ID Task Task Name Duration Start Finish Predecessors

Half 2, 2012 Half 1, 2013 Half 2, 2013


Mode J A S O N D J F M A M J J A
1 1. GENERAL 16 days Sat 7/21/12 Tue 8/7/12
2 1.1 Stake Out 1 day Sat 7/21/12 Sat 7/21/12
3 1.2 Move In 1 day Sat 7/21/12 Sat 7/21/12
4 1.3 Mobilization 15 days Sun 7/22/12 Tue 8/7/12 3
5 1.4 Site Fencing 1 day Sun 7/22/12 Sun 7/22/12 3
6 1.5 Temporary Office 10 days Mon 7/23/12 Fri 8/3/12 5
7 1.6 Bunkhouse 4 days Sat 8/4/12 Tue 8/7/12 6
8 1.7 Temporary Warehouse 4 days Sat 8/4/12 Tue 8/7/12 6
9 1.8 Temporary Water 1 day Sat 8/4/12 Sat 8/4/12 6
10 1.9 Temporary Security 1 day Sat 8/4/12 Sat 8/4/12 6
11 1.10 Power Supply 1 day Sat 8/4/12 Sat 8/4/12 6
12 2. SITE WORKS 35 days Sun 8/5/12 Thu 9/20/12 11
13 2.1 Clearing and Grubbing 4 days Sun 8/5/12 Wed 8/8/12 11
14 2.2 Disposal of Debris 1 day Thu 8/9/12 Thu 8/9/12 13
15 2.3 Excavation 30 days Wed 8/8/12 Tue 9/18/12 4
16 3. STRUCTURAL WORKS 104 days Wed 9/19/12 Fri 2/8/13
17 3.1 Regular Footing 30 days Wed 9/19/12 Tue 10/30/12 15
18 3.2 Wall Footing 30 days Wed 9/19/12 Tue 10/30/12 15
19 3.3 Ground Floor Structural 9 days Wed 10/31/12Mon 11/12/12
20 3.3.1 Fabrication of Rebars 1 day Wed 10/31/12Wed 10/31/12
21 3.3.1.1 Slabs 1 day Wed 10/31/12Wed 10/31/12 18
22 3.3.1.2 Columns 1 day Thu 11/1/12 Thu 11/1/12 21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
23 3.3.2 Installation of Formworks 1 day Fri 11/2/12 Fri 11/2/12 22
24 3.3.3 Concrete Pouring 6 days Mon 11/5/12 Mon 11/12/12 23
25 3.4 Second Floor Structural 9 days Tue 11/13/12 Fri 11/23/12
26 3.4.1 Shoring of Table forms 1 day Tue 11/13/12 Tue 11/13/12 24
27 3.4.2 Fabrication of Rebar 1 day Wed 11/14/12Wed 11/14/12
28 3.4.3.1 Slabs 1 day Wed 11/14/12Wed 11/14/12 26
29 3.4.3.2 Beams 1 day Wed 11/14/12Wed 11/14/12 26
30 3.4.3.3 Columns 1 day Wed 11/14/12Wed 11/14/12 26
31 3.4.3 Installation of Precast Ledge 1 day Wed 11/14/12Wed 11/14/12
32 3.5.3 Installation of Formworks 1 day Thu 11/15/12 Thu 11/15/12 27
33 3.5.4 Concrete Pouring 6 days Fri 11/16/12 Fri 11/23/12 32
34 3.5 Third Floor Structural 9 days Sat 11/24/12 Wed 12/5/12
35 3.5.1 Shoring of Table forms 1 day Sat 11/24/12 Sat 11/24/12 33
36 3.5.2 Fabrication of Rebar 1 day Mon 11/26/12Mon 11/26/12 35
37 3.5.3.1 Slabs 1 day Mon 11/26/12Mon 11/26/12
38 3.5.3.2 Beams 1 day Mon 11/26/12Mon 11/26/12
39 3.5.3.3 Columns 1 day Mon 11/26/12Mon 11/26/12
40 3.5.3 Installation of Precast Ledge 1 day Mon 11/26/12Mon 11/26/12
41 3.6.3 Installation of Formworks 1 day Tue 11/27/12 Tue 11/27/12 39
42 3.6.4 Concrete Pouring 6 days Wed 11/28/12Wed 12/5/12 41
43 3.6 Fourth Floor Structural 8 days Thu 12/6/12 Mon 12/17/12
44 3.6.1 Shoring of Table forms 1 day Thu 12/6/12 Thu 12/6/12 42

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
45 3.6.2 Fabrication of Rebar 1 day Fri 12/7/12 Fri 12/7/12 44
46 3.6.3.1 Slabs 1 day Fri 12/7/12 Fri 12/7/12 44
47 3.6.3.2 Beams 1 day Fri 12/7/12 Fri 12/7/12 44
48 3.6.3.3 Columns 1 day Fri 12/7/12 Fri 12/7/12 44
49 3.6.3 Installation of Precast Ledge 1 day Fri 12/7/12 Fri 12/7/12
50 3.6.4 Installation of Formworks 1 day Sat 12/8/12 Sat 12/8/12
51 3.6.5 Concrete Pouring 6 days Mon 12/10/12Mon 12/17/12 50
52 3.7 Fifth Floor Structural 9 days Tue 12/18/12 Fri 12/28/12
53 3.7.1 Shoring of Table forms 1 day Tue 12/18/12 Tue 12/18/12 51
54 3.7.2 Fabrication of Rebar 1 day Wed 12/19/12Wed 12/19/12 53
55 3.7.3.1 Slabs 1 day Wed 12/19/12Wed 12/19/12 53
56 3.7.3.2 Beams 1 day Wed 12/19/12Wed 12/19/12 53
57 3.7.3.3 Columns 1 day Wed 12/19/12Wed 12/19/12 53
58 3.7.3 Installation of Precast Ledge 1 day Wed 12/19/12Wed 12/19/12
59 3.7.4 Installation of Formworks 1 day Thu 12/20/12 Thu 12/20/12 57
60 3.7.5 Concrete Pouring 6 days Fri 12/21/12 Fri 12/28/12 59
61 3.8 Sixth Floor Structural 9 days Mon 12/31/12Thu 1/10/13
62 3.8.1 Shoring of Table forms 1 day Mon 12/31/12Mon 12/31/12 60
63 3.8.2 Fabrication of Rebar 1 day Tue 1/1/13 Tue 1/1/13 62
64 3.8.3.1 Slabs 1 day Tue 1/1/13 Tue 1/1/13 62
65 3.8.3.2 Beams 1 day Tue 1/1/13 Tue 1/1/13 62
66 3.8.3.3 Columns 1 day Tue 1/1/13 Tue 1/1/13 62

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
67 3.8.3 Installation of Precast Ledge 1 day Tue 1/1/13 Tue 1/1/13
68 3.8.4 Installation of Formworks 1 day Wed 1/2/13 Wed 1/2/13 66
69 3.8.5 Concrete Pouring 6 days Thu 1/3/13 Thu 1/10/13 68
70 3.9 Seventh Floor Structural 9 days Fri 1/11/13 Wed 1/23/13
71 3.9.1 Shoring of Table forms 1 day Fri 1/11/13 Fri 1/11/13 69
72 3.9.2 Fabrication of Rebar 1 day Mon 1/14/13 Mon 1/14/13 71
73 3.9.3.1 Slabs 1 day Mon 1/14/13 Mon 1/14/13 71
74 3.9.3.2 Beams 1 day Mon 1/14/13 Mon 1/14/13 71
75 3.9.3.3 Columns 1 day Mon 1/14/13 Mon 1/14/13 71
76 3.9.3 Instllation of Precast Ledge 1 day Mon 1/14/13 Mon 1/14/13
77 3.9.4 Installation of Formworks 1 day Tue 1/15/13 Tue 1/15/13 75
78 3.9.5 Concrete Pouring 6 days Wed 1/16/13 Wed 1/23/13 77
79 3.10 Eight Floor Structural 9 days Thu 1/24/13 Tue 2/5/13
80 3.10.1 Shoring of Table forms 1 day Thu 1/24/13 Thu 1/24/13 78
81 3.10.2 Fabrication of Rebar 1 day Fri 1/25/13 Fri 1/25/13 80
82 3.10.3.1 Slabs 1 day Fri 1/25/13 Fri 1/25/13 80
83 3.10.3.2 Beams 1 day Fri 1/25/13 Fri 1/25/13 80
84 3.10.3.3 Columns 1 day Fri 1/25/13 Fri 1/25/13 80
85 3.10.3 Installation of Precast Ledge 1 day Fri 1/25/13 Fri 1/25/13
86 3.10.4 Installation of Formworks 1 day Mon 1/28/13 Mon 1/28/13 84
87 3.10.5 Concrete Pouring 6 days Tue 1/29/13 Tue 2/5/13 86
88 3.11 Mechanical Roof Deck 3 days Wed 2/6/13 Fri 2/8/13

