Académique Documents
Professionnel Documents
Culture Documents
DOI: 10.7251/BMC170702039H
ABSTRACT
Tunnel Karavanke lies on the trans-European transport Corridor X and connects the A2 motorway in
the Republic of Slovenia to the A11 motorway in Austria. Existing Karavanke tunnel was built over
30 years ago as a single-tube and is currently a safety problem in the trans-European transport
corridor. Based on the Directive of the European Parliament and the Council on minimum safety
requirements for tunnels in the trans-European road network, the Republic of Slovenia and the
Republic of Austria has decided to participate in the construction of the new eastern tunnel tube and
the rehabilitation of existing western tunnel tube until 2019.
In 2016, we started with a drilling research work in the context of the implementation of geological,
geotechnical and hydrogeological investigations. We got more than 1000 meters of drilling core.
Particular attention during the drilling was in very demanding conditions in the geological layer,
which content methane. Some of the geological formation in this area contains a large amount of
methane (over 30 %).
In this article, we want to describe the technology that allowed drilling in a manner appropriate to
ensure the core of the high degree of security.
1. INTRODUCTION
The Karawanks tunnel is located on X. Pan-European Transport Corridor and it connects the
A2 motorway in the Republic of Slovenia with the A1 motorway in the Republic of Austria.
The existing tunnel was build more than 30 years ago as a single two-way tube tunnel, but it
is now perceived as the bottleneck in Pan-European transport corridor. Under the directive of
the European Parliament and the Council of minimum safety requirements for tunnels on
trans-European road network, the Republic of Slovenia and the Republic of Austria decided
to cooperate in construction of new eastern tube and rehabilitation of the existing western tube
by 2019.
39
7th BALKANMINE CONGRESS – Proceedings, Prijedor 2017
For the purpose of geological, geotechnical and hydrogeological surveys, the drilling started
in 2016. Drilling in Permo-Carboniferous layers was demanding and required special
attention. The formation is gas-bearing and contains large quantities of methane (more than
30 %). This article aims to describe technology used for drilling in order to obtain core and
also maintain high level of safety.
2. TUNNEL SURVEYS
For the purpose of geo-mechanical core research, drilling of fourteen horizontal structural
boreholes of various lengths was planned. The drilling locations within the existing tube were
in the existing blind underground facilities, existing partially-built walking paths (type GQ)
and in turning point PBN2, which consists of two trafficked crossbeams (type FQ) and
another tunnel tube finished in the pre-construction phase. Transport of drilling units and
equipment to specific locations was carried out when the road in the existing tube was
completely closed. Construction site preparations consist of drilling unit installation,
installation of settling-tanks, electrical wiring and installation of ventilation system. Diesel
generator was used as a primary energy source to supply all energy consumers on the site.
The generator was located in storage spaces, out of the main tunnel tube. Electrical equipment
40
7th BALKANMINE CONGRESS – Proceedings, Prijedor 2017
used for electrical supply on the sites was in accordance with designed project documentation.
Building site management was designed in order to give special attention to ventilation
system, since the presence of methane and other toxic gases was expected during the drilling.
Therefore separate compression ventilation was established. Fresh air supply was provided
from the main tunnel tube. Establishment and use of necessary ventilation equipment was
organized in accordance with designed project documentation on building site ventilation.
The drilling was performed by drilling rig DIAMEC 262 (Figure 1a) and CMV MK1400 FG
(Figure 1b).
Figure 1: (a) Drilling rig DIAMEC 262 on site, (b) Drilling rig CMV MK1400 FG on site
Two smaller drilling units were used on site PBN2, as with cross-beams type GQ and FQ, and
a larger drilling unit could only be used on turning point PBN2, because of its size. At any
time during the contractual relationship, the contractor was bound to specific requirements;
organizational special requirements, technical special requirements and formal special
requirements. In addition, the contractor has undertaken to carry out the drilling in tunnel
outside the tourist season and without hindering transport through the Karawanks tunnel.
The biggest challenge was presented by specific technical requirements, such as adequate
ventilation with continuous monitoring of toxic gasses presence, or appropriate reaction in
case of maximum permitted gases level overrun, and preserving a 100% intact core. In order
to preserve a core, the contractor implemented technology using a single coring unit in the
area to a depth of 6 meters. Drilling to the final depth was carried out by a double coring unit
with inner dividable tube and use of triple coring unit. This technology provides extracting the
intact core by extrusion, using devices such as extrusion with water and similar. In the areas,
where the core loss had been foreseen or poor geo-mechanical conditions were expected,
triple or double coring unit with inner dividable tube was used. The drilling equipment used in
this project met the criteria ISO 22475-1:2006 [2]. Directions of boreholes are different, that
is in direction of the existing tunnel tube or transverse to the existing tunnel tube. Inclination
of boreholes is 5 degrees downwards from the horizontal. Diamond drill bits of different
granule sizes were used most of the time (95 %).
