CALCULO DEL ADELANTO POR MATERIALES E INSUMOS DE ACUERDO A LA FORMULA POLINOMICA

K= 0.387*(Jor / Joo) + 0.181*(HeCeDr /HoCeDo) + 0.193*(AgTur /AgTuo) + 0.080*(Ccr / Cco) + 0.159*(GGr /GGo)

Monom Factor (%) Símbolo Indice Descripción


io
1 0.387 100.000 Jo 47 MANO DE OBRA
2 0.181 61.326 HeCeD 37 HERRAMIENTA MANUAL
0.181 27.072 21 CEMENTO PORTLAND TIPO I
0.181 11.602 30 DÓLAR MAS INFLACION DEL MERCADO USA
3 0.193 34.715 AgTu 72 TUBERIA DE PVC
0.193 65.285 5 AGREGADO GRUESO
4 0.080 100.000 Ag 03 ACERO DE CONSTRUCCION CORRUGADO
5 0.159 100.000 GG 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR

CALCULO DEL MONTO MAXIMO AUTORIZADO


MONTO PARCIAL MONTO
INCIDENCIA CONTRATO Imo Ima MATERIALES
CODIGO IND ELEMENTO % COEF. MONOMIO
PARCIALES SIN IGV Aug-16 Sep-16 DEFLATADO

Jo 47 MANO DE OBRA 100.000% 0.387 0.387 1,384,602.38 535,841.12 562.24 562.24


HeCeD 37 HERRAMIENTA MANUAL 61.326% 0.181 0.11100006 1,384,602.38 153,690.95 289.39 290.69
21 CEMENTO PORTLAND TIPO I 27.072% 0.181 0.04900032 1,384,602.38 67,845.96 457.28 459.93 68,239.14
30 DÓLAR MAS INFLACION DEL MERCADO USA 11.602% 0.181 0.02099962 1,384,602.38 29,076.12 467.56 474.82
AgTu 72 TUBERIA DE PVC 34.715% 0.193 0.06699995 1,384,602.38 92,768.29 412.85 415.68 93,404.20
05 AGREGADO GRUESO 65.285% 0.193 0.12600005 1,384,602.38 174,459.97 439.92 437.98 173,690.62
Ag 03 ACERO DE CONSTRUCCION CORRUGADO 100.000% 0.080 0.08 1,384,602.38 110,768.19 461.45 466.04 111,869.99
GG 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 100.000% 0.159 0.159 1,384,602.38 220,151.78 430.96 431.85
1.000

DEL MONTO TOTAL DEL CONTRATO 447,203.94


TOTAL INCIDENCIA DE MATERIALES E INSUMOS 32.30% (A)
MONTO DE CONTRATO SIN IGV 1,384,602.38 (B)
MONTO MAXIMO DE MATERIALES SEGÚN POLINOMICA SIN IGV 447,203.94 C = ( A X B ) AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE
CALCULO DEL ADELANTO POR MATERIALES E INSUMOS DE ACUERDO A LA FORMULA POLINOMICA

Subpresupuesto 001 AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ALCANTARILLADO


Fecha Presupuesto 6/12/2017

Moneda NUEVOS SOLES

AREA GEOGRAFICA 1 AMAZONAS - CONDORCANQUI - NIEVA - URAKUSA

K= 0.339*(Jor / Joo) + 0.174*(CeAcFr /CeAcFo) + 0.250*(AgTur /AgTuo) + 0.078*(Mer / Meo) + 0.159*(GGr /GGo)

Monom Factor (%) Símbolo Indice Descripción


io
1 0.339 100.000 Jo 47 MANO DE OBRA
2 0.174 45.977 CeAcF 21 CEMENTO PORTLAND TIPO I
0.174 24.713 32 FLETE TERRESTRE
0.174 29.310 3 ACERO DE CONSTRUCCION CORRUGADO
3 0.250 51.600 AgTu 5 AGREGADO GRUESO
0.250 48.400 72 TUBERIA DE PVC
4 0.078 100.000 Me 49 MAQUINARIA Y EQUIPO IMPORTADO
5 0.159 100.000 GG 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR

CALCULO DEL MONTO MAXIMO AUTORIZADO


MONTO PARCIAL MONTO
INCIDENCIA CONTRATO Imo Ima MATERIALES
CODIGO IND ELEMENTO % COEF. MONOMIO PARCIALES SIN IGV Aug-16 Sep-16 DEFLATADO

Jo 47 MANO DE OBRA 100.000% 0.339 0.339 1,140,790.22 386,727.88 562.24 562.24


CeAcF 21 CEMENTO PORTLAND TIPO I 49.977% 0.174 0.08695998 1,140,790.22 99,203.09 457.28 459.93 99,777.99
32 FLETE TERRESTRE 24.713% 0.174 0.04300062 1,140,790.22 49,054.69 463.48 462.71
3 ACERO DE CONSTRUCCION CORRUGADO 29.310% 0.174 0.0509994 1,140,790.22 58,179.62 461.45 466.04 58,758.32
AgTu 5 AGREGADO GRUESO 51.600% 0.250 0.129 1,140,790.22 147,161.94 439.92 437.98 146,512.97
72 TUBERIA DE PVC 48.400% 0.250 0.121 1,140,790.22 138,035.62 412.85 415.68 138,981.82
Me 49 MAQUINARIA Y EQUIPO IMPORTADO 100.000% 0.078 0.078 1,140,790.22 88,981.64 298.91 303.08
GG 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 100.000% 0.159 0.159 1,140,790.22 181,385.64 430.96 431.85
1.000

DEL MONTO TOTAL DEL CONTRATO 444,031.11


TOTAL INCIDENCIA DE MATERIALES E INSUMOS 38.92% (A)
MONTO DE CONTRATO SIN IGV 1,140,790.22 (B)
MONTO MAXIMO DE MATERIALES SEGÚN POLINOMICA SIN IGV 444,031.11 C = ( A X B ) AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ALCANTARILLADO

RESUMEN DEL ANALISIS

MONTO MAXIMO DE MATERIALES SEGÚN POLINOMICA SIN IGV 447,203.94 I AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE
MONTO MAXIMO DE MATERIALES SEGÚN POLINOMICA SIN IGV 444,031.11 II AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ALCANTARILLADO

MONTO MAXIMO DE MATERIALES SEGÚN POLINOMICA SIN IGV 891,235.05 ( I + II )

MONTO MAXIMO PERMITIDO A SOLICITAR POR MATERIALES SIN IGV 512,006.75 (D) 20% DEL MONTO TOTAL DEL CONTRATO

CONCLUSION EL CONTRATO Y LA FORMULA POLINOMICA PERMITEN SOLICITAR HASTA EL 20% S/. 512,006.75 SIN IGV
CALCULO DEL ADELANTO POR MATERIALES E INSUMOS DE ACUERDO A LA FORMULA POLINOMICA
EL CONTRATISTA SOLICITA S/. 512,006.75 20.00% DEL MONTO DE CONTRATO
CALCULO DEL ADELANTO POR MATERIALES E INSUMOS DE ACUERDO A LA FORMULA POLINOMICA

PREAGRUPAMIENTO - DE FORMULA POLINOMICA


MONTO DEL CONTRATO SIN IGV - AMPLAICION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE S/. 1,384,602.38

Indice Descripción % Inicio % Saldo Agrupamiento


SOLO MATERIALES O
TODOS LOS INSUMOS DE
INSUMOS DE ACUERDO A
ACUERDO A EXPEDIENTE
EXPEDIENTE

AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE


AGUA POTABLE

4 AGREGADO FINO 0.200 0.000 2,769.20 2,769.20


38 HORMIGON 0.979 0.000 13,555.26 13,555.26
05 AGREGADO GRUESO 11.265 12.606 4+38+80 155,975.46 155,975.46
80 CONCRETO PREMEZCLADO 0.162 0.000 2,243.06 2,243.06

10 APARATO SANOTARIO CON GRIFERIA 0.023 0.000 318.46 318.46


66 TUBERIA DE ASBESTO CEMENTO 0.005 0.000 69.23 69.23
72 TUBERIA DE PVC 6.700 6.745 10+66+73 92,768.36 92,768.36
73 DUCTOS Y ACCESORIOS DE TELEFONOS DE PVC 0.017 0.000 235.38 235.38

267,934.41

MONTO DEL CONTRATO SIN IGV - AMPLAICION Y MEJORAMIENTO DEL SISTEMA DE ALCANTARILLADO S/. 1,140,790.22
AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ALCANTARILLADO

4 AGREGADO FINO 0.257 0.000 2,931.83 2,931.83 500


38 HORMIGON 0.454 0.000 5,179.19 5,179.19 agregado grueso
05 AGREGADO GRUESO 11.911 12.875 4+38+80 135,879.52 135,879.52 ductos
80 CONCRETO PREMEZCLADO 0.253 0.000 2,886.20 2,886.20

10 APARATO SANOTARIO CON GRIFERIA 0.251 0.000 2,863.38 2,863.38


72 TUBERIA DE PVC 10.845 12.077 10+73 123,718.70 123,718.70
73 DUCTOS Y ACCESORIOS DE TELEFONOS DE PVC 0.981 0.000 11,191.15 11,191.15

284,649.97
552,584.38
552,584.38

MONTO MAXIMO AUTORIZADO DE ACUERDO A LA FORMULA POLINOMICA - PREAGRUPAMIENTO S/. 552,584.38

MONTO SOLICITADO POR EL CONTRATISTA S/. 512,006.75


CALCULO DEL ADELANTO POR MATERIALES E INSUMOS DE ACUERDO A LA FORMULA POLINOMICA

DESCRIPCION DE MATERIALES SOLICITADOS


MATERIALES
Indice Descripción INCIDENCIA MONTO EN S/.
AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE

4 AGREGADO FINO 0.200


38 HORMIGON 0.979 3,664.71
05 AGREGADO GRUESO 11.265 155,975.46
80 CONCRETO PREMEZCLADO 0.162

10 APARATO SANOTARIO CON GRIFERIA 0.023


66 TUBERIA DE ASBESTO CEMENTO 0.005
72 TUBERIA DE PVC 6.700 92,768.36
73 DUCTOS Y ACCESORIOS DE TELEFONOS DE PVC 0.017 252,408.53

AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE ALCANTARILLADO

4 AGREGADO FINO 0.257


38 HORMIGON 0.454
05 AGREGADO GRUESO 11.911 135,879.52
80 CONCRETO PREMEZCLADO 0.253

10 APARATO SANOTARIO CON GRIFERIA 0.251


72 TUBERIA DE PVC 10.845 123,718.70
73 DUCTOS Y ACCESORIOS DE TELEFONOS DE PVC 0.981 259,598.22

TOTAL S/. 512,006.75 512,006.75


I.G.V. 92,161.22
MONTO TOTAL SOLICTADO POR EL CONTRATISTA INCLUIDO EL I.G.V. 604,167.97

DE ACUERDO AL CALENDARIO DE ADQUISICION DE MATERIALES SE REQUIERE ADQUIRIR TODO EL PRIMER ESTAMOS DENTRO DE LO PROGRAMADO

POR LO TANTO EL ADELANTO DE MATERIALES ES PROCEDENTE POR EL MONTO SOLICTADO DE S/ 604,167.97 INC I.G.V.
CALENDARIO DE ADQUISICIÓN DE INSUMOS
Obra: MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCION DEL SISTEMA DE ALCANTARILLADO DE LA LOCALIDAD DE MIRAFLORES, DISTRITO DE HUAMBO - RODRIGUEZ DE MENDOZA - AMAZONAS

CONTRATISTA CONSORCIO EJECUTOR HUAMBO


Fecha: OCTUBRE - 2016

PLAZO DE EJECUCIÓN = 180 D.C.


