Vous êtes sur la page 1sur 1

PROJECT: Proposed 2- Storey Residential

PROJECT: Proposed 2- Storey Residential LOCATION : Blk. 15, Lot 4, Roman St. Sacred Heart Village, Novaliches, Quezon City
OWNER: Engr. Ramon See

TIMELINE OF ACTIVITIES
APRIL
ACTIVITIES
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1 SITE CLEARING
2 LAY OUT AND STAKING
3 BARRACKS AND STORAGE
4 EXCAVATION OF COLUMN FOOTING
5 EXCAVATION OF WALL FOOTING
6 FABRICATION OF FOOTING REBARS
7 FABRICATION OF COLUMN REBARS
8 FABRICATION OF WALL FOOTING REBARS
9 ERECTION OF COLUMN REBARS H
10 POURING OF CONCRETE COLUMN FOOTING
11 INSTALLATION OF WALL FOOTING REBARS
12 POURING OF CONCRETE WALL FOOTING
13 CHB LAYING UNTIL BEAM SOFFIT O
14 COLUMN FORMWORKS
15 POURING CONCRETE COLUMN UNTIL BEAM SOFFIT
16 FABRICATION OF FLOOR BEAM REBARS
17 INSTALLATION OF FLOOR BEAM
L
18 FLOOR BEAM FORMWORKS
19 POURING OF CONCRETE FLOOR BEAM
20 INSTALLATION OF STEEL DECK
21 INSTALLATION OF SLAB REBARS
22 POURING OF CONCRETE SLAB I
23 FABRICATION OF COLUMN REBARS (GF)
24 CHB LAYING (GF)
25 COLUMN FORMWORKS
26 POURING OF CONCRETE COLUMN (GF) D
27 FABRICATION OF BEAM REBARS 27 27
28 INSTALLATION OF BEAM REBARS 28 28 28 28 28
29 BEAM FORMWORKS 29 29 29 29 29
30 POURING OF CONCRETE BEAM A 30
31 INSTALLATION OF STEEL DECK (SF) 31 31
32 INSTALLATION OF SLAB REBARS (SF) 32 32
33 POURING OF SECOND FLOOR SLAB 33
34 CONSTRUCTION OF STAIRWAY 34 34 34
35 INSTALLATION OF COLUMN REBARS (SF)
Y 35 35 35 35
36 CHB LAYING (SF) 36 36 36 36 36 36
37 ELECTRICAL ROUGH- IN (GF) 37 37 37
38 PLUMBING ROUGH- IN (GF) 38 38 38
39 COLUMN FORMWORKS (SF) 39 39 39 39
40 POURING OF COLUMN (SF) 40 40 40 40
41 FABRICATION OF ROOF BEAM REBARS 41
42 INSTALLATION OF ROOF BEAM
43 ROOF BEAM FORMWORKS
44 POURING OF CONCRETE ROOF BEAM
45 FABRICATION OF TRUSSES
46 INSTALATION OF TRUSSES
47 INSTALLATION OF ROOF
48 PLASTERING (GF)
49 PLASTERING (SF)
50 PLASTERING OF EXTERIOR WALLS
51 PLASTERING OF TRIMS AND MOLDINGS
52 FABRICATION OF RAILINGS
53 INSTALLATION OF WINDOWS
54 ELECTRICAL ROUGH- IN (SF)
55 PLUMBING ROUGH- IN (SF)
56 INSTALLATION OF CEILING
57 INSTALLATION OF TILES
58 CARPENTRY
59 INSTALLATION OF PLUMBING FIXTURES
60 INSTALLATION OF LIGHTING FIXTURES
61 PAINT JOB
62 FURNISHING

Vous aimerez peut-être aussi