Académique Documents
Professionnel Documents
Culture Documents
VOLTEX
AD
Focus on:
Geotechnical Engineering
• Southern Cape Landslip
• Upgrading the Kranspoort Pass
Profile:
Dr Phil Paige-Green
PASSION
FOR PROGRESS
On the morning of Ahmed Kathrada’s quiet” during the apartheid years, when “… I express the hope that you will choose
death, the renowned and respected car- they needed us most. This is why many the correct way.”
toonist Nanda Sooben took to social media black civil engineering practitioners still So what is the correct way? My per-
asking, “Are there any good men left?” claim that SAICE is a “white” organisa- sonal answer to the icon would be along
After the recent cabinet reshuffle, I tion. The culture of SAICE, supported by these lines:
asked our members if SAICE should take a our membership statistics, shows oth- “Our involvement is unattached to
stand. Some of our members have encour- erwise. But we shouldn’t miss the point. any individual, political party or schisms
aged SAICE to engage. SAICE’s young SAICE should not repeat its mistakes, as in party politics. It is principally asso-
members, particularly, wish SAICE to be we will be judged severely for it in future, ciated with good governance and the
heard, and seen to be heard on the matter. in both moral and metaphysical terms. role of state in creating conditions for
Other members are quiet – and I I attended the funeral of Donald democratic process, and social justice in
respect that, too. SAICE has always cher- Macleod PrEng, who was City Engineer South Africa. Civil engineering serves all
ished the complexity of views that ema- of Durban from 1976 to 1992. Millions South Africans. Recent instances of dys-
nate from our diverse membership. This is of people enjoy safe sanitation in Durban functional and unaccountable behaviour
the brilliance of our own democracy. But because of Don’s leadership. At the memo- in parliament, as well as unclear reasons
I must make the point that Elie Wiesel rial I noticed the humility and understated for ministerial appointments, cause
made – indifference, while it is tempting, elegance of the full life of a good man. In concern about our government’s ability
is a peril. Wiesel argues that, because it his SAICE presidential address in 1987, to properly respond to the development,
benefits the aggressor and not the victim, he said, “We should never see the fruits of infrastructure and socio-economic
indifference is a friend of the enemy. technology as being of greater importance well-being of South Africa. I am a civil
At the recent ICE Conference in Cape than people. Our respect for the dignity engineer. I protest for the South Africa I
Town (April 2017), Yunus Ballim PrEng, and immeasurable value of the human love, because I believe in its resilience.”
Vice Chancellor of Sol Plaatje University being should always be upheld.” He was With sword in one hand and pen in
in Kimberley, and professor of civil engi- known as a leftist in the nationalist climate the other, my answer to Nanda Sooben is,
neering at Wits University, on a platform of the day. As a white civil engineer, he was “Yes! There are still good men and women
with distinguished colleagues Sundran known for rescuing black people during left amongst 52 million South Africans.
Naicker PrEng and Paul Jowitt CEng, the Cator Manor uprising, and delivering We have 13 000 of them – we are civil
articulated two gems that appealed to my sanitation to black communities in a time engineering professionals.”
civil engineering sense of social justice. when policies and nationalist establish-
He said: ment dictated otherwise.
■ To be a civil engineer, is to be funda- Having worked with his son, Neil
mentally engaged in critical matters of Macleod PrEng, at SAICE, the Macleod
the human condition; and name is in the company of those bas-
■ For civil engineers to avoid politics tions of social justice mentioned in this
– to not be involved in politics – is article – so, too, is the name of every
flawed and imaginary. Civil engineers civil engineering practitioner who abides
must intervene in places of power and by the traditions and tenets of this
spaces of powerlessness. incredible profession.
Civilution expressly requires of us to be I am aware that SAICE is a nonpar-
honest with introspection. In the malaise tisan, impartial and unprejudiced voice
of our country’s past, SAICE practised for civil engineering professionals. Our
great circumspection when sharing views objectives are the growth and develop-
outside of cold concrete civil engineering. ment of our members, and the promotion
At the turn of the millennium, some of of the science and practice of civil engi-
our members from previously disadvan- neering and the advancement of the civil
taged communities reluctantly joined engineering profession. Ahmed Kathrada
SAICE, because SAICE was “deafeningly would have agreed with us and then said,
Focus on:
Geotechnical Engineering
• Southern Cape Landslip
• Upgrading the Kranspoort Pass
Profile:
ON THE COVER P7
Dr Phil Paige-Green
ON THE COVER The 8.5 m shored jacking pit ready to start pushing the jacking shield in a trenchless
Keller’s Franki Africa is known for overcoming
technology operation on the Paarl bulk sewer line in the Western Cape
challenges, and for delivering cost-effective
geotechnical solutions using a wide range
of technologies in a host of different ground
conditions, as demonstrated in its recent
trenchless work on a sewer line in Paarl
FROM THE CEO’S DESK
(the photo shows the treated jacking face
holding cobbles and fines in suspension).
The Don . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
South African
Institution of
Civil Engineering
ON THE COVER
Franki overcomes challenges on the Paarl bulk sewer line . . . . . . . . . . . . . . . . . . . . . . 7
Isivili Enjiniyering
April 2017 Vol 25 No 3
PUBLISHED BY SAICE
Block 19, Thornhill Office Park,
PROFILE
Bekker Street, Vorna Valley, Midrand
Private Bag X200, Halfway House, 1685
Tel 011 805 5947/8, Fax 011 805 5971
http://www.saice.org.za | civilinfo@saice.org.za Loving his job because it’s meaningful . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
CHIEF EXECUTIVE OFFICER
Manglin Pillay Pr Eng
manglin@saice.org.za
Tel 011 805 5947/8
EDITOR
Verelene de Koker
verelene@saice.org.za
Tel 011 805 5947/8, Cell 083 378 3996
GEOTECHNICAL ENGINEERING
EDITORIAL PANEL
Marco van Dijk (chairman), Irvin Luker (vice-chairman),
Sundran Naicker (president), Manglin Pillay (CEO),
Steven Kaplan (COO), Johan de Koker, Andile Gqaji,
Southern Cape Landslip, Mossel Bay . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Gerhard Heymann, Jeffrey Mahachi, Avi Menon,
Jones Moloisane, Beate Scharfetter, Marie Ashpole,
Verelene de Koker (editor), Elsabé Maree (editor’s
assistant), Barbara Spence (advertising) St Helena Airport dry gut rockfill . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
ANNUAL SUBSCRIPTION RATE
R675.00 (VAT included)
PRINTING
Town Hill pipe jack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
Fishwicks, Pretoria
P53
Civil Engineering April 2017 3
excellence in execution
1
DOWN
2
1. The formula p=m•v is used to calculate.
ACROSS
You’re an engineering professional. You’ve spent years studying your chosen field.
So you don’t need us to help you with the answers to this crossword. Completing it,
however, will be revealing. Your rarity should be rewarding - and with PPS, it is.
Bespoke financial solutions and rewards tailored for graduate professionals only.
To find out more, contact your PPS-accredited financial adviser or visit pps.co.za
#R AREISREWARDING
PPS offers unique financial solutions to select graduate professionals. PPS is an authorised Financial Services Provider.
ON THE COVER
THE CHALLENGE
The path of the sewer pipeline (in the town of Paarl in the Western
Cape) includes a stretch of approximately 105 m across Arboretum
Road and the N1 highway, followed by a section of around 110 m
which runs parallel to the Boschenmeer Golf Estate boundary wall
at a depth of –6 and –8 m.
According to Field, the main challenges were the relatively
unstable ground conditions, which comprised sands from 0 to –4 m
deep, with loose cobbles and boulders from –4 m to –8 m, and a
very high water table.
SANRAL also had strict wayleave conditions prohibiting the
Drakenstein Municipality from conducting work beneath the N1
unless they were able to prove that every conceivable precaution had
been taken to protect the highway and to ensure uninterrupted use.
It was obvious that a trenchless methodology, like pipe jacking,
would be required for the new sewer to run under the roads without
interrupting traffic. The depth of the pipeline and its proximity
to the Boschenmeer Golf Estate boundary wall also made open
excavation impractical.
When the ground conditions were analysed, a new challenge
was encountered! Field explains: “Firstly, the level of the sewer
passed directly through the cobble layer between –4 to –8 m deep,
and when pipe jacking is performed through this type of ground
it is virtually impossible to prevent collapse of the cobbles during
excavation. Secondly, the high water table tended to draw fines from
the surrounding ground towards the jacking shield. Both of these
conditions could have led to over-excavation resulting in ground
Jet grouting rig working on the Paarl bulk sewer line alongside the N1
level settlement.”
FRANKI’S PROACTIVE PROPOSAL piles, full displacement screwpiles, rotapiles, micropiles, the
Franki approached the Drakenstein Municipality with a proposal famous Frankipile (driven cast-in-situ pile) and many more. It
to treat the ground beneath Arboretum Road and the N1, as well is also well-known for its soil improvement systems, including
as alongside the Boschenmeer Golf Estate boundary wall. dynamic compaction, deep soil mixing, accelerated consolida-
The proposal entailed jet grouting – which involves the tion, and of course jet grouting as discussed above.
mixing and partial replacement of the in-situ soil with cement Franki’s skills in trenchless technology are just as impressive.
slurry – to consolidate the in-situ ground condition along the For more than 30 years it has successfully been providing pipe
sewer centreline and between the depths of –4 to –9 m, and jacking and other trenchless technologies – augering, thrust
to then install a pipe jack through the treated ground. “The boring and large-diameter case boring – to a wide range of
treatment of the ground would prevent collapse of the sand and clients in southern Africa.
cobbles during pipe jack excavation and would reduce the ingress Trenchless technology is a ‘family’ of methods, materials and
of water to manageable levels,” Field says. equipment capable of being used for the installation, replacement
He adds that jet grouting was Franki’s preferred method of or rehabilitation of existing underground infrastructure with
treatment, as high-pressure jetting can be used to consolidate in- minimal disruption to surface traffic, business and other activi-
situ ground at exact levels, and can provide up to 2.5 m diameter ties. It is, therefore, often the most cost-effective solution.
columns with only an 80 mm drill stem. Pipe jacking, an integral part of this ‘family’, is a technique
The municipality’s design team included the proposed for installing underground pipelines, ducts and culverts.
solution in the tender document for this phase of the works Powerful hydraulic jacks are used to push specially designed
and, in August 2016, Franki was appointed by the main pipes through the ground behind a shield at the same time as
contractor, Vakala Construction, to carry out the specialist excavation is taking place within the shield. The method provides
geotechnical work. a flexible, structural, watertight, finished pipeline as the tunnel
is excavated.
THE RESULT
Field says that the jet grouting went according to plan and was CONCLUSION
carried out with zero impact on traffic. “In addition, once the jet By being part of the Keller Group, Franki’s leadership in the
grouting had been completed and the site cleared, there was no geotechnical space in southern Africa has been significantly
remaining evidence at ground level that the ground beneath had enhanced. Keller is the world’s largest independent geotechnical
been treated. engineering contractor, offering Franki significant advantages,
“The entire pipe jacking operation went smoothly, with such as access to a wide range of innovative technologies, state-
the ground treatment working better than even our highest of-the-art machinery and a wealth of geotechnical intellectual
expectations.” property and experience.
The sub-contract work was completed by Franki on time
(February 2017) and within budget. INFO
Victor Ferreira
FRANKI – MORE THAN JUST PILES Franki Africa
Franki is renowned for its geotechnical solutions using an array +27 11 531 2700
of different piles, including driven tube piles, precast piles, auger victor.ferreira@franki.co.za
While at the University of Natal, Phil was offered a position at TURNING A DILEMMA INTO MEANINGFUL WORK
the then National Institute of Road Research at the CSIR, where The theme of Phil’s PhD thesis in the mid-80s (University of
he started in 1976, and remained until his retirement from the Pretoria) was, The influence of geotechnical properties on the
CSIR in 2013. performance of gravel-wearing course materials. “With my PhD
“I consider myself lucky in my career. As Isaac Newton said way came the realisation that I had a bit of a dilemma – was I doing
back in 1676: ‘If I have seen further, it is by standing on the shoulders the work of a geologist or an engineer? The material selection and
of giants’. I have managed to meet and work with many of the giants performance modelling of unpaved road behaviour led onto the
in the geotechnical field, all of whom have helped me, a relative design, which was suddenly an engineering issue more than engi-
dwarf, to see further. In fact, there are only three or four names on neering geology, but I knew I couldn’t be an engineer, although I
the list of the past 32 Gold Medal recipients that I never got to meet. did join SAICE at that time as a visitor.”
Many of the remainder I have worked closely with over the years – As it turned out, Phil moved into materials investigation for
these include such giants as Tony Williams, Tony Brink, Gary Jones, low-volume paved roads and then the design of these, which is
Frank Netterberg, Hartmut Weinert, Peter Day and many others. I what still keeps him busy today as an independent consultant.
am also happy to see that I am the fourth engineering geologist to “The overlap between engineering geology and geotechnical
be honoured with this prestigious engineering award, the others engineering was nowhere more apparent to me than when I
being Tony Brink, Frank Netterberg and Hartmut Weinert, all of recently looked at bridges which had lost their approach fi lls
whom I have worked with over the years, and coincidentally all of during the 2013 floods in the Gaza Province in Mozambique. The
whom had spent at least part of their careers at the CSIR.” embankment strength is a function of the geological/geotechnical
properties, as well as of the construction and design. The erosion
FIRST GEOTECHNICAL TASK is a function of the geomorphology, rainfall and design. The failure
When he started at the CSIR, Gary Jones was his first boss, and is thus a combination of geology, geotechnical, geomorphological
one of his first geotechnical jobs was the proposed Wonderfontein and engineering inputs, together with the one thing we can’t
section of the N4. Gary told Phil to go and profile the sites of two control – the climate. My career has re-treaded my geological
embankment fills and a bridge foundation, and do some CPT pro- background into a much wider horizon overlapping geotechnical
files using the newly introduced equipment (before piezocones). and road engineering. I like to think I know enough about all of
“I did the field work, went back to the office and sent the field these issues now to pull them into one composite solution.”
sheets through to Gary. He called me in and told me that I had only And indeed, Phil’s life-work has culminated in him becoming
done half a job, and that I needed to analyse them as well and see if a specialist in low-volume roads. “In the past there were no design
the preliminary designs were adequate. I didn’t have a clue what to
do and so, after a quick course by Gary in applied foundation engi-
neering, I carried on and did it. It transpired that the materials were I have managed to meet and work with many of the
very weak, fissured, residual clays, and one of the embankments
giants in the geotechnical field, all of whom have
and the bridge foundations would probably have failed as designed
originally – I am pleased to say they are still there today!” helped me, a relative dwarf, to see further.
Civil Engineering April 2017 11
irony is that this same problem exists in rural South Africa, but
the available expertise is not fully utilised here.
GLOBAL FOOTPRINT
During his interesting and varied career Phil has worked on
every continent (36 countries) except Antarctica, but he says that
the lack of roads will not stop him from still going there, too!
One of his major growing experiences was spending two years
in the Middle East Gulf region in the mid-1990s, based in the
Sultanate of Oman, where he was the only engineering geologist/
pavement person in the area. Hence he was called in to look at all
sorts of problems – slope instability, construction and stabilisa-
tion problems, salt damage problems, settlement of buildings,
and even the review of a freeway design in Pakistan.
Over the years Phil has also developed a working under-
standing of languages as diverse as Arabic, Italian, Zulu, French,
Portuguese and Afrikaans, that is apart from his native English.
Being able to deal with language barriers in the work environ-
Dr Phil Paige-Green with his wife Pam, who he has been married to ment, even if on a limited scale only, has stood Phil in good stead
happily for 38 years, and their children Timothy and Alexandra
on many projects.
methods specific to low-volume roads. Conventional road design AWARDS AND RECOGNITION
methods were simply downscaled to construct low-volume roads, The SAICE Geotechnical Gold Medal is undoubtedly the most
but we cannot afford that any longer, particularly in light of the fact prestigious recognition of Phil’s work. He received many other
that at least 75% of our roads are low-volume. Our approach has awards as well, of which the following are very special to him:
therefore been to find other ways of designing, using cheaper mate- ■ 1998: Joint recipient of the ATC Award for the best paper
rials, leaving out whole layers where possible, and so forth, resulting presented at the annual Transportation Convention with
in many more lengths of road for the same amount of money.” Dr Frank Netterberg for their paper titled Wearing course
Phil revels in the fact that this approach has the potential to materials for unpaved roads in southern Africa: A review
uplift the whole of Sub-Saharan Africa. His work in a number ■ 2000: George Dehlen Award for Excellent Mentorship
of African countries, and also currently in India, entails estab- ■ 2008: JD Roberts Research Award
lishing this design philosophy. In India, Phil and his team are
designing 5 000 km of low-volume roads. If one considers that GIVING BACK
India has approximately 170 000 villages which do not have The past few years have been a period in Phil’s life where he has
road access at all, it puts the extent of the need into perspective. tried to give something back, his motto being Albert Einstein’s
In Africa (particularly in Ethiopia, Tanzania, Ghana, Zambia, saying “Try not to become a man of success; rather become
Malawi and Mozambique) Phil has prepared (or is still involved a man of value”, the reasoning being that a man of value will
in) manuals on how to design roads using these methods. The give more than he receives. And indeed, Phil has supervised
At least 75% of South Africa’s roads are low-volume, necessitating more economical approaches to road design and construction
Verelene de Koker
verelene@saice.org.za
BACKGROUND
Towards the end of 2015, attention
started to be drawn to several
residential properties in the suburb
of Hartenbos in the coastal town of
Mossel Bay in the Southern Cape
(refer to Figures 1 and 2), which were
showing signs of severe cracking and
structural distress (refer to Figures
3–5). A preliminary geotechnical
study was commissioned by the
Home Owners Associations of the
two affected complexes to assess the
cause of the problems observed. The
Figure 1: Aerial photo of the area affected by the landslip
preliminary investigations indicated
that a deep-seated landslip was slowly and it not only demonstrates the role to the continual movement of the ground
developing between the two complexes. and responsibility of civil engineers in and the urgency of the matter, time was of
Initial observations indicated that our society, but also the potential scale the essence in the investigations.
approximately 30 residential houses were of emotional distress caused to society
affected by the landslip, and due to the when geotechnical uncertainty is not PROJECT DESCRIPTION
high safety risk, residents were evacuated defined and interpreted. The findings The area affected by the landslip consists
from zones showing significant vertical discussed in this article also highlight the of two group residential complexes, which
and lateral displacement of the ground. fact that geotechnical conditions which are separated by a steep embankment.
Subsequent to the initial investigations, may impact residential developments (or The upper complex is situated in an old
Mossel Bay Municipality commissioned a any civil engineering project) may extend gravel quarry, and the lower complex in
more detailed study to further investigate beyond the footprint of any particular an old clay quarry. The affected area also
the problem and assess possible solutions. structural element. extends into an adjacent private residen-
To date, over 45 houses have been tial neighbourhood.
affected, several of which have been AIMS AND OBJECTIVES
condemned and demolished. The scale of The aim of the detailed investigations was Site geology
the problem is yet to be fully understood. to determine the trigger mechanism of The geology of the site was important
This case study highlights one of the the landslip and the depth of the failure in understanding the origin and
most significant landslips in the Southern zone, as well as the feasibility of possible mechanisms of this landslip. The landslip
Cape in recent South African history, solutions identified in the process. Due area is underlain by a thick sequence
Engineering Fields:
GEOTECHNICAL
CIVIL
STRUCTURAL
MECHANICAL
ELECTRICAL
Branches:
www.kanteys.co.za
CONTAMINATION
ENVIRONMENTAL
CAPE TOWN (021) 405 9600 GEORGE (044) 874 2177 EAST LONDON (043) 762 6443
DURBAN (031) 266 6535 PIETERMARITZBURG (033) 347 5453 PORT SHEPSTONE (039) 315 1519 QUANTITY SURVEYING
JOHANNESBURG (011) 501 4760 PORT ELIZABETH (041) 373 0738 www.kanteys.co.za & COST ENGINEERING
Figure 4: Typical distress observed in many of the residential structures
of alluvial sediments of the Uitenhage under fluctuating sea levels, with interfin- continental uplift and regression of sea
Group, which consists locally of the gering of marine, estuarine and alluvial levels resulted in increased erosion of
younger Buffelskloof Formation and the sediments. The Kirkwood Formation the interior Cape Fold Belt mountains,
older underlying Kirkwood Formation. was deposited in a low-energy fluvial and rivers flowing from these high-lying
The depositional environment was a environment, and consists mainly of areas bisected lower-lying alluvial ter-
dynamic coastal embayment created mudstone and fine sandstone. Subsequent races, depositing thick sequences of sand,
ŽŶƐƵůƚŝŶŐŶŐŝŶĞĞƌŝŶŐ'ĞŽůŽŐŝƐƚƐΘ'ĞŽƚĞĐŚŶŝĐĂĂůŶŐŝŶĞĞƌƐ KƵƌ'ĞŽƚĞĐŚŶŝĐĂůWƌŽĨĞƐƐŝŽ
ŽŶĂů^ĞƌǀŝĐĞƐŝŶĐůƵĚĞ͗
,K&&/͗>ĞǀĞůϯDĂŐŐŶĞƚƵŝůĚŝŶŐ͕ĚƐƚĂŶƵƐŝŶĞƐƐWĂƌŬ ĂƐƚƚ>ŽŶĚŽŶKĨĨŝĐĞ͗
Ϯ/ďŚƵďĞƐŝZĚ͕ZŝǀĞƌŚŽƌƐĞsĂůůĞLJ͕ƵƌďĂŶ͕^ŽƵƚŚĨƌŝĐĂ ϭϬ
ĞƌĞĂdĞƌƌĂĐĞ ¾ ^ŝƚĞ/ŶǀĞƐƚŝŐĂƚŝŽŶƐĨŽƌ͗
W͘K͘ŽdžϮϯϵϰ͕tĞƐƚǀŝůůĞϯϯϲϯϬ ĞƌĞĞĂ͕ĂƐƚ>ŽŶĚŽŶ͕^ŽƵƚŚĨƌŝĐĂ 9 ŽŵŵĞƌĐŝĂů͕/ŶĚƵƐƚƌƌŝĂů͕ĂŶĚWŽƌƚĞǀĞůŽƉŵĞŶƚƐ
D/>͗ĚƵƌďĂŶΛŵƐũŐĞŽƚĞĞĐŚŶŝĐĂů͘ĐŽ͘njĂ D/>͗ĞĂƐƚůŽŶĚŽŶΛŵƐũŐĞŽƚĞĐŚŶŝĐĂů͘ĐŽ͘njĂ 9 ĂŵƐ͕WŝƉĞůŝŶĞƐ͕dƵŶ ŶŶĞůƐĂŶĚWŝƉĞ:ĂĐŬŝŶŐ
d>͗нϮϳ;ϯϭͿϵϰϬϰϵϱϬ d>͗нϮϳ;ϰϯͿϳϮϭϮϮϮϮ 9 ZŽĂĚƐ͕ZĂŝů͕ƌŝĚŐĞƐĂŶĚ/ŶĨƌĂƐƚƌƵĐƚƵƌĞ
ǁǁǁ͘ŐĞŽƚĞĐŚĂĨƌŝĐĂ͘ĐŽŵ
^ůŽƉĞ&ĂŝůƵƌĞZĞŚĂďŝůŝƚĂƚŝŽŶĂŶĚ>ĂƚĞƌĂůƌĞƚĂŝŝŶŝŶŐ 9 ZƵƌĂůĂŶĚhƌďĂŶZĞƐƐŝĚĞŶƚŝĂůĞǀĞůŽƉŵĞŶƚ
ƐLJƐƚĞŵƐ ¾ 'ƌŽƵŶĚ/ŵƉƌŽǀĞŵĞŶƚ;Ě ĚĞĞƉĂŶĚƐŚĂůůŽǁͿ
D^: 'ĞŽƚĞĐŚŶŝĐĂů ŽŶƐƵůƚŝŶŐ ^ĞƌǀŝĐĞƐ ;WƚLJͿ >ƚĚ ;D^:Ϳ͕ 'ĞŽůŽŐŝƐƚƐĂŶĚ'ĞŽƚĞĐŚŶŝĐĂůŶŐŝŶĞĞƌƐ;^/'ͬ^/ͿĂƌĞŝŶ ¾ EƵŵĞƌŝĐĂůDŽĚĞůůŝŶŐͲ& &ŝŶŝƚĞůĞŵĞŶƚŶĂůLJƐŝƐ
ĞƐƚĂďůŝƐŚĞĚ ŝŶ ^ĞƉƚĞŵďĞƌ ϮϮϬϭϱ͕ ĚƌĂǁƐ ŝƚƐ ĐĂƉĂďŝůŝƚLJ ĨƌŽŵ ŝƚƐƐ ƉůĂĐĞƚŽĞŶƐƵƌĞƋƵĂůŝƚĂƚŝǀĞ͕ĐŽŶƐŝƐƚĞŶƚΘƌĞůŝĂďůĞƌĞƐƵůƚƐĨƌŽŵ ¾ ĞƐŝŐŶŽĨĞĞƉĂŶĚ^ŚĂ ĂůůŽǁ&ŽƵŶĚĂƚŝŽŶƐ
ůĞĂĚĞƌƐŚŝƉǁŚĞƌĞŐĞŽƚĞĐŚŶŝĐĂůĞdžƉĞƌŝĞŶĐĞĂĐĐƵŵƵůĂƚĞĚďLJŝƚƐ ĨŝĞůĚƐƚĂĨĨΘƚŚĞŝƌƐĂĨĞƚLJ͘ ¾ ĞƐŝŐŶŽĨĂƌƚŚĂŵƐ͕d dĂŝůŝŶŐƐĂŵƐĂŶĚĂŶĂůƐ
ĨŽƵƌĚŝƌĞĐƚŽƌƐŝƐƐŽŵĞϴϲLJĞĂƌƐ͘dŚĞĨŝƌŵĐƵƌƌĞŶƚůLJŚĂƐŽĨĨŝĐĞƐƐ ¾ ĞƐŝŐŶŽĨƵƚͲKĨĨtĂůůƐ ĂŶĚŝĂƉŚƌĂŐŵtĂůůƐ
ŝŶƵƌďĂŶĂŶĚĂƐƚ>ŽŶĚŽŶǁ ǁŝƚŚƐĂƚĞůůŝƚĞŽĨĨŝĐĞƐŝŶĂƉĞdŽǁŶ D^: ŚĂƐ Ă ǁŝĚĞ ƌĂŶŐĞ ŽĨ ĚĞƐŝŐŶ ĞdžƉĞƌŝĞŶĐĞ ƚŚĂƚ ŐŽĞƐ ĨƌŽŵ ¾ WŝƉĞ:ĂĐŬĞƐŝŐŶĂŶĚ^Ɖ ƉĞĐŝĨŝĐĂƚŝŽŶ
ĂŶĚ WŽƌƚ ůŝnjĂďĞƚŚ͘ ĐŽŵďŝŶĂƚŝŽŶ ŽĨ ƉƌŽĨĞƐƐŝŽŶĂů ƚƌĂĚŝƚŝŽŶĂůƐŽůƵƚŝŽŶƐƚŽƚŚĞŵŽƌĞƌĞĐĞŶƚĂƉƉƌŽĂĐŚĞƐŝŶŐƌŽƵŶĚ ¾ dƵŶŶĞůZŽĐŬŵĂƐƐŚĂƌĂ ĂĐƚĞƌŝnjĂƚŝŽŶΘ^ƵƉƉŽƌƚĞƐŝŐŶ
ŐĞŽƚĞĐŚŶŝĐĂůĞŶŐŝŶĞĞƌƐĂŶĚ ĞŶŐŝŶĞĞƌŝŶŐŐĞŽůŽŐŝƐƚƐǁŝƚŚŝŶƚŚĞ ŝŵƉƌŽǀĞŵĞŶƚƐ͕ŐĞŽƐLJŶƚŚĞƚŝĐƐƌƌĞŝŶĨŽƌĐĞĚĞĂƌƚŚƐƚƌƵĐƚƵƌĞƐĂŶĚ WŝůŝŶŐĂŶĚŐƌŽƵŶĚŝŵƉƌŽǀĞŵĞŶƚ
¾ ĂƌƚŚǁŽƌŬƐDĂŶĂŐĞŵĞŶƚĂŶĚYƵĂůŝƚLJƐƐƵƌĂŶĐĞŽŶƚƌŽů
ƉƌĂĐƚŝĐĞ ƉƌŽǀŝĚĞƐ Ă ƐƉĞĐŝĂĂů ďůĞŶĚ ŽĨ ƐŬŝůůƐ͕ ŵĂƚĐŚĞĚ ǁŝƚŚ ƉŝůŝŶŐ͘LJƚŚĞƵƐĞŽĨĨĂŵŽƵƐƐŽŽĨƚǁĂƌĞƉĂĐŬĂŐĞƐƐƵĐŚĂƐWůĂdžŝƐ͕ ¾ 'ĞŽƐLJŶƚŚĞƚŝĐĞƐŝŐŶƐ
ƉƌĂĐƚŝĐĂůĂƉƉůŝĐĂƚŝŽŶĂŶĚĚĞĚ D^:ĐĂŶĂůƐŽŵŽĚĞůĐŽŵƉůĞdž ƉƌŽũĞĐƚƐ
Ɖ ĂŶĚ ƉƌŽǀŝĚĞ ƐĞŶƐŝƚŝǀŝƚLJ ¾ /ŶƐƚƌƵŵĞŶƚĂƚŝŽŶĂŶĚDŽŶŝƚŽƌŝŶŐ
ĚŝĐĂƚŝŽŶ͘
¾ WŝůĞ/ŶƚĞŐƌŝƚLJdĞƐƚŝŶŐ͕WůůĂƚĞ>ŽĂĚdĞƐƚŝŶŐ͕ZĞƐŝƐƚŝǀŝƚLJdĞƐƚŝŶŐ
ĂŶĂůLJƐŝƐĂŶĚƉƌĞĚŝĐƚƐŚŽƌƚĂŶĚ ůŽŶŐƚĞƌŵĚĞĨŽƌŵĂƚŝŽŶƐŽĨŽƵƌ
¾ >ĂƚĞƌĂů^ƵƉƉŽƌƚĞƐŝŐŶ
ŐĞŽͲĞŶŐŝŶĞĞƌŝŶŐƐƚƌƵĐƚƵƌĞƐ͘
^ƚĂŶĚĂƌĚƐ ĂŶĚ WƌŽƚŽĐŽůƐ ĨŽƌ 'ĞŽƚĞĐŚŶŝĐĂů ^ŝƚĞ ŝŶǀĞƐƚŝŐĂƚŝŽŶƐƐ ¾ ŽŶƚƌĂĐƚŽƌDĂŶĂŐĞŵĞŶ Ŷƚ
ĂƐďĂƐĞĚŽŶĐƵƌƌĞŶƚƐƚĂŶĚĂƌƌĚƐĂŶĚĐŽĚĞƐƐƵƉƉŽƌƚĞĚďLJ^ŽƵƚŚ ¾ dĞƌƌĂŝŶǀĂůƵĂƚŝŽŶ
ĨƌŝĐĂŶ/ŶƐƚŝƚƵƚŝŽŶƐŽĨŶŐŝŶĞĞĞƌŝŶŐ ¾ ^ůŽƉĞ^ƚĂďŝůŝƚLJƐƐĞƐƐŵĞ ĞŶƚƐ
The striations (slickensides) A high-precision three-dimensional soft or weak ground. The CSW test posi-
(3D) survey was undertaken of several tions were situated in locations where the
observed at particle level structures in the area to determine the perceived slip plane associated with the
demonstrate that the upper magnitude and direction of movement. landslip was assumed to be close to the
Due to time constraints, the installation existing ground surface.
Kirkwood (composed of 88% to of geotechnical instrumentation was not A 2D model of the slope was then
92% clay/silt) has been sheared possible. Following the high-precision generated using computer software, and a
survey results, it became evident that slope stability analysis was undertaken to
along distinct failure planes. such instrumentation (inclinometers, assess conceptual failure mechanisms.
etc) would probably have been damaged
in a relatively short period of time by the PROBLEMS ENCOUNTERED
extent of the movement measured. AND INNOVATIONS
Continuous Surface Wave (CSW) tests It became evident during the core drilling
were also employed to assess the ground operations that the ground was moving
stiff ness profi le and help identify zones of continuously, and it resulted in the
contractor drilling through his lower steel
casing on quite a few occasions due to the
ground movement below. The boreholes
essentially became crude inclinometers,
information which was later used to
model the slope stability and determine
the depth of the problem. The extent
of the ground movement is shown in
Figures 6 and 7.
