QI-04 CONTRACTOR:
(Version-2, 20/10/10)
DAILY PROGRAMME
* Sector W4,– Dewatering for line 4, 6 and 10 2)excavation and exposing pipe from ch 6 to 12 from chamber for
line 1 3)excavation and removal of concrete encased duct at road crossing at d53/12/1 and chipping existing
port and breaking of existing backdrop at d53/12 for line 4 4)deflection test for 3-new chamber for line 6 and
rectification of removed kerbstone and excavation to formation level of new chamber d53/13/26n/1 for line 6
5)excavation and trench sheeting from ch 7 to 13 from d53/23/1 to d53/23 for line 10
* Sector W6– at line 2 : Sheet Pilling and Excavation at h13/8C BD , at Line 3 : Excavation and expose Ext Pipe Bet
H13/17/16 to H13/17/3 , at Line 4 : Reinstatement of Ceramic Tiles Bet H13/12/3 to 2 , At line 8 : Asphalt
Cutting Bet h19 to H18 , At line 9 : Excavation works .
*Sector W7 – Excavation works at H9 BD location , Bet H9/2 to H9/1 Excavation and exposing of Ext Pipe .
Manpower:
Staf No. Total Staf No. Total Staf No. Total
Construction Director 01 Secretary 01 Charge Hand* 07
Project Manager 01 Time keeper 01 Asst. Surveyor* 01
Dy. Project Manager 01 CAD Technician 04 Mason* 03
Construction Manager 01 HSE Engineer 01 Operator* 11
Site Agent 01 Office boy 02 Pipe Fitter* 03
QS 01 Site Engineer* 03 Welder* 03
PRO 01 Foreman* 01 Carpenter* 04
Accountant 01 Safety Officer* 04 Steel Fixer* 00
QA/QC 01 Surveyor* 04 Laminator* 02
Planning Engineer 01 Chainman* 04 Watchman 05
Supervisor 01 Driver* 05 Others: (SOP) 10
Material Engineer 01 Labors* 83 Asst. Welder 01
Remarks: * Direct Staff particularly involved in mentioned sectors.
Date: Date: