CONSULTANT: DC QC Form No.

QI-04 CONTRACTOR:
(Version-2, 20/10/10)

DAILY PROGRAMME

CLIENT: Abu Dhabi Sewerage Services Company Date: 31 January 2012


PROJECT & CONTRACT NO: CONSTRUCTION WORKS ASSOCIATED LOCATION :
WITH REHABILITATION AND REPLACEMENT OF EXISTING SEWER LINES IN Sectors W2, W4, W6 , W7
ABUDHABI ISLAND AREA Contract No. O - 1792

WORK DONE , WORK TESTED & TESTING DETAILS, WORK ACCEPTED,


DESCRIPTION OF MATERIALS USED and QUANTITY
* Sector W2 – Backfilling and Reinstatement Ongoing at all areas .

* Sector W4,– Dewatering for line 4, 6 and 10 2)excavation and exposing pipe from ch 6 to 12 from chamber for
line 1 3)excavation and removal of concrete encased duct at road crossing at d53/12/1 and chipping existing
port and breaking of existing backdrop at d53/12 for line 4 4)deflection test for 3-new chamber for line 6 and
rectification of removed kerbstone and excavation to formation level of new chamber d53/13/26n/1 for line 6
5)excavation and trench sheeting from ch 7 to 13 from d53/23/1 to d53/23 for line 10

* Sector W6– at line 2 : Sheet Pilling and Excavation at h13/8C BD , at Line 3 : Excavation and expose Ext Pipe Bet
H13/17/16 to H13/17/3 , at Line 4 : Reinstatement of Ceramic Tiles Bet H13/12/3 to 2 , At line 8 : Asphalt
Cutting Bet h19 to H18 , At line 9 : Excavation works .
*Sector W7 – Excavation works at H9 BD location , Bet H9/2 to H9/1 Excavation and exposing of Ext Pipe .
Manpower:
Staf No. Total Staf No. Total Staf No. Total
Construction Director 01 Secretary 01 Charge Hand* 07
Project Manager 01 Time keeper 01 Asst. Surveyor* 01
Dy. Project Manager 01 CAD Technician 04 Mason* 03
Construction Manager 01 HSE Engineer 01 Operator* 11
Site Agent 01 Office boy 02 Pipe Fitter* 03
QS 01 Site Engineer* 03 Welder* 03
PRO 01 Foreman* 01 Carpenter* 04
Accountant 01 Safety Officer* 04 Steel Fixer* 00
QA/QC 01 Surveyor* 04 Laminator* 02
Planning Engineer 01 Chainman* 04 Watchman 05
Supervisor 01 Driver* 05 Others: (SOP) 10
Material Engineer 01 Labors* 83 Asst. Welder 01
Remarks: * Direct Staff particularly involved in mentioned sectors.

PLANT / MACHINERY: [ WG = Working; IL = Idle; BD = Break Down ]


Type Model No. WG IL BD Type Mod No. Typ M No.
Pick Up (3T) 03 03 Bob Cat 02 02
DC Pick Up 00 00 Dewatering Pumps:
Mini Bus (14 Seat)* Electrical Pumps 02 02
01 01 (Submersible)
Mini Bus (65 Seat)* 01 01 Diesel Pumps (6" & 07 07
Car (Salon) 03 03 Jetting Pumps 04 04
JCB 03 03 Overpumping Pumps:
Asphalt Cutter Elec’l Pumps 11 11
02 02 (Submersible)
Compressor Jack Hammer 03 03 Diesel Pumps (6" & 04 04
Excavator 06 06 Welding Machine 02 02
Plate Compactor 03 03 Shovel 00 00
Crane * 00 00 Jack Hammer Exc. 00 00
Tipper 03 03 Generator 00 00
Drill Excavator 00 00 Vibrator 00 00
Remarks: Common equipment with mark of “*” being utilized for the whole project.
For Contractor: Checked by (DC):

Date: Date: