Académique Documents
Professionnel Documents
Culture Documents
Page 1
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
23 3.3.2 Installation of Formworks 1 day Fri 11/2/12 Fri 11/2/12 22
24 3.3.3 Concrete Pouring 6 days Mon 11/5/12 Mon 11/12/12 23
25 3.4 Second Floor Structural 9 days Tue 11/13/12 Fri 11/23/12
26 3.4.1 Shoring of Table forms 1 day Tue 11/13/12 Tue 11/13/12 24
27 3.4.2 Fabrication of Rebar 1 day Wed 11/14/12Wed 11/14/12
28 3.4.3.1 Slabs 1 day Wed 11/14/12Wed 11/14/12 26
29 3.4.3.2 Beams 1 day Wed 11/14/12Wed 11/14/12 26
30 3.4.3.3 Columns 1 day Wed 11/14/12Wed 11/14/12 26
31 3.4.3 Installation of Precast Ledge 1 day Wed 11/14/12Wed 11/14/12
32 3.5.3 Installation of Formworks 1 day Thu 11/15/12 Thu 11/15/12 27
33 3.5.4 Concrete Pouring 6 days Fri 11/16/12 Fri 11/23/12 32
34 3.5 Third Floor Structural 9 days Sat 11/24/12 Wed 12/5/12
35 3.5.1 Shoring of Table forms 1 day Sat 11/24/12 Sat 11/24/12 33
36 3.5.2 Fabrication of Rebar 1 day Mon 11/26/12Mon 11/26/12 35
37 3.5.3.1 Slabs 1 day Mon 11/26/12Mon 11/26/12
38 3.5.3.2 Beams 1 day Mon 11/26/12Mon 11/26/12
39 3.5.3.3 Columns 1 day Mon 11/26/12Mon 11/26/12
40 3.5.3 Installation of Precast Ledge 1 day Mon 11/26/12Mon 11/26/12
41 3.6.3 Installation of Formworks 1 day Tue 11/27/12 Tue 11/27/12 39
42 3.6.4 Concrete Pouring 6 days Wed 11/28/12Wed 12/5/12 41
43 3.6 Fourth Floor Structural 8 days Thu 12/6/12 Mon 12/17/12
44 3.6.1 Shoring of Table forms 1 day Thu 12/6/12 Thu 12/6/12 42
Page 2
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
45 3.6.2 Fabrication of Rebar 1 day Fri 12/7/12 Fri 12/7/12 44
46 3.6.3.1 Slabs 1 day Fri 12/7/12 Fri 12/7/12 44
47 3.6.3.2 Beams 1 day Fri 12/7/12 Fri 12/7/12 44
48 3.6.3.3 Columns 1 day Fri 12/7/12 Fri 12/7/12 44
49 3.6.3 Installation of Precast Ledge 1 day Fri 12/7/12 Fri 12/7/12
50 3.6.4 Installation of Formworks 1 day Sat 12/8/12 Sat 12/8/12
51 3.6.5 Concrete Pouring 6 days Mon 12/10/12Mon 12/17/12 50
52 3.7 Fifth Floor Structural 9 days Tue 12/18/12 Fri 12/28/12
53 3.7.1 Shoring of Table forms 1 day Tue 12/18/12 Tue 12/18/12 51
54 3.7.2 Fabrication of Rebar 1 day Wed 12/19/12Wed 12/19/12 53
55 3.7.3.1 Slabs 1 day Wed 12/19/12Wed 12/19/12 53
56 3.7.3.2 Beams 1 day Wed 12/19/12Wed 12/19/12 53
57 3.7.3.3 Columns 1 day Wed 12/19/12Wed 12/19/12 53
58 3.7.3 Installation of Precast Ledge 1 day Wed 12/19/12Wed 12/19/12
59 3.7.4 Installation of Formworks 1 day Thu 12/20/12 Thu 12/20/12 57
60 3.7.5 Concrete Pouring 6 days Fri 12/21/12 Fri 12/28/12 59
61 3.8 Sixth Floor Structural 9 days Mon 12/31/12Thu 1/10/13
62 3.8.1 Shoring of Table forms 1 day Mon 12/31/12Mon 12/31/12 60
63 3.8.2 Fabrication of Rebar 1 day Tue 1/1/13 Tue 1/1/13 62
64 3.8.3.1 Slabs 1 day Tue 1/1/13 Tue 1/1/13 62
65 3.8.3.2 Beams 1 day Tue 1/1/13 Tue 1/1/13 62
66 3.8.3.3 Columns 1 day Tue 1/1/13 Tue 1/1/13 62
Page 3
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
67 3.8.3 Installation of Precast Ledge 1 day Tue 1/1/13 Tue 1/1/13
68 3.8.4 Installation of Formworks 1 day Wed 1/2/13 Wed 1/2/13 66
69 3.8.5 Concrete Pouring 6 days Thu 1/3/13 Thu 1/10/13 68
70 3.9 Seventh Floor Structural 9 days Fri 1/11/13 Wed 1/23/13
71 3.9.1 Shoring of Table forms 1 day Fri 1/11/13 Fri 1/11/13 69
72 3.9.2 Fabrication of Rebar 1 day Mon 1/14/13 Mon 1/14/13 71
73 3.9.3.1 Slabs 1 day Mon 1/14/13 Mon 1/14/13 71
74 3.9.3.2 Beams 1 day Mon 1/14/13 Mon 1/14/13 71
75 3.9.3.3 Columns 1 day Mon 1/14/13 Mon 1/14/13 71
76 3.9.3 Instllation of Precast Ledge 1 day Mon 1/14/13 Mon 1/14/13
77 3.9.4 Installation of Formworks 1 day Tue 1/15/13 Tue 1/15/13 75
78 3.9.5 Concrete Pouring 6 days Wed 1/16/13 Wed 1/23/13 77
79 3.10 Eight Floor Structural 9 days Thu 1/24/13 Tue 2/5/13
80 3.10.1 Shoring of Table forms 1 day Thu 1/24/13 Thu 1/24/13 78
81 3.10.2 Fabrication of Rebar 1 day Fri 1/25/13 Fri 1/25/13 80
82 3.10.3.1 Slabs 1 day Fri 1/25/13 Fri 1/25/13 80
83 3.10.3.2 Beams 1 day Fri 1/25/13 Fri 1/25/13 80
84 3.10.3.3 Columns 1 day Fri 1/25/13 Fri 1/25/13 80
85 3.10.3 Installation of Precast Ledge 1 day Fri 1/25/13 Fri 1/25/13
86 3.10.4 Installation of Formworks 1 day Mon 1/28/13 Mon 1/28/13 84
87 3.10.5 Concrete Pouring 6 days Tue 1/29/13 Tue 2/5/13 86
88 3.11 Mechanical Roof Deck 3 days Wed 2/6/13 Fri 2/8/13
Page 4
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
89 3.11.1 Shoring of Table forms 1 day Wed 2/6/13 Wed 2/6/13 87
90 3.11.2 Fabrication of Formworks 1 day Thu 2/7/13 Thu 2/7/13 89
91 3.11.2 Slabs 1 day Fri 2/8/13 Fri 2/8/13 90
92 4 ARCHITECTURAL 70 days Thu 12/6/12 Wed 3/13/13
93 4.1 WET WORKS 39 days Thu 12/6/12 Tue 1/29/13
94 4.1.1 Ground Floor Wet works 2 days Thu 12/6/12 Fri 12/7/12
95 4.1.1.1 Plastering of walls 2 days Thu 12/6/12 Fri 12/7/12 42
96 4.1.2 Second Floor Wet works 7 days Mon 12/10/12Tue 12/18/12
97 4.1.2.1 Marking of partitions 1 day Mon 12/10/12Mon 12/10/12 95
98 4.1.2.2 CHB Layering 2 days Tue 12/11/12 Wed 12/12/12 97
99 4.1.2.3 Shotcrete 4 days Tue 12/11/12 Fri 12/14/12 97
100 4.1.2.4 Plastering 2 days Mon 12/17/12Tue 12/18/12 99
101 4.1.3 Third Floor Wet works 7 days Wed 12/19/12Thu 12/27/12
102 4.1.3.1 Marking of partitions 1 day Wed 12/19/12Wed 12/19/12 100
103 4.1.3.2 CHB Layering 1 day Thu 12/20/12 Thu 12/20/12 102
104 4.1.3.3 Shotcrete 4 days Thu 12/20/12 Tue 12/25/12 102
105 4.1.3.4 Plastering 2 days Wed 12/26/12Thu 12/27/12 104
106 4.1.4 Fourth Floor Wet works 7 days Mon 12/24/12Tue 1/1/13
107 4.1.4.1 Marking of partitions 1 day Mon 12/24/12Mon 12/24/12
108 4.1.4.2 CHB Layering 2 days Tue 12/25/12 Wed 12/26/12 107
109 4.1.4.3 Shotcrete 4 days Tue 12/25/12 Fri 12/28/12 107
110 4.1.4.4 Plastering 2 days Mon 12/31/12Tue 1/1/13 109
Page 5
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
111 4.1.5 Fifth Floor Wet works 7 days Wed 1/2/13 Thu 1/10/13
112 4.1.5.1 Marking of partitions 1 day Wed 1/2/13 Wed 1/2/13 110
113 4.1.5.2 CHB Layering 2 days Thu 1/3/13 Fri 1/4/13 112
114 4.1.5.3 Shotcrete 4 days Thu 1/3/13 Tue 1/8/13 112
115 4.1.5.4 Plastering 2 days Wed 1/9/13 Thu 1/10/13 114
116 4.1.6 Sixth Floor Wet works 7 days Fri 1/11/13 Mon 1/21/13
117 4.1.6.1 Marking of partitions 1 day Fri 1/11/13 Fri 1/11/13 115
118 4.1.6.2 CHB Layering 2 days Mon 1/14/13 Tue 1/15/13 117
119 4.1.6.3 Shotcrete 4 days Mon 1/14/13 Thu 1/17/13 117
120 4.1.6.4 Plastering 2 days Fri 1/18/13 Mon 1/21/13 119
121 4.1.7 Seventh Floor Wet works 7 days Tue 1/22/13 Wed 1/30/13
122 4.1.7.1 Marking of partitions 1 day Tue 1/22/13 Tue 1/22/13 120
123 4.1.7.2 CHB Layering 2 days Wed 1/23/13 Thu 1/24/13 122
124 4.1.7.3 Shotcrete 4 days Wed 1/23/13 Mon 1/28/13 122
125 4.1.7.4 Plastering 2 days Tue 1/29/13 Wed 1/30/13 124
126 4.1.8 Eighth Floor Wet works 7 days Thu 1/31/13 Fri 2/8/13
127 4.1.8.1 Marking of partitions 1 day Thu 1/31/13 Thu 1/31/13 125
128 4.1.8.2 CHB Layering 1 day Fri 2/1/13 Fri 2/1/13 127
129 4.1.8.3 Shotcrete 4 days Fri 2/1/13 Wed 2/6/13 127
130 4.1.8.4 Plastering 2 days Thu 2/7/13 Fri 2/8/13 129
131 4.1.9 MRD Wet works 3 days Mon 2/11/13 Wed 2/13/13
132 4.1.9.1 Marking of partitions 1 day Mon 2/11/13 Mon 2/11/13 130
Page 6
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
133 4.1.9.2 CHB Layering 1 day Tue 2/12/13 Tue 2/12/13 132
134 4.1.9.3 Plastering 2 days Tue 2/12/13 Wed 2/13/13 132
135 4.2 DRY WORKS 47 days Tue 12/11/12 Wed 2/13/13
136 4.2.1 GROUND FLOOR Dry Works 9 days Tue 12/11/12 Fri 12/21/12
137 4.2.1.1 Erection of Dry wall 2 days Tue 12/11/12 Wed 12/12/12 97
138 4.2.1.2 Gypsum board 2 days Tue 12/11/12 Wed 12/12/12 97
139 4.2.1.3 Toilet and Bath Installation 2 days Thu 12/13/12 Fri 12/14/12 138
140 4.2.1.4 Sticking Wallpaper 1 day Mon 12/17/12Mon 12/17/12 139
141 4.2.1.5 Interior Painting 2 days Mon 12/17/12Tue 12/18/12 139
142 4.2.1.6 Door Installation 1 day Wed 12/19/12Wed 12/19/12 141
143 4.2.1.7 Granite Table Top Installation 1 day Thu 12/20/12 Thu 12/20/12 142
144 4.2.1.8 Tile Layering 1 day Fri 12/21/12 Fri 12/21/12 143
145 4.2.2 Second Floor Dry Works 9 days Mon 12/24/12Thu 1/3/13
146 4.2.2.1 Erection of Dry wall 2 days Mon 12/24/12Tue 12/25/12 144
147 4.2.2.2 Gypsum board 2 days Mon 12/24/12Tue 12/25/12 144
148 4.2.2.3 Toilet and Bath Installation 2 days Wed 12/26/12Thu 12/27/12 147
149 4.2.2.4 Sticking Wallpaper 1 day Fri 12/28/12 Fri 12/28/12 148
150 4.2.2.5 Interior Painting 2 days Fri 12/28/12 Mon 12/31/12 148
151 4.2.2.6 Door Installation 1 day Tue 1/1/13 Tue 1/1/13 150
152 4.2.2.7 Granite Table Top Installation 1 day Wed 1/2/13 Wed 1/2/13 151
153 4.2.2.8 Tile Layering 1 day Thu 1/3/13 Thu 1/3/13 152
154 4.2.3 Third Floor Dry Works 9 days Thu 1/3/13 Tue 1/15/13
Page 7
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
155 4.2.3.1 Erection of Dry wall 2 days Thu 1/3/13 Fri 1/4/13 152
156 4.2.3.2 Gypsum board 2 days Thu 1/3/13 Fri 1/4/13 152
157 4.2.3.3 Toilet and Bath Installation 2 days Mon 1/7/13 Tue 1/8/13 156
158 4.2.3.4 Sticking Wallpaper 1 day Wed 1/9/13 Wed 1/9/13 157
159 4.2.3.5 Interior Painting 2 days Wed 1/9/13 Thu 1/10/13 157
160 4.2.3.6 Door Installation 1 day Fri 1/11/13 Fri 1/11/13 159
161 4.2.3.7 Granite Table Top Installation 1 day Mon 1/14/13 Mon 1/14/13 160
162 4.2.3.8 Tile Layering 1 day Tue 1/15/13 Tue 1/15/13 161
163 4.2.4 Fourth Floor Dry Works 9 days Tue 1/15/13 Fri 1/25/13
164 4.2.4.1 Erection of Dry wall 2 days Tue 1/15/13 Wed 1/16/13 161
165 4.2.4.2 Gypsum board 2 days Tue 1/15/13 Wed 1/16/13 161
166 4.2.4.3 Toilet and Bath Installation 2 days Thu 1/17/13 Fri 1/18/13 165
167 4.2.4.4 Sticking Wallpaper 1 day Mon 1/21/13 Mon 1/21/13 166
168 4.2.4.5 Interior Painting 2 days Mon 1/21/13 Tue 1/22/13 166
169 4.2.4.6 Door Installation 1 day Wed 1/23/13 Wed 1/23/13 168
170 4.2.4.7 Granite Table Top Installation 1 day Thu 1/24/13 Thu 1/24/13 169
171 4.2.4.8 Tile Layering 1 day Fri 1/25/13 Fri 1/25/13 170
172 4.2.5 Fifth Floor Dry Works 9 days Fri 1/25/13 Wed 2/6/13
173 4.2.5.1 Erection of Dry wall 2 days Fri 1/25/13 Mon 1/28/13 170
174 4.2.5.2 Gypsum board 2 days Fri 1/25/13 Mon 1/28/13 170
175 4.2.5.3 Toilet and Bath Installation 2 days Tue 1/29/13 Wed 1/30/13 174
176 4.2.5.4 Sticking Wallpaper 1 day Thu 1/31/13 Thu 1/31/13 175
Page 8
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
177 4.2.5.5 Interior Painting 2 days Thu 1/31/13 Fri 2/1/13 175
178 4.2.5.6 Door Installation 1 day Mon 2/4/13 Mon 2/4/13 177
179 4.2.5.7 Granite Table Top Installation 1 day Tue 2/5/13 Tue 2/5/13 178
180 4.2.5.8 Tile Layering 1 day Wed 2/6/13 Wed 2/6/13 179
181 4.2.6 Sixth Floor Dry Works 9 days Wed 2/6/13 Mon 2/18/13
182 4.2.6.1 Erection of Dry wall 2 days Wed 2/6/13 Thu 2/7/13 179
183 4.2.6.2 Gypsum board 2 days Wed 2/6/13 Thu 2/7/13 179
184 4.2.6.3 Toilet and Bath Installation 2 days Fri 2/8/13 Mon 2/11/13 183
185 4.2.6.4 Sticking Wallpaper 1 day Tue 2/12/13 Tue 2/12/13 184
186 4.2.6.5 Interior Painting 2 days Tue 2/12/13 Wed 2/13/13 184
187 4.2.6.6 Door Installation 1 day Thu 2/14/13 Thu 2/14/13 186
188 4.2.6.7 Granite Table Top Installation 1 day Fri 2/15/13 Fri 2/15/13 187
189 4.2.6.8 Tile Layering 1 day Mon 2/18/13 Mon 2/18/13 188
190 4.2.7 Seventh Floor Dry Works 9 days Mon 2/18/13 Thu 2/28/13
191 4.2.7.1 Erection of Dry wall 2 days Mon 2/18/13 Tue 2/19/13 188
192 4.2.7.2 Gypsum board 2 days Mon 2/18/13 Tue 2/19/13 188
193 4.2.7.3 Toilet and Bath Installation 2 days Wed 2/20/13 Thu 2/21/13 192
194 4.2.7.4 Sticking Wallpaper 1 day Fri 2/22/13 Fri 2/22/13 193
195 4.2.7.5 Interior Painting 2 days Fri 2/22/13 Mon 2/25/13 193
196 4.2.7.6 Door Installation 1 day Tue 2/26/13 Tue 2/26/13 195
197 4.2.7.7 Granite Table Top Installation 1 day Wed 2/27/13 Wed 2/27/13 196
198 4.2.7.8 Tile Layering 1 day Thu 2/28/13 Thu 2/28/13 197
Page 9
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
199 4.2.8 Eight Floor Dry Works 9 days Thu 2/28/13 Tue 3/12/13
200 4.2.8.1 Erection of Dry wall 2 days Thu 2/28/13 Fri 3/1/13 197
201 4.2.8.2 Gypsum board 2 days Thu 2/28/13 Fri 3/1/13 197
202 4.2.8.3 Toilet and Bath Installation 2 days Mon 3/4/13 Tue 3/5/13 201
203 4.2.8.4 Sticking Wallpaper 1 day Wed 3/6/13 Wed 3/6/13 202
204 4.2.8.5 Interior Painting 2 days Wed 3/6/13 Thu 3/7/13 202
205 4.2.8.6 Door Installation 1 day Fri 3/8/13 Fri 3/8/13 204
206 4.2.8.7 Granite Table Top Installation 1 day Mon 3/11/13 Mon 3/11/13 205
207 4.2.8.8 Tile Layering 1 day Tue 3/12/13 Tue 3/12/13 206
208 4.2.9 MRD Dry Works 1 day Wed 3/13/13 Wed 3/13/13
209 4.2.9.1 Door Installation 1 day Wed 3/13/13 Wed 3/13/13 207
210 5 MEPFS Works
211 5.1 Mechanical Works 9 days Wed 1/16/13 Sat 1/26/13
212 5.1.1 Ground Floor Mechanical Works 2 days Wed 1/16/13 Thu 1/17/13
213 5.1.1.1 Heat, Ventilating, and Air Condition 1 day Wed 1/16/13 Wed 1/16/13 173
214 5.1.1.2 Exhaust fan and Accessories Installation 1 day Thu 1/17/13 Thu 1/17/13 213
215 5.1.2 Second Floor Mechanical Works 2 days Thu 1/17/13 Fri 1/18/13
216 5.1.2.1 Heat, Ventilating, and Air Condition 1 day Thu 1/17/13 Thu 1/17/13 213
217 5.1.2.2 Exhaust fan and Accessories Installation 1 day Fri 1/18/13 Fri 1/18/13 216
218 5.1.3 Third Floor Mechanical Works 2 days Fri 1/18/13 Sat 1/19/13
219 5.1.3.1 Heat, Ventilating, and Air Condition 1 day Fri 1/18/13 Fri 1/18/13 216
Page 10
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
220 5.1.3.2 Exhaust fan and Accessories Installation 1 day Sat 1/19/13 Sat 1/19/13
221 5.1.4 Fourth Floor Mechanical Works 2 days Mon 1/21/13 Tue 1/22/13
222 5.1.4.1 Heat, Ventilating, and Air Condition 1 day Mon 1/21/13 Mon 1/21/13 219
223 5.1.4.2 Exhaust fan and Accessories Installation 1 day Tue 1/22/13 Tue 1/22/13 222
224 5.1.5 Fifth Floor Mechanical Works 2 days Tue 1/22/13 Wed 1/23/13
225 5.1.5.1 Heat, Ventilating, and Air Condition 1 day Tue 1/22/13 Tue 1/22/13 222
226 5.1.5.2 Exhaust fan and Accessories Installation 1 day Wed 1/23/13 Wed 1/23/13 225
227 5.1.6 Sixth Floor Mechanical Works 2 days Wed 1/23/13 Thu 1/24/13
228 5.1.6.1 Heat, Ventilating, and Air Condition 1 day Wed 1/23/13 Wed 1/23/13 225
229 5.1.6.2 Exhaust fan and Accessories Installation 1 day Thu 1/24/13 Thu 1/24/13 228
230 5.1.7 Seventh Floor Mechanical Works 2 days Thu 1/24/13 Fri 1/25/13
231 5.1.7.1 Heat, Ventilating, and Air Condition 1 day Thu 1/24/13 Thu 1/24/13 228
232 5.1.7.2 Exhaust fan and Accessories Installation 1 day Fri 1/25/13 Fri 1/25/13 231
233 5.1.8 Eight Floor Mechanical Works 2 days Fri 1/25/13 Sat 1/26/13
234 5.1.8.1 Heat, Ventilating, and Air Condition 1 day Fri 1/25/13 Fri 1/25/13 231
235 5.1.8.2 Exhaust fan and Accessories Installation 1 day Sat 1/26/13 Sat 1/26/13
Page 11
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
238 6.1.1.1 Pipe Sleeves Installation 1 day Wed 10/31/12Wed 10/31/12
239 6.1.1.2 Storm Drainage System 1 day Wed 10/31/12Wed 10/31/12
240 6.1.1.3 Plumbing Fixtures Installation 1 day Wed 10/31/12Wed 10/31/12
241 6.1.1.4 Sanitary Pipes Installation 1 day Wed 10/31/12Wed 10/31/12
242 6.1.1.5 Sanitary Fixtures Installation 1 day Wed 10/31/12Wed 10/31/12
243 6.1.2 Second Floor Plumbing Works 1 day Wed 11/14/12Wed 11/14/12
244 6.1.2.1 Pipe Sleeves Installation 1 day Wed 11/14/12Wed 11/14/12
245 6.1.2.2 Storm Drainage System 1 day Wed 11/14/12Wed 11/14/12
246 6.1.2.3 Plumbing Fixtures Installation 1 day Wed 11/14/12Wed 11/14/12
247 6.1.2.4 Sanitary Pipes Installation 1 day Wed 11/14/12Wed 11/14/12
248 6.1.2.5 Sanitary Fixtures Installation 1 day Wed 11/14/12Wed 11/14/12
249 6.1.3 Third Floor Plumbing Works 1 day Mon 11/26/12Mon 11/26/12
250 6.1.3.1 Pipe Sleeves Installation 1 day Mon 11/26/12Mon 11/26/12
251 6.1.3.2 Storm Drainage System 1 day Mon 11/26/12Mon 11/26/12
252 6.1.3.3 Plumbing Fixtures Installation 1 day Mon 11/26/12Mon 11/26/12
253 6.1.3.4 Sanitary Pipes Installation 1 day Mon 11/26/12Mon 11/26/12
254 6.1.3.5 Sanitary Fixtures Installation 1 day Mon 11/26/12Mon 11/26/12
255 6.1.4 Fourth Floor Plumbing Works 1 day Fri 12/7/12 Fri 12/7/12
