Vous êtes sur la page 1sur 23

SRI LANKA OPERATIONS CENTRE

GOVERNMENT OF SPAIN ASSISTED PERMANENT STEEL BRIDGE PROJECT 
CONSTRUCTION THONDAMANARU BRIDGE IN JAFFNA  
 
PREAMBLE TO BILL OF QUANTITIES  
 
TABLE OF CONTENTS 
 
 
Page No. 
 
PREAMBLE TO BILLS OF QUANTITIES............................................................................................................. 3 
SECTION 1 ‐ GENERAL..........................................................................................................................................3 
1.1  BID PROCESS...............................................................................................................................................3 
1.2  COMPLEMENTARY DOCUMENTS .....................................................................................................................3 
1.3.  METHOD OF MEASUREMENT .........................................................................................................................3 
1.4.  UNITS AND EXTENSION OF BILL OF QUANTITIES .................................................................................................4 
1.5.  EXTENT OF WORKS ......................................................................................................................................4 
1.6  ADDITIONAL WORK ......................................................................................................................................5 
1.7  MATERIALS SUPPLY ......................................................................................................................................5 
SECTION 2 – RATES AND PRICES ..........................................................................................................................6 
2.1  RATES AND SUMS ........................................................................................................................................6 
2.2  TAXES AND DUTIES .......................................................................................................................................6 
2.3  VALUE ADDED TAX.......................................................................................................................................6 
2.4  PROVISIONAL SUM .......................................................................................................................................6 
2.5  PROVISIONAL QUANTITY ............................................................................................................................... 6 
2.6  PROVISIONAL ITEM.......................................................................................................................................7 
2.7  LUMP SUM ITEM .........................................................................................................................................7 
2.11  PROTECTION OF COMPLETED WORK AND CLEARING UPON COMPLETION ............................................................7 
2.12  RATE ANALYSIS ........................................................................................................................................7 
SECTION 3 – SITE WORKS ....................................................................................................................................7 
3.1  SITE CLEARANCE ..........................................................................................................................................7 
3.2  EARTHWORKS .............................................................................................................................................8 
SECTION 4 ‐  CONCRETE WORKS........................................................................................................................10 
4.1  GENERAL ..................................................................................................................................................10 
4.2  BLINDING CONCRETE ..................................................................................................................................11 
4.3  SHUTTERING / FORM WORK .........................................................................................................................11 
4.4  STEEL REINFORCEMENT ............................................................................................................................... 11 
SECTION – 5  MISCELLANEOUS WORKS .............................................................................................................11 
5.1  ACCESS FACILITIES ......................................................................................................................................11 
5.2  EXISTING SERVICES AND STRUCTURES ............................................................................................................12 
5.3  PAINTING & PROTECTIVE COATINGS ..............................................................................................................12 
5.4  AMENDMENTS TO DESIGNS .........................................................................................................................12 
5.5   ABBREVIATIONS:........................................................................................................................................12 
5.6  PROVISION OF FACILITIES: ............................................................................................................................12 
SECTION 6 ‐   DAYWORK SCHEDULE...................................................................................................................13 
6.1  GENERAL ..................................................................................................................................................13 
6.2  LABOUR ...................................................................................................................................................13 

Page 1 of 18 
6.3  MATERIALS ...............................................................................................................................................14 
6.4  CONSTRUCTIONAL PLANT ............................................................................................................................15 
 
 
 
SRI LANKA OPERATIONS CENTRE

PREAMBLE TO BILLS OF QUANTITIES 
 
SECTION 1 ‐ GENERAL 
 
1.1  Bid Process 
 
This  is  a  Locally  Competitive  Bidding  (LCB)  Contract  primarily  payable  in  local  currency  and  the 
format of the Bill of Quantities is prepared accordingly to realize that requirement and it allows the 
Bidder to insert rates only in local currency (Sri Lanka Rupees).  
 
The Bidder shall neither insert additional items in to the Bill of Quantities nor made any alterations 
to the item descriptions and quantities.   
 
1.2  Complementary Documents 
 
The attention of the Contractor is explicitly directed to the Conditions of Contract (Part I and Part II), 
Technical Specifications, Scope and Description of Works and Tender Drawings that are to be read in 
conjunction with the Bills of Quantities and its Preamble. No other external documents shall be used 
for any references. 
 
1.3.  Method of Measurement 
 
The Works as executed shall be measured for payment in accordance with the method adopted in 
the Bills of Quantities and under the item as therein set forth. The contractor’s rate shall include for 
the  complete  execution  of  the  works  as  depicted  on  drawings  and  as  specified  in  Technical 
Specifications.  Measurement  criteria,  definition  rules  and  additional  description  conditions  shall 
apply  where  appropriate  with  the  “Civil  Engineering  Standard  Method  of  Measurement”  (1974 
Edition)  and  any  subsequent  edition  thereof  published  by  the  Institution  of  Civil  Engineers,  and 
‘Standard  Method  of  Measurements  for  Building  Works  6th  Edition  (SMM6)”  subject  to  specific 
changes for this Contract. 
 
The  net  measurement  or  weight  of  the  finished  work  in  place  shall  always  be  taken  and  except 
where  otherwise  stated  or  where  separate  items  are  provided,  no  allowance  shall  be  made  for 
cutting, waste, laps, circular work, etc. and no deductions shall be made for grout nicks, joggle holes, 
rounded arises or for linkages for fitting ironwork and the like. 
 
Payment  shall  be  effected  only  for  those  materials  that  are  incorporated  in  the  permanent  works 
and  taken  over  the  stocks  as  stipulated  in  the  specifications  to  the  approval  of  the  Engineer.  Any 
surplus materials delivered to the site shall become the property of the Contractor unless otherwise 
directed  by  the  Engineer  and  the  Contractor  shall  reimburse  any  money  that  was  paid  by  the 
Employer on account of these materials. 
 
Unless specific items have been provided for in the Bill of Quantities, no separate measurement shall 
be made in respect of items whether specified or not requiring mortar/sealant, assembling, building‐
in  or  fixing  to  concrete,  block  works,  metal  work  or  timber,  painting  and  protective  treatment, 
welding,  drilling,  bolting  inclusive  of  bolts,  nuts  and  washers,  screws,  nails  and  plugs,  jointing  and 
joint materials, box out and filling thereof, grouting, packing, bedding, insulation between different 
metals, making good, conduits and fittings, cutting, waste, labour  materials and all incidental work 
to the items concerned and their surroundings.  

Page 3 of 18 
1.4.  Units and Extension of Bill of Quantities 
 
All sizes and quantities provided in the Bill of Quantities have been in metric units, figures involving 
decimals including sums of money are written in the British tradition, namely with a full stop in the 
decimal  position  and  commas  between  each  successive  group  of  three  digits  to  the  left  of  the 
decimal position. 
 
1.5.  Extent of Works 
 
Notwithstanding  any  limits  that  may  be  implied  by  the  wording  of  the  individual  items  and  /or 
explanation provided in this preamble, it is to be clearly understood by the contractor that the rates 
and sums that are entered in the Bills of Quantities shall be for the work finished complete in every 
respect. The bidder shall be deemed to have taken full account of all requirements and obligations 
whether  expressed  or  implied,  covered  by  all  parts  of  this  Contract  and  to  have  priced  the  items 
herein accordingly. The rates and sum shall therefore be included for all incidental and contingent 
expenses and risks of every kind necessary to construct, complete and maintain the whole of works 
in  accordance  with  the  Contract.  Full  allowance  shall  be  made  in  the  rates  and/or  sums  inter‐alias 
that are referred to and/or specified herein. 
 
ƒ site investigations that may be necessary for proper and complete execution 
ƒ all setting out and survey works 
ƒ provision  of  temporary  services  such  as  water  supply,  electricity,  fencing,  watching, 
lighting; etc. 
ƒ paying fees and giving notice to authorities, public etc. 
ƒ payment of all patent rights and royalties 
ƒ reinstatement of the site on completion of works to the satisfaction of the Engineer 
ƒ safety precautions and all measures to prevent and suppress fire and other hazards during 
implementation 
ƒ interference to the works by persons, vehicles, vessels and the like using the existing land 
and water facilities 
ƒ maintenance of access to the existing roads in a motor‐able status and waterways during 
the period of construction 
ƒ works in connection with the protection and safety of adjacent structures 
ƒ supplying,  maintaining  and  removing  on  completion  contractor’s  own  accommodation, 
offices,  stores,  workshops,  transport,  welfare  services  and  all  charge  in  connection 
therewith unless otherwise directed by the Engineer 
ƒ working  in  dry  conditions  including  dewatering  if  required  except  where  otherwise 
permitted by the specification 
ƒ maintaining  public  roads  and  footpaths,  and  maintaining  access  upon  existing  roads  or 
recognized routes 
ƒ supply, inspection, sampling and testing of materials and of the Works under construction 
including the provision and use of equipment. 
ƒ except where separate items are provided for bringing plant to the site and removing on 
completion, for providing transporting to site, setting to work operating (including all fuel 
and  consumable  stores),  maintaining  and  removing  from  the  site  upon  completion  all 
construction  plant  and  equipment  necessary  for  the  execution  of  the  work  including  the 
cost of all tests and other requirements in respect to such plant and equipment 
ƒ recruitment, bringing to and repatriate from the site, accommodating and feeding and all 
other  incidental  costs  and  expenses  involved  in  the  provision  of  all  necessary  skilled  and 
unskilled labour and supervision 
ƒ supporting faces of excavation temporary or permanent shoring, shuttering and scaffolding 
etc. 
ƒ cost of design based on tender drawings, preparation of working drawings and related data 
for materials, pipe work and equipment  
ƒ all ancillary parts, minor fittings, bolts, nuts, gaskets, washers, fixing, etc., joining materials, 
protective  coatings  and  sleevings  and  other  relevant  items  not  specifically  listed  but 
necessary for proper installation of the materials, pipe works and equipment (applicable to 
materials supplied by the contractor) 
ƒ costs of packing, protection, storage, insurance and related documentation for shipment to 
Sri Lanka for materials, pipes, fittings, equipment, etc. 
ƒ cost of unloading at port, road transport to site, offloading, stacking and storage in suitable 
sheds, double handling as needed at site for materials, pipes, fittings, equipment, etc. 
 
No  claim  shall  be  considered  for  further  payment  in  respect  of  any  work  or  method  of  execution, 
which may be described in the Contract or is inherent in the construction of the work and detailed 
on the drawings on account of; 
 
ƒ items that have been omitted from the Bill of Quantities, but depicted on the drawings 
ƒ any omission from the wording of the items or from a clause in the Preamble or  
ƒ no mention of such work or method of execution having been in the Preamble 
 
Items against which no rates or sum is entered by the contractor whether quantities are stated or 
not shall not be paid for when executed, but will be regarded as covered by other rates in the Bill of 
Quantities.  
 
The quantities set out in the Bill of Quantities are the estimated quantities of the work and they shall 
not be taken as the actual and correct magnitude of the works to be executed by the contractor in 
fulfillment of his obligation under the Contract. The contractor shall be deemed to have taken into 
account all of the following in his tender prices and his construction programmes. 
 
ƒ all recognized holidays, festivals, religious and other local customs 
ƒ any stoppage of work or delays due to adverse weather conditions 
 
1.6  Additional Work 
 
The  relevant  Clauses  of  this  Preamble  shall  be  deemed  to  apply  equally  to  any  work  subsequently 
ordered  for  execution  by  the  Contractor  either  under  Provisional  Sum  or  Variation  Orders,  except 
where specifically varied therein. 
 
