Vous êtes sur la page 1sur 58

[G.R. NO. 135362. December 13, 1999] ARTICLE VI. ARBITRATION.

All cases of dispute between CONTRACTOR and OWNERS representative shall be


HEIRS OF AUGUSTO L. SALAS, JR., petitioners, vs. LAPERAL REALTY referred to the committee represented by:
CORPORATION, respondents.
a. One representative of the OWNER;
b. One representative of the CONTRACTOR;
DECISION c. One representative acceptable to both OWNER and CONTRACTOR.[8]
DE LEON, JR., J.:
On May 5, 1998, respondent spouses Abrajano and Lava and respondent
Before us is a petition for review on certiorari of the Order[1] of Branch 85 of Dacillo filed a Joint Answer with Counterclaim and Crossclaim[9] praying for
the Regional Trial Court of Lipa City[2] dismissing petitioners complaint[3] for dismissal of petitioners Complaint for the same reason.
rescission of several sale transactions involving land owned by Augusto L. Salas, Jr.,
their predecessor-in-interest, on the ground that they failed to first resort to On August 9, 1998, the trial court issued the herein assailed Order dismissing
arbitration. petitioners Complaint for non-compliance with the foregoing arbitration clause.
Salas, Jr. was the registered owner of a vast tract of land in Lipa City, Batangas Hence this petition.
spanning 1,484,354 square meters.
On May 15, 1987, he entered into an Owner-Contractor Petitioners argue, thus:
Agreement[4] (hereinafter referred to as the Agreement) with respondent Laperal
The petitioners causes of action did not emanate from the Owner-Contractor
Realty Corporation (hereinafter referred to as Laperal Realty) to render and provide
Agreement.
complete (horizontal) construction services on his land.
On September 23, 1988, Salas, Jr. executed a Special Power of Attorney in
The petitioners causes of action for cancellation of contract and accounting are
favor of respondent Laperal Realty to exercise general control, supervision and
covered by the exception under the Arbitration Law.
management of the sale of his land, for cash or on installment basis.
On June 10, 1989, Salas, Jr. left his home in the morning for a business trip to
Nueva Ecija. He never returned. Failure to arbitrate is not a ground for dismissal.[10]
On August 6, 1996, Teresita Diaz Salas filed with the Regional Trial Court of
Makati City a verified petition for the declaration of presumptive death of her In a catena of cases[11] inspired by Justice Malcolms provocative dissent
husband, Salas, Jr., who had then been missing for more than seven (7) years. It was in Vega v. San Carlos Milling Co.[12], this Court has recognized arbitration
granted on December 12, 1996.[5] agreements as valid, binding, enforceable and not contrary to public policy so much
Meantime, respondent Laperal Realty subdivided the land of Salas, Jr. and sold so that when there obtains a written provision for arbitration which is not complied
subdivided portions thereof to respondents Rockway Real Estate Corporation and with, the trial court should suspend the proceedings and order the parties to
South Ridge Village, Inc. on February 22, 1990; to respondent spouses Abrajano and proceed to arbitration in accordance with the terms of their
Lava and Oscar Dacillo on June 27, 1991; and to respondents Eduardo Vacuna, agreement[13] Arbitration is the wave of the future in dispute resolution. [14] To brush
Florante de la Cruz and Jesus Vicente Capalan on June 4, 1996 (all of whom are aside a contractual agreement calling for arbitration in case of disagreement
hereinafter referred to as respondent lot buyers). between parties would be a step backward.[15]
On February 3, 1998, petitioners as heirs of Salas, Jr. filed in the Regional Trial
Nonetheless, we grant the petition.
Court of Lipa City a Complaint[6] for declaration of nullity of sale, reconveyance,
cancellation of contract, accounting and damages against herein respondents which A submission to arbitration is a contract.[16] As such, the Agreement,
was docketed as Civil Case No. 98-0047. containing the stipulation on arbitration, binds the parties thereto, as well as their
On April 24, 1998, respondent Laperal Realty filed a Motion to Dismiss [7]on the assigns and heirs.[17] But only they. Petitioners, as heirs of Salas, Jr., and respondent
ground that petitioners failed to submit their grievance to arbitration as required Laperal Realty are certainly bound by the Agreement. If respondent Laperal Realty,
under Article VI of the Agreement which provides: had assigned its rights under the Agreement to a third party, making the former,
the assignor, and the latter, the assignee, such assignee would also be bound by the The petitioners contention is without merit. For while rescission, as a general
arbitration provision since assignment involves such transfer of rights as to vest in rule, is an arbitrable issue,[20] they impleaded in the suit for rescission the
the assignee the power to enforce them to the same extent as the assignor could respondent lot buyers who are neither parties to the Agreement nor the latters
have enforced them against the debtor[18] or in this case, against the heirs of the assigns or heirs. Consequently, the right to arbitrate as provided in Article VI of the
original party to the Agreement. However, respondents Rockway Real Estate Agreement was never vested in respondent lot buyers.
Corporation, South Ridge Village, Inc., Maharami Development Corporation,
spouses Abrajano, spouses Lava, Oscar Dacillo, Eduardo Vacuna, Florante de la Cruz Respondent Laperal Realty, as a contracting party to the Agreement, has the
right to compel petitioners to first arbitrate before seeking judicial relief. However,
and Jesus Vicente Capellan are not assignees of the rights of respondent Laperal
to split the proceedings into arbitration for respondent Laperal Realty and trial for
Realty under the Agreement to develop Salas, Jr.s land and sell the same. They are,
the respondent lot buyers, or to hold trial in abeyance pending arbitration between
rather, buyers of the land that respondent Laperal Realty was given the authority to
develop and sell under the Agreement. As such, they are not assigns contemplated petitioners and respondent Laperal Realty, would in effect result in multiplicity of
suits, duplicitous procedure and unnecessary delay. On the other hand, it would be
in Art. 1311 of the New Civil Code which provides that contracts take effect only
in the interest of justice if the trial court hears the complaint against all herein
between the parties, their assigns and heirs.
respondents and adjudicates petitioners rights as against theirs in a single and
Petitioners claim that they suffered lesion of more than one-fourth (1/4) of complete proceeding.
the value of Salas, Jr.s land when respondent Laperal Realty subdivided it and sold
WHEREFORE, the instant petition is hereby GRANTED. The Order dated August
portions thereof to respondent lot buyers. Thus, they instituted action[19]against
19, 1998 of Branch 85 of the Regional Trial Court of Lipa City is hereby NULLIFIED
both respondent Laperal Realty and respondent lot buyers for rescission of the sale
transactions and reconveyance to them of the subdivided lots.They argue that and SET ASIDE. Said court is hereby ordered to proceed with the hearing of Civil
Case No. 98-0047.
rescission, being their cause of action, falls under the exception clause in Sec. 2 of
Republic Act No. 876 which provides that such submission [to] or contract [of Costs against private respondents.
arbitration] shall be valid, enforceable and irrevocable, save upon such grounds as
exist at law for the revocation of any contract. SO ORDERED.
BF CORPORATION, petitioner, vs. COURT OF APPEALS, SHANGRI-LA PROPERTIES, provided for a clause requiring prior resort to arbitration before judicial
COLAYCO, ALFREDO C. RAMOS, INC., RUFO B. intervention could be invoked in any dispute arising from the contract. The
MAXIMO G. LICAUCO III and BENJAMIN C. RAMOS, respondents. following day, SPI submitted a copy of the conditions of the contract containing the
arbitration clause that it failed to append to its motion to suspend proceedings.
DECISION
Petitioner opposed said motion claiming that there was no formal contract
ROMERO, J.: between the parties although they entered into an agreement defining their rights
and obligations in undertaking the project. It emphasized that the agreement did
The basic issue in this petition for review on certiorari is whether or not the not provide for arbitration and therefore the court could not be deprived of
contract for the construction of the EDSA Plaza between petitioner BF Corporation jurisdiction conferred by law by the mere allegation of the existence of an
and respondent Shangri-la Properties, Inc. embodies an arbitration clause in case of arbitration clause in the agreement between the parties.
disagreement between the parties in the implementation of contractual provisions. In reply to said opposition, SPI insisted that there was such an arbitration
Petitioner and respondent Shangri-la Properties, Inc. (SPI) entered into an clause in the existing contract between petitioner and SPI. It alleged that
agreement whereby the latter engaged the former to construct the main structure suspension of proceedings would not necessarily deprive the court of its jurisdiction
of the EDSA Plaza Project, a shopping mall complex in the City of Mandaluyong. over the case and that arbitration would expedite rather than delay the settlement
of the parties respective claims against each other.
The construction work was in progress when SPI decided to expand the
project by engaging the services of petitioner again. Thus, the parties entered into In a rejoinder to SPIs reply, petitioner reiterated that there was no arbitration
an agreement for the main contract works after which construction work began. clause in the contract between the parties. It averred that granting that such a
clause indeed formed part of the contract, suspension of the proceedings was no
However, petitioner incurred delay in the construction work that SPI longer proper. It added that defendants should be declared in default for failure to
considered as serious and substantial.[1] On the other hand, according to petitioner, file their answer within the reglementary period.
the construction works progressed in faithful compliance with the First Agreement
until a fire broke out on November 30, 1990 damaging Phase I of the In its sur-rejoinder, SPI pointed out the significance of petitioners admission of
Project.[2] Hence, SPI proposed the re-negotiation of the agreement between them. the due execution of the Articles of Agreement. Thus, on page D/6 thereof, the
signatures of Rufo B. Colayco, SPI president, and Bayani Fernando, president of
Consequently, on May 30, 1991, petitioner and SPI entered into a written petitioner appear, while page D/7 shows that the agreement is a public document
agreement denominated as Agreement for the Execution of Builders Work for the duly notarized on November 15, 1991 by Notary Public Nilberto R. Briones as
EDSA Plaza Project. Said agreement would cover the construction work on said document No. 345, page 70, book No. LXX, Series of 1991 of his notarial register. [5]
project as of May 1, 1991 until its eventual completion.
Thereafter, upon a finding that an arbitration clause indeed exists, the lower
According to SPI, petitioner failed to complete the construction works and court[6] denied the motion to suspend proceedings, thus:
abandoned the project.[3] This resulted in disagreements between the parties as
regards their respective liabilities under the contract. On July 12, 1993, upon SPIs It appears from the said document that in the letter-agreement dated
initiative, the parties respective representatives met in conference but they failed May 30, 1991 (Annex C, Complaint), plaintiff BF and defendant Shangri-La
to come to an agreement.[4] Properties, Inc. agreed upon the terms and conditions of the Builders
Work for the EDSA Plaza Project (Phases I, II and Carpark), subject to the
Barely two days later or on July 14, 1993, petitioner filed with the Regional execution by the parties of a formal trade contract. Defendants have
Trial Court of Pasig a complaint for collection of the balance due under the submitted a copy of the alleged trade contract, which is entitled `Contract
construction agreement. Named defendants therein were SPI and members of its Documents For Builders Work Trade Contractor dated 01 May 1991, page
board of directors namely, Alfredo C. Ramos, Rufo B. Colayco, Antonio B. Olbes, 2 of which is entitled `Contents of Contract Documents with a list of the
Gerardo O. Lanuza, Jr., Maximo G. Licauco III and Benjamin C. Ramos. documents therein contained, and Section A thereof consists of the
abovementioned Letter-Agreement dated May 30, 1991. Section C of the
On August 3, 1993, SPI and its co-defendants filed a motion to suspend
said Contract Documents is entitled `Articles of Agreement and
proceedings instead of filing an answer. The motion was anchored on defendants
Conditions of Contract which, per its Index, consists of Part A (Articles of
allegation that the formal trade contract for the construction of the project
Agreement) and B (Conditions of Contract). The said Articles of Against the above backdrop, the lower court found that per the May 30, 1991
Agreement appears to have been duly signed by President Rufo B. agreement, the project was to be completed by October 31, 1991. Thereafter, the
Colayco of Shangri-La Properties, Inc. and President Bayani F. Fernando of contractor would pay P80,000 for each day of delay counted from November 1,
BF and their witnesses, and was thereafter acknowledged before Notary 1991 with liquified (sic) damages up to a maximum of 5% of the total contract price.
Public Nilberto R. Briones of Makati, Metro Manila on November 15,
The lower court also found that after the project was completed in accordance
1991. The said Articles of Agreement also provides that the `Contract
Documents' therein listed `shall be deemed an integral part of this with the agreement that contained a provision on progress payment billing, SPI
took possession and started operations thereof by opening the same to the public
Agreement, and one of the said documents is the `Conditions of Contract
in November, 1991. SPI, having failed to pay for the works, petitioner billed SPI in
which contains the Arbitration Clause relied upon by the defendants in
the total amount of P110,883,101.52, contained in a demand letter sent by it to SPI
their Motion to Suspend Proceedings.
on February 17, 1993. Instead of paying the amount demanded, SPI set up its own
This Court notes, however, that the `Conditions of Contract referred to, claim of P220,000,000.00 and scheduled a conference on that claim for July 12,
contains the following provisions: 1993. The conference took place but it proved futile.
`3. Contract Document. Upon the above facts, the lower court concluded:
Three copies of the Contract Documents referred to Considering the fact that under the supposed Arbitration Clause invoked
in the Articles of Agreement shall be signed by the by defendants, it is required that `Notice of the demand for arbitration of
parties to the contract and distributed to the Owner a dispute shall be filed in writing with the other party x x x x in no case x x
and the Contractor for their safe keeping. x x later than the time of final payment x x x x which apparently, had
(underscoring supplied) elapsed, not only because defendants had taken possession of the
finished works and the plaintiffs billings for the payment thereof had
And it is significant to note further that the said `Conditions of Contract is
remained pending since November, 1991 up to the filing of this case on
not duly signed by the parties on any page thereof --- although it bears
July 14, 1993, but also for the reason that defendants have failed to file
the initials of BFs representatives (Bayani F. Fernando and Reynaldo M. any written notice of any demand for arbitration during the said long
de la Cruz) without the initials thereon of any representative of Shangri-
period of one year and eight months, this Court finds that it cannot stay
La Properties, Inc.
the proceedings in this case as required by Sec. 7 of Republic Act No. 876,
Considering the insistence of the plaintiff that the said Conditions of because defendants are in default in proceeding with such arbitration.
Contract was not duly executed or signed by the parties, and the failure
The lower court denied SPIs motion for reconsideration for lack of merit and
of the defendants to submit any signed copy of the said document, this
directed it and the other defendants to file their responsive pleading or answer
Court entertains serious doubt whether or not the arbitration clause
within fifteen (15) days from notice.
found in the said Conditions of Contract is binding upon the parties to the
Articles of Agreement. (Underscoring supplied.) Instead of filing an answer to the complaint, SPI filed a petition
for certiorari under Rule 65 of the Rules of Court before the Court of Appeals. Said
The lower court then ruled that, assuming that the arbitration clause was valid
appellate court granted the petition, annulled and set aside the orders and stayed
and binding, still, it was too late in the day for defendants to invoke arbitration. It the proceedings in the lower court. In so ruling, the Court of Appeals held:
quoted the following provision of the arbitration clause:
The reasons given by the respondent Court in denying petitioners motion
Notice of the demand for arbitration of a dispute shall be filed in writing
to suspend proceedings are untenable.
with the other party to the contract and a copy filed with the Project
Manager. The demand for arbitration shall be made within a reasonable
1. The notarized copy of the articles of agreement attached as Annex A to
time after the dispute has arisen and attempts to settle amicably have
petitioners reply dated August 26, 1993, has been submitted by them to the
failed; in no case, however, shall the demand he made be later than the
respondent Court (Annex G, petition). It bears the signature of petitioner Rufo B.
time of final payment except as otherwise expressly stipulated in the
Colayco, president of petitioner Shangri-La Properties, Inc., and of Bayani Fernando,
contract.
president of respondent Corporation (Annex G-1, petition). At page D/4 of said
articles of agreement it is expressly provided that the conditions of contract are Notice of the demand for arbitration dispute shall be filed in writing with the other
`deemed an integral part thereof (page 188, rollo). And it is at pages D/42 to D/44 party to the contract and a copy filed with the Project Manager. The demand for
of the conditions of contract that the provisions for arbitration are found (Annexes arbitration shall be made within a reasonable time after the dispute has arisen and
G-3 to G-5, petition, pp. 227-229). Clause No. 35 on arbitration specifically provides: attempts to settle amicably had failed; in no case, however, shall the demand be
made later than the time of final payment except as otherwise expressly stipulated
Provided always that in case any dispute or difference shall arise between the in the contract (underscoring supplied)
Owner or the Project Manager on his behalf and the Contractor, either during the
progress or after the completion or abandonment of the Works as to the quoted in its order (Annex A, petition). As the respondent Court there said, after
construction of this Contract or as to any matter or thing of whatsoever nature the final demand to pay the amount of P110,883,101.52, instead of paying,
arising thereunder or in connection therewith (including any matter or being left by petitioners set up its own claim against respondent Corporation in the amount
this Contract to the discretion of the Project Manager or the withholding by the of P220,000,000.00 and set a conference thereon on July 12, 1993. Said conference
Project Manager of any certificate to which the Contractor may claim to be entitled proved futile. The next day, July 14, 1993, respondent Corporation filed its
or the measurement and valuation mentioned in clause 30 (5) (a) of these complaint against petitioners. On August 13, 1993, petitioners wrote to respondent
Conditions or the rights and liabilities of the parties under clauses 25, 26, 32 or 33 Corporation requesting arbitration. Under the circumstances, it cannot be said that
of these Conditions), the Owner and the Contractor hereby agree to exert all efforts petitioners resort to arbitration was made beyond reasonable time. Neither can
to settle their differences or dispute amicably. Failing these efforts then such they be considered in default of their obligation to respondent Corporation.
dispute or difference shall be referred to Arbitration in accordance with the rules
and procedures of the Philippine Arbitration Law. Hence, this petition before this Court. Petitioner assigns the following errors:
A.
The fact that said conditions of contract containing the arbitration clause bear only
the initials of respondent Corporations representatives, Bayani Fernando and THE COURT OF APPEALS ERRED IN ISSUING THE EXTRAORDINARY
Reynaldo de la Cruz, without that of the representative of petitioner Shangri-La WRIT OF CERTIORARI ALTHOUGH THE REMEDY OF APPEAL WAS
Properties, Inc. does not militate against its effectivity. Said petitioner having AVAILABLE TO RESPONDENTS.
categorically admitted that the document, Annex A to its reply dated August 26,
1993 (Annex G, petition), is the agreement between the parties, the initial or B.
signature of said petitioners representative to signify conformity to arbitration is no THE COURT OF APPEALS ERRED IN FINDING GRAVE ABUSE OF
longer necessary. The parties, therefore, should be allowed to submit their dispute DISCRETION IN THE FACTUAL FINDINGS OF THE TRIAL COURT THAT:
to arbitration in accordance with their agreement.
(i) THE PARTIES DID NOT ENTER INTO AN AGREEMENT TO
2. The respondent Court held that petitioners `are in default in proceeding with ARBITRATE.
such arbitration. It took note of `the fact that under the supposed Arbitration (ii) ASSUMING THAT THE PARTIES DID ENTER INTO THE
Clause invoked by defendants, it is required that Notice of the demand for AGREEMENT TO ARBITRATE, RESPONDENTS
arbitration of a dispute shall be filed in writing with the other party x x x in no case x ARE ALREADY IN DEFAULT IN INVOKING THE
x x later than the time of final payment, which apparently, had elapsed, not only AGREEMENT TO ARBITRATE.
because defendants had taken possession of the finished works and the plaintiffs
billings for the payment thereof had remained pending since November, 1991 up to On the first assigned error, petitioner contends that the Order of the lower
the filing of this case on July 14, 1993, but also for the reason that defendants have court denying the motion to suspend proceedings is a resolution of an incident on
failed to file any written notice of any demand for arbitration during the said long the merits. As such, upon the continuation of the proceedings, the lower court
period of one year and eight months, x x x. would appreciate the evidence adduced in their totality and thereafter render a
decision on the merits that may or may not sustain the existence of an arbitration
Respondent Court has overlooked the fact that under the arbitration clause clause. A decision containing a finding that the contract has no arbitration clause
can then be elevated to a higher court in an ordinary appeal where an adequate
remedy could be obtained. Hence, to petitioner, the Court of Appeals should have
dismissed the petition for certiorari because the remedy of appeal would still be The issue, therefore, posed before the Court of Appeals in a petition for
available to private respondents at the proper time.[7] certiorari is whether the Arbitration Clause does not in fact exist. On its face, the
question is one of fact which is not proper in a petition for certiorari.
The above contention is without merit.
The Court of Appeals found that an Arbitration Clause does in fact exist. In
The rule that the special civil action of certiorari may not be invoked as a
resolving said question of fact, the Court of Appeals interpreted the construction of
substitute for the remedy of appeal is succinctly reiterated in Ongsitco v. Court of
the subject contract documents containing the Arbitration Clause in accordance
Appeals[8] as follows: with Republic Act No. 876 (Arbitration Law) and existing jurisprudence which will be
extensively discussed hereunder. In effect, the issue posed before the Court of
x x x. Countless times in the past, this Court has held that `where appeal is the Appeals was likewise a question of law. Being a question of law, the private
proper remedy, certiorari will not lie. The writs of certiorari and prohibition are respondents rightfully invoked the special civil action of certiorari.
remedies to correct lack or excess of jurisdiction or grave abuse of discretion
equivalent to lack of jurisdiction committed by a lower court. `Where the proper It is that mode of appeal taken by private respondents before the Court of
remedy is appeal, the action for certiorari will not be entertained. x x x. Certiorari is Appeals that is being questioned by the petitioners before this Court. But at the
not a remedy for errors of judgment. Errors of judgment are correctible by appeal, heart of said issue is the question of whether there exists an Arbitration
errors of jurisdiction are reviewable by certiorari. Clause because if an Arbitration Clause does not exist, then private respondents
took the wrong mode of appeal before the Court of Appeals.
Rule 65 is very clear. The extraordinary remedies of certiorari, prohibition For this Court to be able to resolve the question of whether private
and mandamus are available only when `there is no appeal or any plain, speedy and respondents took the proper mode of appeal, which, incidentally, is a question of
adequate remedy in the ordinary course of law x x x. That is why they are referred law, then it has to answer the core issue of whether there exists an Arbitration
to as `extraordinary. x x x. Clause which, admittedly, is a question of fact.

The Court has likewise ruled that certiorari will not be issued to cure errors in Moreover, where a rigid application of the rule that certiorari cannot be a
proceedings or correct erroneous conclusions of law or fact. As long as a court acts substitute for appeal will result in a manifest failure or miscarriage of justice, the
within its jurisdiction, any alleged errors committed in the exercise of its jurisdiction provisions of the Rules of Court which are technical rules may be relaxed.[10] As we
will amount to nothing more than errors of judgment which are reviewable by shall show hereunder, had the Court of Appeals dismissed the petition for certiorari,
timely appeal and not by a special civil action of certiorari.[9]v. Court of Appeals, 327 the issue of whether or not an arbitration clause exists in the contract would not
Phil. 1, 41-42 (1996).9 have been resolved in accordance with evidence extant in the record of the case.
Consequently, this would have resulted in a judicial rejection of a contractual
This is not exactly so in the instant case. While this Court does not deny the provision agreed by the parties to the contract.
eventual jurisdiction of the lower court over the controversy, the issue posed
basically is whether the lower court prematurely assumed jurisdiction over it. If the In the same vein, this Court holds that the question of the existence of the
lower court indeed prematurely assumed jurisdiction over the case, then it arbitration clause in the contract between petitioner and private respondents is a
becomes an error of jurisdiction which is a proper subject of a petition legal issue that must be determined in this petition for review on certiorari.
for certiorari before the Court of Appeals. And if the lower court does not have Petitioner, while not denying that there exists an arbitration clause in the
jurisdiction over the controversy, then any decision or order it may render may be contract in question, asserts that in contemplation of law there could not have been
annulled and set aside by the appellate court. one considering the following points. First, the trial court found that the conditions
However, the question of jurisdiction, which is a question of law depends on of contract embodying the arbitration clause is not duly signed by the
the determination of the existence of the arbitration clause, which is a question of parties. Second, private respondents misrepresented before the Court of Appeals
fact. In the instant case, the lower court found that there exists an arbitration that they produced in the trial court a notarized duplicate original copy of the
clause. However, it ruled that in contemplation of law, said arbitration clause does construction agreement because what were submitted were mere photocopies
not exist. thereof. The contract(s) introduced in court by private respondents were therefore
of dubious authenticity because: (a) the Agreement for the Execution of Builders
Work for the EDSA Plaza Project does not contain an arbitration clause, (b) private
respondents surreptitiously attached as Annexes `G-3 to `G-5 to their petition the parties, was signed by representatives of both parties and duly notarized. The
before the Court of Appeals but these documents are not parts of the Agreement of failure of the private respondents representative to initial the `Conditions of
the parties as there was no formal trade contract executed, (c) if the entire Contract would therefor not affect compliance with the formal requirements for
compilation of documents is indeed a formal trade contract, then it should have arbitration agreements because that particular portion of the covenants between
been duly notarized, (d) the certification from the Records Management and the parties was included by reference in the Articles of Agreement.
Archives Office dated August 26, 1993 merely states that the notarial record of
Nilberto Briones x x x is available in the files of (said) office as Notarial Registry Petitioners contention that there was no arbitration clause because the
contract incorporating said provision is part of a hodge-podge document, is
Entry only, (e) the same certification attests that the document entered in the
therefore untenable. A contract need not be contained in a single writing. It may be
notarial registry pertains to the Articles of Agreement only without any other
collected from several different writings which do not conflict with each other and
accompanying documents, and therefore, it is not a formal trade contract, and (f)
the compilation submitted by respondents are a mere hodge-podge of documents which, when connected, show the parties, subject matter, terms and consideration,
as in contracts entered into by correspondence.[13] A contract may be encompassed
and do not constitute a single intelligible agreement.
in several instruments even though every instrument is not signed by the parties,
In other words, petitioner denies the existence of the arbitration clause since it is sufficient if the unsigned instruments are clearly identified or referred to
primarily on the ground that the representatives of the contracting corporations did and made part of the signed instrument or instruments.Similarly, a written
not sign the Conditions of Contract that contained the said clause. Its other agreement of which there are two copies, one signed by each of the parties, is
contentions, specifically that insinuating fraud as regards the alleged insertion of binding on both to the same extent as though there had been only one copy of the
the arbitration clause, are questions of fact that should have been threshed out agreement and both had signed it.[14]
below.
The flaw in petitioners contentions therefore lies in its having segmented the
This Court may as well proceed to determine whether the arbitration clause various components of the whole contract between the parties into several parts.
does exist in the parties contract. Republic Act No. 876 provides for the formal This notwithstanding, petitioner ironically admits the execution of the Articles of
requisites of an arbitration agreement as follows: Agreement. Notably, too, the lower court found that the said Articles of Agreement
also provides that the `Contract Documents therein listed `shall be deemed an
Section 4. Form of arbitration agreement. A contract to arbitrate a controversy integral part of this Agreement, and one of the said documents is the `Conditions of
thereafter arising between the parties, as well as a submission to arbitrate an Contract which contains the Arbitration Clause. It is this Articles of Agreement that
existing controversy, shall be in writing and subscribed by the party sought to be was duly signed by Rufo B. Colayco, president of private respondent SPI, and Bayani
charged, or by his lawful agent. F. Fernando, president of petitioner corporation. The same agreement was duly
subscribed before notary public Nilberto R. Briones. In other words, the
The making of a contract or submission for arbitration described in section two subscription of the principal agreement effectively covered the other documents
hereof, providing for arbitration of any controversy, shall be deemed a consent of incorporated by reference therein.
the parties of the province or city where any of the parties resides, to enforce such This Court likewise does not find that the Court of Appeals erred in ruling that
contract of submission. (Underscoring supplied.) private respondents were not in default in invoking the provisions of the arbitration
clause which states that (t)he demand for arbitration shall be made within a
The formal requirements of an agreement to arbitrate are therefore the reasonable time after the dispute has arisen and attempts to settle amicably had
following: (a) it must be in writing and (b) it must be subscribed by the parties or failed. Under the factual milieu, private respondent SPI should have paid its
their representatives. There is no denying that the parties entered into a written liabilities under the contract in accordance with its terms. However,
contract that was submitted in evidence before the lower court. To subscribe misunderstandings appeared to have cropped up between the parties ostensibly
means to write underneath, as ones name; to sign at the end of a brought about by either delay in the completion of the construction work or by
document.[11] That word may sometimes be construed to mean to give consent to force majeure or the fire that partially gutted the project. The almost two-year
or to attest.[12] delay in paying its liabilities may not therefore be wholly ascribed to private
respondent SPI.
The Court finds that, upon a scrutiny of the records of this case, these
requisites were complied with in the contract in question. The Articles of
Agreement, which incorporates all the other contracts and agreements between
Besides, private respondent SPIs initiative in calling for a conference between In this connection, it bears stressing that the lower court has not lost its
the parties was a step towards the agreed resort to arbitration. However, petitioner jurisdiction over the case. Section 7 of Republic Act No. 876 provides that
posthaste filed the complaint before the lower court. Thus, while private proceedings therein have only been stayed. After the special proceeding of
respondent SPIs request for arbitration on August 13, 1993 might appear an arbitration[16] has been pursued and completed, then the lower court may confirm
afterthought as it was made after it had filed the motion to suspend proceedings, it the award[17] made by the arbitrator.
was because petitioner also appeared to act hastily in order to resolve the
controversy through the courts. It should be noted that in this jurisdiction, arbitration has been held valid and
constitutional. Even before the approval on June 19, 1953 of Republic Act No. 876,
The arbitration clause provides for a reasonable time within which the parties this Court has countenanced the settlement of disputes through
may avail of the relief under that clause. Reasonableness is a relative term and the arbitration.[18] Republic Act No. 876 was adopted to supplement the New Civil
question of whether the time within which an act has to be done is reasonable Codes provisions on arbitration.[19] Its potentials as one of the alternative dispute
depends on attendant circumstances.[15] This Court finds that under the resolution methods that are now rightfully vaunted as the wave of the future in
circumstances obtaining in this case, a one-month period from the time the parties international relations, is recognized worldwide. To brush aside a contractual
held a conference on July 12, 1993 until private respondent SPI notified petitioner agreement calling for arbitration in case of disagreement between the parties
that it was invoking the arbitration clause, is a reasonable time. Indeed, petitioner would therefore be a step backward.
may not be faulted for resorting to the court to claim what was due it under the
WHEREFORE, the questioned Decision of the Court of Appeals is hereby
contract. However, we find its denial of the existence of the arbitration clause as an
AFFIRMED and the petition for certiorari DENIED. This Decision is immediately
attempt to cover up its misstep in hurriedly filing the complaint before the lower
court. executory. Costs against petitioner.
SO ORDERED.
HI-PRECISION STEEL CENTER, INC., petitioner, Steel Builders filed a "Request for Adjudication" with public respondent CIAC. In its
vs. Complaint filed with the CIAC, Steel Builders sought payment of its unpaid progress
LIM KIM STEEL BUILDERS, INC., and CONSTRUCTION INDUSTRY ARBITRATION buildings, alleged unearned profits and other receivables. Hi-Precision, upon the
COMMISSION, respondents. other hand, in its Answer and Amended Answer, claimed actual and liquidated
damages, reimbursement of alleged additional costs it had incurred in order to
FELICIANO, J.: complete the project and attorney's fees.

On 18 June 1993, a "Petition for Extension to File Petition for Review" 1 was filed The CIAC formed an Arbitral Tribunal with three (3) members, two (2) being
before the Court, petitioner Hi-Precision Steel Center, Inc. ("Hi-Precision") stating appointed upon nomination of Hi-Precision and Steel Builders, respectively; the
that it intended to file a Petition for Review on Certiorari in respect of the 13 third member (the Chairman) was appointed by the CIAC as a common nominee of
November 1992 Award 2 and 13 May 1993 Order 3 of public respondent the two (2) parties. On the Chairman was a lawyer. After the arbitration proceeding,
Construction Industry Arbitration Commission ("CIAC") in Arbitration Case No. 13- the Arbitral Tribunal rendered a unanimous Award dated 13 November 1992, the
90. The Petition (really a Motion) prayed for an extension of thirty (30) days or until dispositive portion of which reads as follows:
21 July 1993 within which to file a Petition for Review.
WHEREFORE, premises considered, the Owner [petitioner Hi-
An opposition 4 to the Motion was filed by private respondent Lim Kim Steel Precision] is ordered to pay the Contractor [private respondent
Builders, Inc. ("Steel Builders") on 5 July 1993. On the same day, however, the Court Steel Builders] the amount of P6,400,717.83 and all other claims
issued a Resolution 5 granting the Motion with a warning that no further extension of the parties against each other are deemed compensated and
would be given. offset. No pronouncement as to costs.

The Opposition, the subsequent Reply 6 of petitioner filed on 20 July 1993 and the The Parties are enjoined to abide by the award. 11
Petition for Review 7 dated 21 July 1993, were noted by the Court in its
Resolution 8 of 28 July 1993. The Court also required private respondent Steel Upon motions for reconsideration filed, respectively, by Hi-Precision and
Builders to file a Comment on the Petition for Review and Steel Builders complied. Steel Builders, the Arbitral Tribunal issued an Order dated 13 May 1993
which reduced the net amount due to contractor Steel Builders to
The Petition prays for issuance of a temporary restraining order 9 to stay the P6,115,285.83. 12
execution of the assailed Order and Award in favor of Steel Builders, which
application the Court merely noted, as it did subsequent Urgent Motions for a In its Award, the Arbitral Tribunal stated that it was guided by Articles 1169, 1192
temporary restraining order. 10 and 2215 of the Civil Code. With such guidance, the arbitrators concluded that (a)
both parties were at fault, though the Tribunal could not point out which of the
Petitioner Hi-Precision entered into a contract with private respondent Steel parties was the first infractor; and (b) the breaches by one party affected the
Builders under which the latter as Contractor was to complete a P21 Million discharge of the reciprocal obligations of the other party. With mutual fault as a
construction project owned by the former within a period of 153 days, i.e. from 8 principal premise, the Arbitral Tribunal denied (a) petitioner's claims for the
May 1990 to 8 October 1990. The project completion date was first moved to 4 additional costs allegedly incurred to complete the project; and (b) private
November 1990. On that date, however, only 75.8674% of the project was actually respondent's claim for profit it had failed to earn because of petitioner's take over
completed. Petitioner attributed this non-completion to Steel Builders which of the project.
allegedly had frequently incurred delays during the
original contract period and the extension period. Upon the other hand, Steel The Tribunal then proceeded to resolve the remaining specific claims of the parties.
Builders insisted that the delays in the project were either excusable or due to Hi- In disposing of these multiple, detailed claims the Arbitral Tribunal, in respect of
Precision's own fault and issuance of change orders. The project was taken over on one or more of the respective claims of the parties: (a) averaged out the conflicting
7 November 1990, and eventually completed on February 1991, by Hi-Precision. amounts and percentages claimed by the parties; 13 (b) found neither basis nor
justification for a particular claim; 14 (c) found the evidence submitted in support of
particular claims either weak or non-existent; 15 (d) took account of the admissions
of liability in respect of particular claims; 16 (e) relied on its own expertise in arbitration, and when it nonetheless persisted in its awards of
resolving particular claims; 17 and (f) applied a "principle of equity" in requiring damages in favor of the
each party to bear its own loss resulting or arising from mutual fault or delay respondent. . . .;
(compensation morae). 18
(3) The public respondent committed serious error in law, if not
Petitioner Hi-Precision now asks this Court to set aside the Award, contending grave abuse of discretion, for its abject failure to apply the
basically that it was the contractor Steel Builders who had defaulted on its doctrine of waiver, estoppel against the contractor, the private
contractual undertakings and so could not be the injured party and should not be respondent herein, when it agreed on November 16, 1990 to
allowed to recover any losses it may have incurred in the project. Petitioner Hi- award termination of the contract and the owner's takeover of
Precision insists it is still entitled to damages, and claims that the Arbitral Tribunal the project . . .;
committed grave abuse of discretion when it allowed certain claims by Steel
Builders and offset them against claims of Hi-Precision. (4) The public respondent committed serious error in law, if not
grave abuse of discretion, when it did not enforce the law
A preliminary point needs to be made. We note that the Arbitral Tribunal has not between the parties, the "technical specification[s]" which is one
been impleaded as a respondent in the Petition at bar. The CIAC has indeed been of the contract documents, particularly to par. (a), sub-part 3.01,
impleaded; however, the Arbitral Award was not rendered by the CIAC, but rather part 3, Sec. 2b, which expressly requires that major site work
by the Arbitral Tribunal. Moreover, under Section 20 of Executive Order No. 1008, activities like stripping, removal and stockpiling of top soil shall be
dated 4 February 1985, as amended, it is the Arbitral Tribunal, or the single done "prior to the start of regular excavation or backfiling work",
Arbitrator, with the concurrence of the CIAC, which issues the writ of execution the principal issue in arbitration being non-compliance with the
requiring any sheriff or other proper officer to execute the award. We consider that contract documents;
the Arbitral Tribunal which rendered the Award sought to be reviewed and set
aside, should be impleaded even though the defense of its Award would (5) The public respondent committed serious error in law, if not
presumably have to be carried by the prevailing party. grave abuse of discretion, when it found, in the May 13, 1993
Order, the petitioner "guilty of estoppel" although it is claimed
Petitioner Hi-Precision apparently seeks review of both under Rule 45 and Rule 65 that the legal doctrine of estoppel does not apply with respect to
of the Rules of Court. 19 We do not find it necessary to rule which of the two: a the required written formalities in the issuance of change order . .
petition for review under Rule 45 or a petition for certiorari under Rule 65 — is .;
necessary under Executive Order No. 1008, as amended; this issue was, in any case,
not squarely raised by either party and has not been properly and adequately (6) The exceptional circumstances in Remalante vs. Tibe, 158
litigated. SCRA 138, where the Honorable Supreme Court may review
findings of facts, are present in the instant case, namely; (a) when
In its Petition, Hi-Precision purports to raise "legal issues," and in presenting these the inference made is manifestly absurd, mistaken or impossible
issues, prefaced each with a creative formula: (Luna vs. Linatoc, 74 Phil. 15); (2) when there is grave abuse of
discretion in the appreciation of facts (Buyco vs. People, 95 Phil.
(1) The public respondent [should be the "Arbitral 253); (3) when the judgment is premised on a misapprehension of
Tribunal'] committed serious error in law, if not grave abuse of facts (De la Cruz v. Sosing, 94 Phil. 26 and Castillo vs. CA, 124 SCRA
discretion, when it failed to strictly apply Article 1191, New Civil 808); (4) when the findings of fact are conflicting (Casica v.
Code, against the Villaseca, 101 Phil. 1205); (5) when the findings are contrary to
contractor . . .; the admissions of the parties (Evangelista v. Alto Surety, 103 Phil.
401), and therefore, the findings of facts of the public respondent
(2) The public respondent committee serious error in law, if not in the instant case may be reviewed by the Honorable Supreme
grave abuse of discretion, when it failed to rule in favor of the Court. 20 (Emphasis partly applied and partly in the original)
owner, now petitioner herein, all the awards it claimed on
From the foregoing, petitioner Hi-Precision may be seen to be making two (2) basic other or even both parties in any effort to subvert or defeat that objective for their
arguments: private purposes. The Court will not review the factual findings of an arbitral
tribunal upon the artful allegation that such body had "misapprehended the facts"
(a) Petitioner asks this Court to correct legal errors committed by and will not pass upon issues which are, at bottom, issues of fact, no matter how
the Arbitral Tribunal, which at the same time constitute grave cleverly disguised they might be as "legal questions." The parties here had recourse
abuse of discretion amounting to lack of jurisdiction on the part of to arbitration and chose the arbitrators themselves; they must have had confidence
the Arbitral Tribunal; and in such arbitrators. The Court will not, therefore, permit the parties to relitigate
before it the issues of facts previously presented and argued before the Arbitral
(b) Should the supposed errors petitioner asks us to correct be Tribunal, save only where a very clear showing is made that, in reaching its factual
characterized as errors of fact, such factual errors should conclusions, the Arbitral Tribunal committed an error so egregious and hurtful to
nonetheless be reviewed because there was "grave abuse of one party as to constitute a grave abuse of discretion resulting in lack or loss of
discretion" in the misapprehension of facts on the part of the jurisdiction. 22 Prototypical examples would be factual conclusions of the Tribunal
Arbitral Tribunal. which resulted in deprivation of one or the other party of a fair opportunity to
present its position before the Arbitral Tribunal, and an award obtained through
fraud or the corruption of arbitrators. 23 Any other, more relaxed, rule would result
Executive Order No. 1008, as amended, provides, in its Section 19, as follows:
in setting at naught the basic objective of a voluntary arbitration and would reduce
arbitration to a largely inutile institution.
Sec. 19. Finality of Awards. — The arbitral award shall be binding
upon the parties. It shall be final and inappealable except on
Examination of the Petition at bar reveals that it is essentially an attempt to re-
questions of law which shall be appealable to the Supreme Court.
assert and re-litigate before this Court the detailed or itemized factual claims made
before the Arbitral Tribunal under a general averment that the Arbitral Tribunal had
Section 19 makes it crystal clear that questions of fact cannot be raised in
"misapprehended the facts" submitted to it. In the present Petition, too, Hi-
proceedings before the Supreme Court — which is not a trier of facts — in
Precision claims that the Arbitral Tribunal had committed grave abuse of discretion
respect of an arbitral award rendered under the aegis of the CIAC.
amounting to lack of jurisdiction in reaching its factual and legal conclusions.
Consideration of the animating purpose of voluntary arbitration in general,
and arbitration under the aegis of the CIAC in particular, requires us to
The first "legal issue" submitted by the Petition is the claimed misapplication by the
apply rigorously the above principle embodied in Section 19 that the
Arbitral Tribunal of the first and second paragraphs of Article 1911 of the Civil
Arbitral Tribunal's findings of fact shall be final and inappealable.
Code. 24 Article 1191 reads:
Voluntary arbitration involves the reference of a dispute to an impartial body, the
Art. 1191. The power to rescind obligations is implied in reciprocal
members of which are chosen by the parties themselves, which parties freely
ones, in case one of the obligors should not comply with what is
consent in advance to abide by the arbitral award issued after proceedings where
incumbent upon him.
both parties had the opportunity to be heard. The basic objective is to provide a
speedy and inexpensive method of settling disputes by allowing the parties to avoid
the formalities, delay, expense and aggravation which commonly accompany The injured party may choose between the fulfillment and the
ordinary litigation, especially litigation which goes through the entire hierarchy of rescission of the obligation, with the payment of damages in
courts. Executive Order No. 1008 created an arbitration facility to which the either case. He may also seek rescission, even after he has chosen
construction industry in the Philippines can have recourse. The Executive Order was fulfillment, if the latter should become impossible.
enacted to encourage the early and expeditious settlement of disputes in the
construction industry, a public policy the implementation of which is necessary and The court shall decree the rescission claimed, unless there be just
important for the realization of national development goals. 21 cause authorizing the fixing of a period.

Aware of the objective of voluntary arbitration in the labor field, in the construction
industry, and in any other area for that matter, the Court will not assist one or the
This is understood to be without prejudice to the rights of third waiver on the part of the latter of its right to a 15-day notice of contract
persons who have acquired the thing, in accordance with articles termination. Whether or not that Agreement dated 16 November 1990 (a
1385 and 1388 and the Mortgage Law. document not submitted to this Court) is properly characterized as constituting
waiver on the part of Steel Builders, may be conceded to be prima facie a question
Hi-Precision contends energetically that it is the injured party and that Steel of law; but, if it is, and assuming arguendo that the Arbitral Tribunal had erred in
Builders was the obligor who did not comply with what was incumbent upon it, resolving it, that error clearly did not constitute a grave abuse of discretion resulting
such that Steel Builders was the party in default and the entity guilty of negligence in lack or loss of jurisdiction on the part of the Tribunal.
and delay. As the injured party, Hi-Precision maintains that it may choose between
the fulfillment or rescission of the obligation in accordance with Article 1191, and is A third "legal issue" posed by Hi-Precision relates to the supposed failure on the
entitled to damages in either case. Thus, Hi-Precision continues, when the part of the Arbitral Tribunal "to uphold the supremacy of 'the
contractor Steel Builders defaulted on the 153rd day of the original contract period, law between the parties' and enforce it against private respondent [Steel
Hi-Precision opted for specific performance and gave Steel Builders a 30-day Builders]." 27 The "law between that parties" here involved is the "Technical
extension period with which to complete the project. Specifications" forming part of the Contract Documents. Hi-Precision asserts that
the Arbitral Tribunal did not uphold the "law between the parties," but instead
What petitioner Hi-Precision, in its above argument, disregards is that the substituted the same with "its [own] absurd inference and 'opinion' on mud." Here
determination of whether Hi-Precision or Steel Builders was the "injured party" is again, petitioner is merely disguising a factual question as a "legal issue," since
not to be resolved by an application of Article 1191. That determination is petitioner is in reality asking this Court to review the physical operations relating,
eminently a question of fact, for it requires ascertainment and identification of e.g., to site preparation carried out by the contractor Steel Builders and to
which the two (2) contending parties had first failed to comply with what is determine whether such operations were in accordance with the Technical
incumbent upon it. In other words, the supposed misapplication of Article 1191, Specifications of the project. The Arbitral Tribunal resolved Hi-Precision's claim by
while ostensibly a "legal issue," is ultimately a question of fact, i.e., the finding that Steel Builders had complied substantially with the Technical
determination of the existence or non-existence of a fact or set of facts in respect of Specifications. This Court will not pretend that it has the technical and engineering
which Article 1191 may be properly applied. Thus, to ask this Court to correct a capability to review the resolution of that factual issue by the Arbitral Tribunal.
claimed misapplication or non-application of Article 1191 is to compel this Court to
determine which of the two (2) contending parties was the "injured party" or the Finally, the Petition asks this Court to "review serious errors in the findings of fact of
"first infractor." As noted earlier, the Arbitral Tribunal after the prolonged the [Arbitral Tribunal]." 28 In this section of its Petition,
arbitration proceeding, was unable to make that factual determination and instead Hi-Precision asks us to examine each item of its own claims which the Arbitral
concluded that both parties had committed breaches of their respective Tribunal had rejected in its Award, and each claim of the contractor Steel Builders
obligations. We will not review, and much less reverse, that basic factual finding of which the Tribunal had granted. In respect of each item of the owner's claims and
the Arbitral Tribunal. each item of the contractor's claims, Hi-Precision sets out its arguments, to all
appearances the same arguments it had raised before the Tribunal. As summarized
A second "legal issue" sought to be raised by petitioner Hi-Precision relates to the in the Arbitral Award, Contractor's Claims were as follows:
supposed failure of the Arbitral Tribunal to apply the doctrines of estoppel and
waiver as against Steel Builders. 25 The Arbitral Tribunal, after declaring that the 12.1. Unpaid Progress Billing 1,812,706.95
parties were mutually at fault, proceeded to enumerate the faults of each of the
parties. One of the faults attributed to petitioner Hi-Precision is that it had failed to 12.2. Change Order 1 0.00
give the contractor Steel Builders the required 15-day notice for termination of the 12.3. -do- 2 10,014.00
contract. 26 This was clearly a finding of fact on the part of the Tribunal, supported 12.4. -do- 3 320,000.00
by the circumstance that per the record, petitioner had offered no proof that it had 12.5. -do- 4 112,300.70
complied with such 15-day notice required under Article 28.01 of the General 12.6. -do- 5 398,398.00
Conditions of Contract forming part of the Contract Documents. Petitioner Hi- 12.7. -do- 6 353,050.38
Precision's argument is that a written Agreement dated 16 November 1990 with 12.8. -do- 7 503,836.53
Steel Builders concerning the take over of the project by Hi-Precision, constituted 12.9. -do- 8 216,138.75
12.10. -do- 9 101,621.40 a) prior to take-over 392,781.45
12.11. -do- 10 7,200.00 b) after the take-over
12.12. -do- 11 0.00
12.13. -do- 12 7,800.00 Civil Works 1,158,513.88
12.14. -do- 13 49,250.00 Materials 4,213,318.72
12.15. -do- 14 167,952.00 Labor 2,155,774.79
12.16. -do- 15 445,600.00 Equipment Rental 1,448,208.90
12.17. -do- 16 92,457.30
12.18. -do- 17 1,500.00 ———————
12.19. 20,240.00
12.20. 63,518.00
P8,974,816.45
12.21. 0.00
12.22. 0.00
Total Amount Paid for Construction 23,650,183.00
12.23. 0.00
Less: Contract Price (21,000,000.00)
12.24. 0.00
12.25. 0.00
12.26. 730,201.57 IA Excess of amount paid
12.27. 1,130,722.70 over contract price 2,650,163.29
12.28. 0.00
12.29. 273,991.00 IB Other items due from Lim
12.30. 0.00 Kim Steel Builders

——————— a. Amount not yet deducted


from Downpayment due
12.31. 7,318,499.28 29 to non-completion of Project
(P24.1326%) 2,027,138.40
=============
b. Due to Huey Commercial
used for HSCI Project 51,110.40
Upon the other hand, the petitioner's claims we are asked to review and grant are
summarized as follows:
IC Additional construction expenses
1. Actual Damages
a. Increases in prices since Oct. 5,272,096.81
Advance Downpayment
[at] signing of Contract b. Cost of money of (a) 873,535.49
which is subject to 40%
deduction every progress ID Installation of machinery
billing (40% of Contract Price) P8,406,000.00
a. Foreign exchange loss 11,565,048.37
Progress Billings 5,582,585.55
b. Cost of money (a) 2,871,987.01
Advances made to Lim Kim
I[E] Raw Materials
a. Foreign exchange loss 4,155,982.18 =============
b. Cost of money (a) 821,242.72
c. Additional import levy of 5% 886,513.33 We consider that in asking this Court to go over each individual claim submitted by
d. Cost of money (c) 170,284.44 it and each individual countering claim submitted by Steel Builders to the Arbitral
e. Cost of money on marginal Tribunal, petitioner Hi-Precision is asking this Court to pass upon claims which are
deposit on Letter of Credit 561,195.25 either clearly and directly factual in nature or require previous determination of
factual issues. This upon the one hand. Upon the other hand, the Court considers
IF Cost of money on holding to CRC INTY 3,319,609.63 that petitioner Hi-Precision has failed to show any serious errors of law amounting
to grave abuse of discretion resulting in lack of jurisdiction on the part of the
Total Actual Damages 35,295,927.32 Arbitral Tribunal, in either the methods employed or the results reached by the
Arbitral Tribunal, in disposing of the detailed claims of the respective parties.
2. Liquidated Damages 2,436,000.00
WHEREFORE, for all the foregoing, the Petition is hereby DISMISSED for lack of
3. Attorney's Fees 500,000.00 merit. Costs against petitioner.

P38,231,927.3230 SO ORDERED.
HOME BANKERS SAVINGS & TRUST CO., petitioner, vs. THE HONORABLE COURT Respondents Alfredo Lim and Santos Lim purchased the portion of land
OF APPEALS, PABLO N. AREVALO, FRANCISCO A. UY, SPOUSES LEANDRO A. denominated as Unit No. 7[6] for P700,000.00 on October 1988 and had been fully
SORIANO, JR. and LILIAN SORIANO, ALFREDO LIM and FELISA CHI LIM/ALFREDO paid as of March 18, 1989; Santos Lim subsequently sold and assigned his share of
LIM, respondents. the property to private respondent Felisa Chi Lim on May 12, 1989.

DECISION It is stipulated in their respective contracts that their individual townhouses will be
fully completed and constructed as per plans and specifications and the respective
AUSTRIA-MARTINEZ, J.: titles thereto shall be delivered and transferred to private respondents free from all
liens and encumbrances upon their full payment of the purchase price. However,
Before us is a petition for review on certiorari under Rule 45 of the Rules of despite repeated demands, Garcia/TransAmerican failed to comply with their
Court seeking to annul the Decision[1] of the Court of Appeals (CA) dated undertakings.
November 28, 1996 in CA-G.R. SP No. 40892 and its Resolution dated February 19,
1997 denying petitioners motion for reconsideration. On May 30, 1989, Engr. Garcia and his wife Lorelie Garcia obtained from
petitioner Home Bankers Savings and Trust Company (formerly Home Savings Bank
Each of private respondents entered into separate contracts to sell with and Trust Company) a loan in the amount of P4,000,000.00 and without the prior
TransAmerican Sales and Exposition (TransAmerican) through the latters approval of the Housing and Land Use Regulatory Board (HLURB), the spouses
Owner/General Manager, Engr. Jesus Garcia, involving certain portions of land mortgaged[7] eight lots covered by TCT Nos. 3349 to 3356 as collateral. Petitioner
covered by Transfer Certificate of Title (TCT) No. 19155, located at No. 45 Gen. Lim registered its mortgage on these titles without any other encumbrance or lien
Street, Heroes Hill, Quezon City, together with one unit three-storey townhouse to annotated therein. The proceeds of the loan were intended for the development of
be built on each portion, as follows: the lots into an eight-unit townhouse project. However, five out of these eight titles
turned out to be private respondents townhouses subject of the contracts to sell
Respondent Pablo N. Arevalo purchased the portion of land denominated as Unit with Garcia/TransAmerican.
No. 5[2] for the amount of P750,000.00 on August 21, 1988 and had already fully
paid the purchase price on September 3, 1988; When the loan became due, Garcia failed to pay his obligation to petitioner.
Consequently, petitioner instituted an extrajudicial foreclosure[8] on the subject
lots and being the highest bidder in the public auction, a certificate of sale[9] in its
Respondent Alfredo Lim purchased the portion of land denominated as Unit No.
favor was issued by the sheriff on February 26, 1990. Subsequently, the sheriffs
1[3] for the amount of P800,000.00 on December 22, 1988 and fully paid the same
certificate of sale was registered and annotated on the titles of the subject lots in
upon execution of the agreement on the same day;
the Register of Deeds of Quezon City.

Respondent Francisco A. Uy purchased the portion of land denominated as Unit No. On November 8, 1990, private respondents filed a complaint with the Office of
6[4] on October 29, 1988 in the amount of P800,000.00 payable in installments and Appeals, Adjudication and Legal Affairs (OAALA), HLURB, against
had allegedly made a total payment of P581,507.41. He ordered to stop the Garcia/TransAmerican as seller/developer of the property and petitioner, as
payment of all [postdated] checks from September 1990 to November 1995 on the indispensable party, for non-delivery of titles and non-completion of the subdivision
ground of non-completion of his unit and had later learned of the foreclosure of the project.[10] They prayed for the completion of the units, annulment of the
property; mortgage in favor of petitioner, release of the mortgage on the lots with fully paid
owners and delivery of their titles, and for petitioner to compute individual loan
Respondent spouses Leandro A. Soriano, Jr. and Lilian Soriano purchased the values of amortizing respondents and to accept payments from them and damages.
portion of land denominated as Unit No. 3[5] on February 15, 1990 in the amount Petitioner filed its Answer contending that private respondents have no cause
of P1,600,000.00 and had allegedly made a payment of P669,960.00. They had of action against it; that at the time of the loan application and execution of the
stopped paying because of non-completion of the project and had later learned of promissory note and real estate mortgage by Garcia, there were no known
the foreclosure of the property; individual buyers of the subject land nor annotation of any contracts, liens or
encumbrances of third persons on the titles of the subject lots; that the loan was
granted and released without notifying HLURB as it was not necessary.
Private respondents filed their Reply and a motion for the judgment on the Deliver to Complainant Alfredo Lim TCT No. 3356
pleadings. Petitioner did not file a rejoinder. Private respondents filed a free from all liens and encumbrances.
manifestation reiterating for a judgment on their pleadings and asked that the
4.3. AS TO THE THIRD CAUSE OF ACTION
reliefs prayed for be rendered as far as petitioner was concerned. Upon motion of
private respondents, the case against Garcia/TransAmerican was archived for To compute and/or determine the loan value of
failure to serve summons on him/it despite efforts to locate his whereabouts or its complainant Francisco A. Uy who was not able to
office. The case was then considered submitted for decision. complete or make full payment and to accept
payment and/or receive amortization from said
On August 16, 1991, OAALA rendered its Decision,[11] the dispositive portion
complainant Francisco A. Uy and upon full payment
of which reads:
to deliver TCT No. 3351 free from all liens and
encumbrances.
WHEREFORE, Judgment is hereby rendered as follows:
4.4. AS TO THE FOURTH CAUSE OF ACTION
1. Declaring the mortgage executed by and between respondents Engr. Jesus
To compute and/or determine the loan value of
Garcia/TransAmerican Sales and Exposition and Home Bankers Savings and Trust
Complainant Spouses Leandro A. Soriano, Jr. and
Company (formerly Home Savings Bank and Trust Company) to be unenforceable
Lilian Soriano who were not able to complete or
as against all the complainants;
make full payment and to accept and/or receive
amortization from said Complainants Soriano and
2. Ordering the Register of Deeds of Quezon City to cancel the annotations of the upon full payment to deliver TCT No. 3354 free
mortgage indebtedness between respondents Engr. Jesus Garcia and Home from all liens and encumbrances.
Bankers Savings and Trust Company (formerly Home Savings Bank and Trust
Company); 4.5. AS TO THE FIFTH CAUSE OF ACTION
Deliver to complainant Alfredo Lim and Felisa Chi
3. Ordering, likewise the Register of Deeds of Quezon City to cancel the Lim TCT No. 3350 free from all liens and
annotation of the Certificate of Sale in favor of the respondent Home Bankers encumbrances.
Savings and Trust Company on the following Transfer Certificates of Title to wit:
without prejudice to its right to require respondent Engr. Jesus
1) TCT No. 3350 Garcia/TransAmerican to constitute new collaterals in lieu of the said titles
2) TCT No. 3351 sufficient in value to cover the mortgage obligation.[12]
3) TCT No. 3352
4) TCT No. 3354
Petitioner filed an appeal with the Board of Commissioners of the HLURB
5) TCT No. 3356
which dismissed the same in a decision dated June 15, 1992.[13] Petitioner then
elevated the case to the Office of the President which rendered a decision dated
4. Ordering respondent Home Bankers Savings and Trust Company (formerly Home June 30, 1995[14] dismissing the appeal and affirming the June 15, 1992 decision of
Savings Bank and Trust Company) to: the HLURB. Petitioners motion for reconsideration was also denied in a Resolution
dated May 7, 1996.[15]
4.1. AS TO THE FIRST CAUSE OF ACTION
Petitioner filed a petition for review with the CA which, in the herein assailed
Deliver to Complainant Pablo N. Arevalo TCT No. decision dated November 28, 1996, denied the petition and affirmed the decision of
3352 free from all liens and encumbrances. the Office of the President. The CA applied the case of Union Bank of the Philippines
4.2. AS TO THE SECOND CAUSE OF ACTION vs. HLURB, et al.,[16] where it was held that the act of a subdivision developer of
mortgaging the subdivision without the knowledge and consent of a unit buyer and
without the approval of the National Housing Authority (NHA, now HLURB) is
violative of Section 18 of P.D. No. 957 thus, falling under the exclusive jurisdiction of Notably, the issues raised are mere rehash of the issues already passed upon
HLURB. by the HLURB, the Office of the President and the CA which we uphold as we find
no reversible errors committed.
The CA upheld the findings of the OAALA, HLURB that private respondents had
already entered into separate contracts to sell with TransAmerican as early as 1988 Petitioner claims that HLURB has no power to declare the mortgage contract
while it was only in 1989 that spouses Garcia applied for a loan with petitioner and over real property executed between a real estate developer and petitioner, a
executed a mortgage contract over the subject lots; that the proceeds of the loan banking institution, void or unenforceable, as it is properly within the jurisdiction of
were purposely intended for the development of a property which was the same the Regional Trial Court. Petitioner asserts that being a mortgagee of the subject
property subject of the contracts to sell; that despite the contracts to sell, lots and a purchaser in good faith, it is not a project owner, developer, or dealer
Garcia/TransAmerican did not apprise petitioner of the existence of these contracts contemplated under P.D. No. 1344, the law which expanded the jurisdiction of the
nor did petitioner exhaust any effort to inquire into their existence since petitioner NHA; and that since there is no seller-buyer relationship existing between it and
merely relied on the purported clean reconstituted titles in the name of Garcia; that private respondents, HLURB has no jurisdiction to rule on the validity of the
the mortgage of the subject lots without the consent of the buyers and the mortgage and to annul foreclosure proceedings.
authorization of the HLURB is a clear violation of P.D. No. 957; that the mortgage
contract is void and unenforceable against private respondents. The argument is untenable.
The CA did not err in affirming the decision of the Office of the President that
Petitioners motion for reconsideration was denied by the CA in its Resolution
HLURB has jurisdiction to declare invalid the mortgage contract executed between
dated February 19, 1997.[17]
Garcia/TransAmerican and petitioner over the subject lots insofar as private
Petitioner is now before us raising the following grounds in support of its respondents are concerned. It correctly relied on Union Bank of the Philippines vs.
petition: HLURB, et al.[18] where we squarely ruled on the question of HLURBs jurisdiction to
hear and decide a condominium buyers complaint for: (a) annulment of a real
A. THE OFFICE OF THE PRESIDENT ERRED IN RULING THAT THE HLURB
estate mortgage constituted by the project owner without the consent of the buyer
HAS JURISDICTION TO NULLIFY OR DECLARE UNENFORCEABLE THE
and without the prior written approval of the NHA; (b) annulment of the
REAL ESTATE MORTGAGE VALIDLY CONSTITUTED BY THE OWNER. foreclosure sale; and (c) annulment of the condominium certificate of title that was
B. ASSUMING ARGUENDO THAT THE HLURB HAS JURISDICTION, issued to the highest bidder at the foreclosure sale, thus:
RESPONDENT COURT MANIFESTLY ERRED IN FINDING THE REAL
ESTATE MORTGAGE IN FAVOR OF HOME AS INVALID AND . . . The issue in HLURB Case No. REM-062689-4077 is the validity of the real estate
UNENFORCEABLE AGAINST RESPONDENTS. mortgage of Davids condominium unit that FRDC executed in favor of the Union
Bank and Far East Bank without prior approval of the National Housing Authority
C. IN THE EVENT THAT THE DECISION OF THE RESPONDENT COURT and the legality of the title which the mortgage banks acquired as highest bidder
FINDING THE REAL ESTATE MORTGAGE IN FAVOR OF HOME AS therefore in the extrajudicial foreclosure sale. The applicable provisions of P.D. No.
INVALID AND UNENFORCEABLE AGAINST RESPONDENTS IS UPHELD, 957, otherwise known as The Subdivision and Condominium Buyers Protective
THE UNREGISTERED CONTRACTS TO SELL IN FAVOR OF RESPONDENTS Decree are quoted hereunder as follows:
SHOULD ALSO BE HELD VALID ONLY AS TO THE PARTIES THERETO BUT
UNENFORCEABLE AGAINST PETITIONER.
Sec. 3. NATIONAL HOUSING AUTHORITY. The National Housing Authority shall have
Private respondents filed their Comment and petitioner filed its Reply thereto. exclusive jurisdiction to regulate the real estate trade and business in accordance
with the provisions of this Decree.
In a Resolution dated February 23, 2004, we gave due course to the petition
and required the parties to submit their respective memoranda which they
Section 18. Mortgages No mortgage on any unit or lot shall be made by the owner
complied with.
or developer without prior written approval of the authority. Such approval shall
The petition is devoid of merit. not be granted unless it is shown that the proceeds of the mortgage loan shall be
used for the development of the condominium or subdivision project and effective
measures have been provided to ensure such utilization. The loan value of each lot
or unit covered by the mortgage shall be determined and the buyer thereof if any
shall be notified before the release of the loan. The buyer may, at his option, pay his against project owners, developers, dealers,
installment for the lot or unit directly to the mortgagee who shall apply the brokers, or salesmen; and cases of specific
payments to the corresponding mortgage indebtedness secured by the particular performance.
lot or unit being paid for, with a view to enabling said buyer to obtain title over the
lot or unit promptly after full payment thereof. Executive Order No. 90 dated December 17, 1986 changed the name of the Human
Settlements Regulatory Commission to Housing and Land Use Regulatory Board
P.D. No. 1344 of April 2, 1978 expanded the jurisdiction of the National Housing (HLURB).
Authority to include the following:
Clearly, FRDCs act of mortgaging the condominium project to Bancom and FEBTC,
Sec. 1. In the exercise of its function to regulate the real estate trade and business without the knowledge and consent of David as buyer of a unit therein, and without
and in addition to its powers provided for in Presidential Decree No. 957, the the approval of the NHA (now HLURB) as required by P.D. No. 957, was not only an
National Housing Authority shall have exclusive jurisdiction to hear and decide unsound real estate business practice but also highly prejudicial to the buyer. David,
cases of the following nature: who has a cause of action for annulment of the mortgage, the mortgage foreclosure
sale, and the condominium certificate of title that was issued to the UBP and FEBTC
A. Unsound real estate business practices; as the highest bidders at the sale. The case falls within the exclusive jurisdiction of
the NHA (now HLURB) as provided in P.D. No. 957 of 1976 and P.D. No. 1344 of
B. Claims involving refund and any other claims filed by 1978.
subdivision lot or condominium unit buyer against
the project owner, developer, dealer, broker or
We hold that the jurisdiction of the HLURB to regulate the real estate trade is broad
salesman; and
enough to include jurisdiction over complaints for specific performance of the sale,
C. Cases involving specific performance of contractual and or annulment of the mortgage, of a condominium unit, with damages.[19]
statutory obligations filed by buyers of subdivision
lot or condominium unit against the owner, Petitioner avers that the Union Bank ruling is not applicable in its case, since it
developer, broker or salesman. had no knowledge of any buyer of the subject lots at the time the mortgage was
constituted; that there was no construction in the subject lots at the time petitioner
On February 7, 1981, Executive Order No. 648 transferred the regulatory and quasi- accepted the same as collateral; that the title to the subject property was still in the
judicial functions of the NHA to the Human Settlements Regulatory Commission. process of being reconstituted and the loan was in fact meant for the development
of the subject lots into an eight-unit townhouse project.
Sec. 8. TRANSFER OF FUNCTIONS. The regulatory functions of the National Housing We are not persuaded.
Authority pursuant to Presidential Decree Nos. 957, 1216, 1344 and other related
laws are hereby transferred to the Commission, together with such applicable Contrary to petitioners claim that there were no buyers of the subject lots at
personnel, appropriation, records, equipment and property necessary for the the time of the constitution of the mortgage, records show that private
enforcement and implementation of such functions. Among these regulatory respondents Arevalo, Uy, Alfredo Lim and Santos Lim had entered into contracts to
functions are: sell with Garcia/TransAmerican as early as 1988 for their respective lots. In fact,
they, except for Uy, had already fully paid their townhouse units in 1988 without
1. Regulation of the real estate trade and business: the certificates of title being delivered to them. Garcia mortgaged the subject lots
without their knowledge and consent.
7. Approval of mortgage on any subdivision lot or
condominium unit made by the owner or While private respondents spouses Soriano bought the subject lots after the
developer; constitution of the mortgage in favor of petitioner, the subject lots are, as early as
1988, subdivision lots which as defined under Section 2(e) of P.D. No. 957 to mean
11. Hear and decide cases on unsound real estate any of the lots, whether residential, commercial, industrial, or recreational in a
business practices; claims involving refund filed subdivision project[20] are entitled to the protection of P.D. No. 957.
Under Section 18 of P.D. No. 957, it is provided that no mortgage on any unit property being sold to them. It was precisely in order to deal with this kind of
or lot shall be made by the owner or developer without prior written approval of situation that P.D. No. 957 was enacted, its very essence and intendment being to
the authority. Such approval shall not be granted unless it is shown that the provide a protective mantle over helpless citizens who may fall prey to the
proceeds of the mortgage loan shall be used for the development of the razzmatazz of what P.D. No. 957 termed unscrupulous subdivision and
condominium or subdivision project and effective measures have been provided to condominium sellers.
ensure such utilization. As in the Union Bank, the mortgage was constituted on the
subject lots in favor of petitioner without the prior written approval from the Concededly, P.D. No. 957 aims to protect innocent lot buyers. Section 18 of the
HLURB, thus HLURB has jurisdiction to rule on the validity of the mortgage. decree directly addresses the problem of fraud committed against buyers when the
lot they have contracted to purchase, and which they have religiously paid for, is
Notwithstanding that petitioner became the owner of the subject lots by being
mortgaged without their knowledge. The avowed purpose of P.D. No. 957 compels
the highest bidder in the extrajudicial foreclosure sale, it must be remembered that
the reading of Section 18 as prohibitory acts committed contrary to it are void. Such
it was first a mortgagee of the same. Since the lot was mortgaged in violation of
construal ensures the attainment of the purpose of the law: to protect lot buyers,
Section 18 of P.D. No. 957, HLURB has jurisdiction to declare the mortgage void
so that they do not end up still homeless despite having fully paid for their home
insofar as private respondents are concerned and to annul the foreclosure sale.
lots with their hard-earned cash.[22]
In Far East Bank and Trust Co. vs. Marquez,[21] we held that Section 18 of P.D. No.
957 is a prohibitory law, and acts committed contrary to it are void. We said:
Since the mortgage is void, HLURBs orders of the cancellation of the sheriffs
certificate of sale, release of the mortgaged lots and delivery of the corresponding
In determining whether a law is mandatory, it is necessary to ascertain the
titles to respondents who had fully paid the purchase price of the units are but the
legislative intent, as stated by Sen. Arturo M. Tolentino, an authority on civil law:
necessary consequences of the invalidity of the mortgage for the protection of
private respondents.
There is no well-defined rule by which a mandatory or prohibitory law may, in all
circumstances, be distinguished from one which is directory, suppletory, or Anent the second issue, petitioner contends that since the titles on their face
permissive. In the determination of this question, the prime object is to ascertain were free from any claims, liens and encumbrances at the time of the mortgage, it
the legislative intention. Generally speaking, those provisions which are mere is not obliged under the law to go beyond the certificates of title registered under
matter of form, or which are not material, do not affect any substantial right, and the Torrens system and had every reason to rely on the correctness and validity of
do not relate to the essence of the thing to be done, so that compliance is a matter those titles.
of convenience rather than substance, are considered to be directory. On the other
We are not convinced.
hand, statutory provisions which relate to matters of substance, affect substantial
rights and are the very essence of the thing required to be done, are regarded as While the cases[23] cited by petitioner held that the mortgagee is not under
mandatory. obligation to look beyond the certificate of title when on its face, it was free from
lien or encumbrances, the mortgagees therein were considered in good faith as
In Philippine National Bank vs. Office of the President, we had occasion to mull over they were totally innocent and free from negligence or wrongdoing in the
the intent of P.D. No. 957 thus: transaction. In this case, petitioner knew that the loan it was extending to
Garcia/TransAmerican was for the purpose of the development of the eight-unit
. . . [T]he unmistakable intent of the law [is] to protect innocent lot buyers from townhouses. Petitioners insistence that prior to the approval of the loan, it
scheming subdivision developers. As between these small lot buyers and the undertook a thorough check on the property and found the titles free from liens
gigantic financial institutions which the developers deal with, it is obvious that the and encumbrances would not suffice. It was incumbent upon petitioner to inquire
law as an instrument of social justice must favor the weak. Indeed, the petitioner into the status of the lots which includes verification on whether Garcia had
Bank had at its disposal vast resources with which it could adequately protect its secured the authority from the HLURB to mortgage the subject lots. Petitioner
loan activities, and therefore is presumed to have conducted the usual due failed to do so. We likewise find petitioner negligent in failing to even ascertain
diligence checking and ascertaining (whether thru ocular inspection or other modes from Garcia if there are buyers of the lots who turned out to be private
of investigation) the actual status, condition, utilization and occupancy of the respondents. Petitioners want of knowledge due to its negligence takes the place of
property offered as collateral, . . . On the other hand, private respondents obviously registration, thus it is presumed to know the rights of respondents over the lot. The
were powerless to discover attempt of the land developer to hypothecate the conversion of the status of petitioner from mortgagee to buyer-owner will not
lessen the importance of such knowledge.[24] Neither will the conversion set aside Having been negligent in finding out what respondents rights were over the lot,
the consequence of its negligence as a mortgagee.[25] petitioner must be deemed to possess constructive knowledge of those rights.
Judicial notice can be taken of the uniform practice of banks to investigate,
As to the third issue, petitioner contends that private respondents were
examine and assess the real estate offered as security for the application of a loan.
negligent in failing to register their contracts to sell in accordance with Section 17 of
We cannot overemphasize the fact that the Bank cannot barefacedly argue that
P.D. No. 957; that private respondents unregistered contracts to sell are binding
simply because the title or titles offered as security were clean of any
only on them and Garcia/TransAmerican but not on petitioner which had no actual
encumbrances or lien, that it was thereby relieved of taking any other step to verify
or constructive notice of the sale at the time the mortgage was constituted.
the over-reaching implications should the subdivision be auctioned on
foreclosure.[26] We find apropos to cite our ruling in Far East Bank and Trust Co. vs. We disagree.
Marquez, thus:[27]
Section 17 of P.D. No. 957[28] provides that the seller shall register the
contracts to sell with the Register of Deeds of Quezon City. Thus, it is Garcias
Petitioner argues that it is an innocent mortgagee whose lien must be respected
responsibility as seller to register the contracts and petitioner should not blame
and protected, since the title offered as security was clean of any encumbrances or
lien. We do not agree. private respondents for not doing so. As we have said earlier, considering
petitioners negligence in ascertaining the existence or absence of authority from
HLURB for Garcia/TransAmerican to mortgage the subject lots, petitioner cannot
. . . As a general rule, where there is nothing on the certificate of title to indicate
claim to be an innocent purchaser for value and in good faith. Petitioner is bound by
any cloud or vice in the ownership of the property, or any encumbrance thereon,
private respondents contracts to sell executed with Garcia/TransAmerican.
the purchaser is not required to explore further than what the Torrens Title upon its
face indicates in quest for any hidden defect or inchoate right that may The last paragraph of Section 18 of P.D. No. 957 provides that respondents
subsequently defeat his right thereto. This rule, however, admits of an exception as who have not yet paid in full have the option to pay their installment for the lot
where the purchaser or mortgagee has knowledge of a defect or lack of title in the directly to the mortgagee (petitioner) who is required to apply such payments to
vendor, or that he was aware of sufficient facts to induce a reasonably prudent man the corresponding mortgage indebtedness secured by the particular lot or unit
to inquire into the status of the property in litigation. being paid for, with a view to enabling said buyer to obtain title over the lot or unit
promptly after full payment thereof. Thus, petitioner is obliged to accept the
Petitioner bank should have considered that it was dealing with a [townhouse] payment of remaining unpaid amortizations, without prejudice to petitioner banks
project that was already in progress. A reasonable person should have been aware seeking relief against the subdivision developer.[29]
that, to finance the project, sources of funds could have been used other than the
Notably, although no issue was taken on the fact that the case against
loan, which was intended to serve the purpose only partially. Hence, there was
Garcia/TransAmerican, the developer/seller and mortgagor of the subject lots, was
need to verify whether any part of the property was already the subject of any
archived for failure to serve summons on him/it as his whereabouts or the office
other contract involving buyers or potential buyers. In granting the loan, petitioner
could not be located, it must be stated that Garcia/TransAmerican is not an
bank should not have been content merely with a clean title, considering the
indispensable party since a final determination on the validity of the mortgage over
presence of circumstances indicating the need for a thorough investigation of the
the subject lots can be rendered against petitioner. Thus, the absence of
existence of buyers like respondent. Having been wanting in care and prudence, the
Garcia/TransAmerican did not hamper the OAALA from resolving the dispute
latter cannot be deemed to be an innocent mortgagee.
between private respondents and petitioner.

Petitioner cannot claim to be a mortgagee in good faith. Indeed it was negligent, as In China Bank vs. Oliver,[30] we held that the mortgagor, who allegedly
found by the Office of the President and by the CA. Petitioner should not have misrepresented herself to be Mercedes M. Oliver, the registered owner of TCT No.
relied only on the representation of the mortgagor that the latter had secured all S-50195, is not an indispensable party in a case filed by a person claiming to be the
requisite permits and licenses from the government agencies concerned. The true registered owner, for annulment of mortgage and cancellation of title against
former should have required the submission of certified true copies of those the mortgagee, China Bank. We found therein that even without the mortgagor, the
documents and verified their authenticity through its own independent effort. true Mercedes Oliver can prove in her complaint that she is the real person referred
in the title and she is not the same person using the name who entered into a deed
of mortgage with the mortgagee, China Bank.
In the present case, private respondents, in their complaint, alleged that the liability to private respondents for the non-completion of the projects; or to herein
mortgage was constituted without the prior written approval of the HLURB which is petitioner, as mortgagee.
in violation of Section 18 of P.D. No. 957. Petitioners admission that it granted and
The present case merely involves the liability of petitioner bank to private
released the loan without notifying the HLURB because of its belief that it was not
respondents as buyers of the lots and townhouse units.
necessary to do so, is fatal to petitioners defense. As a consequence thereof, the
mortgage constituted in favor of petitioner can be declared invalid as against WHEREFORE, the petition is DISMISSED for lack of merit.
private respondents even without the presence of Garcia/TransAmerican. It is
worthy to mention that the assailed decision was rendered merely against SO ORDERED.
petitioner and had not made any pronouncement as to Garcia/TransAmericans
LM POWER ENGINEERING CORPORATION, petitioner, vs. CAPITOL INDUSTRIAL After trial on the merits, the RTC[14] ruled that the take-over of some work items
CONSTRUCTION GROUPS, INC., respondent. by respondent was not equivalent to a termination, but a mere modification, of the
Subcontract. The latter was ordered to give full payment for the work completed by
PANGANIBAN, J.:
petitioner.
Alternative dispute resolution methods or ADRs -- like arbitration, mediation,
Ruling of the Court of Appeals
negotiation and conciliation -- are encouraged by the Supreme Court. By enabling
parties to resolve their disputes amicably, they provide solutions that are less time- On appeal, the CA reversed the RTC and ordered the referral of the case to
consuming, less tedious, less confrontational, and more productive of goodwill and arbitration. The appellate court held as arbitrable the issue of whether respondents
lasting relationships.[1] take-over of some work items had been intended to be a termination of the original
contract under Letter K of the Subcontract. It ruled likewise on two other issues:
Before us is a Petition for Review on Certiorari[2] under Rule 45 of the Rules of
whether petitioner was liable under the warranty clause of the Agreement, and
Court, seeking to set aside the January 28, 2000 Decision of the Court of whether it should reimburse respondent for the work the latter had taken over.[15]
Appeals[3] (CA) in CA-GR CV No. 54232. The dispositive portion of the Decision
reads as follows: Hence, this Petition.[16]
WHEREFORE, the judgment appealed from is REVERSED and SET ASIDE. The parties The Issues
are ORDERED to present their dispute to arbitration in accordance with their Sub-
In its Memorandum, petitioner raises the following issues for the Courts
contract Agreement.The surety bond posted by [respondent] is [d]ischarged.
consideration:
The Facts
A. Whether or not there exist[s] a controversy/dispute between petitioner and
On February 22, 1983, Petitioner LM Power Engineering Corporation and respondent regarding the interpretation and implementation of the Sub-Contract
Respondent Capitol Industrial Construction Groups Inc. entered into a Subcontract Agreement dated February 22, 1983 that requires prior recourse to voluntary
Agreement involving electrical work at the Third Port of Zamboanga.[5] arbitration;
On April 25, 1985, respondent took over some of the work contracted to B. In the affirmative, whether or not the requirements provided in Article III [1] of
petitioner.[6] Allegedly, the latter had failed to finish it because of its inability to CIAC Arbitration Rules regarding request for arbitration ha[ve] been complied
procure materials.[7] with[.][17]
Upon completing its task under the Contract, petitioner billed respondent in the The Courts Ruling
amount of P6,711,813.90.[8] Contesting the accuracy of the amount of advances
and billable accomplishments listed by the former, the latter refused to The Petition is unmeritorious.
pay. Respondent also took refuge in the termination clause of the First Issue:
Agreement.[9] That clause allowed it to set off the cost of the work that petitioner
had failed to undertake -- due to termination or take-over -- against the amount it Whether Dispute Is Arbitrable
owed the latter. Petitioner claims that there is no conflict regarding the interpretation or the
Because of the dispute, petitioner filed with the Regional Trial Court (RTC) of Makati implementation of the Agreement. Thus, without having to resort to prior
(Branch 141) a Complaint[10] for the collection of the amount representing the arbitration, it is entitled to collect the value of the services it rendered through an
alleged balance due it under the Subcontract. Instead of submitting an Answer, ordinary action for the collection of a sum of money from respondent. On the other
respondent filed a Motion to Dismiss,[11] alleging that the Complaint was hand, the latter contends that there is a need for prior arbitration as provided in the
premature, because there was no prior recourse to arbitration. Agreement. This is because there are some disparities between the parties positions
regarding the extent of the work done, the amount of advances and billable
In its Order[12] dated September 15, 1987, the RTC denied the Motion on the accomplishments, and the set off of expenses incurred by respondent in its take-over
ground that the dispute did not involve the interpretation or the implementation of of petitioners work.
the Agreement and was, therefore, not covered by the arbitral clause.[13]
We side with respondent. Essentially, the dispute arose from the parties ncongruent Supposedly, as a result of the take-over, respondent incurred expenses in excess of
positions on whether certain provisions of their Agreement could be applied to the the contracted price. It sought to set off those expenses against the amount claimed
facts.The instant case involves technical discrepancies that are better left to an by petitioner for the work the latter accomplished, pursuant to the following
arbitral body that has expertise in those areas. In any event, the inclusion of an provision:
arbitration clause in a contract does not ipso facto divest the courts of jurisdiction to
If the total direct and indirect cost of completing the remaining part of the WORK
pass upon the findings of arbitral bodies, because the awards are still judicially
reviewable under certain conditions.[18] exceed the sum which would have been payable to [petitioner] had it completed the
WORK, the amount of such excess [may be] claimed by [respondent] from either of
In the case before us, the Subcontract has the following arbitral clause: the following:
6. The Parties hereto agree that any dispute or conflict as regards to interpretation 1. Any amount due [petitioner] from [respondent] at the time of the termination of
and implementation of this Agreement which cannot be settled between this Agreement.[22]
[respondent] and [petitioner] amicably shall be settled by means of arbitration x x
The issue as to the correct amount of petitioners advances and billable
x.[19]
accomplishments involves an evaluation of the manner in which the parties
Clearly, the resolution of the dispute between the parties herein requires a referral completed the work, the extent to which they did it, and the expenses each of them
to the provisions of their Agreement. Within the scope of the arbitration clause are incurred in connection therewith. Arbitrators also need to look into the computation
discrepancies as to the amount of advances and billable accomplishments, the of foreign and local costs of materials, foreign and local advances, retention fees
application of the provision on termination, and the consequent set-off of expenses. and letters of credit, and taxes and duties as set forth in the Agreement. These data
can be gathered from a review of the Agreement, pertinent portions of which are
A review of the factual allegations of the parties reveals that they differ on the reproduced hereunder:
following questions: (1) Did a take-over/termination occur? (2) May the expenses
incurred by respondent in the take-over be set off against the amounts it owed C. CONTRACT PRICE AND TERMS OF PAYMENT
petitioner? (3) How much were the advances and billable accomplishments?
All progress payments to be made by [respondent] to [petitioner] shall be subject to
The resolution of the foregoing issues lies in the interpretation of the provisions of a retention sum of ten percent (10%) of the value of the approved quantities. Any
the Agreement. According to respondent, the take-over was caused by petitioners claims by [respondent] on [petitioner] may be deducted by [respondent] from the
delay in completing the work. Such delay was in violation of the provision in the progress payments and/or retained amount. Any excess from the retained amount
Agreement as to time schedule: after deducting [respondents] claims shall be released by [respondent] to
[petitioner] after the issuance of [the Ministry of Public Works and Highways] of the
G. TIME SCHEDULE
Certificate of Completion and final acceptance of the WORK by [the Ministry of
[Petitioner] shall adhere strictly to the schedule related to the WORK and complete Public Works and Highways].
the WORK within the period set forth in Annex C hereof. NO time extension shall be
D. IMPORTED MATERIALS AND EQUIPMENT
granted by [respondent] to [petitioner] unless a corresponding time extension is
granted by [the Ministry of Public Works and Highways] to the CONSORTIUM.[20] [Respondent shall open the letters of credit for the importation of equipment and
materials listed in Annex E hereof after the drawings, brochures, and other technical
Because of the delay, respondent alleges that it took over some of the work
data of each items in the list have been formally approved by [the Ministry of Public
contracted to petitioner, pursuant to the following provision in the Agreement: Works and Highways]. However, petitioner will still be fully responsible for all
K. TERMINATION OF AGREEMENT imported materials and equipment.

[Respondent] has the right to terminate and/or take over this Agreement for any of All expenses incurred by [respondent], both in foreign and local currencies in
the following causes: connection with the opening of the letters of credit shall be deducted from the
Contract Prices.
6. If despite previous warnings by [respondent], [petitioner] does not execute the
WORK in accordance with this Agreement, or persistently or flagrantly neglects to N. OTHER CONDITIONS
carry out [its] obligations under this Agreement.[21]
2. All customs duties, import duties, contractors taxes, income taxes, and other agreement to submit an existing or future controversy to CIAC jurisdiction,
taxes that may be required by any government agencies in connection with this notwithstanding the reference to a different arbitration institution or arbitral body
Agreement shall be for the sole account of [petitioner].[23] in such contract or submission. When a contract contains a clause for the
submission of a future controversy to arbitration, it is not necessary for the parties
Being an inexpensive, speedy and amicable method of settling
to enter into a submission agreement before the claimant may invoke the
disputes,[24] arbitration -- along with mediation, conciliation and negotiation -- is
jurisdiction of CIAC.
encouraged by the Supreme Court. Aside from unclogging judicial dockets,
arbitration also hastens the resolution of disputes, especially of the commercial The foregoing amendments in the Rules were formalized by CIAC Resolution Nos. 2-
kind.[25] It is thus regarded as the wave of the future in international civil and 91 and 3-93.[31]
commercial disputes.[26] Brushing aside a contractual agreement calling for
The difference in the two provisions was clearly explained in China Chang Jiang
arbitration between the parties would be a step backward.[27]
Energy Corporation (Philippines) v. Rosal Infrastructure Builders et al.[32] (an
Consistent with the above-mentioned policy of encouraging alternative dispute extended unsigned Resolution) and reiterated in National Irrigation Administration
resolution methods, courts should liberally construe arbitration clauses. Provided v. Court of Appeals,[33] from which we quote thus:
such clause is susceptible of an interpretation that covers the asserted dispute, an
order to arbitrate should be granted.[28] Any doubt should be resolved in favor of Under the present Rules of Procedure, for a particular construction contract to fall
within the jurisdiction of CIAC, it is merely required that the parties agree to submit
arbitration.[29]
the same to voluntary arbitration Unlike in the original version of Section 1, as
Second Issue: applied in the Tesco case, the law as it now stands does not provide that the parties
should agree to submit disputes arising from their agreement specifically to the CIAC
Prior Request for Arbitration for the latter to acquire jurisdiction over the same. Rather, it is plain and clear that
According to petitioner, assuming arguendo that the dispute is arbitrable, the failure as long as the parties agree to submit to voluntary arbitration, regardless of what
to file a formal request for arbitration with the Construction Industry Arbitration forum they may choose, their agreement will fall within the jurisdiction of the CIAC,
Commission (CIAC) precluded the latter from acquiring jurisdiction over the such that, even if they specifically choose another forum, the parties will not be
question. To bolster its position, petitioner even cites our ruling in Tesco Services precluded from electing to submit their dispute before the CIAC because this right
Incorporated v. Vera.[30] We are not persuaded. has been vested upon each party by law, i.e., E.O. No. 1008.[34]

Section 1 of Article II of the old Rules of Procedure Governing Construction Clearly, there is no more need to file a request with the CIAC in order to vest it with
Arbitration indeed required the submission of a request for arbitration, as follows: jurisdiction to decide a construction dispute.

SECTION. 1. Submission to Arbitration -- Any party to a construction contract The arbitral clause in the Agreement is a commitment on the part of the parties to
wishing to have recourse to arbitration by the Construction Industry Arbitration submit to arbitration the disputes covered therein. Because that clause is binding,
Commission (CIAC) shall submit its Request for Arbitration in sufficient copies to the they are expected to abide by it in good faith.[35] And because it covers the dispute
Secretariat of the CIAC; PROVIDED, that in the case of government construction between the parties in the present case, either of them may compel the other to
contracts, all administrative remedies available to the parties must have been arbitrate.[36]
exhausted within 90 days from the time the dispute arose.
Since petitioner has already filed a Complaint with the RTC without prior recourse to
Tesco was promulgated by this Court, using the foregoing provision as reference. arbitration, the proper procedure to enable the CIAC to decide on the dispute is to
request the stay or suspension of such action, as provided under RA 876 [the
On the other hand, Section 1 of Article III of the new Rules of Procedure Governing Arbitration Law].[37]
Construction Arbitration has dispensed with this requirement and recourse to the
CIAC may now be availed of whenever a contract contains a clause for the WHEREFORE, the Petition is DENIED and the assailed Decision AFFIRMED. Costs
submission of a future controversy to arbitration, in this wise: against petitioner.

SECTION 1. Submission to CIAC Jurisdiction An arbitration clause in a construction SO ORDERED.


contract or a submission to arbitration of a construction dispute shall be deemed an
RIZAL COMMERCIAL BANKING CORPORATION, petitioner, vs. MAGWIN as plaintiff therein to prosecute its action for an unreasonable length of time x x
MARKETING CORPORATION, NELSON TIU, BENITO SY and ANDERSON x.[10] On 31 July 2000 petitioner moved for reconsideration of the Order by
UY, respondents. informing the trial court of respondents unremitting desire to settle the case
amicably through a loan restructuring program.[11] On 22 August 2000 petitioner
DECISION notified the trial court of the acquiescence thereto of respondent Nelson Tiu as an
officer of Magwin Marketing Corporation and defendant in the civil case. [12]
BELLOSILLO, J.:
On 8 September 2000 the court a quo issued an Order reconsidering the
WE ARE PERTURBED that this case should drag this Court in the banal dismissal without prejudice of Civil Case No. 99-518
attempts to decipher the hazy and confused intent of the trial court in proceeding
with what would have been a simple, straightforward and hardly arguable Acting on plaintiffs Motion for Reconsideration of the Order dated 20 July 2000
collection case. Whether the dismissal without prejudice for failure to prosecute was dismissing this case for failure to prosecute, it appearing that there was already
unconditionally reconsidered, reversed and set aside to reinstate the civil case and conformity to the restructuring of defendants indebtedness with plaintiff by
have it ready for pre-trial are matters which should have been clarified and resolved defendant Nelson Tiu, President of defendant corporation per Manifestation and
in the first instance by the court a quo.Unfortunately, this feckless imprecision of Motion filed by plaintiff on 22 August 2000, there being probability of settlement
the trial court became the soup stock of the parties and their lawyers to further among the parties, as prayed for, the Order dated 20 July 2000 is hereby set aside.
delay the case below when they could have otherwise put things in proper order
efficiently and effectively. Plaintiff is directed to submit the compromise agreement within 15 days from
receipt hereof. Failure on the part of plaintiff to submit the said agreement shall
On 4 March 1999 petitioner Rizal Commercial Banking Corporation (RCBC) cause the imposition of payment of the required docket fees for re-filing of this
filed a complaint for recovery of a sum of money with prayer for a writ of case.[13]
preliminary attachment against respondents Magwin Marketing Corporation,
Nelson Tiu, Benito Sy and Anderson Uy.[1] On 26 April 1999, the trial court issued a
On 27 July 2000 petitioner filed in Civil Case No. 99-518 a Manifestation and
writ of attachment. [2] On 4 June 1999 the writ was returned partially satisfied since
Motion to Set Case for Pre-Trial Conference alleging that [t]o date, only defendant
only a parcel of land purportedly owned by defendant Benito Sy was attached. [3] In
Nelson Tiu had affixed his signature on the May 10, 2000 letter which informed the
the meantime, summons was served on each of the defendants, respondents
defendants that plaintiff [herein petitioner] already approved defendant Magwin
herein, who filed their respective answers, except for defendant Gabriel Cheng who
Marketing Corporations request for restructuring of its loan obligations to plaintiff
was dropped without prejudice as party-defendant as his whereabouts could not be
but subject to the terms and conditions specified in said letter.[14] This motion was
located.[4] On 21 September 1999 petitioner moved for an alias writ of attachment
followed on 5 October 2000 by petitioners Supplemental Motion to Plaintiffs
which on 18 January 2000 the court a quo denied.[5]
Manifestation and Motion to Set Case for Pre-Trial Conference affirming that
Petitioner did not cause the case to be set for pre-trial.[6] For about six (6) petitioner could not submit a compromise agreement because only defendant
months thereafter, discussions between petitioner and respondents Magwin Nelson Tiu had affixed his signature on the May 10, 2000 letter x x x. [15] Respondent
Marketing Corporation, Nelson Tiu, Benito Sy and Anderson Uy, as parties in Civil Anderson Uy opposed the foregoing submissions of petitioner while respondents
Case No. 99-518, were undertaken to restructure the indebtedness of respondent Magwin Marketing Corporation, Nelson Tiu and Benito Sy neither contested nor
Magwin Marketing Corporation.[7] On 9 May 2000 petitioner approved a debt supported them.[16]
payment scheme for the corporation which on 15 May 2000 was communicated to
The trial court, in an undated Order (although a date was later inserted in
the latter by means of a letter dated 10 May 2000 for the conformity of its officers,
the Order), denied petitioners motion to calendar Civil Case No. 99-518 for pre-trial
i.e., respondent Nelson Tiu as President/General Manager of Magwin Marketing
stating that -
Corporation and respondent Benito Sy as Director thereof. [8] Only respondent
Nelson Tiu affixed his signature on the letter to signify his agreement to the terms
and conditions of the restructuring.[9] Acting on plaintiffs [herein petitioner] Manifestation and Motion to Set Case for
Pre-Trial Conference, the Opposition filed by defendant Uy and the subsequent
On 20 July 2000 the RTC of Makati City, on its own initiative, issued Supplemental Motion filed by plaintiff; defendant Uys Opposition, and plaintiffs
an Order dismissing without prejudice Civil Case No. 99-518 for failure of petitioner Reply; for failure of the plaintiff to submit a compromise agreement pursuant to the
Order dated 8 September 2000 plaintiffs motion to set case for pre-trial conference hold otherwise, so petitioner avers, would violate Art. 2029 of the Civil Code which
is hereby denied.[17] provides that [t]he court shall endeavor to persuade the litigants in a civil case to
agree upon some fair compromise, and this Courts ruling in Goldloop Properties,
On 15 November 2000 petitioner filed its Notice of Appeal from the 8 Inc. v. Court of Appeals[23] where it was held that the trial court cannot dismiss a
September 2000 Order of the trial court as well as its undated Order in Civil Case complaint for failure of the parties to submit a compromise agreement.
No. 99-518. On 16 November 2000 the trial court issued two (2) Orders, one of
On the other hand, respondent Anderson Uy filed his comment after several
which inserted the date 6 November 2000 in the undated Order rejecting
extensions asserting that there are no special and important reasons for
petitioners motion for pre-trial in the civil case, and the other denying due course
undertaking this review. He also alleges that petitioners attack is limited to
to the Notice of Appeal on the ground that the Orders dated 8 September 2000 and
the Order dated 8 September 2000 as to whether it is conditional as the Court of
6 November 2000 are interlocutory orders and therefore, no appeal may be taken x
Appeals so found and the applicability to this case of the ruling in Goldloop
x x.[18]
Properties, Inc. v. Court of Appeals. Respondent Uy claims that
On 7 December 2000 petitioner elevated the Orders dated 8 September 2000, the Order reconsidering the dismissal of Civil Case No. 99-518 without prejudice is
6 November 2000 and 16 November 2000 of the trial court to the Court of Appeals on its face contingent upon the submission of the compromise agreement which in
in a petition for certiorari under Rule 65 of the Rules of Civil Procedure.[19] In the the first place was the principal reason of petitioner to justify the withdrawal of
main, petitioner argued that the court a quo had no authority to compel the the Order declaring his failure to prosecute the civil case. He further contends that
parties in Civil Case No. 99-518 to enter into an amicable settlement nor to deny the trial court did not force the parties in the civil case to execute a compromise
the holding of a pre-trial conference on the ground that no compromise agreement agreement, the truth being that it dismissed the complaint therein for petitioners
was turned over to the court a quo.[20] dereliction.

On 28 September 2001 the appellate court promulgated Finally, respondent Uy contests the relevance of Goldloop Properties, Inc. v.
its Decision dismissing the petition for lack of merit and affirming the Court of Appeals, and refers to its incongruence with the instant case, i.e., that the
assailed Orders of the trial court[21] holding that - complaint of petitioner was dismissed for failure to prosecute and not for its
reckless disregard to present an amicable settlement as was the situation
x x x although the language of the September 8, 2000 Order may not be clear, yet, a in Goldloop Properties, Inc., and that the dismissal was without prejudice, in
careful reading of the same would clearly show that the setting aside of the Order contrast with the dismissal with prejudice ordered in the cited case. For their part,
dated July 20, 2000 which dismissed petitioners complaint x x x for failure to respondents Magwin Marketing Corporation, Nelson Tiu and Benito Sy waived their
prosecute its action for an unreasonable length of time is dependent on the right to file a comment on the instant petition and submitted the same for
following conditions, to wit: a) The submission of the compromise agreement by resolution of this Court.[24]
petitioner within fifteen (15) days from notice; and b) Failure of petitioner to submit The petition of Rizal Commercial Banking Corporation is meritorious. It directs
the said compromise agreement shall cause the imposition of the payment of the our attention to questions of substance decided by the courts a quo plainly in a way
required docket fees for the re-filing of the case; so much so that the non- not in accord with applicable precedents as well as the accepted and usual course
compliance by petitioner of condition no. 1 would make condition no. 2 effective, of judicial proceedings; it offers special and important reasons that demand the
especially that petitioners manifestation and motion to set case for pre-trial exercise of our power of supervision and review. Furthermore, petitioners
conference and supplemental motion x x x [were] denied by the respondent judge in objections to the proceedings below encompass not only the Order of 8 September
his Order dated November 6, 2000, which in effect means that the Order dated July 2000 but include the cognate Orders of the trial court of 6 and 16 November
20, 2000 was ultimately not set aside considering that a party need not pay docket 2000. This is evident from the prayer of the instant petition which seeks to reverse
fees for the re-filing of a case if the original case has been revived and reinstated. [22] and set aside the Decision of the appellate court and to direct the trial court to
proceed with the pre-trial conference in Civil Case No. 99-518. Evidently, the
On 2 April 2002 reconsideration of the Decision was denied; hence, this substantive issue involved herein is whether the proceedings in the civil case should
petition. progress, a question which at bottom embroils all the Orders affirmed by the Court
of Appeals.
In the instant case, petitioner maintains that the trial court cannot coerce the
parties in Civil Case No. 99-518 to execute a compromise agreement and penalize
their failure to do so by refusing to go forward with the pre-trial conference. To
On the task at hand, we see no reason why RTC-Br. 135 of Makati City should agreement for the consideration of the trial court. Nothing in the second paragraph
stop short of hearing the civil case on the merits. There is no substantial policy do we read that the reconsideration is subject to two (2) qualifications. Certainly far
worth pursuing by requiring petitioner to pay again the docket fees when it has from it, for in Goldloop Properties, Inc. v. Court of Appeals[28] a similar directive, i.e.,
already discharged this obligation simultaneously with the filing of the complaint [t]he parties are given a period of fifteen (15) days from today within which to
for collection of a sum of money. The procedure for dismissed cases when re-filed is submit a Compromise Agreement, was held to mean that should the parties fail in
the same as though it was initially lodged, i.e., the filing of answer, reply, answer to their negotiations the proceedings would continue from where they left
counter-claim, including other foot-dragging maneuvers, except for the rigmarole of off. Goldloop Properties, Inc. further said that its order, or a specie of it, did not
raffling cases which is dispensed with since the re-filed complaint is automatically constitute an agreement or even an expectation of the parties that should they fail
assigned to the branch to which the original case pertained. [25] A complaint that is to settle their differences within the stipulated number of days their case would be
re-filed leads to the re-enactment of past proceedings with the concomitant full dismissed.
attention of the same trial court exercising an immaculate slew of jurisdiction and
The addition of the second sentence in the second paragraph does not change
control over the case that was previously dismissed,[26] which in the context of the
the absolute nullification of the dismissal without prejudice decreed in the first
instant case is a waste of judicial time, capital and energy.
paragraph.The sentence [f]ailure on the part of plaintiff to submit the said
What judicial benefit do we derive from starting the civil case all over again, agreement shall cause the imposition of payment of the required docket fees for re-
especially where three (3) of the four (4) defendants, i.e., Magwin Marketing filing of this case is not a directive to pay docket fees but only a statement of the
Corporation, Nelson Tiu and Benito Sy, have not contested petitioners plea before event that may result in its imposition. The reason for this is that the trial court
this Court and the courts a quo to advance to pre-trial conference? Indeed, to could not have possibly made such payment obligatory in the same civil case, i.e.,
continue hereafter with the resolution of petitioners complaint without the usual Civil Case No. 99-518, since docket fees are defrayed only after the dismissal
procedure for the re-filing thereof, we will save the court a quo invaluable time and becomes final and executory and when the civil case is re-filed.
other resources far outweighing the docket fees that petitioner would be forfeiting
It must be emphasized however that once the dismissal attains the attribute
should we rule otherwise.
of finality, the trial court cannot impose legal fees anew because a final and
Going over the specifics of this petition and the arguments of respondent executory dismissal although without prejudice divests the trial court of jurisdiction
Anderson Uy, we rule that the Order of 8 September 2000 did not reserve over the civil case as well as any residual power to order anything relative to the
conditions on the reconsideration and reversal of the Order dismissing without dismissed case; it would have to wait until the complaint is docketed once
prejudice Civil Case No. 99-518. This is quite evident from its text which does not again.[29] On the other hand, if we are to concede that the trial court retains
use words to signal an intent to impose riders on the dispositive portion - jurisdiction over Civil Case No. 99-518 for it to issue the assailed Orders, a
continuation of the hearing thereon would not trigger a disbursement for docket
Acting on plaintiffs Motion for Reconsideration of the Order dated 20 July 2000 fees on the part of petitioner as this would obviously imply the setting aside of the
dismissing this case for failure to prosecute, it appearing that there was already order of dismissal and the reinstatement of the complaint.
conformity to the restructuring of defendants indebtedness with plaintiff by
Indubitably, it is speculative to reckon the effectivity of the Order of dismissal
defendant Nelson Tiu, President of defendant corporation per Manifestation and
without prejudice to the presentation of the compromise agreement. If we are to
Motion filed by plaintiff on 22 August 2000, there being probability of settlement
admit that the efficacy of the invalidation of the Order of dismissal is dependent
among the parties, as prayed for, the Order dated 20 July 2000 is hereby set aside.
upon this condition, then we must inquire: from what date do we count the fifteen
(15)-day reglementary period within which the alleged revival of the order of
Plaintiff is directed to submit the compromise agreement within 15 days from dismissal began to run? Did it commence from the lapse of the fifteen (15) days
receipt hereof. Failure on the part of plaintiff to submit the said agreement shall provided for in the Order of 8 September 2000?Or do we count it from the 6
cause the imposition of payment of the required docket fees for re-filing of this November 2000 Order when the trial court denied the holding of a pre-trial
case.[27] conference? Or must it be upon petitioners receipt of the 16 November
2000 Order denying due course to its Notice of Appeal? The court a quo could not
Contrary to respondent Uys asseverations, the impact of the second have instituted an Order that marked the proceedings before it with a shadow of
paragraph upon the first is simply to illustrate what the trial court would do after instability and chaos rather than a semblance of constancy and firmness.
setting aside the dismissal without prejudice: submission of the compromise
The subsequent actions of the trial court also belie an intention to revive As also explained therein, the proper course of action that should have been
the Order of dismissal without prejudice in the event that petitioner fails to submit taken by the court a quo, upon manifestation of the parties of their willingness to
a compromise agreement. The Orders of 6 and 16 November 2000 plainly manifest discuss a settlement, was to suspend the proceedings and allow them reasonable
that it was retaining jurisdiction over the civil case, a fact which would not have time to come to terms (a) If willingness to discuss a possible compromise is
been possible had the dismissal without prejudice been resuscitated. Surely, the expressed by one or both parties; or (b) If it appears that one of the parties, before
court a quo could not have denied on 6 November 2000 petitioners motion to the commencement of the action or proceeding, offered to discuss a possible
calendar Civil Case No. 99-518 for pre-trial if the dismissal had been restored to life compromise but the other party refused the offer, pursuant to Art. 2030 of the Civil
in the meantime. By then the dismissal without prejudice would have already Code. If despite efforts exerted by the trial court and the parties the negotiations
become final and executory so as to effectively remove the civil case from the still fail, only then should the action continue as if no suspension had taken place. [33]
docket of the trial court.
Ostensibly, while the rules allow the trial court to suspend its proceedings
The same is true with the Order of 16 November 2000 denying due course to consistent with the policy to encourage the use of alternative mechanisms of
petitioners Notice of Appeal. There would have been no basis for such exercise of dispute resolution, in the instant case, the trial court only gave the parties fifteen
discretion because the jurisdiction of the court a quo over the civil case would have (15) days to conclude a deal. This was, to say the least, a passive and paltry attempt
been discharged and terminated by the presumed dismissal thereof. Moreover, we of the court a quo in its task of persuading litigants to agree upon a reasonable
note the ground for denying due course to the appeal: the Orders dated 8 concession.[34] Hence, if only to inspire confidence in the pursuit of a middle ground
September 2000 and 6 November 2000 are interlocutory orders and therefore, no between petitioner and respondents, we must not interpret the trial
appeal may be taken from x x x.[30] This declaration strongly suggests that courts Orders as dismissing the action on its own motion because the parties,
something more was to be accomplished in the civil case, thus negating the claim specifically petitioner, were anxious to litigate their case as exhibited in their
that the Order of dismissal without prejudice was resurrected upon the parties several manifestations and motions.
failure to yield a compromise agreement. A final order issued by a court has been
We reject respondent Uys contention that Goldloop Properties, Inc. v. Court of
defined as one which disposes of the subject matter in its entirety or terminates a
particular proceeding or action, leaving nothing else to be done but to enforce by Appeals is irrelevant to the case at bar on the dubious reasoning that the complaint
of petitioner was dismissed for failure to prosecute and not for the non-submission
execution what has been determined by the court, while an interlocutory order is
of a compromise agreement which was the bone of contention in that case, and
one which does not dispose of a case completely but leaves something more to be
decided upon.[31] that the dismissal imposed in the instant case was without prejudice, in contrast to
the dismissal with prejudice decreed in the cited case. To begin with, whether the
Besides the semantic and consequential improbabilities of respondent Uys dismissal is with or without prejudice if grievously erroneous is detrimental to the
argument, our ruling in Goldloop Properties, Inc., is decisive of the instant cause of the affected party; Goldloop Properties, Inc. does not tolerate a wrongful
case. In Goldloop Properties, Inc., we reversed the action of the trial court in dismissal just because it was without prejudice. More importantly, the facts
dismissing the complaint for failure of the plaintiff to prosecute its case, which was in Goldloop Properties, Inc. involve, as in the instant case, a dismissal for failure to
in turn based on its inability to forge a compromise with the other parties within prosecute on the ground of the parties inability to come up with a compromise
fifteen (15) days from notice of the order to do so and held - agreement within fifteen (15) days from notice of the courts order therein. All told,
the parallelism between them is unmistakable.
Since there is nothing in the Rules that imposes the sanction of dismissal for failing
Even if we are to accept on face value respondents understanding of Goldloop
to submit a compromise agreement, then it is obvious that the dismissal of the
Properties, Inc. as solely about the failure to submit a compromise agreement, it is
complaint on the basis thereof amounts no less to a gross procedural infirmity
apparent that the present case confronts a similar problem. Perhaps initially the
assailable by certiorari. For such submission could at most be directory and could
issue was one of failure to prosecute, as can be observed from the Order dated 20
not result in throwing out the case for failure to effect a compromise. While a
July 2000, although later reversed and set aside. But thereafter, in the Order of 6
compromise is encouraged, very strongly in fact, failure to consummate one does
November 2000, the trial court refused to proceed to pre-trial owing to the failure
not warrant any procedural sanction, much less an authority to jettison a civil
of the plaintiff to submit a compromise agreement pursuant to the Order dated 8
complaint worth P4,000,000.00 x x x Plainly, submission of a compromise
September 2000. When the civil case was stalled on account of the trial courts
agreement is never mandatory, nor is it required by any rule.[32]
refusal to call the parties to a pre-trial conference, the reason or basis therefor was
the absence of a negotiated settlement - a circumstance that takes the case at bar
within the plain ambit of Goldloop Properties, Inc. In any event, given that the party who has shown a sincere desire for such give-and-take.[37] All things
instant case merely revolves around the search for a reasonable interpretation of considered, we see no compelling circumstances to uphold the dismissal of
the several Orders of the trial court, i.e., as to whether the dismissal without petitioners complaint regardless of its characterization as being without prejudice.
prejudice was revived upon petitioners helplessness to perfect an out-of-court
In fine, petitioner cannot be said to have lost interest in fighting the civil case
arrangement, with more reason must we employ the ruling in Goldloop Properties,
to the end. A court may dismiss a case on the ground of non prosequitur but the
Inc. to resolve the parties differences of opinion.
real test of the judicious exercise of such power is whether under the circumstances
We also find nothing in the record to support respondent Uys conclusion that plaintiff is chargeable with want of fitting assiduousness in not acting on his
petitioner has been mercilessly delaying the prosecution of Civil Case No. 99-518 to complaint with reasonable promptitude. Unless a partys conduct is so indifferent,
warrant its dismissal. A complaint may be dismissed due to plaintiffs fault: (a) if he irresponsible, contumacious or slothful as to provide substantial grounds for
fails to appear during a scheduled trial, especially on the date for the presentation dismissal, i.e., equivalent to default or non-appearance in the case, the courts
of his evidence in chief, or when so required at the pre-trial; (b) if he neglects to should consider lesser sanctions which would still amount to achieving the desired
prosecute his action for an unreasonable length of time; or (c) if he does not comply end.[38] In the absence of a pattern or scheme to delay the disposition of the case or
with the rules or any order of the court. None of these was obtaining in the civil of a wanton failure to observe the mandatory requirement of the rules on the part
case. of the plaintiff, as in the case at bar, courts should decide to dispense rather than
wield their authority to dismiss.[39]
While there was a lull of about six (6) months in the prosecution of Civil Case
No. 99-518, it must be remembered that respondents themselves contributed Clearly, another creative remedy was available to the court a quo to attain a
largely to this delay. They repeatedly asked petitioner to consider re-structuring the speedy disposition of Civil Case No. 99-518 without sacrificing the course of
debt of respondent Magwin Marketing Corporation to which petitioner graciously justice. Since the failure of petitioner to submit a compromise agreement was the
acceded. Petitioner approved a new debt payment scheme that was sought by refusal of just one of herein respondents, i.e., Benito Sy, to sign his name on
respondents, which it then communicated to respondent Corporation through a the conforme of the loan restructure documents, and the common concern of the
letter for the conformity of the latters officers, i.e., respondent Nelson Tiu as courts a quo was dispatch in the proceedings, the holding of a pre-trial conference
President/General Manager and respondent Benito Sy as Director was the best-suited solution to the problem as this stage in a civil action is where
thereof. Regrettably, only respondent Nelson Tiu affixed his signature on the letter issues are simplified and the dispute quickly and genuinely reconciled. By means of
to signify his concurrence with the terms and conditions of the arrangement. The pre-trial, the trial court is fully empowered to sway the litigants to agree upon some
momentary lag in the civil case was aggravated when respondent Benito Sy for fair compromise.
unknown and unexplained reasons paid no heed to the adjustments in the
Dismissing the civil case and compelling petitioner to re-file its complaint is a
indebtedness although curiously he has not opposed before this Court or the
dangerous, costly and circuitous route that may end up aggravating, not resolving,
courts a quo petitioners desire to go ahead with the pre-trial conference.
the disagreement. This case management strategy is frighteningly deceptive
Admittedly, delay took place in this case but it was not an interruption that because it does so at the expense of petitioner whose cause of action, perhaps, may
should have entailed the dismissal of the complaint even if such was designated as have already been admitted by its adverse parties as shown by three (3) of four (4)
without prejudice. To constitute a sufficient ground for dismissal, the inattention of defendants not willing to contest petitioners allegations, and more critically, since
plaintiff to pursue his cause must not only be prolonged but also be unnecessary this approach promotes the useless and thankless duplication of hard work already
and dilatory resulting in the trifling of judicial processes. In the instant case, the undertaken by the trial court. As we have aptly observed, [i]nconsiderate dismissals,
adjournment was not only fleeting as it lasted less than six (6) months but was also even if without prejudice, do not constitute a panacea nor a solution to the
done in good faith to accommodate respondents incessant pleas to congestion of court dockets. While they lend a deceptive aura of efficiency to
negotiate. Although the dismissal of a case for failure to prosecute is a matter records of individual judges, they merely postpone the ultimate reckoning between
addressed to the sound discretion of the court, that judgment however must not be the parties. In the absence of clear lack of merit or intention to delay, justice is
abused. The availability of this recourse must be determined according to the better served by a brief continuance, trial on the merits, and final disposition of the
procedural history of each case, the situation at the time of the dismissal, and the cases before the court.[40]
diligence of plaintiff to proceed therein.[35] Stress must also be laid upon the official
directive that courts must endeavor to convince parties in a civil case to
consummate a fair settlement,[36] and to mitigate damages to be paid by the losing
WHEREFORE, the Petition for Review is GRANTED. The Decision dated 28
September 2001 and Resolution dated 2 April 2002 of the Court of Appeals in CA-
G.R. SP No. 62102 are REVERSED and SET ASIDE.
The Orders dated 8 September 2000, 6 November 2000 and 16 November
2000 of the Regional Trial Court, Branch 135, of Makati City, docketed as Civil Case
No. 99-518, are also REVERSED and SET ASIDE insofar as these Orders are
interpreted to impose upon and collect anew from petitioner RIZAL COMMERCIAL
BANKING CORPORATION docket or legal fees for its complaint, or to dismiss without
prejudice Civil Case No. 99-518, or to preclude the trial court from calling the
parties therein to pre-trial conference, or from proceeding thereafter with dispatch
to resolve the civil case.
Civil Case No. 99-518 is deemed REINSTATED in, as it was never taken out
from, the dockets of the Regional Trial Court, Branch 135, of Makati City. The trial
court is ORDERED to exercise its jurisdiction over Civil Case No. 99-518, to
CONDUCT the pre-trial conference therein with dispatch, and to UNDERTAKE
thereafter such other proceedings as may be relevant, without petitioner being
charged anew docket or other legal fees in connection with its reinstatement. Costs
against respondents.
SO ORDERED.
METRO CONSTRUCTION, INC., petitioner, vs. CHATHAM PROPERTIES, refurbishing, furniture, and accessories necessary for the completion
INC., respondent. of the project.
DAVIDE, JR., C.J.: 3. Under Section 1.04 of the Supplemental Contract, the total amount of
procurement and transportation cost[s] and expenses which may be
The core issue in this case is whether under existing law and rules the Court of reimbursed by MCI from CHATHAM shall not exceed the amount of
Appeals can also review findings of facts of the Construction Industry Arbitration P75,000,000.00.
Commission (CIAC). 4. In the course of the construction, Change Orders No. 1, 4, 8A, 11, 12
Respondent Chatham Properties, Inc. (CHATHAM) and petitioner Metro and 13 were implemented, payment of which were recommended by
Construction, Inc. (MCI) entered into a contract for the construction of a multi- xxx RKDCCI and approved by one of CHATHAMs Project Managers,
storey building known as the Chatham House located at the corner of Herrera and Romulo F. Sugay.
Valero Streets, Salcedo Village, Makati City, Metro Manila. In April 1998, MCI sought 5. On 15 September 1995, CHATHAM through its Project Manager,
to collect from CHATHAM a sum of money for unpaid progress billings and other
Romulo F. Sugay, agreed to give P20,000 per floor for five (5) floors,
charges and instituted a request for adjudication of its claims with the CIAC. The
or a total of P100,000.00 as bonus/incentive pay to MCIs construction
case was docketed as CIAC Case No. 10-98. The arbitral tribunal was composed of workers for the completion of each floor on schedule. CHATHAM
Joven B. Joaquin as Chairman, and Beda G. Fajardo and Loreto C. Aquino as
reimbursed MCI the amount of P60,000.00 corresponding to bonuses
members.
advanced to its workers by the latter for the 14th, 16th, and 17th floors.
The preliminary conference before the CIAC started in June 1998 and was
6. CHATHAMs payments to MCI totaled P104,875,792.37, representing
concluded a month after with the signing of the Terms of Reference (TOR) of the payments for portions of MCIs progress billings and xxx additional
Case.[1] The hearings immediately started with the presentation of MCIs witnesses,
charges.
namely: Ms. Ma. Suzette S. Nucum, Chief Accountant; Ms. Isabela Redito, Office
Engineer; Mr. John Romulo, Field Manager; and Dr. John Y. Lai, The parties then stipulated on the following issues, again, as set forth in the
President. CHATHAMs witnesses were: Engr. Ruperto Kapunan III, Managing TOR:
Director of RK Development and Construction Co., Inc. (RKDCCI), which was the
1. Is MCI entitled to its claims for unpaid progress billings amounting to
Construction Manager firm hired by CHATHAM to oversee the construction work of
P21,062,339.76?
the Chatham House; Engr. Alex Bautista, Area Manager of RKDCCI; Mr. Avelino M.
Mercado, CHATHAMs Project Manager; and Engr. Jose T. Infante. 2. Were the approved Change Orders 1, 4, 8a, 11, 12 and 13 fully paid by
[2] CHATHAM? If not, is MCI entitled to its claim for the unpaid balance?
In the meantime, the TOR was amended and finalized on 19 August 1998.
3. Is CHATHAM liable for Change Orders 7a, 7b, 10, 14, 15, 16, 17, 19 and
The facts, as admitted by the parties before the CIAC and incorporated in the
20?
original TOR, are as follows:
1. On 21 April 1994, the parties formally entered into a xxx contract for 4. Were the CHB works from the 8th to the 31st floors part of the original
contract or in the nature of extra/additional works? Is CHATHAM
the construction of the Chatham House xxx for the contract price of
liable for the same? If so, how much?
P50,000,000.00 inclusive of value-added tax, subject to adjustments
in accordance with Article 9 of the contract. Construction of the 5. Is MCI entitled to an additional reimbursement of P40,000.00 for
project, however, commenced on 15 April 1994 upon the release by bonuses granted to workers as an incentive for the early completion
CHATHAM of the downpayment. of each floor?
2. On 12 July 1994, a Supplemental Contract was executed by and 6. Were the deductions in the amount of P1,393,458.84 made by
between the parties whereby CHATHAM authorized MCI to procure CHATHAM in MCIs progress billing reasonable?
in behalf of the former materials, equipment, tools, fixtures,
7. Is MCIs claim of P1,646,502.00 for labor escalation valid?
8. Is MCI entitled to payment of attendance fee? To what extent and how CHATHAM to prove that MCI was remiss in submitting suppliers invoices and/or
much? receipts in support of its billings against the Supplemental Contract was in fact later
on abandoned when CHATHAMs witness Mercado admitted that the matter of
9. Did MCI fail to complete and/or deliver the project within the
adherence to the payment provision of the Supplemental Contract is a non-
approved completion period? If so, is MCI liable for liquidated
issue. This was borne out by the fact that progress billings and payments under
damages and how much?
both contracts were made on the basis of percentage of project completion.
10. Whether or not CHATHAM is entitled to claim x x actual damages? If
so, to what extent and how much? Both documentary and testimonial evidence prove that, effectively, the
construction contract and supplemental contract is but one agreement for a lump
11. Whether or not CHATHAM is entitled to x x x additional sum contract amount of P125,000,000.00.
counterclaims as follows:
xxx
11.1 Core testing expenses and penalty for concrete strength failure
P3,630,587.38
There was also the admitted fact that the contract was negotiated and awarded in
the absence of a complete construction plan. In any case, in support of the total
11.2. Expenses to rectify structural steel works for the foundation contract amount of P125 MILLION, is a Cost Breakdown (Exh. 17-L), where the
P1,331,139.74. estimated quantities of owner furnished materials (OFM) are indicated. It is
however, understood that these quantities are estimates, based on (an) incomplete
11.3. Cost of additional materials (concrete & rebars) supplied by CPI set of construction plans. It is likewise understood that except for the OFM, all the
P5,761,457.91 other costs in the Cost Breakdown form the basis for the lump-sum agreement
under the contract, subject to adjustment only if there are any significant changes
12. Are the parties entitled to their respective claims for attorneys fees in the contract plans.
and cost of litigation? If so, how much?[3]
In the resolution of these issues, the CIAC discovered significant data, which RKDCCI in its letter to MCI dated 15 Feb. 1995 (Exh. 4), informed MCI that it was
were not evident or explicit in the documents and records but otherwise revealed confirming the agreement allegedly accepted by Dr. Lai that the Building Committee
or elicited during the hearings, which the CIAC deemed material and relevant to the will take over the management of the construction operations (of the project) albeit
complete adjudication of the case. In its decision of 19 October 1998,[4] the CIAC under certain conditions. Specifically, the take over was for an interim period and
made the following findings and conclusions: will extend only after concreting of up to basement level 5 or up to 30 May 1995
whichever is later. The letter also stated that the Building Committee xxx will be
responsible for management and direction including management of MCI engineers
It was established during the hearing that the contract was awarded to MCI through
at the site, sequencing of work, additional labor, additional equipment and
negotiation as no bidding was conducted. xxx It was also revealed that two
management of the yard and staging area. The letter, however, emphasized that
agreements were entered into, one is labeled Construction Contract for the total
the intent is not a take over of the contract or take over of the entire work and in
fixed amount of P50,000,000.00 and the other a Supplemental Contract for an
fact, it was mentioned that MCI will still be responsible for earth anchoring and
amount not to exceed P75,000,000.00. The latter is supposed to cover the
steel fabrication work.
procurement of materials for the project. The Construction Contract provides for
monthly progress billings and payments based on actual accomplishments of the
various phases of work. The Supplemental Contract provides for reimbursement of CHATHAM claims that the interim take-over was necessitated by MCIs delay in the
[the] total amount of procurement and transportation costs and expenses, upon progress of its work, due allegedly to MCIs lack of manpower and
MCIs presentation of suppliers invoices/receipts. equipment. During the hearings of this case, this claim of MCIs lack of manpower,
necessary equipment, qualified engineers and inefficient construction management
was testified to by both Mr. Mercado [of CHATHAM] and Engr. Kapunan of RKDCCI.
However, from testimonies of witnesses from both parties, it was revealed that the
CHATHAMs witnesses, however, testified that in spite of these alleged deficiencies,
two distinct manner(s) of payment to MCI was set aside. The earlier attempt by
MCI was nevertheless allowed to continue to take full control of the
operations. When asked why termination of the contract was not resorted to if as peculiar circumstances surrounding the contracting and implementation of the
truly, MCI was not performing its contracted obligations, witnesses Mercado and CHATHAM House Project, it arrived at the following fundamental conclusions:
Kapunan cited special relations between the owner of MCI (Dr. John Lai) and the
president of CHATHAM (Mr. Lamberto UnOcampo) as the reason. 1. That indeed special friendly relations were present between the
parties in this case, although decisions by either party on any
On the other hand, Dr. Lai contends that, as explained in his letter to CHATHAM particular issue were made not purely on the basis of such special
dated 17 February 1995, (Exh. 4-A) MCIs work was on schedule. During the relations. For example, this Tribunal believes that, contrary to the
hearings, Dr. Lai also insisted that beginning 15 February 1995, MCI was relieved of allegation of (CHATHAMs) witnesses, the decision not to terminate
full control of the construction operations, that it was relegated to (be) a mere the contract was not due to the admitted special relations only, but
supplier of labor, materials and equipment, and that the alleged interim takeover also due to the greater problems the project would be faced with by
actually extended through the completion of the project. Dr. Lai cited CHATHAMs terminating the MCI contract and mobilizing another contractor.
purchases of materials, fielding labor force and sub-contracting works allegedly for
2. That while there was no official termination of the contract, the
the project without his knowledge and consent as proof that CHATHAM had taken
full control of the project. manner by which CHATHAM had taken upon themselves the
procurement of materials, the fielding of labor, the control over MCIs
engineers, and the subcontracting of various phases of work on its
To the above allegation of MCI that CHATHAM went ahead and procured materials,
own, is considered by this Tribunal as implied termination of the
hired labor and entered into sub-contract agreements with the intention of
contract. The idea of allowing MCI to remain on the project in spite of
eventually charging the costs thereof to MCI, witness Mercado countered, that
what CHATHAM claims (to be) MCIs shortcomings, and MCIs
CHATHAM has the right to do this under the provisions of Article 27 of the contract,
agreement to stay on the project under conditions set by CHATHAM,
dealing with Recision, Cancellation, Termination of Contract.
is believed a matter of mutual benefit to both parties.

By way of responding to the various counterclaims of CHATHAM, MCI referred to a 3. That CHATHAMs invoking its rights under the provisions of Article 27
letter of [the former] addressed to MCI dated 18 January 1997 (Exhibit E-1) the first of the construction contract is believed out of place, as it failed to
paragraph of which reads as follows: observe the required antecedent acts before it can exercise its
prerogative under the said contract provision.
After evaluating all the documents issued and received from both Chatham 4. That there is no reason to believe, either party was in any way guilty of
Properties Inc. and Metro Construction, Inc., the Building Committee of Chatham bad faith in acting as it did on certain relevant matters. However, this
Properties, Inc. evaluated them. The Building Committee finds the total receivable Tribunal is of the belief that due perhaps to the eagerness on the part
of Metro Construction is in the amount of EIGHT MILLION PESOS (P8,000,000.00) particularly of CHATHAMs representatives to take such steps it
only. considered necessary to insure completion of the project within the
period desired by CHATHAM, it deviated from some generally
When queried by the Tribunal if the said amount already took into account the accepted procedures in the construction industry in dealing with
costs and expenses (Chatham) claims to have incurred for the account of MCI, Mr. MCI. One example was not giving MCI the opportunity to rectify some
Mercado answered in the affirmative. When queried further how the amount was of what CHATHAM considered as construction deficiencies and
arrived at, Mr. Mercado replied that it was the sum the Building Committee figured instead engaging the services of other parties to undertake the
it was willing to pay MCI simply to close the issue. corrective works and later on charging the costs thereof to MCI.

Mr. Mercado even added that while MCI is not actually entitled to this amount, it In addition to the above conclusions resulting from what this Tribunal considered
was out of friendship that CHATHAM offered this sum to MCI as final settlement peculiar of circumstances surrounding the implementation of the project that were
under the contract. revealed during the proceedings of this case, this Tribunal finds the necessity of
establishing a cut-off date with regard to the fiscal liability of one party towards the
It is with the above attendant circumstances that this Tribunal will be guided in the other.
resolution of issues brought before it for adjudication. From what this Tribunal finds
Mr. Avelino Mercado of CHATHAM presented a list of what he claims as its Total accomplishment as of 23 May 1996 at 94.12% P117,655,000.00
Payments to MCI (Exhibit 7) summarized as follows: Add approved change orders 5,353,091.08
Total P123,008,091.08
a. Down payment (Paid in two equal trances) P20,000,000.00 Less payments up to 23 May 1996 99,002,358.42
Balance due MCI as of 23 May 1996 P24,005,732.66
b. Cash Advance for Mobilization 800,000.00
c. Payments of Progress Billings up to Billing No. 19 71,081,183.44 Of the above balance of P24,005,732.66 as of 23 May 1996, the only payments
made by CHATHAM to MCI is the sum of P5,750,000.00 from June 1996 onwards,
d. Other Payments (Mar 1994 to Apr 1996) 5,474,419.67 allegedly to cover MCI payrolls. It is of course noted that CHATHAMs suspension of
e. Advances on MCI Payrolls (April 1996 to March 1997) 8,196,755.51 further payments to MCI was because it had been undertaking on its own, the
further procurement of materials and sub-contracting of various phases of works on
Total P104,752,358.42 the project.

The records of this case show that the last progress payment to MCI was in January In consideration of the above facts, this Tribunals conclusion that there was in fact
1996 representing payment of Progress Billing No. 19 for the period ending 31 an implied take over of the project is further confirmed. Furthermore, this Tribunal
December 1995. The percentage of completion claimed then by MCI was 80.02%, additionally concludes that the cut-off date for purposes of delineating the financial
the amount evaluated and eventually paid to MCI was the equivalent of 77.15% obligations of the parties between them should be 23 May 1996, the date when
work accomplishment. No further progress payments were made thereafter, other CHATHAM evaluated MCIs accomplishment at 94.10% but nevertheless suspended
than for advances to cover MCI payrolls from April 1996 to March 1997 in the all further progress payments to MCI.
amount of P8,196,755.51 and for various advances and payments of approved
change orders in the amount of P5,474,419.67. MCI presented further documentary evidence (Exhibit E-6) the subject of which is
PUNCHLISTING-CIVIL STRUCTURAL. In this particular document which bears the
In the meantime, up to Billing No. 23 for the period ending 30 April 1996, MCI billed signatures of representatives of both MCI and RKDCCI, MCI tried to prove that as of
CHATHAM a total accomplishment of 95.29%. This billing was however, evaluated 30 August 1996 it had actually attained 99.16% work accomplishment. While it may
by CHATHAM, and in its letter to MCI dated 27 May 1996 (Exhibit E) it confirmed be true that as of that date the project had reached 99.16% completion, there is no
that MCIs remaining balance of work stands at P7,374,201.15 as of 23 May incontrovertible evidence showing that MCI was responsible for such
1996. This amount, percentage-wise, equals roughly 5.88% of the contract amount accomplishment. This was in fact actually testified to by Engr. Alex Bautista of
as testified to by Engr. Jose Infante. (Exhibit 22-B). Therefore, what was computed RKDCCI, when he said that it was an evaluation of the projects completion stage,
as MCIs work accomplishment as of 23 May 1996 was 94.12% and it is this not necessarily MCIs work accomplishment. This Tribunal therefore stands firm on
evaluation which this Tribunal believes MCI is entitled to as of said date. its conclusion that MCIs accomplishment is only up to the extent of 94.10%. [5]

Applying this percentage of completion of 94.12% to the P125,000,000.00 contract With those findings, the CIAC disposed of the specific money claims by either
amount gives a total accomplishment equivalent to P117,650,000.00 as of 23 May granting or reducing them. On Issue No. 9, i.e., whether CHATHAM failed to
1996. Add to this amount the sum of P5,353,091.08 representing the total of complete and/or deliver the project within the approved completion period and, if
approved Change Orders as of 31 December 1995 gives a total MCI accomplishment so, whether CHATHAM is liable for liquidated damages and how much, the CIAC
of P123,003,091.08, as CHATHAM saw it. Of this amount, CHATHAM admitted ruled in this wise:
having paid MCI the total sum of P104,752,358.42 only (Exhibit 7) up to March 15,
1997, leaving a balance of P18,250,732.66. It should be noted that of the total This Tribunal holds that the provision of the contract insofar as the Overall Schedule
payment of P104,752,358.42, the sum of P5,750,000.00 was paid after May 1996 so is concerned cannot justifiably be applied in the instant case in view of the implied
that as of 23 May 1996, CHATHAMs total payment to MCI was P99,002,358.42. take-over of the Chatham House project by CHATHAM. Accordingly, this Tribunal
finds no necessity to resolve whether or not MCI complete[d] and/or deliver[ed] the
Effectively, therefore, the amount due MCI as of 23 May 1996 amounted to project within the approved completion period. In fact, Mr. Mercado testified that it
P24,005,732.66 computed as follows:
was CHATHAM who ultimately completed the project, with assistance of the Less: Total payments-Item II-6 of TOR 104,875,792.37
construction managers. Balance Due MCI P 23,518,417.31
B. AMOUNTS HELD CPI IS ENTITLED TO:
In any case, this Tribunal finds merit in RKDCCIs claim that MCI was in delay in the B.1. Liquidated Damages P 3,062,498.78
concreting milestone and that [it] is liable for liquidated damages therefor. This, B.2. Actual Damages 335,994.50
notwithstanding MCIs invoking that Chatham is estopped from claiming liquidated B.3. Penalties 1,778,285.44
damages after it failed to deduct the alleged liquidated damages from MCIs B.4 Cash Payments in Behalf of MCI 2,214,715.68
progress billings. This Tribunal holds that such failure to deduct, which CHATHAM Total Amount Due CPI P 7,391,494.40
claims it did in order not to hamper progress of work in the project, is an option C. NET AMOUNT DUE MCI (A minus B) P16,126,922.91
which [it] may or may not exercise. WHEREFORE, judgment is hereby rendered in favor of the Claimant [MCI] directing
Respondent [CHATHAM] to pay Claimant [MCI] the net sum of SIXTEEN MILLION
However, this Tribunal finds that CHATHAMs Exh. 11-A where the liquidated ONE HUNDRED TWENTY SIX THOUSAND NINE HUNDRED TWENTY TWO & 91/100
damages on delays in concreting milestone was applied is not consistent with [its] (16,126,922.91) PESOS.
own Exhibit 3-I. This Tribunalnotes that in Exh. 11-A, CHATHAM included a SO ORDERED.[7]
projected delay of 85 days for the Helipad Concreting works, while no such Impugning the decision of the CIAC, CHATHAM instituted a petition for review
projected delay was included in Exh. 3-I as it should be. with the Court of Appeals, which was docketed as CA-G.R. SP No. 49429. In its
petition, CHATHAM alleged that:
This Tribunal holds that Exh. 3-I showing a delay of 294 days in concreting
milestones should rightfully be used in computing liquidated damages. Accordingly, The Arbitral Tribunal grossly erred in failing to indicate specific reference to the
this Tribunal holds that MCI is liable for liquidated damages in the amount of evidence presented or to the transcript of stenographic notes in arriving at its
P3,062,498.78 as follows: questioned Decision, in violation of the cardinal rule under Section 1, Rule 36 of the
Revised Rules of Civil Procedure that a judgment must state clearly and definitely
1/4x1/3[(1/10xP125,000,000.00)1%]x294=P3,062,498.78.[6] the facts and the law on which it is based.

The CIAC then decreed: The Tribunals conclusions are grounded entirely on speculations, surmises and
conjectures.
Accordingly, as presented below, all the amounts due MCI are first listed and added
up and the total payment is deducted therefrom. The admitted total payment The Arbitral Tribunal grossly erred in failing to consider the evidence presented by
figure as reflected in the Terms of Reference is the amount applied instead of the CHATHAM and the testimony of its witnesses.
total reflected in CHATHAMs Summary of Payments which incidentally reflected a
lesser amount. From the Balance Due MCI the Amounts CPI is Held Entitled To is The Arbitral Tribunal gravely abused its discretion in considering arbitrarily that
deducted and the Net Amount Due MCI is arrived at. there was an implied takeover contrary to the facts and evidence submitted.

A. AMOUNTS HELD MCI IS ENTITLED TO: The Arbitral Tribunal committed grave error and gross misapprehension of facts in
A.1. From the original contract: 94.12% of P125,000,000.00 P117,650,000.00 holding that CHATHAM is not entitled to liquidated damages despite failure of MCI
A.2 Approved Change Orders 5,353,091.08 to meet the over-all schedule of completion.
A.3 Pending Change Orders 1,648,560.46
A.4 CHB Works 1,248,654.71
The Arbitral Tribunal manifestly erred in holding that MCI is entitled to its claim for
A.5 Workers Bonus -0-
unpaid progress billings.
A.6 Disputed Deductions 909,484.70
A.7 Labor Escalation 1,076,256.00
A.8 Attendance Fee 508,162.73
Total P128,394,209.68
The Arbitral Tribunal committed gross and reversible error in equating the 2. Testimony of Engr. Bautista that the takeover was only partial and temporary and
percentage of MCIs work accomplishment with the entire work in place, despite limited to the management portion on the basement only and that MCI was always
evidence to the contrary. in control of the project.[13]

The Arbitral Tribunal gravely erred in making 23 May 1996 as the cut-off date for 3. Testimony of Engr. Infante that MCI personnel were constantly present in the
purposes of delineating the financial obligations of the parties. project and the intervention (not takeover) by CHATHAM was justified to ensure
completion of the project on time.[14]
The Arbitral Tribunal erred in denying CHATHAM its claim for actual damages
pursuant to Article 27.8 of the Construction Contract. 4. Documentary exhibits evincing the nature and extent of MCIs work during the
takeover period which belied its claims that it was not in control of the project
The facts set forth in CHATHAMs Answer with Compulsory Counterclaim as well as because of the takeover thus:
its documentary and testamentary evidence were not overturned or controverted
by any contrary evidence.[8] Exhibit 4 Letter dated 15 February 1995 of Engr. Kapunan of RKDCCI to John Lai of
MCI stating that the takeover of directions or management of the field operations is
In its decision of 30 September 1999,[9] the Court of Appeals simplified the interim, i.e. while the takeover is effective immediately it will extend only after
assigned errors into one core issue, namely, the propriety of the CIACs factual concreting Level B-1 or approximately until 30 May 1995 which ever is later.
findings and conclusions. In upholding the decision of the CIAC, the Court of
Appeals confirmed the jurisprudential principle that absent any showing of Exhibit 4-A Letter dated 17 February 1995 written by Dr. Lai of MCI to Engr.
arbitrariness, the CIACs findings as an administrative agency and quasi-judicial body Kapunan in response to the latters 15 February 1995 letter stating that [A]lso we
should not only be accorded great respect but also given the stamp of were assured that we will not beresponsible for any errors or accidents that may
finality. However, the Court of Appeals found exception in the CIACs disquisition of occur during this INTERIM period, indicating that Dr. Lai was very much aware of
Issue No. 9 on the matter of liquidated damages. the interim period.
The Court of Appeals disagreed with the CIACs finding that there was an
Exhibit 4-C - Letter dated 18 February 1995 written by Engr. Ben C. Ruiz of RKDCCI
implied takeover by CHATHAM of the project and that it was unnecessary for the
to Dr. Lai containing the reasons for the takeover.
CIAC to rule on whether MCI completed and/or delivered the project within the
approved completion schedule of the project since CHATHAM failed to observe the
antecedent acts required for the termination of the contract, as set forth in the Exhibit 8A Letter dated 5 September 1995 written by Dr. E.G. Tabujara to Dr.
Construction Agreement. Lai/Romy Laron (Project Manager of MCI) requesting for an engineer of MCI to
accompany the inspector of RKDCCI to witness batching procedures. By so doing,
The Court of Appeals ascertained that the evidence overwhelmingly proved Dr. E.G. Tabujara acknowledged that Dr. Lai was in control of the project.
that there was no takeover by CHATHAM and that MCI exercised complete control,
authority and responsibility over the construction. In support of this conclusion, the Exhibit 8 Letter dated 4 September 1995 by Engr. Romulo R. Sugay to Dr. Lai
appellate court pointed to the following evidentiary bases:[10] offering an incentive to the workers of MCI to exert (their) best effort for topping
off by the end of December; another clear indication that Dr. Lai was in control of
1. Testimony of CHATHAMs Engr. Kapunan that the interim takeover for the works the project.
on the basement was triggered by lack of manpower and delays as early as
February 1995, as evidenced by their assessment[11] and that the interim takeover Exhibit 4-D Letter dated 4 January 1996 indicating that Mr. H.T. Go offered Dr Lai an
was only with respect to the direction or management of the field operations and incentive of P1,800,000 on the condition that MCI meets the new
was limited only to works on the basement and intended to assist MCI to catch up schedule/milestones. MCIs acceptance of the incentive offer likewise shows that
with the schedule of completion, since at that time the project was very much MCI was in control of the Project.
delayed; thereafter, the MCI was back in full control of the project. [12]
Exhibits 3, 3-I, 3-M, 3-N, 3-W-1, 3-X, 3-Y, and 3-Z among others containing The Court of Appeals disposed of the controversy in this wise:
reminders to MCI of its duties and shortcomings, likewise attest to the fact that MCI
was in control (of) and responsible for the Project, although markedly deficient. As is extant from the records, the completion date of the Project under the
Construction Contract or under the revised construction schedule was never met by
Exhibits 5, 5-A, 5-B, 5-C, 5-D, 5-E, 5-F, 5-O, C-7, and E-9 evidencing that MCI reason of [MCIs] lack of manpower, necessary equipment, qualified engineers and
continued to manage other works on the project even during the time of the inefficient management of the construction works on the Project. Thus, under the
interim takeover of the basement works, as seen in the series of communications Contract (Exhibit 1), [MCI] had 780 days, or until 22 January 1996, from starting
between CHATHAM or RKDCCI and MCI within the period beginning February 1995 date, or April 12, 1994, to finish the project. The completion date, however, was not
to 30 May 1995. followed and was revised as early as December 17, 1994, extending the milestone
dates up to March 15, 1996 (Exhibits 3-G and 3-H). As of December 25, 1995, the
5. Respondents Request for Adjudication, Annex G, Records, Folder No. 6 - which number of days delayed was already 294 days. Thus, on February 22, 1996, the
incorporated Change Order No. 12, among others, dated 28 August 1995, contract milestones were again revised, inclusive of 53 days extension, to May 23,
recommended by the RKDCCI and accepted by Dr. Lai, and which request for an 1996 (Exhibits 3-I and 3-O). The May 23, 1996 turnover milestone nor the July 22,
extension of 25 days readily showed that even after 30 May 1995, after the close of 1996 turnover of the whole project were neither met (Exhibits 3-P, 3-R, 3-S and 3-T
the supposed takeover period, MCI was still the contractor in complete control of but [CHATHAM] was again constrained to allow [MCI] to continue working on the
the project for it would not have otherwise accepted the said change order if it Project to complete the balance of the works (Exhibit M). And all throughout the
(were) no longer the Contractor of the project due to the termination of the construction of the Project, [CHATHAM] had to assist [MCI] along the way to
Construction agreement as of said date on account of the alleged takeover. expedite the execution and completion of the Project (Exhibits 3-K and 3-V).