41
7th BALKANMINE CONGRESS – Proceedings, Prijedor 2017
As already noted, special attention was given to the process of drilling in the area of gas-
bearing layers. Those layers are parts of geological formations from the Precambrian period
or contacts between Permo-Carboniferous layers and other geological formations. The
presence of methane and other dangerous gases was detected by combined detectors that were
installed above the mouth of the boreholes and in various parts of building sites, where lower
air-flow was expected. Gas detectors Drager X-am 7000 and Drager PAC 7000 were
measuring the presence of oxygen (O2), methane (CH4), carbon dioxide (CO2), carbon
monoxide (CO) and hydrogen sulfide (H2S). Detectors were equipped with light and sound
signalization, and programmed to trigger an alarm system in case of increased concentration
of dangerous gases [3]. In addition to the above-mentioned measures, there was also a
preventer in every borehole, ensuring borehole closing in case of dangerous gas intrusion.
While drilling, the contractor met some unfavorable conditions, especially when maximum
permitted levels of dangerous gases, methane and carbon monoxide, were exceeded and also
exhaled. With the first larger methane exhalation, the presence of this gas had to be measures
in the main tunnel tube as well, and consequently, the road through the Karawanks tunnel had
to be closed. In order to prevent these kinds of events, the contractor, the tunnel operator
DARS and fire brigade GARS Jesenice together established a protocol, which was drawn up
to foresee actions in case of dangerous gases occurrence in the construction site itself as well
as in the main tunnel tube. When exhalation of methane and/or carbon dioxide was measured
and detected, the drilling in such conditions caused many problems to the contractor. This
meant that the drilling was performed in atmosphere, where additional ventilation was
necessary and the speed of drilling process decreased substantially, due to degasification for
boreholes and building site itself. During the gasification of the boreholes, unfavorable geo-
mechanical conditions were identified. Due to pressure, those conditions are likely to
additionally affect the core collapse. To prevent this situation, the contractor used special
pipes, but after the pipes were used, they detected pressures on the borehole mouths and the
drilling in safe conditions was not possible anymore. After measuring, presence of dangerous
gases was detected, exceeding 10 bars.
While drilling works were in progress, National Laboratory of Health, Environment and Food
from Maribor performed measurement of gasometry within some boreholes. The data
generated are presented in the following table:
42
7th BALKANMINE CONGRESS – Proceedings, Prijedor 2017
Further on, all the boreholes were also equipped with safety valves with manometers that
monitor and detect pressures of gases. This monitoring is still applied.
43
7th BALKANMINE CONGRESS – Proceedings, Prijedor 2017
methane. It was concluded, that some parts of electrical equipment, preventing explosive
atmosphere to form, should be provided. At the same time, the supply of such equipment
would have great impact on estimated cost and the project termination date.
6. CONCLUSIONS
Throughout the project cycle, the building contractor has concluded or got confirmation to
some previously asked questions:
Research work concept has to be prepared in close cooperation between the design
engineer and the potential contractor. Only close cooperation will ensure achieving
results, necessary for constructing underground facilities. The contractor will research
technical solutions of the implementation work and the design engineer will study the
amount of research work which will lead to quality preparation of documentation for
executing the project.
Research work needs to be carried out in order to reach sufficient level of quantity and
quality. Assessment of investment and implementation of investment depend on level of
exploration and quality of work performed. Sufficient quantity of research work and its
quality determine the accuracy level of investment assessment.
In the phase of research, close cooperation between the contractor and the investor is
needed. It is acknowledged that geological, mining and building projects are of most
complex ones, because they largely deviate from original plans. When there are geological
surprises, the situation becomes even more complex. The work here needs to be carried
out in such a way, that the investor realizes their goals and that the contractor can work in
safe environment. That is why, all the possible risks have to be predicted in the research
stage. At the same time all measures providing safe and quality work need to be
implemented.
It is necessary that project documentation includes all risks and appropriate measures, that
were detected and carried out and on the basis of those provide new ones. New risks and
measures need to be carefully specified, because this is the only way to implement the
project allowing the investor to use financial resources within the forecast budget and
financial implementation will ensure safe and quality performance at the same time.
REFERENCES
[1] DARS, 2015, Predlog programa geoloških, getehničnih in hidrogeoloških raziskav za izdelavo
strokovnih podlag projektne dokumentacije za dograditev vzhodne cevi predora Karavanke, DRI
Ljubljana
[2] Vodušek Tadej in Hudournik Miran, 2016, Tehnološki elaborate vrtalnih del – izvedba raziskovalnih
vrtalnih del v predoru Karavanke, RGP Velenje
[3] DARS, 2015, Elaborati - Geološke, geomehanske in hidrogeoloških raziskave za izdelavo strokovnih
podlag projektne in varnostne dokumentacije za dograditev vzhodne cevi predora Karavanke, Akis
Trbovlje
44