256 6.1.4.1 Pipe Sleeves Installation 1 day Fri 12/7/12 Fri 12/7/12
257 6.1.4.2 Storm Drainage System 1 day Fri 12/7/12 Fri 12/7/12
258 6.1.4.3 Plumbing Fixtures Installation 1 day Fri 12/7/12 Fri 12/7/12
259 6.1.4.4 Sanitary Pipes Installation 1 day Fri 12/7/12 Fri 12/7/12
Page 12
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
260 6.1.4.5 Sanitary Fixtures Installation 1 day Fri 12/7/12 Fri 12/7/12
261 6.1.5 Fifth Floor Plumbing Works 1 day Wed 12/19/12Wed 12/19/12
262 6.1.5.1 Pipe Sleeves Installation 1 day Wed 12/19/12Wed 12/19/12
263 6.1.5.2 Storm Drainage System 1 day Wed 12/19/12Wed 12/19/12
264 6.1.5.3 Plumbing Fixtures Installation 1 day Wed 12/19/12Wed 12/19/12
265 6.1.5.4 Sanitary Pipes Installation 1 day Wed 12/19/12Wed 12/19/12
266 6.1.5.5 Sanitary Fixtures Installation 1 day Wed 12/19/12Wed 12/19/12
267 6.1.6 Sixth Floor Plumbing Works 1 day Tue 1/1/13 Tue 1/1/13
268 6.1.6.1 Pipe Sleeves Installation 1 day Tue 1/1/13 Tue 1/1/13
269 6.1.6.2 Storm Drainage System 1 day Tue 1/1/13 Tue 1/1/13
270 6.1.6.3 Plumbing Fixtures Installation 1 day Tue 1/1/13 Tue 1/1/13
271 6.1.6.4 Sanitary Pipes Installation 1 day Tue 1/1/13 Tue 1/1/13
272 6.1.6.5 Sanitary Fixtures Installation 1 day Tue 1/1/13 Tue 1/1/13
273 6.1.7 Seventh Floor Plumbing Works 1 day Mon 1/14/13 Mon 1/14/13
274 6.1.7.1 Pipe Sleeves Installation 1 day Mon 1/14/13 Mon 1/14/13
275 6.1.7.2 Storm Drainage System 1 day Mon 1/14/13 Mon 1/14/13
276 6.1.7.3 Plumbing Fixtures Installation 1 day Mon 1/14/13 Mon 1/14/13
277 6.1.7.4 Sanitary Pipes Installation 1 day Mon 1/14/13 Mon 1/14/13
278 6.1.7.5 Sanitary Fixtures Installation 1 day Mon 1/14/13 Mon 1/14/13
279 6.1.8 Eighth Floor Plumbing Works 1 day Fri 1/25/13 Fri 1/25/13
280 6.1.8.1 Pipe Sleeves Installation 1 day Fri 1/25/13 Fri 1/25/13
281 6.1.8.2 Storm Drainage System 1 day Fri 1/25/13 Fri 1/25/13
Page 13
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
282 6.1.8.3 Plumbing Fixtures Installation 1 day Fri 1/25/13 Fri 1/25/13
283 6.1.8.4 Sanitary Pipes Installation 1 day Fri 1/25/13 Fri 1/25/13
284 6.1.8.5 Sanitary Fixtures Installation 1 day Fri 1/25/13 Fri 1/25/13
285 7.1 EXGA Works
286 7.1.1 Material Procurement GF-8th Floor 23 days Thu 2/28/13 Mon 4/1/13
287 7.1.1.1 Aluminum 23 days Fri 3/1/13 Tue 4/2/13 198
288 7.1.1.1.1 Purchasing and Ordering 15 days Fri 3/1/13 Thu 3/21/13 198
289 7.1.1.1.2 Delivery 8 days Fri 3/22/13 Tue 4/2/13 288
290 7.1.1.2 Glass 23 days Fri 3/1/13 Tue 4/2/13 198
291 7.1.1.2.1 Purchasing and Ordering 15 days Fri 3/1/13 Thu 3/21/13 198
292 7.1.1.2.2 Delivery 8 days Fri 3/22/13 Tue 4/2/13 291
293 7.1.1.3 Embed 16 days Wed 4/3/13 Wed 4/24/13