The presence of abundant gravel
(pebbles) resulted in poor recovery during
drilling operations and an inadequate as-
sessment of the shear strength properties
associated with the landslip. Good core
recovery was, however, obtained in the
Kirkwood clays, and one of the failure
planes was recovered in the core. Th is
allowed for more accurate sampling for
shear strength tests.
10 μm 1 Probe = 250 pA Signal A = SE2 Contrast = 29.9%
Mag = 1.00 KX EHT = 5.00 kV Brightness = 50.2% RESULTS OF THE INVESTIGATIONS
WD = 3.0 mm Column Mode = High Resolution 7 December 2016 The geological model that was con-
structed from the drilling data indicates a
sloping palaeo-channel in the Kirkwood
clay, which is now fi lled with Buffelskloof
Formation conglomerate. Seepage of
groundwater was also noted where the
palaeo-channel daylights on the sloping
embankment between the upper and
lower residential developments.
The CSW test results, presented in
Figure 8, clearly indicate that the upper
Kirkwood Formation was of a very low
stiff ness (soft consistency).
The upper Kirkwood Formation was
identified as the zone in which the land-
slip is occurring. Consolidated, undrained
shear strength test results demonstrated
very low cohesion and friction angles
that varied between 10° and 21°. Some
10 μm 1 Probe = 250 pA Signal A = SE2 Contrast = 29.9% interesting information and discussions
Mag = 1.00 KX EHT = 5.00 kV Brightness = 50.4%
WD = 2.9 mm Column Mode = High Resolution 7 December 2016 were noted on several occasions by
experienced laboratory testing staff who
Figure 9: Microscopic view of soil fabric showing striated, slickensided performed the shear strength testing.
orientation (general direction shown by red lines)
Further microscopic assessment was
Unit
Material name Color weight Strength Cohesion Phi Water Hu Ru
(kN/m3 ) type (kPa) (deg) surface type
6.00 kN/m2
28.00 kN/m2
w
35 0.62 Lower Estate
20.00 kN/m2 28.00 kN/m2
2.50 kN/m 2 w
performed by SCI-BA Laboratories and in the upper part of the Kirkwood problems that could be encountered in
Scientific Consultants on undisturbed Formation which underlies two built- future development of this area. As has
upper Kirkwood material, and a few up residential estates in Mossel Bay, been noted in previous civil engineering
interesting characteristics were observed resulting in severe structural distress articles, geotechnical investigations are
(see Figure 9). to approximately 45 houses. Significant often overlooked or tend to be heavily
The striations (slickensides) observed damage to municipal services has also constrained by time and costs, rather
at particle level demonstrate that the been reported. The cost of this natural than ensuring a thorough understanding
upper Kirkwood (composed of 88% to disaster is estimated to be in the millions of the ground conditions and potential
92% clay/silt) has been sheared along of rands, and has had a major social im- risks that may impact a development.
distinct failure planes. Depending on the pact on the area. The ground movement The local and national civil engineering
degree of surface water ingress and pene- is on-going and the affected area has fraternity need to take into account the
tration into the Kirkwood, the disturbed not been fi rmly delineated. At the time potential consequences of geotechnical
mass is expected to continue moving. this article was written, a conceptual uncertainty, as the social impact to the
Furthermore, it is interesting to note solution has been proposed and is being public we serve may be far-reaching,
that the landslip movement is tending to considered by the authorities. Certainly, with disastrous long-term effects.
reflect the monthly rainfall patterns in the cost of any solution will be extremely
the Mossel Bay area. expensive, and unless sufficient funding
PROJECT TEAM
Analysis of potential failure planes, can be acquired, the future of the area
using 2D slope modelling, indicates very remains uncertain. Mossel Bay
Client
low factors of safety along semi-circular Questions that need to be asked Municipality
planes in the upper 10 m of the Kirkwood include whether this disaster could have
clay. Potential failure planes extend been predicted – a question that does not Kantey & Templer
from the upper complex/estate, where have a simple answer. Certain elements of (Pty) Ltd
tension cracks are visible, to the lower the problem, such as poor soil conditions, Consultants
comlex/estate, where a classical bulging groundwater seepage and steep slopes, Outeniqua
Geotechnical Services
toe of the embankment is observed. definitely point towards a potential slope
The conceptual slope model is shown in failure, albeit with 20/20 hindsight vision, Geotechnical
Geopractica
Figure 10. but preventing development under these drilling
Contracting (Pty) Ltd
contractor
conditions would preclude large parts of
CONCLUSION the Southern Cape. Unlimited – people’s
Th is investigation has established that Th is case study should, however, serve Project value lives have been
changed forever
a significant slope failure is occurring as a reminder of potential geotechnical
Project Management
CPT (Starting April)
JHB (Starting July)
-BF>ÁͱMLÁͱ?ÁLA>Á(˕ÁÁ<>ÁͮÁ=:QKÁͱGEQ
For middle to senior managers who
need to launch or manage projects.
Project Management
Principles and Practices
CPT (Starting May)
DBN (Starting September)
JHB (Starting July)
KIM (Starting October)
QTN (Starting June)
UTN (Starting September)
-BF>ÁͱMLÁͱ?ÁLA>Áͱ˕ÁÁ<>ÁͭÁ=:QKÁͱGEQ
For middle to senior managers managing
projects and requiring increased technical skills.
Western Cape, Gauteng, KwaZulu-Natal, Dar Es Salaam, Addis Ababa, Rest of Africa
South Africa South Africa South Africa Tanzania Ethiopia
t: +27 (0)11 460 6980
USBED20173E
t: +27 (0)21 918 4488 t: +27 (0)11 460 6980 t: +27 (0)31 535 7117 e: tanzania@usb-ed.com e: ethiopia@usb-ed.com e: africa@usb-ed.com
e: info@usb-ed.com e: info@usb-ed.com e: info@usb-ed.com
GRLWEAP Predicts:
• Driving stresses
• Hammer performance
• Relation between pile bearing
capacity and net set per blow
• Total driving time
Available in standard
DQGRႇVKRUHYHUVLRQV
info@pile.com | www.pile.com
100
90
80
Percentage finer by weight
70
60
50
40
30
20
10
0
0.001 0.01 0.1 1 10 100 1 000
Particle size (mm)
CLAY FINE MEDIUM COARSE FINE MEDIUM COARSE FINE MEDIUM COARSE
COBBLES BOULDERS
FRACTION SILT FRACTION SAND FRACTION GRAVEL FRACTION
Figure 1: Graphical display of the grading limits for the rockfill material
should water enter the fi ll (“poorly σ3 = confining pressure in the fi ll parameter for deeper-seated failures. A
graded” material). bulk rockfi ll density of 2 150 kg/m³ was
A graphical display of the grading enve- From several laboratory test results on used.
lopes for the rockfi ll material is shown in materials from various dams the typical However, where c = 0 kPa in slope
Figure 1. φ 0 and Δφ ranges can be determined as stability analysis, shallow slope failures
summarised in Table 1. with low factors of safety are the most
Rockfill embankment slope stability critical, as was the case for the bench
Detailed analyses were performed using Table 1: Typical φ 0 and Δφ material ranges slopes selected. In this case the confining
the US Corps of Engineers’ approach for based on laboratory tests pressures were much lower, and for the
dams, which defines 1.5 as an allowable rockfi ll φ varied between 47° and 52°
Relative
FOS for embankment slope analysis. Material density φ0 Δφ (44° and 48° for gravel). It was therefore
Without the availability of conclusive (%) (°) (°) proposed that φ = 46° to φ = 49° should be
laboratory tests at the initial stages of the used in the analysis, which was consistent
100 55 10
project to guide the selection of shear Rockfill with the values and ranges as recorded in
50 45 8
strength parameters to use in the slope Table 1.
stability analysis, empirical methods were 100 51 8 The finally proposed rockfi ll embank-
Gravel
50 41 3
used to derive acceptable shear strength ment slope geometry was as follows:
parameters. Research has shown that ■ Benches 10 m high at a slope of 1:1.36
the following relationship can be used to In the case of high internal confi ning with a 4 m wide horizontal surface
determine the shear strength parameter pressures (say fi ll heights > 50 m) it between benches, which equates to an
φ (with c = 0 kPa) for rockfi ll, gravel and can be shown that φ may vary between average (relative) slope of 1:1.76.
sand: 41° and 45° for rockfi ll at between 50% ■ Maximum embankment height 110 m.
and 100% relative density, while the The shear strength parameters of the
σ3 corresponding values for gravel may excavated material were re-tested
φ = φ 0 – Δφlog
1 atmosphere vary between 40° and 43°. Normally the once exposed in the initial stages of
compaction of rockfi lls should be at least the excavations to verify the above-
Where: between 75% and 80% of the bulk relative mentioned analysis. The following tests
φ = the friction angle density. The composition of the rockfi ll and observations were conducted on the
φ 0 = the friction angle at 1 atmosphere that was used to construct the dry gut initial trial embankment procedure (and
pressure (101.3 kPa) embankment contained a substantial were repeated for any change in mate-
Δφ = the correction for confining pres- gravel content, hence φ = 42° was pro- rial composition) to verify the material
sure variation posed as an acceptable shear strength characteristics and performance (initially
CONSTRUCTION CHALLENGES
The biggest challenge in constructing
the St Helena Airport was creating and
maintaining an efficient planning and
logistics chain. There were no major
construction plant or building materials
on the island, and virtually everything
had to be shipped to the island. The con-
tractor chartered a 2 500 ton ocean-going
vessel for the duration of the contract to
accommodate their plant and materials
supply requirements. With no harbour
on the island, a temporary jetty had to be
constructed to accommodate roll-on-roll-
off facilities. Other early works establish-
ments consisted of a temporary fuel
facility (1.5 million litres), construction
of a 14.5 km haul road over very harsh
rocky and steep terrain, borehole explora-
tions to source adequate groundwater
for construction water, construction of
staff accommodation and workshops,
the establishment of a fully equipped
internationally accredited laboratory, and
the erection of crushing and concrete
batching plants.
Risk awareness during project
execution was absolutely crucial for
the success of the project, and both the
St Helena government and the project
team ran and shared a comprehensive
risk and opportunity register. Th is was
vital to identify and mitigate any risks
to the health and safety of personnel,
and to protect the special features of the
island prior to the commencement of
any sector of the works. Th is approach
was instrumental to the ultimate goal of
successfully completing the contract on
A haul road of 14.5 km had to be constructed over very harsh, rocky and steep terrain
time and within budget (construction
works for the airport infrastructure
source materials, a sensitivity analysis was completed in April 2016, and an
was computed. Aerodrome Certification was issued by
Fixing the final vertical Fixing the final vertical alignment ASSI on 10 May 2016).
of the runway was vital, considering
alignment of the runway was the lead time required in setting up the
PROJECT TEAM
procedures for the necessary flight path
vital, considering the lead
sensitivity analysis and the follow-on re- Department of
time required in setting up the quirements with early submissions to the Client International Development,
UK Government
Aviation Regulator for final approvals. As
procedures for the necessary such any later adjustment to the runway
Main
flight path sensitivity analysis and alignment would have had serious time-
Contractor
Basil Read (Pty) Ltd
delay consequences for the construction
the follow-on requirements with programme.
