Académique Documents
Professionnel Documents
Culture Documents
REINFORCEMENT
Lean Concrete 2 steel man, 5 helper 2 weeks
Footings 2 mason, 2 helper 1 footing per day
Columns 1 mason, 1 helper 1 column per 1 ½ day
Walls 1 mason, 1 helper 1 room per day
Beams 2 mason, 4 helper 1 beam per 3 days
Stairs 2 steel man, 2 helper 1 riser per day
Tie Beams 2 mason, 4 helper 1 beam per 3 days
Slab decking 1 fabricator, 4 steel man,
5 helper 1 room per 2 days
CONCRETE POURING
Lean Concrete 2 mason, 3 helper 2 weeks
Columns 3 operator, 5 helper 1 column per ½ hour
Beams 3 operator, 5 helper 1 beam per ½ hour
Stairs (Crane & Bucket) 2 mason, 2 helper 1 riser per day
Tie Beams 3 operator, 8 helper 1 tie beam per ½ hour
Slab on Fill (Direct Pouring) 4 mason, 3 operator, 6
helper 1 room per day
Plastering 2 person 1 room per 2 dys
CHB LAYING
CHB Laying- Ground Floor 1 mason, 1 helper 1 room per 1 ½ day
CHB Laying- 2nd Floor – 4th Floor 1 mason, 1 helper 1 room per 1 ½ day
Plastering 1 mason, 1 helper 1 room per 2 days
TILING WORKS
30 X 30 Floor with pattern (Classroom) 2 tile setter, 2 helper 1 room per week
30 X 30 Floor with pattern (Corridor) 2 tile setter, 2 helper 1 room per week
30 X 30 Floor + Wall (T&B) 2 tile setter, 2 helper 1 room per week
PAINTING WORKS
Patching 2 painter 1 room per day
Primer 2 painter 1 room per day
Paint 2 painter 1 room per day
ROOF
Roof Trusses 2 welder, 4 helper 3 months
OTHERS
Door Installation 2 installer, 1 helper 1 room per day
Window Installation 2 installer, 1 helper 1 room per day
Fixtures Installation (Female CR) 2 installer, 2 helper 1 toilet bowl per day
Fixtures Installation (Male CR) 2 installer, 2 helper 1 urinal per 1 ½ day