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
89 3.11.1 Shoring of Table forms 1 day Wed 2/6/13 Wed 2/6/13 87
90 3.11.2 Fabrication of Formworks 1 day Thu 2/7/13 Thu 2/7/13 89
91 3.11.2 Slabs 1 day Fri 2/8/13 Fri 2/8/13 90
92 4 ARCHITECTURAL 70 days Thu 12/6/12 Wed 3/13/13
93 4.1 WET WORKS 39 days Thu 12/6/12 Tue 1/29/13
94 4.1.1 Ground Floor Wet works 2 days Thu 12/6/12 Fri 12/7/12
95 4.1.1.1 Plastering of walls 2 days Thu 12/6/12 Fri 12/7/12 42
96 4.1.2 Second Floor Wet works 7 days Mon 12/10/12Tue 12/18/12
97 4.1.2.1 Marking of partitions 1 day Mon 12/10/12Mon 12/10/12 95
98 4.1.2.2 CHB Layering 2 days Tue 12/11/12 Wed 12/12/12 97
99 4.1.2.3 Shotcrete 4 days Tue 12/11/12 Fri 12/14/12 97
100 4.1.2.4 Plastering 2 days Mon 12/17/12Tue 12/18/12 99
101 4.1.3 Third Floor Wet works 7 days Wed 12/19/12Thu 12/27/12
102 4.1.3.1 Marking of partitions 1 day Wed 12/19/12Wed 12/19/12 100
103 4.1.3.2 CHB Layering 1 day Thu 12/20/12 Thu 12/20/12 102
104 4.1.3.3 Shotcrete 4 days Thu 12/20/12 Tue 12/25/12 102
105 4.1.3.4 Plastering 2 days Wed 12/26/12Thu 12/27/12 104
106 4.1.4 Fourth Floor Wet works 7 days Mon 12/24/12Tue 1/1/13
107 4.1.4.1 Marking of partitions 1 day Mon 12/24/12Mon 12/24/12
108 4.1.4.2 CHB Layering 2 days Tue 12/25/12 Wed 12/26/12 107
109 4.1.4.3 Shotcrete 4 days Tue 12/25/12 Fri 12/28/12 107
110 4.1.4.4 Plastering 2 days Mon 12/31/12Tue 1/1/13 109

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
111 4.1.5 Fifth Floor Wet works 7 days Wed 1/2/13 Thu 1/10/13
112 4.1.5.1 Marking of partitions 1 day Wed 1/2/13 Wed 1/2/13 110
113 4.1.5.2 CHB Layering 2 days Thu 1/3/13 Fri 1/4/13 112
114 4.1.5.3 Shotcrete 4 days Thu 1/3/13 Tue 1/8/13 112
115 4.1.5.4 Plastering 2 days Wed 1/9/13 Thu 1/10/13 114
116 4.1.6 Sixth Floor Wet works 7 days Fri 1/11/13 Mon 1/21/13
117 4.1.6.1 Marking of partitions 1 day Fri 1/11/13 Fri 1/11/13 115
118 4.1.6.2 CHB Layering 2 days Mon 1/14/13 Tue 1/15/13 117
119 4.1.6.3 Shotcrete 4 days Mon 1/14/13 Thu 1/17/13 117
120 4.1.6.4 Plastering 2 days Fri 1/18/13 Mon 1/21/13 119
121 4.1.7 Seventh Floor Wet works 7 days Tue 1/22/13 Wed 1/30/13
122 4.1.7.1 Marking of partitions 1 day Tue 1/22/13 Tue 1/22/13 120
123 4.1.7.2 CHB Layering 2 days Wed 1/23/13 Thu 1/24/13 122
124 4.1.7.3 Shotcrete 4 days Wed 1/23/13 Mon 1/28/13 122
125 4.1.7.4 Plastering 2 days Tue 1/29/13 Wed 1/30/13 124
126 4.1.8 Eighth Floor Wet works 7 days Thu 1/31/13 Fri 2/8/13
127 4.1.8.1 Marking of partitions 1 day Thu 1/31/13 Thu 1/31/13 125
128 4.1.8.2 CHB Layering 1 day Fri 2/1/13 Fri 2/1/13 127
129 4.1.8.3 Shotcrete 4 days Fri 2/1/13 Wed 2/6/13 127
130 4.1.8.4 Plastering 2 days Thu 2/7/13 Fri 2/8/13 129
131 4.1.9 MRD Wet works 3 days Mon 2/11/13 Wed 2/13/13
132 4.1.9.1 Marking of partitions 1 day Mon 2/11/13 Mon 2/11/13 130