The earthworks volume-sensitivity
early submissions to the Aviation Contract Design Build Operate
analysis clearly showed that the slightest
Regulator for final approvals. variation in the material performance
OPEN
INVITATION
Keep up to date with the latest technical and regulatory information
on geosynthetics and earn CPD Points.
t &BDIMFDUVSFJTJOoNJOVUFTFHNFOUT
t $1%QPJOUTQFSMFDUVSF
t "DDSFEJUFECZ4"*$&
octarine 3961
Accredited CPD
Any time, any place!
www.kaytech.co.za
Photo 1: The presence of a waterfall is typically the most prominent indication that there are possibilities for small hydropower development
SITE DESCRIPTION
The immediate section of the N3 where
the sink hole occurred is located on a
fi ll embankment constructed on the
lower slopes of the Townhill escarpment
approximately 1 km north of the Peter
Figure 1: Town Hill pipe jack site location
Brown Bridge. Two drainage lines off the
elevated north-eastern escarpment flank
converge slightly downslope of this road
section and were piped through the fill
embankment when it was constructed.
Sealed ARMCO pipes
The outlet from the pipes flow into
the Town Bush stream, a tributary of the
Outlet
New inlet Msunduze River. Continuous seepage,
Jacking pit likely to be gravity-fed by springs
New 900Ø pipe
from the upper Townhill slopes, was
New outlet / inlet New 1473Ø evident down the drainage line, which
concrete pipe
increased substantially during the wetter
summer months.
N3SB
EMERGENCY WORKS
Given the poor condition of the Armco
pipe, and to prevent the likelihood of fur-
ther sinkhole development, it was decided
Figure 3: Existing Armco pipe collapsed and damaged
to carry out temporary emergency works
until the more permanent pipe jack solu-
and shale. A thick mantle of massive reddish brown silty clay or clayey silt. tion could be implemented.
unsorted slump and talus material over- Fragments of deeply weathered, very soft To stabilise the collapsed section of
lies the bedrock in this area. The slump (broke in the hand) shale were randomly the pipe and cavities identified during
comprises silts and clays with variable found in the holes. the camera survey, probes were drilled
hard rock dolerite core stones (0.5 m to around the pipe from the surface with an
2.0 m) in the finer material matrix. The CAMERA SURVEY auger capable of drilling down through
material used in the construction of the Drawings provided by SANRAL sug- the stiff clayey horizon to a depth of 10
fi ll embankment comprised predomi- gested that two 900 mm Armco pipes m, and simultaneously pressure grouting
nantly slump and talus taken from the N3 originated approximately 75 m apart closed any voids that existed around
cuttings further up the road. According to within the reserve of the northbound the collapsed pipe. Th is was done to
SANRAL (South African National Roads carriageway and converged to discharge prevent the cavities from reflecting
Agency Limited), some ‘foreign’ material across the N3 downslope of the south- through to the surface and manifesting
could also be expected in the valley lines. bound carriageway embankment. as sink holes.
Three auger holes, excavated on either As part of the investigation, a The operation had mixed success in
side of the N3 motorway and one in the camera survey was commissioned. The that the collapsed section of pipe beneath
median, revealed soft to moderately stiff, pipes were surveyed with the aid of a the sinkhole was sealed, but elsewhere
ON
CLAY
CONSTRUCT
ON
SAND
with
BubbleLock™
Interlocking
Blocks
cast in situ
Hyson Cells BubbleLock
is sacrificial plastic
formwork used to cast
interlocking, flexible /
quasi-rigid concrete
block paving and liners in
situ with the formwork
remaining embedded in
the structure as perfectly
fitting jointing.
PowerPoints
and video clips
HYSON CELLS®
Tel +27 (0) 11 957 2478
Skype shadrack.hyson
www.hysoncells.co.za
ParaDrain®
P araDrain®
Years
Geotechnical works in progress on the Kranspoort Pass (November 2016)
Geotechnical engineering
through the Kranspoort Pass
Mpumalanga. At the time, the steep 5 km PROJECT DESCRIPTION
Donovan Hugo Pr Eng
Director Kranspoort Pass, which is located within The safety improvements to the
HHO Africa this section of road, comprised a single Kranspoort Pass included widening to
don@hho.co.za descending lane and a single ascending accommodate two lanes in each direction,
lane, with limited climbing lanes. Sight dis- geometric improvements, the installation
tance and emergency stopping measures of concrete barriers and the provision of
were also a concern, particularly with the two arrestor beds.
Bruce Barratt Pr Sci Nat
Engineering Geologist increased use of the pass by heavy vehicles,
HHO Africa and accidents were a regular occurrence GEOTECHNICAL INVESTIGATIONS
bruce@hho.co.za on the pass. Safety improvements were Following initial visual inspections, which
therefore a key aspect of the project. included limited joint measurements and
This article summarises the geotech- assessment, a geotechnical investigation
INTRODUCTION nical investigations and design that were was conducted. This comprised drilling of
HHO Africa were appointed in 2011 by carried out at the Kranspoort Pass, and rotary core boreholes along the proposed
the South African National Roads Agency highlights some of the challenges that cut widenings. A total of twenty-one
Limited (SANRAL) to carry out designs for were revealed during construction and boreholes were drilled, with many of the
the upgrade of National Route 11 Section how these were addressed to ensure a safe setups proving to be very challenging
10 between Middelburg and Loskopdam, journey through the pass. on the steep terrain. The purpose of the
MATERIALS ASSESSMENT
Based on the findings of the laboratory
testing of rock cores, material quali-
ties could be attributed to the various
proposed cut widenings, with recom-
mendations for re-use as either fi ll, sub-
base, selected subgrade or base course
material. Furthermore, assessment of
excavatability could be made, with most
of the cuts in quartzitic sandstone being
classified as extremely hard ripping and
requiring blasting.
GEOTECHNICAL DESIGN
Geotechnical design of the cut widenings
Construction of soil nail tie-back gabion wall (February 2016)
essentially involved the installation
Learn more:
www.geobrugg.com/debrisflow
FOR AN ECONOMICAL
SOLUTION TO DEBRIS FLOW
Geobrugg Southern Africa (Pty) Ltd | Unit 3 Block B Honeydew Business Park | 1503 Citrus Street | Honeydew 2170 | South Africa | T +27 11 794 3248 | info@geobrugg.com | www.geobrugg.com
Wall 3 Versfeld Pass, Piketberg
Patrick Beales Pr Eng The recent upgrading of this pass, originally built by a local farmer
Senior Geotechnical Engineer
Kantey & Templer Consulting Engineers with 16 labourers in just three months, has added a further chapter
pbeales@ct.kanteys.co.za
to its more than 70-year old history.
Fall
0.75 m
2% Fall
1.5 m
1.0
2% Fall
m
5 .0
2.0
m
m
Tecco G5/3
steel mesh
200 × 200 × 10 mm
Ex
galvanised steel
ist
used, due to the variable soil/bedrock, a extended through the Reinforced Earth It was evident at the start of the works
TerraLink® system was decided on. In this embankment and fi xed on the outside of at Wall 3 that erosion below the toe of
case the Reinforced Earth structure was the steel TerraTrel panels by means of a the new Reinforced Earth system could
not used as the primary earth retaining 200×200 head plate and nut. By nominally potentially lead to localised slope failures
system, but was rather used to connect tensioning the rock bolts, the TerraTrel below the wall, so an erosion protection
the facing elements to the primary became an extension of the 200×200 head and stabilising mesh from Geobrugg was
soil reinforcements to create a vertical plate, thereby providing further lateral installed below the new Reinforced Earth
facing and widen the road shoulder. The stabilisation and reducing the TerraTrel wall system. Due to the current drought
TerraTrel facing was connected to the deformation. conditions in the Western Cape, it was
back face with a Geostrap®. Founding conditions on steep slopes decided to delay the revegetation of the
will always have inherent issues to lower slope.
CONSTRUCTION CHALLENGES overcome and, although the bearing
The variable and localised nature and ori- pressures were relatively low, the founding CONCLUSION
entation of hard rock outcrops necessitated conditions on the slope varied from loose The importance of retaining the geotech-
the need to implement steel strips and soils to solid rock, which would certainly nical engineer during construction phases
Geostraps to ensure the internal stability have led to differential settlement along is an effective method of managing the
of the Reinforced Earth system. the front face (TerraTrel panels). In order subsurface risks. This is even more evident
It was a concern during construction to create a uniform and stable foundation in the ‘design and construct’ contract where
that the steel TerraTrel panels were prone for the system, vertical rock bolts were contractual risk shedding does not indem-
to slight lateral deformation, which could installed 1 m into the rock to exploit the nify the project from geotechnical issues or
have led to vertical settlement of the enhanced end-bearing characteristics reduce the geotechnical uncertainty.
road layerworks and deformation to the as ‘mini-piles’. These ‘mini-piles’ were This project demonstrated that a de-
surfacing. Rock bolts (25 mm and 32 mm fi xed to a continuous reinforced beam, so sign team in regular communication with
diameter galvanised bolts), used for tem- that the system could be perceived as a one another can manage the geotechnical
porary stability during excavation, were continuous piled beam raft. risk and deliver a successful project.
John Versfeld and his 16 labourers
would probably agree that the latest works
in this pass have contributed another
chapter to its history.
PROJECT TEAM
Western Cape
Government:
Client Department of
Transport and Public
Works
Figure 6: Aerial view of completed road widening embankment; note that the revegetation of the Project value
R8.4 million
slope below Wall 3 still has to be undertaken (Photo: Paul Fairbrother) (Wall 3 only)
2016 saw Fairbrother Geotechnical Engineering achieve significant growth in the geotechnical and piling indus-
try and, in particular, the private development market in Cape Town. Offering client-driven design and construct
solutions, Fairbrother has been at the forefront of some of Cape Town’s largest private developments.
PRIVATE PROJECT IN FOCUS
Bantry Hills Apartments – successfully completed turnkey solu-
tion which included 24 000m3 of bulk excavations, 10m deep
basements with 1650m2 of lateral support and 200 1800kN
foundation piles.
www.recosa.co.za
The problem with MSE walls –
a case study in support of integrated
geotechnical engineering design
INTRODUCTION Developments and the eThekwini Metro
Mechanically Stabilised Earth (MSE) Municipality, and has been adopted by the
Frans van der Merwe Pr Eng
walls have a growing application in place Cabinet as a national priority project. Geotechnical Engineer
of conventional retaining systems for The dual bridges, each 88.5 m in SMEC South Africa
varying reasons, most notably economy length, comprise four spans with slanted frans.vandermerwe@smec.com
and constructability. However, there have piers and an integral deck consisting of
recently been a number of failures or pre-tensioned beams. The abutments to
instances of poor performance of these the bridges are also slanted and include
Charles Warren-Codrington
systems throughout the southern African some 200 m of MSE wall (MSEW) ap- Geotechnical Engineer
region. An evaluation of these indicates proach fi lls. The site is situated in an allu- SMEC South Africa
that there are two fundamental causes vial plain, with the western portion of the charles.warren-codrington@smec.com
for poor performance. The first relates site previously cultivated as a watercress
to the nature in which MSE structures farm, while the eastern portion was used
are planned, designed and constructed. as a dump site for sludge from a nearby
Fernando Pequenino Pr Eng
The second relates to the need for the wastewater works. Principal Geotechnical Engineer
geotechnical designer to develop a clear The site offered poor founding condi- GaGE Consulting Geotechnical Engineers
understanding of the subsurface condi- tions for the MSEW and bridge struc- fernando@gageconsulting.co.za
tions, together with a need for routine tures, with over 120 mm of settlement
verifications of the ground conditions,
design, construction and materials during
the process of construction. This article
presents a case study of the planning, de-
sign and construction of an MSE wall, in
this case a Reinforced Earth® wall, which
was successfully constructed over a poor
subgrade in Durban. In the context of the
preceding discussion, the case for inte-
grated design by geotechnical engineers
is made, given the uncertainties with the
“design and build” procurement model
which is typically used for the supply of
MSE systems.
www.theconcreteinstitute.org.za
+27 11 315 0300
Vertical
displacement
(m)
–0.08
–0.07
–0.07
–0.06
–0.06
–0.06
–0.05
–0.05
–0.04
–0.04
–0.04
–0.03
–0.03
–0.02
–0.02
–0.02
–0.01
–0.01
–0.00
0.00
0.00
Figure 1: Staged finite element analysis – the analyses corresponded well to the surveyed
settlements measured on targets placed on the MSEW panels
■ Development of tender and design Initial detailed design where the one ignores the subgrade
specifications, appropriately consid- An initial detailed design was undertaken provided between stone columns and the
ering the various design constraints; using typical and varying parameters for other incorporates the subgrade.
■ Finalisation of design and design the MSE structure to account for different The MSEW consisted of a tiered
interfaces, with consideration of the systems which could potentially be used. walkway system with specially made
final selected MSE system (by winning This required the selection of a number of panels, 3 m wide and 1.5 m high, according
tenderer, Reinforced Earth), including performance criteria against which various to the architectural requirements. The
peer review of respective designs; and MSE technologies could be evaluated, and settlement performance was modelled
■ Implementation of an appropriate a cost benefit and optimisation exercise. in finite element software to establish
quality assurance, testing, construc- This optimisation duly considered various the improvement that could be expected
tion and performance monitoring influencing elements – such as ground in the overall behaviour of the system
regime. This included an appropriate improvement on overall stability and whilst using a dynamic replacement
level of construction supervision by the settlement, and the availability and selec- stone column foundation with a granular
geotechnical designer and the supplier. tion of fill material on internal stability. platform. The offset between the two
The above steps are expanded upon fur- Due to the poor founding soil stiff- tiers implied that the top and lower tiers
ther below in the context of the project. ness values, associated low bearing would influence each other. The maximum
capacity and expected high settlements, tension line would, however, be at a flatter
Geotechnical investigation ground improvement measures were angle when compared to a non-tiered
A comprehensive investigation was con- implemented for the foundations of the system, and therefore strip lengths need
ducted, appropriate to the geotechnical MSEW. This ground improvement was to be reviewed for pull-out, differently to
conditions and structure proposed, achieved by means of dynamic replace- methods used for a non-tiered system.
and adhering to the SAICE Code. ment with the rapid impact compaction Without any soil improvement, some
Investigations were undertaken by ARQ (RIC) method. The RIC specially adapted 120 mm of settlement was expected
Consulting and comprised several rotary machine uses a 9 ton weight from a drop due to the fi ll placement. The dynamic
core boreholes to depths of up to 17 m, height of 1.5 m. replacement stone columns and G6
in-situ testing (SPT and DPSH) and labo- The stone column raft was capped platform were shown to improve the
ratory testing on soils and rock. with a load transfer platform, consisting settlement behaviour in a staged finite
The DPSH tests showed very little of a high-strength bi-directional geo- element analysis to some 50 mm, while
resistance through the alluvial mate- textile, and a granular raft consisting the estimated self-weight settlement was
rials, with the probe progressing some a G6 material. The platform was estimated to be negligible at some 12 mm.
200 mm per blow in some instances. reviewed in accordance to methods
The SPT results, using cautious estimate described in SANS 207:2006 and the Tender and design specifications
SPT-N blow count, was in the order Recommendations for Design and Considering the design limitations,
of 8 over the top 5 m, and SPT-N blow Analysis of Earth Structures using development of a specification for the
count of 13 from 5 to 10 m. Mudstone Geosynthethics Reinforcements (EBGEO). supply and internal design of the system,
and dolerite were encountered at depths The two methods differ in the way the with due consideration of the SANS
exceeding 10 m. soils between stone columns are analysed, 10160 and SANS 207 requirements, was
Finalisation of design 10
Although performance criteria were set EPDM, t = 25 mm
Neely & Tan (2010)
at tender stage, these governed the range
5 EPDM, t = 20 mm
of several design parameters important to Choufani et al (2011)
the design. The finalisation of the design
was dependent on having discrete design 0
values, which were only known once the 0 10 20 30 40 50 60 70
final MSE system was selected (i.e. suc- Vertical strain (%)
cessful tender is known).
This stage also included peer review Figure 2: Compression behaviour of HDPE and EPDM
bearing pad materials (Damiens et al 2013)
and collaboration on the design with the
suppliers on their internal stability de-
signs and compliance with specification. Although performance criteria were set at tender stage,
Similarly the supplier was able to review
these governed the range of several design parameters important
the owner’s external stability designs.
This ensured that design assumptions to the design.
Civil Engineering April 2017 51
basis, thus absolving the owner and/or
consultant of any responsibility, is not
correct. Notwithstanding the fact that
the contractual mechanisms enabling a
design-and-build approach are seldom
put into place, there are highly complex
interactions between internal and
external design factors, and between the
soils and structural members making up
the MSE system. If failure occurs, the
responsibility will invariably need to be
shared, as it will always be difficult to
identify a single causational factor which
led to the failure.
Bearing pads placed on vertical Furthermore, the recent trend by
joints between panels owners and consultants of providing
contractors with limited or inappropriate
investigation, design specifications and
and interfaces were understood. One Quality assurance parameters, and performance criteria, un-
such example was the internal or The final and most important stage of a fairly jeopardises the entire industry. It is
inter-panel settlement: fully integrated geotechnical design is a clear dereliction of design responsibility.
As settlements were very much driving the implementation of an appropriate Whilst it is understood that both
external design and performance criteria, quality assurance, testing, construction COLTO and SANS 207 are currently
it was important that this was com- and performance monitoring regime. under review, limitations to these will
municated and considered in the internal This must include an appropriate level of remain. The requirement for adequate
design, and in particular the concrete construction supervision and oversight by ground information and an integrated
panel façade and the larger-than-normal the geotechnical designer. approach to the geotechnical engineering
panels used. Bearing pads are utilised to For the ground improvement, quality design of MSE represents best practice
absorb internal (as a result of settlement of assurance was undertaken by reviewing and reduces the risk for all project par-
the fill) and some external settlement (as a the continuous number of blows versus ticipants. Likewise, the introduction of
result of foundation settlement). These are penetration plots, plate load tests, DPSH new and conflicting technologies implies
placed in horizontal joints of discrete pre- and continuous surface wave (CSW) more involvement of geotechnical design
cast concrete panels in order to allow the testing, which all provided verification engineers in defining the problem and
panel and the reinforcement to move down of the subsoil conditions and the perfor- levelling the playing field, not less.
with the reinforced fill as it is placed, and mance of the ground improvement. This
settles. This mitigates downdrag stress and was in addition to standard quality assur- ACKNOWLEDGEMENTS
provides flexibility to the façade to account ance and testing of the concrete, backfi ll, The authors would like to thank Tongaat
for differential foundation settlements. layerworks, materials supplied, survey, Hulett Developments and the eThekwini
SANS 207:2006 states that for discrete line and levels. Metropolitan Municipality for their
panels the vertical movement capacity of Settlement was monitored on panels kind permission to publish this article.
the system should be a minimum of 1 in and in the roadway, and limits set which The contribution of Mr Alan Parrock
150 relative to the panel height. governed the timing for placement of final of ARQ Specialist Engineers is also
Ethylene propylene diene monomer road layer works and ancillary features. acknowledged.
(EPDM) bearing pads of 25 mm were placed
in the joints between the discrete panels at CONCLUSION REFERENCES
a spacing of 0.75 m. The expected stress- It is essential that professionals charged A full list of references can be provided by
strain relationship is provided in Figure 2 with the responsibility of planning, de- the authors on request.
for three different types of bearing pads. signing and implementing MSE retaining
The foundation and internal settle- systems understand the application,
PROJECT DATA
ments, panel rotation and weight of the limitations and costs associated with such
panels were all modelled in geotechnical technologies, which are ever developing Co-funded by eThekwini
Municipality (60%)
finite element software to analyse the and advancing. This responsibility is Client
and Tongaat Hulett
number of bearing pads required on often exacerbated by difficult subsurface Developments (40%)
the vertical joints between panels. conditions, restricted right-of-way and
Consultant SMEC South Africa
Additionally, the loads in the steel strips marginal sites with challenging topo-
were reviewed to compare them to the graphy, variable climatic conditions and Fountain Civil
Engineering (FCE), with
capacities they have been designed for and other environmental constraints. Contractor
Reinforced Earth as
to establish if additional or higher loads The notion that in projects where MSE supplier
are attracted to the strip at the facing- public money is involved these systems
Project value R145 million
strip interface (Tconn). are procured on a design-and-build
SITE CHALLENGES
With the site dipping from northeast
O f fi
ces to southwest at roughly 1:18, the client
opted to terrace the site in preparation
for the expansion, with CDC2 and the
CDC2
office structures located on the upper
R CDC1
i nte et a inin terrace, adjoining CDC1, and two phases
r fac gw
e st a
ruc ll of the factory component of the operation
ture
Factory 2 located on a lower terrace – some 8 m
Factory 1 lower than CDC2 – to optimise materials
production, handling and distribution.
These terracing operations neces-
sitated lateral support being applied to the
8 m high cut slopes, which took the form
of a mesh-reinforced and shotcreted soil-
Figure 1: The AMKA factory and warehouse site on the corner nailed wall, half of which was treated as
of the M10 and R55 arterials in Sunderland Ridge
a permanent structure to support CDC1,
improvement designs are undertaken and looking across the warehouse footprint in close proximity to the warehouse were
monitored for compliance by a so-called towards the office structure). effectively eliminated as being untenable.
