Académique Documents
Professionnel Documents
Culture Documents
Actual Actual
BOQ P3 Activity Name Type QTY Finish Remarks
Finish QTY
Total 3043 1644
BOQ4 ‐ Distribution chamber 334 317
Distribution chamber Walls to Level 13.70 Stage 2 RC Walls 147 02‐01‐2018 02‐01‐2018
170 Done
Distribution chamber Baffle Wall Stage 2 RC Walls 23 02‐01‐2018 02‐01‐2018
Distribution chamber Cast in situ reinforced concrete solid slabs, beams and staircases at Level 13.70 RC Slabs 164 10‐01‐2018 15‐01‐2018 147 Done
BOQ5 ‐ Sedimentation basin B 1480 591
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 30 cm ‐ Train # 9 RC Walls 93 15‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 30 cm ‐ Train # 10 RC Walls 93 06‐01‐2018 06‐01‐2018 93 Done
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 30 cm ‐ Train # 7 RC Walls 93 13‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 30 cm ‐ Train # 8 RC Walls 93 13‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 20 cm ‐ Train # 2 RC Walls 4 04‐01‐2018
09‐01‐2018 48 Done
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 20 cm ‐ Train # 3 RC Walls 38 14‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 20 cm ‐ Train # 4 RC Walls 38 14‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 20 cm ‐ Train # 5 RC Walls 38 22‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 20 cm ‐ Train # 6 RC Walls 38 22‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 20 cm ‐ Train # 7 RC Walls 38 23‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 20 cm ‐ Train # 8 RC Walls 38 23‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 20 cm ‐ Train # 9 RC Walls 38 30‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 20 cm ‐ Train # 10 RC Walls 38 30‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 20 cm ‐ Train # 11 RC Walls 38 31‐01‐2018
Sedimentation basin B Walls ‐ Higher level +4.60 ‐ ts 20 cm ‐ Train # 12 RC Walls 38 31‐01‐2018
Sedimentation basin B Baffle wall ‐ Higher level ‐ +4.20 ‐ Train # 11 RC Walls 11 06‐01‐2018 03‐01‐2018 12 Done
Sedimentation basin B Baffle wall ‐ Higher level ‐ +4.20 ‐ Train # 12 RC Walls 11 06‐01‐2018 03‐01‐2018 12 Done
Sedimentation basin B Baffle wall ‐ Higher level ‐ +4.60 ‐ Train # 3 RC Walls 11 09‐01‐2018 04‐01‐2018 13 Done
Sedimentation basin B Baffle wall ‐ Higher level ‐ +4.60 ‐ Train # 4 RC Walls 11 09‐01‐2018 04‐01‐2018 13 Done
Sedimentation basin B Baffle wall ‐ Higher level ‐ +4.60 ‐ Train # 5 RC Walls 11 16‐01‐2018
Sedimentation basin B Baffle wall ‐ Higher level ‐ +4.60 ‐ Train # 6 RC Walls 11 23‐01‐2018
Sedimentation basin B Baffle wall ‐ Higher level ‐ +4.60 ‐ Train # 7 RC Walls 11 23‐01‐2018
Sedimentation basin B Baffle wall ‐ Higher level ‐ +4.60 ‐ Train # 8 RC Walls 11 16‐01‐2018
Sedimentation basin B Baffle wall ‐ Higher level ‐ +4.60 ‐ Train # 9 RC Walls 11 16‐01‐2018 15‐01‐2018 12 Done
Sedimentation basin B Baffle wall ‐ Higher level ‐ +4.60 ‐ Train # 10 RC Walls 11 16‐01‐2018 15‐01‐2018 12 Done
Sedimentation basin B (Over flow channel +6.70) ‐ Walls ‐ From +6.70 to +9.00 ‐ Zone 3 ‐ Trains # 9 , 10 , 11 , 12 RC Walls 33 12‐01‐2018
10‐01‐2018 73 Done
Sedimentation basin B (Over flow channel +6.70) ‐ RC solid slabs at +9.00 ‐ Zone 3 ‐ Trains # 9 , 10 , 11 , 12 RC Slabs 44 12‐01‐2018
Sedimentation basin B (Receiving channel +8.50) ‐ Walls ‐ From +9.50 to +11.50 ‐ Zone 2 ( Trains # 5 , 6 , 7 , 8 ) ‐ Sou RC Walls 56 27‐01‐2018
Sedimentation basin B (Receiving channel +8.50) ‐ slabs at Level +11.50 ‐ Zone 2 ( Trains # 5 , 6 , 7 , 8 ) RC Slabs 35 27‐01‐2018
Sedimentation basin B (Receiving channel +8.50) ‐ Walls ‐ From +9.50 to +11.50 ‐ Zone 3 ‐ Southern wall RC Walls 36 10‐01‐2018
06‐01‐2018 75 Done
Sedimentation basin B (Receiving channel +8.50) ‐ slabs at Level +11.50 ‐ Zone 3 ( Trains # 9 , 10 , 11 , 12 ) RC Slabs 19 10‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.70 on Walls +4.60 ‐ Zone 1 ‐ ( Train # 1) RC Slabs 16 09‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.70 on Walls +4.60 ‐ Zone 1 ‐ ( Train # 2) RC Slabs 16 09‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.70 on Walls +4.60 ‐ Zone 1 ‐ ( Train # 3) RC Slabs 16 21‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.70 on Walls +4.60 ‐ Zone 1 ‐ ( Train # 4) RC Slabs 16 21‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.70 on Walls +4.60 ‐ Zone 2 ‐ ( Train # 5) RC Slabs 16 30‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.70 on Walls +4.60 ‐ Zone 2 ‐ ( Train # 6) RC Slabs 16 30‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.70 on Walls +4.60 ‐ Zone 2 ‐ ( Train # 7) RC Slabs 16 30‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.70 on Walls +4.60 ‐ Zone 2 ‐ ( Train # 8) RC Slabs 16 30‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.00 on Baffle Walls +4.20 ‐ Zone 2 ‐ ( Train # 7) RC Slabs 9 17‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.00 on Baffle Walls +4.20 ‐ Zone 2 ‐ ( Train # 8) RC Slabs 9 17‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.00 on Baffle Walls +4.20 ‐ Zone 3 ‐ ( Train # 9) RC Slabs 9 17‐01‐2018
14‐01‐2018 68 Done
Sedimentation basin B Walkway ‐ Solid slabs at +9.00 on Baffle Walls +4.20 ‐ Zone 3 ‐ ( Train # 10) RC Slabs 9 17‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.00 on Baffle Walls +4.20 ‐ Zone 3 ‐ ( Train # 11) RC Slabs 9 17‐01‐2018
Sedimentation basin B Walkway ‐ Solid slabs at +9.00 on Baffle Walls +4.20 ‐ Zone 3 ‐ ( Train # 12) RC Slabs 9 17‐01‐2018
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 1) RC Walls 3.5 07‐01‐2018
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 2) RC Walls 3.5 07‐01‐2018 08‐01‐2018 Done
10
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 3) RC Walls 3.5 07‐01‐2018
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 4) RC Walls 3.5 07‐01‐2018
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 5) RC Walls 6 12‐01‐2018
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 6) RC Walls 6 12‐01‐2018
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 7) RC Walls 6 27‐01‐2018
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 8) RC Walls 6 27‐01‐2018
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 9) RC Walls 6 27‐01‐2018
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 10) RC Walls 6 27‐01‐2018
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 11) RC Walls 6 27‐01‐2018