Código Recurso Und Cantidad Precio (S/.) Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
30 Días 30 Días 30 Días 30 Días 30 Días 30 Días

01 SISTEMA DE AGUA POTABLE 407,745.36


0201800003 ABRAZADERA EN UNION PENDOLA - TUBERIA 2" und 18.13 40.00 1,216.79 1,216.79
0202000007 ABRAZADERA EN UNION PENDOLA - TUBERIA 4" und 18.13 5.00 3,911.33 3,911.33
0202000008 ACERO CORRUGADO fy=/12ü0 kfl/cm2 GRADO GO kg 2.75 5.00 337.21 337.21
0202010003 ACERO LISO DE 3/4" m 5.14 4.50 13.50 13.50
0202010005 ADAPTADOR PVC 01/2" und 0.70 4.50 511.97 511.97
0202010006 ADAPTADOR PVC 2" und 3.78 10.00 125.00 125.00
0202010022 ADAPTADOR PVC SAP 1" und 2.19 6.00 180.00 180.00
ADAPTADOR PVC SAP 2 1/2" und 3.68
ADAPTADOR PVC SAP und 3.78
ADAPTADOR PVC SAP 3" und 8.35
ADAPTADOR PVC SAP 4" und 12.92
ADAPTADOR PVC SAP 0=7." und 6.16
ADAPTADOR UPR PVC 1" und 2.48
ADAPTADOR UPR PVC 21/2" und 3.68
ADAPTADOR UPR PVC 2" und 6.16
ADAPTADOR UPR PVC 4" und 9.94
Adaptador UPR PVC 01/2" und 0.70
ADAPTADORES HDPII 0 2" und 3.66
AD IT 1VO 1 MPERM EABILIZANTE kg 5.29
AFIRMADO m3 163.23
AGUA m3 4.32
ALAMBRE NEGRO N* 1G kg 4.50
ALAMBRE NEGRO N* 8 kg 4.50
ANDAMIO DE MADERA p2 4.02
ANGULO DE l"xl"xl/8" m 66.43
ARENA FINA m3 211.16
ARENA GRUESA m3 206.51
ARMES DE SEGURIDAD + LINEA DE VIDA und 210.53
BALDE HERMETICO PARA AGUA CON TAPA 15L pza 12.51
BARRENO DE 7/8" xS PIES und 352.34
BISAGRA AI.UMINIZADA DE 3" X 3" und 2.44
BISAGRAS DE SEGURIDAD DE 4" und 2.44
QUSHING DE BRONCE 0 l/2"xl" und 6.39
CAJA DE CONCRETO DE 0.80x0.60x0.50 P/CONEX. DOMICIL und 55.76
CALAMINA GALVANIZADA 1.83x0.83mx0.22mm PL 20.36
CAMILLA RIGIDA und 661.65
CANASTILLA DE BRONCE DE 5" und 132.19
CARTILLAS INFORMATICAS DE SEGURIDAD GLB. 1,539.85
CEMENTO PORTLANDTIPO 1 (42.5KG) bis 24.50
CALENDARIO DE ADQUISICIÓN DE INSUMOS
Obra: MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCION DEL SISTEMA DE ALCANTARILLADO DE LA LOCALIDAD DE MIRAFLORES, DISTRITO DE HUAMBO - RODRIGUEZ DE MENDOZA - AMAZONAS

CONTRATISTA CONSORCIO EJECUTOR HUAMBO


Fecha: OCTUBRE - 2016

PLAZO DE EJECUCIÓN = 180 D.C.


Código Recurso Und Cantidad Precio (S/.) Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
30 Días 30 Días 30 Días 30 Días 30 Días 30 Días

CINTA NORMALIZADA DE SEÑALIZACION m 1.37


CLAVOS DE 2 1/7.". 3" Y4" kg 4.62
CLAVOS PARA CALAMINA kg 6.50
CLAVOS PARA MADERA C/C 3" kg 4.62
CODO 'JO' F‘G" 0 1/7." und 1.80
CODO DE 22.5’ PVC !>AI’ CLASE 10 DE 1" und 2.37
CODO DE 22.G* PVC ÜAP CLASE 10 DC 3/*1" und 1.50
CODO DE 22.5- PVC SAP CLASE 10 DE 4" und 11.13
CODO DE 45* PVC SAP CLASE 10 DE 1" und 2.44
CODO DE 45° PVC SAP CLASE 10 DE 112" und 1.07
CODO DE 45° PVC SAP CLASE 10 DE 2" und 5.07
CODO DE 45° PVC SAP CLASE 10 DE 3/4" und 1.50
CODO DE 45° PVC SAP CLASE 10 DE 4" und 11.13
CODO DE 90° DE PVC 0 4" und 5.56
CODO DE 90° PVC SAP CLASE 10 DE 1" und 2.11
CODO DE 90° PVC SAP CLASE 10 DE 2" und 7.91
CODO DE 90° PVC SAP CLASE 10 DE 4" und 11.13
CODO DE F°G° DE 3"x90° und 7.59
CODO HDPE4" DE 90° und 9.62
CODO PVC 90° DE 4" und 7.91
CODO PVC SAP 2 1/2"x90° und 5.64
CODO PVC SAP 90° DE 2 1/2" und 5.48
CODO PVC SAP 90° DE 3" und 5.96
CODO PVC SAP 01 1/2" und 5.56
CRUZ PVC SAP DE 2" und 28.00
CRUZ PVC SAP DE 3" und 11.92
EPOXICO gln 96.76
ESTACAS DE MADERA CAPIRONA 1"x1"x0.30m. und 1.81
EXTINTORES PARA FUEGO 6KG TIPO B und 145.35
EXTINTORES PARA FUEGO 6KG TIPO C und 145.35
GIGANTOGRAFIA PARA CARTEL DE OBRA m2 42.11
GRAPAS kg 6.47
GRAPAS DE ACERO 3/8" und 0.74
GRAVA m3 83.13
GRAVA DE 2" m3 83.13
GRAVA DE 01" m3 83.13
Grava 0 máx=1/2" m3 165.21
GRIFO DE BRONCE 1/2" - PESADO und 16.14
GRILLETE DE 1/2" und 5.87
GUARDACABLE DE 3/8" und 1.85
CALENDARIO DE ADQUISICIÓN DE INSUMOS
Obra: MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCION DEL SISTEMA DE ALCANTARILLADO DE LA LOCALIDAD DE MIRAFLORES, DISTRITO DE HUAMBO - RODRIGUEZ DE MENDOZA - AMAZONAS

CONTRATISTA CONSORCIO EJECUTOR HUAMBO


Fecha: OCTUBRE - 2016

PLAZO DE EJECUCIÓN = 180 D.C.


Código Recurso Und Cantidad Precio (S/.) Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
30 Días 30 Días 30 Días 30 Días 30 Días 30 Días

HIPOCLORITO DE CALCIO AL 70% kg 15.00


HIPOCLORITO DE SODIO DE 8% AL 10% It 12.96
HORMIGON m3 183.64
IMPRESORA und 851.69
IMPRIMANTE kg 16.31
INSTRUMENTO CALIBRADO PARA CALIDAD DE AIRE pza 625.53
INSTRUMENTO CALIBRADO PARA CALIDAD DEL SUELO pza 240.59
INSTRUMENTO CALIBRADO PARA NIVELES DE RUIDO pza 96.24
LADRILLO KK18 HUECOS 9X12.5X23 cm und 1.05
LETRINA pza 5,097.50
LIJA DE FIERRO # 80 pza 1.53
LLAVE DE PASO DE 1/2" PVC und 4.09
MADERA CAPIRONA P2 2.05
MADERA CAPIRONA DE 2"x2"x12' und 2.05
MADERA CAPIRONA DE 2"x3"x10 p2 2.05
MADERA CAPIRONA ROLLIZO DE 4"x1.25 m und 6.03
MADERA CAPIRONA ROLLIZO DE 4"x4 m und 6.03
MADERA TRATADA 3"x3" L=1.45m und 21.58
MADERA TRATADA 6"x6" L=2.00m und 21.58
MADERA TRATADA e=1" L=0.375 und 21.58
MALLA DELIMITADORA DE PLASTICO m 1.37
MASILLA SELLADORA DE POLIURETANO gln 18.35
NIPLE DE F°G° DE 1/2 " x 1 1/2" und 1.80
NIPLE DE F°G° DE 3"x4" und 8.04
NIPLE F°G° 2 1/2" und 7.15
NIPLE F°G° DE 2" und 6.40
NIPLE F°G° 0=2" und 6.00
NIPLE HDPE L=1.5" 0 4" und 12.51
NIPLE PVC L=1.5" 2 1/2" und 6.71
NIPLE PVC L=1.5" 2" und 6.71
NIPLE PVC SAP 1" und 3.48
NIPLE PVC SAP 2" und 6.71
NIPLE PVC SAP 3" und 2.02
NIPLE PVC SAP 4" und 3.58
PAPEL BONDA4 80 GRAMOS mil 28.39
PEGAMENTO PARA PVC gln 105.00
PERNOS DE 3/8" X 2 1/2" und 0.46
PIEDRA CHANCADA 1/2" m3 154.88
PIEDRA CHANCADA 1/4" m3 83.13
PIEDRA CHANCADA 1/8" m3 83.13
CALENDARIO DE ADQUISICIÓN DE INSUMOS
Obra: MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCION DEL SISTEMA DE ALCANTARILLADO DE LA LOCALIDAD DE MIRAFLORES, DISTRITO DE HUAMBO - RODRIGUEZ DE MENDOZA - AMAZONAS

CONTRATISTA CONSORCIO EJECUTOR HUAMBO


Fecha: OCTUBRE - 2016

PLAZO DE EJECUCIÓN = 180 D.C.


Código Recurso Und Cantidad Precio (S/.) Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
30 Días 30 Días 30 Días 30 Días 30 Días 30 Días

PIEDRA MEDIANA DE 3" m3 99.71


PIEDRA MEDIANA DE 4" m3 165.21
PINTURA ESMALTE GAL 40.00
PINTURA ESMALTE SINTETICO GL 40.00
PINTURA LATEX GL 30.04
PLACA DIFUSORA (MADERA TRATADA e=1") und 21.26
0202170001 PLATINA DE ACERO DE 1/2"x2 1/2"x6" und 1.85 8.00 240.00 240.00
0202910005 PLUMONES GRUESO N°47 und 3.61 0.01 38.28 38.28
0202910006 PROTECTOR DE OIDOS und 7.22 10.00 60.00 60.00
0202910007 PRUEBAS: ROTURA DE PROBETAS und 32.62 30.00 60.00 60.00
0203020003 REDUCCION 0-1/2" und 1.09 3.25 45,338.89 13,601.67 13,601.67 18,135.56
02030200030008 REDUCCION PVC SAP CLASE 10 DE 1" -1/2" und 3.50 6.12 97.92 97.92
0204000000 REDUCCION PVC SAP CLASE 10 DE 2" a 1" und 10.00 120.00 2,787.17 1,393.59 1,393.59
0205000047 REDUCCION PVC SAP CLASE 10 DE 2" a 1/2" und 5.00 60.00 5,739.99 2,870.00 2,870.00
0205010004 REDUCCION PVC SAP CLASE 10 DE 2" a 3/4" und 4.47 120.00 9,072.52 4,536.26 4,536.26
0205010019 REDUCCION PVC SAP CLASE 10 DE 3" a 1/2" und 5.96 90.00 137,180.88 68,590.44 68,590.44
0205010033 REDUCCION PVC SAP CLASE 10 DE 3" a 2" und 22.00 100.00 3,192.00 1,596.00 1,596.00
0205360016 REDUCCION PVC SAP CLASE 10 DE 3" a 3/4" und 5.96 120.00 283.61 283.61
0205360017 REDUCCION PVC SAP CLASE 10 DE 4" a 2" und 9.94 100.00 236.34 236.34
0205360018 REDUCCION PVC SAP CLASE 10 DE 4" a 3" und 11.92 100.00 367.64 367.64
0205360019 REDUCCION PVC SAP CLASE 10 DE 4" a 3/4" und 6.96 100.00 551.46 551.46
0210010043 REGLA DE MADERA p2 4.68 20.00 20.00 20.00
0210280006 REJILLA METALICA 0.40 x 0.50M und 143.51 300.00 300.00 300.00
0212100103 RIEL 2X3X1/2 mi 0.96 600.00 600.00 600.00
0212910034 SISTEMA DE VENOCLISIS und 6.63 150.00 300.00 300.00
0217010022 SOLDADURA ELECTRICA CELLOCORD P 1/4" kg 19.74 1.50 1,995.53 1,995.53
0221000094 SUMINISTRO E INST. CABLE TIPO BOA DE 3/8" m 15.40 27.00 50,772.25 25,386.13 25,386.13
0226160019 TABLAS DE MADERA CAPIRONA 6"x1" L=1,60m und 21.58 4.00 30.00 30.00
0229060001 TABLAS DE MADERA CAPIRONA 6"x1" L=2.00m und 21.58 6.00 98.27 98.27
0229070086 TACHOS DE COLOR (SEGUN NORMA) und 66.27 40.00 80.00 80.00
0229120064 TAPA METALICA 0.40x0.40M E=1/8" INC. MARCO Y PINTURA und 85.88 30.00 1,491.00 1,491.00
0230160066 TAPA METALICA 0.60x0.40M E=1/8" INC. MARCO Y PINTURA und 85.88 9.00 973.50 973.50
0230170012 TAPA METALICA 0.60x0.60M E=1/8" INC. MARCO Y PINTURA und 114.50 20.00 2,691.00 2,691.00
0230170013 TAPA METALICA 0.70x0.40M E=1/8" INC. MARCO Y PINTURA und 76.33 18.00 2,128.50 2,128.50
0230460048 TAPA METALICA 0.70x0.70M E=1/8" INC. MARCO Y PINTURA und 143.13 120.00 146.86 146.86
0230510100 TAPA Y MARCO METALICO DE 0.50x0.70M E=1/8" und 114.50 8.00 1,734.73 1,734.73
0230510101 TAPON HEMBRA PVC 01/2", PERFORADA und 0.79 7.00 386.26 386.26
0230510102 TAPON PVC HEMBRA PERFORADO 2 1/2" und 1.60 5.00 24.09 24.09
0230990056 TAPON PVC SAP 1" und 1.89 2.50 330.50 330.50
0231510021 TAPON PVC SAP 3/4" und 7.95 80.00 12,640.00 12,640.00
CALENDARIO DE ADQUISICIÓN DE INSUMOS
Obra: MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCION DEL SISTEMA DE ALCANTARILLADO DE LA LOCALIDAD DE MIRAFLORES, DISTRITO DE HUAMBO - RODRIGUEZ DE MENDOZA - AMAZONAS

CONTRATISTA CONSORCIO EJECUTOR HUAMBO


Fecha: OCTUBRE - 2016

PLAZO DE EJECUCIÓN = 180 D.C.


Código Recurso Und Cantidad Precio (S/.) Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
30 Días 30 Días 30 Días 30 Días 30 Días 30 Días

0238000003 TAPON RANURADO DE 3" und 4.97 100.00 13,616.54 1,361.65 12,254.89
0239020100 TECKNOPORT 1" pin 46.53 2.00 141.39 141.39
0239050000 TEE HDPE DE 4" und 6.74 3.00 145.12 145.12
0239060010 TEE PVC CLASE 10 DE 1" und 4.13 25.00 190.53 190.53
0239080049 TEE PVC CLASE 10 DE 2" und 15.00 350.00 350.00 350.00
0239500098 TEE PVC CLASE 10 DE 3" und 35.00 25.00 1,157.46 1,157.46
0239980005 TEE PVC CLASE 10 DE 3/4" und 1.69 1,500.00 1,500.00 1,500.00
0239990054 TEE PVC CLASE 10 DE 4" und 11.92 275.00 275.00 275.00
0239990055 TEE PVC SAP 2 1/2" und 4.12 242.00 242.00 242.00
0239990056 TEE PVC SAP 3" und 10.87 88.00 88.00 88.00
0239990057 TEE PVC SAP 01" und 4.13 187.00 374.00 374.00
0239990058 TEE PVC SAP 0 2" und 9.28 182.00 364.00 364.00
0239990059 TEE PVC SAP 0 3" und 10.87 308.00 308.00 308.00
0239990060 TEE PVC SAP 01/2" und 1.09 198.00 198.00 198.00
0239990061 TEMPLADOR DE ACERO DE 3/8" und 13.68 120.00 4,320.00 4,320.00
0239990062 THINNER gln 12.96 176.00 352.00 352.00
0243130012 TONER PARA IMPRESORAS und 238.47 80.00 240.00 240.00
0243130014 TORNILLO AUTORROSCANTE und 0.28 110.00 3,368.20 3,368.20
0243130015 TRANSPORTE VJE 503.33 70.00 140.00 140.00
0243920002 TRIPLAY DE 10 MM PARA ENCOFRADO pin 70.54 2.50 12,058.90 3,617.67 3,617.67 4,823.56
0244010001 TRIPLAY LUPUNA4'x8'x12 mm PL 70.54 2.00 189.29 189.29
0244030035 TUBERIA HDPE SDR 9,4710 ASTMD3035 0=2" m 14.44 47.00 282.00 282.00
0244030036 TUBERIA HDPE SDR 9,4710ASTMD3O35 0=4" m 28.87 30.00 4,500.00 4,500.00
0246910004 TUBERIA PVC SAP 0=1/2" m 1.85 0.30 1,148.25 1,148.25
0251110003 TUBERIA F°G° 0 3/4" m 20.10 30.00 60.00 60.00
0253050007 TUBERIA PVC CLASE 10 DE 1" m 3.29 18.00 200.22 200.22
0254160002 TUBERIA PVC CLASE 10 DE 1/2" m 1.29 2.80 98.97 98.97
0254190003 TUBERIA PVC CLASE 10 DE 2" m 6.36 40.00 695.06 695.06
0256020086 TUBERIA PVC CLASE 10 DE 3" m 14.17 170.00 170.00 170.00
0256020087 TUBERIA PVC CLASE 10 DE 3/4" m 2.48 55.00 110.00 110.00
0256900012 TUBERIA PVC CLASE 10 DE 4" m 16.81 15.00 1,800.00 1,800.00
0262000013 TUBERIA PVC SAL 01/2" m 1.85 10.00 5,741.25 5,741.25
0265000108 TUBERIA PVC SAP 1 1/2" m 4.50 240.00 1,606.80 1,606.80
0265000109 TUBERIA PVC SAP 2 1/2" m 8.42 280.00 392.00 392.00
0265020111 TUBERIA PVC SAP CLASE 10 0 2" m 6.36 170.00 1,488.35 1,488.35
0265020112 TUBERIA PVC SAP CLASE 100 3" m 14.17 35.00 70.00 70.00
0265020113 TUBERIA PVC SAP CLASE 100 4" m 18.33 75.00 300.00 300.00
0265030011 TUBO DE F°G° 0 = 3" m 93.33 5.00 5.00 5.00
0265030013 UNION DRESSER 2" und 125.11 12.00 12.00 12.00
0265030017 UNION DRESSER 4" und 153.98 28.00 280.00 280.00
CALENDARIO DE ADQUISICIÓN DE INSUMOS
Obra: MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCION DEL SISTEMA DE ALCANTARILLADO DE LA LOCALIDAD DE MIRAFLORES, DISTRITO DE HUAMBO - RODRIGUEZ DE MENDOZA - AMAZONAS