Competence Level 4 geo-professional.1 A key issue raised in the design review Under the imposed constraints and
In the present instance the engineering was the critical potential loss of support risk of potentially metastable karstic con-
design and site supervision aspects of this beneath the rows of warehouse racks in ditions beneath CDC1, the professional
project were referred to Alastair Morgan CDC2 which exert very high point loads team were of the view that compaction
Pr Eng (Technical Director at Geoid on the surface bed. It was reasoned that grouting presented the only truly viable
Geotechnical Engineers) who, amongst a even a small loss of support beneath the solution – particularly so since the client’s
small fraternity of experienced geotech- surface bed could translate to significant brief was that nothing should hinder or
nical engineers of a similar generation, tilting of the proposed 15 m high racks, place at risk the CDC1 operations, which
has the requisite Level 4 accreditation to with collateral damage occasioned by needed to remain fully functional and
undertake D4 design and review work. knocking over adjacent racking in a essentially unaffected for the full duration
domino effect. of the adjacent construction.
STRUCTURAL DESIGN As such, the scope of the ground im- The compaction (or low mobility)
From a structural design perspective, the provements was extended from simply the grouting process is designed to intersect
requisite loss of support criterion may be structural foundations alone, to include and fill the disseminated voids and cavities
considered as: the footprint of the entire warehouse which occur in the dolomite residuum, i.e.
■ provided for by appropriate structural floor, with particular attention paid to the essentially above bedrock level, with a view
(foundation) members, and major warehouse columns (illustrated in to interrupting or inhibiting the sinkhole-
■ mitigated by making use of ap- Figure 2). forming mechanism – but not intended
propriate ground improvement Despite the fact that most of the to fill the massive caverns assumed to
techniques, in combination. warehouse is interpreted to fall within occur within the dolomite rock mass at
As such, there may be a cost benefit trade- an IHC5 zone, the stability of the surface great depth. It essentially involves drilling
off between ground improvement and bed necessitated a conservative view a pilot hole, using a rotary percussion
structural rigidity of the foundation, de- being taken of this comparatively more drilling rig through the dolomite profile,
pending on the particular circumstances. favourable zone, in the knowledge that the nominally 5 m into the proven bedrock,
In the present instance, the structural hazard classification is, in reality, based to prove the competent rock horizon. A
members necessary to span a 15 m loss of on limited advance information. low-mobility grout – nominally 10 MPa
support in the IHC7 zone were assessed by cement:sand grout mix with a slump of
structural engineering company EDS to be GROUND IMPROVEMENT around 100–130 mm and a consistency
prohibitively large for the affected portions Several ground improvement techniques of toothpaste – is injected in an upstage
of the office block structure. A 5 m loss of were considered for this site, and weighed sequence from the bottom of the hole,
support was selected as the maximum void up against the environmental considera- under pressure of between 2–3.5 MPa. The
which could reasonably be accommodated tions and the impact on the existing opera- operation is undertaken across the site in a
in the structure, and the sector identified tion. Given the sensitivity of the existing grid pattern, utilising primary, secondary
for major ground improvement as de- CDC1 warehouse – which does not and, where necessary, tertiary (and sub-
scribed below, to treat the perceived highly evidently have any ground improvement sequent) stages to progressively ‘seal’ the
voided founding environment. applied, due to the less onerous regulations voids to the designer’s requirements.
The adjacent sectors of the CDC2 of the past – and the vulnerability of the RODIO Geotechnics (Pty) Ltd were
warehouse on IHC5 land comprise the racking to loss of support or movement appointed to undertake the grouting
heavy surface bed punctuated by nine free- induced by heavy vibrations, as well as the operations, which commenced in
standing concrete columns supporting the risk to the soil-nailed lateral support for June 2016, under the direction of the
entire warehouse structure (see Figure 2 CDC1, all forms of dynamic compaction geotechnical specialist.
DOLOMITE OBSERVATIONS
On the basis of a rudimentary assessment
of the incomplete, but comprehensive,
dataset of approximately 1 200 compac-
tion grouting boreholes drilled to date,
a normalised 3D surface of the dolomite
rockhead is presented in Figure 3.
Our preliminary observations are as
follows:
■ The local Sunderland Ridge dolomite
bedrock morphology is inferred to
follow a very similar mosaic to that
exposed in the Lyttleton dolomite
quarry, illustrated in Figure 4.
Figure 3: A normalised 3D surface of the dolomite rockhead
■ The mosaic comprises numerous rela-
tively steeply-sided pinnacles – many
GROUND PENETRATING RADAR expose horizons exhibiting possible cavi- of which protrude above the reduced
In view of the anticipated cost implica- ties and/or significant solution channels, platform ground level – interspersed
tions of the grouting, experimental use which could then be specifically targeted by deep troughs which, on this site, are
was made of ground penetrating radar for treatment and rehabilitation. typically no more than 20 m deep.
(GPR) to scan the site from ground level, Although the initial results appeared ■ Infi ll material comprises typical
from which a composite, georeferenced to hold much promise for predicting chert rubble with relatively limited
3D image was generated of the relative problematic areas and targeting the traces of the low-density, porous and
density of the ground, in an attempt to compaction grouting operations, very problematic WAD (weathered altered
dolomite).
■ As with the Lyttleton quarry, the pin-
nacle formation is relatively random,
with no appreciable pattern, other
than perhaps several sets of prefer-
ential troughs on an ill-defined, but
nominally northwest-southeast axis.
■ The projection of these pinnacles,
interspersed with troughs of thick
chert rubble infi ll, was well exposed
during the soil-nailing lateral support
installation in the cutting immediately
adjacent to CDC1, shown in Figure 5.
■ These pinnacle protrusions were typi-
cally measured to occur at between
2–6 m centres, in keeping with the
dolomite hazard class previously inter-
preted for this portion of the site.
GROUTING OBSERVATIONS
Taking an orthogonal view of the same idealised bedrock
surface as an underlay for the compaction grouting dataset, the
composite image shown in Figure 6 is generated, from which the
following preliminary observations are made:
■ At an elementary level, there appears to be no appreciable
difference in the dolomite morphology between the IHC7
(office) and IHC5 (warehouse) portions of the site.
■ Notwithstanding this, the grout takes (i.e. grout volumes
consumed during injection) in the IHC7 zone are appreciably
higher than those in the IHC5, which supports the original
assessment of the two hazard class zones on this site.
■ As would be expected, higher grout takes typically corre-
spond with a deeper rockhead – blue zones versus the shallow
red zones.
■ Notwithstanding this, significant grout takes also occur in
the transition zones between the shallow and deep dolomite,
which are interpreted to be the steeply-sided perimeter of the
pinnacle formation.
■ Portions of the site underlain by shallow bedrock are not,
however, a guarantee of problem-free bedrock, a case in point
being where the two most severely impacted support columns
for the warehouse (light blue base outline in Figure 6) are
underlain by shallow dolomite rock.
ww
Civil Engineering April 2017 57
Using the modelling techniques as dis-
cussed, the design is interpreted to have
satisfied not only the requisite 5 m loss
of support for the structural foundations,
but also the greatly increased support
of the warehouse surface beds – within
the original budget and without compro-
mising the original scope of work.
ACKNOWLEDGEMENTS
The authors of Geoid Geotechnical
Engineers would like to thank AMKA
Products for both the professional ap-
pointment to undertake this project
on their behalf, and the permission to
Figure 5: The projection of Lyttleton-type pinnacles, interspersed with troughs publish these preliminary findings within
of thick chert rubble infill, was well exposed during the soil-nailing lateral this article.
support installation in the cutting immediately adjacent to CDC1
NOTE
■ Th is seeming anomaly may possibly otherwise, for subsequent work within the 1. Geo-professionals in Competence Level 4
be attributed to the prominent steeply broader context of the site and the local shall, in addition to the minimum of five
sloped sides of the pinnacles which, we foundation support requirement. years practice as experienced geo-profes-
interpret, render it highly susceptible Based on this progressively refined sionals, enjoy recognition by the profession
to WAD and cavity formation, or model, the designers were able to as specialist geo-professionals, possessing a
alternatively the presence of a shallow eliminate a vast number of unnecessary level of specialist knowledge and experience
‘throat’ feature in shallow rock, either secondary/tertiary remedial work in above that expected of the profession. They
of which may be responsible for the areas exhibiting comparatively favourable should be making a contribution to the state
high grout takes. conditions, which furthermore provided of practice of the development of dolomite
the rational basis for localised detailed land by the application of advanced tech-
CONCLUSIONS perimeter grouting of the foundation niques or by means of research, publications
Despite the greatly expanded scope of bases where required. or involvement in engineering education.
work, largely brought about by the need
to support the warehouse surface bed in
addition to the key foundations – an item
which was essentially not fully budgeted IHC7
for – the ground improvement designers
were constrained to do whatever possible
to protect the budget against significant
cost overruns.
As the geotechnical specialist was IHC5
appointed on a design-as-you-construct
basis, an iterative grouting methodology
was adopted, comprising initially broad
concentric circles of progressively con-
centrated grouting, rather than a simpler
sequential operation from one side of the
site to the other, drilling all possible nodes
in the process.
This procedure did, however, require
that the ground improvement works had to
be scheduled with a reasonable head-start
preceding and accommodated by the main Legend
Grout Volume
contractor, GD Irons Construction, with Eliminated
Negligible
provision for progressive release of sectors Small
spacing was used for the detailed gravity survey. This resulted
in a significantly higher resolution of bedrock patterns than the
previous survey conducted on a 30 m grid spacing. Not only did
this higher resolution allow poor zones to be delineated, but it
allowed better predictions to be made with respect to the width
of solution features and the delineation of shallow bedrock.
The success of detecting ‘grykes’ or solution features is
directly related to the spacing of the gravity grid. A feature
smaller than the ‘cell’ size, which is half the spacing of the gravity
grid, will not be detected. The detailed survey carried out on a
10 m grid for this investigation, therefore, allowed the successful
delineation of all areas where a potential existed for medium or
large-sized sinkholes to develop. A comparison of the difference
in detail is given in Figures 2 and 3.
An additional 31 boreholes drilled were sited using the
detailed gravity survey. These were often drilled across narrow
zones of deeper bedrock predicted by the survey to confirm the
width of solution features (grykes). This enabled new hazard
zones to be identified with precision (Figure 4), and the site was
divided into three zones as follows:
■ Zone A: Zone A includes areas where shallow or outcropping
bedrock is dominant. As the bedrock is considered to have
cavernous conditions and overburden is not considered to be
particularly competent, this portion of the site is considered
to have a high potential for small sinkholes to develop and
a moderate potential for the development of medium-sized
sinkholes. It must be noted that a typical sinkhole size is not
expected to exceed 3 m in diameter in these areas.
■ Zone B: Th is zone includes areas where thick, more com-
petent chert overburden overlies deeper dolomite bedrock.
These areas are considered to present a moderate hazard
level and it is likely that medium to large-sized sinkholes will
develop in these areas, should they occur.
