500
System Name Number of Intersections 2007 2008 2009 2010 2011
North Neil Interconnect (partial) 7 intersections - Fiber $ 23,000
North Mattis Interconnect 7 intersections - Radio $ 21,000
Kirby (4th-State) Interconnect 4 intersections - Radio $ 13,500
Interconnect
Interconnect Total $ 23,000 $ 21,000 $ - $ 13,500 $ -
Current Funding in CIP $ 136,510 $ 42,000 $ 42,000 $ 42,000 $ 42,000
Additional Funds Required $ - $ 106,900 $ 45,700 $ 59,200 $ 45,700
Projected Funding $ 136,510 $ 148,900 $ 87,700 $ 101,200 $ 87,700
Total Estimated Expenditures $ 133,651 $ 123,900 $ 62,700 $ 76,200 $ 62,700
Contingency* $ 2,859 $ 25,000 $ 25,000 $ 25,000 $ 25,000
Balance $ - $ - $ - $ - $ -
*Contingeny funds are reserved to pay the City's share of traffic signal upgrades at the intersection of City streets with State routes. It is also reserved in the event of the failure of an
expensive piece of equipment that the Traffic & Lighting Operating budget could not absorb (most commonly to purchase a video detection system when detection at an intersection fails).
Replacement
State Street and University Avenue 1963 NA X in need of replacement 2003
University Avenue and Fourth Street 1963 NA X in need of replacement 2003
Wanut Street and University Avenue 1963 NA X in need of replacement 2003
(14 intersections)
Market Street and Mercury Drive** 1999 2019 2039
Bradley Avenue and Clayton Blvd. 2001 2021 2041
Bradley Avenue and Country Fair Drive 2001 2021 2041
Replacement
State Street and University Avenue 1963 NA X in need of replacement 2003
University Avenue and Fourth Street 1963 NA X in need of replacement 2003
Wanut Street and University Avenue 1963 NA X in need of replacement 2003
(14 intersections)
Market Street and Mercury Drive** 1999 2019 2039
Bradley Avenue and Clayton Blvd. 2001 2021 2041
Bradley Avenue and Country Fair Drive 2001 2021 2041