1.7  Materials Supply 
 
The  basic  construction  and  formworks  materials  shall  be  supplied  by  UNOPS  to  the  contractor  as 
follows to the stock yard at site and contractor shall be responsible for local carriage, haulage to the 
work site.  
• Cement 
• Reinforcement bars 
• Basic  shuttering materials of Black Plywood except propping 
• Neoprene Bearing 
• ---------------------------
   
SECTION 2 – RATES AND PRICES 
 
2.1  Rates and Sums  
 
The rates and sums entered by the contractor against all items in the Bill of Quantities shall bear a 
proper relationship to the cost of carrying out the work described in the Contract. All on costs and 
similar charges that are applicable to the Contract as a whole shall be spread over all items in the Bill 
of Quantities whilst those that are applicable only to particular sections of the Contract shall only to 
be spread over the relevant items in that particular sections. 
 
2.2  Taxes and Duties 
 
The contractor shall include all local taxes except VAT for the materials and services to be procured 
locally in his unit rate for various item of works included in the Bill of Quantities. 
 
The unit rate for materials, goods and equipment to be imported from overseas shall INCLUDE VAT 
and  other  import  duties  such  as  custom  duties,  cess,  excise  duty,  etc.  The  Employer  is  not 
responsible  to  pay  any  VAT  or  custom  duty  for  any  imported  items  to  be  incorporated  in  the 
permanent works.  
 
2.3  Value Added Tax 
 
As  set  out  in  the  “Instruction  to  Bidders”,  VAT  payable  to  the  Government  of  Sri  Lanka  shall  be 
calculated separately and the total VAT amount shall be inserted in the space provided in the Grand 
Summary  Page  of  the  Bills  of  Quantities.  VAT  shall  neither  be  included  in  the  unit  rate  for  various 
items of work nor in the tendered price. However, the total VAT component be carried over to the 
Form  of  Tender.  The  applicable  rate  for  VAT  in  the  BOQ  items  for  civil  engineering  works  set  by 
Government Sri Lanka and the contractor shall authenticate this rate and include in the Summary Bill 
of Quantities.  
 
2.4  Provisional Sum  
 
Provisional sums items shall be dealt with as provided for in the Conditions of Contract. Provisional 
Sums  are  represented  by  the  words  ‘Provisional  Sum  (PS)’  entered  under  the  description.  Items 
marked  “Provisional”  in  the  Bills  of  Quantities  are  provisional  and  shall  not  be  executed  unless 
instructed by the Engineer. They may be expended wholly or in part as instructed by the Engineer. 
The contractor shall be entitled for an amount of 15% of the actual cost of services to cover all his 
financial and administrative costs including cost of liaison with external agencies, profits, overheads 
and any other costs for the “provisional sum” item.  This percentage will be the basis of assessing the 
actual amount payable to the contractor. 
 
 
 
2.5  Provisional Quantity 
 
Certain  items  in  the  Bill  of  Quantities  are  designated  as  “Provisional  Quantity”  in  the  description 
column  to  indicate  that  the  quantities  for  the  work  covered  by  such  items  are  the  best  possible 
estimates that can be made in advance of the execution of the work or that the provision of such 
facilities as are described in the items may not in the event be required under the contract.  All items 
so designated shall be used only at the direction and discretion of the Engineer and if not used either 
wholly or in part shall, as to the amount not used, be deducted from the Contract Price.   
 
2.6  Provisional Item 
 
Any item that is designated as “Provisional Item” in the description column of the Bill of Quantity is 
to  indicate  that  the  provision  of  such  facilities  of  work  is  uncertain  at  the  time  of  document 
preparation.  All  items  so  designated  shall  be  used  only  at  the  direction  and  discretion  of  the 
Engineer. The unit rate if any quoted by the contractor shall be applicable for the amount of work 
executed under such items.  
 
2.7  Lump Sum Item 
 
Certain  items  in  the  Bill  of  Quantities  are  designated  as  “Lump  Sum  (LS)”  in  the  unit  column  to 
indicate  that  the  payment  will  be  effected  as  a  sum  on  satisfactory  completion  of  that  particular 
work. Lump sum items stipulated in Bill of Quantities that are related to a specific work shall be paid 
on the basis of the proportion of actual work done to the total work of that specific item as assessed 
by the Engineer. Items with quantities and units shall be paid against number of units used and/or 
incorporated in the works. 
 
2.11  Protection of Completed Work and Clearing upon Completion 
 
The Contractor shall allow in his rates for protecting completed work from subsequent operations, 
making  good  of  all  damage  to  completed  work,  clearing  away  all  rubbish  as  it  accumulates  and 
leaving the site in a tidy condition to the satisfaction of the Engineer. 
 
2.12  Rate Analysis   
 
The contractor must be submit the detailed breakdown of tendered rates and lump sum items for all 
or part of the Bill of Quantity items for quoted items in the bid as apart of the tender documents. 
The  detailed  breakdown  of  rates  shall  include  the  actual  calculations  of  the  labour,  materials, 
plant/equipment costs for works, the build up of measured rates with profit, overheads and other 
allowances used to arrive at the tender price. 
 
Rate  Analysis  is  considered  to  be  mandatory.  Any  bid  unaccompanied  with  Rate  Analysis  will  be 
disqualified.  
 
SECTION 3 – SITE WORKS 
 
3.1  Site Clearance 
 
The unit rate quoted for site clearance shall include for but not limited to the removal and grubbing 
out of all trees, shrubs, debris, boulders and all other objectionable materials from the designated 
area and dispose of same to approved tip provided by the contractor. The measurement shall be the 
plan area of the land within the limit of the site demarcated by the Engineer for the installation of 
various  structures.  The  rate  shall  also  include  supply  and  spreading  of  at  least  150  mm  thick  of 
topsoil cover over the site upon completion of the works. 
 