■ Zone C: Zone C includes areas where bedrock is deep, solu-
tions are wide, cavernous conditions exist and the overburden
is not competent. These areas are typically associated with
CONCLUSION
This case study demonstrates that far better resolution of
bedrock topography is possible using a smaller gravity survey
grid spacing. Appropriately spaced gravity grids allow for better
zonation of sites, as well as better identification and prediction of
the width of solution features within generally shallow bedrock
areas. The additional cost of the gravity survey will be offset by
reduced drilling requirements, and the production of a more
confident zonation and development plan. In this specific case
more land was deemed usable than the original investigations
had indicated.
ACKNOWLEDGEMENT
The authors wish to gratefully acknowledge the interactions with
and the contributions from Richard Day, geophysicist.
REFERENCES
1. SANS 1936: 2012. Development on dolomite land, Part 1, SABS.
2. SANS 1936: 2012. Development on dolomite land, Part 2, SABS.
3. SANS 1936: 2012. Development on dolomite land, Part 3, SABS.
4. SANS 1936: 2012. Development on dolomite land, Part 4, SABS.
5. A’Bear, A G & Richer, L R 2011. Proceedings, 15th African Regional
Conference on Soil Mechanics and Geotechnical Engineering,
626–631.
6. A’Bear, A G, Day, R W & Richer, L R 2015. Proceedings, First Southern
African Geotechnical Conference, 201–204.
Engineered fill
Compacted
stone head
17 VW rod extensometers
22 Edge of load
± 23.0 m
Competent
layer 1 000 mm ø CAP Edge of fill (base)
± 28.0 m
29.0 VW rod extensometers Bedrock
with 6-point monitoring
CONCLUSION
Ground improvement with rigid inclu- Figure 7 Aerial view of the ground improvement operations in the
first area of the Clairwood Logistic Park development
sions has numerous advantages compared
to conventional piled foundations,
particularly in challenging ground condi- piling, particularly in challenging soil such as warehouses, storage reservoirs,
tions. As with all ground improvement conditions, and often leads to programme treatment plants, basins and retention
techniques, structures are founded on and cost benefits for the project. facilities, road embankments, etc, which
inexpensive light/shallow foundations Furthermore, the inherent redundancy often have stringent differential settlement
once the ground improvement has been in ground improvement solutions provides criteria. It is, however, not suitable for
completed. This generally leads to a reduced risk in challenging ground condi- structures with highly concentrated loads,
significant reduction in the cost of the tions (in ground characterisation, design or structures with stringent total settle-
overall foundation system when com- and implementation) when compared to ment requirements.
pared with piled solutions which require piled foundations, which provide the full
pile caps, ground beams and thick rafts bearing resistance for the structure. It is REFERENCES
or slabs. Installation of rigid inclusions an alternative to piling for structures over The list of references is available from the
is significantly faster than conventional large footprints with distributed loads, author.
Figure 1: Existing GG6 stacker (left) and bucket wheel reclaimer (right)
PROJECT OVERVIEW
The GG6 Expansion project aims to
increase semi-soft coking coal produc-
tion at the Grootegeluk (GG) coal mine
through modifications and additions to
the existing GG2/6 plant and associated
materials handling systems. The project
called for the construction of a new
6 000 t coal silo, coal beneficiation plant,
upgrading and expansion of the existing
GG6 stockyard, and numerous overland
conveyors connecting the beneficiation
plant with the stockyard.
One of the main criteria of the project
was that the production of the existing
plant should not be affected by the
construction of the expansion project.
This was especially challenging in the
stockyard area, as the extension of the
rail beams for the stacker and bucket
wheel reclaimer (see Figure 1) had to be
constructed in close proximity to the
existing stockyard feed conveyor. Deep
excavations would be challenging, and it
was important for the design engineers to
have a good understanding of the depth of
the underlying bedrock. Figure 2: Typical layout of a CSW test
Geophones
Plate
Soil
Bedrock
Direct wave
Refracted wave
a vibrating shaker. The velocity of a me- methods were considered – the CSW test shear wave velocity profi le with depth,
chanically generated shear wave is affected and the seismic refraction test. With the which can then be used to classify the
by the medium that it travels through. The CSW test a mechanical shaker is placed ground profi le.
denser the medium, the higher the velocity. on the ground together with 3–5 geo- With the seismic refraction test pulses
Thus, by measuring the shear wave phones (see Figure 2). The shaker is used of low frequency seismic energy are
velocity of any ground stratum, a ground to generate Rayleigh waves with a range emitted by a source such as a hammer
classification can be established based on of different frequencies (low frequencies blow to the ground (refer to Figure 3).
the measured shear wave velocity. These have a deeper penetration). Depending The seismic waves propagate downward
typical velocities can be seen in Table 1. on the size of the shaker, waves can through the ground until they are
For the investigation of the GG6 penetrate up to twenty metres deep. The reflected off the subsurface, such as
project, only two surface wave test output produced from the test gives the bedrock. The refracted waves are detected
Vs (m/s)
Soil Depth
Description 150 250 350 450
legend (m)
0
Aeolian sand 1
2.1
Silty fine sand
2
Coarse sandy gravel
3.37 Completely weathered basalt boulders
becoming highly weathered soft rock
3
Depth (m)
Aeolian sand
4.37
Silty medium, to coarse sand
4
Basalt
5.37
Completely weathered very soft rock
5
Basalt
6
7 Highly to completely weathered very
soft to soft rock CSW 1
Stiff Soils
Soft Rock
7
Figure 4: Borehole profile log (left) versus CSW test results (right)
be seen in Figure 4.
Depth (m)
3
any other services that the probe might
damage. As the CSW test is a non-
4
destructive test, no excavation permit was
required and the testing could be done in
5
the three-day window that was allowed
by the mine for short duration non-risk
6
work. For any period longer that three
days, or for work that is deemed to carry a
7
CSW 2 CSW 4 Stiff Soils risk of injury (such as test pits and DPSH
CSW 3 CSW 5 Soft Rock probing), a full medical and induction to
the mine would have been required, thus
substantially increasing the cost.
Figure 7: CSW results along the reclaimer rail beams
The results from the CSW test
also gave the design engineers a better
understanding of the soil profi le below
Vs (m/s) the largest and most critical (in terms of
150 200 250 300 350 400 450 risk associated with founding conditions)
0
portions of the project site. The results
allowed the design engineers to suf-
1
ficiently identify risk in terms of founding
conditions and enabled them to choose
2 the correct method of founding the rele-
vant structures. It also allowed the cost
Depth (m)
16
Dense coarser
12 particles alone
Peak dilation angle ψ: °
All-sand-fines All-salt-fines
0
–5 5 15 25 35
Finer fraction F (%)
INTERNAL EROSION
Particle loss from internally unstable
soils can result in distress (termed suf-
fosion) in some cases and in other cases
no distress (termed suff usion). Recent
research at WITS, using salt dissolution
as an analogue for the eroded particles,
has explored why this may be the case,
using an in-house apparatus called the
vertical axis restrained internal erosion
direct shear box (variedSB) (MacRobert
et al 2015; MacRobert & Day 2016). Th is
showed that internally unstable soils can
have two different fabrics, depending
Figure 2: HYPROP device for determining soil moisture characteristics
on the percentage of erodible particles.
When the percentage of erodible parti-
cles is lower than a transition fi ner frac-
tion (Ft ≈ 15%), the loss of fi ner particles Figure 3: Dr Irvin Luker handling apparatus to
has a negligible effect on shear strength be used on an 8 500 kg drop-mass
for the ‘rapid’ load capacity test
(see Figure 1). Th is behaviour is due
to one type of fabric in which coarser
particles dominate inter-granular load
transfer. However, when the percentage
of erodible particles exceeds this transi-
tion value, the loss of fi ner particles
results in a reduction in shear strength,
which becomes greater as the fi ner frac-
tion increases. Th is behaviour is due to
a second fabric in which fi ner particles
increasingly hinder coarser particles
from attaining a dense arrangement. In
this second fabric, coarser particles also
dominate inter-granular load transfer so
that they are left in a very loose arrange-
ment following fi ner particle loss.
ZRUNVZKHQ\RXGR
$0(0%(52)7+( *5283
SHORTCOMINGS IN ESTIMATION OF
PARTICLE-SIZE DISTRIBUTION
Suction tests on samples taken from the housing development
mentioned previously showed considerable heave potential in
spite of a hydrometer analysis showing only 6% clay fraction.
A microscopic investigation was undertaken in an attempt to Photo 4: The large agglomeration of silt and clay-sized particles
understand why this should be. Clay is not normally considered appears to be bound together by minute, blue-stained,
high-cation exchange capacity clay particles
suitable for analysis by light microscope. Some of the reasons for
INFO
Prof Elizabeth (Lize) Theron
Research Group Leader: Soil Mechanics
Department of Civil Engineering: CUT
051 507 3646
etheron@cut.ac.za
12
GENERATING SLOPE
STABILITY PROBLEMS
Elevation (m)
80
60
Score (%)
40
0 10 20 30 40
20
Years of experience
Claims Cast in Concrete 15–16 May 2017 Midrand SAICEcon15/01759/18 Bruce Raath cheryl-lee@saice.org.za
Durability and Repairs of
14–15 August 2017 Midrand SAICEcon15/01757/18 Bruce Raath cheryl-lee@saice.org.za
Concrete Structures
Date to be confirmed TBC
Legal Liability
Cecil Townsend
Occupational Health and Date to be confirmed TBC SAICEcon17/02038/20 dawn@saice.org.za
Naude
Safety Act (OHSA)
Date to be confirmed TBC
C Brooker
SAICEtr15/01808/18 sybul@sarf.org.za /
Stormwater Drainage Date to be confirmed Durban Matt Braune
SARF12/0107/15 tshidi@sarf.org.za
Alaster Goyns
26 July 2017 Cape Town
Concrete Road Design SAICEtr15/01802/18 B Perrie sybul@sarf.org.za /
30 August 2017 Durban
and Construction CSSA-N-2013-08 Dr P Strauss tshidi@sarf.org.za
12 September 2017 Midrand
Traffic Signals Design 19–20 June 2017 Gauteng
and Optimisation – with SAICEtr15/01803/18 Dr John sybul@sarf.org.za /
special emphasis on 29–30 August 2017 Bloemfontein SARF14BRT09/17 Sampson tshidi@sarf.org.za
BRT
Construction of SAICEtr15/01809/18 sybul@sarf.org.za /
19 September 2017 Port Elizabeth E Kleyn
G1 Bases SARF14/9103/17 tshidi@sarf.org.za
Getting Acquainted
with Basic Contract
17–18 August 2017 Midrand CESA-864-05/2019 Theuns Eloff lizelle@ally.co.za
Administration and
Quality Control
If you would like to discuss any topics that you feel are relevant to SAICE
members, scan the QR code alongside to access SAICE’s blog.
ACTURER
UF S
N
A
A
M
SS
NCRETE
OCI
AT I O N
CO
Address: Office 0400, Standard Plaza Building, 440 Hilda Street, Hatfield, Pretoria, 0083
u
et
e
Q
al
it
y c nc
r Tel: (011) 805 6742 • Email: admin@cma.org.za • Website: www.cma.org.za
a s t in c o
CIVIL DESIGNER 8.0
The completely integrated, fit for purpose
infrastructure design system
www.civildesigner.com