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
133 4.1.9.2 CHB Layering 1 day Tue 2/12/13 Tue 2/12/13 132
134 4.1.9.3 Plastering 2 days Tue 2/12/13 Wed 2/13/13 132
135 4.2 DRY WORKS 47 days Tue 12/11/12 Wed 2/13/13
136 4.2.1 GROUND FLOOR Dry Works 9 days Tue 12/11/12 Fri 12/21/12
137 4.2.1.1 Erection of Dry wall 2 days Tue 12/11/12 Wed 12/12/12 97
138 4.2.1.2 Gypsum board 2 days Tue 12/11/12 Wed 12/12/12 97
139 4.2.1.3 Toilet and Bath Installation 2 days Thu 12/13/12 Fri 12/14/12 138
140 4.2.1.4 Sticking Wallpaper 1 day Mon 12/17/12Mon 12/17/12 139
141 4.2.1.5 Interior Painting 2 days Mon 12/17/12Tue 12/18/12 139
142 4.2.1.6 Door Installation 1 day Wed 12/19/12Wed 12/19/12 141
143 4.2.1.7 Granite Table Top Installation 1 day Thu 12/20/12 Thu 12/20/12 142
144 4.2.1.8 Tile Layering 1 day Fri 12/21/12 Fri 12/21/12 143
145 4.2.2 Second Floor Dry Works 9 days Mon 12/24/12Thu 1/3/13
146 4.2.2.1 Erection of Dry wall 2 days Mon 12/24/12Tue 12/25/12 144
147 4.2.2.2 Gypsum board 2 days Mon 12/24/12Tue 12/25/12 144
148 4.2.2.3 Toilet and Bath Installation 2 days Wed 12/26/12Thu 12/27/12 147
149 4.2.2.4 Sticking Wallpaper 1 day Fri 12/28/12 Fri 12/28/12 148
150 4.2.2.5 Interior Painting 2 days Fri 12/28/12 Mon 12/31/12 148
151 4.2.2.6 Door Installation 1 day Tue 1/1/13 Tue 1/1/13 150
152 4.2.2.7 Granite Table Top Installation 1 day Wed 1/2/13 Wed 1/2/13 151
153 4.2.2.8 Tile Layering 1 day Thu 1/3/13 Thu 1/3/13 152
154 4.2.3 Third Floor Dry Works 9 days Thu 1/3/13 Tue 1/15/13

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
155 4.2.3.1 Erection of Dry wall 2 days Thu 1/3/13 Fri 1/4/13 152
156 4.2.3.2 Gypsum board 2 days Thu 1/3/13 Fri 1/4/13 152
157 4.2.3.3 Toilet and Bath Installation 2 days Mon 1/7/13 Tue 1/8/13 156
158 4.2.3.4 Sticking Wallpaper 1 day Wed 1/9/13 Wed 1/9/13 157
159 4.2.3.5 Interior Painting 2 days Wed 1/9/13 Thu 1/10/13 157
160 4.2.3.6 Door Installation 1 day Fri 1/11/13 Fri 1/11/13 159
161 4.2.3.7 Granite Table Top Installation 1 day Mon 1/14/13 Mon 1/14/13 160
162 4.2.3.8 Tile Layering 1 day Tue 1/15/13 Tue 1/15/13 161
163 4.2.4 Fourth Floor Dry Works 9 days Tue 1/15/13 Fri 1/25/13
164 4.2.4.1 Erection of Dry wall 2 days Tue 1/15/13 Wed 1/16/13 161
165 4.2.4.2 Gypsum board 2 days Tue 1/15/13 Wed 1/16/13 161
166 4.2.4.3 Toilet and Bath Installation 2 days Thu 1/17/13 Fri 1/18/13 165
167 4.2.4.4 Sticking Wallpaper 1 day Mon 1/21/13 Mon 1/21/13 166
168 4.2.4.5 Interior Painting 2 days Mon 1/21/13 Tue 1/22/13 166
169 4.2.4.6 Door Installation 1 day Wed 1/23/13 Wed 1/23/13 168
170 4.2.4.7 Granite Table Top Installation 1 day Thu 1/24/13 Thu 1/24/13 169
171 4.2.4.8 Tile Layering 1 day Fri 1/25/13 Fri 1/25/13 170
172 4.2.5 Fifth Floor Dry Works 9 days Fri 1/25/13 Wed 2/6/13
173 4.2.5.1 Erection of Dry wall 2 days Fri 1/25/13 Mon 1/28/13 170
174 4.2.5.2 Gypsum board 2 days Fri 1/25/13 Mon 1/28/13 170
175 4.2.5.3 Toilet and Bath Installation 2 days Tue 1/29/13 Wed 1/30/13 174
176 4.2.5.4 Sticking Wallpaper 1 day Thu 1/31/13 Thu 1/31/13 175

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
177 4.2.5.5 Interior Painting 2 days Thu 1/31/13 Fri 2/1/13 175
178 4.2.5.6 Door Installation 1 day Mon 2/4/13 Mon 2/4/13 177
179 4.2.5.7 Granite Table Top Installation 1 day Tue 2/5/13 Tue 2/5/13 178
180 4.2.5.8 Tile Layering 1 day Wed 2/6/13 Wed 2/6/13 179
181 4.2.6 Sixth Floor Dry Works 9 days Wed 2/6/13 Mon 2/18/13
182 4.2.6.1 Erection of Dry wall 2 days Wed 2/6/13 Thu 2/7/13 179
183 4.2.6.2 Gypsum board 2 days Wed 2/6/13 Thu 2/7/13 179
184 4.2.6.3 Toilet and Bath Installation 2 days Fri 2/8/13 Mon 2/11/13 183
185 4.2.6.4 Sticking Wallpaper 1 day Tue 2/12/13 Tue 2/12/13 184
186 4.2.6.5 Interior Painting 2 days Tue 2/12/13 Wed 2/13/13 184
187 4.2.6.6 Door Installation 1 day Thu 2/14/13 Thu 2/14/13 186
188 4.2.6.7 Granite Table Top Installation 1 day Fri 2/15/13 Fri 2/15/13 187
189 4.2.6.8 Tile Layering 1 day Mon 2/18/13 Mon 2/18/13 188
190 4.2.7 Seventh Floor Dry Works 9 days Mon 2/18/13 Thu 2/28/13
191 4.2.7.1 Erection of Dry wall 2 days Mon 2/18/13 Tue 2/19/13 188
192 4.2.7.2 Gypsum board 2 days Mon 2/18/13 Tue 2/19/13 188
193 4.2.7.3 Toilet and Bath Installation 2 days Wed 2/20/13 Thu 2/21/13 192
194 4.2.7.4 Sticking Wallpaper 1 day Fri 2/22/13 Fri 2/22/13 193
195 4.2.7.5 Interior Painting 2 days Fri 2/22/13 Mon 2/25/13 193
196 4.2.7.6 Door Installation 1 day Tue 2/26/13 Tue 2/26/13 195
197 4.2.7.7 Granite Table Top Installation 1 day Wed 2/27/13 Wed 2/27/13 196
198 4.2.7.8 Tile Layering 1 day Thu 2/28/13 Thu 2/28/13 197

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
199 4.2.8 Eight Floor Dry Works 9 days Thu 2/28/13 Tue 3/12/13
200 4.2.8.1 Erection of Dry wall 2 days Thu 2/28/13 Fri 3/1/13 197
201 4.2.8.2 Gypsum board 2 days Thu 2/28/13 Fri 3/1/13 197
202 4.2.8.3 Toilet and Bath Installation 2 days Mon 3/4/13 Tue 3/5/13 201
203 4.2.8.4 Sticking Wallpaper 1 day Wed 3/6/13 Wed 3/6/13 202
204 4.2.8.5 Interior Painting 2 days Wed 3/6/13 Thu 3/7/13 202
205 4.2.8.6 Door Installation 1 day Fri 3/8/13 Fri 3/8/13 204
206 4.2.8.7 Granite Table Top Installation 1 day Mon 3/11/13 Mon 3/11/13 205
207 4.2.8.8 Tile Layering 1 day Tue 3/12/13 Tue 3/12/13 206
208 4.2.9 MRD Dry Works 1 day Wed 3/13/13 Wed 3/13/13
209 4.2.9.1 Door Installation 1 day Wed 3/13/13 Wed 3/13/13 207
210 5 MEPFS Works
211 5.1 Mechanical Works 9 days Wed 1/16/13 Sat 1/26/13
212 5.1.1 Ground Floor Mechanical Works 2 days Wed 1/16/13 Thu 1/17/13
213 5.1.1.1 Heat, Ventilating, and Air Condition 1 day Wed 1/16/13 Wed 1/16/13 173
214 5.1.1.2 Exhaust fan and Accessories Installation 1 day Thu 1/17/13 Thu 1/17/13 213

215 5.1.2 Second Floor Mechanical Works 2 days Thu 1/17/13 Fri 1/18/13
216 5.1.2.1 Heat, Ventilating, and Air Condition 1 day Thu 1/17/13 Thu 1/17/13 213
217 5.1.2.2 Exhaust fan and Accessories Installation 1 day Fri 1/18/13 Fri 1/18/13 216

218 5.1.3 Third Floor Mechanical Works 2 days Fri 1/18/13 Sat 1/19/13
219 5.1.3.1 Heat, Ventilating, and Air Condition 1 day Fri 1/18/13 Fri 1/18/13 216

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
220 5.1.3.2 Exhaust fan and Accessories Installation 1 day Sat 1/19/13 Sat 1/19/13

221 5.1.4 Fourth Floor Mechanical Works 2 days Mon 1/21/13 Tue 1/22/13
222 5.1.4.1 Heat, Ventilating, and Air Condition 1 day Mon 1/21/13 Mon 1/21/13 219
223 5.1.4.2 Exhaust fan and Accessories Installation 1 day Tue 1/22/13 Tue 1/22/13 222

224 5.1.5 Fifth Floor Mechanical Works 2 days Tue 1/22/13 Wed 1/23/13
225 5.1.5.1 Heat, Ventilating, and Air Condition 1 day Tue 1/22/13 Tue 1/22/13 222
226 5.1.5.2 Exhaust fan and Accessories Installation 1 day Wed 1/23/13 Wed 1/23/13 225

227 5.1.6 Sixth Floor Mechanical Works 2 days Wed 1/23/13 Thu 1/24/13
228 5.1.6.1 Heat, Ventilating, and Air Condition 1 day Wed 1/23/13 Wed 1/23/13 225
229 5.1.6.2 Exhaust fan and Accessories Installation 1 day Thu 1/24/13 Thu 1/24/13 228

230 5.1.7 Seventh Floor Mechanical Works 2 days Thu 1/24/13 Fri 1/25/13
231 5.1.7.1 Heat, Ventilating, and Air Condition 1 day Thu 1/24/13 Thu 1/24/13 228
232 5.1.7.2 Exhaust fan and Accessories Installation 1 day Fri 1/25/13 Fri 1/25/13 231

233 5.1.8 Eight Floor Mechanical Works 2 days Fri 1/25/13 Sat 1/26/13
234 5.1.8.1 Heat, Ventilating, and Air Condition 1 day Fri 1/25/13 Fri 1/25/13 231
235 5.1.8.2 Exhaust fan and Accessories Installation 1 day Sat 1/26/13 Sat 1/26/13

236 6.1 Plumbing Works 64 days Wed 10/31/12Fri 1/25/13


237 6.1.1 Ground Floor Plumbing Works 1 day Wed 10/31/12Wed 10/31/12
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
238 6.1.1.1 Pipe Sleeves Installation 1 day Wed 10/31/12Wed 10/31/12
239 6.1.1.2 Storm Drainage System 1 day Wed 10/31/12Wed 10/31/12
240 6.1.1.3 Plumbing Fixtures Installation 1 day Wed 10/31/12Wed 10/31/12
241 6.1.1.4 Sanitary Pipes Installation 1 day Wed 10/31/12Wed 10/31/12
242 6.1.1.5 Sanitary Fixtures Installation 1 day Wed 10/31/12Wed 10/31/12
243 6.1.2 Second Floor Plumbing Works 1 day Wed 11/14/12Wed 11/14/12
244 6.1.2.1 Pipe Sleeves Installation 1 day Wed 11/14/12Wed 11/14/12
245 6.1.2.2 Storm Drainage System 1 day Wed 11/14/12Wed 11/14/12
246 6.1.2.3 Plumbing Fixtures Installation 1 day Wed 11/14/12Wed 11/14/12
247 6.1.2.4 Sanitary Pipes Installation 1 day Wed 11/14/12Wed 11/14/12
248 6.1.2.5 Sanitary Fixtures Installation 1 day Wed 11/14/12Wed 11/14/12
249 6.1.3 Third Floor Plumbing Works 1 day Mon 11/26/12Mon 11/26/12
250 6.1.3.1 Pipe Sleeves Installation 1 day Mon 11/26/12Mon 11/26/12
251 6.1.3.2 Storm Drainage System 1 day Mon 11/26/12Mon 11/26/12
252 6.1.3.3 Plumbing Fixtures Installation 1 day Mon 11/26/12Mon 11/26/12
253 6.1.3.4 Sanitary Pipes Installation 1 day Mon 11/26/12Mon 11/26/12
254 6.1.3.5 Sanitary Fixtures Installation 1 day Mon 11/26/12Mon 11/26/12
255 6.1.4 Fourth Floor Plumbing Works 1 day Fri 12/7/12 Fri 12/7/12
256 6.1.4.1 Pipe Sleeves Installation 1 day Fri 12/7/12 Fri 12/7/12
257 6.1.4.2 Storm Drainage System 1 day Fri 12/7/12 Fri 12/7/12
258 6.1.4.3 Plumbing Fixtures Installation 1 day Fri 12/7/12 Fri 12/7/12
259 6.1.4.4 Sanitary Pipes Installation 1 day Fri 12/7/12 Fri 12/7/12

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
260 6.1.4.5 Sanitary Fixtures Installation 1 day Fri 12/7/12 Fri 12/7/12
261 6.1.5 Fifth Floor Plumbing Works 1 day Wed 12/19/12Wed 12/19/12
262 6.1.5.1 Pipe Sleeves Installation 1 day Wed 12/19/12Wed 12/19/12
263 6.1.5.2 Storm Drainage System 1 day Wed 12/19/12Wed 12/19/12
264 6.1.5.3 Plumbing Fixtures Installation 1 day Wed 12/19/12Wed 12/19/12
265 6.1.5.4 Sanitary Pipes Installation 1 day Wed 12/19/12Wed 12/19/12
266 6.1.5.5 Sanitary Fixtures Installation 1 day Wed 12/19/12Wed 12/19/12
267 6.1.6 Sixth Floor Plumbing Works 1 day Tue 1/1/13 Tue 1/1/13
268 6.1.6.1 Pipe Sleeves Installation 1 day Tue 1/1/13 Tue 1/1/13
269 6.1.6.2 Storm Drainage System 1 day Tue 1/1/13 Tue 1/1/13
270 6.1.6.3 Plumbing Fixtures Installation 1 day Tue 1/1/13 Tue 1/1/13
271 6.1.6.4 Sanitary Pipes Installation 1 day Tue 1/1/13 Tue 1/1/13
272 6.1.6.5 Sanitary Fixtures Installation 1 day Tue 1/1/13 Tue 1/1/13
273 6.1.7 Seventh Floor Plumbing Works 1 day Mon 1/14/13 Mon 1/14/13
274 6.1.7.1 Pipe Sleeves Installation 1 day Mon 1/14/13 Mon 1/14/13
275 6.1.7.2 Storm Drainage System 1 day Mon 1/14/13 Mon 1/14/13
276 6.1.7.3 Plumbing Fixtures Installation 1 day Mon 1/14/13 Mon 1/14/13
277 6.1.7.4 Sanitary Pipes Installation 1 day Mon 1/14/13 Mon 1/14/13
278 6.1.7.5 Sanitary Fixtures Installation 1 day Mon 1/14/13 Mon 1/14/13
279 6.1.8 Eighth Floor Plumbing Works 1 day Fri 1/25/13 Fri 1/25/13
280 6.1.8.1 Pipe Sleeves Installation 1 day Fri 1/25/13 Fri 1/25/13
281 6.1.8.2 Storm Drainage System 1 day Fri 1/25/13 Fri 1/25/13

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
282 6.1.8.3 Plumbing Fixtures Installation 1 day Fri 1/25/13 Fri 1/25/13
283 6.1.8.4 Sanitary Pipes Installation 1 day Fri 1/25/13 Fri 1/25/13
284 6.1.8.5 Sanitary Fixtures Installation 1 day Fri 1/25/13 Fri 1/25/13
285 7.1 EXGA Works
286 7.1.1 Material Procurement GF-8th Floor 23 days Thu 2/28/13 Mon 4/1/13
287 7.1.1.1 Aluminum 23 days Fri 3/1/13 Tue 4/2/13 198
288 7.1.1.1.1 Purchasing and Ordering 15 days Fri 3/1/13 Thu 3/21/13 198
289 7.1.1.1.2 Delivery 8 days Fri 3/22/13 Tue 4/2/13 288
290 7.1.1.2 Glass 23 days Fri 3/1/13 Tue 4/2/13 198
291 7.1.1.2.1 Purchasing and Ordering 15 days Fri 3/1/13 Thu 3/21/13 198
292 7.1.1.2.2 Delivery 8 days Fri 3/22/13 Tue 4/2/13 291
293 7.1.1.3 Embed 16 days Wed 4/3/13 Wed 4/24/13
294 7.1.1.3.1 Ground Floor 2 days Wed 4/3/13 Thu 4/4/13 292
295 7.1.1.3.2 Second Floor 2 days Fri 4/5/13 Mon 4/8/13 294
296 7.1.1.3.3 Third Floor 2 days Tue 4/9/13 Wed 4/10/13 295
297 7.1.1.3.4 Fourth Floor 2 days Thu 4/11/13 Fri 4/12/13 296
298 7.1.1.3.5 Fifth Floor 2 days Mon 4/15/13 Tue 4/16/13 297
299 7.1.1.3.6 Sixth Floor 2 days Wed 4/17/13 Thu 4/18/13 298
300 7.1.1.3.7 Seventh Floor 2 days Fri 4/19/13 Mon 4/22/13 299
301 7.1.1.3.8 Eight Floor 2 days Tue 4/23/13 Wed 4/24/13 300
302 8.1 Punchlisting 120 days Mon 4/15/13 Fri 9/27/13
303 8.1.1 Ground Floor 15 days Mon 4/15/13 Fri 5/3/13 297

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
304 8.1.2 Second Floor 15 days Mon 5/6/13 Fri 5/24/13 303
305 8.1.3 Third Floor 15 days Mon 5/27/13 Fri 6/14/13 304
306 8.1.4 Fourth Floor 15 days Mon 6/17/13 Fri 7/5/13 305
307 8.1.5 Fifth Floor 15 days Mon 7/8/13 Fri 7/26/13 306
308 8.1.6 Sixth Floor 15 days Mon 7/29/13 Fri 8/16/13 307
309 8.1.7 Seventh Floor 15 days Mon 8/19/13 Fri 9/6/13 308
310 8.1.8 Eight Floor 15 days Mon 9/9/13 Fri 9/27/13 309
311 9.1 HANDOVER 84 days Mon 7/8/13 Thu 10/31/13
312 9.1.1 Ground Floor 6 days Mon 7/8/13 Mon 7/15/13 306
313 9.1.2 Second Floor 6 days Mon 7/29/13 Mon 8/5/13 307
314 9.1.3 Third Floor 6 days Mon 8/19/13 Mon 8/26/13 308
315 9.1.4 Fourth Floor 6 days Mon 9/9/13 Mon 9/16/13 309
316 9.1.5 Fifth Floor 6 days Mon 9/30/13 Mon 10/7/13 310
317 9.1.6 Sixth Floor 6 days Tue 10/8/13 Tue 10/15/13 316
318 9.1.7 Seventh Floor 6 days Wed 10/16/13Wed 10/23/13 317
319 9.1.8 Eight Floor 6 days Thu 10/24/13 Thu 10/31/13 318
320

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 16
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 17
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 18
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 19
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 20
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 21
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 22
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 23
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 24
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 25
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 26
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 27
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 28
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 29
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: CE159 SCHEDULING
Summary Manual Summary Rollup Progress
Date: Fri 9/15/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only