3.2  Earthworks 
 
Excavation in all Material except Rock: 
 
The  rates  and  prices  for  earth  excavations  including  dredging  shall  be  for  all  types  of  ground 
conditions encountered except rock but including ground situation above or below water level.  The 
contractor  shall  make  allowances  for  the  possibility  of  permission  not  being  granted  to  the  use  of 
explosives for blasting and other operations. 
 
o Quantity  of  material  excavated  as  the  product  of  the  horizontal  area  of  the  base  of 
permanent work to be constructed and the mean depth below ground level or measured 
as  the  volume  to  be  occupied  by  permanent  work  below  ground  level,  whichever  is  the 
greater. In no case shall any of the following quantities be included in the measurement for 
payment. 
 
• material  excavated  outside  the  vertical  planes  of  neat  outline  of  foundation 
structures unless shown otherwise on the drawings 
• excavation  and/or  backfill  for  pipeline,  storm  sewers  and  under  drains  except  as 
allowed  for  in  pipeline  construction  as  specified  in  pipe  work,  valves  and  fittings 
laying & installation 
• excavations work performed prior to the taking of measurements of the undisturbed 
natural ground 
• quantity  of  any  material  re‐handled,  except  where  the  drawings  indicate  or  the 
Engineer directs the excavation after embankment has been placed 
• excavation carried outside of cofferdams 
• additional  excavation  required  due  to  the  swelling  of  the  foundation  when  driving 
piles 
• removal  of  slides,  cave‐ins,  silting  or  filling  due  to  the  action  of  the  elements  or 
whether and/or carelessness of the Contractor 
• volume of excavated unsuitable material shall be measured as the actual volume of 
material removed as directed by the Engineer 
• excavation for trenches of pipeline is described elsewhere in this Preamble 
 
No allowance is made for any bulking or for any extra transport required due to bulking.  The rates 
shall include but not by way of limitation for: 
 
ƒ excavation to the correct depth and preserving the bottoms of excavations in a state 
suitable for the reception of concrete, pipes or pipe bedding, and no payment shall 
be  made  for  any  concrete  or  pipe  bedding  required  for  filling  of  over‐excavated 
volumes or disturbed areas to the net dimensions as indicated on the Drawings 
ƒ any  additional  excavation  required  for  shuttering,  working  space,  temporary  or 
permanent shoring, and subsequent refilling and ramming and disposal of surplus 
ƒ provision  of  land  areas  for  the  temporary  storage  of  any  material  required  for 
backfilling that cannot be stored alongside the excavation for any reason, together 
with  the  cost  of  transporting,  loading  including  disposal  of  surplus  and  unloading 
such material and all other charges incurred in this respect 
ƒ trimming  the  bottoms  of  excavations  including  bottoming  to  falls  and  trimming  to 
sloping surfaces where required or indicated on the Drawings 
ƒ taking all precautions by supporting faces of excavation to ensure the safety of the 
workmen and to prevent damage to adjacent walls, building and all other structures 
and services and to prevent damage to road and other surfaces by slip or breaking 
away or trench sides or other cause including permanent and/or temporary shoring 
of trenches 
ƒ keeping the site and trenches and all other excavations free from water arising from 
whatever cause 
ƒ for clearing any scrub or other vegetable growth including all trees and for disposing 
of the whole of the cleared material to top provided by the Contractor 
ƒ all temporary and permanent measures required to protect and support all existing 
pipes, cables and services including all chambers, gullies and foundations thereto, or 
repair  or  replace  them  should  they  become  damaged  due  to  the  Contractor's 
activities 
ƒ all  barriers,  lighting,  warning  signs  and  any  other  measures  necessary  to  ensure 
complete safety around the area of the works 
ƒ reinstatement  of  all  affected  surfaces  and  structures  except  where  separate  items 
are included for permanent reinstatement of roads 
 
Structural Excavation: 
 
The volume of material excavated for the installation of permanent structure shall be measured as 
the product of the horizontal plan area of the base of that structure and the mean depth below the 
ground level. The mean depth shall be measured to the underside of the specified blinding concrete. 
 
Excavation in Rock: 
 
Excavation in rock in all cases shall be measured as extra over to excavation in normal materials by 
volume from the level at which rock is encountered.  The measurement of rock in general shall be as 
described elsewhere in this Clause. The volume of rock measured for trench excavation shall be to 
the maximum bottom width of trench permitted under the Specification or actual width, whichever 
is less and to the depth of bedding bottom level or as authorized by the Engineer.  
 
An isolated localized quantity of rock or other hard materials such as concrete encountered within 
the excavation of normal materials shall not be measured separately for payment unless its volume 
exceeds 1 cum except where the minimum volume shall be limited to 0.25 cum when the extent of 
net width of excavation is less than 2.5m. 
 
Fill: 
 
Fill shall be measured where a separate item is provided as the net volume above ground level of the 
permanent  earthwork  to  the  dimensions  shown  on  the  Drawings  or  directed  by  the  Engineer 
irrespective  of  source  of  material.    The  rate  shall  include  for  selection,  handling,  placing  and 
compaction in compliance with the specifications of excavated or imported material. 
 
Backfill: 
 
Backfill shall be measured (where items provided in BOQ) as the net difference between the volume 
measured under excavation as stated previously and the volume of installed permanent work below 
ground level.  The rate shall include for selection, handling placing and compaction of excavated or 
imported material. 
 
SECTION 4 ‐  CONCRETE WORKS 
 
4.1  General 
 
Concrete  required  for  major  structural  construction  shall  be  ready‐mix  concrete  and  subject  to 
Engineers approval. The unit rates for provision and placing of concrete shall include but not limited 
to following items. 
 
