EPCM CONTRACTOR:OUI JV PACKAGE 14- Rev.

G
PACKAGE CONTRACTOR:ELECO ICE PETROLEUM JV UTILITIES,INTERCONNECTING,OFFSITE(MPEI 0801&0803) 03-Jun-16
120 DAYS PROJECT MANAGEMENT SCHEDULE
# Activity ID Activity Name Rem Start Finish 2016
Dur v
Apr May Jun Jul Aug Sep Oct
1 183 05-Apr-16 04-Nov-16 05-Apr-16
MPEI 120 Days Schedule Rev.G
2 183 05-Apr-16 04-Nov-16 05-Apr-16
PACKAGE 14 - MPEI - 0801 / 0803 (120-DAYS SCHE
PACK
3 A1000 CONTRACT AWARD (Effective Date) 0 05-Apr-16 05-Apr-16
4 A1010 KICKOFF MEETING 2 05-May-16 06-May-16 05-May-16 06-May-16, KICKOFF MEETING
5 MOBILIZATION DOCUMENTATION
MOBI 105 06-Apr-16 05-Aug-16 06-Apr-16 05-Aug-16
6 A1020 MOBILIZATION DOCUMENTATION 105 06-Apr-16 05-Aug-16 06-Apr-16 05-Aug-16, MOBILIZATION DOCUMENTATION
7 Const
Construction Execution 64 16-May-16 28-Jul-16 16-May-16 28-Jul-16
8 A1030 Project & Site Org. Charts - Preparation / Submittal 30 16-May-16 18-Jun-16 16-May-16 18-Jun-16, Project & Site Org. Charts - Preparation / Submittal
9 A1040 Project & Site Org. Charts - OUI JV Review / Approval 10 20-Jun-16 30-Jun-16 20-Jun-16 30-Jun-16, Project & Site Org. Charts - OUI JV Review / Approval
10 A1050 Construction Execution Plan - Preparation / Submittal 30 16-May-16 18-Jun-16 16-May-16 18-Jun-16, Construction Execution Plan - Preparation / Submittal
11 A1060 Construction Execution Plan - OUI JV Review / Approval 10 20-Jun-16 30-Jun-16 20-Jun-16 30-Jun-16, Construction Execution Plan - OUI JV Review / Approval
12 A1070 Procurement and Subcontracting Plan - Preparation / Submittal 40 16-May-16 30-Jun-16* 16-May-16 30-Jun-16*, Procurement and Subcontracting Plan - Preparation / Submittal
13 A1080 Procurement and Subcontracting Plan - OUI JV Review / Appro 10 01-Jul-16 12-Jul-16 01-Jul-16 12-Jul-16, Procurement and Subcontracting Plan - OUI JV Review / Approval
14 A1090 Manpower Plan - Preparation / Submittal 40 16-May-16 30-Jun-16 16-May-16 30-Jun-16, Manpower Plan - Preparation / Submittal
15 A1100 Manpower Plan - OUI JV Review / Approval 10 01-Jul-16 12-Jul-16 01-Jul-16 12-Jul-16, Manpower Plan - OUI JV Review / Approval
16 A1110 Equipment Plan - Preparation / Submittal 40 16-May-16 30-Jun-16 16-May-16 30-Jun-16, Equipment Plan - Preparation / Submittal
17 A1120 Equipment Plan - OUI JV Review / Approval 10 01-Jul-16 12-Jul-16 01-Jul-16 12-Jul-16, Equipment Plan - OUI JV Review / Approval
18 A1130 Scaffolding Plan - Preparation / Submittal 54 16-May-16 16-Jul-16 16-May-16 16-Jul-16, Scaffolding Plan - Preparation / Submittal
19 A1140 Scaffolding Plan - OUI JV Review / Approval 10 18-Jul-16 28-Jul-16 18-Jul-16 28-Jul-16, Scaffolding Plan - OUI JV Review / Approval
20 A1150 Project Interfacing Plan - Preparation / Submittal 54 16-May-16 16-Jul-16 16-May-16 16-Jul-16, Project Interfacing Plan - Preparation / Submittal
21 A1160 Project Interfacing Plan - OUI JV Review / Approval 10 18-Jul-16 28-Jul-16 18-Jul-16 28-Jul-16, Project Interfacing Plan - OUI JV Review / Approval
22 Projec Controls
Project 74 09-May-16 02-Aug-16 09-May-16 02-Aug-16
23 A1170 Level 2 Schedule - Preparation / Submittal 26 09-May-16 07-Jun-16 09-May-16 07-Jun-16, Level 2 Schedule - Preparation / Submittal
24 A1180 Level 2 Schedule - OUI JV Review / Approval 10 08-Jun-16 18-Jun-16 08-Jun-16 18-Jun-16, Level 2 Schedule - OUI JV Review / Approval
25 A1190 Level 4 Schedule - Preparation / Submittal 38 23-May-16 05-Jul-16* 23-May-16 05-Jul-16*, Level 4 Schedule - Preparation / Submittal
26 A1200 Level 4 Schedule - OUI JV Review / Approval 10 06-Jul-16 16-Jul-16 06-Jul-16 16-Jul-16, Level 4 Schedule - OUI JV Review / Approval
27 A1210 Work Progress Measurement - Preparation / Submittal 14 06-Jul-16 21-Jul-16 06-Jul-16 21-Jul-16, Work Progress Measurement - Preparation / Submittal
28 A1220 Work Progress Measurement - OUI JV Review / Approval 10 22-Jul-16 02-Aug-16 22-Jul-16 02-Aug-16, Work Progress Measurement - OUI JV Review / Approval
29 HSSE 62 06-Apr-16 16-Jun-16 06-Apr-16 16-Jun-16
30 A1230 Site HSE Plan - Preparation / Submittal 45 06-Apr-16 27-May-16 06-Apr-16 27-May-16, Site HSE Plan - Preparation / Submittal
31 A1240 Site HSE Plan - OUI JV Review / Approval 10 28-May-16 08-Jun-16 28-May-16 08-Jun-16, Site HSE Plan - OUI JV Review / Approval
32 A1250 Environmental and Waste Management Plan - Preparation / Sub 45 06-Apr-16 27-May-16 06-Apr-16 27-May-16, Environmental and Waste Management Plan - Preparation / Submittal
33 A1260 Environmental and Waste Management Plan - OUI JV Review / 10 28-May-16 08-Jun-16 28-May-16 08-Jun-16, Environmental and Waste Management Plan - OUI JV Review / Approval
34 A1270 Emergency Response Plan - Preparation / Submittal 45 14-Apr-16 04-Jun-16 14-Apr-16 04-Jun-16, Emergency Response Plan - Preparation / Submittal
35 A1280 Emergency Response Plan - OUI JV Review / Approval 10 06-Jun-16 16-Jun-16 06-Jun-16 16-Jun-16, Emergency Response Plan - OUI JV Review / Approval
36 A1290 Site Security Plan - Preparation / Submittal 45 14-Apr-16 04-Jun-16 14-Apr-16 04-Jun-16, Site Security Plan - Preparation / Submittal
37 A1300 Site Security Plan - OUI JV Review / Approval 10 06-Jun-16 16-Jun-16 06-Jun-16 16-Jun-16, Site Security Plan - OUI JV Review / Approval
38 QA/QC 57 07-May-16 12-Jul-16 07-May-16 12-Jul-16
39 A1310 Project Quality Management Plan - Preparation / Submittal 30 07-May-16 10-Jun-16 07-May-16 10-Jun-16, Project Quality Management Plan - Preparation / Submittal
40 A1320 Project Quality Management Plan - OUI JV Review / Approval 10 11-Jun-16 22-Jun-16 11-Jun-16 22-Jun-16, Project Quality Management Plan - OUI JV Review / Approval
41 A1330 Inspection and Testing Plan - Preparation / Submit tal 30 07-May-16 10-Jun-16 07-May-16 10-Jun-16, Inspection and Testing Plan - Pr eparation / Submittal
42 A1340 Inspection and Testing Plan - O UI JV Review / Approval 10 11-Jun-16 22-Jun-16 11-Jun-16 22-Jun-16, Inspection and Testing Plan - OUI JV Review / Approval
43 A1350 Document, Material, and NCR Control Plans - Preparation / Sub 30 07-May-16 10-Jun-16 07-May-16 10-Jun-16, Document, Material, and NCR Control Plans - Preparation / Submittal
44 A1360 Document, Material, and NCR Control Plans - OUI JV Review 10 11-Jun-16 22-Jun-16 11-Jun-16 22-Jun-16, Document, Material, and NCR Control Plans - OUI JV Review / Approval
45 A1370 Painting Procedures and Documentation - Preparation / Submitt 30 07-May-16 10-Jun-16 07-May-16 10-Jun-16, Painting Procedures and Documentation - Preparation / Submittal
46 A1380 Painting Procedures and Documentation - OUI JV Review / App 10 11-Jun-16 22-Jun-16 11-Jun-16 22-Jun-16, Painting Procedures and Documentation - OUI JV Review / Approval
47 A1390 Welding Procedures and Documentation - Preparation / Submit 40 16-May-16 30-Jun-16 16-May-16 30-Jun-16, Welding Procedures and Documentation - Preparation / Submittal
48 A1400 Welding Procedures and Documentation - OUI JV Review / App 10 01-Jul-16 12-Jul-16 01-Jul-16 12-Jul-16, Welding Procedures and Documentation - OUI JV Review / Approval
49 A1410 NDT Methods and Documentation - Preparation / Submittal 40 16-May-16 30-Jun-16 16-May-16 30-Jun-16, NDT Methods and Documentation - Preparation / Submittal
50 A1420 NDT Methods and Documentation - OUI JV Review / Approval 10 01-Jul-16 12-Jul-16 01-Jul-16 12-Jul-16, NDT Methods and Documentation - OUI JV Review / Approval
51 Contr
Contract Administration 105 06-Apr-16 05-Aug-16 06-Apr-16 05-Aug-16
52 A1430 Performance Bond - Preparation / Submittal 71 06-Apr-16 27-Jun-16 06-Apr-16 27-Jun-16, Performance Bond - Preparation / Submittal
53 A1440 Performance Bond - OUI JV Review / Approval 10 28-Jun-16 08-Jul-16 28-Jun-16 08-Jul-16, Performance Bond - OUI JV Review / Approval
54 A1450 Parent Company Guarantee - Preparation / Submittal 71 06-Apr-16 27-Jun-16 06-Apr-16 27-Jun-16, Parent Company Guarantee - Preparation / Submittal
55 A1460 Parent Company Guarantee - OUI JV Review / Approval 10 28-Jun-16 08-Jul-16 28-Jun-16 08-Jul-16, Parent Company Guarantee - OUI JV Review / Approval
56 A1470 CIDB Levy - Preparation / Submittal 71 06-Apr-16 27-Jun-16 06-Apr-16 27-Jun-16, CIDB Levy - Preparation / Submittal
57 A1480 CIDB Levy - OUI JV Review / Approval 10 28-Jun-16 08-Jul-16 28-Jun-16 08-Jul-16, CIDB Levy - OUI JV Review / Approval
58 A1490 Insurances - Preparation / Submittal 47 06-Apr-16 30-May-16 06-Apr-16 30-May-16, Insurances - Preparation / Submittal
59 A1500 Insurances - OUI JV Review / Approval 10 31-May-16 10-Jun-16 31-May-16 10-Jun-16, Insurances - OUI JV Review / Approval
60 A1510 Invoice for 1st Milestone - Preparation / Submittal (within 5 days 14 09-Jul-16 25-Jul-16 09-Jul-16 25-Jul-16, Invoice for 1st Milestone - Preparation / Submittal (within 5 days of 25th of M
61 A1520 Invoice for 1st Milestone - OUI JV Review / Approval 10 26-Jul-16 05-Aug-16 26-Jul-16 05-Aug-16, Invoice for 1st Milestone - OUI JV Review / Approval
62 MATERIALS DELIVERY
MATER 4 16-Jul-16 21-Jul-16 16-Jul-16 21-Jul-16
63 A1530 First Delivery of Painting Materials 0 16-Jul-16* 16-Jul-16*
64 A1540 First Delivery of Free-Issued Piping Materials 0 21-Jul-16 21-Jul-16
65 MOBILIZATION OF DIRECT MANPOWER
MOBIL 98 13-Jul-16 04-Nov-16 13-Jul-16
66 A1550 First Arrival of Welders (20 ea) 0 21-Jul-16* 21-Jul-16*
67 A1560 First Arrival of Blasting and Painting Labor (7 ea) 0 13-Jul-16 13-Jul-16
68 A1570 First Arrival of Riggers and Fitters for Pipe Fab (20 ea) 0 21-Jul-16 21-Jul-16
69 A1580 First Arrival of Workers for Steel Erection (25 ea) 0 12-Oct-16* 12-Oct-16*
70 A1590 First Arrival of Riggers and Fitters for Pipe Install (25 ea) 0 04-Nov-16* 04-Nov-16*
71 TEMPORARY PIPING FABRICATION SHOP (PFS) [OFF SITE]
TEMP 164 09-Apr-16 17-Oct-16 09-Apr-16 17-Oct-16
72 A1600 Overall Plot Plan 3 09-Apr-16 12-Apr-16 09-Apr-16 12-Apr-16, Overall Plot Plan
73 A1610 Survey Site and Report Results 21 13-Apr-16 06-May-16 13-Apr-16 06-May-16, Survey Site and Report Results
74 A1620 Workshop Design 30 29-Apr-16 02-Jun-16 29-Apr-16 02-Jun-16, Workshop Design
75 Const
Construction 140 07-May-16 17-Oct-16 07-May-16 17-Oct-16
76 A1630 Clear Site 14 07-May-16 23-May-16 07-May-16 23-May-16, Clear Site
77 A1640 Level Site 40 24-May-16 08-Jul-16 24-May-16 08-Jul-16, Level Site
78 A1650 Install Fencing 21 17-Jun-16 11-Jul-16 17-Jun-16 11-Jul-16, Install Fencing
79 A1660 Lay Down and Compact Crusher-run 10 12-Jul-16 22-Jul-16 12-Jul-16 22-Jul-16, Lay Down and Compact Crusher-run
80 A1670 Workshop - Build Concrete Foundation 30 20-Jul-16 23-Aug-16 20-Jul-16 23-Aug-16, Workshop - Build Concrete Foundation
81 A1680 PFS Partially Operational 0 22-Jul-16* 22-Jul-16*
82 A1690 Workshop - Fabricate Steel Structure 40 23-Jul-16 07-Sep-16 23-Jul-16 07-Sep-16, Workshop - Fabricate Steel Structu
83 A1700 Workshop - Erect Steel Structure 30 05-Aug-16 08-Sep-16 05-Aug-16 08-Sep-16, Workshop - Erect Steel Structure
84 A1710 Workshop - Install Roofing and Cladding 30 22-Aug-16 24-Sep-16 22-Aug-16 24-Sep-16, Workshop - Install R
85 A1720 Workshop - Install Power and Lighting 63 05-Aug-16 17-Oct-16 05-Aug-16 17-Oct-16, W
86 A1730 Workshop - Deliver Cranes and Supports 14 24-Aug-16 08-Sep-16 24-Aug-16 08-Sep-16, Workshop - Deliver Cranes and S
87 A1740 Workshop - Install Cranes and Supports 30 09-Sep-16 13-Oct-16 09-Sep-16 13-Oct-16, Wor
88 A1750 Workshop - Deliver Auto Blasting and Painting System 3 26-Sep-16 28-Sep-16 26-Sep-16 28-Sep-16, Workshop - Deliv
89 A1760 Workshop - Install Auto Blasting and Painting System 7 29-Sep-16 06-Oct-16 29-Sep-16 06-Oct-16, Workshop
90 A1770 Workshop - Deliver Auto Welding System 7 01-Sep-16* 08-Sep-16 01-Sep-16* 08-Sep-16, Workshop - Deliver Auto Welding S
91 A1780 Workshop - Install Auto Welding System 33 09-Sep-16 17-Oct-16 09-Sep-16 17-Oct-16, W
92 A1790 Mobilize Camp, Offices, and Warehouse 47 24-Aug-16 17-Oct-16 24-Aug-16 17-Oct-16, M
93 A1800 PFS Fully Operational 0 17-Oct-16* 17-Oct-16*
94 TEMPORARY CONSTRUCTION FACILITIES (TCF) [ON SITE]
TEMP 114 18-May-16 27-Sep-16 18-May-16 27-Sep-16
95 Engin
Engineering and Permitting 114 18-May-16 27-Sep-16 18-May-16 27-Sep-16
96 A1810 Visit Site 3 18-May-16* 20-May-16 18-May-16* 20-May-16, Visit Site
97 A1820 Signboard and Fencing Design - Preparation / Submittal 1 27-May-16* 27-May-16 27-May-16* 27-May-16, Signboard and Fencing Design - Preparation / Submittal
98 A1830 Signboard and Fencing Design - OUI JV Review / Approval 1 28-May-16 28-May-16 28-May-16 28-May-16, Signboard and Fencing Design - OUI JV Review / Approval
99 A1840 Signboard and Fencing Design - PSP Submittal 7 30-May-16 06-Jun-16 30-May-16 06-Jun-16, Signboard and Fencing Design - PSP Submittal
100 A1850 Signboard and Fencing Design - Petronas Approval 7 07-Jun-16 14-Jun-16 07-Jun-16 14-Jun-16, Signboard and Fencing Design - Petronas Approval
101 A1860 Signboard and Fencing Design - MDKT Approval 14 15-Jun-16 30-Jun-16 15-Jun-16 30-Jun-16, Signboard and Fencing Design - MDKT Approval
102 A1870 Buildings Design - Preparation / Submittal 14 28-May-16* 13-Jun-16 28-May-16* 13-Jun-16, Buildings Design - Preparation / Submittal
103 A1880 Buildings Design - OUI JV Review / Approval 7 14-Jun-16 21-Jun-16 14-Jun-16 21-Jun-16, Buildings Design - OUI JV Review / Approval
104 A1890 Buildings Design - PSP Submittal 21 22-Jun-16 15-Jul-16 22-Jun-16 15-Jul-16, Buildings Design - PSP Submittal
105 A1900 Buildings Design - Petronas Approval 7 16-Jul-16 23-Jul-16 16-Jul-16 23-Jul-16, Buildings Design - Petronas Approval
106 A1910 Buildings Design - MDKT Approval 56 25-Jul-16 27-Sep-16 25-Jul-16 27-Sep-16, Buildings Design -
107 Const
Construction 81 16-Jun-16 17-Sep-16 16-Jun-16 17-Sep-16
108 A1920 Install Fencing 21 16-Jun-16 09-Jul-16 16-Jun-16 09-Jul-16, Install Fencing
109 A1930 Lay Down and Compact Crusher-run 14 02-Jul-16 18-Jul-16 02-Jul-16 18-Jul-16, Lay Down and Compact Crusher-run
110 A1940 Mobilize Offices and Warehouse 48 25-Jul-16 17-Sep-16 25-Jul-16 17-Sep-16, Mobilize Offices and Wareh
111 A1950 Build Workshop 40 25-Jul-16 08-Sep-16 25-Jul-16 08-Sep-16, Build Workshop
112 A1960 Mobilize Toilets, Tanks, and Service 14 02-Aug-16 17-Aug-16 02-Aug-16 17-Aug-16, Mobilize Toilets, Tanks, and Service
113 A1970 Mobilize Dumpsters and Service 7 18-Aug-16 25-Aug-16 18-Aug-16 25-Aug-16, Mobilize Dumpsters and Service
114 A1980 Mobilize Diesel Generators and Tank 14 26-Aug-16 10-Sep-16 26-Aug-16 10-Sep-16, Mobilize Diesel Generators and T
115 A1990 Mobilize Warehousing and Material Handling Equipment 40 03-Aug-16 17-Sep-16 03-Aug-16 17-Sep-16, Mobilize Warehousing and
116 A2000 Mobilize TCF Labor 14 02-Sep-16 17-Sep-16 02-Sep-16 17-Sep-16, Mobilize TCF Labor
117 A2010 TCF Fully Operational 0 17-Sep-16* 17-Sep-16*
118 0801 0 22-Jul-16 22-Jul-16 22-Jul-16 22-Jul-16
119 A2020 START OF PIPING FABRICATION 0 22-Jul-16* 22-Jul-16*
120 0803 0 22-Jul-16 22-Jul-16 22-Jul-16 22-Jul-16
121 A2030 START OF PIPING FABRICATION 0 22-Jul-16* 22-Jul-16*