294 7.1.1.3.1 Ground Floor 2 days Wed 4/3/13 Thu 4/4/13 292
295 7.1.1.3.2 Second Floor 2 days Fri 4/5/13 Mon 4/8/13 294
296 7.1.1.3.3 Third Floor 2 days Tue 4/9/13 Wed 4/10/13 295
297 7.1.1.3.4 Fourth Floor 2 days Thu 4/11/13 Fri 4/12/13 296
298 7.1.1.3.5 Fifth Floor 2 days Mon 4/15/13 Tue 4/16/13 297
299 7.1.1.3.6 Sixth Floor 2 days Wed 4/17/13 Thu 4/18/13 298
300 7.1.1.3.7 Seventh Floor 2 days Fri 4/19/13 Mon 4/22/13 299
301 7.1.1.3.8 Eight Floor 2 days Tue 4/23/13 Wed 4/24/13 300
302 8.1 Punchlisting 120 days Mon 4/15/13 Fri 9/27/13
303 8.1.1 Ground Floor 15 days Mon 4/15/13 Fri 5/3/13 297
Page 14
ID Task Task Name Duration Start Finish Predecessors
Half 2, 2012 Half 1, 2013 Half 2, 2013
Mode J A S O N D J F M A M J J A
304 8.1.2 Second Floor 15 days Mon 5/6/13 Fri 5/24/13 303
305 8.1.3 Third Floor 15 days Mon 5/27/13 Fri 6/14/13 304
306 8.1.4 Fourth Floor 15 days Mon 6/17/13 Fri 7/5/13 305
307 8.1.5 Fifth Floor 15 days Mon 7/8/13 Fri 7/26/13 306
308 8.1.6 Sixth Floor 15 days Mon 7/29/13 Fri 8/16/13 307
309 8.1.7 Seventh Floor 15 days Mon 8/19/13 Fri 9/6/13 308
310 8.1.8 Eight Floor 15 days Mon 9/9/13 Fri 9/27/13 309
311 9.1 HANDOVER 84 days Mon 7/8/13 Thu 10/31/13
312 9.1.1 Ground Floor 6 days Mon 7/8/13 Mon 7/15/13 306
313 9.1.2 Second Floor 6 days Mon 7/29/13 Mon 8/5/13 307
314 9.1.3 Third Floor 6 days Mon 8/19/13 Mon 8/26/13 308
315 9.1.4 Fourth Floor 6 days Mon 9/9/13 Mon 9/16/13 309
316 9.1.5 Fifth Floor 6 days Mon 9/30/13 Mon 10/7/13 310
317 9.1.6 Sixth Floor 6 days Tue 10/8/13 Tue 10/15/13 316
318 9.1.7 Seventh Floor 6 days Wed 10/16/13Wed 10/23/13 317
319 9.1.8 Eight Floor 6 days Thu 10/24/13 Thu 10/31/13 318
320
Page 15
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 16
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 17
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 18
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 19
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 20
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 21
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 22
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 23
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 24
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 25
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 26
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 27
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 28
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 29
Half 2, 2013 Half 1, 2014 Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017 Half 2, 2017
A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Page 30