Académique Documents
Professionnel Documents
Culture Documents
sarwonohm2@yahoo.co.id
CASES
(Chow Kok Fong (2006):” Construction Contracts Dictionary”, Sweet & Maxwell Asia)
CLAIMS
© Sarwono Hardjomuljadi
BACKGROUND
CASES
OWNER
EMPLOYER
CONTRACTOR
ENGINEER
Constructor
Consultant (E, P) (C)
Contractual
Supervisory
Consultancy
© Sarwono Hardjomuljadi
HUBUNGAN
FIDIC CONDITIONSKERJA FIDIC CONDITIONS
OF CONTRACT FOR EPC/OF CONTRACT
TURNKEY FOR
PROJECT,
EPC/
1st 1999 PROJECT, 1st Edition, 1999
TURNKEY
Edition,
Owner
EMPLOYER CONTRACTOR
ENGINEER ENGINEER
Constructor
( EPC)
CASES
By using the EPC/Turnkey Contract, the Employer thought that they already
shift the risks to the contractor side, but EPC/Turnkey Contract with too limited
information or too simple basic design would create problems in the
procurement process, because the tender proposal must be higher (because
the contractor will include the risk which may occured). If case that the
employer could accept this higher tender proposal, the use of EPC/Turnkey may
be recommended.
The condition might be worsen since most of conditions of contract was “tailor-
made” and was not standardized. Instead of controlling the contract price, a
modified EPC/Turnkey Contract would create more problems and finally
everything
CASES
The above sub-clause shows that the Contract Price in EPC Contract is
“fixed contract price”, means that in case there are some works
necessary to be done on completing the Work (Constructive Change
Order), such cost “shall be added to the contract price” and not “shall be
included in the Contract Price” as for the cost of additional work in the
Construction Contract.
FIDIC International Training Seminar
“Management of Construction Claims”
Jakarta July 25-26, 2011
Sub-Clause 17.4 Consequences of Employer Risks
If the (Contractor suffers delay and/or incurs Cost from rectifying this lost or
damage, the Contractor shall give a further notice to the Employer and shall be
entitled subject to Sub Clause 20.1 [Contractor’s Claim]
b) payment of any such Cost, which “shall be added to” the Contract
Price.
(Conditions of Contract for EPC/Turnkey Project-1999)
CASES
After the price and technical evaluation, Contractor A was then appointed as the
Contractor for the Coal Power Plant Project P to conduct the design, engineering,
procurement and construction works including the pier. During the construction, the
actual sea water level was lower than predicted by the contractor when preparing the
design. The ship was consequently unable to unload and the coal supply would be
disrupted.
The Contractor had the schedule of rates and prices attached to the contract, so in order
to avoid further failure, the Employer instructed the Contractor to use the former
Employer’s design. The final price of the pier then became even higher than the original
price of the pier with the length of X meter
In the contract, there was schedule of rates and prices attached to the contract
for foundation works. It could be considered by the Contractor that the payment
for this work would be based on such unit price.