Sedimentation basin B Drain trough precast unit (overflow chamber) (Train # 12) RC Walls 6 27‐01‐2018
Sedimentation basin B Baffle wall ‐ Higher level ‐ +4.60 ‐ Receiving Tank RC Walls / 23 06‐01‐2018
Sedimentation basin B Receiving Tank ‐ Walls ‐ Higher level +4.60 up to +10.60 (Over flow wall) RC Walls 29 06‐01‐2018 04‐01‐2018 150 Done
Sedimentation basin B Receiving Tank ‐ Walls ‐ Higher level +4.60 up to +11.50 (Remaining) RC Walls 75 06‐01‐2018
Sedimentation basin B Receiving Tank ‐ Cast in situ solid slabs at 11.50 RC Slabs 20 27‐01‐2018
BOQ6 ‐ Clear Water Tank 467 234
Clear Water Tank Cast in situ reinforced concrete solid slabs and beams(up to + 6.90) ‐ Zone 3 RC Slabs 30‐01‐2018 11‐01‐2018 24 Partially Cast
210
Clear Water Tank Cast in situ reinforced concrete solid slabs and beams(up to + 6.90) ‐ Zone 4 RC Slabs 30‐01‐2018
Clear Water Tank Columns (up to + 6.90) ‐ Zone 3 RC Columns 10‐01‐2018 Done
03‐01‐2018
Clear Water Tank Retaining Walls (up to + 6.90) ‐ Zone 3 RC Walls 04‐01‐2018 Done
96 189
Clear Water Tank Columns (up to + 6.90) ‐ Zone 4 RC Columns 10‐01‐2018 07‐01‐2018 Partially Cast
Clear Water Tank Retaining Walls (up to + 6.90) ‐ Zone 4 RC Walls 07‐01‐2018 07‐01‐2018 Done
Clear Water Tank Walls(up to + 10.80)‐ higher level ‐ Zone 2 RC Walls 04‐01‐2018
21 03‐01‐2018 21 Done
Clear Water Tank Cast in situ reinforced concrete solid slabs and beams ( up to + 10.80 ) ‐ Zone 2 RC Slabs 04‐01‐2018
1/2
Concrete Plan For ‐ Jan 2018 Data Date15‐Jan‐18
Actual Actual
BOQ P3 Activity Name Type QTY Finish Remarks
Finish QTY
BOQ6 ‐ Clear Water Tank Pump House 18 18
Clear Water P H Parapet works ( at + 11.00 ) RC Parapet 18 07‐Jan‐18 10‐01‐2018 18 Done
BOQ8 ‐ Chemical Building 580 201
Chemical Building RC Slab on Grade RC FDN 580 20‐01‐2018 09‐01‐2018 201 Partially Cast
BOQ13 ‐ Warehouse Building 164 22
Warehouse Building Plain concrete Grade 20 under Ground Beams Plain Concrete 10 02‐01‐2018 02‐01‐2018 22 Done
Warehouse Building Ground beams on level +4.90 RC FDN 61 17‐01‐2018
Warehouse Building Slab on Grade RC FDN 93 29‐01‐2018
Additional items 261
Intake Basin Pouring&Curing blocks (500 x 500 x 500) Precast block ‐‐‐‐ ‐‐‐‐ ‐‐‐‐‐‐ 75 Continous
Intake St. & Pump Room Columns +4.50 : +12.30 RC Columns ‐‐‐ ‐‐‐ 13‐01‐2018 8 Partially Cast
Intake St. & Pump Room Cantliver on columns at Intake Chamber RC Columns ‐‐‐ ‐‐‐ 07‐01‐2018 3 Partially Cast
Intake St. & Pump Room Parapet at Intake Chamber & 2 Posts at Pump Room RC Slabs ‐‐‐ ‐‐‐ 11‐01‐2018 16 Done
Substation Intake Parapet concrete works RC Slabs ‐‐‐‐ ‐‐‐‐ 02‐01‐2018 11 Done
Substation Intake Electrical & HVAC Room RC Slabs ‐‐‐‐ ‐‐‐‐ 13‐01‐2018 18 Done
Sedimentation basin A Mass Concrete Level +4.60 Train 10,11 RC FDN ‐‐‐‐ ‐‐‐‐ 03‐01‐2018 32 Done
Sedimentation basin A Mass Concrete Level +4.60 Train 8 RC FDN ‐‐‐‐ ‐‐‐‐ 15‐01‐2018 16 Done
Sedimentation basin B Mass Concrete Level +0.8 Train 2 , 3 RC FDN ‐‐‐‐ ‐‐‐‐ 14‐01‐2018 20 Done
Clear Water Tank Parapet for slab at +10.80 ‐ Zone 2 RC Slabs ‐‐‐‐ ‐‐‐‐ 04‐01‐2018 1 Done
Clear Water P H HVAC Foundation at +7.40 RC Slabs ‐‐‐‐ ‐‐‐‐ 03‐01‐2018 8 Partially Cast
Clear Water P H HVAC Foundation and plinths ( at + 11.00 ) RC Slabs ‐‐‐‐ ‐‐‐‐ 10‐01‐2018 53 Done
2/2