6. Exhibits 3-J, 3-M, 3-Q, 3-R, 3-V, 3-W-1, 3-W-2, 5-F, 5-1, 6, 12-II, 12-JJ, 12-MM, and From the foregoing disquisitions, it is clear that [MCI] is liable for liquidated
12-NN tending to prove that RKDCCI monitored the work from start to finish and damages, as per Article 13.5 of the Construction Contract, for its failure to complete
had zealously pointed out to MCI the defects or improper execution of the the project within the period stipulated in the Construction Contract and even
construction works, and gave MCI all the opportunity to rectify the construction despite an extension of 53 days from the original schedule or of the overall
deficiencies and complete the works of the project. schedule of completion. [MCI] should therefore pay [CHATHAM] the amount of
liquidated damages equivalent to P24,125,000.00 for 193 days of delay in the
The Court of Appeals concluded that the interim takeover was necessitated by overall schedule of completion counted from overall completion date on July 22,
CHATHAMs insistence to meet its own turnover dates with the buyers of the 1996 up to the date of completion on February 15, 1997, as stated in the Certificate
projects units. Thus, CHATHAM was constrained to hire subcontractors with of Occupancy, computed as follows, to wit:
sufficient manpower and supervision and incur various expenses to facilitate the
completion of the project and/or assist MCI in making up for its delay. 1/10[1%(P125,000,000.00)] per day x 193 days
=[1/10 (P1,250,000.00)] per day x 193 days
The Court of Appeals then considered it imperative to determine whether MCI =P125,000.00 per day x 193 days
failed to complete the project on time for which it may be held liable for liquidated =P24,125,000.00
damages based on the delays in the overall schedule of completion pursuant to Art.
13.5 of the Construction Agreement, to wit:
IN VIEW OF ALL THE FOREGOING, judgment is hereby rendered partially granting
[CHATHAMs] claim for liquidated damages. The Tribunals Decision dated 19
13.5. Over-All Schedule For not meeting the final completion date of the PROJECT, October 1998 is hereby AFFIRMED with the modification on [MCIs] liability for
the OWNER will deduct from the Contract Sum or amounts due the CONTRACTOR, liquidated damages in the amount of P24,125,000.00. Thus,
the amount equivalent to 1/10 of 1% of the Contract Sum for every calendar day of
delay, provided, however, that the maximum penalty should not exceed 25% of the
A. AMOUNTS [MCI] IS ENTITLED TO:
fee payable to the CONTRACTOR as stipulated in the Bill of Quantities. Penalties
A.1. From the original contract: 94.12% of P125,000,000.00 P117,650,000.00
from concreting milestones shall be deducted from the penalty of Over-All A.2 Approved Change Orders 5,353,091.08
Schedule.[15]
A.3 Pending Change Orders 1,648,560.46
A.4 CHB Works 1,248,654.71 Administrative Circular No. 1-95; (2) legislation, in particular, Republic Act No. 7902,
A.5 Workers Bonus -0- which amended Batas Pambansa Blg. 129; and (3) amendments to the Rules on Civil
A.6 Disputed Deductions 909,484.70 Procedure, modifying E.O. No. 1008 in the sense that questions of facts, of law, or
A.7 Labor Escalation 1,076,256.00 mixed questions of facts and law may be the subject of an appeal of the CIACs
A.8 Attendance Fee 508,162.73 decision to the Court of Appeals, it is still E.O. No. 1008 which remains to be the
Total P128,394,209.68 fundamental and substantive law that endows parties to an arbitral controversy the
Less: Total payments-Item ll-6 of TOR 104,875,792.37 right to appeal. Hence, the provisions on appeal of E.O. No. 1008 should be
Balance Due Respondent P 23,518,417.31 controlling, i.e., only questions of law should be entertained. Therefore, the only
B. AMOUNTS [CHATHAM] IS ENTITLED TO: effect of these rules on E.O. No. 1008 is the transfer of the appeal forum from the
B.1. Liquidated Damages P 24,125,000.00 Supreme Court to the Court of Appeals.
B.2. Actual Damages 335,994.50
MCI further asserts that, even assuming that the CIACs findings of facts are
B.3. Penalties 1,778,285.44
reviewable on appeal, the Court of Appeals gravely abused its discretion when it
B.4 Cash Payments in Behalf of MCI 2,214,715.68
Total Amount Due CPI P 28,453,995.62 accepted hook, line and sinker CHATHAMs contention that MCI was in delay, and
ignored competent, clear and substantial evidence that prove the contrary, and
C. NET AMOUNT DUE [CHATHAM] (B minus A) P 4,935,578.31
that CHATHAM is not entitled to liquidated damages.
Correspondingly, Respondent [MCI] is hereby directed to pay the Petitioner For its part, CHATHAM avers that the evolution on the rules governing appeals
[CHATHAM] the net sum of FOUR MILLION NINE HUNDRED THIRTY-FIVE THOUSAND from judgments, decisions, resolutions, orders or awards of the CIAC convincingly
FIVE HUNDRED SEVENTY-EIGHT & 31/100 (P4,935,578.31) PESOS.[16] discloses that E.O. No. 1008 has already been superseded. With the power of the
Supreme Court to promulgate rules concerning the protection and enforcement of
MCI promptly filed on 25 October 1999 a motion for reconsideration. In its constitutional rights, pleadings, practice, and procedure in all courts, its issuances
Resolution of 4 February 2000, the Court of Appeals denied MCIs motion for and amendments to the Rules on Civil Procedure, not to mention R.A. No. 7902, as
reconsideration for lack of merit, as well as CHATHAMs Motion to Lift Garnishment enacted by Congress, effectively modified E.O. No. 1008. Accordingly, the
and Levy Pending Appeal, filed on 13 October 1999, for being premature. [17] judgments, awards, decisions, resolutions, orders or awards of the CIAC are now
appealable to the Court of Appeals on questions of facts, mixed questions of facts
Thus, MCI filed the instant petition for review to challenge the decision of the and law, and questions of law, and no longer with the Supreme Court on exclusively
Court of Appeals. MCI alleges that the Court of Appeals erred in reviewing and questions of law. Further, the TOR cannot limit the expanded jurisdiction of the
reversing the CIACs factual findings, that there was an implied takeover by Court of Appeals based on the latest rules. Thus, the Court of Appeals did not err in
CHATHAM of the project, and that MCI was not in delay in the overall schedule. In reviewing the factual findings of the CIAC.
so doing, the Court of Appeals contravened Section 19 of Executive Order (E.O.) No.
1008,[18] which limits the review of an Arbitral Award to only questions of law, thus: CHATHAM also contends that, even if the Court of Appeals can only review
questions of law, said court did not err in rendering the questioned decision as the
Section 19. Finality of Awards The arbitral award shall be binding upon the conclusions therein, drawn as they were from factual determinations, can be
parties. It shall be final and inappealable (sic) except on questions of law which shall considered questions of law.
be appealable to the Supreme Court. Finally, CHATHAM asseverates that the Court of Appeals did not commit grave
abuse of discretion in reversing the CIACs ascertainment on the implied take-over
MCI then asserts that as signatories to the contract, it and CHATHAM complied and liquidated damages.
with this legal provision when they included as part of their TOR the stipulation that
[t]he decision of the Arbitral Tribunal shall be final and non-appealable except on This Court shall now resolve the primary issue raised in this case.
questions of law. Accordingly, the binding character of this provision upon the E.O. No. 1008 vests upon the CIAC original and exclusive jurisdiction over
parties is conclusive and final. disputes arising from, or connected with, contracts entered into by parties involved
MCI also contends that while it may be argued that recent (1) issuances by the in construction in the Philippines, whether the dispute arises before or after the
Supreme Court, specifically, Circular No. 1-91, which eventually became Revised completion of the contract, or after the abandonment or breach thereof. [19] By
express provision of Section 19 thereof, the arbitral award of the CIAC is final and Section 9(3) thereof reads:
unappealable, except on questions of law, which are appealable to the Supreme
Court. Section 9. Jurisdiction. -- The Court of Appeals shall exercise:
The parties, however, disagree on whether the subsequent Supreme Court
issuances on appellate procedure and R.A. No. 7902 removed from the Supreme (3) Exclusive appellate jurisdiction over all final judgments, decisions, resolutions,
Court its appellate jurisdiction in Section 19 of E.O. No. 1008 and vested the same in orders or awards of Regional Trial Courts and quasi-judicial agencies,
the Court of Appeals, and whether appeals from CIAC awards are no longer instrumentalities, boards or commissions, including the Securities and Exchange
confined to questions of law. Commission, the Social Security Commission, the Employees Compensation
Commission and the Civil Service Commission, except those falling within the
On 27 February 1991, this Court issued Circular No. 1-91, which prescribes the appellate jurisdiction of the Supreme Court in accordance with the Constitution, the
Rules Governing Appeals to the Court of Appeals from Final Orders or Decisions of Labor Code of the Philippines under Presidential Decree No. 442, as amended, the
the Court of Tax Appeals and Quasi-Judicial Agencies. Pertinent portions thereof provisions of this Act, and of subparagraph (1) of the third paragraph and
read as follows: subparagraph (4) of the fourth paragraph of Section 17 of the Judiciary Act of 1948.

1. Scope -- These rules shall apply to appeals from final orders or decisions of the The Court of Appeals shall have the power to try cases and conduct hearings,
Court of Tax Appeals. They shall also apply to appeals from final orders or decisions receive evidence and perform any and all acts necessary to resolve factual issues
of any quasi-judicial agency from which an appeal is now allowed by statute to the raised in cases falling within its original and appellate jurisdiction, including the
Court of Appeals or the Supreme Court. Among these agencies are the Securities power to grant and conduct new trials or further proceedings. x x x
and Exchange Commission, Land Registration Authority, Social Security Commission,
Civil Aeronautics Board, Bureau of Patents, Trademarks and Technology Transfer, Then this Court issued Administrative Circular No. 1-95,[21] which revised
National Electrification Administration, Energy Regulatory Board, National Circular No. 1-91. Relevant portions of the former reads as follows:
Telecommunications Commission, Secretary of Agrarian Reform and Special
Agrarian Courts under R.A. No. 6657, Government Service Insurance System,
1. Scope. --These rules shall apply to appeals from judgments or final orders of the
Employees Compensation Commission, Agricultural Inventions Board, Insurance Court of Tax Appeals and from awards, judgments, final orders or resolutions of any
Commission and Philippine Atomic Energy Commission. quasi-judicial agency from which an appeal is authorized to be taken to the Court of
Appeals or the Supreme Court. Among these agencies are the Securities and
2. Cases not Covered. -- These rules shall not apply to decisions and interlocutory Exchange Commission, Land Registration Authority, Social Security Commission,
orders of the National Labor Relations Commission or the Secretary of Labor and Civil Aeronautics Board, Bureau of Patents, Trademarks and Technology Transfer,
Employment under the Labor Code of the Philippines, the Central Board of National Electrification Administration, Energy Regulatory Board, National
Assessment Appeals, and other quasi-judicial agencies from which no appeal to the Telecommunication Commission, Department of Agrarian Reform under Republic
courts is prescribed or allowed by statute. Act No. 6657, Government Service Insurance System, Employees Compensation
Commission, Agricultural Inventions Board, Insurance Commission, Philippine
3. Who may appeal and where to appeal. -- The appeal of a party affected by a final Atomic Energy Commission, Board of Investments, and Construction Industry
order, decision, or judgment of the Court of Tax Appeals or a quasi-judicial agency Arbitration Commission.
shall be taken to the Court of Appeals within the period and in the manner herein
provided, whether the appeal involves questions of fact or of law or mixed Section 2. Cases Not Covered. These rules shall not apply to judgments or final
questions of fact and law. From final judgments or decisions of the Court of orders issued under the Labor Code of the Philippines, Central Board of Assessment
Appeals, the aggrieved party may appeal by certiorari to the Supreme Court as Appeals, and by other quasi-judicial agencies from which no appeal to the court is
provided in Rule 45 of the Rules of Court. prescribed or allowed.

Subsequently, on 23 February 1995, R.A. No. 7902 was enacted. It expanded Section 3. Where to Appeal. -- An appeal under these rules may be taken to the
the jurisdiction of the Court of Appeals and amended for that purpose Section 9 of Court of Appeals within the period and in the manner herein provided, whether the
B.P. Blg. 129, otherwise known as the Judiciary Reorganization Act of 1980. [20] appeal involves questions of fact, of law, or mixed questions of fact and law.
Thereafter, this Court promulgated the 1997 Rules on Civil Procedure. Sections In the second place, the language of Section 1 of Circular No. 1-91 emphasizes
1, 2 and 3 of Rule 43 thereof provides: the obvious inclusion of the CIAC even if it is not named in the enumeration of
quasi-judicial agencies. The introductory words [a]mong these agencies are
Section 1. Scope. -- This Rule shall apply to appeals from judgments or final orders preceding the enumeration of specific quasi-judicial agencies only highlight the fact
of the Court of Tax Appeals and from awards, judgments, final orders or resolutions that the list is not exclusive or conclusive. Further, the overture stresses and
of or authorized by any quasi-judicial agency in the exercise of its quasi-judicial acknowledges the existence of other quasi-judicial agencies not included in the
functions. Among these agencies are the Civil Service Commission, Central Board of enumeration but should be deemed included. In addition, the CIAC is obviously
Assessment Appeals, Securities and Exchange Commission, Office of the President, excluded in the catalogue of cases not covered by the Circular and mentioned in
Land Registration Authority, Social Security Commission, Civil Aeronautics Board, Section 2 thereof for the reason that at the time the Circular took effect, E.O. No.
Bureau of Patents, Trademarks and Technology Transfer, National Electrification 1008 allows appeals to the Supreme Court on questions of law.
Administration, Energy Regulatory Board, National Telecommunications
In sum, under Circular No. 1-91, appeals from the arbitral awards of the CIAC
Commission, Department of Agrarian Reform under Republic Act No. 6657,
may be brought to the Court of Appeals, and not to the Supreme Court alone. The
Government Service Insurance System, Employees Compensation Commission,
grounds for the appeal are likewise broadened to include appeals on questions of
Agricultural Inventions Board, Insurance Commission, Philippine Atomic Energy
facts and appeals involving mixed questions of fact and law.
Commission, Board of Investments, Construction Industry Arbitration Commission,
and voluntary arbitrators authorized by law. The jurisdiction of the Court of Appeals over appeals from final orders or
decisions of the CIAC is further fortified by the amendments to B.P. Blg.129, as
Section 2. Cases Not Covered. This Rule shall not apply to judgments or final orders introduced by R.A. No. 7902. With the amendments, the Court of Appeals is vested
issued under the Labor Code of the Philippines. with appellate jurisdiction over all final judgments, decisions, resolutions, orders or
awards of Regional Trial Courts and quasi-judicial agencies, instrumentalities,
Section 3. Where to Appeal. -- An appeal under this Rule may be taken to the Court boards or commissions, except those within the appellate jurisdiction of the
of Appeals within the period and in the manner herein provided, whether the Supreme Court in accordance with the Constitution, the Labor Code of the
appeal involves question of fact, of law, or mixed questions of fact and law. Philippines under Presidential Decree No. 442, as amended, the provisions of this
Act, and of subparagraph (1) of the third paragraph and subparagraph (4) of the
Through Circular No. 1-91, the Supreme Court intended to establish a uniform fourth paragraph of Section 17 of the Judiciary Act of 1948.
procedure for the review of the final orders or decisions of the Court of Tax Appeals While, again, the CIAC was not specifically named in said provision, its
and other quasi-judicial agencies provided that an appeal therefrom is then allowed inclusion therein is irrefutable. The CIAC was not expressly covered in the
under existing statutes to either the Court of Appeals or the Supreme Court. The exclusion. Further, it is a quasi-judicial agency or instrumentality. The decision
Circular designated the Court of Appeals as the reviewing body to resolve questions in Luzon Development Bank v. Luzon Development Bank Employees [24] sheds light on
of fact or of law or mixed questions of fact and law. the matter, thus:
It is clear that Circular No. 1-91 covers the CIAC. In the first place, it is a quasi-
judicial agency. A quasi-judicial agency or body has been defined as an organ of Assuming arguendo that the voluntary arbitrator or the panel of voluntary
government other than a court and other than a legislature, which affects the rights arbitrators may not strictly be considered as a quasi-judicial agency, board or
of private parties through either adjudication or rule-making.[22] The very definition commission, still both he and the panel are comprehended within the concept of a
of an administrative agency includes its being vested with quasi-judicial powers. The quasi-judicial instrumentality. It may even be stated that it was to meet the very
ever increasing variety of powers and functions given to administrative agencies situation presented by the quasi-judicial functions of the voluntary arbitrators here,
recognizes the need for the active intervention of administrative agencies in as well as the subsequent arbitrator/arbitral tribunal operating under the
matters calling for technical knowledge and speed in countless controversies which Construction Industry Arbitration Commission, that the broader term
cannot possibly be handled by regular courts.[23] The CIACs primary function is that instrumentalities was purposely included in [Section 9 of B.P. Blg. 129 as amended
of a quasi-judicial agency, which is to adjudicate claims and/or determine rights in by R.A. No. 7902].
accordance with procedures set forth in E.O. No. 1008.
An instrumentality is anything used as a means or agency. Thus, the terms
governmental agency or instrumentality are synonymous in the sense that either of
them is a means by which a government acts, or by which a certain government act The foregoing discussion renders academic MCIs assertion on the binding
or function is performed. The word instrumentality, with respect to a state, effect of its stipulation with CHATHAM in the TOR that the decision of the CIAC shall
contemplates an authority to which the state delegates governmental power for be final and non-appealable except on questions of law. The agreement merely
the performance of a state function. adopted Section 19 of E.O. No. 1008, which, as shown above, had been modified.
The TOR, any contract or agreement of the parties cannot amend, modify,
Any remaining doubt on the procedural mutation of the provisions on appeal
limit, restrict or circumscribe legal remedies or the jurisdiction of courts. Rules of
in E.O. No. 1008, vis--vis Circular No. 1-91 and R.A. No. 7902, was completely
procedure are matters of public order and interest and unless the rules themselves
removed with the issuance by the Supreme Court of Revised Administrative Circular
so allow, they cannot be altered, changed or regulated by agreements between or
No. 1-95 and the 1997 Rules of Civil Procedure. Both categorically include the CIAC
stipulations of the parties for their singular convenience.[29]
in the enumeration of quasi-judicial agencies comprehended therein. Section 3 of
the former and Section 3, Rule 43 of the latter, explicitly expand the issues that may Having resolved the existence of the authority of the Court of Appeals to
be raised in an appeal from quasi-judicial agencies or instrumentalities to the Court review the decisions, awards, or final orders of the CIAC, the Court shall now
of Appeals within the period and in the manner therein provided. Indisputably, the determine whether the Court of Appeals erred in rendering the questioned decision
review of the CIAC award may involve either questions of fact, of law, or of fact and of 30 September 1999.
law.
Settled is the general rule that the findings of facts of the Court of Appeals are
In view of all the foregoing, we reject MCIs submission that Circular No. 1-91, binding on us. There are recognized exceptions to the rule, such as when the
B.P. Blg. 129, as amended by R.A. 7902, Revised Administrative Circular 1-95, and findings are contrary to those of the trial court, [30] as in this case. Hence, we have to
Rule 43 of the 1997 Rules of Civil Procedure failed to efficaciously modify the take a closer reexamination of this case.
provision on appeals in E.O. No. 1008. We further discard MCIs claim that these
amendments have the effect of merely changing the forum for appeal from the The CIAC is certain that the evidence overwhelmingly tended to prove that the
Supreme Court to the Court of Appeals. manner by which CHATHAM took charge in the procurement of materials, fielding
of labor, control of MCI engineers and the subcontracting of various phases of the
There is no controversy on the principle that the right to appeal is work, constituted an implied takeover of the project. The CIAC then concludes that
statutory. However, the mode or manner by which this right may be exercised is a the cut-off date for delineating the fiscal liabilities of the parties is 23 May 1996
question of procedure which may be altered and modified provided that vested when CHATHAM evaluated MCIs work accomplishment at 94.12% and then
rights are not impaired. The Supreme Court is bestowed by the Constitution with suspended all further progress payments to MCI. For these reasons, the CIAC found
the power and prerogative, inter alia, to promulgate rules concerning pleadings, it trifling to determine whether MCI was in delay based on the Overall
practice and procedure in all courts, as well as to review rules of procedure of Schedule. However, the CIAC discovered that MCI was in delay for 294 days in the
special courts and quasi-judicial bodies, which, however, shall remain in force until concreting milestone and held the latter liable for liquidated damages in the
disapproved by the Supreme Court.[25] This power is constitutionally enshrined to amount of P3,062,498.78.
enhance the independence of the Supreme Court.[26]
The Court of Appeals made a contrary conclusion and declared that MCI was in
The right to appeal from judgments, awards, or final orders of the CIAC is delay for 193 days based on the overall schedule of completion of the project and
granted in E.O. No. 1008. The procedure for the exercise or application of this right should incur liquidated damages in the amount of P24,125,000.00.
was initially outlined in E.O. No. 1008. While R. A. No. 7902 and circulars
subsequently issued by the Supreme Court and its amendments to the 1997 Rules It is undisputed that the CIAC and the Court of Appeals found MCI liable for
on Procedure effectively modified the manner by which the right to appeal ought to liquidated damages but on different premises. Based on the CIACs assessment,
be exercised, nothing in these changes impaired vested rights. The new rules do not MCIs responsibility was anchored on its delay in the concreting milestone, while the
take away the right to appeal allowed in E.O. No. 1008. They only prescribe a new Court of Appeals evaluation concentrated on MCIs delay in completing the project
procedure to enforce the right. [27] No litigant has a vested right in a particular based on the overall schedule of work. The variance in the evaluation spells a
remedy, which may be changed by substitution without impairing vested rights; staggering difference in the party who should ultimately be held liable and the net
hence, he can have none in rules of procedure which relate to remedy. [28] amount involved.
A study of the final computation of the net amount due in both the final
disquisitions of the CIAC and the Court of Appeals shows that all the other figures
therein are constant, save for the amount of liquidated damages for which MCI Exhibits 4, 4-A, 4-C, 8A, 8, 4-D, 3, 3-I, 3-M, 3-N, 3-W-1, 3-X, 3-Y, 3-Z, 5,5-A, 5-B,
should be accountable. If this Court concurs with the CIACs conclusions, MCIs 5-C 5-D, 5-E, 5-F, 5-O, C-7, E-9, etc.,[32] relied upon by the Court of Appeals when
responsibility for liquidated damages is, as already stated, P3,062,498.78. Setting considered by themselves and singly, seemingly and initially evince MCIs control
this off against CHATHAMs overall fiscal accountability would bring the latters total over the project. However, they eventually lose evidentiary puissance to support
liability to MCI to P16,126,922.91. If the Court of Appeals is correct, MCI would be the Court of Appeals conclusion when reckoned against the totality of the evidence
held liable for a much higher P24,125,000 liquidated damages. Setting this off that CHATHAM took charge of the completion of the project, particularly, the fact
against CHATHAMs monetary responsibilities, MCI would still have to pay that CHATHAM suspended all progress billing payments to MCI.The continued
CHATHAM P4,935,578.31. presence and participation of MCI in the project was, as found by the CIAC, a matter
of mutual benefit to and convenience of the parties.
After painstakingly combing through the voluminous records, we affirm the
findings of the CIAC. The evidence taken as a whole or in their totality reveals that WHEREFORE, IN VIEW OF ALL THE FOREGOING, the assailed 30 September
there was an implied takeover by CHATHAM on the completion of the project. The 1999 decision of the Court of Appeals in CA-G.R. SP No. 49429 is hereby PARTIALLY
evidence that appears to accentuate the Court of Appeals decision ironically MODIFIED by setting aside the order directing Metro Construction, Inc. to pay
bolstered the CIACs conclusion. The testimonies of Engr. Kapunan, Engr. Bautista, Chatham Properties, Inc. the amount of P4,935,578.31. The arbitral award of the
Dr. Lai, and the letter of Engr. Ruiz,[31] acknowledging the temporary takeover by Construction Industry Arbitration Commission in CIAC Case 10-98, promulgated on
CHATHAM of the project, underscore the palpable fact that there was indeed a 19 October 1998, directing Chatham Properties, Inc. to pay Metro Construction, Inc.
takeover. We confer particular credit to Dr. Lais testimony that as of 15 February the sum of SIXTEEN MILLION ONE HUNDRED TWENTY-SIX THOUSAND NINE
1995, MCI was relieved of full control of the construction operations, that it was HUNDRED TWENTY-TWO & 91/100 (P16,126,922.91) PESOS, is accordingly
relegated to a mere supplier of labor, materials and equipment, and that the REINSTATED.
alleged interim takeover actually extended through the completion of the
No pronouncement as to costs.
project. Even CHATHAM admits the takeover but sugarcoated the same with words
like interim and charging the costs to MCI. With these glaring admissions, we can SO ORDERED.
even consider that the takeover was not implied but blatant.
PHILROCK, INC., petitioner, vs. CONSTRUCTION INDUSTRY ARBITRATION moral and exemplary damages and tort should be included as an issue along with
COMMISSION and Spouses VICENTE and NELIA CID, respondents. breach of contract, and whether the seven officers and engineers of Philrock who
are not parties to the Agreement to Arbitrate should be included in the arbitration
PANGANIBAN, J.:
proceedings. No common ground could be reached by the parties, hence, on April
2, 1994, both the Cid spouses and Philrock requested that the case be remanded to
Courts encourage the use of alternative methods of dispute resolution. When the trial court. On April 13, 1994, the CIAC issued an Order stating, thus:
parties agree to settle their disputes arising from or connected with construction
contracts, the Construction Industry Arbitration Commission (CIAC) acquires 'x x x the Arbitral Tribunal hereby formally dismisses the above-captioned case for
primary jurisdiction. It may resolve not only the merits of such controversies; when referral to Branch 82 of the Regional Trial Court, Quezon City where it first
appropriate, it may also award damages, interests, attorneys fees and expenses of originated.
litigation.
The Case SO ORDERED.'

Before us is a Petition for Review under Rule 45 of the Rules of Court. The
The Cid spouses then filed with said Branch of the Regional Trial Court of Quezon
Petition seeks the reversal of the July 9, 1997 Decision [1] and the February 24, 1998
City a Motion To Set Case for Hearing which motion was opposed by Philrock.
Resolution of the Court of Appeals (CA) in the consolidated cases docketed as CA-
GR SP Nos. 39781 and 42443. The assailed Decision disposed as follows:
On June 13, 1995, the trial court declared that it no longer had jurisdiction over the
case and ordered the records of the case to be remanded anew to the CIAC for
WHEREFORE, judgment is hereby rendered DENYING the petitions and,
arbitral proceedings.
accordingly, AFFIRMING in toto the CIACs decision. Costs against petitioner.[2]

Pursuant to the aforementioned Order of the Regional Trial C[o]urt of Quezon City,
The assailed Resolution ruled in this wise:
the CIAC resumed conducting preliminary conferences. On August 21, 1995, herein
[P]etitioner Philrock requested to suspend the proceedings until the court clarified
Considering that the matters raised and discussed in the motion for reconsideration its ruling in the Order dated June 13, 1995. Philrock argued that said Order was
filed by appellants counsel are substantially the same arguments which the Court based on a mistaken premise that 'the proceedings in the CIAC fell through because
had passed upon and resolved in the decision sought to be reconsidered, and there of the refusal of [Petitioner] Philrock to include the issue of damages therein,'
being no new issue raised, the subject motion is hereby DENIED.[3] whereas the true reason for the withdrawal of the case from the CIAC was due to
Philrock's opposition to the inclusion of its seven officers and engineers, who did
The Facts not give their consent to arbitration, as party defendants. On the other hand,
private respondent Nelia Cid manifested that she was willing to exclude the seven
The undisputed facts of the consolidated cases are summarized by the CA as officers and engineers of Philrock as parties to the case so as to facilitate or
follows: expedite the proceedings. With such manifestation from the Cid spouses, the
Arbitral Tribunal denied Philrock's request for the suspension of the
"On September 14, 1992, the Cid spouses, herein private respondents, filed a proceedings. Philrock's counsel agreed to the continuation of the proceedings but
Complaint for damages against Philrock and seven of its officers and engineers with reserved the right to file a pleading elucidating the position he [had] raised
the Regional Trial Court of Quezon City, Branch 82. regarding the Court's Order dated June 13, 1995. The parties then proceeded to
finalize, approve and sign the Terms of Reference. Philrock's counsel and
On December 7, 1993, the initial trial date, the trial court issued an Order dismissing representative, Atty. Pericles C. Consunji affixed his signature to said Terms of
the case and referring the same to the CIAC because the Cid spouses and Philrock Reference which stated that 'the parties agree that their differences be settled by
had filed an Agreement to Arbitrate with the CIAC. an Arbitral Tribunal x x x x' (p. 9, Terms of Reference, p. 200, Rollo).

Thereafter, preliminary conferences were held among the parties and their On September 12, 1995, [P]etitioner Philrock filed its Motion to Dismiss, alleging
appointed arbitrators. At these conferences, disagreements arose as to whether therein that the CIAC had lost jurisdiction to hear the arbitration case due to the
parties' withdrawal of their consent to arbitrate. The motion was denied by x x x Ruling of the Court of Appeals
CIAC per Order dated September 22, 1995. On November 8, public respondent
ordered the parties to appear before it on November 28, 1995 for the continuation
of the arbitral proceedings, and on February 7, 1996, public respondent directed The CA upheld the jurisdiction of the CIAC[5] over the dispute between
[P]etitioner Philrock to set two hearing dates in the month of February to present petitioner and private respondent. Under Executive Order No. 1008, the CIAC
its evidence and to pay all fees assessed by it, otherwise x x x Philrock would be acquires jurisdiction when the parties agree to submit their dispute to voluntary
deemed to have waived its right to present evidence. arbitration. Thus, in the present case, its jurisdiction continued despite its April 13,
1994 Order referring the case back to the Regional Trial Court (RTC) of Quezon City,
Hence, petitioner instituted the petition for certiorari but while said petition was Branch 82, the court of origin. The CIACs action was based on the principle that
pending, the CIAC rendered its Decision dated September 24, 1996, the dispositive once acquired, jurisdiction remains until the full termination of the case unless a
portion of which reads, as follows: law provides the contrary. No such full termination of the case was evident in the
said Order; nor did the CIAC or private respondents intend to put an end to the
case.
'WHEREFORE, judgment is hereby rendered in favor of the Claimant, directing
Respondent to pay Claimant as follows: Besides, according to Section 3 of the Rules of Procedure Governing
Construction Arbitration, technical rules of law or procedure are not applicable in a
1. P23,276.25 representing the excess cash payment for materials single arbitration or arbitral tribunal.Thus, the dismissal could not have divested the
ordered by the Claimants, (No. 7 of admitted facts) plus interests CIAC of jurisdiction to ascertain the facts of the case, arrive at a judicious resolution
thereon at the rate of 6% per annum from September 26, 1995 to the of the dispute and enforce its award or decision.
date payment is made.
Since the issues concerning the monetary awards were questions of fact, the
2. P65,000.00 representing retrofitting costs. CA held that those awards were inappropriate in a petition for certiorari. Such
questions are final and not appealable according to Section 19 of EO 1008, which
3. P13,404.54 representing refund of the value of delivered but provides that arbitral awards shall be x x x final and [u]nappealable except on
unworkable concrete mix that was laid to waste. questions of law which shall be appealable to the Supreme Court x x x.
4. P50,000.00 representing moral damages. Nevertheless, the CA reviewed the records and found that the awards were
supported by substantial evidence. In matters falling under the field of expertise of
5. P50,000.00 representing nominal damages. quasi-judicial bodies, their findings of fact are accorded great respect when
supported by substantial evidence.
6. P50,000.00 representing attorney's fees and expenses of litigation.
Hence, this Petition.[6]
7. P144,756.80 representing arbitration fees, minus such amount that
may already have been paid to CIAC by respondent. Issues

Let a copy of this Decision be furnished the Honorable Salvador C. Ceguera,


presiding judge, Branch 82 of Regional Trial Court of Quezon City who referred this The petitioner, in its Memorandum, raises the following issues:
case to the Construction Industry Arbitration Commission for arbitration and proper A. Whether or not the CIAC could take jurisdiction over the case of Respondent Cid
disposition.' (pp. 44-45, Rollo, CA-G.R. SP No. 42443) "[4] spouses against Petitioner Philrock after the case had been dismissed by both the
RTC and the CIAC.
Before the CA, petitioner filed a Petition for Review, docketed as CA-GR SP No.
42443, contesting the jurisdiction of the CIAC and assailing the propriety of the B. Whether or not Respondent Cid spouses have a cause of action against Petitioner
monetary awards in favor of respondent spouses. This Petition was consolidated by Philrock.
the CA with CA-GR SP No. 39781, a Petition for Certiorari earlier elevated by C. Whether or not the awarding of the amount of P23,276.75 for materials ordered
petitioner questioning the jurisdiction of the CIAC. by Respondent Spouses Cid plus interest thereon at the rate of 6% from 26
September 1995 is proper.
D. Whether or not the awarding of the amount of P65,000.00 as retrofitting costs is signed the Terms of Reference[10] on August 21, 1995, in which the parties
proper. stipulated the circumstances leading to the dispute; summarized their respective
positions, issues, and claims; and identified the composition of the tribunal of
E. Whether or not the awarding of the amount of P1,340,454 for the value of the
arbitrators. The document clearly confirms both parties intention and agreement to
delivered but the allegedly unworkable concrete which was wasted is proper.
submit the dispute to voluntary arbitration. In view of this fact, we fail to see how
F. Whether or not the awarding o[f] moral and nominal damages and attorney's the CIAC could have been divested of its jurisdiction.
fees and expenses of litigation in favor of respondents is proper. Finally, as pointed out by the solicitor general, petitioner maneuvered to avoid
G. Whether or not Petitioner Philrock should be held liable for the payment of the RTCs final resolution of the dispute by arguing that the regular court also lost
arbitration fees.[7] jurisdiction after the arbitral tribunals April 13, 1994 Order referring the case back
to the RTC. In so doing, petitioner conceded and estopped itself from further
In sum, petitioner imputes reversible error to the CA (1) for upholding the questioning the jurisdiction of the CIAC. The Court will not countenance the effort
jurisdiction of the CIAC after the latter had dismissed the case and referred it to the of any party to subvert or defeat the objective of voluntary arbitration for its own
regular court, (2) for ruling that respondent spouses had a cause of action against private motives. After submitting itself to arbitration proceedings and actively
petitioner, and (3) for sustaining the award of damages. participating therein, petitioner is estopped from assailing the jurisdiction of the
This Courts Ruling CIAC, merely because the latter rendered an adverse decision.[11]
The Petition has no merit.
First Issue: Jurisdiction Second Issue: Cause of Action
Petitioner avers that the CIAC lost jurisdiction over the arbitration case after both Petitioner contends that respondent spouses were negligent in not engaging
parties had withdrawn their consent to arbitrate. The June 13, 1995 RTC Order the services of an engineer or architect who should oversee their construction, in
remanding the case to the CIAC for arbitration was allegedly an invalid mode of violation of Section 308 of the National Building Code. It adds that even if the
referring a case for arbitration. concrete it delivered was defective, respondent spouses should bear the loss arising
We disagree. Section 4 of Executive Order 1008 expressly vests in the CIAC from their illegal operation. In short, it alleges that they had no cause of action
original and exclusive jurisdiction over disputes arising from or connected with against it.
construction contracts entered into by parties that have agreed to submit their We disagree. Cause of action is defined as an act or omission by which a party
dispute to voluntary arbitration.[8] violates the right of another.[12] A complaint is deemed to have stated a cause of
It is undisputed that the parties submitted themselves to the jurisdiction of action provided it has indicated the following: (1) the legal right of the plaintiff, (2)
the Commission by virtue of their Agreement to Arbitrate dated November 24, the correlative obligation of the defendant, and (3) the act or the omission of the
1993. Signatories to the Agreement were Atty. Ismael J. Andres and Perry Y. Uy defendant in violation of the said legal right.[13] The cause of action against
(president of Philippine Rock Products, Inc.) for petitioner, and Nelia G. Cid and petitioner was clearly established. Respondents were purchasers of ready-mix
Atty. Esteban A. Bautista for respondent spouses.[9] concrete from petitioner. The concrete delivered by the latter turned out to be of
substandard quality. As a result, respondents sustained damages when the
Petitioner claims, on the other hand, that this Agreement was withdrawn by structures they built using such cement developed cracks and
respondents on April 8, 1994, because of the exclusion of the seven engineers of honeycombs. Consequently, the construction of their residence had to be stopped.
petitioners in the arbitration case. This withdrawal became the basis for the April
13, 1994 CIAC Order dismissing the arbitration case and referring the dispute back Further, the CIAC Decision clearly spelled out respondents cause of action
to the RTC. Consequently, the CIAC was divested of its jurisdiction to hear and against petitioner, as follows:
decide the case.
Accordingly, this Tribunal finds that the mix was of the right proportions at the time
This contention is untenable. First, private respondents removed the obstacle it left the plant. This, however, does not necessarily mean that all of the concrete
to the continuation of the arbitration, precisely by withdrawing their objection to mix delivered had remained workable when it reached the jobsite. It should be
the exclusion of the seven engineers. Second, petitioner continued participating in noted that there is no evidence to show that all the transit mixers arrived at the site
the arbitration even after the CIAC Order had been issued. It even concluded and
within the allowable time that would ensure the workability of the concrete mix aware of it, a memorandum having been submitted citing all the
delivered. demands of [c]laimants. This assurance was made on July 31, 1992
when Respondents Secillano, Martillano and Lomibao came to see
On the other hand, there is sufficiently strong evidence to show that difficulties Claimant Nelia Cid and offered to refund P23,276.25, [t]he difference
were encountered in the pouring of concrete mix from certain transit mixers between the billing by Philrocks Marketing Department in the
necessitating the [addition] of water and physically pushing the mix, obviously amount of P125,586.25 and the amount charged by Philrock's
because the same [was] no longer workable. This Tribunal holds that the Batching Plant Department in the amount of only P102,586.25, which
unworkability of said concrete mix has been firmly established. [c]laimant refused to accept by saying, Saka na lang.[18]
The same issue was discussed during the hearing before the arbitration
There is no dispute, however, to the fact that there are defects in some areas of the tribunal on December 19, 1995.[19] It was also mentioned in that tribunals Decision
poured structures. In this regard, this Tribunal holds that the only logical reason is dated September 24, 1996.[20]
that the unworkable concrete was the one that was poured in the defective
sections.[14] The payment of interest is based on Article 2209 of the Civil Code, which
provides that if the obligation consists of the payment of a sum of money, and the
Third Issue: Monetary Awards debtor incurs delay, the indemnity for damages shall be the payment of legal
interest which is six per cent per annum, in the absence of a stipulation of the rate.
Petitioner assails the monetary awards given by the arbitral tribunal for
alleged lack of basis in fact and in law. The solicitor general counters that the basis Awards for Retrofitting Costs, Wasted Unworkable But Delivered Concrete, and
for petitioners assigned errors with regard to the monetary awards is purely factual Arbitration Fees
and beyond the review of this Court. Besides, Section 19, EO 1008, expressly Petitioner maintains that the defects in the concrete structure were due to
provides that monetary awards by the CIAC are final and unappealable. respondent spouses failure to secure the services of an engineer or architect to
We disagree with the solicitor general. As pointed out earlier, factual findings supervise their project. Hence, it claims that the award for retrofitting cost was
of quasi-judicial bodies that have acquired expertise are generally accorded great without legal basis. It also denies liability for the wasted unworkable but delivered
respect and even finality, if they are supported by substantial evidence. [15] The concrete, for which the arbitral court awarded P13,404.54.Finally, it complains
Court, however, has consistently held that despite statutory provisions making the against the award of litigation expenses, inasmuch as the case should not have
decisions of certain administrative agencies final, it still takes cognizance of been instituted at all had respondents complied with the requirements of the
petitions showing want of jurisdiction, grave abuse of discretion, violation of due National Building Code.
process, denial of substantial justice or erroneous interpretation of the We are unconvinced. Not only did respondents disprove the contention of
law.[16] Voluntary arbitrators, by the nature of their functions, act in a quasi-judicial petitioner; they also showed that they sustained damages due to the defective
capacity, such that their decisions are within the scope of judicial review.[17] concrete it had delivered. These were items of actual damages they sustained due
Petitioner protests the award to respondent spouses of P23,276.25 as excess to its breach of contract.
payment with six percent interest beginning September 26, 1995. It alleges that this Moral and Nominal Damages, Attorneys Fees and Costs
item was neither raised as an issue by the parties during the arbitration case, nor
was its justification discussed in the CIAC Decision. It further contends that it could Petitioner assails the award of moral damages, claiming no malice or bad faith
not be held liable for interest, because it had earlier tendered a check in the same on its part.
amount to respondent spouses, who refused to receive it.
We disagree. Respondents were deprived of the comfort and the safety of a
Petitioners contentions are completely untenable. Respondent Nelia G. Cid house and were exposed to the agony of witnessing the wastage and the decay of
had already raised the issue of overpayment even prior to the formal arbitration. In the structure for more than seven years. In her Memorandum, Respondent Nelia G.
paragraph 9 of the Terms of Reference, she stated: Cid describes her familys sufferings arising from the unreasonable delay in the
construction of their residence, as follows: The family lives separately for lack of
9. Claimants were assured that the problem and her demands had been space to stay in. Mrs. Cid is staying in a small dingy bodega, while her son occupies
the subject of several staff meetings and that Arteche was very much another makeshift room. Their only daughter stayed with her aunt from 1992 until
she got married in 1996. x x x.[21] The Court also notes that during the pendency of in gross and evident bad faith in refusing to satisfy plaintiffs valid, just and
the case, Respondent Vicente Cid died without seeing the completion of their demandable claim.
home.[22] Under the circumstances, the award of moral damages is proper.
We disagree. The award is not only for attorneys fees, but also for expenses of
Petitioner also contends that nominal damages should not have been granted, litigation. Hence, it does not matter if respondents represented themselves in
because it did not breach its obligation to respondent spouses. court, because it is obvious that they incurred expenses in pursuing their action
before the CIAC, as well as the regular and the appellate courts. We find no reason
Nominal damages are recoverable only if no actual or substantial damages to disturb this award.
resulted from the breach, or no damage was or can be shown.[23] Since actual
damages have been proven by private respondents for which they were amply WHEREFORE, the Petition is DENIED and the assailed Decision AFFIRMED;
compensated, they are no longer entitled to nominal damages. however, the award of nominal damages is DELETED for lack of legal basis. Costs
against petitioner.
Petitioner protests the grant of attorneys fees, arguing that respondent
spouses did not engage the services of legal counsel. Also, it contends that SO ORDERED.
attorneys fees and litigation expenses are awarded only if the opposing party acted
Melo, (Chairman), Vitug, Gonzaga-Reyes, and Sandoval-Gutierrez, JJ., concur.
SEA-LAND SERVICE, INC., petitioner, vs. COURT OF APPEALS, A.P. November 10, 1992, averring that whatever damages sustained by Florex were
MOLLER/MAERSK LINE and MAERSK-TABACALERA SHIPPING AGENCY (FILIPINAS), caused by petitioner, which actually received and transported Florexs cargo on its
INC., respondents. vessels and unloaded them.

YNARES-SANTIAGO, J.: On January 1, 1993, petitioner filed a Motion to Dismiss the Third Party
Complaint[6] on the ground of failure to state a cause of action and lack of
This petition for review on certiorari seeks to annul and set aside the decision of the jurisdiction, the amount of damages not having been specified therein. Petitioner
Court of Appeals dated September 29, 1995 in CA-G.R. SP No. 35777,[1] dismissing also prayed either for dismissal or suspension of the Third Party Complaint on the
the petition for certiorari filed by petitioner to annul the two (2) orders issued by ground that there exists an arbitration agreement between it and respondent
the Regional Trial Court of Quezon City, Branch 216, in Civil Case No. Q-92-12593. AMML. On September 27, 1993, the lower court issued an Order denying
petitioners Motion to Dismiss. Petitioners Motion for Reconsideration was likewise
The facts are as follows: denied by the lower court in its August 22, 1994 Order.

On April 29, 1991, petitioner Sea-Land Services, Inc. and private respondent A.P. Undaunted, petitioner filed a petition for certiorari[7] with the Court of Appeals on
Moller/Maersk Line (hereinafter referred to as "AMML"), both carriers of cargo in November 23, 1994. Meanwhile, petitioner also filed its Answer to the Third Party
containerships as well as common carriers, entered into a contract entitled, "Co- Complaint in the trial court.
operation in the Pacific"[2] (hereinafter referred to as the "Agreement"), a vessel
sharing agreement whereby they mutually agreed to purchase, share and exchange On September 29, 1995, respondent Court of Appeals rendered the assailed
needed space for cargo in their respective containerships. Under the Agreement, Decision dismissing the petition for certiorari. With the denial of its Motion for
they could be, depending on the occasion, either a principal carrier (with a Reconsideration, petitioner filed the instant petition for review, raising the
negotiable bill of lading or other contract of carriage with respect to cargo) or a following issues
containership operator (owner, operator or charterer of containership on which the
cargo is carried). I. THE COURT OF APPEALS DISREGARDED AN AGREEMENT TO ARBITRATE IN
VIOLATION OF STATUTE AND SUPREME COURT DECISIONS HOLDING THAT
During the lifetime of the said Agreement, or on 18 May 1991, Florex International, ARBITRATION IS A CONDITION PRECEDENT TO SUIT WHERE SUCH AN AGREEMENT
Inc. (hereinafter referred to as "Florex") delivered to private respondent AMML TO ARBITRATE EXISTS.
cargo of various foodstuffs, with Oakland, California as port of discharge and San
Francisco as place of delivery. The corresponding Bill of Lading No. MAEU II. THE COURT OF APPEALS HAS RULED IN A MANNER NOT IN ACCORD WITH
MNL110263 was issued to Florex by respondent AMML. Pursuant to the JURISPRUDENCE WHEN IT REFUSED TO HAVE THE THIRD-PARTY COMPLAINT
Agreement, respondent AMML loaded the subject cargo on MS Sealand Pacer, a DISMISSED FOR FAILURE TO STATE A CAUSE OF ACTION AND FOR RULING THAT THE
vessel owned by petitioner. Under this arrangement, therefore, respondent AMML FAILURE TO STATE A CAUSE OF ACTION MAY BE REMEDIED BY REFERENCE TO ITS
was the principal carrier while petitioner was the containership operator. ATTACHMENTS.[8]

The consignee refused to pay for the cargo, alleging that delivery thereof was Resolving first the issue of failure to state a cause of action, respondent Court of
delayed. Thus, on June 26, 1992, Florex filed a complaint against respondent Appeals did not err in reading the Complaint of Florex and respondent AMMLs
Maersk-Tabacalera Shipping Agency (Filipinas), Inc. for reimbursement of the value Answer together with the Third Party Complaint to determine whether a cause of
of the cargo and other charges.[3] According to Florex, the cargo was received by the action is properly alleged. In Fil-Estate Golf and Development, Inc. vs. Court of
consignee only on June 28, 1991, since it was discharged in Long Beach, California, Appeals,[9] this Court ruled that in the determination of whether or not the
instead of in Oakland, California on June 5, 1991 as stipulated. complaint states a cause of action, the annexes attached to the complaint may be
considered, they being parts of the complaint.
Respondent AMML filed its Answer[4] alleging that even on the assumption that
Florex was entitled to reimbursement, it was petitioner who should be liable. Coming now to the main issue of arbitration, the pertinent clauses of the "Co-
Accordingly, respondent AMML filed a Third Party Complaint [5] against petitioner on operation in the Pacific" contract entered into by the parties provide:
16.2 For the purposes of this agreement the Containership agreement between the Lines within 14 days after service by one
Operator shall be deemed to have issued to the Principal Carrier Line upon the other of a notice specifying the nature of the
for good consideration and for both loaded and empty containers dispute or claim and requiring reference of such dispute or claim
its non-negotiable memo bills of lading in the form attached to arbitration pursuant to this Article.
hereto as Appendix 6, consigned only to the Principal Carrier or its
agents, provisions of which shall govern the liability between the 32.2 Failing agreement upon an arbitrator within such period of
Principal Carrier and the Containership Operator and that for the 14 days, the dispute shall be settled by three Arbitrators, each
purpose of determining the liability in accordance with either party appointing one Arbitrator, the third being appointed by the
Lines memo bill of lading, the number of packages or customary President of the London Maritime Arbitrators Association.
freight units shown on the bill of lading issued by the Principal
Carrier to its shippers shall be controlling. 32.3 If either of the appointed Arbitrators refuses or is incapable
of acting, the party who appointed him shall appoint a new
16.3 The Principal Carrier shall use all reasonable endeavours to Arbitrator in his place.
defend all in personam and in rem suits for loss of or damage to
cargo carried pursuant to bills of lading issued by it, or to settle 32.4 If one of the parties fails to appoint an Arbitrator either
such suits for as low a figure as reasonably possible. The Principal originally or by way of substitution for two weeks after the other
Carrier shall have the right to seek damages and/or an party having appointed his Arbitrator has sent the party making
indemnity from the Containership Operator by arbitration default notice by mail, fax or telex to make the appointment, the
pursuant to Clause 32 hereof. Notwithstanding the provisions of party appointing the third Arbitrator shall, after application from
the Lines memo bills of lading or any statutory rules incorporated the party having appointed his Arbitrator, also appoint an
therein or applicable thereto, the Principal Carrier shall be Arbitrator in behalf of the party making default.
entitled to commence such arbitration at any time until one year
after its liability has been finally determined by agreement,
32.5 Any such arbitration shall be in accordance with the
arbitration award or judgment, such award or judgment not
Arbitration Act 1950 as amended by the Arbitration Act 1979 or
being the subject of appeal, provided that the Containership
any other subsequent legislation and the arbitrators award shall
Operator has been given notice of the said claim in writing by
be final and binding upon Lines. To the extent permitted by the
the Principal Carrier within three months of the Principal Carrier
Arbitration Act 1979 the Lines hereto exclude pursuant to S 3(1)
receiving notice in writing of the claim. Further the Principal
of that Act the jurisdiction of the English High Court of Justice to
Carrier shall have the right to grant extensions of time for the
entertain any appeal or application under Section 1 and 2 of the
commencement of suit to any third party interested in the cargo
Arbitration Act 1979.[10]
without prior reference to the Containership Operator provided
that notice of any extension so granted is given to the
From the foregoing, the following matters are clear: First, disputes between the
Containership Operator within 30 days of any such extension
Principal Carrier and the Containership Operator arising from contracts of carriage
being granted.
shall be governed by the provisions of the bills of lading issued to the Principal
Carrier by the Containership Operator. Second, the Principal Carrier shall use its
xxxxxxxxx
best efforts to defend or settle all suits against it for loss of or damage to cargo
pursuant to bills of lading issued by it. Third, the Principal Carrier shall have the
32. ARBITRATION right to seek damages and/or indemnity from the Containership Operator by
arbitration, pursuant to Clause 32 of the agreement. Fourth, the Principal Carrier
32.1 If at any time a dispute or claim arises out of or in connection shall have the right to commence such arbitration any time until one year after its
with the Agreement the Lines shall endeavour to settle such liability has been finally determined by agreement, arbitration award or judgment,
amicably, failing which it shall be referred to arbitration by a provided that the Containership Operator was given notice in writing by the
single arbitrator in London, such arbitrator to be appointed by
Principal Carrier within three months of the Principal Carrier receiving notice in respondent AMML is barred from taking judicial action against petitioner by the
writing of said claim. clear terms of their Agreement.

Prescinding from the foregoing matters, we find that both the trial court and the As the Principal Carrier with which Florex directly dealt with, respondent AMML can
Court of Appeals erred in denying petitioners prayer for arbitration. and should be held accountable by Florex in the event that it has a valid claim
against the former. Pursuant to Clause 16.3 of the Agreement, respondent AMML,
To begin with, allowing respondent AMMLs Third Party Claim against petitioner to when faced with such a suit "shall use all reasonable endeavours to defend" itself or
proceed would be in violation of Clause 16.2 of the Agreement. As summarized, the "settle such suits for as low a figure as reasonably possible". In turn, respondent
clause provides that whatever dispute there may be between the Principal Carrier AMML can seek damages and/or indemnity from petitioner as Containership
and the Containership Operator arising from contracts of carriage shall be governed Operator for whatever final judgment may be adjudged against it under the
by the provisions of the bills of lading deemed issued to the Principal Carrier by the Complaint of Florex. The crucial point is that collection of said damages and/or
Containership Operator. On the other hand, to sustain the Third Party Complaint indemnity from petitioner should be by arbitration.
would be to allow private respondent to hold petitioner liable under the provisions
of the bill of lading issued by the Principal Carrier to Florex, under which the latter is All told, when the text of a contract is explicit and leaves no doubt as to its
suing in its Complaint, not under the bill of lading petitioner, as containership intention, the court may not read into it any other intention that would contradict
operator, issued to respondent AMML, as Principal Carrier, contrary to what is its plain import.[11]Arbitration being the mode of settlement between the parties
contemplated in Clause 16.2. expressly provided for by their Agreement, the Third Party Complaint should have
been dismissed.
The Court of Appeals ruled that the terms of the Agreement "explicitly required
that the principal carriers claim against the containership operator first be finally This Court has previously held that arbitration is one of the alternative methods of
determined by, among others, a court judgment, before the right to arbitration dispute resolution that is now rightfully vaunted as "the wave of the future" in
accrues." However, the Court of Appeals failed to consider that, precisely, international relations, and is recognized worldwide. To brush aside a contractual
arbitration is the mode by which the liability of the Containership Operator may be agreement calling for arbitration in case of disagreement between the parties
finally determined. This is clear from the mandate of Clause 16.3 that "(T)he would therefore be a step backward.[12]
Principal Carrier shall have the right to seek damages and/or an indemnity from the
Containership Operator by arbitration" and that it "shall be entitled to commence WHEREFORE, premises considered, the instant Petition for Review on Certiorari is
such arbitration at any time until one year after its liability has been finally GRANTED. The decision of the Court of Appeals in CA-G.R. SP No. 35777 is
determined by agreement, arbitration award or judgment". REVERSED and SET ASIDE. The Regional Trial Court of Quezon City, Branch 77, is
ordered to DISMISS Respondent AMMLs Third Party Complaint in Civil Case No. Q-
For respondent Court of Appeals to say that the terms of the contract do not 92-12593. No pronouncement as to costs.
require arbitration as a condition precedent to judicial action is erroneous. In the
light of the Agreement clauses aforequoted, it is clear that arbitration is the mode SO ORDERED.
provided by which respondent AMML as Principal Carrier can seek damages and/or
indemnity from petitioner, as Containership Operator. Stated differently, Davide, Jr., C.J., (Chairman), Puno, Kapunan, and Pardo, JJ., concur.
MAGELLAN CAPITAL MANAGEMENT CORPORATION and MAGELLAN CAPITAL Disagreeing with the position taken by petitioners, respondent Zosa invoked
HOLDINGS CORPORATION, petitioners, vs. ROLANDO M. ZOSA and HON. JOSE P. the Arbitration Clause of the Employment Agreement, to wit:
SOBERANO, JR., in his capacity as Presiding Judge of Branch 58 of the Regional
Trial Court Of Cebu, 7th Judicial Region, respondents. 23. Arbitration. In the event that any dispute, controversy or claim arises out of or
under any provisions of this Agreement, then the parties hereto agree to submit
DECISION such dispute, controversy or claim to arbitration as set forth in this Section and the
determination to be made in such arbitration shall be final and binding. Arbitration
BUENA, J.: shall be effected by a panel of three arbitrators. The Manager, Employee and
Corporation shall designate one (1) arbitrator who shall, in turn, nominate and elect
Under a management agreement entered into on March 18, 1994, Magellan who among them shall be the chairman of the committee. Any such arbitration,
Capital Holdings Corporation [MCHC] appointed Magellan Capital Management including the rendering of an arbitration award, shall take place in Metro
Corporation [MCMC] as manager for the operation of its business and Manila. The arbitrators shall interpret this Agreement in accordance with the
affairs.[1] Pursuant thereto, on the same month, MCHC, MCMC, and private substantive laws of the Republic of the Philippines. The arbitrators shall have no
respondent Rolando M. Zosa entered into an "Employment Agreement" designating power to add to, subtract from or otherwise modify the terms of Agreement or to
Zosa as President and Chief Executive Officer of MCHC. grant injunctive relief of any nature. Any judgment upon the award of the
Under the "Employment Agreement", the term of respondent Zosa's arbitrators may be entered in any court having jurisdiction thereof, with costs of the
employment shall be co-terminous with the management agreement, or until arbitration to be borne equally by the parties, except that each party shall pay the
March 1996,[2] unless sooner terminated pursuant to the provisions of the fees and expenses of its own counsel in the arbitration.
Employment Agreement.[3] The grounds for termination of employment are also
provided in the Employment Agreement. On November 10, 1995, respondent Zosa designated his brother, Atty. Francis
Zosa, as his representative in the arbitration panel[9] while MCHC designated Atty.
On May 10, 1995, the majority of MCHCs Board of Directors decided not to re- Inigo S. Fojas[10] and MCMC nominated Atty. Enrique I. Quiason[11] as their
elect respondent Zosa as President and Chief Executive Officer of MCHC on account respective representatives in the arbitration panel. However, instead of submitting
of loss of trust and confidence[4] arising from alleged violation of the resolution the dispute to arbitration, respondent Zosa, on April 17, 1996, filed an action for
issued by MCHC's board of directors and of the non-competition clause of the damages against petitioners before the Regional Trial Court of Cebu [12] to enforce
Employment Agreement.[5] Nevertheless, respondent Zosa was elected to a new his benefits under the Employment Agreement.
position as MCHC's Vice-Chairman/Chairman for New Ventures Development.[6]
On July 3, 1996, petitioners filed a motion to dismiss[13] arguing that (1) the
On September 26, 1995, respondent Zosa communicated his resignation for trial court has no jurisdiction over the instant case since respondent Zosa's claims
good reason from the position of Vice-Chairman under paragraph 7 of should be resolved through arbitration pursuant to Section 23 of the Employment
the Employment Agreement on the ground that said position had less responsibility Agreement with petitioners; and (2) the venue is improperly laid since respondent
and scope than President and Chief Executive Officer. He demanded that he be Zosa, like the petitioners, is a resident of Pasig City and thus, the venue of this case,
given termination benefits as provided for in Section 8 (c) (i) (ii) and (iii) of granting without admitting that the respondent has a cause of action against the
the Employment Agreement.[7] petitioners cognizable by the RTC, should be limited only to RTC-Pasig City.[14]
In a letter dated October 20, 1995, MCHC communicated its non-acceptance Meanwhile, respondent Zosa filed an amended complaint dated July 5, 1996.
of respondent Zosa's resignation for good reason, but instead informed him that
the Employment Agreement is terminated for cause, effective November 19, 1995, On August 1, 1996, the RTC Branch 58 of Cebu City issued an Order denying
in accordance with Section 7 (a) (v) of the said agreement, on account of his breach petitioners motion to dismiss upon the findings that (1) the validity and legality of
of Section 12 thereof. Respondent Zosa was further advised that he shall have no the arbitration provision can only be determined after trial on the merits; and (2)
further rights under the said Agreement or any claims against the Manager or the the amount of damages claimed, which is over P100,000.00, falls within the
Corporation except the right to receive within thirty (30) days from November 19, jurisdiction of the RTC.[15] Petitioners filed a motion for reconsideration which was
1995, the amounts stated in Section 8 (a) (i) (ii) of the Agreement. [8] denied by the RTC in an order dated September 5, 1996.[16]
In the interim, on August 22, 1996, in compliance with the earlier order of the merits until the said issue is resolved. The questioned orders are set aside insofar as
court directing petitioners to file responsive pleading to the amended complaint, they contravene this Courts resolution of the issues raised as herein pronounced.
petitioners filed their Answer Ad Cautelam with counterclaim reiterating their
position that the dispute should be settled through arbitration and the court had no The petitioner is required to remit to this Court the sum of P81.80 for cost within
jurisdiction over the nature of the action.[17] five (5) days from notice.
On October 21, 1996, the trial court issued its pre-trial order declaring the pre-
trial stage terminated and setting the case for hearing. The order states: SO ORDERED.[22]

ISSUES: Petitioners filed a motion for partial reconsideration of the CA decision praying
(1) for the dismissal of the case in the trial court, on the ground of lack of
jurisdiction, and (2) that the parties be directed to submit their dispute to
The Court will only resolve one issue in so far as this case is concerned, to wit:
arbitration in accordance with the Employment Agreement dated March 1994. The
CA, in a resolution promulgated on June 20, 1997, denied the motion for partial
Whether or not the Arbitration Clause contained in Sec.23 of the Employment reconsideration for lack of merit.
Agreement is void and of no effect: and, if it is void and of no effect, whether or not
the plaintiff is entitled to damages in accordance with his complaint and the In compliance with the CA decision, the trial court, on July 18, 1997, rendered
defendants in accordance with their counterclaim. a decision declaring the arbitration clause in the Employment Agreement partially
void and of no effect. The dispositive portion of the decision reads:
It is understood, that in the event the arbitration clause is valid and binding
between the parties, the parties shall submit their respective claim to the WHEREFORE, premises considered, judgment is hereby rendered partially declaring
Arbitration Committee in accordance with the said arbitration clause, in which the arbitration clause of the Employment Agreement void and of no effect, only
event, this case shall be deemed dismissed.[18] insofar as it concerns the composition of the panel of arbitrators, and directing the
parties to proceed to arbitration in accordance with the Employment Agreement
On November 18, 1996, petitioners filed their Motion Ad Cautelam for the under the panel of three (3) arbitrators, one for the plaintiff, one for the
Correction, Addition and Clarification of the Pre-trial Order dated November 15 defendants, and the third to be chosen by both the plaintiff and defendants. The
1996,[19] which was denied by the court in an order dated November 28, 1996. [20] other terms, conditions and stipulations in the arbitration clause remain in force
and effect."[23]
Thereafter, petitioners MCMC and MCHC filed a Motion Ad Cautelam for the
parties to file their Memoranda to support their respective stand on the issue of the In view of the trial courts decision, petitioners filed this petition for review on
validity of the arbitration clause contained in the Employment Agreement. In an
certiorari, under Rule 45 of the Rules of Court, assigning the following errors for the
order dated December 13, 1996, the trial court denied the motion of petitioners
Courts resolution:
MCMC and MCHC.
On January 17, 1997, petitioners MCMC and MCHC filed a petition for I. The trial court gravely erred when it ruled that the arbitration clause under the
certiorari and prohibition under Rule 65 of the Rules of Court with the Court of employment agreement is partially void and of no effect, considering that:
Appeals, questioning the trial court orders dated August 1, 1996, September 5,
1996, and December 13, 1996.[21] A. The arbitration clause in the employment agreement dated March
1994 between respondent Zosa and defendants MCHC and MCMC is
On March 21, 1997, the Court of Appeals rendered a decision, giving due
valid and binding upon the parties thereto.
course to the petition, the decretal portion of which reads:
B. In view of the fact that there are three parties to the employment
WHEREFORE, the petition is GIVEN DUE COURSE. The respondent court is directed agreement, it is but proper that each party be represented in the
to resolve the issue on the validity or effectivity of the arbitration clause in the arbitration panel.
Employment Agreement, and to suspend further proceedings in the trial on the
C. The trial court grievously erred in its conclusion that petitioners MCMC the issue on the validity and effectivity of the arbitration clause is determinable by
and MCHC represent the same interest. the regular courts, and do not fall within the exclusive and original jurisdiction of
the SEC.
D. Respondent Zosa is estopped from questioning the validity of the
arbitration clause, including the right of petitioner MCMC to
The determination and validity of the agreement is not a matter intrinsically
nominate its own arbitrator, which he himself has invoked.
connected with the regulation and internal affairs of corporations (see Pereyra vs.
IAC, 181 SCRA 244; Sales vs. SEC, 169 SCRA 121); it is rather an ordinary case to be
II. In any event, the trial court acted without jurisdiction in hearing the case below, decided in accordance with the general laws, and do not require any particular
considering that it has no jurisdiction over the nature of the action or suit since
expertise or training to interpret and apply (Viray vs. CA, 191 SCRA 308).[26]
controversies in the election or appointment of officers or managers of a
corporation, such as the action brought by respondent Zosa, fall within the original
Furthermore, the decision of the Court of Appeals in CA-G.R. SP No. 43059
and exclusive jurisdiction of the Securities and Exchange Commission.
affirming the trial courts assumption of jurisdiction over the case has become the
law of the case which now binds the petitioners. The law of the case doctrine has
III. Contrary to respondent Zosas allegation, the issue of the trial courts jurisdiction been defined as a term applied to an established rule that when an appellate court
over the case below has not yet been resolved with finality considering that
passes on a question and remands the cause to the lower court for further
petitioners have expressly reserved their right to raise said issue in the instant
proceedings, the question there settled becomes the law of the case upon
petition. Moreover, the principle of the law of the case is not applicable in the subsequent appeal.[27] To note, the CAs decision in CA-G.R. SP No. 43059 has
instant case.
already attained finality as evidenced by a Resolution of this Court ordering entry of
judgment of said case, to wit:
IV. Contrary to respondent Zosas allegation, petitioners MCMC and MCHC are not
guilty of forum shopping.
ENTRY OF JUDGMENT

V. Contrary to respondent Zosas allegation, the instant petition for review involves
This is to certify that on September 8, 1997 a decision/resolution rendered in the
only questions of law and not of fact.[24] above-entitled case was filed in this Office, the dispositive part of which reads as
follows:
We rule against the petitioners.
It is error for the petitioners to claim that the case should fall under the G.R. No. 129615 (Magellan Capital Management Corporation, et al. vs. Court of
jurisdiction of the Securities and Exchange Commission [SEC, for brevity]. The Appeals, Rolando Zosa, et al.).- Considering the petitioners manifestation dated
controversy does not in anyway involve the election/appointment of officers of August 11, 1997 and withdrawal of intention to file petition for review on certiorari,
petitioner MCHC, as claimed by petitioners in their assignment of the Court Resolved to DECLARE THIS CASE TERMINATED and DIRECT the Clerk of
errors. Respondent Zosas amended complaint focuses heavily on the illegality of Court to INFORM the parties that the judgment sought to be reviewed has become
the Employment Agreements Arbitration Clause initially invoked by him in seeking final and executory, no appeal therefore having been timely perfected.
his termination benefits under Section 8 of the employment contract. And under
Republic Act No. 876, otherwise known as the Arbitration Law, it is the regional trial and that the same has, on September 17, 1997, become final and executory and is
court which exercises jurisdiction over questions relating to arbitration. We thus hereby recorded in the Book of Entries of Judgments. [28]
advert to the following discussions made by the Court of Appeals, speaking thru
Justice Minerva P. Gonzaga-Reyes,[25] in C.A.-G.R. S.P. No. 43059, viz: Petitioners, therefore, are barred from challenging anew, through another remedial
measure and in any other forum, the authority of the regional trial court to resolve
As regards the fourth assigned error, asserting that jurisdiction lies with the SEC, the validity of the arbitration clause, lest they be truly guilty of forum-shopping
which is raised for the first time in this petition, suffice it to state that the Amended which the courts consistently consider as a contumacious practice that derails the
Complaint squarely put in issue the question whether the Arbitration Clause is valid orderly administration of justice.
and effective between the parties. Although the controversy which spawned the
action concerns the validity of the termination of the service of a corporate officer,
Equally unavailing for the petitioners is the review by this Court, via the instant by the parties, except that each party shall pay the fees and expenses of its own
petition, of the factual findings made by the trial court that the composition of the counsel in the arbitration. (Emphasis supplied).
panel of arbitrators would, in all probability, work injustice to respondent Zosa. We
have repeatedly stressed that the jurisdiction of this Court in a petition for review From the foregoing arbitration clause, it appears that the two (2) defendants
on certiorari under Rule 45 of the Revised Rules of Court is limited to reviewing only [petitioners] (MCMC and MCHC) have one (1) arbitrator each to compose the panel
errors of law, not of fact, unless the factual findings complained of are devoid of of three (3) arbitrators. As the defendant MCMC is the Manager of defendant
support by the evidence on record, or the assailed judgment is based on MCHC, its decision or vote in the arbitration proceeding would naturally and
misapprehension of facts.[29] certainly be in favor of its employer and the defendant MCHC would have to
protect and preserve its own interest; hence, the two (2) votes of both defendants
Even if procedural rules are disregarded, and a scrutiny of the merits of the
(MCMC and MCHC) would certainly be against the lone arbitrator for the plaintiff
case is undertaken, this Court finds the trial courts observations on why the
[herein defendant].Hence, apparently, plaintiff [defendant] would never get or
composition of the panel of arbitrators should be voided, incisively correct so as to
receive justice and fairness in the arbitration proceedings from the panel of
merit our approval. Thus,
arbitrators as provided in the aforequoted arbitration clause. In fairness and justice
to the plaintiff [defendant], the two defendants (MCMC and MCHC)[herein
From the memoranda of both sides, the Court is of the view that the defendants petitioners] which represent the same interest should be considered as one and
[petitioner] MCMC and MCHC represent the same interest. There is no quarrel that
should be entitled to only one arbitrator to represent them in the arbitration
both defendants are entirely two different corporations with personalities distinct
proceedings. Accordingly, the arbitration clause, insofar as the composition of the
and separate from each other and that a corporation has a personality distinct and panel of arbitrators is concerned should be declared void and of no effect, because
separate from those persons composing the corporation as well as from that of any
the law says, Any clause giving one of the parties power to choose more arbitrators
other legal entity to which it may be related.
than the other is void and of no effect (Article 2045, Civil Code).

But as the defendants [herein petitioner] represent the same interest, it could
The dispute or controversy between the defendants (MCMC and MCHC) [herein
never be expected, in the arbitration proceedings, that they would not protect and
petitioners] and the plaintiff [herein defendant] should be settled in the arbitration
preserve their own interest, much less, would both or either favor the interest of
proceeding in accordance with the Employment Agreement, but under the panel of
the plaintiff. The arbitration law, as all other laws, is intended for the good and three (3) arbitrators, one (1) arbitrator to represent the plaintiff, one (1) arbitrator
welfare of everybody. In fact, what is being challenged by the plaintiff herein is not
to represent both defendants (MCMC and MCHC)[herein petitioners] and the third
the law itself but the provision of the Employment Agreement based on the said
arbitrator to be chosen by the plaintiff [defendant Zosa] and defendants
law, which is the arbitration clause but only as regards the composition of the panel [petitioners].
of arbitrators. The arbitration clause in question provides, thus:
x x x x x x x x x[30]
In the event that any dispute, controversy or claim arise out of or under any
provisions of this Agreement, then the parties hereto agree to submit such dispute, In this connection, petitioners attempt to put respondent in estoppel in
controversy or claim to arbitration as set forth in this Section and the determination assailing the arbitration clause must be struck down. For one, this issue of estoppel,
to be made in such arbitration shall be final and binding. Arbitration shall be as likewise noted by the Court of Appeals, found its way for the first time only on
effected by a panel of three appeal. Well-settled is the rule that issues not raised below cannot be resolved on
arbitrators. The Manager, Employee,and Corporation shall designate one (1) review in higher courts.[31] Secondly, employment agreements such as the one at
arbitrator who shall, in turn, nominate and elect as who among them shall be the bar are usually contracts of adhesion. Any ambiguity in its provisions is generally
chairman of the committee. Any such arbitration, including the rendering of an resolved against the party who drafted the document. Thus, in the relatively recent
arbitration award, shall take place in Metro Manila. The arbitrators shall interpret case of Phil. Federation of Credit Cooperatives, Inc. (PFCCI) and Fr. Benedicto
this Agreement in accordance with the substantive laws of the Republic of the Jayoma vs. NLRC and Victoria Abril,[32] we had the occasion to stress that where a
Philippines. The arbitrators shall have no power to add to, subtract from or contract of employment, being a contract of adhesion, is ambiguous, any ambiguity
otherwise modify the terms of this Agreement or to grant injunctive relief of any therein should be construed strictly against the party who prepared it. And, finally,
nature. Any judgment upon the award of the arbitrators may be entered in any respondent Zosa never submitted himself to arbitration proceedings (as there was
court having jurisdiction thereof, with costs of the arbitration to be borne equally none yet) before bewailing the composition of the panel of arbitrators. He in fact,
lost no time in assailing the arbitration clause upon realizing the inequities that may would give undue advantage to a party in the negotiating table is anathema to the
mar the arbitration proceedings if the existing line-up of arbitrators remained very purpose of arbitration and should, therefore, be resisted.
unchecked.
WHEREFORE, premises considered, the petition is hereby DISMISSED and the
We need only to emphasize in closing that arbitration proceedings are decision of the trial court dated July 18, 1997 is AFFIRMED.
designed to level the playing field among the parties in pursuit of a mutually
acceptable solution to their conflicting claims. Any arrangement or scheme that SO ORDERED.
DEL MONTE CORPORATION-USA, PAUL E. DERBY, JR., DANIEL COLLINS and LUIS 23[12] of the Civil Code. According to private respondents, DMC-USA products
HIDALGO, petitioners, vs. COURT OF APPEALS, JUDGE BIENVENIDO L. REYES in his continued to be brought into the country by parallel importers despite the
capacity as Presiding Judge, RTC-Br. 74, Malabon, Metro Manila, MONTEBUENO appointment of private respondent MMI as the sole and exclusive distributor of Del
MARKETING, INC., LIONG LIONG C. SY and SABROSA FOODS, INC., respondents. Monte products thereby causing them great embarrassment and substantial
damage. They alleged that the products brought into the country by these
DECISION importers were aged, damaged, fake or counterfeit, so that in March 1995 they had
to cause, after prior consultation with Antonio Ongpin, Market Director for Special
BELLOSILLO, J.: Markets of Del Monte Philippines, Inc., the publication of a "warning to the trade"
paid advertisement in leading newspapers. Petitioners DMC-USA and Paul E. Derby,
This Petition for Review on certiorari assails the 17 July 1998 Decision[1] of the Jr., apparently upset with the publication, instructed private respondent MMI to
Court of Appeals affirming the 11 November 1997 Order[2] of the Regional Trial stop coordinating with Antonio Ongpin and to communicate directly instead with
Court which denied petitioners Motion to Suspend Proceedings in Civil Case No. petitioner DMC-USA through Paul E. Derby, Jr.
2637-MN. It also questions the appellate courts Resolution[3] of 30 October 1998
which denied petitioners Motion for Reconsideration. Private respondents further averred that petitioners knowingly and
surreptitiously continued to deal with the former in bad faith by involving
On 1 July 1994, in a Distributorship Agreement, petitioner Del Monte disinterested third parties and by proposing solutions which were entirely out of
Corporation-USA (DMC-USA) appointed private respondent Montebueno their control. Private respondents claimed that they had exhausted all possible
Marketing, Inc. (MMI) as the sole and exclusive distributor of its Del Monte avenues for an amicable resolution and settlement of their grievances; that as a
products in the Philippines for a period of five (5) years, renewable for two (2) result of the fraud, bad faith, malice and wanton attitude of petitioners, they should
consecutive five (5) year periods with the consent of the parties. The Agreement be held responsible for all the actual expenses incurred by private respondents in
provided, among others, for an arbitration clause which states the delayed shipment of orders which resulted in the extra handling thereof, the
actual expenses and cost of money for the unused Letters of Credit (LCs) and the
12. GOVERNING LAW AND ARBITRATION[4]
substantial opportunity losses due to created out-of-stock situations and
unauthorized shipments of Del Monte-USA products to the Philippine Duty Free
This Agreement shall be governed by the laws of the State of California and/or, if Area and Economic Zone; that the bad faith, fraudulent acts and willful negligence
applicable, the United States of America. All disputes arising out of or relating to this of petitioners, motivated by their determination to squeeze private respondents
Agreement or the parties relationship, including the termination thereof, shall be out of the outstanding and ongoing Distributorship Agreement in favor of another
resolved by arbitration in the City of San Francisco, State of California, under the party, had placed private respondent LILY SY on tenterhooks since then; and, that
Rules of the American Arbitration Association. The arbitration panel shall consist of the shrewd and subtle manner with which petitioners concocted imaginary
three members, one of whom shall be selected by DMC-USA, one of whom shall be violations by private respondent MMI of the Distributorship Agreement in order to
selected by MMI, and third of whom shall be selected by the other two members justify the untimely termination thereof was a subterfuge. For the foregoing,
and shall have relevant experience in the industry x x x x private respondents claimed, among other reliefs, the payment of actual damages,
exemplary damages, attorneys fees and litigation expenses.
In October 1994 the appointment of private respondent MMI as the sole and
exclusive distributor of Del Monte products in the Philippines was published in On 21 October 1996 petitioners filed a Motion to Suspend
several newspapers in the country. Immediately after its appointment, private Proceedings[13] invoking the arbitration clause in their Agreement with private
respondent MMI appointed Sabrosa Foods, Inc. (SFI), with the approval of respondents.
petitioner DMC-USA, as MMIs marketing arm to concentrate on its marketing and In a Resolution[14] dated 23 December 1996 the trial court deferred
selling function as well as to manage its critical relationship with the trade. consideration of petitioners Motion to Suspend Proceedings as the grounds alleged
On 3 October 1996 private respondents MMI, SFI and MMIs Managing therein did not constitute the suspension of the proceedings considering that the
Director Liong Liong C. Sy (LILY SY) filed a Complaint[5] against petitioners DMC-USA, action was for damages with prayer for the issuance of Writ of Preliminary
Paul E. Derby, Jr.,[6]Daniel Collins[7] and Luis Hidalgo,[8] and Dewey Ltd.[9] before the Attachment and not on the Distributorship Agreement.
Regional Trial Court of Malabon, Metro Manila. Private respondents predicated
their complaint on the alleged violations by petitioners of Arts. 20, [10] 21[11] and
On 15 January 1997 petitioners filed a Motion for Reconsideration to which demands a full blown trial, as correctly held by the Court of Appeals. Moreover,
private respondents filed their Comment/Opposition. On 31 January 1997 they claim that the issues before the trial court were not joined so that the
petitioners filed their Reply.Subsequently, private respondents filed an Urgent Honorable Judge was not given the opportunity to satisfy himself that the issue
Motion for Leave to Admit Supplemental Pleading dated 2 April 1997. This Motion involved in the case was referable to arbitration. They submit that, apparently,
was admitted, over petitioners opposition, in an Order of the trial court dated 27 petitioners filed a motion to suspend proceedings instead of sending a written
June 1997. demand to private respondents to arbitrate because petitioners were not sure
whether the case could be a subject of arbitration. They maintain that had
As a result of the admission of the Supplemental Complaint, petitioners filed
petitioners done so and private respondents failed to answer the demand,
on 22 July 1997 a Manifestation adopting their Motion to Suspend Proceedings of
petitioners could have filed with the trial court their demand for arbitration that
17 October 1996 and Motion for Reconsideration of 14 January 1997.
would warrant a determination by the judge whether to refer the case to
On 11 November 1997 the Motion to Suspend Proceedings was denied by the arbitration. Accordingly, private respondents assert that arbitration is out of the
trial court on the ground that it "will not serve the ends of justice and to allow said question.
suspension will only delay the determination of the issues, frustrate the quest of the
Private respondents further contend that the arbitration clause centers more
parties for a judicious determination of their respective claims, and/or deprive and on venue rather than on arbitration. They finally allege that petitioners filed their
delay their rights to seek redress."[15]
motion for extension of time to file this petition on the same date[20] petitioner
On appeal, the Court of Appeals affirmed the decision of the trial court. It held DMC-USA filed a petition to compel private respondent MMI to arbitrate before the
that the alleged damaging acts recited in the Complaint, constituting petitioners United States District Court in Northern California, docketed as Case No. C-98-
causes of action, required the interpretation of Art. 21 of the Civil Code [16] and that 4446. They insist that the filing of the petition to compel arbitration in the United
in determining whether petitioners had violated it "would require a full blown trial" States made the petition filed before this Court an alternative remedy and, in a
making arbitration "out of the question."[17] Petitioners Motion for way, an abandonment of the cause they are fighting for here in the Philippines, thus
Reconsideration of the affirmation was denied. Hence, this Petition for Review. warranting the dismissal of the present petition before this Court.

The crux of the controversy boils down to whether the dispute between the There is no doubt that arbitration is valid and constitutional in our
parties warrants an order compelling them to submit to arbitration. jurisdiction.[21] Even before the enactment of RA 876, this Court has countenanced
the settlement of disputes through arbitration. Unless the agreement is such as
Petitioners contend that the subject matter of private respondents causes of absolutely to close the doors of the courts against the parties, which agreement
action arises out of or relates to the Agreement between petitioners and private would be void, the courts will look with favor upon such amicable arrangement and
respondents. Thus, considering that the arbitration clause of the Agreement will only interfere with great reluctance to anticipate or nullify the action of the
provides that all disputes arising out of or relating to the Agreement or the parties arbitrator.[22] Moreover, as RA 876 expressly authorizes arbitration of domestic
relationship, including the termination thereof, shall be resolved by arbitration, disputes, foreign arbitration as a system of settling commercial disputes was
they insist on the suspension of the proceedings in Civil Case No. 2637-MN as likewise recognized when the Philippines adhered to the United
mandated by Sec. 7 of RA 876[18] - Nations "Convention on the Recognition and the Enforcement of Foreign Arbitral
Awards of 1958" under the 10 May 1965 Resolution No. 71 of the Philippine Senate,
Sec. 7. Stay of Civil Action. If any suit or proceeding be brought upon an issue arising giving reciprocal recognition and allowing enforcement of international arbitration
out of an agreement providing for arbitration thereof, the court in which such suit or agreements between parties of different nationalities within a contracting state. [23]
proceeding is pending, upon being satisfied that the issue involved in such suit or
proceeding is referable to arbitration, shall stay the action or proceeding until an A careful examination of the instant case shows that the arbitration clause in
arbitration has been had in accordance with the terms of the the Distributorship Agreement between petitioner DMC-USA and private
agreement. Provided, That the applicant for the stay is not in default in proceeding respondent MMI is valid and the dispute between the parties is
with such arbitration. arbitrable. However, this Court must deny the petition.
The Agreement between petitioner DMC-USA and private respondent MMI is
Private respondents claim, on the other hand, that their causes of action are a contract. The provision to submit to arbitration any dispute arising therefrom and
rooted in Arts. 20, 21 and 23 of the Civil Code,[19] the determination of which the relationship of the parties is part of that contract and is itself a contract. As a
rule, contracts are respected as the law between the contracting parties and
produce effect as between them, their assigns and heirs. [24]Clearly, only parties to
the Agreement, i.e., petitioners DMC-USA and its Managing Director for Export
Sales Paul E. Derby, Jr., and private respondents MMI and its Managing Director
LILY SY are bound by the Agreement and its arbitration clause as they are the only
signatories thereto. Petitioners Daniel Collins and Luis Hidalgo, and private
respondent SFI, not parties to the Agreement and cannot even be considered
assigns or heirs of the parties, are not bound by the Agreement and the arbitration
clause therein. Consequently, referral to arbitration in the State of California
pursuant to the arbitration clause and the suspension of the proceedings in Civil
Case No. 2637-MN pending the return of the arbitral award could be called
for[25] but only as to petitioners DMC-USA and Paul E. Derby, Jr., and private
respondents MMI and LILY SY, and not as to the other parties in this case, in
accordance with the recent case of Heirs of Augusto L. Salas, Jr. v. Laperal Realty
Corporation,[26] which superseded that of Toyota Motor Philippines Corp. v. Court of
Appeals.[27]
In Toyota, the Court ruled that "[t]he contention that the arbitration clause
has become dysfunctional because of the presence of third parties is untenable
ratiocinating that "[c]ontracts are respected as the law between the contracting
parties"[28] and that "[a]s such, the parties are thereby expected to abide with good
faith in their contractual commitments."[29] However, in Salas, Jr., only parties to
the Agreement, their assigns or heirs have the right to arbitrate or could be
compelled to arbitrate. The Court went further by declaring that in recognizing the
right of the contracting parties to arbitrate or to compel arbitration, the splitting of
the proceedings to arbitration as to some of the parties on one hand and trial for
the others on the other hand, or the suspension of trial pending arbitration
between some of the parties, should not be allowed as it would, in effect, result in
multiplicity of suits, duplicitous procedure and unnecessary delay. [30]
The object of arbitration is to allow the expeditious determination of a
dispute.[31] Clearly, the issue before us could not be speedily and efficiently resolved
in its entirety if we allow simultaneous arbitration proceedings and trial, or
suspension of trial pending arbitration. Accordingly, the interest of justice would
only be served if the trial court hears and adjudicates the case in a single and
complete proceeding.[32]
WHEREFORE, the petition is DENIED. The Decision of the Court of Appeals
affirming the Order of the Regional Trial Court of Malabon, Metro Manila, in Civil
Case No. 2637-MN, which denied petitioners Motion to Suspend Proceedings, is
AFFIRMED. The Regional Trial Court concerned is directed to proceed with the
hearing of Civil Case No. 2637-MN with dispatch. No costs.
SO ORDERED.

Vous aimerez peut-être aussi