CONTRATISTA CONSORCIO EJECUTOR HUAMBO


Fecha: OCTUBRE - 2016

PLAZO DE EJECUCIÓN = 180 D.C.


Código Recurso Und Cantidad Precio (S/.) Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
30 Días 30 Días 30 Días 30 Días 30 Días 30 Días

0265030018 UNION HDPE 2" und 13.95 45.00 180.00 180.00


0265050007 UNION HDPE 4" und 24.64 15.00 225.00 225.00
0265050012 UNION UNIVERSAL DE F°G° DE 2" und 31.57 12.00 168.00 168.00
0265050017 UNION UNIVERSAL F°G° 0=2" und 31.57 25.00 400.00 400.00
0265050050 UNION UNIVERSAL HDPE DE 2" und 32.03 12.00 336.00 336.00
0265050054 UNION UNIVERSAL HDPE DE 4" und 57.74 90.00 900.00 900.00
0265050055 UNION UNIVERSAL PVC 0 1/2" und 2.58 135.00 810.00 810.00
0265080027 UNION UNIVERSAL PVC 2 1/2" und 17.18 35.00 35.00 35.00
0265110008 UNION UNIVERSAL PVC 2" und 15.65 125.00 250.00 250.00
0265130086 UNION UNIVERSAL PVC DE 1" und 8.34 10.00 140.00 140.00
0265140005 UNION UNIVERSAL PVC DE 2" und 15.65 10.00 10.00 10.00
0265140007 UNION UNIVERSAL PVC 0 4" und 15.65 10.00 280.00 280.00
0265140106 UNION UNIVERSAL PVC SAP D=1" und 8.34 18.00 288.00 288.00
0265140110 UNION UNIVERSAL PVC SAP D=2" und 15.65 19.00 57.00 57.00
0265140111 UNION UNIVERSAL PVC SAP D=3" und 14.31 15.00 45.00 45.00
0265140112 UNION UNIVERSAL PVC SAP D=4" und 34.78 15.00 1,350.00 1,350.00
0265140113 UNION UNIVERSAL PVC SAP 1/2" und 3.00 15.00 90.00 90.00
0265150022 UNION UNIVERSAL PVC SAP DE 2" und 15.65 18.00 108.00 108.00
0265210025 VALVULA COMPUERTA DE BRONCE DE 2 1/2" und 48.12 80.00 480.00 480.00
0265210026 VALVULA COMPUERTA DE BRONCE DE 2" und 72.00 78.00 468.00 468.00
0265210027 VALVULA COMPUERTA DE BRONCE DE 4" und 96.24 174.00 348.00 348.00
0266050004 VALVULA COMPUERTA HDPE DE 2" und 38.49 38.00 76.00 76.00
0268470003 VALVULA COMPUERTA HDPE DE 4" und 67.37 180.00 180.00 180.00
0268470004 VALVULA COMPUERTA 01/2" und 20.31 185.00 185.00 185.00
0271010040 VALVULA COMPUERTA PVC 2 1/2" und 43.31 175.00 14,000.00 14,000.00
0271090074 VALVULA COMPUERTA PVC 2" und 72.00 15.00 600.00 600.00
0271090075 VALVULA COMPUERTA TIPO PLACA 0.42mx0.60mx3mn und 96.24 8.00 16.00 16.00
0271090076 VALVULA DE AGUA DE 4" und 45.66 6.00 240.00 240.00
0271990021 VALVULA ESFERICA DE 1" und 22.11 18.00 54.00 54.00
0271990022 VALVULA ESFERICA DE 2" und 78.00 28.00 84.00 84.00
0271990023 VALVULA ESFERICA DE 3" und 86.61 26.00 260.00 260.00
0271990024 VALVULA ESFERICA DE 4" und 115.48 8.00 8.00 8.00
0272000121 VALVULA ESFERICA 0=2" und 72.18 25.00 643.75 321.88 321.88
0272000122 WATER STOP pvc 6" m 27.00 20.00 19,407.67 9,703.84 9,703.84
0272000123 YESO EN BOLSA DE 25 KG bis 13.23 15.00 18,159.62 9,079.81 9,079.81
CALENDARIO DE ADQUISICIÓN DE INSUMOS
Obra: MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCION DEL SISTEMA DE ALCANTARILLADO DE LA LOCALIDAD DE MIRAFLORES, DISTRITO DE HUAMBO - RODRIGUEZ DE MENDOZA - AMAZONAS

CONTRATISTA CONSORCIO EJECUTOR HUAMBO


Fecha: OCTUBRE - 2016

PLAZO DE EJECUCIÓN = 180 D.C.


Código Recurso Und Cantidad Precio (S/.) Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
30 Días 30 Días 30 Días 30 Días 30 Días 30 Días

02 SISTEMA DE ALCANTARILLADO 433,907.09


0201800003 LUBRICANTE PARA TUBERIA PVC UF gal 11.0011 40.00 440.04 440.04
0202000007 ALAMBRE NEGRO RECOCIDO # 16 kg 520.8460 5.00 2,604.23 2,604.23
0202000008 ALAMBRE NEGRO RECOCIDO # 8 kg 194.3746 5.00 971.87 971.87
0202010002 CLAVOS PARA MADERA CON CABEZA DE 2 1/2" kg 0.8820 5.00 4.41 4.41
0202010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg 116.2340 4.50 523.05 523.05
0202010008 CLAVOS PARA MADERA CON CABEZA DE 5" kg 100.1675 8.00 801.34 801.34
0202170001 CLAVOS PARA CALAMINA kg 11.3438 8.00 90.75 90.75
0203020003 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 9,288.3577 3.25 30,187.16 9,056.15 9,056.15 12,074.86
0204000000 ARENA FINA m3 20.0179 120.00 2,402.15 600.54 600.54 1,201.08
0204000011 ARENA FINA CLASIFICADA m3 4.5000 120.00 540.00 135.00 135.00 270.00
0205000046 PIEDRA GRANDE PUESTA EN OBRA m3 7.5600 100.00 756.00 189.00 189.00 378.00
0205000047 OVER m3 124.2820 60.00 7,456.92 1,864.23 1,864.23 3,728.46
0205010004 ARENA GRUESA m3 102.6263 120.00 12,315.16 3,078.79 3,078.79 6,157.58
0205010019 MATERIAL DE PRESTAMO SELECCIONADO OBRA m3 748.2584 90.00 67,343.26 16,835.82 16,835.82 33,671.63
0205010033 ARENA GRUESA CLASIFICADA m3 4.5000 100.00 450.00 112.50 112.50 225.00
0205360016 GRAVA PARA FILTRO DE 1" - 2" m3 260.3475 120.00 31,241.70 15,620.85 15,620.85
0205360020 GRAVA FINA CLASIFICADA m3 4.5000 100.00 450.00 225.00 225.00
0205360021 GRAVA GRUESA CLASIFICADA m3 8.0000 100.00 800.00 400.00 400.00
0205360022 GRAVA PARA FILTRO DE 1/2" - 2" m3 156.2085 100.00 15,620.85 7,810.43 7,810.43
0210140080 CACHIMBA UPVC 6" x 4" u 79.0000 30.00 2,370.00 2,370.00
0210280007 REJILLA METALICA SEGUN DISEÑO u 2.0000 250.00 500.00 500.00
0221000094 CEMENTO PORTLAND TIPO I (42.5 kg) bls 1,963.8218 27.00 53,023.19 21,209.28 15,906.96 15,906.96
0229060001 YESO kg 32.0600 6.00 192.36 192.36
0230160066 IMPERMEABILIZANTE kg 109.8711 9.00 988.84 988.84
0230460048 PEGAMENTO PARA PVC gal 20.9543 120.00 2,514.52 2,514.52
0231510022 CAJA DE CONCRETO DE DESAGUE DE 12" X 24" u 79.0000 120.00 9,480.00 9,480.00
0238000003 HORMIGON m3 52.0056 100.00 5,200.56 5,200.56
0239050000 AGUA PUESTA EN OBRA m3 50.6300 3.00 151.89 45.57 45.57 60.76
0239500098 REGLA DE MADERA u 6.1855 25.00 154.64 154.64
0243040009 MADERA TORNILLO O SIMILAR ASERRADA PARA TIJERAL p2 622.8000 4.00 2,491.20 2,491.20
0243040010 MADERA TORNILLO O SIMILAR 2"X3" p2 268.6320 4.00 1,074.53 1,074.53
0243920002 MADERA PARA ENCOFRADO p2 4,116.2251 2.50 10,290.56 10,290.56
0243920003 MADERA PARA CERCO p2 95.0000 16.00 1,520.00 1,520.00
0244010001 ESTACA DE MADERA p2 2,275.8450 2.00 4,551.69 4,551.69
0246910004 ALAMBRE DE PUAS m 1,939.6667 0.30 581.90 581.90
0250010016 TAPA C/MARCO FºFº REDONDO PARA BUZON D=0.60 INGRESO pza 47.0000 450.00 21,150.00 21,150.00
0254190003 PINTURA ESMALTE gal 1.3193 40.00 52.77 52.77
0266030089 ANILLO PARA TUB. PVC NTP ISO 4435-2 DN 160 MM u 404.8000 3.00 1,214.40 1,214.40
CALENDARIO DE ADQUISICIÓN DE INSUMOS
Obra: MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCION DEL SISTEMA DE ALCANTARILLADO DE LA LOCALIDAD DE MIRAFLORES, DISTRITO DE HUAMBO - RODRIGUEZ DE MENDOZA - AMAZONAS

CONTRATISTA CONSORCIO EJECUTOR HUAMBO


Fecha: OCTUBRE - 2016

PLAZO DE EJECUCIÓN = 180 D.C.


