Hirarchy Control
Hirarchy Control
Risk Identified
People /
Process / Activity / Task Environment at Hazard / Cause of Incident / Adverse L1 C1 RFN ** Current Mitigating Controls L2 C2 RRN * Additional Controls Required
Risk Adverse Effect / Effect / Environmental
Environmental Aspect Impact
Using Hand Tools Helper Crew, Electric shock, tool slip / Permanent disability, Long 3 2 6 ENG/S 1 3 3 EL/SUB
Mechanic Crew, wear using wrong tool for term absence due to EG 1. TAKE 5 & Daily pre start briefing
Foreman, task treatment for clear instruction
Supervisor
Feb 2010
Using Hand Tools Helper Crew, Electric shock, tool slip / Permanent disability, Long 3 2 6 1 3 3
Mechanic Crew, wear using wrong tool for term absence due to
PT. Leighton Contractors Indonesia
Foreman, task treatment
Supervisor
RISK ASSESSMENT REPORT
Approved By :
(PM/Delegated)
Note: Attach meeting attandance if more.
Hirarchy Control
Hirarchy Control
Risk Identified
People /
Process / Activity / Task Environment at Hazard / Cause of Incident / Adverse L1 C1 RFN ** Current Mitigating Controls L2 C2 RRN * Additional Controls Required
Risk Adverse Effect / Effect / Environmental
Environmental Aspect Impact
Feb 2010
Team
ols Required By whom By When Status Legal and Other Requirements Reference
Feb 2010
Team
ols Required By whom By When Status Legal and Other Requirements Reference
Feb 2010