ƒ All costs incurred in determining the mixes to satisfy the Specification including application 
any admixtures as required 
ƒ Provision  of  storing,  mixing,  transporting,  placing  and  compaction  mechanical  means  or 
Batching Plants expect the supply of construction materials (Sand, Cement, and Aggregate 
shall  be  supplied  by  UNOPS).  The  water  or  any  ice  required  shall  be  supplied  by  the 
contractor. 
ƒ excavation as required below previously filled levels and backfilling except where separate 
items are provided 
ƒ roughening  the  surface  of  previously  executed  or  existing  work  as  required  in  order  to 
providing the necessary bond with new concrete 
ƒ Realizing the required quality of finishes within the specified tolerance 
ƒ forming slops, falls and the like as specified in the contract 
ƒ incorporating holes or box out for pipes, bolts, frames for covers and other steel work as 
required 
ƒ building in cable conduits, pipes, junction boxes etc. 
ƒ forming 25mm chamfers on all external arises to exposed concrete 
ƒ allowing  for  all  construction  joints,  keys,  stop  ends,  temporary  stops  and  shuttering  of 
other than permanently exposed faces  
ƒ provision and removal all shuttering/ form work, scaffolding as required 
ƒ curing of the concrete and all other measures to protect freshly poured concrete beating 
from direct sunlight and wave action 
ƒ trawling,  rubbing  down  etc.  and  making  good  the  concrete  surfaces  to  provide  the 
specified finishes 
ƒ cost of control testing throughout the period of concreting and for the testing of concrete 
and  remedial  work  ordered  by  the  Engineer  consequent  to  the  results  of  control  tests 
falling below the minimum specified 
ƒ extra working hours of personnel to maintain continuity of casting 
ƒ daily return to the Engineer showing the quantities of cement and the number of mixing of 
each class of concrete used in each section of the works as well as for temporary works 
 
The  measurement  of  concrete  shall  be  either  by  cubic  metre,  square  metre  or  linear  metre  of 
completed  structure  as  stipulated  in  the  BOQ.    In  the  event  of  volumetric  measure  is  used,  no 
deductions  shall  be  made  for  channels  recesses  or  rebates  less  than  600mm  girth,  for  splays  or 
chamfers  less  than  300mm  measured  on  the  splay,  for  holes  or  ducts  formed  in  the  concrete  less 
than 300mm girth.  Fillets less than 300 mm on the splay shall be measured. 
 
 
4.2  Blinding Concrete 
 
Rates for blinding concrete if a separate item is provided in the bill of quantity shall include for all 
additional  excavation  and  disposal  of  surplus,  necessary  sawn  shuttering  where  indicated  on  the 
Drawings  or  directed  by  the  Engineer.  Supply  of  construction  materials  (Sand,  Cement,  and 
Aggregate  shall  be  supplied  by  UNOPS).  The  water  or  any  ice  required  shall  be  supplied  by  the 
contractor. Measure for payment of this work shall be in sqm. 
 
4.3 Shuttering / Form work 
 
The unit rate for supply and placing of concrete shall include the cost of preparing, fitting, fixing of 
shuttering/form  works  with  necessary  scaffolding  in  all  cases  since  no  separate  item  would  be 
included in the Bill of Quantities for measurement and payment of form work. Supply of necessary 
materials,  equipment  for  preparing  fitting  fixing  of  formworks,  scaffolding  materials  shall  be 
procured by contractor and shall be include in the unit rate of concrete. Hence, the cost thereof for 
supply of necessary materials, equipment for preparing fitting fixing of formworks, scaffolding shall 
be deemed to be included in the rates for concrete work. 
 
4.4 Steel Reinforcement 
 
The  contractor  shall  prepare  and  submit  reinforcement  bar  schedules  for  all  reinforced  concrete 
structures  based  on  the  detailed  construction  drawings  provided  by  the  Employer  or  for  any 
additional works for approval by the Engineer prior to fabrication and fixing of any reinforcements in 
the works. The schedules shall be submitted well in advance to allow adequate time for checking. 
 
The  rates  for  steel  reinforcement  bar  and  steel  fabric  reinforcement  shall  include  for  local 
transporting, storing, cleaning, cutting, fabricating, all labour in working, distribution to various parts 
of  the  works,  fixing  in  position,  supporting,  for  the  use  of  binding  wire  and  for  welding  where 
indicated.  The  steel  reinforcing  bars  shall  be  supplied  by  UNOPS  to  the  contractor  at  storage.  The 
unit of measurement for steel reinforcement is the metric tonne (1MT = 1000 kg.) where separate 
item is provided and the weight of steel shall be calculated net with no allowance made for wastage 
or laps and the cost of these shall deemed to be covered in the unit rates. 
 
The weight of steel supports, spacer bars and ties including stirrups and binders used to locate and 
hold the reinforcement in place shall not included in the quantity and the cost of these shall deemed 
to be covered in the unit rates. 
 
SECTION – 5  MISCELLANEOUS WORKS 
 
5.1  Access Facilities 
 
The  Contractor  shall  provide  adequate  access  facilities  to  various  sites  within  the  project  area  to 
facilitate  construction  activities  at  no  extra  cost  to  the  Employer.  These  new  facilities  provided  by 
the  Contractor  shall  be  extended  to  other  contractors  executing  works  for  the  project  or  other 
agencies. 
 
 
 
5.2  Existing Services and Structures 
 
The Contractor's attention is specifically drawn to connections to and protecting of existing services 
and  installations.    The  Contractor  shall  be  deemed  to  have  included  in  his  tender  rates  and  prices 
adequate provision to comply with all such requirements. 
 
5.3  Painting & Protective Coatings 
 
The  rate  for  painting  and  protective  coatings  whether  measured  separately  or  included  in  other 
items are to include for all temporary staging ladders and the like, covering the adjacent works to 
prevent splashing providing adequate protection to the work being painted or coated against dust, 
spray and other foreign matter, for all preparation and priming, carrying out the work in materials 
and colours to the requirements of the Engineer, curling in edges, washing off stains, and leaving the 
whole  of  the  work  perfect  on  completion.    The  rates  for  painting  are  to  allow  the  applying  of  the 
final coat of paint immediately prior to handing over any section of the work. 
 
5.4  Amendments to Designs 
 
Where  amendments  are  required  to  the  civil  designs  due  to  prevailing  ground  conditions,  the 
amended  designs  shall  be  produced  by  the  Contractor  and  approved  by  the  Engineer.    No  extra 
payment shall be made for this work to the Contractor. 
 
5.5   Abbreviations:  
 
The units of measurement described in the Bill of Quantities are metric units.  Abbreviations used in 
he Bill of Quantities are as follows : 
 
km  Kilometre 
l. m.  Linear metre 
cm  Centimetre 
mm  Millimetre 
sq. m.  Square metre 
cu. m.  Cubic metre 
No.  Number 
kg  Kilogram 
tonne (t)  Tonne (1000 Kilograms) 
litre  Litre 
ha.  Hectare 
hrs.  Hours 
L.S.  Lump Sum 
P.S.  Provisional Sum 
   
5.6  Provision of facilities: 
 
Separate items are not provided for the following which are deemed to be included in the Contract 
Price : 
 
(a) Construction  and  maintenance  of  any  deviation  or  access  roads  and  all  expenses 
incurred due to passing of the traffic through or around the Site: 
 
(b) Cost of negotiations for any land required by the Contractor in addition to that made 
available to him free of charge; 
 
(c) The  subsequent  removal  of  the  Contractor’s  site  accommodation  as  required  and 
quarrying facilities and the reinstatement of the area on completion of the Contract; 
 
(d) Protection of the Works from water & from any other source; 
 
(e) Setting out and verification of all survey details and dimensions; 
 
(f) Provision and preservation of survey control points; 
 
(g) Provision of all samples and test certificates : and 
 
(h) Water supply and services. 
 
(i) Measures to reduce emissions and temporary protection of the environment. 
 
SECTION 6 ‐   DAYWORK SCHEDULE 
 
6.1  General 
 
This  Section  refers  to  the  provision  incorporated  in  Clause  52.4  of  General  Conditions  of  Contract 
and  the  work  shall  not  be  executed  on  a  Daywork  basis  except  by  written  order  of  the  Engineer. 
Contractor shall be entitled to payment in respect of labour, material and plant used for dayworks at 
the rates given in the schedules of Day Works presented below. 
 
The  Dayworks  rates  inserted  in  this  section  by  the  Contractor  shall  cover  all  expenses  relating  to 
administration,  financial  cost,  overhead  and  profit,  cost  of  liaison  with  external  agencies  and  all 
other costs related to Day Works.  
   
6.2  Labour 
 
The time engaged by the category of labour directly performing work ordered by the Engineer and 
for  which  they  are  competent  to  perform  shall  be  measured.    The  time  of  gangers  (charge  hands) 
actually doing the work with the gangs shall also be measured but not the time of foremen or other 
supervisory personnel. 
 
The given rate shall cover all direct costs to the Contractor including the amount of wages paid to 
such  labour,  transportation  time,  overtime,  subsistence,  allowances,  and  any  sums  paid  to  or  on 
behalf of such labour for social benefits in accordance with the Sri Lankan Law. 
 
 
 
 
 
 
 
 
 
   SCHEDULE OF DAYWORK RATES 
 
LABOUR 
 
RATE  
ITEM  DESCRIPTION  UNIT 
(SL Rs.) 
1.  Ganger  Day   
2.  Unskilled Labourer  Day 
3.  Operator for Crawler Mounted Machine  Day 
4.  Operator for Wheel Mounted Machine  Day 
5.  Operator for Pneumatic tools  Day 
6.  Driver  for  Trucks  /  Bowser  /  Tractor/  Lorry  /  Trailer  Day 
7.  etc.  Day 
8.  Mechanic  Day 
9.  Electrician  Day 
10.  Painter  Day 
11.  Welder  Day 
12.  Bar Bender/Reinforcement Worker  Day 
13.  Mason/Concrete Worker  Day 
14.  Carpenter/Form Worker  Day 
15.  Pipe Layer / Fitter / Plumber  Day 
16.  Light Vehicle Driver  Day 
Skilled Labour (other categories)   
 
NOTE:  The  above  rates  are  subjected  to  an  annual  escalation  increment  of  10%  per  annum, 
from the second year onwards after the date of commencement of the Contract. 
 
6.3  Materials 
 
The given rates shall cover the price, freight, insurance, handling, expenses, damage, losses, etc, and 
shall provide for delivery to store for stock piling at the site; and  
 
The cost of any materials supplied by Employer for use on Dayworks shall not be taken into account 
and additional percentage quoted also not applicable. 
 
The  Contractor  must  submit  his  receipts/bills  to  the  Engineer  in  support  of  all  Dayworks  materials 
payment claims. 
 
SCHEDULE OF DAYWORK RATES 
 
MATERIALS 
 
RATE 
ITEM  DESCRIPTION  UNIT 
(SLRs./cts) 
1.  a).  Ready mix concrete up to Gr.20  Cu.m   
  b).  ‐ do ‐ from Gr. 20 up to Gr. 35 A  Cu.m 
     
2.  Cement Ordinary Portland or Equivalent in Bags (50 Kg)  Bag 
RATE 
ITEM  DESCRIPTION  UNIT 
(SLRs./cts) 
     
3.  Ribbed TOR Steel reinforcing Bar  Tonne 
     
4.  Fine aggregate for concrete as specified  Cu.m 
     
5.  Coarse aggregate for concrete as Specified  Cu.m 
     
6.  a).  Timber  (Class 1)  Cu.m 
  b).  Plywood Sheets (½ inch)  Sq.m 
     
7.  a). Bricks/Masonry Blocks  No 
  b). Masonry Blocks (400 x 200 x 400)  No 
  c). Rubble 225 x 150 mm  Cu.m 
     
8.  Hume Pipes 0.6 dia x2.4 m lengths  No 
     
9.  Channel Steel (H,L,.I)  Tonne 
     
10.  GI Sheets (2.4 x 1.2)   ‐ 24 guage  No 
     
11.  Sheet Piles  Tonne 
     
12.  (a). Paints (Enamel/Emulsion)  Litre 
  (b). Anticorrosive/Al. Paints  Litre 
  (c). Thinner  Litre 
     
13.  Asphalt  Litre 
     
14.  Fuel    
  a). Petrol  Litre 
  b). Diesel  Litre 
     
15.  Reinforcement (mild steel)  Tonne 
     
16.  Shuttering Planks  Sq.m 
     
17.  River Sand  Cu.m 
 
 
NOTE:   The above rates are subjected to an annual escalation increment of 5% per annum from 
the second year onwards after the date of commencement of the Contract. 
 
6.4  Constructional Plant 
 
In  calculating  the  payment  due  to  the  Contractor  for  Constructional  Plant  employed  on  daywork, 
only the actual number of working hours will be eligible for payment, except that where applicable 
and agreed with the Engineer, the travelling time from the part of the Site where the Construction 
Plant was located when ordered by the Engineer to be employed on daywork and the time for return 
journey  thereto  shall  be  included  for  payment.  The  cost  of  drivers  and  operators  will  be  paid 
separately as described under the section on “Daywork Labour”.  
 
The  given  rate  shall  cover;  due  and  complete  allowances  for  depreciation,  interest,  indemnity  and 
insurance, repairs, maintenance, supplies, fuel, lubricants, and other consumables, and all overhead 
profit and administrative costs related to the use of such equipment; and 
 
 
SCHEDULE OF DAYWORK RATES 
 
CONSTRUCTIONAL PLANT 
 
MINIMU
RATE 
ITEM  DESCRIPTION  M  UNIT 
(SLRs./cts) 
CAPACITY 
1.  a). Excavator ‐ Crawler mounted  0.4  Cu.m  Hour   
  b). –do–  0.7  Cu.m  Hour 
  c). –do–  1.2  Cu.m  Hour 
       
2.  a). Bull‐Dozer  with  Ripper‐  Crawler  90 HP  Hour 
  Mounted  200 HP  Hour 
  b). –do‐     
3.    70 HP  Hour 
  a). Back‐Hoe  Excavator  ‐  Wheel  mounted     
  with bucket width 0.3,0.45 and 0.6 m  85 HP  Hour 
  b). –do–     
4.    1.4 Cu.m  Hour 
  a). Front End Loader ‐ Wheel mounted  2.3 Cu.m  Hour 
  b).  –do–  3.2 Cu.m  Hour 
  c).  –do–     
5.    90 HP  Hour 
  Motor Grader ‐ Wheel mounted      
6.    2 Tonne  Hour 
  a). Mobile Crane  5 Tonne  Hour 
  b). –do–     
7.    55  Hour 
  a).    Concrete pump cart  Cu.m/Hr  Hour 
  b).     –do–  95   
8.    Cu.m/Hr  Hour 
  Boom Truck      
9.    15 Tonne  Hour 
  a).    Dump Truck    Hour 
  b).    –do–  4 Tonne  Hour 
  c)    –do–  8 Tonne   
10.    11Tonne  Km 
  a). Trailer Truck for Pipe Transport     Km 
  b). –do‐ without load  17 Tonne   
11.      Km 
  a). Low  bed  Trailer  with  prime  mover  for      
  Machine / Pipe Transport with load  17 Tonne  Km 
MINIMU
RATE 
ITEM  DESCRIPTION  M  UNIT 
(SLRs./cts) 
CAPACITY 
  b). –do‐ without load     
12.      Hour 
  a). Agitator Car/Concrete Transport Truck     Hour 
  b). –do–  3 Cum.   
13.    6 Cum.  Hour 
  a).    Water Bowser    Hour 
  b).  –do–  1000 Lit   
14.    4000 Lit  Hour 
  Tractor with Trailer     
15.    2 Cu.m.  Hour 
  a). Lorry / Pickup / Truck     Hour 
  b). Lorry   1.5 Tonne  
16.    10 Tonne  Hour 
  a). Concrete mixer Truck (with self loading     
          Facilities)  1.4 Cum.  Hour 
  b).    –do–     
17.    3.2 Cum.  Hour 
  Plate compactor/Vibrator     
18.    2 Tonne  Hour 
  Rammer Compactor / Vibrator     
19.    80 Kg.  Hour 
  a). Roller compactor / Vibrator    Hour 
  b). –do–  4 Tonne   
20.    10 Tonne  Hour 
  Form Vibrator     
21.    0.4 Kw  Hour 
  Poker Vibrator Plant including 25, 32,     
  50 mm  poker  0.4 Kw   
22.      Hour 
  a)   Diesel Generator    Hour 
  c). –do–  1 kVA  Hour 
  d). –do–  5 kVA  Hour 
  e). –do–  25 kVA   
23.    60 kVA  Hour  
  a).    Portable Air Compressor including rock     
         Breakers & Hammers   175 cfm  Hour  
  b).   –do‐     
24.    300 cfm  Hour 
  a). Submersible Pump    Hour 
  b). –do–  1 HP  Hour 
  c). –do–  3 HP   
25.    7 HP  Hour 
  a). Portable self priming engine driven     
  Centrifugal diesel pump   50 mm  Hour 
  b). –do‐    Hour  
  c). –do‐  60 mm   
26.    75 mm  Hour 
  Spray painting Equipment     
MINIMU
RATE 
ITEM  DESCRIPTION  M  UNIT 
(SLRs./cts) 
CAPACITY 
27.      Hour 
  a). Portable  Welding  Plant  including      
  Welding rods 500 A    Hour  
  b). Oxy‐Acetalene  Welding  Set  including     
  welding rods     
28.      Hour 
  Bar Cutting / Bending Machine     
29.      Hour   
  a). Concrete Mixer    Hour  
  b). –do–  0.3 Cum.   
30.    1.4 Cum.  Hour 
Asphalt Cutter with diamond disc 
 
NOTE:   The  above  rates  are  subjected  to  an  annual  escalation  of  10%  per  annum,  from  the 
second year after the date of commencement of the Contract.  
BILL OF QUANTITIES