Código Recurso Und Cantidad Precio (S/.) Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
30 Días 30 Días 30 Días 30 Días 30 Días 30 Días

0266030090 ANILLO PARA TUB. PVC NTP ISO 4422 DN 160 MM u 9.0000 3.00 27.00 27.00
0266300008 CALAMINA # 30 DE 1.83m x 0.83m x 3mm pza 102.0868 38.00 3,879.30 3,879.30
0272000121 TUBERIA PVC SAP C-7.5, 4" m 131.2500 25.00 3,281.25 3,281.25
0272000135 TUBERIA PVC SAP C-7.5, 4" PERFORADA m 1,157.1000 45.00 52,069.50 52,069.50
0272060085 CODO PVC SAP S/P 6" X 90° u 3.0000 35.00 105.00 105.00
0272060086 ADAPTADOR PVC-SAP 6" u 6.0000 18.00 108.00 108.00
0272060087 CODO PVC SAP 4" X 90º u 42.0400 8.00 336.32 336.32
0272060088 CODO PVC SAP S/P 4" X 45° u 12.0000 8.00 96.00 96.00
0272130017 TUBERIA PVC NTP ISO 4435 DN=160 MM S-20 m 220.1850 25.00 5,504.63 5,504.63
0272130018 TUBERIA PVC NTP ISO 4435 DN=160 MM S-25 m 2,071.1355 30.00 62,134.07 62,134.07
0272300020 CODO M-H PVC UF 160MM u 1.0000 45.00 45.00 45.00
0272300021 CODO 45° M-H PVC 160MM UF ISO 4435-2 u 9.0000 45.00 405.00 405.00
0272300022 CODO 90° M-H PVC 160MM UF ISO 4435-2 u 3.0000 45.00 135.00 135.00
0273010029 TUBERIA PVC SAL 4" m 833.3910 13.00 10,834.08 10,834.08
0273130023 TEE PVC 160MM UF ISO 4422 u 9.0000 45.00 405.00 405.00
0278000075 VALVULA COMPUERTA F.F. BB. DE 6" u 3.0000 680.00 2,040.00 2,040.00

3 MITIGACIÓN AMBIENTAL 8,499.50


0202000024 PLANTONES DE MOROCHO u 500.0000 3.00 1,500.00 225.00 225.00 225.00 225.00 300.00 300.00
0202000025 ABONO kg 100.0000 5.00 500.00 75.00 75.00 75.00 75.00 100.00 100.00
0202000026 REPOSICION DE AREAS VERDES m2 200.0000 3.00 600.00 90.00 90.00 90.00 90.00 120.00 120.00
0202610008 ANALGESICO u 50.0000 5.00 250.00 37.50 37.50 37.50 37.50 50.00 50.00
0212090103 CAJA u 1.0000 10.00 10.00 1.50 1.50 1.50 1.50 2.00 2.00
0229040010 CINTA SEÑALADORA AMARILLA rll 5.0000 40.00 200.00 30.00 30.00 30.00 30.00 40.00 40.00
0229990005 ALGODON pqt 10.0000 5.00 50.00 7.50 7.50 7.50 7.50 10.00 10.00
0229990030 GASA glb 5.0000 10.00 50.00 7.50 7.50 7.50 7.50 10.00 10.00
0229990032 JABON GERMICIDA u 7.0000 3.50 24.50 3.68 3.68 3.68 3.68 4.90 4.90
0230540003 LETREROS DE SEÑALIZACIÓN MADERA DE 2X1.5 M2 TRIPLAY u 9.0000 80.00 720.00 108.00 108.00 108.00 108.00 144.00 144.00
0230740000 PASTILLAS MI SALUD PARA AGUA u 10.0000 7.00 70.00 10.50 10.50 10.50 10.50 14.00 14.00
0230740006 CICATRIZANTES pqt 1.0000 100.00 100.00 15.00 15.00 15.00 15.00 20.00 20.00
0230980011 ROPA DE TRABAJO (CHALECOS COLOR NARANJA) pza 90.0000 30.00 2,700.00 405.00 405.00 405.00 405.00 540.00 540.00
0239080002 ALCOHOL YODADO L 3.0000 10.00 30.00 4.50 4.50 4.50 4.50 6.00 6.00
0239080050 REFRIGERIOS JUGO SANWICH u 150.0000 7.00 1,050.00 157.50 157.50 157.50 157.50 210.00 210.00
0239080051 LAPICERO AZUL TINTA SECA u 10.0000 3.50 35.00 5.25 5.25 5.25 5.25 7.00 7.00
0239080052 IMPRESIONES MATERIAL EDUCATIVO glb 500.0000 0.30 150.00 22.50 22.50 22.50 22.50 30.00 30.00
0239080053 FOTOCOPIAS DE MATERIAL INFORMATIVO u 600.0000 0.10 60.00 9.00 9.00 9.00 9.00 12.00 12.00
0239500099 TACHOS DE COLORES DE POLIETILENO PARA RESIDUOS SÓLIDOS 100 L ROTULADOS DE DOS u 4.0000 100.00 400.00 60.00 60.00 60.00 60.00 80.00 80.00
COLORES VERDE Y AMARILLO

TOTAL EN MATERIALES SIN IGV 850,151.95 35,130.13 156,912.59 311,151.91 194,898.50 106,287.49 45,771.33
PORCENTAJE DE AVANCE MENSUAL 4.13% 18.46% 36.60% 22.93% 12.50% 5.38%
CALENDARIO DE ADQUISICIÓN DE INSUMOS
Obra: MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y CONSTRUCCION DEL SISTEMA DE ALCANTARILLADO DE LA LOCALIDAD DE MIRAFLORES, DISTRITO DE HUAMBO - RODRIGUEZ DE MENDOZA - AMAZONAS

CONTRATISTA CONSORCIO EJECUTOR HUAMBO


Fecha: OCTUBRE - 2016

PLAZO DE EJECUCIÓN = 180 D.C.


Código Recurso Und Cantidad Precio (S/.) Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6
30 Días 30 Días 30 Días 30 Días 30 Días 30 Días

PORCENTAJE DE AVANCE ACUMULADO 4.13% 22.59% 59.19% 82.11% 94.62% 100.00%