ESTIMATE

18 Reinforced cement concrete 1:1.5:3 for


beam and lintel .Using 20mm brockan
stone .

Including the cost of all materials and

labour etc. complete. But excluding


the cost of reinforcement.
out side lintel 2 7.9 0.2 0.6 1.896
2 10.4 0.2 0.45 1.8886
2 7.9 0.2 0.45 1.422
1 7 0.2 0.3 0.42
5.6266 m3 9000 50,639.76

19 Reinforced cement concrete 1:1.5:3 for


slab .Using 20mm brockan stone .

Including the cost of all materials and

labour etc. complete. But excluding


the cost of reinforcement.
slab 1 8.8 12 0.12 12.672
stair 1 9 1.2 0.12 1.296
13.968 m3 9000 125,712.00
Reinforcement for R.C.C works
20 bent,tied
and placed in position . Using HYSD
steel

including the cost of binding wair, all


materal and labour etc.complet.
Say item no 3,6,9,11 and 12 .Qty 22.955 m3
Say 28.937 m3/120.00 kg 2295.5 kg 60 137,727.84

21 Wall plastring CM 1:4.Using good

quality sand including the cost of

all materials and labour etc. complete.


inside
wall in side and outside 2 50 2.8 280
column 14 1.3 3.3 60.06
beam 2 7.9 1.2 18.96
2 10.4 0.9 18.72
2 7.9 0.9 14.22
1 7 0.6 4.2
slab 1 8.5 12 102
498.16 m2 410 204,245.60

S3 5/12
ESTIMATE

22 Solid block masonry(20cm thick)

in CM 1:5 .Using good quality Solid


block(30x20x15cm) .Including the

cost of all materials and labour etc.


out side 1 50 0.2 2.8 28
28

diduction
door d 1 1.2 0.2 2.1 0.504
d1 1 0.9 0.2 2.1 0.378
d2 2 0.8 0.2 2.1 0.672
w1 4 0.5 0.2 1.5 0.6
SW2 1 0.8 0.2 1.5 0.24
w3 1 1.5 0.2 1.5 0.45
kw1 1 0.5 0.2 0.75 0.075
kw2 1 1 0.2 0.75 0.15
v 2 0.6 0.2 0.45 0.108
3.177
After diduction 24.823 m3 4100 101,774.30

23 Laying Floor Tiles using good quality


ceramic Tiles 60x60cm including
the cost of all materials and labour
etc.
floor 1 11 8 88
wall 2 6.1 3 36.6
124.6 m2 2155 268,513.00
SECOND FLOOR

24 Reinforced cement concrete 1:1.5:3 for

column .Using 20mm brockan stone .

Including the cost of all materials and

labour etc. complete. But excluding


the cost of reinforcement.
column 14 0.2 0.4 3 3.36
3.36 m3 9000 30,240.00

25 Reinforced cement concrete 1:1.5:3 for


beam and lintel .Using 20mm brockan
stone .

Including the cost of all materials and

labour etc. complete. But excluding

S3 6/12
ESTIMATE

the cost of reinforcement.


out side lintel 2 7.9 0.2 0.6 1.896
2 10.4 0.2 0.45 1.8886
2 7.9 0.2 0.45 1.422
1 7 0.2 0.3 0.42
5.6266 m3 9000 50,639.76

26 Reinforced cement concrete 1:1.5:3 for


slab .Using 20mm brockan stone .

Including the cost of all materials and

labour etc. complete. But excluding


the cost of reinforcement.
slab 1 8.8 12.5 0.12 13.2
stair 1 9 1.2 0.12 1.296
14.496 m3 9000 130,464.00
Reinforcement for R.C.C works
27 bent,tied
and placed in position . Using HYSD
steel

including the cost of binding wair, all


materal and labour etc.complet.
Say item no 3,6,9,11 and 12 .Qty 23.483 m3
Say 28.937 m3/120.00 kg 2348.3 kg 60 140,895.84

28 Wall plastring CM 1:4.Using good

quality sand including the cost of

all materials and labour etc. complete.


inside
wall in side and outside 2 50 2.8 280
column 14 1.3 3.3 60.06
beam 2 7.9 1.2 18.96
2 10.4 0.9 18.72
2 7.9 0.9 14.22
1 7 0.6 4.2
slab 1 8.5 12 102
498.16 m2 410 204,245.60

29 Solid block masonry(20cm thick)

in CM 1:5 .Using good quality Solid


block(30x20x15cm) .Including the

cost of all materials and labour etc.


out side 1 50 0.2 2.8 28
28

S3 7/12