SUMMARY

A. Bill of Quantities
DIVISION-1 : General and Site Facilities SLR:
DIVISION-2 : Main Bridge Work SLR:
DIVISION-4 : Approach Road SLR:

SUB-TOTAL-A: SLR:

B. Add

Provisional Sum for Physical


Contingencies (10% of A) SLR:

SUB-TOTAL-B: SLR:

TOTAL (A+B) : SLR:

Discount in % and the total amount


in SLR (Excluding Provisional Sum),
If any offered by the tenderer SLR:

TOTAL TENDERED SUM : SLR:

Total SLR (In Words)……………………………………………………….…

Note: All National Contractors shall quote their Rates by SLR


DIVISION-1: GENERAL AND SITE FACILITIES

BoQ Pay Reference Unit Rate Amount


Item Item Specificatio Description of work Unit Quantity
SLR SLR
No. No. n no.
Contractor's Establishment on site: Establishing of all the
facilities on or adjacent to the Site that the Contractor deems
1.1 108(1) 108(1) LS 1 3,000,000 3,000,000
necessary for fulfilment of all his obligations under the Contract

The work of temporarily supporting and protecting public utility


1.2 113(1) 113(1) services during execution of the Works for the Demolition and PS 1 200,000 200,000
Rebuilding of Property as instructed by Engineer

Special and Additional Tests to be done elsewhere.


1.3 130.8(b)

130(15) a) Special and Additional Tests PS 1 - -


1.4 816(1) 816 Relocation of Utilities as required and instructed by Engineer
a) Relocation Cost PS 1 600,000 600,000
Allow for providing and maintaining Project Sign Boards in the
1.5 131(1) 131(1) format acceptable to the Engineer. no. 3 - -

Providing and fixing Marble stone for foundation laying both end of
1.6 133(1) 133 the bridge as per direction of Engineer PS 1 - -

Allow for providing all necessary Insurances for workforce for all
1.7 132(1) 132 risks L.S. 1 1,000,000 1,000,000

Allow for providing all necessary bonds and securities as are


1.8 132(2) 132 required and detailed in the Tender Documents, Conditions of L.S. 1 1,000,000 1,000,000
Contract or this Specification under this contract

TOTAL (DIVISION-1) 5,800,000


DIVISION-2: BRIDGE CONSTRUCTION WORKS
A. FOUNDATION WORKS
BoQ Pay Reference Unit Rate Amount
Item Item Specification Description of work Unit Quantity
SLR SLR
No. No. no.
All clearing and grubbing necessary for the performance of the work covered by
2.1 201(1) 201 the Contract in accordance with the Specifications. Sq.m. 0

Construction and removal of cofferdam (starting from both end with opening 35m
in middle at first stage. This 35m opening will be constructed in second stage after
construction of pile and pile cap) for the construction of bored cast in situ piles and
2.2 the construction of in situ RCC T Girder/ PC beam by carried earth with slope cu.m 5,500
protection by filling gunny bag and proper compection as per direction of Engineer.
Removal work will be started after constructon of Bridge, as per instruction of
Engineer.
TOTAL (DIVISION-2)
DIVISION-4: APPROACH ROAD

A. PREPARATION WORKS OF ROAD CONSTRUCTION


BoQ Pay Reference Unit Rate Amount
Item Item Specificatio Description of work Unit Quantity
SLR SLR
No. No. n no.
Clearing, grubbing disposal of vegetation and debris plus removal and stock piling of
4.1 201(1) 201 sq.m 6,500
topsoil
4.2 201 Uprooting and removal of trees as stated below:
4.2(1) 201(2) a) Trees with girth 250mm to 1000mm no. 0
4.2(2) 201(3) b) Trees with girth 1000mm to 2000mm no. 0
4.2(3) 201(4) c) Trees with girth 2000mm to 3000mm no. 0
4.2(4) 201(5) d) Trees with girth beyond 3000mm no. 0
Removal of Existing Pavement including Sub-base, Base and Bituminous Wearing
4.3 204(1) 204 Coarse etc and remove all scrap materials at a safe place as per direction of the Cu.m. 100
Engineer
Removal of Existing Structure, remove all scrap materials at a safe place as per
4.4 202(1) 202 PS 1 200,000 200,000
direction of the Engineer
SUB-TOTAL -A:

TOTAL (DIVISION-4):
Rate Analysis (Example)

1:   Cement concrete (1:3:6, grade 15 cube strength) for the foundation with cement, sand and stone 
aggregate (20 mm down graded). Including mixing, laying, compacting, maintaining levels, curing, carriage 
of all materials.
Data For Concrete in Cum: 8.5
 Materials   Unit  Quantity  Unit Cost in LKR  Total Cost LRR
 Cement   Kg 
 Sand, F.M>2.5   Cum 
 Stone Aggregate, 20 mm downgraded   Cum 
 Allow for water collection for mix   Cum 
Subtotal for materials:
Labour:
 Skilled labour/Mason   WD 
 Semiskilled labour for casting   WD 
 Unskilled labour for curing   WD 
 Unskilled labour for screening   WD 
Subtotal for Labour:
Tools & Equipments:
 2.5% tools on labour cost: 
Rental cost:
 Rental cost for mixer machine (400 ltrs)   WD 
 Rental cost for concrete vibrator   WD 
Operation & maintenance cost:
 Operator for mixer machine   WD 
 Operator for vibrator   WD 
 Fuel and lubricant (5 ltr for mixer + 2 ltr for   Ltr 
vibrator per day) 
 Service and repair for mixer and vibrator   WD 

Subtotal for equipment rental, operation & maintenance cost:
 Subtotal for materials, labour, equipment rental, operation & maintenance cost: 
Contractor's Overhead cost 15%
Contractor's profit 7%
Contractor's overhead and profit:
Total cost for 8.5 cum concrete works for foundation:
Total cost for 1.0 cum concrete works for foundation:
Grand Total for 1 Cum concrete works in LKR:
Grand Total for 1 Cum concrete works in USD:

Vous aimerez peut-être aussi